Professional Documents
Culture Documents
Abstract
At Bayswater Colliery various methods of
controlling highwall stabii were investigated.
The use of presplitting was trialled and its
effectiveness measured. The presplit hole spacing
and explosive charge were based on those succes&lly used in other coal mines in the Hunter
Valley. The major presplit design parameter to be
determined was the stand-off distance between
the presplit line and the back row of the production blast. This could not be transfmed directly
from other sites due to the difference between the
Bayswaters production blast geometry and
geology to that of other sites. Using highwall face
surveys and Oricas SUR..YPlus@ software, the
average back-break behind normal production
blasts was determined. This was then used to
select the stand-off distance between the back
row production blastholes to the presplit line.
While presplit designs are normally based on
powder factor (kg/m2), the use of energy factor
(MJ/m2) was also investigated as a possible
design criteria.
Presplit results were evaluated using half
barrel factor measurements and a visual assessment ofback-break. The final presplit design was
successfi.llly implemented to form advancing
highwalls which had halfbarrel factors ranging
from 42% at the ends ofthe blast block to 67% in
the centre.
Due to the high drilling requirements of
presplitting, a method called double stitching was
investigated as a cost effective alternative. This
method involves drilling the back row blastholes
on a spacing which is closer than the normal
production blasthole spacing and reducing the
charge in each hole. Developing the double stitch
design consisted of determining the back row
burden, spacing, powder factor, and the loading
arrangement of air and explosives decks. Again,
results were evaluated visuahy and also by measuring halfbarrel factors. SURVEYPlus@ was
used to assess the amount of damage beyond the
Introduction
Bayswater Colliery operates the Bayswater
No. 3 open cut coal mine situated 6 km south of
Muswellbrook in the Hunter Valley region of
NSW, Australia. It is a multi-seam truck and
shovel operation.
The mine is currently handling 30 million bcm
of overburden per annum to produce 4.8 million
tonne ofROM coal, at an approximate stripping
ratio of 7.5: 1. The finished product is 4.0 million
tonne. Mining is carried out by two P&H 4 100
and one P&H 2800 shovels. Drilling is done by
Driltech D90KS and D75KS machines.
In truck and shovel mining, highwall stabiity
has a significant impact on safety and coal recovery. Various methods of controlling highwall
Figure I
1 of 7
Surveyplus sofhvare sh
view of highwall and back row of
preceding blast
Face Profded
MAO7# 1
MAO7#2
MAO7#3
MAo7##4
MAO8# 1
MAO8#2
MAO8#3
Average
Average backbreak
distance (m)
2.95
2.65
2.32
2.48
2.52
2.48
2.80
2.60
2 of 7
Figure 3
Figure 4
Figure 5
3 of 7
Figure 6
4 of 7
Figure 9
Figure 8
5 of 7
Results of double-stitching
trials
As expected, the HBF for double stitching
was significantly lower than that for presplitting.
HBF values of only 11% to 14 % were achieved
with double stitching compared with values in the
42 to 67% range for presplitting. However, the
HBF is a measure of highwall smoothness rather
than soundness or stability. The lower HBF value
does not necessarily mean that the highwall is
more hazardous.
Despite their lower HBF values, the
highwalls produced by double stitching were
visually acceptable and satisfactory to the mine.
The backbreak behind double stitching was
also evaluated. After blasting a double stitched
strip, the resulting face was surveyed and its
position relative to the back row in the blast was
measured. The average backbreak distance
between the back row blastholes and the resulting
face was found to be 3.1 m. These results are
summa&d in Table 2. This table also shows
results from two u.nm&ed production blasts in
this area of the pit, which produced an average
backbreak of 3.4 m.
The average backbreak was 3.1 m. But
because the HBF was 11 to 14%, backbreak was
zero in the places where halfbarrels were visible.
Therefore, the wall produced by double stitching
was relatively rough. This roughness could lead to
poorer performance in subsequent blasts. The
effect of rough walls needs to be assessed during
the subsequent blasts.
Table 2
Average backbreak
Face Profded
(Double stitched) distance (m)
3.1
MAl6#5ds
3.2
MA16Mds
2.9
MAl6#3ds
Average backbreak
HBF
Cost of Presplitting vs
Double Stitching
A detailed cost analysis was done to compare presplitting and double stitching. The following typical blast at Bayswater was analysed:
Figure 10
Figure II
13%
11%
14%
3.1 m
3.4 m
Copyright 2000 International Society of Explosives Engineers
1999G Volume 2 - Comparison of Highwall Control Methods at Bayswater Colliery - P 130
6 of 7
18
25
8x9m
35m
Double
stitching
18
25
8x9m
35m
3m
8m
6m
4m
4.5 m
Presplitting
Number of rows
Blastholes per row
Burden x spacing
Bench height
Presplit stand-off
to back row
Back row burden
Presplit and double
stitchingspa&lg
Conclusions
Highwall face surveys and Oricas
Surveyplus so&are wereuseti in determining
the average backbreak behind normal production
blasts. This average backbreak then became an
indicator of the stand-off distance for trial presplit
blasts. In these trials, a very high standard of
presplit highwalls was achieved, as evidenced by
HBF values of42 to 67%.
In subsequent trials with double stitched
highwalls, an approximate 2% decrease in the
cost per bcm was achieved when compared to
presplitting. There is no evidence ofthis cost
benefit having been achieved at the cost of safety
However, to increase the HBF (currently 11 to
14%) of double stitched faces and to reduce the
average backbreak, additional work will need to
be done. This would include optimising the
blasthole pattern weight and distribution of
charge, powder factor or energy factor, and delay
timing for the double stitched row.
When compared to a base case (ie. an
unmodified production blastwithout any wall
control techniques), double stitching was margin-
Acknowledgements
The authors extend their thanks to
Bayswater Colliery CO and Orica Explosives for
permission to publish this paper.
The authors would also like to thank Tim
Hagan, GeoffBrent and Nigel Irvine for their
useful inputs.
References
1. Leinberger, P, Chung, S. H. and Nan Lee
1992. Blasting Techniques for PitWall Control
at Into Limiteds Thompson Open Pit. Proc.
18th SEE Conference on Explosives and
Blasting Technique. Orlando, SEE.
2. Brent G F., and Armstrong L. W., 1998. Large
Diameter Presplitting Improved Through Two
Novel Techniques, Proceedings of the Twentyforth Annual Conference on Explosives and
Blasting Technique, New Orleans, Louisiana,
ISEE.
3. Danell,R.E., 1993.PresplittingforFinalWall
Blasting Theory and Calculations, Proceedings
of the 6th Mining, Drilhng and Blasting BHP
Research Seminar. Cairns, BHP
4. Goswami T., 1997, Bulga Blast Audit Report,
Orica Explosives Internal Report, Nov 1997.
7 of 7