You are on page 1of 2

Civil Engineering Measurement. Task 3.

Student id:08042187
Take off list for project: Reinforced Concrete Equipment Platform
No.

Item

Excavation of topsoil

2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25

CESMM3
code
E311

Unit

Note

M3

Taken as only over foundation plan


area (Walls and Columns)

Backfilling of structures to
topsoil
Excavation of foundations

E531

M3

E324

M3

Backfilling to structures
excavated material
Excavation ancillaries,
preparation of excavated
surfaces
Provision of concrete blinding
bed
Placing of concrete blinding bed

E613

M3

Material other than topsoil, rock or


other artificial hard material (walls and
columns)
Both Walls and columns

E522

M3

Both Walls and columns

F224

M2

F511

M2

Formwork rough finish, plane


vertical 0.4-1.22m
Provision of reinforced concrete
foundations
Placing of reinforced concrete
foundations exceeds 500mm
High Yield steel bar
reinforcement 12mm dia
High Yield steel bar
reinforcement 32mm dia
Mild steel bar reinforcement
8mm dia
Provision of reinforced concrete
walls
Placing of reinforced concrete
walls 150mm-300mm
Formwork fair finish to wall
width exceeding 1.22m
Deduct fair finish formwork
Add rough finish formwork
Formwork fair finish to wall,
plane plane vertical not
exceeding 0.4-1.22m
Deduct fair finish work
Add rough finish work
High yield steel bar
reinforcement 12mm dia
High yield steel bar 8mm dia
Provision of concrete design mix
to beams and slabs
Placing of reinforced suspended
concrete slab thickness 300-

G144

M2

F263

M3

Bottom of trench to both walls and


columns
Bottom of trench to both walls and
columns
Rough finish below ground level to
both walls and columns
Designed mix C30, 20mm aggregate

F624

M3

G524

tonne

To walls

G528

tonne

To columns

G512

tonne

To columns

F263

M3

Designed mix C30, 20mm aggregate

F642

M3

Designed mix C30, 20mm aggregate

G245

M2

Fair finish above ground

G245
G145
G244

M2
M2
M2

G244
G144
G524

M2
M2
tonne

G522
F263

tonne
M3

F633

M3

Designed mix C30, 20mm aggregate


For beams the wall thickness must be
deducted

26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43

500mm
Formwork fair finish, plane
horizontal width exceeding
1.22m
Deduct fair finish formwork
Formwork fair finish, plane
vertical width exceeding 1.22m
High yield steel bar
reinforcement bar 32mm dia
High yield steel bar
reinforcement 20mm dia
High yield steel bar
reinforcement 16mm dia
High yield steel bar
reinforcement
Provision of reinforced concrete
to columns
Placing of reinforced concrete
columns are n.e 0.1-0.25m2
Formwork fair finish concrete
components of cross section area
500 x 500 columns
Deduct fair finish formwork
Add rough finish formwork
High yield steel bar
reinforcement 32mm dia
Mild steel bar reinforcement
8mm dia
Deduct backfilling excavated
material
Add excavation ancillaries,
disposal of excavated material
Deduct backfilling to excated
topsoil
Add excavated ancillaries,
disposal of topsoil

G215

M2

Fair finish above ground

G215
G245

M2
M2

Where slab meets bottom of columns


Fair finish above ground

G528

tonne

G526

tonne

G525

tonne

G522

tonne

F263

M3

Designed mix C30, 20mm aggregate

F653

M3

Designed mix C30, 20mm aggregate

G282

M2

Fair finish above ground

G282

M2

G182
G528

M2
tonne

Fair finish above ground less topsoil


depth
Rough finish below ground

G522

tonne

E613

M3

Walls and columns

E532

M3

Walls and columns

E611

M3

Walls and columns

E531

M3

Walls and columns

You might also like