Professional Documents
Culture Documents
3
2
1
REV.
22/9/2016
DATE
MEC
ORIGINATOR
MEC
REVIEWED
MEC HO
APPD
ACB
APPD
PGESCO
DESCRIPTIO
N
ORIGINATOR: MEC
TABLE OF CONTENTS
1.0 SCOPE
2.0 PURPOSE
3.0 DEFINITION
4.0 REFERENCE DOCUMENTS
5.0 RESPONSIBILITIES
6.0 SEQUENCE OF WORK
7. RESOURCES
8. HEALTH, SAFETY & ENVIRONMENT
1.0 SCOPE
This Auxiliary Boiler Critical Lifts Unloading, Rotating and Erection Working Procedure is prepared in
full compliance with the ACB specifications and other ACB documents and shall not after modify or
adjust any of the requirements unless specifically agreed per ACB.
The scope of this Auxiliary Boiler Critical lifts Unloading, Rotating and Erection working procedure is to
provide the detailed description of lifting plan.
2.0 PURPOSE
The purpose of this lifting plan is to set the safe methodology for Auxiliary Boiler Critical Lifts Unloading,
Rotating and Erection Working Procedure to be followed during execution in South Helwan
Supercritical Power Plant.
3.0 DEFINITION
The following definitions are applied:
3.1
ACB
AC-Boiler
3.2
MEC
3.3
PROJECT
5.0 RESPONSIBILITIES
MECS Site Manager shall be responsible for overall Auxiliary Boiler Critical Lifts Unloading, Rotating
and Erection activities, ensure that all pre-construction formalities, approvals and preparation are done
sufficiently in advance to start the construction activity as per the schedule.
MECS HSE Manager shall be responsible for overall Auxiliary Boiler Critical Lifts Unloading, Rotating
and Erection safe operation, ensuring that all safety measures are implemented and HSE formalities,
approvals and preparation are done sufficiently in advance to start the construction activity as per the
HSE roles.
MECS Q.C. Manager shall be responsible for overall Auxiliary Boiler Critical Lifts Unloading, Rotating
and Erection quality control, formalities, approvals and preparation are done sufficiently in advance to
start the construction activity.
MECS Engineer (Mechanical) shall be responsible for actual performance of work directly at site,
Coordination with other departments, receiving material from store, storing at site, Handling,
Traceability, installation all in accordance with approved specification and drawings by obtaining Work
permit from relevant authorities.
MECS Q.C Engineer shall be responsible for welding in accordance with approved WPS, specification
by assigning qualified welders for welding works, welding consumable control, and to ensure correct
consumables are being used and preparation/compilation of QC records and reports.
MECS Safety officer shall be responsible for the conduct of safe working practice as per ACB/MECs
procedure and ensure that all activities are performed by strictly adhering to safe working practice and
Permit to work procedure.
Ground will be checked before lifting operation. If necessary, ground will be compacted or
tested. The ground must be firm enough to prevent the crane from sinking and to protect the
existing foundation and anchor bolts.
Quantity
Weight
/
Weight
Each (ton)
(ton)
100
100
6.2.4 :Tension Wire Analysis during Unloading shifting and rotation only
Main Crane MLT 1500 / two wires 3 X 8 mt length
As per Drawing No. 15EB021-M-500 Lugs distance is 7200mm
Tail Crane MLT 1200 / two wires 2.5 X 8 mt length and two wires 2.5 X 6mt + spider beam
Load weights =65 % of total weight at worst case = 65*105/100 = 68.25 Ton.
No.2 steel sling wire 2.5 X 8 mt X 47 Ton. And Connected each one by shackle 85 Ton.
Each wire load = 47 Ton as per SWL tables on 60 degree.
No.2 steel sling wire 2.5 X 6 mt X 54 Ton. And Connected each one by shackle 68.25 Ton.
Each wire load = 54 Ton.
Quantity
Weight
Weight
Each (ton)
100
(ton)
100
-8.8
7.0 RESOURCES
Resources shall be mobilized as required to ensure that the work is carried out as per schedule and in a safe
manner