Professional Documents
Culture Documents
6.0
RISK MANAGEMENT
Risk management is the most extensive and indispensable part of project
management. The risk must be perceived by the task project manager
keeping in mind the end goal to distinguish the underlying drivers of risk of
the undertaking as to follow the results towards the achievement of the
venture. Furthermore, risk management is considered as a systematic way
of identifying, analyzing and responding to risks in order to achieve the
project objectives. It is essential from the early stages of a project as major
decisions such as choice of alignment and selection of construction
methods can be influenced. According to Smith (1999), the process of risk
management may be defined as identification of risk, analysis of the
implications, response to minimize risk and allocation to appropriate
contingencies. Risk management is an iterative process in which the
effectiveness of control actions is constantly evaluated, new risks are
discovered, and existing risks are reassessed. This process continues until all
the risks are closed or the project is completed. Risk management process
can give improvement of construction project management processes
and effective use of resources as well as minimizing cost impact, schedule
delays, other issues impact that could delay the project progress. Risk
management process is the basic principle of understanding and
managing risks in a project. It consists of the main phases which are
identification, assessment and analysis, and response (Smith et al. 2006) as
shown in Figure 1 below:
75
Risk analysis
Risk identification
Risk control
Risk review
Risk response
risk
management
process
involves
the
systematic
application
of
II.
III.
IV.
76
Risks
identification
List of potential
risks
Risk
analysis
Prioritized
risks list
Risk
planning
Risk
monitoring
Risk avoidance
& contingency
plans
Risk
assessment
Risk
Management
Plan
is
prepared
to
document
the
risk
Aim
Objective:
d) Maintain growth
e) Minimize the effects that a loss will have on other persons and on
society
6.3
As said over, this segment will further clarify the Risk Management Process of its
four stages and how it can be utilized as a part of overseeing risks inside of this
project.
6.3.1
Risk Identification
Significant Risks
Need for making an advertising effort
High staffing costs
Lack of operational and financial
79
planning
Insufficiently skilled staff
Design
Schedule
Technology
level
of
technological
has
not
been
profile
does
not
match
acquisition strategy
Supplier Capabilities
Management
risk
and
assessments
not
the
not
results
Customers
Environmental
Logistical
of
resources-particularly
6.3.2
Risk Evaluation
This process analyses each risk from the risk register in terms of its probability
and impact on the project if it were to occur. It should be performed as
soon as possible after risks have been identified so that appropriate time
and resources can be allocated to the more serious risks. It uses the
probability and impact matrix (PIM) to rank and prioritize risks, and this
81
information is placed back on the risk register. Like all the processes within
risk management, this one should be performed regularly because new
risks will be identified and the characteristics of existing risks may change as
the project progresses.
The inputs, tools and techniques, and outputs of this process are
summarized in the table below.
Table 6.2: The inputs, tools and techniques, and outputs of this risk
management process
Inputs
Data
gathering
Representation
Outputs
& Project
documents
updates
techniques
Cost management plan
Schedule
environment -
plan
Risk register
Enterprise
factors
Organizational
process -
assets
82
This is developed during process and will explain the overall approach that
needs to be taken to risk management on this particular project. It will detail
the amount of risk is acceptable and who should be involved in carrying out
the qualitative analysis of the known risks.
Element of risk
management plan
Budget
Definition of
probability &
Impact
Risk
management
activities
schedule
Definition risk
categories
Probability &
impact matrix
Stakeholder risk
tolerances
Risk Register
This is the central repository of all of the known risks that are to be analyzed.
These include industry studies of similar projects by risk specialists and risk
databases from industry or proprietary sources.
These will include the tools needed to carry out qualitative risk analysis,
policies, procedures and guidelines for risk management, and historical
information including lessons learned from previous projects.
Tool and techniques of Qualitative risk analysis
There are six tools and techniques that can be used:
Risk probability assessment investigates the likelihood that each specific risk will
occur, whereas risk impact assessment investigates the potential effect on a
project objective such as schedule, cost, quality, or performance.
Risk probability= likelihood each risk will occur
Risk impact = looks at potential effect on schedule, cost, quality or performance
Both the likelihood and impact are given a score according to the definitions
given in the risk management plan and these can be considered together to
provide a risk score. Risks with a high score will be given high priority while those
with a low score will be included on a watch list for future monitoring.
Evaluation of each risks importance and, hence, priority for attention can be
done using a probability and impact matrix as shown in table 6.3 below:
84
Threats
Opportunities
0.90
0.05
0.18
0.54
0.72
0.72
0.54
0.18
0.05
0.75
0.04
0.15
0.45
0.60
0.60
0.45
0.15
0.04
0.50
0.03
0.10
0.30
0.40
0.40
0.30
0.10
0.03
0.25
0.01
0.05
0.15
0.20
0.20
0.15
0.05
0.01
0.10
0.01
0.02
0.06
0.08
0.08
0.06
0.02
0.01
Impact
0.05
0.20
0.60
0.80
0.80
0.60
0.20
0.05
This specifies combinations of probability and impact that lead to rating the risks
as low, moderate, or high priority. The type of management response should be:
a)
Threats
I.
High-risk (shown in red boxes) are priority and need a hard line response.
II.
Low-risk (pink boxes) needs to have a contingency made for them & monitored
b)
Opportunities
I.
Red boxes show ones to pursue first as they offer the most benefit & are more easily
achieved.
II.
It is conceivable to rate a risk independently for expense, time, scope and quality.
Furthermore, it can create approaches to focus one general rating for every risk.
A general rating plan can be produced to mirror the association's inclination for
one target over another and utilizing those inclinations to add to a weighting of
the risk that are evaluated by goal.
85
This involves examining how well the risk is understood and the accuracy, quality,
reliability, and integrity of the data regarding it. If data quality is unacceptable, it
may be necessary to gather higher-quality data
Risk Categorization
The risk breakdown structure (RBS) is the normal way to help structure and
organize all identified risks into appropriate categories, and these will assist in
determining which aspects of the project have the highest degree of uncertainty.
Risks that are likely to occur in the immediate future require more urgent attention
than those that may occur later on in the project. Indicators of priority should
include the time required to affect a risk response. In some qualitative analyses
the assessment of risk urgency can be combined with the risk ranking determined
from the probability and impact matrix to give a final risk severity rating.
Expert Judgment
This would relate to experience of the probability and impact of typical risks for
projects of this type and could come from anyone with relevant experience.
Output of Qualitative risk analysis
This process will create the following output:
Qualitative risk
analysis output
Project
document
updates
then use the prioritized list of risks to focus attention on those items of high
significance to the most important objectives.
Risks grouped by categories - this can point to common underlying causes of risk,
which may in turn suggest a holistic approach to dealing with them. Discovering
concentrations of risk may also improve the effectiveness of risk responses.
List of risks requiring response in the near-term includes those risks that require an
urgent response and those that can be handled at a later date may be put into
different groups.
List of risks for additional analysis and response - some risks might warrant more
analysis, including Quantitative Risk Analysis, as well as response action.
Watch lists of low-priority risks - those that are not assessed as important in this
process can be placed on a watch list for continued monitoring.
Trends in the analysis results - as this process is iterative, trends for particular types
of risk may become apparent. This information can be fed back into the risk
management process.
6.3.2.2 Quantitative risk analysis
This is the process of analyzing the effect of those risks identified in the previous
process as having the potential to substantially impact the project. It may be used
to assign a numerical rating to those risks individually or to evaluate their
aggregate effect. In some projects it may be possible to develop effective risk
responses without this process. The availability of time and budget, and the need
for qualitative or quantitative statements about risk and impacts, will determine
which method(s) to use.
The inputs, tools and techniques, and outputs of this process are summarized in
the table below.
87
Table 6.4: The inputs, tools and techniques, and outputs of this risk management
process
Inputs
Data
gathering
Outputs
& Project
Representation
documents
updates
techniques
Cost management plan
Schedule
plan
Risk register
Enterprise
environment
factors
Organizational
process
assets
88
This is developed during process and defines the level of risk which is seen as
acceptable, how risks will be managed, who will be responsible for carrying out
risk related activities, the time and cost of each risk activity and how the
communication of risk is to occur.
Costs are also quantifiable and can be used as an input for this process.
Schedule timings are presented in a quantifiable manner, which means that risks
that will impact time scales can easily be quantified within this process.
Risk Register
This is the central repository of all of the known risks that are to be analyzed. It was
updated in the previous process to include information on relative ranking,
categorization and urgency of responses.
These include industry studies of similar projects by risk specialists and risk
databases from industry or proprietary sources.
These will include the tools needed to carry out qualitative risk analysis, policies,
procedures and guidelines for risk management, and historical information
including lessons learned from previous projects
Tool and techniques of Quantitative Risk analysis
There are three tools and techniques that can be used:
89
Outcome 1
Event
A
Event
C
Decision
1
Outcome 2
Outcome 3
Outcome 4
Event
B
Decision
2
Outcome 5
90
Expert judgment
Rather than ask each expert for a single value for each, the project manager
would normally encourage each experts to provide an optimistic, pessimistic and
realistic probability and impact value for each risk.
Output of Quantitative risk analysis
This process will create the following output:
Quantitative risk
report details:
Quantitative
approaches
Quantitative outputs
Quantitative
recommendations
The risk register is further updated to include a quantitative risk report detailing
quantitative approaches, outputs, and recommendations. Updates include the
following:
Probabilistic analysis of the project. Estimates are made of potential project
schedule and cost outcomes listing the possible completion dates and costs with
their associated confidence levels. This output, often expressed as a cumulative
91
6.4
Risks analysis expands on the danger data produced in the identification step,
changing over it into choice making data. In the analysing step, three more
components are included to the risk's entrance the master risks list, the risk
probability, effect and impact, and also the exposure. These components permit
operations staff to rank risks, which thusly permit them to direct the most vitality
into dealing with the rundown of top risks.
6.4.1 Risk Probability
Risk probability is a measure of the likelihood that the results portrayed in
the risk statement will really happen and is communicated as a numerical
quality. Risk probability must be more noteworthy than zero, or the risk does
not represent a threat. In like manner, the probability must be under 100
percent, or the risk is a conviction as such, it is a known issue.
92
for
Numeric score
language
calculations
expressions
1% through 33%
17%
Low
50%
Medium
84%
High
6.4.2
Risk Impact
93
Low impact/low probability Risks in the bottom left corner are low level,
and you can often ignore them.
Low impact/high probability Risks in the top left corner are of moderate
importance if these things happen, you can cope with them and move
on. However, you should try to reduce the likelihood that they'll occur.
High impact/low probability Risks in the bottom right corner are of high
importance if they do occur, but they're very unlikely to happen. For these,
however, you should do what you can to reduce the impact they'll have if
they do occur, and you should have contingency plans in place just in
case they do.
High impact/high probability Risks towards the top right corner are of
critical importance. These are your top priorities, and are risks that you must
pay close attention to.
The most ideal approach to estimate losses is by a numeric scale which the bigger
the number, the more prominent the effect to the business. The length of all risks
94
inside of an expert risks rundown utilize the same units of estimation, basic
prioritization methods will work. It is useful to make interpretation tables to change
over particular units, for example, time or cash into qualities that can be
contrasted with the subjective units utilized somewhere else as a part of the
investigation, as showed in the accompanying table. This specific table is a
logarithmic change where the score is generally equivalent to the log10 (RM loss)1.
High values indicate serious loss. Medium values show partial loss or reduced
effectiveness. Low values indicate small or trivial losses. The scoring system for
estimating monetary loss should reflect the organization's values and policies. A
RM 10,000 monetary loss that is tolerable for one organization may be
unacceptable for another.
Table 6.6: Score of Monetary Loss
Score
Monetory loss
Under RM 100
RM 100- RM 1,000
RM 1,000- RM 10,000
RM 10,000- RM 100,000
RM 100,000- RM 1,000,000
RM 1,000,000- RM 10 million
95
RM 1 billion- RM 10 billion
10
Over RM 10 billon
criterion
Schedule impact
Technical impact
Low
Slip 1 week
Slight
effect
on
performance
2
Medium
Slip 2 weeks
Moderate
effect
on performance
3
High
Slip 1 month
Severe effect on
performance
100
Critical
catastrophic
accomplish
Unable to deliver
Mission cannot be
accomplish
96
6.4.3
Risk Exposure
Risk exposure is the same thing as Risk score, so it is also can be calculated this
way:
RE=RP+RI-(RPxRI)
RE=0.5+0.3-0.5x0.3=0.65
Where:
RE= risks exposure
RP = Risk Probability (which is a number from 0 to 1, 0 means that the risk has no
probability of occurring and 1 means that the risk will definitely occur)
RI = Risk Impact (which is the impact of the risk, also from 0 to 1, 0 means that the
risk has no impact on the project whatsoever and 1 means that the risk has the
97
highest impact on the project. For example, if a risk has a 50% probability of
occurring and has impact of 0.3 over the project, then the risk Exposure will be
note that RE also ranges between 0 and 1. 0 means that the risk is not critical at all
and does not need to be managed, while 1 means that the risk is very critical.
Sometimes a high-probability risk has low impact and can be safely ignored;
sometimes a high-impact risk has low probability and can be safely ignored. The
risks that have high probability and high impact are the ones most worth
managing, and they are the ones that produce the highest exposure values.
At the point when scores are utilized to evaluate probability and effect, it is now
and then advantageous to make a matrix that considers the conceivable mixes
of scores and afterward doles out them to low-risk, medium-risk, and high-risk
categories. For the utilization of a tripartite lprobabilities score where 1 is low and 3
is high, the conceivable results may be communicated as a table where every
cell is a conceivable quality for risk exxposure. In this game plan, it is anything but
difficult to order risks as low, medium, or high relying upon their position inside of
the table. The accompanying table is a sample indicating probabilities and
impact.
Table 6.8: sample indicating probabilities and impact.
Low impact= 1
Medium impact= 2
High
impact= 3
High probability = 3
Medium probabilty= 2
2
Low probability
The advantage of this tabular format is that it is easy to understand through its use
of colours (red for the high-risk zone in the upper-right corner, green for low risk in
the lower-left corner, and yellow for medium risk along the diagonal). It also uses a
well-defined terminology; "High risk" is easier to comprehend than "high exposure."
98
Risk analysis provides a prioritized risk list to guide IT operations in risk planning
activities. Within the MOF Risk Management Discipline, this is called the master risks
list (described previously in Risk Lists). Detailed risk information including condition,
context, root cause, and the metrics used for prioritization (probability, impact,
exposure) are often recorded for each risk in the risk statement form.
Risk analysis gives an organized risk list to guide IT operations in risk planning
analysis. Inside of the MOF Risk Management Discipline, this is known as the expert
risk list (depicted beforehand in Risk Lists). Itemized risk information including
condition, context, root cause, and the metrics used for prioritization (probability,
impact, exposure) are frequently recorded for every riskr in the risk statement form.
6.4.4 Risk Factor Charts
A risk factor chart helps the group quickly determine the exposure it faces
for all general categories of risk. One line of such a chart might look like the
row in the following table.
Table 6.9 : Risk Factors
Risk Factors
Early
Aggressive
Domain
Protective Factors
Individual
Self-Control
Behaviour
Lack
of
Parental Family
Parental Monitoring
Supervision
Substance Abuse
Peer
Academic Competence
Drug Availability
School
Poverty
Community
Strong
Neighbourhood
Attachment
99
6.4.5
1)
a) Product size risks associated with overall size of the software to be built
b) Business impact risks associated with constraints imposed by
management or the marketplace
c) Customer characteristics risks associated with sophistication of the
customer and the developer's ability to communicate with the customer
in a timely manner
d) Process definition risks associated with the degree to which the
software process has been defined and is followed
e) Development environment risks associated with availability and quality
of the tools to be used to build the project
f) Technology to be built risks associated with complexity of the system to
be built and the "newness" of the technology in the system
100
g) Staff size and experience risks associated with overall technical and
project experience of the software engineers who will do the work
Social capital development projects, including road projects, are subject to
various risks throughout their life cycle, from the planning and construction stage
to the maintenance stage, due to long construction and maintenance periods
and wide geographical coverage. For the proper execution of such projects, it is
essential to quantify these risks for their appropriate management.
The access for the residential project only can be assessed by one road that
passes the road of locals owner. From the analysis, the risks that have been
identified are:
a) During
the
construction
phase,
residents
may
be
disrupted
and
Estate management
f) Cash Solvency Risks. This is the risk that the revenues generated the business
activities and investments are not adequate to cover fixed operating
expenses of the enterprise. This insolvency may not be permanent if the firm
has adequate operating reserves, the ability to take out property or
portfolio level debt, or the ability to raise capital through secondary stock
offerings, asset dispositions or other means to cover short-term imbalances.
g) Interest Rate Risk. This risk is associated with the use of leverage at the
individual property level, at a division or business line, or at the enterprise
level. Depending on the term structure of debt, this risk might cause erosion
in net earnings, negative cash flows, or a capital crisis if refinancing existing
maturing debt at higher rates is not feasible
h) Static Attribute Risks. Real estate is comprised of a bundle of right which
can be enjoyed as a whole or split into parts and transferred, either
temporarily or permanently. Thus, one of the risks associated with the asset
is the risk of claims on those rights that can cloud the title. In addition to
rights, real estate is a physical asset and as such, it subject to risks ranging
from the quality of construction to the adequacy of maintenance.
102
i)
Linkages Risks. Similarly, the locational nature of real estate and its
dependence on conditions in its market or trade area as well as
connectivity to ancillary uses as part of a larger urban system exposes the
value proposition to changes affecting commuting and transit patterns.
j)
Management Risk. This risk stems from the fact that high cost housing and
commercial investments must be managed over time. In most cases,
property management activity must be proactive, responding to changing
market dynamics and competitive conditions, operating requirements and
rent rolls. In effect, real estate investments are enterprises which require a
continuous, on-going management and sufficient resource commitment
and expertise to maintain value and capture
k) Exit Risk. Exit risk occurs at the eventual point in time when an investor,
tenant or other party seeks to sell or transfer an asset and there is
insufficient demand to acquire the asset at the desired price. This could
occur for a variety of reason ranging from erosion in net income to an
increase in cost of capital and thus hurdle rates by potential investors
6.5
Risk Planning
6.5.1
Risk Identification
A risk is any occasion that could keep the project from going ahead as
arranged, or from fruitful consummation. Risks can be distinguished from
some distinctive sources. Some may be very clear and will be distinguished
before project kickoff.
Others will be distinguished amid the venture lifecycle, and a risk can be
recognized by anybody associated with the project. Some risk will be
manufactured into the project itself, while others will be the consequence
of outside impacts that are totally outside the control of the project group.
The Project Manager has general obligation regarding overseeing project
risk. Project colleagues may be allocated particular territories of obligation
regarding answering to the project manager. All through all periods of the
project, a particular subject of discourse will be risk identification. The
103
Probability that the occasion will happen. For instance, a 50% chance
that the seller won't have a creature state that meets the criteria
accessible.
Schedule Impact. The quantity of hours, days, week, or months that a risk
component could affect the timetable. As a case, the creatures require an
extra 3 months to meet age prerequisites.
Scope Impact. The effect the risk will have on the imagined
achievements of the venture. Postponed creature conveyance may bring
about a diminishment in the quantity of studies that can be finished inside
of the agreement time of execution.
Quality Impact. A risk occasion may bring about a lessening in the nature
of work or items that are created. As an illustration, absence of subsidizing
brought about by expense overwhelms may bring about the diminishment
of the study size and effect factual strengthening
Cost Impact. The effect the risk occasion, on the off chance that it
happens is liable to have on the project budget.
6.5.2
Risk Responsibilities
Function
Implementing sustainable development
at the local level through local Agenda
21
policy
efficiently
and
and
implementing
consultant
to
the
government.
The main services include technical
consultancy,
project
management
sector,
in
particular
infrastructure works.
Tenaga Nasional Berhad (TNB)
TNBs
core
generation,
activities
are
transmission
the
and
distribution of electricity.
Other activities include repair, test and
maintain the power plants, provide
engineering,
procurement
and
106
Urban
and
Regional
Planning
Department (JPBD)
the development
management
disasters
inside
of
and
crises
and
outside
the
107
Project Team: The project manager must assign members of the project
team the roles of recorder and timekeeper
108
Project Sponsor: May participate depending on the size and scope of the
project
For each of the impact categories the impact assessment should include
consideration of the following areas of impact also:
cost
Scope
Schedule
other
impact
categories.
Schedule
delays
Most risks will be assigned one category, but some might be assigned more than
one, or all.
Technical or IT risks.
Organizational risks.
Financial risks.
110
External risks.
Compliance risks.
For instance, technical risks are associated with the operation of applications or
programs including computers or perimeter security devices (e.g., a computer
that connects directly to the Internet could be at risk if it does not have antivirus
software). An example of a project management risk could be the inadequacy of
the project manager to complete and deliver a project, causing the company to
delay the release of a product to the marketplace. Organizational risks deal with
how the company's infrastructure relates to business operations and the
protection of its assets (e.g., the company does not have clear segregation of
duties between its production and development environments), while financial
risks encompass events that will have a financial impact on the organization (e.g.,
investing the company's cash reserves in a highly speculative investment
scheme). External risks are those events that impactthe organization but occur
outside of its control (e.g., natural disasters such as earthquakes and floods).
Finally, a compliance risk occurs when a company does not comply with
mandated federal regulations, which often results in fines or legal sanctions.
6.5.5
RISK RESPONSE
Opportunities
Avoid
Exploit
111
the
uncertainty
associated
with
eliminated,
this
timeconsuming
Transfer
Share
Transferring
and
risk
for
others,
involves
those
costeffectiveness of
this must be
to
whom
opportunities
are
Mitigate
Enhance
threshold.
Taking
and
impact,
thereby
maximizing
the risk has occurred. Risk mitigation percent, this is effectively an exploit
may require resources or time and thus
response.
6.5.6
RISK MITIGATION
Reassign
organizational
accountability,
responsibility,
and
Risk reduction
Risk transfer
Each of these mitigation techniques can be an effective tool in reducing
individual risks and the risk profile of the project. The risk mitigation plan captures
the risk mitigation approach for each identified risk event and the actions the
project management team will take to reduce or eliminate the risk.
Risk avoidance usually involves developing an alternative strategy that has a
higher probability of success but usually at a higher cost associated with
accomplishing a project task. A common risk avoidance technique is to use
proven and existing technologies rather than adopt new techniques, even
though the new techniques may show promise of better performance or lower
costs.
Risk sharing involves partnering with others to share responsibility for the risk
activities. Many organizations that work on international projects will reduce
political, legal, labor, and others risk types associated with international projects
by developing a joint venture with a company located in that country. Partnering
with another company to share the risk associated with a portion of the project is
advantageous when the other company has expertise and experience the
project team does not have. If the risk event does occur, then the partnering
company absorbs some or all of the negative impact of the event.
Risk reduction is an investment of funds to reduce the risk on a project. On
international projects, companies will often purchase the guarantee of a currency
rate to reduce the risk associated with fluctuations in the currency exchange rate.
A project manager may hire an expert to review the technical plans or the cost
estimate on a project to increase the confidence in that plan and reduce the
project risk. Assigning highly skilled project personnel to manage the high risk
activities is another risk reduction method. Experts managing a high risk activity
can often predict problems and find solutions that prevent the activities from
having a negative impact on the project. Risk transfer is a risk reduction method
that shifts the risk from the project to another party. The purchase of insurance on
114
certain items is a risk transfer method. The risk is transferred from the project to the
insurance company.
6.5.7
115
Contingency funds are funds set aside by the project team to address unforeseen
events that cause the project costs to increase. Projects with a high risk profile will
typically have a large contingency budget. Although the amount of contingency
allocated in the project budget is a function of the risks identified in the risk
analysis process, contingency is typically managed as one line item in the project
budget.
Some project managers allocate the contingency budget to the items in the
budget that have high risk rather than developing one line item in the budget for
contingencies. This approach allows the project team to track the use of
contingency against the risk plan. This approach also allocates the responsibility to
manage the risk budget to the managers responsible for those line items. The
availability of contingency funds in the line item budget may also increase the use
of contingency funds to solve problems rather than finding alternative less costly
solutions. Most project managers, especially on more complex projects will
manage contingency funds at the project level with approval of the project
manager required before contingency funds can be used.
Contingency may also be reflected in the project budget, as a line item to cover
unexpected expenses. The amount to budget for contingency may be limited to
just the high probability risks. This is normally determined by estimating the cost if a
risk occurs, and multiplying it by the probability.
6.6
RISK MONITORING
According to Winch, 2002 this final step of Risk Management is vital since all
information about the identified risks is collected and monitored. The continuous
supervision over the Risk Management helps to discover new risks, keep track of
identified risks and eliminate past risks from the risk assessment and project.
6.6.1
4. Capture lessons learned for future risk assessment and allocation efforts
The risk monitoring process occurs after the risk mitigation and planning processes.
It must continue for the life of the project because risks are dynamic. The list of risks
and associated risk management strategies will likely change as the project
matures and new risks develop or anticipated risks disappear.
Occasional project risk reviews repeat the tasks of identification, assessment,
analysis, mitigation and planning. Regularly scheduled project risk reviews can be
used to ensure that project risk is an agenda item at all project development and
construction management meetings. If unanticipated risks emerge or a risk's
impact is greater than expected, the planned response or risk allocation may not
be adequate. At this point, the project team must perform extra reaction wanting
to control the risk.
Risk monitoring and updating tasks can vary depending on unique project goals,
but three tasks should be integrated into design and construction management
plans:
1. Develop consistent and comprehensive reporting procedures.
2. Monitor risk and contingency resolution.
3. Provide feedback of analysis and mitigation for future risk assessment and
allocation.
There are tools and techniques used to risk monitor and control may be:
Monitoring of the overall project status are there any changes in the
project that can effect and cause new possible risks
Status meetings discussions with risks owner, share experience and helping
managing the risks.
117