You are on page 1of 110

Project Title :

ENGINEERING PROCUREMENT AND CONSTRUCTION


COMPRESSED NATURAL GAS - TAMBAK LOMBOK

HAZOP AND HAZID STUDIES REPORT

DOCUMENT STATUS
Approved
:
Approved
:
as Noted
Not Approved

24 JUL 2013

REISSUED FOR REVIEW

YS

MTH

MEF

28 JUN 2013

ISSUED FOR REVIEW

YS

MTH

MEF

REV

DATE

DESCRIPTION

PREPARED

CHECKED

APPROVED

COMPANY

PT. Enviromate Technology International


PT Pertadaya Gas

HAZOP/HAZID of CNG PLANT TAMBAK LOROK

TABLE OF CONTENTS

INTRODUCTION

1.1
1.2
1.3
1.4

BACKGROUND
STUDY OBJECTIVES
SCOPE OF HAZOP/HAZID STUDY
REPORT LAYOUT

7
7
8
8

PROJECT DESCRIPTION

2.1
OVERVIEW
2.1.1
Inlet scrubber (V-100)
2.1.2
Station Inlet metering (M-100 A/B)
2.1.3
Dryer Unit (D-100 A/B)
2.1.4
Compressor (K-101 / / K-109)
2.1.5
CNG Cooler ( E-100)
2.1.6
CNG storage cylinders (V-200 1/../ 82)
2.1.7
Double pipe Exchanger
2.1.8
CNG Heat Exchanger (E-200)
2.1.9
Pressure reducing system (PV-0501 A/B)
2.1.10 Storage and Decanting process
2.1.11 Station Outlet Metering (M-200 A/B)
2.1.12 Waste Heat recovery Unit (E-300)
2.1.13 Fuel Gas
2.1.14 Instrument air
2.1.15 Cooling water (E-400)
2.1.16 Fire water system
2.1.17 Water treatment system (W-001)
2.1.18 Insulation
2.1.19 Vent System

9
9
9
10
10
11
11
12
12
12
12
13
13
13
13
14
14
14
14
14

STUDY METHODOLOGY

16

3.1
HAZOP
3.1.1
Overview
3.1.2
Worksheet Definition
3.2
HAZID
3.2.1
Overview
3.2.2
Worksheet Definitions

16
16
16
16
16
17

HAZOP/HAZID REVIEW SESSIONS

18

4.1
4.2
4.3
4.4
4.5

INTRODUCTION
THE HAZOP/HAZID TEAM
GUIDE WORDS
DRAWINGS REVIEWED
SELECTED NODES

18
18
18
19
20

HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

JULY 2013

PT. Enviromate Technology International


PT Pertadaya Gas

HAZOP/HAZID of CNG PLANT TAMBAK LOROK

HAZOP/HAZID RESULTS

21

5.1
5.2

ACTIONS/RECOMMENDATIONS
MAJOR HAZARD SCENARIO

21
23

HAZOP/HAZID FOLLOW-UP

25

REFERENCES

26

APPENDIX A
APPENDIX B
APPENDIX C
APPENDIX D

HAZOP/HAZID SUMMARY RECOMMENDATIONS


HAZOP REVIEW WORKSHEETS
HAZID REVIEW WORKSHEETS
DRAWINGS

HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

PT. PROSIM

EXECUTIVE SUMMARY
The PT Perta Daya Gas has awarded to PT. Enviromate Technology International (PT. ETI) to
conduct and construction of Compressed Natural Gas (CNG) facility. The plant will be located at
Tambak Lorok, Central Java, Indonesia. The CNG facility is consisting of following equipment:
Gas-Liquid separation system, Gas Drying & H2S adsorption system, Gas Compression system,
CNG Cylinders storage package, Heat Exchangers and Metering systems.
The Utility for supporting CNG Plant are consisting Fuel Gas System, Gas power generation, Air
Instrument Package, Waste Heat Recovery Unit, Pumps, Cooling towers, Water treatment Package
and Sump system.
The incoming gas is taken from existing pipe then being compressed to CNG storage cylinders by
CNG Compressors. Storage CNG will be performed maximum at 20 hours/day and decanting phase
will be performed on the peak load within 4 hours/day (18.00 to 23.00). The design capacity of
CNG Plant is 19.88 MMSCFD gas to the CNG storage cylinders.
Waste heat recovery Unit is provided to utilize the energy from exhaust compressor gas engine to
reduce Joule Thompson effect on the pressure reducing system. The WHRU will heat water from
tank which will be utilized as heating media of the CNG gas on CNG heat exchanger.
Cooling water system which consisting of Cooling Tower, Circulation pumps and CNG cooler will
be pro-vided to optimize the requirement of CNG cylinders.
The HAZOP/HAZID review sessions were carried out at the Istana Karang Laut office in Plaza
Citivew Kemang, Jakarta, utilizing 2 days for review, over the period 17th, and 21st June 2013.
The study identified 40 HAZOP recommendations and 18 HAZID recommendations. The
recommendations would reduce potential safety or operability problems associated with the process
or improve the clarity of the process drawings.
HAZOP
Design
It was noted in the HAZOP It identified during the review and also with discussion with Tambak
Lorok, some of the valve arrangement need to be lock open to ensure that it doesnt block due to
human error (eg. at upstream BDV, by pass line). General comments also noted to provide setting
for all the instrumentation system (e.g. PIC, PSHH, PSV)
Its been reviewed that gas from suction compressor can be directed to downstream of E-200 to
metering M-200 resulting in double counting of sales gas from Gundih meter with M-100. It was
recommended to install additional check valve to PG-2"-3C-027 to prevent that case.
It recommended to provide SOP to accommodate gas release from vent of sump tank due to gas
blow by from V-100, to ensure equipment purchase suitable as per hazardous area classification and
also to nsure vent stack at sump tank is located high enough to prevent exposure to
personnel/operator at Incoming Scrubber System.

HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

PT. PROSIM

In the Waste Heat Recovery Unit, it was recommended to provide PSHH at downstream P-500A/B
to trip P-500A/B in the case of manual valve at upstream E-300 inadvertenly close resulting in
overpressure of the system.
The existing fire water capacity need to be reviewed to ensure source of water and its amount is
adequate to handle fire on the CNG plant in addition with existing fire water requirement in
Tambak Lorok.
It was discussed also that the design of floating valve T-600 to be radar type.
Maintenance and Operational
Based on the discussion raised up, its required to develop operating manual for delivery gas
including showing correlation between pressure and flow at storage period and operation of
redundant equipment such as compressor.
To control corrosion at basin cooling tower, it was recommended to provide SOP to control PH at
cooling tower periodically.
HAZID
In the HAZID session, location of the lightning stack has not identified yet, therefore it is
recommended to review the location of the lightning stack to be away from the venting stack to
reduce the probability of fire on the vent stack
It was reviewed also that high noise level around the compressor area will potentially injured the
personnel who operate the plant in daily basis. It was recommended to have noise study and provide
warning sign the area to use ear plug protection.
Fire and Gas detection was also reviewed in the HAZID, it is recommended to provide the
philosophy of the fire and gas detection system of the plant in formal documentation and provide
clear actions of each detector, which one create alarm or shut down/blowdown of the plant. Fire
detection philosophy was not provided in the building, specifically in the electrical room such as
control room/MCC/batery room. It is recommended to provide clear philosophy, e.g. providing early
warning system for smoke detection in electrical room (High Sensitivity Smoke Detector), including
fire suppression system such as portable fire extinguisher or automatic fire suppresion system (e.g.
FM-200,etc)
The scenario of fire and explosion in the CNG plant was not established yet during the review
especially in relation position of the processing facility to location where stand by personnel
available such as control room. Therefore, review of this scenario is recommended to justify design
and location of the control room building. It is include also the fire and explosion impact to
surrounding facility at Tambak Lorok. In the discussion also identified that the control room will not
provided with glass windows to avoid explosion effect from the plant, hence that CCTV is
recommended to be provided in the control room to monitor the plant.
During the review, location of the vent stack has not been identified yet. Therefore, dispersion and
radiation analysis need to be done to define safe location and height required for the vent stack.
Consideration for emergency situation was also reviewed, and it is recommended to review
emergency evacuation plan including emergency route, muster point location, safety equipment lay
out and emergency lighting.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

PT. PROSIM

Good communication among parties involved (Tambak Lorok and Gundih) also important to make
sure operability and deliverability of the process plant, especially to handle emergency situation.
Therefore a procedure defining internal and external communication need to be established among
parties to make sure the plant is operated safely.
MAJOR HAZARD SCENARIO
The Major Hazard of this plant is :

Process Hazard :
1. High Pressure Gas containment in the CNG Storage Tanks
2. Gas Compression System
3. Hot water circulation system
4. Cold Venting

Non Process Hazard :


1. Control Room located in hazardous area
2. Human Error - Alarm
3. Communication between ETI, IP, Gundih
4. Transportation

HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

PT. PROSIM

1 INTRODUCTION

1.1 BACKGROUND
PT. Perta Daya Gas is planning to develop CNG Plant Project. The plant will be located at Tambak
Lorok, Central Java province, Indonesia.
PT. Perta Daya Gas therefore commissioned an independent Chairman and Scribe for a series of
safety studies to review and identify hazards and operability issues related to operation of
Compressed Natural Gas Plant Project.
This report details the Hazard and Operability (HAZOP) and Hazard Identification (HAZID) review
and includes a summary of the recommendations identified during the review, as well as the
HAZOP/HAZID review worksheets.
1.2 STUDY OBJECTIVES
The objectives of the HAZOP study are to:

Identify safety related hazards and operability problems related to the process that could directly
threaten the safety of production personnel or cause operational problems;

Determine the seriousness of the consequences for the identified problems;

Identify engineering and procedural safeguards already incorporated into the design that will
reduce the likelihood or the severity of consequences related to the identified problem;

Evaluate the adequacy of existing engineering and procedural safeguards; and

Recommend additional safeguards or operational procedures where necessary.

The objectives of the HAZID study include:

Assess changes and consider new requirements that have emerged since the last PHA;

Identification of new hazard causes or initiating factors associated with the modifications with a
potential to result in major accident events (MAEs), which may give rise to serious and
immediate risk to health and safety of personnel;

Assessment of the consequences of these new MAEs;

Determination of risk based on the likelihood and the severity of the consequences for each
identified MAEs;

Identification of existing safeguards that may include engineering or operational controls and
measures included in the design for prevention and/or mitigation of the MAEs;

Evaluation of the residual risk taking into account the existing control and mitigation measures;
and

Recommendation of additional safeguards or procedures, where necessary to demonstrate as


Low as Reasonable Practicable (ALARP).

HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

PT. PROSIM

1.3 SCOPE OF HAZOP/HAZID STUDY


The HAZOP/HAZID study covers these packages in detail:
1. Main Proces System:

V-100 : Gas Scrubber

M -100A/B & M -200A/B : Station Inlet & Outlet Metering

D-100A/B : Gas Dryer

K-101 to K109 : CNG Compressors

E-100 : CNG Cooler & E-200 : CNG Heat Exchager

V-200-1 to V-200-80 : CNG Compartement

V-400 : Sump Tank

2. Utilities

WHRU and Hot Water circulation

Water Treatment Facilities and Cold water circulation

Open & Close Drains

Venting system

Instrument Air System

Fuel Gas System

Fire Water Ring

Engine Generator

1.4 REPORT LAYOUT


This HAZOP/HAZID report is structured as follows:

Section 1 gives an introduction, defining the objectives and scope of the study;

Section 2 describes the process;

Section 3 describes the HAZOP/HAZID methodology;

Section 4 describes the HAZOP/HAZID workshops;

Section 5 lists the references given in the report;

Appendix A presents the summary HAZOP & HAZID recommendations;

Appendix B presents the HAZOP review worksheets;

Appendix C presents the HAZID review worksheets; and

Appendix D presents the Drawings used, outlining the nodes.

HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

PT. PROSIM

2 PROJECT DESCRIPTION
2.1 OVERVIEW
The CNG facility is consisting of following equipment: Gas-Liquid separation system, Gas Drying
& H2S adsorption system, Gas Compression system, CNG Cylinders storage package, Heat
Exchangers and Metering systems.
The Utility for supporting CNG Plant are consisting Fuel Gas System, Gas power generation, Air
Instru-ment Package, Waste Heat Recovery Unit, Pumps, Cooling towers, Water treatment Package
and Sump system.
The incoming gas is taken from existing pipe then being compressed to CNG storage cylinders by
CNG Compressors. Storage CNG will be performed maximum at 20 hours/day and decanting phase
will be performed on the peak load within 4 to 5 hours/day (18.00 to 23.00). The design capacity of
CNG Plant is 19.88 MMSCFD gas to the CNG storage cylinders.
Waste heat recovery Unit is provided to utilize the energy from exhaust compressor gas engine to
reduce Joule Thompson effect on the pressure reducing system. The WHRU will heat water from
tank which will be utilized as heating media of the CNG gas on CNG heat exchanger.
Cooling water system which consisting of Cooling Tower, Circulation pumps and CNG cooler will
be pro-vided to optimize the requirement of CNG cylinders.
2.1.1 Inlet scrubber (V-100)
The gas scrubber (V-100) will be installed on incoming gas to remove any hydrocarbon liquid from
upstream facility. The liquid level on the gas scrubber will be controlled by control valve LV-0101
to avoid liquid carried over to the CNG Plant. High liquid level on the scrubber will initiate the
valve to open, then if liquid level has reached normal condition valve will be closed, so the valve
will be as on/off mode.
The gas scrubber is provided with PSV-0101A/B with set pressure of 34 barg for overpressure
protection, One PSV will be on operation and another one as spare.
Inlet line will be provided with SDV-0101 in order to isolate the plant in emergency condition. The
initiators of SDV-0101 closing refer to Cause & effect diagram.
2.1.2 Station Inlet metering (M-100 A/B)
The metering will measure natural gas inlet to CNG plant. Total gas inlet is 19.88 MMSCFD. Gas
inlet would be 19.88 MMSCFD and flows to inlet compressor and 1.1 MMSCFD flows to auxiliary
fuel gas. Metering type is 2x100% custody orifice meter. Metering will be operated in continous
operation. Flow and accumulation flow should be monitored by flow computer. Gas inlet to
metering tends to consist of high moisture. Orifice should be designed for wet gas condition.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

PT. PROSIM

2.1.3 Dryer Unit (D-100 A/B)


The outlet gas from gas scrubber (V-100) will be dried through Gas Drying Unit (D-100A/B). Unit
consist of two Gas Dryer + H2S absorber, i.e D-100A/B and D-200A/B. These will be operated on
parallel configuration. Maximum capacity of drying Unit is 10 MMSCFD. The range of inlet
pressure is 20.6-25 barg. One bed will be on drying mode and the other one is on regenerating
mode. Gas dryer will remove water and H2S content on the feed gas to produce moisture dew point
to -40oC and maximum 3 ppm H2S. Dew point meter and H2S meter should be installed within
Dryer package unit. Adsorption time is 4-8 hours and the regeneration time is 4-8 hours (heating,
cooling and standby).
Gas dryer pre filter (F-100) will be provided at upstream of desiccant gas dryer (D-100A/B) to
ensure that gas goes to molecular sieve is clean and no hydrocarbon liquid carried over. One filter
will be operated and bypass line opened during filter maintenance, pressure differential indicator
will be provided across the filter such that operator will able to determine the switching operation.
Gas dryer after filter (F-110) will be provided on the downstream of desiccant gas dryer (D-100A/B)
to ensure that are there is no solid particle carried over on the gas before entering the CNG
compressor. One filter will be operated and bypass line opened during filter maintenance, pressure
differential indicator will be provided across the filter such that operator will able to determine the
switching operation.
Blower, electric heater, air cooler and liquid knocked out drum will be provided on the regeneration
line. A portion of dried gas will be utilized as regeneration gas. The regeneration gas will be heated
by an electric heater then after removing the water on the desiccants, the regent gas will be cooling
downed via the air cooler then liquid will be removed on the liquid knocked out drum. After
removing liquid on the knocked out drum, regent gas will be re-injected on the main gas line.
The valve sequences on the dryer unit will be controlled by a microprocessor on the dryer unit
package. Running and fault status on the dryer package will be transferred to Plant Control System
(PCS) for monitoring only.
This system is auto mode. No interlock system to main PCS.
2.1.4 Compressor (K-101 / / K-110)
The dry gas from dryer with operating pressure of 20.6-25 barg at 26.7-51.7 oCwill be transferred to
the storage cylinder at pressure of 250 barg through CNG compressors (K101/102/103/104/105/106/107/108/109/110). There are 10 (ten) compressor trains with 9 (nine)
compressors will be operated in parallel and 1 (one) compressor on standby mode.
Each compressor will be operated with outlet capacity of 2.3 MMSCFD at inlet pressure of 24 barg.

HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

10

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

PT. PROSIM

The compressor is reciprocating type in three stages compression, air coolers will be provided on
each discharge stage to enhance the efficiency of compressor.
The maximum discharge pressure and temperature from CNG compressor are 250 barg and 48OC
respectively. The compressor will be supplied by vendor as a skid including electrical and
instrumentation inside. Control system of CNG compressor is provided with PLC by vendor, the
operating parameter will be transferred to Plant Control System (PCS) for monitoring purpose.
Shutdown system of the compressors will be managed by PLC, trigger of shutdown such as lube oil
pressure low, suction pressure low, discharge pressure high, discharge temperature high and High
vibration will be further developed by vendor.
Compressors are driven by Gas Engine drive with fuel gas that supplied from upstream of dryer
skid.
2.1.5 CNG Cooler ( E-100)
Compressed gas from CNG compressor with temperature of 48oC will be cooled down to 35oC
before entering to CNG cylinders. Cooling water system is closed loop cooling system which
involving CNG cooler (E-100), Cooling water circulation pump (P-200A/B) and Cooling Tower (E400). The compressed natural gas need to be cooled down to 35oC for optimizing the requirement of
cylinder storage capacity. The temperature of cooling water inlet to CNG cooler (E-100) is 30oC and
temperature cooling water outlet at 39oC. To avoid prolonged overpressure due to tube rupture,
CNG Compressor would be shut downed by PSHH-0503 then CNG gas would be release to cooling
water return line to Cooling tower (E-400).
DURING DECANTING PERIOD:
Cooling water to CNG Cooler will be discontinued to produce CNG stream with temperature 48oC
and it will be commingled with CNG stream from compartment (Temperature 35 oC).
If pressure decreases and disturbing performance of CNG compressor then CNG stream could be
flowed through E-100 bypass line. Restriction orifice installed in this bypass line to giving sufficient
backpressure for CNG compressor.
2.1.6 CNG storage cylinders (V-200 1/../ 82)
CNG from E-200 will be stored at CNG storage cylinders. The CNG storage cylinders are consisting
of 95 compartment (base on 20 hours storage time at 18.7 MMSCFD CNG inlet). Each
compartment is consisting of 8 tube cylinders. One cylinder has capacity of 2.38 m3. Three CNG
compartment will be arranged in 1 (one) bank. Each bank will be provided 1 unit manual valve for
incoming and outgoing CNG. Pressure relief device (PSV) protect respectives cylinders. Discharge
PSV will be released to atmosphere and no additional pipe is required for PSV discharge line.

HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

11

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

PT. PROSIM

2.1.7 Double pipe Exchanger


Double pipe exchanger would be installed at downstream of PV-0501 to minimize temperature
drop during CNG depressuring by PV-0501 A/B. Heating media is using Hot water in outer pipe
side and CNG stream in inner pipe. Timer valve (KV) would be opened to supply hot water to outer
pipe of double pipe exchanger. Restriction orifice (RO) is provided on hot water inlet to restrict
capacity of hot water to exchanger.
If temperature at downstream PV-0501 close with -25o C, Hot water supply could be discontinued
this condition occur when pressure in compartments was dropped.
2.1.8 CNG Heat Exchanger (E-200)
The CNG Heat exchanger is required during decanting stage, this is to reheat CNG on the
downstream of pressure reducing valve. The temperature decrease due to large pressure drop in
PV0501A/B, this is called Joule Thompson effect. Temperature on the downstream can be lower
than the dew point of CNG such that condensation may occurs.
The CNG heat exchanger (E-200) maximum duty is 4100 kW (basis 4 hours decanting time) then
duty will decrease gradually as the upstream pressure is reduced during decanting process. The
initial stage of decanting, the temperature of CNG will be increased from -38oC to about 30oC. The
heating media for this heat exchanger is hot water system with temperature of 90oC. Hot water
circulation flowrate is 140 m3/hr and the flowrate to E-200 will be controlled by (TV0502).
Temperature control Valve (TV-0502) will manipulate hot water flowrate to E-200 to maintain CNG
export to the pipeline at temperature of 30oC. Temperature control is using cascade with TIC-0502.
2.1.9 Pressure reducing system (PV-0501 A/B)
The pressure of CNG outlet to PLN will be maintained at 28 barg and temperature of 30oC. PIC0501A/B are used for controlling CNG outlet pressure. Pressure reducing system will be provided
by two control valves ( PV0501A/B) with one operating and one standby.
This valve is designed base on 4 hours decanting time (96 MMSCFD).
2.1.10 Storage and Decanting process
The storage and decanting process will be performed by opening and closing delivery valve (KV0501A/B) downstream of CNG storage cylinders. Storage CNG will be carried out fixed maximum
20 hours per day and decanting will be performed 4 to 5 hours per day. During decanting period the
CNG Cooler (E-100) will be bypassed to reduced joule thomphson effect on the downstream of PV0501A/B.

HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

12

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

PT. PROSIM

Duration of decanting can be resetted from the control room, but changing setting time shall refer to
operating pressure on the CNG storage cylinders. Over pressure on the CNG cylinders will initiate
high pressure on the discharge compressor then process shutdown can be triggered.
2.1.11 Station Outlet Metering (M-200 A/B)
The metering system with 2x100% with crossover will measure natural gas outlet from CNG plant.
Total gas outlet is 113 MMSCFD for 4 hours. Metering is used as custody meter. Flow and
accumulation flow should be monitored in main PLC. For Gas composition analysis, one sampling
connection is installed at the upstream of Outlet Metering (M200A/B).
Gas Flow would be measured for 4 hours per day during decanting time. Totalizer would count total
value base on measured gasflow.
2.1.12 Waste Heat recovery Unit (E-300)
The exhaust gas from gas engines ducting will be utilized as source of energy to increase the
temperature of hot water from 63oC to 90oC. Exhaust gas from each turbine will be commingled on
header before entering WHRU, and water will be heating up on the WHRU boiler.
Hot water from WHRU will be stored on the hot water storage Tank at temperature of 90oC.
During storage phase (20 hours), WHRU would heat water in Hot water tank (T-200) for
approximately 10 hours from 30o to 90o C. The water circulating pump (P-500 A/B) with capacity of
45m3/hr is used to circulate water from T-200 through WHRU heater (E-300) and back to T-200.
During decanting phase (4 hours), Hot water pump (P-300 A/B) with capacity of 140 m3/h will
circulate hot water from T-200 to E-200 and back to T-200. Temperature of hot water in the Hot
water tank (T-200) is controlled by manipulating damper position on each exhaust gas Turbine of
CNG compressors.
2.1.13 Fuel Gas
Fuel gas is supplied for two (2) units gas engine generators (1 operation & 1 stand by) thru Fuel gas
strainer and for ten (10) units gas engine compressors (9 operation and 1 unit standby). The fuel gas
strainer is designed based on capacity of less than 1.5 MMSCFD.
Fuel Gas metering (FQI-0901) is provided to measure auxilary fuel gas consumption in CNG
facility.
2.1.14 Instrument air
The instrument air will be provided on CNG plant to enhace the overall reliability of the Plant.
Instrument air requirement is calculated based on the number of control valves and on-off control
valves plus a design margin of 20%. Three (3) Air compressors will be provided with two operating
as lead and lag basis and one compressor as a standby.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

13

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

PT. PROSIM

Instrument air system will be provided with a drying unit such that the dew point of instrument air is
less than -40oC.
2.1.15 Cooling water (E-400)
Water as cooling media will be utilized for CNG Cooler (E-100) before storage stage, The CNG
from gas compressor with temperature of 48oC will be cooled down to 35oC using cooled water.
Cooling water is supplied to the heat exchangers through the Cooling Tower Pump (P-200 A/B) at
flowrate of 35m3/hr. After taking heat of CNG, cooling water leaves heat exchanger at temperature
of 30oC is re-circulated to the Cooling Tower ( E-400) for cooling down and reused. Make-up water
will be provided to compensate water losses on the Cooling Tower (E-400).
2.1.16 Fire water system
Fire water will be taken from existing fire water system in front of CNG plant.
Fire hydrants and monitors will be located based on equipment layout during detail engineering.
2.1.17 Water treatment system (W-001)
Auxiliary water for CNG plant will be taken from well in plant. Well water will be treated by
Reverse osmisis (RO) technology prior to be used as make up water. Total consumption for make
up water is 3.2 m3/h. The feedwater to the RO unit will be design accordingly based on input from
vendor.
2.1.18 Insulation
Personnel Protection Insulation (PP) shall be specified on all lines with normal operating
temperatures above 70C. This will be applied only to sections of pipe that personnel could come
into contact with during normal operation.
Heat Conservation Insulation (HC) shall be specified for heated systems above 65C (e.g. hot water
from WHRU).
Noise Abatement Insulation (NI) shall be specified on compressor suction and discharge lines,
subject to vendor confirmation.
2.1.19 Vent System
Relief Gas from Pressure safety valves and Blow down system would be collected to vent header
then to vent stack. Automatic drain would be provided to controlling liquid level at bottom vent
stack.
Flame arrester would be installed at upstream of vent stack to avoid flame due to lightning or other
fire source.

HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

14

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

PT. PROSIM

Relief gas from CNG cylinders would be free vent to atmosphere instead of to vent header line as
per client and manufacture requirement.
The vent stack with providing water seal at the bottom of the vent stack to prevent air ingress.

HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

15

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

PT. PROSIM

3 STUDY METHODOLOGY

3.1 HAZOP
3.1.1 Overview
The study was carried out using the traditional HAZOP Guide Word method, where the system is
broken down into manageable sections and a set of standard Guide Words applied. The
methodology requires exhaustive consideration of each process activity to determine if there are any
potential problems in relation to safety or operations that may arise due to deviations in the process.
The Causes and Consequences of each deviation are identified. The HAZOP team evaluates the
severity of the problem and adequacy of existing safeguards, and where necessary, recommends
additional safeguards as Actions. The hazard and operability problems highlighted in the course of
the review were captured in the HAZOP Review worksheets (Appendix A).
3.1.2 Worksheet Definition
All concerns raised are documented in the HAZOP Review Worksheets, which include the column
headers as described in Table 3.2a.
Table 3.1a

HAZOP Review Worksheet

Column Heading
No.

Description
Reference Number

Guide word/Deviation

A set of standard guide words used to analyse and determine


potential problems that arise

Possible Causes

Causes or problems identified

Possible Consequences

Description of the consequences of the possible impact of the cause

Type

Types of issues that are involved, either Drawing Error/Comment,


Engineering, Operability, Safety, Financial and Regulatory

Safeguard

Description of the safeguards in place

Recommendations/Comment

Description of the recommendation(s) that could be in place

Action Party

Relevant party taking responsibility for action(s) identified

The completed HAZOP review worksheets are attached in Appendix A.


3.2 HAZID
3.2.1 Overview
HAZID review is used as a means to identifying potential hazards, determining the associated
consequences and evaluating means of preventing the hazard or controlling the consequences. They
should not be confused with a HAZOP review which looks at specific areas of the process to
identify potential design/operating problems and determine ways of improving the process design to
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

16

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

PT. PROSIM

prevent such incidents from occurring. A HAZID review is based on a combination of identification,
analysis and brainstorming activities. The technique exhaustively considers each review area, by
reference to an agreed set of guidewords. During the review, each facility was considered in turn
with the facility broken down according to specific areas or enclosed buildings, e.g., Main Deck.
3.2.2 Worksheet Definitions
All findings during the HAZID sessions are recorded by the scribe using HAZID worksheets. These
worksheets contain the column headings given in Table 3.3b.
Table 3.3b

HAZID Record Sheet Headings

Column Heading

Description

No.

Reference number

Category / Guideword

Initiating event and guideword used to generate hazard scenario

Event Description

Description of scenario and mode of realization

Consequence

Description of the consequences of the hazard or possible impact and


escalation of the scenario

Prevention

Existing measures to prevent the hazard from occurring

Control

Existing measures to control or mitigate the hazard to prevent escalation

Recommendation /
Comments

Actions generated during the review. Comments on the protective systems


in place, justification of the design are also included in italics.

Action Party

Responsibility for addressing each action item will be assigned to the


design team or to the project team

Ranking

Qualitative ranking of the frequency and consequence of the hazard


(carried out after the review is completed to save time during the review
itself)

HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

17

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

PT. PROSIM

4 HAZOP/HAZID REVIEW SESSIONS

4.1 INTRODUCTION
The HAZOP/HAZID review sessions were carried out at the Istana Karang Laut office in
Plaza Citiview Kemang, Jakarta, utilizing 2 days for review, over the period 17th and 21st
June 2013.
4.2 THE HAZOP/HAZID TEAM
The HAZOP/HAZID team comprises a multidisciplinary team of personnel involved with the design
and operation of the facilities, led by a safety consultant from PT PROSIM The names and
attendance records of the HAZOP/HAZID team members for each of the systems are tabulated in
Table 4.2a.
Table 4.2a

HAZOP/HAZID Team Attendance

Name

Co.

Role

June
2013

June
2013

17

21

Margaretha T

PT PROSIM

Chairman

Yulia Tirtasiwi

PT PROSIM

Scribe

Sugiyanto

PT ETI

Process Engineer

Bernardo

PT ETI

Rudolf S

PT ETI

Suarno

PT ETI

Cut Julia

PT IKL

Project Manager

Warno Abdullah

PT IKL

Engineering Manager

Suseno

PT IKL

Process Engineer

Irvan N

PT IKL

Haidar

PT IKL

Gigin Ginanjar

PT IKL

PT IKL

Isa

Process Engineer

4.3 GUIDE WORDS


The full set of Guide Words used in the HAZOP/HAZID Review is listed in Table 4.3a & b. It
should be noted that if not found to be applicable or not to produce any problem of concern that had
not already been raised, the Guide Word was not recorded in the Worksheets for that node.
Table 4.3a
No.
1
2
3
4
5
6
7

HAZOP Guide Words

Guide Word
No Flow
Less Flow
More Flow
Reverse Flow
Misdirected Flow
Less Level
More Level

HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

18

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

8
9
10
11
12
13
14
15
16
17
18
19
20
21

PT. PROSIM

Less Pressure
More Pressure
Less Temperature
More Temperature
Contaminants
Composition
Corrosion / Erosion
Instrumentation
Relief
Personnel Safety
External Factors
Operations
Maintenance
Drawing

Table 4.3b

HAZID Guide Words

Safety System

Guide Word

No.

Comments

Non Process

Structural Failures

Extreme weather/subsidence/fatigue

Events

Impact

Collisions

Transportation

Helicopter/personnel baskets/vessels

Lifting

Dropped Objects

Non Process Fires

Fires/escalated fires

Toxic Release

Chemical spill

Security

Pirates/fishermen

Noise

High noise areas/vibration

Health hazards

Diseases/working condition/chemicals

Loss of
containment

Ignition

Fires from individual process systems

Safety Systems

Ignition Sources

Escape/ Refuge

Personnel escape to TR

Communication

Hotlines/radio, etc

Emergency Lighting

Lighting during escape/ evacuation

Discharge to air

Vent/ flare/ relief, etc

Discharge to water

Produced water, etc

Discharge to soil

Gas/ water injection , etc

Waste disposal

Hazardous material/ solids/ sanitary waste,


etc.

Environmental
Hazards

4.4 DRAWINGS REVIEWED


A basic Piping and Instrumentation (P&ID) for the process acted as a basis for discussion during the
review, along with the operating procedures. The drawings used are attached in Appendix B.

HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

19

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

PT. PROSIM

4.5 SELECTED NODES


The process was initially broken down according to the step and then by each action comprising the
step. Each action was considered separately with the full list of Guide Words applied. Thus each
action becomes a node, so, for instance, each feed line into a reactor was considered as a separate
node. The nodes used are presented in Table 4.5a & b while the associated worksheets are given in
Appendix A (HAZOP) and Appendix B (HAZID).
Table 4.5a

Nodes Reviewed in HAZOP

Node

Section

Drawing Number

Rev

N1

Incoming Gas from Gundih field through Gas Scrubber V100 to Station Inlet Metering M100A/B

TS78-P-PID-001
TS78-P-PID-002

B
B

N2

Outlet Station Inlet Metering to Gas Dryer Prefilter F-100,


Gas Dryer 100A/B, Gas Dryer After Filter F-110
including Regenerator Filter

TS78-P-PID-003

N2R
N3

Regeneration System
Compression System K101 (typical for K102 to K109),
including Blowdown Tank VE301A

TS78-P-PID-003
TS78-P-PID-004

B
B

N4

Inlet CNG Cooler E-100 to CNG Compartment


(STORAGE TIME)
Inlet CNG Heat Exchanger E-200 to Station Outlet
Metering M-200A/B (DECANTING)

TS78-P-PID-005 Sheet 1 of 2

TS78-P-PID-005 Sheet 2 of 2

TS78-P-PID-006

Hot water circulation including Hot Water Tank T-200,


Hot Water Pump P300A/B and circulation to E-100 and
E-200
Waste Heat Recovery Unit include Water circulation
pump P-500A/B and WHRU
Water Treatment Plant

TS78-P-PID-007
TS78-P-PID-005 sheet 2 of 2

B
B

N5
N6

TS78-P-PID-007

TS78-P-PID-012

TS78-P-PID-011

N10

Cooling System, including Make up Water Tank T-400,


Make Up Water Pump P-100, Cooling Tower E-400 and
Cooling Tower Pump P-200 A/B
Sump Tank V-400 including Sump Tank P-400

TS78-P-PID-010

N11

Fuel Gas System

TS78-P-PID-009

N12

Instrument Air System

N13

Fire Water System

TS78-P-PID-008 Sheet 1 of 2
TS78-P-PID-008 Sheet 2 of 2
TS78-P-PID-013

N14

Power Generation system

TS78-P-PID-014

N15

Vent Gas System, including discharge of pressure


relieving device and BDVs vent header, KO Drum V-600,
up to Vent Stack VS-100

TS78-P-PID-015

N7
N8
N9

Table 4.5b

Node Reviewed in HAZID

Node
N1

Section

Drawing Number

CNG Plant Tambak Lorok

TS78-L-LY-001

HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

20

Rev
B1

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

PT. PROSIM

5 HAZOP/HAZID RESULTS

5.1 ACTIONS/RECOMMENDATIONS
A total of 40 HAZOP recommendations and 18 HAZID recommendations were generated during the
review. The recommendations would reduce potential safety or operability problems associated with
the process or improve the clarity of the process drawings (P&IDs). A complete list of the
recommendations made by the team during the review itself is tabulated in Appendix A. A unique
number is assigned to each recommendation and the node identification number is included so that it
may easily be traced back to the review worksheets (Appendix B & C). Brief summary of
highlighted recommendations are presented below.
HAZOP
Design
It was noted in the HAZOP It identified during the review and also with discussion with Tambak
Lorok, some of the valve arrangement need to be lock open to ensure that it doesnt block due to
human error (eg. at upstream BDV, by pass line). General comments also noted to provide setting
for all the instrumentation system (e.g. PIC, PSHH, PSV)
Its been reviewed that gas from suction compressor can be directed to downstream of E-200 to
metering M-200 resulting in double counting of sales gas from Gundih meter with M-100. It was
recommended to install additional check valve to PG-2"-3C-027 to prevent that case.
It recommended to provide SOP to accommodate gas release from vent of sump tank due to gas
blow by from V-100, to ensure equipment purchase suitable as per hazardous area classification and
also to nsure vent stack at sump tank is located high enough to prevent exposure to
personnel/operator at Incoming Scrubber System.
In the Waste Heat Recovery Unit, it was recommended to provide PSHH at downstream P-500A/B
to trip P-500A/B in the case of manual valve at upstream E-300 inadvertenly close resulting in
overpressure of the system.
The existing fire water capacity need to be reviewed to ensure source of water and its amount is
adequate to handle fire on the CNG plant in addition with existing fire water requirement in Tambak
Lorok.
It was discussed also that the design of floating valve T-600 to be radar type.
Maintenance and Operational
Based on the discussion raised up, its required to develop operating manual for delivery gas
including showing correlation between pressure and flow at storage period and operation of
redundant equipment such as compressor.
To control corrosion at basin cooling tower, it was recommended to provide SOP to control PH at
cooling tower periodically.

HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

21

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

PT. PROSIM

HAZID
In the HAZID session, location of the lightning stack has not identified yet, therefore it is
recommended to review the location of the lightning stack to be away from the venting stack to
reduce the probability of fire on the vent stack
It was reviewed also that high noise level around the compressor area will potentially injured the
personnel who operate the plant in daily basis. It was recommended to have noise study and provide
warning sign the area to use ear plug protection.
Fire and Gas detection was also reviewed in the HAZID, it is recommended to provide the
philosophy of the fire and gas detection system of the plant in formal documentation and provide
clear actions of each detector, which one create alarm or shut down/blowdown of the plant. Fire
detection philosophy was not provided in the building, specifically in the electrical room such as
control room/MCC/batery room. It is recommended to provide clear philosophy, e.g. providing early
warning system for smoke detection in electrical room (High Sensitivity Smoke Detector), including
fire suppression system such as portable fire extinguisher or automatic fire suppresion system (e.g.
FM-200,etc)
The scenario of fire and explosion in the CNG plant was not established yet during the review
especially in relation position of the processing facility to location where stand by personnel
available such as control room. Therefore, review of this scenario is recommended to justify design
and location of the control room building. It is include also the fire and explosion impact to
surrounding facility at Tambak Lorok. In the discussion also identified that the control room will not
provided with glass windows to avoid explosion effect from the plant, hence that CCTV is
recommended to be provided in the control room to monitor the plant.
During the review, location of the vent stack has not been identified yet. Therefore, dispersion and
radiation analysis need to be done to define safe location and height required for the vent stack.
Consideration for emergency situation was also reviewed, and it is recommended to review
emergency evacuation plan including emergency route, muster point location, safety equipment lay
out and emergency lighting.
Good communication among parties involved (Tambak Lorok and Gundih) also important to make
sure operability and deliverability of the process plant, especially to handle emergency situation.
Therefore a procedure defining internal and external communication need to be established among
parties to make sure the plant is operated safely.

HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

22

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

PT. PROSIM

5.2 MAJOR HAZARD SCENARIO


The Major Hazard of this plant is :

Process Hazard :
1. High Pressure Gas containment in the CNG Storage Tanks
2. Gas Compression System
3. Hot water circulation system
4. Cold Venting

Non Process Hazard :


5. Control Room located in hazardous area
6. Human Error - Alarm
7. Communication between ETI, IP, Gundih
8. Transportation

HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

23

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

PT. PROSIM

The hazard management plant can be shown as follow:

HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

24

JULY 2013

PT. Enviromate Technology International


PT. Pertadaya Gas

PT. PROSIM

6 HAZOP/HAZID FOLLOW-UP
The project, design and operation team should conduct a HAZOP/HAZID follow up session to
response the HAZOP/HAZID recommendations. The response and action plan shall be back up with
the relevant data and justification whether the recommendation is agreed or rejected. At the end, the
team shall formulate action plans, steward all action items and ensure that the relevant changes are
made to the design to address hazard and operability concerns identified as part of this
HAZOP/HAZID.

HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB

25

JULY 2013

PT. Enviromate Technology International

HAZOP/HAZID of CNG PLANT TAMBAK LOROK

7 REFERENCES

/1/

Process Plan Description - TS78 - P - BD - 001

/2/

Drawing List :

No

Drawing Title

Drawing Number

Rev

1
2
3
4
5

PID - Incoming Scrubber System


PID - Station Inlet Metering (M-100A/B)
PID - Gas Dryer (Vendor Package)
PID - Compressor System / K-101 (Vendor Package)
PID - Storage and Decanting System

B
B
B
B
B

PID - CNG Heat Exchanger

7
8
9

PID - Station Outlet Metering (M-200A/B)


PID - Waste Heat Recovery Unit
PID - Instrument Air System

10

PID - Instrument Air Network

11
12
13
14
15
16
17
18
19
20
21
22
23
24
19
20

PID - Fuel Gas System


PID - Sump System
PID - Cooling System
PID - Water Treatment Plant
PID - Fire Water System
PID - Power Generator System
PID - Vent Gas System
General Plant Lay Out
PFD Inlet Metering and Dryer
PFD Gas Compression System
PFD CNG Storage and Pressure Reducing System
PFD Waste Heat Recovery Unit
PFD Cooling Water System
PFD Heat Material Balance
UFD Fuel Gas System
UFD Instrument air system

TS78-P-PID-001
TS78-P-PID-002
TS78-P-PID-003
TS78-P-PID-004
TS78-P-PID-005 Sheet 1
of 2
TS78-P-PID-005 Sheet 2
of 2
TS78-P-PID-006
TS78-P-PID-007
TS78-P-PID-008 Sheet 1
of 2
TS78-P-PID-008 Sheet 2
of 2
TS78-P-PID-009
TS78-P-PID-010
TS78-P-PID-011
TS78-P-PID-012
TS78-P-PID-013
TS78-P-PID-014
TS78-P-PID-015
TS78-L-LY-001
TS78-P-PFD-001
TS78-P-PFD-002
TS78-P-PFD-003
TS78-P-PFD-004
TS78-P-PFD-005
TS78-P-PFD-006
TS78-P-UFD-001
TS78-P-UFD-002

HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BA26

B
B
B
B
B
B
B
B
B
B
B
B
B1
B
B
B
B
B
B
B
B

JULY 2013

PT. Enviromate Technology International

HAZOP/HAZID of CNG PLANT TAMBAK LOROK

Appendix A

HAZOP/HAZID Summary Recommendation

PT ENVIROMATE TECHNOLOGY INDONESIA

PT ISTANA KARANG LAUT

Appendix B - HAZOP Review Worksheet

SUMMARY HAZOP RECOMMENDATION


NODE
1

Causes / Concerns
SDV 0101 at upstream V-100
close due to failure

Consequences
Comments / Recommendations
Potential overpresurization of upstream plant (Santos Ensure existing pipeline design pressure is higher
Facility ) resulting in hydrocarbon release leading to than maximum discharge pressure from Gundih
fire or fatality
facility

Rec Number
CNG-HP-1

SDV 0101 at upstream V-100


close due to failure

Loss of Production

CNG-HP-2

Any of manual valve at


incoming line to V-100
inadvertently close
PV 0105 stuck close or manual
valve around the PV 0105
inadvertently close
Control loop malfunction
causing LV-0101 to open fully

Potential overpresurization of upstream plant (Santos Provide operating manual for delivery gas
Facility ) resulting in hydrocarbon release leading to
fire or fatality
Potential overpressurization of V-100 resulting in
Provide setting pressure PIC-0105 to show at PID
hydrocarbon release leading to fire or fatality
TS78-P

CNG-HP-3

Gas blowby to Sump Tank V-400 leading to potential Provide SOP to accommodate gas release from vent
vessel damage (design pressure 3.5 barG), fire and
of sump tank due to gas blow by from V-100
explosion

CNG-HP-5

Control loop malfunction


causing LV-0101 to open fully

Ensure equipment purchase suitable as per


hazardous area classification

CNG-HP-6

Control loop malfunction


causing LV-0101 to open fully

Gas blowby to Sump Tank V-400 leading to potential


vessel damage (design pressure 3.5 barG), fire and
explosion
Gas blowby to Sump Tank V-400 leading to potential
vessel damage (design pressure 3.5 barG), fire and
explosion

Ensure vent stack at sump tank is located high


enough to prevent exposure to personnel/operator

CNG-HP-7

Sour Gas (H2S) and water


content in the production gas
Manual by pass valve at
downstream line PG-10-30-053
from metering M100A/B to
Compressor unit unit is
inadvertenly open
Manual valve upstream BDV0301 inadvertenly close in the
event of ESD and BDV-0301
required to open
Blower E-101 at regeneration
unit damage/ not in operation

Internal corrosion of piping and vessel leading to


release of hydrocarbon gas and potential fire
Potential wet gas to Gas Compression system
resulting in equipment damage

Consider to provide corrosion coupon at upstream


V-100
LC by pass manual valve 10" at downstream line
PG-10-30-053 and update PID

CNG-HP-8

Review availability of isolation valve (SDV) from


Gundih facility in the case of overpressure from
pipeline

CNG-HP-4

CNG-HP-9

Overpresurization of upstream equipment leading to Provide Lock Open (LO) at manual valve upstream
fire/fatality
BDV-0301

CNG-HP-10

No regeneration process causing wet gas going to


compressor

Ensure interlock system install to prevent


overtemperature/overpressure in the case P-101
shutdown, Electric Heater should also shutdown
(Check with vendor)

CNG-HP-11

D-200 A-B shutdown

Potential reverse flow leading to equipment damage

Ensure D-200 A-B including regeneration system


has adequate design to accomadate reverse flow

CNG-HP-12

Switch operation between


compressors

Potential human error to operate manual valve and


safety devices

Provide operating manual for operating redundant


equipments, including compressors

CNG-HP-13

One of running compressor fails Less of CNG production


to operate

Review sizing of manual valve incoming CNG


compartment to be available at market or provide
spare manual valve in the case of maintenance
required

CNG-HP-14

Fouling/Plugging at E-100 or
loss of cooling water

Provide portable temperature detector to check skin


temperature of CNG compartment

CNG-HP-15

Loss of containment/piping leak Tube leak at E-100


due to corrosion

Provide SOP to control PH at cooling tower


periodically

CNG-HP-16

SDV0601 fails close or manual


valve in the metering station
inadvertenly closed
Gas from suction compressor
going to downstream of E-200 to
metering M-200
Manual valve upstream BDV0505 inadvertenly close in the
event of ESD and BDV-0505
required to open
Hot Water Pump P-300A/B stop
due to failure OR Strainer at
upstream P-300A/B blockage

Show setting point of PV 0501A/B

CNG-HP-17

2R

2R

Inefficiency in cooling resulting in high temperature


leading to less CNG production

Potential overpressurization of CNG HE E-200


leading to hydrocarbon release and potential fire

Double counting of sales gas from Santos meter with Install additional check valve at line PG-2"-3C-027
M-100

CNG-HP-18

Overpresurization of upstream equipment leading to Provide Lock Open (LO) manual valve at upstream
fire/fatality
BDV-0505

CNG-HP-19

Loss of hot water supply leading to inefficient heat


transfer and lower gas sales temperature

CNG-HP-20

Provide low temperature switch at line PG-12"-3C021 to close KV-0503 A to prevent low temperature
in the gas sales

Hot Water Pump P-300A/B stop High temperature in the circulation water around the Provide low temperature alarm at line PG-12"-3Cdue to failure OR Strainer at
waste heat recovery unit
021 to alert operator
upstream P-300A/B blockage

CNG-HP-21

Three way valve TV-0502 to E- Loss of hot water supply leading to inefficient heat
200 is inadvertenly close
transfer and lower gas sales temperature
Any manual valve at upstream E- Potential overpressure of downstream pump
300 inadvertenly close or check
One or more gas engine driver
Less of flue gas to E-300 resulting in lower
shutdown
temperature generated for water circulation

CNG-HP-22

7
7

Start up

Condense water from flue gas at Corrosion at E-300 leading to equipment damage
E-300

CNG PLANT TAMBAK LOROK

Provide Temperature Control Valve at bypass line


of E-200
Vendor to provide minimum flow recycle line at P500A/B
Review requirement set point of TIA-0704

Low gas temperature from exhaust gas compressor to Provide drain line at lowest point gas ducting E-300
WHRU resulting condensation at gas ducting E-300

Page 1 of 2

Review requirement TIA-0705

CNG-HP-23
CNG-HP-25

CNG-HP-26

CNG-HP-27

SUMMARY HAZOP RECOMMENDATION

PT ENVIROMATE TECHNOLOGY INDONESIA

NODE
7
9

10

Causes / Concerns
Drawing
Manual valve at outlet T-100 is
inadvertenly close or strainer
blocked
Manual valve or strainer at inlet
Basin cooling water is
inadvertently close
Manual valve at upstream P200A/B inadvertenly close or
strainer blocked
Liquid control valve failure at
individual equipments (V-300,
Compressor K-101-109, V-100)

PT ISTANA KARANG LAUT

Appendix B - HAZOP Review Worksheet

Consequences

Comments / Recommendations
Revise drawing TS78-P-PID-007 to show setting
point of all instrumentation alarm and trip

Rec Number
CNG-HP-28

Loss of pump suction and potential pump damage

Provide lock open (LO) for manual valve upstream


P-100 and P-600

CNG-HP-29

Potential overflow at T-600

Review design of floating valve T-600 to be radar


type

CNG-HP-30

Loss of pump suction and potential pump damage

Provide lock open (LO) for manual valve upstream


P-200

CNG-HP-31

Build up pressure in Sump Tank V-400 leading to


potential overpressurization

Review outlet line at venting V-400 to be sufficient


for case high pressure gas introduced from
upstream equipment to this vessel

CNG-HP-32

11

3" Manual valves at


Loss of fuel gas supply leading to compressor
incoming/outgoing line Fuel
shutdown
Gas filter is inadvertently closed

Provide lock open (LO) for 3" manual valves at


upstream and downstream Fuel Gas Filter

CNG-HP-33

12

Manual valve upstream of


Instrument Air Receiver V-300
inadvertently closed

Potential overpressurization of upstream piping

Confirm availability of high pressure trip at


internal of Air Compressor C300A/B/C package to
shut down compressor in the case of block of
discharge

CNG-HP-34

12

Loss of instrument air supply potentially leading to


PSD

Lock Open (LO) for manual valve downstream


Instrument Air Receiver V-310

CNG-HP-35

13

Manual valve downstream


Instrument Air Receiver V-310
inadvertently closed
Operation

Review existing Tambak Loroks fire water capacity


to be adequate for fire water handling in CNG
Plant

CNG-HP-36

13

Operation

Consider to provide additional flowmeter to


measure fire water consumption for Tambak Lorok

CNG-HP-37

14

Any manual valve down stream Overheating at GE-100A leading to equipment


GE-100A to cooling system
damage
inadvertenly close

Confirm availability of TSHH to trip Gas


Generator GE-100A in case of high temperature has
been included in the generator package.

CNG-HP-38

14

Any manual valve down stream Overheating at GE-100A leading to equipment


GE-100A to cooling system
damage
inadvertenly close
Lighting struck during
Fire at vent stack
PSV/BDV release

Lock Open (LO) for manual valve downstream GE100A

CNG-HP-39

Consider to install CO2 snuffing system at VS-100


to extinguish fire at vent stack completed with
fusible plug

CNG-HP-40

15

CNG PLANT TAMBAK LOROK

Page 2 of 2

SUMMARY HAZOP RECOMMENDATION

PT. ENVIROMATE TECHNOLOGY INTERNATIONAL

PT ISTANA KARANG LAUT

Appendix A SUMMARY HAZOP/HAZID

SUMMARY HAZID RECOMMENDATION


HAZID
No.
4.1.3

Hazard Description

Consequences

Lightning

Possible damage to the


equipment and potential
fire

Prevention

4.3.1

Light vehicles impact


e.g. Car

Potential impact to
piping/equipment
leading to hydrocarbon
release, fire, personnel
injury/fatality and asset
damage
High noise level from Potential personnel ear compressor and gas
injury
engine area
Toxic Material during Personnel injury
MSDS provided in the
handling chemical: for
storage facility
cooling water,
corrosion inhibitor e.g.
oxygen scavanger

4.7.1

4.8.1

Control

Recommendation/ Comment

Rec Number

Co.

Pr

Ri

Type

S (4)
C(3)

S (H16)
C(H12)

Design

S (4)
C(4)

S (H8)
C(H8)

Operation /
Maintenance

CNG-HD- 3

S (1)
C(-)

S (H3)
C(-)

Design

Ensure portable eye wash station CNG-HD- 4


provided during chemical
handling (e.g : at control room,
loading area and water treatment
area)

S (1)
C(-)

S (H3)
C(-)

Design

Grounding provided
for each equipment

Update EQL drawing to show


CNG-HD- 1
Lightning protection at CNG
compartment area (lightning
stack) in process/utility area
vehicle park area away Operation cars shall be equipped CNG-HD- 2
from process area
with flame arrestor and diesel
engine

Provide SOP to wear ear plug


around noise area

4.8.3

Hazardous waste
disposal

Personnel injury during PPE - hand gloves,


handling waste disposal face shield

Alocate waste disposal resulting


from operation/construction
activity in safe area (third party)

CNG-HD- 5

S (1)
C(-)

S (H3)
C(-)

Operation /
Maintenance

4.9.6

Hot Surfaces at
exhaust gas, WHRU
and heat exchanger (E200)
Leak from Process
Equipment

Potential injury due to


exposure to heat

PPE

Provide warning sign around


hot surface equipment and
pipings

CNG-HD- 6

S (2)
C(-)

S (M4)
C(-)

Design

4.10.1

Loss of Containment

personal protection
insulation provided

Release of hydrocarbon Unit SD by low


resulting in potential
pressure trip
fire/explosion leading to
injury/fatality
Release of hydrocarbon NA
resulting in potential
fire/explosion leading to
injury/fatality

Gas detection system


at process area

Define philosophy of fire and


gas detection system and
develop fire and gas detection
area at process plant
Fire hydrant provided Regularly to check temperature
with source from
in the MCC cabinet and DCS
existing IP
panel to monitor short circuit
and provide portable fire
extinguisher

CNG-HD- 7

S (4)
C(4)

S (H8)
C(H8)

Design

CNG-HD- 8

S (4)
C(4)

S (H8)
C(H8)

Operation /
Maintenance

Heat & Smoke


detector, Portable Fire
Extinguisher provided
at control room &
MCC room
Lightning protection
provided at CNG
compartment area

Regularly to check temperature


in the MCC cabinet and DCS
panel to monitor short circuit
and provide portable fire
extinguisher
Define safe location and
minimum height required for
vent stack and vent location to
be suitable with wind directions
so that dispersed gas will not be
exposed to process plan

CNG-HD- 9

S (4)
C(4)

S (H8)
C(H8)

Operation /
Maintenance

CNG-HD- 10

S (4)
C(4)

S (H8)
C(H8)

Design

ERP

Provide emergency evacuation


risk analysis to determine safe
evacuation route and location of
muster area

CNG-HD- 11

S (4)
C(4)

S (H8)
C(H8)

Design

CNG-HD- 12

S (4)
C(4)

S (H8)
C(H8)

Operation /
Maintenance

Heat and Smoke


detector

Form emergency response team


(ERT) and conduct emergency
drill
Review scenario of fire and
explosion from gas plant to the
area of standby personnel such
as control room and provide
mitigation plan (design and
location of the building) to
anticipate fire/explosion

CNG-HD- 13

S (4)
C(4)

S (H8)
C(H8)

Design

S (4)
C(4)

S (H8)
C(H8)

Design

Define safety requirement on


CNG-HD- 14
control room specification to
accommodate fire/explosion
scenario e.g. door, wall and
window specifications
Consider to provide CCTV in the CNG-HD- 15
control room for monitoring
purpose
Define internal and external
CNG-HD- 16
communication system (PABX)
for connecting operator in the
control room to outside parties

S (4)
C(4)

S (H8)
C(H8)

Design

S (4)
C(4)

S (H8)
C(H8)

Design

Define safety layout at CNG


plant to show ESD push button,
fire hydrant, etc

S (4)
C(4)

S (H8)
C(H8)

Design

4.11.1

Battery

Fire/explosion in the
event of hydrocarbon
release.

4.11.2

Vent

Fire/explosion in the
event of hydrocarbon
release in process area if
stroke by lightning

4.12.1

Fire on Plant area

Personnel trap/ unable


to evacuate leading to
injury/fatality

4.14.1

Control room

Fire or explosion from


process area impact to
control room leading to
potential personnel
injury/fatality

Inability to monitor
process area

Battery room is
located in non
hazardous area

4.15.1

Inability to contact
control room within
emergency

Inability to coordinate
Each operator
response leading to
provided with hand
potential major accident held radio
leading to personnel
injury/fatality and asset
loss

F&G alarm system

4.16.1

Inability to initiate
ESD

Inability to control fire


Local ESD push
leading to potential
button at control
major accident leading to room
personnel injury/fatality
and asset loss

4.18.3

Blowdown of water
from cooling tower,
discharge RO

Potential contamination
from process fluid

CNG PLANT TAMBAK LOROK

Discharge water is
Define Sampling point Define Sampling point to
connected to existing to monitor discharge monitor discharge water
canal (IP)
water

Page 1 of 1

CNG-HD- 17

CNG-HD- 18

HAZID Worksheet Summary

PT. Enviromate Technology International

HAZOP/HAZID of CNG PLANT TAMBAK LOROK

Appendix B

HAZOP Review Worksheets

PT ENVIROMATE TECHNOLOGY INDONESIA

Appendix B - HAZOP Review Worksheet

Node
1
Review date 17-Jun-13
Client
Project
Facility
Section

Comment
Design
Intent

Abbreviations

PT ENVIROMATE TECHNOLOGY INTERNATIONAL


Compressed Natural Gas Plant
Tambak Lorok
Incoming Gas from Gundih field through Gas Scrubber V-100 to
Station Inlet Metering M100A/B

PT. ISTANA KARANG LAUT

SOP
IM

Standard Operating Procedures


Inspection & Maintenance

PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C

Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk

To remove any hydrocarbon liquid from upstream facility and measure natural gas inlet to CNG plant

Design
DP : 34 barG
Conditions:

DT: 65 deg C

Opt.
Conditions

OP : 20.6-30.9 barG

Drawing

PID - Incoming Scrubber System


PID - Station Inlet Metering (M-100A/B)

No.

Guide
Words
Parameter: Flow
1.1.1
No

Deviation

No Flow

OT : 26.7-51.7 deg C

Capacity Flowrate : 20 MMSCFD


TS78-P-PID-001
TS78-P-PID-002

Causes / Concerns

SDV 0101 at upstream V-100 close


due to failure

Consequences

Safeguards

Potential overpresurization Pressure regulator (PV) at


of upstream plant (Gundih upstream facility to adjust
Facility ) resulting in
discharge pressure
hydrocarbon release
leading to fire or fatality

Initiating
L

Co

Pr

S (4)
C(4)

Ri
Ri

S (M4)
C(M4)

Loss of Production

1.1.2

No

No Flow

Any of manual valve at incoming


line to V-100 inadvertently close

Potential overpresurization Pressure regulator (PV) at


of upstream plant (Gundih upstream facility to adjust
Facility ) resulting in
discharge pressure
hydrocarbon release
leading to fire or fatality

S (4)
C(4)

S (M4)
C(M4)

Comments / Recommendations

B
B

Rec. No.

Ensure existing pipeline design


pressure is higher than maximum
discharge pressure from Gundih
facility

CNG-HP-1

Review availability of isolation


valve (SDV) from Gundih facility
in the case of overpressure from
pipeline

CNG-HP-2

Provide operating manual for


delivery gas

CNG-HP-3

Loss of Production

CNG PLANT TAMBAK LOROK

Page 1 of 53

HAZOP Node N1

PT ENVIROMATE TECHNOLOGY INDONESIA

No.
1.1.3

1.1.4

Guide
Words
No

No

Appendix B - HAZOP Review Worksheet

Deviation
No Flow

No Flow

Causes / Concerns

Co

Pr

Ri

PV 0105 stuck close or manual valve Potential


PIH-0103 set at 31 barg as
around the PV 0105 inadvertently
overpressurization of V-100 high pressure alarm to
close
resulting in hydrocarbon
alert operator
release leading to fire or
fatality
PIHH-0103 set at 33 barG
to close SDV-0101
PSV 0101A/B set at 34
barG is sized for fire case

S (4)
C(4)

S (M4)
C(M4)

Any of manual valves at Station Inlet Potential overpresurization PIH-0103 set at 30 barg as
Metering M100A/B inadvertently
of upstream M-100A/B
high pressure alarm to
close
resulting to fire or fatality alert operator

S (4)
C(4)

S (M4)
C(M4)

S (-)
C(2)

S (-)
C(L2)

1.2.1

Less

Less Flow

Refer to No Flow - manual valves


partially closed

1.3.1

More

More Flow

Slugging

1.4.1

Reverse

Reverse Flow

1.5.1

Part of

Misdirected Flow No additional significant issues of


concerns identified

1.5.1

Part of

Misdirected Flow No additional significant issues of


concerns identified

No additional significant issues of


concerns identified

Consequences

Safeguards

PT. ISTANA KARANG LAUT

Initiating
L

Comments / Recommendations
Provide setting pressure PIC-0105
to show at PID TS78-P

Rec. No.
CNG-HP-4

Note : maximum upstream pressure


from Gundih is not more than 34 barG

PIHH-0103 set at 33 barG


to close SDV-0101
PSV 0101A/B set at 34
barG is sized for block
discharge

High level at V-100 leading Slug Catcher provided at


to liquid carry over to
Gundih facility
metering skid M-100 and
downstream equipment
LV-0101 will maintain
level in Gas Scrubber V100
LIH-0102 as high level
alarm to alert operator
LIHH-0102 will close SDV0102

Parameter: Level

CNG PLANT TAMBAK LOROK

Page 2 of 53

HAZOP Node N1

PT ENVIROMATE TECHNOLOGY INDONESIA

No.
1.6.1

Guide
Words
Less

Appendix B - HAZOP Review Worksheet

Deviation
Less Level

Causes / Concerns

Consequences

Safeguards

Control loop malfunction causing LV- Gas blowby to Sump Tank LIL-0102 alarm to alert
0101 to open fully
V-400 leading to potential Operator
vessel damage (design
pressure 3.5 barG), fire and
explosion
LILL-0102 to initiate
shutdown of SDV-0102

PT. ISTANA KARANG LAUT

Initiating
L

Co

Pr

Ri

Comments / Recommendations

S (4)
C(4)

S (M4)
C(M4)

Provide SOP to accommodate gas


release from vent of sump tank due
to gas blow by from V-100

CNG-HP-5

Ensure equipment purchase


suitable as per hazardous area
classification

CNG-HP-6

Ensure vent stack at sump tank is


located high enough to prevent
exposure to personnel/operator

CNG-HP-7

Sump Tank open to


atmosphere
1.6.2

Less

Less Level

1.7.1

More

More Level

1.7.2

1.7.3

1.7.4

More

More

More

More Level

More Level

More Level

CNG PLANT TAMBAK LOROK

Manual valve at bypass line LV-0101


or manual drain valves
inadvertently open, leak at liquid
lines

Gas blowby to Sump Tank LIL-0102 alarm to alert


V-400 leading to potential Operator
vessel damage (design
pressure 3.5 barG), fire and
explosion
LILL-0102 to initiate
shutdown of SDV-0102
Sump Tank open to
atmosphere
Control loop malfunction causing LV- High level at V-100 leading LIH-0102 as high level
0101 to stuck close
to liquid carry over to
alarm to alert Operator to
metering skid M-100 and
open by pass line
downstream equipment

Any of manual valve


upstream/downstream LV-0101
inadvertently close

SDV-0102 fails closed

Slugging

LIHH-0102 to initiate
shutdown of SDV-0101
High level at V-100 leading LIH-0102 as high level
to liquid carry over to
alarm to alert Operator to
metering skid M-100 and
open by pass line
downstream equipment

S (4)
C(4)

S (M4)
C(M4)

S (-)
E (2)
C(2)

S (-)
E (L2)
C(L2)

S (-)
C(2)

S (-)
C(L2)

S (-)
C(2)

S (-)
C(L2)

Rec. No.

LIHH-0102 to initiate
shutdown of SDV-0101
High level at V-100 leading LIH-0102 as high level
to liquid carry over to
alarm to alert Operator to
metering skid M-100 and
open by pass line
downstream equipment
LIHH-0102 to initiate
shutdown of SDV-0101
High level at V-100 leading LIH-0102 as high level
to liquid carry over to
alarm to alert Operator to
metering skid M-100 and
open by pass line
downstream equipment

Page 3 of 53

HAZOP Node N1

PT ENVIROMATE TECHNOLOGY INDONESIA

No.

Guide
Words

Deviation

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Consequences

Safeguards

PT. ISTANA KARANG LAUT

Initiating
L

Co

Pr

Ri

S (4)
C(4)

S (M4)
C(M4)

S (-)
E (2)
C(2)

S (-)
E (L2)
C(L2)

S (-)
C(2)

S (-)
C(L2)

S (4)
C(4)

S (M4)
C(M4)

Comments / Recommendations

Rec. No.

LIHH-0102 to initiate
shutdown of SDV-0101
as
1.8.1

1.8.2
1.9.1

Less

Less
More

Less Pressure

Less Pressure
More Pressure

Loss of containment/piping leak


due to corrosion

Release of hydrocarbon
PIL-0102 as low pressure
leading to environmental alarm at incoming V-100
pollution and potential fire to alert operator
PILL-0102 at incoming V100 will initiate closure of
SDV 0101
Fire and Gas Detector at V100

Refer to Misdirected Flow 1.5.1


Refer to No Flow 1.1.1, 1.1.2, 1.1.3,
1.1.4 ; Less Level 1.6.1, 1.6.2
PV-0105 stuck open

Manual valve at by pass line PV0105 inadvertently open

Potential overpressure at
Metering M100A/B and
downstream equipment

PIH-S01 set at 30 bar as


high pressure alarm to
alert operator

Potential overpressure at
Metering M100A/B and
downstream equipment

PSH 0301A/B at 32 barG


to close SDV-0101
PIH-S01 set at 30 bar as
high pressure alarm to
alert operator
PSH 0301A/B at 32 barG
to close SDV-0101

Parameter: Temperature
1.10.1
Less
Less Temperature No additional significant issues of
concerns identified
1.11.1

More

More temperature No additional significant issues of


concerns identified

Parameter: Contamination
1.12.1
As Well
Contamination
As

No additional significant issues of


concerns identified

Parameter: Composition
1.13.1
Other
Composition
Than

No additional significant issues of


concerns identified

Parameter: Corrosion / Erosion


1.14.1
Other
Corrosion /
Than
Erosion

Sour Gas (H2S) and water content in Internal corrosion of piping


the production gas
and vessel leading to
release of hydrocarbon gas
and potential fire

Wall thickness of piping


and equipment already
considered sour gas
condition

Consider to provide corrosion


coupon at upstream V-100

CNG-HP-8

Parameter: Instrumentation

CNG PLANT TAMBAK LOROK

Page 4 of 53

HAZOP Node N1

PT ENVIROMATE TECHNOLOGY INDONESIA

No.
1.15.1

Guide
Words
Other
Than

Parameter: Relief
1.16.1
Other
Than
Parameter: Safety
1.17.1
Other
Than

Deviation

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Instrumentation

No additional significant issues of


concerns identified

Relief

No additional significant issues of


concerns identified

Occupational
Safety

No additional significant issues of


concerns identified

Parameter: External Factor


1.18.1
Other
External Factors
Than
Parameter: Operation & Maintenance
1.19.1
Other
Operations
Than

Fire at plant

Overpresurization of
piping leading to
equipment damage

Safeguards

Fire and Gas Detector at V100

Initiating
L

Co

Pr

Ri

S (-)
C(2)

S (-)
C(L2)

Comments / Recommendations

Rec. No.

No additional significant issues of


concerns identified

1.20.1

Other
Than

Maintenance

Single isolation valve for


Maintenance of PSV-0101A/B

1.20.2

Other
Than

Maintenance

No additional significant issues of


concerns identified

Parameter: Drawing
1.21.1
Other
Than

Consequences

PT. ISTANA KARANG LAUT

Potential exposure of high NA


pressure to personnel
during maintenance of PSV0101A/B

Note: Certification/testing of PSV is


conducted during online operation
without dismantle of PSV itself.
Dismantle of PSV can only be
conducted if there is a risk assessment
for single valve at upstream of the PSV

Drawing

CNG PLANT TAMBAK LOROK

Page 5 of 53

HAZOP Node N1

PT ENVIROMATE TECHNOLOGY INDONESIA

Node

Appendix B - HAZOP Review Worksheet

Abbreviations

Review date 17-Jun-13


Client
Project
Facility
Section

Comment
Design
Intent

SOP

Standard Operating Procedures

IM

Inspection & Maintenance

PT ENVIROMATE TECHNOLOGY INTERNATIONAL


Compressed Natural Gas Plant
Tambak Lorok
Outlet Station Inlet Metering to Gas Dryer Prefilter F-100, Gas
Dryer 100A/B, Gas Dryer After Filter F-110 including Regenerator
Filter

PM
Preventative Maintenance
USD
Unit Shutdown
PSD
Process Shutdown
ESD
Emergency Shutdown
H,M,L
High, Medium, Risk
Co
Consequence
Pr
Probability
Ri
Risk
S
Safety Risk
C
Commercial Risk
One bed of dryer will be on drying mode and the other one is on regenerating mode. Adsorption time is 4-8 hours and the regeneration time 4-8 hours (heating, cooling and standby)
To remove water and H2S content on the feed gas to produce moisture dew point to -40 deg C and max 3 ppm H2S

Design
DP : 34 barG
Conditions:
Opt.
OP : 20.6-30.9 barG
Conditions
Drawing

PT. ISTANA KARANG LAUT

DT: 250 deg C


OT : 26.7-51.7 deg C

PID - Gas Dryer (Vendor Package)

No.

Guide
Words
Parameter: Flow
2.1.1
No

Deviation

No Flow

Capacity Flowrate : 20 MMSCFD


TS78-P-PID-003

Drawing No.

Causes / Concerns

Any of manual valve at Gas Dryer


package is inadvertenly close

Consequences

Safeguards

Potential
PIH 0102 alarm set at 30
overpressurization of
barG to alert Operator
upstream equipment of D100 leading to rupture and
potential fire event
PIHH 0102 set at 33 barG to
initiate closure of SDV 0101

Initiating
L

Co

Pr

Ri

S (4)
C(4)

S (M4)
C(M4)

S (4)
C(4)

S (M4)
C(M4)

Comments / Recommendations

Rev:

Action Party

Rec. No.

PSV 0101A/B set at 33 barg


2.2.1

Less

Less Flow

F-100 Blockage

Potential
PIH 0102 alarm set at 30
overpressurization of
barG to alert Operator
upstream equipment of D100 leading to rupture and
potential fire event
PIHH 0102 set at 33 barG to
initiate closure of SDV 0101
PSV 0101A/B set at 33 barg
PDI at F-100 as local
indicator for operator

CNG PLANT TAMBAK LOROK

Page 6 of 53

HAZOP Node N2

PT ENVIROMATE TECHNOLOGY INDONESIA

No.

2.2.2

Guide
Words

Less

Deviation

Less Flow

Appendix B - HAZOP Review Worksheet

Causes / Concerns

D-100A/B Blockage (caking)

Consequences

Co

Pr

Ri

S (4)
C(4)

S (M4)
C(M4)

S (4)
C(4)

S (M4)
C(M4)

Depressurization of the
BDV position indication
system, loss of gas to flare and alarm
and loss of production

S (-)
C(3)

S (-)
C(M3)

S (4)
C(4)

S (M4)
C(M4)

Potential wet gas to Gas


Compression system
resulting in equipment
damage
Potential
overpressurization of
upstream equipment of D100 leading to rupture and
potential fire event

Safeguards

Initiating
L

PT. ISTANA KARANG LAUT

Comments / Recommendations

Action Party

Rec. No.

AIH (dew point alarm) at


downstream of Dryer unit

PSH 0301A set at 32 bar at


Gas Dryer D-100A/B to
close SDV-0101

PSV 0301A set at 34 barG is


sized for block discharge
PDSH for Local indicator at
D-100A/B for operator
AIH (dew point alarm) at
downstream of Dryer unit

Potential wet gas to Gas


Compression system
resulting in equipment
damage
Potential
PSV 0301A set at 34 barG is
overpressurization of
sized for block discharge
upstream equipment of D100 leading to rupture and
potential fire event
PDI at F-110 as local
indicator for operator
Potential wet gas to Gas
AIH (dew point alarm) at
Compression system
downstream of Dryer unit
resulting in equipment
damage

2.2.3

Less

Less Flow

F-110 Blockage

2.2.4

Less

Less Flow

see No Flow 2.1.1 For partial blockage

2.3.1

More

More Flow

BDV-0301 open due to failure

2.4.1

Reverse

Reverse Flow

No additional significant issues of


concerns identified

2.5.1

Part of

Misdirected Flow Refer to More Flow 2.3.1

2.5.2

Part of

Misdirected Flow Manual valve at 1/2-in drain line


inadvertently open/leak or liquid
trap at F-100 and F-110 stuck open

Gas blowby to Sump Tank SOP/Maintenance of liquid


leading to gas cloud and
trap
potential fire and explosion

2.5.3

Part of

Misdirected Flow Manual bypass line of F-100 is


inadvertenly open

Potential condense liquid


carry over to D-100
resulting in equipment
damage

CNG PLANT TAMBAK LOROK

SOP

Page 7 of 53

HAZOP Node N2

PT ENVIROMATE TECHNOLOGY INDONESIA

No.
2.5.4

Guide
Words
Part of

2.5.5

Part of

2.5.6

Part of

Deviation

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Consequences

Misdirected Flow Manual bypass line of F-110 is


inadvertenly open

Safeguards

Potential condense liquid


carry over to compressor
unit resulting in
equipment damage
Misdirected Flow Manual valve to regeneration unit is Ineffective regeneration
inadvertenly open
process in Gas Dryer D100A/B

SOP

Misdirected Flow Manual by pass valve at


downstream line PG-10-30-053 from
metering M100A/B to Compressor
unit unit is inadvertenly open

SOP

Parameter: Level
2.6.1
Less
2.7.1
More

Less Level
More Level

Refer to Misdirected Flow 2.5.2


Liquid trap of F-100 stuck close

Parameter: Pressure
2.8.1
Less

Less Pressure

Loss of containment/leak on D-100


due to corrosion

2.8.2
2.9.2

Less
More

Less Pressure
More Pressure

Refer to More Flow 2.3.1


See No Flow 2.1.1, 2.1.2, 2.2.1,
Misdirected Flow 2.5.2

2.9.1

More

More Pressure

Liquid trap of F-100 stuck open

2.9.

More

More Pressure

Potential wet gas to Gas


Compression system
resulting in equipment
damage

Initiating
L

PT. ISTANA KARANG LAUT

Co

Pr

Ri

Comments / Recommendations

S (-)
C(3)

S (-)
C(M6)

LC by pass manual valve 10" at


downstream line PG-10-30-053
and update PID

S (4)
C(4)

S (M4)
C(M4)

S (4)
C(4)

S (M4)
C(M4)

Action Party

Rec. No.

PSV 0301B set at 34 barG is


sized for block discharge
CNG-HP-9

High level at F-100 leading SOP to open by pass


to liquid carry over to Gas manual valve 1/2"
Dryer D-100A/B

Release of hydrocarbon
leading to environmental
damage and potential fire

Fire and gas detection


system

Low level at F-100 leading Sump tank connected to


to gas blow by to Sump
atmospheric
Tank
Manual valve upstream BDV-0301 Overpresurization of
NA
inadvertenly close in the event of
upstream equipment
ESD and BDV-0301 required to open leading to fire/fatality

Provide Lock Open (LO) at


manual valve upstream BDV0301

CNG-HP-10

Parameter: Temperature
2.10.1
Less
Less Temperature No additional significant issues of
concerns identified
2.11.1

More

More temperature No additional significant issues of


concerns identified

Parameter: Contamination
2.12.1
As Well
Contamination
As

No additional significant issues of


concerns identified

Parameter: Composition
2.13.1
Other
Composition
Than

No additional significant issues of


concerns identified

Parameter: Corrosion / Erosion

CNG PLANT TAMBAK LOROK

Page 8 of 53

HAZOP Node N2

PT ENVIROMATE TECHNOLOGY INDONESIA

No.
2.14.1

Guide
Words
Other
Than

Appendix B - HAZOP Review Worksheet

Deviation
Corrosion /
Erosion

Causes / Concerns

Sour Gas (H2S) and water content in Internal corrosion of piping


the production gas
and vessel leading to
release of hydrocarbon gas
and potential fire

Parameter: Instrumentation
2.15.1
Other
Instrumentation
Than

No additional significant issues of


concerns identified

Parameter: Relief
2.16.1
Other
Than

Relief

No additional significant issues of


concerns identified

Occupational
Safety

No additional significant issues of


concerns identified

Parameter: Safety
2.17.1
Other
Than

Parameter: External Factor


2.18.1
Other
External Factors
Than
Parameter: Operation & Maintenance
2.19.1
Other
Operations
Than
2.20.1

Other
Than

Parameter: Drawing
2.21.1
Other
Than

Fire

Safeguards
Wall thickness of piping
and equipment already
considered sour gas
condition

Overpresurization of drier F & G


leading to equipment
damage

Initiating
L

Co

Pr

Ri

S (3)
C(4)

S (M3)
C(M4)

S (-)
C(2)

S (-)
C(M4)

Comments / Recommendations

Action Party

Rec. No.

No additional significant issues of


concerns identified

Maintenance

No additional significant issues of


concerns identified

Drawing

No additional significant issues of


concerns identified

CNG PLANT TAMBAK LOROK

Consequences

PT. ISTANA KARANG LAUT

Page 9 of 53

HAZOP Node N2

PT ENVIROMATE TECHNOLOGY INDONESIA

Appendix B - HAZOP Review Worksheet

2R
Node
Review date 17-Jun-13
Client
Project
Facility
Section

Comment
Design
Intent
Design
Opt.
Drawing

Abbreviations

PT. ISTANA KARANG LAUT

SOP
IM

Standard Operating Procedures


Inspection & Maintenance

PT ENVIROMATE TECHNOLOGY INTERNATIONAL


Compressed Natural Gas Plant
Tambak Lorok
Regeneration System

PM
Preventative Maintenance
USD
Unit Shutdown
PSD
Process Shutdown
ESD
Emergency Shutdown
H,M,L
High, Medium, Risk
Co
Consequence
Pr
Probability
Ri
Risk
S
Safety Risk
C
Commercial Risk
One bed of dryer will be on drying mode and the other one is on regenerating mode. Adsorption time is 12 hours and the regeneration time 12 hours (heating, cooling and standby)
To collect water from the dryer and refresh molecular sieves to be ready to absorb
DP : 34 barG
OP : 20.6-30.9 barG
PID - Gas Dryer (Vendor Package)

No.

Guide
Words
Parameter: Flow
2R.1.1
No

Deviation

No Flow

DT: 250 deg C


OT : 26.7-51.7 deg C

Capacity Flowrate : 20 MMSCFD


TS78-P-PID-003

Drawing No.

Causes / Concerns

Consequences

Manual valve to regeneration system No regeneration process


inadvertenly close
causing wet gas going to
compressor

Safeguards

F-101 to collect any


condense liquid

Initiating
L

Co

Pr

Ri

S (-)
C(3)

S (-)
C(M3)

S (-)
C(3)

S (-)
C(M3)

S (-)
C(3)

S (-)
C(M3)

Comments / Recommendations

Rev:

Action Party

Rec. No.

AIH (dew point alarm) at


downstream of Dryer unit
Back up dryer available

2R.1.2

2R.1.3

No

No

No Flow

No Flow

Blower E-101 at regeneration unit


damage/ not in operation

F-102 blockage

No regeneration process
causing wet gas going to
compressor

Potential
AIH (dew point alarm) at
overtemperature/overpres downstream of Dryer unit
sure at gas regeneration
system
Back up dryer available
Pump cavitation
Regular Filter mainentance

Overpressurization of
equipment upstream of F102 leading to equipment
damage

CNG PLANT TAMBAK LOROK

F-102 to collect any


condense liquid

Ensure interlock system install to prevent


overtemperature/overpressure in the case P-101
shutdown, Electric Heater should also
shutdown
(Check with vendor)

CNG-HP-11

PSH-0301B alarm to alert


Operator

Page 10 of 53

HAZOP Node N2R

PT ENVIROMATE TECHNOLOGY INDONESIA

No.
2R.2.1

Guide
Words
Less

Deviation
Less Flow

2R.2.
2R.3.1

Less
More

Less Flow
More Flow

2R.4.1

Reverse

Reverse Flow

2R.5.1

Part of

2R.5.

Part of

#N/A
Part of
Parameter: Level
2R.6.1
Less
2R.7.
More

Appendix B - HAZOP Review Worksheet

Causes / Concerns
F-102 partially blocked

Consequences

Safeguards

Pump cavitation

Regular Filter maintenance

Overpressurization of
equipment upstream of F102 leading to equipment
damage

PSH-0301B alarm to alert


Operator

Initiating
L

PT. ISTANA KARANG LAUT

Co

Pr

Ri

S (-)
C(3)

S (-)
C(M3)

S (-)
C(3)

S (-)
C(M3)

S (4)
C(4)

S (M4)
C(M4)

S (4)
C(4)

S (M4)
C(M4)

S (-)
C(3)

S (-)
C(M3)

S (4)
C(4)

S (M4)
C(M4)

Comments / Recommendations

Action Party

Rec. No.

No additional significant issues of


concerns identified
D-200 A-B shutdown

Potential reverse flow


leading to equipment
damage

potential more flow at D- AIH (dew point alarm) at


100 A-B resulting potential downstream of Dryer unit
offspec to compressor
leading to compressor
damage
PIL 501 at SS-101 as Low
pressure alarm to alert
operator
PILL 501 at SS-101 to
shutdown SDV-151
Misdirected Flow Manual valve at drain line of F-102 Gas blowby to Sump Tank Sump Tank connected to
or separator after cooler
leading to gas cloud and
Atmospheric
inadvertently open/leak
potential fire and explosion
Misdirected Flow Liquid trap at F-102 or at separator
after cooler stuck open

Gas blowby to Sump Tank Sump Tank connected to


leading to gas cloud and
Atmospheric
potential fire and explosion

Ensure D-200 A-B including regeneration


system has adequate design to accomadate
reverse flow

CNG-HP-12

Liquid trap maintenance


Less Level
More Level

See Misdirected flow 2R.5.2


Liquid trap of F-102 or at drain line
of separator stuck close

High level at F-102 leading Manual by pass valve on


to liquid carry over to Gas around liquid trap
Dryer D-100A/B
Second liquid trap provided
on the pipe to Sump Tank
AIH (dew point alarm)-0301
at downstream of F-101

Parameter: Pressure
2R.8.1
Less

2R.8.2

Less

Less Pressure

Loss of containment/leak on
Release of hydrocarbon
regeneration system due to corrosion leading to environmental
damage and potential fire

Less Pressure

See Misdirected flow 2R.5.1

CNG PLANT TAMBAK LOROK

F & G system

Page 11 of 53

HAZOP Node N2R

PT ENVIROMATE TECHNOLOGY INDONESIA

No.
2R.8.3

Guide
Words
Less

Deviation
Less Pressure

Appendix B - HAZOP Review Worksheet

Causes / Concerns
Regeneration pump loss of power
due to mechanical problem

2R.9.1
More
More Pressure
See Now Flow 2R.1.3
Parameter: Temperature
2R.10.1 Less
Less Temperature Electric heater stop due to
mechanical failure

2R.11.1

More

More temperature Cooler stop due to motor failure

Parameter: Contamination
2R.12.1 As Well
Contamination
As

No additional significant issues of


concerns identified

Parameter: Composition
2R.13.1 Other
Composition
Than

No additional significant issues of


concerns identified

Parameter: Corrosion / Erosion


2R.14.1 Other
Corrosion /
Than
Erosion

No additional significant issues of


concerns identified

Parameter: Relief
2R.16.1 Other
Than

Relief

No additional significant issues of


concerns identified

Occupational
Safety

No additional significant issues of


concerns identified

Parameter: External Factor


2R.18.1 Other
External Factors
Than

No additional significant issues of


concerns identified

Parameter: Operation & Maintenance


2R.19.1 Other
Operations
Than

No additional significant issues of


concerns identified

2R.20.1

Other
Than

Parameter: Drawing
2R.21.1 Other
Than

Maintenance

No additional significant issues of


concerns identified

Drawing

No additional significant issues of


concerns identified

CNG PLANT TAMBAK LOROK

gas cannot circulate to


regeneration system
resulting in wet gas to
compressor

Safeguards
AIH (dew point alarm) at
downstream of Dryer unit

In efficient heat absorbtion Maintenance


to D-100

liquid cannot be condense


and separated to the
separator

Sour Gas (H2S) and water content in Internal corrosion of piping


the production gas
and vessel leading to
release of hydrocarbon gas
and potential fire

Parameter: Instrumentation
2R.15.1 Other
Instrumentation
Than

Parameter: Safety
2R.17.1 Other
Than

Consequences

AIH (dew point alarm) at


downstream of Dryer unit
AIH (dew point alarm) at
downstream of Dryer unit

Wall thickness of piping


and equipment already
considered sour gas
condition

Page 12 of 53

Initiating
L

PT. ISTANA KARANG LAUT

Co

Pr

Ri

S (-)
C(3)

S (-)
C(M3)

S (-)
C(3)

S (-)
C(M3)

S (-)
C(3)

S (-)
C(M3)

S (4)
C(4)

S (M4)
C(M4)

Comments / Recommendations

Action Party

Rec. No.

HAZOP Node N2R

PT ENVIROMATE TECHNOLOGY INDONESIA

Appendix B - HAZOP Review Worksheet

Node
3
Review date 17-Jun-13

Abbreviations

Client
Project
Facility
Section

PT ENVIROMATE TECHNOLOGY INTERNATIONAL


Compressed Natural Gas Plant
Tambak Lorok
Compression System K101 (typical for K102 to K110), including
Blowdown Tank VE301

Comment
Design
Intent

Nine (9) compressor online and One (1) stand by; reciprocating type compressor, three-stages
To compress natural gas and transfer to the storage cylinder

SOP
IM

Standard Operating Procedures


Inspection & Maintenance

PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C

Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk

Design
Shut Off Pressure :
Conditions:

Design Capacity: 2.17 MMSCFD each


compressor

Opt.
Conditions

Suction Pressure : 26 barG


Discharge Pressure : 250 barG

Drawing

PID - Compressor System / K-101 (Vendor Package)

No.

Guide
Words
Parameter: Flow
3.1.1
No

Deviation

No Flow

PT. ISTANA KARANG LAUT

Flowrate : 20 MMSCFD
Power : TBA KW (each compressor)

Causes / Concerns

SDV W151 fails close

Drawing No.

Consequences

Safeguards

Potential
overpressurization of
upstream equipment and
piping leading to loss of
integrity and fire event

TS78-P-PID-004

Comments / Recommendations

Rev:

Action Party

Rec. No.

PSH-0301A at Gas Dryer D100A/B to close SDV-0101

PSV 0301A/B at dryer unit


Low suction pressure to
compressor leading to
compressor damage and
production loss

PT-501 displayed in control


room

PIL 501 at SS-101 as Low


pressure alarm to alert
operator

CNG PLANT TAMBAK LOROK

Page 13 of 53

HAZOP Node N3

PT ENVIROMATE TECHNOLOGY INDONESIA

No.

3.2.1

Guide
Words

Less

Deviation

Less Flow

CNG PLANT TAMBAK LOROK

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Blockage of filter FF-201

Consequences

Safeguards

Potential
overpressurization of
upstream equipment and
piping leading to loss of
integrity and fire event

PT. ISTANA KARANG LAUT

Comments / Recommendations

Action Party

Rec. No.

PILL 501 at SS-101 to


shutdown SDV-151
PSH-0301A at Gas Dryer D100A/B to close SDV-0101

PDI - S01 provided around


FF 201
PSV 0301A/B at dryer unit

Page 14 of 53

HAZOP Node N3

PT ENVIROMATE TECHNOLOGY INDONESIA

Node

Appendix B - HAZOP Review Worksheet

Abbreviations

Review date 17-Jun-13


Client
Project
Facility
Section

Comment
Design
Intent

Standard Operating Procedures

IM

Inspection & Maintenance

PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C
CNG Storage cylinder consist of 95 compartments. 5 compartments will be arranged in 1 bank (each has 40 tubes).
Operation : 19-20 hours storage time, 4-5 hours decanting time

Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk

To cooling down compressed gas and storage to CNG compartment

PID - Storage and Decanting System

No.

Guide
Words
Parameter: Flow
4.1.1
No

4.2.1

SOP

PT ENVIROMATE TECHNOLOGY INTERNATIONAL


Compressed Natural Gas Plant
Tambak Lorok
Inlet CNG Cooler E-100 to CNG Compartment (STORAGE TIME)

Design
CNG Cooler : DP (shell) : 7 barG; (tube) : 263 barG
Conditions: CNG Compartment : DP : 374 barG
Opt.
CNG Cooler : Storage Period (Inlet /Outlet Shell side) : OP : 3 barG
Conditions CNG Cooler : Storage Period (Inlet /Outlet tube side) : OP : 249
barG
Drawing

PT. ISTANA KARANG LAUT

Less

Deviation

Causes / Concerns

No Flow

Manual valves at inlet CNG


Compartement inadvertenly close

Less Flow

See no flow partially

CNG PLANT TAMBAK LOROK

CNG Cooler DT : 65 deg C


CNG Compartment DT : 70 deg C

Duty CNG Cooler: 201 kW

CNG Cooler : Storage Period (Inlet /Outlet Shell side) 2.38 m3 each cylinder
: OT : 30 deg C/ 39 deg C
CNG Cooler : Storage Period (Inlet /Outlet tube side)
: OT : 48 deg C/35 deg C
Drawing No.
TS78-P-PID-005 Sheet 1 of 2

Consequences

Less of CNG production

Page 15 of 53

Safeguards

Comments / Recommendations

Rev:

Action Party

Rec. No.

Local pressure indicator


provided each
compartment

HAZOP Node N4

PT ENVIROMATE TECHNOLOGY INDONESIA

No.
4.2.2

Guide
Words
Less

Deviation
Less Flow

Appendix B - HAZOP Review Worksheet

Causes / Concerns
One of running compressor fails to
operate

Consequences
Less of CNG production

Safeguards
Indicator of online
compressor in control
room

PT. ISTANA KARANG LAUT

Comments / Recommendations
Review sizing of manual valve
incoming CNG compartment to
be available at market or provide
spare manual valve in the case of
maintenance required

Action Party

Rec. No.
CNG-HP-14

Standby compressor
available

Indication of pressure
and flow of storage
period by graph to
shown loss of production
4.3.1

More

More Flow

No additional significant issues of


concerns identified

4.4.1

Reverse

Reverse Flow

No additional significant issues of


concerns identified

4.5.1

Part of

Misdirected Flow KV-0503A leak or fails open (storage No adverse consequence


condition)

Parameter: Level
4.6.1
Less
4.7.1
More
Parameter: Pressure
4.8.1
Less
4.9.1
More
4.9.2
More

Less Level
More Level

Not relevant
Not relevant

Less Pressure
More Pressure
More Pressure

Refer to Less Flow


Refer to No Flow
Storage time more than 20 hours

PV-0501A/B will hold


the pressure
PIHH 0509 set at 33 barG
will open XV-0506 and
circulate gas to suction
compressor

Potential over pressure at


overall plant
PIH-S01 set 30 barG
alarm to alert Operator
PIHH-S01 set 32 barG to
close SDVSV-101/102/103 set@
78/165/294 barg

CNG PLANT TAMBAK LOROK

Page 16 of 53

HAZOP Node N4

PT ENVIROMATE TECHNOLOGY INDONESIA

No.

Guide
Words

Deviation

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Consequences

More

More
Temperature

Parameter: Contamination
4.12.1
As Well
Contamination
As

Parameter: Composition
4.13.1
Other
Composition
Than
Parameter: Corrosion / Erosion
4.14.1
Other
Corrosion /
Than
Erosion
Parameter: Instrumentation
4.15.1
Other
Instrumentation
Than

Parameter: Relief
4.16.1
Other
Than

Relief

CNG PLANT TAMBAK LOROK

Comments / Recommendations

Action Party

Rec. No.

Maximum discharge
pressure of Compressor
255 barG is less than
MAWP Tube storage
design 373 barG

Parameter: Temperature
4.10.1
Less
Less Temperature No additional significant issues of
concerns identified
4.11.1

Safeguards

PT. ISTANA KARANG LAUT

Fouling/Plugging at E-100 or loss of Inefficiency in cooling


TIH-0503/TIH 0508/TIH
cooling water
resulting in high
0509 alarm will alert
temperature leading to less operator
CNG production

Provide portable temperature


detector to check skin
temperature of CNG
compartment

CNG-HP-15

Tube leak at E-100

Provide SOP to control PH at


cooling tower periodically

CNG-HP-16

Gas contamination to
cooling water system
leading to gas release at
cooling tower
Gas trapped at shell side
resulting in eficient heat
transfer

Gas detector at cooling


tower fan

Explosion-proof motor of
cooling tower
TIH-0503/TIH 0508/TIH
0509 alarm will alert
operator

No additional significant issues of


concerns identified
See contamination

Instrument air failure

Unable to supply gas to


customer

Nitrogen back up is
provided to open KV0501 to deliver gas from
CNG compartement to
tambak lorok

No additional significant issues of


concerns identified

Page 17 of 53

HAZOP Node N4

PT ENVIROMATE TECHNOLOGY INDONESIA

No.

Guide
Words
Parameter: Safety
4.17.1
Other
Than

Deviation

Occupational
Safety

Appendix B - HAZOP Review Worksheet

Causes / Concerns

No additional significant issues of


concerns identified

Parameter: Operation & Maintenance


4.19.1
Other
Operations
Than

No additional significant issues of


concerns identified

Other
Than

Parameter: Drawing
4.21.1
Other
Than

Maintenance

No additional significant issues of


concerns identified

Drawing

No additional significant issues of


concerns identified

CNG PLANT TAMBAK LOROK

Safeguards

Comments / Recommendations

Action Party

Rec. No.

No additional significant issues of


concerns identified

Parameter: External Factor


4.18.1
Other
External Factors
Than

4.20.1

Consequences

PT. ISTANA KARANG LAUT

Page 18 of 53

HAZOP Node N4

PT ENVIROMATE TECHNOLOGY INDONESIA

Appendix B - HAZOP Review Worksheet

Node
5
Review date 17-Jun-13

Abbreviations

PT. ISTANA KARANG LAUT

SOP
IM

Standard Operating Procedures


Inspection & Maintenance

PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C

Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk

Client
Project
Facility
Section

PT ENVIROMATE TECHNOLOGY INTERNATIONAL


Compressed Natural Gas Plant
Tambak Lorok
Inlet CNG Heat Exchanger E-200 to Station Outlet Metering M200A/B (DECANTING)

Comment
Design
Intent

E-200 and M-200A/B will be operated during decanting time only. Decanting Time 4-5 hours.
To avoid condensation on the upstream of pressure reducing valve and to measure natural gas outlet from CNG Plant

Design
CNG Heat Exchanger : DP (shell) : 5.5 barG; (tube) : 34 barG
Conditions: M-200A/B : DP : 34 barG

CNG Heat Exchanger DT : 120 deg C


M-200A/B DT : 65 deg C

Duty CNG Heat Exchanger 3860 kW


Capacity M-200A/B: 113 MMSCFD

Opt.
Conditions

CNG Heat Exchanger : Inlet /Outlet Shell side : OP : 2 barG / 1.4


barG
CNG Heat Exchanger : Inlet /Outlet tube side : OP : 26.7 barG / 26
barG

CNG Heat Exchanger : Inlet /Outlet Shell side : OT : 90


deg C / 65 deg C
CNG Heat Exchanger : Inlet /Outlet tube side : OT- 38
deg C / 30 deg C

Decanting : 113 MMSCFD

Drawing

PID - CNG Heat Exchanger

TS78-P-PID-005 Sheet 2 of 2

PID - Station Outlet Metering (M-200A/B)

TS78-P-PID-006

No.

Guide
Words
Parameter: Flow
5.1.1

No

Deviation

No Flow

CNG PLANT TAMBAK LOROK

Causes / Concerns

Consequences

Safeguards

Comments / Recommendations

Rev:

B
B

Action Party

Rec. No.

Any of manual valves on the


Compressor shut off
PIH 0502 set at 250psig to
decanting line to E-200 inadvertenly pressure is 255 barg vs
alert operator
close or PV0501A/B stuck close
design pressure of
equipment is 263 barg - no
adverse consequence
identified

Page 19 of 53

HAZOP Node N5

PT ENVIROMATE TECHNOLOGY INDONESIA

No.

Guide
Words

Deviation

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Consequences

Safeguards

PT. ISTANA KARANG LAUT

Comments / Recommendations

Action Party

Rec. No.

PIHH 0502 set at 255 psig to


shutdown compressor

Loss of gas to customer

FT-0601A/B at M-200A/B
displayed at control room
FILL 0601 A/Bset at 5
MMSCFD for alarm to alert
operator

5.1.2

No

No Flow

5.2.1

Less

Less Flow

SDV0601 fails close or manual valve Potential


PV0501 A/B to regulate the Show setting point of PV 0501A/B
in the metering station inadvertenly overpressurization of CNG pressure
closed
HE E-200 leading to
hydrocarbon release and
potential fire
PIH 0509 set at 31 psig to
alert operator
PSHH 0509 set at 33 barG to
close KV 0501A
Refer to No Flow - valve partially closed

5.3.1

More

More Flow

PV0501A/B stuck open

5.4.2

Reverse

Reverse Flow

5.5.1

Part of

Gas from suction compressor going


to downstream of E-200 to metering
M-200
Misdirected Flow BDV-0505 fails open

5.5.2

Part of

Misdirected Flow XV-0506 fails open

Parameter: Level
5.6.1
Less

Less Level

CNG PLANT TAMBAK LOROK

Potential
PIH 0509 set at 31 psig to
overpressurization of CNG alert operator
HE E-200 and downstream
piping
PSHH 0509 set at 33 barG to
close KV 0501A
Double counting of sales
Install additional check valve at
gas from Gundih meter
line PG-2"-3C-027
with M-100
Loss of gas to vent
BDV position indicator and
alarm in control room
Loss of gas back to system
instead to customer

CNG-HP-17

CNG-HP-18

Valve position indicator and


alarm in control room

No additional significant issues of


concerns identified

Page 20 of 53

HAZOP Node N5

PT ENVIROMATE TECHNOLOGY INDONESIA

No.
5.7.1

Guide
Words
More

Parameter: Pressure
5.8.1
Less

5.9.1
5.9.

More
More

Deviation

Appendix B - HAZOP Review Worksheet

Causes / Concerns

More Level

No additional significant issues of


concerns identified

Less Pressure

Loss of containment/leak on
Decanting Line

More Pressure
More Pressure

see no flow and more flow

Consequences

Release of hydrocarbon
leading to environmental
damage and potential fire

Manual valve upstream BDV-0505


Overpresurization of
inadvertenly close in the event of
upstream equipment
ESD and BDV-0505 required to open leading to fire/fatality

Safeguards

PT. ISTANA KARANG LAUT

Comments / Recommendations

Action Party

Rec. No.

F&G

NA

Provide Lock Open (LO) manual


valve at upstream BDV-0505

CNG-HP-19

Parameter: Temperature
5.10.1
Less
Less Temperature No additional significant issues of
concerns identified
5.11.1

More

More temperature No additional significant issues of


concerns identified

Parameter: Contamination
5.12.1
As Well
Contamination
As

Tube leak at E-200

Parameter: Composition
5.13.1
Other
Composition
Than

No additional significant issues of


concerns identified

Parameter: Corrosion / Erosion


5.14.1
Other
Corrosion /
Than
Erosion

No additional significant issues of


concerns identified

Parameter: Instrumentation
5.15.1
Other
Instrumentation
Than

No additional significant issues of


concerns identified

Parameter: Relief
5.16.1
Other
Than

Relief

No additional significant issues of


concerns identified

Occupational
Safety

No additional significant issues of


concerns identified

Parameter: Safety
5.17.1
Other
Than

Gas contamination to hot


Atmospheric venting at Hot
water system leading to gas Water Tank T-200
release at WHRU

Parameter: External Factor

CNG PLANT TAMBAK LOROK

Page 21 of 53

HAZOP Node N5

PT ENVIROMATE TECHNOLOGY INDONESIA

No.
5.18.1

Guide
Words
Other
Than

Deviation
External Factors

Parameter: Operation & Maintenance


5.19.1
Other
Operations
Than
5.20.

Other
Than

Parameter: Drawing
5.21.1
Other
Than

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Safeguards

Comments / Recommendations

Action Party

Rec. No.

No additional significant issues of


concerns identified
No additional significant issues of
concerns identified

Maintenance

No additional significant issues of


concerns identified

Drawing

No additional significant issues of


concerns identified

CNG PLANT TAMBAK LOROK

Consequences

PT. ISTANA KARANG LAUT

Page 22 of 53

HAZOP Node N5

PT ENVIROMATE TECHNOLOGY INDONESIA

Appendix B - HAZOP Review Worksheet

Node
6
Review date 17-Jun-13

Abbreviations

Client
Project
Facility
Section

PT ENVIROMATE TECHNOLOGY INTERNATIONAL


Compressed Natural Gas Plant
Tambak Lorok
Hot water circulation including Hot Water Tank T-200, Hot Water
Pump P300A/B and circulation to E-200

Comment

Circulation to E-200 will be on decanting time only

Design
Intent

To heat compressed gas from storage facility to be ready for sales gas

Design
E-500 DP : 2 barG
Conditions: T-200 DP : 0.17 barG
Source Pressure : atm; Discharge Pump : 3.35 barG

Drawing

PID - Waste Heat Recovery Unit


PID - CNG Heat Exchanger

Guide
Words
Parameter: Flow
6.1.1
No

6.1.2

No

Deviation

No Flow

No Flow

CNG PLANT TAMBAK LOROK

SOP
IM

Standard Operating Procedures


Inspection & Maintenance

PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C

Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk

Temperature: 120 deg C

Opt.
Conditions

No.

PT. ISTANA KARANG LAUT

T-200 : 290 m3
P-300 : 140 m3/hr
E-500 : 127 kW
Power : 36.8 kW

CNG Heat Exchanger : Inlet /Outlet Shell side : OT : 90 deg C / 65 deg C

TS78-P-PID-007
TS78-P-PID-005 sheet 2 of 2

Drawing No.

Causes / Concerns

Hot Water Pump P-300A/B stop


due to failure OR Strainer at
upstream P-300A/B blockage

Manual valve on the downstream


P300A/B inadvertently closed

Consequences

Safeguards

Loss of hot water supply


leading to inefficient heat
transfer and lower gas
sales temperature

TT-0512 as low temperature


alarm to alert operator

High temperature in the


circulation water around
the waste heat recovery
unit

TIC 0703 set at 85 deg C to


control exhaust gas supply
from compressor

TAH 0703 set at 85 deg C


alarm to alert operator
TAH 0706 set at 85 deg C
alarm to alert operator
Low discharge pressure for SOP to operate standby
hot water circulation
pump P-300B
leading to inefficient heat
transfer
Loss of hot water supply
TT-0512 as low temperature
leading to inefficient heat alarm to alert operator
transfer and lower gas
sales temperature

Page 23 of 53

Iniating L

Rev:

Comments / Recommendations

S (-)
C(2)

S (-)
C(L2)

Provide low temperature switch at line


PG-12"-3C-021 to close KV-0503 A to
prevent low temperature in the gas
sales

CNG-HP-20

Provide low temperature alarm at line


PG-12"-3C-021 to alert operator

CNG-HP-21

S (-)
C(2)

Action Party

B
B

Rec. No.

S (-)
C(L2)

HAZOP Node N6

PT ENVIROMATE TECHNOLOGY INDONESIA

No.

Guide
Words

Deviation

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Consequences
High temperature in the
circulation water around
the waste heat recovery
unit

6.2.1

Less

Less Flow

Potential
overpressurization of
upstream piping
Three way valve TV-0502 to E-200 is Loss of hot water supply
inadvertenly close
leading to inefficient heat
transfer and lower gas
sales temperature
High temperature in the
circulation water around
the waste heat recovery
unit

Safeguards

Iniating L

PT. ISTANA KARANG LAUT

Comments / Recommendations

S (-)
C(2)

S (-)
C(L2)

Provide Temperature Control Valve at


bypass line of E-200

S (-)
C(2)

S (-)
C(L2)

S (-)
C(2)

S (-)
C(L2)

S (-)
C(2)

S (-)
C(L2)

S (-)
C(2)

S (-)
C(L2)

Action Party

Rec. No.

TIC 0703 set at 85 deg C to


control exhaust gas supply
from compressor
TAH 0703 set at 85 deg C
alarm to alert operator
TAH 0706 set at 95 deg C
alarm to alert operator
PSHH 0703A set at 4.5 barG
to close P-300A/B
TT-0512 as low temperature
alarm to alert operator

CNG-HP-22

TIC 0703 set at 85 deg C to


control exhaust gas supply
from compressor
TAH 0703 set at 85 deg C
alarm to alert operator

Three way valve TV-0502 to by pass Not adverse consequence


line E-200 is inadvertenly close
6.3.1

More

More Flow

Hot Water Pump P-300A andB


running simultaneously

Excess hot water supply to TIC-0502 as high


E-200 resulting in potential temperature alarm to alert
overheating
operator
Pump running status
indication at control room

6.4.1

Reverse

Reverse Flow

6.5.1

Part of

Misdirected Flow 2-in manual valve at T-200 to open


drain inadvertently open

Parameter: Level
6.6.1
Less
6.6.2
Less

6.7.1

More

Less Level
Less Level

More Level

CNG PLANT TAMBAK LOROK

No additional significant issues of


concerns identified
Loss of hot water supply
SOP
leading to inefficient heat
transfer
Overheating of water to E- LSL-0702 to shutdown P300 system
500A/B

see misdirected flow 6.5.1


More evaporation with less make up Loss of hot water supply
water
leading to inefficient heat
transfer

Make up water activated

Vapor Condenser E-500


provided

LSL 0701 to start P-600


pump for make up water
Overheating of water to E- LSL-0702 to shutdown P300 system
500A/B
Potential overflow to open LSH 0701 to stop make up
drain
water and provide warning
to operator
Overflow line to Open
Drain

Page 24 of 53

HAZOP Node N6

PT ENVIROMATE TECHNOLOGY INDONESIA

Appendix B - HAZOP Review Worksheet

No.

Guide
Deviation
Causes / Concerns
Words
Parameter: Pressure
6.8.1
Less
Less Pressure
refer to No Flow 6.1.1
6.9.1
More
More Pressure
Refer to No Flow
Parameter: Temperature
6.10.1
Less
Less Temperature Leak at hot water system at
discharge P-300A/B

6.10.2

Less

Less Temperature Fouling/Plugging at E-200

6.10.3

Less

Less Temperature Refer to No Flow

6.11.1

More

More
Temperature
Parameter: Contamination
6.12.1
As Well
Contamination
As

Parameter: Composition
6.13.1
Other
Composition
Than

Consequences

Loss of hot water supply


leading to inefficient heat
transfer and lower gas
sales temperature
High temperature in the
circulation water around
the waste heat recovery
unit

Inefficiency in heating
resulting in lower gas
temperature

Safeguards

TT-0512 as low temperature


alarm to alert operator

Iniating L

PT. ISTANA KARANG LAUT

S (-)
C(2)

S (-)
C(L2)

S (-)
C(2)

S (-)
C(L2)

S (-)
C(2)

S (-)
C(L2)

Comments / Recommendations

Action Party

Rec. No.

TIC 0703 set at 85 deg C to


control exhaust gas supply
from compressor
TAH 0703 set at 85 deg C
alarm to alert operator
TAH 0706 set at 85 deg C
alarm to alert operator
TT-0512 as low temperature
alarm to alert operator

Refer to More Flow

E-200 Tube/tube sheet leak

Gas introduce to hot water T-200 is venting to


system leading to potential atmosphere
overpressure of hot water
system

No additional significant issues of


concerns identified

d
6.14.1

Other
Than

Corrosion /
Erosion

No additional significant issues of


concerns identified

Parameter: Instrumentation
6.15.1
Other
Instrumentation
Than

No additional significant issues of


concerns identified

Parameter: Relief
6.16.1
Other
Than

Relief

No additional significant issues of


concerns identified

Occupational
Safety

No additional significant issues of


concerns identified

Parameter: Safety
6.17.1
Other
Than

Parameter: External Factor


6.18.1
Other
External Factors
Than

CNG PLANT TAMBAK LOROK

No additional significant issues of


concerns identified

Page 25 of 53

HAZOP Node N6

PT ENVIROMATE TECHNOLOGY INDONESIA

No.

Guide
Deviation
Words
Parameter: Operation & Maintenance
6.19.1
Other
Operations
Than
6.20.1

Other
Than

Parameter: Drawing
6.21.1
Other
Than

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Safeguards

Iniating L

Comments / Recommendations

Action Party

Rec. No.

No additional significant issues of


concerns identified

Maintenance

No additional significant issues of


concerns identified

Drawing

No additional significant issues of


concerns identified

CNG PLANT TAMBAK LOROK

Consequences

PT. ISTANA KARANG LAUT

Page 26 of 53

HAZOP Node N6

PT ENVIROMATE TECHNOLOGY INDONESIA

Appendix B - HAZOP Review Worksheet

Node
7
Review date 17-Jun-13
Client
Project
Facility
Section

Abbreviations

PT ENVIROMATE TECHNOLOGY INTERNATIONAL


Compressed Natural Gas Plant
Tambak Lorok
Waste Heat Recovery Unit include Water circulation pump P500A/B and WHRU

PT. ISTANA KARANG LAUT

SOP
IM

Standard Operating Procedures


Inspection & Maintenance

PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C

Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk

Comment
Design
Intent

To recover heat from exhaust gas of compressor and heating water for heating media E-100 and E-200

Design
Conditions:

Pressure: WHRU : 18 Barg

Temperature: WHRU : 545 deg C

P-500 : 48 m3/hr

Opt.
Conditions

Shell / Coil : 0.03 barG / 3 barG

Shell / Coil OT : 490 deg C / 63 to 90 deg C

Power : 1283 kW

Drawing

PID - Waste Heat Recovery Unit

No.

Guide
Words
Parameter: Flow
7.1.1
No

Deviation

No Flow

TS78-P-PID-007

Drawing No.

Causes / Concerns

Water Circulation Pump P-500A/B


stop due to failure OR Strainer at
upstream P-500A/B blockage

Consequences

Loss of water circulation


leading to overheating of
hot water circulation to T200

Safeguards

TIC-0703 to close
dampener from
compressor flue gas

Iniating L

S (-)
C(2)

S (-)
C(L2)

Comments / Recommendations

Rev:

Action Party

Rec. No.

TIC-0703 as high
temperature alarm to alert
operator
PSV-0701 as thermal relief
routed to open drain
Pump running status
indication at control room

Low discharge pressure for SOP to operate standby


water circulation leading to pump P-500B
inefficient heat transfer

CNG PLANT TAMBAK LOROK

Page 27 of 53

HAZOP Node N7

PT ENVIROMATE TECHNOLOGY INDONESIA

No.
7.1.2

Guide
Words
No

Deviation
No Flow

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Consequences

Any manual valve at upstream E-300 Loss of water circulation


inadvertenly close or check valve
leading to overheating of
blockage
hot water circulation to T200

Safeguards
TIC-0703 to close
dampener from
compressor flue gas

Iniating L

PT. ISTANA KARANG LAUT

S (-)
C(2)

S (-)
C(L2)

Less

Less Flow

Any manual valve on the water


circulation line at WHRU system
partially closed

7.3.1

More

More Flow

Water Circulation Pump P-500A/B


running simultaneously

7.4.1

Reverse

Reverse Flow

No additional significant issues of


concerns identified

7.5.1

Part of

Misdirected Flow 3/4" manual valve to open drain


inadvertenly open

7.5.2

Part of

Parameter: Level
7.6.1
Less
7.7.1

More

Misdirected Flow Manual valve to venting open

Less Level

No additional significant issues of


concerns identified

More Level

No additional significant issues of


concerns identified

CNG PLANT TAMBAK LOROK

Loss of water circulation


leading to overheating of
hot water circulation to T200

Action Party

Rec. No.

TIC-0703 as high
temperature alarm to alert
operator
PSV-0701 as thermal relief

Potential overpressure of
downstream pump
7.2.1

Comments / Recommendations

Vendor to provide minimum flow


recycle line at P-500A/B
TIC-0703 to close
dampener from
compressor flue gas

S (-)
C(2)

S (-)
C(L2)

S (-)
C(2)

S (-)
C(L2)

S (-)
C(2)

S (-)
C(L2)

CNG-HP-23

TIC-0703 as high
temperature alarm to alert
operator
PSV-0701 as thermal relief

Excess water circulation to Pump running status


E-300/T-200 - no safety
indication at control room
consequence

Loss of water circulation


leading to overheating of
hot water circulation to T200

TIC-0703 to close
dampener from
compressor flue gas

Loss of water circulation


leading to overheating of
hot water circulation to T200

TIC-0703 to close
dampener from
compressor flue gas

TIC-0703 as high
temperature alarm to alert
operator
PSV-0701 as thermal relief

TIC-0703 as high
temperature alarm to alert
operator
PSV-0701 as thermal relief

Page 28 of 53

HAZOP Node N7

PT ENVIROMATE TECHNOLOGY INDONESIA

Appendix B - HAZOP Review Worksheet

No.

Guide
Deviation
Causes / Concerns
Words
Parameter: Pressure
Refer to No Flow 6.1.1
7.8.1
Less
Less Pressure
Refer to No Flow
7.9.1
More
More Pressure
Parameter: Temperature
7.10.1
Less
Less Temperature Refer to No Flow
One or more gas engine driver
shutdown

Start up

7.11.1

More

More
Temperature

Parameter: Contamination
7.12.1
As Well As Contamination

Refer to No Flow, Less Flow,


Misdirected Flow

No additional significant issues of


concerns identified

Parameter: Corrosion / Erosion


7.14.1
Other
Corrosion /
Than
Erosion

Condense water from flue gas at E300

Parameter: Instrumentation
7.15.1
Other
Instrumentation
Than

No additional significant issues of


concerns identified

Parameter: Relief
7.16.1
Other
Than

Relief

No additional significant issues of


concerns identified

Occupational
Safety

No additional significant issues of


concerns identified

Parameter: External Factor


7.18.1
Other
External Factors
Than

No additional significant issues of


concerns identified

Parameter: Operation & Maintenance


7.19.1
Other
Operations
Than

No additional significant issues of


concerns identified

7.20.1

Other
Than

Maintenance

Safeguards

Iniating L

Less of flue gas to E-300


TIA 0704 to alert operator
resulting in lower
temperature generated for
water circulation
Low gas temperature from
exhaust gas compressor to
WHRU resulting
condensation at gas
ducting E-300

S (-)
C(2)

S (-)
C(L2)

Corrosion at E-300 leading Check with vendor the


to equipment damage
requirement of TIA-0705
as low temperature alarm

S (-)
C(2)

Comments / Recommendations

Action Party

Rec. No.

Review requirement set point of


TIA-0704

CNG-HP-25

Provide drain line at lowest point


gas ducting E-300

CNG-HP-26

Review requirement TIA-0705

CNG-HP-27

No additional significant issues of


concerns identified

Parameter: Composition
7.13.1
Other
Composition
Than

Parameter: Safety
7.17.1
Other
Than

Consequences

PT. ISTANA KARANG LAUT

S (-)
C(M6)

No additional significant issues of


concerns identified

Parameter: Drawing

CNG PLANT TAMBAK LOROK

Page 29 of 53

HAZOP Node N7

PT ENVIROMATE TECHNOLOGY INDONESIA

No.
7.21.1
7.21.2
7.21.3

Guide
Words
Other
Than
Other
Than
Other
Than

Deviation

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Consequences

Safeguards

Iniating L

PT. ISTANA KARANG LAUT

Comments / Recommendations

Action Party

Rec. No.

Drawing
Drawing
Drawing

CNG PLANT TAMBAK LOROK

Revise drawing TS78-P-PID-007 to


show setting point of all
instrumentation alarm and trip

Page 30 of 53

CNG-HP-28

HAZOP Node N7

PT ENVIROMATE TECHNOLOGY INDONESIA

Appendix B - HAZOP Review Worksheet

Node
8
Review date 17-Jun-13
Client
Project
Facility
Section

Abbreviations

PT ENVIROMATE TECHNOLOGY INTERNATIONAL


Compressed Natural Gas Plant
Tambak Lorok
Water Treatment Plant

PT. ISTANA KARANG LAUT

SOP
IM

Standard Operating Procedures


Inspection & Maintenance

PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C

Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk

Comment
Design
Intent

to treat sea water and provide potable water for cooling media

Design
Pressure : 7 barG
Conditions:

Temperature: 65 deg C

Opt.
Conditions

Pressure : 4 barG

Temperature : ambient

Drawing

PID - Water Treatment Plant

No.

Guide
Words
Parameter: Flow
8.1.1
No

8.1.2

8.1.3

No

No

Deviation

No Flow

No Flow

No Flow

TS78-P-PID-012

Drawing No.

Causes / Concerns

Manual valve at inlet Feed Pump


P701 inadvertenly close

Pump P701 stop due to failure

MOV-1201 (valve on duty)


inadvertenly close

Consequences

Safeguards

Iniating L

No make up water supply SOP to monitor Water


for cooler/heater leading Treatment Plant (WTP)
to low performance of heat
transfer
Low suction pressure of
PSL1209 to stop P702
P702 resulting in pump
damage
No make up water supply Pump maintenance
for cooler/heater leading
to low performance of heat
transfer
Low suction pressure of
PSL1209 to stop P702
P702 resulting in pump
damage
No make up water supply SOP to monitor Water
for cooler/heater leading Treatment Plant (WTP)
to low performance of heat
transfer
Low suction pressure of
P702 resulting in pump
damage

CNG PLANT TAMBAK LOROK

Flow : 3.2 m3/hr

S (-)
C(1)

S (-)
C(L2)

S (-)
C(1)

S (-)
C(L2)

S (-)
C(1)

S (-)
C(L2)

Comments / Recommendations

Rev:

Action Party

Rec. No.

PSL1209 to stop P702

Page 31 of 53

HAZOP Node N8

PT ENVIROMATE TECHNOLOGY INDONESIA

No.
8.1.4

Guide
Words
No

No Flow

High Pressure Pump P702 failure

No make up water supply Pump maintenance


for cooler/heater leading
to low performance of heat
transfer

8.1.5

No

No Flow

Manual valve downstream P702


inadvertenly close

No make up water supply SOP to monitor Water


for cooler/heater leading Treatment Plant (WTP)
to low performance of heat
transfer

8.1.6

8.1.7

No

No

Deviation

Appendix B - HAZOP Review Worksheet

No Flow

No Flow

Causes / Concerns

S (-)
C(1)

S (-)
C(L2)

S (-)
C(1)

S (-)
C(L1)

LS-1201 to stop Hi press


Pump PU-201
High Pressure Pump PU-201 failure No make up water supply Pump maintenance
for cooler/heater leading
to low performance of heat
transfer

S (-)
C(1)

S (-)
C(L2)

Manual valve downstream PU-201


inadvertenly close

S (-)
C(1)

S (-)
C(L2)

Manual valve downstream Buffer


Tank TK-02 inadvertenly close

Consequences

Safeguards

Iniating L

PT. ISTANA KARANG LAUT

Potential overpressure of PSH 1211 to stop P702 and


upstream equipment
P701
Potential overfilling TK02 LS-1201 to stop Feed Pump
P701

No make up water supply SOP to monitor Water


for cooler/heater leading Treatment Plant (WTP)
to low performance of heat
transfer
Potential overpressure of
upstream equipment
Potential overpressure of
upstream equipment

PSH 1216 to stop PU-201


PI 1201, PI 1202 and PI
1203 to monitor differential
pressure

S (-)
C(1)

S (-)
C(L2)

8.2.1

Less

Less Flow

Filter F-1A//B blockage

8.2.2

Less

Less Flow

Filter FX-01/02 blockage

Potential overpressure of
upstream equipment

PDI 1201 to monitor


differential pressure

S (-)
C(1)

S (-)
C(L2)

8.2.3

Less

Less Flow

RO-A blockage

Potential overpressure of
upstream equipment

PSH 1211 to stop P702 and


P701

S (-)
C(1)

S (-)
C(L2)

8.3.1

More

More Flow

Control valve upstream FM 1205


stuck open

Potential overflow to TK01 LS01 to stop FEED pump


P701

S (-)
C(1)

S (-)
C(L1)

8.4.1

Reverse

Reverse Flow

No additional significant issues of


concerns identified

8.5.1

Part of

8.5.2

Part of

Misdirected Flow Manual valve for sample


inadvertenly open
Misdirected Flow Manual drain valve from RO-A to
open ditch inadvertenly open

Parameter: Level
8.6.1
Less
8.7.1
More
Parameter: Pressure
8.8.1
Less

Less Level

No additional significant issues of


concerns identified

More Level

see more flow

Less Pressure

see no flow

CNG PLANT TAMBAK LOROK

Loss of make up water to


environment
Loss of make up water to
environment

Comments / Recommendations

Action Party

Rec. No.

SOP
SOP

Page 32 of 53

HAZOP Node N8

PT ENVIROMATE TECHNOLOGY INDONESIA

No.

8.9.1

Guide
Words
More

Deviation

More Pressure

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Consequences

Safeguards

Iniating L

PT. ISTANA KARANG LAUT

Comments / Recommendations

Action Party

Rec. No.

see no flow and less flow

Parameter: Temperature
8.10.1
Less
Less Temperature No additional significant issues of
concerns identified
8.11.1

More

More
Temperature

No additional significant issues of


concerns identified

Parameter: Contamination
8.12.1
As Well
Contamination
As

No additional significant issues of


concerns identified

Parameter: Composition
8.13.1
Other
Composition
Than

Manual valve from chemical source Low make up water


inadvertenly close
quality leading to scale

Parameter: Corrosion / Erosion


8.14.1
Other
Corrosion /
Than
Erosion

No additional significant issues of


concerns identified

Parameter: Instrumentation
8.15.1
Other
Instrumentation
Than

No additional significant issues of


concerns identified

Parameter: Relief
8.16.1
Other
Than

Relief

No additional significant issues of


concerns identified

Occupational
Safety

No additional significant issues of


concerns identified

Parameter: Safety
8.17.1
Other
Than

Parameter: External Factor


8.18.1
Other
External Factors
Than

No additional significant issues of


concerns identified

Parameter: Operation & Maintenance


8.19.1
Other
Operations
Than

No additional significant issues of


concerns identified

8.20.1

Other
Than

Parameter: Drawing
8.21.1
Other
Than

Maintenance

SOP

No additional significant issues of


concerns identified

Drawing

CNG PLANT TAMBAK LOROK

Page 33 of 53

HAZOP Node N8

PT ENVIROMATE TECHNOLOGY INDONESIA

Appendix B - HAZOP Review Worksheet

Node
9
Review date 17-Jun-13
Client
Project
Facility
Section

Abbreviations

PT ENVIROMATE TECHNOLOGY INTERNATIONAL


Compressed Natural Gas Plant
Tambak Lorok
Cooling System, including Make up Water Tank T-100, Make Up
Water Pump P-100, Cooling Tower E-400 and Cooling Tower Pump
P-200 A/B

PT. ISTANA KARANG LAUT

SOP
IM

Standard Operating Procedures


Inspection & Maintenance

PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C

Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk

Comment
Design
Intent

To provide cooling media for E-100

Design
Conditions:

Pressure: Cooling Tower : 3.5 Barg

Temperature: 65 deg C

Capacity T-100 : 54 m3

Opt.
Conditions

Pressure : ATM

Temperature : 30 - 45 deg C

Power P-100 : 0.85 kW; P-200A/B :


5.88 kW

Drawing

PID - Cooling System

No.

Guide
Words
Parameter: Flow
9.1.1
No

9.1.2

9.1.3

No

No

Deviation

No Flow

No Flow

No Flow

CNG PLANT TAMBAK LOROK

TS78-P-PID-011

Drawing No.

Causes / Concerns

Manual valve at inlet T-100 is


inadvertenly close

Manual valve at outlet T-100 is


inadvertenly close or strainer
blocked

Make up water pump P-100 broken


or stop

Consequences

Safeguards

Low level at T-100 leading LSL 1101 to shutdown


to loss of pump suction and Pump P-600
potential pump damage

Loss of make up water for Temperature alarm at


cooling media and make up WHRU, E-100 and E-200
T-200 leading to ineffective
heat transfer
Loss of pump suction and
potential pump damage
Loss of make up water for
cooling media and make up
T-200 leading to ineffective
heat transfer
Loss of make up water for
cooling media leading to
ineffective heat transfer

Iniating L

S (-)
C(2)

S (-)
C(M4)

S (-)
C(2)

S (-)
C(M4)

S (-)
C(2)

S (-)
C(L2)

Comments / Recommendations

Provide lock open (LO) for manual


valve upstream P-100 and P-600

Rev:

Action Party

Rec. No.

CNG-HP-29

Temperature alarm at
WHRU, E-100 and E-200

Pump running status


indication at control room

Page 34 of 53

HAZOP Node N9

PT ENVIROMATE TECHNOLOGY INDONESIA

No.

9.1.4

Guide
Words
No

Deviation

No Flow

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Manual valve or strainer at inlet


Basin cooling water is inadvertently
close

Consequences

Loss of make up water for


cooling media leading to
ineffective heat transfer

Safeguards
Pump maintenance
Temperature alarm at E-100

Iniating L

PT. ISTANA KARANG LAUT

S (-)
C(2)

S (-)
C(L2)

Potential overflow at T-600 Floating valve at T-600 to


start/stop pump P-100
9.1.5

No

No Flow

Cooling water pump P-200A/B


broken or not in operation

9.1.6

No

No Flow

9.1.7

No

9.2.1

Pump running status


indication at control room

S (-)
C(2)

S (-)
C(L2)

Manual valve at upstream P-200A/B Loss of pump suction and


inadvertenly close or strainer
potential pump damage
blocked
Loss of make up water for
cooling media leading to
ineffective heat transfer

Strainer Maintenance
periodically

S (-)
C(2)

S (-)
C(M4)

No Flow

Manual valve at downstream P200A/B inadvertently close

PSH 1108A to stop P200A/B

S (-)
C(2)

S (-)
C(L2)

Less

Less Flow

Refer to No Flow - valve partially closed

9.3.1

More

More Flow

9.4.1

Reverse

Reverse Flow

Cooling Tower Pump P-200 A and B More of water cooling


running simultenaously
media - no adverse
consequence
No additional significant issues of
concerns identified

9.5.1

Part of

Misdirected Flow 3" manual valve at T-100/E-400 to


open drain inadvertenly open

Low level at T-100 leading LSL 1101 to shutdown


to loss of pump suction and Pump P-600
potential pump damage

9.5.1

Part of

Misdirected Flow 2" manual valve at E-400 to open


drain inadvertenly open

Low level at E-400 leading Floating valve will flow


to loss of pump suction and water from T-600
potential pump damage

Less Level

see no flow 9.1.1, 9.1.2,9.1.3,9.5.1

Less Level

Make up water pump P-100 fails to


stop

Loss of water for cooling


media resulting insufficent
heat absorbed during heat
transfer leading to CN gas
offspec
Low level at T-100 leading LSL 1101 to shutdown
to loss of pump suction and Pump P-100
potential pump damage

S (-)
C(2)

S (-)
C(M4)

Parameter: Level
9.6.1
Less

9.6.2

Less

CNG PLANT TAMBAK LOROK

Loss of make up water for


cooling media leading to
ineffective heat transfer

Potential
overpressurization of
piping at pump discharge

Comments / Recommendations

Action Party

Rec. No.

Review design of floating valve T600 to be radar type

CNG-HP-30

Provide lock open (LO) for manual


valve upstream P-200

CNG-HP-31

Pump running status


indication at control room

Page 35 of 53

HAZOP Node N9

PT ENVIROMATE TECHNOLOGY INDONESIA

No.

Guide
Words

Deviation

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Consequences

Safeguards

S (-)
C(2)

S (-)
C(L2)

S (-)
C(2)

S (-)
C(M4)

S (-)
C(2)

S (-)
C(L2)

Comments / Recommendations

Action Party

Rec. No.

High level at Cooling


Tower basin T-600

9.7.1

More

Parameter: Pressure
9.8.1
Less

More Level

Less Pressure

Float valve will stop


incoming flow to cooling
tower
Float valve at Cooling Tower basin E- Potential overflow to open SOP
400 failure
drain

Iniating L

PT. ISTANA KARANG LAUT

Leak in water supply line to E-100

9.9.1
More
More Pressure
see no flow 9.1.1, 9.1.2,9.1.3
Parameter: Temperature
9.10.1
Less
Less Temperature No additional significant issues of
concerns identified
9.11.1

More

More
Temperature

Parameter: Contamination
9.12.1
As Well As Contamination

Motor at E-400 fails to run

No additional significant issues of


concerns identified

Parameter: Corrosion / Erosion


9.14.1
Other
Corrosion /
Than
Erosion

No additional significant issues of


concerns identified

Parameter: Instrumentation
9.15.1
Other
Instrumentation
Than

No additional significant issues of


concerns identified

Parameter: Relief
9.16.1
Other
Than

Relief

No additional significant issues of


concerns identified

Occupational
Safety

No additional significant issues of


concerns identified

Parameter: External Factor


9.18.1
Other
External Factors
Than

No additional significant issues of


concerns identified

Parameter: Operation & Maintenance


9.19.1
Other
Operations
Than

No additional significant issues of


concerns identified

9.20.1

Other
Than

Maintenance

CNG PLANT TAMBAK LOROK

high temperature of water


supply to E-100 leading to
less production

TT-0503 at E-100 as high


temperature alarm to alert
operator

No additional significant issues of


concerns identified

Parameter: Composition
9.13.1
Other
Composition
Than

Parameter: Safety
9.17.1
Other
Than

Loss of water for cooling


media resulting insufficent
heat absorbed during heat
transfer leading to CN gas
offspec

No additional significant issues of


concerns identified

Page 36 of 53

HAZOP Node N9

PT ENVIROMATE TECHNOLOGY INDONESIA

No.

Guide
Words
Parameter: Drawing
9.21.1
Other
Than

Deviation

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Consequences

Safeguards

Iniating L

PT. ISTANA KARANG LAUT

Comments / Recommendations

Action Party

Rec. No.

Drawing

CNG PLANT TAMBAK LOROK

Page 37 of 53

HAZOP Node N9

PT ENVIROMATE TECHNOLOGY INDONESIA

Appendix B - HAZOP Review Worksheet

Node
10
Review date 17-Jun-13
Client
Project
Facility
Section

Abbreviations

PT ENVIROMATE TECHNOLOGY INTERNATIONAL


Compressed Natural Gas Plant
Tambak Lorok
Sump Tank V-400 including Sump Tank P-400

PT. ISTANA KARANG LAUT

SOP
IM

Standard Operating Procedures


Inspection & Maintenance

PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C

Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk

Comment
Design
Intent

To collect liquid drain from vessel (closed drain system)

Design
Conditions:

Pressure : 3.5 barG

Temperature: 45 deg C

P-400 Capacity : 1.2 m3/hr

Opt.
Conditions

Tank Ops Pressure : ATM; P


Pump Suc Pressure : Atm, Disch Pressure : 2 barG

Temperature : AMB

Power P-400 : 0.3 kW

Drawing

PID - Sump System

No.

Guide
Words
Parameter: Flow
10.1.1
No

Deviation

TS78-P-PID-010

Drawing No.

Causes / Concerns

No Flow

4" manual valve at inlet V-400


inadvertenly closed

Consequences

Safeguards

Iniating L

High level at source vessel Safeguards at source vessel

S (-)
C(1)

S (-)
C(L1)

10.2.1

Less

Less Flow

No additional significant issues of


concerns identified

10.3.1

More

More Flow

Liquid control valve failure at


individual equipments (V-300,
Compressor K-101-109, V-100)

Build up pressure in Sump Open venting to atmosphere


Tank V-400 leading to
potential
overpressurization

S (-)
C(1)

S (-)
C(L1)

10.3.2

More

More Flow

Manual drain valves at individual


equipments inadvertently open
during online operation

Build up pressure in Sump Open venting to atmosphere


Tank V-400 leading to
potential
overpressurization
Loss of level at the source LT at individual equipment
vessel
as low level alarm to alert
operator; and as low level
trip to initiate USD

S (-)
C(1)

S (-)
C(L1)

CNG PLANT TAMBAK LOROK

Page 38 of 53

Comments / Recommendations

Review outlet line at venting V400 to be sufficient for case high


pressure gas introduced from
upstream equipment to this
vessel

Rev:

Action Party

Rec. No.

CNG-HP-32

HAZOP Node N10

PT ENVIROMATE TECHNOLOGY INDONESIA

No.

Guide
Words

Deviation

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Consequences

Safeguards

Iniating L

PT. ISTANA KARANG LAUT

Comments / Recommendations

Action Party

Rec. No.

Double-valve provided at
drain line of the individual
equipments
10.4.1

Reverse

Reverse Flow

10.5.1

Part of

Misdirected Flow No additional significant issues of


concerns identified

Parameter: Level
10.6.1
Less

10.7.1

More

No additional significant issues of


concerns identified

Less Level

Sump Pump P-400 fails to stop due


to LT-1001 failure to function

Loss of liquid level leading Pump will be stopped


to Sump Pump P-400
during no signal (FC)
damage due to cavitation

S (-)
C(1)

S (-)
C(L1)

More Level

Pump stopped due to no power


supply or pump damage

Overfilling of Sump Tank


V-400 and liquid release
from vent to environment

S (-)
C(1)

S (-)
C(L1)

LAH 1001 as high level


alarm to alert operator

SOP - draining activity is


attended by operator
Standby portable pump will
be provided and connected
to available spare nozzle
Parameter: Pressure
10.8.1
Less
10.9.1
10.9.2

More
More

Less Pressure

No additional significant issues of


concerns identified

More Pressure
More Pressure

Refer to More flow


Blockage of flame arrestor at vent
line

Potential
overpressurization of V400

Bug screen provided

Parameter: Temperature
10.10.1
Less
Less Temperature No additional significant issues of
concerns identified
10.11.1

More

More
Temperature

Parameter: Contamination
10.12.1
As Well As Contamination

No additional significant issues of


concerns identified
No additional significant issues of
concerns identified

Parameter: Composition
10.13.1
Other
Composition
Than

No additional significant issues of


concerns identified

Parameter: Corrosion / Erosion


10.14.1
Other
Corrosion /
Than
Erosion

No additional significant issues of


concerns identified

Parameter: Instrumentation
10.15.1
Other
Instrumentation
Than

No additional significant issues of


concerns identified

CNG PLANT TAMBAK LOROK

Page 39 of 53

HAZOP Node N10

PT ENVIROMATE TECHNOLOGY INDONESIA

No.

Guide
Words
Parameter: Relief
10.16.1
Other
Than
Parameter: Safety
10.17.1
Other
Than

Deviation

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Relief

No additional significant issues of


concerns identified

Occupational
Safety

No additional significant issues of


concerns identified

Parameter: External Factor


10.18.1
Other
External Factors
Than

No additional significant issues of


concerns identified

Parameter: Operation & Maintenance


10.19.1
Other
Operations
Than

No additional significant issues of


concerns identified

10.20.1

Other
Than

Parameter: Drawing
10.21.1
Other
Than

Maintenance

Consequences

Safeguards

Iniating L

PT. ISTANA KARANG LAUT

Comments / Recommendations

Action Party

Rec. No.

No additional significant issues of


concerns identified

Drawing

CNG PLANT TAMBAK LOROK

Page 40 of 53

HAZOP Node N10

PT ENVIROMATE TECHNOLOGY INDONESIA

Appendix B - HAZOP Review Worksheet

Node
11
Review date 17-Jun-13
Client
Project
Facility
Section

Abbreviations

PT ENVIROMATE TECHNOLOGY INTERNATIONAL


Compressed Natural Gas Plant
Tambak Lorok
Fuel Gas System

PT. ISTANA KARANG LAUT

SOP
IM

Standard Operating Procedures


Inspection & Maintenance

PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C

Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk

Comment
Design
Intent

To provide fuel to compressor

Design
Conditions:

Pressure : 13.5 barG

Temperature: 45 deg C

Opt.
Conditions
Drawing

Pressure : 10 barG

Temperature : 21 deg C

PID - Fuel Gas System

No.

Guide
Words
Parameter: Flow
11.1.1
No

Deviation

Capacity : 1.5 m3

TS78-P-PID-009

Drawing No.

Causes / Concerns

Consequences

Safeguards

Iniating L

No Flow

3" Manual valves at


incoming/outgoing line Fuel Gas
filter is inadvertently closed

Loss of fuel gas supply


leading to compressor
shutdown

PT-0902 as low pressure


alarm to alert operator

S (-)
C(4)

S (-)
C(M4)

PT-0902 as low pressure


alarm to alert operator

S (-)
C(4)

S (-)
C(M4)

Standby PCV available


PDI 0901A/B to monitor
differential pressure

S (-)
C(2)

S (-)
C(L2)

Back up fuel gas filter


available
PT-0902 as low pressure
alarm to alert operator
PT-0902 as high pressure
alarm to alert operator

S (-)
C(1)

S (-)
C(L1)

11.1.2

No

No Flow

PCV-0901A/B stuck closed

Loss of fuel gas supply


leading to compressor
shutdown

11.2.1

Less

Less Flow

Pump N4 stop due to failure

Less of fuel gas supply


leading to compressor
shutdown

11.3.1

More

More Flow

PCV-0901A/B stuck open

11.4.1

Reverse

Reverse Flow

No additional significant issues of


concerns identified

CNG PLANT TAMBAK LOROK

Potential
overpressurization of
downstream equipment

Page 41 of 53

Comments / Recommendations

Provide lock open (LO) for 3"


manual valves at upstream and
downstream Fuel Gas Filter

Rev:

Action Party

Rec. No.

CNG-HP-33

HAZOP Node N11

PT ENVIROMATE TECHNOLOGY INDONESIA

No.
11.5.1

Guide
Words
Less

Parameter: Level
11.6.1
Less
11.7.1

More

Deviation

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Consequences

Safeguards

Iniating L

PT. ISTANA KARANG LAUT

Comments / Recommendations

Action Party

Rec. No.

Misdirected Flow No additional significant issues of


concerns identified
Less Level

No additional significant issues of


concerns identified

More Level

No additional significant issues of


concerns identified

Parameter: Pressure
Refer to No Flow and Less Flow
11.8.1
Less
Less Pressure
Refer to More Flow
11.9.1
More
More Pressure
Parameter: Temperature
11.10.1
Less
Less Temperature No additional significant issues of
concerns identified
11.11.1

More

More
Temperature

Parameter: Contamination
11.12.1
As Well As Contamination

No additional significant issues of


concerns identified
No additional significant issues of
concerns identified

Parameter: Composition
11.13.1
Other
Composition
Than

No additional significant issues of


concerns identified

Parameter: Corrosion / Erosion


11.14.1
Other
Corrosion /
Than
Erosion

No additional significant issues of


concerns identified

Parameter: Instrumentation
11.15.1
Other
Instrumentation
Than

No additional significant issues of


concerns identified

Parameter: Relief
11.16.1
Other
Than

Relief

No additional significant issues of


concerns identified

Occupational
Safety

No additional significant issues of


concerns identified

Parameter: Safety
11.17.1
Other
Than

Parameter: External Factor


11.18.1
Other
External Factors
Than

No additional significant issues of


concerns identified

Parameter: Operation & Maintenance


11.19.1
Other
Operations
Than

No additional significant issues of


concerns identified

11.20.1

Other
Than

Parameter: Drawing
11.21.1
Other
Than

Maintenance

No additional significant issues of


concerns identified

Drawing

CNG PLANT TAMBAK LOROK

Page 42 of 53

HAZOP Node N11

PT ENVIROMATE TECHNOLOGY INDONESIA

Appendix B - HAZOP Review Worksheet

Node
12
Review date 17-Jun-13
Client
Project
Facility
Section

Abbreviations

PT ENVIROMATE TECHNOLOGY INTERNATIONAL


Compressed Natural Gas Plant
Tambak Lorok
Instrument Air System

PT. ISTANA KARANG LAUT

SOP
IM

Standard Operating Procedures


Inspection & Maintenance

PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C

Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk

Comment
Design
Intent

To provide instrument air for instrumented system

Design
Pressure : 12 barG
Conditions:
Opt.
Conditions

Pressure : 6 - 10 barG

Drawing

PID - Instrument Air System


PID - Instrument Air Network

No.

Guide
Words
Parameter: Flow
12.1.1
No

Deviation

No Flow

Temperature: 45 deg C

Capacity 183.63 SCFM (each)

Temperature : AMB - 40 deg C

Power: 30 kW (each)

Causes / Concerns

Manual valve upstream of


Instrument Air Receiver V-300
inadvertently closed

Consequences

No

No Flow

CNG PLANT TAMBAK LOROK

Any manual valve upstream of Air


Dryer Prefilter F300A/B
inadvertently closed

Safeguards

Loss of instrument air


Instrument air supply from
supply potentially leading Instrument Air Receiver Vto PSD
300 is provided for 5
minutes in operation

Potential
overpressurization of
upstream piping

12.1.2

TS78-P-PID-008 Sheet 1 of 2
TS78-P-PID-008 Sheet 2 of 2

Drawing No.

Iniating L

S (-)
C(2)

S (-)
C(L2)

PT-0803 set at 7 barg as low


pressure alarm to alert
Operator
NA

Loss of instrument air


Instrument air supply from
supply potentially leading Instrument Air Receiver Vto PSD
300 is provided for 5
minutes in operation

Page 43 of 53

Comments / Recommendations

Confirm availability of high


pressure trip at internal of Air
Compressor C300A/B/C package to
shut down compressor in the case of
block of discharge
S (-)
C(2)

Rev:

Action Party

B
B

Rec. No.

CNG-HP-34

S (-)
C(L2)

HAZOP Node N12

PT ENVIROMATE TECHNOLOGY INDONESIA

No.

12.1.3

12.1.4

12.1.5

12.1.6

Guide
Words

No

No

No

No

12.1.7

12.2.1

Deviation

No Flow

No Flow

No Flow

No Flow

No Flow

Less

Less Flow

CNG PLANT TAMBAK LOROK

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Consequences

Safeguards
PSV 0801 set at 12 barG
release air to atmosphere

Any manual valve upstream of Air


Dryer D300A/B inadvertently
closed

Potential
overpressurization of
upstream piping
Loss of instrument air
supply potentially leading
to PSD

PSV 0801 set at 12 barG


release air to atmosphere

Any manual valve upstream Air


Dryer after filter F301A/B
inadvertently closed

Potential
overpressurization of
upstream piping
Loss of instrument air
supply potentially leading
to PSD

Instrument air supply from


Instrument Air Receiver V300 is provided for 5
minutes in operation
PSV 0802 release air to
atmosphere

Potential
overpressurization of
upstream piping
Loss of instrument air
supply potentially leading
to PSD

PSV 0802 release air to


atmosphere

Manual valve downstream


Instrument Air Receiver V-310
inadvertently closed

Air Dryer Prefilter F300A/B


blockage

S (-)
C(2)

S (-)
C(L2)

S (-)
C(2)

S (-)
C(L2)

S (-)
C(2)

S (-)
C(L2)

S (-)
C(2)

S (-)
C(L2)

Comments / Recommendations

Action Party

Rec. No.

Instrument air supply from


Instrument Air Receiver V300 is provided for 5
minutes in operation

Potential
overpressurization of
upstream piping
Any manual valve downstream Air Loss of instrument air
Dryer after filter F301A/B
supply potentially leading
inadvertently closed
to PSD

Air Compressors package


trip/broken

Iniating L

PT. ISTANA KARANG LAUT

Instrument air supply from


Instrument Air Receiver V300 is provided for 5
minutes in operation

Auto start of standby


compressor by PSLL-0803
Nitrogen back up at
downstream F-310A/B

Loss of instrument air


Instrument air supply from
supply potentially leading Instrument Air Receiver Vto PSD
310 is provided for 5
minutes in operation
Potential
overpressurization of
upstream piping
Less of instrument air
PDI 0801 to monitor
supply potentially leading differential pressure
to PSD
Wet instrument air quality Dew Point Meter D0801
resulting in
instrumentation damage
leading to potential
shutdown
Spare Air Dryer Prefilter
available

Page 44 of 53

Lock Open (LO) for manual valve


downstream Instrument Air Receiver
V-310

CNG-HP-35

HAZOP Node N12

PT ENVIROMATE TECHNOLOGY INDONESIA

No.

Deviation

Appendix B - HAZOP Review Worksheet

12.2.2

Guide
Words
Less

Causes / Concerns

Less Flow

Air Dryer D-200A/B blockage

12.2.3

Less

Less Flow

Air Dryer After Filter F301A/B


blockage

12.3.1

More

More Flow

12.4.1

Reverse

Reverse Flow

All Air Compressor running


simultaneously - no adverse
consequence
No additional significant issues of
concerns identified

12.5.1

Part of

Misdirected Flow 3/4" manual drain valve at V-300


inadvertently close

Consequences

Safeguards

Less of instrument air


PDI 0802A/B to monitor
supply potentially leading differential pressure
to PSD
Wet instrument air
Dew Point Meter DE 0801
resulting in
instrumentation damage
leading to potential
shutdown
Spare Air Dryer available
Less of instrument air
PDI 0802 to monitor
supply potentially leading differential pressure
to PSD
Wet instrument air quality Dew Point Meter D0801
resulting in
instrumentation damage
leading to potential
shutdown
Spare Air Dryer After filter
available

S (-)
C(2)

S (-)
C(L2)

S (-)
C(2)

S (-)
C(L2)

High pressure air blowby


to sump tank V-400

S (-)
C(2)

S (-)
C(L2)

S (-)
C(2)

S (-)
C(L2)

Sump Tank V-400 is open to


atmosphere

Iniating L

PT. ISTANA KARANG LAUT

Comments / Recommendations

Action Party

Rec. No.

Less of instrument air


supply potentially leading
to PSD
Parameter: Level
12.6.1
Less
12.7.1

More

Parameter: Pressure
12.8.1
Less
12.9.1

More

Less Level

No additional significant issues of


concerns identified

More Level

Water condensation in V-300 and


lube oil entrainment from
compressors

Less Pressure

see no flow, less flow, misdirected flow

More Pressure

see no flow

Low quality of instrument SOP to monitor LG 0801


air leading to potential
instrument damage and
shutdown

Parameter: Temperature
12.10.1 Less
Less Temperature No additional significant issues of
concerns identified
12.11.1

More

More
Temperature

No additional significant issues of


concerns identified

Parameter: Contamination

CNG PLANT TAMBAK LOROK

Page 45 of 53

HAZOP Node N12

PT ENVIROMATE TECHNOLOGY INDONESIA

No.
12.12.1

Guide
Words
As Well
As

Deviation
Contamination

Appendix B - HAZOP Review Worksheet

Causes / Concerns

No additional significant issues of


concerns identified

Parameter: Corrosion / Erosion


12.14.1 Other
Corrosion /
Than
Erosion

No additional significant issues of


concerns identified

Parameter: Instrumentation
12.15.1 Other
Instrumentation
Than

No additional significant issues of


concerns identified

Parameter: Relief
12.16.1 Other
Than

Relief

No additional significant issues of


concerns identified

Occupational
Safety

No additional significant issues of


concerns identified

Parameter: External Factor


12.18.1 Other
External Factors
Than

No additional significant issues of


concerns identified

Parameter: Operation & Maintenance


12.19.1 Other
Operations
Than

No additional significant issues of


concerns identified

12.20.1

Other
Than

Parameter: Drawing
12.21.1 Other
Than
12.21.2

Other
Than

Maintenance

No additional significant issues of


concerns identified

Drawing

No additional significant issues of


concerns identified

Drawing

No additional significant issues of


concerns identified

CNG PLANT TAMBAK LOROK

Safeguards

Iniating L

Comments / Recommendations

Action Party

Rec. No.

No additional significant issues of


concerns identified

Parameter: Composition
12.13.1 Other
Composition
Than

Parameter: Safety
12.17.1 Other
Than

Consequences

PT. ISTANA KARANG LAUT

Page 46 of 53

HAZOP Node N12

PT ENVIROMATE TECHNOLOGY INDONESIA

Appendix B - HAZOP Review Worksheet

Node
13
Review date 17-Jun-13

Abbreviations

Client
Project
Facility
Section

PT ENVIROMATE TECHNOLOGY INTERNATIONAL


Compressed Natural Gas Plant
Tambak Lorok
Fire Water System

Comment

Fire water is supplied from existing facility

Design
Intent

to provide cooling system and extinguish fire from the process plant and building

Design
Conditions:

Pressure : ATM

Temperature: 45 deg C

Opt.
Conditions

Pressure : ATM

Temperature : ambient

Drawing

PID - Fire Water System

No.

Guide
Words
Parameter: Flow
13.1.1
No

Deviation

Causes / Concerns

Any of manual valve at fire water


ring inadvertently close/stuck close

Existing fire water pump inoperation Fail to supply fire water in


case of fire leading to fire
escalation
Any of manual valve at fire water
Lack of fire water supply
ring partially close
resulting in inadequate
water to extinguishing fire

13.1.2

No

No Flow

13.2.1

Less

Less Flow

13.3.1

More

More Flow

No additional significant issues of


concerns identified

13.4.1

Reverse

Reverse Flow

No additional significant issues of


concerns identified

13.5.1

Part of

Misdirected Flow No additional significant issues of


concerns identified

Parameter: Level
13.6.1
Less

Less Level

CNG PLANT TAMBAK LOROK

SOP
IM

Standard Operating Procedures


Inspection & Maintenance

PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C

Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk

Drawing No.

TS78-P-PID-013

Consequences

No Flow

Lack of fire water supply


resulting in inadequate
water to extinguishing fire

PT. ISTANA KARANG LAUT

Safeguards

SOP

SOP

Iniating L

S (3)
C(3)

S (M3)
C(M3)

S (3)
C(3)

S (M3)
C(M3)

S (3)
C(3)

S (M3)
C(M3)

Comments / Recommendations

Rev:

Action Party

Rec. No.

No additional significant issues of


concerns identified

Page 47 of 53

HAZOP Node N13

PT ENVIROMATE TECHNOLOGY INDONESIA

No.
13.7.1

Guide
Words
More

Parameter: Pressure
13.8.1
Less
13.9.1
More

Deviation

Appendix B - HAZOP Review Worksheet

Causes / Concerns

More Level

No additional significant issues of


concerns identified

Less Pressure
More Pressure

see less flow


No additional significant issues of
concerns identified

Consequences

Safeguards

Iniating L

PT. ISTANA KARANG LAUT

Comments / Recommendations

Action Party

Rec. No.

Parameter: Temperature
13.10.1
Less
Less Temperature No additional significant issues of
concerns identified
13.11.1

More

More
Temperature

Parameter: Contamination
13.12.1
As Well As Contamination

No additional significant issues of


concerns identified
No additional significant issues of
concerns identified

Parameter: Composition
13.13.1
Other
Composition
Than

No additional significant issues of


concerns identified

Parameter: Corrosion / Erosion


13.14.1
Other
Corrosion /
Than
Erosion

No additional significant issues of


concerns identified

Parameter: Instrumentation
13.15.1
Other
Instrumentation
Than

No additional significant issues of


concerns identified

Parameter: Relief
13.16.1
Other
Than

Relief

No additional significant issues of


concerns identified

Occupational
Safety

No additional significant issues of


concerns identified

Parameter: Safety
13.17.1
Other
Than

Parameter: External Factor


13.18.1
Other
External Factors
Than

No additional significant issues of


concerns identified

Parameter: Operation & Maintenance


13.19.1
Other
Operations
Than
13.19.2

Other
Than

Operations

13.20.1

Other
Than

Maintenance

Parameter: Drawing
13.21.1
Other
Than

Review existing Tambak Loroks fire


water capacity to be adequate for fire
water handling in CNG Plant

CNG-HP-36

Consider to provide additional flowmeter


to measure fire water consumption for
Tambak Lorok

CNG-HP-37

No additional significant issues of


concerns identified

Drawing

CNG PLANT TAMBAK LOROK

Page 48 of 53

HAZOP Node N13

PT ENVIROMATE TECHNOLOGY INDONESIA

Appendix B - HAZOP Review Worksheet

Node
14
Review date 17-Jun-13

Abbreviations

Client
Project
Facility
Section

PT ENVIROMATE TECHNOLOGY INTERNATIONAL


Compressed Natural Gas Plant
Tambak Lorok
Power Generation system

Comment

GE-100 A is main generator and GE-100B is back up generator (emergency???)

Design
Intent

to provide power for CNG plant

Design
Conditions:
Opt.

Pressure :

Temperature:

Pressure :

Temperature :

Conditions
Drawing

PID - Power Generator System

No.

Guide
Words
Parameter: Flow
14.1.1
No

Deviation

No Flow

PT. ISTANA KARANG LAUT

SOP
IM

Standard Operating Procedures


Inspection & Maintenance

PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C

Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk

Capacity : 600 kW
TS78-P-PID-014

Drawing No.

Causes / Concerns

Power Generator unable to operate


due to damage

Consequences

Safeguards

No power generated
Standby Generator
leading to plant shutdown provided

Iniating L

S (-)
C(3)

S (-)
C(M3)

Comments / Recommendations

Rev:

Action Party

Rec. No.

Back up power supply from


PLN available
XV 1401 or XV 1402 or XV - 1403
inadvertenly close
PV 1401 or PV-1402 stuck close
Manual valve up stream GE-100A
inadvertenly close
No additional significant issues of
concerns identified

14.2.1

Less

Less Flow

14.3.1

More

More Flow

No additional significant issues of


concerns identified

14.4.1

Reverse

Reverse Flow

No additional significant issues of


concerns identified

14.5.1

Part of

Misdirected Flow 2-in manual valve to drain system


open

14.6.1

Less

Less Level

Hydrocarbon gas release to


environment

CNG PLANT TAMBAK LOROK

No additional significant issues of


concerns identified

Page 49 of 53

HAZOP Node N14

PT ENVIROMATE TECHNOLOGY INDONESIA

No.
14.7.1

Guide
Words
More

Deviation
More Level

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Consequences

Safeguards

Iniating L

PT. ISTANA KARANG LAUT

Comments / Recommendations

S (-)
C(3)

S (-)
C(M3)

Confirm availability of TSHH to


trip Gas Generator GE-100A in
case of high temperature has been
included
in (LO)
the generator
package.
Lock Open
for manual
valve

Action Party

Rec. No.

No additional significant issues of


concerns identified

Parameter: Pressure
see less flow
14.8.1
Less
Less Pressure
see more flow
14.9.1
More
More Pressure
Parameter: Temperature
14.10.1
Less
Less Temperature No additional significant issues of
concerns identified
14.11.1

More

More
Temperature

Any manual valve down stream GE- Overheating at GE-100A


100A to cooling system inadvertenly leading to equipment
close
damage, plant shutdown

CNG-HP-38

CNG-HP-39

downstream GE-100A
Parameter: Contamination
14.12.1
As Well As Contamination

No additional significant issues of


concerns identified

Parameter: Composition
14.13.1
Other
Composition
Than

No additional significant issues of


concerns identified

Parameter: Corrosion / Erosion


14.14.1
Other
Corrosion /
Than
Erosion

No additional significant issues of


concerns identified

Parameter: Instrumentation
14.15.1
Other
Instrumentation
Than

No additional significant issues of


concerns identified

Parameter: Relief
14.16.1
Other
Than

Relief

No additional significant issues of


concerns identified

Occupational
Safety

No additional significant issues of


concerns identified

Parameter: Safety
14.17.1
Other
Than

Parameter: External Factor


14.18.1
Other
External Factors
Than

No additional significant issues of


concerns identified

Parameter: Operation & Maintenance


14.19.1
Other
Operations
Than

No additional significant issues of


concerns identified

14.20.1

Other
Than

Parameter: Drawing
14.21.1
Other
Than

Maintenance

No additional significant issues of


concerns identified

Drawing

No additional significant issues of


concerns identified

CNG PLANT TAMBAK LOROK

Page 50 of 53

HAZOP Node N14

PT ENVIROMATE TECHNOLOGY INDONESIA

Appendix B - HAZOP Review Worksheet

Node
15
Review date 17-Jun-13

Abbreviations

Client
Project
Facility
Section

PT ENVIROMATE TECHNOLOGY INTERNATIONAL


Compressed Natural Gas Plant
Tambak Lorok
Vent Gas System, including discharge of pressure relieving device
and BDVs vent header, KO Drum V-600, up to Vent Stack VS-100

Comment

Normally Flare system has no hydrocarbon gas flowing


Drain and liquid outlet of Vent Stack is normally close

Design
Intent

To gather release gas from process relief valves and BDV and routing gas to safe area

Design
Conditions:

Pressure : 5.5 barG

Temperature: 85 deg C

Opt.
Conditions

Pressure : ATM - 2 barG

Temperature : 10-60 deg C

Drawing

PID - Vent Gas System

No.

Guide
Words
Parameter: Flow
15.1.1
No

Deviation

PT. ISTANA KARANG LAUT

SOP
IM

Standard Operating Procedures


Inspection & Maintenance

PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C

Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk

Capacity Vent Stack : 12.5


MMSCFD

TS78-P-PID-015

Drawing No.

Causes / Concerns

No Flow

No additional significant issues of


concerns identified

Consequences

Safeguards

Iniating L

15.2.1

Less

Less Flow

No additional significant issues of


concerns identified

15.3.1

More

More Flow

PSV or BDV passing

Loss of gas to atmosphere Flame arrestor installed


resulting gas cloud around
process area and potential
fire if ignited

S (4)
C(4)

S (M4)
C(M4)

15.4.1

Reverse

Reverse Flow

Air ingress to venting system

Potential fire/explosion
inside piping

S (4)
C(4)

S (M4)
C(M4)

15.5.1

Part of

Misdirected Flow No additional significant issues of


concerns identified

CNG PLANT TAMBAK LOROK

Water seal at bottom of vent


stack to prevent air ingress
to venting system

Page 51 of 53

Comments / Recommendations

Rev:

Action Party

Rec. No.

HAZOP Node N15

PT ENVIROMATE TECHNOLOGY INDONESIA

No.

Guide
Words
Parameter: Level
15.6.1
Less
15.7.1

More

Parameter: Pressure
15.8.1
Less
15.9.1

More

Deviation

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Less Level

No additional significant issues of


concerns identified

More Level

Liquid carry over from PSV/BDV

Less Pressure

No additional significant issues of


concerns identified

More Pressure

No additional significant issues of


concerns identified

Consequences

release of hydrocarbon
liquid to environment

Safeguards

Vent stack is equipped by


dead leg to collect liquid
and drain to Sump Tank V400

Iniating L

PT. ISTANA KARANG LAUT

S (-)
C(2)

S (-)
C(L2)

S (4)
C(3)

S (M4)
C(M3)

Comments / Recommendations

Action Party

Rec. No.

Parameter: Temperature
15.10.1
Less
Less Temperature No additional significant issues of
concerns identified
15.11.1

More

More
Temperature

Parameter: Contamination
15.12.1
As Well As Contamination

No additional significant issues of


concerns identified
No additional significant issues of
concerns identified

Parameter: Composition
15.13.1
Other
Composition
Than

No additional significant issues of


concerns identified

Parameter: Corrosion / Erosion


15.14.1
Other
Corrosion /
Than
Erosion

No additional significant issues of


concerns identified

Parameter: Instrumentation
15.15.1
Other
Instrumentation
Than

No additional significant issues of


concerns identified

Parameter: Relief
15.16.1
Other
Than
Parameter: Safety
15.17.1
Other
Than

Relief

No additional significant issues of


concerns identified

Occupational
Safety

No additional significant issues of


concerns identified

Parameter: External Factor


15.18.1
Other
External Factors
Than

Lighting struck during PSV/BDV


release

Parameter: Operation & Maintenance


15.19.1
Other
Operations
Than

No additional significant issues of


concerns identified

15.20.1

Other
Than

Maintenance

Fire at vent stack

Consider to install CO2 snuffing


system at VS-100 to extinguish
fire at vent stack completed with
fusible plug

CNG-HP-40

No additional significant issues of


concerns identified

Parameter: Drawing

CNG PLANT TAMBAK LOROK

Page 52 of 53

HAZOP Node N15

PT ENVIROMATE TECHNOLOGY INDONESIA

No.
15.21.1
15.21.2

Guide
Words
Other
Than
Other
Than

Deviation

Appendix B - HAZOP Review Worksheet

Causes / Concerns

Consequences

Safeguards

Iniating L

PT. ISTANA KARANG LAUT

Comments / Recommendations

Action Party

Rec. No.

Drawing
Drawing

CNG PLANT TAMBAK LOROK

Page 53 of 53

HAZOP Node N15

PT. Enviromate Technology International

HAZOP/HAZID of CNG PLANT TAMBAK LOROK

Appendix C

HAZID Review Worksheets

PT. ENVIROMATE TECHNOLOGY INDONESIA

Node
Review
date
Client
Project
Area
Comment

Drawing

No.

PT ISTANA KARANG LAUT

Appendix C HAZID Review Worksheet


SAA
Co Consequency

Abbreviations

1
17-Jun-13
PT. ENVIROMATE TECHNOLOGY INTERNATIONAL
COMPRESSED NATURAL GAS PLANT
TAMBAK LOROK
The plan is located beside Indonesia Power Company. The
North side is sea side. The South side is Turbine Generator
belong by IP.
General Lay Out CNG Plant

P
Ri
Rec
S
C
H,M,L
Drawing No.

Hazard Description

Consequences

Prevention

4.1.1

Category/
Guideword
Natural Events

Earthquake

Potential of loss of
plant integrity
leading to damage
and hydrocarbon
release

4.1.2

Natural Events

Rob in process area

Potential damage to
process equipment

4.1.3

Natural Events

Lightning

Possible damage to
the equipment and
potential fire

Control

Probabitliy
Risk
Recommendation
Safety Risk
Commercial Risk
High, Medium, Low
TS78-L-LY-001

Recommendation/
Comment

Plant, equipment,
building and
foundation design
anticipated to
accommodate
earthquake factor
(0.15G), referring to
UBC-1997 and soil
investigation result
Plant is designed NA
above Rob
posistion (80 cm
above average
ground level vs
70 cm average
rob) and in high
position
Grounding provided
for each equipment

Update EQL drawing to


show Lightning
protection at CNG
compartment area
(lightning stack) in
process/utility area

Rec Number

CNG-HD- 1

Rev.

B1

Action Party

Co.

S (4)
C(3)

Pr

Ri

S (H16)
C(H12)

Lightning protection at
CNG compartment
area (lightning stack)
in process/utility area

CNG PLANT TAMBAK LOROK

Page 1 of 7

HAZID Worksheet Node 1

PT. ENVIROMATE TECHNOLOGY INDONESIA

No.
4.1.4

Category/
Guideword
Natural Events

Hazard Description

Consequences

Prevention

Settlement

Possible damage to
the equipment and
potential fire
No major concern
Damage to the
equipment, loss of
production

Control

Recommendation/
Comment

4.1.5
4.2.1

Natural Events
External Events

4.3.1

Transportation

4.3.2

Transportation

4.4.1

Lifting

4.5.1

Non Process Fires Bush fire

No additional
significant issues of
concerns identified

4.6.1

Security

Loss of production. Fence line around Security's Officer stand


Potential major
the plant area
by 24 hrs at plant area
accident leading to
personnel
injury/fatality

Pile foundation (block


design) provided to
withstand settlement
Land slide
External corrosion
Painting &
Periodic maintenance
coating for piping and inspection for all
and equipment
surface vessels and
pipings
Light vehicles impact Potential impact to vehicle park area away Operation cars shall be
equipped with flame
e.g. Car
piping/equipment
from process area
arrestor and diesel engine
leading to
hydrocarbon
release, fire,
personnel
injury/fatality and
asset damage
Heavy equipment to
Potential impact to Concrete road
Pipe bridge provided
gas plant e.g. mobile
piping/equipment
to connect each
crane
leading to
equipment across road
hydrocarbon
release, fire,
personnel
injury/fatality and
asset damage
Lifting equipment
Potential damage to SOP for lifting
(mobile crane, forklift) pipeline and
activity including
failure
equipment
certified
personnel to
conduct the
lifting

Theft/sabotage

CNG PLANT TAMBAK LOROK

PT ISTANA KARANG LAUT

Appendix C HAZID Review Worksheet

Page 2 of 7

Rec Number

CNG-HD- 2

Action Party

Co.

Pr

Ri

S (-)
C(3)

S (-)
C(H9)

S (4)
C(4)

S (H8)
C(H8)

S (4)
C(4)

S (H8)
C(H8)

S (-)
C(2)

S (-)
C(M4)

S (4)
C(4)

S (H8)
C(H8)

S (4)
C(4)

S (H8)
C(H8)

HAZID Worksheet Node 1

PT. ENVIROMATE TECHNOLOGY INDONESIA

No.

Category/
Guideword

Hazard Description

Consequences

4.6.2

Security

Vandalism

No additional
significant issues of
concerns identified

4.6.3

Security

Wild animals (tiger,


crocodile and snake)

No additional
significant issues of
concerns identified

4.7.1

Noise

4.8.1

Health Hazards

High noise level from Potential personnel


compressor and gas
ear injury
engine area
Toxic Material during Personnel injury
handling chemical: for
cooling water,
corrosion inhibitor e.g.
oxygen scavanger

Prevention

Control

SOP for control


personnel
incoming to the
plant
-

Recommendation/
Comment

Health Hazards

Handling molecular
sieve at dryer system

Rec Number

Action Party

Co.

Pr

Ri

S (4)
C(4)

S (H8)
C(H8)

Provide SOP to wear ear


plug around noise area

CNG-HD- 3

S (1)
C(-)

S (H3)
C(-)

MSDS provided
in the storage
facility

Ensure portable eye wash


station provided during
chemical handling (e.g : at
control room, loading area
and water treatment area)

CNG-HD- 4

S (1)
C(-)

S (H3)
C(-)

S (1)
C(-)

S (H3)
C(-)

S (1)
C(-)

S (H3)
C(-)

S (1)
C(-)

S (M4)
C(-)

PPE - hand
gloves, face
shield
SOP for chemical
handling
4.8.2

PT ISTANA KARANG LAUT

Appendix C HAZID Review Worksheet

Personnel exposure PPE - hand


to H2S resulting in gloves, face
personnel injury
shield

JSA

SOP for handling


molecular sieve at
dryer system
4.8.3

Health Hazards

Personnel hygiene and Health impact to


living activity
operator

CNG PLANT TAMBAK LOROK

Toilet and pantry Medical emergency


are provided in
provided (clinic) for
control room
operation personnel
building

Page 3 of 7

HAZID Worksheet Node 1

PT. ENVIROMATE TECHNOLOGY INDONESIA

No.
4.8.3

4.9.1

PT ISTANA KARANG LAUT

Appendix C HAZID Review Worksheet

Category/
Guideword
Health Hazards

Hazard Description

Consequences

Prevention

Control

Hazardous waste
disposal

Personnel injury
during handling
waste disposal

PPE - hand
gloves, face
shield

Maintenance/
construction

Working at high
Fall and slip
location such as
resulting in
lightning pole, WHRU injury/fatality

Maintenance
access provided
at WHRU

Recommendation/
Comment
Alocate waste disposal
resulting from
operation/construction
activity in safe area (third
party)

Rec Number

Action Party

Co.

Pr

Ri

S (1)
C(-)

S (H3)
C(-)

Permit to works system

S (4)
C(-)

S (H8)
C(-)

permit to works system

S (4)
C(4)

S (H8)
C(H8)

permit to works system

S (4)
C(-)

S (H8)
C(-)

ELCB (Earth Leakage


Circuit Breaker)
provided for electrical
equipment/devices e.g.
welding machine
PPE
Provide warning sign
around hot surface
equipment and pipings

S (4)
C(-)

S (H8)
C(-)

S (2)
C(-)

S (M4)
C(-)

CNG-HD- 5

SOP for working


at height during
maintenance and
construction,
including
competent
personnel
4.9.2

Maintenance/
construction

Hot/cold Work

4.9.3

Maintenance/
construction

Confined Space Entry

4.9.5

Maintenance/
construction

Electrical Hazards

4.9.6

Maintenance/
construction

Hot Surfaces at
Potential injury due
exhaust gas, WHRU
to exposure to heat
and heat exchanger (E200)

CNG PLANT TAMBAK LOROK

Fire and potential


fatality

SOP for hot/cold


work activity
during
construction,
including
competent
personnel
Potential fatality
SOP for confined
due to asphyxiation space entry
during
maintenance and
construction,
including
Potential
Proper insulation
electrocution
for
resulting in
cabling/wiring
injury/fatality
personal
protection
insulation
provided

Page 4 of 7

CNG-HD- 6

HAZID Worksheet Node 1

PT. ENVIROMATE TECHNOLOGY INDONESIA

No.
4.10.1

Category/
Guideword
Loss of
Containment

PT ISTANA KARANG LAUT

Appendix C HAZID Review Worksheet

Hazard Description

Consequences

Prevention

Control

Recommendation/
Comment
Define philosophy of fire
and gas detection system
and develop fire and gas
detection area at process
plant

Rec Number

Leak from Process


Equipment

Release of
hydrocarbon
resulting in
potential
fire/explosion
leading to
injury/fatality

Unit SD by low
pressure trip

Gas detection system


at process area

Fire hydrant provided Regularly to check


temperature in the MCC
with source from
cabinet and DCS panel to
existing IP
monitor short circuit and
provide portable fire
extinguisher

CNG-HD- 8

CNG-HD- 7

Action Party

Co.

Pr

Ri

S (4)
C(4)

S (H8)
C(H8)

4.10.2

Loss of
Containment

Diesel Leak

No additional
significant issues of
concerns identified

4.11.1

Ignition Sources

Battery

Fire/explosion in
the event of
hydrocarbon
release.

Battery room is
located in non
hazardous area

Heat & Smoke detector,


Portable Fire
Extinguisher provided
at control room & MCC
room

Regularly to check
temperature in the MCC
cabinet and DCS panel to
monitor short circuit and
provide portable fire
extinguisher

CNG-HD- 9

S (4)
C(4)

S (H8)
C(H8)

4.11.2

Ignition Sources

Vent

Fire/explosion in
the event of
hydrocarbon
release in process
area if stroke by
lightning

Lightning protection
provided at CNG
compartment area

Define safe location and


minimum height required
for vent stack and vent
location to be suitable
with wind directions so
that dispersed gas will not
be exposed to process
plan

CNG-HD- 10

S (4)
C(4)

S (H8)
C(H8)

S (4)
C(4)
S (4)
C(4)

S (H8)
C(H8)
S (H8)
C(H8)

4.11.3

Ignition Sources

Static electricity from


external vehicle

CNG PLANT TAMBAK LOROK

Fire/explosion in
the event of
hydrocarbon
release.

vehicle park area away


from process area

Page 5 of 7

HAZID Worksheet Node 1

PT. ENVIROMATE TECHNOLOGY INDONESIA

No.
4.12.1

Category/
Guideword
Escape/ Refuge

Hazard Description

Consequences

Fire on Plant area

Personnel trap/
ERP
unable to evacuate
leading to
injury/fatality

4.13.1

Emergency
Lighting

Personnel trap in
wrong way

4.14.1

Manned Building Control room

CNG PLANT TAMBAK LOROK

PT ISTANA KARANG LAUT

Appendix C HAZID Review Worksheet

Personnel
injury/fatality

Prevention

Control

Recommendation/
Comment
Provide emergency
evacuation risk analysis to
determine safe evacuation
route and location of
muster area

Form emergency response


team (ERT) and conduct
emergency drill

Rec Number

Co.

Pr

Ri

CNG-HD- 11

S (4)
C(4)

S (H8)
C(H8)

CNG-HD- 12

S (4)
C(4)

S (H8)
C(H8)

S (4)
C(4)
S (4)
C(4)

S (H8)
C(H8)
S (H8)
C(H8)

Emergency
lighting for
evacuation is
provided in
control room and
evacuation route

Fire or explosion
from process area
impact to control
room leading to
potential personnel
injury/fatality

Action Party

Heat and Smoke


detector

Review scenario of fire


and explosion from gas
plant to the area of
standby personnel such as
control room and provide
mitigation plan (design
and location of the
building) to anticipate
fire/explosion

CNG-HD- 13

S (4)
C(4)

S (H8)
C(H8)

Define safety requirement


on control room
specification to
accommodate
fire/explosion scenario
e.g. door, wall and
window specifications

CNG-HD- 14

S (4)
C(4)

S (H8)
C(H8)

Inability to monitor process area

S (4)
C(4)
S (4)
C(4)

S (H8)
C(H8)
S (H8)
C(H8)

Consider to provide
CCTV in the control room
for monitoring purpose

Page 6 of 7

CNG-HD- 15

HAZID Worksheet Node 1

PT. ENVIROMATE TECHNOLOGY INDONESIA

No.

Hazard Description

Consequences

Prevention

Control

4.15.1

Category/
Guideword
Communication

Inability to contact
control room within
emergency

Each operator
provided with
hand held radio

F&G alarm system

4.16.1

Shutdown

Inability to initiate
ESD

Local ESD push


button at control
room

4.16.2

Shutdown

Loss of power

Inability to
coordinate response
leading to potential
major accident
leading to
personnel
injury/fatality and
asset loss
Inability to control
fire leading to
potential major
accident leading to
personnel
injury/fatality and
asset loss
Plant shutdown
resulting loss of
production
Uncontrolled
process upset

ESD is fail safe


action
-

Rec Number

Action Party

Co.

Pr

Ri

S (4)
C(4)

S (H8)
C(H8)

CNG-HD- 17

S (4)
C(4)

S (H8)
C(H8)

UPS is provided

S (-)
C(4)

S (-)
C(H8)

S (-)
C(4)

S (-)
C(H8)

S (-)
C(-)

S (-)
C(-)

S (-)
C(-)

S (-)
C(-)

Define safety layout at


CNG plant to show ESD
push button, fire hydrant,
etc

4.17.1

Other

Plant layout

4.18.1

Discharge to air

Note: venting only for


emergency situation

4.18.3

Discharge to
water

Blowdown of water
from cooling tower,
discharge RO

Potential
contamination from
process fluid

4.18.4

Discharge to soil

No additional significant
issue of concern
identified

4.18.5

Waste disposal

Disposal of operation/ Potential


construction waste e.g. environmental
plant, log
disturbance

Recommendation/
Comment
Define internal and
external communication
system (PABX) for
connecting operator in the
control room to outside
parties

CNG-HD- 16

Alternative power
source from PLN for
emergency equipment
-

CNG PLANT TAMBAK LOROK

PT ISTANA KARANG LAUT

Appendix C HAZID Review Worksheet

Discharge water is
connected to existing
canal (IP)

Define Sampling point to


monitor discharge water

CNG-HD- 18

Alocate waste disposal


resulting from
operation/construction
activity in safe area (third
party)

CNG-HD- 5

Page 7 of 7

HAZID Worksheet Node 1

PT. Enviromate Technology International

Appendix D

Drawings Reviewed

HAZOP/HAZID of CNG PLANT TAMBAK LOROK

NODE 1

NODE 2
2
NODE

NODE 2R

NODE 3

NODE 4

NODE 6
NODE 5

NODE 5

NODE 7

NODE 6

NODE 12

NODE 12

NODE 11

NODE 10

NODE 9

NODE 8

NODE 13

NODE 14

NODE 15

You might also like