You are on page 1of 6
Darras FOUNDATIONS L.L.C. 2S > (pps ge) obwlws Tel. : 00971 4 3934337 Fax : 00971 4 3934778 P.O. Box: 20605, Dubai - U.A.E. E- mail: dallas @emirates.net.ae vavig-rarerey: dale SAVIE-FATEWA: Qu PEI aga tetea: “Gye dallas @emirates.net.ae : 45/9! a0! CONSULTANTS: MAIN CONTRACTOR ‘SHORING DESIGN PROPOSED B+G+6+R RESIDENTIAL BUILDING FOR MR. MOHD. NOOR MAHMOOD MOHD. MASHROOM. PLOT NO. 421-194, AL WARQA FIRST, DUBAI, UA. MIS. AL AJMI ENGINEERING CONSULTANTS MIS, DUBAI EURO CONTRACTING CO. SHORING CONTRACTOR M/S. DALLAS FOUNDATIONS L.L.C. Revision D c 8 A Zea JOB No : PL-610 ‘GEO FOUNDATION GROUP LL.C.AAQ2013 Date : 7/9204 CA ea HSE pa DALLAS FOUNDATIONS L.L¢, PO. box 20605 Dube, LAE Prepared) Trial Checked By ‘Signature | tial Signature | inal MIS.AL AJMI ENGINEERING CONSULTANTS. ‘Approved BY Signature (C:\PLS10_SH_DUBAL_EURO :front-cover DALLAS rouornonsice (pps do clstass _paahes CONTENTS : A. INTRODUCTION A Scope of Work A2 Shoring Details B. COMPUTER ANALYSIS USING ReWaRD 2.5 c. DESIGN OF H-BEAM C.1 DESIGN OF CONCRETE PLANKS D. SOIL REPORT D.1 Extract from soil report E. REFERENCES F. REPORT FORMS F.1— Third Party Insurance F.2 Trade Licence (GEO FOUNDATION GROUP L.L.¢.AAG2013 Date : 7/5/2014 ©: \PL-610_SH_OUBAL_EURO : Contents DALLAS rowosnonsice lppigh obubwes (p2t > METHOD STATEMENT FOR SHORING WORKS: 1.0 INTRODUCTION: The Excavation required for the Proposed B+G+6 Residential Building for Mr. Mohd. Noor Mahmood Mohd. Mashroom Plot no. 421-194 Al Warga First, Dubai requiring permanent shoring system for protection of basement area @ neighbor construction side 5.0 m away from the shoring limit. Overall excavation depth will be -3.80 m. For the above shoring works, we are proposing permanent Soldier Piles shoring system using 457x191x74kg /m @ 1.60 m c/e from which our scope of work covers the only installation of shoring using Beams for an approximate excavation depth -3.80 m. 1.1. LOCATION AND PROTECTION OF EXISTING SERVICES BY MAIN CONTRACTOR: All the underground services falling in line the shoring system will be located by carrying out trial trenches up to max. 2.0 m below ground level. If any underground informed for future instruction. 1.2. WORKING PLATEFORM: Prior to the installation of the B-Beams, the site should be excavated and leveled as per requirements by the main contractor. The excavation should be sufficient to allow the shoring equipment access to each and every location. 1.3. SURVEY WORKS: A qualified survey by would carry out setting out surveying works. The plot line (building line) will be marked and the shoring line will be established as per Dubai Municipality approved shop drawings. Facility will be provided to the engineer for checking the points. DALLAS sounosronsitc (ppd) slolws (p> 2.0 INSTALLATION OF H-BEAM: 2.1 GENERAL: The shoring system with section 457 x 191 x 74kg/m @ 1.60me/e (beams length 8.0m) is proposed for retaining the excavation starting from 0.0m to a toe level at -8.0 m is required for a safe excavation depth up to -3.80m. Center -to-center distance between the adjacent H-Beams shall be 1.60 m as per the submitted design. 2.2. METHOD OF INSTALLTION: (For beam driving insertion) The H-Beam will be driven by ABI machine with Vibro hammer, beams are lifted in vertical position using ABI Machine. Beams location is to be set as per approved design at site. Leveling of beams is to be done prior to beam driving to ensure the verticality of each driven pile. 2.3. INSTALLATION OF CONCRETE PANELS: ‘The installation of concrete panels between the H-Beams walls to be done by main contractor following appropriate procedure. After the installation of all the beams is completed, excavation shall be carried out up to the required level on several stages, after each stage, for the stability of the H- beams wall, itis important that the panel will be install in steps directly after the excavation (high free stands of the soil especially over a longer period must be avoided). The concrete panels must be fixed tight to the H-beams and pressed against the undisturbed soil. Any soil movements behind the wall from over excavation or too high free stands are refilled in compacted layer. 3.0 DESIGN OF SHORING SYSTEM: The design is based on the available soil report and according to our submitted calculations. ‘SHEET #07 a DALLAS rounosnonsice (pps) sluluws (pts / PROJECT : PROPOSED B+G+6+R RESIDENTIAL BUILDING LOCATION PLOT NO. 421-194, AL WARQA FIRST, DUBAI, UAE. CONSULTANTS —_: M/S.AL AJMI ENGINEERING CONSULTANTS SOLDIER PILE DESIGN FOR PLOT SIDE SHORING WITH SOLDIER PILES AT 1.6 M C/C FOR A MAX. EXC. DEPTH 3.8 M L ‘SURCHARGE 20 KN/M2 DESIGN OF SECTION Excavation Depth . 3,80 m (from EGL 0.0M ) ‘Maximum Spacing of H-Beam . 1.60 m cle ‘Maximum Moment per section = 169.9 kN-m/m (ReWARD 2.5) Ultimate Factor . 14 Ultimate Moment per section = 380.6 kNm Sx required . 380.6 x 1000 25 = 1,384 om? Sx Provided a 1,458 om? > 4,384 om? OK, DEPTH OF EMBEDMENT (With reference to Elev 0.0) Zero BM at Elev. . -6.00 m (ReWARD 2.5) Embedment . 6.00 - 3.60 . 2.20 m Factor of safety : 14 Embedment Required . 220 x14 . 3.08 m Length of section required - 3.08 +3.80 : 6.88 m |1- Beam 8.0 m ong GEO FOUNDATION GROUP LL AAQI2013 Date: 7/3/2014 (G1PL.610_SH_DUBA_EURO:Des of Section (S201-1) SHEET #08, a DALLAS rowoxronsicc (pp db) olulwaa parts PROJECT : PROPOSED B+G+6+R RESIDENTIAL BUILDING LOCATION + PLOT NO. 421-194, AL WARQA FIRST, DUBAI, U, CONSULTANTS : —MIS.AL AJMI ENGINEERING CONSULTANTS. DESIGN OF CONCRETE PLANKS @ 1,6 M SPACING CIC SHORING WITH SOLDIER PILES AT 1.6 M CIC FOR A MAX. EXC. DEPTH 3.8 M SURCHARGE 20 KN/M2 Maximum Horizontal Pressure at Excavation Depth 3.8 m = 23.65 kN/m2 (ReWARD 2.5) Span 1.60 Uniform load on the planks = 14.78 kNim? Plank Height = 500 mm Maximum Moment/Span = 44.78 x0.50x2.56 8 = 3.78 kNm Ultimate Moment = 378 x14 = 5.30 KNm Using Precast Panels of size 500 mm width x 100 mm thicki Man 5.30 kN b 500 mm h 100 mm Cover 30 mm bar dia 12mm ¢ 64 mm fo . 30 Nimm* f, 425 Nimm? M. 0.086 dha, z 57.4 mm 085d = = =~ 60.8 mm z 57.4 mm As req 251 mm? No of bars 3.00 Spacing Require: 443 mm Use T 12 atspacing of 130 mm cic - ong direction Use T8 at spacing of 130 mm cic - short direction GEO FOUNDATION GROUP LL.C.AA@2013 Date : 7192014 C:APL-510_SH_DUBAL_EURO Plank Design (Sec 1-1)

You might also like