You are on page 1of 4

September 15,

2015

PROPOSAL FOR THE CONSTRUCTION OF TWO STOREY RESIDENTIAL


To: Sir Jun Rivera
Angeles, Pampanga
Dear Sir,
As per request we are submitting our formal quotation to the following transaction
for your consideration.
SUBJECT:
Supply of labor & some necessary tools to be used in erection of two storey
residential, approximate 267.62 square meters. Roughin in only with complete roofing,
without ceiling, and installation of propose electrical , plumbing and storm drainage.
Plastering inside is included.
Scope of works on the other page.
Total Amount cost of labor Php. 1,284,571

TERMS AND CONDITIONS;


13% Down payment, for mobilization of project.
And balance, base upon weekly progress billing.
Duration time: For 92 working days
Therefore, through this proposal we gladly hope to be of service to you soon.
Thanks and God Bless!

Respectfully yours,

(Roman) Alipio S. Gatto Jr.


685. Galanto Compound.
Sta. Quiteria,
Caloocan City

SCOPE OF WORKS

1. Lay-out of 19.80 meters X 29.80 meters.


2. Excavation of 26 holes for columns (foundation) & tie beam.
3. Fabrication of reinforcing bars putting (columns) & stirrupt.
4. Installation of assemble reinforcing bars columns.
5. Concrete pouring of putting (columns).
6. Installation of reinforcing bars tie beam.
7. Concrete pouring of tie beams around with dowels.
8. Concrete pouring of columns.
9. Installation of Scup holdings around.
10. Laying of C.H.B around 6 & partitions 5"
11. Concrete pouring of columns.
FORM WORKS SECOND FLOOR
12. Installation of Zippo & Runner for beams around.
13. Fabrication of form works for siding of beams.
14.
Fabrication & Installation stirrupt of beams around & partitions.
15. Installation form works slab second floor
16. Installation reinforcing bars slab, cross wise with bottom bar and top
bars
17. Installation extra bars of beams L/4 & L/5 & dowels.
18. Also installation of P.V.C pipe for electrical purposes.
19. Installation of P.V.C pipe & for water line purposes
20. Concrete pouring of slab, second floor with 4 thick.
21. Laying of C.H.B. # 5 around & 4 thick CHB partitions (second floor)
22. Installation of stirrupt & assemble of roof beam around including
partitions.
23. Installation of all door jambs. Ground floor and second floor (15
Units).
24. Concrete pouring of ground floor.
25. Assemble & Concrete pouring of stairway to second floor without
railings.
26. Fabrication & Installation of steel trusses ground floor & second floor

NOTE: No finishing of flooring ground floor & second floor.

QUANTITY OF MATERIALS
365 pcs. 16 mm x 7.5 mts. 40 PSI
450 pcs. 16 mm x 6 mts. 20 PSI
650 pcs. 12mm x 7.5 mts.
1,750 pcs 10 mmA
400 pcs. 10 mm x 6 mts.
250 pcs. Kilos G.I wire 1/16
85 Cub. Mts. White sand
20 Cub Mts. White Sand
20 Cub Mts. Gravel G.I
15 Cub Mts. Gravel 3/4
2100 Bags Portland cement
110 pcs. Angle Bar- x2x2
40 kilos. Welding Rod 6013
15 Units Door Jambs In different Sizes
2,300 C.H.B. #6
1,500 C.H.B. #5
20 pcs. P.V.C. Pipe #6 Neltex
21 pcs. P.V.C. Pipe #4 Neltex
15 pcs. P.V.C. Pipe # 2 Neltex
120 pcs. P.V.C. Pipe # orange
30 pcs. Long elbow
30 pcs. P.V.C. Moldex Blue
15 pcs. Moldex Blue
20 pcs. y 4 x 4
20 pcs. y 4 x 2
20 pcs. Elbow 4
10 pcs. Elbow 4 45 degrees
6 Clean out 4
8 pcs. Clean out 2
50 pcs. Elbow Blue
25 pcs. Tee Blue
15 pcs. Elbow
10 pcs. Tee
6 Quarts Solvent Cement
70 pcs. x 4 x 8 Plywood
15 pcs. x 4 x 8 Plywood
500 pcs. 2 x 4 x 10 Cocolumber
600 pcs. 2 x 3 x 10 Cocolumber

4
5
1
1

Box C. Wnail #4 50 kilos


Box C. Wnail #3 50 kilos
Box C. Wnail # 2
Box. C. Wnail 1