Professional Documents
Culture Documents
TECHNIQUE
BUILDING CONSTRUCTION
MANAS ARORA 3RD YEAR B
ROLL NO. 3
SHEET 1 - INTRODUCTION
SHEET 2 - OPEN CUT/COVER TECHNIQUE
SHEET 3 - BOTTOMS UP TECHNIQUE
SHEET 4 - BOTTOMS UP TECHNIQUE
SHEET 5 - TOP DOWN TECHNIQUE
SHEET 6 - TOP DOWN TECHNIQUE
SHEET 7 - TOP DOWN TECHNIQUE
SUBMISSION :
SUBMITTED TO :
SIGNATURE :
SIZE OF A SITE
VOLUME OF WORK
SHAPE AND TYPOGRAPHICAL CONDITIONS OF SITE
NEIGHBORHOOD CONDITIONS OF A SITE
GEOTECHNICAL CONDITIONS
INTERNAL LAYOUT OF THE BASEMENT OR OTHER RELATED
STRUCTURES
7. AVAILABILITY OF RESOURCES FOR THE PROJECT
8. AVAILABILITY OF EXPERTISE SKILL
9. APPROPRIATENESS OF THE METHODS SELECTED FOR THE
CONSTRUCTION
10. SPECIAL PERFORMANCE REQUIREMENTS IMPOSED
INVOLVEMENTS
1. GROUND STABILIZATION
USUALLY GROUTING METHOD IS USED TO
STABILIZE GROUND WEAKER IN NATURE. GROUT IS
A KIND OF FLUID FORM MATERIAL FOR INJETTING
INTO THE SUB-SOIL. THE MATERIAL CAN BE OF
CEMENT OR CHEMICAL BASE. IT CAN GET
HYDRATED INSIDE THE SOIL AND MAKE THE SUBSOIL
MUCH STRONGER TO WITHSTAND ITSELF OR TO
RESIST PENETRATION OF GROUND WATER.
4. EXCAVATION ARRANGEMENT
5. DEWATERING
7. BASEMENT CONSTRUCTION
BASEMENT OR SIMILAR UNDERGROUND STRUCTURES CAN BE CONSTRUCTED USING THE FOLLOWING APPROACHES:
1. OPEN CUT ARRANGEMENT
2. BOTTOM-UP ARRANGEMENT
3. TOP-DOWN ARRANGEMENT
OPEN CUT
BOTTOM UP
TOP-DOWN
SIZE OF SITE
SITE ENVIRONMENT
UNOBSTRUCTED
ADAPTABLE TO MOST
ENVIRONMENT
ADAPTABLE TP MOST
COMPLEX ENVIRONMENT
PROTECTION
SIMPLEST PROTECTION
SPECIAL PROVISION
NOT MUCH
NOT MUCH
TEMPORARY VERTICAL
SUPPORT REQUIRED
MACHINE SUITABLE
SPOIL REMOVAL
LARGE MACHINE
SMALL MACHINE
LARGE MACHINE
USING RAMP
STAGED PLATFORM OR
BUCKET
CONSTRUCTION METHODS
BUILDING
CONSTRUCTION
SHEET NO.
MANAS ARORA
3RD YEAR - B
VASTU KALA ACADEMY
SIGNATURE :
APPLICATION:
LIMITED CONSTRAINT OF SITE.
SITE MUST LARGE ENOUGH TO APPLY THIS TECHNIQUE.
SUITABLE FOR CLAY TO SAND SOIL LOW SOIL
SETTLEMENT.
ALLOW WORKING SPACE PROVIDE STABILITY TO SOIL.
SPEED OF CONSTRUCTION LOWEST PERFORMANCE
BOTTOM UPWARDS.
CONSTRUCTION AND CONSIDER BACKFILL WORK
DEPTH NOT EXCEED TWO STOREY HEIGHT.
LOW COST METHOD NOT HAVE COMPLICATED ACTION.
ADVANTAGES:
EXCAVATE
CONSTRUCT BOTTOM UP
RODS ARE INSERTED INTO THE SOIL ALONGSIDE THE SLOPE AND CONRETE ARE SPRAYED ONTO THEM, TO
PREVENT THE SOIL FROM ERODING OR SLIDING DURING RAINY DAYS. IN SOME CASES, PILE SHEETING MAY BE
PROVIDED TO REDUCE DIFFERENTIAL SETTLEMENT TO THE ADJACENT BUILDINGS.
IN BUILT UP URBAN AREA, SUCH A TECHNIQUE IS OFTEN IMPRATICAL IN VIEW OF SITE CONSTRAINTS AND THE
NEED TO RESTRICT GROUND MOVEMENTS ADJACENT TO THE EXCAVATION. THE MAIN CRITERIA TO CONSIDER
FOR AN OPEN CUT TECHNIQUE IS THE GEOLOGICAL CONDITION OF THE SITE, AS THIS HAS A DIRECT EFFECT
OON THE EARTH SLOPE.
BACKFILL
CONTRCUTION SEQUENCE OF
OPEN CUT TECHNIQUE
DISADVANTAGES
.
CONSTRUCTION METHODS
BUILDING
CONSTRUCTION
SHEET NO.
MANAS ARORA
3RD YEAR - B
VASTU KALA ACADEMY
SIGNATURE :
BOTTOMS UP METHOD
ADVANTAGES:
.
DISADVANTAGES:
CONSTRUCTION METHODS
BUILDING
CONSTRUCTION
SHEET NO.
MANAS ARORA
3RD YEAR - B
VASTU KALA ACADEMY
SIGNATURE :
BOTTOMS UP METHOD
CONSTRUCTION OF BASEMENT USING BOTTOM-UP APPROACH
-A MUCH COMPLICATED CASE (LANGHAM PLACE)
PROVISION OF A WORK PLATFORM FOR THE STATIONING OF EQUIPMENT AND HANDLING OF SPOIL TO FACILITATE THE EXCAVATION PROCESS
DETAIL SEEING THE SHEET PILE WALL AND THE TYPICAL STRUTS/KING POSTS/SHORES/ BRACINGS LATERAL SUPPORT SYSTEM
ARRANGEMENT FOR THIS KIND OF BOTTOM-UP APPROACH CONSTRUCTION METHOD.
BASEMENT FLOOR
SUPPORT BY
TRADITIONAL
PROP SYSTEM
CONSTRUCTION METHODS
BUILDING
CONSTRUCTION
SHEET NO.
MANAS ARORA
3RD YEAR - B
VASTU KALA ACADEMY
SIGNATURE :
THE USE OF A
MATERIAL HOIST FOR
THE REMOVAL OF
SPOIL FROM THE
BASEMENT INTERIOR
1.
FLOOR SLAB
EXCAVATION SURFACE
RETAINING
WALL
2.
STEEL COLUMN
FINAL EXCAVATION SURFACE
PILE
BEARING STRATUM
3.
CONSTRUCTION METHODS
BUILDING
CONSTRUCTION
SHEET NO.
MANAS ARORA
3RD YEAR - B
VASTU KALA ACADEMY
SIGNATURE :
PREFFERED METHOD :
ADVANTAGES:
TYPICAL TOP-DOWN ARRANGEMENT AS IN PIONEER CENTER AND CHEUNG KONG CENTER PROJECTS.
DISADVANTAGES:
SELECTION:
USED FOR DEEP EXCAVATION PROJECTS WHERE TIE BACK
INSTALLATION WAS NOT FEASIBLE AND SOIL MOVEMENTS HAD TO
BE MINIMIZED.
COMMONLY USED IN HILLY AREAS AND SUITABLE FOR BASEMENT
OF LARGE SIZE.
CONSTRUCT USING PERMANENT PERIMETER WALLS.
USING SMALL EXCAVATION AT CERTAIN PLACE.
GROUND FLOOR SLAB AS A SUPPORTING.
PRE FOUNDED COLUMNS ARE STRUCTURAL COLUMNS/ PILES
FORMED BEFORE BASEMENT EXCAVATION.
CONSTRUCTION METHODS
BUILDING
CONSTRUCTION
SHEET NO.
MANAS ARORA
3RD YEAR - B
VASTU KALA ACADEMY
SIGNATURE :
CONSTRUCTION METHODS
BUILDING
CONSTRUCTION
SHEET NO.
MANAS ARORA
3RD YEAR - B
VASTU KALA ACADEMY
SIGNATURE :