REVISED DETAIL ESTIMATE FOR PROVISION OF NEW ROAD CUTS AND CLOSING OF EXISTING
OPEN CUTS OVER DRAIN CUM FOOTPATH ALONG RIGHT CARRIAGE WAY OF ROAD FROM
KHAIRA DISTRIBUTORY TO KAHNA (DIVERSION OF CONTINGENCY FOR LEFT CARRIAGE WAY)
Sub Base Course
FOR FOOTPATH
217
Kms)
= Rs. 1,596.40
Carriage charges
Carriage charges for %Cft Material
(Rate with lead upto 10 Km)
Km
10
to
200
190
Km @ 15.98
Per Km.
Rs.407.17
Rs.3,036.20
Km
17
Km @
Per Km.
Rs.55.25
S.Total
Rs.3,498.62
200
to
217
3.25
0.20
(+)
Total
Rs.
699.72
Rs.4,198.34 =
Total
Sub Engineer
Rs.4,198.34
Rs.5,794.74
Executive Engineer
Provincial Highway Sub Division
Lahore.
DESCRIPTION OF ITEM:
Item No. 3 (a)
(ii)
Detail
Amount (Rs.)
MATERIAL
1
Total
Contractor's Profit & Overhe
Total
120 Cft
375.00
% Cft
450.00
450.00
90.00
540.00
20.00 Percent
LABOUR
2
2.00 Nos.
620.00
620.00
62.00
682.00
136.40
818.40
10.00 Percent
20.00 Percent
COMPACTION CHARGES
1
1 Day
238.00
1056.40
ITEM RATES
Labour rate per 100 Cft
Labour rate per Cum
Rs.
Rs.
1056.40
373.12
Say
Say
1056.40
373.10
Rs.
Rs.
1596.40
563.85
Say
Say
1596.40
563.85
Executive Engineer .
Provincial Highway Division
Lahore
.
ANALYSIS OF RATE FOR P/F Precast Paving Blocks (Paving Tiles) 50 mm Thick
Unit = P.Sft.
Take 100 Sft Area for Analysis Purpose.
1
10
10
32.00
(31+33)/2
100
Sft.
P.Sft.
Rs.3,200
Rs.80.00
Rs.226.80
10
=
@
Rs.800.00
10.00
No
P% Nos.
10
10
@ Rs.1,080.00
4
21.00
Cft.
P% Cft.
=
@ Rs.238.00
0.21
2.00
Hours
P.Hour
Rs.476.00
Rs.1,200.00
Rs.5,182.80
10
10
Rs.12.00
100.00 Sft.
P.Sft.
Total
(+)
(+)
G.Total
Rs.5,942.80
100
Rs.120.00
Rs.640.00
Rs.5,942.80
Rs.59.43
Executive Engineer
Provincial Highway Division
Lahore.
10
@ Rs.3,231.35
10
0.25
Cft.
=
2.50
Rs.24.24
Cft.
P% Cft.
Rs.331.95
Rs.936.00
Rs.25.00
10.00
No
Rs.93.60
Each
(78x1.20) - Ex foctory rate
10
=
@
7.5
P%0 Cft.
@ Rs.13,278.00
0.75
Rs.2.50
(10000 / 4000)
10.00
Each
No
10
0.08
(1/12)
@ Rs.16,460.40
1.50
P.%Cft
1.20
Cft.
Rs.197.52
Over
PCC
Bed
Bet
Kerb
stones
10
0.50
0.415
x
(0.5+0.33)/2
1.17
Total
@ Rs.1,108.10
7
5.00
Sft.
=
=
0.49
5.49
Sft.
Sft.
P% Sft.
Rs.60.79
Rs.100.00
Rs.206.46
Rs.1,881.96
10
10
10
No
@ Rs.2,064.60
P% Sft.
(890.70+586.95+586.95)
Total
1881.96
10
1881.955 -
206.46
1675.50
1675.50
10
188.20 P.Rft.
167.55 P.Rft.
Without Paint
Executive Engineer
Provincial Highway Division
Lahore.
20
0.50
0.83
(10/12)
16.67
Cft
20
0.42
x
(0.50+0.33)/2
0.67
(8/12)
11.07
Cft
27.73
Cft
Total
@ Rs.3,368.65 P %Cft.
2
Rs.934
Dismantling of R.C.C.
Slab
20
0.50
(6/12)
50.00
Cft
Walls
20
0.66
1.42
(17/12)
37.40
Cft
87.40
Cft
Total
@ Rs.5,512.30 P %Cft.
3
Slab.
R.C.C 1:2:4.
1
20
x
@
4
Steel
Rs.4,818
0.75
75.00
Cft
Rs.18,634
8.02 Lbs
=
P. Cft
601.50
601.50
0.4536
Lbs.
=
272.84 Kg.
Rs.25,255
Total
Rs.49,641
700.95
Rs.30
0.4536
317.95 Kg.
P.Kg.
Balance
Rs.40,102
20
(-)
Rs.9,539
Rs.40,102
= 2005.11 P.Rft.
Executive Engineer
Redecking and Widening of 3' Span 32'-40' road way
Analysis of Rate for Closing of Existing Opening over Walk Way Drain
Unit
=
Each
Take 20 Rft length for analysis purpose
1
20
=
@
Rft.
Rs.182.19 P.Rft.
Rs.3,644
20
=
@
20.00
20.00
Rft.
Rs.167.55 P.Rft.
Rs.3,351
20
0.67
(8/12)
66.67
Cft
@ Rs.1,207.60 P %Cft.
4
Rs.805
20
0.33
(4/12)
33.33
Cft
@ Rs.5,794.74 P %Cft.
5
Rs.1,932
20
=
@
Rs.59.43
100.00 Sft.
P.Sft.
Rs.5,943
Total
Rate per Rft
Rs.15,674
20
Rs.15,674
783.71 P.Rft.
Executive Engineer
Provincial Highway Division
Lahore
Lahore
REVISED DETAIL ESTIMATE FOR PROVISION OF NEW ROAD CUTS AND CLOSING OF
EXISTING OPEN CUTS OVER DRAIN CUM FOOTPATH ALONG RIGHT CARRIAGE WAY OF ROAD
FROM KHAIRA DISTRIBUTORY TO KAHNA (DIVERSION OF CONTINGENCY FOR LEFT
CARRIAGE WAY)
1
40
320.00 Rft.
Total
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
=
40.00
50.00
42.00
49.00
55.00
28.00
35.00
23.00
32.00
29.00
26.00
51.00
53.00
30.00
31.00
18.00
17.00
49.00
51.00
34.00
37.00
52.00
22.00
19.00
31.00
51.00
35.00
31.00
36.00
1057.00
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
Rft.
48.00
Cft
No.
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
Length
40.00
50.00
42.00
49.00
55.00
28.00
35.00
23.00
32.00
29.00
26.00
51.00
53.00
30.00
31.00
18.00
17.00
49.00
51.00
34.00
37.00
52.00
22.00
19.00
31.00
51.00
35.00
31.00
36.00
Executive Engineer
Page 10
Page 11
COMPARATIVE STATEMENT
REVISED DETIAL ESTIMATE FOR PROVISION OF NEW ROAD CUTS AND CLOSING OF EXISTING OPEN CUTS OVER DRAIN C
FOOTPATH ALONG RIGHT CARRIAGE WAY OF ROAD FROM KHAIRA DISTRIBUTORY TO KAHNA (DIVERSION OF CONTINGE
FOR LEFT CARRIAGE WAY)
As Per T.S Estimate
S.No
Qty
Unit
Rate
Amount
Qty
Rate
Amount
Different
Qty
(3-11)
Description of item,
Different Amount
Excess
(13-6)
Saving
(13-6)
11
12
13
14
15
16
320
P.Rft.
1607.45
514384
320
2005.11
641635
127251
127251
1318
P.Rft.
778.30
1025799
1137
778.30
884927
-181
3950
1544134
1544134
24
16460.40
3950
1530513
1530513
2
3
24
%Cft.
16460.40
Sub Total:-
(-)
Total:-
16000
(-)
-140872
0
127251
127251
-13621
-13621
16000
1528134
1514513
127251
-13621
1.528
1.515
0.127
-0.014
99%
Sub Engineer
MPARATIVE STATEMENT
ROAD CUTS AND CLOSING OF EXISTING OPEN CUTS OVER DRAIN CUM
ROM KHAIRA DISTRIBUTORY TO KAHNA (DIVERSION OF CONTINGENCY
LEFT CARRIAGE WAY)
Remarks
17
Due
to
Requirment
Below
Side
ABSTRACT
REVISED DETAIL ESTIMATE FOR PROVISION OF NEW ROAD CUTS AND CLOSING OF
EXISTING OPEN CUTS OVER DRAIN CUM FOOTPATH ALONG RIGHT CARRIAGE WAY OF
ROAD FROM KHAIRA DISTRIBUTORY TO KAHNA (DIVERSION OF CONTINGENCY FOR LEFT
CARRIAGE WAY)
Sr. No.
DESCRIPTION OF ITEM
Qty
Unit
Rate
Amount
(Rs.)
320
P.Rft.
2005.11
641635
1,137
P.Rft.
778.30
884927
24
%Cft.
16460.40
3950
Total
Cradit of Old Kerb Stone 2x160=320 No. (One Rft each) @ 50 P.Rft
1530512
(-)
16000
G.Total:-
1514512
Amount in Million
1.515
Sub Engineer
Sub Divisional Officer
Provincial Highway Sub Division
Executive Engineer
Provincial Highway Division
Lahore.
Lahore
AMOUNT
Rs.1.515 MILLION
EXECUTIVE ENGINEER
PROVINCIAL HIGHWAY DIVISION
LAHORE
PROVINCE
PUNJAB
STATION
LAHORE
DIVISION
NAME OF WORK
MAJOR HEAD
AMOUNT
---
RS.
1.515
MILLION
REVISED DETAIL ESTIMATE FOR PROVISION OF NEW ROAD CUTS AND CLOSING
OF EXISTING OPEN CUTS OVER DRAIN CUM FOOTPATH ALONG RIGHT CARRIAGE
WAY OF ROAD FROM KHAIRA DISTRIBUTORY TO KAHNA (DIVERSION OF
CONTINGENCY FOR LEFT CARRIAGE WAY)
History
RATES
The rates provided in the estimate are based on rates as notified by the Finance Department
on web site 2nd Quarter 2011 Rates.
EXECUTION
Work will be alloted to the approved contractors of C&W Department after calling
competitive tenders.
COST
Total cost of this estimate comes to
Rs.1.515
Million.
TIME
It will take 01 Months to complete the work.
Executive Engineer
Provincial Highway Division
Lahore.
Page 18