Professional Documents
Culture Documents
Civil Engineers
Ground Improvement 162
February 2009 Issue GI1
Pages 314
doi: 10.1680/grim.2009.162.1.3
Paper 800013
Received 01/11/2006
Accepted 12/03/2008
Keywords: embankments/railway
systems/rehabilitation, reclamation
& renovation
Arul Arulrajah
Senior Lecturer, Civil
Engineering, Faculty of
Engineering and Industrial
Sciences, Swinburne
University of Technology,
Melbourne, Australia
Affendi Abdullah
Technical Consultant,
Ranhill Consulting, Kuala
Lumpur Malaysia
Myint Win Bo
Director (Geo-Services),
DST Consulting Engineers Inc.,
Ontario, Canada
Abdelmalek Bouazza
Associate Professor,
Department of Civil
Engineering, Monash
University, Melbourne,
Australia
CEnv
P
Pall coll
s
T
Th
t
U
Us
Up
v
imp
c
f
all col
fcol
creep col
h
v9ert
d col
u col
9
c
d col
d comp
u comp
d soil
s
u col
u soil
1. INTRODUCTION
The electrified high-speed railway project runs between
Rawang in the state of Selangor and Bidor in the state of Perak
in Peninsular Malaysia over a total length of 110 km. Figure 1
indicates the location of the project site in Peninsular Malaysia.
The geotechnical design of the project includes ground
improvement of the existing foundation to sustain the imposed
dead and traffic loads for train speeds of up to 160 km/h. The
clients design requirements are a maximum post-construction
settlement of 25 mm in six months and a differential
settlement of 10 mm over a chord spanning 10 m. In addition,
the degree of consolidation to be achieved is not to be lower
than 8590%. The required minimum long-term factor of
Arulrajah et al.
KELATAN
IPOH
PENANG
PERAK
RA
ST
OF
KUALA
LUMPUR
RA
ST
S
IT
PAHANG
S
IT
MA
SELANGOR
OF
CC
LA
MA
A
SINGAPORE
CC
LA
A
PENINSULAR
MALAYSIA
2. VIBROREPLACEMENT WITH
STONE COLUMNS
Vibro-replacement with stone
columns is a subsoil
RAWANG (km 3555)
improvement method in
which large-sized columns of
KUALA LUMPUR
coarse backfill material are
installed in the soil by means
of special depth vibrators.
The stone columns and the
intervening soils form an
integrated foundation support
system having low
compressibility and improved
load-bearing capacity. Vibro-replacement with stone columns
allows for the treatment of a wide range of soils, from soft
clays to loose sands, by forming reinforcing elements of low
compressibility and high shear strength. In addition to
improving strength and deformation properties, stone columns
densify in situ soil, rapidly drain the generated excess pore
water pressures, accelerate consolidation and minimise postconstruction settlement. Normally the columns fully penetrate
the weak layer with the result that the stone column and
natural soil combination develops greatly enhanced bearing
capacity and reduced compressibility characteristics. The
method is an ideal solution for use in embankments as it
negates the effect of a hard point. The dry or wet method of
installation can be used depending on the proximity to the
existing railway track and water sources. The size of the
vibrator is around 40 cm and penetration of the vibrator into
the ground with water jetting will result in a hole of diameter
5060 cm being created. An annular space is created between
the vibrator and the hole through which the stone is fed to the
compaction point. The up and down motion of the vibrator is
used to laterally displace the stone into the ground and at the
same time compact the stone column. This will result in the
creation of the required diameter of column. Figure 2 presents
Arulrajah et al.
portion of the load, m9, which depends on the area ratio, Acol /A,
and the final improvement factor n2 . The process described
below has to be repeated for each of the various soil layers
Th 0:044
Us
Up
04
06
08
10
00001
E1/E2 40
Barrons solution
Biot theory
10
de
d
Rigid
E1 E2 Raft
v1 v2
kh
Smooth Rigid
v1 03, v2 03
0001
001
c rt
Th
d 2e
01
10
02
m9 n2 1=n2
Arulrajah et al.
100
Friction ratio: %
1
2
3
4
10
11
Depth: m
11
12
Depth: m
9
10
Depth: m
Depth: m
10
11
9
10
11
12
12
12
13
13
13
13
14
14
14
14
15
15
15
15
16
16
16
16
17
17
17
17
18
18
18
18
19
19
19
19
20
20
20
20
Figure 4. Plot of typical pre-treatment CPT result at stone column location (chainage 352130)
Embankment
CL
4950
4950
Min. 5000
New track
Rehab. track
CL
15
1
CL
50%
15
1
1000 mm
300 mm sub-ballast
2
3000
50%
Formation
1 m compacted
sand blanket
1000 mm
stone column
Embedded in
SPT N 10
5000 mm
max.
Soft/loose
material
Dense layer
W
Figure 5. Schematic of stone column treatment scheme for new alignment comprising two new tracks (dimensions in mm)
Arulrajah et al.
S
Embankment
CL
4950
1 m compacted
sand blanket
Min. 5000
4950
New track
Rehab. track
CL
CL
1000 mm
300 mm sub-ballast
15
1
2
1
15
1
50%
Existing
ground
50%
Fill
Formation
Soft/loose
material
Embedded in
SPT N 10
Existing
ground
1000 mm
stone column
Dense layer
S
W
Figure 6. Schematic of stone column treatment scheme for partial width treatment next to the existing railway track
(dimensions in mm)
Crane
Crane tracks
Firm fill
Dial gauge
Top of sand platform
Jack
Reference
beam
Sand blanket
15 m 15 m plate
Sand blanket
1 m nominal diameter
stone column
Figure 7. Schematic diagram showing single column plate load test set-up
Arulrajah et al.
00
320
05
45 line
280
15
20
211 mm
25
30
35
40
42 mm
45
50
40
20
80
60
120
100
160
200
240
280
320
140
180
220
260
300
Load: kN
Settlement (i): m
Settlement: mm
10
240
200
160
Embankment height: m
120
120
60
55
50
45
40
35
30
25
20
15
10
05
00
280
320
30
60
90 120 150 180 210 240 270 300 330 360 390
Time: days
(a)
50
Settlement: mm
200
240
Settlement (i 1): m
100
150
200
250
300
30
60
90 120 150 180 210 240 270 300 330 360 390
Time: days
(b)
well in the area in which they were installed and within the
predictions made at the design stage.
3. DRY DEEP SOIL MIXING (CEMENT COLUMNS)
Dry deep soil mixing (DSM) technology is a development of the
limecement column method. It is a form of soil improvement
involving mechanical mixing of in situ soft and weak soils
with a cementitious compound such as lime, cement or a
combination of both in different proportions. The mixture is
often referred to as the binder. The binder is injected into the
soil in a dry form. The moisture in the soil is utilised for the
binding process, resulting in an improved soil with higher
shear strength and lower compressibility. The removal of the
8
160
Arulrajah et al.
mc
mE
Clayey silt
Silty clay
Clay
Organic clay
Peat
Silty, clayey sand
0.80.9
0.8
0.70.8
0.60.7
0.6
0.9
150200
150200
150
100
5075
200250
11
12
Pall col
imp
0:5
c v9ert tan()
u col cu col
Soil description
15
10
17
18
Arulrajah et al.
19
20
where Ecol and Esoil are Youngs modulus; cu col and cu soil are
undrained cohesion; cd col and cd soil are drained cohesion;
u col and u soil are undrained angle of friction; d col and
d soil are drained angle of friction of the column and in situ
soil, respectively; and a is the area replacement ratio calculated
as a (Acol /s 2 ) for square grid pattern of spacing, s. In the
calculations it can be assumed that the settlements will be
equal in the soil and in the stabilised columns to ensure
compatibility.
3.2. Dry deep soil mixing installation
The results of soil investigation at the treatment area revealed
the presence of a wide range of soils along the track, ranging
from very soft silty clay or clayey silt to loose silty clayey
sand. 11 Figure 11 shows a typical CPT plot at the DSM
treatment location.
Deep soil mixing treatment was used to treat soft soils over an
800 m length of the railway line. Over 50 000 linear metres of
0.6 m diameter columns were installed at the site to depths of
614 m. 11 The embankment heights in the DSM treatment
areas varied between 1.53 m. Column spacing generally
ranges between 1.01.5 m. Typically the spacing of the column
grids (square/rectangle) varies between 1.01.3 m centre to
centre under the location of the proposed rail tracks and 1.4
1.5 m centre to centre in the remaining area underneath the
000
0
Friction ratio
Fs/Qt: %
Local friction
Fs: kN/m2
000
20000
000
1000
Pore pressure
Pw: kPa
10000
50000
Depth: m
10
12
Maximum depth 1100 m
Figure 11. Plot of typical pre-treatment CPT result at deep soil mixing location (chainage 341690)
10
Arulrajah et al.
1490 m
50 m
Ridge
25 m CL 25 m
262 m
262 m
New track
Rehab. track
CL
CL
Working
platform
Embankment
Existing
ground
06 m dia.
cement
columns
Treatment 2290 m
Figure 12. Schematic of dry deep soil mixing treatment scheme (Raju 11 )
Kentledge blocks
Settlement: mm
Grillage beams
30
60
Time: days
90
120
150
180
210
20
10
0
10
20
RSG-3
Sand blanket
Cement
columns
20
40
Load: t
60
Lateral displacement: mm
5
25 20 15 10 5
0
10
0
15
20
25
4
80
100
120
Depth: m
0
2
Settlement: mm
RSG-6
8
12
16
4
20
6
24
I-1
8
10
Load cycle 1
Load cycle 2
I-2
I-3
Arulrajah et al.
11
5. REMOVAL/REPLACEMENT
This method is possibly the most widely used and economical
treatment option for improving the presence of shallow soft
soil deposits. The removal and replacement method was used in
the project at locations where there was soft cohesive material
present. The unsuitable materials were removed from the site
and the excavation trench and they were replaced with suitable
fill materials, which were subsequently compacted. 5 Excavation
to depths greater than 2 m may require temporary protection
methods such as the use of temporary sheet piles. Non-woven
geotextiles were provided as a separation layer at the base of
the excavation works to ensure an effective separation between
the in situ soils at the base of the excavation and the suitable
fill. Figure 19 shows a schematic drawing of the removal and
replacement works.
6. CONCLUSION
In this paper, the various ground improvement techniques used
in a major high-speed railway project in Malaysia have been
discussed.
CL Embankment
4950
Min. 5000
4950
New track Rehab. track
300 mm sub-ballast
CL 15
15 CL
1
1
3000
50%
50%
Formation
Fill
1
1
2 Layers of high strength
2
2
geogrid, Kg 400/200
150 mm sand
Detail A
5000
Soft/loose
material
250 250 mm
RC square pile
at designed spacing
Dense layer
250 250 precast RC piles (Grade 45) at designed spacing
Direction of track
300 mm
crusher run
Geogrid, kg 400/200
Top and bottom layer 200 kN/m
along the track
1000 overlapping
150 mm sand
Varies
250 mm 250 mm
precast
RC piles Grade 45
Geogrid, kg 400/200
Detail A
12
Arulrajah et al.
Piled transition
with individual
pile cap
Bridge works
865 m
10 m overlap of
10 m
top geogrid
5 m Individual pile cap
800 800 350 mm
750 mm
Geogrids
Continuous slab
1m
400 mm
L1
L1
L1
L1
L1
L1
L1
L1
L1
L1
1m
L2 6 m
Articulated slab
L2 6 m
Civil works
S 15 m
RC piles
5 pile spacing 75 m
Civil works
Piled transition
with individual
pile cap
Bridge works
Articulated slab
Abutment
RC piles with
individual pile caps
750 mm
5 pile spacing 75 m
Figure 18. Schematic diagram showing bridge approach transition using geogrid-reinforced piled embankments
Embankment
CL
4950
1500 or D
(whichever is greater)
2
1
Min. 5000
Slope to
suit site
condition
300 mm sub-ballast
2
3000
Formation
2
Existing
ground level
Standing
water level
4950
Track embankment
5000 mm
max.
2
1
Base of excavation
OGL
D
Slope
to suit site
condition
Figure 19. Schematic diagram showing typical cross-section of removal/replacement works (dimensions in mm)
have been discussed. The results from numerous load tests and
settlement plates indicate that the stringent performance
requirements of the new railway project were met.
Ground improvement by means of dry deep soil mixing allows
for the treatment of a wide range of soils, ranging from soft
clays to loose sands by forming stronger reinforcing elements
of low compressibility and high shear strength. In this paper,
the design methodology, installation methodology, load testing
and field instrumentation for dry deep soil mixing for railway
Ground Improvement 162 Issue GI1
Arulrajah et al.
13
6.
7.
8.
9.
10.
11.
REFERENCES
1. PRIEBE J. H. The design of vibro replacement. Proceedings
of the Institution of Civil Engineers, Ground Engineering,
1995, Technical paper GT 037-13 E 3137.
2. ARULRAJAH A. and AFFENDI A. Vibro replacement design of
high-speed railway embankments. Proceedings of the 2nd
World Engineering Congress, Kuching, Malaysia, University
Putra, Malaysia, 2002, 157164.
3. BO M. W and CHOA V. Reclamation and Ground
Improvement. Thomson Learning, Singapore, 2004.
4. BALAAM N. P. and BOOKER J. R. Analysis of rigid rafts
supported by granular piles. International Journal of
Numerical and Analytical Methods in Geomechanics, 1981,
5, No. 4, 379403.
5. ARULRAJAH A., ABDULLAH A. and HAR L. Y. K. Geosynthetic
applications in a high-speed railway project. Proceedings of
12.
13.
14.
14
Arulrajah et al.