Training Overview
www.mass.gov/energy/greencommunities
www.mass.gov/energy/greencommunities
Training Overview
http://www.mass.gov/eea/energy-utilities-cleantech/renewable-energy/solar/sunshot-rooftop-solarchallenge.html
Matt Piantedosi
10
Poll Question
12
Prescriptive Process
Prescriptive Process
http://www.mass.gov/eea/energy-utilities-clean-tech/renewableenergy/solar/sunshot-rooftop-solar-challenge.html
15
Prescriptive Process
18
16
17
7 Steps
11 Questions
Prescriptive Process
14
Prescriptive Process
Capacity of 10 kW.
Flush-mounted solar PV systems.
Range from 3.0 to 3.5 pounds per square foot, comparable
to a second layer of roofing singles.
One- and Two-Family Residences built after 1976
13
11 Questions.
Requires familiarity with structure under consideration.
Requires expertise in construction/ engineering.
1.
2.
3.
4.
5.
19
21
11.
10.
23
22
8.
7.
20
24
Prescriptive Process
Prescriptive Process
25
26
Prescriptive Process
27
28
Prescriptive Process
29
Technical Contacts
http://www.mass.gov/eea/energy-utilities-clean-tech/renewable-energy/solar/solarpermitting-and-structural-review-rsc2.html
Questions??
Feedback/Questions
Emma Krause at emma.krause@state.ma.us
phone: (617) 626-7371
30
32
MA Licensing Requirements
Guidance Memo 13-01
33
34
General Contractors (GCs) may advertise and contract to install solar PV Systems:
GCs must subcontract to licensed electrician.
Advertising to install solar PV is not subject to regulation by the Board.
http://www.mass.gov/ocabr/docs/dpl/boards/el/carroll-decision.pdf
http://www.mass.gov/ocabr/licensee/dpl-boards/el/
35
Example of an installation that may require a rough inspection before the installation of PV modules.
36
41
Poll Question
Solar PV Modules
Racking
Inverter
40
38
39
37
42
Common confusion
PV Violations and Safety Concerns
MassCECs Minimum Technical Requirements
43
44
Instructions to supplement
the Uniform Application
for Permit to Perform
Electrical Work
45
46
Installation Documentation
47
To supplement an onsite
inspection, detailed photos
should be available for all:
48
Article 250
Article 300
Article 690
50
51
Wiring Methods
Article 705
49
52
Array Violations
53
54
55
56
CADMUS
CADMUS
57
58
59
300.4
338.10(B)(4)(b)
334.30
338.12(A)(1)
60
10
CADMUS
61
CADMUS
62
CADMUS
CADMUS
63
64
65
66
11
CADMUS
CADMUS
67
68
Ground-mount arrays
In readily accessible
locations, conductors
shall be guarded or
installed in a raceway
CADMUS
CADMUS
PV conductors in readily accessible locations shall be installed in a raceway.
69
70
CADMUS
PV conductors in readily accessible locations shall be guarded or installed in a raceway.
71
72
CADMUS
12
PV Output Violations
CADMUS
Readily accessible PV conductors properly guarded.
73
74
690.8 calculations
310.15 ampacity/temperature/conduit fill
CADMUS
Undersized PV output conductors.
75
76
CADMUS
CADMUS
CADMUS
Unprotected PV output conductors.
77
78
13
CADMUS
CADMUS
PV output conductors installed in conduit.
79
80
Outdoor enclosures
CADMUS
81
82
CADMUS
Enclosures must be installed so as to prevent moisture from entering or accumulating in accordance with 314.15
CADMUS
83
84
14
DC AFCI Protection
Circuit Voltage
Circuit Current
CADMUS
85
86
DC AFCI Protection
Inverters
Combiner boxes
Micro inverters (not required)
CADMUS
87
88
Intended to protect
first responders
Original proposal:
690.12(1)
Disconnect power
directly under array
Module-level shutdown
Compromise:
Combiner-level
shutdown
Source: UL.com
CADMUS
89
90
CADMUS
15
690.12(2)
Under 30 Volts
240 Volt-Amps (Watts)
A typical module:
Source: UL.com
Within 10 seconds
Considerations:
~250 Watts
~30 Volts
690.12(3)
Measured between:
Any 2 conductors
Any conductor and ground
Source: UL.com
91
92
690.12(4)
690.12(5)
Equipment that performs the rapid shutdown shall be listed and identified.
Equipment that performs the rapid shutdown shall be listed and identified.
This provision shall be enforced as of January 1, 2017. In lieu of a
comprehensive listing prior to this enforcement date, the individual
components shall be listed as to their specific circuit functions, and the
system as installed shall be performance tested in the presence of the
authority having jurisdiction.
http://www.mass.gov/eopss/docs/dfs/osfm/cmr/cmr-secured/527012.pdf
on Red
93
94
Microinverters
AC modules
Exterior string inverters if either:
Dwelling
Commercial
DC-to-DC Optimizers/Converters
CADMUS
95
96
16
Understanding 690.47(C)
DC Grounding Electrode
Conductor (GEC) runs to an
electrode or ground bar:
1. A separate electrode installed
for DC system grounding
2. The electrode that serves for
AC system grounding
3. Main panel ground bar
97
Inverter
Main
Service
Panel
(1)
(3)
(2)
(1 only)
AC/DC bond
98
Article 250.24(A)(5)
Neutral conductor
bonded to frame
CADMUS
99
100
PV Interconnection
CADMUS
101
102
17
Article 705.12
PV
Wind
Cogeneration
etc.
103
104
outside
inside
Fused PV
Disconnect
PV Inverter
Utility
Meter
Main
Service
Panelboard
CADMUS
105
106
2.
3.
6.
107
108
120% of
100A=120A
Main + PV = 118A
120% Busbar = 120A
118A feeds < 120A bus
18
110
Backfeed
3-phase circuits
Nuisance tripping
Helping Massachusetts Municipalities Create A Cleaner Energy Future
QUESTIONS??
109
See 705.12(D)(5)
http://www.mass.gov/eea/energy-utilities-cleantech/renewable-energy/solar/solar-permitting-andstructural-review-rsc2.html
CADMUS
111
112