Professional Documents
Culture Documents
DOCUMENT STATUS
Approved
:
Approved
:
as Noted
Not Approved
24 JUL 2013
YS
MTH
MEF
28 JUN 2013
YS
MTH
MEF
REV
DATE
DESCRIPTION
PREPARED
CHECKED
APPROVED
COMPANY
TABLE OF CONTENTS
INTRODUCTION
1.1
1.2
1.3
1.4
BACKGROUND
STUDY OBJECTIVES
SCOPE OF HAZOP/HAZID STUDY
REPORT LAYOUT
7
7
8
8
PROJECT DESCRIPTION
2.1
OVERVIEW
2.1.1
Inlet scrubber (V-100)
2.1.2
Station Inlet metering (M-100 A/B)
2.1.3
Dryer Unit (D-100 A/B)
2.1.4
Compressor (K-101 / / K-109)
2.1.5
CNG Cooler ( E-100)
2.1.6
CNG storage cylinders (V-200 1/../ 82)
2.1.7
Double pipe Exchanger
2.1.8
CNG Heat Exchanger (E-200)
2.1.9
Pressure reducing system (PV-0501 A/B)
2.1.10 Storage and Decanting process
2.1.11 Station Outlet Metering (M-200 A/B)
2.1.12 Waste Heat recovery Unit (E-300)
2.1.13 Fuel Gas
2.1.14 Instrument air
2.1.15 Cooling water (E-400)
2.1.16 Fire water system
2.1.17 Water treatment system (W-001)
2.1.18 Insulation
2.1.19 Vent System
9
9
9
10
10
11
11
12
12
12
12
13
13
13
13
14
14
14
14
14
STUDY METHODOLOGY
16
3.1
HAZOP
3.1.1
Overview
3.1.2
Worksheet Definition
3.2
HAZID
3.2.1
Overview
3.2.2
Worksheet Definitions
16
16
16
16
16
17
18
4.1
4.2
4.3
4.4
4.5
INTRODUCTION
THE HAZOP/HAZID TEAM
GUIDE WORDS
DRAWINGS REVIEWED
SELECTED NODES
18
18
18
19
20
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
JULY 2013
HAZOP/HAZID RESULTS
21
5.1
5.2
ACTIONS/RECOMMENDATIONS
MAJOR HAZARD SCENARIO
21
23
HAZOP/HAZID FOLLOW-UP
25
REFERENCES
26
APPENDIX A
APPENDIX B
APPENDIX C
APPENDIX D
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
JULY 2013
PT. PROSIM
EXECUTIVE SUMMARY
The PT Perta Daya Gas has awarded to PT. Enviromate Technology International (PT. ETI) to
conduct and construction of Compressed Natural Gas (CNG) facility. The plant will be located at
Tambak Lorok, Central Java, Indonesia. The CNG facility is consisting of following equipment:
Gas-Liquid separation system, Gas Drying & H2S adsorption system, Gas Compression system,
CNG Cylinders storage package, Heat Exchangers and Metering systems.
The Utility for supporting CNG Plant are consisting Fuel Gas System, Gas power generation, Air
Instrument Package, Waste Heat Recovery Unit, Pumps, Cooling towers, Water treatment Package
and Sump system.
The incoming gas is taken from existing pipe then being compressed to CNG storage cylinders by
CNG Compressors. Storage CNG will be performed maximum at 20 hours/day and decanting phase
will be performed on the peak load within 4 hours/day (18.00 to 23.00). The design capacity of
CNG Plant is 19.88 MMSCFD gas to the CNG storage cylinders.
Waste heat recovery Unit is provided to utilize the energy from exhaust compressor gas engine to
reduce Joule Thompson effect on the pressure reducing system. The WHRU will heat water from
tank which will be utilized as heating media of the CNG gas on CNG heat exchanger.
Cooling water system which consisting of Cooling Tower, Circulation pumps and CNG cooler will
be pro-vided to optimize the requirement of CNG cylinders.
The HAZOP/HAZID review sessions were carried out at the Istana Karang Laut office in Plaza
Citivew Kemang, Jakarta, utilizing 2 days for review, over the period 17th, and 21st June 2013.
The study identified 40 HAZOP recommendations and 18 HAZID recommendations. The
recommendations would reduce potential safety or operability problems associated with the process
or improve the clarity of the process drawings.
HAZOP
Design
It was noted in the HAZOP It identified during the review and also with discussion with Tambak
Lorok, some of the valve arrangement need to be lock open to ensure that it doesnt block due to
human error (eg. at upstream BDV, by pass line). General comments also noted to provide setting
for all the instrumentation system (e.g. PIC, PSHH, PSV)
Its been reviewed that gas from suction compressor can be directed to downstream of E-200 to
metering M-200 resulting in double counting of sales gas from Gundih meter with M-100. It was
recommended to install additional check valve to PG-2"-3C-027 to prevent that case.
It recommended to provide SOP to accommodate gas release from vent of sump tank due to gas
blow by from V-100, to ensure equipment purchase suitable as per hazardous area classification and
also to nsure vent stack at sump tank is located high enough to prevent exposure to
personnel/operator at Incoming Scrubber System.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
JULY 2013
PT. PROSIM
In the Waste Heat Recovery Unit, it was recommended to provide PSHH at downstream P-500A/B
to trip P-500A/B in the case of manual valve at upstream E-300 inadvertenly close resulting in
overpressure of the system.
The existing fire water capacity need to be reviewed to ensure source of water and its amount is
adequate to handle fire on the CNG plant in addition with existing fire water requirement in
Tambak Lorok.
It was discussed also that the design of floating valve T-600 to be radar type.
Maintenance and Operational
Based on the discussion raised up, its required to develop operating manual for delivery gas
including showing correlation between pressure and flow at storage period and operation of
redundant equipment such as compressor.
To control corrosion at basin cooling tower, it was recommended to provide SOP to control PH at
cooling tower periodically.
HAZID
In the HAZID session, location of the lightning stack has not identified yet, therefore it is
recommended to review the location of the lightning stack to be away from the venting stack to
reduce the probability of fire on the vent stack
It was reviewed also that high noise level around the compressor area will potentially injured the
personnel who operate the plant in daily basis. It was recommended to have noise study and provide
warning sign the area to use ear plug protection.
Fire and Gas detection was also reviewed in the HAZID, it is recommended to provide the
philosophy of the fire and gas detection system of the plant in formal documentation and provide
clear actions of each detector, which one create alarm or shut down/blowdown of the plant. Fire
detection philosophy was not provided in the building, specifically in the electrical room such as
control room/MCC/batery room. It is recommended to provide clear philosophy, e.g. providing early
warning system for smoke detection in electrical room (High Sensitivity Smoke Detector), including
fire suppression system such as portable fire extinguisher or automatic fire suppresion system (e.g.
FM-200,etc)
The scenario of fire and explosion in the CNG plant was not established yet during the review
especially in relation position of the processing facility to location where stand by personnel
available such as control room. Therefore, review of this scenario is recommended to justify design
and location of the control room building. It is include also the fire and explosion impact to
surrounding facility at Tambak Lorok. In the discussion also identified that the control room will not
provided with glass windows to avoid explosion effect from the plant, hence that CCTV is
recommended to be provided in the control room to monitor the plant.
During the review, location of the vent stack has not been identified yet. Therefore, dispersion and
radiation analysis need to be done to define safe location and height required for the vent stack.
Consideration for emergency situation was also reviewed, and it is recommended to review
emergency evacuation plan including emergency route, muster point location, safety equipment lay
out and emergency lighting.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
JULY 2013
PT. PROSIM
Good communication among parties involved (Tambak Lorok and Gundih) also important to make
sure operability and deliverability of the process plant, especially to handle emergency situation.
Therefore a procedure defining internal and external communication need to be established among
parties to make sure the plant is operated safely.
MAJOR HAZARD SCENARIO
The Major Hazard of this plant is :
Process Hazard :
1. High Pressure Gas containment in the CNG Storage Tanks
2. Gas Compression System
3. Hot water circulation system
4. Cold Venting
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
JULY 2013
PT. PROSIM
1 INTRODUCTION
1.1 BACKGROUND
PT. Perta Daya Gas is planning to develop CNG Plant Project. The plant will be located at Tambak
Lorok, Central Java province, Indonesia.
PT. Perta Daya Gas therefore commissioned an independent Chairman and Scribe for a series of
safety studies to review and identify hazards and operability issues related to operation of
Compressed Natural Gas Plant Project.
This report details the Hazard and Operability (HAZOP) and Hazard Identification (HAZID) review
and includes a summary of the recommendations identified during the review, as well as the
HAZOP/HAZID review worksheets.
1.2 STUDY OBJECTIVES
The objectives of the HAZOP study are to:
Identify safety related hazards and operability problems related to the process that could directly
threaten the safety of production personnel or cause operational problems;
Identify engineering and procedural safeguards already incorporated into the design that will
reduce the likelihood or the severity of consequences related to the identified problem;
Assess changes and consider new requirements that have emerged since the last PHA;
Identification of new hazard causes or initiating factors associated with the modifications with a
potential to result in major accident events (MAEs), which may give rise to serious and
immediate risk to health and safety of personnel;
Determination of risk based on the likelihood and the severity of the consequences for each
identified MAEs;
Identification of existing safeguards that may include engineering or operational controls and
measures included in the design for prevention and/or mitigation of the MAEs;
Evaluation of the residual risk taking into account the existing control and mitigation measures;
and
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
JULY 2013
PT. PROSIM
2. Utilities
Venting system
Engine Generator
Section 1 gives an introduction, defining the objectives and scope of the study;
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
JULY 2013
PT. PROSIM
2 PROJECT DESCRIPTION
2.1 OVERVIEW
The CNG facility is consisting of following equipment: Gas-Liquid separation system, Gas Drying
& H2S adsorption system, Gas Compression system, CNG Cylinders storage package, Heat
Exchangers and Metering systems.
The Utility for supporting CNG Plant are consisting Fuel Gas System, Gas power generation, Air
Instru-ment Package, Waste Heat Recovery Unit, Pumps, Cooling towers, Water treatment Package
and Sump system.
The incoming gas is taken from existing pipe then being compressed to CNG storage cylinders by
CNG Compressors. Storage CNG will be performed maximum at 20 hours/day and decanting phase
will be performed on the peak load within 4 to 5 hours/day (18.00 to 23.00). The design capacity of
CNG Plant is 19.88 MMSCFD gas to the CNG storage cylinders.
Waste heat recovery Unit is provided to utilize the energy from exhaust compressor gas engine to
reduce Joule Thompson effect on the pressure reducing system. The WHRU will heat water from
tank which will be utilized as heating media of the CNG gas on CNG heat exchanger.
Cooling water system which consisting of Cooling Tower, Circulation pumps and CNG cooler will
be pro-vided to optimize the requirement of CNG cylinders.
2.1.1 Inlet scrubber (V-100)
The gas scrubber (V-100) will be installed on incoming gas to remove any hydrocarbon liquid from
upstream facility. The liquid level on the gas scrubber will be controlled by control valve LV-0101
to avoid liquid carried over to the CNG Plant. High liquid level on the scrubber will initiate the
valve to open, then if liquid level has reached normal condition valve will be closed, so the valve
will be as on/off mode.
The gas scrubber is provided with PSV-0101A/B with set pressure of 34 barg for overpressure
protection, One PSV will be on operation and another one as spare.
Inlet line will be provided with SDV-0101 in order to isolate the plant in emergency condition. The
initiators of SDV-0101 closing refer to Cause & effect diagram.
2.1.2 Station Inlet metering (M-100 A/B)
The metering will measure natural gas inlet to CNG plant. Total gas inlet is 19.88 MMSCFD. Gas
inlet would be 19.88 MMSCFD and flows to inlet compressor and 1.1 MMSCFD flows to auxiliary
fuel gas. Metering type is 2x100% custody orifice meter. Metering will be operated in continous
operation. Flow and accumulation flow should be monitored by flow computer. Gas inlet to
metering tends to consist of high moisture. Orifice should be designed for wet gas condition.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
JULY 2013
PT. PROSIM
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
10
JULY 2013
PT. PROSIM
The compressor is reciprocating type in three stages compression, air coolers will be provided on
each discharge stage to enhance the efficiency of compressor.
The maximum discharge pressure and temperature from CNG compressor are 250 barg and 48OC
respectively. The compressor will be supplied by vendor as a skid including electrical and
instrumentation inside. Control system of CNG compressor is provided with PLC by vendor, the
operating parameter will be transferred to Plant Control System (PCS) for monitoring purpose.
Shutdown system of the compressors will be managed by PLC, trigger of shutdown such as lube oil
pressure low, suction pressure low, discharge pressure high, discharge temperature high and High
vibration will be further developed by vendor.
Compressors are driven by Gas Engine drive with fuel gas that supplied from upstream of dryer
skid.
2.1.5 CNG Cooler ( E-100)
Compressed gas from CNG compressor with temperature of 48oC will be cooled down to 35oC
before entering to CNG cylinders. Cooling water system is closed loop cooling system which
involving CNG cooler (E-100), Cooling water circulation pump (P-200A/B) and Cooling Tower (E400). The compressed natural gas need to be cooled down to 35oC for optimizing the requirement of
cylinder storage capacity. The temperature of cooling water inlet to CNG cooler (E-100) is 30oC and
temperature cooling water outlet at 39oC. To avoid prolonged overpressure due to tube rupture,
CNG Compressor would be shut downed by PSHH-0503 then CNG gas would be release to cooling
water return line to Cooling tower (E-400).
DURING DECANTING PERIOD:
Cooling water to CNG Cooler will be discontinued to produce CNG stream with temperature 48oC
and it will be commingled with CNG stream from compartment (Temperature 35 oC).
If pressure decreases and disturbing performance of CNG compressor then CNG stream could be
flowed through E-100 bypass line. Restriction orifice installed in this bypass line to giving sufficient
backpressure for CNG compressor.
2.1.6 CNG storage cylinders (V-200 1/../ 82)
CNG from E-200 will be stored at CNG storage cylinders. The CNG storage cylinders are consisting
of 95 compartment (base on 20 hours storage time at 18.7 MMSCFD CNG inlet). Each
compartment is consisting of 8 tube cylinders. One cylinder has capacity of 2.38 m3. Three CNG
compartment will be arranged in 1 (one) bank. Each bank will be provided 1 unit manual valve for
incoming and outgoing CNG. Pressure relief device (PSV) protect respectives cylinders. Discharge
PSV will be released to atmosphere and no additional pipe is required for PSV discharge line.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
11
JULY 2013
PT. PROSIM
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
12
JULY 2013
PT. PROSIM
Duration of decanting can be resetted from the control room, but changing setting time shall refer to
operating pressure on the CNG storage cylinders. Over pressure on the CNG cylinders will initiate
high pressure on the discharge compressor then process shutdown can be triggered.
2.1.11 Station Outlet Metering (M-200 A/B)
The metering system with 2x100% with crossover will measure natural gas outlet from CNG plant.
Total gas outlet is 113 MMSCFD for 4 hours. Metering is used as custody meter. Flow and
accumulation flow should be monitored in main PLC. For Gas composition analysis, one sampling
connection is installed at the upstream of Outlet Metering (M200A/B).
Gas Flow would be measured for 4 hours per day during decanting time. Totalizer would count total
value base on measured gasflow.
2.1.12 Waste Heat recovery Unit (E-300)
The exhaust gas from gas engines ducting will be utilized as source of energy to increase the
temperature of hot water from 63oC to 90oC. Exhaust gas from each turbine will be commingled on
header before entering WHRU, and water will be heating up on the WHRU boiler.
Hot water from WHRU will be stored on the hot water storage Tank at temperature of 90oC.
During storage phase (20 hours), WHRU would heat water in Hot water tank (T-200) for
approximately 10 hours from 30o to 90o C. The water circulating pump (P-500 A/B) with capacity of
45m3/hr is used to circulate water from T-200 through WHRU heater (E-300) and back to T-200.
During decanting phase (4 hours), Hot water pump (P-300 A/B) with capacity of 140 m3/h will
circulate hot water from T-200 to E-200 and back to T-200. Temperature of hot water in the Hot
water tank (T-200) is controlled by manipulating damper position on each exhaust gas Turbine of
CNG compressors.
2.1.13 Fuel Gas
Fuel gas is supplied for two (2) units gas engine generators (1 operation & 1 stand by) thru Fuel gas
strainer and for ten (10) units gas engine compressors (9 operation and 1 unit standby). The fuel gas
strainer is designed based on capacity of less than 1.5 MMSCFD.
Fuel Gas metering (FQI-0901) is provided to measure auxilary fuel gas consumption in CNG
facility.
2.1.14 Instrument air
The instrument air will be provided on CNG plant to enhace the overall reliability of the Plant.
Instrument air requirement is calculated based on the number of control valves and on-off control
valves plus a design margin of 20%. Three (3) Air compressors will be provided with two operating
as lead and lag basis and one compressor as a standby.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
13
JULY 2013
PT. PROSIM
Instrument air system will be provided with a drying unit such that the dew point of instrument air is
less than -40oC.
2.1.15 Cooling water (E-400)
Water as cooling media will be utilized for CNG Cooler (E-100) before storage stage, The CNG
from gas compressor with temperature of 48oC will be cooled down to 35oC using cooled water.
Cooling water is supplied to the heat exchangers through the Cooling Tower Pump (P-200 A/B) at
flowrate of 35m3/hr. After taking heat of CNG, cooling water leaves heat exchanger at temperature
of 30oC is re-circulated to the Cooling Tower ( E-400) for cooling down and reused. Make-up water
will be provided to compensate water losses on the Cooling Tower (E-400).
2.1.16 Fire water system
Fire water will be taken from existing fire water system in front of CNG plant.
Fire hydrants and monitors will be located based on equipment layout during detail engineering.
2.1.17 Water treatment system (W-001)
Auxiliary water for CNG plant will be taken from well in plant. Well water will be treated by
Reverse osmisis (RO) technology prior to be used as make up water. Total consumption for make
up water is 3.2 m3/h. The feedwater to the RO unit will be design accordingly based on input from
vendor.
2.1.18 Insulation
Personnel Protection Insulation (PP) shall be specified on all lines with normal operating
temperatures above 70C. This will be applied only to sections of pipe that personnel could come
into contact with during normal operation.
Heat Conservation Insulation (HC) shall be specified for heated systems above 65C (e.g. hot water
from WHRU).
Noise Abatement Insulation (NI) shall be specified on compressor suction and discharge lines,
subject to vendor confirmation.
2.1.19 Vent System
Relief Gas from Pressure safety valves and Blow down system would be collected to vent header
then to vent stack. Automatic drain would be provided to controlling liquid level at bottom vent
stack.
Flame arrester would be installed at upstream of vent stack to avoid flame due to lightning or other
fire source.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
14
JULY 2013
PT. PROSIM
Relief gas from CNG cylinders would be free vent to atmosphere instead of to vent header line as
per client and manufacture requirement.
The vent stack with providing water seal at the bottom of the vent stack to prevent air ingress.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
15
JULY 2013
PT. PROSIM
3 STUDY METHODOLOGY
3.1 HAZOP
3.1.1 Overview
The study was carried out using the traditional HAZOP Guide Word method, where the system is
broken down into manageable sections and a set of standard Guide Words applied. The
methodology requires exhaustive consideration of each process activity to determine if there are any
potential problems in relation to safety or operations that may arise due to deviations in the process.
The Causes and Consequences of each deviation are identified. The HAZOP team evaluates the
severity of the problem and adequacy of existing safeguards, and where necessary, recommends
additional safeguards as Actions. The hazard and operability problems highlighted in the course of
the review were captured in the HAZOP Review worksheets (Appendix A).
3.1.2 Worksheet Definition
All concerns raised are documented in the HAZOP Review Worksheets, which include the column
headers as described in Table 3.2a.
Table 3.1a
Column Heading
No.
Description
Reference Number
Guide word/Deviation
Possible Causes
Possible Consequences
Type
Safeguard
Recommendations/Comment
Action Party
16
JULY 2013
PT. PROSIM
prevent such incidents from occurring. A HAZID review is based on a combination of identification,
analysis and brainstorming activities. The technique exhaustively considers each review area, by
reference to an agreed set of guidewords. During the review, each facility was considered in turn
with the facility broken down according to specific areas or enclosed buildings, e.g., Main Deck.
3.2.2 Worksheet Definitions
All findings during the HAZID sessions are recorded by the scribe using HAZID worksheets. These
worksheets contain the column headings given in Table 3.3b.
Table 3.3b
Column Heading
Description
No.
Reference number
Category / Guideword
Event Description
Consequence
Prevention
Control
Recommendation /
Comments
Action Party
Ranking
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
17
JULY 2013
PT. PROSIM
4.1 INTRODUCTION
The HAZOP/HAZID review sessions were carried out at the Istana Karang Laut office in
Plaza Citiview Kemang, Jakarta, utilizing 2 days for review, over the period 17th and 21st
June 2013.
4.2 THE HAZOP/HAZID TEAM
The HAZOP/HAZID team comprises a multidisciplinary team of personnel involved with the design
and operation of the facilities, led by a safety consultant from PT PROSIM The names and
attendance records of the HAZOP/HAZID team members for each of the systems are tabulated in
Table 4.2a.
Table 4.2a
Name
Co.
Role
June
2013
June
2013
17
21
Margaretha T
PT PROSIM
Chairman
Yulia Tirtasiwi
PT PROSIM
Scribe
Sugiyanto
PT ETI
Process Engineer
Bernardo
PT ETI
Rudolf S
PT ETI
Suarno
PT ETI
Cut Julia
PT IKL
Project Manager
Warno Abdullah
PT IKL
Engineering Manager
Suseno
PT IKL
Process Engineer
Irvan N
PT IKL
Haidar
PT IKL
Gigin Ginanjar
PT IKL
PT IKL
Isa
Process Engineer
Guide Word
No Flow
Less Flow
More Flow
Reverse Flow
Misdirected Flow
Less Level
More Level
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
18
JULY 2013
8
9
10
11
12
13
14
15
16
17
18
19
20
21
PT. PROSIM
Less Pressure
More Pressure
Less Temperature
More Temperature
Contaminants
Composition
Corrosion / Erosion
Instrumentation
Relief
Personnel Safety
External Factors
Operations
Maintenance
Drawing
Table 4.3b
Safety System
Guide Word
No.
Comments
Non Process
Structural Failures
Extreme weather/subsidence/fatigue
Events
Impact
Collisions
Transportation
Helicopter/personnel baskets/vessels
Lifting
Dropped Objects
Fires/escalated fires
Toxic Release
Chemical spill
Security
Pirates/fishermen
Noise
Health hazards
Diseases/working condition/chemicals
Loss of
containment
Ignition
Safety Systems
Ignition Sources
Escape/ Refuge
Personnel escape to TR
Communication
Hotlines/radio, etc
Emergency Lighting
Discharge to air
Discharge to water
Discharge to soil
Waste disposal
Environmental
Hazards
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
19
JULY 2013
PT. PROSIM
Node
Section
Drawing Number
Rev
N1
Incoming Gas from Gundih field through Gas Scrubber V100 to Station Inlet Metering M100A/B
TS78-P-PID-001
TS78-P-PID-002
B
B
N2
TS78-P-PID-003
N2R
N3
Regeneration System
Compression System K101 (typical for K102 to K109),
including Blowdown Tank VE301A
TS78-P-PID-003
TS78-P-PID-004
B
B
N4
TS78-P-PID-005 Sheet 1 of 2
TS78-P-PID-005 Sheet 2 of 2
TS78-P-PID-006
TS78-P-PID-007
TS78-P-PID-005 sheet 2 of 2
B
B
N5
N6
TS78-P-PID-007
TS78-P-PID-012
TS78-P-PID-011
N10
TS78-P-PID-010
N11
TS78-P-PID-009
N12
N13
TS78-P-PID-008 Sheet 1 of 2
TS78-P-PID-008 Sheet 2 of 2
TS78-P-PID-013
N14
TS78-P-PID-014
N15
TS78-P-PID-015
N7
N8
N9
Table 4.5b
Node
N1
Section
Drawing Number
TS78-L-LY-001
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
20
Rev
B1
JULY 2013
PT. PROSIM
5 HAZOP/HAZID RESULTS
5.1 ACTIONS/RECOMMENDATIONS
A total of 40 HAZOP recommendations and 18 HAZID recommendations were generated during the
review. The recommendations would reduce potential safety or operability problems associated with
the process or improve the clarity of the process drawings (P&IDs). A complete list of the
recommendations made by the team during the review itself is tabulated in Appendix A. A unique
number is assigned to each recommendation and the node identification number is included so that it
may easily be traced back to the review worksheets (Appendix B & C). Brief summary of
highlighted recommendations are presented below.
HAZOP
Design
It was noted in the HAZOP It identified during the review and also with discussion with Tambak
Lorok, some of the valve arrangement need to be lock open to ensure that it doesnt block due to
human error (eg. at upstream BDV, by pass line). General comments also noted to provide setting
for all the instrumentation system (e.g. PIC, PSHH, PSV)
Its been reviewed that gas from suction compressor can be directed to downstream of E-200 to
metering M-200 resulting in double counting of sales gas from Gundih meter with M-100. It was
recommended to install additional check valve to PG-2"-3C-027 to prevent that case.
It recommended to provide SOP to accommodate gas release from vent of sump tank due to gas
blow by from V-100, to ensure equipment purchase suitable as per hazardous area classification and
also to nsure vent stack at sump tank is located high enough to prevent exposure to
personnel/operator at Incoming Scrubber System.
In the Waste Heat Recovery Unit, it was recommended to provide PSHH at downstream P-500A/B
to trip P-500A/B in the case of manual valve at upstream E-300 inadvertenly close resulting in
overpressure of the system.
The existing fire water capacity need to be reviewed to ensure source of water and its amount is
adequate to handle fire on the CNG plant in addition with existing fire water requirement in Tambak
Lorok.
It was discussed also that the design of floating valve T-600 to be radar type.
Maintenance and Operational
Based on the discussion raised up, its required to develop operating manual for delivery gas
including showing correlation between pressure and flow at storage period and operation of
redundant equipment such as compressor.
To control corrosion at basin cooling tower, it was recommended to provide SOP to control PH at
cooling tower periodically.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
21
JULY 2013
PT. PROSIM
HAZID
In the HAZID session, location of the lightning stack has not identified yet, therefore it is
recommended to review the location of the lightning stack to be away from the venting stack to
reduce the probability of fire on the vent stack
It was reviewed also that high noise level around the compressor area will potentially injured the
personnel who operate the plant in daily basis. It was recommended to have noise study and provide
warning sign the area to use ear plug protection.
Fire and Gas detection was also reviewed in the HAZID, it is recommended to provide the
philosophy of the fire and gas detection system of the plant in formal documentation and provide
clear actions of each detector, which one create alarm or shut down/blowdown of the plant. Fire
detection philosophy was not provided in the building, specifically in the electrical room such as
control room/MCC/batery room. It is recommended to provide clear philosophy, e.g. providing early
warning system for smoke detection in electrical room (High Sensitivity Smoke Detector), including
fire suppression system such as portable fire extinguisher or automatic fire suppresion system (e.g.
FM-200,etc)
The scenario of fire and explosion in the CNG plant was not established yet during the review
especially in relation position of the processing facility to location where stand by personnel
available such as control room. Therefore, review of this scenario is recommended to justify design
and location of the control room building. It is include also the fire and explosion impact to
surrounding facility at Tambak Lorok. In the discussion also identified that the control room will not
provided with glass windows to avoid explosion effect from the plant, hence that CCTV is
recommended to be provided in the control room to monitor the plant.
During the review, location of the vent stack has not been identified yet. Therefore, dispersion and
radiation analysis need to be done to define safe location and height required for the vent stack.
Consideration for emergency situation was also reviewed, and it is recommended to review
emergency evacuation plan including emergency route, muster point location, safety equipment lay
out and emergency lighting.
Good communication among parties involved (Tambak Lorok and Gundih) also important to make
sure operability and deliverability of the process plant, especially to handle emergency situation.
Therefore a procedure defining internal and external communication need to be established among
parties to make sure the plant is operated safely.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
22
JULY 2013
PT. PROSIM
Process Hazard :
1. High Pressure Gas containment in the CNG Storage Tanks
2. Gas Compression System
3. Hot water circulation system
4. Cold Venting
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
23
JULY 2013
PT. PROSIM
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
24
JULY 2013
PT. PROSIM
6 HAZOP/HAZID FOLLOW-UP
The project, design and operation team should conduct a HAZOP/HAZID follow up session to
response the HAZOP/HAZID recommendations. The response and action plan shall be back up with
the relevant data and justification whether the recommendation is agreed or rejected. At the end, the
team shall formulate action plans, steward all action items and ensure that the relevant changes are
made to the design to address hazard and operability concerns identified as part of this
HAZOP/HAZID.
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BB
25
JULY 2013
7 REFERENCES
/1/
/2/
Drawing List :
No
Drawing Title
Drawing Number
Rev
1
2
3
4
5
B
B
B
B
B
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
19
20
TS78-P-PID-001
TS78-P-PID-002
TS78-P-PID-003
TS78-P-PID-004
TS78-P-PID-005 Sheet 1
of 2
TS78-P-PID-005 Sheet 2
of 2
TS78-P-PID-006
TS78-P-PID-007
TS78-P-PID-008 Sheet 1
of 2
TS78-P-PID-008 Sheet 2
of 2
TS78-P-PID-009
TS78-P-PID-010
TS78-P-PID-011
TS78-P-PID-012
TS78-P-PID-013
TS78-P-PID-014
TS78-P-PID-015
TS78-L-LY-001
TS78-P-PFD-001
TS78-P-PFD-002
TS78-P-PFD-003
TS78-P-PFD-004
TS78-P-PFD-005
TS78-P-PFD-006
TS78-P-UFD-001
TS78-P-UFD-002
HAZOP & HAZID REPORT - CNG GAS PLANT - TAMBAK LOROK REV BA26
B
B
B
B
B
B
B
B
B
B
B
B
B1
B
B
B
B
B
B
B
B
JULY 2013
Appendix A
Causes / Concerns
SDV 0101 at upstream V-100
close due to failure
Consequences
Comments / Recommendations
Potential overpresurization of upstream plant (Santos Ensure existing pipeline design pressure is higher
Facility ) resulting in hydrocarbon release leading to than maximum discharge pressure from Gundih
fire or fatality
facility
Rec Number
CNG-HP-1
Loss of Production
CNG-HP-2
Potential overpresurization of upstream plant (Santos Provide operating manual for delivery gas
Facility ) resulting in hydrocarbon release leading to
fire or fatality
Potential overpressurization of V-100 resulting in
Provide setting pressure PIC-0105 to show at PID
hydrocarbon release leading to fire or fatality
TS78-P
CNG-HP-3
Gas blowby to Sump Tank V-400 leading to potential Provide SOP to accommodate gas release from vent
vessel damage (design pressure 3.5 barG), fire and
of sump tank due to gas blow by from V-100
explosion
CNG-HP-5
CNG-HP-6
CNG-HP-7
CNG-HP-8
CNG-HP-4
CNG-HP-9
Overpresurization of upstream equipment leading to Provide Lock Open (LO) at manual valve upstream
fire/fatality
BDV-0301
CNG-HP-10
CNG-HP-11
CNG-HP-12
CNG-HP-13
CNG-HP-14
Fouling/Plugging at E-100 or
loss of cooling water
CNG-HP-15
CNG-HP-16
CNG-HP-17
2R
2R
Double counting of sales gas from Santos meter with Install additional check valve at line PG-2"-3C-027
M-100
CNG-HP-18
Overpresurization of upstream equipment leading to Provide Lock Open (LO) manual valve at upstream
fire/fatality
BDV-0505
CNG-HP-19
CNG-HP-20
Provide low temperature switch at line PG-12"-3C021 to close KV-0503 A to prevent low temperature
in the gas sales
Hot Water Pump P-300A/B stop High temperature in the circulation water around the Provide low temperature alarm at line PG-12"-3Cdue to failure OR Strainer at
waste heat recovery unit
021 to alert operator
upstream P-300A/B blockage
CNG-HP-21
Three way valve TV-0502 to E- Loss of hot water supply leading to inefficient heat
200 is inadvertenly close
transfer and lower gas sales temperature
Any manual valve at upstream E- Potential overpressure of downstream pump
300 inadvertenly close or check
One or more gas engine driver
Less of flue gas to E-300 resulting in lower
shutdown
temperature generated for water circulation
CNG-HP-22
7
7
Start up
Condense water from flue gas at Corrosion at E-300 leading to equipment damage
E-300
Low gas temperature from exhaust gas compressor to Provide drain line at lowest point gas ducting E-300
WHRU resulting condensation at gas ducting E-300
Page 1 of 2
CNG-HP-23
CNG-HP-25
CNG-HP-26
CNG-HP-27
NODE
7
9
10
Causes / Concerns
Drawing
Manual valve at outlet T-100 is
inadvertenly close or strainer
blocked
Manual valve or strainer at inlet
Basin cooling water is
inadvertently close
Manual valve at upstream P200A/B inadvertenly close or
strainer blocked
Liquid control valve failure at
individual equipments (V-300,
Compressor K-101-109, V-100)
Consequences
Comments / Recommendations
Revise drawing TS78-P-PID-007 to show setting
point of all instrumentation alarm and trip
Rec Number
CNG-HP-28
CNG-HP-29
CNG-HP-30
CNG-HP-31
CNG-HP-32
11
CNG-HP-33
12
CNG-HP-34
12
CNG-HP-35
13
CNG-HP-36
13
Operation
CNG-HP-37
14
CNG-HP-38
14
CNG-HP-39
CNG-HP-40
15
Page 2 of 2
Hazard Description
Consequences
Lightning
Prevention
4.3.1
Potential impact to
piping/equipment
leading to hydrocarbon
release, fire, personnel
injury/fatality and asset
damage
High noise level from Potential personnel ear compressor and gas
injury
engine area
Toxic Material during Personnel injury
MSDS provided in the
handling chemical: for
storage facility
cooling water,
corrosion inhibitor e.g.
oxygen scavanger
4.7.1
4.8.1
Control
Recommendation/ Comment
Rec Number
Co.
Pr
Ri
Type
S (4)
C(3)
S (H16)
C(H12)
Design
S (4)
C(4)
S (H8)
C(H8)
Operation /
Maintenance
CNG-HD- 3
S (1)
C(-)
S (H3)
C(-)
Design
S (1)
C(-)
S (H3)
C(-)
Design
Grounding provided
for each equipment
4.8.3
Hazardous waste
disposal
CNG-HD- 5
S (1)
C(-)
S (H3)
C(-)
Operation /
Maintenance
4.9.6
Hot Surfaces at
exhaust gas, WHRU
and heat exchanger (E200)
Leak from Process
Equipment
PPE
CNG-HD- 6
S (2)
C(-)
S (M4)
C(-)
Design
4.10.1
Loss of Containment
personal protection
insulation provided
CNG-HD- 7
S (4)
C(4)
S (H8)
C(H8)
Design
CNG-HD- 8
S (4)
C(4)
S (H8)
C(H8)
Operation /
Maintenance
CNG-HD- 9
S (4)
C(4)
S (H8)
C(H8)
Operation /
Maintenance
CNG-HD- 10
S (4)
C(4)
S (H8)
C(H8)
Design
ERP
CNG-HD- 11
S (4)
C(4)
S (H8)
C(H8)
Design
CNG-HD- 12
S (4)
C(4)
S (H8)
C(H8)
Operation /
Maintenance
CNG-HD- 13
S (4)
C(4)
S (H8)
C(H8)
Design
S (4)
C(4)
S (H8)
C(H8)
Design
S (4)
C(4)
S (H8)
C(H8)
Design
S (4)
C(4)
S (H8)
C(H8)
Design
S (4)
C(4)
S (H8)
C(H8)
Design
4.11.1
Battery
Fire/explosion in the
event of hydrocarbon
release.
4.11.2
Vent
Fire/explosion in the
event of hydrocarbon
release in process area if
stroke by lightning
4.12.1
4.14.1
Control room
Inability to monitor
process area
Battery room is
located in non
hazardous area
4.15.1
Inability to contact
control room within
emergency
Inability to coordinate
Each operator
response leading to
provided with hand
potential major accident held radio
leading to personnel
injury/fatality and asset
loss
4.16.1
Inability to initiate
ESD
4.18.3
Blowdown of water
from cooling tower,
discharge RO
Potential contamination
from process fluid
Discharge water is
Define Sampling point Define Sampling point to
connected to existing to monitor discharge monitor discharge water
canal (IP)
water
Page 1 of 1
CNG-HD- 17
CNG-HD- 18
Appendix B
Node
1
Review date 17-Jun-13
Client
Project
Facility
Section
Comment
Design
Intent
Abbreviations
SOP
IM
PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C
Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk
To remove any hydrocarbon liquid from upstream facility and measure natural gas inlet to CNG plant
Design
DP : 34 barG
Conditions:
DT: 65 deg C
Opt.
Conditions
OP : 20.6-30.9 barG
Drawing
No.
Guide
Words
Parameter: Flow
1.1.1
No
Deviation
No Flow
OT : 26.7-51.7 deg C
Causes / Concerns
Consequences
Safeguards
Initiating
L
Co
Pr
S (4)
C(4)
Ri
Ri
S (M4)
C(M4)
Loss of Production
1.1.2
No
No Flow
S (4)
C(4)
S (M4)
C(M4)
Comments / Recommendations
B
B
Rec. No.
CNG-HP-1
CNG-HP-2
CNG-HP-3
Loss of Production
Page 1 of 53
HAZOP Node N1
No.
1.1.3
1.1.4
Guide
Words
No
No
Deviation
No Flow
No Flow
Causes / Concerns
Co
Pr
Ri
S (4)
C(4)
S (M4)
C(M4)
Any of manual valves at Station Inlet Potential overpresurization PIH-0103 set at 30 barg as
Metering M100A/B inadvertently
of upstream M-100A/B
high pressure alarm to
close
resulting to fire or fatality alert operator
S (4)
C(4)
S (M4)
C(M4)
S (-)
C(2)
S (-)
C(L2)
1.2.1
Less
Less Flow
1.3.1
More
More Flow
Slugging
1.4.1
Reverse
Reverse Flow
1.5.1
Part of
1.5.1
Part of
Consequences
Safeguards
Initiating
L
Comments / Recommendations
Provide setting pressure PIC-0105
to show at PID TS78-P
Rec. No.
CNG-HP-4
Parameter: Level
Page 2 of 53
HAZOP Node N1
No.
1.6.1
Guide
Words
Less
Deviation
Less Level
Causes / Concerns
Consequences
Safeguards
Control loop malfunction causing LV- Gas blowby to Sump Tank LIL-0102 alarm to alert
0101 to open fully
V-400 leading to potential Operator
vessel damage (design
pressure 3.5 barG), fire and
explosion
LILL-0102 to initiate
shutdown of SDV-0102
Initiating
L
Co
Pr
Ri
Comments / Recommendations
S (4)
C(4)
S (M4)
C(M4)
CNG-HP-5
CNG-HP-6
CNG-HP-7
Less
Less Level
1.7.1
More
More Level
1.7.2
1.7.3
1.7.4
More
More
More
More Level
More Level
More Level
Slugging
LIHH-0102 to initiate
shutdown of SDV-0101
High level at V-100 leading LIH-0102 as high level
to liquid carry over to
alarm to alert Operator to
metering skid M-100 and
open by pass line
downstream equipment
S (4)
C(4)
S (M4)
C(M4)
S (-)
E (2)
C(2)
S (-)
E (L2)
C(L2)
S (-)
C(2)
S (-)
C(L2)
S (-)
C(2)
S (-)
C(L2)
Rec. No.
LIHH-0102 to initiate
shutdown of SDV-0101
High level at V-100 leading LIH-0102 as high level
to liquid carry over to
alarm to alert Operator to
metering skid M-100 and
open by pass line
downstream equipment
LIHH-0102 to initiate
shutdown of SDV-0101
High level at V-100 leading LIH-0102 as high level
to liquid carry over to
alarm to alert Operator to
metering skid M-100 and
open by pass line
downstream equipment
Page 3 of 53
HAZOP Node N1
No.
Guide
Words
Deviation
Causes / Concerns
Consequences
Safeguards
Initiating
L
Co
Pr
Ri
S (4)
C(4)
S (M4)
C(M4)
S (-)
E (2)
C(2)
S (-)
E (L2)
C(L2)
S (-)
C(2)
S (-)
C(L2)
S (4)
C(4)
S (M4)
C(M4)
Comments / Recommendations
Rec. No.
LIHH-0102 to initiate
shutdown of SDV-0101
as
1.8.1
1.8.2
1.9.1
Less
Less
More
Less Pressure
Less Pressure
More Pressure
Release of hydrocarbon
PIL-0102 as low pressure
leading to environmental alarm at incoming V-100
pollution and potential fire to alert operator
PILL-0102 at incoming V100 will initiate closure of
SDV 0101
Fire and Gas Detector at V100
Potential overpressure at
Metering M100A/B and
downstream equipment
Potential overpressure at
Metering M100A/B and
downstream equipment
Parameter: Temperature
1.10.1
Less
Less Temperature No additional significant issues of
concerns identified
1.11.1
More
Parameter: Contamination
1.12.1
As Well
Contamination
As
Parameter: Composition
1.13.1
Other
Composition
Than
CNG-HP-8
Parameter: Instrumentation
Page 4 of 53
HAZOP Node N1
No.
1.15.1
Guide
Words
Other
Than
Parameter: Relief
1.16.1
Other
Than
Parameter: Safety
1.17.1
Other
Than
Deviation
Causes / Concerns
Instrumentation
Relief
Occupational
Safety
Fire at plant
Overpresurization of
piping leading to
equipment damage
Safeguards
Initiating
L
Co
Pr
Ri
S (-)
C(2)
S (-)
C(L2)
Comments / Recommendations
Rec. No.
1.20.1
Other
Than
Maintenance
1.20.2
Other
Than
Maintenance
Parameter: Drawing
1.21.1
Other
Than
Consequences
Drawing
Page 5 of 53
HAZOP Node N1
Node
Abbreviations
Comment
Design
Intent
SOP
IM
PM
Preventative Maintenance
USD
Unit Shutdown
PSD
Process Shutdown
ESD
Emergency Shutdown
H,M,L
High, Medium, Risk
Co
Consequence
Pr
Probability
Ri
Risk
S
Safety Risk
C
Commercial Risk
One bed of dryer will be on drying mode and the other one is on regenerating mode. Adsorption time is 4-8 hours and the regeneration time 4-8 hours (heating, cooling and standby)
To remove water and H2S content on the feed gas to produce moisture dew point to -40 deg C and max 3 ppm H2S
Design
DP : 34 barG
Conditions:
Opt.
OP : 20.6-30.9 barG
Conditions
Drawing
No.
Guide
Words
Parameter: Flow
2.1.1
No
Deviation
No Flow
Drawing No.
Causes / Concerns
Consequences
Safeguards
Potential
PIH 0102 alarm set at 30
overpressurization of
barG to alert Operator
upstream equipment of D100 leading to rupture and
potential fire event
PIHH 0102 set at 33 barG to
initiate closure of SDV 0101
Initiating
L
Co
Pr
Ri
S (4)
C(4)
S (M4)
C(M4)
S (4)
C(4)
S (M4)
C(M4)
Comments / Recommendations
Rev:
Action Party
Rec. No.
Less
Less Flow
F-100 Blockage
Potential
PIH 0102 alarm set at 30
overpressurization of
barG to alert Operator
upstream equipment of D100 leading to rupture and
potential fire event
PIHH 0102 set at 33 barG to
initiate closure of SDV 0101
PSV 0101A/B set at 33 barg
PDI at F-100 as local
indicator for operator
Page 6 of 53
HAZOP Node N2
No.
2.2.2
Guide
Words
Less
Deviation
Less Flow
Causes / Concerns
Consequences
Co
Pr
Ri
S (4)
C(4)
S (M4)
C(M4)
S (4)
C(4)
S (M4)
C(M4)
Depressurization of the
BDV position indication
system, loss of gas to flare and alarm
and loss of production
S (-)
C(3)
S (-)
C(M3)
S (4)
C(4)
S (M4)
C(M4)
Safeguards
Initiating
L
Comments / Recommendations
Action Party
Rec. No.
2.2.3
Less
Less Flow
F-110 Blockage
2.2.4
Less
Less Flow
2.3.1
More
More Flow
2.4.1
Reverse
Reverse Flow
2.5.1
Part of
2.5.2
Part of
2.5.3
Part of
SOP
Page 7 of 53
HAZOP Node N2
No.
2.5.4
Guide
Words
Part of
2.5.5
Part of
2.5.6
Part of
Deviation
Causes / Concerns
Consequences
Safeguards
SOP
SOP
Parameter: Level
2.6.1
Less
2.7.1
More
Less Level
More Level
Parameter: Pressure
2.8.1
Less
Less Pressure
2.8.2
2.9.2
Less
More
Less Pressure
More Pressure
2.9.1
More
More Pressure
2.9.
More
More Pressure
Initiating
L
Co
Pr
Ri
Comments / Recommendations
S (-)
C(3)
S (-)
C(M6)
S (4)
C(4)
S (M4)
C(M4)
S (4)
C(4)
S (M4)
C(M4)
Action Party
Rec. No.
Release of hydrocarbon
leading to environmental
damage and potential fire
CNG-HP-10
Parameter: Temperature
2.10.1
Less
Less Temperature No additional significant issues of
concerns identified
2.11.1
More
Parameter: Contamination
2.12.1
As Well
Contamination
As
Parameter: Composition
2.13.1
Other
Composition
Than
Page 8 of 53
HAZOP Node N2
No.
2.14.1
Guide
Words
Other
Than
Deviation
Corrosion /
Erosion
Causes / Concerns
Parameter: Instrumentation
2.15.1
Other
Instrumentation
Than
Parameter: Relief
2.16.1
Other
Than
Relief
Occupational
Safety
Parameter: Safety
2.17.1
Other
Than
Other
Than
Parameter: Drawing
2.21.1
Other
Than
Fire
Safeguards
Wall thickness of piping
and equipment already
considered sour gas
condition
Initiating
L
Co
Pr
Ri
S (3)
C(4)
S (M3)
C(M4)
S (-)
C(2)
S (-)
C(M4)
Comments / Recommendations
Action Party
Rec. No.
Maintenance
Drawing
Consequences
Page 9 of 53
HAZOP Node N2
2R
Node
Review date 17-Jun-13
Client
Project
Facility
Section
Comment
Design
Intent
Design
Opt.
Drawing
Abbreviations
SOP
IM
PM
Preventative Maintenance
USD
Unit Shutdown
PSD
Process Shutdown
ESD
Emergency Shutdown
H,M,L
High, Medium, Risk
Co
Consequence
Pr
Probability
Ri
Risk
S
Safety Risk
C
Commercial Risk
One bed of dryer will be on drying mode and the other one is on regenerating mode. Adsorption time is 12 hours and the regeneration time 12 hours (heating, cooling and standby)
To collect water from the dryer and refresh molecular sieves to be ready to absorb
DP : 34 barG
OP : 20.6-30.9 barG
PID - Gas Dryer (Vendor Package)
No.
Guide
Words
Parameter: Flow
2R.1.1
No
Deviation
No Flow
Drawing No.
Causes / Concerns
Consequences
Safeguards
Initiating
L
Co
Pr
Ri
S (-)
C(3)
S (-)
C(M3)
S (-)
C(3)
S (-)
C(M3)
S (-)
C(3)
S (-)
C(M3)
Comments / Recommendations
Rev:
Action Party
Rec. No.
2R.1.2
2R.1.3
No
No
No Flow
No Flow
F-102 blockage
No regeneration process
causing wet gas going to
compressor
Potential
AIH (dew point alarm) at
overtemperature/overpres downstream of Dryer unit
sure at gas regeneration
system
Back up dryer available
Pump cavitation
Regular Filter mainentance
Overpressurization of
equipment upstream of F102 leading to equipment
damage
CNG-HP-11
Page 10 of 53
No.
2R.2.1
Guide
Words
Less
Deviation
Less Flow
2R.2.
2R.3.1
Less
More
Less Flow
More Flow
2R.4.1
Reverse
Reverse Flow
2R.5.1
Part of
2R.5.
Part of
#N/A
Part of
Parameter: Level
2R.6.1
Less
2R.7.
More
Causes / Concerns
F-102 partially blocked
Consequences
Safeguards
Pump cavitation
Overpressurization of
equipment upstream of F102 leading to equipment
damage
Initiating
L
Co
Pr
Ri
S (-)
C(3)
S (-)
C(M3)
S (-)
C(3)
S (-)
C(M3)
S (4)
C(4)
S (M4)
C(M4)
S (4)
C(4)
S (M4)
C(M4)
S (-)
C(3)
S (-)
C(M3)
S (4)
C(4)
S (M4)
C(M4)
Comments / Recommendations
Action Party
Rec. No.
CNG-HP-12
Parameter: Pressure
2R.8.1
Less
2R.8.2
Less
Less Pressure
Loss of containment/leak on
Release of hydrocarbon
regeneration system due to corrosion leading to environmental
damage and potential fire
Less Pressure
F & G system
Page 11 of 53
No.
2R.8.3
Guide
Words
Less
Deviation
Less Pressure
Causes / Concerns
Regeneration pump loss of power
due to mechanical problem
2R.9.1
More
More Pressure
See Now Flow 2R.1.3
Parameter: Temperature
2R.10.1 Less
Less Temperature Electric heater stop due to
mechanical failure
2R.11.1
More
Parameter: Contamination
2R.12.1 As Well
Contamination
As
Parameter: Composition
2R.13.1 Other
Composition
Than
Parameter: Relief
2R.16.1 Other
Than
Relief
Occupational
Safety
2R.20.1
Other
Than
Parameter: Drawing
2R.21.1 Other
Than
Maintenance
Drawing
Safeguards
AIH (dew point alarm) at
downstream of Dryer unit
Parameter: Instrumentation
2R.15.1 Other
Instrumentation
Than
Parameter: Safety
2R.17.1 Other
Than
Consequences
Page 12 of 53
Initiating
L
Co
Pr
Ri
S (-)
C(3)
S (-)
C(M3)
S (-)
C(3)
S (-)
C(M3)
S (-)
C(3)
S (-)
C(M3)
S (4)
C(4)
S (M4)
C(M4)
Comments / Recommendations
Action Party
Rec. No.
Node
3
Review date 17-Jun-13
Abbreviations
Client
Project
Facility
Section
Comment
Design
Intent
Nine (9) compressor online and One (1) stand by; reciprocating type compressor, three-stages
To compress natural gas and transfer to the storage cylinder
SOP
IM
PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C
Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk
Design
Shut Off Pressure :
Conditions:
Opt.
Conditions
Drawing
No.
Guide
Words
Parameter: Flow
3.1.1
No
Deviation
No Flow
Flowrate : 20 MMSCFD
Power : TBA KW (each compressor)
Causes / Concerns
Drawing No.
Consequences
Safeguards
Potential
overpressurization of
upstream equipment and
piping leading to loss of
integrity and fire event
TS78-P-PID-004
Comments / Recommendations
Rev:
Action Party
Rec. No.
Page 13 of 53
HAZOP Node N3
No.
3.2.1
Guide
Words
Less
Deviation
Less Flow
Causes / Concerns
Consequences
Safeguards
Potential
overpressurization of
upstream equipment and
piping leading to loss of
integrity and fire event
Comments / Recommendations
Action Party
Rec. No.
Page 14 of 53
HAZOP Node N3
Node
Abbreviations
Comment
Design
Intent
IM
PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C
CNG Storage cylinder consist of 95 compartments. 5 compartments will be arranged in 1 bank (each has 40 tubes).
Operation : 19-20 hours storage time, 4-5 hours decanting time
Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk
No.
Guide
Words
Parameter: Flow
4.1.1
No
4.2.1
SOP
Design
CNG Cooler : DP (shell) : 7 barG; (tube) : 263 barG
Conditions: CNG Compartment : DP : 374 barG
Opt.
CNG Cooler : Storage Period (Inlet /Outlet Shell side) : OP : 3 barG
Conditions CNG Cooler : Storage Period (Inlet /Outlet tube side) : OP : 249
barG
Drawing
Less
Deviation
Causes / Concerns
No Flow
Less Flow
CNG Cooler : Storage Period (Inlet /Outlet Shell side) 2.38 m3 each cylinder
: OT : 30 deg C/ 39 deg C
CNG Cooler : Storage Period (Inlet /Outlet tube side)
: OT : 48 deg C/35 deg C
Drawing No.
TS78-P-PID-005 Sheet 1 of 2
Consequences
Page 15 of 53
Safeguards
Comments / Recommendations
Rev:
Action Party
Rec. No.
HAZOP Node N4
No.
4.2.2
Guide
Words
Less
Deviation
Less Flow
Causes / Concerns
One of running compressor fails to
operate
Consequences
Less of CNG production
Safeguards
Indicator of online
compressor in control
room
Comments / Recommendations
Review sizing of manual valve
incoming CNG compartment to
be available at market or provide
spare manual valve in the case of
maintenance required
Action Party
Rec. No.
CNG-HP-14
Standby compressor
available
Indication of pressure
and flow of storage
period by graph to
shown loss of production
4.3.1
More
More Flow
4.4.1
Reverse
Reverse Flow
4.5.1
Part of
Parameter: Level
4.6.1
Less
4.7.1
More
Parameter: Pressure
4.8.1
Less
4.9.1
More
4.9.2
More
Less Level
More Level
Not relevant
Not relevant
Less Pressure
More Pressure
More Pressure
Page 16 of 53
HAZOP Node N4
No.
Guide
Words
Deviation
Causes / Concerns
Consequences
More
More
Temperature
Parameter: Contamination
4.12.1
As Well
Contamination
As
Parameter: Composition
4.13.1
Other
Composition
Than
Parameter: Corrosion / Erosion
4.14.1
Other
Corrosion /
Than
Erosion
Parameter: Instrumentation
4.15.1
Other
Instrumentation
Than
Parameter: Relief
4.16.1
Other
Than
Relief
Comments / Recommendations
Action Party
Rec. No.
Maximum discharge
pressure of Compressor
255 barG is less than
MAWP Tube storage
design 373 barG
Parameter: Temperature
4.10.1
Less
Less Temperature No additional significant issues of
concerns identified
4.11.1
Safeguards
CNG-HP-15
CNG-HP-16
Gas contamination to
cooling water system
leading to gas release at
cooling tower
Gas trapped at shell side
resulting in eficient heat
transfer
Explosion-proof motor of
cooling tower
TIH-0503/TIH 0508/TIH
0509 alarm will alert
operator
Nitrogen back up is
provided to open KV0501 to deliver gas from
CNG compartement to
tambak lorok
Page 17 of 53
HAZOP Node N4
No.
Guide
Words
Parameter: Safety
4.17.1
Other
Than
Deviation
Occupational
Safety
Causes / Concerns
Other
Than
Parameter: Drawing
4.21.1
Other
Than
Maintenance
Drawing
Safeguards
Comments / Recommendations
Action Party
Rec. No.
4.20.1
Consequences
Page 18 of 53
HAZOP Node N4
Node
5
Review date 17-Jun-13
Abbreviations
SOP
IM
PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C
Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk
Client
Project
Facility
Section
Comment
Design
Intent
E-200 and M-200A/B will be operated during decanting time only. Decanting Time 4-5 hours.
To avoid condensation on the upstream of pressure reducing valve and to measure natural gas outlet from CNG Plant
Design
CNG Heat Exchanger : DP (shell) : 5.5 barG; (tube) : 34 barG
Conditions: M-200A/B : DP : 34 barG
Opt.
Conditions
Drawing
TS78-P-PID-005 Sheet 2 of 2
TS78-P-PID-006
No.
Guide
Words
Parameter: Flow
5.1.1
No
Deviation
No Flow
Causes / Concerns
Consequences
Safeguards
Comments / Recommendations
Rev:
B
B
Action Party
Rec. No.
Page 19 of 53
HAZOP Node N5
No.
Guide
Words
Deviation
Causes / Concerns
Consequences
Safeguards
Comments / Recommendations
Action Party
Rec. No.
FT-0601A/B at M-200A/B
displayed at control room
FILL 0601 A/Bset at 5
MMSCFD for alarm to alert
operator
5.1.2
No
No Flow
5.2.1
Less
Less Flow
5.3.1
More
More Flow
5.4.2
Reverse
Reverse Flow
5.5.1
Part of
5.5.2
Part of
Parameter: Level
5.6.1
Less
Less Level
Potential
PIH 0509 set at 31 psig to
overpressurization of CNG alert operator
HE E-200 and downstream
piping
PSHH 0509 set at 33 barG to
close KV 0501A
Double counting of sales
Install additional check valve at
gas from Gundih meter
line PG-2"-3C-027
with M-100
Loss of gas to vent
BDV position indicator and
alarm in control room
Loss of gas back to system
instead to customer
CNG-HP-17
CNG-HP-18
Page 20 of 53
HAZOP Node N5
No.
5.7.1
Guide
Words
More
Parameter: Pressure
5.8.1
Less
5.9.1
5.9.
More
More
Deviation
Causes / Concerns
More Level
Less Pressure
Loss of containment/leak on
Decanting Line
More Pressure
More Pressure
Consequences
Release of hydrocarbon
leading to environmental
damage and potential fire
Safeguards
Comments / Recommendations
Action Party
Rec. No.
F&G
NA
CNG-HP-19
Parameter: Temperature
5.10.1
Less
Less Temperature No additional significant issues of
concerns identified
5.11.1
More
Parameter: Contamination
5.12.1
As Well
Contamination
As
Parameter: Composition
5.13.1
Other
Composition
Than
Parameter: Instrumentation
5.15.1
Other
Instrumentation
Than
Parameter: Relief
5.16.1
Other
Than
Relief
Occupational
Safety
Parameter: Safety
5.17.1
Other
Than
Page 21 of 53
HAZOP Node N5
No.
5.18.1
Guide
Words
Other
Than
Deviation
External Factors
Other
Than
Parameter: Drawing
5.21.1
Other
Than
Causes / Concerns
Safeguards
Comments / Recommendations
Action Party
Rec. No.
Maintenance
Drawing
Consequences
Page 22 of 53
HAZOP Node N5
Node
6
Review date 17-Jun-13
Abbreviations
Client
Project
Facility
Section
Comment
Design
Intent
To heat compressed gas from storage facility to be ready for sales gas
Design
E-500 DP : 2 barG
Conditions: T-200 DP : 0.17 barG
Source Pressure : atm; Discharge Pump : 3.35 barG
Drawing
Guide
Words
Parameter: Flow
6.1.1
No
6.1.2
No
Deviation
No Flow
No Flow
SOP
IM
PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C
Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk
Opt.
Conditions
No.
T-200 : 290 m3
P-300 : 140 m3/hr
E-500 : 127 kW
Power : 36.8 kW
TS78-P-PID-007
TS78-P-PID-005 sheet 2 of 2
Drawing No.
Causes / Concerns
Consequences
Safeguards
Page 23 of 53
Iniating L
Rev:
Comments / Recommendations
S (-)
C(2)
S (-)
C(L2)
CNG-HP-20
CNG-HP-21
S (-)
C(2)
Action Party
B
B
Rec. No.
S (-)
C(L2)
HAZOP Node N6
No.
Guide
Words
Deviation
Causes / Concerns
Consequences
High temperature in the
circulation water around
the waste heat recovery
unit
6.2.1
Less
Less Flow
Potential
overpressurization of
upstream piping
Three way valve TV-0502 to E-200 is Loss of hot water supply
inadvertenly close
leading to inefficient heat
transfer and lower gas
sales temperature
High temperature in the
circulation water around
the waste heat recovery
unit
Safeguards
Iniating L
Comments / Recommendations
S (-)
C(2)
S (-)
C(L2)
S (-)
C(2)
S (-)
C(L2)
S (-)
C(2)
S (-)
C(L2)
S (-)
C(2)
S (-)
C(L2)
S (-)
C(2)
S (-)
C(L2)
Action Party
Rec. No.
CNG-HP-22
More
More Flow
6.4.1
Reverse
Reverse Flow
6.5.1
Part of
Parameter: Level
6.6.1
Less
6.6.2
Less
6.7.1
More
Less Level
Less Level
More Level
Page 24 of 53
HAZOP Node N6
No.
Guide
Deviation
Causes / Concerns
Words
Parameter: Pressure
6.8.1
Less
Less Pressure
refer to No Flow 6.1.1
6.9.1
More
More Pressure
Refer to No Flow
Parameter: Temperature
6.10.1
Less
Less Temperature Leak at hot water system at
discharge P-300A/B
6.10.2
Less
6.10.3
Less
6.11.1
More
More
Temperature
Parameter: Contamination
6.12.1
As Well
Contamination
As
Parameter: Composition
6.13.1
Other
Composition
Than
Consequences
Inefficiency in heating
resulting in lower gas
temperature
Safeguards
Iniating L
S (-)
C(2)
S (-)
C(L2)
S (-)
C(2)
S (-)
C(L2)
S (-)
C(2)
S (-)
C(L2)
Comments / Recommendations
Action Party
Rec. No.
d
6.14.1
Other
Than
Corrosion /
Erosion
Parameter: Instrumentation
6.15.1
Other
Instrumentation
Than
Parameter: Relief
6.16.1
Other
Than
Relief
Occupational
Safety
Parameter: Safety
6.17.1
Other
Than
Page 25 of 53
HAZOP Node N6
No.
Guide
Deviation
Words
Parameter: Operation & Maintenance
6.19.1
Other
Operations
Than
6.20.1
Other
Than
Parameter: Drawing
6.21.1
Other
Than
Causes / Concerns
Safeguards
Iniating L
Comments / Recommendations
Action Party
Rec. No.
Maintenance
Drawing
Consequences
Page 26 of 53
HAZOP Node N6
Node
7
Review date 17-Jun-13
Client
Project
Facility
Section
Abbreviations
SOP
IM
PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C
Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk
Comment
Design
Intent
To recover heat from exhaust gas of compressor and heating water for heating media E-100 and E-200
Design
Conditions:
P-500 : 48 m3/hr
Opt.
Conditions
Power : 1283 kW
Drawing
No.
Guide
Words
Parameter: Flow
7.1.1
No
Deviation
No Flow
TS78-P-PID-007
Drawing No.
Causes / Concerns
Consequences
Safeguards
TIC-0703 to close
dampener from
compressor flue gas
Iniating L
S (-)
C(2)
S (-)
C(L2)
Comments / Recommendations
Rev:
Action Party
Rec. No.
TIC-0703 as high
temperature alarm to alert
operator
PSV-0701 as thermal relief
routed to open drain
Pump running status
indication at control room
Page 27 of 53
HAZOP Node N7
No.
7.1.2
Guide
Words
No
Deviation
No Flow
Causes / Concerns
Consequences
Safeguards
TIC-0703 to close
dampener from
compressor flue gas
Iniating L
S (-)
C(2)
S (-)
C(L2)
Less
Less Flow
7.3.1
More
More Flow
7.4.1
Reverse
Reverse Flow
7.5.1
Part of
7.5.2
Part of
Parameter: Level
7.6.1
Less
7.7.1
More
Less Level
More Level
Action Party
Rec. No.
TIC-0703 as high
temperature alarm to alert
operator
PSV-0701 as thermal relief
Potential overpressure of
downstream pump
7.2.1
Comments / Recommendations
S (-)
C(2)
S (-)
C(L2)
S (-)
C(2)
S (-)
C(L2)
S (-)
C(2)
S (-)
C(L2)
CNG-HP-23
TIC-0703 as high
temperature alarm to alert
operator
PSV-0701 as thermal relief
TIC-0703 to close
dampener from
compressor flue gas
TIC-0703 to close
dampener from
compressor flue gas
TIC-0703 as high
temperature alarm to alert
operator
PSV-0701 as thermal relief
TIC-0703 as high
temperature alarm to alert
operator
PSV-0701 as thermal relief
Page 28 of 53
HAZOP Node N7
No.
Guide
Deviation
Causes / Concerns
Words
Parameter: Pressure
Refer to No Flow 6.1.1
7.8.1
Less
Less Pressure
Refer to No Flow
7.9.1
More
More Pressure
Parameter: Temperature
7.10.1
Less
Less Temperature Refer to No Flow
One or more gas engine driver
shutdown
Start up
7.11.1
More
More
Temperature
Parameter: Contamination
7.12.1
As Well As Contamination
Parameter: Instrumentation
7.15.1
Other
Instrumentation
Than
Parameter: Relief
7.16.1
Other
Than
Relief
Occupational
Safety
7.20.1
Other
Than
Maintenance
Safeguards
Iniating L
S (-)
C(2)
S (-)
C(L2)
S (-)
C(2)
Comments / Recommendations
Action Party
Rec. No.
CNG-HP-25
CNG-HP-26
CNG-HP-27
Parameter: Composition
7.13.1
Other
Composition
Than
Parameter: Safety
7.17.1
Other
Than
Consequences
S (-)
C(M6)
Parameter: Drawing
Page 29 of 53
HAZOP Node N7
No.
7.21.1
7.21.2
7.21.3
Guide
Words
Other
Than
Other
Than
Other
Than
Deviation
Causes / Concerns
Consequences
Safeguards
Iniating L
Comments / Recommendations
Action Party
Rec. No.
Drawing
Drawing
Drawing
Page 30 of 53
CNG-HP-28
HAZOP Node N7
Node
8
Review date 17-Jun-13
Client
Project
Facility
Section
Abbreviations
SOP
IM
PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C
Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk
Comment
Design
Intent
to treat sea water and provide potable water for cooling media
Design
Pressure : 7 barG
Conditions:
Temperature: 65 deg C
Opt.
Conditions
Pressure : 4 barG
Temperature : ambient
Drawing
No.
Guide
Words
Parameter: Flow
8.1.1
No
8.1.2
8.1.3
No
No
Deviation
No Flow
No Flow
No Flow
TS78-P-PID-012
Drawing No.
Causes / Concerns
Consequences
Safeguards
Iniating L
S (-)
C(1)
S (-)
C(L2)
S (-)
C(1)
S (-)
C(L2)
S (-)
C(1)
S (-)
C(L2)
Comments / Recommendations
Rev:
Action Party
Rec. No.
Page 31 of 53
HAZOP Node N8
No.
8.1.4
Guide
Words
No
No Flow
8.1.5
No
No Flow
8.1.6
8.1.7
No
No
Deviation
No Flow
No Flow
Causes / Concerns
S (-)
C(1)
S (-)
C(L2)
S (-)
C(1)
S (-)
C(L1)
S (-)
C(1)
S (-)
C(L2)
S (-)
C(1)
S (-)
C(L2)
Consequences
Safeguards
Iniating L
S (-)
C(1)
S (-)
C(L2)
8.2.1
Less
Less Flow
8.2.2
Less
Less Flow
Potential overpressure of
upstream equipment
S (-)
C(1)
S (-)
C(L2)
8.2.3
Less
Less Flow
RO-A blockage
Potential overpressure of
upstream equipment
S (-)
C(1)
S (-)
C(L2)
8.3.1
More
More Flow
S (-)
C(1)
S (-)
C(L1)
8.4.1
Reverse
Reverse Flow
8.5.1
Part of
8.5.2
Part of
Parameter: Level
8.6.1
Less
8.7.1
More
Parameter: Pressure
8.8.1
Less
Less Level
More Level
Less Pressure
see no flow
Comments / Recommendations
Action Party
Rec. No.
SOP
SOP
Page 32 of 53
HAZOP Node N8
No.
8.9.1
Guide
Words
More
Deviation
More Pressure
Causes / Concerns
Consequences
Safeguards
Iniating L
Comments / Recommendations
Action Party
Rec. No.
Parameter: Temperature
8.10.1
Less
Less Temperature No additional significant issues of
concerns identified
8.11.1
More
More
Temperature
Parameter: Contamination
8.12.1
As Well
Contamination
As
Parameter: Composition
8.13.1
Other
Composition
Than
Parameter: Instrumentation
8.15.1
Other
Instrumentation
Than
Parameter: Relief
8.16.1
Other
Than
Relief
Occupational
Safety
Parameter: Safety
8.17.1
Other
Than
8.20.1
Other
Than
Parameter: Drawing
8.21.1
Other
Than
Maintenance
SOP
Drawing
Page 33 of 53
HAZOP Node N8
Node
9
Review date 17-Jun-13
Client
Project
Facility
Section
Abbreviations
SOP
IM
PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C
Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk
Comment
Design
Intent
Design
Conditions:
Temperature: 65 deg C
Capacity T-100 : 54 m3
Opt.
Conditions
Pressure : ATM
Temperature : 30 - 45 deg C
Drawing
No.
Guide
Words
Parameter: Flow
9.1.1
No
9.1.2
9.1.3
No
No
Deviation
No Flow
No Flow
No Flow
TS78-P-PID-011
Drawing No.
Causes / Concerns
Consequences
Safeguards
Iniating L
S (-)
C(2)
S (-)
C(M4)
S (-)
C(2)
S (-)
C(M4)
S (-)
C(2)
S (-)
C(L2)
Comments / Recommendations
Rev:
Action Party
Rec. No.
CNG-HP-29
Temperature alarm at
WHRU, E-100 and E-200
Page 34 of 53
HAZOP Node N9
No.
9.1.4
Guide
Words
No
Deviation
No Flow
Causes / Concerns
Consequences
Safeguards
Pump maintenance
Temperature alarm at E-100
Iniating L
S (-)
C(2)
S (-)
C(L2)
No
No Flow
9.1.6
No
No Flow
9.1.7
No
9.2.1
S (-)
C(2)
S (-)
C(L2)
Strainer Maintenance
periodically
S (-)
C(2)
S (-)
C(M4)
No Flow
S (-)
C(2)
S (-)
C(L2)
Less
Less Flow
9.3.1
More
More Flow
9.4.1
Reverse
Reverse Flow
9.5.1
Part of
9.5.1
Part of
Less Level
Less Level
S (-)
C(2)
S (-)
C(M4)
Parameter: Level
9.6.1
Less
9.6.2
Less
Potential
overpressurization of
piping at pump discharge
Comments / Recommendations
Action Party
Rec. No.
CNG-HP-30
CNG-HP-31
Page 35 of 53
HAZOP Node N9
No.
Guide
Words
Deviation
Causes / Concerns
Consequences
Safeguards
S (-)
C(2)
S (-)
C(L2)
S (-)
C(2)
S (-)
C(M4)
S (-)
C(2)
S (-)
C(L2)
Comments / Recommendations
Action Party
Rec. No.
9.7.1
More
Parameter: Pressure
9.8.1
Less
More Level
Less Pressure
Iniating L
9.9.1
More
More Pressure
see no flow 9.1.1, 9.1.2,9.1.3
Parameter: Temperature
9.10.1
Less
Less Temperature No additional significant issues of
concerns identified
9.11.1
More
More
Temperature
Parameter: Contamination
9.12.1
As Well As Contamination
Parameter: Instrumentation
9.15.1
Other
Instrumentation
Than
Parameter: Relief
9.16.1
Other
Than
Relief
Occupational
Safety
9.20.1
Other
Than
Maintenance
Parameter: Composition
9.13.1
Other
Composition
Than
Parameter: Safety
9.17.1
Other
Than
Page 36 of 53
HAZOP Node N9
No.
Guide
Words
Parameter: Drawing
9.21.1
Other
Than
Deviation
Causes / Concerns
Consequences
Safeguards
Iniating L
Comments / Recommendations
Action Party
Rec. No.
Drawing
Page 37 of 53
HAZOP Node N9
Node
10
Review date 17-Jun-13
Client
Project
Facility
Section
Abbreviations
SOP
IM
PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C
Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk
Comment
Design
Intent
Design
Conditions:
Temperature: 45 deg C
Opt.
Conditions
Temperature : AMB
Drawing
No.
Guide
Words
Parameter: Flow
10.1.1
No
Deviation
TS78-P-PID-010
Drawing No.
Causes / Concerns
No Flow
Consequences
Safeguards
Iniating L
S (-)
C(1)
S (-)
C(L1)
10.2.1
Less
Less Flow
10.3.1
More
More Flow
S (-)
C(1)
S (-)
C(L1)
10.3.2
More
More Flow
S (-)
C(1)
S (-)
C(L1)
Page 38 of 53
Comments / Recommendations
Rev:
Action Party
Rec. No.
CNG-HP-32
No.
Guide
Words
Deviation
Causes / Concerns
Consequences
Safeguards
Iniating L
Comments / Recommendations
Action Party
Rec. No.
Double-valve provided at
drain line of the individual
equipments
10.4.1
Reverse
Reverse Flow
10.5.1
Part of
Parameter: Level
10.6.1
Less
10.7.1
More
Less Level
S (-)
C(1)
S (-)
C(L1)
More Level
S (-)
C(1)
S (-)
C(L1)
More
More
Less Pressure
More Pressure
More Pressure
Potential
overpressurization of V400
Parameter: Temperature
10.10.1
Less
Less Temperature No additional significant issues of
concerns identified
10.11.1
More
More
Temperature
Parameter: Contamination
10.12.1
As Well As Contamination
Parameter: Composition
10.13.1
Other
Composition
Than
Parameter: Instrumentation
10.15.1
Other
Instrumentation
Than
Page 39 of 53
No.
Guide
Words
Parameter: Relief
10.16.1
Other
Than
Parameter: Safety
10.17.1
Other
Than
Deviation
Causes / Concerns
Relief
Occupational
Safety
10.20.1
Other
Than
Parameter: Drawing
10.21.1
Other
Than
Maintenance
Consequences
Safeguards
Iniating L
Comments / Recommendations
Action Party
Rec. No.
Drawing
Page 40 of 53
Node
11
Review date 17-Jun-13
Client
Project
Facility
Section
Abbreviations
SOP
IM
PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C
Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk
Comment
Design
Intent
Design
Conditions:
Temperature: 45 deg C
Opt.
Conditions
Drawing
Pressure : 10 barG
Temperature : 21 deg C
No.
Guide
Words
Parameter: Flow
11.1.1
No
Deviation
Capacity : 1.5 m3
TS78-P-PID-009
Drawing No.
Causes / Concerns
Consequences
Safeguards
Iniating L
No Flow
S (-)
C(4)
S (-)
C(M4)
S (-)
C(4)
S (-)
C(M4)
S (-)
C(2)
S (-)
C(L2)
S (-)
C(1)
S (-)
C(L1)
11.1.2
No
No Flow
11.2.1
Less
Less Flow
11.3.1
More
More Flow
11.4.1
Reverse
Reverse Flow
Potential
overpressurization of
downstream equipment
Page 41 of 53
Comments / Recommendations
Rev:
Action Party
Rec. No.
CNG-HP-33
No.
11.5.1
Guide
Words
Less
Parameter: Level
11.6.1
Less
11.7.1
More
Deviation
Causes / Concerns
Consequences
Safeguards
Iniating L
Comments / Recommendations
Action Party
Rec. No.
More Level
Parameter: Pressure
Refer to No Flow and Less Flow
11.8.1
Less
Less Pressure
Refer to More Flow
11.9.1
More
More Pressure
Parameter: Temperature
11.10.1
Less
Less Temperature No additional significant issues of
concerns identified
11.11.1
More
More
Temperature
Parameter: Contamination
11.12.1
As Well As Contamination
Parameter: Composition
11.13.1
Other
Composition
Than
Parameter: Instrumentation
11.15.1
Other
Instrumentation
Than
Parameter: Relief
11.16.1
Other
Than
Relief
Occupational
Safety
Parameter: Safety
11.17.1
Other
Than
11.20.1
Other
Than
Parameter: Drawing
11.21.1
Other
Than
Maintenance
Drawing
Page 42 of 53
Node
12
Review date 17-Jun-13
Client
Project
Facility
Section
Abbreviations
SOP
IM
PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C
Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk
Comment
Design
Intent
Design
Pressure : 12 barG
Conditions:
Opt.
Conditions
Pressure : 6 - 10 barG
Drawing
No.
Guide
Words
Parameter: Flow
12.1.1
No
Deviation
No Flow
Temperature: 45 deg C
Power: 30 kW (each)
Causes / Concerns
Consequences
No
No Flow
Safeguards
Potential
overpressurization of
upstream piping
12.1.2
TS78-P-PID-008 Sheet 1 of 2
TS78-P-PID-008 Sheet 2 of 2
Drawing No.
Iniating L
S (-)
C(2)
S (-)
C(L2)
Page 43 of 53
Comments / Recommendations
Rev:
Action Party
B
B
Rec. No.
CNG-HP-34
S (-)
C(L2)
No.
12.1.3
12.1.4
12.1.5
12.1.6
Guide
Words
No
No
No
No
12.1.7
12.2.1
Deviation
No Flow
No Flow
No Flow
No Flow
No Flow
Less
Less Flow
Causes / Concerns
Consequences
Safeguards
PSV 0801 set at 12 barG
release air to atmosphere
Potential
overpressurization of
upstream piping
Loss of instrument air
supply potentially leading
to PSD
Potential
overpressurization of
upstream piping
Loss of instrument air
supply potentially leading
to PSD
Potential
overpressurization of
upstream piping
Loss of instrument air
supply potentially leading
to PSD
S (-)
C(2)
S (-)
C(L2)
S (-)
C(2)
S (-)
C(L2)
S (-)
C(2)
S (-)
C(L2)
S (-)
C(2)
S (-)
C(L2)
Comments / Recommendations
Action Party
Rec. No.
Potential
overpressurization of
upstream piping
Any manual valve downstream Air Loss of instrument air
Dryer after filter F301A/B
supply potentially leading
inadvertently closed
to PSD
Iniating L
Page 44 of 53
CNG-HP-35
No.
Deviation
12.2.2
Guide
Words
Less
Causes / Concerns
Less Flow
12.2.3
Less
Less Flow
12.3.1
More
More Flow
12.4.1
Reverse
Reverse Flow
12.5.1
Part of
Consequences
Safeguards
S (-)
C(2)
S (-)
C(L2)
S (-)
C(2)
S (-)
C(L2)
S (-)
C(2)
S (-)
C(L2)
S (-)
C(2)
S (-)
C(L2)
Iniating L
Comments / Recommendations
Action Party
Rec. No.
More
Parameter: Pressure
12.8.1
Less
12.9.1
More
Less Level
More Level
Less Pressure
More Pressure
see no flow
Parameter: Temperature
12.10.1 Less
Less Temperature No additional significant issues of
concerns identified
12.11.1
More
More
Temperature
Parameter: Contamination
Page 45 of 53
No.
12.12.1
Guide
Words
As Well
As
Deviation
Contamination
Causes / Concerns
Parameter: Instrumentation
12.15.1 Other
Instrumentation
Than
Parameter: Relief
12.16.1 Other
Than
Relief
Occupational
Safety
12.20.1
Other
Than
Parameter: Drawing
12.21.1 Other
Than
12.21.2
Other
Than
Maintenance
Drawing
Drawing
Safeguards
Iniating L
Comments / Recommendations
Action Party
Rec. No.
Parameter: Composition
12.13.1 Other
Composition
Than
Parameter: Safety
12.17.1 Other
Than
Consequences
Page 46 of 53
Node
13
Review date 17-Jun-13
Abbreviations
Client
Project
Facility
Section
Comment
Design
Intent
to provide cooling system and extinguish fire from the process plant and building
Design
Conditions:
Pressure : ATM
Temperature: 45 deg C
Opt.
Conditions
Pressure : ATM
Temperature : ambient
Drawing
No.
Guide
Words
Parameter: Flow
13.1.1
No
Deviation
Causes / Concerns
13.1.2
No
No Flow
13.2.1
Less
Less Flow
13.3.1
More
More Flow
13.4.1
Reverse
Reverse Flow
13.5.1
Part of
Parameter: Level
13.6.1
Less
Less Level
SOP
IM
PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C
Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk
Drawing No.
TS78-P-PID-013
Consequences
No Flow
Safeguards
SOP
SOP
Iniating L
S (3)
C(3)
S (M3)
C(M3)
S (3)
C(3)
S (M3)
C(M3)
S (3)
C(3)
S (M3)
C(M3)
Comments / Recommendations
Rev:
Action Party
Rec. No.
Page 47 of 53
No.
13.7.1
Guide
Words
More
Parameter: Pressure
13.8.1
Less
13.9.1
More
Deviation
Causes / Concerns
More Level
Less Pressure
More Pressure
Consequences
Safeguards
Iniating L
Comments / Recommendations
Action Party
Rec. No.
Parameter: Temperature
13.10.1
Less
Less Temperature No additional significant issues of
concerns identified
13.11.1
More
More
Temperature
Parameter: Contamination
13.12.1
As Well As Contamination
Parameter: Composition
13.13.1
Other
Composition
Than
Parameter: Instrumentation
13.15.1
Other
Instrumentation
Than
Parameter: Relief
13.16.1
Other
Than
Relief
Occupational
Safety
Parameter: Safety
13.17.1
Other
Than
Other
Than
Operations
13.20.1
Other
Than
Maintenance
Parameter: Drawing
13.21.1
Other
Than
CNG-HP-36
CNG-HP-37
Drawing
Page 48 of 53
Node
14
Review date 17-Jun-13
Abbreviations
Client
Project
Facility
Section
Comment
Design
Intent
Design
Conditions:
Opt.
Pressure :
Temperature:
Pressure :
Temperature :
Conditions
Drawing
No.
Guide
Words
Parameter: Flow
14.1.1
No
Deviation
No Flow
SOP
IM
PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C
Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk
Capacity : 600 kW
TS78-P-PID-014
Drawing No.
Causes / Concerns
Consequences
Safeguards
No power generated
Standby Generator
leading to plant shutdown provided
Iniating L
S (-)
C(3)
S (-)
C(M3)
Comments / Recommendations
Rev:
Action Party
Rec. No.
14.2.1
Less
Less Flow
14.3.1
More
More Flow
14.4.1
Reverse
Reverse Flow
14.5.1
Part of
14.6.1
Less
Less Level
Page 49 of 53
No.
14.7.1
Guide
Words
More
Deviation
More Level
Causes / Concerns
Consequences
Safeguards
Iniating L
Comments / Recommendations
S (-)
C(3)
S (-)
C(M3)
Action Party
Rec. No.
Parameter: Pressure
see less flow
14.8.1
Less
Less Pressure
see more flow
14.9.1
More
More Pressure
Parameter: Temperature
14.10.1
Less
Less Temperature No additional significant issues of
concerns identified
14.11.1
More
More
Temperature
CNG-HP-38
CNG-HP-39
downstream GE-100A
Parameter: Contamination
14.12.1
As Well As Contamination
Parameter: Composition
14.13.1
Other
Composition
Than
Parameter: Instrumentation
14.15.1
Other
Instrumentation
Than
Parameter: Relief
14.16.1
Other
Than
Relief
Occupational
Safety
Parameter: Safety
14.17.1
Other
Than
14.20.1
Other
Than
Parameter: Drawing
14.21.1
Other
Than
Maintenance
Drawing
Page 50 of 53
Node
15
Review date 17-Jun-13
Abbreviations
Client
Project
Facility
Section
Comment
Design
Intent
To gather release gas from process relief valves and BDV and routing gas to safe area
Design
Conditions:
Temperature: 85 deg C
Opt.
Conditions
Drawing
No.
Guide
Words
Parameter: Flow
15.1.1
No
Deviation
SOP
IM
PM
USD
PSD
ESD
H,M,L
Co
Pr
Ri
S
C
Preventative Maintenance
Unit Shutdown
Process Shutdown
Emergency Shutdown
High, Medium, Risk
Consequence
Probability
Risk
Safety Risk
Commercial Risk
TS78-P-PID-015
Drawing No.
Causes / Concerns
No Flow
Consequences
Safeguards
Iniating L
15.2.1
Less
Less Flow
15.3.1
More
More Flow
S (4)
C(4)
S (M4)
C(M4)
15.4.1
Reverse
Reverse Flow
Potential fire/explosion
inside piping
S (4)
C(4)
S (M4)
C(M4)
15.5.1
Part of
Page 51 of 53
Comments / Recommendations
Rev:
Action Party
Rec. No.
No.
Guide
Words
Parameter: Level
15.6.1
Less
15.7.1
More
Parameter: Pressure
15.8.1
Less
15.9.1
More
Deviation
Causes / Concerns
Less Level
More Level
Less Pressure
More Pressure
Consequences
release of hydrocarbon
liquid to environment
Safeguards
Iniating L
S (-)
C(2)
S (-)
C(L2)
S (4)
C(3)
S (M4)
C(M3)
Comments / Recommendations
Action Party
Rec. No.
Parameter: Temperature
15.10.1
Less
Less Temperature No additional significant issues of
concerns identified
15.11.1
More
More
Temperature
Parameter: Contamination
15.12.1
As Well As Contamination
Parameter: Composition
15.13.1
Other
Composition
Than
Parameter: Instrumentation
15.15.1
Other
Instrumentation
Than
Parameter: Relief
15.16.1
Other
Than
Parameter: Safety
15.17.1
Other
Than
Relief
Occupational
Safety
15.20.1
Other
Than
Maintenance
CNG-HP-40
Parameter: Drawing
Page 52 of 53
No.
15.21.1
15.21.2
Guide
Words
Other
Than
Other
Than
Deviation
Causes / Concerns
Consequences
Safeguards
Iniating L
Comments / Recommendations
Action Party
Rec. No.
Drawing
Drawing
Page 53 of 53
Appendix C
Node
Review
date
Client
Project
Area
Comment
Drawing
No.
Abbreviations
1
17-Jun-13
PT. ENVIROMATE TECHNOLOGY INTERNATIONAL
COMPRESSED NATURAL GAS PLANT
TAMBAK LOROK
The plan is located beside Indonesia Power Company. The
North side is sea side. The South side is Turbine Generator
belong by IP.
General Lay Out CNG Plant
P
Ri
Rec
S
C
H,M,L
Drawing No.
Hazard Description
Consequences
Prevention
4.1.1
Category/
Guideword
Natural Events
Earthquake
Potential of loss of
plant integrity
leading to damage
and hydrocarbon
release
4.1.2
Natural Events
Potential damage to
process equipment
4.1.3
Natural Events
Lightning
Possible damage to
the equipment and
potential fire
Control
Probabitliy
Risk
Recommendation
Safety Risk
Commercial Risk
High, Medium, Low
TS78-L-LY-001
Recommendation/
Comment
Plant, equipment,
building and
foundation design
anticipated to
accommodate
earthquake factor
(0.15G), referring to
UBC-1997 and soil
investigation result
Plant is designed NA
above Rob
posistion (80 cm
above average
ground level vs
70 cm average
rob) and in high
position
Grounding provided
for each equipment
Rec Number
CNG-HD- 1
Rev.
B1
Action Party
Co.
S (4)
C(3)
Pr
Ri
S (H16)
C(H12)
Lightning protection at
CNG compartment
area (lightning stack)
in process/utility area
Page 1 of 7
No.
4.1.4
Category/
Guideword
Natural Events
Hazard Description
Consequences
Prevention
Settlement
Possible damage to
the equipment and
potential fire
No major concern
Damage to the
equipment, loss of
production
Control
Recommendation/
Comment
4.1.5
4.2.1
Natural Events
External Events
4.3.1
Transportation
4.3.2
Transportation
4.4.1
Lifting
4.5.1
No additional
significant issues of
concerns identified
4.6.1
Security
Theft/sabotage
Page 2 of 7
Rec Number
CNG-HD- 2
Action Party
Co.
Pr
Ri
S (-)
C(3)
S (-)
C(H9)
S (4)
C(4)
S (H8)
C(H8)
S (4)
C(4)
S (H8)
C(H8)
S (-)
C(2)
S (-)
C(M4)
S (4)
C(4)
S (H8)
C(H8)
S (4)
C(4)
S (H8)
C(H8)
No.
Category/
Guideword
Hazard Description
Consequences
4.6.2
Security
Vandalism
No additional
significant issues of
concerns identified
4.6.3
Security
No additional
significant issues of
concerns identified
4.7.1
Noise
4.8.1
Health Hazards
Prevention
Control
Recommendation/
Comment
Health Hazards
Handling molecular
sieve at dryer system
Rec Number
Action Party
Co.
Pr
Ri
S (4)
C(4)
S (H8)
C(H8)
CNG-HD- 3
S (1)
C(-)
S (H3)
C(-)
MSDS provided
in the storage
facility
CNG-HD- 4
S (1)
C(-)
S (H3)
C(-)
S (1)
C(-)
S (H3)
C(-)
S (1)
C(-)
S (H3)
C(-)
S (1)
C(-)
S (M4)
C(-)
PPE - hand
gloves, face
shield
SOP for chemical
handling
4.8.2
JSA
Health Hazards
Page 3 of 7
No.
4.8.3
4.9.1
Category/
Guideword
Health Hazards
Hazard Description
Consequences
Prevention
Control
Hazardous waste
disposal
Personnel injury
during handling
waste disposal
PPE - hand
gloves, face
shield
Maintenance/
construction
Working at high
Fall and slip
location such as
resulting in
lightning pole, WHRU injury/fatality
Maintenance
access provided
at WHRU
Recommendation/
Comment
Alocate waste disposal
resulting from
operation/construction
activity in safe area (third
party)
Rec Number
Action Party
Co.
Pr
Ri
S (1)
C(-)
S (H3)
C(-)
S (4)
C(-)
S (H8)
C(-)
S (4)
C(4)
S (H8)
C(H8)
S (4)
C(-)
S (H8)
C(-)
S (4)
C(-)
S (H8)
C(-)
S (2)
C(-)
S (M4)
C(-)
CNG-HD- 5
Maintenance/
construction
Hot/cold Work
4.9.3
Maintenance/
construction
4.9.5
Maintenance/
construction
Electrical Hazards
4.9.6
Maintenance/
construction
Hot Surfaces at
Potential injury due
exhaust gas, WHRU
to exposure to heat
and heat exchanger (E200)
Page 4 of 7
CNG-HD- 6
No.
4.10.1
Category/
Guideword
Loss of
Containment
Hazard Description
Consequences
Prevention
Control
Recommendation/
Comment
Define philosophy of fire
and gas detection system
and develop fire and gas
detection area at process
plant
Rec Number
Release of
hydrocarbon
resulting in
potential
fire/explosion
leading to
injury/fatality
Unit SD by low
pressure trip
CNG-HD- 8
CNG-HD- 7
Action Party
Co.
Pr
Ri
S (4)
C(4)
S (H8)
C(H8)
4.10.2
Loss of
Containment
Diesel Leak
No additional
significant issues of
concerns identified
4.11.1
Ignition Sources
Battery
Fire/explosion in
the event of
hydrocarbon
release.
Battery room is
located in non
hazardous area
Regularly to check
temperature in the MCC
cabinet and DCS panel to
monitor short circuit and
provide portable fire
extinguisher
CNG-HD- 9
S (4)
C(4)
S (H8)
C(H8)
4.11.2
Ignition Sources
Vent
Fire/explosion in
the event of
hydrocarbon
release in process
area if stroke by
lightning
Lightning protection
provided at CNG
compartment area
CNG-HD- 10
S (4)
C(4)
S (H8)
C(H8)
S (4)
C(4)
S (4)
C(4)
S (H8)
C(H8)
S (H8)
C(H8)
4.11.3
Ignition Sources
Fire/explosion in
the event of
hydrocarbon
release.
Page 5 of 7
No.
4.12.1
Category/
Guideword
Escape/ Refuge
Hazard Description
Consequences
Personnel trap/
ERP
unable to evacuate
leading to
injury/fatality
4.13.1
Emergency
Lighting
Personnel trap in
wrong way
4.14.1
Personnel
injury/fatality
Prevention
Control
Recommendation/
Comment
Provide emergency
evacuation risk analysis to
determine safe evacuation
route and location of
muster area
Rec Number
Co.
Pr
Ri
CNG-HD- 11
S (4)
C(4)
S (H8)
C(H8)
CNG-HD- 12
S (4)
C(4)
S (H8)
C(H8)
S (4)
C(4)
S (4)
C(4)
S (H8)
C(H8)
S (H8)
C(H8)
Emergency
lighting for
evacuation is
provided in
control room and
evacuation route
Fire or explosion
from process area
impact to control
room leading to
potential personnel
injury/fatality
Action Party
CNG-HD- 13
S (4)
C(4)
S (H8)
C(H8)
CNG-HD- 14
S (4)
C(4)
S (H8)
C(H8)
S (4)
C(4)
S (4)
C(4)
S (H8)
C(H8)
S (H8)
C(H8)
Consider to provide
CCTV in the control room
for monitoring purpose
Page 6 of 7
CNG-HD- 15
No.
Hazard Description
Consequences
Prevention
Control
4.15.1
Category/
Guideword
Communication
Inability to contact
control room within
emergency
Each operator
provided with
hand held radio
4.16.1
Shutdown
Inability to initiate
ESD
4.16.2
Shutdown
Loss of power
Inability to
coordinate response
leading to potential
major accident
leading to
personnel
injury/fatality and
asset loss
Inability to control
fire leading to
potential major
accident leading to
personnel
injury/fatality and
asset loss
Plant shutdown
resulting loss of
production
Uncontrolled
process upset
Rec Number
Action Party
Co.
Pr
Ri
S (4)
C(4)
S (H8)
C(H8)
CNG-HD- 17
S (4)
C(4)
S (H8)
C(H8)
UPS is provided
S (-)
C(4)
S (-)
C(H8)
S (-)
C(4)
S (-)
C(H8)
S (-)
C(-)
S (-)
C(-)
S (-)
C(-)
S (-)
C(-)
4.17.1
Other
Plant layout
4.18.1
Discharge to air
4.18.3
Discharge to
water
Blowdown of water
from cooling tower,
discharge RO
Potential
contamination from
process fluid
4.18.4
Discharge to soil
No additional significant
issue of concern
identified
4.18.5
Waste disposal
Recommendation/
Comment
Define internal and
external communication
system (PABX) for
connecting operator in the
control room to outside
parties
CNG-HD- 16
Alternative power
source from PLN for
emergency equipment
-
Discharge water is
connected to existing
canal (IP)
CNG-HD- 18
CNG-HD- 5
Page 7 of 7
Appendix D
Drawings Reviewed
NODE 1
NODE 2
2
NODE
NODE 2R
NODE 3
NODE 4
NODE 6
NODE 5
NODE 5
NODE 7
NODE 6
NODE 12
NODE 12
NODE 11
NODE 10
NODE 9
NODE 8
NODE 13
NODE 14
NODE 15