Professional Documents
Culture Documents
TABLE OF CONTENTS
1.0
1.1
Introduction ................................................................................................. 1
1.2
Fieldwork ..................................................................................................... 1
1.3
2.0
2.1
Introduction ................................................................................................. 2
2.2
2.3
2.4
3.0
3.1
4.0
Geotechnical Report
Page i
1.0
1.1
Introduction
Foundation investigation has been carried out at proposed River site found in the
Upper West Region.
1.2
Fieldwork
The fieldwork was carried out between 11th and 13th February, 2010.
To facilitate the attainment of the requirement of the fieldwork, and also
ensure compliance with the requirements of soil sample recovery and
performance of specified field tests such as standard penetration tests and
recovery of undisturbed clayey/compressible soils, a 1-ton mobile cable
percussion boring rig was used to undertake subsoil investigation.
1.3
Percussion drilling in soft ground involved the drilling of two (2No.) boreholes at
Kulun. One borehole was drilled at each approach.
The various depths attained in soft ground and decomposed rock are shown in
Table 1. Sampling and in-situ testing were carried out in the boreholes in
accordance with project specifications.
All boreholes in soft ground were deemed to have attained refusal when a total
of 50 blows have been applied during any one of the three 0.15m (6-ins)
sampler advancement during SPT. The final depths of the boreholes ranged
from 9.5m in BH 1 to 6.8m in BH 2. Duration for chiseling in each borehole
averaged one hour thirty minutes.
Geotechnical Report
Page 1
Depth in Rock
Ground
(Chiselling with
(Percussion
California Hammer)
Drilling)
Total
Depth
B1
9.5m
0.0m
9.5m
B2
6.8m
0.0m
6.8m
2.0
SUBSURFACE CONDITIONS
2.1
Introduction
This section present the results of the field activities and samples recovered as
part of the investigations.
2.2
Surficial Soil Profile
The boreholes sunk at the site revealed the following ground conditions;
Thickness
Average SPT N
7
SILT
Loose to medium dense coarse 2.1m 9.3m
Geotechnical Report
9.3m 9.5m
refusal
Page 2
2.3
Country Rock
Bedrock of weathered Granite belonging to the Middle Precambrian granitic
rocks, with minor belts of Birrimian rocks was encountered in all locations
drilled. It was chiselled at all borehole locations. The geological map indicates
that granite was to be expected along the project corridor. At Kulun the
material actually chiseled is greyish sand with fined grained gravel (weathered
rock).
2.4
Groundwater Conditions
Groundwater was encountered at a depth of 4.65m in BH1 and 4.0m in BH2.
Within the project area, the major rainy season occurs from mid August to
October. Groundwater levels are normally expected to peak at mid September
to mid October and be at lowest in mid December to mid April. Seasonal
fluctuation in groundwater level is dependent on several factors notable are;
geology, rainfall amount, topography, catchment area size, groundwater
abstraction and recharge rates, surface drainage and land-use characteristics.
Geotechnical Report
Page 3
3.0
3.1
The results obtained for N may be used to estimate bearing capacity for
granular soils of weathered granite formations. This is done in conjunction with
estimated width (B) of footing, and this is read off in the relationship established
by Terzargi and Peck curve for soils, ultimate bearing pressure in kN/m
Qult
2
N
B 0.3
B
0.08
4.0
FOUNDATION DEPTH AND TYPE
At the Kulun bridge site a foundation depth of 9.3m should be adopted. This will
mainly be in the competent weathered rock horizon.
It is therefore recommended that a design bearing capacity of 500
750KN/m2 be used and footings placed at 5.5m. At that footing depth,
either piles or caissons is to be used.
Geotechnical Report
Page 4
APPENDIX A
Geotechnical Report
Page 5
BOREHOLE LOG
PROJECT:
Kulun
LOCATION:
BORING METHOD: Percussion Drilling
pH Value
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
4
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
5
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
6
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
7
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
8
8.1
8.2
8.3
8.4
8.5
8.6
8.7
8.8
8.9
9
9.1
9.2
9.3
9.4
9.5
(%)
Chemical
Tests
Cl- (mgl-1)
Type
Shear
Test
Cu (kN/m2)
Level*
(m)
N-value
Soil/Rock Description
Fines %
Sample
Consistency
Limits
nmc LL PI DFS
Sand %
OD
In-situ
Test
Gravel (%)
Symbol
Soil Profile
SO42- (mgl-1)
Borehole No.: 1
spt1
N=8
6.8
19
48
52
spt2
N=3
6.7 Non-plastic
78
22
N=5
5.1 Non-plastic
86
14
spt3
- Ground water
spt4
N=6
32.8 Non-plastic
83
11
spt5
N=4
15.0 Non-plastic
93
N=6
16.7 Non-plastic
78
22
N=7
17.2
65
35
7.6 Non-plastic
43
56
spt6
spt7
20
spt8
N=24
spt9
N>50
Very hard granitic rock
CPT
End of borehole
LEGEND
ds - disturbed sample
ud - undisturbed sample
spt - Standard Penetration Test Sample
CPT - Cone Penetration Test
N-value
Cu - Cohesion
- Coefficient of shear resistance
SO42- - Sulphate Content
Cl- - Chloride Content
Note
Hole chisseled for 1.5hours. There was no pentration
Cone test performed at 9.5m. There was no penetration after 60 blows
Geotechnical Report
Page 6
BOREHOLE LOG
PROJECT:
Kulun
LOCATION:
BORING METHOD: Percussion Drilling
(%)
pH Value
N-value
Chemical
Tests
Cl- (mgl-1)
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
4
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
5
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
6
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
Soil/Rock Description
Cu (kN/m2)
Type
Shear
Test
Fines %
Sample
Consistency
Limits
nmc LL PI DFS
Sand %
OD
Level*
(m)
In-situ
Test
Gravel (%)
Symbol
Soil Profile
SO42- (mgl-1)
Borehole No.: 2
ds1
spt1
N=5
11.7
29
14
26
74
spt2
N=6
15.4
20
45
55
N=5
24.3
24
10
49
51
spt3
- Ground water
spt4
N=6
22.1
27
10
43
57
spt5
N>50
9.4
21
35
57
13.6 Non-plastic
92
spt6
CPT
LEGEND
ds - disturbed sample
ud - undisturbed sample
spt - Standard Penetration Test Sample
CPT - Cone Penetration Test
N-value
Cu - Cohesion
- Coefficient of shear resistance
SO42- - Sulphate Content
Cl- - Chloride Content
Note
Hole chisseled for 1.5hours. There was no pentration
Cone test performed at 6.8m. There was no penetration after 60 blows
Geotechnical Report
Page 7
KULUN
BRIDGE
BOREHOLE LOCATION
12-02-10
44m
KuB3
KuB4
15m
48m
BH2
KUlun
BH1
51m
34.7m
52m
44m
KuB2
KuB1
Bulenge/Wa
Geotechnical Report
Page 8
APPENDIX B
Geotechnical Report
Page 9
Table 3:
Location
Foundation Soil
Soil Thickness
Proposed Foundation
Allowable Bearing
Depth
Pressure
Pressure
BH 1
9.3m
9.3m
1267kN/m
422 KN/m
BH2
6.4m
5.7m
1267KN/m
422KN/m
Geotechnical Report
Page 10