Professional Documents
Culture Documents
T
TN
TU
NOMENCLATURE
BK
Manuscript received September 17, 2003; revised March 3, 2004. Paper no.
TPWRS-00540-2003.
The authors are with the Electrical and Computer Engineering Department, University of Waterloo, Waterloo, ON N2L 3G1, Canada (e-mail:
waselkha@engmail.uwaterloo.ca).
Digital Object Identifier 10.1109/TPWRS.2005.846114
to include nontraditional alternative capacitys investment options to address the varying economic environments [5]. Distributed generation (DG) is one of the new attractive alternative capacity options for DISCOs planning. DG reduces the
systems capital cost by deferring distribution facilities [6]. DG
reduces the power flow in the system, thus improving the system
voltage profile [7], [8], minimizing the system losses [7][10],
and relieving the heavy loaded feeders and extending the equipments lifetime [6].
This paper proposes the implementation of DISCO DG as an
economical attractive new tool for the DSP problem to make
use of its economical and operational benefits, solve the lacking
electric power supply problem, and meet the load growth
requirements with a reasonable price. The new integrated DSP
model with DG implementation aims to minimize DISCOs
capital investment and operating costs in new facility capacities
(substations, transformers, feeders, and DGs) as well as payments to be made toward DISCOs system loss compensation,
cost of DGs generated power, and cost of power purchased
from the main grid. The proposed model decides the necessary
new facilities sizing and siting as well as the required power to
be imported from the main grid through DISCOs substations
or an existing intertie to meet the demand in an optimal way.
The attractive feature of the proposed optimization model is
that it uses binary decision variables, thereby providing the optimal decisions without any need for rounding the solution. The
results of this model can be used to provide the new estimation
for billing DISCOs customers. Several comprehensive analysis
scenarios are discussed to cover the different possibilities that
can exist in DISCOs territories. The scenarios models are carried out to investigate the optimal economical DGs investment
feasibility based on the proposed new objective function and
its constraints.
1159
3)
Cost of Scenario A or
Cost of Scenario B
(1)
Cost of Scenario A
(2)
Cost of Scenario B
(3)
where from [11],
1160
1)
(4)
2) Distribution Feeders Thermal Capacity: The DISCOs
feeder has a capacity limit for the total power flow through it
during peak loads.
2)
(5)
3) Distribution Substations Capacity: The summation of
total power delivered by the substations transformers to the
DISCOs network must be within the substations capacity
limit.
(6)
4) Voltage Drop: The DISCO provides the predetermined
maximum permissible voltage drop limit [12].
(7)
5) DG Operation: The DGs generated power must be less
than the DGs capacity.
3)
(8)
6) Interties Delivery Power Capacity Limit: The interties
delivery power cost rates are predetermined by the DISCO and
the other identitys contract. The rate of charge depends on the
amount of power purchased by the DISCO.
MVA
MVA
MVA
MVA
(9)
1161
can fit in relatively small areas [14], [15]. The systems existing
substation capacity is 40 MVA, which is capable of serving the
normal operation load. The total load growth to be served is
51.1 MVA at the horizon year. Two three-phase 10-MVA potential transformers can be installed for expanding the existing
substation, each of 0.2 M$. The cost of upgrading the existing
primary distribution feeder with another of higher capacity is
0.15 M$/km [12]. All existing equipment and feeders costs are
entered as zeroes for the optimization model. The system power
factor is set to 0.9. The DISCOunt rate is taken as 12.5%.
It is important to mention that DG siting has some environmental restrictions. Therefore, this paper adopted the use of the
natural gas generator set since this technology is known to be
environmentally friendly and produces the least pollution compared to other fossil fuels DGs [14], [15].
III. ANALYSIS AND RESULTS
The main two scenarios discussed in Section III are carried
out to evaluate the feasibility of implementing DG investment
in DSP versus other traditional planning options. The new facility investment is mandatory in order to serve the DISCOs
load growth in its territory. Each one of the main two scenarios
is divided further into two cases. In the first case, there is no
need for DISCOs feeders upgrading. On the other hand, in the
second case, the DISCOs feeders upgrading is essential as the
power flow exceeds the feeders thermal capacity. These scenarios are discussed in detail as follows.
A. Scenario A: DG versus Substation Expansion
If there is difficulty in finding suitable land for building new
substations, existence of rapid economic variation that may lead
to high investment risks, or a long time government regulatory
permission is required, then expanding an existing substation
is the available option. In this scenario, two candidate transformers are used in the optimization model for investigating the
existing substation expansion option. During the proposed scenarios, the existing DISCOs feeder thermal capacities may be
violated, and therefore, the analysis is done under the following
two conditions.
1162
TABLE I
DG VERSUS SUBSTATION EXPANSION
Fig. 2.
Fig. 3.
Fig. 4.
1163
TABLE II
DG VERSUS SUBSTATION EXPANSION WITH FEEDER UPGRADING
Fig. 5. Scenario A: DISCOs buses voltage profile with feeder upgrading for
the substation planning option.
Table II shows that in the case of the substation expansion option, three out of four outgoing feeder segments from the substation are upgraded with an investment decision of 4.5 M$. However, the rest of the five feeder segments are kept without upgrading, as their power flow is less than their thermal capacity
limits. As we mentioned before, two transformers are selected
by the optimization model to meet the load growth.
On the other hand, implementing DG as an alternative option in DSP provides 20% less total planning cost. These savings are gained without any need for feeders upgrading while
keeping the feeder thermal capacity limit. The optimal DGs
siting occurs at bus-1 for 1-MVA operating capacity and another
as backup and three groups, each consisting of 4-MVA operating
capacity and 1-MVA backup at buses 2, 4, and 8.
Fig. 5 shows the DISCOs bus voltage profile. It is obvious
that in the case of substation expansion, the voltage profile will
be the same as in Fig. 2, while in the case of DG, the voltage
profile is better than that for substation expansion alone and different from that obtained in Fig. 2, as the obtained optimal DGs
sizing and siting is different from that obtained in Table I. Results show an improvement in the voltage of DISCOs buses
14, 7, and 8, with less improvement than those in Fig. 2 at
DISCOs buses 5 and 6.
Fig. 6 shows the power flow in DISCOs feeders. The feeders
power flow in the case of an expanding substation is quite similar to that shown in Fig. 3, as the violated feeders have been
chosen to be upgraded, while in the case of DG planning, it is
different from its similar DG planning case in Fig. 3, as DGs
can limit the feeders power flow to their thermal capacity limit.
The optimal DGs sizing and siting and the existing substation
power obtained from the optimization model are given in Fig. 7.
1164
TABLE III
DG VERSUS INTERTIE
peak demand growth. The output solution for the intertie planning option is shown in the first column of Table III, where three
intertie transactions are carried out.
However, in the case of using DG as an alternative option with
the intertie option for DSP, much better planning decisions are
obtained. The proposed optimization model (1) and (3) calculation is carried out taking constraints (4)(9) and setting multiple DG units, as discussed in Scenario A. The second column
in Table III shows the output solution for DG investment and
intertie options. It is to be noted that in three groups of DGs,
each group contains 4-MVA operating capacity, and 1-MVA as
backup at DISCOs buses 2, 6, and 8 is chosen in addition to a
single transaction taking place by the intertie of 0.7328 MVA.
This intertie amount of power is practically acceptable as the intertie feeder already exists, unlike the case of expanding an existing substation (see the second column in Table I). Therefore,
we get the optimal intertie transactions and the DGs sizing and
siting with a lower total planning cost than in the case of purchasing power from the intertie alone by a total planning savings
of 16.2%.
Table III provides detailed results obtained from the optimization model for Scenario B. It is obvious that by investing in DG
rather than purchasing power at high market price rates from an
existing intertie, the DISCO can reduce its customers bills by
a value of $3.6882/MWh.
As discussed before in Scenario A, Fig. 8 shows a better
voltage profile for all DISCOs buses in the case of DG planning with intertie rather than the intertie planning option alone.
A reduction in the primary feeders power flow, as shown
in Fig. 9, occurs that results in the reduction of the DISCOs
system losses cost and relief of feeders loading. Fig. 10 shows
the optimal DG sizing and siting, intertie transactions, and substation purchased power in the case of introducing DG and intertie planning options to the DSP optimization model.
2) DISCOs Feeder Thermal Capacity Is Violated: If the
DISCOs primary feeders thermal capacity is violated, then
Fig. 8.
Fig. 9.
Fig. 10.
TABLE IV
DG VERSUS INTERTIE WITH FEEDER UPGRADING
1165
REFERENCES
[1]
[2]
[3]
[4]
[5]
[6]
[7]
[8]
[9]
[10]
[11]
[12]
[13]
[14]
[15]
[16]
[17]
Walid El-Khattam (S00) is currently working toward the Ph.D. degree at the
University of Waterloo, Waterloo, ON, Canada.
He is with the teaching faculty in the Department of Electrical Power and
Machines, Ain Shams University, Cairo, Egypt.
M. M. A. Salama (F02) is a Professor in the Electrical and Computer Engineering Department at University of Waterloo, Waterloo, ON, Canada.