Professional Documents
Culture Documents
7650-2013
Claimant:
Respondent:
Matter:
Resolution No. 51
Lima, January 29, 2016
SUMMARY: In this case, it has been established
that the "Primary Sulfide Project" is not covered by
the guarantees granted by the Stability Agreement
entered into between the Peruvian State and the
appellant in 1998, since that project was
implemented after concluding the Stability
Agreement. Hence, the Tax Court did not incur a
defect of nullity by issuing the contested RTF (Tax
Court Resolution), which affirms the resolution
rendered by the Tax Administration; thus the
judgment under appeal that declares the Claim
substantiated in part should be reversed and, after
amended, the Claim should be declared
unsubstantiated in every respect.
IN SUM: The Court heard the above cause and examined the four
supporting volumes of the administrative case record; and Mr. Cueva
Chauca drafted the opinion. The judgment rendered by Resolution No. 31,
of December 17, 2014, on page 1065, is a matter of appeal on the point in
which it declares the Claim substantiated in part.
ASSIGNMENT OF ERROR:
SUNAT.- In a brief on page 1104, it appeals the judgment in holding
that the judgment was not on the merits of the proceedings and the law,
because of the following: i) It failed to show cause why it has not
applied the precepts of Article 83 of the Consolidated Uniform Text
(TUO) of the General Mining Law, specifically the fourth paragraph and
also the provisions of Article 22 of the Regulations of Title Nine of that
Law; ii) it is clear that the contractual benefits from concluding a
Stability
Page 1 of 16
Page 2 of 16
included in the Stability Agreement between the Peruvian State and the
claimant; ii) Law No. 30230 does not aim to restrict or limit the benefits to
investors, but quite the opposite, it aims to promote and encourage
investment, which is clear not only from the title of the Law itself, but from
the content therein, as all its provisions seek to promote investment, an
aim that would not be met if benefits are cut back as claimed in the
judgment; iii) it can be discerned from Article 83-B of Law No. 30230 that
this recently-enacted rule provides a broader stability benefit, as it states
that the stability lies not only with activities related to investment, but with
additional investments, provided they are carried out within the same
concession; being that this article did not exist, one must conclude that
before the articles existence, the stability benefit lay solely with the
investment subject of the contract, as was examined in the resolution of
the Tax Court, subject of the Claim; iv) the resolution under appeal
makes it impossible that the State fulfill its purpose of offering
administrative justice and effective protection from the courts; even more
so if one is incorrectly interpreting the tax laws that inform our legal
system.
GROUNDS:
FIRST.- In the case at bar, the claimant submits as the Principal Petition
of its Claim that Tax Court Resolution No. 8252-1-2013 be declared null
and void, by which it was decided to affirm Intendance Resolution No.
055-014-0001394/SUNAT. As its First Accessory Petition: that
Intendance Resolution No. 055-014-0001394/SUNAT be declared totally
null and void, as well as Assessment Resolutions No. 052-003-0005092
through 052-003-0006103, issued in relation to the Mining Royalties for
January-December 2008, and Penalty Resolutions No. 052-002-0004037
through 052-002-0004057. As its Second Accessory Petition: that
SUNAT be ordered i) to reimburse SMCV any sum that the latter may
have paid to the former in performance of the resolutions
Page 3 of 16
Page 4 of 16
investment program that was established against the profits from the
"Cerro Verde Leaching Project"; thus it cannot be argued that the former
was part of the latter, or that it was included in the Stability Agreement
between the Peruvian State and the claimant; while the plaintiff argues
that investment in the original project was just a requirement to accede
to the Stability Agreement and that this is made extensive to all
subsequent investments of the company.
FOURTH.- The claimant bases its petition on the content of the so-called
contract-law and submits, then, that the Mining Royalty Law No. 28258
that was enacted on June 3, 2004, as subsequent to concluding the
Stability Agreement, would not apply it contends to the mining
concession, by having concluded a Stability Agreement before the entry
into force of such law. In this regard, this calls for analyzing the legal
nature of this concept and for this most scholar works favor the thesis of
the contract-law as a civil contract; indeed, Baldo Kresalja notes: "This
thesis has received greater acceptance in the national law. It is based
primarily on the historical interpretation of Article 1357 of the Civil Code and
the choice of the legislature to define the contract-law as a private law
contract, as detailed in the Framework Law for Private Investment Growth,
approved by Legislative Decree 757, with regard to legal Stability
Agreements. It so states that:
The legal Stability Agreements are concluded under Article 1357 of
the Civil Code and have the status of contracts having force of law;
as such they cannot be unilaterally amended or terminated by the
State. Such contracts have a civil and non-administrative nature
and may only be amended or cancelled by agreement between the
parties.
In the same vein, the historical interpretation of Article 1357 of the Civil
Code is said to clarify this controversy; at the same time an important
sector also supports the thesis of the contract-law as
Page 5 of 16
legal nature of the mining royalties regime; in fact, counsel for SUNAT
said in his oral argument, that the Stability Agreement was only limited
to aspects of tax, exchange-rate and administrative nature; and
considering that mining royalties have a content of economic
contribution foreign thus to the Stability Agreement, the Claim becomes
unsubstantiated as the aforementioned agreement did not expressly
cover or shield it for later regulations that have no tax, exchange-rate or
administrative nature; that reasoning is relevant; if proven, analyzing
the terms of the contract and the rules of the General Mining Law and
other related and applicable ones to the case at hand would serve no
purpose; however the multi-judge court does not share this view,
because in having determined that the nature of the contract-law is (at
least evident in this case) administrative in nature, there can be no
doubt that the Mining Royalty Law could not be applied to the present
case because the Law is an administrative contract; thus immunity
would apply to all that the State subsequently issues in exercise of its
"ius imperium" that can directly affect the guaranteed investment.
SIXTH.- In that regard, we must analyze whether or not the new project
already mentioned, is within the scope of the contract-law and with that in
mind, we should in principle set off from the contract itself under the legal
principle or maxim PACTA SUND SERVANDA in the sense that the
contract is law between the parties that have agreed to it and whoever
denies the concurrence of wills expressed therein must prove it; therefore
in this case, after examining the document, one can see that the contract
concluded only applies to the investment of the Cerro Verde Leaching
Project and this follows from the joint interpretation of the clauses
contained therein, which expressly state that the contract concluded
intended to protect the investments that the mining company undertook to
make in that project; in fact Clause One so states: In brief of January 25,
1996, the holder invoking the provisions of Article 82 of the Consolidated
Page 7 of 16
Text of the General Mining Law, Supreme Decree No. 014-92-EM, which
will be called hereinafter "Consolidated Uniform Text," submitted to the
Ministry of Energy and Mines an application to be guaranteed under
contract the benefits set forth in articles 72, 80 and 84 of that legal text,
in regard to the investment in its concession Cerro Verde No. 1, No. 2
and No. 3, hereinafter "the Cerro Verde Leaching Project." Note that
from the beginning the application for benefits expressly asked for such
investment; on the other hand, in 1.3 it was stated that "The objective of
the study is to evaluate the feasibility to expand the production capacity
from 72,000,000 to 105,000,000 pounds (48 MT) of copper cathode per
year from heap leaching of copper ore with 65% recovery, also installing
the necessary equipment to improve the leaching of secondary sulfides
and increasing production." In this section, as can be seen, that
particular investment is also expressly mentioned. Mention is also
made in the contract of the "Development of a new geological model,
part of the basis of the feasibility study, which has created a computer
model of the mining sites of Santa Rosa and Cerro Verde. Estimation of
mineral reserves and two pits, one for Santa Rosa and another for
Cerro Verde that were designed for mined levels on a large scale,
preparation of mining plans, and copper production forecasts are also
listed. Description of all operations for a new treatment capacity,
including those part of the Leaching Project and support facilities, as
well as of the results of the leaching pilot test in secondary sulfur
stockpiles are also included." There is no doubt that in the light of those
contract clauses, the Stability Benefit had been expressly agreed for
such investment.
SEVENTH.- Likewise, one can see that Clause Two states: "On May 6,
1996, by Executive Resolution 158-96-EM/DGM, the General Mining
Page 8 of 16
amendments
or
concerning
numerical
errors,
Page 9 of 16
will commence for a test period of thirty additional days, upon expiry the
General Mining Bureau will decide within sixty days. Under the
responsibility of the General Director, if the observations have not been
remedied by the time limit, the benefits of this contract shall be
automatically suspended; if failure continues for sixty additional days, the
contract shall terminate." Clause Eight reads as follows: "8.1 The term
of the guarantees agreed upon in this contract shall extend for fifteen
years, starting from the fiscal year in which the investment is verified
and the latter shall be approved by the General Mining Bureau." As can
be inferred from such clauses, the parties explicitly indicated the
subject of the contract and therefore submitting the feasibility project for
such investment was not only a requirement for access to the Stability
Benefit as the claimant contends, but the underpinning for approval and
subsequent project development, as expressly stated in the latter."
EIGHTH.- In this regard, it is in principle noteworthy that Article 62 of the
Constitution states in its first paragraph that the freedom to contract
guarantees that the parties will be able to validly agree, in accordance
with the rules in force at the time the contract is executed. Accordingly,
this freedom must respect the limits provided by the law. Baldo Kresalja
and Csar Ochoa argue that "In our view, in principle and with
qualifications, the essential content of the freedom of contract has the
following indications: the right to decide whether to conclude or not a
contract, the right to choose with whom to conclude a contract; the right
to regulate the content of the contracts, i.e., the rights and obligations
of the parties, which in fact constitute the contractual freedom or the
contractual arrangements."2. In this sense, when considering the latter
meaning of the right to freedom of contract, both parties freely
expressed their willingness to enter into a contract and clearly
expressed the content and scope of that contract transaction; thus one
Baldo Kresalja/Csar Ochoa. Derecho Constitucional Econmico. Fondo Edit. PUCP. Page 280
Page 10 of 16
Page 11 of 16
as all its provisions seek to promote investment, an aim that would not be
met if benefits are cut back as claimed in the judgment; in this regard, it
can be discerned from Article 83-B of Law No. 30230 that this recentlyenacted rule provides a broader Stability Benefit, as it states that the
stability lies not only with the activities related to the investment, but
with additional investments, provided they are carried out within the
same concession; being that this article did not exist, one must
conclude that before the article existed, the Stability Benefit lay solely
with the investment subject of the contract, as was examined in the
resolution of the Tax Court, subject of the Claim.
ELEVENTH.- On the other hand, it is noted that the claimant and the
respondents alike support their allegations in various reports, pointing
out the following:
1. In a brief of January 7, 2016, SUNAT submitted the Technical Report,
prepared by Dr. Francisco Javier Ruiz de Castillo Ponce de Len, of
September 11, 2015, which leads from a logical interpretation of Article
83 of the TUO of the General Mining Law to assert that the content of
each tax Stability Agreement comprises a specific investment program;
thus concluding that only the mining activity covered by that program
benefits from the guarantee consisting in the release of the payment of
mining royalties and in that sense, the mining activity relating to the
development of the "Primary Sulfide Project" was subject to the
payment of mining royalties for the period October-December 2006 and
January-December 2007.
2. On January 7, 2016, the company Sociedad Minera Cerro Verde
presented the reports, of Doctors Csar Landa Arroyo and Jorge W.
Pevrano, which indicated that the judgment under appeal properly
focused on the dispute at issue, being consistent between what was
raised by the parties and the final decision, besides its grounds being
Page 12 of 16
sufficiently stated, along with the findings of fact and the conclusions of
law underlying the decision of the court below.
3. On January 7, 2016, the claimant presented the report, issued by Dr.
Csar Garca Novoa, which expounds the vision of the Tax Court on
the legal nature of the Stability Agreements as distorted, carrying a
concept of the Stability Agreements from the unique perspective of
private law. The report also indicates that the literal interpretation that
the State has given to the contract is inaccurate, since the content of
the Stability Agreement is never the initial investment; adding that
given its regulatory nature, commensurate with its status as a
contract-law, the contract should be interpreted not only on the basis
of its text, but mainly through a teleological approach and,
subsequently, by following a principlist hermeneutical tenet.
4. On January 12, 2016 SUNAT presented the Technical Report from
Auditor Efran Flores Torres on the same date; it indicates that the
benefits of stability are defenses to the common legal treatment, the
scope of which should be restricted to the field of objective application,
clearly given by the General Mining Law and its Regulations, and the
terms of the legal Stability Agreements themselves in mining. It further
notes that the described benefits cannot be made extensive to
activities, operations and investments not covered by the subject or
object of such contracts, which are the investment programs and the
feasibility studies; thus concluding that the exploitation of minerals
through the Primary Sulfide Plant, which is an investment not stabilized
by being neither the subject nor the object of the contract signed in
1998, is within the scope of mining royalties.
Page 13 of 16
Page 14 of 16
that declares the Claim substantiated in part should be reversed and, after
amended, the Claim should be declared unsubstantiated; since it stems
from the foregoing, the resolution rendered by the Tax Court did not incur
a defect that under Subsections 1) and 2) of Article 10 of Law No. 27444
entails the declaration of nullity of an administrative decision.
With regard to the Subordinate Petition of the Claim, whereby the
appellant requests that Tax Court Resolution No. 08252-1-2013 be
declared partially null and void in the sense that through Tax Court
Resolution No. 1166 9-1-2013 (an integral part of the first resolution) it
rejects the petition to expand the scope of the proceedings, filed by
Sociedad Minera Cerro Verde against Tax Court Resolution No. 082521-2013, which requested the waiver of interest and penalties as provided
in article 170 of the Tax Code; it should be noted that the review of the
appeal on page 1913 of the administrative record did not lead to that
argument being raised by the applicant during the appeal; being thus
fitting that the above petition be declared inadmissible.
THIRTEENTH.- What has been stated in this resolution is sufficient to
rebut the opinion voiced in the tax report on page 1197, which is
reflected in the requirements of Article 142 of the Consolidated Uniform
Text of the Organic Law of the Judicial Branch. For these reasons, the
Sixth Contentious-Administrative Court Specialized in Tax- and
Customs Matters of the Superior Court of Justice of Lima:
REVERSES the judgment rendered by Resolution No. 31, of December
17, 2014, on page 1065, which declares the Claim substantiated in part
and, AFTER AMENDED, it declares the Claim unsubstantiated with
respect to the principal petition and the accessory petitions; and
inadmissible with respect to the subordinated petition of the Claim. In the
proceedings brought by Sociedad Minera Cerro Verde, against
Page 15 of 16
the Tax Court and the Superintendancy of the National Customs and
Tax Administration, on nullity of administrative resolution.
So Ordered.
ODRIA ODRIA
LVANO VERGARA
CUEVA CHAUCA
BLCCH
Page 16 of 16