Order Confirmation
Plant Maintenance
Order Confirmation
IW42
Logistics Plant Maintenance Service
Processing Confirmation Entry
Overall completion confirmation

Document Overview

Purpose

The actual hours worked per operation are recorded / posted to the PM order via
time confirmation. Any materials used may be posted at this time. Technical
reporting to the notification may also be performed at this time.

Trigger
Actual hours worked and materials used need to be recorded and posted to the PM order

Prerequisites

The Order must have been released

Helpful Hints

If confirmations for multiple PM orders are to be entered, refer to Business Process


Procedure 'PM Order Collective Confirmation'.

A) Enter PM Order Confirmation-IW42


In Operation Enter 010 specific to each person.