ACS 1000 Training

ACS 1000
Operation

ACS 1000 Operation &


Maintenance

ACS 1000 Training-Rev.C1


ABB Ltd - 1 -

Course G700

ACS 1000
Operation

Starting ACS 1000


Checks before start:

ACS 1000 Training-Rev.C1


ABB Ltd - 2 -

All cabinet doors,


including the protective
separation door and the
control section door are
closed
No alarm or error
message on CDP312
control panel display
No emergency off is
active

Page 1

ACS 1000 Training

ACS 1000
Operation

Starting ACS 1000

Closing the MCB:

ACS 1000 Training-Rev.C1


ABB Ltd - 3 -

ACS 1000
Operation

Switch the grounding


isolator to OPEN position
Press the MAIN CIRCUIT
ONLINE button on the
control section door of
the ACS1000

Starting ACS 1000

Opening / Closing the Ground Switch: The yellow light


Ground switch unlocked must be ON.
Opening the grounding switch: it has to move easily from closed
to open position. (and vice-versa), and to stay in vertical position.

ACS 1000 Training-Rev.C1


ABB Ltd - 4 -

If it does not move easily or if it has the


tendency to turn back, check the proper
closing of the doors of all the MV
cabinets.
If it refuses to move even if the yellow
light Ground switch unlocked is ON,
there might be a problem with the
solenoid or the blocking pin.

Page 2

ACS 1000
Operation

Starting ACS 1000

ACS 1000 Training

Charging the DC Link:

n The CDP312 control panel


displays CHARGING.
Charging of the DC Link
lasts a few seconds

n The ACS1000 is now


ACS 1000 Training-Rev.C1
ABB Ltd - 5 -

READY TO START

ACS 1000
Operation

Starting ACS 1000


Entering Setpoint and
starting up the ACS 1000:

Change the setpoint by


using UP/DOWN keys

ACS 1000 Training-Rev.C1


ABB Ltd - 6 -

To change the setpoint


press REF on the the
CDP312 control panel

Page 3

ACS 1000 Training

ACS 1000
Operation

Starting ACS 1000


Entering Setpoint and
starting up the ACS 1000:

ACS 1000 Training-Rev.C1


ABB Ltd - 7 -

ACS 1000
Operation

Press a ENTER key to exit


the setpoint mode

Select the sense of


rotation using
or
key

Starting ACS 1000


Entering Setpoint and
starting up the ACS 1000:

ACS 1000 Training-Rev.C1


ABB Ltd - 8 -

Start the ACS1000 by


pressing
Magnetazion of the motor
takes place
After a few seconds the
motor speed is ramped up
to the reference speed
The display now indicates
that the motor is running

Page 4

ACS 1000 Training

ACS 1000
Operation

Starting ACS 1000


Stopping the motor

ACS 1000 Training-Rev.C1


ABB Ltd - 9 -

ACS 1000
Operation

Press the STOP key on


the CDP312 control panel
The ACS1000 stops
following the preset stop
function
The MCB remains closed

When zero speed is


reached the display
shows READY TO START

Stopping ACS1000
De-energizing the ACS 1000

ACS 1000 Training-Rev.C1


ABB Ltd - 10 -

Press the main circuit


OFFLINE button on the
control section door
MCB opens and the DC
Link start to discharge
Wait approx. 5 minutes
until DC Link capacitors
are discharged to a safe
level and the light GND.ISOLATOR UNLOCKED is
on

Page 5

ACS 1000 Training

ACS 1000
Operation

Stopping ACS 1000


De-energizing the ACS 1000

Display shows that Earth


isolator is closed

ACS 1000 Training-Rev.C1


ABB Ltd - 11 -

Close the grounding


isolator switch when the
light GND.-ISOLATOR
UNLOCKED is on

CDP312 Control Panel

ACS 1000 Training-Rev.C1


ABB Ltd - 12 -

ACS 1000
Operation

Page 6

ACS 1000 Training

ACS 1000
Operation

CDP312 Control Panel

Control panel mode selections keys


Actual signal display
mode

Parameter mode

ACS 1000 Training-Rev.C1


ABB Ltd - 13 -

Function mode (not used)

Drive selection mode (not


used)

ACS 1000
Operation

CDP312 Control Panel

Actual signal display mode


Act signal/fault history
selection

Act signal/fault message


scrolling

ACS 1000 Training-Rev.C1


ABB Ltd - 14 -

2 displays can be selected in the Act signal display


mode:
Actual signal display
Fault history display

Page 7

ACS 1000 Training

ACS 1000
Operation

CDP312 Control Panel

Parameter mode
Group selection
Fast value change

Parameter selection
Slow value change

ACS 1000 Training-Rev.C1


ABB Ltd - 15 -

Enter change mode


Accept new value
The parameter mode is used to check and change
the ACS 1000 parameters

ACS 1000
Operation

CDP312 Control Panel

Control panel operational keys


Keypad/external control
Fault reset
Setpoint setting function
Forward
Reverse

ACS 1000 Training-Rev.C1


ABB Ltd - 16 -

Start
Stop

Page 8

ACS 1000 Training-Rev.C1


ABB Ltd - 17 -

ACS 1000 Training

Page 9