Professional Documents
Culture Documents
PUMPLINES
Getting safe and durable pipelines.
By Joe Nasvik
Determining how best to set up a pumpline system for concrete isnt usually the concrete
contractors responsibility; you leave it to the experts. Its one of those details the concrete
pumping contractors usually cover as part of their scope of work. But like everything in
concrete construction, contractors should know the basics for all aspects of the work.
Setting up a pumpline can be as simple as rolling out a small diameter hose on a jobsite and
connecting it to a concrete pump. But it can also be as complicated as placing concrete 1000
feet above ground, running it through bends cast into thrust-blocks, and stand pipes
expanding and contracting several inches per day while being secured to the structure. The
latter requires careful planning.
Closely related to the success of a pumping system is the concrete mix. The mix and the line
must be compatible so placement can proceed in a straightforward manner. Pumping
companies and those who design pumpline systems often have little voice in the design of
mixes; the project requirements for concrete govern that. But communication is necessary
to achieve a good delivery system. Steel pipes, or slicklines, must be the proper size and the
proper type of pipe with the right wear properties in relation to the concrete mixes to
achieve good productivity at the right price.
Safety is always a consideration, too. A plugged line can result in high line pressures, putting
everyone nearby at risk. Safe pumplines involve both the proper design and safe work
practices.
must be set up. Foundation contractors often prefer flexible hose instead of slickline for this.
Kyle Rask, director of safety and risk management for Brundage Bone, Kent, Wash., says
400 to 500 feet is about as far as you can reach with a flexible line.
Commercial applications can be more complex. Depending on the experience of the
contractor or pumping company, a pumping consultant is sometimes involved when
specifications are being developed, when contractors are bidding the job, or when its close
to the start of construction. High-rise buildings require the most expertise. John Schantz,
chief engineer for ConForms, Port Washington, Wisc., a supplier of abrasion-resistant
piping systems, says its because on commercial projects, concrete is typically pumped
longer distances and at higher pump pressures.
Projects placing higher concrete volumes require additional planning for pumplines.
Schantz says his company provides pumpline design as part of what they offer a client, with
high-rise projects being a large percentage of this work. One of the first considerations is
how long the pipe needs to last. Lines on big projects can be in place for a long time and
contractors dont want to replace them while a job is in progress. Selecting the type of pipe
to use depends primarily on the amount of concrete yardage involved and the type of
aggregate being usedwear is considerably higher in some parts of the country due to local
aggregates. Pipe wear can be up to five times more depending on a projects location,
Schantz adds. The pressure required to move concrete to the point of placement is also a
factor. In a typical 5-inch standpipe, moving concrete 1 vertical foot requires approximately
1.1 pounds of pressure. Pumping concrete 1000 vertical feet therefore requires a minimum
pressure of 1100 psi.
Once wear and pressure factors are calculated, a decision can be made on the type of pipe.
Brown says pipe is often selected based on its expected life, the goal being to choose pipe
that will last through the project but wear out by the end. The highest wear, highest pressure
pipe is induction heated, single wall pipe and couplings, used for high-rise construction
projects. It can handle pressure up to 5000 psi and beyond.
Twin-wall pipe is the most wear-resistant and is commonly used on boom trucks and
placing booms. But its rated as low-pressure pipe, typically operating at pressures below
1250 psi on booms. The inner layer of this pipe is harder, more brittle steel and therefore
more wear-resistant, while the outer layer is softer and more ductile.
Projects such as high-rise buildings require riser pipelines to be permanently anchored to
the structure for the duration of a project. Pipe bends or sweeps are secured by casting them
through concrete thrust blocks, preventing the pipe from moving due to the forces of the
concrete moving in the line.
Its also common for high-rise projects to include placing booms, often mounted on top of
self-rising core-forming systems. Buildings with larger deck structures may have two or
more placing booms, so included in the installation might be diversion valve systems at
ground level, directing concrete from one standpipe to another, adding to the complexity of
a system.
Designs for pumplines intended to remain in place for the life of a project, such as high-rise
construction, must also include ways to clean the line and dispose of the concrete. A 100foot long section of 5-inch line holds about 1/2 cubic yard of concrete. By the time the One
World Trade Center project in New York City tops out, filling the slickline to deliver
concrete will require about 10 cubic yards of concrete. The usual way to empty the line after
a placement is to include a diversion valve to empty the line back into a ready-mix truck.
Cleaning uses compressed air, blowing out the standpipe from above.
During all this activity there sometimes isnt much thought given to safety. The objective is
more one of fix the problem now, and think about safety later. The better approach is to
conduct safety training sessions, carefully plan for pumpable concrete mixes, make
knowledgable decisions on line design, and have experienced pump operators. All of this
taken together is the proactive way to the best outcome.
When thinking about pump safety, consider the following:
Pumps are built to deliver constant volume. When a line plugs, pump pressure
instantly spikes to the pumps maximum capacity in order to keep output volume constant.
Pump operators must constantly monitor line pressure. When problems arise, line
Workers should work with their back to the pumpline whenever possible.
Workers should remain a reasonable and prudent distance away when air is
introduced into a pumpline for any reason. Wait until a steady flow of concrete resumes.
Position a laborer at the hopper when the pump operator is at the point of placement
to be sure lumps, foreign material, and air doesnt get into the hopper due to low concrete
levels.
A small number of project owners still specify unsafe practices, especially regarding
boom pumps. Address any issues before a job starts.
Pumps near excavations should be located at least 1 foot away for every vertical foot
of drop.
Workers must have stable footing near hose ends when placing concrete.
The American Concrete Pumping Association (ACPA) suggests that the operator on your job
be ACPA certified. Certified operators must complete an intense ACPA safety training
program that includes special emphasis on the hazards of air getting into the delivery
system (see A Word About Hose Whipping). ACPAs website, has a special Contractor tab
with free downloadable safety information.
When we think about concrete pumping we automatically focus on the concrete pump.
There isnt anything romantic about pumplines; they are just a collection of tubes. But
pumplines are the delivery mechanism contractors works with. They are carefully designed
to provide good, safe service with few problems. When all goes well, its natural not to think
about themthats the way it should be.
http://www.concreteconstruction.net/products/how-to-specify-and-use-concretepumplines_o