17-Aug-15
DESCRIPTION
UNIT
PRELIMINARY PARTICULARS
1.1
Funding
The funding shall be provided by the Guyana Power & light Inc., of
40 Main street, North Cummingsburg, Georgetown.
1.2
Engineer
The Engineer shall be the Civil Engineer - Administrative Department,
Guyana Power & Light Inc.
1.3
Contract
The Bills of Quantities have been prepared in accordance with the
General Conditions of contract, Form of Tender and Agreement.
The Conditions of contract should be carefully read as such conditions
may have a considerable bearing on the tender.
1.4
Quantities
The quantities shown in Bill Nr. 3 have been measured net, as fixed
in position, and the bidder shall allow in his prices for waste, laps,
etc. The quantities given are thus generally not suitable for the
ordering of materials.
1.5
Provisional Sum
The term 'Provisional Sum' shall mean a sum provided for works or
for costs which cannot be entirely foreseen, defined or detailed at
the time the tender documents are prepared. Such sums shall be
used in whole or in part as directed by the Engineer & shall be
deemed to be inclusive of any profit required by the contractor,
unless otherwise indicated.
1.6
Description of Site
The site of the proposed works is located at the new Bartica
Commercial Office
1.7
Description of Works
Construction of concrete, chain link mesh and razor wire fence
measuring approximately 182ft to secure the ISPS designated area at
GPL's Kingston Compound
1.8
QTY
RATE
TOTAL
17-Aug-15
NO.
DESCRIPTION
UNIT
QTY
RATE
TOTAL
GENERAL MATTERS
Allow for the following General Matters in the Unit Rates of Measured
Work.
A.
B.
C.
D.
E.
F.
G.
H.
3.0
TEMPORARY WORKS
Allow for the following Temporary Works, constructed to the
Engineer's satisfaction, and for dismantling and removing
from site on completion.
A.
Toilet & Washing facilities for GPL supervisor and Contractors staff.
Sum
B.
Mass area for workers and barrier to prevent persons from coming
into contact with the works.
Sum
C.
Sum
D.
Sum
E.
Sum
F.
Sum
G.
Sum
H.
2 4
TEMPORARY WORKS TO SUMMARY - PG
Prov.Sum
Not Applicable
Not Applicable
20,000
17-Aug-15
NO.
DESCRIPTION
UNIT
QTY
RATE
TOTAL
OTHER MATTERS
Allow for the following Insurance's:
(1) Contractor's All Risk Insurance
The Insurance must be for the entire contract period.
(Construction Period + Defects Liability Period)
Prov.Sum
40,000
Prov.Sum
40,000
Prov.Sum
40,000
B.
Prov.Sum
40,000
C.
Prov.Sum
40,000
Not Applicable
D.
Sum
E.
Allow for clearing the site of all vegetation, trees and shrubs and
maintaining same during the execution of the project.
Sum
F.
Sum
G.
Allow for the safety and health of workers and keep on site an
adequate First Aid Kit.
Sum
17-Aug-15
NO.
DESCRIPTION
UNIT
1.0
Preliminary Particulars
2.0
General Matters
3.0
Temporary Works
4.0
Other matters
QTY
RATE
TOTAL
17-Aug-15
DESCRIPTION
UNIT
GENERALLY
II
III
IV
II
Use of mechanically operated plant for the time engaged in the work.
No allowance mace for idle time.
QTY
RATE
TOTAL
17-Aug-15
NO.
DESCRIPTION
UNIT
QTY
RATE
TOTAL
OVERHEADS
Overheads for the purpose of the Contractor shall mean the following:
Head office charges
Site supervision and site charges
Time loss due to inclement weather
Bonus or other incentive payments
All other liabilities and obligations whatsoever
II
B.
PRIME COST
Including the following sums for works which may be executed as day
work.
Materials
Prov Sum
II
III
Labour
IV
Plant
VI
25,000
%
Prov Sum
25,000
%
Prov Sum
%
20,000
UNIT
QTY
Excavate trench for strip foundation not exceeding 6' deep and
dispose of material as directed by the Engineer.
cu. Yd
10
3.2
sq yd
10
3.3
Sum
3.4
sq yd
10
sq yd
10
3.6
Level and compact white sand in layers of 4" to receive floor slab
cu. Yd
3.70
cu. Yd
3.8
Concrete Works
Provide and place 3000psi reinforced concrete (19mm
cu yd
cu yd
cu yd
cu yd
cu yd
3.2
2.5
1.8
0.8
2
Sq Yd
Sq Yd
Sq Yd
Sq Yd
6.5
35
18
12
lbs
lbs
lbs
lbs
lbs
450.00
575.00
375.50
675.72
70.00
3.1
3.5
3.8.1
3.8.2
3.8.3
3.8.4
3.8.5
DESCRIPTION
Ditto foundation
Ditto Columns
Ditto Beams
Ditto Ground Floor Slab
Ditto First and Second Floor Slab
3.90
Formwork
Provide and place fair faced finish formwork (including all braces,
3.9.1
3.9.2
3.9.3
3.9.4
Ditto foundation
Ditto Columns
Ditto Beams
Ditto First and Second Floor Slab
3.10
Reinforcement
Provide for rebar as indicated in drawings. Laps to be 40d and
Ditto foundation
Ditto Columns
Ditto Beams
Ditto Floor Slabs
Ditto Curb Wall
3.10.1
3.10.2
3.10.3
3.10.4
3.10.5
RATE
AMOUNT
3.11
Provide and place No 65 BRC fabric to Ground Floor Slab, include for
a minimum lap 6" lap.
Sy
3.12
Provide and place DPM fabric to Ground Floor Slab, include for a
minimum lap 6" lap.
Sy
3.13
Block Work
Provide for the laying (stretcher bond) of 6" x 8" x 16" HCB blocks for
curb wall. Blocks to be laid with 12mm joints to all sides. All cores to
be filled with concrete and reinforce with 10mm HT rebar to every
other core. (reinforcement measured separately)
sq yd
10.00
3.14
METAL WORK
Ly
20
Ly
Ly
25
Nr
washer.
Nr
16
3.14.6
Nr
16
3.14.7
Metal work in mild steel R.H.S; etch and two coats zinc chromate
primer after fabrication.
3.14.1
3.14.2
2" dia. Galvanized pipe post support welded to hand rail and base
steel plate.
3.14.3
2" dia. Galvanized pipe welded together to for ladder 12" wide from
top of hand rail to base of trestle fixed to beams.
3.14.4
6" x 6" x 1/4" thick base plate holed four times for 1/2" diameter
Anchor bolts 1/2" diameter x 3" long cast in concrete, with nut and
TO BILL SUMMARY
CLIENT:
MAIN SUMMARY
Bill No.
Description
BILL NR 1 - PRELIMINARIES
CONTINGENCY
Total
50,000
TOTAL