Professional Documents
Culture Documents
A. Holy sink
B. Lavatory
C. Baptismal shrine
D. Sacrarium (Your Answer)
Correct
Q.4) Tunnels shall have: the following except
A. A clear height of 0.6m above the pipe & shall be limited in length
to 1/2 the depth of the trench.
B. Driven pipes shall have at least one pipe size larger than the pipe to
be laid
C. Shall be back-filled in thin layers of 0.3m above the top of the pipe
with clean earth which shall not contain stones, boulders, cinders or
other materials which can damage or break the pipes or cause
corrosive action.(Your Answer)
D. None of the above
Correct
Q.5) the minimum cross sectional area at the seat of the control valve or the
supply pipe or tubing which feeds the device outlet. If two or more lines
supply one outlet, the effective opening shall be the sum of the crosssectional areas of the individual supply lines or the area or the single outlet,
whichever is smaller.
the sum of all the areas of the perforation of the strainer is equivalent to the
outlet area.
intervals for piping 38mm diameter & smaller & _______m intervals for
piping 51mm & larger in dia.
accessible may be of seamless drawn brass not less than Ga. 20 B&S or
______mm thk.
A. 0.90
B. 0.80 (Your Answer)
C. 0.70
D. 0.60
Correct
Q.14) All porcelain enamel surfaces on plumbing fixtures shall be
__________
A. Mold resistant
B. Acid resistant (Your Answer)
C. Corrosion resistant
D. None of the above
Correct
Q.15) All pipe determinations shall be based on eighty percent (___) the
reduced pressure.
A. 70%
B. 60%
C. 80% (Your Answer)
D. 90%
Correct
Q.16) ______________ must be supported at least every other joint except that
when the developed length between supports exceeds 1.2m, they shall be
provided at each joint.
Q.17) ____________
A. Steel tube
B. Plastic tube (Your Answer)
C. Aluminum tube
D. Concrete tube
Correct
Q.18) ________ m max. length of supply piping.
A. 61 (Your Answer)
B. 62
C. 63
D. 64
Correct
Q.19) If water closets or other plumbing fixtures are installed in the buildings
A. WASTE TANK
B. SEPTIC TANK (Your Answer)
C. SEWAGE DISPOSAL SYSTEM
D. NONE OF THE ABOVE
Correct
Q.20) Drainage pipes shall be run in practical alignments & at a uniform
slope between manholes of not less than ______________ toward the
point of disposal.
A. 22 degrees bend
B. 45 degrees bend
C. 60 degrees bend or other approved fittings of longer sweeps
D. 30 degress bend (Your Answer)
Correct
Q.22) All piping of plumbing systems shall be of durable ____________-
Q.23) a physical separation, which may be a low inlet into the indirect waste
receptor from the fixture, appliance or device indirectly connected
A. AIR SEPARATION
B. AIR BREAK (Your Answer)
C. AIR DEVISOR
D. NONE OF THE ABOVE
Correct
Q.24) a length of soil or waste stack corresponding in the general to a storey
height, but in no case less than 2.43m within which the horizontal
branches from one floor or storey of a building are connected to the
stack.
A. 1,2
B. 1,1 (Your Answer)
C. 2,1
D. 2,3
Correct
Q.26)
A. 45 wye branches
B. Combination wye & 1/8 bend branches
C. 30 wye bend (Your Answer)
D. Or other approved fittings of longer sweeps.
Correct
Q.27) Horizontal drainage lines connecting to other horizontal drainage lines shall
enter through the following given below except:
A. 45 wye branches
B. Combination wye & 1/8 bend branches
C. Or other approved fittings of longer sweeps.
D. 30 wye bend (Your Answer)
Correct
Q.28) Birth of plumbing profession in the Philippines
A. INTRAMUROS (Your Answer)
B. BARASOAIN
C. BATAAN
D. CEBU
Correct
Q.29) Vertical drainage lines connecting to other horizontal drainage line shall
enter through
A. 45 wye branches
B. Or other approved fittings of longer sweeps.
C. 60 degree branches or offsets (only for pipes installed in true
vertical position
D. 45 degree branches (Your Answer)
Correct
Q.30)
Correct
Q.33) In PROHIBITED FITTINGS & PRACTICES under this rule no
____________ shall be threaded.
A. GI soil pipe
B. Cast iron soil pipe (Your Answer)
C. PVC soil Pipe
D. None of the above
Correct
Q.34) Further, a _________ and bathtub or shower shall be installed to meet the
basic requirements of sanitation and personal hygiene.
A. SINK
B. LAVATORY (Your Answer)
C. BASIN
D. NONE OF THE ABOVE
Correct
Q.35) fixture directly connected to the drainage system shall be equipped with a
________.
A. VENTILATING SYSTEM
B. WATER-SEALED TRAP (Your Answer)
C. SOIL PIPES
D. WASTE PIPES
Correct
Q.36) Any such pipe or piping _______mm or larger in diameter may have a
slope of 10mm/m or 1% provided it is approved by Administrative
Authority
A. 100 mm
B. 102 mm (Your Answer)
C. 101 mm
D. 104 mm
Correct
Q.37) Water pipes & fittings with a lead content that exceed ____ shall be
prohibited & shall not be used in potable piping systems.
A. 8% (Your Answer)
B. 9%
C. 10%
D. 11%
Correct
Q.38) Water Closet & Urinal Tanks shall be equipped with a listed ________ &
shall be installed with the critical level at least 25mm above the full
opening of the overflow pipe.
A. Corporation cock
B. Gatevalve
C. Ballcock (Your Answer)
D. None of the above
Correct
Q.39) THE TOTAL NUMBERS OF SET OF SANITARY/ PLUMBING
PLANS REQUIRED BY THE BUILDING OFFICIAL WHEN
APPLYING FOR PERMIT
A. 4
B. 5
C. 3
D. 6 (Your Answer)
Correct
Q.40) THE SANITARY AND PLUMBING PERMIT WILL BE REVOKE
IF THE PROJECT HAS BEEN ABANDONED OR SUSPENDED
FOR HOW MANY DAYS
A. 120 (Your Answer)
B. 60
C. 30
D. 100
Correct
Q.41) The quantity of water required to be supplied to every plumbing fixture
shall be represented by ____________
A. Fixture Units FU
B. Fixture drain FD (Your Answer)
C. Fixture Trap FT
D. None of the above
Correct
Q.42) the minimum airgap for Effective openings not greater than 25mm in
A. 54mm
B. 53mm
C. 52mm
D. 51mm (Your Answer)
Correct
Q.47) The minimum air gap for Lavatories & other fixtures with effective
openings not greater than 13mm in diameter if not affected by wall
A. 25 (Your Answer)
B. 24
C. 23
D. 22
Correct
Q.48) The minimum air gap for Lavatories & other fixtures with effective
openingsnot greater than 13mm in diameter if affected by walls
A. 36mm
B. 37mm
C. 38mm (Your Answer)
D. 39mm
Correct
Q.49) The minimum air gap for Sinks, laundry trays, goosenecks bath faucets &
other fixtures with effective openings not greater than 19mm in diameter. if not
affected by wall
A. 40mm
B. 39mm
C. 38mm (Your Answer)
D. 37mm
Correct
Q.50) the minimum air gap for Sinks, laundry trays, goosenecks bath faucets &
other fixtures witheffective openings not greater than 19mm in diameter. if affected
by wall
A. 56mm
B. 57mm (Your Answer)
C. 58mm
D. 59mm
Correct
Q.51) THE EXPIRATION OF THE PERMIT FOR SANITARY /
PLUMBING WILL BE EXPIRED AFTER HOW MANY YEARS
FROM THE DATE OF ISSUANCE
A. 2
B. 1 (Your Answer)
C. 1.5
D. 3
Correct
Q.52) THE DRAWINGS, SPECIFICATION, CALCULATIONS AND ETC
FOR PLUMBING / SANITARY PERMIT WILL BE SIGNED BY
A a Registered & Licensed
A. DRAINAGE ENGINEER
B. MASTER PLUMBER (Your Answer)
C. SANITARY ENGINEER
D. ARCHITECT
Correct
Q.53) Restaurant kitchen & other special-use sink may be made of approvedtyped sheet steel not less than Ga.16 U.S. B&S or 1.6mm thk.
C. 25
D. 19 (Correct Answer)
Correct
Q.57) Inadequate water pressure water pressure less than _____ Kpa
A. 103 (Your Answer)
B. 104
C. 105
D. 106
Correct
Q.58) In Screwed Pipe - IPS shall be supported at approximately _______m
intervals for piping 19mm diameter & smaller & _______m intervals for
piping 25mm & larger in diameter.
A. 3.5 / 3.0
B. 3.0 / 3.5
C. 3.6/ 3.0
D. 3.0 / 3.6 (Your Answer)
Correct
Q.59) In Ground
A. 155
B. 152 (Correct Answer)
C. 153 (Your Answer)
D. 154
Correct
Q.62) For vertical piping,Screwed Pipe - Iron Pipe Size (IPS) shall be
supported at not less than every other storey
A. Drift
B. Height (Your Answer)
C. Level
D. Dimension
Correct
Q.63) For vertical piping, _________ - shall be supported at each storey or at
a maximum intervals of 3m o.c.
A. Lead tubing
B. Copper tubing (Your Answer)
C. Steel tubing
D. G.i. tubing
Correct
Q.64) For vertical piping, cast iron pipes- Bell & Spigot & Hubless pipe shall
be supported at_____ or closer.
A. Every 2 storey
B. Every storey (Your Answer)
C. Every 3 storey
D. Every 4 storey
Correct
Q.65) FOR THE SET OF SANITARY/ PLUMBING PLANS
Correct
Q.66) FOR THE SET OF SANITARY/ PLUMBING PLANS REQUIRED
BY THE BUILDING OFFICIAL WHEN APPLYING FOR PERMIT
HOW MANY SET OF DRAWINGS WILL BE PROVIDED FOR
THE ADMINISTRATIVE AUTHORITY
A. 1 (Your Answer)
B. 4
C. 3
D. 2
Correct
Q.67) FOR THE SET OF SANITARY/ PLUMBING PLANS
C. 3
D. 2
Correct
Q.71) Fixture unit of Urinal (pedestal or similar type)
A. 10 (Your Answer)
B. 15
C. 12
D. 9
Incorrect
Q.72) Fixture unit of Urinal (flush tank)
A. 2
B. 3 (Correct Answer)
C. 4
D. 5 (Your Answer)
Incorrect
Q.73) fixture unit of Water Closet (flush tank & flushometer-tank),
Hose Bibb or Sill Cock (standard type) private use
A. 2
B. 3 (Correct Answer)
C. 4
D. 5 (Your Answer)
Correct
Q.74) fixture unit of Water Closet (flush tank & flushometer-tank),
Hose Bibb or Sill Cock (standard type) public use
A. 5 (Your Answer)
B. 4
C. 3
D. 2
Correct
Q.75) fixture unit of Water Closet (economical flush) public use
A. 5 (Your Answer)
B. 4
C. 3
D. 2
Correct
A. ABS Acrylonitrile-Butadiene-Styrene
B. PVC (POLYVINYL CHLORIDE)
C. Vitrified clay pipe
D. A,b (Your Answer)
E. B,c
Correct
Q.82) consists of two independently acting internally or externally loaded check
valves, four properly located test cocks with connectors & two isolation
gate valves.
A. Metal sheath
B. Polybuthane sheath
C. Polyethylene sheath (Correct Answer)
D. Plastic sheath (Your Answer)
Correct
Q.88)
_____________
in
A. Supply piping
B. Vent piping (Correct Answer)
C. Drainage piping (Your Answer)
D. None of the above
Correct
Q.91) No _____________ shall be located in a room or compartment,
which is not properly lighted & ventilated.
A. CATCH BASIN
B. LAVATORY
C. BIBB
D. WATER CLOSET (Your Answer)
Correct
Q.92) In GRADE OF HORIZONTAL PIPING If it is impracticable to obtain such
slope due to the following conditions except,