Professional Documents
Culture Documents
Date: 18.12.2010
TENDER DOCUMENT
FOR
INSTALLATION OF PILED SUPPORTS FOR 48-INCH
OFFSHORE PIPELINE
OF
SINGLE POINT MOORING SYSTEM PROJECT
OF
VISAKH REFINERY
OF
HINDUSTAN PETROLEUM CORPORATION LIMITED
(HPCL)
RFQ NO: 21534102-501-ITB-021
Date: 18.12.2010
- 1 of 237 -
Rev 0
Date: 18.12.2010
INDEX
SECTION
NO:
TABLE OF CONTENTS
INSTRUCTION TO BIDDERS
SCOPE OF WORK
SCHEDULE OF PRICE
TABLE-1
FORMAT A
CHECK LIST
ANNEXURES
Annexure -1
Acknowledgement
Annexure-2
Undertaking by bidder
Annexure -3
Annexure -4
Annexure-5
Terms Of Payment
Annexure-6
Loading factors
11
INTEGRITY PACT
12
HPCL FORMATS
*****************
- 2 of 237 -
Rev 0
Date: 18.12.2010
SECTION 1
NOTICE INVITING TENDER (NIT)
- 3 of 237 -
Rev 0
Date: 18.12.2010
Rev 0
2)
RFQ Name
3)
4)
5)
6a)
Tender Fee
Tender issue date
Bid Due Date
Bid opening date and time
(PART I UNPRICED)
6b) Venue
7)
8)
- 4 of 237 -
9)
Date: 18.12.2010
Rev 0
A) TECHNICAL CRITERIA
I.
Bidder shall have marine construction experience in any of the fields such as
civil, fabrication and installation of structures, piling, offshore installation, pipeline
supports, platforms, rigs, jetty etc. in water depths ranging from 5m to 15m.
Bidder should have experience or back to back arrangements for diving experience
covering installation and inspection of pipeline, civil and steel structures in water
depths ranging from 5m to 15m.
Bidder preferably be the vessel owner and operator of marine spread with piling
equipment or have confirmed arrangement for hire of such vessels for the
proposed work. For which bidder shall submit documentary proof of such
arrangement along with their bid.
Bidder shall have experience of having successfully carried out and completed
similar work(which is also mentioned in clause 2.1-A-I) during the last 7 years
ending last day of the month previous to the one in which applications are invited,
which experience should be any one of the following:
II.
III.
IV.
a.
Three similar completed works, each costing not less than Rs. 4 Crores for Indian
Bidders
or
b. Two similar completed works, each costing not less than Rs. 5 Crores for Indian
Bidders .
or
c. One similar completed work costing not less than Rs. 8 Crores for Indian Bidders
Bidders fulfilling all above Technical criteria (i.e Section 2.1-A)-I to Section 2.1-A)IV .)will only be considered for further evaluation.
B) FINANCIAL CRITERIA
Average Annual Financial Turnover during the last 3 years, ending 31st
March, of the previous financial year, should be at least Rs. 3 Crores for Indian
Bidders
Bidders fulfilling both the above Technical and Financial criteria will only be
considered for further evaluation.
(Detailed Pre-qualification criteria along with other requirements is given in Section 2
of tender documents)
- 5 of 237 -
Date: 18.12.2010
Rev 0
- 6 of 237 -
Date: 18.12.2010
Rev 0
18) Bidders are requested to acknowledge receipt of this bid document along with all
enclosures and send their acknowledgement as per Annexure 1.
Bidders may send their confirmation atleast 7 days prior to bid closing date regarding
their participation in the subject bid. The correspondence address is as follows:
Mr. Prakash Wankhade
Senior Manager-Materials,
Central Engineering,
Petroleum House,
Hindustan Petroleum Corporation Limited,
17, Jamshedji Tata Road,
Mumbai- 400 020, India.
Telephone
: 0091 22 22863633
e-mail
: pwankhade@hpcl.co.in
Mr. M Mohan
Project Manger
M/S INTEC Asia Pacific Sdn Bhd
19th Floor, Sunway Tower 2,
86, Jalang Ampang,
50450 Kuala Lumpur, Malaysia
Tel: + 603 2032 2488
Email: 21534102.visakh@intecsea.com
19) Bidder to note that Grievance Redressal Mechanism is available for all such
bidders participating in the tender. The details of the Grievance Redressal
Mechanism are available on HPCL website
www.hindustanpetroleum.com.
All communications in this regard to be sent to Head-Materials, Central Engg.
Co-ordinator, Grievance Redressal Cell, Central Engineering, Hindustan
Petroleum Corpn. Ltd., Petroleum House, 6th Floor, 17 J R D Tata Road,
Mumbai 400 020.
The names of the Independent External Monitors appointed for our HPCL are
given below :
1. Mrs Ranjana Kumar
2. Shri D Chatterjee
- 7 of 237 -
Date: 18.12.2010
SECTION 2
- 8 of 237 -
Rev 0
2.0
Date: 18.12.2010
Rev 0
GENERAL
Bidders are requested to submit documentary proof in support of meeting the prequalification criteria mentioned below, along with PART-I UNPRICED part of the
bid.
2.1
PRE-QUALIFICATION CRITERIA
A)
TECHNICAL CRITERIA
I. Bidder shall have marine construction experience in any of the fields such as
civil, fabrication and installation of structures, piling, offshore installation, pipeline
supports, platforms, rigs, jetty etc. in water depths ranging from 5m to 15m.
II. Bidder should have experience or back to back arrangements for diving
experience covering installation and inspection of pipeline, civil and steel structures
in water depths ranging from 5m to 15m.
III Bidder preferably be the vessel owner and operator of marine spread with piling
equipment or have confirmed arrangement for hire of such vessels for the proposed
work. For which bidder shall submit documentary proof of such arrangement along
with their bid.
IV. Bidder shall have experience of having successfully carried out and completed
similar work(which is also mentioned in clause 2.1-A-I) during the last 7 years
ending last day of the month previous to the one in which applications are invited,
which experience should be any one of the following:
a Three similar completed works, each costing not less than Rs. 4 Crores for Indian
Bidders
or
b. Two similar completed works, each costing not less than Rs. 5 Crores for Indian
Bidders .
or
c. One similar completed work costing not less than Rs. 8 Crores for Indian Bidders
Bidders fulfilling all above Technical criteria (i.e Section 2.1-A)-I to Section 2.1-A)IV .)will only be considered for further evaluation..
B)
FINANCIAL CRITERIA
Average Annual Financial Turnover during the last 3 years, ending 31st
March, of the previous financial year, should be at least Rs. 3 Crores for Indian
Bidders and
- 9 of 237 -
Date: 18.12.2010
Rev 0
Bidders fulfilling both the above Technical and financial criteria will only be
considered for further evaluation.
2.2
OTHER REQUIREMENTS
2.2.1 Technical : The following other requirements shall be applied for the prequalification of Bidders:
a) Bidder must indicate in the bid the detailed execution methodology for the proposed
work. The proposed methodology shall be subject to review and approval by Owner/
PMC.
b) Bidders must necessarily furnish documentary evidence to substantiate experience,
claimed by them with specific reference to responsibility in Installation, Value of job
completed by copies of the purchase orders and Certificate of Completion for similar
projects of this nature from respective Owner / Client etc.
c) BIDDER submitting their PQ details shall not be under liquidation, court receivership or
similar proceedings.
d) BIDDER must ensure that the following activities are performed by them directly and
not sub-contracted:
i)
Project Management.
ii)
iii)
Construction Management.
- 10 of 237 -
Date: 18.12.2010
Rev 0
ASSOCIATE
If the bidder proposes to take up the package jointly with an Associate (whether Indian
or Foreign) or they relies upon the experience of such an Associate, with whom the
bidder has entered into a tie-up/teaming agreement/MOU, the bidder shall submit the
following details/documents:
i)
ii)
iii)
iv)
Parties who are affiliates of one another can decide which Affiliate will make a bid.
Only one affiliate may submit a bid. Two or more affiliates are not permitted to make
- 11 of 237 -
Date: 18.12.2010
Rev 0
separate bids directly or indirectly. If 2 or more affiliates submit a bid, then any one or
all of them are liable for disqualification. However upto 3 affiliates may make a joint bid
as a consortium, and in which case the conditions applicable to a consortium shall apply
to them.
Affiliate of a Party shall mean any company or legal entity which:
(a) controls either directly or indirectly a Party, or
(b) which is controlled directly or indirectly by a Party; or
(c) is directly or indirectly controlled by a company, legal entity or partnership which
directly or indirectly controls a Party.
Control means actual control or ownership of at least a 50% voting or other
controlling interest that gives the power to direct, or cause the direction of, the
management and material business decisions of the controlled entity.
4. Bids may be submitted by:
a) a single person/ entity (called sole bidder);
b) a newly formed incorporated joint venture (JV) which has not completed 3
financial years from the date of commencement of business;
c) a consortium (including an unincorporated JV) having a maximum of 3 (three)
members;
d) an Indian arm of a foreign company.
5. Fulfilment of Eligibility criteria and certain additional conditions in respect of each of
the above 4 types of bidders is stated below, respectively:
a) The sole bidder (including an incorporated JV which has completed 3 financial
years after date of commencement of business) shall fulfil each eligibility criteria.
b) In case the bidder is a newly formed and incorporated joint venture and which has
not completed three financial years from the date of commencement of business,
then either the said JV shall fulfil each eligibility criteria or any one constituent
member/ promoter of such a JV shall fulfil each eligibility criteria. If the bid is
received with the proposal that one constituent member/ promoter fulfils each
eligibility criteria, then this member/promoter shall be clearly identified and he/it
shall assume all obligations under the contract and provide such comfort
letter/guarantees as may be required by Owner. The guarantees shall cover inter alia
the commitment of the member/ promoter to complete the entire work in all
respects and in a timely fashion, being bound by all the obligations under the
contract, an undertaking to provide all necessary technical and financial support to
the JV to ensure completion of the contract when awarded, an undertaking not to
withdraw from the JV till completion of the work, etc.
c) In case the bidder(s) is/are a consortium (including an unincorporated JV), then
the following conditions shall apply:
1) Each member in a consortium may only be a legal entity and not an individual
person;
2) the Bid shall specifically identify and describe each member of the consortium;
- 12 of 237 -
Date: 18.12.2010
Rev 0
3) the consortium member descriptions shall indicate what type of legal entity the
member is and its jurisdiction of incorporation (or of establishment as a legal\
entity other than as a corporation) and provide evidence by a copy of the articles
of incorporation (or equivalent documents);
4) One participant member of the consortium shall be identified as the Prime
member and contracting entity for the consortium;
5) this prime member shall be solely responsible for all aspects of the Bid/Proposal
including the execution of all tasks and performance of all consortium
obligations;
6) the prime member shall fulfil each eligibility criteria;
7) a commitment shall be given from each of the consortium members in the form
of a letter signed by a duly authorized officer clearly identifying the role of the
member in the Bid and the members commitment to perform all relevant tasks
and obligations in support of the Prime/lead member of the Consortium and a
commitment not to withdraw from the consortium;
8) No change shall be permitted in the number, nature or share holding pattern of
the Consortium members after pre-qualification, without the prior written
permission of the Owner.
9) No change in project plans, timetables or pricing will be permitted as a
consequence of any withdrawal or failure to perform by a consortium member;
10) No consortium member shall hold less than 25% stake in a consortium;
11) Entities which are affiliates of one another are allowed to bid either as a sole
bidder or as a consortium only;
12) Any person or entity can bid either singly or as a member of only one
consortium.
d) In case the bidder is an Indian arm (subsidiary, authorized agent, branch office or
affiliate) of a foreign bidder, then the foreign bidder shall have to fulfill each
eligibility criteria. If such foreign company desires that the contract be entered into
with the Indian arm, then a proper back to back continuing (parent company)
guarantee shall be provided by the foreign company clearly stating that in case of any
failure of any supply or performance of the equipment, machinery, material or plant
or completion of the work in all respects and as per the warranties/ guarantees that
may have been given, then the foreign company shall assume all obligations under
the contract. Towards this purpose, it shall provide such comfort letter/guarantees as
may be required by Owner. The guarantees shall cover inter alia the commitment of
the foreign company to complete the entire work in all respects and in a timely
fashion, being bound by all the obligations under the contract, an undertaking to
provide all necessary technical and financial support to the Indian arm or to render
the same themselves so as to ensure completion of the contract when awarded, an
undertaking not to withdraw from the contract till completion of the work, etc.
- 13 of 237 -
Date: 18.12.2010
Rev 0
In the absence of above information in the PQ bidding document, the bid is liable
to be rejected.
- 14 of 237 -
Date: 18.12.2010
SECTION 3
INSTRUCTION TO BIDDERS
- 15 of 237 -
Rev 0
Date: 18.12.2010
TABLE OF CONTENTS
3.0
3.1
DEFINITI0NS
3.1.1
COST OF BIDDING
3.1.2
BID FEE
3.1.3
3.1.4
3.1.5
3.1.6
LANGUAGE OF BIDS
3.1.7
CORRECTIONS IN BID
3.1.8
3.1.9
PROCESS TO BE CONFIDENTIAL
3.1.10
WRONG INFORMATION
3.1.11
CLARIFICATION OF BIDS
3.1.12
COMPANY DOCUMENTS
3.1.13
SITE VISIT
3.1.14
PRE-BID MEETING
3.1.15
3.1.16
3.1.17
FIRM OFFER
3.1.18
3.1.19
INDIAN LAWS
3.1.20
3.2
TECHNICAL REQUIREMENTS
3.2.1
3.2.2
3.2.3
TECHNICAL SUBMISSION
3.3
3.3.1
GENERAL
- 16 of 237 -
Rev 0
Date: 18.12.2010
3.3.2
SIGNING OF BIDS
3.3.3
3.3.4
3.3.5
BID VALIDITY
3.3.6
BID OPENING
3.3.7
3.3.8
3.3.9
3.3.10
3.3.11
NOTIFICATION OF AWARD
3.3.12
3.3.13
SECURITY DEPOSIT
3.3.14
- 17 of 237 -
Rev 0
3.0
Date: 18.12.2010
Rev 0
a.
b.
c.
d.
The Tender/ Bid shall mean the tender / bid submitted by the CONTRACTOR
for acceptance by OWNER.
e.
f.
g.
h.
- 18 of 237 -
Date: 18.12.2010
Rev 0
i. The SUB-CONTRACTOR shall mean any person or firm or company (other than
the CONTRACTOR) to whom any part of work has been entrusted by the
CONTRACTOR, with the written consent of the Engineer-in-Charge, and the Legal
Representatives, Successors and permitted Assigns of such person, firm or
Company.
j. The WORK shall mean and include all things, matters and facilities to be
surveyed, designated, engineered, procured, fabricated, loaded out, tied down, sea
fastened, towed out, transported, installed, tested, commissioned made good and
guaranteed by contractor in accordance with the CONTRACT and shall include all
extras, additional, altered, or substituted works as required for the purpose of the
CONTRACT.
k. The CONTRACT shall mean the agreement between OWNER and
CONTRACTOR for the execution of the WORK including therein all documents
such as the Notice Inviting Tender (NIT), Instructions to Bidders, General
Conditions of Contract, Special Conditions of Contract, Specifications, Drawings,
General Requirements, Time Schedule, Schedule of Prices, Letter of Acceptance of
Tender, Agreed Variations, if any etc.
l. The CONTRACT DOCUMENT shall mean collectively the Tender/Bid
Documents, Drawings, Specifications, General Conditions of Contract, Special
Conditions of Contract, Schedule of Rates/Prices, Instruction to Bidders, Letter of
Acceptance of Tender, Agreed Variation, if any and other documents constituting the
Tender and acceptance thereof.
m. CONSTRUCTIONAL PLANT/EQUIPMENT shall mean means all Plants,
Barges, Vessels/Floating crafts, equipments, tools, appliances, things, facilities,
machinery, apparatus of whatever nature needed, in or about the work or temporary
works (as hereinafter defined) or execution of works covered under the contract but
does not includes materials or other things intended to form or forming part of the
works.
n. TEMPORARY WORK shall mean all temporary works of every kind required in
or about the execution, completion or maintenance of the WORK.
o. SPECIFICATIONS shall mean all directions, various technical specifications,
provisions and requirements attached to the CONTRACT, which pertain to the
method and manner of performing the WORK to the quantities and qualities of the
WORK and the materials to be furnished under the CONTRACT for the WORK as
may be amplified or modified by Owner/PMC. Drawings for the performance of the
CONTRACT in order to provide the unforeseen conditions or in the best interests of
- 19 of 237 -
Date: 18.12.2010
Rev 0
the WORK. It shall also include the latest edition including all addenda/corrigenda
of relevant Specifications and Codes.
p. DRAWINGS shall include maps, plans, sketches and tracings or prints thereof
with any modifications approved by writing by the owner/PMC/Engineer-in-Charge
and such other Drawings as may from time to time be furnished or approved in
writing by the Owner/PMC/Engineer-in-Charge.
q. SITE shall mean the land and water and other places on, under in or through
which the work is to be carried out and any other lands, water or places provided by
Owner for the purpose of the CONTRACT together with any place designated in the
CONTRACT as forming part of the SITE.
r. Notice in Writing or Written Notice, shall mean a notice written, typed or
printed form sent (unless delivered personally) or otherwise proved to have been
received by registered post / courier / fax to the last known private or business
address or registered office of the CONTRACTOR and shall be deemed to have been
received in the ordinary course of post as if it would have been delivered.
s. The COMPLETION CERTIFICATE / PROVISIONAL ACCEPTANCE shall
mean certificate to be issued by the PMC/Engineer-in-Charge when the WORK has
been completed as per the CONTRACT.
t. The FINAL CERTIFICATE in relation to the WORK shall mean the certificate
regarding the satisfactory compliance of the various provisions of the CONTRACT
by the CONTRACTOR issued by the PMC/Engineer-in-Charge after the period of
liability is over.
u. Approved shall mean approved in writing including subsequent written
confirmation of previous verbal approval and Approval means approval in writing
including as aforesaid.
v. The Period of Liability in relation to a WORK means the specified period from
the date of completion of WORK as indicated in completion certificate up to the date
of issue of final certificate during which the CONTRACTOR stands responsible for
rectifying all defects that may appear in the WORK.
w. The Alteration/Variation Order means an order given in writing by the
PMC/Engineer-in-Charge to effect additions to or deletions from and alterations in
the WORK.
- 20 of 237 -
Date: 18.12.2010
Rev 0
x. Fax of Acceptance shall mean the first intimation by FAX by OWNER to the
successful bidder whose tender has been accepted. The date of issue of the Fax of
acceptance shall be reckoned as the commencement date of the contract.
y. Letter of Acceptance shall mean an intimation by a Letter to Tenderer that the
Tender has been accepted in accordance with the provisions contained therein.
z.
aa. Construction Season means that portion of the year between 1st December of one
year and last day of February of the next year both days inclusive when weather is
generally good for offshore construction activities because the occurrence of violent
storms and/or monsoons is least likely.
bb. Construction Superintendent(s) means those person(s) designated in writing by
the contractor to the COMPANY/PMC as being in full charge of each spread
performing works at the site.
cc. Day means a Calendar day of twenty four (24) consecutive hours beginning at
0000 hrs (midnight) and ending at 2400 hrs (midnight) as referred to local time at the
site.
dd. Demobilisation of any Spread means removal of all that spread from the site and
clean up and restoration as stipulated in the contract, as applying to that part of the
site in which that spread was employed.
ee. Demobilisation of the Contractor means removal of all things forming part of
the Mobilisation of the contractor including all temporary facilities, return of
personnel and equipment and the clean up and restoration of the site as required in
this contract.
ff. Guarantee means the period and
warranty/guarantee in respect of the works.
other
conditions
governing
the
gg. Inspector(s) means the person or persons of independent agency designated by the
COMPANY in writing to the contractor to observe test, record and report to the
COMPANY/PMC quality surveillance of the contractors work.
- 21 of 237 -
Date: 18.12.2010
Rev 0
hh. Kick-off Meeting means a meeting convened by the COMPANY to discuss and
finalise the work execution plan and procedures with the contractor.
ii. Mechanical Completion All equipments, pipelines etc have been installed and
tested by the CONTRACTOR in accordance with PROJECT specifications /
drawings, etc and is ready for pre-commissioning.
jj. Pre-Commissioning includes checking and testing of the equipment, machinery
etc. following MECHANICAL COMPLETION necessary to enable the PROJECT
to be ready for COMMISSIONING including full system leak test, SPM
installation and allignment check etc that are made by the CONTRACTOR as
required by the contract and making them ready for use.
kk.
ll.
Monsoon Season means that portion of the year between 16th June through 15th
September (both days inclusive) when monsoon, storms and high seas are of such
frequency and intensity at offshore site location that construction work cannot be
scheduled with any assurance.
oo.
Punch list means those minor items/jobs relating to works outstanding at the
time of pre-commissioning which do not affect the normal operations of the
COMPANY and which have been mutually agreed by the COMPANY/PMC and
the Contractor to be carried out/further completed (within a fixed time frame) by
the contractor to the satisfaction of the COMPANY/PMC in accordance with the
contract.
pp. Scheduled Completion Date means a date when the completion of entire works is
scheduled to be achieved in accordance with the construction schedule. The
- 22 of 237 -
Date: 18.12.2010
Rev 0
scheduled completion date for entire works of this project shall be as per section
4.7.5 of Special Conditions of Contract.
qq. Spread shall mean that combination of construction equipment including all
necessary work barges, material barges, supporting tugs etc. and whatever is
required to execute the works and personnel as defined in the contract and Schedule
of Rates and Prices capable of performing specific portion of the work e.g. Derrick
barge spread, hook-up barge spread etc.
rr. Third Party means any group, agency, person or persons who may be engaged in
activity associated with the work specified but who shall remain at arms length from
the work and who shall not have a direct responsibility or authority under the terms
of this contract, or any contractual relationship to the COMPANY, the contractor or
the contractors sub-contractor for the works.
ss. Vendor when used in connection with materials/plants/equipments/spare parts
procurement, means the equipment/materials manufacturer, supplier (authorized and
approved by the equipment(s) manufacturer) of materials/plants/equipments/ spare
parts to the contractor.
tt. Free issue materials are the Material which the COMPANY has agreed to supply
free of cost to the CONTRACTOR.
uu.
vv.
- 23 of 237 -
3.1
Date: 18.12.2010
Rev 0
GENERAL
The Instructions to Bidders have been detailed out in order to facilitate the Bidders
to submit their Bids considering various aspects spelt out in the subsequent
paragraphs. Instructions are in addition to the General Instructions to Bidders
regarding submission of tender given in Cl .3 of General Conditions of Contract
(GCC) and the instructions mentioned below will take precedence over the
instructions contained in Cl 3 of General Conditions of Contract to the extent of
contradiction.
- 24 of 237 -
Date: 18.12.2010
Rev 0
and a copy to
The Senior Manager-Materials,
Attn: Mr. Prakash Wankhade,
Central Engineering
Petroleum House,
Hindustan Petroleum Corporation Limited,
17, Jamshedji Tata Road, Mumbai- 400 020,India
Telephone
: 0091 22 22863633
e-mail : pwankhade@hpcl.co.in
The OWNER/PMC will respond in writing or by fax / e-mail to any such request for
clarification which they receive earlier than 7 days prior to the deadline for the
submission of bid. Any such inquiries and all replies there to will be circulated to all
bidders (without identifying the source of enquiry), unless a bidder request that such
enquiry is to be treated as confidential.
If confidentiality is requested,
OWNER/PMC shall decide, in its sole opinion and without giving reasons, whether
such inquiry should be treated as confidential. If the decision is not to treat the
- 25 of 237 -
Date: 18.12.2010
Rev 0
inquiry as confidential, Bidder will be given the option to withdrawing the inquiry or
confirming that the inquiry as well as the reply may be circulated to all Bidders. If
deemed appropriate by OWNER/PMC, a reply may be furnished or subsequently
repeated in the form of a written addendum to the bid document.
3.1.5 Addendum /Corrigendum To Bidding Documents
At any time prior to the deadline for opening of Bids, the Owner/PMC may, for
any reason whether at their own initiation or in response to a clarification requested
by a prospective Bidder(s), modify the Bidding Documents by the issuance of an
Addendum(s) / Corrigendum(s). Addendum(s) / Corrigendum(s) will be sent in
writing or by Fax/email to all Bidders and will be binding upon them. Bidder shall
promptly acknowledge receipt of these by Fax/email to the Owner/PMC and shall
enclose one copy of such Addendum(s) / Corrigendum(s) along with the Bid. All
such Addendum(s) / Corrigendum(s) issued shall form part of Bidding Documents.
All addenda/corrigenda issued during the time of bidding will be deemed to have
been taken into account in the Bid and such addenda/corrigenda will be incorporated
into the Purchase Order.
3.1.6 Language of Bids
The bid prepared by the Bidder and all correspondence and documents relating to the
bid, exchanged by the Bidder and the OWNER/PMC, shall be written in the English
language. All information in the Bid shall be in English language. Information in
any other language shall be accompanied with its translation in English. Failure to
comply with this condition may disqualify a BID. In the event of any
contradictions between meanings as derived from various languages of the BID,
the meaning as derived from English language copy of the BID shall govern.
3.1.7 Corrections in Bid
All changes / alterations / corrections in the BID shall be signed in full by the person
or persons signing the Bid, with date. No erasure, use of correction fluid and / or
overwriting is permitted. All blank spaces shall be filled in by typewriter or in ink
and inter-lineation, alterations or erasures, if any occur, shall be formally explained
- 26 of 237 -
Date: 18.12.2010
Rev 0
- 27 of 237 -
Date: 18.12.2010
Rev 0
- 28 of 237 -
Date: 18.12.2010
Rev 0
entirely at the Bidders risk and cost. BIDDER shall not take a team of more than 3
(Three) persons on such a visit.
BIDDER shall be responsible for obtaining and maintaining the necessary VISA /
permits and documentation with respect to entry, stay, work in INDIA, from the
relevant authorities. Even any exit / departure permits to leave India shall be
obtained by BIDDER.
All communication pertaining to the visit to the WORK SITE shall be to the address
indicated in this Section.
Note: Bidder has to make necessary arrangement for offshore visit, if required at
their own cost.
3.1.14 Pre-Bid Meeting
COMPANY/PMC will arrange a pre-bid meeting on 28.12.2010; 0930 Hours IST, a
pre-bid meeting concerning the RFQ, which shall be held at COMPANY/PMCs
sole discretion.
At least seven (7) working days prior to any meeting to be held upon Bidders
request, BIDDER shall submit to COMPANY/PMC an agenda of all subjects to be
discussed including a brief summary of each subject. BIDDER shall be permitted to
represent at this meeting by a maximum no of 3 (three) personnel, whose names and
designation shall be sent along with Bidders request for such a meeting.
COMPANY/PMC shall not permit any such clarification meeting to be used as a
means of negotiation with respect to the proposed CONTRACT and / or any of its
terms and conditions and the Price.
All expenses incurred by BIDDER for the clarification meeting(s) shall be at
Bidders own account.
3.1.15 Correction of errors in price bids
Owner/PMC will check Price Bids for any arithmetic errors in computation and
summation. Owner/PMC will correct errors as follows:
- 29 of 237 -
Date: 18.12.2010
Rev 0
Where there is a discrepancy between amounts in figures and words, the amount in
words will govern.
Where there is a discrepancy between the lump sum prices and price break up, in
that event lump sum prices will be considered final and break up of prices adjusted
accordingly.
3.1.16 Owner/PMCs Rights To Accept / Reject Any Or All Bids
Notwithstanding what is stated above, Owner/PMC reserves the right to accept or
reject any or all Bids at any time prior to the award of contract without assigning any
reason whatsoever and without thereby incurring any liability to the affected Bidder
for Owner/PMCs action.
3.1.17 Firm Offer
The prices quoted by bidders shall remain firm, fixed and valid until completion of
the Contract performance to the satisfaction of the Owner/PMC and will not be
subject to escalation / variation on any account. It may be noted that no deviation on
this account will be acceptable and offer not containing firm price will not be
considered for evaluation.
3.1.18 Form Of Bid / Additional Requirement
The forms given in the Bid Document are the minimum requirements to be furnished
by the bidder. Additional information, if required, can also be attached with the
form.
3.1.19 Indian Laws
Bidder is reminded that they will be subject to Indian laws, Government of India
rules and regulations/ guidelines, practices and conditions as applicable from time to
time. All matters shall be subject to jurisdiction of Indian courts only.
3.1.20 Local Conditions
It will be imperative for each bidder to fully inform themselves of all local
conditions and factors which may have any effect on the execution of the contract as
- 30 of 237 -
Date: 18.12.2010
Rev 0
particularly requested to familiarize themselves with the Income Tax & Withholding
Tax, Insurances, the Companies Act, the Customs & Excise duties, Service Tax,
Works Contract Tax and other related acts and laws prevalent in India.
- 31 of 237 -
3.2
Date: 18.12.2010
Rev 0
TECHNICAL REQUIREMENTS
BIDDER is requested to submit a Technical Proposal containing the information and
in the format as set out in the following attachments.
Attachment-A Project Execution Procedures
BIDDER shall provide description of its procedures for performing construction and
installation procedures and systems for Project management, Construction
management, Control, Testing, Commissioning etc.
Attachment-B Project Execution Plan
The Project Execution Plan shall be a discrete document which provides an outline
and explanation of the Bidders proposal approach towards organisation, planning,
management, and execution of the Installation of the Piles.
Attachment-C Technical Submission
BIDDER is required to submit a Technical Submission containing the minimum
information required by the COMPANY/PMC to allow it to analyse and evaluate the
technical basis of the Bidders Technical Proposal.
In preparing its Technical Proposal, BIDDER is required to review the BID
DOCUMENT and the Project Specifications in particular and bring to
COMPANY/PMCs attention any omissions, conflicts, or discrepancies.
The BIDDER shall submit copies of all the procedures it proposes to be used
in the performance of WORK. Preferentially, BIDDER should propose its
standard procedures with which its work force is already fully familiar, but
modified as necessary to meet the requirements if this RFQ. In developing the
procedures BIDDER should take full notice of COMPANY/PMCs requirements
- 32 of 237 -
Date: 18.12.2010
Rev 0
iii)
iv)
v)
- 33 of 237 -
Date: 18.12.2010
Rev 0
vi)
Copy of a typical site safety and health manual intended for use by the
labour force. It should be one that was used for a project constructed in
India or in a country with similar conditions.
- 34 of 237 -
Date: 18.12.2010
Rev 0
vii)
Qualifications of Vendors
Control of Procurement
Qualification of Subcontractors
Field Inspection
Quality Audits
Handling of Non-Conformance
It is the intent that Bidders standard quality assurance system should be used
on the PROJECT, modified as may be necessary to meet COMPANY/PMCs
requirements.
BIDDER shall provide evidence of the nationally or internationally
recognized standards upon which its system is based and for how long the
- 35 of 237 -
Date: 18.12.2010
Rev 0
3.2.2
3.2.2.1 General
This section describes the content and general format of the Bidders Project
Execution Plan. BIDDER shall include sufficient information to clearly describe its
plan with the understanding that this plan shall be expanded and supplemented if the
BIDDER is awarded this PROJECT.
3.2.2.2 Introduction
Defines purpose and Scope of the Plan and Project.
3.2.2.3 Project Organization
Organization chart showing the Bidders proposed project organization, both in its
home and branch engineering and procurement offices and at SITE, showing lines of
authority/responsibility and communication. Separate chart shall be provided for the
overall organization and for each engineering and procurement office and for field
construction including any office in India or at the WORK SITE. (If Applicable)
Define all major interfaces including those with Subcontractors and explain the
principles of interface management that will be applied. An interface is considered
major if a performance failure across the interface could have a serious disruptive
effect on PROJECT continuity, efficiency, or completion, or substantially increase
the risk of such disruption occurring.
Key project position shall be identified by title and brief job description.
Relationship and communications channels shall be defined, between Contractor,
Subcontractor (s), authorities etc.
- 36 of 237 -
Date: 18.12.2010
Rev 0
Project Manager
Construction Manager
Project Engineers
Construction Superintendents
For each nomination, BIDDER shall provide a resume showing the candidates
position or grade within the company, ability with the English language (oral and
written), age, experience with Bidders company and the experience of relevance to
this PROJECT, and the date of availability for this work.
BIDDER shall also provide a tabulation and chart showing the anticipated length of
assignment of all key personnel both in the engineering office and the field and shall
confirm that such personnel are available to work on the basis, and that key staff will
not be removed without COMPANY/PMCs approval in accordance with the
CONTRACT.
Same information as outlined above shall be supplied for each Subcontractor.
- 37 of 237 -
Date: 18.12.2010
Rev 0
- 38 of 237 -
Date: 18.12.2010
Rev 0
BIDDER shall indicate whether any of the following tasks will be subcontracted, and
if yes, BIDDER shall provide the subcontractors/vendors name, address, contact
name and scope of services and equipment:
Safety
3.2.2.8 Engineering
A description of how the BIDDER proposes to engineer and design the WORK
including the following aspects:
a)
b)
c)
d)
e)
f)
g)
- 39 of 237 -
h)
Date: 18.12.2010
Rev 0
of
3.2.2.9 Construction
I) A description of how and step by step procedures of the BIDDER plans to install
the Piles including the following aspects:
a) Details of all items of construction spreads and equipment, onshore and
offshore, and including all subcontractors equipment. Major equipment
details such as piling and backfilling shall be provided to the level of detail
commensurate with the technical and performance requirements stated or
implied in the COMPANY/PMCs Project Specifications.
b) Detailed explanation of the system proposed to ensure that all construction
equipment are adequate for the purpose and have been duly tested and
certified as required before use on WORK SITE.
c) The preparation and distribution of documents and systems to control the
WORK SITE organization, i.e. an outline WORK SITE coordination
procedure.
d) Plans for construction staffing in terms of direct labour and Subcontracts.
e) A detailed subcontracting plan including the numbers and sizes of
subcontracts, the type of subcontracts and the basis for soliciting bids.
f) A list of potential subcontractors.
g) Bidders procedure for evaluating the capability of potential subcontractors.
h) Basic subcontracting documents for soliciting bids including forms of bids,
agreement, bonds, and guarantees including intended terms and conditions.
i) Details of the security system BIDDER proposes to organize for all security
matters both inside and outside the WORK SITE including selection of
competent and effective security officers and personnel.
- 40 of 237 -
Date: 18.12.2010
Rev 0
Safe Working
Quality Control
- 41 of 237 -
Date: 18.12.2010
Rev 0
t) Emergency procedures.
3.2.2.10 Construction Support Facilities
BIDDER shall define all infrastructure and temporary construction facilities needed
to support the efficient completion of the PROJECT.
This section should address as applicable: construction camp, temporary buildings,
temporary utilities, communications, transportation, logistics, life support, roads,
dock, storage areas, etc.
3.2.2.11 Procurement Plans
BIDDER shall define how they intend to procure and supply the materials required
for permanent installation in the works.
3.2.2.12 Schedules and Milestone
Contains Bidders proposed project schedule, which is commensurate with the
project definition contained in the BID DOCUMENT. The project schedule must
demonstrate the Bidders understanding and interpretation of the requirements
contained in the PROJECT SPECIFICATION. Schedule shall be developed using
the work breakdown structure. Schedule should show key milestone dates and be
supported by Bidders preliminary assessment of technical and construction
manpower levels, peaks, and profiles.
Schedules shall be in network diagram form and sufficiently detailed to cover all
activities under this CONTRACT.
These schedules and the work breakdown structure shall become part of the
CONTRACT as Level I Schedules once accepted by COMPANY/PMC. These
Schedules shall reflect the commencement date occurring within the validity period
and show the logic and timing of execution of all WORK. The network schedule
form should also be summarized in bar chart form.
BIDDER shall propose milestone activities and dates covering all interfaces of the
WORK within the Bidders responsibility. These key milestone activities shall
cover the period of installation and construction and MECHANICAL
- 42 of 237 -
Date: 18.12.2010
Rev 0
- 43 of 237 -
3.2.3
Date: 18.12.2010
Rev 0
Mooring System
Lifting/Handling System
Accommodation/Offices
Piling Facilities
Backfilling
BIDDER shall describe the vessel(s) present and future planning utilisation for any
other project.
3.2.3.2 Back Filling
BIDDER shall identify the backfilling subcontractor (if any), along with the
following details:
- 44 of 237 -
Date: 18.12.2010
Dredger Type(s)
Mooring Systems
Operating Limitations
Support Vessels
Rev 0
- 45 of 237 -
Date: 18.12.2010
Rev 0
Pre-Installation Survey
Inspection Activity
- 46 of 237 -
Testing
Equipment
Date: 18.12.2010
Rev 0
3.2.3.9 Certification
BIDDER shall provide details for certification activities required for the completion
of the WORK for offshore.
3.2.3.10 Permits
BIDDER shall provide details of the permits required for offshore activities:
Marine Permits
Others
- 47 of 237 -
3.3
Date: 18.12.2010
Rev 0
PART I
The PART I termed as Un-priced Bid shall contain the following:
- 48 of 237 -
Date: 18.12.2010
Rev 0
All documentary evidence in support of the bidder having satisfied the prequalification criteria mentioned in SECTION 2.
Power of attorney in the name of person who has signed the bidding
documents.
Deviations (if any) - Bidders are requested to submit their bid strictly based on
the terms, conditions and specifications contained in the Bid document.
However, in case of any unavoidable deviations the same has to be specified in
separate sheet as per format attached as Annexure 3. HPCL/INTEC reserves
the right to evaluate the offer containing deviations having financial
implications after adding cost of such deviations as determined by
HPCL/INTEC. OWNER/PMC also reserves the right either for acceptance or
rejection of deviations if any, stipulated by the Bidders.
- 49 of 237 -
Date: 18.12.2010
Rev 0
One copy of Schedule of Price as per SECTION 6, prepared for this contract
with price blanked out.
Note: Price data should not be given at any part of this un-priced bid. Un-priced bid
containing price data is liable for rejection at the sole discretion of
HPCL/INTEC.
All these documents are to be put in a sealed envelope and super scribed as
Installation of Piled Supports for Offshore Pipeline of Single Point Mooring System
of Hindustan Petroleum Corporation Ltd RFQ No: 21534102-501-ITB-021
(CONFIDENTIAL) due on 17.01.2011 Technical/Un-priced Bid PART-I.
BID DOCUMENT (ORIGINAL) PLUS THREE COPIES OF ALL
ATTACHMENTS SHALL BE SUBMITTED IN SEALED COVERS AS
MENTIONED ABOVE.
All pages of the bidding document shall be duly signed by an authorized
representative of the bidder and further the company seal shall also be affixed on all
- 50 of 237 -
Date: 18.12.2010
Rev 0
pages as token of acceptance failing which HPCL/INTEC has the right to reject the
offer.
B) PART -II
The PART-II termed as Priced Bid shall contain SCHEDULE of PRICES as per
Section 6. This should be put in a sealed envelope and super scribed as Installation
of Piled Supports for Offshore pipeline of Single Point Mooring System of
Hindustan Petroleum Corporation Ltd RFQ No: 21534102-501-ITB-021
(CONFIDENTIAL) Priced Bid- PART -II.
Priced bid shall contain two sets of the PRICE SCHEDULE marked ORIGINAL &
DUPLICATE, duly signed and stamped on all pages. This shall not stipulate any
conditions. Price bid containing any stipulations is liable to be rejected at the
sole discretion of HPCL/INTEC.
The two sealed envelopes (Envelope 1 containing PART-1 (UNPRICED BID) and
Envelope 2 containing PART-II (PRICED BID) should be submitted together in
another sealed envelope. The single envelope shall be pasted with CUT OUT SLIP
as per Annexure-4.
Note:
i)
Price bids containing overwriting / cuttings / erasures in the quoted price and
in case these are not attested by the signatory of the bid, such prices are liable
to be rejected at the sole discretion of OWNER/PMC, without giving any
further notice.
The bid shall be sent by courier to Mr. P. Wankhade, Senior Manager (Materials)
Central Engineering, Petroleum House, Hindustan Petroleum Corporation Limited, 17,
Jamshedji Tata Road, Mumbai- 400 020, India
- 51 of 237 -
E)
Date: 18.12.2010
Rev 0
The bid documents has to reach above mentioned HPCL office at Mumbai on or
before the due date and time specified in the Notice Inviting Tender. The time and
date hereafter referred to as the bid closing date/bid due date.
- 52 of 237 -
Date: 18.12.2010
Rev 0
- 53 of 237 -
Date: 18.12.2010
Rev 0
qualified and are technically and commercially acceptable, shall be opened at a later
date to be intimated by the Owner/PMC.
3.3.7 Deviation To Bid Requirement
Bidder must submit the offer in line with the bid stipulations without taking any
deviation. The Bidder is cautioned that any exceptions taken to the following Terms
and Conditions included in this Bid document may result in rejection of the Bidders
proposal.
i)
Time Schedule.
ii)
Schedule Of Prices.
iii)
iv)
Security Deposit.
v)
vi)
vii)
Arbitration
viii)
Exceptions, clarifications, queries and deviations, to terms and conditions other than
those mentioned above, if unavoidable, bidders may stipulate the same as per format
given in Annexure-3. This shall form part of unpriced bid (Part-I).
Bidder shall note that clarifications / queries / deviations mentioned elsewhere
in the offer shall not be given any cognizance.
Bidder shall, however, note that OWNER/PMC reserves their right not to seek any
clarification on deviations sought by the bidder and to evaluate their offers on as
received basis.
3.3.8 Bid Evaluation Criteria
The bids received from the bidders shall be evaluated on the basis of the Bid
Evaluation Criteria (BEC) as mentioned hereunder. OWNER/PMC reserves the right
- 54 of 237 -
Date: 18.12.2010
Rev 0
to change any criteria of Bid evaluation at their discretion. However, any such
change will be intimated to all the bidders.
3.3.8.1 Bids without Earnest Money deposit (EMD) / Bid Bond will be considered as nonresponsive and such bids are liable for rejection at the sole discretion of
OWNER/INTEC.
In case the bidder, in their covering letter to the bid, stipulates that EMD has been
forwarded separately and in case the EMD is not received before the un-priced bid
opening, their offer will be rejected at the sole discretion of OWNER/PMC.
3.3.8.2 If any price is indicated in the Part 1 (Unpriced Bid) of the Bid, such tenders shall
be rejected straight away without further notice.
3.3.8.3 If a bidder fails to respond to clarifications/required information within the cut-off
period, their bid will be rejected or will be evaluated on the basis of available data, at
OWNER/PMCs sole discretion.
3.3.8.4 Determination of Responsiveness
(i)
For the purpose of this clause, a substantially responsive bid is one which
comprises all information / documents (i.e project management , planning
and scheduling, HO and field setup, procurement, inspection and expediting ,
coordination with Owner/PMC, QA/QC programme, consent letters of the
sub-contractor/ backup consultant / licensor etc) and which conforms to the
terms and conditions and specifications of the Bidding Document without
material deviation or reservation. A deviation or reservation is one which
affects in any substantial way the scope, quality or performance of the works
or which limits in any substantial way or is inconsistent with the Bidding
document, the owners right or contractors obligation, and which would
affect unfairly the competitive position of Bidders presenting substantially
responsive bids.
- 55 of 237 -
(ii)
Date: 18.12.2010
Rev 0
Only those bids, which are complete in all respects and are in accordance
with the terms and conditions and technical specifications of the Bidding
document, shall be considered for evaluation. Such bids shall be deemed to
be under consideration immediately after opening of Bids.
(iii)
Bidder will not be permitted to change the substance of the Bids after
opening of Bids.
(iv)
3.3.8.5 After opening of priced bids, all the prices will be checked for arithmetic errors, if
any. Item rates which have not been quoted for in the first instance, irrespective of
whether these are incidental to the categories of works for which rates have already
been quoted or belong to separate categories, will not be called for from the bidders.
The prices of such bidders will be evaluated based on loading by the highest quoted
item rate by any bidder for such item. Item for which rates are not quoted by the
bidders will be evaluated as deemed fit by OWNER/PMC. However, in case a bidder
has not quoted rates for any items, which amount to 10% of OWNER/PMCs
estimate or more, such bids shall be considered incomplete and shall be rejected.
3.3.8.6 The prices quoted by the bidders who have retained deviations to the terms and
conditions for which loading basis has been specified in the Bid documents or such
deviations which are otherwise considered acceptable and can be quantified, shall be
loaded accordingly. The prices quoted by all the tenderers shall be loaded for the
deviations to the terms and conditions and/or technical specifications as per the
loading factors given in Annexure 6.
If any loading factor other than those specified in the Annexure 6 are required, they
will be intimated to the bidder before opening of priced bids.
- 56 of 237 -
Date: 18.12.2010
Rev 0
Base Price
The total price for the complete work as quoted in the Schedule of
Lumpsum Prices shall be taken as base price for evaluation.
(ii)
For the purpose of evaluation of Bids, Foreign Exchange (TT selling rate) as
intimated by Scheduled Bank / published in Economic Times, on the day prior to
opening of Price Bid will be considered.
- 57 of 237 -
Date: 18.12.2010
Rev 0
modification which has the effect of altering the value of their offer) after
opening of Techno-contractual bids without specific reference by the
COMPANY/PMC shall render the bid liable to be rejected without notice and
without further reference to the Bidder.
(ii)
No bid may be withdrawn in the interval between the deadline for the
submission of bids and the expiration of the period of the bid validity
specified by the bidder on the bid form.
Withdrawal or unsolicited
modification of a bid during this interval shall result in the bidders forfeiture
of its bid security.
3.3.11 Notification Of Award
Prior to the expiring of the period of Bid validity prescribed by the OWNER/PMC,
the OWNER will notify the successful Bidder by Fax of Acceptance (FOA) that their
Bid has been accepted. This notification of award shall contain the sum, which the
OWNER will pay to the successful bidder in consideration of the execution and
completion of the work as per Contract. OWNER will be the sole judge in the
matter of award of Contract and the decision of OWNER will be final and binding.
3.3.12 Signing of contract agreement
- 58 of 237 -
Date: 18.12.2010
Rev 0
Detailed letter of acceptance (LOA) along with all its enclosures shall be issued to
the successful bidder after issue of Fax of Acceptance by the OWNER. The
successful bidder shall sign Agreement with the OWNER within 10 days from the
date of issue of detailed letter of acceptance on a non-judicial stamp paper. The cost
of non-judicial stamp paper shall be borne by the BIDDER.
Upon execution of agreement by the successful Bidder, OWNER will return the
EMD of unsuccessful Bidders.
3.3.13 Security Deposit
The successful bidder is required to make security deposit to the OWNER as
specifed in clause 4 b) of HPCLs General Conditions of Contract.
3.3.14 Project Management Consultant (PMC)
M/s.INTEC Asia Pacific SDN BHD, Kuala Lumpur, Malaysia is the Project
Management Consultant (PMC) of the OWNER and will be performing various
actions in relation to the biding process and in the evaluation of the bids for and on
behalf of the OWNER.
******************
- 59 of 237 -
Date: 18.12.2010
SECTION - 4
SPECIAL CONDITIONS OF CONTRACT (SCC)
- 60 of 237 -
Rev 0
Date: 18.12.2010
Rev 0
INDEX
S. NO:
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
4.12
4.13
4.14
4.15
4.16
4.17
4.18
4.19
4.20
4.21
4.22
4.23
4.24
4.25
4.26
4.27
4.28
4.29
4.30
4.31
4.32
4.33
TABLE OF CONTENTS
GENERAL
INTERPRETATION
LAWS/ARBITRATION
NOTICES
LIABILITY OF GOVERNMENT OF INDIA
WORK SITE / SCOPE OF WORK
COMMENCEMENT/COMPLETION DATES
GENERAL OBLIGATIONS OF CONTRACTOR
PAYMENT
SECURITY DEPOSIT / PERFORMANCE GUARANTEE
DUTIES & TAXES
INTELLECTUAL PROPERTY
WORK EXECUTION
MISCELLANEOUS
SURVEYS
REVIEW OF CONTRACTORS DOCUMENTS
SUPPORT DIVING
WORKMEN
MATERIALS AND WORKMANSHIP
CERTIFICATE OF COMPLETION AND ACCEPTANCE
OF THE WORK
CONSTRUCTIONAL PLANT AND EQUIPMENT,
TEMPORARY WORKS AND MATERIALS
OFFSHORE POLLUTION RESPONSIBILITY
PROCEDURE FOR MEASUREMENT OF WORKS
COMPLETION CERTIFICATE
MARKING, PACKING, LOADING AND SECURING
SUPPLY OF CONSUMABLES
DIVERSION OF MARINE SPREAD
INFORMATION FOR DATA STORAGE
COMPLIANCE WITH LOCAL LAW & REGULATIONS
THIRD PARTY INSPECTION & CERTIFICATION
AGENCIES AND MARINE WARRANTY SURVEYOR
GUARANTEES, LIABILITIES AND LIQIDATED
DAMAGES
INSURANCE
FORCE MAJEURE
- 61 of 237 -
PAGE NO:
Date: 18.12.2010
Rev 0
4.1 GENERAL
Special Conditions of Contract shall be read in conjunction with the Schedule of
Prices, General Conditions of Contract, Project Specifications and Drawings, Scope
of Work and any other document forming part of this contract wherever the context
so requires.
Wherever it is stated anywhere in this bidding document that such and such supply is
to be effected or such and such work is to be carried out, it shall be understood that
the same shall be effected/carried out by the Contractor at their own cost, unless a
different intention is specifically and expressly stated herein or otherwise explicit
from the context.
The materials, design and workmanship shall satisfy the relevant Standards, the job
specifications contained in the BID documents and codes referred to. Where the job
specifications stipulate requirements in addition to specifications, these additional
requirements
shall
also
be
satisfied.
In
the
absence
of
any
ii)
- 62 of 237 -
Date: 18.12.2010
iii)
iv)
v)
Scope of Work
vi)
Instruction to Bidders
vii)
Rev 0
Drawings
Interpretation
4.2.1 Words imparting the singular meaning only also include the plural and vice versa
except where the context otherwise requires.
4.2.2 The headings and sub-titles in these conditions of contract are included solely for
convenience and shall not be deemed to be part thereof and shall not affect the
meaning or operation of the contract.
4.2.3 Reference to Section, Clause and Article and Provision shall have the same
meaning.
4.2.4 Governing Language
The governing language for the contract shall be English. All contract documents
and all correspondence and communication to be given and all other documentation
to be prepared and supplied under the contract shall be written in English and the
contract shall be construed and interpreted in accordance with English language.
4.2.5 Amendments to the Contract
- 63 of 237 -
Date: 18.12.2010
Rev 0
Severability
If any provision or the condition of the contract is prohibited or rendered invalid or
unenforceable then such prohibition or invalidity or unenforceability shall not affect
the other provisions or conditions of the contract.
Laws/Arbitration
- 64 of 237 -
Date: 18.12.2010
Rev 0
Notices
Any notice to be given under the contract shall be given by sending the same by
personal delivery, post, telegram, telex or telefax to the address of the relevant party
set forth below:
To the COMPANY
The Senior Manager (Materials),
Hindustan Petroleum Corporation Limited
Mumbai
To the Contractor
(Name of successful bidder will be incorporated)
Any notice sent by telefax / telegraph/ telex shall be confirmed within 2 days after
dispatch of notice sent by post.
Any notice delivered personally or sent by telegraph, telex, telefax shall be deemed
to have been delivered on the date of its dispatch.
- 65 of 237 -
Date: 18.12.2010
Rev 0
Either party may, by notice to the other party in writing, change its postal, cable or
telex/telefax address for receipt of such notice.
In this connection, notices shall include any instructions, orders and certificates to
given under the contract.
4.5
- 66 of 237 -
Date: 18.12.2010
Rev 0
COMMENCEMENT/COMPLETION DATES
of
the
contractor
for
access
to
site
to
proceed
with
the
- 67 of 237 -
Date: 18.12.2010
Rev 0
extension of time for completion of the works and compensation for the spread
actually deployed at offshore site in accordance with applicable schedule of rates, or
if no such rates are available then at the rates as may be mutually agreed.
4.7.3 Start of fabrication/installation
Prior to taking to fabrication/installation of any major component of work, the
contractor shall submit to COMPANY/PMC their proposed construction sequence
and procedures and obtain COMPANY/PMCs approval in writing. If no response is
provided by the COMPANY/PMC to the contractor within 14 working days after
receipt by the COMPANY/PMC, then the proposed construction sequence and
procedure shall be deemed to be approved by the COMPANY/PMC.
4.7.4 Rate of progress
4.7.4.1 Contractor shall monitor progress of all the activities specified in the programme of
works pursuant to clause 4.8.4 and submit free of cost monthly progress report about
various aspects of the works to the COMPANY/PMC as per proforma to be agreed
upon during kick off meeting. The periodicity of such reports may be changed by the
COMPANY/PMC on mutual agreement between both parties
Extracts of the progress report to be termed as Executive Summary shall be
submitted in 6 copies along with 6 copies of monthly progress report.
All the materials, plant and labour to be provided by the contractor and the manner
and speed of execution and maintenance of the works are to be conducted in a
manner to the satisfaction of COMPANY/PMCs representative in accordance with
the contract. Should the rate of progress of the works or any part of them at any time
falls behind or is found to be too slow to ensure completion of the works by the
stipulated time or extended time for completion, the COMPANY/PMCs
representative shall so notify the contractor in writing. The contractor shall reply to
the written notice giving details of the measures they prescribe to compensate for the
- 68 of 237 -
Date: 18.12.2010
Rev 0
time lost. The contractor shall not be entitled to any additional payment for taking
such steps. If at any time it should appear to the COMPANY/PMCs representative
that the actual progress of works does not conform to the approved programme the
contractor shall produce at the request of the COMPANY/PMCs representative a
revised programme showing the modification to the approved programme necessary
to ensure completion of the works within the time for completion as defined in
clause 4.7.5 hereunder.
The submission to and approval by the COMPANY/PMCs representative of such
programme as the furnishing of such particulars shall not relieve the contractor of
any of their duties or responsibilities under the contract.
4.7.4.2 In case during execution of works the progress falls behind schedule, contractor shall
deploy extra manpower, constructional plant and equipment, resources to make up
the progress. Programme for deployment of extra manpower/constructional plant and
equipment resources will be submitted to the COMPANY/PMC for their review and
approval which approval shall not be unreasonably withheld. All time and cost
effect in this respect shall be borne by the contractor unless otherwise expressly
provided in the contract.
4.7.5 Date of completion / Period
The completion period for the works described in the contract will be 2 (Two)
months from date of issue of Fax of Acceptance (FOA) by OWNER and no work
shall exceed beyond February 2011.
4.8
- 69 of 237 -
Date: 18.12.2010
Rev 0
Offshore and Onshore (data contained in the bidding documents), climatic and
physical conditions, and (b) all criteria of design contained in the bidding
documents.
4.8.1.2 Subject to clause 4.8.1.1 and 4.15, the contractor shall, nevertheless, be deemed to
have knowledge of the site and its surroundings and information available in
connection therewith and to have satisfied themselves the form and nature thereof
including, the sub-surface Offshore (data contained in the bidding documents), the
hydro-logical and climatic conditions, the quantities and nature of the work and
materials necessary for the completion of the works, the means of access, and in
general to have obtained himself all necessary information of all risks, contingencies
and circumstances affecting their obligations and responsibilities therewith under the
contract and their ability to perform it. However, if during pre-construction survey
contractor detects physical conditions and/or obstructions affecting the work, the
contractor shall take all measures to overcome above.
4.8.1.3 Contractor shall be deemed to have satisfied themselves as to the correctness and
sufficiency of the contract price for the works. The consideration provided in the
contract for the contractor undertaking the works shall cover all the contractors
obligations and all matters and things necessary for proper execution and
maintenance of the works in accordance with the contract and for complying with
any instructions which the COMPANY/PMC may issue in accordance with in
connection therewith and of any proper and reasonable measures which the
contractor takes in the absence of specific instructions from the COMPANY/PMC.
Contractor is advised that it is fully responsible for conducting any additional
WORK SITE and subsurface investigation both Offshore and Onshore that
Contractor deems necessary to perform the WORK.
Contractor shall be deemed to have inspected and examined the WORK SITE and to
have full and complete knowledge of the surface and subsurface conditions Offshore
- 70 of 237 -
Date: 18.12.2010
Rev 0
existing at the WORK SITE and its surroundings, and to have satisfied themselves
before submitting their PROPOSAL as to the nature of the ground and the subsoil,
and to have taken into account by information in connection therewith which may
have been provided by or on behalf of COMPANY. Contractor shall have satisfied
themselves as to the form and nature of the WORK SITE, the extent and nature of
the WORK and MATERIALS necessary, the means of communication with access
to the work site, the availability of port facilities and marine conditions at the ports,
details of the road and highway network, the accommodation they may require and
in general to have obtained all necessary information as to the risk, contingencies
and all other circumstances influencing or affecting their PROPOSAL. Failure to
visit the site or failure to study the Bidding Documents will in no way relieve the
successful bidder from furnishing any material or performing any work in
accordance with the Bidding Documents.
COMPANY/PMC shall not be liable for any claims from Contractor by reason of
any error, insufficiency or omission due to the information provided by the
COMPANY/PMC.
4.8.2 Weather Conditions
a)
The contractor shall bear all cost and delays due to adverse weather
conditions/weather down time experienced during Offshore works including load
out and tie down under the contract.
b)
The contractor shall subject to paragraph (d) below bear all the cost and delays
due to adverse weather conditions/weather down time experienced during the
transportation of works.
c)
The contractor shall bear all the costs and delays due to adverse weather
conditions/weather down time of the constructional plant and equipment/marine
spread, etc. experienced during the execution of the works at offshore site,
including any extended period except the cost and delays due to adverse weather
conditions/weather down time experienced during any extended period falling in
- 71 of 237 -
Date: 18.12.2010
Rev 0
monsoon season arising from reasons attributable to the COMPANY or its other
contracts.
d)
If the works entered into monsoon season then the COMPANY shall bear cost
and delays/slippage attributable to the COMPANY or its other contractors
(delay/slippages not attributable to the COMPANY or its other contractors
excluded) added to the schedule completion date reaches/enters monsoon season.
In such an event and provided that the COMPANY requires the contractor to
continue to work during monsoon seasons the COMPANY shall bear cost and
delays due to adverse weather conditions/weather down time experienced only
during the period which falls within the monsoon season required to execute the
works that are in delay and shall extend the completion schedule accordingly.
However, the COMPANY may request the contractor to demobilize during
monsoon season instead of requesting the contractor to continue the work during
monsoon season. The cost of such additional de-mobilization/re-mobilization
shall be borne by the COMPANY which shall be mutually agreed, if not
available in schedule of price. All costs and delays due to adverse weather
conditions/weather down time under situations other than those specified
hereinabove shall be to contractors account.
- 72 of 237 -
4.8.3.3 The
contractor
shall
Date: 18.12.2010
accept
instructions
and
directions
only from
Rev 0
the
accordance with the contract, the time and cost effect shall be for COMPANYs
account.
- 73 of 237 -
Date: 18.12.2010
Rev 0
contractor shall conform to the duties and period specified in the contract. The
COMPANY/PMC and the contactor shall discuss and agree upon the works
procedures to be followed for effective execution of the works. The constructional
plant and equipment and temporary works which the contractor intends to deploy
shall be clearly specified.
programme shall not relieve the contractor of any of his duties or responsibilities
under the contract.
4.8.5 Contractors Organization
4.8.5.1 The contractor shall supply to the COMPANY/PMC along with their BID, an
organization chart showing the proposed organization to be established by the
contractor for execution of the work including the identities and curriculam vitae of
the key personnel to be deployed.
- 74 of 237 -
Date: 18.12.2010
Rev 0
be responsible for
accommodation and catering of all labour local or expatriates required for the
execution of the works and for all costs/charges in connection thereof.
The contractor shall be responsible for obtaining all necessary permits or visas from
the concerned authorities for the entry of all labour and personnel to be deployed
into India.
The contractor shall at their own expense be responsible for the repatriation to the
country from which they were mobilized for all their and their sub-contractors
personnel deployed upon the works at site and shall be responsible for the suitable
maintenance of all such personnel from the cessation of their deployment on the
work to their departure from India.
4.8.5.2 The contractor shall provide and deploy on the site for carrying out the works only
those technicians/assistants who are skilled and experienced in their respective trades
and those foremen and leading respective trades and those foremen and leading
hands who are competent to give proper supervision to the work they are required to
supervise.
Further, only those skilled, semi-skilled and unskilled workmen who are necessary
for the proper and timely execution of the works shall be deployed at site.
4.8.5.3 The COMPANYs representative may at any time object to and require the
contractor to remove forthwith from the site a supervisor or any other authorized
representative or employee of the contractors sub-contractor(s) or any person(s)
deployed by contractor or their sub-contractor(s), if in the opinion of the
COMPANYs representative the person in question has mis-conducted himself or his
- 75 of 237 -
Date: 18.12.2010
Rev 0
- 76 of 237 -
Date: 18.12.2010
Rev 0
dimensions, orientation and alignment of all parts of the works, and for the provision
of all necessary instruments appliance and labour in connection therewith. If at any
time during the progress of the works, any error appears or arises in the position,
orientation, alignment, levels, depths or dimensions of any part of the works, the
contractor shall rectify the error at their own cost to the satisfaction of COMPANYs
representative/engineers representative. The checking of any setting out of any line,
level, depths, coordinate, orientation or alignment or position of a marker by the
COMPANYs representative or the Engineers representative shall not in any way
relieve the contractor of their responsibility for the correctness thereof. Contractor
shall carefully protect and preserve all bench marks, sight rails, pegs and other things
used in setting out the works. In case any data/instruction supplied by COMPANY
or its representative after pre-construction survey leads to changes/additions in scope
of work, the same shall be dealt with as per the provisions of clause 4.33.
4.8.7 Safety procedures and restrictions
4.8.7.1 The
contractor
shall
not
do
any
exploratory
excavations,
including
The contractor shall comply with the HSE requirements . The contractor shall also
be responsible to comply with code requirements of international maritime
- 77 of 237 -
Date: 18.12.2010
Rev 0
c)
Contractor shall conduct a safety studies methodology which shall be completed and
submitted to COMPANY/PMC within 30 days of contract award. Further, the
contractor shall implement the findings of the safety studies without impact on
schedule or contract price.
PAYMENT
- 78 of 237 -
Date: 18.12.2010
Rev 0
- 79 of 237 -
Date: 18.12.2010
Rev 0
- 80 of 237 -
Date: 18.12.2010
Rev 0
due to which the amount withheld by the COMPANY has been removed/settled
and the contractor submits fresh invoice for the same.
4.9.2.5
Invoice for Extra work: No invoice for extra work/change order on account of
change order will be submitted by the contractor unless the said extra work/change
order has been authorized/approved by the COMPANY in writing in accordance
with Clause 4.33.1.
Payment against all these change orders/extra work shall be made within 90 days of
receipt of invoice by COMPANY after the mutually agreed settlement or the
completion of change order whichever is later.
After due vetting of the documents for change in duties/taxes under change in law by
COMPANY, invoice on account of change in duties/taxes under change in law shall
be submitted by the contractor along with the necessary supporting documents in a
single invoice after payment of all duties/taxes.
4.9.2.6 All the payments by the COMPANY shall be remitted by Telegraphic/Telex transfer
to the contractors bank account to be specified by the contractor in writing to the
COMPANY before submission of the first invoice. The payment shall be made in
currencies stated in the contract. The COMPANY shall be deemed to have arranged
payment to the contractor on the date of transmission of the cable instruction by the
COMPANYs bankers to the contractors bank in the country where the money is
required to be paid to the Contractor.
Bank charges of bank(s) in India shall be borne by COMPANY whereas bank
charges of bank(s) in contractors designated locations, if any, shall be borne by
contractor.
- 81 of 237 -
Date: 18.12.2010
Rev 0
The contractor have to bear fund transfer as well as bankers cheque charges. HPCL
will not take any responsibility for delay in transmission of funds by Telex /
Telegraphic due to whatsoever reasons.
4.9.1.7 In the event of COMPANY noticing at any time that any amount has been disbursed
wrongly to the contractor or any other amount is due from the contractor to the
COMPANY, the COMPANY may without prejudice to its rights recover such
amounts by other means after notifying the contractor or deduct such amount from
any payment failing due to the contractor. The details of such recovery, if any, will
be intimated to the contractor.
undisputed amount under subsequent invoice for any amount that has been omitted
in previous invoice by mistake on the part of the COMPANY or the contractor.
4.9.1.8 The COMPANY shall not be responsible/ obligated for making any payments or any
other
related
obligations
under
this
contract
to
the
contractors
sub-
contractors/vendors. The contractor shall be fully liable and responsible for meeting
all such obligations and all payments to be made to its sub-contractors/vendors and
any other third party engaged by the contractor in any way connected with the
discharge of the contractors obligation under the contract and in any manner
whatsoever.
4.10 Security Deposit / Performance Guarantee
4.10.1 The contractor shall furnish to the COMPANY towards Security Deposit as specified
in Clause 4 b) of General Conditions of Contract for due performance of the
contract. The security deposit can be in the form of a irrevocable bank guarantee as
per prescribed HPCL format. This irrevocable bank guarantee shall be drawn in
favour of the COMPANY and shall be valid upto a period of Scheduled Completion
Date for the works of the contract and warranty period plus sixty (60) days. Bank
guarantee shall be from a scheduled / nationalized bank in India for Indian Bidders
- 82 of 237 -
Date: 18.12.2010
Rev 0
and for non-Indian bidders the bank guarantee shall be from Indian Branch of a
foreign bank or scheduled /nationalized bank in India.
4.10.2 In the event completion of works is delayed beyond the scheduled completion date
for any reasons whatsoever, the contractor shall get the validity of the guarantee
suitably extended so as to make it valid for 12 months plus 90 days from the actual
date of completion of works.
4.10.3 The COMPANY shall have the right under this guarantee to invoke the bankers
guarantee and claim the amount thereunder in the event of the contractor failing to
honour any of the commitments entered into under this contract. In case contractor
fails to furnish the requisite bank guarantee as stipulated above, then the COMPANY
shall have the option to terminate the contract and forfeit the bid security amount and
no compensation for the works performed shall be payable upon such termination.
Upon completion of works the above said guarantee shall be considered to constitute
the contractors guarantee / warranty for the work done by them or for the works
supplied and their performance as per the specifications and any other conditions
against this contract. The guarantee / warranty shall be in force for 12 months plus a
claim period of 3 months from the completion date as specified in clause 4.7.5
4.10.4 The bank guarantees shall be from a scheduled / nationalised bank in India for Indian
bidders. For non-Indian bidders the bank guarantees shall be from Indian branch of a
foreign bank or a scheduled /nationalised bank in India.
4.10.5 The contractor shall also arrange for the Performance guarantee to remain valid until
the expiration of the guarantee period for entire works.
- 83 of 237 -
Date: 18.12.2010
Rev 0
4.10.6 The COMPANY shall return the performance guarantee to the contractor upon the
expiration of the performance guarantee unless any extension is required in
accordance with the contract.
4.11 Duties & Taxes
It will be imperative for each bidder to fully inform themselves of all taxes, duties,
levies, royalties etc which may affect the execution of the contract as described in
the bidding documents. In their own interest, the bidders are particularly requested to
familiarise themselves with the rules and regulations regarding but not limited to
Income Tax / Withholding Tax, Insurance , Companies Act, Customs Duty,
Countervailing Duty (CVD), various Cesses, Service Tax, Works Contracts Tax,
Excise Duty, Local Taxes etc. It is the responsibility of the bidder that such factors
have been properly been investigated and considered while submitting the BID. No
claim whatsoever including those for financial adjustments to the contract awarded
under the bidding documents will be entertained by the COMPANY and neither any
change in time schedule of the contract nor any financial adjustments arising thereof
shall be permitted by the COMPANY on account of failure of the bidder to appraise
themselves of Indian & Local laws.
Contractors quoted price shall be inclusive of all taxes and duties, including Works
Contract Tax (WCT), Income Tax / Withholding Tax, Customs Duty / Excise Duty
ans all other charges, but excluding Service Tax, with respect to work rendered
hereunder whether or not in effect on the date of this CONTRACT but that are
imposed, directly or indirectly, prospectively or retrospectively by the Government
of India or any other Government.
Contractor before submission of First invoice for running payment shall register
themselves and the CONTRACTOR at their own cost with the Reserve Bank of
India, Income Tax, Sales Tax, Excise /Customs Departments and such other Central
- 84 of 237 -
Date: 18.12.2010
Rev 0
or State Governments and all statutory bodies as may be required under the rules and
regulations governing in India in connection with performance of the Work.
In case of applicability of concessional rates of duties and taxes on supply items
under this contract, HPCL will furnish necessary certification/forms to Contractor
after placement of order subject to the confirmation from HPCL to enable the
Contractor to avail concessional rates of duties & taxes.
- 85 of 237 -
4.11.1.2
a)
Date: 18.12.2010
Rev 0
Customs duty leviable on constructional plant and equipments other than those
covered under clause (a), tools and tackles, consumables, components and spares
required for completion of works (which partly/wholly get consumed in process of
fabrication, installation, pre-commissioning and commissioning) and imported
temporarily by contractor to be re-exported wholly/partly after use, is to be included
in lump sum price of schedule of prices and shall be paid directly by the contractor
to the customs authorities. Timely completion of all import formalities pertaining to
clearance of customs, payment of customs duty, if any, actual re-export formalities
and other related activities shall be complied with solely by the contractor at their
own cost. The COMPANY shall in no way be responsible for any delays and losses
encountered by contractor in this regard. Save allowing the arrival of materials and
- 86 of 237 -
Date: 18.12.2010
Rev 0
equipment and goods, loaded on the marine spread/barges and constructional plant
and equipment at site without touching Indian Port in which case the customs
authority agrees to depute their officer(s) for examination of goods and
constructional plant and equipment at site as and when request is made the custom
clearance will have to be carried out by the contractor as per Indian Customs Law
irrespective of whether customs duty is applicable or not applicable. However, IGM
and bill of entry shall be filed with the custom authority by the contractor well in
advance.
4.11.1.3
It shall be the
The
Date: 18.12.2010
Rev 0
their sub-contractor(s) or their personnel shall bear all taxes, if any, levied on the
contractors, sub-contractors and vendors personnel. The amount of tax withheld
by the COMPANY shall at all times be in accordance with India Tax Law and the
COMPANY shall furnish to the contractor a consolidated statement for the tax
deducted at source and paid to the Tax authorities.
Should the contractor fail to submit returns/pay taxes in time as stipulated
under the Indian Income Tax Act or other rules of Republic of India and
consequently any interest or penalty is imposed by the Indian Income Tax
authority, the said interest/penalty shall be paid by the contractor only.
The COMPANY shall, if so required by applicable laws in force, at the time of
payment, deduct income tax payable by the contractor at the rates in force from the
amount due to the contractor and pay to the concerned tax authority directly.
The contractor shall agree that they and their sub-contractor(s) shall pay Indian
Income Tax as may be imposed/levied on them by the Indian Income Tax authorities
for the payments received by them for the works under the contract.
The contractor, their sub-contractor(s), vendor(s) and the personnel deployed by
them shall comply with the Indian Income Tax Act in force from time to time.
The contractor shall indemnify COMPANY against any and all liabilities or claims
arising out of this contract for such taxes including interest and penalty which any
such tax authority may assess or levy against the COMPANY/contractor.
4.11.3 SERVICE TAX
Bidders quoted Lumpsum price shall be exclusive of Service Tax the rate of which
will be at prevalent rate. However any increase in service tax if any after CDD, the
deferential tax amount for such increase wiil be on contractors account.
- 88 of 237 -
Date: 18.12.2010
Rev 0
INTELLECTUAL PROPERTY
Secrecy
Neither the COMPANY nor the contractor nor their personnel, agents nor any subcontractor shall divulge to any one (other than persons designated by the party
disclosing the information) any information designated in writing as confidential
and obtained from the disclosing party during the course of the execution of works
so long as and to the extent that the information has not become part of the public
domain. This obligation does not apply to information furnished or made known
to the recipient of the information without restriction as to its use by third parties
or the recipient of the information without restriction as to its use by third parties
or which was in recipients possession at the time of disclosure by the disclosing
party. Upon completion of the works or in the event of termination pursuant to the
provisions of the contract, contractor shall immediately return to the COMPANY
all drawings, plans, specifications and other documents supplied to the contractor
by or on behalf of the COMPANY or prepared by the contractor solely for the
purpose of the performance of the works, including all copies made thereof by the
contractor.
- 89 of 237 -
Date: 18.12.2010
Rev 0
4.12.2.2 The contractor shall keep on each site at least three copies of each and every
drawing, specification and contract document in excess of their own requirement
and those copies shall be available at all times for use by the COMPANYs
representative and the Engineer/Engineers representative and by any other person
authorized by the COMPANYs representative, who shall be provided an
adequately sized site office or offices, for the safe-keeping and use of such
documents, by the contractor throughout the duration of the contract. Where one
or more of contractors yards/offices/offshore spreads are deployed in the works,
all requirements of the contract and contractors obligation under the contract shall
apply equally at each yard/office/offshore spread so deployed.
4.13
WORK EXECUTION
4.13.1 Representation
4.13.1.1 General
There may be more than one COMPANYs representative, Engineer, Engineers
representative at the same time. The COMPANY shall appoint and notify the
contractor in writing of the name(s) of the COMPANYs representative.
The
COMPANY from time to time may appoint some other person(s) as COMPANYs
representative in place of the person(s) previously appointed.
4.13.1.2 COMPANYs Representative
The duties of the COMPANYs representative are to act on behalf of the
COMPANY for overall coordination and Project Management at site.
The
COMPANYs representative shall have the authority and powers to the extent so
authorized and notified by the COMPANY to the contractor in writing from time to
time. The COMPANYs representative shall liaise with the contractor and monitor
the progress for the timely completion of the works.
He will communicate
- 90 of 237 -
Date: 18.12.2010
Rev 0
He shall also monitor that the works are carried out in accordance with the
specifications, drawings and other terms and conditions of the contract as inspected
by Engineer/Engineers representative. The COMPANYs representative shall have
the right to inspect any part of the works at all reasonable time and order necessary
tests to be carried out under supervision of Engineer/Engineers representative and
reject such works which are not in accordance with the contract.
He has the right to scrutinize the contractors records for the work being done In
general, he shall have the authority to oversee the execution of the works by the
contractor and to monitor compliance by the contractor of provisions of the
contractor.
Approval by the COMPANYs representative of any or all documents shall in no
way relieve the contractor of the responsibilities of execution of the work in
accordance with the terms and conditions of the contract.
All notices, instructions, orders, certificates, approval and all other communications
shall be given by the COMPANYs representative, save as otherwise provided in the
contract. The COMPANYs representative shall carry out such duties in issuing
decisions, certificates and orders as specified in the contract.
All notices,
COMPANYs
perusal/approval
at
the
base
office
at
- 91 of 237 -
Date: 18.12.2010
Rev 0
- 92 of 237 -
Date: 18.12.2010
Rev 0
work
pertaining
to
design,
engineering,
procurement,
fabrication,
All sub-contracting
- 93 of 237 -
Date: 18.12.2010
Rev 0
In case of materials and other allied requirements to be procured for the works
covered under the contract, the contractor shall subject to the limitation with regard
to selection of vendor(s), make(s) of equipment/material as contained in
4.13.2.3(ii), procure the required equipment/material from amongst the make(s)
and vendor(s) of the respective plant/equipment/material which have been found to
be acceptable and approved by the COMPANY/PMC. The contractor shall not
- 94 of 237 -
Date: 18.12.2010
Rev 0
procure equipment/material of make(s) and from vendor(s) other than those agreed
and approved by the COMPANY/PMC. COMPANY/PMCs approval/comments
for list of proposed vendors for critical equipment(s) will be given within 14
working days after submission of such list by contractor.
ii)
The
COMPANY/PMC shall have right to hold detailed technical discussion with the
vendor(s) and visit vendors premises. The COMPANY/PMC shall examine the
details submitted by the contractor and ascertain the suitability of the proposed
make(s) and/or vendor(s) capabilities to execute the work. The COMPANY/PMC
shall have authority to disapprove or reject the proposed make(s) and/or vendor(s)
which do not meet the requirement of the contract.
COMPANY/PMC in this regard shall be final and binding on the contractor. The
purchase order will be issued by the contractor only after written approval of the
COMPANY/PMC from amongst make(s) and vendor(s) which have been
approved by the COMPANY/PMC which approval shall not be unreasonably
withheld.
iii)
Procurement
of
equipments/materials
from
vendor(s)
as
approved
by
COMPANY/PMC from the suggested vendor list shall not relieve the contractor of
their obligations and responsibilities under this contract.
4.13.2.4
Approval
- 95 of 237 -
Date: 18.12.2010
Rev 0
ii)
iii)
The contract price as contained in the contract shall remain firm and unchanged
except as otherwise provided in the contract. Cost benefits however accruing to
the contractor shall be passed on to the COMPANY.
4.13.2.4.2 The contractor shall not be entitled for any time and cost compensation on
account of observance of requirements given in sub-clause 4.13.2.1 through
4.13.2.4.1 above.
4.14
4.14.1
Miscellaneous
The COMPANYs representative on behalf of the COMPANY shall have full
power and authority to supply to the contractor or to instruct the contractor to
prepare further specifications, drawings or job instruction necessary for the proper
and adequate execution of the works in accordance with the contract price. The
contractor shall carry out these instructions and be bound by them.
- 96 of 237 -
Date: 18.12.2010
Rev 0
4.14.2 Unless otherwise specified, the contractor shall pay all tonnage and other royalties,
rent and other payments or compensation, if any, for getting stone, sand, gravel, clay
or other materials required for the works or temporary works.
4.14.3 All operation necessary for the execution of the works and for the construction of
any temporary works shall, so far as compliance with the requirements of the
contract permits, be carried out so as not to interfere unnecessarily or improperly
with public convenience or the access to use and occupation of navigable and other
water, waterways, channels, roads, harbors or harbor area, fisheries, natural harbors
and anchorage and other places of shelter by sea or lands, public or private roads and
footpaths or properties, whether in the possession of the COMPANY or of any other
person and the contractor shall indemnify the COMPANY against all claims,
demands, proceedings, damages costs, charges and expensive whatever arising in
relation to any said matters in so far as the contractor is responsible therefore.
4.14.4 The Contractor shall use every reasonable means to prevent any of the highway,
waterways or bridges, locks, docks, sea walls, harbor works or navigation marks,
communicating with or on the routes to the site from being damaged or obstructed
by any traffic of the contractor or any of its sub-contractors. The contractor shall
select routes, choose and use vehicles and vessels and restrict and distribute loads
and cargo such that any extra ordinary traffic and material from and to the site will
be limited as much as is reasonably possible and so that no unnecessary damage or
injury may be occasioned to highways and the other facilities and areas aforesaid.
4.14.5 The contractor shall in accordance with the requirements of the COMPANYs
representative, afford all reasonable opportunities and access to the works/site to the
COMPANY or to any other contractors employed by the COMPANY and their
workmen and to the workmen of the COMPANY and of any other duly constituted
authorities who may be employed in the execution on or near the site of any work
not included in the contract or of any contract which the COMPANY may enter into
- 97 of 237 -
Date: 18.12.2010
Rev 0
in connection with or ancillary to the works for carrying out their work. When
instructed by the COMPANY or its representative, the contractor shall also liaise and
coordinate with COMPANYs other contractors for proper execution of the works.
Subject to clause 4.27 of the contract, in complying with the requirements of this
section at written instruction of COMPANY/COMPANYs representative should
contractor be delayed in the construction schedule, or should contractor incur
additional costs, COMPANY will compensate the contractor only for the standby
charges of the spread so affected (as certified by the COMPANYs representative) at
the rate as set out in the contract and contractor will receive an appropriate extension
of time if it affects critical path of the construction schedule and provided the
contractor had notified immediately to the COMPANY about occurrence of such
hindrance to their works provided further and to the extent the delay or any part of it
is attributable to the COMPANY, its agents and other contractors or any other duly
constituted authorities who may be employed in the execution on or near the site of
any work not included in the contract or of any contract which the COMPANY may
enter into in connection with or ancillary to the works.
- 98 of 237 -
Date: 18.12.2010
Rev 0
If the marine spreads proposed by the contractor under this contract are found to be
inadequate to complete the works covered under this contract, then the contractor
shall deploy additional spreads as required to complete the works under this contract
within the contract price and without any time effect to the COMPANY.
4.14.8 Contractor shall keep informed the COMPANY/PMC, of delays or likely delays for
entry into/exit from ports, of supply boats and/or cargo ships carrying on board
materials/equipments for the work. Any delay to work pursuant to delays in entry
into/exit from ports as aforesaid shall be to contractors account. The COMPANY
will also not accept any liability on account of aforesaid delays and the cost incurred
by the contractor, if any, in this regard shall be to contractors account. All the
vessels / barges etc are subject to security check by COMPANY / Visakapatanam
Port / Customs / Navy/Coast Guard etc. It shall be contractors responsibility to
provide to and fro transport between docks/jetties and anchorage area for the
purpose, without extra cost to COMPANY.
4.14.9 On the completion of the works, the contractor shall clear away and remove from
site all temporary works, construction plant and equipment, surplus materials, which
they had provided, including any wreckage, debris and rubbish of every kind caused
by contractor or their sub-contractor and leave the whole of the site and works clean
and in a workman like and safe condition. If the contractor fails to remove all such
materials, debris and rubbish, the COMPANY shall have the right to get them
removed and any cost incurred by the COMPANY in doing so shall be recovered
from the contractor.
4.14.10
The contractor shall not dump any material in the sea especially in the vicinity of
the facilities which are being installed under the contract.
4.14.11
It shall be the responsibility of the contractor to fully comply with the following
security provisions:
- 99 of 237 -
i)
Date: 18.12.2010
Rev 0
For all the personnel (Indian/Foreigners) and vessel (Indian registered as well as
Foreign registered) of contractor and/or their sub-contractors, the procedure for
security clearance as listed below will have to be strictly followed/complied with
before entering the work site. Any subsequent changes/modifications as may be
issued from time to time in this regard shall also have to be duly complied without
any time and cost impact to the COMPANY.
Visakhapatnam Port authorities /COMPANY personnel has the right to deny
permission to any person/vessel to go to the site in case either the required
procedures are not complied with or any person/vessel comes without stipulated
advance notice, and in that case the COMPANY will not be liable for any cost and
time impact.
Passes for all the personnel are to be obtained well in advance from the
Visakhapatnam Port authorities after providing the prescribed declaration forms
along with 2 stamp size photographs in respect of each person.
a) Indian
Nationals
(excluding
vessel
crew):
Before
mobilizing/deputing
- 100 of 237 -
Date: 18.12.2010
Rev 0
- 101 of 237 -
Date: 18.12.2010
Rev 0
Contractor is to ensure that only such expatriates who are having valid passports and
valid business visas are deployed for work under the contract. Expatriates having
tourists visas are not permitted to work.
Contractors personnel (crew/workers) proceeding to offshore should not be in
possession of any personal camera/photography materials, arms/ammunition, liquor,
prohibited drugs etc.
All passes issued for the construction activities should be surrendered after
construction activities are over in a particular working season.
Contractor is to ensure that all the personnel engaged by them abide by the Security
& Discipline rules prescribed from time to time by OWNER and Visakapatanam
Port authorities.
Contractor and their sub-contractor(s)/agents are to comply with any directive as
may be prescribed/given by the COMPANY/ Port authorities/Navy/Coast Guard etc
from time to time in respect of Security matters.
ii) For all vessels (Indian/Foreign flag) before they are allowed to enter site, minimum 4
months in advance the contractor must submit the details of the vessels along with
the crew list (Indian/Foreign) and necessary valid certificates to COMPANY for
obtaining Ministry of Defence (MOD) clearance, etc.
clearance, the vessels shall be inspected by Indian Navy or any other authorized
agency (as authorized from time to time to inspect the vessel) before they can be
allowed to proceed to site. The location of inspection and other procedures can be
discussed with COMPANY before inspection.
Contractor is advised to give preference to Indian flag vessels for undertaking
various operations off the Indian cost. The Foreign vessels may be employed only
when suitable Indian vessels are not available.
- 102 of 237 -
Date: 18.12.2010
Rev 0
barges/vessels (such as number of sailings) going directly to the offshore site at least
four (4) weeks prior to the start of the construction season.
Procedure for Naval Security Clearance of vessels/barges proposed to be deployed at
offshore
1) Any vessel/barge, before being deployed at offshore, shall be offered by the
contractor for clearance by the Indian Navy and foreign flag vessel shall have
clearance from Ministry of Surface Transport (MOST).
2) The contractor shall apply to the concerned personnel
- 103 of 237 -
Date: 18.12.2010
Rev 0
3) The concerned personnel of HPCL will send all the details giving reference of
the contract to the office of the Chief of Security section giving the tentative
date/dates of arrival of the vessel/barge concerned.
4) The COMPANY will forward all the relevant vessel documents received from
the contractor with a recommendatory letter to Ministry of Petroleum & Natural
Gas (MOPNG) for onward endorsement to MOD for clearance of the
vessel/spread. However, the responsibility of obtaining MOD clearance will be
that of the contractor.
5) The COMPANY will also submit one additional copy of all the relevant
documents to Naval Headquarters at the following mailing address
The Chief of Naval Staff
(For Director of Intelligence)
Naval Headquarters
C/o Defence HQ Post Office
New Delhi 110 011
6) The contractor shall inform the Naval authorities of the arrival date of the
spread/vessel at least a week in advance of its actual arrival. The Contractor will
then arrange for fixing up the date and place for clearance of such vessel and
transportation of the inspection team and any other naval requirement at the time
of clearance. The inspection would be carried out at a point outside the field at
any of the locations as per the convenience of all the parties involved. All
laisoning work shall be carried out by Contractor.
- 104 of 237 -
Date: 18.12.2010
Rev 0
7) After inspection, Naval Security Clearance number will be given on the spot,
which should be retained by the vessel/barge concerned throughout its stay at
offshore.
iv)
4.15
Surveys
4.15.1 i)
The contractor shall, at their own cost, independently carry out preconstruction/pre-installation survey of the sites with their survey equipment before
start of offshore pile construction/installation. It shall be the sole responsibility of
the contractor to suitably mark all the pile locations, submarine pipeline route etc.
to enable them to proceed with the work. The contractor will use side scan sonar
and sub-bottom profiler or any other equipment approved by the COMPANYs
representative to locate and mark the same before dropping anchors etc. and will
also constantly check and monitor the position of such anchors due to possible drift
or anchor dragging. The contractor shall be fully responsible for any damage
- 105 of 237 -
Date: 18.12.2010
Rev 0
All time and cost affect due to obstructions and physical conditions including
debris, if any, making impossible or adversely affecting performance of the works,
which were not reported during or immediately after the pre-construction survey
and are encountered and reported during installation shall be to the contractors
account.
The contractor shall report presence of any debris at the site(s) during preconstruction survey.
paragraph, the COMPANY shall not be liable for any time and cost effect in respect
of debris found during installation, unless the contractor proves with evidence to the
satisfaction of the COMPANY/PMC that such debris occurred for reasons not
attributable to the contractor and their sub-contractor(s) and that the same was not
existing upto the time pre-construction survey was carried out and the same is found
to be there at the time of installation.
The contractor shall show video cassettes to establish the presence and quantity of
debris noticed during pre-construction survey and installation, duly witnessed by the
COMPANYs representative.
However, if the debris or unwarranted material is proved by the contractor to be
attributable to the COMPANY or its other contractors, the COMPANY shall
compensate removal of these in accordance with the contract.
4.15.3 Post-Installation Survey
The contractor shall carry out as installed, surveys for the installation. If any
debris or unwanted material which was not found and reported by contractor to the
COMPANY/PMC during pre-construction survey is observed during post
installation survey, the same shall be removed by the contractor without any time
- 106 of 237 -
Date: 18.12.2010
Rev 0
service
to
and
fro
between
contractors
design
center(s)
and
COMPANY/PMCs office(s) shall be borne by the contractor and the time taken in
transit shall also be to contractors account.
4.17
Support Diving
The contractor shall at their own cost provide all equipment facilities and personnel
needed to perform diving operation required for performance of the works or for the
inspection of the works carried out. All diving and other special diving equipment
shall be provided by the contractor at their own cost to take care of any sub-sea work
during execution of works including provisions of facilities for Video Monitoring
and Underwater Ultrasonic testing of welds if required to carry out scope of work
covered under the contract.
elsewhere or diver held Video Equipment and show the necessary video tape to
COMPANYs representative when required by him to satisfy about underwater
works carried out by contractor.
4.18
Workmen
- 107 of 237 -
Date: 18.12.2010
Rev 0
4.18.1.1 The contractor shall make their own arrangements for the engagement of all
workmen, local or otherwise, and for their transport, housing, feeding and
payment.
4.18.1.2 The contractor shall provide at site adequate supply of drinking water and other
water for use by their personnel at site. Contractor to note that water supply &
power supply for any purpose will NOT be provided by OWNER.
4.18.1.3 In any illness of an epidemic nature breaks out, the contractor shall comply with
and carry out whatever regulations, orders and requirements are imposed by the
Government or the local medical or sanitary authorities for the purpose of
promptly dealing with and overcoming it.
4.18.1.4 The contactor shall at all times take all reasonable precautions to prevent any
unlawful riotous or disorderly conduct by or amongst the persons deployed for the
works at site and for the preservation of peace and the protection of persons and
property in the neighbourhood of the work.
4.18.1.5 The contractor shall ensure that the provisions of this clause 4.18 are complied
with by their sub-contractors also.
4.19
4.19.1 General
All materials and workmanship shall be as specified in the contract and in
accordance with the requirements of the contract.
In the event of any revision(s) in the Codes and Standards which become effective
after the date two weeks prior to the date of submission of price bids, the cost effect
will be borne by the COMPANY subject to such change(s) being effected with prior
approval of the COMPANY.
- 108 of 237 -
Date: 18.12.2010
Rev 0
All materials and workmanship shall be subjected from time to time to tests,
inspections which the COMPANYs representative may direct as per the contract
either at the place/agency of manufacture or fabrication or at the site or at such other
place(s) or agency(ies) as may be required for erection of the works as per contract
without any time and cost effect to COMPANY.
The contractor shall provide assistance, instruments machines, labour and materials
which are normally required for examining, measuring and testing any work and the
quality, weight or quantity of any material used and shall supply samples of
materials before incorporation in the works for testing, as may be selected and
required
by
the
COMPANYs/Engineers
representative.
The
inspection at the time mutually agreed or if it is agreed between the parties that the
COMPANYs inspector shall not do so, then the contractor may proceed with the
test and/or inspection in the absence of the COMPANYs inspector and provide the
COMPANY with a certified report of the results thereof.
Tests of materials, equipment, systems and workmanship shall include but are not
limited to the tests referred to in and required by the contract specifications.
- 109 of 237 -
Date: 18.12.2010
Rev 0
- 110 of 237 -
Date: 18.12.2010
Rev 0
4.19.3.3 The costs of all radiography, ultrasonic, magnetic particle or other inspection of
weld or base metal, as provided for in sub-clause 4.19.3.1 and the costs of all other
testing and inspection as provided for in the sub-clause 4.19.3.2 upto the limits
prescribed in the contract specifications shall be to contractors account.
4.19.3.4 Unless otherwise specified cost of all works/tests etc. as specified in contract are
deemed to be included in the lump sum price of the contract.
4.19.4 Additional Tests
If any additional test is ordered by the COMPANYs representative which either:
a) is not provided for in contract specifications
b) though provided for in the contract specifications, is ordered by the
COMPANYs representative to be carried out by an independent person/agency
at any place/agency other than the site or at the place/agency of manufacture or
fabrication of the materials; the cost and time effect of the test shall be borne by
the contractor if the test shows that workmanship or materials are not in
accordance with the provisions of the contract.
- 111 of 237 -
Date: 18.12.2010
Rev 0
Whenever the contractor is ready to carry out any such test or inspection, the
contractor shall give reasonable advance notice of such test and or inspection and of
the place and time thereof. The contractor shall obtain from any relevant third party
or manufacturer necessary permission or consent to enable the COMPANYs
representative/authorized inspector to attend the test and/or inspection.
The
contractor shall provide every facility for and necessary assistance in obtaining the
right of access including (without limitation thereto) the provision of local transport
to and from the site for the COMPANYs personnel including COMPANYs
representative and Engineer/Engineers representative. All accesses to works in at
site provided by the contractor shall in all respects be protected and safe.
The contractor shall provide the COMPANYs representative with a certified report
of the results of any such test and/or inspection.
4.19.6 Opportunity for Inspection of Works
4.19.6.1 Any part of the works shall not be covered up or put out of view without the
approval of the COMPANYs representative or the Engineer/Engineers
representative and the contractor shall give reasonable notice and provide full
opportunity to the COMPANYs representative or the Engineer/Engineers
representative to examine and measure any work by providing the facilities for
examinations and measurement including the equipment required for them which
is about to be covered up or put out of view or installed below the surface of the
sea and to examine any part of the work before other part of the work is placed.
The contractor shall give reasonable notice to the COMPANYs representative or
Engineer/Engineers representative whenever any work is ready or about to be
ready for examination and the COMPANYs representative or Engineer/Engineers
representative shall without unreasonable delay, unless he considers it unnecessary
and advises the contractor accordingly, examine/measure/inspect the works.
Contractor
shall
mobilize
vendor
representative
- 112 of 237 -
during
pre-
Date: 18.12.2010
Rev 0
4.19.6.2 The contractor shall uncover any part of the works or make openings in or through
it as the COMPANYs representative from time to time directs and shall reinstate
and make good such part or parts to the satisfaction of the COMPANYs
representative in accordance with contract.
4.19.6.3 If any part uncovered or opened pursuant to Clause 4.19.6.2 has been covered up
or put out of view after compliance with the requirements of Clause 4.19.6.1 an
after inspection is found to be executed in accordance with the contract the
expenses for uncovering making openings in or through, reinstating and making
the same good shall be borne by the COMPANY and appropriate time extension
shall be granted to the contractor in the event that project critical path is affected.
Should project critical path not be affected only cost impact will apply. But in any
other case all the expenses shall be borne by the contractor and time affect, if any,
shall be to contractors account.
4.19.7 Removal/replacement of improper work and materials
4.19.7.1 During the progress of the works the COMPANYs representative shall have the
power to order:
i) the removal from site of any materials which are not in accordance with the contract
and which are supplied by the contractor. The material shall be removed by the
contractor at their own expense.
ii) the substitution of proper and suitable materials according to contract specifications.
iii) the removal and rectifications of any work (notwithstanding any previous test thereof
or interim payment therefore) which in respect of material or workmanship is not in
accordance with contract.
Such orders shall be issued by the COMPANYs representative in writing.
- 113 of 237 -
Date: 18.12.2010
Rev 0
4.19.7.2 In case of default on the part of the contractor in carrying out an order pursuant to
clause 4.19.7.1 the COMPANY shall be entitled to deploy other person/agency to
carry out such works and all expenses directly related thereto shall be recoverable
from the contractor by the COMPANY. COMPANY will notify the contractor of
the amount, with details, so incurred by it. If the contractor fails to pay the amount
to the COMPANY within 30 days from the receipt of the invoice with the required
back-up documents the amount may be deducted by the COMPANY from any
money which is due or which may become due to the contractor.
4.19.7.3 In the event contractor proposes substitution of any materials/equipment, it shall be
the contractors responsibility to prove to the COMPANYs representative that the
materials/equipment offered by them are equivalent or better in specifications than
those specified in the contract.
Cost savings, if any, arising out of any substitution of materials/equipment shall be
passed on to the COMPANY. Cost increase if any due to substitution shall be
borne by the contractor. No extension of time on this account shall be granted to
the contractor.
4.20.1 When the whole of the works have been completed in accordance with the contract
and have satisfactorily passed tests prescribed in the contract, the contractor shall
notify the COMPANY/PMC in writing enclosing all the required documents and
reports for review and acceptance by the COMPANYs representative.
- 114 of 237 -
The
Date: 18.12.2010
Rev 0
contractor will also notify the COMPANYs representative in writing within 7 days
in advance regarding the likely completion date of the works.
As the work progresses, the contractor shall continue to provide the required details
and data for review by the COMPANYs representative to assist in the expeditious
inspection of the works when completed. The COMPANYs representative will
review promptly and revert within 14 days after receipt of such notice. If the works
are found to be complete in all respect and carried out in accordance with the
contract then the COMPANY shall issue a completion certificate as provided for in
clause 4.20.2. If some defects and/or deficiencies are noticed in the works, the same
shall be notified to the contractors in writing within 14 days after receipt of
contractors notice. Such defects and/or deficiencies attributable to the contractors
work and workmanship shall be rectified promptly by the contractor at their own
expenses for which no extension will be granted. The contractor shall thereafter
repeat the procedure for giving notice as stated above.
4.20.2 If the COMPANY/PMC is satisfied that the entire works have been completed as
specified in the contract and have successfully passed all tests provided in the
contract then the COMPANY will issue a Completion Certificate.
4.20.3 The contractor shall not use or occupy any part of the works unless its use or
occupation has been agreed to by the COMPANY/PMC in writing.
4.20.4 COMPANYs acceptance of the works shall not operate as a waiver of the
COMPANYs rights under guarantees in the contract herein contained as to any
defects and deficiencies under clause 4.31.1.
4.21
Date: 18.12.2010
Rev 0
for the construction and completion of the works and the contractor shall not remove
them or any part of them (save for the purpose of moving them form one part of the
site to another) without the written consent of the COMPANYs representative,
which will not be unreasonably withheld or delayed, subject, however, to the
provisions contained in the contract. Unless otherwise specified in the contract,
upon completion of the work the contractor shall remove from the site all
constructional plant and equipment brought by the contractor on to the site and any
surplus materials.
- 116 of 237 -
Date: 18.12.2010
Rev 0
- 117 of 237 -
Date: 18.12.2010
Rev 0
4.21.3.1 The contractor shall acquaint themselves with all the formalities and procedures of
Indian Governmental Agencies such as Customs, Excise, licensing authorities etc.
It shall be sole responsibility of the contractor to get the materials, equipment,
constructional plant and equipment and other things required of the works cleared
from all Governmental Agencies including but not limited to, Customs/Excise and
pay all duties/taxes/charges/fees/expenses including fines/penalties imposed, if
any, except where otherwise expressly provided in the contract to be paid by the
COMPANY. The contractor shall be responsible for import of said constructional
plant and equipment, material, equipment or other things etc. Customs clearance
will have to be obtained by the contractor as per Customs law irrespective of
whether Customs Duty is applicable or not applicable. As regards examination of
goods at site the same shall be carried out by Customs Officer on receipt of
information. However, IGM and bill of entry shall be filed by the contractor with
the Customs Authority well in advance of arrival of heavy equipment mentioned
above at offshore site. The contractor shall also be responsible for re-export of
said constructional plant and equipment and any unused materials within 15 days
after completion of the works. The contractor shall obtain any and all necessary
Governmental Clearance required for such import/re-export.
4.21.3.2 The contractor shall schedule all activities in advance, taking into account any
possible delays in complying with the aforesaid requirements. No extension of
time shall be granted to the contractor on this account.
4.21.3.3 The contractor shall defend and indemnify the COMPANY against all claims,
charges and expenses whatsoever which arises on account of not obtaining
requisite import/re-export permit clearance and/or on account of not re-exporting
their belongings including but not limited to constructional plant and equipment,
unused materials, consumables, components etc. expeditiously after completion of
works, in accordance with the contract.
- 118 of 237 -
Date: 18.12.2010
Rev 0
4.21.3.4 In the event of any part of the works being damaged/ lost subsequent to payment of
Customs Duty due to reasons not attributable to the COMPANY, it shall be the
contractors responsibility to make good the same through fresh import and to pay
and bear the Customs Duty applicable.
4.21.4
The operation of clause 4.21.3 shall not be deemed to imply any approval by the
COMPANYs representative of the material of equipment of other matters referred
to therein nor shall it prevent the rejection of any materials or equipment at any
time by the COMPANYs representative.
preceding sentences, it is specifically agreed that the contractor shall comply with
the following:
i) Solid waste, such as tins, bottles or any form of trash must be transported to shore in
appropriate containers.
ii) Solid combustible waste may be burned and the ashes may be disposed of into the
sea.
- 119 of 237 -
Date: 18.12.2010
Rev 0
iii) Edible garbage which may be consumed by aquatic life without harm may be
disposed of into the sea.
iv) All waste oil and greases shall be placed in containers and taken ashore for disposal.
The contractor shall either curb all areas subject to contamination and connect these
to a collecting tank or sump or provide drip pans under any equipment or area where
pollutants might logically originate and connect these pans to a sump.
v) Care will be taken to secure all deck cargo in such a manner as to ensure that the
cargo, its covers (plastic or tarpaulins) or its fastenings will not be lost into the sea.
The Contractor shall inform themselves and their supervisors of such laws, orders
and regulations and to make all their employees and the sub-contractors fully
cognizant of their responsibilities thereafter.
The COMPANYs representative may discuss interpretations and applications of the
laws, orders and regulations referred above with the contractors representative or
construction superintendent, but such discussion shall not in any way relieve the
contractor of their responsibility hereunder. In addition and without in any way
limiting, restricting or prejudicing any of the COMPANYs other rights and
remedies, whether arising under any other provisions of this contract or under any
rule of law, the contractor shall :
i) Clean up and remove any pollution resulting from its non-compliance with the
provisions of this section, at their cost and expenses; and
ii) If the contractor fails to do so, the COMPANY may clean up and remove the
pollution in which case the contractor shall reimburse the COMPANY upon receipt
of bill therefore from the COMPANY the cost of such clean up and removal.
Such costs and expenses set forth in (i) and (ii) above shall be subject to the
limitations set forth in the following paragraph :
- 120 of 237 -
Date: 18.12.2010
Rev 0
- 121 of 237 -
Date: 18.12.2010
Rev 0
4.23.1 Payment of works or part thereof whose price is subject to adjustment shall be based
on measurement of quantum of work executed and measured as stipulated herein.
The measurement of works shall be based on the as installed drawings which shall
be prepared based on the latest revision of approved AFC and shop drawings and
shall specifically, include all the changes incorporated during the execution of the
entire works with their reasons for changes duly approved by COMPANY/PMC.
These drawings are required to be submitted along with weight/length calculation
sheets within 45 days of completion of installation of respective items.
4.23.2 The COMPANYs representative shall ascertain and determine by a measurement
the value in accordance with the contract of work done pursuant to the contract.
The COMPANYs representative will give notice to the contractors authorized
representative when he wants any parts of the works to be measured. The contractor
shall forthwith attend or send a qualified person to assist the COMPANYs
representative or the Engineer/Engineers representative in that measurement and
shall furnish all particulars measurement by either of them. Should the contractor
not attend or neglect or omit to send representative then the measurement made by
the COMPANYs representative or approved by him shall be taken to be correct.
4.23.3 Works shall be measured on as installed basis net of all loss and wastage of
materials for the purpose of payments under the contract notwithstanding any
general or local custom, unless otherwise specifically prescribed in the contract.
4.23.4 The mode of measurement shall be in Metric System. Length will be measured in
meters and rounded off to 2nd decimal place.
4.23.5
- 122 of 237 -
4.24
Date: 18.12.2010
Rev 0
Completion Certificate
No certificate other than the Completion Certificate shall be deemed to constitute
approval of any work or other matter in respect of which it is issued or shall be taken
as an admission of the due performance of the contract or any part of it or of the
accuracy of any claim or demand made by the contractor or of extra work/change
order having been ordered by the COMPANY/PMC nor shall any other certificate
conclude or prejudice any of the rights of the COMPANY.
4.24.1 The contract shall not be considered as completed until a Completion certificate has
been signed by the COMPANYs representative on behalf of the COMPANY and
delivered to the contractor stating that the works have been completed to the
satisfaction of the COMPANYs representative in accordance with the contract.
4.25
4.25.1 General
The contractor shall comply with the specifications and instructions for handling and
storage, marking and loading, etc. as detailed in the contract specifications and any
other instructions which may be issued by the COMPANY/PMC.
4.25.2 The contractor shall load and stack the material in seaworthy condition conforming
to the prescribed standards in force to withstand land/ocean journey and insuring the
safety of cargo en-route and also arrival of material at ultimate destination in good
condition. Each package shall have on its outer side the following marking in
English in indelible paints.
i)
Port of loading
ii)
Name of contractor
iii)
Port of destination
- 123 of 237 -
iv)
Date: 18.12.2010
Rev 0
4.25.3 In addition to the marking stated above, each package approved by the
COMPANYs representative shall carry a serial number or other appropriate
indelible marking/identification indicating the COMPANYs representatives
certificate of quality and/or the contractors certificate of quality and/or the
contractors certification of inspection and other documents as may be issued with
reference thereto.
The
The contractor shall ensure that no packages are shipped unless marked to comply
with all the instructions of the COMPANY/PMC.
4.25.5 Markings shall be correlated in invoices, packing list and on bill of lading, express
receipt of mailing certificates exactly as they appear on the equipment/materials.
4.26
Supply of Consumables
The contractor shall be responsible for furnishing all consumables required for
fabrication, installation, testing, trial runs, flushing, pre-commissioning and
commissioning as per scope of contract.
4.27
without affecting the overall schedule of completion. It is likely that the other
contractors/agencies may be carrying out their activities in nearby vicinity during the
same working season. It is imperative that the contractor shall coordinate with other
contractors/agencies, if required and necessary, as and when instructed by the
COMPANY/PMC in writing.
- 124 of 237 -
Date: 18.12.2010
Rev 0
contractor
shall
furnish
all
the
information
as
sought
by
the
4.29.1 The contractor shall comply with all the laws, rules and regulations including but not
limited to those related to security matters (clause 4.14.11), Contract Labour Act,
Minimum Wages Act, ESI/PF Act etc. and shall keep the COMPANY harmless and
indemnified for any action brought against it for any violation/non-compliance of
any of the acts etc.
- 125 of 237 -
Date: 18.12.2010
Rev 0
4.29.2 The contractor shall give all notices and pay/bear all duties, taxes, charges, fees and
expenses except where otherwise expressly provided in the contract required to be
given or paid by any national or state statue, ordinance or other law or any regulation
or by-law of any international, local or other duly constituted authority in relation to
the performance of the works or of any temporary works and by the rules and
regulations of all public bodies and companies whose property or rights are affected
or may be affected in any way by the works or any temporary works. The contractor
shall acquire all permits, approval and or licenses form all local, state or central
government authorities or public sector undertakings in India, which such authorities
require the contractor to obtain in their name and which are necessary for the
performance of the contract including import licenses for materials and
visas/clearance from security angle etc. for the contractors and sub-contractors
personnel and entry permits for all imported constructional plant and equipment and
shall acquire all other permits, approvals and/or licenses which are not the
responsibility of the COMPANY and which are necessary for the performance of the
contract.
However, COMPANY shall assist contractor and/or sub-contractor upon receiving
written request from contractor to acquire the necessary permit, approvals and/or
licenses including work permit, visas and import licenses from all local, state or
central Government authorities or public sectors to the extent of issuing
recommendatory letters and documents mandatorily required to be submitted by
COMPANY to the concerned authorities without assuming any liability whatsoever.
4.29.3 The contractor shall comply with and confirm in all respects and shall ensure that all
their sub-contractors also comply with and confirm in all respects with the
provisions of any statute, ordinance or law as aforesaid and the regulations or byelaws of any international, local or other duly constituted authority which may be
applicable to the works or to any temporary works and with such rules and
regulations of public bodies and companies as aforesaid and shall be responsible for
- 126 of 237 -
Date: 18.12.2010
Rev 0
all costs arising from compliance and/or violation of the same and shall keep the
COMPANY indemnified against all penalties and liabilities of every kind for breach
of any statute, ordinance or law, regulations or bye-law
4.29.4 Without limitation of the generality of clause 4.29.3 the contractor shall observe and
comply with and shall ensure that all their sub-contractors also observe and comply
with the laws, regulations or requirements of any states which are littoral states with
respect to any sea areas comprised at the site and of any international authority or
international convention or other rule of international law or custom applicable
thereto for establishing or regulating freedom of navigation on the high seas,
conservation and protection of fisheries, policing and jurisdiction in territorial water
and exercise of sovereign rights over the sea-bed.
4.29.5 The contractor shall keep informed the COMPANY and appropriate Indian
authorities reasonably in advance, of all obstructions in the waters of the Bay of
Bengal and any other area of the continental shelf within Indian jurisdiction and
adjacent waters and the approaches to them which the works will involve. The
contractor shall have regard to all warnings and information issued by the statutory
authorities.
4.29.6 Subject to provisions of the contract, the contractor shall defend, indemnify and hold
the COMPANY harmless from and against all penalties, liabilities, damages, claims,
fines and expenses of whatever nature arising out of or resulting form the violation
of such laws or rules or regulation having the force of law within the scope of clause
no. 4.29.3, 4.29.4 and 4.29.5 by the contractor or their sub-contractors including
their personnel.
4.29.7 All fossils, coins, articles of value of antiquity and structure and other remains or
things of geological or archeological interest discovered at the site or during the
works shall be the absolute property of the COMPANY. The contractor shall take
- 127 of 237 -
Date: 18.12.2010
Rev 0
ii)
The Certification shall be in accordance with the rules, standards and regulations
stipulated in the CONTRACT and as required by the Certification Agency.
iii)
The certification agency will inspect and certify the work barge, at
COMPANYS discretion, at the barge setup yard prior to its travel to
Visakhapatnam. CONTRACTOR to obtain certification of the barge from
certification agency before commencement of travel to Visakhapatnam Port.
However, certification from certification agency shall not relieve any obligations
of the contractor under the contract.
iv)
The Certification Agency will review and approve all drawings, documents and
procedures related to design, engineering, procurement, fabrication, installation
and testing and CONTRACTOR shall submit the same during design &
engineering stage.
v)
The Certification Agency will review and approve the drawings and documents
related to sea fastening and load out and those shall be submitted by the
CONTRACTOR atleast 60 days prior to the activity.
- 128 of 237 -
vi)
Date: 18.12.2010
Rev 0
The Certification Agency will attend to the tests and inspections that shall be
carried out by The CONTRACTOR at their shop for witness and approval during
fabrication, if any. CONTRACTOR to give atleast 14 days prior notice for shop
inspections, if any. However, for all site/ barge related inspection activities,
inspector will be available at spot.
vii)
The Certification Agency will station their inspectors at installation site and work
barge to fulfill the activities of tests and inspection as required for the
Certification.
viii)
The Certification Agency will issue the Certificates upon completion and
satisfaction for the activities of Certification.
j) The contractor shall meet the requirements of the certification agencies and shall
also be responsible to co-ordinate with the certification agencies in supplying to
them in a timely manner, specifications, drawings, plans, calculations and all
such other information relating to the work as may be required by the
certification agencies from time to time including assistance at the appropriate
sites to carry out their work.
The contractor shall ensure at their own cost quick supply of required copies of
documents/drawings to the certification agency by fastest courier service
available.
Should the requirements of certification agencies exceed those of contract
specifications, the same shall be dealt in accordance with section 4.33.1.
k) In addition OWNER will appoint a MARINE WARRANTY SURVEYOR for
their insurance purpose at their own cost. CONTRACTOR shall provide all
necessary facilities and also comply with requirements of the Marine Warranty
Surveyor at no extra cost to OWNER.
- 129 of 237 -
4.31
Date: 18.12.2010
Rev 0
- 130 of 237 -
Date: 18.12.2010
Rev 0
COMPANY from any money which is due or may become due to the contractor
including COMPANYs right to encash the performance guarantee furnished by
the contractor in accordance with provision of clause 4.10.
4.31.1.3 The period of guarantee for any part of the works shall be as specified in clause
4.31.1.1. If the works or any part thereof cannot be used by reason of such
defect/damage and/or making good of such defect, and/or damage the warranty
period of the works or such part thereof as the case may be shall be extended by a
period equal to the period during which the works or such part thereof cannot be
used by the COMPANY due to any of the aforesaid reasons. The contractor shall
arrange for the performance guarantee to remain valid until the expiration of the
extended warranty period with respect to such part of the works.
4.31.1.4 To the intent that during the period of guarantee the works shall remain in as good
condition (fair wear and tear excepted) as they were at the beginning of the period
of guarantee and that all things shall continue to perform or operate (fair wear and
tear excepted) during the period of guarantee in accordance with all relevant
contract specifications or contract conditions. The contractor shall do all repair,
amendment,
reconstruction,
rectification
and
making
good
of
defects,
imperfections, shrinkages and settlements, including where necessary the repair or,
if repair proves impossible, the replacement of any plant machinery, equipment
thing or process, which the COMPANY requires of the contractor in writing
during the guarantee period or within fourteen days after the expiration of the
period of guarantee as a result of any inspection make during the period of the
guarantee.
4.31.1.5 The contractor shall be and remain responsible during the period of guarantee for
making good with all possible speed any defects arising from contractors
defective design and engineering (other than a design made, furnished or specified
by the COMPANY and for which the contractor has disclaimed responsibility in
- 131 of 237 -
Date: 18.12.2010
Rev 0
writing within 15 days time after receipt of the COMPANYs instruction) of the
aforesaid structure, which may develop under the conditions provided for in the
contract and under proper use in the works or any portion thereof.
4.31.1.7 The contractor shall carry out all the works and supply and install all replacement
materials pursuant to this section at no additional cost to the COMPANY including
the cost of timely transport of materials and equipments to site if the need for the
work is due to poor workmanship or faulty materials supplied by the contractor or
due to the use of materials not in accordance with the contract or specifications or
due to neglect or failure of the contractor to comply with any obligations.
4.31.1.8 During the guarantee period if the contractor is required by the COMPANY to visit
the offshore site for checking and carrying out remedial work of facilities all
expenses towards personnel, traveling to and from the site, living and
accommodation etc. while in India for remedial works shall be borne by the
contractor unless such defects are caused by the COMPANY or COMPANYs
agents/other contractors.
4.31.2 Completion and Liquidated damages
4.31.2.1 Completion
The scheduled completion date(s) for the works covered under the contract shall be
as per clause 4.7.5 above.
However, the COMPANY reserves in itself the right, if the exigencies of the project
under consideration so required, to phase out the completion of any part of the works
by mutual agreement.
4.31.2.2 Liquidated Damages
- 132 of 237 -
Date: 18.12.2010
Rev 0
limiting or reducing in any manner any other provisions of the CONTRACT, and in
particular any such provision pertaining to their obligation, liability or responsibility
shall procure and maintain at their own cost and expenses the various insurance
policies specified herein or the benefit of and in the joint names of the COMPANY
and the contractor against all risks upto the contract value thereof or such additional
- 133 of 237 -
Date: 18.12.2010
Rev 0
sum as may be specified in the CONTRACT in such a manner that the COMPANY
and the CONTRACTOR are covered
i)
from the commencement of the WORK until the date of issue of certificate of
completion and acceptance for loss or damage arising from a cause, occurring
prior to the date of issue of certificate of completion and acceptance and for
any loss or damage occasioned by the contractor in the course of any
operations carried out by them.
ii)
during the guarantee period against any loss or damage arising from either the
contractor complying with their obligations under the contract or for
completing any outstanding work.
OR
for loss or damage in respect of the works completed by the contractor prior to
the commencement of the guarantee period.
4.32.1.2
i)
ii)
Insurance to cover all risks (a) In respect of their employees, personnel and
representatives deputed to work under the CONTRACT (b) covering all
vessels, marine spreads, barges, ships and marine crafts (whether navigable
or not) and ERECTION EQUIPMENT including but not limited to hull and
machinery owned, leased, chartered or hired by the CONTRACTOR or any
- 134 of 237 -
Date: 18.12.2010
Rev 0
iv)
v)
- 135 of 237 -
vi)
Date: 18.12.2010
Rev 0
vii)
All Risks Physical Damage Insurance for the full replacement value and
covering loss of or damage to ERECTION EQUIPMENT supplied and all
other property belonging to or hired or used by CONTRACTOR or
SUBCONTRACTORS at WORK SITE.
viii)
which
shall
arise
out
of
or
in
consequence
of
COMPANY shall at all times until Commissioning at their own expense provide
and maintain the following insurance:
a) Third party liability covering bodily injury or loss of human life
(engineers
and
workmen
not
belonging
to
CONTRACTOR
or
- 136 of 237 -
Date: 18.12.2010
Rev 0
/ loss of human life and damage of equipment/ property shall not exceed US
$ 5,000,000 (US Dollars Five Millions only)
b) CAR (Construction All Risks) Insurance or any such equivalent cover in
conjunction with Hull & Machinery policy, against all risks of physical loss
or damage to WORK for full replacement value which includes all
CONSUMABLES and MATERIALS including FIM supplied to or provided
by COMPANY and/or CONTRACTOR and/or their SUBCONTRACTORS
and which are to be incorporated into the WORK (except ERECTION
EQUIPMENT and other property belonging to or rented by CONTRACTOR
or SUBCONTRACTOR) while at WORK SITE from the start of the WORK
until Commissioning. This policy shall also include loss or damage due to
pollution from the start of WORK until Commissioning.
4.32.1.4
- 137 of 237 -
Date: 18.12.2010
Rev 0
the CONTRACTOR shall ensure that COMPANY obtains the benefit of such
insurance policies.
4.32.1.6 COMPANY will name CONTRACTOR and their SUBCONTRACTORS as
additional insured and shall include a cross liability provision on the policy specified
in Clause 4.32.1.3.
- 138 of 237 -
Date: 18.12.2010
Rev 0
and against any losses, damages, cost or claims relating to COMPANYs property
except in case of gross negligence or willful misconduct of the CONTRACTOR,
their SUBCONTRACTOR(S) their agents or employees, in which case the
CONTRACTOR shall be liable to bear any loss or damage occurring to the property
of the COMPANY as a result of its gross negligence or willful misconduct, provided
however, that such liability shall be limited to 100% of the contract price.
- 139 of 237 -
Date: 18.12.2010
Rev 0
Gross Negligence means: any act or failure to act (whether sole, joint or
concurrent) by a person or entity which was intended to cause, or which was in
reckless disregard of or wanton indifference to avoidable and harmful
consequences such person or entity knew, or should have known, would result
from such act or failure to act. Notwithstanding the foregoing, gross negligence
shall not include any action taken in good faith for the safeguard of life or
property.
willful misconduct means : International disregard of good and prudent
standards of performance or proper conduct under the contract with knowledge
that it is likely to result in any injury to any person or persons or loss or damage of
property.
4.32.1.13
The contractor shall prior to commencing any relevant part of the WORK
CONTRACTOR and as required under the terms of such policies shall be paid by
the CONTRACTOR. The CONTRACTOR shall produce a certificate from
CONTRACTORs insurance underwriters to the effect that all premia under the
policy have been paid and indicating validity of the policy. It shall be the
responsibility of the contractor to pay the premium in time and to keep the policies
- 140 of 237 -
Date: 18.12.2010
Rev 0
moneys due or which may become due to CONTRACTOR in addition to any other
remedies COMPANY may have under this CONTRACT.
However, if the policy lapses due to any reason, then the loss, damages and all
liabilities on account of the policy having lapsed shall be to the account of the
contractor, nothing in this clause shall be construed by the CONTRACTOR as a
waiver of their obligations to insure as required under the CONTRACT. Further
nothing in this clause shall impose upon the COMPANY any obligation to insure on
behalf of the CONTRACTOR. The COMPANY may exercise its option to do so as
stated herein but failure to exercise such option shall not entitle the
CONTRACTOR to seek damages from the COMPANY or eschew responsibilities
under the CONTRACT including their duties to insure and keep valid insurance
policies.
4.32.1.16
Notice of any occurrence which may give rise to any claim for loss or
COMPANY
giving full
details
of
such occurrence,
without
delay.
- 141 of 237 -
4.32.1.17
Date: 18.12.2010
Rev 0
with the insurance company and shall settle any and all claims with the insurance
company thereafter, keeping the COMPANY informed of all such action taken by
the CONTRACTOR. However, the CONTRACTOR shall proceed with the repair
and/or replacement of component/personnel and execution of the WORK and carry
out the CONTRACT without waiting for the settlement of the claim.
CONTRACTOR shall prepare and follow-up any claims made under the policies
effected as required under the CONTRACTOR at the CONTRACTORs risk and
cost. The CONTRACTOR shall not give any release or make any compromise with
the insurer without the prior written consent of the COMPANY, in respect of the
insurance claims in which COMPANYs interest is involved, which consent shall
not be unreasonably withheld.
4.32.2 War Risks
4.32.2.1
- 142 of 237 -
Date: 18.12.2010
Rev 0
the CONTRACT on account of above said demobilization, the Force Majeure clause
in the CONTRACT shall come into force. The foregoing provisions of this clause
shall not be construed to prevent the CONTRACTOR/COMPANY from invoking
the provisions of Force Majeure clause when the conditions stated in clause 4.32.5
occur. Any demobilization and remobilization ordered by the COMPANY under the
provisions of this clause 4.32.2 shall be to COMPANYs account, provided that the
details of such demobilization and remobilization including the place, duration and
cost of such demobilization shall be mutually discussed and agreed between the
parties.
Any additional cost incurred by the CONTRACTOR in protecting and preserving the
WORK prior to the CONTRACTOR leaving the SITE under this clause 4.32.2 and
time lost as a result of any suspension under this clause 4.32.2 shall be to the sole
account of the COMPANY.
4.32.3 WARRANTY SURVEYOR
Warranty Surveyor any marine surveyor appointed by COMPANY for insurance
warranty or other purposes.
COMPANY will appoint a Warranty Surveyor as required by the Insurance Policy at
its cost. CONTRACTOR shall provide all facilities as required and obtain all
- 143 of 237 -
Date: 18.12.2010
Rev 0
Force Majeure
The following provisions for Force Majeure shall be read in conjunction with Cl 13 of GCC.
4.33.1
The term Force Majeure as employed herein shall mean act of God, revolt, riot,
fire, flood, war, typhoon and Acts and Regulations of respective Governments of
the two parties, namely the COMPANY and the Contractor.
4.33.2
In the event of either party being rendered unable by Force Majeure to perform any
obligation required to be performed by them under the contract, other than the
obligation to make payments due and payable under this contract except when the
COMPANY is physically prevented by a force majeure event from making
payment, in which case the obligation shall be suspended the relative obligation of
the party affected by such force majeure shall upon notification to the other party
be suspended for the period of delay which is caused by such force majeure event.
4.33.3
Upon the occurrence of such cause upon its termination, the party alleging that it
has been rendered unable as aforesaid thereby shall notify the other party in
writing within seventy-two (72) hours of the alleged beginning and ending thereof
giving full particulars and satisfactory evidence in support of its claim.
4.33.4
Time for performance of the relative obligation suspended by the force majeure
shall then stand extended by the period of delay which is directly caused by force
majeure event. The party who has given such notice shall be excused from the
performance or timely performance of its obligations under the contract, for so
long as the relevant event of force majeure continues and to the extent that such
partys performance is prevented, hindered or delayed, provided the party or
parties affected by the event of force majeure shall use reasonable efforts to
- 144 of 237 -
Date: 18.12.2010
Rev 0
mitigate the effect thereof upon its performance of the contract to fulfill its
obligation under the contract.
4.33.5
b)
Give rise to any claim for damages or additional cost or expense occasioned
thereby, if such delay or non-performance is caused by the occurrence of an
event of force majeure. Force majeure conditions are not payable under any
circumstances.
- 145 of 237 -
Date: 18.12.2010
SECTION 5
SCOPE OF WORK
- 146 of 237 -
Rev 0
Date: 18.12.2010
Rev 0
5.0 INTRODUCTION
The objective for the work described herein is for CONTRACTOR to perform the
remedial work of providing firm support to 48 Offshore crude pipeline located in the
vicinity of sand trap area in Visakhapatnam Port using piled supports and supporting
clamps as per details provided herein. The proposed pile supports are for 260m section
of the installed offshore pipeline route i.e. from Ch150 to Ch410 m wherein the seabed
and pipeline profile was noticed to have been changed from the as-built status due to
sand trap dredging activity undertaken by Visakhapatnam Port Trust (VPT) in the
vicinity of the 48 offshore pipeline route of Single Point Mooring System of HPCL
located at Visakhapatnam, India.
5.1 SCOPE OF WORK
The base scope of work shall include but not limited to the following:
Provide permanent steel clamp supports for the 48 Offshore pipeline at regular
intervals along the pipeline section in the proximity of sand trap area. These steel
pipeline clamp supports are bolted and supported by a plate connected to a beam
which is further held by two piles driven into the seabed on either side of the
pipeline. This arrangement will always hold the pipeline in its vertical as well as
horizontal alignment even if the sand below the pipeline slips due to dredging
activities undertaken by VPT in the vicinity of the pipeline. This arrangement will
also have minimum restrictions to sand movement towards the sand trap. The piled
support for the pipeline provides an effective solution to protection for the entire
pipeline design life. The piled support consists of a 12.7mm thick 300mm wide
plate supporting the pipeline. This plate shall be connected to a horizontal beam with
stiffener plates which will be on top of the pipeline with an acceptable clearance.
- 147 of 237 -
Date: 18.12.2010
Rev 0
The beam will be held by means of bolted connections to two piles driven into the
seabed adjacent to the pipeline on both the sides of pipeline i.e. sand trap side and
Dolphin Hill side. The piles to be driven shall be 24 19.1mm thick structural
steel. This remedial work shall be undertaken as EPCI (Engineering, Procurement,
Construction and Installation) package which is planned to be executed before the
next dredging season of Feb 2011.
Preparation of detail fabrication and installation drawings for review and approval of
HPCL/INTEC. CONTRACTOR shall be responsible for all engineering pertaining
to preparation of site, temporary structures, and all installation engineering.
CONTRACTOR shall provide calculations to show the adequacy of selected
hammer/s to drive the piles. A dynamic wave equation analysis is required. All
lifting arrangement, riggings and lift appurtenances shall be calculated to comply
with project and industry standards. Lift charts shall be prepared for all major lifts to
ensure lift loads and radius are within the crane capacity. All temporary works shall
be engineered to ensure compliance to safety, health and environment requirements.
All engineering to be performed by CONTRACTOR shall be reviewed and approved
by HPCL/INTEC prior to implementation.
Provide standard 3 coat epoxy paint (suitable for marine application) system (total
minimum 400 DFT) for the piles/pipe support structures. The extent of the painting
shall be as indicated in drawing no. 21534102-401-DRW-026 (Sht 2).
CONTRACTOR shall use the paint manufactured by a reputed paint manufacturer
approved by HPCL/INTEC. The painting system proposed and painting procedure
shall be submitted to HPCL/INTEC for their review and approval.
Design and install anodes for the piles/structures. The design of the anode shall be as
per DNV-RP-B401 and shall be for a design life of thirty years. CONTRACTOR
shall procure the anodes from reputed anode manufacturer approved by
- 148 of 237 -
Date: 18.12.2010
Rev 0
Preparation and submission of Work Procedures and Inspection Test Plans (ITP) for
various activities of the work for review and approval of HPCL/INTEC. The work
shall be executed as per approved Procedures and ITPs.
Providing diving support for the execution of work. CONTRACTOR shall provide
under-water inspection of the installation work by carrying out diver survey of the
work. All under-water inspection videos shall be recorded on digital media to be
submitted together with the final as-built documentation.
Where the initial bathymetry survey showed the water depth to be excessive and the
designed pile installation cannot be performed, CONTRACTOR shall seek the next
course of action from HPCL/INTEC. If back-filling is required, CONTRACTOR
shall perform the back-filling operations as directed by HPCL/INTEC. Any
- 149 of 237 -
Date: 18.12.2010
Rev 0
CONTRACTOR shall excavate around the pipeline locally where the supports are to
be installed, where necessary. CONTRACTOR shall ensure that any such
excavation shall not introduce excessive free spans on the pipeline prior to
completion of the support installation. If necessary, CONTRACTOR shall provide
adjacent support by air-bags or sand bags as necessary.
All materials required for the work including 24 piles, beams, clamps, anodes,
paints etc shall be in the scope of supply of Contractor. Bidder to note that HPCL
will not issue any materials required for the work and the complete materials
required for the work shall be entirely in the scope of CONTRACTOR.
CONTRACTOR shall fabricate all permanent structures including the piles, beams,
support plates, anodes and all necessary components in accordance to design
drawings and specifications. The piles and structures shall be painted in accordance
to project specification mentioned above. All materials and fabrication procedures
shall be procured in accordance to the design drawings and to be approved by
HPCL/INTEC prior to fabrication. CONTRACTOR shall submit the list of the
vendors from whom they intend to procure the materials and get them approved by
HPCL/INTEC.
Liaise and seek approval/permit from local authorities and Government departments
and certification by necessary government authorities.
- 150 of 237 -
Date: 18.12.2010
Rev 0
Provide experienced supervision and managerial site staff to manage and execute the
work as per the best industrial practices.
Date: 18.12.2010
SECTION 6
SCHEDULE OF PRICE
- 152 of 237 -
Rev 0
6.1
6.2
Contents which are in the form of instructions / queries, are to be redrafted as affirmative replies and are to be reintroduced at
the same designated Serial Nos.
6.3
6.4
Bidder shall quote the prices strictly as per the Schedule of Price Format.
6.5
Complete typed matter/contents of the price schedule / price attachments are to be made available in the un-priced offer, with
prices blanked-out.
6.6
BIDDERs Schedule of Price shall not include any provision or condition for price escalation.
6.7
The Price quoted shall include all CONSTRUCTION EQUIPMENT and manpower required to execute the WORK to enable
OWNER to have a completed and workable PROJECT, which is operable in accordance with the PROJECT
SPECIFICATIONS and guarantees set forth in the CONTRACT.
6.8
The Schedule of Price shall include all taxes & duties as specified in Special Conditions of Contract.
6.9
For all items, on Lumpsum basis, payment will be made on actual quantity based on unit rates derived from the Lumpsum
amount
Breakdown of Price for Installation of Piled Supports for 48-inch Offshore Pipeline
- 153 of 237 -
Sr.
No
Description
Quantity
Lumpsum
Lumpsum
Lumpsum
- 154 of 237 -
Amount
Sr.
No
Quantity
Description
Lumpsum
14 Rows
(one row
consisting
of 1 pair
of 24
piles,
connectin
g beam,
clamp,
anode etc)
- 155 of 237 -
Amount
Sr.
No
Description
Quantity
Amount
Lumpsum
Total
Notes:
Signature of Bidder
Name & designation
With seal & Date
- 156 of 237 -
FORMAT A
(Total Cenvatable Excise Duty and cenvatable CVD amount included in the lumpsum price)
FORMAT B
(CIF Price for Imported Items)
Format A
Input Tax Credit available against Taxes & Duties included in the Lumpsum price and Input tax credit on service tax which
will be charged separately
- 157 of 237 -
Sl.no
Description
In Figures
In Words
1.
2.
Above Cenvatable duty shall be deducted from the lumpsum price for the purpose of evaluation.
3.
Cenvatable amounts as mentioned above shall be considered as mandatory discount since the same has been taken into consideration for
evaluation and shall be deducted from the RA bills (of supplies) on pro-rata basis. The amount of cenvatable excise duty and cenvatable
CVD shall be reimbursed to contractor on production of all related documents in accordance with the provision of bidding document
subject to ceiling amount mentioned above.
4.
- 158 of 237 -
Format B
CIF Price for Imported Items
Sl.no
Description
Insurance (2)
1.
2.
CIF Value mentioned above shall be used for the purpose of calculation on account of variation in custom duty.
3.
CIF value mentioned in this form shall not include raw materials required by vendor.
4.
C&F value mentioned above shall not be more than total of foreign currency component quoted above.
Signature:
With seal and date:
- 159 of 237 -
Date: 18.12.2010
SECTION7
CHECKLIST
(To be submitted along with UNPRICED bid (Part-1) of BID document
- 160 of 237 -
Rev 0
Date: 18.12.2010
Sl No.
Description
3
4
5
7
8
9
10
11
12
13
14
- 161 of 237 -
Bidders
confirmation
(Yes/No)
Rev 0
Sl No.
Description
15
16
17
18
19
20
21
22
23
24
25
26
27
28
- 162 of 237 -
Bidders
confirmation
(Yes/No)
Sl No.
29
30
31
32
33
34
35
Description
Bidders
confirmation
(Yes/No)
- 163 of 237 -
SECTION 8
ANNEXURES
- 164 of 237 -
Annexure-1
ACKNOWLEDGEMENT
Dated:
HINDUSTAN PETROLEUM CORPORATION LIMITED
Central Engineering,
Petroleum House,
17, Jamshedji Tata Road,
Mumbai- 400 020
INDIA
Attention: Mr. P. Wankhade Senior Manager (Materials)
Copy to : Mr. M. Mohan, Project Manager, INTEC Asia Pacific SDN BHD,
Kuala Lumpur, Malaysia
Sub: Request for Quotation for _____________________________
RFQ No.:
Item
Due Date
Dear Sirs,
We are in receipt of above-mentioned BID document along with all enclosures.
a) We confirm that we shall submit our offer to reach you latest by final due date.
b) We regret to offer item against above-mentioned BID document because
_____________ . BID documents are being returned to you shortly.
Thanking you,
- 165 of 237 -
(NAME OF BIDDER)
Place:___________________
Date:____________________
NOTE: The Bidders representative who is signing the bid should sign this undertaking.
- 166 of 237 -
Annexure-3
NAME OF WORK:
NAME OF BIDDER:
Bidder is required to comply with the requirements of the Bid Document, and not to stipulate
any exceptions or deviation. In case it is unavoidable, Bidder may stipulate exceptions and
deviations to bid requirements only as per the format below and enclose this with Part I of
bid.
SL.
NO.
SUBJECT
DEVIATION
CLAUSE
Note: All exceptions/deviations taken by Bidder to the stipulations of the Bid Document
shall be brought out in the techno-commercial bid (and not in the Bid Document or price bid)
as per this format. Any exceptions/deviations brought out elsewhere in the bid shall not be
construed as valid.
Signature of Bidder
- 167 of 237 -
Annexure-4
CUT-OUT-SLIP
DO NOT OPEN THIS IS A QUOTATION
Client
Due Date :
To
HINDUSTAN PETROLEUM CORPORATION LIMITED
Central Engineering,
Petroleum House,
17, Jamshedji Tata Road,
Mumbai- 400 020
INDIA
From
(Full Name and address of the Bidder with contact person)
- 168 of 237 -
Annexure-5
TERMS OF PAYMENT
Terms of Payment shall be as follows:
A)
i)
ii)
iii)
Note:
a)
All the payments to the contractor for this job will be made in the
respective currency of the bid.
b)
c)
d)
Any payment received by the contractor from HPCL shall be utilized for
expeditious execution of THIS CONTRACT only.
- 169 of 237 -
B)
Mobilization Advance:
A provision for payment of interest bearing mobilization advance up to 10% (ten
percent) of contract value at an interest rate State Bank of India (SBI) PLR + 0.5%
per annum, either on submission of a separate Bank Guarantee covering
mobilization advance alone or Composite Bank Guarantee covering mobilization
advance and Security Deposit, subject to the condition that the work will be
completed within the contractual completion period. If not, interest at penal rate of
2% above the rate charged by financial institutions/banks shall be charged for the
entire duration of the contract from the date of availing advance.
Such advance shall be paid to the contractor in two installments as under.
-
Recovery of mobilization advance paid (along with interest accrued) to the contractor
shall be made from each running account bill (gross value) on a prorata basis.
Balance amount, if any, remaining unrecovered will be deducted in full from the final
bill.
Bank Guarantee towards mobilization advance shall stand reduced
proportionally on monthly basis to the unrecovered amount only.
The MA paid to the contractor shall be used by them only for execution of the subject
work and they shall satisfy HPCL/INTEC in this regard, if required.
All BGs (Towards Bid fee, Mobilization advance, Security deposit etc) shall be from
a scheduled / nationalised commercial bank in India and for non-Indian bidders the
same shall be from an Indian branch of a foreign bank or any nationalized / scheduled
commercial bank in India).
- 170 of 237 -
Annexure-6
LOADING FACTORS
Sl No
1
a)
b)
c)
d)
PRICE LOADING
No Loading
1%
2%
Bank interest at 1.0% per month
for the quoted delivery period
subject to minimum of 1.5% of the
quoted price
e) Advance payment with balance against Calculate as per (1.d) above and
despatch documents
add further 1%
2
PERFORMANCE BANK GUARANTEE
a) 10%
No Loading
b) Other than 10% (indemnity bond not to be To be loaded by percentage by
considered as PBG)
which PBG is short of 10%
3
PRICE REDUCTION DUE TO DELAY
The loading factor shall be calculated as
per the formula
LF = Lx 1 - L1XL2
2
LN X LX
WhereLx Max LD % as per GPC/GCC
LN - Min LD% (LD per week) as
per
GPC/GCC
L1 - Min LD% (LD per week)
agreed by the vendor
L2 - Max LD% agreed by the
vendor
4
PRICE VARIATION
a) Firm price
No Loading
b) In case of increase in price on PVC with Load by percentage offered
ceiling specified
- 171 of 237 -
c) No formula specified
- 172 of 237 -
SECTION 9
TECHNICAL DOCUMENT
(Attachment)
LONG TERM REMEDIAL WORK PROPOSED
FOR HPCL SUBSEA PIPELINE AT THE SAND TRAP
AREA
- 173 of 237 -
SECTION 10
- 174 of 237 -
(SPECIMEN)
GENERAL TERMS & CONDITIONS OF WORKS CONTRACT
1 PRELIMINARY
1.1 This is a Contract for execution of __________________ work
at_______________________. (please fill up the blanks)
1.2 The tenderer for the abovementioned item of work is____________________________.
(please give the name and address of the tenderer)
1.3 The terms and conditions mentioned hereunder are the terms and conditions of the
Contract for the execution of the work mentioned under item 1.1 above.
1.4 It is the clear understanding between Hindustan Petroleum Corporation Limited and the
tenderer ______________________________________ that (name and address of the
tenderer)
in
case
the
tender
of
______________________________________________________________ is
(name and address of the tenderer) accepted by Hindustan
Petroleum Corporation Limited and an intimation to that effect is so issued and
also
a
Purchase
Order
is
placed
with________________________________________________________
(name and address of the tenderer) this document will be termed as a Contract between the
parties and terms and conditions hereunder would govern the parties interest.
1.5 Interpretation of Contract Documents: All documents forming part of the Contract are to
be taken mutually explanatory. Should there be any discrepancy, inconsistency, error or
omission in the contract, the decision of the Owner/Engineer-in-Charge/Site-in-Charge shall
be the final and the contractor shall abide by the decision. The decision shall not be
arbitrable. Works shown upon the drawings but not mentioned in the specification or
described in the specifications without being shown on the drawings shall nevertheless be
deemed to be included in the same manner as if they are shown in the drawings and described
in the specifications.
1.6 Special conditions of Contract : The special conditions of contract, if any provided and
whenever and wherever referred to shall be read in conjunction with General Terms and
Conditions of contract, specifications, drawings, and any other documents forming part of
this contract wherever the context so requires. Notwithstanding the subdivision of the
documents into separate sections, parts volumes, every section, part or volume shall be
deemed to be supplementary or complementary to each other and shall be read in whole. In
case of any misunderstanding arising the same shall be referred to decision of the Owner/
Engineer-in-Charge/Site-in-Charge and their decision shall be final and binding and the
decision shall not be arbitrable. It is the clear understanding that wherever it is mentioned that
the Contractor shall do/perform a work and/or provide facilities for the performance of the
work, the doing or the performance or the providing of the facilities is at the cost and
expenses of the work not liable to be paid or reimbursed by the Owner.
- 175 of 237 -
2. DEFINITIONS
In this contract unless otherwise specifically provided or defined and unless a contrary
intention appears from the contract the following words and expressions are used in the
following meanings;
2.1 The term "Agreement" wherever appearing in this document shall be read as "Contract".
2.2 The "Authority" for the purpose of this Contract shall be the Chairman and Managing
Director or any other person so appointed or authorised.
2.3 The "Chairman and Managing Director" shall mean the Chairman and Managing
Director of HINDUSTAN PETROLEUM CORPORATION LIMITED or any person so
appointed, nominated or designated and holding the office of Chairman & Managing
Director.
2.4 The "Change Order" means an order given in writing by the Engineer-in-Charge or by
Owner to effect additions to or deletion from or alterations into the Work.
2.5 The "Construction Equipment" means all appliances and equipment of whatsoever
nature for the use in or for the execution, completion, operation or maintenance of the work
except those intended to form part of the Permanent Work.
2.6 The "Contract" between the Owner and the Contractor shall mean and include all
documents like enquiry, tender submitted by the contractor and the purchase order issued by
the owner and other documents connected with the issue of the purchase order and orders,
instruction, drawings, change orders, directions issued by the Owner/Engineer-inCharge/Site-in-Charge for the execution, completion and commissioning of the works and the
period of contract mentioned in the Contract including such periods of time extensions as
may be granted by the owner at the request of the contractor and such period of time for
which the work is continued by the contractor for purposes of completion of the work.
2.7 "The Contractor" means the person or the persons, firm or Company whose tender has
been accepted by the Owner and includes the Contractor's legal heirs, representative,
successor(s) and permitted assignees.
2.8 The "Drawings" shall include maps, plans and tracings or prints thereof with any
modifications approved in writing by the Engineer-in-Charge and such other drawings as
may, from time to time, be furnished or approved in writing by the Engineer-in-Charge.
2.9 The "Engineer-in-Charge or Site-in-Charge" shall mean the person appointed or
designated as such by the Owner and shall include those who are expressly authorized by the
owner to act for and on its behalf.
2.10 "The Owner" means the HINDUSTAN PETROLEUM CORPORATION LIMITED
incorporated in India having its Registered office at PETROLEUM HOUSE, 17,
JAMSHEDJI TATA ROAD, BOMBAY - 400020 and Marketing office at
____________________________________________ or their successors or assignees.
- 176 of 237 -
2.11 The "Permanent Work" means and includes works which form a part of the work to be
handed over to the Owner by the Contractor on completion of the contract.
2.12 The "Project Manager" shall mean the Project Manager of HINDUSTAN
PETROLEUM CORPORATION LIMITED, or any person so appointed, nominated or
designated.
2.13 The "Site" means the land on which the work is to be executed or carried out and such
other place(s) for purpose of performing the Contract.
2.14 The "Specifications" shall mean the various technical and other specifications attached
and referred to in the tender documents. It shall also include the latest editions, including all
addenda/corrigenda or relevant Indian Standard Specifications and Bureau Of Indian
Standards.
2.15 The "Sub-Contractor" means any person or firm or Company (other than the Contractor)
to whom any part of the work has been entrusted by the Contractor with the prior written
consent of the Owner/Engineer-in-Charge/Site-in- Charge and their legal heirs,
representatives, successors and permitted assignees of such person, firm or Company.
2.16 The "Temporary Work" means and includes all such works which are a part of the
contract for execution of the permanent work but does not form part of the permanent work
confirming to practices, procedures applicable rules and regulations relevant in that behalf.
2.17 The "Tender" means the document submitted by a person or authority for carrying out
the work and the Tenderer means a person or authority who submits the tender offering to
carry out the work as per the terms and conditions.
2.18 The "Work" shall mean the works to be executed in accordance with the Contract or part
thereof as the case may be and shall include extra, additional, altered or substituted works as
maybe required for the purposes of completion of the work contemplated under the Contract.
3. SUBMISSION OF TENDER
3.1 Before submitting the Tender, the Tenderer shall at their own cost and expenses visit the
site, examine and satisfy as to the nature of the existing roads, means of communications, the
character of the soil, state of land and of the excavations, the correct dimensions of the work
facilities for procuring various construction and other material and their availability, and shall
obtain information on all matters and conditions as they may feel necessary for the execution
of the works as intended by the Owners and shall also satisfy of the availability of suitable
water for construction of civil works and for drinking purpose and power required for
fabrication work etc. Tenderer, whose tender may be accepted and with whom the Contract is
entered into shall not be eligible and be able to make any claim on any of the said counts in
what so ever manner for what so ever reasons at any point of time and such a claim shall not
be raised as a dispute and shall not be arbitrable.
A pre-bid meeting may be held as per the schedule mentioned in the tender.
3.2 The Tenderer shall be deemed to have satisfied fully before tendering as to the
correctness and sufficiency of his tender for the works and of the rates and prices quoted in
the schedule of quantities which rates and prices shall except as otherwise provided cover all
his obligations under the contract.
- 177 of 237 -
3.3 It must be clearly understood that the whole of the conditions and specifications are
intended to be strictly enforced and that no work will be considered as extra work and
allowed and paid for unless they are clearly outside the scope, spirit, meaning of the Contract
and intent of the Owner and have been so ordered in writing by Owner and/or Engineer-inCharge/Site-in-Charge, whose decision shall be final and binding.
3.4 Before filling the Tender the Contractor will check and satisfy all drawings and materials
to be procured and the schedule of quantities by obtaining clarification from the Owner on all
the items as may be desired by the Tenderer. No claim for any alleged loss or compensation
will be entertained on this account, after submission of Tender by the Tenderer/Contractor
and such a claim shall not be arbitrable.
3.5 Unless specifically provided for in the tender documents or any Special Conditions,
no escalation in the Tender rates or prices quoted will be permitted throughout the
period of contract or the period of actual completion of the job whichever is later on
account of any variation in prices of materials or cost of labour or due to any other
reasons. Claims on account of escalation shall not be arbitrable.
3.6 The quantities indicated in the Tender are approximate. The approved schedule of rates of
the contract will be applicable for variations upto plus or minus 25% of the contract value.
No revision of schedule of rates will be permitted for such variations in the contract value,
including variations of individual quantities, addition of new items, alterations,
additions/deletions or substitutions of items, as mentioned above.
Quantities etc. mentioned and accepted in the joint measurement sheets shall alone
be final and binding on the parties.
3.7 Owner reserve their right to award the contract to any tenderer and their decision in this
regard shall be final. They also reserve their right to reject any or all tenders received. No
disputes could be raised by any tenderer(s) whose tender has been rejected.
3.8 The Rates quoted by the Tenderer shall include Costs and expenses on all counts viz. cost
of materials, transportation of machine(s), tools, equipments, labour, power, Administration
charges, price escalations, profits, etc. etc. except to the extent of the cost of material(s), if
any, agreed to be supplied by Owner and mentioned specifically in that regard in condition of
Contract, in which case, the cost of such material if taken for preparation of the Contractor's
Bill(s) shall be deducted before making payment of the Bill(s) of the Contractor. The
description given in the schedule of quantities shall unless otherwise stated be held to include
wastage on materials, carriage and cartage, carrying in and return of empties, hoisting,
setting, fitting and fixing in position and all other expenses necessary in and for the full and
complete execution and completion of works and in accordance with good practice and
recognised principles in that regard.
3.9 Employees of the State and Central Govt. and employees of the Public Sector
Undertakings, including retired employees are covered under their respective service
conditions /rules in regard to their submitting the tender. All such persons should ensure
compliance to the respective/applicable conditions, rules etc. etc. Any person not complying
- 178 of 237 -
with those rules etc. but submitting the tender in violation of such rules, after being so noticed
shall be liable for the forfeiture of the Earnest
Money Deposit made with the tender, termination of Contract and sufferance on account of
forfeiture of Security Deposit and sufferance of damages arising as a result of termination of
Contract.
3.10 In consideration for having a chance to be considered for entering into a contract
with the Owner, the Tenderer agrees that the Tender submitted by him shall remain
valid for the period prescribed in the tender conditions, from the date of opening of the
tender. The Tenderer shall not be entitled during the said validity period, to revoke or
cancel the tender without the consent in writing from the Owner.
In case the tenderer revokes or cancels the tender or varies any of terms of the tender without
the Consent of the Owner, in writing, the Tenderer forfeits the right to the refund of the
Earnest Money paid along with the tender.
3.11 The prices quoted by the Tenderer shall be firm during the validity period of the
bid and Tenderer agrees to keep the bid alive and valid during the said period. The
Tenderers shall particularly take note of this factor before submitting their
tender (s).
3.12 The works shall be carried out strictly as per approved specifications. Deviations, if any,
shall have to be authorised by the Engineer-in-Charge/Site-in-Charge in writing prior to
implementing deviations. The price benefit, if any, arising out of the accepted deviation shall
be passed on to the Owner. The decision of Engineer-in-Charge shall be final in this matter.
3.13 The contractor shall make all arrangements at his own cost to transport the required
materials outside and inside the working places and leaving the premises in a neat and tidy
condition after completion of the job to the satisfaction of Owner. All materials except those
agreed to be supplied by the Owner shall be supplied by the contractor at his own cost and the
rates quoted by the Contractor should be inclusive of all royalties, rents, taxes, duties, octroi,
statutory levies, if any, etc. etc.
3.14 The Contractor shall not carry on any work other than the work under this Contract
within the Owners premises without prior permission in writing from the
Engineer-in-Charge/ Site-in-charge.
3.15 The Contractor shall be bound to follow and ensure compliance to all the safety and
security regulations and other statutory rules applicable to the area. In the event of any
damage or loss or sufference caused due to non-observance of such rules and
regulations, the contractor shall be solely responsible for the same and shall keep the
Owner indemnified against all such losses and claims arising from the same.
3.16 At any time after acceptance of tender, the Owner reserves the right to add, amend or
delete any work item, the bill of quantities at a later date or reduce the scope of work in the
overall interest of the work by prior discussion and intimation to the Contractor. The decision
of Owner, with reasons recorded therefor, shall be final and binding on both the Owner and
the Contractor. The Contractor shall not have right to claim compensation or damage etc. in
- 179 of 237 -
that regard. The Owner reserves the right to split the work under this contract between two or
more contractors without assigning any reasons.
3.17 Contractor shall not be entitled to sublet, sub contract or assign, the work under this
Contract without the prior consent of the Owner obtained in writing.
3.18 All signatures in tender document shall be dated as well as all the pages of all sections of
the tender documents shall be initialled at the lower position and signed,
wherever required in the tender papers by the Tenderer or by a person holding Power of
Attorney authorising him to sign on behalf of the tenderer before submission of tender.
3.19 The tender should be quoted in English, both in figures as well as in words. The rates
and amounts tendered by the Tenderer in the Schedule of rates for each item and in such a
way that insertion is not possible. The total tendered amount should also be indicated both in
figures and words with the signature of tenderer.
If some discrepancies are found between the rates given in words and figures of the
amount shown in the tender, the following procedure shall be applied :
(a) When there is a difference between the rates in figures and words, the rate which
corresponds to the amount worked out by the tenderer shall be taken as correct.
(b) When the rate quoted by the tenderer in figures and words tallies but the amount is
incorrect, the rate quoted by the tenderer shall be taken as correct.
(c) When it is not possible to ascertain the correct rate in the manner prescribed above
the rate as quoted in words shall be adopted.
3.20 All corrections and alterations in the entries of tender paper will be signed in full by the
tenderer with date. No erasures or over writings are permissible.
3.21 Transfer of tender document by one intending tenderer to the another one is not
permissible. The tenderer on whose name the tender has been sent only can quote.
3.22 The Tender submitted by a tenderer if found to be incomplete in any or all manner is
liable to be rejected. The decision of the Owner in this regard is final and binding. In case of
any error/discrepancy in the amount written in words and figures, the lower amount between
the two shall prevail.
4. DEPOSITS
a) EARNEST MONEY DEPOSIT (EMD)
The tenderer will be required to pay a sum as specified in the covering letter, as earnest
money deposit alongwith the tender either thru a crossed demand draft or a non-revokable
Bank Guarantee in favour of Hindustan Petroleum Corporation Limited, from any Scheduled
Bank (other than a Co-Operative Bank) payable at Mumbai in favour of Hindustan Petroleum
Corporation Limited, Mumbai in the proforma enclosed. The earnest money deposit will be
refunded after finalisation of the contract.
Note: Public sector enterprises and small scale units registered with National
Small Scale Industries are exempted from payment of Earnest Money Deposit. Small scale
units registered with National Small Scale Industries should enclose a photocopy of their
registration certificate with their quotation to make their quotation eligible for consideration.
The Registration Certificate should remain valid during the period of the contract that may be
- 180 of 237 -
entered into with such successful bidder. Such tenderers should ensure validity of the
Registration Certificate for the purpose.
b) SECURITY DEPOSIT:
The tenderer, with whom the contract is decided to be entered into and intimation is so given
will have to make a security deposit of one percent (1%) of the total contract value in the
form of account payee crossed demand draft drawn in favour of the Owner, within 15 days
from the date of intimation of acceptance of their tender, failing which the Owner reserves
the right to cancel the Contract and forfeit the EMD.
1% of PO/Contract value as Security deposit will be acceptable in the form of Demand
draft upto Rs. 50,000/- and in the form of Demand draft / Bank guarantee beyond Rs.
50,000/-.
Composite Performance Bank Guarantee (CPBG) for 10% of PO value towards
Performance Bank Guarantee inclusive of Security Deposit shall be accepted (in lieu of
deduction of retention money); such CPBG shall be valid upto a period of 3 months
beyond the expiry of defect liability period. Demand Draft should be drawn on
Scheduled Banks, other than co-operative bank.
5. EXECUTION OF WORK
All the works shall be executed in strict conformity with the provisions of the contract
documents and with such explanatory details, drawings, specifications and instructions as
may be furnished from time to time to the Contractor by the Engineer-in-Charge/ Site-inCharge, whether mentioned in the Contract or not. The Contractor shall be responsible for
ensuring that works throughout are executed in the most proper and workman- like manner
with the quality of material and workmanship in strict accordance with the specifications and
to the entire satisfaction of the Engineer-in- Charge/Site-in-Charge.
The completion of work may entail working in monsoon also. The contractor must maintain
the necessary work force as may be required during monsoon and plan to execute the job in
such a way the entire project is completed within the contracted time schedule. No extra
charges shall be payable for such work during monsoon. It shall be the responsibility of the
contractor to keep the construction work site free from water during and off the monsoon
period at his own cost and expenses.
For working on Sundays/Holidays, the contractor shall obtain the necessary permission from
Engineer Incharge/Site Incharge in advance. The contractor shall be permitted to work
beyond the normal hours with prior approval of Engineer-In-Charge/Site-In-Charge and the
contractors quoted rate is inclusive of all such extended hours of working and no extra
amount shall be payable by the owner on this account.
5.a. SETTING OUT OF WORKS AND SITE INSTRUCTIONS
5.a.1. The Engineer-in-Charge/Site-in-Charge shall furnish the Contractor with only the four
corners of the work site and a level bench mark and the Contractor shall set out the works and
shall provide an efficient staff for the purpose and shall be solely responsible for the accuracy
of such setting out.
5.a.2. The Contractor shall provide, fix and be responsible for the maintenance of all
- 181 of 237 -
necessary stakes, templates, level marks, profiles and other similar things and shall take all
necessary precautions to prevent their removal or disturbance and shall be responsible for
consequences of such removal or disturbance should the same take place and for their
efficient and timely reinstatement. The Contractor shall also be responsible for the
maintenance of all existing survey marks, either existing or supplied and fixed by the
Contractor. The work shall be set out to the satisfaction of the Engineer-in-Charge/Site-inCharge. The approval thereof or joining in setting out the work shall not relieve the
Contractor of his responsibility.
5.a.3. Before beginning the works, the Contractor shall, at his own cost, provide all necessary
reference and level posts, pegs, bamboos, flags ranging rods, strings and other materials for
proper layout of the work in accordance with the scheme, for bearing marks acceptable to the
Engineer-in-Charge/Site-in-Charge. The Centre longitudinal or face lines and cross lines shall
be marked by means of small masonary pillars. Each pillar shall have distinct marks at the
centre to enable theodolite to be set over it. No work shall be started until all these points are
checked and approved by the Engineer-in-Charge/Site-in-Charge in writing. But such
approval shall not relieve the contractor of any of his responsibilities. The Contractor shall
also provide all labour, materials and other facilities, as necessary, for the proper checking of
layout and inspection of the points during construction.
5.a.4. Pillars bearing geodetic marks located at the sites of units of works under construction
should be protected and fenced by the Contractor.
5.a.5. On completion of works, the contractor shall submit the geodetic documents according
to which the work was carried out.
5.a.6. The Engineer-in-Charge/Site-in-Charge shall communicate or confirm his instructions
to the contractor in respect of the executions of work in a "work site order book" maintained
in the office having duplicate sheet and the authorised representative of the contractor shall
confirm receipt of such instructions by signing the relevant entries in the book.
5.a.7. All instructions issued by the Engineer-in-Charge/Site-in-Charge shall be in writing.
The Contractor shall be liable to carry out the instructions without fail.
5.a.8. If the Contractor after receipt of written instruction from the Engineer-in-Charge/
Site-in-Charge requiring compliance within seven days fails to comply with such drawings or
'instructions' or both as the Engineer-in-Charge/Site-in-Charge may issue, owner may employ
and pay other persons to execute any such work whatsoever that may be necessary to give
effect to such drawings or `instructions' and all cost and expenses incurred in connection
therewith as certified by the Engineer-in-Charge/
Site-in-Charge shall be borne by the contractor or may be deducted from amounts due or that
may become due to the contractor under the contract or may be recovered as a debt.
5.a.9. The Contractor shall be entirely and exclusively responsible for the horizontal and
vertical alignment, the levels and correctness of every part of the work and shall rectify
effectually any errors or imperfections therein. Such rectifications shall be carried out by the
Contractor, at his own cost.
- 182 of 237 -
5.a.10. In case any doubts arise in the mind of the Contractor in regard to any expressions,
interpretations, statements, calculations of quantities, supply of material rates, etc. etc., the
contractor shall refer the same to the Site-in-Charge/ Engineer-in-Charge for his clarification,
instructions, guidance or clearing of doubts. The decision of the Engineer-in-Charge/Site-inCharge shall be final and the contractor shall be bound by such a decision.
5.a.11. "The Contractor shall take adequate precautions, to ensure that his operations do not
create nuisance or misuse of the work space that shall cause unnecessary disturbance or
inconvenience to others at the work site".
5.a.12. "All fossils, coins articles of value of antiquity and structure or other remains of
geological or archaeological discovered on the site of works shall be declared to be the
property of the Owner and Contractor shall take reasonable precautions to prevent his
workmen or any other persons from removing or damaging any such articles or thing and
shall immediately inform the Owner/ Engineer-in-Charge/Site-in-Charge."
5.a.13. "Contractor will be entirely and exclusively responsible to provide and maintain at his
expenses all lights, guards, fencing, etc. when and where even necessary or/as required by the
Engineer-in-Charge/Site-in-Charge for the protection of works or safety and convenience to
all the members employed at the site or general public."
5.b. COMMENCEMENT OF WORK
The contractor shall after paying the requisite security deposit, commence work within 15
days from the date of receipt of the intimation of intent from the Owner informing that the
contract is being awarded. The date of intimation shall be the date/day for counting the
starting day/date and the ending day/date will be accordingly calculated. Penalty, if any, for
the delay in execution shall be calculated accordingly. Contractor should prepare detailed
fortnightly construction programme for approval by the Engineer-in-Charge within one
month of receipt of Letter Of Intent. The work shall be executed strictly as per such time
schedule. The period of Contract includes the time required for testing, rectifications, if any,
re-testing and completion of work in all respects to the entire satisfaction of the Engineer-inCharge.
A Letter of Intent is an acceptance of offer by the Owner and it need not be accepted by the
contractor. But the contractor should acknowledge a receipt of the purchase order within 15
days of mailing of Purchase Order and any delay in acknowledging the receipt will be a
breach of contract and compensation for the loss caused by such breach will be recovered by
the Owner by forfeiting earnest money deposit/bid bond.
5.c. SUBLETTING OF WORK
5.c.1. No part of the contract nor any share or interest thereof shall in any manner or
degree be transferred, assigned or sublet, by the Contractor, directly or indirectly to any firm
or corporation whatsoever, without the prior consent in writing of the Owner.
5.c.2. At the commencement of every month the Contractor shall furnish to the
Engineer-in-charge/Site-in-Charge list of all sub-contractors or other persons or firms
engaged by the Contractor.
5.c.3 The contract agreement will specify major items of supply or services for which the
- 183 of 237 -
- 184 of 237 -
with the work therein ordered to uspended until he shall have received a written order to restart. The Contractor shall be entitled to claim extension of time for that period of time the
work was ordered to be suspended. Neither the Owner nor the Contractor shall be entitled to
claim compensation or damages on account of such an extension of time.
5.e.2. In case of suspension of entire work, ordered in writing by
Engineer-in-Charge/Site-in-Charge, for a period of 30 days, the Owner shall have the option
to terminate the Contract as provided under the clause for termination.
The Contractor shall not be at liberty to remove from the site of the works any plant or
materials belonging to him and the Employer shall have lien upon all such plant and
materials.
5.e.3. The contract shall, in case of suspension have the right to raise a dispute and have the
same arbitrated but however, shall not have the right to have the work stopped from further
progress and completion either by the owner or through other contractor appointed by the
owner.
5.f. OWNER MAY DO PART OF WORK
Not withstanding anything contained elsewhere in this contract, the owner upon failure of the
Contractor to comply with any instructions given in accordance with the provisions of this
contract, may instead of Contract and undertaking charge of entire work, place additional
labour force, tools, equipment and materials on such parts of the work, as the Owner may
decide or engage another Contractor to carryout the balance of work. In such cases, the
Owner shall have the right to deduct from the amounts payable to the Contractor the
difference in cost of such work and materials with ten percent overhead added to cover all
departmental charges. Should the total amount thereof exceed the amount due to the
contractor, the Contractor shall pay the difference to the Owner within 15 days of making
demand for payment failing which the Contractor shall be liable to pay interest at 24% p.a. on
such amounts till the date of payment.
5.g. INSPECTION OF WORKS
5.g.1. The Engineer-in-Charge/Site-in-Charge and Officers from Central or State
Government will have full power and authority to inspect the works at any time wherever in
progress, either on the site or at the Contractor's premises/workshops of any person, firm or
corporation where work in connection with the contract may be in hand or where the
materials are being or are to be supplied, and the Contractor shall afford or procure for the
Engineer-in-Charge/Site-in-Charge every facility and assistance to carryout such inspection.
The Contractor shall, at all times during the usual working hours and at all other times at
which reasonable notice of the intention of the Engineer-in-Charge/Site-in-Charge or his
representative to visit the works shall have been given to the Contractor, either himself be
present to receive orders and instructions, or have a responsible agent, duly accredited in
writing, present for the purpose. Orders given to the Contractor's agent shall be considered to
have the same force as if they had been given to the Contractor himself. The Contractor shall
give not less than seven days notice in writing to the Engineer-in-Charge/Site-in-Charge
before covering up or otherwise placing beyond reach of inspection and measurement any
- 185 of 237 -
work in order that the same may be inspected and measured. In the event of breach of above,
the same shall be uncovered at Contractor's expense for carrying out such measurement
and/or
inspection.
5.g.2. No material shall be removed and despatched by the Contractor from the site without
the prior approval in writing of the Engineer-in-charge. The contractor is to provide at all
times during the progress of the work and the maintenance period proper means of access
with ladders, gangways, etc. and the necessary attendance to move and adapt as directed for
inspection or measurements of the works by the Engineer-in-Charge/Site-in-Charge.
5.h. SAMPLES
5.h.1. The contractor shall furnish to the Engineer-in-charge/Site-in-Charge for approval
when requested or required adequate samples of all materials and finishes to be used in the
work.
5.h.2. Samples shall be furnished by the Contractor sufficiently in advance and before
commencement of the work so as the Owner can carry out tests and examinations thereof and
approve or reject the samples for use in the works. All material samples furnished and finally
used/applied in actual work shall fully be of the same quality of the approved samples.
5.i. TESTS FOR QUALITY OF WORK
5.i.1. All workmanship shall be of the respective kinds described in the contract documents
and in accordance with the instructions of the Engineer-in-Charge /
Site-in- Charge and shall be subjected from time to time to such tests at Contractor's cost as
the Engineer-in-Charge/Site-in-Charge may direct at the place of manufacture or fabrication
or on the site or at all or any such places. The Contractor shall provide assistance,
instruments, labour and materials as are normally required for examining, measuring and
testing any workmanship as may be selected and required by the Engineer-in-Charge/Site-inCharge.
5.i.2. All the tests that will be necessary in connection with the execution of the work as
decided by the Engineer-in- charge/Site-in-Charge shall be carried out at the contractors cost
and expenses.
5.i.3. If any tests are required to be carried out in connection with the work or materials or
workmanship to be supplied by the owner, such tests shall be carried out by the Contractor as
per instructions of Engineer-in-Charge/Site-in-Charge and expenses for such tests, if any,
incurred by the contractor shall be reimbursed by the Owner. The contractor should file his
claim with the owner within 15 (fifteen) days of inspection/test and any claim made beyond
that period shall lapse and be not payable.
5.j. ALTERATIONS AND ADDITIONS TO SPECIFICATIONS, DESIGNS
AND WORKS
5.j.1. The Engineer-in-Charge/Site-in-Charge shall have powers to make any alterations,
additions and/or substitutions to the schedule of quantities, the original specifications,
drawings, designs and instructions that may become necessary or advisable or during the
progress of the work and the Contractor shall be bound to carryout such altered/extra/new
- 186 of 237 -
items of work in accordance with instructions which may be given to him in writing signed
by the Engineer-in-Charge/Site- in-Charge. Such alterations, omissions, additions or
substitutions shall not invalidate the contract. The altered, additional or substituted work
which the Contractor may be directed to carryon in the
manner as part of the work shall be carried out by the Contractor on the same conditions in all
respects on which he has agreed to do the work. The time for completion of such altered
added and/or substituted work may be extended for that part of the particular job. The rates
for such additional altered or substituted work under this Clause shall, be worked out in
accordance with the following provisions:
5.j.2. If the rates for the additional, altered or substituted work are specified in the contract for
similar class of work, the Contractor is bound to carryout the additional,
altered or substituted work at the same rates as are specified in the contract.
5.j.3. If the rates for the additional, altered or substituted work are not specifically provided in
the contract for the work, the rates will be derived from the rates for similar class of work as
are specified in the contract for the work. In the opinion of the Engineer-in- Charge/Site-inCharge as to whether or not the rates can be reasonably so derived from the items in this
contract, will be final and binding on the Contractor.
5.j.4. If the rates for the altered, additional or substituted work cannot be determined in the
manner specified above, then the Contractor shall, within seven days of the date of
receipt of order to carry out the work, inform the Engineer-in-Charge/ Site-in-Charge of the
rate at which he intends to charge for such class of work, supported by analysis of the rate or
rates claimed and the Engineer-In-Charge/ Site-in-Charge shall determine the rates on the
basis of the prevailing market rates for both material and labour plus 10% to cover overhead
and profit of labour rates and pay the Contractor accordingly. The opinion of the Engineer-inCharge/Site-in-Charge as to current market rates of materials and the quantum of labour
involved per unit of measurement will be final and binding on the contractor.
5.j.5. The quantities indicated in the Tender are approximate. The approved schedule of
rates of the contract will be applicable for variations of upto +25% of the estimated contract
value. No revision of schedule of rates will be permitted for such variations in the contract
value, even for variations of individual quantities, addition of new items, alterations,
additions/deletions or substitutions of items, as mentioned above.
- 187 of 237 -
the Engineer from requiring replacement of defective work that may become apparent after
the said acceptance and also shall not absolve the Contractor of the obligations under this
contract. It is made clear that such an acceptance does not indicate or denote or establish to
the fact of execution of that work or the Contract until the work is completed in full in
accordance with the provisions of this Contract.
5.l. COMPLETION OF WORK AND COMPLETION CERTIFICATE
As soon as the work is completed in all respects, the contractor shall give notice of such
completion to the site in charge or the Owner and within thirty days of receipt of such notice
the site in charge shall inspect the work and shall furnish the contractor with a certificate of
completion indicating:
a) defects, if any, to be rectified by the contractor
b) items, if any, for which payment shall be made in reduced rates
c) the date of completion.
5.m. USE OF MATERIALS AND RETURN OF SURPLUS MATERIALS
5.m.1. Notwithstanding anything contained to the contrary in any or all of the clauses of this
contract, where any materials for the execution of the contract are procured with the
assistance of Government either by issue from Government stocks or purchase made under
orders or permits or licences issued by Government, the contractor shall use the said
materials economically and solely for the purpose of the contract and shall not dispose them
of without the permission of the Owner.
5.m.2. All surplus(serviceable) or unserviceable materials that may be left over after the
completion of the contract or at its termination for any reason whatsoever, the
Contractor shall deliver the said product to the Owner without any demur. The price to be
paid to the Contractor, if not already paid either in full or in part, however, shall not exceed
the amount mentioned in the Schedule of Rates for such material and in cases where such
rates are not so mentioned, shall not exceed the CPWD scheduled rates. In the event of
breach of the aforesaid condition the contractor shall become liable for contravention of the
terms of the Contract.
5.m.3. The surplus (serviceable) and unserviceable products shall be determined by joint
measurement. In case where joint measurement has failed to take place, the Owner may
measure the same and determine the quantity.
5.m.4. It is made clear that the Owner shall not be liable to take stock and keep possession
and pay for the surplus and unserviceable stocks and the Owner may direct the Contractor to
take back such material brought by the Contractor and becoming surplus and which the
Owner may decide to keep and not to pay for the same.
5.n. DEFECT LIABILITY PERIOD
The contractor shall guarantee the work executed for a period of 12 months from the date of
completion of the job. Any damage or defect that may arise or lie undiscovered at the time of
completion of the job shall be rectified or replaced by the contractor at his own cost. The
decision of the Engineer In-charge/Site-Incharge/Owner shall be the final in deciding whether
the defect has to be rectified or replaced. Equipment or spare parts replaced under
- 188 of 237 -
warranty/guarantees shall have further warranty for a mutually agreed period from the date of
acceptance. The owner shall intimate the defects noticed in writing by a Registered A.D.
letter or otherwise and the contractor within 15 days of receipt of the intimation shall start the
rectification work and complete within the time specified by the owner failing which the
owner will get the defects rectified by themselves or by any other contractor and the expenses
incurred in getting the same done shall be paid by the Contractor under the provision of the
Contract. Thus, defect liability is applicable only in case of job/works contract (civil,
mechanical, electrical, maintenance etc. ) where any damage of defect may arise in future (i.e.
within 12 months from the date of completion of job) or lie undiscovered at the time of
completion of job. In other words, in case of service contracts (like car hire etc.) where there
is no
question of damage or defect arising in future, the defect liability clause is not applicable.
5.o. DAMAGE TO PROPERTY
5.o.1. Contractor shall be responsible for making good to the satisfaction of the Owner any
loss of and any damage to all structures and properties belonging to the Owner or being
executed or procured by the Owner or of other agencies within the premises of the
work of the Owner, if such loss or damage is due to fault and/or the negligence or willful acts
or omission of the Contractor, his employees, agents, representatives or sub-contractors.
5.o.2. The Contractors shall indemnify and keep the Owner harmless of all claims for damage
to Owner's property arising under or by reason of this contract.
6. DUTIES AND RESPONSIBILITIES OF CONTRACTOR
6.a. EMPLOYMENT LIABILITY TOWARDS WORKERS EMPLOYED BY THE
CONTRACTOR
6.a.1 The Contractor shall be solely and exclusively responsible for engaging or employing
persons for the execution of work. All persons engaged by the contractor shall be on
Contractor's payroll and paid by Contractor. All disputes or differences between the
Contractor and his/their employees shall be settled by Contractor.
6.a.2. Owner has absolutely no liability whatsoever concerning the employees of the
Contractor. The Contractor shall indemnify Owner against any loss or damage or liability
arising out of or in the course of his/their employing persons or relation with his/their
employees. The Contractor shall make regular and full payment of wages and on any
complaint by any employee of the Contractor or his sub contractor regarding non-payment of
wages, salaries or other dues, Owner reserves the right to make payments directly to such
employees or sub- contractor of the Contractor and recover the amount in full from the bills
of the Contractor and the contractor shall not claim any compensation or reimbursement
thereof. The Contractor shall comply with the Minimum Wages Act applicable to the area of
work site with regard to payment of wages to his employees and also to employees of his sub
contractor.
6.a.3. The Contractor shall advise in writing or in such appropriate way to all of his
employees and employees of sub-contractors and any other person engaged by him that their
appointment/employment is not by the Owner but by the Contractor and that their present
- 189 of 237 -
appointment is only in connection with the construction contract with Owner and that
therefore, such an employment/appointment would not enable or make them eligible for any
employment/appointment with the Owner either temporarily or/and permanent basis.
6.b. NOTICE TO LOCAL BODIES
The contractor shall comply with and give all notices required under any Government
authority, instruction, rule or order made under any act of parliament, state laws or any
regulations or by-laws of any local authority relating to the works.
6.c. FIRST AID AND INDUSTRIAL INJURIES
6.c.1 Contractor shall maintain first aid facility for his employees and those of his subcontractors.
6.c.2. Contractor shall make arrangements for ambulance service and for the treatment of all
types of injuries. Names and telephone numbers of those providing such services shall be
furnished to Owner prior to start of construction and their name board shall be prominently
displayed in Contractor's field office.
6.c.3. All industrial injuries shall be reported promptly to owner and a copy of contractor's
report covering each personal injury requiring the attention of a physician shall be furnished
to the Owner.
6.d. SAFETY CODE
6.d.1. The Contractor shall at his own expenses arrange for the Safety provisions as may
be necessary for the execution of the work or as required by the Engineer-in-Charge in
respect of all labours directly or indirectly employed for performance of the works and shall
provide all facilities in connections therewith. In case the contractor fails to make
arrangements and provide necessary facilities as aforesaid, the Owner shall be entitled to do
so and recover the cost thereof from the Contractor.
6.d.2. From the commencement to the completion of the works, the contractor shall take full
responsibility for the care thereof and of all the temporary works (defined as meaning all
temporary works of every kind required in or for the execution, completion or maintenance of
the works). In case damage, loss or injury shall happen to the works or to any part thereof or
to temporary works or to any cause whatsoever repair at his (Contractor's) own cost and make
good the same so that at the time of completion, the works shall be in good order and
condition and in conformity in every respect with the requirement of the contract and
Engineer-in-Charge's instructions.
6.d.3. In respect of all labour, directly or indirectly employed in the work for the performance
of the Contractor's part of this agreement, the contractor shall at his own expense arrange for
all the safety provisions as per relevant Safety Codes of C.P.W.D Bureau of Indian Standards,
the Electricity Act/I.E. Rules. The Mines Act and such other Acts as applicable.
6.d.4. The Contractor shall observe and abide by all fire and safety regulations of the
Owner. Before starting construction work, the Contractor shall consult with Owner's Safety
Engineer or Engineer-in-Charge/Site-in-Charge and must make good to the satisfaction of the
Owner any loss or damage due to fire to any portion of the work done or to be done under
this agreement or to any of the Owner's existing property.
- 190 of 237 -
6.d.5. The Contractor will be fully responsible for complying with all relevant provisions of
the Contract Labour Act and shall pay rates of Wages and observe hours of
work/ conditions of employment according to the rules in force from time to time.
6.d.6. The Contractor will be fully responsible for complying with the provision including
documentation and submission of reports on the above to the concerned
authorities and shall indemnify the Corporation from any such lapse for which the
Government will be taking action against them.
6.d.7. Owner shall on a report having been made by an inspecting Office as defined in the
Contract Labour Regulations have the power to deduct from the money due to the Contractor
any sum required or estimated to be required for making good the loss suffered by a
worker(s) by reasons of non-fulfillment of conditions of contract for the benefit of workers
no-payment of wages or of deductions made from his or their wages which are not justified
by the terms of contract or non observance of the said contractor's labour Regulation.
6.e. INSURANCE AND LABOUR
Contractor shall at his own expense obtain and maintain an insurance policy with a
Nationalised Insurance Company to the satisfaction of the Owner as provided hereunder.
6.e.1. EMPLOYEES STATE INSURANCE ACT
i. The Contractor agrees to and does hereby accept full and exclusive liability for the
compliance with all obligations imposed by Employees State Insurance Act, 1948, and the
Contractor further agrees to defend indemnify and hold Owner harmless from any liability or
penalty which may be imposed by the Central, State or local authority by reason of any
asserted violation by Contractor, or sub-contractor of the Employees' State Insurance Act,
1948 and also from all claims, suits or proceedings that may be brought against the Owner
arising under, growing out of or by reason of the work provided for by this contract whether
brought by employees of the Contractor, by third parties or by Central or State Government
authority or any political sub-division thereof.
ii. The Contractor agrees to file with the Employees State Insurance Corporation, the
Declaration forms and all forms which may be required in respect of the Contractor's or subcontractor's employee whose aggregate emuneration is within the specified limit and who are
employed in the work provided or those covered by ESI Act under any amendment to the Act
from time to time. The Contractor shall deduct and secure the agreement of the subcontractor to deduct the employee's contribution as per the first schedule of the Employee's
State Insurance Act from wages and affix the employee's contribution cards at wages
payment intervals. The Contractor shall remit and secure the agreement of the sub contractor
to remit to the State Bank of India, Employee's State
Insurance Corporation Account, the Employee's contribution as required by the Act.
iii. The Contractor agrees to maintain all records as required under the Act in respect of
employees and payments and the Contractor shall secure the agreement of the sub contractor
to maintain such records. Any expenses incurred for the contributions, making contribution or
maintaining records shall be to the Contractor's or sub-contractor's account.
- 191 of 237 -
iv. The Owner shall retain such sum as may be necessary from the total contract value until
the Contractor shall furnish satisfactory proof that all contributions as required by the
Employees State Insurance Act, 1948, have been paid.
v. WORKMAN'S COMPENSATION AND EMPLOYEE'S LIABILITY
INSURANCE
Provide Insurance for all the Contractor's employees engaged in the performance of this
contract. If any of the work is sublet, the Contractor shall ensure that the sub contractor
provides workmen's compensation and Employer's Liability Insurance for the latter's
employees who are not covered under the Contractor's insurance.
vi. AUTOMOBILE LIABILITY INSURANCE
Contractor shall take out an Insurance to cover all risks to Owner for each of his vehicles
plying on works of this contract and these insurances shall be valid for the total contract
period. No extra payment will be made for this insurance. Owner shall not be liable for any
damage or loss not made good by the Insurance Company, should such damage or loss result
from unauthorised use of the vehicle. The provisions of the Motor Vehicle Act would apply.
vii. FIRE INSURANCE
Contractor shall within two weeks after award of contract insure the Works, Plant and
Equipment and keep them insured until the final completion of the Contract against loss or
damage by accident, fire or any other cause with an insurance company to be approved by the
Employer/Consultant in the joint names of the Employer and the Contractor (name of the
former being placed first in the Policy). Such Policy shall cover the property of the Employer
only.
6.e.2. ANY OTHER INSURANCE REQUIRED UNDER LAW OR REGULATION OR
BY OWNER
i. Contractor shall also provide and maintain any and all other insurance which may be
required under any law or regulations from time to time. He shall also carry and maintain any
other insurance which may be required by the Owner.
ii. The aforesaid insurance policy/policies shall provide that they shall not be cancelled till
the Engineer-in-Charge has agreed to their cancellation.
iii. The Contractor shall satisfy to the Engineer-in-Charge/Site-in-Charge from time to time
that he has taken out all insurance policies referred to above and has paid the necessary
premium for keeping the policies alive till the expiry of the defects liability period.
iv. The contractor shall ensure that similar insurance policies are taken out by his subcontractor (if any) and shall be responsible for any claims or losses to the Owner resulting
from their failure to obtain adequate insurance protections in connection thereof. The
contractor shall produce or cause to be proceed by his sub-contractor (if any) as the case may
be, the relevant policy or policies and premium receipts as and when required by the
Engineer-in-Charge/Site-in-Charge.
6.e.3. LABOUR AND LABOUR LAWS
- 192 of 237 -
i. The contractor shall at his own cost employ persons during the period of contract and the
persons so appointed shall not be construed under any circumstances to be in the employment
of the Owner.
ii. All payments shall be made by the contractor to the labour employed by him in accordance
with the various rules and regulations stated above. The contractor shall keep the Owner
indemnified from any claims whatsoever inclusive of damages/costs or otherwise arising
from injuries or alleged injuries to or death of a person employed by the contractor or
damages or alleged damages to the property.
iii. No labour below the age of eighteen years shall be employed on the work. The Contractor
shall not pay less than what is provided under the provisions of the contract labour
(Regulations and Abolition) Act, 1970 and the rules made thereunder and as may be amended
from time to time. He shall pay the required deposit under the Act appropriate to the number
of workman to be employed by him or through sub contractor and get himself registered
under the Act. He shall produce the required Certificates to the Owner before commencement
of the work. The Owner recognises only the Contractor and not his sub contractor under the
provisions of the Act. The Contractor will have to submit daily a list of his workforce. He
will also keep the wage register at the work site or/and produce the same to the Owner,
whenever desired. A deposit may be taken by the Owner from the Contractor to be refunded
only after the Owner is satisfied that all workmen employed by the Contractor have been
fully paid for the period of work in Owner's premises at rates equal to or better than wages
provided for under the Minimum Wages Act. The contractor shall be responsible and liable
for any complaints that may arise in this regard and the consequences thereto.
iv. The Contractor will comply with the provisions of the Employee's Provident Fund Act and
the Family Pension Act as may be applicable and as amended from time to time.
v. The Contractor will comply with the provisions of the payment of Gratuity Act, 1972, as
may be applicable and as amended from time to time.
vi. IMPLEMENTATION OF APPRENTICES ACT, 1961
The Contractor shall comply with the provisions of the Apprentices Act, 1961 and the Rules
and Orders issued thereunder from time to time. If he fails to do so, his failure will be a
breach of the contract and the Engineer-in-Charge may, at his discretion, cancel the contract.
The Contractor shall also be liable for any pecuniary liability arising on account of any
violation by him of the provision of the Act.
vii. MODEL RULES FOR LABOUR WELFARE
The Contractor shall at his own expenses comply with or cause be complied with Model rules
for Labour Welfare as appended to those conditions or rules framed by the Government from
time to time for the protection of health and for making sanitary arrangements for worker
employed directly or indirectly on the works. In case the contractor fails to make
arrangements as aforesaid the Engineer-in-Charge/Site-in-Charge shall be entitled to do so
and recover the cost thereof from the contractor.
6.f. DOCUMENTS CONCERNING WORKS
- 193 of 237 -
6.f.1. All documents including drawings, blue prints, tracings, reproducible models, plans,
specifications and copies, thereof furnished by the Owner as well as all drawings, tracings,
reproducibles, plans, specifications design calculations etc. prepared by the contractor for the
purpose of execution of works covered in or connected with this contract shall be the
property of the Owner and shall not be used by the contractor for any other work but are to be
delivered to the Owner at the completion or otherwise of the contract.
6.f.2. The Contractor shall keep and maintain secrecy of the documents, drawings etc. issued
to him for the execution of this contract and restrict access to such documents, drawings etc.
and further the Contractor shall execute a SECRECY agreement from each or any person
employed by the Contractor having access to such documents, drawings etc. The Contractor
shall not issue drawings and documents to any other agency or individual without the written
approval by the Engineer-in-Charge/Site-in- Charge.
6.f.3. Contractor will not give any information or document etc. concerning details of the
work to the press or a news disseminating agency without prior written approval from
Engineer-in-charge/Site-in-Charge. Contractor shall not take any pictures on site without
written approval of Engineer-in-Charge/Site-in-Charge.
7. PAYMENT OF CONTRACTOR'S BILLS
7.1. Payments will be made against Running Accounts bills certified by the Owner's
Engineer-in-Charge/Site-in-Charge within 15 days from the date of receipt of the
bill..
7.2. Running Account Bills and the final bill shall be submitted by the Contractor together
with the duly signed measurements sheet(s) to the Engineer-in-Charge/ Site-in-Charge of the
Owner in quadruplicate for certification. The Bills shall also be accompanied by quantity
calculations in support of the quantities contained in the bill along with cement consumption
statement, actual/theoretical, wherever applicable duly certified by the Engineer-in-Charge/
Site-in-Charge of the Owner.
7.3. All running account payments shall be regarded as on account payment(s) to be finally
adjusted against the final bill payment. Payment of Running Account Bill(s) shall not
determine or affect in any way the rights of the Owner under this Contract to make the final
adjustments of the quantities of material, measurements of work and adjustments of amounts
etc.etc. in the final bill.
7.4. The final bill shall be submitted by the Contractor within one month of the date of
completion of the work fully and completely in all respects. If the Contractor fails to submit
the final bill accordingly Engineer-in-Charge/Site-in-Charge may make the
measurement and determine the total amount payable for the work carried out by the
Contractor and such a certification shall be final and binding on the Contractor.
The Owner/Engineer- in-Charge/Site-in-Charge may take the assistance of an outside party
for taking the measurement, the expenses of which shall be payable
by the Contractor.
7.5. Payment of final bill shall be made within 30 days from the date of receipt of the
certified bill by the Disbursement Section of the owner.
- 194 of 237 -
7.6 Wherever possible, payment shall be tendered to the contractor in electronic mode
(e-payment) through any of the designated banks. The contractor will comply by
furnishing full particulars of Bank acount (mandate) to which the payments will
be routed. Owner reserves the right to make payment in any alternate mode also.
7.a. MEASUREMENT OF WORKS
7.a.1. All measurements shall be in metric system. All the works will be jointly measured by
the representative of the Engineer-in-Charge/Site-in-Charge and the Contractor or their
authorised agent progressively. Such measurement will be recorded in the Measurement
Book/Measurement Sheet by the Contractor or his authorized representative and signed in
token of acceptance by the Owner or their authorised representative.
7.a.2. For the purpose of taking joint measurement, the Contractor/representative shall be
bound to be present whenever required by the Engineer-in-Charge/Site-in-Charge. If,
however, they are absent for any reasons whatsoever, the measurement will be taken by the
Engineer-in-Charge/Site-in-Charge or his representative and the same would be deemed to be
correct and binding on the Contractor.
7.a.3. In case of any dispute as to the mode of measurement for any item of work, the latest
Indian Standard Specifications shall be followed. In case of any further dispute on the same
the same shall be as per the certification of an outside qualified Engineer/ Consultant. Such a
measurement shall be final and binding on the Owner and the Contractor.
7.b. BILLING OF WORKS EXECUTED
The Contractor will submit a bill in approved proforma in quadruplicate to the Engineer-inCharge/Site-in-Charge of the work giving abstract and detailed measurement for the various
items executed during a month, before the expiry of the first week of the succeeding month.
The Engineer-in-Charge/Site-in-Charge shall take or cause to be taken the requisite
measurements for the purpose of having the bill verified and/or checked before forwarding
the same to the disbursement office of the Owner for further action in terms of the Contract
and payment thereafter. The Engineer-in-Charge/Site-in-Charge shall verify the bills within 7
days of submission of the Bill by the Contractor.
7.c. RETENTION MONEY
10% of the total value of the Running Account and Final Bill will be deducted and retained
by the Owner as retention money on account of any damage/defect liability that may arise for
the period covered under the defect liability period clause of the Contract free of interest. Any
damage or defect that may arise or lie undiscovered at the time of issue of completion
certificate connected in any way with the equipment or materials supplied by contractor or in
workmanship shall be rectified or replaced by the contractor at his own expense failing which
the Owner shall be entitled to rectify the said damage/defect from the retention money. Any
excess of expenditure incurred by the Owner on account of damage or defect shall be payable
by the Contractor. The decision of the Owner in this behalf shall not be liable to be
questioned but shall be final and binding on the Contractor. Thus, deduction towards
retention money is applicable only in case of job/works contracts (civil, mechanical,
electrical, maintenance etc.) where any damage or defect may arise in future (i.e. within 12
- 195 of 237 -
months from the date of completion of job) or lie undiscovered at the time of issue of
completion certificate.
7.d. STATUTORY LEVIES
7.d.1 The Contractor accepts full and exclusive liability for the payment of any and all taxes,
duties, octroi, rates, cess, levies and statutory payments payable under all or any of the
statutes etc.
Variations of taxes and duties arising out of the amendments to the Central / State
enactments, in respect of sale of goods / services covered under this bid shall be to
HPCLs account, so long as :
They relate to the period after the opening of the price bid, but before the contracted
completion period ( excluding permitted extensions due to delay on account of the
contractors, if any) or the actual completion period, whichever is earlier; and
The vendor furnishes documentary evidence of incurrence of such variations, in addition to
the invoices/documents for claiming Cenvat /Input Tax credit, wherever applicable.
All contributions and taxes for unemployment compensation, insurance and old age
pensions or annuities now or hereafter imposed by Central or State Governmental
authorities which are imposed with respect to or covered by the wages, salaries or other
compensations paid to the persons employed by the Contractor and the Contractor shall be
responsible for the compliance with all obligations and restrictions imposed by the Labour
Law or any other law affecting employer-employee relationship and the Contractor further
agrees to comply and to secure the compliance of all sub-contractors with all applicable
Central, State, Municipal and local laws, and regulations and requirements of any Central,
State or Local Government agency or authority.
Contractor further agrees to defend, indemnify and hold harmless from any liability or
penalty which may be imposed by the Central, State or Local authorities by reason of any
violation by Contractor or sub-contractor of such laws, regulations or requirements and also
from all claims, suits or proceedings that may be brought against the Owner arising under,
growing out of, or by reasons of the work provided for by this contract by third parties, or by
Central or State Government authority or any administrative sub-division thereof. The
Contractor further agrees that in case any such demand is raised against the Owner, and
Owner has no way but to pay and pays/makes payment of the same, the Owner shall have the
right to deduct the same from the amounts due and payable to the Contractor. The Contractor
shall not raise any demand or dispute in respect of the same but may have recourse to
recover/receive from the concerned authorities on the basis of the Certificate of the Owner
issued in that behalf.
7.d.2. The rates quoted should be inclusive of all rates, cess, taxes and sales tax on works
contracts wherever applicable. However, wherever the sales tax on works contract is
applicable and is to be deducted at source, the same will be deducted from the bills of the
Contractor and paid to the concerned authorities. The proof of such payments of sales tax on
works contract will be furnished to the contractor.
- 196 of 237 -
7.d.3. Income tax will be deducted at source as per rules at prevailing rates, unless certificate,
if any, for deduction at lesser rate or nil deduction is submitted by the Contractor from
appropriate authority.
7.d.4 The contractor shall provide accurate particulars of PAN number as required, to
enable issuance of TDS (Tax Deduction at Source) certificate.
7.e. MATERIALS TO BE SUPPLIED BY CONTRACTOR
7.e.1. The Contractor shall procure and provide the whole of the materials required for
construction including tools, tackles, construction plant and equipment for the completion
and maintenance of the works except the materials viz. steel and cement which may be
agreed to be supplied as provided elsewhere in the contract. The contractor shall make
arrangement for procuring such materials and for the transport thereof at their own cost and
expenses.
7.e.2. The Owner may give necessary recommendation to the respective authority if so
desired by the Contractor but assumes no responsibility of any nature. The Contractor shall
procure materials of ISI stamp/certification and supplied by reputed suppliers borne on
DGS&D list.
7.e.3. All materials procured should meet the specifications given in the tender document.
The Engineer-in-charge may, at his discretion, ask for samples and test certificates for any
batch of any materials procured. Before procuring, the Contractor should get the approval of
Engineer-in-Charge/Site-in-Charge for any materials to be used for the works.
7.e.4. Manufacturer's certificate shall be submitted for all materials supplied by the
Contractor. If, however, in the opinion of the Engineer-in-Charge/Site-in-Charge any tests are
required to be conducted on the material supplied by the Contractor, these will be arranged by
the Contractor promptly at his own cost.
7.f. MATERIALS TO BE SUPPLIED BY THE OWNER
7.f.1. Steel and Cement maybe supplied by the Owner to the contractor against payment by
Contractor from either godown or from the site or within work premises itself and
the contractor shall arrange for all transport to actual work site at no extra cost.
7.f.2. The contractor shall bear all the costs including loading and unloading, carting from
issue points to work spot storage, unloading, custody and handling and stacking the same and
return the surplus steel and cement to the Owner's storage point after completion of job.
7.f.3. The contractor will be fully accountable for the steel and cement received from the
Owner and contractor will give acknowledgement/receipt for quantity of steel and cement
received by him each time he uplifts cement from Owner's custody.
7.f.4. For all computation purposes, the theoretical cement consumption shall be considered
as per CPWD standards.
7.f.5. Steel and Cement as received from the manufacturer/stockists will be issued to the
contractor. Theoretical weight of cement in a bag will be considered as 50 Kg. Bags weighing
upto 4% less shall be accepted by the contractor and considered as 50 Kg. per bag. Any
shortage in the weight of any cement bag by more than 4% will be to the Owner's account
- 197 of 237 -
only when pointed out by the Contractor and verified by Engineer-in-Charge/Site in Charge
at the time of Contract or taking delivery.
7.f.6. The contractor will be required to maintain a stock register for receipt, issuance and
consumption of steel and cement at site. Cement will be stored in a warehouse at site.
Requirement of cement on any day will be taken out of the warehouse. Cement issued shall
be regulated on the basis of FIRST RECEIPT to go as FIRST ISSUE.
7.f.7. Empty cement bag shall be the property of the Contractor. Contractor shall be
penalised for any excess/under consumption of cement. The penal rate will be twice the rate
of issue of cement for this work.
7.f.8. All the running bills as well as the final bills will be accompanied by cement
consumption statements giving the detailed working of the cement used, cement received and
stock-on-hand.
7.f.9. The Contractor will be fully responsible for safe custody of cement once it is
received by him and during transport. Owner will not entertain any claims of the contractor
for theft, loss or damage to cement while in their custody.
7.f.10. The contractor shall not remove from the site any cement bags at any time.
7.f.11. The Contractor shall advise Engineer-in-charge/Site-in-charge in writing atleast 21
days before exhausting the Cement stocks already held by Contractor to ensure that
such delays do not lead to interruptions in the progress of work.
7.f.12. Cement shall not be supplied by the Owner for manufacturing of mosaic tiles,
precast cement jali and any other bought out items which consume cement and for
temporary works.
7.f.13. Cement in bags and in good usable condition left over after the completion of work
shall be returned by the contractor to the Owner. The Owner shall make payment to the
Contractor at the supply rate for such stocks of cement they accept and receive.
Any refused stock of cement shall be removed by the Contractor from the site at his cost and
expenses within 15 days of completion of the work.
8. PAYMENT OF CLAIMS AND DAMAGES
8.1. Should the Owner have to pay money in respect of claims or demands as aforesaid the
amount so paid and the costs incurred by the Owner shall be charged to and paid by the
Contractor and the Contractor shall not be entitled to dispute or question the right of the
Owner to make such payments notwithstanding the same may have been without his consent
or authority or in law or otherwise to the contrary.
8.2. In every case in which by virtue of the provisions of Workmen's Compensation Act,
1923, or other Acts, the Owner is obliged to pay Compensation to a
Workman employed by the Contractor in execution of the works, the Owner will recover
from the Contractor the amount of compensation so paid and without prejudice to the rights
of Owner under the said Act. Owner shall be at liberty to recover such amount or any part
thereof by deducting it from the security deposit or from any sum due to the Contractor
whether under this contract or otherwise. The Owner shall not be bound to contest any claim
made under Section 12 sub section (1) of the said Act, except on the written request of the
- 198 of 237 -
Contractor and upon his giving to the Owner full security for all costs for which the owner
might become liable in consequence of contesting such claim.
8.a. ACTION AND COMPENSATION IN CASE OF BAD WORK
If it shall appear to the Engineer-in-Charge/Site-in-Charge that any work has been
executed with bad, imperfect or unskilled workmanship, or with materials, or that any
materials or articles provided by the Contractor for execution of the work are not of standards
specified/inferior quality to that contracted for, or otherwise not in accordance with the
contract, the CONTRACTOR shall on demand in writing from the Engineer-in-Charge/Sitein-Charge or his authorised representative specifying the work, materials or articles
complained of, notwithstanding that the same may have been inadvertently passed, certified
and paid for, forthwith rectify or remove and reconstruct the work so specified and at his own
charge and cost and expenses and in the event of failure to do so within a period of 15 days of
such intimation/ information/knowledge, the Contractor shall be liable to pay compensation
equivalent to the cost of reconstruction by the Owner. On expiry of 15 days period mentioned
above, the Owner may by themselves or otherwise rectify or remove and re-execute the work
or remove and replace with others, the materials or articles complained of as the case may be
at the risk and expenses in all respects of the Contractor. The decision of the Engineer-inCharge/ Site-in-Charge as to any question arising under this clause shall be final and
conclusive and shall not be raised as a dispute or shall be arbitrable.
8.b. INSPECTION AND AUDIT OF CONTRACT AND WORKS
This project is subject to inspection by various Government agencies of Government of India.
The contractor shall extend full cooperation to all the Government and other agencies in the
inspection of the works, audit of the Contract and the documents of Contract Bills,
measurements sheets etc. etc. and examination of the records of works and make enquiries
interrogation as they may deem fit, proper and necessary. Upon inspection etc. by such
agencies if it is pointed out that the contract work has not been carried out according to the
prescribed terms and conditions as laid down in the tender documents and if any recoveries
are recommended, the same shall be recovered from the contractors running bills/final
bill/from ordered/suggested Security Deposit/retention money. The Contractor shall not rise
any dispute on any such account and the same shall not be arbitrable.
9. CONTRACTOR TO INDEMNIFY THE OWNER
The Contractor shall indemnify the Owner and every member, officer and employee of the
Owner, also the Engineer-in-Charge/Site-in-Charge and his staff against all the actions,
proceedings, claims, demands, costs, expenses, whatsoever arising out of or in connection
with the works and all actions, proceedings, claims, demands, costs, expenses which may be
made against the Owner for or in respect of or arising out of any failure by the Contractor in
the performance of his obligations under the contract. The Contractor shall be liable for or in
respect of or in consequence of any accident or injury to any workmen or other person in the
employment of the Contractor or his sub contractor and Contractor shall indemnify and keep
indemnified the Owner against all such damages, proceedings, costs, charges and expenses
whatsoever in respect thereof or in relation thereto.
- 199 of 237 -
- 200 of 237 -
b) has failed to commence the works, or has without any lawful excuse under these
conditions suspended the work for 15 consecutive days.
c) has failed to remove materials from the site or to pull down and replace the work within 15
days after receiving from the Engineer written notice that the said materials or work were
condemned and/or rejected by the Engineer under specified conditions.
d) has neglected or failed to observe and perform all or any of the terms acts, matters or
things under this Contract to be observed and performed by the Contractor.
e) has to the detriment of good workmanship or in defiance of the Engineer's instructions to
the contrary sub-let any part of the Contract.
f) has acted in any manner to the detrimental interest, reputation, dignity, name or prestige of
the Owner.
g) has stopped attending to work without any prior notice and prior permission for a period of
15 days.
h) has become untraceable.
i) has without authority acted in violation of the terms and conditions of this contract and has
committed breach of terms of the contract in best judgement of the owner.
j) has been declared insolvent/bankrupt.
k) in the event of sudden death of the Contractor.
12.3 The owner on termination of such contract shall have the right to appropriate the
Security Deposit, Retention Money and invoke the Bank Guarantee furnished by the
contractor and to appropriate the same towards the amounts due and payable by the
contractor as per the conditions of Contract and return to the contractor excess money, if any,
left over.
12.4 In case of Termination of the contract, Owner shall have the right to carry out the
unexecuted portion of the work either by themselves or through any other
contractor (s) at the risk and cost of the Contractor. In view of paucity of time,
Owner shall have the right to place such unexecuted portion of the work on any
nominated contractor(s). However, the overall liability of the Contractor shall be
restricted to 100 % of the total contract value.
12.5 The contractor within or at the time fixed by the Owner shall depute his authorised
representative for taking joint final measurements of the works executed thus far and
submit the final bill for the work as per joint final measurement within 15 days of the
date of joint final measurement. If the contractor fails to depute their representative for joint
measurement, the owner shall take the measurement with their Engineer-in-Charge/Site-inCharge or any other outside representatives. Such a measurement shall not be questioned by
the Contractor and no dispute can be raised by the Contractor for purpose of Arbitration.
12.6 The Owner may enter upon and take possession of the works and all plant, tools,
scaffoldings, sheds, machinery, power operated tools and steel, cement and other
materials of the Contract at the site or around the site and use or employ the same for
completion of the work or employ any other contractor or other person or persons to
- 201 of 237 -
complete the works. The Contractor shall not in any way object or interrupt or do any act,
matter or thing to prevent or hinder such actions, other Contractor or other persons employed
for completing and finishing or using the materials and plant for the works. When the works
shall be completed or as soon thereafter the Engineer shall give a notice in writing to the
Contractor to remove surplus materials and plant, if any, and belonging to the Contractor
except as provided elsewhere in the Contract and should the Contractor fail to do so within a
period of 15 days after receipt thereof the Owner may sell the same by public auction and
shall give credit to the contractor for the amount realised. The Owner shall thereafter
ascertain and certify in writing under his hand what (if anything) shall be due or payable to or
by the Owner for the value of the plant and materials so taken possession and the expense or
loss which the Owner shall have been put to in
procuring the works, to be so completed, and the amount if any, owing to the
Contractor and the amount which shall be so certified shall thereupon be paid by the
Owner to the Contractor or by the Contractor to the Owner, as the case may, and the
Certificate of the Owner shall be final and conclusive between the parties.
12.7 When the contract is terminated by the Owner for all or any of the reasons mentioned
above the Contractor shall not have any right to claim compensation on account of such
termination.
13. FORCE MAJEURE
13.1. Any delay in or failure of the performance of either part hereto shall not constitute
default hereunder or give rise to any claims for damage, if any, to the extent such delays or
failure of performance is caused by occurrences such as Acts of God or an enemy,
expropriation or confiscation of facilities by Government authorities, acts of war, rebellion,
sabotage or fires, floods, explosions, riots, or strikes. The Contractor shall keep records of the
circumstances referred to above and bring these to the notice of the Engineer-in-Charge/Sitein-Charge in writing immediately on such occurrences. The amount of time, if any, lost on
any of these counts shall not be counted for the Contract period. Once decision of the Owner
arrived at after consultation with the Contractor, shall be final and binding. Such a
determined period of time be extended by the Owner to enable the Contractor to complete the
job within such extended period of time.
13.2. If Contractor is prevented or delayed from the performing any of its obligations
under this Agreement by Force Majeure, then Contractor shall notify Owner the
circumstances constituting the Force Majeure and the obligations performance of which is
thereby delayed or prevented, within seven days of the occurrence of the events.
14. ARBITRATION
14.1 All disputes and differences of whatsoever nature, whether existing or which shall at any
time arise between the parties hereto touching or concerning the agreement, meaning,
operation or effect thereof or to the rights and liabilities of the parties or arising out of or in
relation thereto whether during or after completion of the contract or whether before after
determination, foreclosure, termination or breach of the agreement (other than those in
respect of which the decision of any person is, by the contract, expressed to be final and
- 202 of 237 -
binding) shall, after written notice by either party to the agreement to the other of them and to
the Appointing Authority hereinafter mentioned, be referred for adjudication to the Sole
Arbitrator to be appointed as hereinafter provided.
14.2 The appointing authority shall either himself act as the Sole Arbitrator or nominate
some officer/retired officer of Hindustan Petroleum Corporation Limited (referred to as
owner or HPCL) or a retired officer of any other Government Company in the Oil Sector of
the rank of Ch. Manager & above or any retired officer of the Central Government not
below the rank of a Director, to act as the Sole Arbitrator to adjudicate the disputes and
differences between the parties. The contractor/vendor shall not be entitled to raise any
objection to the appointment of such person as the Sole Arbitrator on the ground that the
said person is/was an officer and/or shareholder of the owner, another Govt. Company or
the Central Government or that he/she has to deal or had dealt with the matter to which the
contract relates or that in the course of his/her duties, he/she has/had expressed views on all
or any of the matters in dispute or difference.
14.3 In the event of the Arbitrator to whom the matter is referred to, does not accept the
appointment, or is unable or unwilling to act or resigns or vacates his office for any
reasons whatsoever, the Appointing Authority aforesaid, shall nominate another person as
aforesaid, to act as the Sole Arbitrator.
14.4 Such another person nominated as the Sole Arbitrator shall be entitled to proceed with
the arbitration from the stage at which it was left by his predecessor. It is expressly agreed
between the parties that no person other than the Appointing Authority or a person
nominated by the Appointing Authority as aforesaid, shall act as an Arbitrator. The failure
on the part of the Appointing Authority to make an appointment on time shall only give rise
to a right to a Contractor to get such an appointment made and not to have any other
person appointed as the Sole Arbitrator.
14.5 The Award of the Sole Arbitrator shall be final and binding on the parties to the
Agreement.
14.6 The work under the Contract shall, however, continue during the Arbitration
proceedings and no payment due or payable to the concerned party shall be withheld (except
to the extent disputed) on account of initiation, commencement or pendency of such
proceedings.
14.7 The Arbitrator may give a composite or separate Award(s) in respect of each dispute or
difference referred to him and may also make interim award(s) if necessary.
14.8 The fees of the Arbitrator and expenses of arbitration, if any, shall be borne equally by
the parties unless the Sole Arbitrator otherwise directs in his award with reasons. The
lumpsum fees of the Arbitrator shall be Rs. 40,000/- per case for transportation
contracts and Rs. 60,000/- for engineering contracts and if the sole Arbitrator
completes the arbitration including his award within 5 months of accepting his
appointment, he shall be paid Rs. 10,000/- additionally as bonus. Reasonable actual
expenses for stenographer, etc. will be reimbursed. Fees shall be paid stagewise i.e. 25%
on acceptance, 25% on completion of pleadings/documentation, 25% on completion of
arguments and balance on receipt of award by the parties
- 203 of 237 -
14.9 Subject to the aforesaid, the provisions of the Arbitration and Conciliation Act, 1996 or
any statutory modification or re-enactment thereof and the rules made thereunder, shall apply
to the Arbitration proceedings under this Clause.
14.10 The Contract shall be governed by and constructed according to the laws in force in
India. The parties hereby submit to the exclusive jurisdiction of the Courts situated at
_______ (say Mumbai*) for all purposes. The Arbitration shall be held at ________ (say
Mumbai*) and conducted in English language.
14.11 The Appointing Authority is the Functional Director of Hindustan Petroleum
Corporation Limited.
(Note:- * = While printing the GTCs, each Purchasing Authorities at various location,
may mention the correct place before printing the GTC and not leave Clause 14.10 blank
or as stated above. Bracketed portion is to be removed.
15. GENERAL
15.1. Materials required for the works whether brought by the or supplied by the Owner shall be
stored by the contractor only at places approved by
Engineer-in-Charge/Site-in-Charge. Storage and safe custody of the material shall be the
responsibility of the Contractor.
15.2. Owner and/or Engineer-in-Charge/Site-in-Charge connected with the contract, shall be
entitled at any time to inspect and examine any materials intended to be used in or on the works,
either on the site or at factory or workshop or at other place(s) manufactured or at any places
where these are laying or from which these are being obtained and the contractor shall give
facilities as may be required for such inspection and examination.
15.3. In case of any class of work for which there is no such specification supplied by the owner
as is mentioned in the tender documents, such work shall be carried out in accordance
with Indian Standard Specifications and if the Indian Standard Specifications do not cover the
same the work should be carried out as per standard Engineering practice subject to the approval
of the Engineer-in-Charge/Site-in-Charge.
15.4. Should the work be suspended by reason of rain, strike, lockouts or other cause the
contractor shall take all precautions necessary for the protection of the work and at his own
expense shall make good any damages arising from any of these causes.
15.5 The contractor shall cover up and protect from injury from any cause all new work also
for supplying all temporary doors, protection to windows and any other requisite protection for
the whole of the works executed whether by himself or special tradesmen or sub- contractors and
any damage caused must be made good by the contractors at his own expense.
15.6 If the contractor has quoted the items under the deemed exports, then it will be the
responsibility of the contractor to get all the benefits under deemed exports from the
Government. The Owners responsibility shall only be limited to the issuance of required
certificates. The quotation will be unconditional and phrases like subject to
availability of deemed exports benefit etc. will not find place in it.
16. Integrity Pact : Effective 1st September, 2007, all tenders and contracts shall comply
with the requirements of the Integrity Pact (IP) if the value of such tenders or contracts
exceed Rs.1 crore. Failure to sign the Integrity Pact shall lead to outright rejection of bid.
- 204 of 237 -
- 205 of 237 -
- 206 of 237 -
1.
2.
3.
4.
a.
The safety regulation of the refinery as mentioned in the Fire & safety
Regulations (Latest revision).
b.
All requirements under The Factories Act 1948 and the rules framed there under
in the Factory Rules 1963 including all amendments thereto.
c.
All requirements of Worker Compensation Act & ESIS Act including all
amendments thereto.
d.
QUALIFICATION
DEPLOYED
AND
EXPERIENCE
OF
MANPOWER
TO
BE
a.
b.
c.
HEALTH ASSURANCE/AGE
a.
Contractors to ensure that all their workmen are medically fit for the job they are
deployed, especially for the workmen who are deployed in high risk jobs like
working in confined space, working in height, working under water etc.
b.
Age: No one below 18 years or more than 58 years will be employed in the
refinery.
The duty timings for contractor employees shall be in from 8.30AM to 4.30 PM.
However, extension to the working hours may be granted by HPCL upon
contractors written request and subject to the strict compliance of prevailing
refinery safety and security rules.
- 207 of 237 -
5.
TRAINING
a.
b.
c.
6.
7.
i.
ii.
This program will be conducted by Fire & safety Dept. at the Fire Station
Training Hall and the schedule shall be notified well in advance.
iii.
iv.
The Passing certificate issued to the supervisor will remain valid for one
year.
Workers' Training
i.
ii.
Do not carryout any work without valid work permit issued by authorized
person in the refinery as per Work permit System.
b.
c.
REQUIREMENTS OF SUPERVISION
a.
Contractor will not carryout any work without having supervisor at site. If it is
required to work simultaneously in more than one location under the same
contract, one supervisor must be put in each of the locations. If a supervisor has
to leave his site for any reason, he must stop his activities for that period of time.
b.
For hot work permit, the supervisor must have valid Training Certificate from
Refinery safety dept.
c.
Contractor must provide at least one full time Safety Supervisor when the
contractor has engaged manpower in excess of 100 in contract activities in the
refinery. If the manpower is less than 100, the on-site safety coordination
responsibilities shall be assumed by any one of the contractor's other supervisory
- 208 of 237 -
staff. In both the cases, the contractor must specify in writing the name of such
person to the Engineer-incharge and Manager - Safety.
d.
8.
Contractors all supervisors and workmen must wear the following Personal
Protective Equipments (PPE's) without which the permission to work will be
denied. Basic PPE's should be provided by the contractor.
b.
c.
d.
9.
The contractors whose safety records are not satisfactory will be viewed
seriously and necessary action (viz. cancellation of registration/contracts) shall
be taken against him.
i.
ii.
iii.
Hand Gloves.
ii.
iii.
Contractor shall provide Fire Hoses with Nozzle & Fire Extinguishers of his
own. If he is executing jobs in refinery, for which following specifications
should be adhered to.
b.
Fire Hose : The fire hose should be 63mm/38mm diameter and minimum 15
mtr long, seamless canvass/synthetic fibre woven jacketed, rubberized fabric
reinforced rubber lined hose bearing IS:636-1988 Type A. The fire hose should
have Gun-metal instantaneous type 2 " Male & 2 " Female couplings
bearing IS:903 mark. The couplings should be riveted & doubly wounded with
heavy-duty copper wire to the hose at both ends.
c.
Nozzle : The nozzle to be used with fire hose should be of "Branch Pipe,
Universal" type as per IS:2871-1983. it should be provided with 2 " Female
Instantaneous couplings as per IS:903 (as nozzle with male coupling will
necessitate use of double female coupling)
- 209 of 237 -
d.
10
11.
12.
HAZARD COMMUNICATION
a.
n the event, any contractor employee spot a fire or any serious hazards in
refinery premises, he shall dial Ext 6666, identify himself and report location of
fire when fire station operator is on line. He shall wait until the fire message is
repeated by the fire operator and location confirmed.
b.
c.
The contractor must ensure that each one of his employees clearly understand
this Fire Communication requirement, i.e. in case of fire siren is sounded they
should assemble at designated location near FR Yard Office and south of FR
Boiler House. This may be ensured by contractor while providing on the job
training.
Report to HPCL supervisor on the job, any injury sustained by any of his
employees or any near-miss or any hazardous/dangerous incident at his worksite
within the refinery premises. Hiding any accident or near miss would be viewed
as serious misconduct.
b.
c.
Keep and maintain proper records of all such incidents in respect of his
personal/work site.
d.
e.
REQUIREMENT OF HOUSEKEEPING
Contractor must ensure highest standard of housekeeping in his areas of work on a
day to day basis. All unsatisfactory housekeeping will earn negative rating, which will
attract penal action like cancellation of registration/contract.
13.
- 210 of 237 -
14.
- 211 of 237 -
15.
POLICE VERIFICATION
Contractor who engages labourer for his jobs in the refinery must submit Police
Verification of antecedents of labourers engaged by him.
Note
a.
Every person other than HPCL employee or a casual visitor entering in the refinery
would be governed by above conditions.
b.
The term supervisor would mean any person who oversees the works of a group of
workmen. All other persons will be considered as workmen.
c.
Adherence to terms of contract will also be checked by Fire & Safety Dept personnel.
Violation of any of the above conditions of safety would attract penal actions including
termination of contract/registration.
16.
b)
The workers engaged in scaffolding work must wear safety belt with double
lifetime. This is intended to ensure that lifeline is secured all the time, even
while the person is moving.
c)
Safety nets must be deployed first at 10 feet elevation and at every 20 feet
elevation. These nets should be inside scaffold box as well as extend outwards.
d)
It should be ensured that only trained and experienced workers are engaged in
scaffolding work
- 212 of 237 -
b.
c.
d.
Non-provision of Fire fighting Equipment : Rs.200/- (as per Work Permit conditions)
e.
Non-barricading of area while Rigging, Digging, etc. Rs.100/- and usage of defective
Fire fighting Equipment:
f.
g.
Unauthorized Road closure / blockage: Rs.200/Please note that in case of any non-compliance/deviations to Work Permit conditions and/or
Safety rules is found, applicable Penalty Clause would be exercised, as listed out above. This
will result in stoppage of the job and Work Permit & Gate Pass will be taken from
Contractor's Supervisor. HPCL will prepare a non-compliance Report on the same and Work
Permit/Gate Pass will be returned back (for re-starting the job) only after ensuring complete
compliance of the above Safety requirements.
- 213 of 237 -
SECTION 11
INTEGRITY PACT
- 214 of 237 -
INTEGRITY PACT
All tenders and contracts whose value exceed Rs.1 crore shall comply with the
requirements of the Integrity Pact (IP).Failure to sign the Integrity Pact shall lead to
outright rejection of bid. ( Annexure-I & Annexure-II)
Effective 1st September, 2007, all tenders and contracts shall comply with the
requirements of the Integrity Pact (IP) if the value of such tenders or contracts exceed
Rs.1 crore. Failure to sign the Integrity Pact shall lead to outright rejection of bid.
A suitable Clause to form part of the tender document as mentioned below (H.3)
# H.1 Agreement to be handed over pre-signed by HPCL representative at the time of
sale of tender documents to the vendors as per Annexure - I. Where the tenders are
downloaded from the Net, this Agreement shall be a precondition to the downloading
of the tender documents.
# H.2. Integrity Pact (IP) form (Annexure - II) to be received from the bidder duly
signed along with the technical bid. This document should also be pre-signed by
authorised representative before handing over to bidder.
H.3 IP Clause to be included in the Tender / Bid Documents Integrity Pact (applicable
for cases above Rs.1 Crore)
The Integrity Pact duly signed by the authorized official of HPCL and the Contractor,
will form part of this contract / supply order. Proforma of Integrity Pact (which is
issued along with the bidding document - Annexure- II) shall be returned by the
bidder along with technical bid, duly signed by the same signatory who signs the bid
i.e. who is duly authorized to sign the bid. All the pages of the Integrity Pact shall be
duly signed by the same signatory. Bidders failure to return the Integrity Pact along
with the bid, duly signed, shall lead to outright rejection of such bid. If the Bidder has
been disqualified from the tender process prior to the award of contract according to
the provisions under Integrity Pact, HPCL shall be entitled to demand and recover
from bidder Liquidated damages amount by forfeiting the EMD/Bid security (Bid
Bond) as per provisions of Integrity Pact.
If the contract has been terminated according to provisions of the Integrity Pact, or if
HPCL is entitled to terminate the contract according to provisions of Integrity Pact,
HPCL shall be entitled to demand and recover from the Contractor liquidated
damages amount by forfeiting the Performance Bank Guarantee / Security Deposit as
per Integrity Pact
- 215 of 237 -
Annexure - I
AGREEMENT
(Under Integrity Pact)
No.
Dated
To,
HINDUSTAN PETROLEUM CORPORATION LIMITED
Sub : Purchase of Bidding Documents
Ref. Tender No.
HPCL and the Bidder agree that the Notice Inviting Tender (NIT) is an offer made on the
condition that the bidder will sign the Integrity Pact and the Bid would be kept open in its
original form without variation or modification for a period of (state the number of days from
the last date for the receipt of tenders stated in the NIT) . days and the making of the
bid shall be regarded as an unconditional and absolute acceptance of this condition of the
NIT. We confirm acceptance and compliance with the Integrity Pact in letter and spirit. We
further agree that the contract consisting of the above conditions of NIT as the offer and the
submission of Bid as the Acceptance shall be separate and distinct from the contract which
will come into existence when bid is finally accepted by HPCL. The consideration for this
separate initial contract preceding the main contract is that HPCL is not agreeable to sell the
NIT to the Bidder and to consider the bid to be made except on the condition that the bid
shall be kept open for days after the last date fixed for the receipt of the bids and the
Bidder desires to make a bid on this condition and after entering into this separate initial
contract with HPCL.
HPCL promises to consider the bid on this condition and the Bidder agrees to keep the bid
open for the required period. These reciprocal promises form the consideration for this
separate initial contract between the parties. If Bidder fails to honour the above terms and
conditions , HPCL shall have unqualified , absolute and unfettered right to encash / forfeit the
bid security submitted in this behalf.
Yours faithfully,
(BIDDER) (PURCHASER)
- 216 of 237 -
(INTEGRITY PACT)
Annexure - II
Between
Hindustan Petroleum Corporation Limited (HPCL) hereinafter referred to as The Principal,
and
. hereinafter referred to as The Bidder/
Contractor
Preamble
The Principal intends to award, under laid down organization procedures, contract/s
for The Principle values full compliance with all
relevant laws and regulations, and the principles of economic use of resources, and of fairness
and transparency in its relations with its Bidders/s and Contractor/s.
In order to achieve these goals, the Principal cooperates with the renowned international NonGovernmental Organisation Transparency International (TI). Following TIs national and
international experience, the Principal will appoint an external independent Monitor who will
monitor the tender process and the execution of the contract for compliance with the
principles mentioned above.
Section 1 Commitments of the Principal
(1) The Principal commits itself to take all measures necessary to prevent corruption and to
observe the following principles:
1. No employee of the Principal, personally or through family members, will in
connection with the tender for, or the execution of a contract, demand, take a promise
for or accept, for him/herself or third person, any material or immaterial benefit which
he/she is not legally entitled to.
2. The principal will, during the tender process treat all Bidders with equity and reason.
The Principal will in particular, before and during the tender process, provide to all
Bidders the same information and will not provide to any Bidder confidential /
additional information through which the Bidder could obtain an advantage in relation
to the tender process or the contract execution.
3. The principal will exclude from the process all known prejudiced persons. the Bidder
/ Contractor shall compensate the Principal only to the extent of the damage in the
amount proved.
- 217 of 237 -
The Bidder / Contractor will not instigate third persons to commit offences outlined
above or be an accessory to such offences.
Section 3-Disqualification from tender process and exclusion from future contracts
If the Bidder, before contract award has committed a transgression through a violation of
Section 2 or in any other form such as to put his reliability or credibility as Bidder into
question, the Principal is entitled to disqualify the Bidder from the tender process or to
terminate the contract, if already signed, for such reason.
(1)
- 218 of 237 -
company hierarchy of the Bidder and the amount of the damage. The exclusion will be
imposed for a minimum of 6 months and maximum of 3 years.
(2)
(3)
The Bidder accepts and undertakes to respect and uphold the Principals absolute right
to resort to and impose such exclusion and further accepts and undertakes not to
challenge or question such exclusion on any ground, including the lack of any hearing
before the decision to resort to such exclusion is taken. This undertaking is given
freely and after obtaining independent legal advice.
(4)
If the Bidder / Contractor can prove that he has restored / recouped the damage caused
by him and has installed a suitable corruption prevention system, the Principal may
revoke the exclusion prematurely.
If the Principal has disqualified the Bidder from the tender process prior to the award
according to Section 3, the Principal is entitled to demand and recover from the
Bidder liquidated damages equivalent to Earnest Money Deposit/Bid Security.
(2)
If the Principal has terminated the contract according to Section 3, or if the Principle is
entitled to terminate the contract according to Section 3, the Principal shall be entitled
to demand and recover from the Contractor liquidated damages equivalent to Security
Deposit / Performance Bank Guarantee.
(3)
The bidder agrees and undertakes to pay the said amounts without protest or demur
subject only to condition that if the Bidder / Contractor can prove and establish that
the exclusion of the Bidder from the tender process or the termination of the contract
after the contract award has caused no damage or less damage than the amount of the
liquidated damages, the Bidder / Contractor shall compensate the Principal only to the
extent of the damage in the amount proved.
The Bidder declares that no previous transgression occurred in the last 3 years with
any other Company in any country conforming to the TI approach or with any other
Public Sector Enterprise in India that could justify his exclusion from the tender
process.
(2)
If the Bidder makes incorrect statement on this subject, he can be disqualified from
the tender process or the contract, if already awarded, can be terminated for such
reason.
- 219 of 237 -
(1)
(2)
The Principal will enter into agreements with identical conditions as this one with all
Bidders, Contractors and Subcontractors.
(3)
The Principal will disqualify from the tender process all bidders who do not sign this
Pact or violate its provisions.
The Principal appoints competent and credible External Independent Monitor for
this
Pact.
#
The
Principal
has
nominated
Shri
/Smt.
______________________________________as
External
Independent
Monitor(s) for the purpose of administration of this Pact. The task of the
Monitor is to review independently and objectively, whether and to what extent the
parties comply with the obligations under this agreement.
(2)
The Monitor is not subject to instructions by the representatives of the parties and
performs his functions neutrally and independently. He reports to the Chairperson of
the Board of the Principal.
- 220 of 237 -
This agreement is subject to Indian Law. Place of performance and jurisdiction is the
Registered Office of the Principal, i.e. Mumbai. The Arbitration clause provided in
the main tender document / contract shall not be applicable for any issue / dispute
arising under Integrity Pact.
(2)
(3)
(4)
Should one or several provisions of this agreement turn out to be invalid, the
remainder of this agreement remains valid. In this case, the parties will strive to come
to an agreement to their original intentions.
-----------------------------
-----------------------------
Place
Witness1:
Date
- 221 of 237 -
SECTION 12
HPCL FORMATS
- 222 of 237 -
- 223 of 237 -
3. We, ___________________ Bank further agree that the amount demanded by "the
Corporation" as such shall be final and binding on "the Bank" as to "the Bank's" liability
to pay and amount demanded and "the Bank" undertake to pay "the Corporation" the amount
so demanded on first demand and without any demur notwithstanding any dispute raised by
"the Supplier" or any suit or other legal proceedings including arbitration pending before any
court tribunal or arbitrator relating thereto, our liability under this guarantee being absolute
and unconditional. (We __________________
Bank further agree that the guarantee herein contained shall remain in full force and
continue to have full effect so long as the said amount remains unadjusted, provided,
however, the value of the guarantee shall progressively reduce upon any adjustments being
made by "the Corporation" against the said advance and "the Corporation" rights shall extend
only to the value of the unadjusted amount.
4. We, __________________ Bank further agree with "the Corporation" that "the
Corporation" shall have the fullest liberty without our consent and without affecting in
any manner our obligations hereunder to vary any of the terms and conditions of the said
"order"/or to extend time of performance by "the Supplier" from time to time or to postpone
for any time or from time to time any of the powers exercisable by "the Corporation" against
"the Supplier" and to forbear to enforce any of the terms and
conditions relating to "the Order" and we shall not be relieved from our liability by reason of
any such variation or extension being granted to "the Supplier" or for any forbearance, act or
omission on "the Supplier" or by any such matter or things whatsoever which under the law
relating to suretics would be for this provisions have the
effect of relieving us.
5. Not withstanding anything contained herein above :
i) Our liability under this guarantee shall not exceed Rs..........
ii) This Bank Guarantee shall be valid upto and including .......; and
iii) We are liable to pay the guarantee amount or any part thereof under this Bank
Guarantee only and only if you serve upon us a written claim or demand on or #
before the expiry of 30 days from the date of expiry of this guarantee
6. We, ________________ Bank further undertake not to revoke this guarantee during its
currency except with the previous consent of "the Corporation" in writing.
7. We, ____________________ Bank lastly agree that "the Bank" liability under this
guarantee shall not be affected by any change in the constitution of "the Supplier".
8. We, _________________ Bank has power to issue this guarantee in favour of "the
Corporation" in terms of the documents and/or the agreement/contract or MOU entered into
between"the supplier" and "the Bank" in this regard.
- 224 of 237 -
- 225 of 237 -
Date: 18.12.2010
Rev 0
(SPECIMEN)
BANK GUARANTEE IN LIEU OF EARNEST MONEY
(On Non-Judicial stamp paper of appropriate value)
- 226 of 237 -
3. We, ................................. Bank further agree that the amount demanded by "the
Corporation" as such shall be final and binding on "the Bank" as to "the Bank" 's
liability to pay and the amount demanded and "the Bank" to undertake to pay "the
Corporation" the amount so demanded on first demand and without any demur
notwithstanding any dispute raised by "the Tenderer" or any suit or other legal
proceedings including arbitration pending before any court, tribunal or arbitrator
relating thereto, our liability under this guarantee being absolute and unconditional.
4. We, ....................................... Bank further agree with "the Corporation" that "the
Corporation" shall have the fullest liberty without our consent and without affecting
in any manner our obligations hereunder to vary any of the terms and conditions of
the said "tender"/or to extend time of performance by "the Tenderer" from time to
time or to postpone for any time to time any of the powers exercisable by "the
Corporation" against "the Tenderer" and to forbear to enforce any of the terms and
conditions relating to "the tender" and we shall not be relieved from our liability by
reason of any such variation or extension being granted to "the Tenderer" or for any
forbearance, act or ommission on the part of "the Corporation" or any indulgence by
"the Corporation" to "the tenderer" or by any such matter or things whatsoever which
under the law relating to sureties would but for this provision have the effect of
relieving us.
5. NOTWITHSTANDING anything hereinbefore contained, our liability under this
Guarantee is restricted to Rs. ......... (Rupees....................................... only). Our
liability under this guarantee shall remain in force until expiration of six months
from the due date of opening of the said "tender". Unless a demand or claim under
this guarantee is made on us in writing within said period, that is, on or before
.................................... all rights of "the Corporation" under the said guarantee shall
be forfeited and we shall be relieved and discharged from all liabilities thereunder.
6. We, ........................................ Bank further undertake not to revoke this guarantee
during its
currency except with the previous consent of "the Corporation" in
Writing.
7. We, ......................................... Bank lastly agree that "the Bank" 's liability under this
guarantee shall not be affected by any change in the constitution of "the Tenderer".
8. "The Bank" has power to issue this guarantee in favour of "the Corporation" in terms
of the documents and/or the Agreement/Contract or MOU entered into between "the
Tenderer" and "the Bank" in this regard.
- 227 of 237 -
IN WITNESS WHEREOF the Bank has executed this document on this ..........................
day of ........................
For ........................
Bank
(by its constituted
attorney)
(Signature of a person
authorised
to sign on behalf of "the
Bank")
- 228 of 237 -
- 229 of 237 -
- 230 of 237 -
____________________________ Bank
(by its constituted
attorney) (signature of a
person authorized to sign
on behalf of "the Bank")
- 231 of 237 -
- 232 of 237 -
2. We, ............................. Bank further agree that "the Corporation" shall be sole judge
whether the said "Supplier" has failed to perform or fulfill the said "order" in terms
thereof or committed breach of any terms and conditions of "the order" and the extent of
loss, damage, cost, charges and expenses suffered or incurred or would be suffered or
incurred by "the Corporation" on account thereof and we waive in the favour of "the
Corporation" all the rights and defences to which we as guarantors and/or "the Supplier"
may be entitled to.
3. We, ................................. Bank further agree that the amount demanded by "the
Corporation" as such shall be final and binding on "the Bank" as to "the Bank" 's
liability to pay and the amount demanded and "the Bank" undertake to pay "the
Corporation" the amount so demanded on first demand and without any demur
notwithstanding any
dispute raised by "the Supplier" or any suit or other legal proceedings including
arbitration pending before any court,tribunal or arbitrator relating thereto, our liability
under this guarantee being absolute and unconditional.
4. We, .................................. Bank further agree
with
"the Corporation" that "the Corporation" shall have the fullest liberty without our
consent and without affecting in any manner our obligations hereunder to vary any of
the terms and conditions of the said "order"/or to extend time of performance by "the
Supplier" from time to time or to postpone for any time to time any of the powers
exercisable
by "the Corporation" against "the Supplier" and to forbear to enforce any of the terms
and conditions relating to "the order" and we shall not be relieved from our liability by
reason of any such variation or extension being granted to "the Supplier" or for any
forbearance, act or ommission on the part of "the Corporation" or any indulgence by
"the
Corporation" to "the Supplier" or by any such matter or things whatsoever which under
the law relating to sureties would but for this provision have the effect of relieving us.
5. However, it has been agreed between "the Supplier" and "the Corporation" that there
shall be only one Composite Bank Guarantee for both the advance and security deposit
performance guarantee/Retention Money @ of ____% valid till the end of the defects
liability period as per the terms of the P.O. No. _______________ dated
______________ and that in proportion with the recovery of advance @ ______% per
bill the same amount/value automatically stands credited to the defects liability
account/security deposit or retention money as the case may be and will continue to be
credited/treated till the entire advance of Rs._______________________ is fully
recovered from the running bills and from the date of full recovery of the advance of
- 233 of 237 -
- 234 of 237 -
INDEMNITY BOND
(TO BE NOTORISED AND ON STAMP PAPER OF APPROPRIATE VALUE)
TO,
HINDUSTAN PETROLEUM CORPN. LTD.
(Address as applicable)
Dear Sirs,
WHEREAS Hindustan Petroleum Corporation Limited, a Government of India
Company, registered under the Companies Act, 1956, having its Registered Office at 17,
Jamshedji Tata Road, Bombay 400020 (hereinafter called "the Indemnified" which
expression shall include its successors and assigns) has awarded to M/s.
.......................................... a Partnership Firm/Sole Proprietor Business/a company
having its Registered Office at ....................................................... (hereinafter called
"the Indemnifier", which expression shall include its successors and assigns) a contract
for conditions set out, inter-alia, in "the Indemnified" 's Purchase Order No.
............................. dated .................. (hereinafter referred to as "The Said Contract") to
"the Indemnifier".
AND WHEREAS "the Indemnified" has agreed to supply to "the Indemnifier" raw
material/components to the value of Rs.........(Rupees .............................................. only)
for incorporation in fabrication by "the Indemnifier" in terms of "the said contract", the
components/raw material to be supplied by "the Indemnified" to "the Indemnifier" for
the said fabrication, (hereinafter, for the sake of brevity, referred to as "the said
material") and pending fabrication and delivery at job-site of the completed fabricated
work(s) incorporating "the said material" and accounting for "the said material" shall be
under the sole custody and charge of "the Indemnifier" and shall be kept, stored, altered,
worked upon and/or fabricated at the sole risk and expenses of "the Indemnifier" ;
As a Pre-condition to the supply of "the said material" by "the Indemnified" to "the
Indemnifier", the Indemnified" has required "the Indemnifier" to furnish to "the
Indemnified" security in the manner and upon terms and conditions hereinafter indicated
NOW THEREFORE, in consideration of the premises aforesaid "the Indemnifier" Shri
..................................., Shri ............................ all directors/partners/sole proprietor of
"the Indemnifier" in consideration of aforesaid "contract" hereby irrevocably and
unconditionally and jointly and severally undertake to idemnify and always keep "the
Indemnified" from and against all loss, damage and destruction (inclusive but not
limited to any or all loss or damage or destruction to or of "the said material" or any item
or part thereof) by theft, fire, flood, storm, tempest, lightning, explosion, storage,
chemical or physical action or reaction, bending, wrapping, exposure,rusting, faulty
- 235 of 237 -
- 236 of 237 -
Indemnified" against "the Indemnifier" and "the Indemnifier" hereby waive all rights, if
any,at any time, inconsistent with the terms of this Indemnity.
4. This Indemnity shall not be determined or affected by the liquidation or winding up,
dissolution, or change of constitution or insolvency of "the Indemnifier" and the
obligations of "the Indemnifier" in terms hereof shall not be anywise affected or
suspended by reason of any dispute or disputes having been raised by "the Indemnifier"
(whether now pending before any Arbitrator, Officer, Tribunal or Court) or any denial of
liability by "the Indemnifier" or any other order or communication whatsoever by "the
Indemnifier" stopping or preventing or purporting to stop or prevent any payment by
"the Indemnifier" to "the Indemnified" in terms hereof :
5. The mere statement made by or on behalf of "the Indemnified" in any notice or
demand or other writing addressed to "the Indemnifier" as to any of "the said material"
or item or part thereof supplied to "the Indemnifier" having been lost,damaged,
destroyed, misused or misappropriated while in the custody of "the Indemnifier" before
or after completion of the completed fabricated work(s) incorporating "the said material"
and delivery at job site thereof shall as between "the Indemnifier" and "the Indemnified"
be conclusive of the factum of "the said material" or item or part thereof having been
supplied to "the Indemnifier" and/or the loss, damage,destruction, misuse or
misappropriation thereof, as the case may be, while in the custody of "the Indemnifier"
and/or prior to the completion of the completed fabricated work(s)and delivery to job
site thereof without necessity on the part of "the Indemnified" to produce any
documentary proof or other evidence whatsoever in support of this;
6. The amount stated in any notice of demand addressed by "the Indemnified" to "the
Indemnifier" as the value of any of "the said material", lost, damaged, destroyed or
misused or misappropriated, inclusive relative to the cost and expenses incurred by "the
Indemnified" in connection therewith shall as between "the Indemnifier" and "the
Indemnified" be conclusive of the value of such "said material" and the said costs and
expenses as also of the amount liable to be paid by "the Indemnifer" to "the
Indemnified" in terms and for the purpose of, without necessity for "the Indemnfied" to
produce any voucher, bill or other documentation or evidence whatsoever in support
thereof.
In witness whereof "the Indemnifier" have hereunto set and subscribed his hand this day
and year first hereinabove written in the presence of witnesses.
Yours faithfully,
1)
2)
3)
WITNESSES
1.
2
- 237 of 237 -