Professional Documents
Culture Documents
Adrias Tan
MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
2016Changes
Adrias Tan MSc BSc(Hons)
LLB(Hons) FCIArb FSIArb or timing of execution
to sequence
Delayed drawings or
instructions
Right of access
Setting out
Unforeseen physical
conditions
Fossils
Testing
Extension of Time for
Completion
Loss and Expense due to
Variations
2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Suspension of
works
Evaluation and
Measurement
Omissions
Value
Engineering
Interference
with tests on
completion
Changes in
legislation
Employers
Risks
Contracting Strategies
Lump Sum EPC
Reimbursable
Mixed or Hybrid Design/Bid/Build
Procurement, etc
Pursuing Claims
Administration and Management of
Contract
Familiarity with Contract Documents,
Forms of Contract
Familiarity with Contractual procedures
and protocol
Claims Management
Notices and Timelines
Substantiation of Information
Rationale
Contractor notifies Employer, to enable
Employer to avert unintended
consequences
potential disputes resolved early
2016Extension
Adrias Tan MSc BSc(Hons)
FCIArb FSIArb
Engineers Obligations
Engineer has 42 days to Approve or
Disapprove with Detailed Comments
Engineer can propose for the Contractors
approval an extended time period to
respond
Request any necessary further
particulars
Engineer unreasonably delaying a
response to a Claim or requesting
unnecessary further particulars
Clause 3.5: consulting with Contractor, try
to reach an agreement. If not possible to
reach agreement, make a fair
2016determination
Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Engineers Obligations
Engineer Failure to Respond within 42
days
No express sanctions for the Engineers
failure to provide a timely response
Effect is Contractor unduly relieved of his
contractual obligations; Contractor not
kept aware of his contractual rights and
entitlements arising from such valid
claims and notifications
Engineers Obligations
Prevention Principle
Engineers Obligations
Roberts v Bury Improvement
Commissioners
Engineers Obligations
Shawton Engineering Ltd v DGP
International Ltd
Court of Appeal held that what is a
reasonable time has to be judged as at
the time when the question arose, in the
light of all the relevant circumstances:
There were variations, but no
contractual mechanisms for extending
time on account of the variations (or the
mechanisms have failed). The effect in
law of the variations was that the
Contractor became obligated to complete
their work within a reasonable time
2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Engineers Obligations
Shawton Engineering Ltd v DGP
International Ltd
The judge rejected that a reasonable time
should be ascertained by reference to the
Original Contract Periods as extended
only by the agreed periods for variations
The question of what is a reasonable
time within which to complete particular
work is an objective question and is not
dependent upon the actual time which a
person may have agreed to carry out the
work. Parties may have over or under
estimated what time the work would
require.
time which has to be
2016actually
Adrias Tan MSc BSc(Hons)
LLB(Hons) FCIArbThe
FSIArb