Professional Documents
Culture Documents
(a) Soil stabilisation is done to improve the strength of soil and improve its load bearing capacity.
This process is appropriate where there are: Poor shear strength soils
Highly permeable soil masses
Highly incompressible soils, and
Poor bear capacity foundation soils
Question 2
Total excavation = 6.2 x4.8 x4.0
= 119.04 m3
119.04
6
= 19.84 m3
= (1.6m3/day)/ (8 hrs/day)
= 0.2m3/hr
19.84
0.2
= 99.2hrs
Total wages
= (99.2x$6.50x6) + (99.2x$20)
= $5852.80
Overhead costs
15
100
x 5852.80
= $877.92
Total costs
= $(5852.80+877.92)
= $6730.72
Profit
12.5
100
= $841.34
x $6730.72
= $841.34 + $6730.72
= $7572.06
Question 3
(a) Advantages of a lump sum contract
Easy future reference, that is, its easier to identify a lump sum contract showing future
potential clients
Contactors selection is easy
Contractor will assign the best personnel
(b) Obligations of a contractor with the regard to wages, conditions to work and accommodation
The contractor is to have included in his offer all his costs for supplying all materials both for the
temporary and permanent works, labour including supervision on site. He or she should provide
transport for labourers to and from the site and within. Fencing and watching lights should be
made available for a secure and safe working environment. Paying of fees, taxes and duties to the
authorities and other things required for the constraction, erection, completion and maintainance
of the work.
All wages for the staff is to be paid on time and as per agreed terms. Benefits and awards are to be
paid in time as well.
Schedule cocontract
Can also be called item rate contract
For a schedule contract, the contractor undertakes the executionof work on an item rate basis.
The amount of money to be received by contractor depends upon th quantities of various items of
works actually executed.