You are on page 1of 52

COBie-UK-2012

   


V11
NicholasNisbet
10thJuly2012

UK COBie 2.4 Requirements

2012 AEC3 UK Ltd

July 2012

UK COBie 2.4 Requirements

COBie UK
Required Information for Facility Operation
This document is the potential draft of a new BSI PAS, and should be read in conjunction with the
published examples and templates.
Illustrations are acknowledged from USACE ERDC and AEC3 unless otherwise stated.

Date

Version

Author

2012-02-17

V08

First issue for consultation

nn@aec3.com

2012-02-21

V09

Improved formatting.

nn@aec3.com

Gate process diagram added.


Impact requirements aggregated
Structure used as infrastructure synonym for
building Fabric
2012-03-23

V10

Improved description of sheet, column and row


requirements .

nn@aec3.com

Recommended additional Attributes appended


2012-06-10

V11

COBie drop examples included

nn@aec3.com

COBie Type templates referenced

2012 AEC3 UK Ltd

July 2012

UK COBie 2.4 Requirements

Contents
Required Information for Facility Ownership ........................................................................................... 1
0 Overview .................................................................................................................................................... 6
0.1 The Owners View.................................................................................................................................... 6
0.2 The Designers and Contractors View ...................................................................................................... 6
0.3 Product Specifiers and Suppliers ............................................................................................................. 6
1 Scope .......................................................................................................................................................... 6
1.1 Objective ............................................................................................................................................. 7
1.2 Audience ............................................................................................................................................. 7
1.3 Applicability ........................................................................................................................................ 7
1.4 Organization ........................................................................................................................................ 7
1.5 IFC and COBie ..................................................................................................................................... 8
1.6 Background ......................................................................................................................................... 8
1.7 Process ................................................................................................................................................ 8
1.8 COBie for infrastructure and building ................................................................................................. 9
1.9 COBie for existing facilities and refurbishment .................................................................................. 9
1.10 Use of COBie information ................................................................................................................ 9
1.11 COBie Contacts ................................................................................................................................. 9
1.11 COBie Objects................................................................................................................................... 9
1.12 COBie additional information ......................................................................................................... 11
2 Referenced Standards ............................................................................................................................... 12
3 Definitions ................................................................................................................................................ 13
3.1 Requirements ................................................................................................................................. 13
3.2 Manageable assets........................................................................................................................ 13
3.3 Purposes ......................................................................................................................................... 13
3.4 Gates / Stages ................................................................................................................................ 13
3.5 Metrics ............................................................................................................................................. 13
3.6 Employers Information Requirements .............................................................................................. 14
4 Process Overview ..................................................................................................................................... 15
4.1 Process map and CIC Stages ............................................................................................................. 15
4.1 Gates............................................................................................................................................ 17
4.2
Lower tiers in the design chain and supply chain. ....................................................................... 18
4.3 Strategic, Managerial and Implementation obligations ................................................................. 18
5 Clients strategic Purposes: ....................................................................................................................... 20
5.1 P01: Registry ..................................................................................................................................... 21
5.2 P02: Use and utilisation..................................................................................................................... 23
5.3 P03 Operations .................................................................................................................................. 24
5.4 P04 Maintenance and repair .............................................................................................................. 25
5.5 P05 Replacement ............................................................................................................................... 26
5.6 P06 Assessment and End of use and Repurposing ............................................................................ 26
5.7 P07 Impacts (costs and carbon) ......................................................................................................... 27
5.8 P08 Business questions .................................................................................................................. 32
5.9 P09 Security and surveillance ........................................................................................................ 33
5.10 P10 Regulation and Compliance .................................................................................................... 34
6 Criteria and metrics: ................................................................................................................................. 35
6.1 Compliance to the COBie/IFC schema ............................................................................................. 35
6.2 Completeness .................................................................................................................................... 35
6.3 Accuracy and enumerations and classification .................................................................................. 35
6.4 Units .................................................................................................................................................. 35
6.5 Enumerations and Classifications...................................................................................................... 35
6.4 Metrics............................................................................................................................................... 36
7 Required detail ......................................................................................................................................... 37
7.0 Structure ............................................................................................................................................ 37
7.1 Instruction sheet ................................................................................................................................ 39
7.2 Contact sheet ..................................................................................................................................... 40
7.3 Object sheets ..................................................................................................................................... 41
7.4 Additional information sheets ........................................................................................................... 42
7.5 Specification of objects and additional information sets ................................................................... 42
8 Bibliography ............................................................................................................................................. 43
8.1 Definitive material............................................................................................................................. 43
2012 AEC3 UK Ltd

July 2012

UK COBie 2.4 Requirements


8.2 UK material ....................................................................................................................................... 43
8.3 US material........................................................................................................................................ 43
8.4 Tools.................................................................................................................................................. 44
Annex A: Recommended Attributes ........................................................................................................... 45
A.1 Facility.................................................................................................................................................. 45
A.2 Space and Zone .................................................................................................................................... 47
A.3 Component ........................................................................................................................................... 49
A.4 Type and System .................................................................................................................................. 49
Annex B: COBie checklist .......................................................................................................................... 51
This checklist combines COBie standard and UK implementation rules. ................................................... 51

2012 AEC3 UK Ltd

July 2012

UK COBie 2.4 Requirements

0 Overview

0.1 The Owners View


An owner may require the delivery of COBie from the lead designer and/or lead contractor to support the
timely delivery of information to support the management of the Facility. A complete COBie should be
expected at the time of Handover, but earlier interim deliveries can be used monitor the business case for
the facility and to help plan for taking ownership.
The COBie information can be either be kept as delivered, or held in ordinary databases, or it can be
loaded into existing Facility Management and Operations applications, either automatically or using simple
copy-and-pasting. The owner should be explicit about the purposes for which the information is required
and about the timing and content of any interim deliveries.

0.2 The Designers and Contractors View


COBie allows the team to document their knowledge about a Facility in both its spatial and physical
aspects. Spatially it can document the spaces and their grouping into floors/sectors and into other zones.
Physically it documents the components and their grouping into product types and into other systems.
Usually the information needed to complete the COBie deliverable will be available already, either in your
BIM models or in reports and schedules and in other material prepared for handover.
Some information may be offered to you in unstructured formats (such paper and scanned documents), but
you should arrange to obtain COBie information on specific aspects from other team members and
suppliers.

0.3 Product Specifiers and Suppliers


COBie can be used to document product data to support the specification/selection/replacement process. If
the client requirements include this, then the product Types should be given the specific attributes
appropriate to that Type.
There are currently 700 such templates available for general use. The RIBAE NBL initiative will be
contributing suggested UK specific properties.

1 Scope

Requiredsharedstructured
Informationincludingobjects,propertiesandrelationships
foraFacilityincludingbuildingandinfrastructure
Operationincluding(designandconstruction)stagespriortohandoverand
(use)stagessubsequenttohandover.

This Part defines expectations for the Required shared structured Information relating to spatial and
2012 AEC3 UK Ltd

July 2012

UK COBie 2.4 Requirements


physical assets and their properties and relationships for Facilities including buildings and infrastructure in
Operation including the design and construction stages prior to handover and acquisition and the
subsequent use stages.
It is intended for use during the development of new facilities and during the acquisition and operation of
existing facilities. It is also applicable during the tendering and retendering of FM and operational
contracts. It is intended to be referred to in contractual requirements and specific contract schedules may
modify and refine the requirements. It may act as a checklist for completeness for use by both providers
and recipients of the facility data.

1.1 Objective
The objective of this document is to explain the organization of the COBIE worksheet and identify who
provides what information within the Requirement as the project proceeds from planning, to design, to
commissioning, to occupancy, to handover.

1.2 Audience
The audience for this document is client and any project team member who wants to understand what
information is required by COBie and who is responsible to provide it. This document is primarily
intended for the UK audience.

1.3 Applicability
COBie is a means for sharing structured facility data ready for use by the owner. The COBie spreadsheet
is simply one way to display an underlying harmonized international buildingSMART Industry
Foundation Class Model View. It should be noted that it is ONLY the language code and the
recommended classification lists that vary between locales. COBie data can be created and used
internationally across locales. The details of the classification lists are summarised in section 6.5
The applicable COBIE version is Version 2. Release 4 and the regional code shall be en-UK or enGB
Note: Where North American spelling is used for sheet names, column names and property names, these
should be preserved, in order to support reading by receiving applications that may depend on them.

1.4 Organization
This document and the Examples provide an overview of COBie including the overall structure of the
spreadsheet. The Examples provides a detailed listing of each COBIE worksheet to identify the specific
columns in each worksheet and illustrate what information is to be provided in each row.

2012 AEC3 UK Ltd

July 2012

UK COBie 2.4 Requirements

1.5 IFC and COBie


IFC (Industry Foundation Classes) is an ISO standard data schema for holding and transmitting facility
information throughout the Facility lifecycle. IFC has been developed over the last 16 years by
buildingSMART, a not-for-profit consortium with chapters in the US, UK, Europe, MEA and the Far East
and Australia. www.buildingsmart.org
COBie (Construction Operation Building information exchange) is a data schema for holding and
transmitting information around handover to support the clients ownership and operation of a facility.
www.wbdg.com

1.6 Background
COBie is formally defined as a subset of IFC, including initially the FM-10 Handover MVD and latterly
the full COBie MVD (see normative references and bibliography). It can also be represented in
spreadsheets or relational databases. It was developed by the US Army ERDC with NASA and the
Veterans Association as a response to the perception that specifications for O&M and other
documentation did not allow these owner organisations to take on effective management immediately on
handover. The COBie data schema has subsequently been generalised for international use by ensuring
that classification and unit systems can be specified.
During traditional projects, most of the information required by COBie is already delivered in
unstructured form. COBie gives the opportunity to input critical data just once, allowing it to be re-used in
many outputs, be tested in many ways and be delivered to many applications including facility
management and asset management systems.

Figure 1: Data is preferred to documents for three strategic reasons. (image courtesy of
STABU, NL)

1.7 Process
The COBie process requires that there are progressively more complete contractually required data
deliverables throughout the design and procurement stages, culminating at the Handover point. Any
deliverable after the point of Handover are expected to consist only of corrections and data obtained
during post-occupancy assessments

2012 AEC3 UK Ltd

July 2012

UK COBie 2.4 Requirements

Figure 2: COBie allows a continuously expanding data set to be complete at


handover.(image courtesy of USACE ERDC)

1.8 COBie for infrastructure and building


COBie is intended for use in both building and infrastructure projects, irrespective of whether there is
already structured information from the design chain and supply chain. When using COBie for
infrastructure and civil projects, the Floor sheet may be read as Sector and used for the primary spatial
subdivision of the overall project. Priority has been given to classification systems and plans-of-work that
support both building and infrastructure in a consistent manner.

1.9 COBie for existing facilities and refurbishment


The COBie format can be used to capture in-use and survey information about a facility. If direct data
entry into the COBie sheets is used, then monitoring should ensure that the recommended classifications
and property names are adhered to.

1.10 Use of COBie information


Projects can collect information in COBie as a route to updating FM systems in use, or for use in its own
right, or for interoperability with other standards such as IFC. The Employers Information requirements
may indicate the intended destination, but consistent adherence to the COBie standard serves to isolate the
supply side from these decisions.

1.11 COBie Contacts


Every participant in developing the COBie file and any third party that is referenced should have its
contact details registered in COBie. This ensures that COBie can act as a primary source of information,
as an index to supporting documentation and as an introduction to the parties in the project.

1.11 COBie Objects


Initially only the Facility need be defined, but as the design stabilises, the Floors (Sectors) and Zones can
be registered. These can then be populated with Spaces. Following on, Types and Systems are specified
and the manageable asset Components assigned. During construction specific products can be identified
and Jobs, Spares and other Resources for their maintenance and operations catalogued.

2012 AEC3 UK Ltd

July 2012

UK COBie 2.4 Requirements

Figure 3: COBie represents the Facility as a simple spatial and physical hierarchy.
(image courtesy of AEC3 Ltd)

2012 AEC3 UK Ltd

10

July 2012

UK COBie 2.4 Requirements

1.12 COBie additional information


Additional information relevant to specific kinds of objects can be associated. This additional data can
include Documents, Attributes, Coordinates, economic and environmental Impacts and Issues. Additional
relationships such as Connections and Assemblies can also be documented.

Figure 4: Various kinds of additional information can be associated to the facility and
its constituents.(image courtesy of AEC3 Ltd)

2012 AEC3 UK Ltd

11

July 2012

UK COBie 2.4 Requirements

2 Referenced Standards
o
o
o
o
o
o
o
o
o
o

UKBS1192:2007:Collaborativeproductionofarchitectural,engineeringand
constructioninformation.
UKPAS1192part2:RequiredInformationforFacilityProcurement
UKPAS1192part3:RequiredInformationforFacilityOperation(forthcoming)
ISO16739:2005:IndustryFoundationClasses(IFC2x)PlatformSpecification
ISO16739:2012:IndustryFoundationClasses(IFC4)Specification
ISO29481InformationDeliveryManual
ISO12006part2(UK:CICCPICUniclass)andpart3(IFD)
UKCICUnifiedPlanofWorkprocessmap(WP104,undergoingreviewand
comment)
COBiedocumentation(www.buildingsmartalliance.org)
BSIPAS55:2008Assetmanagement

Seealsothedefinitivemateriallistedin8.1

2012 AEC3 UK Ltd

12

July 2012

UK COBie 2.4 Requirements

3 Definitions
3.1 Requirements
Requirementsarethedocumentedexpectationsoffacilityowners/commissionersforsharable
structuredinformation.ThesearealsoreferredtoastheEmployersInformationRequirements
(EIR)(qv)(alternativelytheClientsInformationRequirements).

NOTE:DetailedrequirementsarescheduledintheExamples

3.2 Manageable assets


Thoseaspectsofthefacilitythatmaybemanagedduringthefacilitylifecycleincludeboth
physicalandspatialobjects,andtheirfunctionalgroupings.

NOTE:Anassetisauniquelyidentifiableelementwhichhasafinancialvalueandagainstwhich
maintenanceactionsarerecorded.

NOTE:Someaspects,suchasthestructuralframe,orindividualpipeandductsegments,fixings
andsecondaryelementsmaybeexcludedfromscopebytheemployer.

3.3 Purposes
ThoseaspectsoftheFacilitythatareintendedtobemanagedbythefacilityowner.

NOTE:SomePurposes,suchassupportingthebusinesscase,maybecommonwiththebriefing
anddesignprocesses.

3.4 Gates / Stages


Astandardisedprocessmapfortheacquisitionofafacilitymaybedividedintostagesand
gatewaysatsomeofwhichtheRequirementsshallbedelivered.

NOTE:ThestagesatwhichDropsarerequiredshouldbespecifiedintheEIRbyreferencetothe
agreedStageandGatenames.SeetheCICPlanofWork

3.5 Metrics
TheacceptabilityofthedeliverablemaybeassessedagainsttheRequirementsshowninthe
Examplesand/oragainstindicativeratiosandcountsbasedontheinformationprovided.

2012 AEC3 UK Ltd

13

July 2012

UK COBie 2.4 Requirements

3.6 Employers Information Requirements


The Employers Information Requirements of the Contract shall nominate:
(a) Which Gates require a data deliverable (Drops)
This document uses the following drops
CIC 1: Drop 1:

brief / early design

CIC 3: Drop 2a:

design development issued for tender

CIC 4: Drop 2b:

tender submission

CIC 5: Drop 3:

contractors design development and planning

CIC 6: Drop 4:

handover

(b) Whether COBie and/or IFC and Version required. Typically this will be either COBie 2.4 UK
or IFC2x3 CV2 with QTO and Space boundaries level 2. Other proprietary model and
document formats may also be required.
(c) Which Purposes are included and excluded for the data by reference to section 5. Typically this
will include P01-P10 (see section 5 below), along with any additional purposes by extension to
section 5.
(d) Any additional checks and metrics by extension to section 6.
(e) Any additional content by extension to section 7. This may define which of the requirable
(green) fields are required.

2012 AEC3 UK Ltd

14

July 2012

UK COBie 2.4 Requirements

4 Process Overview
4.1 Process map and CIC Stages
Note: CIC and individual institutions may publish a concordance with their current plan of works.
4.1.1 CIC 1: Brief - ending with Drop 1
The Brief defining the project objectives, business need, asset management plan, Client priorities and
aspirations; describing the acceptance criteria, including function, mix of uses, scale, location, quality,
cost (Capex & Opex), value, time, safety, health, environment and sustainability (Carbon, embodied and
in use).
4.1.2 CIC 2: Concept
The Project Brief as approved by the Client at the conclusion of Stage 2, establishing the detailed brief,
scope, scale, form and budget and setting out the integrated concept for the Project; Confidence 75 to
80%, margin 20 to 25%
4.1.3 CIC 3: Design Development ending with Drop 2a
The Project Brief as approved by the Client at the conclusion of Stage 3 , developing in detail the
approved concept to finalise the design and definition criteria, establishing the detailed form, character,
function, cost plan (Capex, Opex),Carbon (embodied and in use); defining all components in terms of
overall size, typical detail performance and outline specification.
Confidence 85 to 90%, margin 10 to 15%
4.1.4 CIC 4: Production Information ending with tender and drop 2b
Integrated production information enabling the production of manufacturing and installation information
for construction. Updated Capex, Opex, Carbon use.
Confidence 90 to 95%, margin 5 to 10%
4.1.5 CIC 5: Constructed Information ending with drop 3
fabrication and manufacturing details, verification, operation and maintenance. Updated Capex, Opex, and
Carbon. This should also include as constructed updates to the production information. The model and
the documentation should fully reflect the actual construction, defect and tolerance deviation as the basis
for the asset model.
Confidence 95 to 98%, margin 2 to 5%
4.1.6 CIC 6: Handover - with drop 4
As constructed systems, operation and maintenance, updated predicted in use performance, (Carbon use,
Capex and Opex).
4.1.6.1 CIC 6A : Post fit-out Handover
Updated As constructed systems, operation and maintenance, updated predicted in use performance,
(Carbon use, Capex and Opex).
4.1.7 CIC 7 : Post Practical Completion
As constructed systems, operation and maintenance, in use performance compared against brief,
(function, mix of uses, scale, location, quality, cost (Capex & Opex), value, time, safety, health,
environment and sustainability (Carbon, embodied and in use)).

2012 AEC3 UK Ltd

15

July 2012

UK COBie 2.4 Requirements

Figure 5: Swimlanes showing CIC Stages 1- 7 and Gates G1-G7.

2012 AEC3 UK Ltd

16

July 2012

UK COBie 2.4 Requirements

4.1 Gates

GatesG1toG7occurattheendoftheassociatedstageCIC1CIC7.
COBiedropsshallbemadeatGatesG1,G2,G3andG6

NOTEtheEmployersInformationRequirementsmayaddadditionaldeliverygates.

TheclientappointedfirsttierpartyshalldelivertheRequirementstotheClientatleastatthe
specifiedgatesincludingG3DesigncompletionorG6Handover.

NOTEfirsttierpartywilltypicallybeleaddesignerorcontractor.

Figure 6: Drops are planned to support client decision processes.

2012 AEC3 UK Ltd

17

July 2012

UK COBie 2.4 Requirements

4.2 Lower tiers in the design chain and supply chain.

Partiesmayensurethatlowertierpartiesbesimilarlyobligatedtodeliverspecifiedaspectsof
theRequirementsinpreparationfortheseGates.

NOTEAlowertierpartycouldbeaspecialistdesignerorsubcontractororproductsupplier.
NOTEFigure6showsatypicaldelegationprocess.

Figure 7: Generic process map for delegation of Requirements.(image courtesy of AEC3


Ltd)

4.3 Strategic, Managerial and Implementation obligations

Apartyshallfulfilitsstrategic,managerialanddetailedobligationsforthedeliveryoftheEIR

4.3.1Strategic:
(a) ReceiveandacceptRequirement(EIR)
(b) PropagationofRequirement(EIR)downwardstonexttier
(c) Reviewandapprovalpriortosubmission
2012 AEC3 UK Ltd

18

July 2012

UK COBie 2.4 Requirements

4.3.2ManagementandQualityAssurance

(a) Reviewofreceivedinformation
(b) Receiptandmerge/integrationofdelegatedsubmissions
(c) Reviewofpreparedinformationforcontinuity,completenessandaccuracy

4.3.3Implementation
(a) Entryofexpectedinformation
a. Useofspreadsheetordatabaseapplications
i. Useofcopyandpaste(usepastespecial:textonly)
ii. Useoffilter/sort
iii. Useoftextbasedformulae
b. UseofBIMauthoringtools
i. UseoftheProjectInformationcommands
ii. Useofthevendorsspecificcommandsandtoolkits
iii. UseofexporttoIFCandmappingtoCOBie
c. UseofNBSCreate,Codebook
i. UseoftheexporttoCOBiecommand

Note:ForexampleAutodeskRevitcanbeaugmentedwithCOBietoolkits.

NOTE:Applicationvendorsmayprovidespecificguidanceonthemanagerialand
implementationoftheCOBierequirements

2012 AEC3 UK Ltd

19

July 2012

UK COBie 2.4 Requirements

5 Clients strategic Purposes:


The supply of accurate and complete information shall support the Employers purposes for asset
management. These may include strategic anticipation, planning and execution of the following ten
distinct purposes: [P01-P10]. Each of these purposes shall be explicitly included or excluded from the
Employers Information Requirement. Whilst the COBie format is required for the delivery of this
information, other information requirements may be met by the delivery of the 3D model(s) (IFC and/or
proprietary format) with supporting documents and drawings. These resources should be associated to the
appropriate COBie objects.

Note:TheprimarydriverfortheearlydropsistomanagetheP08businesscasebasedonP02
UseandP07Impacts.

Purpose

Detail

BSI Pas 55 references

P01

Registration

Registration of the assets is a prerequisite


for the following purposes.

4.5.1a, 4.4.6, 4.6.6, 4.5.1.3

P02

Use and utilisation

Includes data for any soft-landings usage


review

4.5.1b, 4.5.1 i, 4.5.1.4

P03

Operations

Includes data for any soft-landings


operational review

4.5.1 i, 4.5.1.2, 4.6.1

P04

Maintenance and
repair

Includes the tasks and required resources


and spares.

4.5.1c, 4.5.1.2, 4.5.1.5,


4.5.2

P05

Replacement

Includes information relating to the


specification and selection of Types.

4.5.1.7

P06

Assessment and reuse

Including end-of-use, re-purposing and


facility capacity analysis

4.5.1d, 4.5.1.6

P07

Impacts

Economic and environmental (but not


social) impacts

4.5.1 iii

P08

Business case

Continuously review is the primary driver


for the intermediate Drops.

4.5.1

P09

Security and
surveillance

Aspects of the model may be specifically


excluded from shared data.

4.4.7

P10

Regulation and
Compliance

Information relating to the H&S and CDM


and safety of operations in the facility

4.5.1 iii, 4.6.2, 4.4.8

Table 1: Summary of Employers Purposes and references to BSI PAS 55 part 1 & 2.

2012 AEC3 UK Ltd

20

July 2012

UK COBie 2.4 Requirements

5.1 P01: Registry


Registration of assets is required to support accurate audit and reporting. This includes GIS, land
and address identification for the facility. Include spaces and users zoning. Include stacking
(Floors) for buildings or sectoring (Sectors) for infrastructure.

5.1.1 Facility, Floor (Sector) and Zones , Spaces


o

One facility

Every distinct Floor (sector) and outside space and site

Every manageable/accessible space.

spaces identified in design drawings and/or related schedules.

Zones at least for public/private access (and other Zones where known).

Note: Design or construction zones need not be provided.

Every Space shall be assigned to one Floor (Sector)

Every Space shall be assigned to one (or more) Zones.

Identity, including Name, Description, Classification, Ext System Id (if available)

Facility and optionally Floor (Sector) : GIS referencing (lat, long, elev, Site address in
SiteDescription, UPRN, TOID, BuildingID and other LandTitleNumber
registration as Attributes.

Note the orientation of the facility (for example rotation from true North) as used in BIM authoring and
analysis tools is not required in COBie.
o

All mandatory fields must be provided as illustrated in the Examples.

Note: In general, properties associated to buildingSMART objects and Pset_ property sets and Base
Quantities quantity sets are mandatory. The example Attributes include other properties provided by BIM
applications.
Note Plan and 3d shapes are not required.

2012 AEC3 UK Ltd

21

July 2012

UK COBie 2.4 Requirements

5.1.2 Components, Types and Systems


o

Every manageable asset Component

every products and equipment found in design drawings and/or schedules.

Every distinct functional System including substructure, structure, envelope

Every distinct Type

Generic or specific products

Constructions and assemblies

Materials

Every Component shall be assigned to one Type

Every Component shall be part of one (or more) Systems.

Identity, including Name, Description, Classification (Types and Systems), Ext System
Id (if available)

All mandatory fields must be provided as illustrated in the Examples and Templates.
Note: In general, properties associated to buildingSMART objects and Pset_ property
sets and Base Quantities quantity sets are mandatory. The example Attributes include
other properties provided by an actual BIM applications.
Note Plan and 3d shapes are not required.

2012 AEC3 UK Ltd

22

July 2012

UK COBie 2.4 Requirements

5.2 P02: Use and utilisation.


Documentation of the intended use, capacity and utilisation of the Facility is required to support
comparisons of actual use and utilisation and portfolio management. It also supports improved
briefing for future projects.
Note: This may include data for soft-landings usage review.

Facility, Floor (Sector) and Zones , Spaces


o

Classification

Functional benefits

areas (net and gross)

the method of measurement used shall be documented on the Facility sheet

bed/pews/occupants/clients.

Note: RICS NRM schedule E contains a list of suggested beneficial measures.


o

Utilisation and hours of intended use

2012 AEC3 UK Ltd

Utilisation as a percentage where 24/7 = 100%

23

July 2012

UK COBie 2.4 Requirements

5.3 P03 Operations


Information necessary for the normal operations of the facility is required to support the facility operators
and the owner to anticipate costs of operations.
Note: This may include data for soft-landings operations review
Types

Power consumption (as Attribute (W) and as a yearly Impact with Impact Type as
Primary Energy Consumption and Impact Stage is use (MJ))

Jobs including start-up, shutdown and operation procedures

Components and Systems


o

Test results and normal settings and readings from Commissioning

2012 AEC3 UK Ltd

24

July 2012

UK COBie 2.4 Requirements

5.4 P04 Maintenance and repair


Information on the recommended maintenance tasks including planned preventative maintenance
is required to support the facility operators to anticipate and plan for costs of maintenance.

Types
o

Jobs including inspection/diagnostics, PPM, repairs (frequency is duplicated with


Impact where the Impact Stage is maintenance)

Spares
Note: labour cost rates are not required

2012 AEC3 UK Ltd

25

July 2012

UK COBie 2.4 Requirements

5.5 P05 Replacement


Information on the reference or expected replacement service life and costs should be available to
the facility operators and to the owner to anticipate costs of maintenance.

Types
o

All the additional columns from Nominal Length through to Code Compliance shall
be provided.

Expected service life (or mean time to failure) shall be provide. (may also be used
within Job and within Impacts)

Estimated replacement cost (may also be used within Impacts)

Job replacement

Impact replacement cycle

The additional Type attributes that are documented in the UK COBie Type Templates

www.bimtaskgroup.org/COBie

Additional attributes as found on the design drawings and those additional properties
found in the Example object templates

5.6 P06 Assessment and End of use and Repurposing


Information on factors and assessment is required to support the management of the end of use stage,
including facility capacity analysis for re-briefing and re-purposing.
Spaces

Client requirements

Physical limitations of spaces (maximum surface loadings, noise criteria, service


provision and capability)

Types
o

Impacts (especially embedded carbon content)

Recyclable percentage

2012 AEC3 UK Ltd

26

July 2012

UK COBie 2.4 Requirements

5.7 P07 Impacts (costs and carbon)


Information is required to support the management of economic and environmental impacts of the facility
throughout the life cycle. Clause 5.7.1 defines the mandatory and optional expectations for Facility
Impacts.
Clauses 5.7.2 onwards offers methods for providing more detail. There are several methods available to
analyse and document discrete Impacts that make up the overall Impact of the Facility. The method
chosen affects how data can be aggregated up to facility and/or disaggregated downwards.

Note: Of the methods for documenting Impact listed below, it is expected that 5.7.2 will predominate
initially, as this is compatible with SFCA and comparable with other standard cost analyses.
Note: energy tariff and carbon trading rate information is not required

5.7.1

Mandatory: Association of Impacts to Facility

The following shall be provided:

Cost and Carbon impacts shall be associated to the Facility

Production and In-Use phases shall be documented separately.

This is equivalent to associating to the Facility:

Costs (capital) and CO2e (embedded) in production phase.

Costs and CO2e in use phase.

Figure 8: Four Facility Impacts


Optionally the following measures may be given

Energy in use phase (Optional)

Costs and CO2e in maintenance phase. (Optional)

Costs and CO2e in replacement phase. (Optional)

5.7.2

Association of Impacts to Systems

Impacts can then be aggregated up to the Facility

2012 AEC3 UK Ltd

27

July 2012

UK COBie 2.4 Requirements

Figure 9: Functional analysis of Impacts by System


Example: Given a complete list of Systems within the Facility

Facility.Impact = Sum (System.Impact)

Figure 11: Summing of constituent Systems to assess the Facility


Sheet

Name

SheetName

RowName

Value

Impact

Production
cost

System

Plumbing 1

Impact

Production
cost

System

External envelope

Unit
800.00

Pounds

7000.00

Pounds

97000.00

Pounds

etc

Impact

Production
cost

Facility

Standard Cell

Figure 12: Example calculation

2012 AEC3 UK Ltd

28

July 2012

UK COBie 2.4 Requirements

5.7.3

Association of Impacts to Floors (Sectors) or Spaces or Zones


Applicable to use phase
Not applicable for maintenance phase
Not applicable for replacement phase
Not applicable for production (capital & embedded) phase
Impacts can then be aggregated up to the Facility from the Floors (Sectors) or Zones or Spaces

Figure 10: A predicted quarterly reading of a Zone

2012 AEC3 UK Ltd

29

July 2012

UK COBie 2.4 Requirements

5.7.4

Association of Impacts to Components

Impacts can then be aggregated up into Systems to the Facility

Impacts can then be aggregated up into Spaces, Zones, Floors (Sectors) to the Facility

Figure 13: Waste analysis for a specific Component

2012 AEC3 UK Ltd

30

July 2012

UK COBie 2.4 Requirements

5.7.5

Association of Impacts to Types

An Impact of a Component is that Impact of the reference Type factored by the ratio of their
quantities. If an Impact such as the production cost of a Type is known, along with at least one
measured Quantity, then the actual Impact of a Component with matching measured Quantity can
be obtained.

Similar Quantities (by name, measurement type and preferably unit) must be associated to Types
and its Components. Whatever the measure(s) are used on the Type, at least one identical
measure must be used on each of its Components. Given matching measures, a ratio can be
calculated to use as a factor to apply to any Impacts associated to the Type. Otherwise the ratio
may be assumed to be "1 .00", or the Component omitted from the calculation

Where there are multiple quantities on the Component and Type, preference should be given to
mass, then volume then area, then length, then unity.

Where there are base, net and gross quantities on the Component and the Type, preference should
be given to gross measures when deriving impact measures.

Impacts can then be aggregated from the Types, through Components up into Systems and
Facility

Impacts can then be aggregated from the Types through Components up into Spaces, Zones and
Floors (Sectors) and Facility

Figure 14: Quantities associated to Type and Component(s)

Figure 15: Impacts associated to Type and Component(s)


Example: Considering the SVP component:

Component.Impact = Type.Impact * (Component.Quantity / Type.Quantity )

Figure 16: Scaling of Component Impacts from reference Types


Sheet

Name

SheetName

RowName

Value

Unit

Impact

Production
cost

Type

Plumbing SVP 1

500.00

Attribute

Length

Type

Plumbing SVP 1

1000

millimeters

Attribute

Length

Component

Plumbing SVP 1:211824

2700

millimeters

Impact

Production
cost

Component

Plumbing SVP 1:211824

Pounds

500.00 * (2700 / 1000)


= 1350.00

Pounds

Figure 11: Example calculation


2012 AEC3 UK Ltd

31

July 2012

UK COBie 2.4 Requirements

5.8

P08 Business questions

Information is required to support the on-going evaluation of the business case for ownership and
operation of the facility. This requires continuous development of the Impacts (P7) and of the beneficial
profile of the asset (P2) from the earliest Drop onwards

CIC Gateway 1: (drop 1) Initial and in-use, benefits and impacts


o

Facility and Spaces

Capacity and benefit values should be associated to spaces and the aggregation
to the facility

With Name, Description and Classification

Briefing and design Documents

Facility and Main fabric Types including Floor, Wall and Roof (Structure) and main
MEP Systems

with estimated areas (covered/served)

Production cost and CO2e Impact (targets)

Maintenance cost and CO2e Impact (targets)

CIC Gateway 3 (drop 2a) and CIC Gateway 4 (drop 2b).


o

As CIC Gateway 1 ( drop 1) plus

Types and Components

Main fabric items including Floor, Wall and Roof Types (Structure) with
Component areas

Main MEP Systems

with Areas served

Use cost and CO2e Impact (targets)

CIC Gateway 5 (drop 3)


o

As drop CIC gateway 4 (drop 2b) plus

Served Zones for each system (not explicit in COBie)

Facility / Zones / Spaces

Capacity and benefit values: Clients performance simulation results.

Impacts: cost and CO2e: Energy simulation results.

Types

2012 AEC3 UK Ltd

Quantities
32

July 2012

UK COBie 2.4 Requirements


o

Systems / Components

Costs (capital) and Impacts (embedded)

Costs (in-use) and Impacts (in-use)

Estimated installation dates

Allocation of Components to Systems

Allocation of Spaces to Zones

CIC 6 : handover (drop 4)


o

As drop CIC Gateway 5 (drop 3) plus

Systems

Capacity

Control systems

Types and Components

5.9

Quantities

Data required for other Purposes (see P01, P03-P06 and P09-P10)

CIC 7 : (drop 5)
o

As drop CIC 6 (drop 4) plus

Information and corrections from post-occupancy assessment.

P09 Security and surveillance

Information is required and/or information may be supressed to support the management of the security
and surveillance of the facility. This may include a confidential schedule of objects (such as CCTV
cameras) or attributes (door key codes) to be omitted or concealed from any version of the Requirements
being held outside of the Employers security.

2012 AEC3 UK Ltd

33

July 2012

UK COBie 2.4 Requirements

5.10 P10 Regulation and Compliance


Information is required to support the maintenance of the health and safety of the users of the facility
including H&S and CDM
o

Issues

may be related to Facility, Floor (Sector), Space, Zone, Component, Type,


System

may be related to Attributes, Documents or Impacts

Safety procedures and cautions within those safety procedures shall be


documented

Jobs

2012 AEC3 UK Ltd

34

July 2012

UK COBie 2.4 Requirements

6 Criteria and metrics:


Parties shall provide management and quality oversight and review of the Requirement in terms of :

6.1 Compliance to the COBie/IFC schema


The deliverables shall be compliant to the COBie/IFC schema.
Note: The most significant rules are listed in the appendix.
Note: Validation can be conducted against the buildingSMART FM-10 handover MVD, the buildingsmart
alliance COBie schema, and published mappings.

6.2 Continuity
The deliverables shall be re-use the names defined in earlier drops for each Facility, Floor (Sector), Zone,
Space, Type, System and Component.
The External System identifiers shall also be maintained.

6.3 Completeness
The deliverables shall be complete as defined in 5.1 Registry and the selected Purposes (5.2-5.10) in the
Employers Information Requirement

6.4 Accuracy and enumerations and classification


For drops 1 and 2, a confidence range of numeric figures for areas and other physical measures of +/- 5%
and 2% shall be acceptable. Other predicted Impacts and performance shall support a confidence range of
numeric figures of +/- 20% and 10%
For drops 3 and 4, an accuracy range of numeric figures against actual of +/- 5% and 2% is expected.
Note: the CIC Plan of Works also refers to expected accuracy

6.5 Units
Units shall be provided separately for all numeric measures except length, area, volume and currency
where used consistently as declared for the Facility overall. Impact durations, warranty durations and Job
frequencies shall be expressed in Years. Job durations shall be expressed in hours.

6.6 Enumerations and Classifications


Enumerations (as specified in the Attributes and Picklists) shall be adhered to.
Classifications must be as provided from the defined Picklists
Sheet
Facility
Facility
Type
Space
System
Contact

Column
Phase
Category
Category
Category
Category
Category

2012 AEC3 UK Ltd

Classification Table
CIC table. RIBA or OGC otherwise
Uniclass Table D (RICS BCIS Facility Classification)
Uniclass table L
Uniclass table D
Uniclass Table G & H or SFCA / SF(CE)CA
Uniclass Table C

35

July 2012

UK COBie 2.4 Requirements

6.7 Metrics
6.7.1 To aid the management process, the following counts and date ranges shall be displayed on the
Instruction sheet for each work sheet and for the COBie data set overall
Example
2012-01-01
2012-03-23
2309

Key
Date of first change
Date of last change
Number of entries

Table 2: Metrics used to assess progress


6.7.2 To track progress, the following summaries shall be made.
Example
Key
4567 Number of objects in total
9876 Number of addition information rows in total.

Table 3: Summary metrics


6.7.3 To aid the management assessment, the following ratios shall be measured
Expected Ratio
Key
More than 10 ?
Additional Information per Object
More than 20 ?
Components per Type
More than 50 ?
Components per System
More than 20 ?
Spaces per Zone
More than 10 ?
Spaces per Floor (Sector)

Table 4: Examples of ratios that can be used to assess completeness and quality
Note: Normal ranges for these ratios will be obtained from the analysis of existing COBie deliverables.
The expected ratios suggested here are provisional

Figure 12: Example of date and ratio metrics measured on a COBie dataset.

2012 AEC3 UK Ltd

36

July 2012

UK COBie 2.4 Requirements

7 Required detail
7.0 Structure
7.0.1 Structure
COBie may be delivered in Spreadsheet XML 2003 format.
Note: This format is acceptable to Microsoft Excel and Open Office applications, so other formats
compatible with these may be anticipated, including XLS and OPS. Formats containing macros or other
embedded code may be rejected by firewalls and security scans.

All sheets, columns and header rows shall be present in the deliverable, named and ordered as in the
examples.
Note: Applications creating COBie data need not reproduce the colour coding of the COBie worksheets
found in the manual COBie template and example files. However when pasting into the COBie sheet, it is
preferable to use paste-special-text-only, to maintain the cells colouration, formatting and validation.

Additional sheets may occur in the deliverable after the final PickLists sheet.
Note: any additional sheets may not be read by receiving applications.
Additional columns may occur in the deliverable to the right of the final specified columns but should
have a header column name.
Note: such columns should be read by receiving applications, as if they were textual Attributes. They can
be used to simplify the generation of COBie information where the Attribute is applicable to the majority
of the objects on the sheet. For example, if all or most Spaces are expected to have a FloorFinish value,
then such a column can be added.
Blank rows should not be inserted between data rows or below the header row.

7.0.1 Naming
Names shall be unique within their sheet, except that the System, Zone and Attribute names must be
unique in conjunction with other columns.
Names shall use neither commas nor unusual punctuation or characters.
Contacts are named by use of their valid email address.
7.0.2 Columns
Mandatory (yellow) fields shall be provided.
Key (salmon) fields shall be provided with text exactly matching a value in the referenced column
System fields (purple) shall be provided if the row is not generated manually.
Requirable fields (green) shall be provided according to the Purposes selected in the Employers
Information Requirement.
7.0.3 Dates
Dates shall be presented in ISO style:
Example
Sheet
2012-03-15T12:45:00
(all sheets)
2012-03-15
Component
2012-03-15
Component
2012-03-15
Job

Column
Created On
Installation Date
Warranty Start Date
Start

Table 5: Date format


2012 AEC3 UK Ltd

37

July 2012

UK COBie 2.4 Requirements

7.0.3 Classifications
Local Classifications shall not contain commas, but shall use a colon to separate any code from the
description. These may be lists. (see 6.5 above)

Example
C3891 : Manufacturers
D376 : Detention secure facilities prisons
CIC 6 : Handover
D376 : Detention secure facilities prisons
L72104 : Washbasins
5A1 : Sanitaryware

Sheet
Contact
Facility
Facility
Space
Type
System

Column
Category
Category
Phase
Category
Category
Category

Table 6: Local classification

7.0.4 Lists
Lists (including local classification see 7.0.3) shall be comma delimited.
Example
L0-01A, L0-01B
WC Pan 211807,Wallgate ALS180 Basin 211808
1. Spray the CWC with a bathroom type cleaner, 2.
Lime scale can be removed using proprietary products
and abrasives, 3. Stains and surface marks may be
removed with the use of a scouring pad ( grade Green
fine) used wet with a liquid cleaning agent if
necessary.
Wallgate ALS180 Basin DL7523, CandG P101
Certificate
1,,10

Sheet
Zone
System
Job

Column
Space Names*
Component Names**
Description (sub tasks)

Job

Resource Names

Attribute

Value (ranges and tables)

Table 7: Comma separated lists


* On the Zone sheet Space lists can be avoided by repeating the row for each member Space.
**On the System sheet Component lists can be avoided by repeating the row for each member
Component.
7.0.5 Numeric Values and units
The units of measure for length, area, volume and currency shall be defined on the Facility sheet.

Example
millimeters
squaremeters
cubicmeters
Pounds

Sheet
Facility
Facility
Facility
Facility

Column
Linear Units
Area Units
Volume Units
Currency Unit

Table 8: Common units of measure


Numeric values shall be provided without units appended. Unknown values may be entered as 0.

Example
millimeters

Sheet
Floor (Sector)

2012 AEC3 UK Ltd

Column
Elevation
38

July 2012

UK COBie 2.4 Requirements


millimeters
millimeters
squaremeters
squaremeters
millimeters
Pounds
millimeters

Floor (Sector)
Space
Space
Space
Type
Type
Coordinate

Height
Useable Height
Gross Area
Net Area
Nominal Length, Nominal Width, Nominal Height
Replacement Cost
Coordinate X Axis, Coordinate Y Axis, Coordinate Z Axis

Table 9: Use of common units of measure

The units of measure on the Attribute and Impacts sheets shall be provided in the separate column,
selected from the Picklists provided.

Example
W
kg

Sheet
Attribute
Impact

Value Column
Value
Value

Unit Column
Unit
Impact Unit

Table 10: Use of units from Picklists.

The units of measure for Durations and Frequencies on the Type and Job sheets, shall be provided in the
separate column, selected from the Picklists provided. The unit of measure for Impact timings shall be
Years.

Example
Year
hour
Year
Year
Year
Year

Sheet
Type
Job
Job
Impact
Impact
Impact

Value Column
Expected Life
Duration
Frequency
LeadInTime
Duration
LeadOutTime

Unit Column
Duration Unit
Duration Unit
Frequency Unit
(fixed)
(fixed)
(fixed)

Table 11: Time units


Note: The Job Frequency is a duration measured between Job starts. The Impact timings define a
repeating cycle, starting at the time of handover. Initial impacts such as capital costs and embedded
carbon should have zeros entered for all three timings LeadInTime, Duration and LeadOutTime.

7.1 Instruction sheet


Note: The Instruction worksheet provides general information about the COBIE file including the version
and release number. Any regional requirements for COBIE files may also be identified through the
Region field.
7.1.1 Title, Version, Release, Status and Region shall be provided. This information should not change.
7.1.2 The metrics specified in section 6 shall be provided. These will develop with the COBie dataset.

Figure 13: Instruction sheet (release should be 4, not 40)

2012 AEC3 UK Ltd

39

July 2012

UK COBie 2.4 Requirements

7.2 Contact sheet


Note: Regardless of when you submit a COBIE file the information about the people who created the data
in the file and the companies that support the project, such as warranty contractors and parts suppliers,
will need to be documented as that information becomes available. Early on the only information in the
Contact table will be the designated person responsible for providing the COBIE data from the designers
(or design-builders) office. As the project progresses and more project partners contribute to COBIE or
when companies that need to be listed for use by facility managers, are found, these will be added to the
Contact worksheet.

Sheet

Contact

Contents
People and Companies: actors and their roles including designers,
consultants, contractors, sub-contractors and suppliers, warrantors and
maintainers.

Figure 14: The information sheet summarises the sheet names and content, starting with
Contact

Example
nn@aec3.com
nn@aec3.com
sales@aec3.com
support@aec3.com
warranty@aec3.com
nn@aec3.com
spares@aec3.com

Sheet
Contact
(all sheets)
Type
Type
Type
Issue
Spare

Column
Email
Created By
Manufacturer
Warranty Guarantor Parts
Warranty Guarantor Labor
Owner
Suppliers

Table 12: Use of Contacts.

2012 AEC3 UK Ltd

40

July 2012

UK COBie 2.4 Requirements

7.3 Object sheets

Figure 15: COBie focuses on 7 principal objects (with 3 additional objects to support
maintenance activities).
Sheet
Facility
Floor
Space
Zone
Type
Component
System
Spare
Job
Resources

Contents
Facility includes the Project, Site and Building/Structure
Floors (Sectors) are the mandatory spatial structure.
Spaces are the spatial locations where inspection, maintenance and operation Jobs
occur.
Zones are additional functional groupings of specs.
Types are the mandatory grouping of Components as types or products, used to
organise maintenance tasks
Components are the physical assets.
Systems are additional functional groupings of Components
Spares are the physical objects and Jobs are the processes used to maintain and
operate the assets.
Jobs are the processes used to maintain and operate the assets.
Support the processes.

Table 13: COBie objects


For infrastructure and civil projects, the Floor sheet can be read as Sector and no elevation or height
information shall be given, but a Coordinate offset shall be provided instead. Components shall be
assigned to the Space (or Spaces) that would be visited to inspect or maintain it, even if they are adjacent
to or outside of the Space.
Note: Equipment Components are typically associated to a single Space. Doors and interior window
Components may require the identification of both Spaces that are connected. Large asset Components
may be inspected and maintained from several Spaces. Some HVAC equipment may be inspected from a
hatchway in a remote Space. However, some receiving systems may read only the first space.

2012 AEC3 UK Ltd

41

July 2012

UK COBie 2.4 Requirements

7.4 Additional information sheets


There is also a variety of additional information that may be associated to the previous Object worksheets.
.
Sheet

Attribute

Document
Impact
Connection

Coordinate
Assembly
Issue

Contents
Additional attributes with name, description, value and units. Property sets of
referenced item. The Attribute worksheet may contain additional information
relating to specific types of object. The Attribute worksheet is required to be used to
capture the distinct. In general intended and provisional data should be replaced with
actual and as built information.
Associated documents including briefing, product data and other required submittals.
All applicable document references. The Document worksheet may contain indexing
information to file based information relating to any phase of the project. The
Document worksheet used to capture the expected product submittals, to link the
actual approved contract submittals, and to link to any appropriate commissioning
documentation.
Economic and environmental impacts for objects at specific life cycle stages
optionally with a flexible repeating pattern
Logical connections between Components
Spatial locations in box, line, or point format. Floors (Sectors), Spaces and
Components can be located, and Spaces given a box size. (Types should be sized
through their Nominal Length, Nominal Width and Nominal Depth.)
Types or Components can be aggregated, so that configurations can be managed
collectively.
Issues and Risks can be recorded and associated to one or two Objects or Documents

Figure 16: Additional information shall be provided as required by the Employers


Purposes.

Where consistent, additional information such as Attribute, Document, Impact and Issue, should be
associated to the Type or System in preference to the Component and associated to the Floor (Sector) or
Zone in preference to the Space.
Example: if all the values on an Attribute of Components sharing the same Type are identical, a single
Attribute should instead be associated to the Type.
Attributes not supporting the clients Purposes shall be omitted.
Example: Attributes relating purely to the graphic appearance or behaviour are not required.

7.5 Specification of objects and additional information sets


The Examples and Templates illustrate the fixed requirements of the COBie/ IFC handover schema and
cover the requirements for specific additional information relating to objects types. See the Annexes.
Type templates can be reviewed and downloaded from:
www.bimtaskgroup.org/COBie

2012 AEC3 UK Ltd

42

July 2012

UK COBie 2.4 Requirements

8 Bibliography
8.1 Definitive material
COBie is freely available. The COBie standard is published
(http://www.buildingsmartalliance.org/index.php/projects/activeprojects/25) and is defined as the FM
Handover MVD (http://www.buildingsmartalliance.org/docs/BSADOC_COBIE/index.htm) which
contains the terms of the COBie license. The COBie spreadsheet is a mapping of the FM Handover MVD
as documented in the COBie responsibility matrix
( http://projects.buildingsmartalliance.org/files/?artifact_id=4093 ).

COBie: http://www.wbdg.org/resources/COBie.php
buildingSMART FM Design Handover view: www.buildingsmart.org buildingSMART Alliance
Handover view: http://www.nibs.org/docs/BSADOC_COBIE/index.htm
(includes Interoperability specification)
The use of Excel or any particular proprietary format or software is not part of the COBie standard. The
published XLS template is available in Spreadsheet XML 2003 and OpenOffice standard formats if
requested.

8.2 UK material
An empty COBie 2.4 sheet is defined in
COBIE-UK-2012.xls
Examples are available in
COBie-UK-2012-example1-drop1.xls and .ifc
COBie-UK-2012-example1-drop2a.xls and .ifc
COBie-UK-2012-example1-drop2b.xls and .ifc
COBie-UK-2012-example1-drop3.xls and .ifc
COBie-UK-2012-example1-drop4.xls and .ifc
Templates for specific objects are found in
www.bimtaskgroup.org/COBie
[type-subtype]_UK.xls and .ifc
Note: An example is SanitaryTerminal_WASHHANDBASIN_UK.xls or
SanitaryTerminal_WASHHANDBASIN_UK.ifc

8.3 US material
Overview: http://buildingsmartalliance.org/index.php/projects/commonbimfiles/
8.3.1
Production of BPie deliverable at Design, Programming stage (not in current scope)
Similar to http://projects.buildingsmartalliance.org/files/?artifact_id=4444
With additional properties as specified by:
http://iug.buildingsmart.com/idms/information-delivery-manuals/idm-for-building-programming
2012 AEC3 UK Ltd

43

July 2012

UK COBie 2.4 Requirements


8.3.2 Production of COBie deliverable at Design, Construction Documents stage.
http://projects.buildingsmartalliance.org/files/?artifact_id=4445
8.3.3 Production of COBie deliverable at Construction, Product Selection stage.
http://projects.buildingsmartalliance.org/files/?artifact_id=4446
8.3.4 Production of COBie deliverable at Construction, Handover stage.
http://projects.buildingsmartalliance.org/files/?artifact_id=4448

8.4 Tools
Note: Tools may support the preparation of COBie datasets directly or through the IFC format which is
supported by most BIM authoring tools.
www.aec3.com BimServices: Command line utilities for mapping between IFC and COBie and making
quality assessments, merging, reporting and comparing. The toolkit includes extended interoperability
specifications that are editable.
BiMServer Custom build with COBie plugins: This download provides a custom build of TNO's BiMServer

with COBie export and import features. Export formats include COBie (spreadsheet XML) and various
HTML reports such as room data sheet and spatial decomposition. A COBie compliance report is also
provided as an export but is subject to pre-validation changes that may be necessary to fit a model into a
valid COBie file. Model merging capability. (includes interoperability specification in the open source
code)
COBie Satellite Server Application: This download provides a standalone client and BiMServer Satellite

application that may be used with or without BiMServer. The primary purpose of this application is to
provide compliance and comparison report exports for COBie (spreadsheet XML) files. In addition to
these file utilities, the application may connect to a running instance of BiMServer and export a COBie
comparison report of two project models.
www.autodesk.com Revit COBie toolkit through usual Autodesk support channels. .
Note: Supporting tools for preparation and consumption are currently documented at
www.buildingsmartalliance.org

2012 AEC3 UK Ltd

44

July 2012

UK COBie 2.4 Requirements

Annex A: Recommended Attributes


A.1 Facility

1234
567801
123445

n/a

GrossArea

20.00 squaremeters

GrossVolume

55.00 cubicmeters

IsLandmarked

false

logical

IsPermanentID

true

logical

LandTitle
Number
NetArea

ESX257525

2012 AEC3 UK Ltd

18.50 squaremeters

Description

Example
Unit

BuildingID

Example
Value

Name

Auniqueidentifierassignedtoa
building.Atemporaryidentifieris
initiallyassignedatthetimeof
makingaplanningapplication.This
temporaryidentifierischangedtoa
permanentidentifierwhenthe
buildingisregisteredintoastatutory
buildingsandpropertiesdatabase.
Sumofallgrossareasofspaces
withinthebuilding.Itincludesthe
areaofconstructionelementswithin
thebuilding.Maybeprovidedin
additiontothequantitiesofthe
spacesandtheconstruction
elementsassigendtothebuilding.In
caseofinconsistencies,the
individualquantitiesofspacesand
constructionelementstake
precedence.
Sumofallgrossvolumesofspaces
enclosedbythebuilding.Itincludes
thevolumesofconstruction
elementswithinthebuilding.May
beprovidedinadditiontothe
quantitiesofthespacesandthe
constructionelementsassigendto
thebuilding.Incaseof
inconsistencies,theindividual
quantitiesofspacesand
constructionelementstake
precedence.
Thisbuildingislistedasahistoric
building(TRUE),ornot(FALSE),or
unknown.
Indicateswhethertheidentity
assignedtoabuildingispermanent
(=TRUE)ortemporary(=FALSE).
Thelandtitlenumber(designation
ofthesitewithinaregionalsystem).
Sumofallnetareasofspaceswithin
thebuilding.Itexcludestheareaof
45

July 2012

UK COBie 2.4 Requirements

NetVolume

46.25 cubicmeters

NumberOf
Storeys
OccupancyType

1 number
prison

RefElevation
RefLatitude

50000.0 millimeters
51,30,0
n/a

RefLongitude

0,7,34

n/a

TrueNorth

0.0,1.0

UPRN

44010823

n/a

TOID

osgb1000001 n/a
134770

2012 AEC3 UK Ltd

n/a

constructionelementswithinthe
building.Maybeprovidedin
additiontothequantitiesofthe
spacesassigendtothebuilding.In
caseofinconsistencies,the
individualquantitiesofspacestake
precedence.
Sumofallnetvolumesofspaces
enclosedbythebuilding.Itexcludes
thevolumesofconstruction
elementswithinthebuilding.May
beprovidedinadditiontothe
quantitiesofthespacesassignedto
thebuilding.Incaseof
inconsistencies,theindividual
quantitiesofspacestake
precedence.
Thenumberofstoreyswithina
building.
Occupancytypeforthisobject.Itis
definedaccordingtothepresiding
nationalbuildingcode.
RefElevation
WorldLatitudeatreferencepoint
(mostlikelydefinedinlegal
description).Definedasinteger
valuesfordegrees,minutes,
seconds,and,optionally,millionths
ofsecondswithrespecttotheworld
geodeticsystemWGS84.
WorldLongitudeatreferencepoint
(mostlikelydefinedinlegal
description).Definedasinteger
valuesfordegrees,minutes,
seconds,and,optionally,millionths
ofsecondswithrespecttotheworld
geodeticsystemWGS84.
Vectorindicatingtheorientationof
themodelagainstgeographicnorth.
TheUPRNisthepersistentkey
identifierprovidingconsistency
acrosstheAddressBaseproduct
range.Allhistoric,alternativeand
provisionaladdressesforaBasic
LandandPropertyUnit(BLPU)are
recordedagainstthesameUPRN.
TheTOIDisauniquefeature
identifierforthebuildingandcomes
fromtheOSMasterMapTopography
Layer.TheTOIDisa16character
numberthatisprefixedwithosgb
andwillstaythesamethroughout
thelifeofafeature.
46

July 2012

UK COBie 2.4 Requirements

Table 14: Recommended additional Facility Attributes


Recommended Facility Attributes are scheduled in specific Templates which can be obtained from
www.buildingsmart.org , www.buildingsmart.org.uk.

Benefit
CeilingCovering

Concealed
FinishCeilingHeight

none

false

FinishFloorHeight

FloorCovering

none

GrossCeilingArea

GrossPerimeter

2012 AEC3 UK Ltd

Description

Unit

Value

Name

A.2 Space and Zone

1 client
n/a

Beneficialmeasure
Labeltoindicatethe
materialorfinishofthe
spaceceiling.Thelabelis
usedforroombook
informationandoften
displayedinroomstamp.
boolean
Concealed
2500.0 millimeters
Heightofthesuspended
ceiling(fromtopofflooring
tothebottomofthe
suspendedceiling).Tobe
providedonlyifthespace
hasasuspendedceilingwith
constantheight.
0 millimeters
Heightoftheflooring(from
baseslabwithoutflooringto
theflooringheight).Tobe
providedonlyifthespace
hasaconstantflooring
height.
n/a
Labeltoindicatethe
materialorfinishofthe
spaceflooring.Thelabelis
usedforroombook
informationandoften
displayedinroomstamp.
squaremeters Sumofallceilingareasofthe
space.Itincludesthearea
coveredbyelementsinside
thespace(columns,inner
walls,etc.).Theceilingarea
isthereal(andnotthe
projected)area(e.g.incase
ofslopedceilings).
11546.8 millimeters
Grossperimeteratthefloor
levelofthisspace.Itallsides
ofthespace,includingthose
partsoftheperimeterthat
47

July 2012

UK COBie 2.4 Requirements

GrossVolume

GrossWallArea

Height

InteriorOrExteriorSpace internal
NetCeilingArea

NetPerimeter

NetVolume

NetWallArea

2012 AEC3 UK Ltd

arecreatedbyvirtual
boundariesandopenings
(likedoors).
cubicmeters Grossvolumeenclosedby
thespace,includingthe
volumeofconstruction
elementsinsidethespace.
squaremeters Sumofallwall(andother
verticallybounding
elements,likecolumns)
areasboundedbythespace.
Itincludestheareacovered
byelementsinsidethewall
area(doors,windows,other
openings,etc.).
2500.0 millimeters
Totalheight(frombaseslab
withoutflooringtoceiling
withoutsuspendedceiling)
forthisspace(measured
fromtopofslabbelowto
bottomofslababove).Tobe
providedonlyifthespace
hasaconstantheight.
n/a
InteriorOrExteriorSpace
squaremeters Sumofallceilingareasofthe
space.Itexcludesthearea
coveredbyelementsinside
thespace(columns,inner
walls,etc.).Theceilingarea
isthereal(andnotthe
projected)area(e.g.incase
ofslopedceilings).
11546.8 millimeters
Netperimeteratthefloor
levelofthisspace.It
excludesthosepartsofthe
perimeterthatarecreated
byvirtualboundariesand
openings(likedoors).Itis
themeasurementusedfor
skirtingboardsandmay
includetheperimeterof
internalfixedobjectslike
columns.
cubicmeters Netvolumeenclosedbythe
space,excludingthevolume
ofconstructionelements
insidethespace.
squaremeters Sumofallwall(andother
verticallybounding
elements,likecolumns)
areasboundedbythespace.
Itexcludestheareacovered
byelementsinsidethewall
area(doors,windows,other
48

July 2012

UK COBie 2.4 Requirements

OccupancyNumber

1 each

OccupancyType

custody

Perimeter
Utilisation
WallCovering

none

n/a

11546.8 millimeters
95.50 percent
n/a

openings,etc.).
Numberofpeoplerequired
fortheactivityassignedto
thisspace.
Occupancytypeforthis
object.Itisdefined
accordingtothepresiding
nationalbuildingcode.
Perimeter
PlannedAvailability
Labeltoindicatethe
materialorfinishofthe
spacewalling.Thelabelis
usedforroombook
informationandoften
displayedinroomstamp.

Table 15: Recommended additional Space and Zone Attributes


Recommended Space and Zone Attributes are scheduled in specific Templates can be obtained from
www.buildingsmart.org , www.buildingsmart.org.uk.

A.3 Component
Name
Area
IsExternal
Length
Mark
MountingHeight
Structural
Tag
Volume

Value
5.74
false
4627.5
DD1120
1200.0
false
DD1120
0.86

Unit
squaremeters
boolean
millimeters
n/a
millimeters
boolean
n/a
cubicmeters

Description
Area
IsExternal
Length
Mark
MountingHeight
Structural
Tag
Volume

Table 16: Recommended Component Attributes


Recommended Component Attributes are restricted to any distinct quantities or positional information, as
most attributing should be done onto the Components Type or System(s) .
Recommended Component Attributes are scheduled in specific Templates can be obtained from
www.buildingsmart.org , www.buildingsmart.org.uk.

A.4 Type and System


Recommended Type and System Attributes, beyond those on the Type and System sheets, should be
appropriate to the Type and System, and are scheduled in specific Templates which can be obtained from
www.buildingsmart.org , www.buildingsmart.org.uk. www.bimtaskgroup.org/cobie

Name
(various)
2012 AEC3 UK Ltd

Description
SeetemplatespublishedbybuildingSMARTand
buildingSMARTUKandtheUKBIMTaskgroupwebsite
49

July 2012

UK COBie 2.4 Requirements

Table 17: recommended Type and System Attributes

2012 AEC3 UK Ltd

50

July 2012

UK COBie 2.4 Requirements

Annex B: COBie checklist


This checklist combines COBie standard and UK implementation rules.

Uniqueness of information
o Every Attribute Name (column A), taken with Sheet-Name (column E) and RowName (column F) must be unique
o Every System Name (column A) taken with Component-Names (column E)
must be unique
o Every Zone Name (column A) taken with Space-Names (column E) must be
unique
o Elsewhere every Name and Email (column A) must be unique.

Clarity of Naming
o Names must not use commas. Emails must be valid.
o Names should not use punctuation nor unusual characters (for example & % )
o Classifications should use the colon to separate code from description and not
use comma

Integrity of References
o Every reference to other sheets must be valid
o Every reference to enumerations and classifications must be valid

Consistency of Units
o Length, Area and Volume and Currency values must be consistent with the
Facility unit declarations.
o Units must be provided separately from the value for all other numeric
Attributes.

Completeness of the Data


o Every Component shall be assigned to at least one Space
o Every Component shall be assigned to one Type
o Every Component shall be assigned to at least one System
o Every Space shall be assigned to at least one Zone
o There shall be multiple Zones.
o There shall be multiple Systems.
o All required (yellow) and reference (salmon) fields including classification must
be provided.
o Attributes for the Facility, Spaces and Zones must be provided as Annex A
above
o Attributes for the Types must be provided as required in the Type Templates
(www.bimtaskgroup.org/COBie)

Accuracy
o Zero, unset or undefined Values should not be documented in Attributes
o Graphical and stylistic information should not be documented in Attributes
o Attributes should not duplicate information found elsewhere.
o Common Attributes (excluding identification, quantities and location) should be
assigned to
the Type or System, not the Component
the Floor or Zone, not the Space
o Common Documents (excluding condition reports, photographs and
commissioning reports) should be assigned to
the Type or System not the Component
the Floor or Zone not the Space

Continuity
o Use the same names as previous COBie deliverables
o Maintain any External System identifiers (Global Ids or GUIDS)

2012 AEC3 UK Ltd

51

July 2012

UK COBie 2.4 Requirements

Concluded

Commentsandcorrectionsarewelcome.

NicholasNisbetMA(Cantab)DipArch(UNL)
Direct:+44(0)1494714933
Skype:nicholasnisbet

TechnicalCoordinator:buildingSMARTUKChapter
Web:http://www.buildingsmart.org.uk/
Email:nn@buildingSMART.org.uk

2012 AEC3 UK Ltd

52

July 2012