Practice Questions
1. There are five levels of stakeholder engagement. What are they?
a. Unaware, Resistant, Neutral, Supportive, Influencing
b. Aware, Resistant, Neutral, Supportive, Leading
or its outcomes.
b. A group of people or an individual impacted by the projects outcomes or directly
involved with the project.
c. A group of people or an individual directly involved with the project or whose interests may be
impacted by the project, its outcomes, or decisions made during the course of the project by
its stakeholders.
d. A group of people or an individual directly involved with the project or whose interests may
impact the project or its outcomes.
3. The stakeholder classification model (or grid) used in Stakeholder Analysis that is based
a. Salience Model
b. Power/Influence Grid
Power/Involvement Grid
d. Authority/Involvement Model
c.
4. The Stakeholder Register is the only Output of the Identify Stakeholders process. The three
a. Provides a clear and do-able plan for interacting with stakeholders in support of the
projects interests
b. Enables the Project Manager to determine the best approach to take in dealing with a
stakeholder or group of stakeholders
c. Maintains - or possibly even increases - both the efficiency and the effectiveness of
stakeholder engagement activities
d. Helps the Project Manager to increase the support of supportive stakeholders and
minimize resistance of negative stakeholders
7. Understanding how human resource requirements will be met and how staffing
9. There are several Project Documents that may serve as Inputs to the Control Stakeholder
Engagement process. Of those listed below, which group of three do you think would be
serve best as Inputs?
a. Risk Register, Issue Log, Change Log
b. Risk Register, Issue Log, Activity List
10. The
is used by the Project Manager to record the various engagement levels that
would apply to each stakeholder, specifically the current and the desired levels of
engagement.
a. Stakeholder Register
b. Stakeholder Management Plan
Power/Engagement Matrix
d. Stakeholder Engagement Assessment Matrix
c.