You are on page 1of 8

TRANSPORTATION RESEARCH RECORD 1543

55

Performance Evaluation of Asphalt


Overlays on Broken and Seated
Concrete Pavements
RAJAGOPAL S. ARUDI, ISSAM MINKARAH, KRISHNA KANDULA, AND
ARCHANA GOSAIN
Evaluating the effectiveness of breaking and seating concrete pavements
prior to asphalt overlay is a subject of great importance for pavement
rehabilitation. A number of studies reported that breaking and seating
delayed reflection cracking, but some indicated that, after 4 to 5 years,
the cracking of the asphalt overlays on broken and seated sections
increased and was about the same as in the other sections. Structural
analysis of these pavements confirmed a significant loss of structural
support. A controlled experimental project in Ohio investigated the
effectiveness of breaking and seating jointed reinforced concrete pavements before asphalt overlay. Four miles of in-service composite pavements carrying heavy traffic were rehabilitated by milling the original
asphalt layer, breaking and seating the concrete slabs, and constructing
new asphalt overlays. Four more miles of the same sections were constructed in the same way except for breaking and seating. After 21/2 years
of study, the results confirm the previous findings regarding the effectiveness of breaking and seating in delaying reflection cracks and reduction in structural capacity, increase in surface deflection, and loss of flexural strength. This study indicates that the type of breaking equipment
used and the extent of breaking are the most significant factors affecting the performance of these pavements.

In composite pavements, thermal movements of the underlying concrete slabs at joints and working cracks induce excessive strains in
the asphalt concrete (AC) overlay, which results in the development
of reflection cracking. The cracks form at the bottom of the asphalt
layer, above a joint or a crack, and propagate vertically to the surface. Such movements are directly proportional to the length of the
slab. This implies that the shorter the length, the better the chance
of reducing crack development and, in turn, reflection cracking.
Reflection cracks cause early deterioration of the overlay, increase
life-cycle costs, and reduce the useful life of the pavement.
The intent of pavement cracking and seating is to create concrete
pieces that are small enough to reduce horizontal slab movements to
a point at which thermal stresses that contribute to reflection cracking will be greatly reduced. These pieces should be large enough to
maintain the original structural strength of the portland cement concrete (PCC) pavement and to provide some aggregate interlock.
Seating of the broken slabs after cracking is intended to reestablish
support between the subbase and the slab.
Thorough slab cracking is essential to the success of breaking and
seating. The continuity of the PCC slab (and its ability to transmit
horizontal slab movement) must be broken to achieve the full potential of the breaking and seating rehabilitation technique.

Department of Civil and Environmental Engineering, University of Cincinnati, P.O. Box 210071, Cincinnati, Ohio 45221-0071.

PREVIOUS INVESTIGATIONS
A considerable range of performance has been achieved with the
breaking and seating procedure. It is apparent that a properly constructed section can alleviate (perhaps eliminate in some cases)
thermal-related reflective cracking in AC overlays.
A performance survey by FHWA found that breaking/cracking
and seating (B/C&S) as a rehabilitation alternative should be
approached with caution. A significant reduction in reflection cracking after 4 to 5 years occurred on only 2 of 22 projects reviewed (1).
The University of Illinois surveyed 70 projects in 12 states and
found that B/C&S treatment reduced reflection cracking in the early
years of the life of the overlay but its effectiveness diminished with
age (1,2). Kentucky surveyed and tested 451 lane-miles of B/C&Streated pavements and found only one section that displayed unexpected reflection cracking; an analysis of the test section revealed
that proper B/C&S had not been achieved. Kentucky reported, performance has been good, and as a result the practice continues routinely (2).
Overall, B/C&S appears to provide benefits by delaying reflection cracking. After 4 to 5 years, the B/C&S sections exhibit approximately the same degree of reflection cracks.
Pavements on reasonably firm subgrades or bases with cracked
pavement sizes of 0.6 to 0.9 m and a 7.6- to 12-cm overlay thickness
have performed the best to date. The actual overlay thickness will
depend on the expected traffic and other usual design parameters.

PRESENT STUDY: OBJECTIVES AND SCOPE


Since 1984, as one of many pavement rehabilitation alternatives, the
Ohio Department of Transportation (ODOT), has used fractured
slab techniques before asphalt overlays (3). Ten projects with a total
length of 63 miles have been rehabilitated with AC overlays after
breaking and seating the concrete pavements. Performance studies
of these projects were inconclusive. As a result, there is some disagreement in Ohio, from district to district, about the effectiveness
of this technique. Nevertheless, it is generally believed that the
breaking and seating method is more suitable for plain (nonreinforced) PCC pavements. Hence, ODOT initiated a study to investigate the effectiveness of breaking and seating jointed reinforced
concrete pavements (JRCP) before asphalt overlay.
Eight sections of in-service composite pavements were selected,
each about 1.6 km with AC over JRCP and carrying heavy traffic.
Four of these sections were rehabilitated by milling the original AC

56

TRANSPORTATION RESEARCH RECORD 1543

layer, breaking and seating the concrete slabs, and constructing new
AC overlays. Four sections adjacent to the break and seat (B/S) sections were rehabilitated in the same way but without breaking and
seating the concrete slabs.
Performance was evaluated by continuously monitoring the
test pavements using deflection measurements and a visual distress
survey.
This research was performed from 1992 through 1995. This paper
presents the details of the testing program and the findings.
TEST SECTIONS
The location and other details of the test sections are presented in
Table 1. Core samples of the concrete pavement and soil subgrade
were taken from each test section.
Tests on concrete cores revealed a large variation in the lab compressive strength. Strength values ranged from 20 685 kPa to 52 400
kPa. However, the compressive strength of most samples was
between 34 475 kPa and 48 265 kPa.
The liquid limit, plasticity index, and sieve analysis test results
were used to classify the subgrade soils using the AASHTO Soil
Classification System. The subgrade soils from the I-71 site were
classified as Type A-4 (silty soils). The soil samples from the SR-4
sections were classified as Type A-6 (clayey soils).
CONSTRUCTION
Construction involved removing the original 7.6-cm asphalt layer,
breaking and seating the PCC slabs (only on the B/S sections), and
placing an AC overlay. The I-71 sections were overlaid with a 21.6cm-thick AC overlay in three layers. The SR-4 sections received a
16.5-cm-thick AC overlay, in three layers. The overlay thickness
design was made by ODOT engineers using ODOT design procedures. In all sections, a 10.2-cm-diameter longitudinal underdrain
was installed along the shoulder at a depth of 0.9 m below the top of
the concrete pavement. Construction of the AC overlays on the I-71
sections was completed in September 1992, and the overlays on the
SR-4 sections were completed in September 1993. The performance
of the AC overlays on the I-71 sections were monitored for three
winter cycles and on the SR-4 sections for two winter cycles.

TABLE 1

Details of Test Sections

For about 300 m at the start of breaking and seating, the concrete
slabs on one section of I-71 were broken with a 2.4-m, 5440-kg guillotine hammer. This section was the passing lane on the northbound
lanes between Station 35100 and Station 88100. The 2.4-m-wide
hammer was dropped at the center of the lane, which is 3.6 m wide.
Because the width of the hammer was smaller than the lane, the
desired result was not achieved. Hence, use of the 2.4-m-wide
hammer was discontinued and further breaking was done with a 1.8m-wide hammer. Two passes of the 1.8-m-wide hammer were
required in each lane to cover the entire 3.6-m width. The hammer
was dropped at an interval of 0.45 m in the longitudinal direction.
The two sections on SR-4 were broken with a pile hammer on a
0.45- 3 0.45-m grid.
An attempt was made to achieve uniform breakage in each section; however, most of the pavements broken with the guillotine
hammer developed problems where drops overlapped, usually in
the middle of the lane. This area was cracked much more than
other parts. Breaking with all types of hammers resulted in thorough slab cracking, and no additional effort was made to break the
reinforcement. Breaking was also more extensive with the pile
hammer.
About 5 lane-miles of pavement could be broken on each working day with the guillotine hammer, while only about 1 lane-mile
was broken when using the pile hammer. Breaking caused some
traffic disruption. However, no data were collected on traffic behavior through the work zone during the breaking operation.
Seating the sections was accomplished with five passes of a
40 350-kg pneumatic roller.

FIELD EVALUATION
Falling weight deflection measurements were made on the original
AC surface, on the exposed concrete surface after milling the AC,
and periodically on the AC overlay. On each section, 30 to 40 measurements were made during each phase.
The intensity of transverse cracks on each section was visually
observed and recorded in conformity with ODOTs Pavement Condition Rating Manual (4). The location of the cracks was measured
with reference to established benchmarks. Crack mapping was performed on the original AC surface, on the exposed concrete surface

Arudi et al.

57

TABLE 2

Comparison of Structural Condition of Original Pavement Sections

after milling, and several times after the AC overlay. When the concrete pavement was exposed, the location of the joints and permanent patches was also recorded. Several benchmarks were established to locate the exact position of cracks, joints, and permanent
patches. On the AC overlays, the date when a crack was first noticed
was noted along with its location. Also, a photographic record of the
condition of the joints and cracks was kept. Many photographs
depicting the condition of joints and cracks before overlay and the
new cracks in the AC overlay were obtained. These photographs
were used to countercheck the location of joints and cracks and to
ascertain the severity of the cracks.

COMPARING CONDITION OF ORIGINAL


PAVEMENT SECTIONS
Structural Condition
Table 2 provides a comparison of the structural parameters of the
control sections and the sections marked for breaking and seating.

FIGURE 1

Spreadability and maximum deflection values have long been used


to define the structural condition of a pavement. Arudi et al. (5) indicated that the ratio of W1/W5 can also be used as a good indicator of
the structural behavior of the pavement. Table 2 indicates that the difference in structural response with respect to maximum deflection,
spreadability, and the W1/W5 ratio between two adjacent sections is
very small, indicating the sections were structurally homogeneous.

Surface Condition
Figures 1 through 4 illustrate the extent of reflection cracking in the
original pavements. The plots in Figures 1 through 4 indicate that
the sections selected are fairly homogeneous from an extent-ofcracking point of view. For comparison, each section was subdivided into five equal subsections of about 320 m. In general, about
35 cracks were present in each subsection on I-71. The SR-4 sections had extensive cracks with 60 to 100 cracks in each subsection.
In most instances, the cracks were sealed; hence, the severity of the
cracks could not be observed.

I-71, Stations 726163 to 779143 (crack density along roadway).

58

TRANSPORTATION RESEARCH RECORD 1543

FIGURE 2

I-71, Stations 35100 to 88100 (crack density along roadway).

After milling the original AC layer and exposing the concrete surface, the exact location of the cracks and joints with respect to the
benchmarks was recorded. More than 80 percent of the slabs had
one to three cracks. Rarely were there slabs with four or more
cracks. The average spacing of cracks varied from 3 to 9 m. This survey also assisted in establishing how many of the cracks in the original AC layer were reflected from the joints and how many from the
cracks.

as B/S sections. These sections survived the winter of 1993 without


developing any cracks, but the pavement exhibited an increase in
deflection characteristics during the first year. The monthly summarized station and divisional data available in the climatological
data of Ohio (6) were studied for the winter months of the past 10
years. The winter of 1993 was mild with normal temperatures prevailing during the entire season.

Performance After Winter 1994


PERFORMANCE OF ASPHALT OVERLAYS
A performance evaluation was made by studying the change in
structural response and surface characteristics of the pavement sections investigated.

Performance After Winter 1993


Construction of the AC overlay was completed on only 4 miles of
I-71 by fall 1992. The completed pavement included control as well

FIGURE 3

Construction of the AC overlay on SR-4 was completed by fall


1993. As a result, all sections were now available for monitoring.
Figures 5 through 8 present changes in the deflection characteristics
of the pavements with time. For all the test sections, the breaking
and seating procedure resulted in an increased surface deflection, a
reduced spreadability, and an increased W1/W5 ratio. The increased
surface deflection was from a loss of the flexural strength. The lower
spreadability and higher W1/W5 of the B/S pavements indicate a
behavior similar to flexible pavements (5). These values on the
SR-4 sections, on which a pile hammer was used, were considerably

SR-4, Stations 217100 to 267100 (crack density along roadway).

Arudi et al.

59

FIGURE 4

SR-4, Stations 105150 to 160150 (crack density along roadway).

lower than those on I-71 on which a guillotine hammer was used.


This finding was caused by the higher degree of breakage in these
sections. The structural response of the sections was fairly consistent during the study period.
After the winter of 1994, cracking was noticed in all control
sections, but only two cracks were noticed in the 4 miles of B/S

sections. These cracks were in areas where the breaking was


not done to the desired specifications. All these cracks were of
low severity. The I-71 sections were overlaid in the fall of 1992
and the SR-4 sections in the fall of 1993. The I-71 sections
survived the winter of 1993 without developing any cracks.
However, the winter 1993 was mild, whereas the winter of

FIGURE 5 I-71, Stations 726163 to 779143 (variation of


structural parameters with time).

FIGURE 6 I-71, Stations 35100 to 88100 (variation of


structural parameters with time).

60

FIGURE 7 SR-4, Stations 217100 to 267100 (variation of


structural parameters with time).

1994 was very severe. The data collected from weather reports (6)
indicate very low temperatures persisting over a long period during the winter of 1994.
The position of the cracks on the AC overlay was compared with
the location of joints and cracks in the underlying concrete slabs. A
summary of these results is presented in Table 3.
Some of the cracks that appeared in the control section are
reflected from either joints or cracks in the PCC layer, while others
that span both lanes have no relation to the cracking of the underlying layer. Core samples taken at the location of the nonreflected
cracks indicated cracking in only the top few inches of the AC overlay. More studies are being conducted to investigate the causes of
these additional cracks.
Thus, it was concluded that breaking and seating concrete pavements delays reflection cracking.

Performance After Winter 1995


All the sections were revisited after the winter of 1995. On average,
there were six to eight new cracks on all the control sections.
Cracks also appeared on the two B/S sections on I-71. There were
no cracks on the B/S sections on SR-4. Figures 1 through 4 and
Table 3 present a comparative study of cracks on the control and
the B/S sections. It is interesting to observe that the sections broken with the pile hammer have been more successful in delaying
cracks than those broken with the guillotine hammer. This finding

TRANSPORTATION RESEARCH RECORD 1543

FIGURE 8 SR-4, Stations 105150 to 160150 (variation of


structural parameters with time).

is obviously caused by the higher degree of breakage achieved with


the pile hammer. However, the total number of cracks on the B/S
sections is still small compared with the number of cracks on the
control sections.

FACTORS THAT SIGNIFICANTLY AFFECTED


PERFORMANCE OF AC OVERLAYS
The primary variables introduced in this study are type of equipment for breaking and extent of breaking. The other variables present are traffic volume and AC overlay thickness.
Three types of breakers were used. Part of one section on
I-71 between Stations 35100 and 45100 was broken with a
2.4-m-wide guillotine hammer. The rest of the sections on I-71
were broken with two passes of a 1.8-m-wide guillotine hammer
in each lane. The two B/S sections on SR-4 were broken with a
pile hammer.
Breaking with the 2.4-m-wide hammer did not produce the
desired effect. Cracks in the longitudinal direction were hardly visible. The sections broken with the 1.8-m-wide hammer produced
cracking in both longitudinal and transverse directions. Breaking
was more extensive with the pile hammer compared with sections
broken with the guillotine hammer. The pile hammer produced
more uniform transverse and longitudinal cracks although pavements broken with the guillotine hammer exhibited severe breaking where drops overlapped, usually in the middle of the lane. Both

Arudi et al.

61

TABLE 3 Summary of Cracks on AC Overlay

the 1.8-m guillotine hammer and the pile hammer produced slab
fragments of the desired size. Breaking with all types of hammers
resulted in thorough slab cracking, but the reinforcement was damaged more by the pile hammer.
Breaking and seating concrete pavements before AC overlay had
the following effects:

Increase in surface deflection


Reduction in spreadability
Loss of flexural strength
Delay in reflection cracking
Reduction in number of reflection cracks

The difference in the mean values of the structural parameters


investigated for the B/S sections and the control sections was
found to be statistically significant (5). There is no evidence of
higher maximum deflections on sections broken with the pile
hammer compared with those broken with the guillotine hammer.
The spreadability values of broken and seated pavements were
lower than the values for the control sections. Concrete pavements,
in general, exhibit higher spreadability than flexible pavements.
The lower spreadability of the B/S sections indicates a behavior
similar to flexible pavements. The spreadability values of sections
on SR-4, on which a pile hammer was used, were considerably
lower than those on I-71, on which a guillotine hammer was used.
This finding is because of the higher degree of breakage in these
sections.
Breaking and seating resulted in higher W1/W5 values compared
with the control sections. Also, SR-4 sections had very high W1/W5

ratios. This result is to be expected because these sections, broken


with the pile hammer, were almost rubblized.
Reflection cracking was observed in all the control sections monitored in this study. On I-71 sections, the first set of cracks was
noticed about 15 months after construction of the AC overlay.
On SR-4 sections, cracks were observed within 7 months of AC
overlay construction. The cracking in both sections occurred after
the severe winter of 1994. No cracking was noticed on any of
the broken and seated sections during this time. However, two
cracks were noticed on the B/S section on I-71, which was broken
with the 2.4-m-wide hammer. This was because the slabs were
not broken extensively. Breaking and seating not only delayed
cracking on the AC overlays but also resulted in a reduced
number of cracks.
Traffic intensity, soil type, and AC thickness had no effect on
performance with respect to either structural effectiveness or
development of reflection cracking. The construction of the I-71
sections was completed in the fall of 1992 while the sections on
SR-4 were completed in the fall of 1993. Reflection cracks on the
SR-4 section appeared after the first winter, whereas cracks in sections on I-71 did not appear until the second winter. However, the
first winter after the completion of I-71 was normal, whereas the
1994 winter was very severe. The early appearance of reflection
cracks on control sections of SR-4 is therefore attributed to the
severity of the winter of 1994 instead of to the age or thickness of
the overlay.
It is thus observed that type of breaking equipment and extent of
breaking are the most important factors governing the early behavior of AC overlays on B/S sections.

62

TRANSPORTATION RESEARCH RECORD 1543

SUMMARY AND CONCLUSIONS

REFERENCES

The following conclusions are drawn on the basis of the results of


a 3-year study of a controlled B/S research project.

1. Thompson, M. R. NCHRP Synthesis of Highway Practice 144: Breaking/


Cracking and Seating Concrete Pavements. TRB, National Research
Council, Washington, D.C., March 1989, 39 pp.
2. Pavement Consultancy Services. Guidelines and Methodologies for the
Rehabilitation of Rigid Highway Pavements Using Asphalt Concrete Overlays. National Asphalt Pavement Association, Beltsville, Md., June 1991.
3. Garnes, A., and B. McQuiston. Pavement Rehabilitation Study on the
National Highway System in Ohio: 19921993. Ohio Division, FHWA,
U.S. Department of Transportation, May 1994.
4. Resource International Inc. Implementation and Revision of Developed
Concepts for ODOT Pavement Management Program. Volume 2 of Pavement Condition Rating Manual. Report FHWA/OH-89/013. FHWA, U.S.
Department of Transportation, Feb. 1987.
5. Arudi, R. S., K. Kandula, I. A. Minkarah, and M. Bhupalam. Categorization of Asphalt Overlays on Broken and Seated Pavements. In Transportation Research Record 1473, TRB, National Research Council, Washington, D.C., 1995, pp. 131137.
6. National Climatic Data Center, Asheville, N.C.

Breaking and seating delayed reflection cracking on the AC


overlays.
The B/S sections exhibited significantly less reflection cracking than the control sections.
As observed from the FWD tests, breaking and seating
resulted in loss of structural capacity of the pavement.
Type of breaking equipment and extent of breaking have a
significant effect on the performance of AC overlays.

ACKNOWLEDGMENTS
The authors gratefully acknowledge the assistance of William F.
Edwards and Roger Green of ODOT for their help in conducting
this study.

The opinions and conclusions expressed in this report are those of the authors.
This report does not constitute a standard, specification, or regulation.
Publication of this paper sponsored by Committee on Flexible Pavement Construction and Rehabilitation.

You might also like