You are on page 1of 20

Daily Site Report

Site:

Haydaria 4xGE Fr.9E Gas Power Plant

Date:
No.

15-Feb-12
29

Clear

Cloudy

Rain Temp. ( C ): - Min.11 Max. 20

PERSONNEL ON SITE
CONTRACTOR/SUBCONTRACTORS
Scope/
Area of Responsibility

No.

Name of Cont./Sub Cont.

TBC

prefabricated building company

Muntather office

Engineer

Technician

site camp

11KV line

site camp

Total

EQUIPMENT
(Identify by contractor/subcontractor. Use the No. from above)
Sub No.

Equipment

hrs./day

Daily- shift
water tanker (3) , compactor ,shovel

Day-shift
10

Daily- shift

Day-shift

Daily- shift

Day-shift

2
3
Not: Use the following abbreviation:

WORK PERFORMED TODAY


(Identify contractor/ subcontractor by number, from subcontractor section)

Sub No.

Feature and description

Location

TBC

site camp

prefabricated building company

site camp

Muntather office

11KV line

Max. 20

Worker

Total

12

21

10

24

37

hrs./day

Location

site camp
site camp
11KV line

This Day Activity


Section

No.

Job description

Eng. in charge

No. of
Persons

Actual
working
hours

civil Activities

Storage area
supplying sub base for storage area ( now are stopped ).
spreading and leveling sub base for storage area .
wetting & compacting for storage area.
Public toilets and sub tanks building
continue buildings .

Caravans installation
continue caravans installation , install walls and doors for caravans bedrooms.

soil investigation
receiving the comments from Dr.Saffa about soil investigation report.

1
2
3

Electrical Activities

Eng.Wissam
Eng.Ali Omran
surveyor Karar

95
90
75
30

17

Eng.Shawkat

Receiving 11KV materials


1

receiving materials for installing 11KV feeding line to site ( remaining only from underground cable )

95

Civil works for 11KV line installation


continue excavation works for poles

55

Testing 11KV materials


samples of poles and cable had send to Baghdad

50

Other electrical works


lighting the site storage containers , today are Purchased 2 projectors ( spotlights) from local markets for this purpose.

Documents

Site storage containers


inventory and arrangement the contents in storage containers.

Eng.Ali Hanoon

admin.Hamza, admin.Jafar

Progress
Plan

Man
Power

Actual

Start

Finish

Start

1/23/2012
1/25/2012
12/28/2011

2/4/2012
2/6/2012
1/20/2012

1/23/2012
1/25/2012
12/28/2012

1/28/2012

2/12/2012

2/4/2012

2/7/2012

3/29/2012

2/7/2012

12/9/2011

2/15/2012

12/9/2011

1/3/2012

1/25/2012

1/4/2012

1/26/2012

2/18/2012

2/4/2012

1/23/2012

1/30/2012

2/7/2012

Finish

Remarks

Next Day Activity


Section No.

Job description & comments

Eng. in charge

Manpower

Civil Activities
1
2
3

compacting sub base for storage area .


continue building works for public toilets foundation and sub tanks ( installing walls ).
continue caravans installation works in site.

Electrical Activities
1
2
3

waiting for receiving remaining materials of 11KV feeding line from contractor( underground cable).
continue civil works for installing 11KV line from tire plant to site area by contractor.
installing 2 projectors ( spotlights ) in site .

Working
Hours

Progress
Plan
Start

Remarks
Finish

No.
1
2
3
4
5
6
7
8

Materials description
Purchased Materials from local markets
projectors
Concrete bricks

Arrived Materials

1
2
3
4
5
6
7
8
9

QTY
2 pieces
500 pieces

Remarks

No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19

Visitor Name

Visitor Position

Reason of visit

Visitor remarks

Daily Site Report

Site Manager Comments:

Advisor Comments:
Project Manager Comments:

Project Operation Comments:

Business & Operation Director Comments:

No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

Employee name

Accidents discretions

Remarks

SUMMARY OF INSPECTIONS PERFORMED TODAY


PROJECT QUALITY CONTROL INSPECTION
Preparation Inspection (Identify feature of work attach Minutes of Meetings and Inspection report):
Initial Inspection (Identify feature of work attach Minutes of Meetings and Inspection report):
requirements,and corrective
actions taken when deficiencies are noted and attached Inspection Report ):

SPECIALIZE INSPECTION
TYPE

FEATURE

OBSERVATIONS

Follow
up
Civil
work
Follow
up
Mechanic
al
Follow
up
Electrical

CORRECTIVE
ACTION

SUMMARY OF INSPECTIONS PERFORMED TODAY

TYPE

SPECIFICATION REFERENCE

TEST RESULTS

CIVIL MATERIALS RECEIVED AT BATCH PLANT


Description

Qty.

Gravel
Sand
Sub - base
Cement KSA
Added Materials

1400 m
900 m
2000m
110 T
4'000 L

Inspection #
OK
OK
OK
OK
OK

Accept/Reject

Accept
Accept
Accept
Accept
Accept

TBC Schedule Progress


Progress Work for the Activites Identified by Primavera Schedule
MATERIALS RECEIVED TODAY
Description

Qty.

Inspection #

Submittal Reference

Accept / Reject

SUBMITTALS TODAY
Item

Specification Reference

Action Taken

SAFETY REPORT
FIRST AID
None
ACCIDENT
None
DOCTOR CASE Toothache , Eczema & Headache
1-Safety glasses .

TRAINING (OJT) 2-Alecture on and the proper use of electric tools .

SECURITY STATUS
ACTIVITY

The security status at site is good.

DIRECTIONS.MISCELLANEOUS REMARKS FROM CLIENT


(verbal instructions received or given by MOE personnel)
CONFLICTS WITH PLANS OR SPECIFICATIONS

I Certify that the above report is a true and accurate record . All material and equipment used
,work performed and tests conducted during the period covered by this report were in strict
compliance with the contract plans and specifications,expect where noted above.
Prepared
Date
Site Planning and Scheduling
Date
Site Project Manager
Date
Attachment List:
Attachment A:

Photos.

You might also like