You are on page 1of 419

This softawre is based on Standard Data book for analysis of Rates for Road and Bridge

Works
This Software runs on Microsoft Excel
INPUT- Input the usage rates of Plant & Machinery, labour and material as applicable
SUMMARY - In this sheet summary of all the rates analysized is presented
ANALYSIS- The analysis has been presented in 16 nos. of spread sheets
Worksheet- 1 : CHAPTER-1 CARRIAGE OF MATERIALS
Worksheet- 2 : CHAPTER-2 SITE CLEARANCE
Worksheet- 3 : CHAPTER-3 EARTH WORK, EROSION CONTROL AND DRAINAGE
Worksheet- 4 : CHAPTER-4 SUB-BASES, BASES (NON- BITUMINOUS) AND
SHOULDERS
Worksheet- 5 : CHAPTER-5 BASES AND SURFACE COURSES (BITUMINOUS)
Worksheet- 6 : CHAPTER-6 CEMENT CONCRETE PAVEMENTS
Worksheet- 7 : CHAPTER-7 GEOSYNTHETICS AND REINFORCED EARTH
Worksheet- 8 : CHAPTER-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD
APPURTENANCES
Worksheet- 9 : CHAPTER-9 PIPE CULVERTS
Worksheet- 10 : CHAPTER-10 MAINTENANCE OF ROADS
Worksheet- 11 : CHAPTER-11 HORTICULTURE
Worksheet- 12 : CHAPTER-12 FOUNDATIONS
Worksheet- 13 : CHAPTER-13 SUB-STRUCTURE
Worksheet- 14 : CHAPTER-14 SUPER-STRUCTURE
Worksheet- 15 : CHAPTER-15 RIVER TRAINING AND PROTECTION WORKS
Worksheet- 16 : CHAPTER-16 REPAIR AND REHABILITATION

INPUT
(A) Usage Rates of Plant and Machinery

Sl. No.

Description of Machine

Activity

Output of
Machine

Output

Unit

Rate

P&M-001

Air Compressor

General Purpose

capacity in cfm

170/250

hour

293.76

P&M-002

Batching and Mixing Plant (a) 30 cum capacity

Concrete Mixing

cum/hour

20

hour

2598

P&M-003

Batching and Mixing Plant (b) 15 - 20 cum capacity

Concrete Mixing

cum/hour

13

hour

1704.24

P&M-004

Bitumen Pressure Distributor

Applying bitumen tack coat

sqm/hour

1750

hour

986.04

P&M-005

Bitumen Boiler oil fired

Bitumen Spraying

capacity in litre

1500

hour

182.52

P&M-006

Concrete Paver Finisher with 40 HP Motor

Paving of concrete surface

cum / hour

20

hour

2637.36

P&M-007

Concrete Pump of 45 & 30 cum capacity

Pumping of concrete

cum / hour

33 / 22

hour

234.36

P&M-008

Concrete Bucket

For Pouring concrete

capacity in cum

hour

14.472

P&M-009

Concrete Mixer (a) 0.4/0.28 cum

Concrete Mixing

cum/hour

2.5

hour

211.68

P&M-010

Concrete Mixer (b) 1 cum

Concrete Mixing

cum/hour

7.5

hour

218

P&M-011

Crane (a) 80 tonnes

Lifting Purpose

hour

1176.12

P&M-012

Cranes b) 35 tonnes

Lifting Purpose

hour

784.62

P&M-013

Cranes c) 3 tonnes

Lifting Purpose

hour

532

P&M-014

Dozer D - 80 - A 12

Spreading /Cutting / Clearing

cum/hour

300/ 150/250

hour

3135.24

P&M-015

Dozer D - 50 - A 15

Spreading /Cutting / Clearing

cum/hour

200/ 120/150

hour

2028.78

P&M-016

Emulsion Pressure Distributor

Applying emulsion tack coat

sqm/hour

1750

hour

735.48

P&M-017

Front End loader 1 cum bucket capacity

Soil loading / Aggregate loading

cum/hour

60 /25

hour

1116

P&M-018

Generator (a) 125 KVA

Genration of electric Energy

KVA

100

hour

2136

P&M-019

Generator( b) 63 KVA

Genration of electric Energy

KVA

50

hour

361.8

P&M-020

GSB Plant 50 cum

Producing GSB

cum/hour

40

hour

872.64

P&M-021

Hotmix Plant - 120 TPH capacity

DBM/BM/SDC/ Premix

cum/hour

40

hour

40201

P&M-022

Hotmix Plant - 100 TPH capacity

DBM/BM/SDC/ Premix

cum/hour

30

hour

30613

P&M-023

Hotmix Plant - 60 to 90 TPH capacity

DBM/BM/SDC/ Premix

cum/hour

25

hour

25856

P&M-024

Hotmix Plant - 40 to 60 TPH capacity

DBM/BM/SDC/ Premix

cum/hour

17

hour

18155

P&M-025

Hydraulic Chip Spreader

Surface Dressing

sqm/hour

1500

hour

2423.52

P&M-026

Hydraulic Excavator of 1 cum bucket

Soil Ordinary/Soil Marshy / Soil


Unsuitable

cum/hour

60 /60 /60

hour

1516.32

P&M-027

Integrated Stone Crusher 100THP

Crushing of Spalls

TPH

100

hour

7967.16

P&M-028

Integrated Stone Crusher 200 HP

Crushing of Spalls

TPH

200

hour

16760.52

P&M-029

Kerb Casting Machine

Kerb Making

P&M-030

Mastic Cooker

Mastic Wearing coat

P&M-031

Mechanical Broom Hydraulic

P&M-032

Rm/hour

80

hour

279.72

capacity in tonne

hour

54.81

Surface Cleaning

sqm/hour

1250

hour

462

Motor Grader 3.35 mtr blade

Clearing /Spreading /GSB /WBM

cum/hour

200/200/50/50

hour

2488

P&M-033

Mobile slurry seal equipment

Mixing and laying slurry seal

sqm/hour

2700

hour

926.64

P&M-034

Paver Finisher Hydrostatic with sensor control 100


TPH

Paving of DBM/ BM/SDC/ Premix

cum/hour

40

hour

2980

P&M-035

Paver Finisher Mechanical 100 TPH

Paving of WMM /Paving of DLC

cum/hour

40/30

hour

1167

P&M-036

Piling Rig with Bantonite Pump

0.75 m dia to 1.2 m dia Boring


attachment

Rm/hour

2 to 3

hour

5023.08

P&M-037

Pneumatic Road Roller

Rolling of Asphalt Surface

cum/hour

25

hour

1143.72

P&M-038

Pneumatic Sinking Plant

Pneumatic Sinking of wells

cum/hour

1.5 to 2.00

hour

3834

P&M-039

Pot Hole Repair Machine

Repair of potholes

cum/hour

hour

827.28

P&M-040

Prestressing Jack with Pump & access

Stressing of steel wires/stands

hour

116.1

P&M-041

Ripper

Scarifying

cum/hour

60

hour

25.704

P&M-042

Rotavator

Scarifying

cum/hour

25

hour

15.66

P&M-043

Road marking machine

Road marking

Sqm/hour

100

hour

85.86

P&M-044

Smooth Wheeled Roller 8 tonne

Soil Compaction /BM Compaction

cum/hour

70/25

hour

625

P&M-045

Tandem Road Roller

Rolling of Aspalt Surface

cum/hour

30

hour

1051.92

Capacity in cum

5.5

km

22.356

Capacity in cum

5.5

tonne.km

2.6784

Capacity in cum

5.5

hour

830

Transportation of soil, GSB, WMM,


Hotmix etc.
Transportation of soil, GSB, WMM,
Hotmix etc.
Transportation of soil, GSB, WMM,
Hotmix etc.

P&M-046

Tipper - 5 cum

P&M-047

Tipper - 5 cum

P&M-048

Tipper - 5 cum

P&M-049

Transit Mixer 4.0/4.5 cum

Transportation of Concrete Mix to site

cum/hour

4.5

hour

854.55

P&M-050

Transit Mixer 4/4.5 cum

Transportation of Concrete Mix to site

cum/hour

4.5

tonne.km

4.32

P&M-051

Transit Mixer 3.0 cum

Transportation of Concrete Mix to site

cum/hour

hour

784.62

P&M-052

Transit Mixer 3.0 cum

Transportation of Concrete Mix to site

cum/hour

tonne.km

5.886

P&M-053

Tractor

Pulling

capacity in HP

50

hour

171.018

P&M-054

Tractor with Rotovator

Rate of Tractor + Rotevator

hour

227.88

P&M-055

Tractor with Ripper

Rate of Tractor 6+ Ripper

hour

285.12

P&M-056

Truck 5.5 cum per 10 tonnes

Material Transport

capacity/cum

4.5

km

20.088

P&M-057

Truck 5.5 cum per 10 tonnes

Material Transport

capacity/cum

4.5

hour

745

P&M-058

Truck 5.5 cum per 10 tonnes

Material Transport

capacity/cum

4.5

tonne.km

2.268

P&M-059

Vibratory Roller 8 tonne

Earth or soil / GSB / WBM

cum/hour

100/60/60

hour

1642

P&M-060

Water Tanker

Water Transport

capacity in KL

hour

111.24

P&M-061

Water Tanker

Water Transport

capacity in KL

km

22.356

P&M-062

Wet Mix Plant 60 TPH

Wet Mix

cum/hour

25

hour

1107

Sl. No.

Description of Machine

P&M-063

Air compressor with pneumatic chisel attachment for cutting hard clay.

hour

513

P&M-064

Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour

hour

2279.88

P&M-065

Belt conveyor system

hour

Value

P&M-066

Boat to carry atleast 20 persons

hour

142.56

P&M-067

Cement concrete batch mix plant @ 175 cum per hour (effective output)

hour

4787.64

P&M-068

Cement concrete batch mix plant @ 75 cum per hour

hour

2052

P&M-069

Cold milling machine @ 20 cum per hour

hour

855.36

P&M-070

Crane 5 tonne capacity

hour

599.4

P&M-071

Crane 10 tonne capacity

hour

627.48

P&M-072

Crane 15 tonne capacity

hour

770.04

P&M-073

Crane 20 tonne capacity

hour

785.16

P&M-074

Crane 40 T capacity

hour

1166.4

P&M-075

Crane with grab 0.75 cum capacity

hour

1176.12

P&M-076

Compressor with guniting equipment along with accessories

hour

Value

P&M-077

Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour.

hour

1107

P&M-078

Epoxy Injection gun

hour

Value

P&M-079

Generator 33 KVA

hour

342.36

P&M-080

Generator 100 KVA

hour

1600

P&M-081

Generator 250 KVA

hour

2973

P&M-082

Induction, deinduction and erection of plant and equipment including all components and accessories for pneumatic method of well
sinking.

hour

Value

P&M-083

Joint Cutting Machine with 2-3 blades (for rigid pavement)

hour

214.92

P&M-084

Jack for Lifting 40 tonne lifting capacity.

day

758.16

P&M-085

Piling rig Including double acting pile driving hammer (Hydraulic rig)

hrs

5023.08

P&M-086

Plate compactor

hour

142.992

P&M-087

Snow blower equipment 140 HP @ 600 cum per hour

hour

Value

P&M-088

Texturing machine (for rigid pavement)

hour

71.496

Unit

P&M-089

Truck Trailor 30 tonne capacity

hour

1864.08

P&M-090

Truck Trailor 30 tonne capacity

t.km

2.268

P&M-091

Tunnel Boring machine

hour

Value

P&M-092

Vibrating Pile driving hammer complete with power unit and accessories.

hour

Value

P&M-093

Wet Mix Plant 100 TPH

hour

1128.6

P&M-094

Wet Mix Plant 75 TPH

hour

2550

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k lfefr


eq[; vfHk;ark] tkZ foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k


lfefr&lg&eq[; vfHk;ark
xzkeh.k fodkl foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k lfefr


&lg&eq[; vfHk;ark] rduhdh ijh{k.k dks"kkax
eaf=keaMy fuxjkuh foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k


lfefr&lg&vfHk;ark izeq[k
ty lalk/ku foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k


lfefr&lg&vfHk;ark izeq[k
is;ty ,oa LoPNrk foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k


lfefr&lg&vfHk;ark izeq[k]
xzkeh.k dk;Z foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k


lfefr&lg&vfHk;ark izeq[k]
Hkou fuekZ.k foHkkx] >kj[k.M] jkph

la;kstd] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k


lfefr&lg&vfHk;ark izeq[k
iFk fuekZ.k foHkkx] >kj[k.M] jkph

(B) Labour
Sl. No.

Description of Labour

Basic Rate

D.A.

Unit

Rate

L-01

Blacksmith (IInd class)

290.00

16.03

day

306.03

L-02

Blacksmith (Ist class)/ Welder/ Plumber/ Electrician

335.00

18.52

day

353.52

L-03

Blaster (Stone cutter)

290.00

16.03

day

306.03

L-04

Carpenter I Class

335.00

18.52

day

353.52

L-05

Chiseller (Head Mazdoor)

290.00

16.03

day

306.03

L-06

Driller (Jumper)

220.00

12.16

day

232.16

L-07

Diver

220.00

12.16

day

232.16

L-08

Fitter

290.00

16.03

day

306.03

L-09

Mali

220.00

12.11

day

232.11

L-10

Mason (IInd class)

290.00

16.03

day

306.03

L-11

Mason (Ist class)

335.00

18.52

day

353.52

L-12

Mate / Supervisor

220.00

12.16

day

232.16

L-13

Mazdoor

210.00

11.61

day

221.61

L-14

Mazdoor/Dresser (Semi Skilled)

220.00

12.16

day

232.16

L-15

Mazdoor/Dresser/Sinker (Skilled)

290.00

16.03

day

306.03

L-16

Medical Officer

335.00

18.52

day

353.52

L-17

Operator(grouting)

290.00

16.03

day

306.03

L-18

Painter I class

335.00

18.52

day

353.52

L-19

Para medical personnel

day

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k lfefr


eq[; vfHk;ark] tkZ foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k


lfefr&lg&eq[; vfHk;ark
xzkeh.k fodkl foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k lfefr


&lg&eq[; vfHk;ark] rduhdh ijh{k.k dks"kkax
eaf=keaMy fuxjkuh foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k


lfefr&lg&vfHk;ark izeq[k
ty lalk/ku foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k


lfefr&lg&vfHk;ark izeq[k
is;ty ,oa LoPNrk foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k


lfefr&lg&vfHk;ark izeq[k]
xzkeh.k dk;Z foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k


lfefr&lg&vfHk;ark izeq[k]
Hkou fuekZ.k foHkkx] >kj[k.M] jkph

la;kstd] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k


lfefr&lg&vfHk;ark izeq[k
iFk fuekZ.k foHkkx] >kj[k.M] jkph

(C) Materials
Sl. No.

Description

M-001

Stone Boulder of size 150 mm and below at Quarry

cum

573.15

M-002

Supply of quarried stone 150 - 200 mm size for Hand Broken at Quarry

cum

598.32

M-003

Boulder with minimum size of 300 mm for Pitching at Quarry

cum

397.97

M-004

Coarse sand at Quarry (Equivalent to Koliwar sand)

cum

219.18

M-005

Coarse sand at Quarry (Equivalent to Koliwar sand)

cum

219.18

M-006

Fine sand at Quarry

cum

120.42

M-007

Moorum at Quarry

cum

129.74

M-008

Gravel/Quarry spall at Quarry

Cum

370.06

Unit

Rate

M-009

Granular Material or hard murrum for GSB works at Quarry

Cum

166.19

M-010

Granular Material or hard murrum for GSB works at Quarry

Cum

166.19

M-011

Fly ash conforming to IS: 3812 ( Part II & I) at source

0.00

Cum

678.64

Unit

Rate at Plant
(HMP /
Batching)

Rate at
Quarry Site

Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) at Quarry

M-012

Description
M-013

Close graded Granular sub-base Material 53 mm to 9.5 mm at Quarry

cum

816.34

816.34

M-014

Close graded Granular sub-base Material 37.5 mm to 9.5 mm at Quarry

cum

889.63

889.63

M-015

Close graded Granular sub-base Material 26.5 mm to 9.5 mm at Quarry

cum

873.73

873.73

M-016

Close graded Granular sub-base Material 9.5 mm to 4.75 mm at Quarry

cum

773.79

773.79

M-017

Close graded Granular sub-base Material 9.5 mm to 2.36 mm at Quarry

cum

696.99

696.99

M-018

Close graded Granular sub-base Material 4.75mm to 2.36 mm at Quarry

cum

541.04

541.04

M-019

Close graded Granular sub-base Material 4.75mm to 75 micron mm at Quarry

cum

518.01

518.01

M-020

Close graded Granular sub-base Material 2.36 mm at Quarry

cum

449.20

449.20

M-021

Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve at Quarry

cum

259.58

259.58

M-022

Coarse graded Granular sub-base Material 2.36 mm & below at Quarry

cum

288.57

288.57

M-023

Coarse graded Granular sub-base Material 4.75mm to 75 micron mm at Quarry

cum

311.50

311.50

M-024

Coarse graded Granular sub-base Material 4.75 mm to 2.36 mm at Quarry

cum

311.50

311.50

M-025

Coarse graded Granular sub-base Material 9.5 mm to 4.75 mm at Quarry

cum

814.39

814.39

M-026

Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm at Quarry

cum

781.01

781.01

M-027

Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm at Quarry

cum

856.35

856.35

M-028

Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm at Quarry

cum

781.01

781.01

M-029

Coarse graded Granular sub-base Material 53 mm to 26 .5 mm at Quarry

cum

730.36

730.36

M-030

Aggregates below 5.6 mm at Quarry

cum

265.64

265.64

M-031

Aggregates 22.4 mm to 2.36 mm at Quarry

cum

867.97

867.97

M-032

Aggregates 22.4 mm to 5.6 mm at Quarry

cum

838.98

838.98

M-033

Aggregates 45 mm to 2.8 mm at Quarry

cum

695.82

695.82

M-034

Aggregates 45 mm to 22.4 mm at Quarry

cum

793.41

793.41

M-035

Aggregates 53 mm to 2.8 mm at Quarry

cum

692.69

692.69

M-036

Aggregates 53 mm to 22.4 mm at Quarry

cum

615.30

615.30

M-037

Aggregates 63 mm to 2.8 mm at Quarry

cum

783.94

783.94

M-038

Aggregates 63 mm to 45 mm at Quarry

cum

595.10

595.10

M-039

Aggregates 90 mm to 45 mm at Quarry

cum

524.74

524.74

M-040

Aggregates 10 mm to 5 mm at Quarry

cum

770.47

770.47

M-041

Aggregates 11.2 mm to 0.09 mm at Quarry

cum

563.97

563.97

M-042

Aggregates 13.2 mm to 0.09 mm at Quarry

cum

690.16

690.16

M-043

Aggregates 13.2 mm to 5.6 mm at Quarry

cum

701.67

701.67

M-044

Aggregates 13.2 mm to 10 mm at Quarry

cum

988.49

988.49

M-045

Aggregates 20 mm to 10 mm at Quarry

cum

1173.82

1173.82

M-046

Aggregates 25 mm to 10 mm at Quarry

cum

989.57

989.57

M-047

Aggregates 19 mm to 6 mm at Quarry

cum

923.01

923.01

M-048

Aggregates 37.5 mm to 19 mm at Quarry

cum

904.17

904.17

M-049

Aggregates 37.5 mm to 25 mm at Quarry

cum

823.08

823.08

M-050

Aggregates 6 mm nominal size at Quarry

cum

544.84

544.84

M-051

Aggregates 10 mm nominal size at Quarry

cum

723.14

723.14

M-052

Aggregates 13.2/12.5 mm nominal size at Quarry

cum

827.86

827.86

M-053

Aggregates 20 mm nominal size at Quarry

cum

938.92

938.92

M-054

Aggregates 25 mm nominal size at Quarry

cum

938.92

938.92

M-055

Aggregates 40 mm nominal size at Quarry

cum

830.30

830.30

Description

Sl. No.

Unit

Rate

M-056

AC pipe 100 mm dia

metre

50.28

M-057

Acrylic polymer bonding coat

litre

129.48

M-058

Alluminium Paint

litre

193.17

M-059

Aluminium alloy plate 2mm Thick

sqm

1580.88

M-060

Aluminium alloy/galvanised steel

tonne

46239.26

M-061

Aluminium sheeting fixed with encapsulated lens type reflective sheeting including 2% towards lettering, cost of angle iron, cost of
drilling holes, nuts, bolts etc.and signs as applicable

sqm

7902.33

M-062

Road studs 100 x 100 mm fitted with lense reflectors vide clause 804.2 of MORTH (5th Revision)

nos

167.01

M-063

Barbed wire

kg

58.68

M-064

Bearing (Cost of parts)

nos

#VALUE!

M-065

Bearing (Cast steel rocker bearing assembly of 250 tonne )

nos

55883.28

M-066

Bearing (Elastomeric bearing assembly consisting of 7 internal layers of elastomer bonded to 6 nos. internal reinforcing steel
laminates by the process of vulcanisation,)

nos

0.50

M-067

Bearing (Forged steel roller bearing of 250 tonne

nos

37256.21

M-068

Bearing (Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces against
stainless steel mating together with cast steel assemblies/fabricated structural steel assemblies duly painted with all components

nos

31752.36

M-069

Bearing (PTFE sliding plate bearing assembly of 80 tonnes )

nos

#VALUE!

M-070

Bearing (Supply of sliding plate bearing of 80 tonne)

nos

22579.27

M-071

Bentonite

kg

2.24

M-072

Binding wire

kg

62.52

M-073

Bitumen ( Cationic Emulsion ) Ex- Bokaro (M.S) Packed

tonne

35692.44

M-074

Bitumen (VG-30 Grade) Ex- Bokaroi Packed

tonne

32859.22

M-075

Bitumen (VG-10 Grade) Ex- Bokaro Packed

tonne

31938.10

M-076

Bitumen (Cutback ) Ex- Bokaro Packed

tonne

37269.96

M-077

Bitumen (emulsion) Ex- Bokaro (M.S) Packed

tonne

37569.11

M-078

Bitumen (modified graded) Ex - Bokaro (CRMB - 55) Packed

tonne

33812.01

M-079

Brick - 75A

each

4.92

M-080

C.I.shoes for the pile

kg

56.39

M-081

Cement

tonne

5210.53

M-082

Cold twisted bars (HYSD Bars) as per IS:1786-2008

tonne

36191.33

M-083

Coller for joints 300 mm dia

nos

#VALUE!

M-084

Compressible Fibre Board(20mm thick)

sqm

603.53

M-085

Connectors/ Staples

each

#VALUE!

M-086

Copper Plate(12m long x 250mmwide)

M-087

Corrosion resistant Structural steel

M-088

Corrugated sheet, 3 mm thick, "Thrie" beam section railing

(PSC / PPC)
average rate

kg

481.39

tonne

37995.24

kg

37.59

M-089

Credit for excavated rock found suitable for use

cum

102.33

M-090

Curing compound

litre

91.13

M-091

Delineators from ISI certified firm as per the standard drawing given in IRC - 79

each

451.08

M-092

Earth Cost or compensation for earth taken from private land

cum

25.10

M-093

Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab unit conforming
to clause 915.1 of IRC: 83 (part II),

metre

19422.70

M-094

Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each

100 nos

1426.61

M-095

Epoxy compound with accessories for preparing epoxy mortar

kg

282.81

M-096

Epoxy mortar

kg

169.69

M-097

Epoxy primer

kg

9.01

M-098

Epoxy resin-hardner mix for prime coat

kg

481.82

M-099

Flag of red color cloth 600 x 600 mm

each

34.46

M-100

Flowering Plants

each

23.94

M-101

Galvanised MS flat clamp

nos

11.07

M-102

Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of required size.

sqm

73.09

M-103

Galvanised structural steel plate 200 mm wide, 6 mm thick, 24 m long

kg

38.63

M-104

Gelatin 80%

kg

112.77

M-105

Geo grids

sqm

77.51

M-106

Geomembrane

sqm

77.51

M-107

Geonets

sqm

77.51

M-108

Geotextile

sqm

60.75

M-109

Geotextile filter fabric

sqm

60.75

M-110

GI bolt 10 mm Dia

nos

11.07

M-111

Grouting pump with agitator

hour

112.77

M-112

Grass (Doob)

kg

3.04

M-113

Grass (Fine)

kg

3.04

M-114

HDPE pipes 75mm dia

metre

152.45

M-115

HDPE pipes 90mm dia

metre

152.45

M-116

Hedge plants

each

22.80

M-117

Helical pipes 600mm diameter

metre

#VALUE!

M-118

Hot applied thermoplastic compound (Sp. Gravity - 2.10)

litre

127.55

M-119

HTS strand

tonne

62418.78

M-120

Joint Sealant Compound

kg

17.81

M-121

Jute netting, open weave, 2.5 cm square opening for seeding and Mulching

sqm

28.71

M-122

LDO for steam curing

litre

#VALUE!

M-123

M.S. Clamps

nos

24.33

M-124

M.S. Clamps

kg

66.31

M-125

M.S.shoes @ 35 Kg per pile of 15 m

kg

42.08

M-126

Mild Steel bars

tonne

34467.93

M-127

Modular strip/box seal expansion joint including anchorage catering to a horizontal movement beyond 70 mm and upto 140mm
assembly comprising of edge beams, central beam,2 modules chloroprene seal, anchorage elements, support and control system,
all steel sections protected against corrosion and installed by the manufacturer or his authorised representative

metre

21404.46

M-128

Modular strip/box seal expansion joint catering to a horizontal movement beyond 140mm and upto 210mm box/box seal joint
assembly containing 3 modules/cells and comprising of edge beams, two central beams, chloroprene seal, anchorage elements,
support and control system, all steel sections protected against corrosion and installed by the manufacturer or his authorised
representative

M-129

metre

#VALUE!

Nipples 12mm

nos

5.64

M-130

Nuts and bolts

kg

45.42

M-131

Paint

litre

138.35

M-132

Pavement Marking Paint

litre

138.35

M-133

Paving Fabric

sqm

60.75

M-134

Perforated geosynthetic pipe 150 mm dia

metre

65.26

M-135

Perforated pipe of cement concrete, internal dia 100 mm

metre

107.89

M-136

Pesticide

kg

56.39

M-137

Pipes 200 mm dia, 2.5 m long for drainage

metre

124.65

M-138

Plastic sheath, 1.25 mm thick for dowel bars

sqm

10.96

M-139

Plastic tubes 50 cm dia, 1.2 m high

nos

#VALUE!

M-140

Polymer braids

metre

#VALUE!

M-141

Pre moulded Joint filler,25 mm thick for expansion joint.

sqm

708.07

M-142

Pre-coated stone chips of 13.2 mm nominal size

cum

#VALUE!

M-143

Preformed continuous chloroprene elastomer or closed cell foam sealing element with high tear strength, vulcanised in a single
operation for the full length of a joint to ensure water tightness.

metre

#VALUE!

M-144

Pre-moulded asphalt filler board

sqm

708.07

M-145

Pre-packed cement based polymer concrete of strength 45 Mpa at 28 days

kg

#VALUE!

M-146

Primer

kg

90.84

M-147

Quick setting compound

kg

99.20

M-148

Random Rubble Stone

cum

359.72

M-149

RCC Pipe NP 4 heavy duty non presure pipe 1000 mm dia

metre

4395.60

M-150

RCC Pipe NP 4 heavy duty non presure pipe 1200 mm dia

metre

5319.60

M-151

RCC Pipe NP 4 heavy duty non presure pipe 300 mm dia

metre

924.00

M-152

Reflectorising glass beads

kg

70.68

M-153

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Copper Strips)

metre

480.32

M-154

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Galvanised carbon steel strips)

metre

480.32

M-155

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced polymer/fibre reinforced polymer/polymeric
strips)

metre

480.32

M-156

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips)

metre

237.03

M-157

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips)

metre

237.03

M-158

Rivets

each

5.64

M-159

Sand bags (Cost of sand and Empty cement bag)

nos

1.73

M-160

Sapling 2 m high 25 mm dia

each

17.54

M-161

Scrap tyres of size 900 x 20

nos

59.20

M-162

Seeds

kg

21.93

M-163

Selected earth (Including royality @ Rs. 24.0 per cum & compensation @ Rs. 1.10 per cum)

cum

25.10

M-164

Separation Membrane of impermeable plastic sheeting 125 micron thick

sqm

11.00

M-165

Sheathing duct

metre

61.80

M-166

Shrubs

each

11.40

M-167

Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing

cum

528.65

M-168

Sodium vapour lamp

each

679.79

M-169

Square Rubble Coursed Stone

cum

360.24

M-170

Steel circular hollow pole of standard specification for street lighting to mount light at 5 m height above deck level

each

#VALUE!

M-171

Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above road level

each

#VALUE!

M-172

Steel drum 300 mm dia 1.2 m high/empty bitumen drum

nos

90.84

M-173

Steel helmet and cushion block on top of pile head during driving.

kg

51.16

M-174

Steel pipe 25 mm external dia as per

IS:1239

metre

97.11

M-175

Steel pipe 50 mm external dia as per

IS:1239

metre

172.29

M-176

Steel wire rope 20 mm

kg

29.76

M-177

Steel wire rope 40 mm

kg

29.76

M-178

Strip seal expansion join

M-179

Structural Steel

M-180

Super plastisizer admixture IS marked as per 9103-1999

M-181

metre

6043.69

tonne

37995.24

kg

112.77

Synthetic Geogrids as per clause 3102.8 and approved design and specifications.

sqm

85.89

M-182

Through and bond stone

each

6.06

M-183

Tie rods 20mm diameter

nos

47.51

M-184

Tiles size 300 x 300 mm and 25 mm thick

each

23.18

M-185

Timber

cum

31666.24

M-186

Traffic cones with 150 mm reflective sleeve

nos

394.70

M-187

Tube anchorage set complete with bearing plate, permanent wedges etc

M-188

Unstaked lime

M-189

average rate

nos

34.35

tonne

4427.31

Water

KL

167.07

M-190

Water based cement paint

litre

75.18

M-191

Welded steel wire fabric

Kg.

#VALUE!

M-192

Wire mesh 50mm x 50mm size of 3mm wire

kg

30.28

M-193

Wooden ballies 2" Dia for bracing

each

17.81

M-194

Wooden ballies 8" Dia and 9 m long (9 m @ Rs. 43.00/m)

each

49.23

M-195

Wooden packing

cum

#VALUE!

Wooden staff for fastening of flag 25 mm dia, 1.0 m long

each

22.52

VG-30 Grade Bulk Bitumen (Ex-Haldia)

MT

27226.00

M-196
M-074 B

Overheads for Road Works

0.1

Contractors profit for Road Works

0.1
0.25

for input of Overheads or Contractors profit please type in column C as


like below

Overheads for Bridge Works (Rehabilitation)

0.3

Type symble of apostrope(') then input value then one space then
symble of percentage (%) for example '08 %

Contractors profit for Bridge Works

0.1

Overheads for Bridge Works

Lead from Mixing Plant to working site

1 km

Lead for E/W borow area to site

1 km

Lead for fly ash from source to site

1 km

Items No.

Summary of Rates calculated and used for analysis of rates of other items

Unit

Rate

per cm height
per letter

0.50

Item 8.3

Printing new letter and figures of any shade (ii) English Roman

Item 8.8

Painting Two Coats on New Concrete Surfaces

sqm

54.00

Item 8.9

Painting angle iron post two coats

sqm

48.00

Item 12.6 (B)

Cement mortor 1:2 (Excluding OH & CP)

cum

3915.00

Item 12.6 (A)

Cement mortor 1:3 (Excluding OH & CP)

cum

3096.00

Item 12.6 (D)

Cement mortor 1:6 (Excluding OH & CP)

cum

2002.00

Item 12.7 (A )

Course Rubble masonary in cement mortor 1:3 (including OH & CP)

cum

3200.00

Item 12.7 ( B)

Random Rubble masonary in cement mortor 1:6 (including OH & CP)

cum

3093.00

Item 12.8 (A)

PCC Grade M15 including OH & CP for Open Foundation by Mixer

cum

4109.00

Item 12.8 (A)

PCC Grade M15 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

2874.00

Item 12.8 (B)


PCC

PCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

3224.00

Item 12.8 (C)

RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

3242.00

Item 12.8 (C)


RCC

RCC Grade M20 including OH & CP for Open Foundation by Batching Plant

cum

4451.00

Item 12.8 (C)

RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant

cum

3113.00

Item 12.8 (D)

PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

3513.00

Item 12.8 (D)

PCC Grade M25 including OH & CP for Open Foundation by Batching Plant

cum

4829.00

Item 12.8 (D)

PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant

cum

3386.00

Item 12.8 (E)

RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

3534.00

Item 12.8 (E)

RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant

cum

3406.00

Item 12.8 (F)

PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

3544.00

Item 12.8 (F)

PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant

cum

3414.00

Item 12.8 (G)

RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

3551.00

Item 12.8 (G)

RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant

cum

3424.00

RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

3631.00

RCC Grade M35 including OH & CP for Open Foundation by Batching Plant

cum

4962.00

RCC Grade M35 excluding OH & CP for Open Foundation by Batching Plant

cum

3805.00

cum

3694.00

cum

3713.00

cum

3373.00

cum

3889.00

cum

3547.00

cum

3920.00

cum

3580.00

cum

3993.00

cum

5243.00

Item 12.8 (H)


Case I
Item 12.8 (H)
Case II
Item 12.8 (H)
Item 12.8 (H)
Item 12.11 (C) i
Item 12.11 (C) i
Item 12.11 (C)
ii
Item 12.11 (C)
ii
Item 12.11 (C)
iii
Item 12.11 (C)
iii
Item 12.11 (C)
iv
Item 12.11 (C)
iv

RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant
PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Mixer
PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Batching Plant
PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Mixer
PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Batching Plant
PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Mixer
PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Batching Plant
PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Mixer
PCC Grade M35 including OH & CP for Well Foundation (Bottom Plug) by Batching Plant

Item 12.11 (C)


iv
Item 12.11 (F)
iv

PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Batching Plant

cum

3651.00

PCC Grade M35 including OH & CP for Well Foundation (Well Cap) by Batching Plant

cum

4962.00

Item No. 3.13

Excavation for Structures (Manual Means)

cum

224.00

Item No. 3.13

Excavation for Structures (Mechenical Meanse)

cum

44.00

Item 14.1(A)

RCC Grade M20 for super-structure including OH & CP by Batching Plant

cum

5085.00

Item 14.1(B)

RCC Grade M20 for super-structure including OH & CP by Batching Plant

cum

5589.00

Item 14.1(E)

RCC Grade M20 for super-structure including OH & CP by Batching Plant

cum

6404.93

Item 14.1(C)

RCC Grade M30 for super-structure including formwork and excluding OH & CP by Batching Plant

cum

4112.00

Item 14.1(C)

RCC Grade M30 for super-structure excluding formwork and excluding OH & CP by Batching Plant

cum

3426.00

Item 14.2 A

Supplying ,fitting and placing HYSD bar reinforcement in super-structure exncluding OH & CP

tonne

41437.00

Item 13.6

Supplying, fitting and placing HYSD including OH & CP for sub-structure

tonne

55828.00

Item 5.17

Fog Seal

sqm

35.00

Crack Prevention courses. Case-I Stress Absorbing Membrane (SAM) crack width less than 6 mm

sqm

47.00

Crack Prevention courses. Case-II Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm

sqm

57.00

Crack Prevention courses. Case-III Stress Absorbing Membrane (SAM) crack width above 9 mm and
cracked area above 50 %

sqm

75.00

Item 5.21 CaseIV

Crack Prevention courses. Case-IV Bitumen Impregnated Geotextile

sqm

125.00

Item 5.15 CaseI

Slurry Seal Case-I 5 mm thickness

sqm

61.00

Item 5.15 CaseII

Slurry Seal Case-II 3 mm thickness

sqm

43.00

Item 5.15 CaseIII

Slurry Seal Case III 1.5 mm thickness

sqm

26.00

Item 5.9 Case-I

Surface Dressing Case-I 19 mm nominal chipping size

sqm

71.00

Item 5.9 CaseII

Surface Dressing Case-II 13 mm nominal size chipping

sqm

57.00

Item 5.21 CaseI


Item 5.21 CaseII
Item 5.21 CaseIV

draft copy
Sr No

Directly Used Items


Ref. to
MoRTH
Spec.

1.1

Description
Loading and unloading of stone boulder / stone
aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage
and return trip
Unit : cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point
ii) Loading by front end loader 1 cum bucket capacity @
25 cum per hour
iii) Maneuvering, reversing, dumping and turning for
return
iv) Waiting time, unforeseen contingencies etc
Total
a) Machinery
Tipper 5.5 tonnes capacity
Front end-loader 1 cum bucket capacity @ 25 cum/hour

Note
1.4

Annexure - I
Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

1 Min
13 Min
2 Min
4 Min
20 Min
hour
hour

0.330
0.330

b) Overheads @ 0.1 on (a)


c) Contractors profit @ 0.1 on (a+b)
Cost for 5.5 cum = a+b+c
Rate per cum = (a+b+c)/ 5.5
Unloading will be by tipping.
Cost of Haulage Excluding Loading and Unloading

830.00
1116.00

273.90
368.28

P&M-048
P&M-017

64.22
70.64
777.04
141.28
141.00

say

Haulage of materials by tipper excluding cost of loading,


unloading and stacking.
Unit : t.km
Taking output 10 tonnes load and lead 10 km = 100 t.km
1.4(I)

Case I

Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery.
i) Tipper 10 tonne capacity
Time taken for onward haulage with load
Time taken for empty return trip.
b) Overheads @ 0.1 on (a)
c) Contractors profit @ 0.1 on (a+b)
cost for 100 t km = a+b+c
Rate per t.km = (a+b+c)/100

hour
hour

0.400
0.290

830.00
830.00

332.00
240.70
57.27
63.00
692.97
6.93
6.90

P&M-048
P&M-048

830.00
830.00

415.00
273.90
68.89
75.78
833.57
8.34
8.30

P&M-048
P&M-048

say
1.4(II)

Case II

Unsurfaced Gravelled Road


Speed with load : 20 km / hour
Speed for empty return trip : 30 km / hour
a)Machinery
Tipper 10 tonnes capacity
Time taken for onward hanlage with load
Time taken for empty return trip
b) Overheads @ 0.1 on (a)
c) Contractors profit @ 0.1 on (a+b)
Cost for 100 t .km = a+b+c
Rate per t.Km = (a+b+c)/100

hour
hour

0.500
0.330

say
1.4(III)

Case III

Katcha Track and Track in river bed / nallah bed and


choe bed.
Speed with load : 10 km / hour
Speed while returning empty : 15 km / hour
a) Machinery
I) Tipper 10 tonnes capacity
1

draft copy

Directly Used Items


Time taken for onward haulage
Time taken for empty return trip
b) Overheads @ 0.1 on (a)
c) Contractors profit @ 0.1 on (a+b)
Cost for 100 t .km = a+b+c
Rate per t.Km = (a+b+c)/100

Annexure - I
hour
hour

1.000
0.670

830.00
830.00

830.00
556.10
138.61
152.47
1677.18
16.77
16.80

say
1.5

P&M-048
P&M-048

Hand Broken Stone Aggregates 63 mm nominal size


Supply of quarried stone, hand breaking into coarse
aggregate 63 mm nominal size (passing 80 mm and retained
on 50 mm sieve) and stacking as directed
Unit : cum
Taking output = 1 cum
a)

b)

Labour
Mate

day

0.060

232.16

13.93

L-12

Mazdoor

day

1.500

221.61

332.42

L-13

cum

1.100

598.32

658.15

M-002

Material
Supply of quarried stone 150 - 200 mm size

c)

Overheads @ 0.1 on (a+b)

100.45

d)

Contractors profit @ 0.1 on (a+b+c)

110.49

Rate per cum = a+b+c+d

1215.44
say

1.6

Crushing of stone aggregates 13.2 mm nominal size.


Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates of
13 mm nominal size.
Unit : cum
Taking Output = 600 cum at crusher location.
a) Labour
Mate
Mazdoor Skilled
Mazdoor including breaking of any oversize boulder.
b) Material
Stone Boulder of size 150 mm and below
c) Machinery
Integrated stone crusher of 200 TPH including belt
conveyor and vibrating screens
Front end loader 1 cum bucket capacity
Tipper 5.5 cum capacity
d) Overheads @ 0.1 on (a+b+c)
e) Contractors profit @ 0.1 on (a+b+c+d)
Cost for 600 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)*0.95/600
1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 95% of above cost will be attributed to the production of
600 cum of stone chips of 13.2 mm size and balance 5% to
the production of stone dust which comes out as a byproduct.
3. The integrated stone crusher includes primary and
secondary crushing units.
Crushing of stone aggregates 20 mm nominal size
Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates of
20 mm nominal size.
Unit : cum
2

L-12
L-14
L-13

day
day
day

0.760
2.000
17.000

232.16
232.16
221.61

176.44
464.32
3767.37

cum

800.000

573.15

458520.00

M-001

Hour

6.000

16760.52

100563.12

P&M-028

Hour
Hour

20.000
20.000

1116.00
830.00

22320.00
16600.00
60241.13
66265.24
728917.61
1154.12
1154.00

P&M-017
P&M-048

say
Note

1.7

1215.00

draft copy

Directly Used Items


Taking Output = 670 cum at crusher location.
a) Labour
Mate
Mazdoor Skilled
Mazdoor including breaking of any size boulder.
b) Material
Stone Boulder of size 150 mm and below
c) Machinery
Integrated stone crusher of 200 TPH including belt
conveyor and vibrating screens
Front end loader 1 cum bucket capacity
Tipper 5.5 cum capacity
d) Overheads @ 0.1 on (a+b+c)
e) Contractors profit @ 0.1 on (a+b+c+d)
Cost for 670 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)*0.90/670

Annexure - I

0.760
2.000
17.000

232.16
232.16
221.61

176.44
464.32
3767.37

cum

800.000

573.15

458520.00

M-001

Hour

6.000

16760.52

100563.12

P&M-028

Hour
Hour

20.000
20.000

1116.00
830.00

22320.00
16600.00
60241.13
66265.24
728917.61
979.14
979.00

P&M-017
P&M-048

say
Note

1.8

1. 800 cum of stone boulders are needed to get 600 cum of


stone chips of size 20 and 40 mm.
2. 90% of above cost will be attributed to the production of
670 cum of stone aggregates of 20mm size and balance
10% will be for smaller size aggregates and stone dust which
comes out as a by-product.
3. The integrated stone crusher includes primary and
secondary crushing units.
Crushing of stone aggregates 40 mm nominal size
Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates of
40 mm nominal size.
Unit : cum
Taking Output = 750 cum at crusher location.
a) Labour
Mate
Mazdoor Skilled
Mazdoor
b) Material
Stone Boulder of size 150 mm and below
c) Machinery
Integrated stone crusher of 200 TPH including belt
conveyor and vibrating screens
Front end loader 1 cum bucket capacity
Tipper 5.5 cum capacity
d) Overheads @ 0.1 on (a+b+c)
e) Contractors profit @ 0.1 on (a+b+c+d)
Cost for 750 cum = (a+b+c+d+e)x0.85
Rate per cum = (a+b+c+d+e)x0.85/750

5.9

510

1. 800 cum of stone boulders are needed to get 600 cum of


stone chips of size 13.2 mm.
2. 85% of above cost will be attributed to the production of
750 cum of stone aggregates of 40mm size and balance
15% will be for smaller size aggregates and stone dust which
comes out as a by-product.
3. The integrated stone crusher includes primary and
secondary crushing units.
Surface Dressing
Providing and laying surface dressing as wearing course in
single coat using crushed stone aggregates of specified size
on a layer of bituminous binder laid on prepared surface and
rolling with 8-10 tonne smooth wheeled steel roller

L-12
L-14
L-13

day
day
day

0.760
2.000
17.000

232.16
232.16
221.61

176.44
464.32
3767.37

cum

800.000

573.15

458520.00

M-001

Hour

6.000

16760.52

100563.12

P&M-028

Hour
Hour

20.000
20.000

1116.00
830.00

22320.00
16600.00
60241.13
66265.24
619579.97
826.11
826.00

P&M-017
P&M-048

say
Note

L-12
L-14
L-13

day
day
day

draft copy

Directly Used Items

Annexure - I

Unit = sqm
Taking output = 9000 sqm
Case -1:-19 mm nominal chipping size
a) Labour

b)

c)

Mate

day

0.440

232.16

102.15

L-12

Mazdoor

day

9.000

221.61

1994.49

L-13

Mazdoor skilled

day

2.000

306.03

612.06

L-15

Mechanical broom @ 1250 sqm per hour

hour

7.200

462.00

3326.40

P&M-031

Air compressor 250 cfm

hour

7.200

293.76

2115.07

P&M-001

Hydraulic self propelled chip spreader @ 1500 sqm per


hour
Tipper 10 tonne capacity for carriage of stone chips
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity

hour

6.000

2423.52

14541.12

P&M-025

hour

6.000

830.00

4980.00

P&M-048

hour

6.000

1116.00

6696.00

P&M-017

Bitumen pressure distributor

hour

6.000

986.04

5916.24

P&M-004

Smooth wheeled roller 8-10 tonne weight

hour

6.000

625.00

3750.00

P&M-044

tonne

10.800

32859.22

354879.58

M-074

cum

135.000

938.92

126754.20

M-053

Machinery

Material
Bitumen@ 1.20 kg per sqm

d)

Crushed stone chipping,19 mm nominal size @ 0.015


cum per sqm
Overheads @ 0.1 on (a+b+c)

e)

Contractors profit @ 0.1 on (a+b+c+d)

52566.73
57823.40

Cost for 9000 sqm= a+b+c+d+e

636057.44

Rate per sqm = (a+b+c+d+e)/9000

70.67
say

71.00

Case - II13 mm nominal size chipping


a) Labour

b)

c)

Mate

day

0.440

232.16

102.15

L-12

Mazdoor

day

9.000

221.61

1994.49

L-13

Mazdoor skilled

day

2.000

306.03

612.06

L-15

Mechanical broom @ 1250 sqm per hour

hour

7.200

462.00

3326.40

P&M-031

Air compressor 250 cfm

hour

7.200

293.76

2115.07

P&M-001

Hydraulic self propelled chip spreader @ 1500 sqm per


hour
Tipper 10 tonne capacity for carriage of stone chips
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity

hour

6.000

2423.52

14541.12

P&M-025

hour

6.000

830.00

4980.00

P&M-048

hour

6.000

1116.00

6696.00

P&M-017

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

986.04

5916.24

P&M-004

Vibratory roller 8-10 tonne weight

hour

6.000

1642.00

9852.00

P&M-059

tonne

9.000

32859.22

295732.98

M-074

cum

90.000

827.86

74507.40

M-052

Machinery

Material
Bitumen@ 1.00 kg per sqm

d)

Crushed stone chipping,13 mm nominal size @ 0.01


cum per sqm
Overheads @ 0.1 on (a+b+c)

e)

Contractors profit @ 0.1 on (a+b+c+d)

42037.59
46241.35

Cost for 9000 sqm= a+b+c+d+e

508654.85

Rate per sqm = (a+b+c+d+e)/9000

56.52
say

Note

5.15

516

1.Where the proposed aggregate fails to pass the stripping


test, an approved adhesion agent may be added to the
binder as per clause 510.2.4. Alternatively, chips may be precoated as per clause 510.2.5
2.Input for the second coat, where required, will be the
same as per the Ist coat mentioned above
Slurry Seal
4

57.00

draft copy

Directly Used Items

Case I

Annexure - I

Providing andlaying slurry seal consisting of a mixture of fine


aggregates, portland cement filler, bituminous emulsion and
water on a road surface including cleaning of surface,
mixing of slurry seal in a suitable mobile plant, laying and
compacting to provide even riding surface
5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum, weight of mix =
264 tonnes
weight of mix = 176 tonnes
a) Labour

b)

c)

Mate

day

0.240

232.16

55.72

L-12

Mazdoor

day

6.000

221.61

1329.66

L-13

Mechanical broom

hour

6.000

462.00

2772.00

P&M-031

Air compressor 250 cfm

hour

6.000

293.76

1762.56

P&M-001

Mobile slurry seal equipment

hour

6.000

926.64

5559.84

P&M-033

Front end loader 1 cum bucket capacity

hour

6.000

1116.00

6696.00

P&M-017

Tipper 5.5 cum capacity for carriage of aggregate from


stockpile on road side to slurry equipment,bitumen
emulsion and filler.
Pneumatic tyred roller with individual wheel load not
exceeding 1.5 tonnes
Water tanker6 KL capacity

hour

6.000

830.00

4980.00

P&M-048

hour

6.000

1143.72

6862.32

P&M-037

hour

2.000

111.24

222.48

P&M-060

tonne

19.360

37569.11

727337.97

M-077

cum

102.080

219.18

22373.89

M-005

tonne

3.520

4427.31

15584.12

M-188

KL

12.000

167.07

2004.82

M-189

Machinery

Material
Residual Binder @ 11 % of mix 80 x 2.2 x 0.11
Fine aggregate 4.75 mm and below 87 % of total mix,80
x 2.2 x 0.87 = 153.12 tonnes. Taking density1.5,=
153.12/1.5 = 102.08 cum
Filler @ 2 % of total mix = 80 x 2.2 x 0.02
Cost of water

d)

Overheads @ 0.1 on (a+b+c)

e)

Contractors profit @ 0.1 on (a+b+c+d)

79754.14
87729.55

Cost for 16000 sqm= a+b+c+d+e

965025.08

Rate per sqm = (a+b+c+d+e)/16000

60.31
say

Case II

60.00

3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour

b)

c)

Mate

day

0.200

232.16

46.43

L-12

Mazdoor

day

5.000

221.61

1108.05

L-13

Mechanical broom

hour

6.000

462.00

2772.00

P&M-031

Air compressor 250 cfm

hour

6.000

293.76

1762.56

P&M-001

Mobile slurry seal equipment

hour

6.000

926.64

5559.84

P&M-033

Front end loader 1 cum bucket capacity

hour

6.000

1116.00

6696.00

P&M-017

Tipper 5.5 cum capacity for carriage of aggregate from


stockpile on road side to slurry equipment,bitumen
emulsion and filler
Water tanker6 KL capacity

hour

6.000

830.00

4980.00

P&M-048

hour

2.000

111.24

222.48

P&M-060

tonne

17.160

37569.11

644685.93

M-077

cum

74.800

219.18

16394.66

M-005

tonne

2.640

4427.31

11688.09

M-188

Machinery

Material
Residual Binder @ 13 % of mix = 60 x 2.2 x 0.13
Fine aggregate 3 mm and below 85 % of total mix, 60x
2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,
Filler @ 2 % of total mix =60x 2.2 x 0.02
5

draft copy

Directly Used Items


Cost of water

Annexure - I
KL

12.000

167.07

Overheads @ 0.1 on (a+b+c)

69792.09

e)

Contractors profit @ 0.1 on (a+b+c+d)

76771.30

Cost for 30000 sqm= a+b+c+d+e

M-189

844484.25

Rate per sqm = (a+b+c+d+e)/20000

42.22
say

Case III

2004.82

d)

42.00

1.5 mm thickness
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour

b)

c)

Mate

day

0.200

232.16

46.43

L-12

Mazdoor

day

5.000

221.61

1108.05

L-13

Mechanical broom

hour

6.000

462.00

2772.00

P&M-031

Air compressor 250 cfm

hour

6.000

293.76

1762.56

P&M-001

Mobile slurry seal equipment

hour

6.000

926.64

5559.84

P&M-033

Front end loader 1 cum bucket capacity

hour

6.000

1116.00

6696.00

P&M-017

Tipper 5.5 cum capacity for carriage of aggregate from


stockpile on road side to slurry equipment,bitumen
emulsion and filler.
Water tanker6 KL capacity

hour

6.000

830.00

4980.00

P&M-048

hour

2.000

111.24

222.48

P&M-060

tonne

12.670

37569.11

476000.62

M-077

cum

43.300

288.57

12495.08

M-022

tonne

1.580

4427.31

6995.15

M-188

KL

12.000

167.07

2004.82

M-189

Machinery

Material
Residual Binder @ 16 % of mix, 36 x 2.2 x 0.16
Fine aggregate 2.36 mm and below,82 % of total
mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density 1.5
Filler @ 2 % of total mix = 36x 2.2 x 0.02
Cost of water

d)

Overheads @ 0.1 on (a+b+c)

e)

Contractors profit @ 0.1 on (a+b+c+d)

52064.30
57270.73

Cost for 24000 sqm= a+b+c+d+e

629978.07

Rate per sqm = (a+b+c+d+e)/24000

26.25
say

5.17

Note

1.Tack coat, if required to be provided, before laying slurry


seal may be measured and paid separately

518

Fog Spray

26.20

Providing and applying low viscosity bitumen emulsion for


sealing cracks less than 3 mm wide or incipient fretting or
disintegration in an existing bituminous surfacing.
Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

Mate

day

0.120

232.16

27.86

L-12

Mazdoor

day

3.000

221.61

664.83

L-13

hour

6.000

462.00

2772.00

P&M-031

Machinery
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm

c)

hour

6.000

293.76

1762.56

P&M-001

Bitumen emulsion pressure distributor @ 1750 sqm per


hour
Material

tonne

6.000

986.04

5916.24

P&M-004

Bitumenemulsion @ 0.75 kg per sqm

tonne

7.880

37569.11

296044.59

d)

Overheads @ 0.1 on (a+b+c)

e)

Contractors profit @ 0.1 on (a+b+c+d)

30718.81
33790.69

Cost for 10500 sqm= a+b+c+d+e

371697.57

Rate per sqm = (a+b+c+d+e)/10500

35.40
6

M-077

draft copy

Directly Used Items

Annexure - I
say

35.00

1.In case it is decided by the engineer to blind the fog spray,


the following may be added
a) Labour

c)

Mate

day

0.160

232.16

37.15

L-12

Mazdoor for precoating of grit

day

4.000

221.61

886.44

L-13

cum

26.250

311.50

8176.88

M-024

tonne

0.790

37569.11

29679.60

M-077

Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm

c)

Bitumenemulsion for precoating grit @ 2 % of grit,39.38


x 0.02
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3878.01
4265.81

Cost for 10500 sqm = a+b+c+d

46923.87

Rate per sqm = (a+b+c+d)/10500

4.47
say

5.21

522
Case - I

4.50

Crack Prevention Courses


Stress Absorbing Membrane (SAM) crack width less
than 6 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width below 6 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 9 kg per
10 sqm and spreading 5.6 mm crushed stone aggregates @
0.11 cum per 10 sqm with hydraulic chip spreader, sweeping
the surface for uniform spread of aggregates and surface
finished to conform to clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

c)

Mate

day

0.240

232.16

55.72

L-12

Mazdoor

day

6.000

221.61

1329.66

L-13

Mechanical broom @ 1250 sqm per hour

hour

6.000

462.00

2772.00

P&M-031

Air compressor 250 cfm

hour

6.000

293.76

1762.56

P&M-001

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

986.04

5916.24

P&M-004

Hydraulic Chip spreader

hour

6.000

2423.52

14541.12

P&M-025

Smooth wheeled road roller 8-10 tonne

hour

6.000

625.00

3750.00

P&M-044

tonne

9.450

33812.01

319523.49

M-078

cum

105.000

544.84

57208.20

M-050

Machinery

Material
Modified binder
Crushed stone aggregates 5.6 mm size

d)

Overheads @ 0.1 on (a+b+c)

40685.90

e)

Contractors profit @ 0.1 on (a+b+c+d)

44754.49

Cost for 10500 sqm= a+b+c+d+e

492299.38

Rate per sqm = (a+b+c+d+e)/10500

46.89
say

Case - II

Stress Absorbing Membrane (SAM) with crack width 6


mm to 9 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width 6 to 9 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 11 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates
@ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.
7

47.00

draft copy

Directly Used Items

Annexure - I

Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

c)

Mate

day

0.240

232.16

55.72

L-12

Mazdoor

day

6.000

221.61

1329.66

L-13

Mechanical broom @ 1250 sqm per hour

hour

6.000

462.00

2772.00

P&M-031

Air compressor 250 cfem capacity

hour

6.000

293.76

1762.56

P&M-001

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

986.04

5916.24

P&M-004

Hydraulic Chip spreader

hour

6.000

2423.52

14541.12

P&M-025

Smooth wheeled road roller 8-10 tonne

hour

6.000

625.00

3750.00

P&M-044

tonne

11.550

33812.01

390528.72

M-078

cum

105.000

723.14

75929.70

M-051

Machinery

Material
Modified binder
Crushed stone chipping 11.2 mm size

d)

Overheads @ 0.1 on (a+b+c)

e)

Contractors profit @ 0.1 on (a+b+c+d)

49658.57
54624.43

Cost for 10500 sqm= a+b+c+d+e

600868.71

Rate per sqm = (a+b+c+d+e)/10500

57.23
say

Case III

57.00

Stress Absorbing Membrane (SAM) crack width above 9


mm and cracked area above 50 %
Providing and laying a single coatn of a stress absorbing
membrane over a cracked road surface, with crack width
above 9 mm and cracked area above 50 % after cleaning
with a mechanical broom, using modified binder complying
with clause 521, sprayed at the rate of 15 kg per 10 sqm and
spreading 11.2 mm crushed stone aggregates @ 0.12 cum
per 10 sqm, sweeping the surface for uniform spread of
aggregates and surface finished to conform to clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

c)

Mate

day

0.240

232.16

55.72

L-12

Mazdoor

day

6.000

221.61

1329.66

L-13

Mazdoor skilled

day

2.000

306.03

612.06

L-15

Mechanical broom @ 1250 sqm per hour

hour

6.000

462.00

2772.00

P&M-031

Air compressor 250 cfem capacity

hour

6.000

293.76

1762.56

P&M-001

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

986.04

5916.24

P&M-004

Hydraulic Chip spreader

hour

6.000

2423.52

14541.12

P&M-025

Smooth wheeled road roller 8-10 tonne

hour

6.000

625.00

3750.00

P&M-044

tonne

15.750

33812.01

532539.16

M-078

cum

126.000

723.14

91115.64

M-051

Machinery

Material
Modified binder
Crushed stone aggregates 11.2 mm size

d)

Overheads @ 0.1 on (a+b+c)

e)

Contractors profit @ 0.1 on (a+b+c+d)

65439.42
71983.36

Cost for 10500 sqm= a+b+c+d+e

791816.93

Rate per sqm = (a+b+c+d+e)/10500

75.41
say

Case IV

Case - IV : Bitumen Impregnated Geotextile


Providing and laying a bitumen impregnated geotextile layer
after cleaning the road surface, geotextile conforming to
requirements of clause 704.3, laid over a tack coat with 1.05
kg per sqm of paving grade bitumen 80 - 100 penetration and
constructed to the requirement of clause 704.4.5
8

75.00

draft copy

Directly Used Items

Annexure - I

Unit = sqm
Taking output = 3500 sqm
a) Labour

b)

Mate

day

0.560

232.16

130.01

L-12

Mazdoor

day

12.000

221.61

2659.32

L-13

Mazdoor skilled

day

2.000

306.03

612.06

L-15

hour

2.800

462.00

1293.60

P&M-031

Machinery
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfem capacity
Bitumen pressure distributor @ 1750 sqm per hour
Pneumatic roller

c)

hour

2.800

293.76

822.53

P&M-001

tonne

2.000

986.04

1972.08

P&M-004

hour

2.000

1143.72

2287.44

P&M-037

tonne

3.680

31938.10

117532.21

M-075

sqm 3850.000

60.75

233893.61

M-108

Material
Paving grade bitumen of 80 - 100 penetration @ 1.05
kg per sqm
Geotextile including 10 % for overlaps

d)

Overheads @ 0.1 on (a+b+c)

e)

Contractors profit @ 0.1 on (a+b+c+d)

36120.29
39732.31

Cost for 10500 sqm= a+b+c+d+e

437055.45

Rate per sqm = (a+b+c+d+e)/3500

124.87
say

8.3

NOTE

As bitumen overlay construction shallfollow closely the fabric


placement on the same day, an output of 3500 sqm only has
been considered for the analysis which will cover a length of
500 m, of 7 m widecarriagway. This can be conveniently
overlaid by a bitumenious course in a day

801

Printing new letter and figures of any shade


Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade
ii) English and Roman

125.00

Hyphens and the like not to be measured and paid for


Detail for 100 letters of 16 cm height. i.e.1600 cm
Unit = per cm height per letter
a) Labour
Mate

day

0.07

232.16

16.25

L-12

Painter Ist class

day

1.25

353.52

441.90

L-18

Mazdoor

day

0.50

221.61

110.81

L-13

Litre

0.50

138.35

69.18

M-131

b) Material
Paint

63.81

c) Overheads @ 0.1 on (a+b)

70.19

d) Contractors profit @ 0.1 on (a+b+c)


Cost for 1600 cm = a+b+c+d

772.14

Rate per cm height per letter = (a+b+c +d)/1600

0.48
say

8.8

803

0.50

Painting Two Coats on New Concrete Surfaces


Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate

day

0.12

232

27.86

L-12

Painter

day

2.00

354

707.04

L-18

Mazdoor

day

1.00

222

221.61

L-13

b) Material
9

draft copy

Directly Used Items


Paint conforming to requirement of clause 803.3.

Annexure - I
Litre

6.00

138

Add for scaffolding @ 1% of labour cost where required


c) Overheads @ 0.1 on (a+b)

179.49

d) Contractors profit @ 0.1 on (a+b+c)

197.44
2171.87

Rate per sqm = (a+b+c+d)/40

54.30
say

803

M-132

8.30

Cost for 40 sqm = a+b+c+d

8.9

830.12

54.00

Painting on Steel Surfaces


Providing and applying two coats of ready mix paint of
approved brand on steel surface after through cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate

day

0.03

232

6.96

L-12

Painter

day

0.45

354

159.08

L-18

Mazdoor

day

0.25

222

55.40

L-13

Litre

1.25

138

172.94

M-131

b) Material
Paint ready mixed approved brand.
Add @ 1% on cost of material for scaffolding

1.73
39.61

c) Overheads @ 0.1 on (a+b)

43.57

d) Contractors profit @ 0.1 on (a+b+c)


Cost for 10 sqm = a+b+c+d

479.31

Rate per sqm = (a+b+c+d)/10


12.6

47.93

SubCement mortar1:3 (1cement :3 sand)


analysis
(A)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement
Sand
b) Labour
Mate
Mazdoor
Total Material and Labour = (a+b)
SubCement mortar1:2 (1cement :2 sand)
analysis
(B)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement
Sand
b) Labour
Mate
Mazdoor
Total Material and Labour = (a+b)
SubCement mortar1:6 (1cement :6 sand)
analysis
(D)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement
Sand
b) Labour
10

say

48.00

2657.37
230.14

MT
cum

0.51
1.05

5210.53
219.18

day
day

0.04
0.90

232.16
221.61

MT
cum

0.672
0.933

5210.53
219.18

day
day

0.04
0.90

232.16
221.61

MT
cum

0.288
1.337

5210.53
219.18

M-81
M-5

9.29 L-12
199.45 L-13
3096.00

3501.47
204.57

M-81
M-5

9.29 L-12
199.45 L-13
3915.00

1500.63
293.07

M-81
M-5

draft copy

12.7

Directly Used Items

1400

(A)

Mate
Mazdoor
Total Material and Labour = (a+b)
Stone masonry work in cement mortar 1:3 in foundation
complete as drawing and Technical Specification

Annexure - I
day
day

0.04
0.90

232.16
221.61

9.29 L-12
199.45 L-13
2002.00

cum
each

5.50
35.00

360.24
6.06

1981.32
211.97

M-169
M-182

cum

1.50

3096.00

4644.00

Item 12.6
(A)

day
day
day

0.66
7.50
9.00

232.16
353.52
221.61

L-12
L-11
L-13

say

153.23
2651.40
1994.49
2909.10
1454.55
16000.06
3200.01
3200.00

M-148
M-182

Unit = cum
Taking output = 5 cum
Square Rubble Coursed Rubble Masonry (first sort)
a)

Material
Stone
Through and bond stone
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A subanalysis)
b) Labour
Mate
Mason
Mazdoor
c) Overhead charges @ 0.25 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 5 cum = a+b+c+d
Rate per cum (a+b+c+d)/5
1405.3

B) Random Rubble Masonry


( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone
Through and bond stone
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in item 12.6 A)
b) Labour
Mate
Mason
Mazdoor
c) Overheads @ 0.25 on (a+b)
d) Contractors profit @ 0.1 on (a+b+c)
Cost for 5 cum = a+b+c+d
Rate per cum (a+b+c+d)/5

cum
Nos

5.50
35.00

359.72
6.06

1978.45
211.97

cum

1.55

3096.00

4798.80

day
day
day

0.62
6.00
9.00

232.16
353.52
221.61

say

12.7 (Add)

The labour already considered in cement mortar has been


taken into account while proposing labour for masonry works.

1400

Stone masonry work in cement mortar 1:6 in foundation


complete as drawing and Technical Specification

1405.3

Unit = cum
Taking output = 5 cum
B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone
Through and bond stone
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in item 13.6 D)
b) Labour
Mate
Mason
Mazdoor
c) Overheads @ 0.25 on (a+b)
d) Contractors profit @ 0.1 on (a+b+c)
11

143.94 L-12
2121.12
L-11
1994.49 L-13
2812.19
1406.10
15467.06
3093.41
3093.00

cum
Nos

5.50
35.00

359.72
6.06

1978.45
211.97

cum

1.55

280.00

434.00

day
day
day

0.62
6.00
9.00

232.16
353.52
221.61

M-148
M-182

143.94 L-12
2121.12 L-11
1994.49 L-13
1720.99
860.50

draft copy

Directly Used Items

Annexure - I

Cost for 5 cum = a+b+c+d


Rate per cum (a+b+c+d)/5
The labour already considered in cement mortar has been
taken into account while proposing labour for masonry works.

12.8

say

9465.46
1893.09
1893.00

1500, 1700 Plain/Reinforced cement concrete in open foundation


& 2100 complete as per drawing and technical specifications
A

PCC Grade M15


Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 63 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
d) Formwork @ 4% on cost of concrete i.e.cost of material,
labour and machinery
e) Overheads @ 0.25 on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/15

Nedle Vibrator is an item of minor T & P which is already


included in overhead charges. Hence not added in rate
analysis of cement concrete works.
B
PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
C
RCC Grade M20
Unit = cum
Case I Using concrete mixer
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
12

MT
cum
cum
cum
cum

4.13
6.75
8.10
4.05
1.35

5210.53
219.18
830.30
938.92
723.14

21519.47
1479.47
6725.43
3802.63
976.24

day
day
day

0.86
1.50
20.00

232.16
353.52
221.61

199.66
530.28
4432.20

hour
hour

6.00
6.00
2,874.00

211.68
361.80

1270.08
2170.80
1724.25

say

11207.63
5603.81
61641.94
4109.46
4109.00

Note

12.8

12.8

MT
cum
cum
cum
cum

5.16
6.75
5.40
5.40
2.70

5210.53
219.18
830.30
938.92
723.14

26886.32
1479.47
4483.62
5070.17
1952.48

day
day
day

0.86
1.50
20.00

232.16
353.52
221.61

199.66
530.28
4432.20

hour
hour

6.00
6.00
3,224.00

211.68
342.36

1270.08
2054.16

MT
cum
cum
cum

5.21
6.75
8.10
5.40

5210.53
219.18
938.92
723.14

27146.84
1479.47
7605.25
3904.96

day
day

0.86
1.50

232.16
353.52

199.66
530.28

draft copy

Directly Used Items


Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II With Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse Sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 km, L-lead in km
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
d) Formwork @ 4% on cost of concrete i.e.cost of material,
labour and machinery
e) Overheads @ 0.25 on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = ( a+b+c+d+e+f )/120

12.8

Annexure - I
day

20.00

221.61

4432.20

hour
hour

6.00
6.00
3,242.00

211.68
342.36

1270.08
2054.16

MT
cum
cum
cum

41.66
54.00
64.80
43.20

5210.53
219.18
938.92
723.14

217070.53
11835.72
60842.02
31239.65

day
day
day

0.84
3.00
18.00

232.16
353.52
221.61

195.01
1060.56
3988.98

hour
hour
hour
hour
T-km
hour

6.00
6.00
6.00
15.00
300L
6
3,113.00

2598.00
1600.00
1116.00
854.55
4.32
234.36

15588.00
9600.00
6696.00
12818.25
1140.00 L= 1
1406.16
14939.23

say

97105.03
48552.51
534077.65
4450.65
4451.00

PCC Grade M25


Unit = cum
Case I Using concrete Mixer
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II With Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
13

MT
cum
cum
cum
cum

5.99
6.75
5.40
5.40
2.70

5210.53
219.18
830.30
938.92
723.14

31211.05
1479.47
4483.62
5070.17
1952.48

day
day
day

0.86
1.50
20.00

232.16
353.52
221.61

199.66
530.28
4432.20

hour
hour

6.00
6.00
3,513.00

211.68
342.36

1270.08
2054.16

MT
cum
cum
cum
cum

47.95
54.00
43.20
43.20
21.60

5210.53
219.18
830.30
938.92
723.14

249844.74
11835.72
35868.96
40561.34
15619.82

day
day
day

0.84
3.00
18.00

232.16
353.52
221.61

195.01
1060.56
3988.98

draft copy

Directly Used Items


Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
d) Formwork @ 3.75% of cost of concrete i.e.cost of material,
labour and machinery
e) Overheads @ 0.25 on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
cost of 120 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/120

12.8

12.8

Annexure - I
hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2598.00
1600.00
1116.00
854.55
4.32

hour

6
3,386.00

234.36

15588.00
9600.00
6696.00
12818.25
1140.00 L= 1
1406.16
15233.38

say

105364.23
52682.12
579503.28
4829.19
4829.00

RCC Grade M25


Unit = cum
Case I Using concrete Mixer
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II With Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity 1 cum
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
F
PCC Grade M30
Unit = cum
Case I Using Concrete Mixer
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
14

MT
cum
cum
cum

6.05
6.75
8.10
5.40

5210.53
219.18
938.92
723.14

31523.68
1479.47
7605.25
3904.96

day
day
day

0.86
1.50
20.00

232.16
353.52
221.61

199.66
530.28
4432.20

hour
hour

6.00
6.00
3,534.00

211.68
342.36

1270.08
2054.16

MT
cum
cum
cum
Kg

48.38
54.00
64.80
43.20
193.52

5210.53
219.18
938.92
723.14
112.77

252085.26
11835.72
60842.02
31239.65
21823.45

day
day
day

0.84
3.00
18.00

232.16
353.52
221.61

195.01
1060.56
3988.98

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2598.00
1600.00
1116.00
854.55
4.32

hour

6.00
3,586.00

234.36

1406.16

MT
cum
cum
cum
cum

6.08
6.75
5.40
5.40
2.70

5210.53
219.18
830.30
938.92
723.14

31680.00
1479.47
4483.62
5070.17
1952.48

15588.00
9600.00
6696.00
12818.25
1140.00 L= 1

draft copy

Directly Used Items


Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II Using Batching Plant, Transit Mixer and Conrete Pump

12.8

Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
G
RCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
15

Annexure - I
day
day
day

0.86
1.50
20.00

232.16
353.52
221.61

199.66
530.28
4432.20

hour
hour

6.00
6.00
3,544.00

211.68
342.36

1270.08
2054.16

MT
cum
cum
cum
cum

48.60
54.00
43.20
43.20
21.60

5210.53
219.18
830.30
938.92
723.14

253231.58
11835.72
35868.96
40561.34
15619.82

day
day
day

0.84
3.00
18.00

232.16
353.52
221.61

195.01
1060.56
3988.98

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2598.00
1600.00
1116.00
854.55
4.32

hour

6.00
3,414.00

234.36

1406.16

MT
cum
cum
cum

6.10
6.75
8.10
5.40

5210.53
219.18
938.92
723.14

31784.21
1479.47
7605.25
3904.96

day
day
day

0.86
1.50
20.00

232.16
353.52
221.61

199.66
530.28
4432.20

hour
hour

6.00
6.00
3,551.00

211.68
342.36

1270.08
2054.16

MT
cum
cum
cum

48.80
54.00
64.80
43.20

5210.53
219.18
938.92
723.14

254273.68
11835.72
60842.02
31239.65

day
day
day

0.84
3.00
18.00

232.16
353.52
221.61

195.01
1060.56
3988.98

hour
hour
hour
hour

6.00
6.00
6.00
15.00

2598.00
1600.00
1116.00
854.55

15588.00
9600.00
6696.00
12818.25

15588.00
9600.00
6696.00
12818.25
1140.00 L= 1

draft copy

12.8

Directly Used Items


Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
H
RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
d) Formwork @ 3% on cost of concrete i.e.cost of material,
labour and machinery
e) Overheads @ 0.25 on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
cost of 120 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/120

Annexure - I
300L

4.32

hour

6.00
3,424.00

234.36

1406.16

MT
cum
cum
cum

6.33
6.75
8.10
5.40

5210.53
219.18
938.92
723.14

32982.63
1479.47
7605.25
3904.96

day
day
day

0.86
1.50
20.00

232.16
353.52
221.61

199.66
530.28
4432.20

hour
hour

6.00
6.00
3,631.00

211.68
342.36

1270.08
2054.16

MT
cum
cum
cum
Kg

50.64
54.00
64.80
43.20
202.56

5210.53
219.18
938.92
723.14
112.77

263861.05
11835.72
60842.02
31239.65
22842.90

day
day
day

0.84
3.00
18.00

232.16
353.52
221.61

195.01
1060.56
3988.98

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2598.00
1600.00
1116.00
854.55
4.32

hour

6.00
3,694.00

234.36

Note:

12.11

1200, 1500 Plain/Reinforced cement concrete, in well foundation


& 1700 complete as per drawing and technical specification

C
Case I
(i)

Bottom Plug
Concrete to be placed using tremie pipe
Using Concrete Mixer
PCC Grade M20
Unit = cum
16

15588.00
9600.00
6696.00
12818.25
1296.00 L= 1
1406.16
13298.11

say
Rate per cum (a+b+c+d)/120 Excluding OH & CP
Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers @ 0.4% of weight of
cement may be added for achieving desired slump of
concrete.

1296.00 L= 1

T-Km

114142.10
57071.05
627781.57
5231.51
5232.00
3805.00

draft copy

Directly Used Items


Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane 3 tonnes capacity for handling tremie pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Note
10% extra cement may be added where under water
concreting is involved.
Case II Using Batching Plant, Transit Mixer and Crane/concrete
pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
(ii)

Annexure - I

MT
cum
cum
cum
cum
Kg

5.55
6.75
5.40
5.40
2.70
18.60

5210.53
219.18
830.30
938.92
723.14
112.77

28918.42
1479.47
4483.62
5070.17
1952.48
2097.54

day
day
day

0.90
1.50
20.00

232.16
353.52
221.61

208.94
530.28
4432.20

hour
hour
hour

6.00
6.00
6.00

211.68
342.36
532.00

1270.08
2054.16
3192.00

3713.00

MT
cum
cum
cum
Kg

44.40
54.00
64.80
43.20
148.80

5210.53
219.18
938.92
723.14
112.77

231347.37
11835.72
60842.02
31239.65
16780.33

day
day
day

0.88
3.00
18.00

232.16
353.52
221.61

204.30
1060.56
3988.98

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2598.00
1600.00
1116.00
854.55
4.32

hour

6.00
3373.00

234.36

1406.16

MT
cum
cum
cum
cum
Kg

5.99
6.75
5.40
5.40
2.70
21.60

5210.53
219.18
830.30
938.92
723.14
112.77

31211.05
1479.47
4483.62
5070.17
1952.48
2435.85

day
day
day

0.90
1.50
20.00

232.16
353.52
221.61

208.94
530.28
4432.20

hour
hour
hour

6.00
6.00
6.00

211.68
342.36
532.00

1270.08
2054.16
3192.00

15588.00
9600.00
6696.00
12818.25
1296.00 L= 1

PCC Grade M25

Case I

Using Concrete Mixer


Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane of 3 tonnes capacity for handling tremie
pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
17

3889.00

draft copy

Directly Used Items


Using Batching Plant, Transit Mixer and Crane/concrete
pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)

Annexure - I

Case II

MT
cum
cum
cum
Kg

47.88
54.00
64.80
43.20
172.80

5210.53
219.18
938.92
723.14
112.77

249480.00
11835.72
60842.02
31239.65
19486.84

day
day
day

0.88
3.00
18.00

232.16
353.52
221.61

204.30
1060.56
3988.98

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2598.00
1600.00
1116.00
854.55
4.32

hour

6.00
3547.00

234.36

1406.16

MT
cum
cum
cum
cum
Kg

6.08
6.75
5.40
5.40
2.70
21.60

5210.53
219.18
830.30
938.92
723.14
112.77

31680.00
1479.47
4483.62
5070.17
1952.48
2435.85

day
day
day

0.90
1.50
20.00

232.16
353.52
221.61

208.94
530.28
4432.20

hour
hour
hour

6.00
6.00
6.00

211.68
342.36
532.00

1270.08
2054.16
3192.00

15588.00
9600.00
6696.00
12818.25
1296.00 L= 1

(iii)
Case I

PCC Grade M30


Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane of 3 tonnes capacity for handling tremie
pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II Using Batching Plant, Transit Mixer and Crane/concrete
pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer
18

3920.00

MT
cum
cum
cum
Kg

48.64
54.00
64.80
43.20
172.80

5210.53
219.18
938.92
723.14
112.77

253440.00
11835.72
60842.02
31239.65
19486.84

day
day
day

0.88
3.00
18.00

232.16
353.52
221.61

204.30
1060.56
3988.98

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2598.00
1600.00
1116.00
854.55
4.32

15588.00
9600.00
6696.00
12818.25
1296.00 L= 1

draft copy

Directly Used Items


Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
(iv)
PCC Grade M35

Annexure - I
hour

6.00
3580.00

234.36

1406.16

MT
cum
cum
cum
cum
Kg

6.29
6.75
5.40
5.40
2.70
21.60

5210.53
219.18
830.30
938.92
723.14
112.77

32774.21
1479.47
4483.62
5070.17
1952.48
2435.85

day
day
day

0.90
1.50
20.00

232.16
353.52
221.61

208.94
530.28
4432.20

hour
hour
hour

6.00
6.00
6.00

211.68
342.36
532.00

1270.08
2054.16
3192.00

Case I

Using Concrete Mixer


Unit = 1 cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane of 3 tonnes capacity for handling tremie
pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II Using Batching Plant, Transit Mixer and Crane/concrete
pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Add 5% of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreteing with tremie pipe..

3993.00

MT
cum
cum
cum
Kg

50.28
54.00
64.80
43.20
172.80

5210.53
219.18
938.92
723.14
112.77

261985.26
11835.72
60842.02
31239.65
19486.84

day
day
day

0.88
3.00
18.00

232.16
353.52
221.61

204.30
1060.56
3988.98

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2598.00
1600.00
1116.00
854.55
4.32

hour

6.00
3651.00

234.36

1406.16
19532.17

d) Overheads @ 0.25 on (a+b+c)


e) Contractors profit @ 0.1 on (a+b+c+d)
cost of 120 cum = a+b+c+d+e
Rate per cum (a+b+c+d+e)/120
F
iv)
Case II

15588.00
9600.00
6696.00
12818.25
1296.00 L= 1

Say

114394.98
57197.49
629172.36
5243.10
5243.00

5210.53
219.18
938.92

263861.05
11835.72
60842.02

Well cap
RCC Grade M35
Using Batching Plant, Transit Mixer and Conrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate

MT
cum
cum
19

50.64
54.00
64.80

draft copy

Directly Used Items


10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader(capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Formwork @ 3% of (a+b+c)
d) Overheads @ 0.25 on (a+b+c)
e) Contractors profit @ 0.1 on (a+b+c+d)
cost of 120 cum = a+b+c+d+e
Rate per cum (a+b+c+d+e)/120

Annexure - I
cum

43.20

723.14

31239.65

day
day
day

0.84
3.00
18.00

232.16
353.52
221.61

195.01
1060.56
3988.98

hour
hour
hour

6.00
6.00
6.00

2598.00
1600.00
1116.00

15588.00
9600.00
6696.00

hour
T-Km
hour

15.00
300L
6.00

854.55
4.32
234.36

Say

3.13

Note

Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, admixers @ 0.4% of weight of
cement may be added for achieving desired slump of
concrete.

304

Excavation for Structures

12818.25
1296.00 L= 1
1406.16
12612.82
108260.06
54130.03
595430.31
4961.92
4962.00

Earth work in excavation of foundation of structures as per


drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom,
backfilling the excavation earth to the extent required and
utilising the remaning earth locally for road work.
I) Ordinary soil
Unit = cum
Taking output = 10 cum
A

Manual Means
(i) Depth upto 3 m
a) Labour
Mate

day

0.320

232.16

74.29

L-12

Mazdoor

day

8.000

221.61

1772.88

L-13

b) Overheads @ 0.1 on (a)

184.72

c) Contractors profit @ 0.1 on (a+b)

203.19

Cost for 10 cum = a+b+c

2235.08

Rate per cum = (a+b+c)/10

223.51
say

Note

224.00

Cost of dewatering may be added where required upto 10 %


of labour cost Assessment for dewatering shall be made as
per site conditions..
Mechanical Means
(i) Depth upto 3 m
Unit = cum
Taking output = 300 cum
a) Labour
Mate
Mazdoor

day

0.32

232

74.29

day

8.00

222

1772.88

hour

6.00

1516

9097.92

b) Machinery
Hydraulic excavator 1.0 cum bucket capacity
c) Overheads @ 0.1 on (a+b)

1094.51

d) Contractors profit @ 0.1 on (a+b+c)

1203.96

Cost for 300 cum = a+b+c+d

13243.56
20

draft copy

Directly Used Items

Annexure - I

Rate per cum = (a+b+c+d)/300

13.6

14.1

44.15

Note

Cost of dewatering upto 5% of (a+b) may be added, where


required. Assessment for dewatering shall be made as per
site conditions..

Section
1600 &
2200

Supplying, fitting and placing HYSD bar reinforcement in


sub-structure complete as per drawing and technical
specifications
Output : MT
Taking output = 1 MT
a) Material
HYSD bars including 5% overlaps and wastage
Binding wire
b) Labour for cutting, bending, shifting to site, tying and
placing in position
Mate
Blacksmith
Mazdoor
c) Overheads @ 0.25 on (a+b)
d) Contractors profit @ 0.1 on (a+b+c)
Rate for per MT (a+b+c+d)

1500
&1600
1700
A
Case II

44.00

MT
kg

1.05
6.00

36191.33
63.00

38000.90
378.00

day
day
day

0.34
2.00
6.50

232.16
353.52
221.61

say

78.93
707.04
1440.47
10151.33
5075.67
55832.34
55832.00

Furnishing and Placing Reinforced/Prestressed cement


concrete in super-structure as per drawing and
Technical Specification
RCC Grade M20
Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum
(i)
(p)

say

For solid slab super-structure, 20-30% of (a+b+c)


Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120
cum
d) Formwork and staging 20 % of (a+b+c)
e) Overheads @ 0.25 on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/120

MT
cum
cum
cum

40.92
54.00
64.80
43.20

5210.53
219.18
938.92
723.14

213214.74
11835.72
60842.02
31239.65

day
day
day

0.84
3.00
18.00

232.16
353.52
221.61

195.01
1060.56
3988.98

hour
hour
hour

6.00
6.00
6.00

2598.00
1600.00
1116.00

15588.00
9600.00
6696.00

hour
T-Km
hour

15.00
300L
6.00
369782.00

854.55
4.32
234.36

369782.00
20.00

say
B
Case II

RCC Grade M25


Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
21

12818.25
1296.00 L= 1
1406.16

73956.40
110934.60
55467.30
610140.30
5084.50
5085.00

draft copy

Directly Used Items


a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum
For formwork and staging add the following:
(i)
(p)

Annexure - I
MT
cum
cum
cum

47.95
54.20
64.80
43.20

5210.53
219.18
938.92
723.14

249844.74
11879.56
60842.02
31239.65

day
day
day

0.84
3.00
18.00

232.16
353.52
221.61

195.01
1060.56
3988.98

hour
hour
hour

6.00
6.00
6.00

2598.00
1600.00
1116.00

15588.00
9600.00
6696.00

hour
T-Km
hour

15.00
300L
6.00
406455.00

854.55
4.32
234.36

For solid slab super-structure, 20-30% of (a+b+c)


Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c)
120 cum
d) Formwork and staging 20 % of (a+b+c)
e)

Overheads @ 0.25 on (a+b+c+d)

f)

Contractors profit @ 0.1 on (a+b+c+d+e)

for

406455.00
20.00

81291.00
121936.50
60968.25

Cost for 15 cum= a+b+c+d+e+f

670650.75

Rate per cum (a+b+c+d+e+f)/120

C
Case II

5588.76
say

5589.00

RCC Grade M 30
Using Batching Plant, Transit Mixer and Concrete Pump.

Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum
For formwork and staging add the following:
(i)
(p)

12818.25
1296.00 L= 1
1406.16

For solid slab super-structure, 20-30% of (a+b+c)


Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120
cum
d) Formwork and staging 20 % of (a+b+c)
e) Overheads @ 0.25 on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f
22

MT
cum
cum
cum

48.79
54.60
64.80
43.20

5210.53
219.18
938.92
723.14

254221.58
11967.23
60842.02
31239.65

day
day
day

0.88
3.00
19.00

232.16
353.52
221.61

204.30
1060.56
4210.59

hour
hour
hour

6.00
6.00
6.00

2598.00
1600.00
1116.00

15588.00
9600.00
6696.00

hour
T-Km
hour

15.00
300L
6.00
411151.00

854.55
4.32
234.36

12818.25
1296.00 L= 1
1406.16

411151.00
20.00

82230.20
123345.30
61672.65
678399.15

draft copy

Directly Used Items

Annexure - I

Rate per cum (a+b+c+d+e+f)/120


say
Rate per cum (a+b+c+d)/120 ( including formwork and excluding OH & CP)
Rate per cum (a+b+c+d)/120 ( excluding formwork and Excluding OH & CP)

PSC Grade M-40


Using concret mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixture @ 0.4% of cement
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Basic Cost of Labour, Material & Mechinery (a+b+c) for 15 cum

5653.33
5653.00
4112.00
3426.00

E
Case 1

Case II

(p)

6.45
6.75
8.10
5.40
25.80

5210.53
219.18
938.92
723.14
112.77

33607.89
1479.47
7605.25
3904.96
2909.49

day
day
day

0.96
2.00
22.00

232.16
353.52
221.61

222.87
707.04
4875.42

hour
hour

6.00
6.00
58637.00

211.68
342.36

1270.08
2054.16

MT
cum
cum
cum
kg
Kg

51.60
54.00
64.80
43.20
206.40
216.00

5210.53
219.18
938.92
723.14
112.77
112.77

268863.16
11835.72
60842.02
31239.65
23275.94
24358.55

day
day
day

0.94
3.50
20.00

232.16
353.52
221.61

218.23
1237.32
4432.20

hour
hour
hour

6.00
6.00
6.00

2598.00
1600.00
1116.00

15588.00
9600.00
6696.00

hour
T-Km
hour

15.00
300L
6.00
473708.00

854.55
4.32
234.36

Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixture @ 0.4% of cement
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum
For formwork and staging add the following:
(i)

MT
cum
cum
cum
kg

12818.25
1296.00 L= 1
1406.16

For solid slab super-structure, 18-28% of (a+b+c)


Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c)
120 cum
d) Formwork and staging 18 % of (a+b+c)
e)

Overheads @ 0.25 on (a+b+c+d)

f)

Contractors profit @ 0.1 on (a+b+c+d+e)

for

473708.00
18.00

85267.44
139743.86
69871.93

Cost for 15 cum= a+b+c+d+e+f

768591.23

Rate per cum (a+b+c+d+e+f)/120

6404.93
say

23

6405.00

draft copy

Directly Used Items


Note

14.2

1600

1.Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, admixers conforming IS: 9103
@ 0.4% of weight of cement may be added for achieving
desired slump of concrete.
2. Cement provided for various components of the super
structure is for estimating purpose only. Actual quantity of
cement will be as per approved mix design. Similarly, the
provision for coarse and fine aggregates is for estimating
purpose and the exact quantity shall be as per the mix
design.
3. The items like needle and surface vibrators are part of
minor T & P which is already covered under the overhead
charges. As such these items have not been added
seperately in the rate analysis.
A) Supplying ,fitting and placing HYSD bar
reinforcement in super-structure complete as per
drawing and technical specifications
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including 5% for laps and wastage
Binding wire
b) Labour for cutting, bending, tying and placing in position

Mate
Blacksmith
Mazdoor
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)

24

Annexure - I

MT
Kg

1.05
8.00

36191.33
62.52

38000.90
500.16

day
day
day

0.44
3.00
8.00
41437.00

232.16
353.52
221.61

102.15
1060.56
1772.88

CHAPTER-1

CARRIAGE OF MATERIALS
Item No.

1.1

1.2
1.3
1.4
(i)
(ii)
(iii)

Descriptions

Unit

Rate (in Rs.)

Loading and unloading of stone boulder / stone aggregates / sand / kanker /Earth/
moorum. (Placing tipper at loading point, loading with front end loader, dumping,
turning for return trip, excluding time for haulage and return trip)

cum

141.00

Loading and Unloading of Boulders by Manual Means

cum

179.00

tonne

236.00

Surfaced Road

tonne.km

6.90

Unsurfaced Gravelled Road

tonne.km

8.30

Katcha Track and Track in river bed / nallah bed and choe bed.

tonne.km

16.80

Loading and Unloading of Cement, Steel ,Bitumen,Hume Pipe (NP4) by Manual Means
and stacking.
Cost of Haulage Excluding Loading and Unloading

25

CHAPTER-2

SITE CLEARANCE
Item No.
2.1

Descriptions

Unit

Rate (in Rs.)

Cutting of Trees, including Cutting of Trunks, Branches and Removal (Cutting of trees, including
cutting of trunks, branches and removal of stumps, roots, stacking of serviceable material with
all lifts and up to a lead of 1000 mtrs and earth filling in the depression/pit.)

(i)

Girth from 300 mm to 600 mm

each

187.00

(ii)

Girth from 600 mm to 900 mm

each

315.00

(iii)

Girth from 900 mm to 1800 mm

each

642.00

each

1242.00

hectare

13969.00

In area of light jungle

hectare

42115.00

In area of thorny jungle

hectare

56291.00

In area of light jungle

hectare

39261.00

In area of thorny jungle

hectare

47510.00

(iv)

Girth above 1800 mm

2.2

Clearing Grass and Removal of Rubbish

2.3

Clearing and Grubbing Road Land .(Clearing and grubbing road land including uprooting rank
vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of
trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to
be used or auctioned up to a lead of 1000 metres including removal and disposal of top organic
soil not exceeding 150 mm in thickness.)

(i)
A
B
(ii)
A
B
2.4

(i)

By Manual Means:-

By Mechanical Means

Dismantling of Structures (Dismantling of existing structures like culverts, bridges, retaining


walls and other structure comprising of masonry, cement concrete, wood work, steel work,
including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable material with all lifts and lead of 1000
metres)
Lime /Cement Concrete

By Manual Means

Lime Concrete, cement concrete grade M-10 and below

cum

268.00

Cement Concrete Grade M-15 & M-20

cum

324.00

Prestressed / Reinforced cement concrete grade M-20 & above

cum

915.00

II

By Mechanical Means for items No. 202( b) & ( c)

Cement Concrete Grade M-15 & M-20

cum

350.00

Prestressed / Reinforced cement concrete grade M-20 & above

cum

628.00

(ii)

Dismantling Brick / Tile work

In lime mortar

cum

156.00

In cement mortar

cum

212.00

In mud mortar

cum

134.00

Dry brick pitching or brick soling

cum

123.00

(iii)

Dismantling Stone Masonry

Rubble stone masonry in lime mortar

cum

179.00

Rubble stone masonry in cement mortar.

cum

212.00

Rubble Stone Masonry in mud mortar.

cum

156.00

Dry rubble masonry

cum

145.00

Dismantling stone pitching/ dry stone spalls.

cum

134.00

Dismantling boulders laid in wire crates including opening of crates and stacking dismantled
materials.

cum

156.00

26

(iv)
(v)

Wood work wrought framed and fixed in frames of trusses upto a height of 5 m above plinth
level
Steel work in all types of sections upto a height of 5 m above plinth level excluding cutting of
rivet.

cum

444.00

Including dismembering

tonne

1201.00

Excluding dismembering.

tonne

867.00

Extra over item No( V ) A and( V ) B for cutting rivets.

tonne

9.30

C
(vi)
A
B
(vii)

Scraping of bricks dismantled from brick work including stacking.


1000
numbers
1000
numbers

In lime/Cement mortar
In mud mortar

978.00
349.00

Scraping of Stone from dismantled stone masonry

In cement and lime mortar

cum

In Mud mortar

cum
sqm

Scarping plaster in lime or cement mortar from brick/ stone masonry


Removing all type of hume pipes and stacking within a lead of 1000 metres including earthwork
and dismantling of masonry works.
Up to 600 mm dia

metre

Above 600 mm to 900 mm dia

metre

metre

Above 900 mm
Dismantling of Flexible Pavements (Dismantling of flexible pavements and disposal of
dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable
materials separately)
By Manual Means

Bituminous courses

cum

Granular courses

cum

498.00
348.00

cum

168.00

cum

981.00

metre

52.00

(viii)
(ix)

2.5

II
A
2.6

2.7

392.00
83.00
11.80

145.00
196.00
336.00

By Mechanical Means
Bituminous course
Dismantling of Cement Concrete Pavement (Dismantling of cement concrete pavement by
mechanical means using pneumatic tools, breaking to pieces not exceeding 0.02 cum in volume
and stock piling at designated locations and disposal of dismantled materials up to a lead of
1000 metres, stacking serviceable and unserviceable materials separately)
Dismantling Guard Rails (Dismantling guard rails by manual means and disposal of dismantled
material with all lifts and up to a lead of 1000 metres, stacking serviceable materials and
unserviceable materials separately.)

2.8

Dismantling Kerb Stone (Dismantling kerb stone by manual means and disposal of dismantled
material with all lifts and up to a lead of 1000 metre)

metre

8.00

2.9

Dismantling Kerb Stone channel (Dismantling kerb stone channel by manual means and disposal
of dismantled material with all lifts and up to a lead of 1000 metre)

metre

13.00

2.10

Dismantling Kilometre Stone (Dismantling of kilometre stone including cutting of earth,


foundation and disposal of dismantled material with all lifts and lead upto 1000 m and back
filling of pit.)
5th KM stone

each

Ordinary KM Stone

each

Hectometre Stone
Dismantling of Fencing (Dismantling of barbed wire fencing/ wire mesh fencing including posts,
foundation concrete, back filling of pit by manual means including disposal of dismantled
material with all lifts and up to a lead of 1000 metres, stacking serviceable material and
unserviceable material separately. )

each

269.00
160.00
32.10

metre

39.90

Dismantling of CI Water Pipe Line (Dismantling of CI water pipe line 600 mm dia including
disposal with all lifts and lead upto 1000 metres and stacking of serviceable material and
unserviceable material separately under supervision of concerned department)

metre

122.00

Removal of Cement Concrete Pipe of Sewer Gutter (Removal of cement concrete pipe of sewer
gutter 1500 mm dia under the supervision of concerned department including disposal with all
lifts and up to a lead of 1000 metres and stacking of serviceable and unserviceable material
separately but excluding earth excavation and dismantling of masonry works.)

metre

182.00

Removal of Telephone / Electric Poles and Lines (Removal of telephone / Electric poles including
excavation and dismantling of foundation concrete and lines under the supervision of concerned
department, disposal with all lifts and up to a lead of 1000 metres and stacking the serviceable
and unserviceable material separately)

each

133.00

2.11

2.12

2.13

2.14

27

CHAPTER-3

EARTH WORK, EROSION CONTROL AND DRAINAGE


Item No.

Descriptions

Unit

Rate (in Rs.)

3.1

Excavation in Soil by Manual Means. (Excavation for roadway in soil using manual means
including loading in truck for carrying of cut earth to embankment site with all lifts and lead
upto1000 metres.)

(i)

Including Royalty @ Rs. 30.0 per cum but excluding the cost of watering, rolling &
compaction

cum

210.00

Including Royalty @ Rs. 30.0 per cum , cost of watering, rolling & compaction

cum

222.00

In case there is a situation where the cross-section is of cut and fill and cut earth is required to
be used in embankment in the immediate vicinity, the item of carriage in the truck shall be
omitted. inclunding Royalty @ Rs. 30.00 per cum.

cum

129.00

Excavation in ordinary rock by manual means (Excavation in ordinary rock using manual means
including loading in a truck and carrying of excavated material to embankment site with in all
lifts and leads upto 1000 metres ) including Royalty @ Rs. 24.00 per cum but excluding cost of
watering , rolling & compaction

cum

268.00

Excavation in ordinary rock using manual means including loading in a truck and
carrying of excavated material to embankment site with in all lifts and leads upto 1000
metres including Royalty @ Rs. 30.00 per cum, cost of watering , rolling & compaction

cum

281.00

In case there is a situation where the cross-section is of cut and fill and cut earth is
required to be used in embankment in the immediate vicinity, the item of carriage in the
truck shall be omitted - inclunding Royalty @ Rs. 30.00 per cum.

cum

187.00

Excavation in Soil with Dozer with lead upto 100 metres (Excavation for road way in soil by
mechanical means including cutting and pushing the earth to site of embankment upto a
distance of 100 metres (average lead50 metres), including trimming bottom and side slopes in
accordance with requirements of lines, grades and cross sections.)

cum

130.00

Excavation in Ordinary Rock with Dozer with lead upto 100 metres (Excavation for roadway in
ordinary rock by deploying a dozer, 80 HP including cutting and pushing the cut earth to site of
embankment upto a distance of 100 metres ( average lead 50 metres ), trimming bottom and
side slopes in accordance with the requirements of lines, grades and cross sections.)

cum

219.00

cum

265.00

Including Royalty @ Rs. 30.00 per cum but excluding the cost of watering, rolling &
compaction.

cum

107.00

Including Royalty @ Rs. 30.00 per cum, cost of watering, rolling & compaction.

cum

122.00

(ii)
Note

3.2 (i)

(ii)

Note

3.3

3.4

3.5

3.6

(i)
(ii)

Excavation in Hard Rock (requiring blasting) with disposal upto 1000 metres (Excavation for
roadway in hard rock (requiring blasting) by drilling, blasting and breaking, trimming of
bottom and side slopes in accordance with requirements of lines, grades and cross sections,
loading and disposal of cut road with in all lifts and leads upto 1000 metres )
Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with disposal upto 1000 metres.
(Excavation for roadwork in soil with hydraulic excavator of0.9 cum bucket capacity including
cutting and loading in tippers, trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and transporting to the embankment location
within all lifts and lead upto 1000m)

3.7

Excavation in Ordinary Rockusing Hydraulic ExcavatorCK-90 and Tippers with disposal upto
1000 metres. (Excavation for roadway in ordinary rock with hydraulic excavator of 0.9 cum
bucket capacity including cutting and loading in tippers, transporting to embankment site within
all lifts and lead upto 1000 m, trimming bottom and side slopes in accordance with
requirements of lines, grades and cross sections.)

(i)

Including Royalty @ Rs. 30.00 per cum but excluding the cost of watering, rolling &
compaction.

cum

124.00

Including Royalty @ Rs. 30.00 per cum, cost of watering, rolling & compaction.

cum

137.00

Excavation in Hard Rock (blasting prohibited) (Excavation for roadway in hard rock (blasting
prohibited) with rock breakers including breaking rock, loading in tippers and disposal within
all lifts and lead upto 1000 metres, trimming bottom and side slopes in accordance with
requirements of lines, grades and cross sections.)
Mechanised

cum

Manual Method

cum

503.00
999.00

(ii)
3.8

28

3.9

Excavation in Hard Rock (controlled blasting) with disposal upto 1000 metres (Excavation for
roadway in hard rock with controlled blasting by drilling, blasting and breaking, trimming of
bottom and side slopes in accordance with requirements of lines, grades and cross sections,
loading and disposal of cut road with in all lifts and leads upto 1000 metres )

cum

337.00

3.10

Excavation in Marshy Soil (Excavation for roadway in marshy soil with hydraulic excavator 0.9
cum bucket capacity including cutting and loading in tippers and disposal with in all lifts and
lead upto 1000 metres, trimming of bottom and side slopes in accordance with requirements of
lines, grades and cross sections.)

(i)

Including Royalty @ Rs. 30.00 per cum but excluding the cost of watering, rolling &
compaction.

cum

114.00

Including Royalty @ Rs. 30.00 per cum, cost of watering, rolling & compaction.

cum

127.00

cum

78.00

sqm

136.00

224.00
44.00

(ii)
3.11

3.12

3.13

Removal of Unserviceable Soil with Disposal upto 1000 metres (Removal of unserviceable soil
including excavation, loading and disposal upto 1000 metres lead but excluding replacement by
suitable soil which shall be paid separately as per clause 305.)
Pre-splitting of Rock Excavation Slopes (Carrying out excavation in hard rock to achieve a
specified slope of the rock face by controlled use of explosives and blasting accessories in
properly aligned and spaced drill holes, collection of the excavated rock by a 80 HP dozer,
loading in tipper by a front end loader and disposing of the material with all lifts and lead upto
1000 m, all as specified in clause No. 303)
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing
and technical specification, including setting out, construction of shoring and bracing, removal
of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation
earth to the extent required and utilising the remaining earth locally for road work.)

(i)

Ordinary soil

Manual Means (Depth upto 3 m)

cum

Mechanical Means (Depth upto 3 m)

cum

(ii)
A
B
(iii)
A
(iv)
A
(v)

Ordinary rock (not requiring blasting)


Manual Means (Depth upto 3 m)

cum

279.00
59.00

cum

471.00

cum

495.00

cum

Mechanical Means
Hard rock ( requiring blasting )
Manual Means
Hard rock ( blasting prohibited )
Mechanical Means
Marshy soil

Manual means ( upto 3 m depth)

cum

Mechanical Means
Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means (Scarifying the
existing granular road surface to a depth of 50 mm and disposal of scarified material within all
lifts and leads upto 1000 metres. )
Scarifying existing bituminous surface to a depth of 50 mm by mechanical means (Scarifying
the existing bituminous road surface to a depth of 50 mm and disposal of scarified material with
in all lifts and lead upto 1000 metres.)

cum

350.00
147.00

sqm

17.40

sqm

6.00

cum

192.00

cum

183.00

3.14

3.15

3.16

(i)
(ii)
3.17

(i)
(ii)
3.18

(i)
(ii)
3.19
Case-I

Embankment Construction with Material Obtained from Borrow Pits (Construction of


embankment with approved material obtained from borrow pits with all lifts and leads,
transporting to site, spreading, grading to required slope and compacting to meet requirement
of table 300-2)

Rolling with vibratory roller


Rolling with smooth wheeled roller
Construction of Embankment with Material Deposited from Roadway Cutting (Construction of
embankment with approved materials deposited at site from roadway cutting and excavation
from drain and foundation of other structures graded and compacted to meet requirement of
table 300-2)

Rolling with vibratory roller


Rolling with smooth wheeled roller

cum

124.00

cum

115.00

cum

228.00

cum

217.00

Construction of Subgrade and Earthen Shoulders (Construction of subgrade and earthen


shoulders with approved material obtained from borrow pits with all lifts & leads, transporting
to site, spreading, grading to required slope and compacted to meet requirement of table No.
300-2)

Rolling with vibratory roller


Rolling with smooth wheeled roller
Compacting Original Ground
Compacting original ground supporting subgrade (Loosening of the ground upto a level of500
mm below the subgrade level, watered, graded and compacted in layers to meet requirement of
table 300-2 for subgrade construction.)

29

(i)
(ii)
Case-II
(i)
(ii)
3.20

3.21

3.22

3.23

3.24

A
B
3.25

A
B
3.26
3.27

3.28

3.29

3.30

3.31

3.32

3.33

3.34

Rolling with vibratory roller


Rolling with smooth wheeled roller

cum

70.00

cum

59.00

cum

38.00

cum

27.00

cum

178.00

cum

78.00

sqm

39.00

sqm

143.00

metre

68.00
56.00

Compacting original ground supporting embankment

Rolling with vibratory roller


Rolling with smooth wheeled roller
Stripping and Storing Top Soil (Stripping, storing of top soil by road side at 15 m internal and reapplication on embankment slopes, cut slopes and other areas in localities where the available
embankment material is not conducive to plant growth)
Stripping, storing and re-laying top soil from borrow areas in agriculture fields. (Stripping of top
soil from borrow areas located in agriculture fields, storing at a suitable place, spreading and relaying after taking the borrow earth to maintain fertility of the agricultural field, finishing it to
the required levels and satisfaction of the farmer.)
Turfing with Sods (Furnishing and laying of the live sods of perennial turf forming grass on
embankment slope, verges or other locations shown on the drawing or as directed by the
engineer including preparation of ground, fetching of rods and watering)
Seeding and Mulching (Preparation of seed bed on previously laid top soil, furnishing and
placing of seeds, fertilizer, mulching material, applying bituminous emulsion at the rate of0.23
litres per sqm and laying and fixing jute netting, including watering for 3 months all as per
clause 308)
Surface Drains in Soil (Construction of unlined surface drains of average cross sectional area
0.40 sqm in soil to specified lines, grades, levels and dimensions to the requirement of clause
301 and 309. Excavated material to be used in embankment within a lead of50 metres (average
lead 25 metres))
Mechanical means
Manual Means
Surface Drains in Ordinary Rock (Construction of unlined surface drain of average cross
sectional area 0.4 sqm in ordinary rock to specified lines, grades, levels and dimensions as per
approved design and to the requirement of clause 301 to 309. Excavated material to be used in
embankment at site.)
Mechanical Means

metre

Manual Means
Surface Drains in Hard Rock (Rate per metre may be worked out based on quantity of hard rock
as per design.)

metre

137.00
84.00

metre

VALUE

Sub Surface Drains with Perforated Pipe (Construction of subsurface drain with perforated pipe
of 100 mm internal diameter of metal/ asbestos cement/ cement concrete/PVC, closely jointed,
perforations ranging from 3 mm to 6 mm depending upon size of material surrounding the pipe,
with 150 mm bedding below the pipe and 300 mm cushion above the pipe, cross section of
excavation 450 x 550 mm. Excavated material to be utilised in roadway at site )

metre

382.00

Aggregate Sub- Surface Drains (Construction of aggregate sub surface drain 300 mm x 450 mm
with aggregates conforming to table 300-4, excavated material to be utilised in roadway )

metre

152.00

metre

2269.00

sqm

2.00

cum

70.00

cum

172.00

Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring Blasting.
(Excavation in hilly area in ordinary rock not requiring ballasting by mechanical means including
cutting and trimming of slopes and disposal of cut material with all lift and lead upto 1000
metres )

cum

244.00

Excavation in Hilly Areas in Hard Rock Requiring Blasting (Excavation in hilly areas in hard rock
requiring blasting, by mechanical means including trimming of slopes and disposal of cut
material with all lifts and lead upto 1000 metres.)

cum

304.00

Underground Drain at Edge of Pavement (Construction of an underground drain 1 m x 1 m


(inside dimensions) lined with RCC-20 cm thick and covered with RCC slab10 cm in thickness on
urban roads)
Preparation and Surface Treatment of formation. (Preparation and surface treatment of
formation by removing mud and slurry, watering to the extent needed to maintain the desired
moisture content, trimming to the required line, grade, profile and rolling with 8-10 tonne
smooth wheeled roller, complete as per clause 310.)
Construction of Rock fill Embankment (Construction of rock fill embankment with broken hard
rock fragments of size not exceeding 300 mm laid in layers not exceeding 500 mm thick
including filling of surface voids with stone spalls, blinding top layer with granular material,
rolled with vibratory road roller, all complete as per clause 313)
Excavation in Hill Area in Soil by Mechanical Means (Excavation in soil in hilly area by
mechanical means including cutting and trimming of side slopes and disposing of excavated
earth with all lifts and lead upto 1000 metres)

3.35

Work in Urban Roads (The cost of earth work in urban roads inhabited area will be
comparatively higher due to following reasons:)

3.36

Embankment Construction with Fly ash/Pond ash available from coal or lignite burning Thermal
Plants as waste material. (Construction of embankment with fly ash conforming to table 1 of
IRC: SP: 58 - 2001 obtained from coal or lignite burning thermal power stations as waste
material, spread and compacted in layer of 200mm thickness each at OMC, all as specified in
IRC: SP: 58-2001 and as per approved plans.)

30

metre

VALUE

cum

111.00

CHAPTER-4

SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS


Item No.

Descriptions

Unit

Rate (in Rs.)

cum
cum
cum

1422.00
1390.00
1257.00

cum
cum
cum

1191.00
1158.00
1026.00

cum
cum
cum

1153.00
1142.00
1111.00

By Mechanical Means
By Manual Means

cum
cum

444.00
440.00

Lime Treated Soil for Sub- Base (Providing, laying and spreading soil on a prepared
sub grade, pulverising, mixing the spread soil in place with rotavator with 3 % slaked
lime with minimum content of 70% of CaO, grading with motor grader and
compacting with the road roller at OMC to achieve at least 98%of the max dry density
to form a layer of sub base.)

cum

501.00

Cement Treated Soil Sub Base/ Base (Providing, laying and spreading soil on a
prepared sub grade, pulverising, adding the designed quantity of cement to the
spread soil, mixing in place with rotavator, grading with the motor grader and
compacting with the road roller at OMC to achieve the desired unconfined
compressive strength and to form a layer of sub-base/base.)

cum

661.00

4.1
A

Granular Sub-base with Close Graded Material (Table:- 400-1)

(i)
(ii)
(iii)
B

for grading- I Material


for grading- II Material
for grading-III Material

Plant Mix Method (Construction of granular sub-base by providing close graded


Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work
site, spreading in uniform layers with motor grader on prepared surface and
compacting with vibratory power roller to achieve the desired density, complete as per
clause 401 )

By Mix in Place Method (Construction of granular sub-base by providing close graded


material, spreading in uniform layers with motor grader on prepared surface, mixing
by mix in place method with rotavator at OMC, and compacting with vibratory roller to
achieve the desired density, complete as per clause 401)

(i)
(ii)
(iii)
4.2

for grading- I Material


for grading- II Material
for grading-III Material

(i)
(ii)
(iii)
4.3

for grading- I Material


for grading- II Material
for grading-III Material

A
B
4.4

4.5

Granular Sub-Base with Coarse Graded Material ( Table:- 400- 2) (Construction of


granular sub-base by providing coarse graded material, spreading in uniform layers
with motor grader on prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the desired density, complete
as per clause 401)

Lime Stabilisation for Improving Subgrade (Laying and spreading available soil in the
subgrade on a prepared surface, pulverising, mixing the spread soil in place with
rotavator with 3 % slaked lime having minimum content of 70% of CaO, grading with
motor grader and compacting with the road roller at OMC to the desired density to
form a layer of improved sub grade)

4.6

Cement Treated Crushed Rock or combination as per clause 403.2 and table 400.4 in
Sub base/ Base (Providing, laying and spreading Material on a prepared sub grade,
adding the designed quantity of cement to the spread Material, mixing in place with
rotavator, grading with the motor grader and compacting with the road roller at OMC
to achieve the desired unconfined compressive strength and to form a layer of subbase/base.)

(i)

For Sub-Base course

cum

1883.00

(ii)

For Base course

cum

1430.00

4.7

Making 50 mm x 50 mm Furrows (Making 50 mm x 50 mm furrows, 25mm deep, 450


to the center line of the road and at one metre interval in the existing thin bituminous
wearing coarse including sweeping and disposal of excavated material within 1000
i) 25 mm deep furrow cutting

sqm

2.90

ii) 50 mm deep furrow cutting

sqm

5.70

31

4.8

4.9

Inverted Choke (Construction of inverted choke by providing, laying, spreading and


compacting screening B type/ coarse sand of specified grade in uniform layer on a
prepared surface with motor grader and compacting with power roller etc)

cum

420.00

1134.00
1127.00
1325.00
1317.00

Water Bound Macadam (Providing, laying, spreading and compacting stone aggregates of
specific sizes to water bound macadam specification including spreading in uniform thickness,
hand packing, rolling with vibratory roller 8-10 tonnes / Smooth 3 wheeled Steel Roller in
stages to proper grade and camber, applying and brooming requisite type of screening/ binding
Materials to fill up the interstices of coarse aggregate, watering and compacting to the required
density.)
By Manual Means

(i)

Grading- I (Using Screening Crushable type such as Moorum or Gravel)

(a)

Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

(b)

Using Screening Type-A (13.2mm Agg.) (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

(ii)

Grading- II (Using Screening Crushable type such as Moorum or Gravel)

(a)

Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

(b)
(c)
(iii)
(a)
(b)
B
(i)
(a)
(b)
(ii)
(a)
(b)
(c)
(iii)
(a)
(b)
4.10

Using Screening Type-A (13.2mm Agg.) (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

Using Screening Type-B (11.2mm Agg.) (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

Grading- III (Using Screening Crushable type such as Moorum or Gravel)


Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

Using Screening Type-B (11.2mm Agg.) (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

By Mechanical Means:
Grading- I (Using Screening Crushable type such as Moorum or Gravel)
Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

Using Screening Type-A (13.2mm Agg.) (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

1266.00
1258.00
1396.00
1388.00

1012.00
1004.00
1203.00
1195.00

Grading- II (Using Screening Crushable type such as Moorum or Gravel)


Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

Using Screening Type-A (13.2mm Agg.) (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

Using Screening Type-B (11.2mm Agg.) (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

1114.00
1106.00
1214.00
1206.00
1263.00
1237.00

Grading- III (Using Screening Crushable type such as Moorum or Gravel)

Using Screening Type-B (11.2mm Agg.) (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller


Crushed Cement Concrete Sub-base / Base (Breaking and crushing of material obtained by
breaking damaged cement concrete slabs to size range not exceeding 75 mm as specified in
table 400.7 transporting the aggregates obtained from breaking of cement concrete slabs at a
lead of L km., laying and compacting the same as sub base/ base course, constructed as WBM
to clause 404 except the use of screening or binding Material.)

cum

1144.00
1136.00
1274.00
1266.00

With Vibratory Roller

cum

239.00

cum

231.00

sqm

19.60

Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

With Smooth 3 wheeled Steel Roller


4.11

1236.00
1229.00
1337.00
1329.00
1385.00
1359.00

Penetration Coat Over Top Layer of Crushed Cement Concrete Base (Spraying of bitumen over
cleaned dry surface of crushed cement concrete base at the rate of 25 kg per 10 sqm by a
bitumen pressure distributor, spreading of key aggregates at the rate of 0.13 cum per 10 sqm
by a mechanical gritter and rolling the surface as per clause 506.3.8)

32

4.12

4.13

4.14

4.15

4.16

4.17

(i)
(ii)
B

(i)
(ii)
4.18

Wet Mix Macadam (Providing, laying, spreading and compacting graded stone aggregate to
wet mix macadam specification including premixing the Material with water at OMC in
mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with
paver in sub- base / base course on well prepared surface and compacting with vibratory roller
to achieve the desired density.)
With Vibratory Roller
With Smooth 3 wheeled Steel Roller
Construction of Median and Island with Soil Taken from Roadway Cutting (Construction of
Median and Island above road level with approved material deposited at site from roadway
cutting and excavation for drain and foundation of other structures, spread, graded and
compacted as per clause 407)
Construction of Median and Island with Soil Taken from Borrow Areas (Construction of median
and Island above road level with approved material brought from borrow pits, spread, sloped
and compacted as per clause 407)

cum

1382.00
1388.00

cum

193.00

cum

219.00

cum

Construction of Shoulders (A. Earthen Shoulders)


B.) Hard Shoulders

VALUE

C.) Paved Shoulders

VALUE

Footpaths and Separators (Construction of footpath/separator by providing a 150 mm


compacted granular sub base as per clause 401 and 25 mm thick cement concrete grade M15,
over laid with precast concrete tiles in cement mortar 1:3 including provision of all drainage
arrangements but excluding kerb channel.)

sqm

639.00

cum
cum

1015.00
1050.00

For 53 mm maximum size


For 45 mm maximum size

cum
cum

1182.00
1234.00

Lime, Fly ash stabalised soil sub-base (Construction of Sub-base using lime - fly ash admixture
with granular soil, free from organic matter/ deleterious material or clayey silts and low
plasticity clays having PI between 5 and 20 and liquid limit less than 25 and commercial dry
lime, slaked at site or pre-slaked with CaO content not less than 50%, fly ash to conform to
gradation as per clause 4.3 of IRC: 88-1984, lime + fly ash content ranging between 10 to
30%, the minimum un-confined compressive strength and CBR value after 28 days curing and 4
days soaking to be 7.5 kg/sq, cm and 25% respectively, all as specified in IRC: 88-1984)

cum

476.00

Crusher Run Macadam Base (Providing crushed stone aggregate, depositing on a prepared
surface by hauling vehicles, spreading and mixing with a motor grader, watering and
compacting with a vibratory roller to clause 410 to form a layer of sub-base/Base)
By Mix in Place Method

For 53 mm maximum size


For 45 mm maximum size
By Mixing Plant :

33

CHAPTER-5

BASES AND SURFACE COURSES (BITUMINOUS)


Item No.
5.1

5.2

Descriptions
Prime coat (Providing and applying primer coat with bitumen emulsion on prepared surface of
granular Base including clearing of road surface and spraying primer at the rate of 0.60 kg/sqm
using mechanical means.)
Tack coat
Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at
the rate of 0.20 kg per sqm on the prepared bituminous/granular surface cleaned with
mechanical broom.

5.3

(i)
(ii)
5.3 A

(i)
(ii)
5.3 B

(i)
(ii)
5.4

A
B
5.5

5.6

(i)
(ii)
5.6 A

(i)
(ii)

Bituminous Macadam (Providing and laying bituminous macadam with 100-120 TPH hot mix
plant producing an average output of 75 tonnes per hour using crushed aggregates of specified
grading premixed with bituminous binder, transported to site, laid over a previously prepared
surface with paver finisher to the required grade, level and alignment and rolled as per clauses
501.6 and 501.7 to achieve the desired compaction)
for Grading I ( 40 mm nominal size )
for GradingII(19 mm nominal size)

Unit

Rate (in Rs.)

sqm

29.00

sqm

10.00

cum
cum

5712.00
5636.00

cum
cum

5795.00
5720.00

cum
cum

5218.00
5142.00

sqm
sqm

277.00
385.00

sqm

235.00

cum
cum

6683.00
6764.00

cum
cum

6796.00
6878.00

Bituminous Macadam (Providing and laying bituminous macadam with 100-120 TPH hot mix
plant producing an average output of 75 tonnes per hour using crushed aggregates of specified
grading premixed with bituminous binder, transported to site, laid over a previously prepared
surface with paver finisher to the required grade, level and alignment and rolled as per clauses
501.6 and 501.7 to achieve the desired compaction)with modified graded bitumen.
for Grading I ( 40 mm nominal size )
for GradingII(19 mm nominal size)
Bituminous Macadam (Providing and laying bituminous macadam with 100-120 TPH hot mix
plant producing an average output of 75 tonnes per hour using crushed aggregates of specified
grading premixed with bituminous binder, transported to site, laid over a previously prepared
surface with paver finisher to the required grade, level and alignment and rolled as per clauses
501.6 and 501.7 to achieve the desired compaction)with VG-30 Bulk bitumen.
for Grading I ( 40 mm nominal size )
for GradingII(19 mm nominal size)
Bituminous Penetration Macadam (Construction of penetration macadam over prepared Base by
providing a layer of compacted crushed coarse aggregate using chips spreader with alternate
applications of bituminous binder and key aggregates and rolling with a smooth wheeled steel
roller 8-10 tonne capacity to achieve the desired degree of compaction)
50 mm thick
75 mm thick
Built-Up-Spray Grout (Providing, laying and rolling of built-up-spray grout layer over prepared
base consisting of a two layer composite construction of compacted crushed coarse aggregates
using motor grader for aggregates. key stone chips spreader may be used with application of
bituminous binder after each layer, and with key aggregates placed on top of the second layer
to serve as a Base conforming to the line, grades and cross-section specified, the compacted
layer thickness being 75 mm)
Dense Graded Bituminous Macadam (Providing and laying dense bituminous macadam with 100120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with bituminous binder @ 4.0 to 4.5% by weight of
total mix of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver
finisher with sensor control to the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH
specification clause No. 507 complete in all respects.)
for Grading I ( 40 mm nominal size )
for GradingII(19 mm nominal size)
Dense Graded Bituminous Macadam (Providing and laying dense bituminous macadam with 100120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with bituminous binder @ 4.0 to 4.5% by weight of
total mix of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver
finisher with sensor control to the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH
specification clause No. 507 complete in all respects.) with Modifed Graded Bitumen.
for Grading I ( 40 mm nominal size )
for GradingII(19 mm nominal size)

34

5.6 B

Dense Graded Bituminous Macadam (Providing and laying dense bituminous macadam with 100120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with bituminous binder @ 4.0 to 4.5% by weight of
total mix of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver
finisher with sensor control to the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH
specification clause No. 507 complete in all respects.) with VG-30 Grade Bulk Bitumen.

(i)
(ii)
5.7

for Grading I ( 40 mm nominal size )


for GradingII(19 mm nominal size)
Semi - Dense Bituminous Concrete (Providing and laying semi dense bituminous concrete with
100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using
crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 to 5 % of mix
and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with
sensor control to the required grade, level and alignment, rolling with smooth wheeled,
vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification
clause No. 508 complete in all respects)
for Grading I ( 13 mm nominal size )
for GradingII(10 mm nominal size)

(i)
(ii)
5.7 A

(i)
(ii)
5.8

(i)
(ii)
5.9

cum
cum

6014.00
6096.00

cum
cum

6951.00
7318.00

cum
cum

7070.00
7451.00

cum
cum

7735.00
7571.00

sqm
sqm

71.00
57.00

Semi - Dense Bituminous Concrete (Providing and laying semi dense bituminous concrete with
100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using
crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 to 5 % of mix
and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with
sensor control to the required grade, level and alignment, rolling with smooth wheeled,
vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification
clause No. 508 complete in all respects) with Modified Graded Bitumen.
for Grading I ( 13 mm nominal size )
for GradingII(10 mm nominal size)
Bituminous Concrete (Providing and laying bituminous concrete with 100-120 TPH batch type
hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of
specified grading, premixed with bituminous binder @ 5.4 to 5.6 % of mix and filler,
transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor
control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and
tandem rollers to achieve the desired compaction as per MORTH specification clause No. 509
complete in all respects)
for Grading-I ( 13 mm nominal size )
for Grading-II(10 mm nominal size)
Surface Dressing (Providing and laying surface dressing as wearing course in single coat using
crushed stone aggregates of specified size on a layer of bituminous binder laid on prepared
surface and rolling with 8-10 tonne smooth wheeled steel roller)

Case -1 19 mm nominal chipping size


Case - II 13 mm nominal size chipping
5.10
Open - Graded Premix Surfacing (Providing, laying and rolling of open - graded premix
surfacing of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using
penetration grade bitumen or cut-back or emulsion to required line, grade and level to serve as
wearing course on a previously prepared base, including mixing in a suitable plant, laying and
rolling with a smooth wheeled roller 8-10 tonne capacity, finished to required level and grades.)
(i)

Case - I: Mechanical method using Penetration grade Bitumen and HMP of appropriate capacity
not less than 75 tonnes/hour .

sqm

109.00

(ii)

Case - II: Open-Graded Premix Surfacing using cationic Bitumen Emulsion

sqm

129.00

i) For Type A

sqm

134.00

i) For Type B

sqm

126.00

5.11

Close Graded Premix Surfacing/Mixed Seal Surfacing (Mechanical means using HMP of
appropriate capacity not less than 75 tonnes/hour. Providing, laying and rolling of close-graded
premix surfacing material of 20 mm thickness composed of 11.2 mm to 0.09 mm (Type-a) or
13.2 mm to 0.09 mm (Type-b) aggregates using penetration grade bitumen to the required
line, grade and level to serve as wearing course on a previously prepared base, including mixing
in a suitable plant, laying and rolling with a Smooth wheeled roller 8-10 tonne capacity, and
finishing to required level and grade. )

35

5.12
(i)
(ii)

5.13

5.14

5.15

(i)
(ii)
(iii)
5.16

5.17
added
5.18

(i)
(ii)
(iii)
(iv)
5.19

5.20

5.21
(i)

Seal Coat (Providing and laying seal coat sealing the voids in a bituminous surface laid to the
specified levels, grade and cross fall using Type A and B seal coats)
Case - I : Type A

sqm

49.00

Case - II : Type B (Providing and laying of premix sand seal coat with HMP of appropriate
capacity not less than 75 tonnes/ hours using crushed stone chipping 6.7 mm size and
penetration bitumen of suitable grade.)

sqm

43.00

Supply of Stone Aggregates for Pavement Courses (Supply of stone aggregates from approved
sources confirming to the physical requirement, specified in the respective specified clauses,
including royalties, fees rents, collection, transportation, stacking and testing and measured in
cum as per clause 514.5 Competitive market rates to be ascertained. Alternatively, rates for
stone crushing given in chapter 1may be adopted, if found economical. In case for supply of
aggregates at site are not available, nearest crusher site may be ascertained. Loading and unloading charges and cost of carriage may be added to these rates to arrive at the cost at site.)

cum

VALUE

Mastic Asphalt (Providing and laying 25 mm thick mastic asphalt wearing course with paving
grade bitumen meeting the requirements given in table 500-29, prepared by using mastic
cooker and laid to required level and slope after cleaning the surface, including providing
antiskid surface with bitumen precoated fine-grained hard stone chipping of 13.2 mm nominal
size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm center to
center in both directions, pressed into surface when the temperature of surfaces not less than
1000C, protruding 1 mm to 4 mm over mastic surface, all complete as per clause 515.)

sqm

#VALUE!

Slurry Seal Providing and laying slurry seal consisting of a mixture of fine aggregates, portland
cement filler, bituminous emulsion and water on a road surface including cleaning of surface,
mixing of slurry seal in a suitable mobile plant, laying and compacting to provide even riding
surface)
5 mm thickness
3 mm thickness
1.5 mm thickness
Recycling of Bituminous Pavement with Central Recycling Plant (Recycling pavement by cold
milling of exiting bituminous layers, planning the surface after cold milling, reclaiming excavated
material to the extent of 30 % of the required quantity, hauling and stock piling the reclaimed
material near the central recycling plant after carrying out necessary checks and evaluation,
adding fresh material including rejuvenators as required, mixing in a hot mix plant, transporting
and laying at site and compacting to the required grade, level and thickness, all as specified in
clause 517.)
Fog Spray

sqm
sqm
sqm
sqm

61.00
43.00
26.00

cum

5911.00

sqm

1.In case it is decided by the engineer to blind the fog spray, the following may be added

sqm

4.50

Bituminous Cold Mix ( Including Gravel Emulsion) (Providing, laying and rolling of bituminous
cold mix on prepared base consisting of a mixture of unheated mineral aggregate and
emulsified or cutback bitumen, including mixing in a plant of suitable type and capacity,
transporting, laying, compacting and finishing to specified grades and levels.)
Using bitumen emulsion and 9.5 mm or 13.2 mm nominal size aggregate
Using bitumen emulsion and 19 mm or 26.5 mm nominal size aggregate
Using cutback bitumen and 9.5 mm or 13.2 mm nominal size aggregate
Using cutback bitumen and 19 mm or 26.5 mm nominal size aggregate

cum
cum
cum
cum

9652.00
9623.00
6667.00
6604.00

Sand Asphalt Base Course (Providing, laying and rolling sand-asphalt base course composed of
sand, mineral filler and bituminous binder on a prepared sub-grade or sub-base to the lines,
levels, grades and cross sections as per the drawings including mixing in a plant of suitable type
and capacity, transporting, laying, compacting and finishing.)

cum

6254.00

Modified Binder (Supply of modified binder produced by mixing bitumen with modifier
such as natural rubber or crumb rubber or any other polymer found compatible with
bitumen and which allows properties given in clause 521.3 and IRC: SP: 53 blending
of modifier with bitumen to be done either at the refinery or at the site plant capable
of producing the modified binder to be delivered in drums which shall be agitated in
melted condition using suitable device before use to ensure uniform dispersion.)

tonne

VALUE

sqm

47.00

Crack Prevention Courses

Stress Absorbing Membrane (SAM) crack width less than 6 mm (Providing and laying
of a stress absorbing membrane over a cracked road surface, with crack width below
6 mm after cleaning with a mechanical broom, using modified binder complying with
clause 521, sprayed at the rate of 9 kg per 10 sqm and spreading 5.6 mm crushed
stone aggregates @ 0.11 cum per 10 sqm with hydraulic chip spreader, sweeping the
surface for uniform spread of aggregates and surface finished to conform to clause
902.)

36

(ii)

(iii)

(iv)

5.22

(i)
(ii)
(iii)
5.8 A

5.8 B

Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm (Providing and


laying of a stress absorbing membrane over a cracked road surface, with crack width
6 to 9 mm after cleaning with a mechanical broom, using modified binder complying
with clause 521, sprayed at the rate of 11 kg per 10 sqm and spreading 11.2 mm
crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to clause 902.)

sqm

57.00

Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above
50 % (Providing and laying a single coat of a stress absorbing membrane over a
cracked road surface, with crack width above 9 mm and cracked area above 50 %
after cleaning with a mechanical broom, using modified binder complying with clause
521, sprayed at the rate of 15 kg per 10 sqm and spreading 11.2 mm crushed stone
aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform spread of
aggregates and surface finished to conform to clause 902.)

sqm

75.00

Case - IV : Bitumen Impregnated Geotextile (Providing and laying a bitumen


impregnated geotextile layer after cleaning the road surface, geotextile conforming to
requirements of clause 704.3, laid over a tack coat with 1.05 kg per sqm of paving
grade bitumen 80 - 100 penetration and constructed to the requirement of clause
704.4.5)

sqm

125.00

cum
cum
cum

6329.00
8770.00
9733.00

Recipe Cold Mix (Providing and laying of premix of crushed stone aggregates and
emulsion binder, mixed in a batch type cold mixing plant, laid over prepared surface,
by paver finisher, rolled with a pneumatic tyred roller initially and finished with a
smooth steel wheel roller, all as per clause 519.3)
75 mm thickness
40 mm thickness
25 mm thickness
Bituminous Concrete (Providing and laying bituminous concrete with 100-120 TPH batch type hot mix
plant producing an average output of 75 tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 5.4 to 5.6 % of mix and filler, transporting the hot mix
to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level
and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MORTH specification clause No. 509 complete in all respects) with Modifed Graded
Bitumen.
(i) for Grading-I ( 13 mm nominal size )

7871.00

(ii) for Grading-II(10 mm nominal size)

7707.00

Bituminous Concrete (Providing and laying bituminous concrete with 100-120 TPH batch type hot mix
plant producing an average output of 75 tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 5.4 to 5.6 % of mix and filler, transporting the hot mix
to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level
and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MORTH specification clause No. 509 complete in all respects) with Bulk VG30
Bitumen.
(i) for Grading-I ( 13 mm nominal size )

cum

6932.00

(ii) for Grading-II(10 mm nominal size)

cum

6768.00

37

CHAPTER-6

CEMENT CONCRETE PAVEMENTS


Item No.
6.1

6.2

6.3

6.4

6.5

6.6

Descriptions

Unit

Rate (in Rs.)

Dry Lean Cement Concrete Sub- base (Construction of dry lean cement concrete Subbase over a prepared sub-grade with coarse and fine aggregate conforming to IS:
383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not
to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement
content not to be less than 150 kg/ cum, optimum moisture content to be determined
during trial length construction, concrete strength not to be less than 10 Mpa at 7
days, mixed in a batching plant, transported to site, laid with a paver with electronic
sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing.)

cum

2238.00

Cement Concrete Pavement (Construction of un-reinforced, dowel jointed, plain


cement concrete pavement over a prepared sub base with 43 grade cement @ 400 kg
per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse
aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per
approved mix design, transported to site, laid with a fixed form or slip form paver,
spread, compacted and finished in a continuous operation including provision of
contraction, expansion, construction and longitudinal joints, joint filler, separation
membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod,
admixtures as approved, curing compound, finishing to lines and grades as per
drawing )

cum

4754.00

Rolled Cement Concrete Base (Construction of rolled cement concrete base course
with coarse and fine aggregate conforming to IS:383, the size of coarse aggregate not
exceeding 25 mm with minimum, aggregate cement ratio15:1 and minimum cement
content of 200 kg/cum, aggregate gradation to be as per table 600-4 after blending,
mixing in batching plant at optimum moisture content, transporting to site, laying with
a paver with electronic sensor, compacting with 8-10 tonnes smooth wheeled
vibratory roller to achieve, the designed flexural strength, finishing and curing.)

cum

2555.00

Transition section between rigid and flexible pavement (Due to change in the
properties of materials and type of construction, a gradual changeover from rigid
pavement to flexible pavement is desirable to avoid any damage at the butting joint.
After provision of an expansion joint in the cement concrete slab, the thickness of slab
should be tapered to 10 cm over a length of 3 m towards the flexible pavement. The
deficiency of thickness caused due to tapering of the slab should be made up by the
asphaltic layers.)
Construction of Base/Sub-base of pavement with lean concrete - fly ash. (Construction
of Base/sub-base using cement, sand, fly ash and coarse aggregates proportioned as
per table 4 of IRC: 74/1979 and with water content ratio, slump and compressive
strength as defined in the said table, mix prepared in a batching and mixing plant and
compacted with a vibratory roller 8-10 tonnes capacity within the time limit laid down
vide clause 7.6.3 of IRC: 74-1979, construction joints properly formed at the end of
day's work, cured for 14 days, all as specified in IRC: 74-1979 and as per approved
plans.)
Cement - Fly ash concrete pavement. (Construction reinforced-reinforced, dowel
jointed, plain cement concrete pavement over a prepared sub base with 43 grade
cement, coarse and fine aggregate conforming to IS 383, maximum size of coarse
aggregate not exceeding 25 mm, replacing cement by fly ash to the extent of 15%
and sand by 10%, mixed in a batching and mixing plant as per approved mix design,
transported to site, laid with a fixed form or slip form paver, spread, compacted and
finished in a continuous operation including provision of contraction, expansion,
construction and longitudinal joints, joint filler, separation membrane, sealant primer,
joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing
compound, finishing to lines and grades as per drawing )

38

Value

cum

2105.00

cum

4397.00

CHAPTER-7

GEOSYNTHETICS AND REINFORCED EARTH


Item No.
7.1

7.2

7.3

7.4

Descriptions

Unit

Rate (in Rs.)

Sub- Surface Drain with Geotextiles (Construction of sub surface drain 200 mm dia using
geotextiles treated with carbon black with physical properties as given in clause 702.2.3 formed
in to a stable network and a planar geocomposite structure, joints wrapped with geotextile to
prevent ingress of soil, all as per clause 702 and approved drawings including excavation and
backfilling)

metre

579.00

Narrow Filter Sub- Surface Drain (Construction of a narrow filter sub- surface drain consisting of
porous or perforated pipe laid in narrow trench surrounded by a geotextile filter fabric, with a
minimum of 450 mm overlap of fabric and installed as per clause 702.3 and 309.3.5 including
excavation and backfilling)

metre

412.00

Laying Paving Fabric Beneath a Pavement Overlay (Providing and laying paving fabric with
physical requirements as per table 704-2 over a tack coat of paving grade Bitumen 80-100
penetration, laid at the rate of 1 kg per sqm over thoroughly cleaned and repaired surface to
provide a water resistant membrane and crack retarding layer. Paving fabric to be free of
wrinkling and folding and to be laid before cooling of tack coat, brooming and rolling of surface
with pneumatic roller to maximise paving fabric contact with pavement surface)

sqm

120.00

Laying Boulder Apron in Crates of Synthetic Geogrids (Providing, preparing and laying of
geogrid crated apron 1 m x 5 m, 600 mm thick including excavation and backfilling with baffles
at 1 metre interval, made with geogrids having characteristics as per clause 704.2, joining sides
with connectors/ring staples, top corners to be tie tensioned, placing of suitable cross interval
ties in layers of 300 mm connecting opposite side with lateral braces and tied with polymer
braids to avoid bulging, constructed as per clause 704.3. filled with stone with minimum size of
200 mm and specific gravity not less than 2.65, packed with stone spalls, keyed to the
foundation recess in case of sloping ground and laid over a layer of geotextile to prevent
migration of fines, all as per clause 704 and laid as per clause 2503.3 and approved design.)

cum

#VALUE!

7.5

Reinforced Earth Retaining Wall (Reinforced earth retaining walls have four main components
as under: a) Excavation for foundation, foundation concrete and cement concrete grooved
seating in the foundation for facing elements (facia material). b) Facia material and its
placement. c) Assembling, joining with facing elements and laying of the reinforcing elements.
d) Earthfill with granular material which is to be retained by the wall.)

(i)

Assembling, joining and laying of reinforcing elements.

With reinforcing element of steel / Aluminium strips / polymeric strips.

Type 1

1.Galvanised carbon steel strips

metre

640.00

Type 2

2.Copper Strips

metre

640.00

Type 3

3.Aluminium Strips

metre

319.00

Type 4

4.Stainless steel strips

metre

319.00

Type 5

5.Glass reinforced polymer/fibre reinforced polymer/polymeric strips

metre

640.00

With reinforcing elements of synthetic geogrids

sqm

124.00

Facing elements of RCC

sqm

1025.00

B
(ii)

39

CHAPTER-8

TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES


Item No.

Descriptions

Unit

Rate (in Rs.)

Cast in Situ Cement Concrete M20 kerb (Construction of cement concrete kerb with top and
bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on M-10 grade
foundation 150 mm thick, foundation having 50 mm projection beyond kerb stone, kerb stone
laid with kerb laying machine, foundation concrete laid manually, all complete as per clause
408)
Using Concrete Mixer

metre

Using Concrete Batching and Mixing Plant

metre

224.00
230.00

8.1

8.2

A
B
8.3
(i)

(ii)
8.4

Cast in Situ Cement Concrete M 20 Kerb with Channel (Construction of cement concrete kerb
with channel with top and bottom width 115 and 165 mm respectively, 250 mm high in M 20
grade PCC on M10 grade foundation 150 mm thick, kerb channel 300 mm wide, 50 mm thick in
PCC M20 grade, sloped towards the kerb, kerb stone with channel laid with kerb laying
machine, foundation concrete laid manually, all complete as per clause 408)
Using Concrete Mixer

metre

Using Concrete Batching and Mixing Plant

metre

409.00
420.00

Printing new letter and figures of any shade (Printing new letter and figures of any shade with
synthetic enamel paint black or any other approved colour to give an even shade)
Hindi ( Matras commas and the like not to be measured and paid for Half letter shall be
counted as half )

cm height
per letter

0.80

English and Roman

cm height
per letter

0.50

(i)

Retro- reflectorised Traffic signs (Providing and fixing of retro- reflectorised cautionary,
mandatory and informatory sign as per IRC :67 made of encapsulated lens type reflective
sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5 mm thick supported on a mild
steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly
designed foundation with M15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below
ground level as per approved drawing)
90 cm equilateral triangle

each

( ii )

60 cm equilateral triangle

each

(v)

60 cm x 45 cm rectangular

each

(vi )

60 cm x 60 cm square

each

( vii )

90 cm high octagon

each

4872.00
3017.00
4231.00
6115.00
4107.00
4967.00
7951.00

Direction and Place Identification signs upto 0.9 sqm size board. (Providing and erecting
direction and place identification retro-reflectorised sign asper IRC:67 made of encapsulated
lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm thick with
area not exceeding 0.9 sqm supported on a mild steel single angle iron post 75 x 75 x 6 mm
firmly fixed to the ground by means of properly designed foundation with M15 grade cement
concrete 45 x 45 x 60 cm, 60 cm below ground level as per approved drawing)

sqm

11435.00

sqm

11748.00

( iii )

60 cm circular

each

( iv )

80 mm x 60 mm rectangular

each

8.5

8.6

8.7

Direction and Place Identification signs with size more than 0.9 sqm size board. (Providing and
erecting direction and place identification retro- reflectorised sign asper IRC :67 made of
encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 2
mm thick with area exceeding 0.9 sqm supported on a mild steel angle iron post 75 mm x 75
mm x 6 mm, 2 Nos. firmly fixed to the ground by means of properly designed foundation with
M 15 grade cement concrete45 cm x 45 cm x 60 cm, 60 cm below ground level as per
approved drawing)
Overhead Signs (Providing and erecting overhead signs with a corrosion resistant aluminium
alloy sheet reflectorised with high intensity retro-reflective sheeting of encapsulated lense type
with vertical and lateral clearance given in clause 802.2 and 802.3 and installed as per clause
802.7 over a designed support system of aluminium alloy or galvanised steel trestles and
trusses of sections and type as per structural design requirements and approved plans)

Truss and Vertical Support

tonne

Aluminium alloy plate for over head sign

tonne

72612.00
2002.00

8.8

Painting Two Coats on New Concrete Surfaces (Painting two coats after filling the surface with
synthetic enamel paint in all shades on new plastered concrete surfaces)

sqm

54.00

8.9

Painting on Steel Surfaces (Providing and applying two coats of ready mix paint of approved
brand on steel surface after through cleaning of surface to give an even shade)

sqm

48.00

8.10

Painting on Wood Surfaces (Providing and applying two coats of ready mix paint of approved
brand on wood surface after through cleaning of surface to give an even shade)

sqm

53.00

40

8.11

Painting Lines, Dashes, Arrows etc on Roads in Two Coats on New Work (Painting lines,
dashes, arrows etc on roads in two coats on new work with ready mixed road marking paint
conforming to IS:164 on bituminous surface, including cleaning the surface of all dirt, dust and
other foreign matter, demarcation at site and traffic control )

(i)

Over 10 cm in width

sqm

(ii)

Up to 10 cm in width

sqm

8.12

92.00
78.00

Painting Lines, Dashes, Arrows etc on Roads in Two Coats on Old Work (Painting lines, dashes,
arrows etc on roads in two coats on old work with ready mixed road marking paint confirming
to IS: 164 on bituminous surface, including cleaning the surface of all dirt, dust and other
foreign matter, demarcation at site and traffic control )

(i)

Over 10 cm in width

sqm

(ii)

Up to 10 cm in width

sqm

63.00
68.00

sqm

514.00

8.13

8.14

Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on
Bituminous Surface (Providing and laying of hot applied thermoplastic compound 2.5 mm thick
including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive
of surface applied glass beads as per IRC:35 .The finished surface to be level, uniform and free
from streaks and holes.)
Kilo Metre Stone (Reinforced cement concrete M15grade kilometre stone of standard design as
per IRC:8-1980, fixing in position including painting and printing etc)

(i)

5th kilometre stone (precast)

each

(ii)

Ordinary Kilometer stone (Precast)

each

(iii)

Hectometer stone (Precast)

each

2646.00
1620.00
450.00

Road Delineators (Supplying and installation of delineators (road way indicators, hazard
markers, object markers), 80-100 cm high above ground level, painted black and white in 15
cm wide stripes, fitted with 80 x 100 mm rectangular or 75 mm dia circular reflectorised panels
at the top, buried or pressed into the ground and confirming toIRC-79 and the drawings.)

each

610.00

Boundary pillar (Reinforced cement concrete M15 grade boundary pillars of standard design as
per IRC:25-1967, fixed in position including finishing and lettering but excluding painting)

each

416.00

metre

227.00

metre

370.00

metre

#VALUE!

metre

1497.00

metre

1128.00

metre

2514.00

8.15

8.16
8.17

8.18

8.19

8.20

8.21

8.22

(i)

G.I Barbed wire Fencing 1.2 metre high (Providing and fixing 1.2 metres high GI barbed wire
fencing with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm placed every 3 metres center to
center founded in M15 grade cement concrete, 0.6 metre below ground level, every 15th post,
last but one end post and corner post shall be strutted on both sides and end post on one side
only and provided with 9 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed
with GI staples, turn buckles etc complete as per clause 807 )
G.I Barbed wire Fencing 1.8 metre high (Providing and fixing 1.8 metres high GI barbed wire
fencing with 2.4 m angle iron posts 50 mm x 50 mm x 6 mm placed every 3 metres center to
center founded in M15 grade cement concrete, 0.6 metre below ground level, every 15th post,
last but one end post and corner post shall be strutted on both sides and end post on one side
only and provided with 12 horizontal lines and 2 diagonals interwoven with horizontal wires,
fixed with GI staples, turn buckles etc complete as per clause 807 )
Fencing with welded steel wire Fabric 75 mm x 50 mm (Suggestive) (Providing 1.20 metre high
fencing with angle iron posts 50 mm x 50 mm x 6 mm at 3 metre center to center with 0.40
metre embedded in M15 grade cement concrete, corner, end and every 10th post to be
strutted, provided with welded steel wire fabric of 75 mm x 50 mm mesh or 75 mm x 25 mm
mesh and fixed to iron posts by flat iron 50 x 5 mm and bolts etc. complete in all respects.)
Tubular Steel Railing on Medium Weight steel channel ( ISMC series) 100 mm x 50 mm
(Providing, fixing and erecting 50 mm dia steel pipe railing in 3 rows duly painted on medium
weight steel channels (ISMC series) 100 mm x 50 mm, 1.2 metres high above ground, 2 m
centre to centre, complete as per approved drawings)
Tubular Steel Railing on Precast RCC posts, 1.2 m high above ground level (Providing, fencing
and erecting 50 mm dia painted steel pipe railing in 3 rows on precast M20 grade RCC vertical
posts1.8 metres high (1.2 m above GL) with 3 holes 50 mm dia for pipe, fixed 2 metres centre
to, complete as per approved drawing)
Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement concrete crash
barrier at the edges of the road, approaches to bridge structures and medians, constructed with
M-20 grade concrete with HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm
dia, 450 mm long at expansion joints filled with pre-moulded asphalt filler board, keyed to the
structure on which it is built and installed as per design given in the enclosure to MOST circular
No. RW/NH - 33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved
drawing and at locations directed by the Engineer, all as specified)
M 20 grade concrete

41

8.23
A

8.24

8.25

8.26
A

Metal Beam Crash Barrier


Type - A, "W" : Metal Beam Crash Barrier (Providing and erecting a "W" metal beam crash
barrier comprising of 3 mm thick corrugated sheet metal beam rail, 70 cm above road/ground
level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre,
1.8 m high, 1.1 m below ground/road level, all steel parts and fitments to be galvanised by hot
dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the
vertical post with a spacer of channel section 150 x 75 x 5 mm, 330 mm long complete as per
clause 810)
Type - B, "THRIE" : Metal Beam Crash Barrier (Providing and erecting a "Thrie" metal beam
crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 85 cm above
road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m
centre to centre, 2 m high with 1.15 m below ground level, all steel parts and fitments to be
galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to
be fixed on the vertical post with a space of channel section 150 x 75 x 5 mm, 546 mm long
complete as per clause 810)
Road Traffic Signals electrically operated (Since it is a ready made item commercially produced
and erected by specialised firm in the electrical and electronic field, rate may be taken based on
market enquiry from firms specialised in this field and ISI certified for the approved design and
drawing.)
Flexible Crash Barrier, Wire Rope Safety Barrier (Providing and erecting a wire rope safety
barrier with vertical posts of medium weight RS Joist (ISMB series) 100 mm x 75 mm (11.50
kg/m), 1.50 m long 0.85 m above ground and 0.65 m below ground level, split at the bottom
for better grip, embedded in M 15 grade cement concrete 450 x 450 x 450 mm, 1.50 m center
to center and with 4 horizontal steel wire rope 40 mm dia and anchored at terminal posts 15 m
apart. Terminal post to be embedded in M 15 gradecementconcretefoundation2400 x 450 x 900
mm (depth), strengthened by a strut of RS joist 100 x 75 mm, 2 m long at 450 inclination and a
tie 100 x 8 mm, 1.50 m long at the bottom, all embedded in foundation concrete as per
approved design and drawing, rate excluding excavation and cement concrete.)

metre

2285.00

metre

2856.00

Value

metre

1652.00

Anti - Glare Devices in Median


Plantation (Plantation of shrubs and plants of approved species in the median. apart from
cutting off glare from vehicle coming from opposite direction, these plants provide a pleasant
envoirenment and are eco-friendly. The rate for this item is available in the chapter 11 on
horticulture. )
Anti - Glare Screen with 25 mm steel pipe framework fixed with circular and rectangular vans
(Providing and erecting an anti - glare screen with 25 mm dia vertical pipes fabricated and
framed in the form of panels of one metre length and 1.75 mtr height fixed with circular vane
250 mm dia at top and rectangular vane 600 x 300 mm at the middle, made out of steel sheet
of 3 mm thickness, end vertical pipes of the panel made larger for embedding in foundation
concrete, applying 2 coats of paint on all exposed surfaces, all as per approved design and
drawings.)

Value

metre

2530.00

metre

690.00

(i)

Street Lighting (Providing and erecting street light mounted on a steel circular hollow pole of
standard specifications for street lighting, 9 m high spaced 40 m apart, 1.8 m overhang on both
sides if fixed in the median and on one side if fixed on the footpath, fitted with sodium vapour
lamp and fixed firmly in concrete foundation.)
For Fixing in Median

each

(ii)

For fixing in Footpath

each

#VALUE!
#VALUE!

Lighting on Bridges (Providing and fixing lighting on bridges, mounted on steel hollow circular
poles of standard specifications, 5 m high fixed on parapets with cement concrete, 20 m apart
and fitted with sodium vapour lamp)

each

#VALUE!

(i)

Cable Duct Across the Road (Providing and laying of a reinforced cement concrete pipe duct,
300 mm dia, across the road (new construction), extending from drain to drain in cuts and toe
of slope to toe of slope in fills, constructing head walls at both ends, providing a minimum fill of
granular material over top and sides of RCC pipe as per IRC:98-1997, bedded on a 0.3 m thick
layer of granular material free of rock pieces, outer to outer distance of pipe at least half dia of
pipe subject to minimum 450 mm in case of double and triple row ducts, joints to be made leak
proof, invert level of duct to be above higher than ground level to prevent entry of water and
dirt, all as per IRC: 98 - 1997 and approved drawings.)
Single Row for one utility service

metre

(ii)

Double Row for two utility services

metre

(iii)

Triple Row for three utility services

metre

#VALUE!
#VALUE!
#VALUE!

8.27

8.28

8.29

Anti - Glare Screen with Rectangular Vane of MS sheet (Providing and erecting anti - glare
screen with rectangular vanes of size 750 x 500 mm made from MS sheet, 3 mm thick and
fixed on MS angle 50 x 50 x 6 mm at an angle of 450 to the direction of flow of traffic, 1.5 m
center to center, top edge of the screen 1.75 m above ground level, vertical post firmly
embedded in cement concrete foundation 0.60 m below ground level, applying 2 coats of paint
on exposed faces, all complete as per approved design and drawings)

42

8.30

8.31

8.32

8.33

(i)
(ii)
8.34
A

8.35

8.36

8.37
A

C
8.38

8.39

Highway Patrolling and Traffic Aid Post (It is proposed to locate one Traffic Aid Post every 5060 km of the highway. )

VALUE

Items related to under pass/ subway/ overhead bridge/ overhead foot bridge (The items
involved for underpass/ subway/ overhead bridge/ overhead foot bridge are earthwork, plain
cement concrete, plastering, painting, information sign etc. The rates for these items are
available in respective chapters which can be adopted for the quantities derived from the
approved designs and drawings)

VALUE

Traffic Control System and Communication system (Providing a traffic control centre and
communication system including telecommunication facilities and related accessories, CCTV,
radar, vehicle detection camera, central computer system These are specialised item of
telecommunication system and are the commercial products. The designer is required to
contact the manufacturers to ascertain market prices. In case of civil works required to be
executed for these installations, pricing may be done as per rates in relevant chapters for
quantities derived approved design and drawing.)
Gantry Mounted Variable Message Sign board (Providing and erecting gantry mounted variable
message sign board electronically operated capable of flashing the desired message over a
designed support system of aluminium alloy or galvanised steel, erected as per approved design
and drawings and with lateral clearance as per clause 802.3)
Gantry Support System

VALUE

tonne

Message Display (Message display board 6 sqm electronically operated with complete electronic
fitments for flashing the pre-determined messages.)

70046.00
VALUE

Traffic Impact Attenuators at Abutments and Piers


With Scrap Tyres (Provision and installation of traffic attenuators at abutment/pier of flyovers
bridges using scrap tyres of size 100 x 20 retrieved from trucks laid in 2 rows and 4 tiers, one
above the other and tied with 20 mm wire rope as per approved design and drawings.)

sqm

617.00

Using Plastic/Steel Barrel, Filled with Sand (Provision and installation of traffic impact attenuator
at abutment/pier of flyovers bridges using plastic/steel barrels 0.60 m dia and 1.0 m in height,
filled with sand in three rows and tied with20 mm steel wire rope as per approved design and
drawings)

sqm

476.00

With HI - DRO cell Sandwich (Patented) ((In this patented HI - DRO cell system, water gets
discharged from plastic tubes on impact over a pre-determined time, thus absorbing the
energy))

sqm

#VALUE!

Road Markers/Road Stud with Lense Reflector (Providing and fixing of road stud 100x 100 mm,
die cast in aluminium, resistant to corrosive effect of salt and grit, fitted with lense reflectors,
installed in concrete or asphaltic surface by drilling hole 30 mm upto a depth of 60 mm and
bedded in a suitable bituminous grout or epoxy mortar, all as per BS 873 part 4:1973)

each

228.00

Traffic Cone (Provision of red fluorescent with white reflective sleeve traffic cone made of low
density polyethylene (LDPE) material with a square base of 390 x 390 x 35 mm and a height of
770 mm, 4 kg in weight, placed at 1.5 m interval, all as per BS 873)

each

480.00

Roadside Amenities
Rest Areas (Providing plainly furnished accommodation for rest rooms, dormitories,
restaurants, stalls, shops, petrol pump, telephone booth, first aid room, traffic aid post, police
assistance booth, including electricity, toilet and sewerage system Pricing may be done based
on current plinth area rates approved by PWD/CPWD/MES for a particular zone. Area is required
to be assessed for specific location as per actual site conditions)

VALUE

Parking areas and Bus Laybyes for Trucks, Buses and Light vehicles (Pricing of parking areas
may be done for the quantities of various items based on the approved dimensions and
pavement design for a particular terrain and soil. Rates for items may be from respective
chapters.)

VALUE

Lawn (Providing a lawn planted with grass and its maintenance )

VALUE

Rumble Strips (Provision of 15 nos rumble strips covered with premix bituminous carpet,
15-20 mm high at center, 250 mm wide placed at 1 m center to center at approved locations to
control speed, marked with white strips of road marking paint.)

sqm

VALUE

Policeman Umbrella (Provision of a 2 m high (floor to roof) umbrella for traffic policeman at
road crossings, where necessary, installed on a raised platform, built on a central support of a
steel pipe 100 mm dia, roof made of 25 mm dia steel pipe to provide covered area of 3 sqm,
roofed with CGI sheets, all steel parts to be given 2 coats of paint)

each

VALUE

43

8.40

8.41
8.42

8.43

8.44
A

8.45

High Mast Pole Lighting at Interchanges and Flyovers (Providing and erecting a high mast pole
lighting with 30 m high hot dip galvanised mast designed to withstand forces exerted with wind
speeds of 180 km per hour with 3 seconds gust, as per IS:875 (Part 3) - 1978, fitted with a
base flange, door at the base of mast with heavy duty internal lock, lantern carriage, suitable
winching arrangement for safe working load of 750 kg and high powered electrically driven
power tools for raising and lowering of lantern carriage, flexible 8 core electric cable,
lightening conductor, earthing terminal, and fixing 2 nos aviation obstruction lights on top of
the mast, all complete as per approved design and drawings This is a specialised work and is
generally done by firms who specialise in such jobs. The detailed designs and estimates are
submitted by the firms alongwith their tender for checks by the Department. The cost of this
work is required to be worked out based on approved design, drawings and estimate of the
lowest tender. A separate contract for this work is concluded as the contractors for road and
bridge works generally donot undertake such jobs.)
Toll Plaza (The construction, operation and maintenance of Toll Plaza can be broken into
separate items of work as under based on the approved design and drawings:-)

VALUE

Safety Devices and signs in Construction Zones (Provision and fixing of traffic signs for limited
period at suitable locations in construction zone comprising of warning zone, approach
transition zone, working zone and terminal transition zone with a minimum distance of 60 cm
from the edge of the kerb in case of kerbed roads and 2 to 3 m from the edge of the
carriageway in case of un-kerbed roads, the bottom edge of the lowest sign plate to be not
less than 2 m above the road level, fixed on 60 mm x 60 mm x 6 mm angle iron post, founded
and installed as per approved design and drawings, removed and disposed of after completion
of construction work, all as per IRC:SP:55-2001)
Portable Barricade in Construction Zone (Installation of a steel portable barricade with
horizontal rail 300 mm wide, 2.5 m in length fitted on a 'A' frame made with 45 x 45 x 5 mm
angle iron section, 1.5 m in height, horizontal rail painted (2 coats) with yellow and white
stripes, 150 mm in width at an angle of 450, 'A' frame painted with 2 coats of yellow paint,
complete as per IRC: SP : 55-2001 )

VALUE

each

2353.00

With Steel Components (Construction of a permanent type barricade made of steel components,
1.5 m high from road level, fitted with 3 horizontal rails 200 mm wide and 4 m long on 50 x 50
x 5 mm angle iron vertical support, painted with yellow and white strips, 150 mm in width at
an angle of450, complete as per IRC:SP:55-2001 )

each

3665.00

With Wooden Components (Construction of a permanent type barricade made of wooden


components, 1.5 m high from road level, fitted with 3 horizontal planks 200 mm wide and
3.66 m long on 100 x 100mm wooden vertical post, painted with yellow and white striups,
150 mm in width at an angle of450, complete as per IRC:SP:55-2001 )

each

7574.00

With Bricks (Construction of a permanent type barricade made with brick work in mud mortar,
1.5 m high, 4 m long, 600 mm thick, plastered with cement mortar 1:6, painted with yellow
and white strips)

each

13245.00

Drum Delineator in Construction Zone (Provision of metal drum/empty bitumen drum delineator,
300 mm in diameter, 800 mm high, filled with earth for stability, painted in circumferential
strips of alternate black and white 100 mm wide fitted with reflectors 3 Nos of 7.5 cm dia, all
as per IRC:SP:55-2001)

each

373.00

Flagman (Positioning of a smart flagman with a yellow vest and a yellow cap and a red flag 600
x 600 mm securely fastened to a staff 1 m in length for guiding the traffic)

each

348.00

Permanent Type Barricade in Construction Zone

8.46

44

CHAPTER-9

PIPE CULVERTS
Item No.

9.1

9.2

A
B
9.3

A
B

Descriptions

Unit

Rate (in Rs.)

PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 mix with crushed stone aggregate 40
mm nominal size mechanically mixed, placed in foundation and compacted by vibration
including curing for 14 days.)

cum

3280.00

1000 mm dia

metre

5525.00

1200 mm dia

metre

6724.00

1000 mm dia

metre

11106.00

1200 mm dia

metre

13508.00

Laying Reinforced Cement Concrete Pipe NP4/prestrssed concrete pipe on first class bedding in
single row . (Laying Reinforced cement concrete pipe NP4/prestrssed concrete pipe for culverts
on first class bedding of granular material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets . )

Laying Reinforced Cement Concrete Pipe NP 4 /prestrssed concrete pipe on first class bedding
in double row . (Laying Reinforced cement concrete pipe NP4 /prestrssed concrete pipe for
culverts on first class bedding of granular material in double row including fixing collar with
cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and
masonry works in head walls and parapets . )

45

CHAPTER-10

MAINTENANCE OF ROADS
Item No.
10.1

10.2

10.3
10.4

10.5

Descriptions
Restoration of Rain Cuts (Restoration of rain cuts with soil, moorum, gravel or a mixture of
these, clearing the loose soil, benching for 300 mm width, laying fresh material in layers not
exceeding 250 mm and compacting with plate compactor or power rammers to restore the
original alignment, levels and slopes)
Maintenance of Earthen Shoulder (filling with fresh soil) (Making up loss of material/
irregularities on shoulder to the design level by adding fresh approved soil and compacting it
with appropriate equipment.)
Maintenance of Earth Shoulder (stripping excess soil) (Stripping excess soil from the shoulder
surface to achieve the approved level and compacting with plate compactor)
Filling Pot- holes and Patch Repairs with open - graded Premix surfacing, 20mm. (Removal of
all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of
surface, painting of tack coat on the sides and base of excavation as per clause 503, back
filling the pot holes with hot bituminous material as per clause 511, compacting, trimming and
finishing the surface to form a smooth continuous surface, all as per clause 3004.2)

Unit

Rate (in Rs.)

cum

92.00

sqm

39.00

sqm

14.00

sqm

123.00

Filling Pot- holes and Patch Repairs with - Bituminous concrete, 40mm. (Removal of all failed
material, trimming of completed excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot
holes with hot bituminous material as per clause 504, compacting, trimming and finishing the
surface to form a smooth continuous surface, all as per clause 3004.2)

(i)

for grading I Material

sqm

(ii)

for grading II Material

sqm

309.00
303.00

10.6

Crack Filling (Filling of crack using slow - curing bitumen emulsion and applying crusher dust in
case crack are wider than 3mm.)

metre

3.60

10.7

Dusting (Applying crusher dust to areas of road where bleeding of excess bitumen has
occurred.)

sqm

0.70

Fog Seal (ref item 5.17)

sqm

35.00

10.8 A
B

Crack Prevention courses. (ref item 5.21)

(i)

Stress Absorbing Membrane (SAM) crack width less than 6 mm

sqm

(ii)

Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm

sqm

47.00
57.00

Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above 50 %

sqm

75.00

Bitumen Impregnated Geotextile

sqm

125.00

sqm

61.00
43.00
26.00

(iii)
(iv)
C
(i)
(ii)
(iii)
D

Slurry Seal (ref item 5.15)


5 mm thickness
3 mm thickness

sqm

1.5 mm thickness

sqm

Surface Dressing for maintance works. (ref item 5.9)

(i)

19 mm nominal chipping size

sqm

(ii)

13 mm nominal size chipping

sqm

71.00
57.00

Repair of joint Grooves with Epoxy Mortar Repair of spalled joint grooves of contraction joints,
longitudinal joints and expansion joints in concrete pavements using epoxy mortar or epoxy
concrete)

metre

380.00

10.10

Repair of old Joints Sealant (Removal of existing sealant and re sealing of contraction,
longitudinal or expansion joints in concrete pavement with fresh sealant material)

metre

21.20

10.11

Hill Side Drain Clearance (Removal of earth from the choked hill side drain and disposing it on
the valley side manually)

metre

29.10

10.12

Land Slide Clearance in soil (Clearance of land slides in soil and ordinary rock by a bull-dozer D
80 A-12, 180 HP and disposal of the same on the valley side)

cum

66.00

10.13

Land slide Clearance in Hard Rock Requiring Blasting (Clearing of land slide in hard rock
requiring blasting for 50% of the boulders and disposal of the same on the valley side.)

cum

115.00

10.14

Snow Clearance on Roads with Dozer (Snow clearance from road surface by a bull- dozer 165
Hp and disposing it on the valley side)

cum

4.60

10.15

Snow Clearance on Roads with Snow Blowers (Snow clearance from road surface by a snow
blower and disposing on the valley side.)

cum

#VALUE!

10.9

46

CHAPTER-11

HORTICULTURE
Item No.
11.1

11.2

Descriptions

Unit

Rate (in Rs.)

Spreading of Sludge Farm Yard Manure or/and good Earth (Spreading of sludge farm yard
manure or/ and good earth in required thickness (cost of sludge, farm- yard manure or/and
good earth to be paid for separately))

cum

18.60

Grassing with ' Doobs' Grass (Grassing with 'Doobs' grass including watering and maintenance
of the lawn for 30 days or more till the grass forms a thick lawn free from weeds and fit for
moving including supplying good earth if needed)

(i)

In rows 15 cm apart in either direction

sqm

(ii)

In rows 7.5 cm apart in either direction


Making Lawns including Ploughing and Dragging with 'Swagha' Breaking of Clod (Making lawns
including ploughing and breaking of clod, removal of rubbish, dressing and supplying doobs
grass roots and planting at 15 cm apart, including supplying and spreading of farm yard
manure at rate of 0.18 cum per 100 sqm)
Maintenance of Lawns or Turfing of Slopes (Maintenance of lawns or Turfing of slopes (rough
grassing)
for a period of one year including watering etc)

sqm

9.50
15.00

sqm

10.10

sqm

230.00

sqm

15.80

sqm

176.00

metre

266.00

metre

11.3

11.4
11.5

11.6
11.7

(b)
11.8
(b)
11.9

11.10

11.11

11.12

Turfing Lawns with Fine Grassing including Ploughing, Dressing (Turfing lawns with fine
grassing including ploughing, dressing including breaking of clods, removal of rubbish,
dressing and supplying doobs grass roots at 10 cm apart, including supplying and spreading of
farm yard manure at rate of0.6 cum per 100 sqm)
Maintenance of Lawns with Fine Grassing for the First Year
a) Planting Permanent Hedges including Digging of Trenches (Planting permanent hedges
including digging of trenches, 60 cm wide and 45 cm deep, refilling the excavated earth mixed
with farmyard manure, supplied at the rate of 4.65 cum per 100 metres and supplying and
planting hedge plants at 30 cm apart)
Maintenance of Hedge for one year

km

188.00
69210.00
164670.00

Planting of Trees and their Maintenance for one Year (Planting of trees by the road side
(Avenue trees) in 0.60 m dia holes, 1 m deep dug in the ground, mixing the soil with decayed
farm yard/sludge mannure, planting the saplings, backfilling the trench, watering, fixing the
tree guard and maintaining the plants for one year)

each

858.00

Renovation Lawns including, Weeding, Forking the Ground, Top Dressing with Forked Soil
(Renovation lawns including, weeding, forking the ground, top dressing with forked soil,
watering and maintenance the lawns, for 30 days or more, till the grass forms a thick lawn,
free from weeds, and fit for moving and disposal of rubbish as directed, including supplying
good earth, if needed but excluding the cost of well decayed farm yard manure)

sqm

15.10

cum

640.00

quintal

VALUE

cum

VALUE

each

1618.00

metre

33.30

Making Tree Guard 53 cm dia and 1.3 m high as per design from empty bitumen drum (Making
tree guard 53 cm dia and 1.3 m high as per design from empty bitumen drum, slit suitably to
permit sun and air, (supplied by the department at stock issue rate)
including providing and
fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets, complete in all respect)

each

378.00

Making Tree Guard 53 cm dia and 2 metres high as per design from empty bitumen drums
(Making tree guard 53 cm dia and 2 metres high as per design from empty bitumen drums, slit
suitably to permit sun and air, ( supplied by the department at stock issue rate)
including
providing and fixing four legs 40 cm long of 30 x 3 mm MS riveted to tree guard and providing
and fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets complete in all respects)

each

746.00

a)

Planting Flowering Plants and Shrubs in Central Verge

km

Maintenance of Flowering Plants and Shrubs in Central Verge for one Year

Supply at Site Well Decayed Farm Yard Manure (Supply at site of work well decayed farm yard
manure, from any available source, approved by the engineer in charge including screening
and stacking)
Supply at Site of Work/ Store - Deoiled Neem Cake (Supply at site of work/ store- deoiled neem
cake duly packed in used gunny bags)

11.13

Supplying Sludge (Supplying sludge duly stacked at site/ store)

11.14

Half Brick Circular Tree Guard, in 2nd class Brick, internal diametre 1.25 metres, and height
1.2 metres, above ground and 0.20 metre below ground (Half brick circular tree guard, in 2nd
class brick, internal diametre 1.25 metres, and height 1.2 metres, above ground and 0.20
metre below ground, bottom two courses laid dry, and top three courses in cement mortar 1:6
( 1 cement 6 sand)
and the intermediate courses being in dry honey comb masonry, as per
design complete)
Edging with 2nd class Bricks, laid dry lengthwise (Edging with 2nd class bricks, laid dry
lengthwise, including excavation, refilling, consolidation, with a hand packing and spreading
nearly surplus earth within a lead of 50 metres)

11.15

11.16

11.17

47

11.18

11.19

11.20

11.21

Wrought Iron and Mild Steel Welded Work (Wrought iron and mild steel welded work) (using
angles, square bars, tees and channel grills, grating frames, gates and tree guards of any
size and design etc. including cost of screens and welding rods or bolts and nuts complete fixed
in position but without the cost of excavation and concrete for fixing which will be paid
separately)
Tree Guard with MS Iron (Providing and fixing MS iron tree guard 60 cm dia and 2 metre high
above ground level formed of 4 Nos (25 x 6 mm) and 8 Nos (25 x 3 mm) vertical MS riveted to
3 Nos (25 x 6 mm) iron rings in two halves, bolted together with 8 mm dia and 30 mm long
bolts including painting two coats with paint of approved brand over a coat of priming,
complete in all respects.)

quintal

6641.00

each tree
guard

1605.00

Tree Guard with MS Angle Iron and Steel Wire (Providing and fixing tree guard 0.60 metre
square, 2.00 metre high fabricated with MS angle iron 30 x 30 x 3 mm, MS iron 25 x 3 mm
and steel wire3 mm dia welded and fabricated as per design in two halves bolted together)

each tree
guard

2127.00

Compensatory Afforestation (Planting trees as compensatory afforestation at the rate of 290


trees per hectare at a spacing of 6 m by grubbing and leveling the ground upto a depth of 150
mm, digging holes 0.9 m dia, 1 m deep, mixing farm yard/sludge manure with soil, planting
of sapling 2 m high with 25 cm dia stem, backfilling the hole and watering)

hectare

101241.00

48

CHAPTER-12

FOUNDATIONS
Item No.
12.1

Descriptions

Excavation for Structures (Earth work in excavation of foundation of structures as per drawing
and technical specification, including setting out, construction of shoring and bracing, removal
of stumps and other deleterious matter, dressing of sides and bottom and backfilling with
approved material.)
Ordinary soil

Unit

Rate (in Rs.)

111.00
143.00
190.00

Manual Means

(i)

upto 3 m depth

cum

(ii)

3 m to 6 m depth

cum

(iii)

Above 6 m depth

cum

Mechanical Means

(i)

Depth upto 3 m

cum

(ii)

Depth 3 m to 6 m

cum

Depth above 6m

cum

(iii)
II

Ordinary rock (not requiring blasting)

63.00
72.00
87.00

Manual Means

(i)

Depth upto 3 m

cum

Mechanical Means

cum

159.00
80.00

III

Hard rock ( requiring blasting )


cum

404.00

cum

401.00

cum

Manual Means

IV

Hard rock ( blasting prohibited )

Mechanical Means

Marshy soil

(i)

upto 3 m depth

Manual means

Mechanical Means

cum

VI

Back Filling in Marshy Foundation Pits

cum

380.00
150.00
237.00

cum

293.00

12.2

Filling Annular Space Around Footing in Rock (Lean cement concrete 1:3:6 nominal mix. Rate
may be taken as per items 13.4.)

12.3

Sand Filling in Foundation Trenches as per Drawing & Technical Specification

12.4

cum

3762.00

(i)

PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed
stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted
by vibration including curing for 14 days.)
Brick masonry work in cement mortar in foundation complete excluding pointing and plastering,
as per drawing and technical specifications
Rate for Brick Work in C. M. 1:2 in foundation

cum

(ii)

Rate for Brick Work in C. M. 1:3 in foundation

cum

5582.00
5312.00
5128.00
4951.00
3096.00
3915.00
2538.00
2002.00

12.5

(iii)

Rate for Brick Work in C. M. 1:4 in foundation

cum

(iv)

Rate for Brick Work in C. M. 1:6 in foundation

cum

12.6 A

Cement mortar1:3 (1cement :3 sand)

cum

Cement mortar1:2 (1cement :2 sand)

cum

Cement mortar1:4 (1cement :4 sand)

cum

Cement mortar1:6 (1cement :6 sand)

cum

12.7

Stone masonry work in cement mortar 1:3 in foundation complete as drawing and Technical
Specification

(a)

Square Rubble Coursed rubble masonry( first sort )

cum

(b)

Random Rubble Masonry

cum

12.8

3200.00
3093.00

Plain/Reinforced cement concrete in open foundation complete as per drawing and technical
specifications

PCC Grade M15

cum

PCC Grade M20

cum

4109.00
4610.00

RCC Grade M20


cum

4635.00

Case I

Using concrete mixer

49

Case II
D

With Batching Plant, Transit Mixer and Concrete Pump

cum

4453.00
5010.00
4831.00

PCC Grade M25

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

RCC Grade M25

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

PCC Grade M30

Case I

Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Concrete Pump

cum

5043.00
4860.00

RCC Grade M30

Case I

Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Concrete Pump

cum

5040.00
4858.00

5053.00
4872.00

RCC Grade M35

Case I

Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Concrete Pump


Providing and constructing temporary island 16 m diameter for construction of well foundation
for 8m dia. Well.
Assuming depth of water 1.0 m and height of island to be 1.25m including Royalty for earth @
Rs. 3768.00 for each Island.
Assuming depth of water 4.0 m and height of island 4.5 m including Royalty for earth @ Rs.
13565.00 for each Island.

cum

5142.00
4962.00

each

37270.00

each

158842.00

metre

3051.00

tonne

74826.00

5349.00
5136.00

12.9
A
B
C

12.10
12.11
A
(i)

Providing and constructing one span service road to reach island location from one pier location
to another pier location including Royalty for earth @ Rs. 225.00 per m for service Road.
Providing and laying cutting edge of mild steel weighing 40 kg per metre for well foundation
complete as per drawing and technical specification.
Plain/Reinforced cement concrete, in well foundation complete as per drawing and technical
specification
Well curb
RCC M20 Grade

Case I

Using concrete mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

(ii)

RCC M25 Grade

Case I

Using concrete mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

(iii)

RCC M35 Grade

Case I

Using concrete mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

PCC M15 Grade

cum

(ii)

PCC M20 Grade

cum

Using concrete mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

Using concrete mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

5313.00
5121.00

RCC M25 Grade

Case I

Using concrete mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

(vi)

4904.00
4708.00

PCC M25 Grade

Case I
(v)

4347.00
4876.00

RCC M20 Grade

Case I
(iv)

5991.00
6095.00

Well steining

(I)
(iii)

5831.00
5620.00

5345.00
5152.00

PCC M30 Grade

Case I

Using concrete mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

50

5360.00
5164.00

(vii)

RCC M30 Grade

Case I

Using concrete mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

(viii)

RCC M35 Grade

Case I

Using concrete mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

(ix)
C
(i)

RCC M40 Grade


PCC Grade M20
Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Crane/concrete pump

cum

Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Crane/concrete pump

cum

Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Crane/concrete pump

cum

Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Crane/concrete pump

cum

Intermediate plug

(I)

Grade M20 PCC

Case I

Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Crane/concrete pump

cum

5734.00
5243.00

5105.00
4638.00

Grade M25 PCC

Case I

Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Crane/concrete pump

cum

(iii)

5629.00
5140.00

PCC Grade M35

Case I

(ii)

5583.00
5093.00

PCC Grade M30

Case I
(iv)

5330.00
4842.00

PCC Grade M25

Case I
(iii)

5492.00
5587.00
5655.00

Bottom Plug

Case I
(ii)

5371.00
5179.00

5347.00
4877.00

Grade M30 PCC

Case I

Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Crane/concrete pump

cum

5390.00
4923.00

cum

3952.00

cum

4433.00
4830.00
4656.00

E
(i)
Case I
(ii)
Case I
(iii)

Top plug
Grade M15 PCC
Using Concrete Mixer
Grade M20 PCC
Using Concrete Mixer
Grade M25 PCC

Case I

Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Crane/concrete pump

cum

(iv)

Grade M30 PCC

Case I

Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Crane/concrete pump

cum

F
(i)

Well cap
RCC Grade M20

Case I

Using concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Concrete Pump

cum

(ii)

Using concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Concrete Pump

cum

5040.00
4859.00

RCC Grade M30

Case I

Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Concrete Pump

cum

(iv)

4591.00
4407.00

RCC Grade M25

Case I
(iii)

4873.00
4694.00

RCC Grade M35

51

5053.00
4872.00

Case I

Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Concrete Pump

cum

RCC M40 Grade

cum

(v)
12.12

5142.00
4962.00
5332.00

Sinking of 6 m external diameter well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.
Sandy soil

(i)

Depth below bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

4655.00
6709.00

metre

8860.00

metre

16620.00

(iii)
a
(iv)
a
b
(v)
a
b
B

Beyond 10m upto 20m


Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .

19944.00
metre

39487.00
metre

47384.00

Clayey soil ( 6m dia. Well )

(i)

Depth below bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

6734.00
15020.00

metre

19837.00

metre

20829.00

(iii)
a
b
(iv)
a
b
c
(v)
a
b
c
C

Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add for dewatering @ 5% of cost, if required.
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 5% of cost for dewatering of the cost, if required

metre

37211.00

metre

48840.00

Add 25% of cost for Kentledge including supports, loading arrangement and Labour ).

metre

46514.00

Beyond 30m upto 40 m


Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 5% of cost for dewatering, if required

metre

88409.00

metre

111395.00

Add 20% of cost for Kentledge including supports, loading arrangement and Labour).

metre

106091.00

metre

18828.00

metre

20665.00

Soft rock (6m dia well )

(i)

Depth of soft rock strata upto 3m

Hard rock (6m dia well )

(i)

Depth of soft rock strata upto 3m

12.13

Sinking of 7 m external diameter well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.
Sandy soil

(i)

Depth below bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

7153.00
9651.00

(iii)

Beyond 10m upto 20m


metre

12747.00

metre

23912.00

a
(iv)
a

Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
meter

52

b
(v)
a
b

Add 20% of cost for Kentledge including supports, loading arrangement and Labour) .
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc.

Clayey soil ( 7m dia. Well )

(I)

Depth below bed level upto 3.0 M

metre

28695.00

metre

56812.00

metre

68175.00

metre

(ii)

Beyond 3m upto 10m depth

metre

9651.00
15396.00

(iii)

Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add for dewatering @ 5% of cost, if required.

metre

20334.00

metre

21350.00

a
b
(iv)
a
b
c
(v)
a
b
c
C

Beyond 20m upto 30 m


Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 5% of cost for dewatering on the cost, if required

metre

38141.00

metre

50060.00

Add 25% of cost for Kentledge including supports, loading arrangement and Labour ).

metre

47677.00

Beyond 30m upto 40 m


Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 5% of cost for dewatering, if required

metre

90619.00

metre

114180.00

Soft rock ( 7m dia well )

(i)

Depth of soft rock strata upto 3m

Hard rock ( 7m dia well )

(i)

Depth upto 3 m

12.14

A
(i)
(ii)
(iii)
a
(iv)
a
b
(v)
a
b
B
(i)

108743.00

Add 20% of cost for Kentledge including supports, loading arrangement and Labour).

metre

16976.00

metre

23564.00

Depth below bed level upto 3.0 M

metre

Beyond 3m upto 10m depth

metre

8762.00
10828.00

metre

14300.00

metre

26825.00

metre

32189.00

metre

63732.00

metre

76478.00

metre

Sinking of 8 m external diameter well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.
Sandy soil

Beyond 10m upto 20m


Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc.
Clayey soil ( 8m dia. Well )

(ii)

Beyond 3m upto 10m depth

metre

11813.00
15980.00

(iii)

Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add for dewatering @ 5% of cost, if required.

metre

21105.00

metre

22160.00

metre

39588.00

metre

51959.00

a
b
(iv)
a
b

Depth upto 3.0 M

Beyond 20m upto 30 m


Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 5% of cost for dewatering on the cost, if required

53

c
(v)
a
b
c
C

Add 25% of cost for Kentledge including supports, loading arrangement and Labour ).

metre

49485.00

Beyond 30m upto 40 m


Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 5% of cost for dewatering, if required

metre

94056.00

metre

118511.00

Add 20% of cost for Kentledge including supports, loading arrangement and Labour).

metre

112868.00

metre

18747.00

metre

23737.00

Soft rock ( 8m dia well )

(i)

Depth in soft rock strata upto 3m

Hard rock ( 8m dia well )

(i)

Depth in hard rock strata upto 3 m

12.15

Sinking of 9 m external diameter well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.
Sandy soil

(i)

Depth below bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

8845.00
11883.00

metre

15693.00

metre

29436.00

metre

35324.00

metre

69936.00

metre

83923.00

(iii)
a
(iv)
a
b
(v)
a
b
B

Beyond 10m upto 20m


Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc.
Clayey soil ( 9m dia. Well )

(i)

Depth below bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

12449.00
17229.00

(iii)

Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add for dewatering @ 5% of cost, if required.

metre

22754.00

metre

23891.00

a
b
(iv)
a
b
c
(v)
a
b
c
C

Beyond 20m upto 30 m


Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 5% of cost for dewatering on the cost, if required

metre

42680.00

metre

56017.00

Add 25% of cost for Kentledge including supports, loading arrangement and Labour ).

metre

53350.00

Beyond 30m upto 40 m


Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 5% of cost for dewatering, if required

metre

101400.00

metre

127764.00

Add 20% of cost for Kentledge including supports, loading arrangement and Labour).

metre

121680.00

metre

23589.00

metre

27370.00

metre

10707.00

Soft rock ( 9m dia well )

(i)

Depth upto 3m

Hard rock ( 9m dia well )

(i)

Depth of hard rock strata upto 3 m

12.16

A
(i)

Sinking of 10 m external diameter well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.
Sandy soil
Depth below bed level upto 3.0 M

54

(ii)

Beyond 3m upto 10m depth

(iii)

Beyond 10m upto 20m


Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .

a
(iv)
a
b
(v)
a
b
B

Beyond 30m upto 40 m


Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc.

metre

12526.00

metre

16543.00

metre

31029.00

metre

37235.00

metre

73722.00

metre

88467.00

Clayey soil (10m dia. Well )

(i)

Depth below bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

13561.00
16923.00

(iii)

Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add for dewatering @ 5% of cost, if required.

metre

22350.00

metre

23468.00

a
b
(iv)
a
'b
c
(v)
a
b
c
C

Beyond 20m upto 30 m


Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 5% of cost for dewatering on the cost, if required

metre

41925.00

metre

55027.00

Add 25% of cost for Kentledge including supports, loading arrangement and Labour ).

metre

52406.00

Beyond 30m upto 40 m


Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 5% of cost for dewatering, if required

metre

99608.00

metre

125506.00

Soft rock (10m dia well )

(i)

Depth of soft rock strata upto 3m

Hard rock (10m dia well )

(i)

Depth of hard rock strata upto 3 m

12.17

119529.00

Add 20% of cost for Kentledge including supports, loading arrangement and Labour).

metre

24049.00

metre

32049.00

Sinking of 11 m external diameter well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.
Sandy soil

(i)

Depth from bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

24850.00
18991.00

(iii)

Beyond 10m upto 20m


Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .

metre

25082.00

metre

47046.00

metre

56455.00

metre

111774.00

metre

134129.00
22613.00
34833.00

a
(iv)
a
b
(v)
a
b
B

Beyond 30m upto 40 m


Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc.
Clayey soil (11 m dia. Well )

(i)

Depth from bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

(iii)

Beyond 10 m upto 20 m

55

a
b
(iv)
a
b
c
(v)
a
b
c
C

Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add for dewatering @ 5% of cost, if required.

metre

48304.00

metre

86292.00

metre

113259.00

Add 25% of cost for Kentledge including supports, loading arrangement and Labour ).

metre

107865.00

Beyond 30m upto 40 m


Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 5% of cost for dewatering, if required

metre

205018.00

metre

258323.00

Add 20% of cost for Kentledge including supports, loading arrangement and Labour).

metre

246022.00

metre

53850.00

metre

72194.00

Soft rock (11m dia well )


Depth of soft rock strata upto 3m

Hard rock (11m dia well )

(i)

Depth of hard rock upto 3 m

46004.00

Beyond 20m upto 30 m


Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 5% of cost for dewatering on the cost, if required

(i)

12.18

metre

Sinking of 12 m external diameter well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.
Sandy soil

(i)

I) Depth below bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

51027.00
56996.00

(iii)

Beyond 10m upto 20m


Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .

metre

75273.00

metre

141192.00

metre

169431.00

metre

335453.00

metre

402543.00

a
(iv)
a
b
(v)
a
b
B

Beyond 30m upto 40 m


Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc.
Clayey soil (12 m dia. Well )

(i)

Depth below bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

55651.00
87825.00

(iii)

Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add for dewatering @ 5% of cost, if required.

metre

115988.00

metre

121788.00

a
b
(iv)
a
b
c
(v)
a
b
c
C

Beyond 20m upto 30 m


Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 5% of cost for dewatering on the cost, if required

metre

217563.00

metre

285551.00

Add 25% of cost for Kentledge including supports, loading arrangement and Labour ).

metre

271954.00

Beyond 30m upto 40 m


Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 5% of cost for dewatering, if required

metre

516898.00

metre

651292.00

Add 20% of cost for Kentledge including supports, loading arrangement and Labour).

metre

620278.00

Soft rock (12m dia well )

(i)

Depth of soft rock strata upto 3m

metre

126892.00

Hard rock (12m dia well )


Depth of hard rock strata upto 3 m

metre

166019.00

(i)

56

12.19

Sinking of Twin D Type well ( other than pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown against each case, complete as per
drawing and technical specifications. Depth of sinking is reckoned from bed level.
Sandy soil

(i)

Depth from bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

11571.00
12464.00

(iii)

Beyond 10m upto 20m


Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .

metre

16460.00

metre

30875.00

metre

37051.00

metre

73355.00

metre

88026.00

a
(iv)
a
b
(v)
a
b

Beyond 30m upto 40 m


Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc.

Clayey soil (Twin D Type Well )

(i)

Depth below bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

13530.00
18783.00

(iii)

Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add for dewatering @ 5% of cost, if required.

metre

24807.00

metre

26047.00

Beyond 20m upto 30 m


Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 5% of cost for dewatering on the cost, if required

metre

46534.00

metre

61076.00

Add 25% of cost for Kentledge including supports, loading arrangement and Labour ).

metre

58167.00

Beyond 30m upto 40 m


Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
meter
Add 5% of cost for dewatering, if required

metre

110558.00

metre

139303.00

Add 20% of cost for Kentledge including supports, loading arrangement and Labour).

metre

132670.00

metre

27882.00

metre

34617.00

a
b
(iv)
a
b
c
(v)
a
b
c
C

Soft rock (Twin D Type well )

(i)

Depth of soft rock strata upto 3m

Hard rock (Twin D Type well )

(i)

Depth of hard rock strata upto 3 m

12.20
Pneumatic sinking of wells with equipment of approved design, drawing and specifications
worked by competent and trained personnel and comprising of compression and decompression
chambers, reducers, two air locks separately for men and plant & materials, arrangement for
supply of fresh air to working chambers, check valves, exhaust valves, shafts made from steel
plates of riveted construction not less than 6 mm thick to withstand an air pressure of 0.50
MPa, controlled blasting of hard rock where required, staircases and 1 m wide landing plate
forms with railing, arrangement for compression and decompression, electric lighting of 50 V
maximum, proper rooms for rest and medical examinations and compliance with safety
precautions as per IS:4138, all as per clause1207.6 of MoRTH Specifications.
12.21
12.22
12.23

12.24

Sand filling in wells complete as per drawing and technical specifications


Providing steel liner 10 mm thick for curbs and 6mm thick for steining of wells including
fabricating and setting out as per detailed drawing
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and
technical specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile
diameter-750 mm)
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and
technical specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile
diameter-1000 mm)

57

#VALUE!

cum

293.00

tonne

68101.00

metre

5290.00

metre

8638.00

12.25

12.26
12.27
12.28
12.29
12.30
12.31
12.32
12.33
12.34
12.35
12.36
12.37
12.38
A

Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and
technical specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile
diameter-1200 mm)
Driven cast-in-place vertical M35 grade R.C.C. pile excluding reinforcement complete as per
drawing and & Technical Specification (Pile diameter - 750 mm)
Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per
drawing and & Technical Specification (Pile diameter - 1000 mm)
Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per
drawing and & Technical Specification (Pile diameter - 1200 mm)
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing
and & Technical Specification (Pile Diameter=500 mm)
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing
and & Technical Specification (Pile Diameter=750 mm)
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing
and & Technical Specification (Pile Diameter=1000 mm)
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing
and & Technical Specification (Size of pile - 300 mm x 300 mm)
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing
and & Technical Specification (Size of pile - 500 mm x 500 mm)
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing
and & Technical Specification (Size of pile - 750 mm x 750 mm)
Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the
pile - H Section steel column 400 x 250 mm (ISHB Series) )
Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the
pile - H Section steel column 450 x 250 mm (ISHB Series) )
Pile load test on single vertical pile in accordance with IS:2911(Part-IV)

metre

11009.00

metre

3943.00

metre

6309.00

metre

9206.00

metre

#VALUE!

metre

#VALUE!

metre

#VALUE!

metre

#VALUE!

metre

#VALUE!

metre

#VALUE!

metre

#VALUE!

metre

#VALUE!

tonne

5300.00

4606.00
4445.00

Cement concrete for reinforced concrete in pile cap complete as per drawing and Technical
Specification
RCC Grade M20

(i)

Using Concrete Mixer

cum

(ii)

Using Batching Plant, Transit Mixer and Concrete Pump

cum

RCC Grade M25

(i)

Using concrete mixer.

cum

(ii)

Using Batching Plant, Transit Mixer and Concrete Pump

cum

5038.00
4916.00

RCC Grade M30

(i)

Using concrete mixer.

cum

(ii)

Using Batching Plant, Transit Mixer and Concrete Pump

cum

RCC Grade M35

5093.00
4932.00

(i)

Using concrete mixer.

cum

(ii)

Using Batching Plant, Transit Mixer and Concrete Pump

cum

12.39

Levelling course for Pile cap

cum

5207.00
5085.00
3934.00

12.40

Supplying, fitting and placing un-coated HYSD bar reinforcement in foundation complete as per
drawing and technical specifications
Supplying, fitting and placing un-coated Mild steel reinforcement complete in foundation as per
drawing and technical specification

tonne

55695.00

tonne

53491.00

12.41

58

CHAPTER-13

SUB-STRUCTURE
Item No.
13.1
13.2
13.3
13.4

Descriptions

Unit

Rate (in Rs.)

Brick masonry work in 1:3 in sub-structure complete excluding pointing and plastering, as per
drawing and technical specifications

cum

5309.00

Pointing with cement mortar (1:3 ) on brick work in substructure as per Technical specifications

10 sqm

536.00

10 sqm

1021.00

Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical
specifications
Stone masonry work in cement mortar 1:3 for substructure complete as per drawing and
Technical Specifications

Random Rubble Masonry

cum

Coursed rubble masonry (first sort )

cum

Ashlar masonry ( first sort )

cum

3086.00
3259.00
4256.00

cum

4347.00

cum

4876.00

5313.00
5121.00

C
13.5

Plain/Reinforced cement concrete in sub-structure complete as per drawing and technical


specifications

PCC Grade M15

(p)

Height upto 5m

PCC Grade M20

(p)

Height upto 5m

PCC Grade M25

(p)

Height upto 5m

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

(q)

Height 5m to 10m

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

(r)

Height above 10m

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

D
(p)

Height upto 5m
Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

Height upto 5m
Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

Height upto 5m
Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

5345.00
5152.00

Height 5m to 10m

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

(r)

5305.00
5094.00

RCC Grade M25

Case I
(q)

5082.00
4880.00

Height above 10m

Case I

(p)

4904.00
4708.00

Height 5m to 10m

Case I
(r)

5799.00
5586.00

RCC Grade M20

Case I
(q)

5555.00
5351.00

Height above 10m

Case I

(p)

5360.00
5164.00

Height 5m to 10m

Case I
(r)

5748.00
5540.00

PCC Grade M30

Case I
(q)

5507.00
5308.00

5520.00
5320.00

Height above 10m

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

RCC Grade M30

(p)

Height upto 5m

59

5783.00
5573.00

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

(q)

Height 5m to 10m

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

(r)

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

Height upto 5m
Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

5492.00
5587.00

Height 5m to 10m

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

(r)

5737.00
5532.00

RCC Grade M35

Case I
(q)

5522.00
5325.00

Height above 10m

Case I

(p)

5371.00
5179.00

5612.00
5709.00

Height above 10m

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

5791.00
5892.00

tonne

55828.00

tonne

52773.00

each

126.00

13.6
13.7
13.8

13.9

Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per
drawing and technical specifications
Supplying, fitting and placing Mild steel reinforcement complete in sub-structure as per
drawing and technical specification
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return
wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of
1V :20H towards drawing foce. Complete as per drawing and Technical specifications
Back filling behind abutment, wing wall and return wall complete as per drawing and Technical
specification

Granular material

cum

Sandy material

cum

546.00
471.00

Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying
the requirements laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not
less than 600 mm with smaller size towards the soil and bigger size towards the wall and
provided over the entire surface behind abutment, wing wall and return wall to the full height
compacted to a firm condition complete as per drawing and technical specification.

cum

1386.00

Supplying, fitting and fixing in position true to line and level cast steel rocker bearing
conforming to IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH specifications complete
including all accessories as per drawing and Technical Specifications.

tonne
capacity

313.00

Supplying, fitting and fixing in position true to line and level forged steel roller bearing
conforming to IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH specifications complete
including all accessories as per drawing and Technical Specifications.

tonne
capacity

209.00

Supplying, fitting and fixing in position true to line and level sliding plate bearing with PTFE
surface sliding on stainless steel complete including all accessories as per drawing and
Technical Specifications and BS: 5400, section 9.1 & 9.2 (for PTFE)
and clause 2004 of
MoRTH Specifications.

tonne
capacity

#VALUE!

13.10

13.11

13.12

13.13

13.14

13.15

13.16

Supplying, fitting and fixing in position true to line and level elastomeric bearing conforming to
cubic
IRC: 83 (Part-II) section IX and clause 2005 of MoRTH specifications complete including all
centimetre
accessories as per drawing and Technical Specifications.

0.72

Supplying, fitting and fixing in position true to line and level sliding plate bearing with stainless
steel plate sliding on stainless steel plate with mild steel matrix complete including all
accessories as per drawing and Technical Specifications.

tonne
capacity

397.00

Supplying, fitting and fixing in position true to line and level POT-PTFE bearing consisting of a
metal piston supported by a disc or unreinforced elastomer confined within a metal cylinder,
sealing rings, dust seals, PTFE surface sliding against stainless steel mating surface,
completre assembly to be of cast steel/fabricated structural steel, metal and elastomer
elements to be as per IRC: 83 part-I & II respectively and other parts conforming to BS: 5400,
section 9.1 & 9.2 and clause 2006 of MoRTH Specifications complete asper drawing and
approved technical specifications.

tonne
capacity

179.00

60

CHAPTER-14

SUPER-STRUCTURE
Item No.
14.1
A
Case I

Descriptions

Unit

Rate (in Rs.)

5297.00
5518.00
5738.00

Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure as per


drawing and Technical Specification
RCC Grade M20
Using Concrete Mixer

(i)

For solid slab super-structure, 20-30% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(ii)

For T-beam & slab, 25-35% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

Height above 10m

cum

(r)
Case II

Using Batching Plant, Transit Mixer and Concrete Pump

(i)

For solid slab super-structure, 20-30% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

(ii)

For T-beam & slab, 25-35% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

RCC Grade M25

Case I

For solid slab super-structure, 20-30% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(ii)

For T-beam & slab, 25-35% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

Height above 10m

cum

(r)

For solid slab super-structure, 20-30% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(ii)

For T-beam & slab, 25-35% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

RCC Grade M 30
For solid slab super-structure, 20-30% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(ii)

For T-beam & slab, 25-35% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

Height above 10m

cum

Case II

5796.00
6037.00
6279.00
6037.00
6279.00
6520.00

5589.00
5822.00
6054.00
5822.00
6054.00
6287.00

Using Concrete Mixer

(i)

(r)

5296.00
5508.00
5720.00

Using Batching Plant, Transit Mixer and Concrete Pump

(i)

Case I

5085.00
5296.00
5508.00

Using Concrete Mixer

(i)

Case II

5518.00
5738.00
5959.00

Using Batching Plant, Transit Mixer and Concrete Pump.

61

5884.00
6129.00
6374.00
6129.00
6374.00
6620.00

(i)

For solid slab super-structure, 20-30% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(ii)

For T-beam & slab, 25-35% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

RCC/PSC Grade M35

Case 1

Using concrete mixer.

(i)

For solid slab super-structure, 18-28% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(ii)

For T-beam & slab, 23-33% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(iii)

For box girder and balanced cantilever, 38-58% of cost of concrete.

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

Height above 10m

cum

(r)
Case II
(i)

For solid slab super-structure, 18-28% of (a+b+c)


Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(ii)

For T-beam & slab, 23-33% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(iii)

For box girder and balanced cantilever, 38-58% of cost of concrete.

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

PSC Grade M-40


For solid slab super-structure, 20-30% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(ii)

For T-beam & slab, 25-35% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

Height above 10m

cum

(r)

5916.00
6166.00
6417.00
6166.00
6417.00
6668.00
6918.00
7420.00
7921.00

5688.00
5929.00
6170.00
5929.00
6170.00
6411.00
6652.00
7134.00
7616.00

Using concrete mixer.

(i)

Case II

5889.00
6124.00
6360.00

Using Batching Plant, Transit Mixer and Concrete Pump

(p)

Case 1

5653.00
5889.00
6124.00

6450.00
6719.00
6988.00
6719.00
6988.00
7256.00

Using Batching Plant, Transit Mixer and Concrete Pump

(i)

For solid slab super-structure, 18-28% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(ii)

For T-beam & slab, 23-33% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(iii)

For box girder and balanced cantilever, 38-58% of cost of concrete.

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

62

6076.00
6333.00
6590.00
6333.00
6590.00
6848.00
7105.00
7620.00
8135.00

F
(i)

PSC Grade M-45


For solid slab/voided slab super-structure, 16-26% of cost of concrete (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

cum

(p)

Height above 10m


For I-beam & slab including launching of precast girders by launching truss upto 40 m span, 2131% of cost of concrete.
Height upto 5m

(q)

Height 5m to 10m

cum

(r)

cum

(p)

Height above 10m


For cast-in-situ box girder, segmental construction and balanced cantilever, 36-56% of cost of
concrete.
Height upto 5m

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

(p)

PSC Grade M-50


For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55% of cost of
concrete
Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

PSC Grade M- 55

(i)

For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55% of cost of
concrete

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

7993.00
8585.00
9177.00

tonne

56975.00

tonne

112231.00

cum

9030.00

sqm

#VALUE!

Construction of precast RCC railing of M30 Grade, aggregate size not exceeding 12 mm, true
to line and grade, tolurence of vertical RCC post not to exceed 1 in 500, centre to centre
spacing between vertical post not to exceed 2000 mm, leaving adequate space between
vertical post for expansion, complete as per approved drawings and technical specifications.

metre

1521.00

Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to
line and grade, tolurence of vertical RCC post not to exceed 1 in 500, centre to centre spacing
between vertical post not to exceed 2000 mm, leaving adequate space between vertical post
for expansion, complete as per approved drawings and technical specifications.

metre

1477.00

14.8

Providing, fitting and fixing mild steel railing complete as per drawing and Technical
Specification

metre

2670.00

14.9

Drainage Spouts complete as per drawing and Technical specification

each

879.00

14.10

PCC M15 Grade leveling course below approach slab complete as per drawing and Technical
specification
Reinforced cement concrete approach slab including reinforcement and formwork complete as
per drawing and Technical specification
Providing anti-corrosive treatment to HYSD reinforcement with Fusion Bonded Epoxy Coating
(FBEC)
(To be taken as per the prevailing market rates.)
Precast - pretensioned Girders (Providing, precasting, transportation and placing in position
precast pretensioned concrete girders as per drawing and technical specifications)

cum

3952.00

cum

7651.00

tonne

VALUE

cum

#VALUE!

metre

#VALUE!

(ii)

(iii)

(i)

14.2
14.3
14.4
14.5

14.6

14.7

14.11
14.12
14.13
14.14

a)
Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per
drawing and technical specifications
High tensile steel wires/strands including all accessories for stressing, stressing operations and
grouting complete as per drawing and Technical Specifications
Providing and laying Cement concrete wearing coat M-30 grade including reinforcement
complete as per drawing and Technical Specifications
Mastic Asphalt (Providing and laying 12 mm thick mastic asphalt wearing course on top of deck
slab excluding prime coat with paving grade bitumen meeting the requirements given in table
500-29, prepared by using mastic cooker and laid to required level and slope after cleaning the
surface, including providing antiskid surface with bitumen precoated fine grained hard stone
chipping of 9.5 mm nominal size at the rate of 0.005cum per 10 sqm and at an approximate
spacing of 10 cm center to center in both directions, pressed into surface when the
temperature of surfaces not less than 100 deg. C, protruding 1 mm to 4 mm over mastic
surface, all complete as per clause 515.)

Providing and fixing Helical pipes in voided concrete slabs

63

cum

cum

6289.00
6560.00
6831.00

6560.00
6831.00
7102.00

7373.00
7915.00
8457.00

7581.00
8143.00
8705.00

14.15

14.16

14.17

14.18
(i)
(ii)
(iii)

(iv)
14.19

14.20

14.21

14.22

14.23

14.24

Crash Barriers (The rate analysis for rigid crash barrier in reinforced cement concrete, semirigid crash barrier with metal beam and flexible crash barrier with wire ropes have been made
and included in chapter-8 on Traffic and Transportation.)
Painting on concrete surface (Providing and applying 2 coats of water based cement paint to
unplastered concrete surface after cleaning the surface of dirt, dust, oil, grease,
efflorescence and applying paint @ of 1 litre for 2 Sq.m. )
Burried Joint (Providing and laying a burried expansion joint, expansion gap being 20 mm,
covered with 12 mm thick, 200 mm wide galvanised wieldable structural steel plate as per IS:
2062, placed symmetrical to centre line of the joint, resting freely over the top surface of the
deck concrete, welding of 8 mm dia. 100 mm long galvanised nails spaced 300 mm c/c along
the centre line of the plate, all as specified in clause 2604.)
Filler joint
Providing & fixing 2 mm thick corrugated copper plate in expansion joint complete as per
drawing & Technical Specification.
Providing & fixing 20 mm thick compressible fibre board in expansion joint complete as per
drawing & Technical Specification.
Providing and fixing in position 20 mm thick premoulded joint filler in expansion joint for fixed
ends of simply supported spans not exceeding 10 m to cater for a horizontal movement upto 20
mm, covered with sealant complete as per drawing and technical specifications.
Providing and filling joint sealing compound as per drawings and technical specifications with
coarse sand and 6% bitumen by weight
Asphaltic Plug joint (Providing and laying of asphaltic plug joint to provide for horizontal
movement of 25 mm and vertical movement of 2 mm, depth of joint varying from 75 mm to
100 mm, width varying from 500 mm to 750 mm (in traffic direction), covered with a closure
plate of 200mm x 6mm of wieldable structural steel conforming to IS: 2062, asphaltic plug to
consist of polymer modified bitumen binder, carefully selected single size aggregate of 12.5
mm nominal size and a heat resistant foam caulking/backer rod, all as per approved drawings
and specifications.)
Elastomeric Slab Steel Expansion Joint (Providing and laying of an elastomeric slab steel
expansion joint, catering to right or skew (less than 20 deg., moderately curved with
maximum horizontal movement upto 50 mm, complete as per approved drawings and standard
specifications to be installed by the manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions for installation and clause 2606 of
MoRTH specifications for road & bridge works.)
Compression Seal Joint (Providing and laying of compression seal joint consisting of steel
armoured nosing at two edges of the joint gap suitably anchored to the deck concrete and a
preformed chloroprene elastomer or closed cell foam joint sealer compressed and fixed into the
joint gap with special adhesive binder to cater for a horizontal movement upto 40 mm and
vertical movement of 3 mm.)
Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint catering to
maximum horizontal movement upto 70 mm, complete as per approved drawings and standard
specifications to be installed by the manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions for installation.)
Modular Strip / Box Seal Joint (Providing and laying of a modular strip Box steel expansion joint
including anchorage catering to a horizontal movement beyond 70 mm and upto 140mm,
complete as per approved drawings and standard specifications to be installed by the
manufacturer/supplier or their authorised representative ensuring compliance to the
manufacturer's instructions for installation.)
Modular Strip / Box Seal Joint (Providing and laying of a modular strip box seal expansion joint
catering to a horizontal movement beyond 140mm and upto 210mm, complete as per
approved drawings and standard specifications to be installed by the manufacturer/supplier or
their authorised representative ensuring compliance to the manufacturer's instructions for
installation.)

64

metre

VALUE

metre

75.00

metre

1289.00

metre

3065.00

metre

214.00

metre

301.00

metre

20.80

metre

960.00

metre

28086.00

metre

#VALUE!

metre

8763.00

metre

29472.00

metre

#VALUE!

CHAPTER-15

RIVER TRAINING AND PROTECTION WORKS


Item No.
15.1

A
15.2

15.3

15.4

A
B

Descriptions
Providing and laying boulders apron on river bed for protection against scour with stone
boulders weighing not less than 40 kg each complete as per drawing and Technical
specification.
Boulder laid dry without wire crates.
Boulder apron laid in wire crates (Providing and laying of boulder apron laid in wire crates
made with 4mm dia GI wire conforming to IS: 280 & IS:4826 in 100mm x 100mm mesh
(weaved diagonally) including 10% extra for laps and joints laid with stone boulders weighing
not less than 40 kg each.)
Cement concrete blocks (size 0.5 x 0.5 x 0.5 m) (Providing and laying of apron with cement
concrete blocks of size 0.5x0.5x0.5 m cast in-situ and made with nominal mix of M-15 grade
cement concrete with a minimum cement content of 250 kg/cum as per IRC: 21-2000.)

Unit

Rate (in Rs.)

cum

1060.00

cum

1327.00

cum

4191.00

cum

1060.00

cum

4191.00

Providing and laying Pitching on slopes laid over prepared filter media including boulder apron
laid dry in front of toe of embankment complete as per drawing and Technical specifications
Stone/Boulder
Cement Concrete blocks of size 0.3x0.3 x0.3 m cast in cement concrete of Grade M15

15.5

Providing and laying Filter material underneath pitching in slopes complete as per drawing and
Technical specification

cum

1546.00

15.6

Geotextile Filter (Laying of a geotextile filter between pitching and embankment slopes on
which pitching is laid to prevent escape of the embankment material through the voids of the
stone pitching/cement concrete blocks as well as to allow free movement of water without
creating any uplift head on the pitching.)

sqm

144.00

Providing and laying Flooring complete as per drawing and Technical specifications laid over
cement concrete bedding.
Rubble stone laid in cement mortar 1:3

cum

Cement Concrete blocks Grade M15

cum

15.9

Dry rubble Flooring

cum

3748.00
5520.00
1388.00

15.10

Curtain wall complete as per drawing and Technical specification

15.7

15.8

Toe protection (A toe wall for toe protection can either be in dry rubble masonry in case of dry
rubble pitching or pitching with stones in wire crates or it can be in PCC M15 nominal mix if
cement concrete block have been used for pitching . Rates for toe wall can be adopted from
respective clauses depending upon approved design. The rate for excavation for foundation,
dry rubble masonry and PCC M15 have been analysed and given in respective chapters.)

Stone masonry in cement mortar (1:3)

cum

Cement concrete Grade M15

cum

3200.00
4109.00

cum

1102.00

cum

1330.00

cum

1942.00

15.11
15.12

15.13

Flexible Apron :Construction of flexible apron 1 m thick comprising of loose stone boulders
weighing not less than 40 kg beyond curtain wall.
Gabian Structure for Retaining Earth (Providing and construction of a gabain structure for
retaining earth with segments of wire crates of size 7 m x 3 m x 0.6 m each divided into 1.5 m
compartments by cross netting, made from 4 mm galvanised steel wire @ 32 kg per 10 sqm
having minimum tensile strength of 300 Mpa conforming to IS:280 and galvanizing coating
conforming to IS:4826, woven into mesh with double twist, mesh size not exceeding 100 x
100 mm, filled with boulders with least dimension of 200 mm, all loose ends to be tied with 4
mm galvanised steel wire)
Gabian Structure for Erosion Control, River Training Works and Protection works (Providing and
constructing gabain structures for erosion control, river training works and protection works
with wire crates of size 2 m x 1 m x 0.3 m each divided into 1m compartments by cross netting,
made from 4 mm galvanised steel wire @ 32 kg per 10 sqm having minimum tensile strength of
300 Mpa conforming to IS:280 and galvanizing coating conforming to IS:4826, woven into
mesh with double twist, mesh size not exceeding 100 mm x 100 mm, filled with boulders with
least dimension of 200 mm, all loose ends to be securely tied with 4 mm galvanised steel
wire.)

65

CHAPTER-16

REPAIR AND REHABILITATION


Item No.

Descriptions

Unit

Rate (in Rs.)

Removal of existing cement concrete wearing coat including its disposal complete as per
Technical specification without causing any detrimental effect to any part of the bridge structure
and removal of dismantled material with all lifts and lead upto 1000m (Thickness 75 mm)

sqm

88.00

Removal of existing asphaltic wearing coat comprising of 50 mm thick asphaltic concrete laid
over 12 mm thick mastic asphalt including disposal with all lift and lead upto 1000m.

sqm

66.00

Guniting concrete surface with cement mortar applied with compressor after cleaning surface
and spraying with epoxy complete as per Technical specification

sqm

#VALUE!

Providing and inserting nipples with approved fixing compound after drilling holes for grouting
as per Technical specifications including subsequent cutting/removal and sealing of the hole as
necessary of nipples after completion of grouting with Cement/Epoxy

each

104.00

kg
kg

128.00
123.00

Patching of damaged concrete surface with polymer concrete and curing compounds, initiator
and promoter, available in present formulations, to be applied as per instructions of
manufacturer and as approved by the Engineer.

sqm

#VALUE!

16.7

Sealing of crack / porous concrete with Epoxy Grout by injection through nipples complete as
per clause 2803.1.

kg

#VALUE!

16.8

Applying epoxy mortar over leached, honey combed and spalled concrete surface and exposed
steel reinforcement complete as per Technical specification

sqm

413.00

Removal of defective concrete, cleaning the surface thoroughly, applying the shotcrete mixture
mechanically with compressed air under pressure, comprising of cement, sand, coarse
aggregates, water and quick setting compound in the proportion as per clause 2807.1., sand
and coarse aggregates conforming to IS: 383 and table 1 of IS: 9012 respectively, water
cement ratio ranging from 0.35 to 0.50, density of gunite not less than 2000 kg/cum, strength
not less than 25 Mpa and workmanship conforming to clause 2807.6.

sqm

#VALUE!

Applying pre-packed cement based polymer mortar of strength 45 Mpa at 28 days for
replacement of spalled concrete

sqm

#VALUE!

16.11

Eproxy bonding of new concrete to old concrete

sqm

607.00

16.12

Providing external prestressing with high tensile steel wires/strands including drilling for
passage of prestessing steel, all accessories for stressing and stressing operation and grouting
complete as per drawing and Technical specification

tonne

295177.00

Providing external prestressing with high tensile steel wires/strands including drilling for
passage of prestessing steel, all accessories for stressing and stressing operation and grouting
complete as per drawing and Technical specification

tonne

285273.00

Providing external prestressing with high tensile steel wires/strands including drilling for
passage of prestessing steel, all accessories for stressing and stressing operation and grouting
complete as per drawing and Technical specification

tonne

277463.00

16.1

16.2

16.3
16.4

16.5
A
B
16.6

16.9

16.10

16.13

16.14

Sealing of cracks/porous concrete by injection process through nipples/Grouting complete as


per Technical specification.
Cement Grout
Cement mortar (1:1) Grouting

16.15

Replacement of bearings complete as per Technical specification

each

#VALUE!

16.16

Rectification of bearings as per Technical specifications

each

#VALUE!

16.17

Replacement of Expansion Joints complete as per drawings

metre

2271.00

16.18

Replacement of damaged concrete railing.

metre

190.00

16.19

Replacement of crash barrier.

metre

355.00

16.20

Replacement of damaged mild steel railing

metre

157.00

16.21

Repair of crash barrier (Repair of concrete crash barrier with cement concrete of M-30 grade by
cutting and trimming the damaged portion to a regular shape, cleaning the area to be repaired
thoroughly, applying cement concrete after erection of proper form work.)

metre

209.00

Repair of RCC Railing (Carrying out repair of RCC M30 railing to bring it to the original shape.)

metre

143.00

Repair of steel Railing (Repair of steel railing to bring it to the original shape)

metre

245.00

16.22
16.23

66

CHAPTER - 1
CARRIAGE OF MATERIALS
Sr
No

Ref. to
MoRTH
Spec.

Description

1.1

Unit Quantity Rate Rs

Cost Rs

Remarks
/ Input
ref.

cum
Loading and Unloading of Stone Boulder/ Stone
aggregates/Sand/ Kanker/Moorum
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage
and return trip

Unit = cum
Taking output = 5.5 cum
Time required for
i)

Positioning of tipper at loading point

1 Min

ii)
Loading by front end loader 1 cum bucket capacity @ 25
cum per hour
iii)
Maneuvering, reversing, dumping and turning for return
iv)

13 Min
2 Min

Waiting time, unforeseen contingencies etc

4 Min

Total
a)

20 Min

Machinery
Tipper 5.5 tonnes capacity

hour

0.330

830.00

273.90

P&M-048

Front end-loader 1 cum bucket capacity @ 25 cum/hour

hour

0.330

1116.00

368.28

P&M-017

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

64.22
70.64

Cost for 5.5 cum = a+b+c

777.04

Rate per cum = (a+b+c)/ 5.5


Note
1.2

141.28

say

Unloading will be by tipping.

141.00

Loading and Unloading of Boulders by Manual Means


Unit = cum
Taking output = 5.5 cum
a)

b)

Labour
Mate

day

0.110

232.16

25.54

L-12

Mazdoor for loading and unloading

day

0.750

221.61

166.21

L-13

hour

0.750

830.00

622.50

P&M-048

Machinery
Tipper 5.5 tonne capacity

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

81.42
89.57

Cost for5.5 cum = a+b+c+d

985.24

Rate per cum = (a+b+c+d)/5.5


Note
1.3

179.13

say

Unloading will be by tipping.

179.00

Loading and Unloading of Cement or Steel by Manual


Means and Stacking.
Unit = tonne
Taking output = 10 tonnes
a)

b)

Labour
Mate

day

0.080

232.16

18.57

L-12

Mazdoor for loading and unloading

day

2.000

221.61

443.22

L-13

hour

2.000

745.00

1490.00

P&M-057

Machinery
Truck 10 tonne capacity

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

195.18
214.70

Cost for10 tonnes = a+b+c+d

2361.67

Rate per tonnes = (a+b+c+d)/10

236.17

say

67

236.00

Sr
No

Ref. to
MoRTH
Spec.

Description

1.4

Unit Quantity Rate Rs

Cost Rs

Remarks
/ Input
ref.

Cost of Haulage Excluding Loading and Unloading


Haulage of materials by tipper excluding cost of loading, unloading and
stacking.

Unit = t.km
Taking output 10 tonnes load and lead 10 km = 100 t.km

(i)

Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty :35 km / hour.
a)

Machinery.
Tipper 10 tonne capacity
Time taken for onward haulage with load

hour

0.400

830.00

332.00

P&M-048

Time taken for empty return trip.

hour

0.290

830.00

240.70

P&M-048

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

57.27
63.00

cost for 100 t km = a+b+c

692.97

Rate per t.km = (a+b+c)/100


1.4

(ii)

6.93

say

6.90

Unsurfaced Graveled Road


Speed with load: 20 km / hour
Speed for empty return trip :30 km / hour
a)

Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage with load

hour

0.500

830.00

415.00

P&M-048

Time taken for empty return trip

hour

0.330

830.00

273.90

P&M-048

b)

Overhead charges @ 0.1 on (a)

68.89

c)

Contractor's profit @ 0.1 on (a+b)

75.78

Cost for 100 t .km = a+b+c

833.57

Rate per t.Km = (a+b+c)/100

1.4

(iii)

8.34

say

8.30

Katcha Track and Track in River Bed/Nallah Bed and


Choked Bed
Speed with load :10 km / hour
Speed while returning empty:15 km / hour
a)

Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage

hour

1.000

830.00

830.00

P&M-048

Time taken for empty return trip

hour

0.670

830.00

556.10

P&M-048

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

138.61
152.47

Cost for 100 t .km = a+b+c

1677.18

Rate per t.Km = (a+b+c)/100

16.77

say

68

16.80

Sr
No
1.5

Ref. to
MoRTH
Spec.

Description

Unit Quantity Rate Rs

Cost Rs

Remarks
/ Input
ref.

Hand Broken Stone Aggregates 63 mm Nominal Size


Supply of quarried stone, hand breaking into coarse aggregate
63 mm nominal size (passing 80 mm and retained on 50 mm
sieve) and stacking as directed
Unit = cum

Taking output = 1 cum


a)

b)

Labour
Mate

day

0.060

232.16

13.93

L-12

Mazdoor

day

1.500

221.61

332.42

L-13

cum

1.100

598.32

658.15

M-002

Material
Supply of quarried stone 150 - 200 mm size

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

100.45
110.49

Rate per cum = a+b+c+d

1.6

1215.44

say

1215.00

Crushing of Stone Aggregates 13.2 mm Nominal Size


Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity comprising
of primary and secondary crushing units, belt conveyor and
vibrating screens to obtain stone aggregates of 13.2 mm
nominal size.
Unit = cum

Taking Output = 600 cum at crusher location.


a)

b)

Labour
Mate

day

0.760

232.16

176.44

L-12

Mazdoor Skilled

day

2.000

306.03

612.06

L-15

Mazdoor including breaking of any oversize boulder.

day

17.000

221.61

3767.37

L-13

cum

800.000

573.15

458520.00

M-001

Material
Stone Boulder of size 150 mm and below

c)

Machinery
Integrated stone crusher of 200 TPH including belt conveyor and
vibrating screens
Front end loader 1 cum bucket capacity

Hour

6.000

16760.52

100563.12

P&M-028

Hour

20.000

1116.00

22320.00

P&M-017

Tipper 5.5 cum capacity

Hour

20.000

830.00

16600.00

P&M-048

d)

Overhead charges @ 0.1 on (a+b+c)

60255.90

e)

Contractor's profit @ 0.1 on (a+b+c+d)

66281.49

Cost for 600 cum = (a+b+c+d+e)x0.95

692641.56

Rate per cum = (a+b+c+d+e) * 0.95 / 600

1154.40

say
Note 1. 800 cum of stone boulders are needed to get 600 cum of stone chips
of size 13.2 mm.
2. 95 per cent of above cost will be attributed to the production of 600
cum of stone chips of 13.2 mm size and balance 5 per cent to the
production of stone dust which comes out as a by-product.
3. The integrated stone crusher includes primary and secondary
crushing units.
1.7

Crushing of Stone Aggregates 20 mm Nominal Size


Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity comprising
of primary and secondary crushing units, belt conveyor and
vibrating screens to obtain stone aggregates of 20 mm nominal
size.
Unit = cum

Taking Output = 670 cum at crusher location.

69

1154.00

Sr
No

Ref. to
MoRTH
Spec.

Description
a)

b)

Unit Quantity Rate Rs

Remarks
/ Input
ref.

Labour
Mate

day

0.760

232.16

176.44

L-12

Mazdoor Skilled

day

2.000

306.03

612.06

L-15

Mazdoor including breaking of any size boulder.

day

17.000

221.61

3767.37

L-13

cum

800.000

573.15

458520.00

M-001

Material
Stone Boulder of size 150 mm and below

c)

Cost Rs

Machinery
Integrated stone crusher of 200 TPH including belt conveyor and
vibrating screens
Front end loader 1 cum bucket capacity

Hour

6.000

16760.52

100563.12

P&M-028

Hour

20.000

1116.00

22320.00

P&M-017

Tipper 5.5 cum capacity

Hour

20.000

830.00

16600.00

P&M-048

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

60255.90
66281.49

Cost for 670 cum = (a+b+c+d+e)x0.90

656186.74

Rate per cum = (a+b+c+d+e) * 0.90 / 670

979.38

say

979.00

0.760

232.16

176.44

L-12

Note 1. 800 cum of stone boulders are needed to get 600 cum of stone chips
of size 20 and 40 mm.
2. 90 per cent of above cost will be attributed to the production of 670
cum of stone aggregates of 20mm size and balance 10 per cent will be
for smaller size aggregates and stone dust which comes out as a byproduct.
3. The integrated stone crusher includes primary and secondary
crushing units.
1.8

Crushing of Stone Aggregates 40 mm Nominal Size


Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity comprising
of primary and secondary crushing units, belt conveyor and
vibrating screens to obtain stone aggregates of 40 mm nominal
size.
Unit = cum

Taking Output = 750 cum at crusher location.


a)

b)

Labour
Mate

day

Mazdoor Skilled

day

2.000

306.03

612.06

L-15

Mazdoor

day

17.000

221.61

3767.37

L-13

cum

800.000

573.15

458520.00

M-001

Material
Stone Boulder of size 150 mm and below

c)

Machinery
Integrated stone crusher of 200 TPH including belt conveyor and
vibrating screens
Front end loader 1 cum bucket capacity

Hour

6.000

16760.52

100563.12

P&M-028

Hour

20.000

1116.00

22320.00

P&M-017

Tipper 5.5 cum capacity

Hour

20.000

830.00

16600.00

P&M-048

d)

Overhead charges @ 0.1 on (a+b+c)

60255.90

e)

Contractor's profit @ 0.1 on (a+b+c+d)

66281.49

Cost for 750 cum = (a+b+c+d+e)x0.85

619731.92

Rate per cum = (a+b+c+d+e)x0.85/750

826.31

say
Note 1. 800 cum of stone boulders are needed to get 600 cum of stone chips
of size 13.2 mm.
2. 85 per cent of above cost will be attributed to the production of 750
cum of stone aggregates of 40mm size and balance 15 per cent will be
for smaller size aggregates and stone dust which comes out as a byproduct.
3. The integrated stone crusher includes primary and secondary
crushing units.

70

826.00

CHAPTER - 2

SITE CLEARANCE
Sr No
2.1

Ref. to
MoRTH
Spec.
201

Description

(i)

Unit Quantity Rate Rs

a)

Labour
Mate

day

0.020

232.16

4.64

L-12

day

0.600

221.61

132.97

L-13

b)

Mazdoors for cutting trees including cutting, refilling, compaction


of backfilling and stacking of serviceable materials within 1000
metres lead by manual means.
Machinery

hour

0.100

171.02

17.10

P&M-053

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

15.47
17.02

Rate for each tree = a+b+c+d


(ii)

187.20
say

187.00

Girth from 600 mm to 900 mm


a) Labour

b)

Mate

day

0.040

232.16

9.29

L-12

Mazdoors for cutting trees including cutting, refilling, compaction


of backfilling, and stacking of serviceable materials within 1000
metres lead by manual means
Machinery

day

0.900

221.61

199.45

L-13

hour

0.300

171.02

51.31

P&M-053

Tractor-trolley
c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

26.00
28.60

Rate for each tree = a+b+c+d

314.65
say

2.1

(iii)

Mate

day

0.080

232.16

18.57

L-12

Mazdoors for cutting trees including cutting, refilling, compaction


of backfilling and stacking of serviceable materials within 1000
metres
Machinery

day

2.000

221.61

443.22

L-13

hour

0.400

171.02

68.41

P&M-053

Tractor-trolley
c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

53.02
58.32

Rate for each tree = a+b+c+d


(iv)

315.00

Girth from 900 mm to 1800 mm


a) Labour

b)

2.1

Remarks/
Input ref.

Cutting of Trees, including cutting of Trunks, Branches and


Removal
Cutting of trees, including cutting of trunks, branches and removal of
stumps, roots, stacking of serviceable material with all lifts and up to a
lead of 1000 metres and earth filling in the depression / pit.
Unit = Each
Girth from 300 mm to 600 mm

Tractor-trolley

2.1

Cost Rs

641.54

Girth above 1800 mm


a) Labour
Mate
Mazdoors for cutting trees including cutting, refilling, compaction
of backfilling and stacking of serviceable materials within 1000
metres
b) Machinery
Tractor-trolley
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate for each tree = a+b+c+d

say

642.00

day
day

0.160
4.000

232.16
221.61

37.15
886.44

hour

0.600

171.02

102.61
102.62
112.88
1241.70
1242.00

say

71

L-12
L-13

P&M-053

Sr No
2.2

Ref. to
MoRTH
Spec.
201

Description

Unit Quantity Rate Rs

Clearing Grass and Removal of Rubbish


Clearing grass and removal of rubbish up to a distance of 50 metres
outside the periphery of the area .
By Manual Means
Unit = Hectare
Taking output = 1 Hectare
a) Labour
Mate
Mazdoor
b) Overhead charges @ 0.1 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Rate per Hectare = a+b+c

day
day

2.000
50.000

232.16
221.61

say
2.3

201

(i)

Unit = Hectare
Taking output = 1 Hectare
By Manual Means:-

In area of light jungle

b)

464.32
11080.50
1154.48
1269.93
13969.23
13969.00

L-12
L-13

Labour
Mate

day

6.000

232.16

1392.96

L-12

Mazdoor

day 150.000

221.61

33241.50

L-13

171.02

171.02

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

hour

1.000

3828.60
42114.63
say

b)

Labour
Mate

day

8.000

232.16

1857.28

L-12

Mazdoor

day 200.000

221.61

44322.00

L-13

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

hour

2.000

171.02

342.04

P&M-053

4652.13
5117.34

Rate per Hectare = a+b+c+d

42115.00

In area of thorny jungle


a)

(ii)

P&M-053

3480.55

Rate per Hectare = a+b+c+d

2.3

Remarks/
Input ref.

Clearing and Grubbing Road Land .


Clearing and grubbing road land including uprooting rank vegetation,
grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal
of stumps of trees cut earlier and disposal of unserviceable materials
and stacking of serviceable material to be used or auctioned, up to a
lead of 1000 metres including removal and disposal of top organic soil
not exceeding 150 mm in thickness.

a)

2.3 (i)

Cost Rs

56290.79
say

56291.00

By Mechanical Means
In area of light jungle
a)

b)

Labour
Mate

day

0.160

232.16

37.15

L-12

Mazdoor

day

4.000

221.61

886.44

L-13

Dozer 80 HP with attachment for removal of trees & stumps

hour

10.000

3135.24

31352.40

P&M-014

Tractor-trolley

hour

1.000

171.02

171.02

P&M-053

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3244.70
3569.17

Rate per Hectare = a+b+c+d

39260.87
say

72

39261.00

Sr No

Ref. to
MoRTH
Spec.

2.3 (ii)

Description
B

Unit Quantity Rate Rs

b)

Labour
Mate

day

0.240

232.16

55.72

L-12

Mazdoor

day

6.000

221.61

1329.66

L-13

Dozer 80 HP with attachment for removal of trees & stumps

hour

12.000

3135.24

37622.88

P&M-014

Tractor-trolley

hour

1.500

171.02

256.53

P&M-053

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3926.48
4319.13

Rate per Hectare = a+b+c+d

47510.39
say

202

Remarks/
Input ref.

In area of thorny jungle


a)

2.4

Cost Rs

47510.00

Dismantling of Structures
Dismantling of existing structures like culverts, bridges, retaining walls
and other structure comprising of masonry, cement concrete, wood
work, steel work, including T&P and scaffolding wherever necessary,
sorting the dismantled material, disposal of unserviceable material and
stacking the serviceable material with all lifts and lead of 1000 metres
Unit = cum
Taking output = 1.25 cum
(i)

Lime /Cement Concrete

By Manual Means

Lime Concrete, cement concrete grade M-10 and below


a)

b)

Labour
Mate

day

0.040

232.16

9.29

L-12

Mazdoor for dismantling and loading

day

1.000

221.61

221.61

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

27.71
30.48

Cost for 1.25 cum = a+b+c+d

335.26

Rate per cum = (a+b+c+d)/ 1.25


2.4 (i)

268.20
say

268.00

Cement Concrete Grade M-15 & M-20


a)

b)

Labour
Mate

day

0.050

232.16

11.61

L-12

Mazdoor for dismantling and loading

day

1.250

221.61

277.01

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

33.48

d)

Contractor's profit @ 0.1 on (a+b+c)

36.83

Cost for 1.25 cum = a+b+c+d

405.10

Rate per cum = (a+b+c+d)/ 1.25


2.4 (i)

324.08
say

324.00

Prestressed / Reinforced cement concrete grade M-20 & above


a)

b)

Labour
Mate

day

0.150

232.16

34.82

L-12

Blacksmith

day

0.250

353.52

88.38

L-02

Mazdoor for dismantling, loading and unloading

day

3.500

221.61

775.64

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

94.50

73

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Unit Quantity Rate Rs

Contractor's profit @ 0.1 on (a+b+c)

1143.47

Rate per cum = (a+b+c+d)/ 1.25


II

914.77
say

915.00

By Mechanical Means for items No. 202( B)& ( C)


Cement Concrete Grade M-15 & M-20
a)

b)

Labour
Mate

day

0.020

232.16

4.64

L-12

Mazdoor for loading and unloading

day

0.250

221.61

55.40

L-13

Mazdoor with Pneumatic breaker

day

0.250

232.16

58.04

L-14

hour

0.670

293.76

196.82

P&M-001

hour

0.270

171.02

46.17

P&M-053

Machinery
Air Compressor 250 cfm with 2 leads of pneumatic breaker @
1.5 cum per hour
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

36.11
39.72

Cost for 1.25 cum = a+b+c+d

436.91

Rate per cum = (a+b+c+d)/ 1.25

349.53
say

2.4 II

b)

Labour
Mate

day

0.050

232.16

11.61

L-12

Mazdoor with Pneumatic breaker

day

0.660

232.16

153.23

L-14

Blacksmith

day

0.250

353.52

88.38

L-02

Mazdoor for loading and unloading

day

0.250

221.61

55.40

L-13

hour

1.000

293.76

293.76

P&M-001

hour

0.270

171.02

46.17

P&M-053

Machinery
Air Compressor 250 cfm with 2 leads of pneumatic breaker @
1.00 cum per hour
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

64.86
71.34

Cost for 1.25 cum = a+b+c+d

784.75

Rate per cum = (a+b+c+d)/ 1.25


(ii)
A

627.80
say

628.00

Dismantling Brick / Tile work


In lime mortar
a)

b)

Labour
Mate

day

0.020

232.16

4.64

L-12

Mazdoor for dismantling, loading and unloading

day

0.500

221.61

110.81

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

16.16

d)

Contractor's profit @ 0.1 on (a+b+c)

17.78

Cost for 1.25 cum = a+b+c+d

195.56

Rate per cum = (a+b+c+d)/ 1.25

156.45
say

2.4 (ii)

350.00

Prestressed / reinforced cement concrete grade M-20 & above


a)

2.4

Remarks/
Input ref.

103.95

Cost for 1.25 cum = a+b+c+d

2.4

Cost Rs

156.00

In cement mortar
a)

b)

Labour
Mate

day

0.030

232.16

6.96

L-12

Mazdoor for dismantling, loading and unloading

day

0.750

221.61

166.21

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

21.93

74

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Unit Quantity Rate Rs

Contractor's profit @ 0.1 on (a+b+c)

265.41

Rate per cum = (a+b+c+d)/ 1.25

212.33

b)

Labour
Mate

day

0.016

232.16

3.71

L-12

Mazdoor for dismantling and loading

day

0.400

221.61

88.64

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

13.85

d)

Contractor's profit @ 0.1 on (a+b+c)

15.24

Cost for 1.25 cum = a+b+c+d

167.63

Rate per cum = (a+b+c+d)/ 1.25

134.10
say

b)

Labour
Mate

day

0.014

232.16

3.25

L-12

Mazdoor for Dismantling, loading and unloading

day

0.350

221.61

77.56

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

12.70
13.97

Cost for 1.25 cum = a+b+c+d

153.66

Rate per cum = (a+b+c+d)/ 1.25

122.92
say

(iii)
A

Rubble stone masonry in lime mortar

b)

Labour
Mate

day

0.024

232.16

5.57

L-12

Mazdoor for dismantling, loading and unloading.

day

0.600

221.61

132.97

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

18.47
20.32

Cost for 1.25 cum = a+b+c+d

223.50

Rate per cum = (a+b+c+d)/ 1.25


B

178.80
say

179.00

Rubble stone masonry in cement mortar.


a)

b)

Labour
Mate

day

0.030

232.16

6.96

L-12

Mazdoor for dismantling, loading and unloading.

day

0.750

221.61

166.21

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

21.93

d)

Contractor's profit @ 0.1 on (a+b+c)

24.13

Cost for 1.25 cum = a+b+c+d

265.41

Rate per cum = (a+b+c+d)/ 1.25

212.33
say

2.4 (iii)

123.00

Dismantling Stone Masonry


a)

2.4 (iii)

134.00

Dry brick pitching or brick soling


a)

2.4

212.00

In mud mortar
a)

2.4 (ii)

Remarks/
Input ref.

24.13

Cost for 1.25 cum = a+b+c+d


say
2.4 (ii)

Cost Rs

212.00

Rubble Stone Masonry in mud mortar.


a)

Labour
Mate

day

0.020

232.16

4.64

L-12

Mazdoor for dismantling, loading and unloading.

day

0.500

221.61

110.81

L-13

75

Sr No

Ref. to
MoRTH
Spec.

Description
b)

Unit Quantity Rate Rs

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

hour

0.270

171.02

17.78
156.45
say

b)

Labour
Mate

day

0.018

232.16

4.18

L-12

Mazdoor for dismantling, loading and unloading.

day

0.450

221.61

99.72

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

15.01
16.51

Cost for 1.25 cum = a+b+c+d

181.59

Rate per cum = (a+b+c+d)/ 1.25

145.28
say

b)

Labour
Mate

day

0.016

232.16

3.71

L-12

Mazdoor for dismantling, loading and unloading.

day

0.400

221.61

88.64

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

13.85
15.24

Cost for 1.25 cum = a+b+c+d

167.63

Rate per cum = (a+b+c+d)/ 1.25

134.10
say

b)

Labour
Mate

day

0.020

232.16

4.64

L-12

Mazdoor for dismantling, loading and unloading

day

0.500

221.61

110.81

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

(iv)

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

16.16
17.78

Cost for 1.25 cum = a+b+c+d

195.56

Rate per cum = (a+b+c+d)/ 1.25

156.45
say

156.00

Wood Work wrought framed and fixed in frames of trusses upto a


height of 5 m above plinth level
a) Labour

b)

Mate

day

0.060

232.16

13.93

L-12

Carpenter

day

0.500

353.52

176.76

L-04

Mazdoor for dismantling, loading and unloading.

day

1.000

221.61

221.61

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

45.85
50.43

Cost for 1.25 cum = a+b+c+d

554.75

Rate per cum = (a+b+c+d)/ 1.25

443.80
say

2.4

(v)

134.00

Dismantling boulders laid in wire crates including opening of


crates and stacking dismantled materials.
a)

2.4

145.00

Dismantling stone pitching/ dry stone spalls.


a)

2.4 (iii)

156.00

Dry rubble masonry


a)

P&M-053

195.56

Rate per cum = (a+b+c+d)/ 1.25

2.4 (iii)

46.17
16.16

Cost for 1.25 cum = a+b+c+d

Remarks/
Input ref.

Machinery
Tractor-trolley

2.4 (iii)

Cost Rs

Steel Work in all types of sections upto a height of 5 m above


plinth level excluding cutting of rivet.
76

444.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit Quantity Rate Rs

Cost Rs

Remarks/
Input ref.

Unit = tonne
Taking output = 1 tonne
A

Including dismembering
a)

Labour
Mate

day

0.140

232.16

32.50

L-12

Blacksmith

day

1.000

353.52

353.52

L-02

Mazdoor for dismantling, loading and unloading

day

2.500

221.61

554.03

L-13

Add 2.5 per cent of cost of labour for gas cutting, ropes, pulleys etc.
b)

23.50

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

hour

0.170

171.02

99.26
1201.07
say

Labour
Mate

day

0.220

232.16

51.08

L-12

Mazdoor for dismantling, loading and unloading

day

2.000

221.61

443.22

L-13

Blacksmith

day

0.500

353.52

176.76

L-02

Add 2.5 per cent of cost of labour for gas cutting, ropes, pulleys etc.
b)

16.78

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

hour

0.170

171.02

29.07

P&M-053

71.69
78.86

Rate per tonne = a+b+c+d


C

1201.00

Excluding dismembering.
a)

2.4 (v)

P&M-053

109.19

Rate per tonne = a+b+c+d


2.4 (v)

29.07

867.45
say

867.00

Extra over item No( v ) A and( v ) B for cutting rivets.


Unit = each
Taking output = 10 rivets
a)

Labour
Mate

day

0.010

232.16

2.32

L-12

Blacksmith

day

0.130

353.52

45.96

L-02

Mazdoor

day

0.130

221.61

28.81

L-13

b)

Overhead charges @ 0.1 on (a)

7.71

c)

Contractor's profit @ 0.1 on (a+b)

8.48

Cost for 10 rivets = a+b+c

93.28

Rate for each rivet = ( a+b+c)/10

9.33
say

2.4

(vi)

9.30

Scraping of Bricks Dismantled from Brick Work including


Stacking.
Unit = numbers
Taking output = 1000 numbers

In lime/Cement mortar
a)

Labour
Mate

day

0.140

232.16

32.50

L-12

Mazdoor

day

3.500

221.61

775.64

L-13

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

80.81
88.90

Rate per1000 Nos = a+b+c


2.4 (iv)

977.85
say

978.00

In mud mortar
a)

Labour
Mate

day

0.050

232.16

11.61

L-12

Mazdoor

day

1.250

221.61

277.01

L-13

77

Sr No

Ref. to
MoRTH
Spec.

Description
b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

Unit Quantity Rate Rs

31.75
349.23
say

(vii)

Remarks/
Input ref.

28.86

Rate per1000 Nos = a+b+c


2.4

Cost Rs

349.00

Scraping of Stone from Dismantled Stone Masonry


Unit = cum
Taking output = 1 cum

In cement and lime mortar


a)

Labour
Mate

day

0.060

232.16

13.93

L-12

Mazdoor

day

1.400

221.61

310.25

L-13

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

32.42
35.66

Rate per cum = a+b+c

392.26
say

2.4 (vii)

a)

Labour
Mate

day

0.010

232.16

2.32

L-12

Mazdoor

day

0.300

221.61

66.48

L-13

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

6.88
7.57

Rate per cum = a+b+c

83.25
say

2.4

(viii)

392.00

In Mud mortar

83.00

Scarping Plaster in Lime or Cement Mortar from Brick/ Stone


Masonry
Unit = sqm
Taking output = 100 sqm
a)

b)

Labour
Mate

day

0.160

232.16

37.15

L-12

Mazdoor for scarping and loading

day

4.000

221.61

886.44

L-13

hour

0.320

171.02

54.73

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

97.83
107.61

Cost for 100 sqm = a+b+c+d

1183.76

Rate per sqm = (a+b+c+d)/100

11.84
say

2.4

(ix)

11.80

Removing all type of Hume Pipes and Stacking within a lead of


1000 metres including Earthwork and Dismantling of Masonry
Works.
Unit = metre
Taking output = 1 metre

Up to 600 mm dia
a)

Labour
Mate

day

0.020

232.16

4.64

L-12

Mazdoor

day

0.520

221.61

115.24

L-13

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

11.99
13.19

Rate per metre = a+b+c

145.06
say

2.4 (ix)

145.00

Above 600 mm to 900 mm dia


a)

Labour
Mate

day

0.030

232.16

6.96

L-12

Mazdoor

day

0.700

221.61

155.13

L-13

b)

Overhead charges @ 0.1 on (a)

16.21

c)

Contractor's profit @ 0.1 on (a+b)

17.83
78

Sr No

Ref. to
MoRTH
Spec.

Description

Unit Quantity Rate Rs

Cost Rs

say

196.00

Rate per metre = a+b+c


2.4 (ix)

196.13

Above 900 mm
a)

Labour
Mate

day

0.050

232.16

11.61

L-12

Mazdoor

day

1.200

221.61

265.93

L-13

b)

Overhead charges @ 0.1 on (a)

27.75

c)

Contractor's profit @ 0.1 on (a+b)

30.53

Rate per metre = a+b+c


Note

2.5

202

Remarks/
Input ref.

335.82
say

336.00

1. The excavation of earth, dismantling of stone masonry work in head


walls and protection works is not included which is to be measured
and paid separately.
2. Credit for retrieved stone from masonry work may be taken as per
actual availability.
Dismantling of Flexible Pavements
Dismantling of flexible pavements and disposal of dismantled
materials up to a lead of 1000 metres, stacking serviceable and
unserviceable materials separately
Unit = cum
Taking output = 1 cum

I
A

By Manual Means
Bituminous courses
a)

b)

Labour
Mate

day

0.060

232.16

13.93

L-12

Mazdoor for dismantling, loading and unloading

day

1.500

221.61

332.42

L-13

hour

0.380

171.02

64.99

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

41.13

d)

Contractor's profit @ 0.1 on (a+b+c)

45.25

Rate per cum = a+b+c+d


2.5 I

497.71
say

498.00

Granular courses
a)

b)

Labour
Mate

day

0.040

232.16

9.29

L-12

Mazdoor for dismantling, loading and unloading.

day

1.000

221.61

221.61

L-13

hour

0.330

171.02

56.44

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

28.73
31.61

Rate per cum = a+b+c+d

347.67
say

2.5

II

By Mechanical Means

Bituminous course
a)

b)

Labour
Mate

day

0.010

232.16

2.32

L-12

Mazdoor

day

0.300

221.61

66.48

L-13

Tractor-trolley

hour

0.380

171.02

64.99

P&M-053

Farm tractor with ripper @ 60 cum per hour

hour

0.017

285.12

4.85

P&M-055

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

13.86
15.25

Rate per cum = a+b+c+d

167.75
say

2.6

202

348.00

Dismantling of Cement Concrete Pavement

79

168.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit Quantity Rate Rs

Cost Rs

Remarks/
Input ref.

Dismantling of cement concrete pavement by mechanical means


using pneumatic tools, breaking to pieces not exceeding 0.02 cum in
volume and stock piling at designated locations and disposal of
dismantled materials up to a lead of 1000 metres, stacking serviceable
and unserviceable materials separately
Unit = cum
Taking output = 1 cum
a)

b)

Labour
Mate

day

0.030

232.16

6.96

L-12

Semi skilled mazdoor for operating pneumatic tools

day

0.500

232.16

116.08

L-14

Mazdoors as helpers including loading and unloading

day

0.500

221.61

110.81

L-13

Air compressor 250 cfm with two leads for pneumatic cutters/
hammers @ 1 cum per hour
Tractor-trolley

hour

1.000

293.76

293.76

P&M-001

hour

0.400

171.02

68.41

P&M-053

Joint Cutting Machine with 2-3 blades

hour

1.000

214.92

214.92

P&M-083

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

81.09
89.20

Rate per cum = a+b+c+d

981.23
say

Note

2.7

202

981.00

The above analysis is for removal of complete pavement. In case full


depth repair work is required to be done after dismantling, provision of
a concrete cutting and sawing machine may be added for 0.25 hours.
Dismantling of Guard Rails
Dismantling guard rails by manual means and disposal of dismantled
material with all lifts and up to a lead of 1000 metres, stacking
serviceable materials and unserviceable materials separately.
Unit = running metre
Taking output = 1 metre
a)

b)

Labour
Mate

day

0.006

232.16

1.39

L-12

Mazdoor including loading and unloading

day

0.150

221.61

33.24

L-13

hour

0.050

171.02

8.55

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

4.32
4.75

Rate per metre = a+b+c+d


2.8

202

52.25
say

52.00

Dismantling of Kerb Stone


Dismantling kerb stone by manual means and disposal of dismantled
material with all lifts and up to a lead of 1000 metre
Unit = running metre
Taking output = 10 metre
a)

Labour
Mate

day

0.010

232.16

2.32

L-12

Mazdoor including loading and unloading

day

0.150

221.61

33.24

L-13

80

Sr No

Ref. to
MoRTH
Spec.

Description
b)

Unit Quantity Rate Rs

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

hour

0.200

171.02

34.20

P&M-053

6.98
7.67

Cost for 10 m = a+b+c+d

84.42

Rate per metre = (a+b+c+d)/10

8.44
say

202

Remarks/
Input ref.

Machinery
Tractor-trolley

2.9

Cost Rs

8.00

Dismantling of Kerb Stone Channel


Dismantling kerb stone channel by manual means and disposal of
dismantled material with all lifts and up to a lead of 1000 metre
Unit = running metre
Taking output = 10 metre
a)

b)

Labour
Mate

day

0.015

232.16

3.48

L-12

Mazdoor including loading and unloading

day

0.225

221.61

49.86

L-13

hour

0.300

171.02

51.31

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

10.47
11.51

Cost for 10 m = a+b+c+d

126.63

Rate per metre = (a+b+c+d)/10

12.66
say

2.10

202

13.00

Dismantling of Kilometre Stone


Dismantling of kilometre stone including cutting of earth, foundation
and disposal of dismantled material with all lifts and lead upto 1000 m
and back filling of pit.
Unit = Each
Taking output = one KM stone

5th KM stone
Quantity of cement concrete = 0.392 cum
a)

b)

Labour
Mate

day

0.130

232.16

30.18

L-12

Mazdoor

day

0.750

221.61

166.21

L-13

hour

0.150

171.02

25.65

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

22.20
24.42

Rate for one 5th KM stone = a+b+c+d

268.67
say

269.00

Ordinary KM Stone
Quantity of cement concrete = 0.269 cum
a)

b)

Labour
Mate

day

0.020

232.16

4.64

L-12

Mazdoor

day

0.500

221.61

110.81

L-13

hour

0.100

171.02

17.10

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

13.26
14.58

Rate for one ordinary KM stone = a+b+c+d

160.39
say

160.00

Hectometre Stone
Quantity of cement concrete = 0.048 cum
a)

Labour
Mate

day

0.004

232.16

0.93

L-12

Mazdoor

day

0.100

221.61

22.16

L-13

81

Sr No

Ref. to
MoRTH
Spec.

Description
b)

Unit Quantity Rate Rs

hour

0.020

171.02

3.42

P&M-053

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2.92

Rate for one Hectometre stone = a+b+c+d

32.08

2.65

say
202

Remarks/
Input ref.

Machinery
Tractor-trolley

2.11

Cost Rs

32.10

Dismantling of Fencing
Dismantling of barbed wire fencing/ wire mesh fencing including posts,
foundation concrete, back filling of pit by manual means including
disposal of dismantled material with all lifts and up to a lead of 1000
metres, stacking serviceable material and unserviceable material
separately.
Unit = running metre
Taking output = 30 metres
a)

b)

Labour
Mate

day

0.150

232.16

34.82

L-12

Mazdoor including loading and unloading

day

3.000

221.61

664.83

L-13

Blacksmith

day

0.750

353.52

265.14

L-02

hour

0.150

171.02

25.65

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

99.04
108.95

Cost for 30 metres = a+b+c+d

1198.44

Rate per metre = (a+b+c+d)/30

39.95
say

2.12

202

39.90

Dismantling of CI Water Pipe Line


Dismantling of CI water pipe line 600 mm dia including disposal with
all lifts and lead upto 1000 metres and stacking of serviceable material
and unserviceable material separately under supervision of concerned
department
Unit = running metre
Taking output = 10 metres
a)

b)

Labour
Mate

day

0.090

232.16

20.89

L-12

Mazdoor

day

2.000

221.61

443.22

L-13

Plumber

day

0.250

353.52

88.38

L-02

Truck 10 tonne capacity

hour

0.250

745.00

186.25

P&M-057

Light Crane 3 tonne capacity

hour

0.500

532.00

266.00

P&M-013

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

100.47
110.52

Cost for 10 metres = a+b+c+d

1215.74

Rate per metre = (a+b+c+d)/10


Note

2.13

202

121.57
say

122.00

232.16

23.22

The rate analysis does not include any excavation in earth or


dismantling of masonry works which are to be measured and paid
separately.
Removal of Cement Concrete Pipe of Sewer Gutter
Removal of cement concrete pipe of sewer gutter 1500 mm dia under
the supervision of concerned department including disposal with all
lifts and up to a lead of 1000 metres and stacking of serviceable and
unserviceable material separately but excluding earth excavation and
dismantling of masonry works.
Unit = running metre
Taking output = 10 metres
a)

Labour
Mate

day
82

0.100

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

Unit Quantity Rate Rs

Mazdoor
b)

day

2.500

221.61

554.03

L-13

Crane 5 tonne capacity

hour

0.300

599.40

179.82

P&M-070

Truck flat body 10 tonne

hour

1.000

745.00

745.00

P&M-057

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

150.21
165.23
1817.49

Rate per metre = (a+b+c+d)/10

181.75
say

2.14

202

Remarks/
Input ref.

Machinery

Cost for 10 metres = a+b+c+d

Note

Cost Rs

182.00

The rate analysis does not include any excavation in earth or


dismantling of masonry works which are to be measured and paid
separately.
Removal of Telephone / Electric Poles and Lines
Removal of telephone / Electric poles including excavation and
dismantling of foundation concrete and lines under the supervision of
concerned department, disposal with all lifts and up to a lead of 1000
metres and stacking the serviceable and unserviceable material
separately
Unit = each
Taking output = 30 Nos
a)

b)

Labour
Mate

day

0.480

232.16

111.44

L-12

Mazdoor

day

10.000

221.61

2216.10

L-13

Electrician/Lineman

day

2.000

353.52

707.04

L-02

hour

1.500

171.02

256.53

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

329.11
362.02

Cost for 30 poles = a+b+c+d

3982.24

Rate per pole = (a+b+c+d)/30

132.74
say

83

133.00

RCD/SOR

Analysis of Rate
CHAPTER - 3

EARTH WORK, EROSION CONTROL AND DRAINAGE


Sr No
3.1

Ref. to
MoRTH
Spec.
301

Description

Quantity

Rate Rs

Note

301

Unit = cum
Taking output = 120 cum
a) Labour
Mate
Mazdoor
b) Machinery
Truck 5.5 cum capacity
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost of 120 cum = a+b+c+d
Rate per cum = (a+b+c+d)/120
Royalty @ Rs. 30.00 per Cum
Rate per cum
Including Royalty @ Rs. 30.0 per cum, cost of watering,
rolling & compaction
Rate per cum
In case there is a situation where the cross-section is of cut
and fill and cut earth is required to be used in embankment
in the immediate vicinity, the item of carriage in the truck
shall be omitted.
Rate per cum

day
day

1.800
45.000

232.16
221.61

417.89
9972.45

L-12
L-13

hour

10.000

745.00

P&M-057

say

7450.00
1784.03
1962.44
21586.81
179.89
30.00
210.00

say

222.00
222.00

129.00
say

129.00

Excavation in ordinary rock using manual means including


loading in a truck and carrying of excavated material to
embankment site with in all lifts and leads upto 1000 metres
including Royalty but excluding rolling , copaction & watering
Unit = cum
Taking output = 120 cum
a) Labour
Mate
Mazdoor
b) Machinery
Truck 5.5 cum capacity
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 120 cum = a+b+c+d
Rate per cum = (a+b+c+d)/120
Royalty @ Rs. 30.00 per Cum
Rate per cum

day
day

2.800
70.000

232.16
221.61

650.05
15512.70

L-12
L-13

hour

10.000

745.00

7450.00
2361.27
2597.40
28571.43
238.10
30.00
268.10
268.00

P&M-057

say

301

Remarks/
Input ref.

Excavation in Ordinary Rock by Manual Means


(i)

3.3

Cost Rs

Excavation in Soil by Manual Means .


Excavation for roadway in soil using manual means
including loading in truck for carrying of cut earth to
embankment site with all lifts and lead upto1000 metres.

(ii)

3.2

Unit

(ii)

Including Royalty @ Rs. 30.00 per Cum , watering , rolling &


compaction.

281.00

Note

In case there is a situation where the cross-section is of cut


and fill and cut earth is required to be used in embankment
in the immediate vicinity, the item of carriage in the truck
shall be omitted. including Royalty @ Rs. 30.00 per cum

187.00

Excavation in Soil with Dozer with lead upto 100 metres


Excavation for road way in soil by mechanical means
including cutting and pushing the earth to site of
embankment upto a distance of 100 metres (average lead50
metres), including trimming bottom and side slopes in
accordance with requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 180 cum
a) Labour
84

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mate
Mazdoor
b) Machinery
Dozer, 80 HP @ 30 cum per hour
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 180 cum = a+b+c+d
Rate per cum = (a+b+c+d)/180
3.4

3.5

301

Excavation in Ordinary Rock with Dozer with lead upto


100 metres
Excavation for roadway in ordinary rock by deploying a
dozer, 80 HP including cutting and pushing the cut earth to
site of embankment upto a distance of 100 metres ( average
lead 50 metres ), trimming bottom and side slopes in
accordance with the requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 108 cum
a) Labour
Mate
Mazdoor
b) Machinery
Dozer, 80 HP @ 20 cum per hour
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 108 cum = a+b+c+d
Rate per cum = (a+b+c+d)/108

301

Quantity

Rate Rs

Remarks/
Input ref.

Cost Rs

day
day

0.080
2.000

232.16
221.61

18.57
443.22

hour

6.000

3135.24

say

18811.44
1927.32
2120.06
23320.61
129.56
130.00

day
day

0.120
3.000

232.16
221.61

27.86
664.83

hour

6.000

3135.24

say

18811.44
1950.41
2145.45
23600.00
218.52
219.00

L-12
L-13
P&M-014

L-12
L-13
P&M-014

Excavation in Hard Rock (requiring blasting)


with
disposal upto 1000 metres
Excavation for roadway in hard rock (requiring blasting)
by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines, grades
and cross sections, loading and disposal of cut road with in
all lifts and leads upto 1000 metres
Unit = cum
Taking 0utput = 180 cum
a)

b)

c)

Labour
Mate

day

0.220

232.16

51.08

L-12

Mazdoor

day

3.000

221.61

664.83

L-13

Driller

day

2.000

232.16

464.32

L-06

Blaster

day

0.250

306.03

76.51

L-03

Dozer, 80 HP @ 30 cum per hour

hour

6.000

3135.24

18811.44

P&M-014

Air compressor, 250 cfm with 2 jack hammer

hour

6.000

293.76

1762.56

P&M-001

Front end loader 1 cum bucket capacity

hour

6.000

1116.00

6696.00

P&M-017

Tipper10 tonne capacity

hour

11.250

830.00

9337.50

P&M-048

7104.58

M-104

Machinery

Materials
Gelatin 80 per cent

d)

Electric Detonators @ 1 detonator for 2 gelatin sticks of


125 gms each
Credit for excavated rock found suitable for use @ 50
per cent quantity blasted
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

kg

63.000

112.77

each

252.000

14.27

cum

90.000

-102.33

3595.07 M-094 /100


(9209.64)
3935.42
4328.97

Cost for 180 cum = a+b+c+d+e

47618.63

Rate per cum = (a+b+c+d+e)/180

264.55
say

265.00
`

Note

1. The quality and availability of rock shall be checked


before affording credit.

85

M-089

RCD/SOR

Analysis of Rate
Sr No

3.6

Ref. to
MoRTH
Spec.

301

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

2. In case some rock is issued to the contractor at site, the


item of carriage shall be reduced/restricted to that extent.
Excavation in Soil using Hydraulic Excavator CK 90 and
Tippers with Disposal upto 1000 metres.
Excavation for roadwork in soil with hydraulic excavator of
0.9 cum bucket capacity including cutting and loading in
tippers, trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and
transporting to the embankment location within all lifts and
lead upto 1000m (including Royalty @ Rs. 30.00 per Cum
but excluding watering, rolling & compaction)
Unit = cum
Taking output = 360 cum
a)

b)

Labour
Mate

day

0.080

232.16

18.57

L-12

Mazdoor

day

2.000

221.61

443.22

L-13

hour

6.000

1516.32

9097.92

P&M-026

hour

16.000

830.00

13280.00

P&M-048

Machinery
Hydraulic excavator 0.9 cum bucket capacity @ 60
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2283.97
2512.37

Cost for 360 cum = a+b+c+d

27636.05

Rate per cum = (a+b+c+d)/360

76.77

Royalty @ Rs. 30.00 per Cum

30.00

Rate per cum

106.77
say

3.7

301

107.00

Excavation in Ordinary Rock using Hydraulic Excavator


CK-90 and Tippers with Disposal upto 1000 metres.
Excavation for roadway in ordinary rock with hydraulic
excavator of 0.9 cum bucket capacity including cutting and
loading in tippers, transporting to embankment site within all
lifts and lead upto 1000 m, trimming bottom and side slopes
in accordance with requirements of lines, grades and cross
sections (including Royalty @ Rs. 30.00 per Cum but
excluding watering, rolling & compaction)
Unit = cum
Taking output = 240 cum
a)

b)

Labour
Mate

day

0.080

232.16

18.57

L-12

Mazdoor

day

2.000

221.61

443.22

L-13

hour

6.000

1516.32

9097.92

P&M-026

hour

11.000

830.00

9130.00

P&M-048

Machinery
Hydraulic Excavator 0.90 cum bucket capacity @ 36
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1868.97
2055.87

Cost for 240 cum = a+b+c+d

22614.55

Rate per cum = (a+b+c+d)/240

94.23

Royalty @ Rs. 30.00 per Cum

30.00

Rate per cum

124.23
say

3.8

301

Excavation in Hard Rock (blasting prohibited)


Excavation for roadway in hard rock (blasting prohibited)
with rock breakers including breaking rock, loading in tippers
and disposal within all lifts and lead upto 1000 metres,
trimming bottom and side slopes in accordance with
requirements of lines, grades and cross sections.
86

124.00

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description
A

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Mechanised
Unit = cum
Taking output = 36 cum
a)

b)

Labour
Mate

day

0.400

232.16

92.86

L-12

Mazdoor for trimming slopes including mannul loading


in truck
Machinery

day

10.000

221.61

2216.10

L-13

Hydraulic excavator with rock breaker attachment @ 6


cum per hour
Tipper 5.5 cum capacity, 1 trip per hour.

hour

6.000

1516.32

9097.92

P&M-026

hour

6.500

830.00

5395.00

P&M-048

cum

18.000

-102.33

-1841.93

M-089

c)

Credit for excavated rock found suitable for use @ 50


per cent of excavated quantity
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1496.00
1645.60

Cost for 36 cum = a+b+c+d

18101.55

Rate per cum = (a+b+c+d)/36


Note

502.82
say

503.00

1. The quality and availability of rock shall be checked


before affording credit.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be restricted/reduced to that extent.

3.8

3.Being small quantity, manual loading will be economical in


this case and has been provided accordingly.
Manual Method
Unit = cum
Taking output = 16 cum
a)

Labour
Mate

day

1.640

232.16

380.74

L-12

Mazdoor including loading in truck

day

16.000

221.61

3545.76

L-13

Chiseller

day

24.000

306.03

7344.72

L-05

Blacksmith

day

1.000

353.52

353.52

L-02

Tipper 5.5 cum capacity, 1 trip per hour.

hour

2.900

830.00

2407.00

P&M-048

cum

8.000

-102.33

-818.63

c)

Credit for excavated rock found suitable for use @ 50


per cent of excavated
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

b)

Machinery

1321.31
1453.44

Cost for 16 cum = a+b+c+d

15987.86

Rate per cum = (a+b+c+d)/16

999.24
say

Note

3.9

301

M-089

999.00

1. Credit is considered for 50 per cent of quantity of work.


2. Loading for disposal will be done manually, being small
quantity.
3. In case some rock is issued to contractor at site, the item
of carriage shall be omitted to the extent of quantity issued
to the contractor.
Excavation in Hard Rock (controlled blasting) with
disposal upto 1000 metres
Excavation for roadway in hard rock with controlled blasting
by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines, grades
and cross sections, loading and disposal of cut road with in
all lifts and leads upto 1000 metres
Unit = cum
Taking output = 180 cum
a)

Labour
Mate

day

0.220

232.16

51.08

L-12

Mazdoor

day

3.000

221.61

664.83

L-13

87

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

b)

c)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Driller

day

2.000

232.16

464.32

L-06

Blaster

day

0.500

306.03

153.02

L-03

Dozer 80 HP @ 30 cum per hour

hour

6.000

3135.24

18811.44

P&M-014

Air compressor, 250 cfm with 2 jack hammers

hour

6.000

293.76

1762.56

P&M-001

Front end loader 1 cum bucket capacity

hour

6.000

1116.00

6696.00

P&M-017

Tipper 5.5 cum capacity, 4 trips per hour.

hour

8.200

830.00

6806.00

P&M-048

7104.58

M-104

Machinery

Materials
Gelatin 80 per cent

d)

Electric Detonators @ 1 detonator for1/2 gelatin stick of


125 gms each
Credit for excavated rock found suitable for use @ 50
per cent quantity blasted
Add 5 per cent of cost of a+b+c towards muffling
arrangements to guard against any rock fly off during
blasting
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

kg

63.000

112.77

each

1008.000

14.27

cum

90.000

-102.33

14380.28 M-094 /100


-9209.64

M-089

2384.22

5006.87
5507.55

Cost for 180 cum = a+b+c+d+e

60583.10

Rate per cum = (a+b+c+d+e)/180

336.57
say

337.00

#REF!
Note

3.10

301

1. Credit is considered for 50 per cent of quantity of


blastered rock, if found suitable for construction..
2. In case some rock is issued to the contractor at site, the
item of carriage shall be reduced to that extent.
Excavation in Marshy Soil
Excavation for roadway in marshy soil with hydraulic
excavator 0.9 cum bucket capacity including cutting and
loading in tippers and disposal with in all lifts and lead upto
1000 metres, trimming of bottom and side slopes in
accordance with requirements of lines, grades and cross
sections (including Royalty @ Rs. 30.00 per Cum but
excluding watering, rolling & compaction)
Unit = cum
Taking output = 300 cum
a)

b)

Labour
Mate

day

0.080

232.16

18.57

L-12

Mazdoor

day

2.000

221.61

443.22

L-13

hour

6.000

1516.32

9097.92

P&M-026

hour

13.640

830.00

11321.20

P&M-048

Machinery
Hydraulic excavator 0.90 cum bucket capacity @ 50
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Overhead charges @ 0.1 on (a+b)

2088.09

d)

Contractor's profit @ 0.1 on (a+b+c)

2296.90

Cost for 300 cum = a+b+c+d

25265.90

Rate per cum = (a+b+c+d)/300

84.22

Royalty @ Rs. 30.00 per Cum

30.00

Rate per cum

114.22
say

3.11

301

Removal of Unserviceable Soil with Disposal upto 1000


metres
Removal of unserviceable soil including excavation, loading
and disposal upto 1000 metres lead but excluding
replacement by suitable soil which shall be paid separately
as per clause 305.
Unit = cum
Taking output = 360 cum
a)

Labour

88

114.00

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Quantity

Rate Rs

day

0.080

232.16

18.57

L-12

Mazdoor

day

2.000

221.61

443.22

L-13

hour

6.000

1516.32

9097.92

P&M-026

hour

16.360

830.00

13578.80

P&M-048

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2313.85
2545.24

Cost for 360 cum = a+b+c+d

27997.60

Rate per cum = (a+b+c+d)/360

77.77
say

3.12

303

Remarks/
Input ref.

Mate

Excavator0.90 cum bucket capacity @ 60 cum per


hour
Tipper 5.5 cum capacity, 4 trips per hour.

Note

Cost Rs

78.00

This item does not include replacement of unsuitable soil by


suitable soil. Replacement, where required, is to be provided
and paid separately under clause 305.
Presplitting of Rock Excavation Slopes
Carrying out excavation in hard rock to achieve a specified
slope of the rock face by controlled use of explosives and
blasting accessories in properly aligned and spaced drill
holes, collection of the excavated rock by a 80 HP dozer,
loading in tipper by a front end loader and disposing of the
material with all lifts and lead upto 1000 m, all as specified in
clause No. 303
Unit = sqm
Taking output = 400 sqm( 120 cum considering 300mm
average depth of excavation over the existing rock face)
a)

b)

c)

Labour
Mate

day

0.600

232.16

139.30

L-12

Mazdoor

day

15.000

221.61

3324.15

L-13

Machinery
Air compressor 250 cfm with 2 leads @ 20 cum per
hour
Dozer, 80 HP

hour

6.000

293.76

1762.56

P&M-001

hour

6.000

3135.24

18811.44

P&M-014

Front end loader 1 cum bucket capacity

hour

6.000

1116.00

6696.00

P&M-017

kg

42.000

112.77

4736.38

M-104

each

672.000

14.27

Materials
Gelatin 80 per cent

d)

Electric Detonators @ 1 detonator for 1/2 gelatin stick


of 125 gms each
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

4505.67
4956.23

Cost for 400 sqm = a+b+c+d+e

54518.58

Rate per sqm = (a+b+c+d+e)/400

136.30
say

Note

In case blasted rock is used to the contractor against


payment for constructed work, the cost of carriage shall be
reduced to that extent.
Excavation for Structures

3.13

304

(i)

Earth work in excavation of foundation of structures as per


drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom,
backfilling the excavation earth to the extent required and
utilising the remaining earth locally for road work.
Ordinary soil
Unit = cum
Taking output = 10 cum

Manual Means (Depth upto 3 m)


a)

9586.85 M-094 /100

Labour

89

136.00

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

day

0.320

232.16

74.29

L-12

Mazdoor

day

8.000

221.61

1772.88

L-13

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

184.72
203.19
2235.08

Rate per cum = (a+b+c)/10

223.51
say

3.13 (i)

Remarks/
Input ref.

Mate

Cost for 10 cum = a+b+c

Note

Cost Rs

224.00

Cost of dewatering may be added where required upto 10


per cent of labour cost Assessment for dewatering shall be
made as per site conditions..
Mechanical Means (Depth upto 3 m)
Unit = cum
Taking output = 300 cum
a)

b)

Labour
Mate

day

0.320

232.16

74.29

L-12

Mazdoor

day

8.000

221.61

1772.88

L-13

hour

6.000

1516.32

9097.92

P&M-026

Machinery
Hydraulic excavator 1.0 cum bucket capacity

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1094.51
1203.96

Cost for 300 cum = a+b+c+d

13243.56

Rate per cum = (a+b+c+d)/300

44.15
say

Note

3.13

(ii)

Cost of dewatering upto 5 per cent of (a+b)


may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
Ordinary Rock (not requiring blasting)

Manual Means (Depth upto 3 m)

44.00

Unit = cum
Taking output = 10 cum
a)

Labour
Mate

day

0.400

232.16

92.86

L-12

Mazdoor

day

10.000

221.61

2216.10

L-13

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

230.90
253.99

Cost for 10 cum = a+b+c

2793.85

Rate per cum = (a+b+c)/10

279.38
say

Note

3.13 (ii)

279.00

Cost of dewatering upto 10 per cent of labour cost may be


added, where required. Assessment for dewatering shall be
made as per site conditions..
Mechanical Means
Unit = cum
Taking output = 216 cum
a)

b)

Labour
Mate

day

0.240

232.16

55.72

L-12

Mazdoor

day

6.000

221.61

1329.66

L-13

hour

6.000

1516.32

9097.92

P&M-026

Machinery
Hydraulic excavator 1.0 cum bucket capacity

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1048.33
1153.16

Cost for 216 cum = a+b+c+d

12684.79

Rate per cum = (a+b+c+d)/216

58.73
say

90

59.00

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description
Note

3.13

(iii)
A

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

1.Cost of dewatering upto 5 per cent of (a+b), may be


added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
Hard Rock ( requiring blasting )
Manual Means
Unit = cum
Taking output = 10 cum
a)

Labour
i) Mate

day

0.530

232.16

123.04

L-12

ii) Driller

day

0.840

232.16

195.01

L-06

iii) Blaster

day

0.400

306.03

122.41

L-03

iv) Mazdoor

day

12.000

221.61

2659.32

L-13

hour

0.67

293.76

196.82

P&M-001

kg

3.500

112.77

394.70

M-104

each

14.000

14.27

b)

Machinery

c)

Air Compressor 250 cfm with 2 jack hammer @ 15 cum


per hour
Material
Blasting Material
Detonator electric

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

428.01

Cost for 10 cum = a+b+c+d+e

4708.15

Rate per cum = (a+b+c+d+e)/10

Note

3.13

(iv)

199.73 M-094 /100


389.10

470.82
say

471.00

Cost of dewatering @ 10 per cent of labour cost may be


added, where required Assessment for dewatering shall be
made as per site conditions.
Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 10 cum

Mechanical Means
a)

Labour
Mate

day

0.200

232.16

46.43

L-12

Mazdoor

day

5.000

221.61

1108.05

L-13

hour

10.000

293.76

2937.60

P&M-001

b)

Machinery

c)

Air Compressor 250 cfm with 2 leads of pneumatic


breaker @ 1 cum per hour
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

409.21
450.13

Cost for 10 cum = a+b+c+d

4951.42

Rate per cum = (a+b+c+d)/10

495.14
say

Note

3.13

(v)

495.00

1. Cost of dewatering upto 5 per cent of (a+b), may be


added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond 3 m is not dug and
hence not included.
Marshy soil
Unit = cum
Taking output = 10 cum

Manual means ( upto 3 m depth)


a)

b)

Labour
Mate/Supervisor

day

0.400

232.16

92.86

L-12

Mazdoor

day

10.000

221.61

2216.10

L-13

Machinery

91

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Tractor-trolley
c)

Quantity

Rate Rs

Remarks/
Input ref.

hour

2.670

171.02

456.62

P&M-053

cum

5.000

25.10

125.50

M-163

Material
Selected earth for refilling

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

289.11
318.02

Cost for 10 cum = a+b+c+d+e

3498.21

Rate per cum = ( a+b+c+d+e)/ 10

349.82
say

Note

Cost Rs

350.00

1. Cost of dewatering @ 30 per cent of (a), may be added,


where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 20 per cent of (a), where required may
be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil

3.13 (v)

Mechanical Means
a)

b)

Labour
i) Mate

day

0.080

232.16

18.57

L-12

ii) Mazdoor for dressing sides, bottom and backfilling

day

2.000

221.61

443.22

L-13

hour

0.170

1516.32

257.77

P&M-026

hour

0.450

830.00

373.50

P&M-048

cum

5.000

25.10

125.50

M-163

Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Material
Selected earth for refilling

d)

Overhead charges @ 0.1 on (a+b+c)

121.86

e)

Contractor's profit @ 0.1 on (a+b+c+d)

134.04

Cost for 10 cum = a+b+c+d+e

1474.47

Rate per cum = (a+b+c+d+e)/10


Note

3.14

305.4.3

147.45
say

147.00

1. Cost of dewatering @ 20 per cent of (a+b) may be


added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where
required may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil
Scarifying Existing Granular Surface to a Depth of 50
mm by Manual Means
Scarifying the existing granular road surface to a depth of 50
mm and disposal of scarified material within all lifts and
leads upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a)

b)

Labour
Mate

day

0.200

232.16

46.43

L-12

Mazdoor including loading and unloading

day

5.000

221.61

1108.05

L-13

hour

1.670

171.02

285.60

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

144.01
158.41

Cost for 100 sqm = a+b+c+d

1742.50

Rate per sqm = (a+b+c+d)/100

17.42
say

Note

In case material is to be reused at site, transportation cost


catered above for disposal shall be deleted.

92

17.40

RCD/SOR

Analysis of Rate
Sr No
3.15

Ref. to
MoRTH
Spec.
305.4.3

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Scarifying Existing Bituminous Surface to a depth of 50


mm by Mechanical Means
Scarifying the existing bituminous road surface to a depth of
50 mm and disposal of scarified material with in all lifts and
lead upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a)

b)

Labour
Mate

day

0.010

232.16

2.32

L-12

Mazdoor

day

0.250

221.61

55.40

L-13

Tractor with ripper attachment @ 60 cum per hour

hour

0.080

285.12

22.81

P&M-055

Front end loader 1 cum bucket capacity @ 25 cum per


hour
Tipper 5.5 cum capacity, 4 trips per hour.

hour

0.200

1116.00

223.20

P&M-017

hour

0.230

830.00

190.90

P&M-048

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

49.46
54.41

Cost for 100 sqm = a+b+c+d

598.51

Rate per sqm = (a+b+c+d)/100

5.99
say

3.16

305

6.00

Construction of Embankment with Material obtained


from Borrowpits
Construction of embankment with approved material
obtained from borrow pits with all lifts and leads, transporting
to site, spreading, grading to required slope and compacting
to meet requirement of table 300-2.
Unit = cum
a)

b)

Labour
Mate

day

0.040

232.16

9.29

L-12

Mazdoor

day

1.000

221.61

221.61

L-13

hour

1.670

1516.32

2532.25

P&M-026

tonne.km

160 x L

2.68

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour

hour

0.500

3135.24

1567.62

P&M-014

Motor grader for grading @ 100 cum per hour

hour

1.000

2488.00

2488.00

P&M-032

Water tanker6 KL capacity

hour

4.000

111.24

444.96

P&M-060

Vibratory roller 8 -10 tonnes @ 100 cum per hour

hour

1.000

1642.00

1642.00

P&M-059

KL

24.000

167.07

4009.64

M-189

cum

100.000

25.10

2510.00

M-092

Machinery
Hydraulic Excavator1 cum bucket capacity @ 60 cum
per hour
Tipper 10 tonne capacity

c)

Material
Cost of water

d)

Compensation & Royalty for earth taken from private


land
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1589.68
1748.64

Cost for 100 cum = a+b+c+d+e

19235.09

Rate per cum = (a+b+c+d+e)/100

192.35
say

Note

3.17

305

428.54 Lead =1 km
& P&M-047
42.85

Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be clearly stated in the cost estimate.
Construction of Embankment with Material Deposited
from Roadway Cutting

93

192.00

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Construction of embankment with approved materials


deposited at site from roadway cutting and excavation from
drain and foundation of other structures graded and
compacted to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a)

b)

c)

Labour
Mate

day

0.020

232.16

4.64

L-12

Mazdoor

day

0.500

221.61

110.81

L-13

Dozer 80 HP for spreading @ 200 cum per hour

hour

0.500

3135.24

1567.62

P&M-014

Motor grader for grading @ 100 cum per hour

hour

1.000

2488.00

2488.00

P&M-032

Water tanker6 KL capacity

hour

4.000

111.24

444.96

P&M-060

Vibratory roller 8-10 tonnes @ 100 cum per hour

hour

1.000

1642.00

1642.00

P&M-059

KL

24.000

167.07

4009.64

M-189

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

1026.77

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1129.44

Rate for 100 cum = a+b+c+d+e

12423.88

Rate per cum = (a+b+c+d+e)/100

Note

3.18

305

124.24
say

124.00

In case the earth cutting is done by dozer and pushed for


filling in the embankment, the input of dozer in the cost of
embankment shall be deleted as the same is already
provided in the cost of excavation. However, if the earth is
dumped by tippers from roadway cutting, the input of dozer
for spreading is required to be provided.
Construction of Subgrade and Earthen Shoulders
Construction of sub-grade and earthen shoulders with
approved material obtained from borrow pits with all lifts &
leads, transporting to site, spreading, grading to required
slope and compacted to meet requirement of table No. 3002
Unit = cum
Taking output = 100 cum
a)

b)

Labour
Mate

day

0.040

232.16

9.29

L-12

Mazdoor

day

1.000

221.61

221.61

L-13

hour

1.670

1516.32

2532.25

P&M-026

tonne.km

175xL

2.68

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour

hour

0.500

3135.24

1567.62

P&M-014

Motor grader for grading @ 50 cum per hour

hour

2.000

2488.00

4976.00

P&M-032

Water tanker with 6 km lead

hour

4.000

111.24

444.96

P&M-060

Vibratory roller 8-10 tonnes @ 80 cum per hour

hour

1.250

1642.00

2052.50

P&M-059

KL

24.000

167.07

4009.64

M-189

cum

100.000

25.10

2510.00

M-092

Machinery
Hydraulic excavator1 cum bucket capacity @ 60 cum
per hour
Tipper 10 tonne capacity

c)

468.72 Lead =1 km
& P&M-047
46.87

Material
Cost of water

Compensation & Royalty for earth taken from private land


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1883.95
2072.34

Cost for 100 cum = a+b+c+d+e

22795.75

Rate per cum = (a+b+c+d+e)/100

227.96
say

94

228.00

RCD/SOR

Analysis of Rate
Sr No
3.19

Ref. to
MoRTH
Spec.
305.3.4

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Compacting Original Ground


Case-I Compacting original ground supporting sub-grade
Loosening of the ground upto a level of 500 mm below the
sub-grade level, watered, graded and compacted in layers to
meet requirement of table 300-2 for sub-grade construction.
Unit = cum
Taking output = 600 cum
a)

b)

c)

Labour
Mate

day

0.120

232.16

27.86

L-12

Mazdoor

day

3.000

221.61

664.83

L-13

Tractor with ripper attachment

hour

9.000

285.12

2566.08

P&M-055

Motor grader for grading

hour

6.000

2488.00

14928.00

P&M-032

Water tanker 6 KL capacity

hour

4.000

111.24

444.96

P&M-060

Vibratory roller 8-10 tonne @ 80 cum/hour

hour

7.500

1642.00

12315.00

P&M-059

KL

24.000

167.07

4009.64

M-189

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3495.64
3845.20

Cost for 600 cum = a+b+c+d+e

42297.20

Rate per cum = (a+b+c+d+e)/600

70.50
say

3.19

70.00

Case-II :Compacting original ground supporting embankment


Loosening, leveling and Compacting original ground
supporting embankment to facilitate placement of first layer
of embankment, scarified to a depth of 150 mm, mixed with
water at OMC and then compacted by rolling so as to
achieve minimum dry density as given in Table 300-2 for
embankment construction.
Unit = cum
Taking output = 600 cum
a)

b)

c)

Labour
Mate

day

0.080

232.16

18.57

L-12

Mazdoor

day

2.000

221.61

443.22

L-13

Tractor with ripper attachment

hour

6.000

285.12

1710.72

P&M-055

Vibratory road roller 8-10 tonne capacity

hour

7.500

1642.00

12315.00

P&M-059

Water tanker6 KL capacity

hour

4.000

111.24

444.96

P&M-060

KL

24.000

167.07

4009.64

M-189

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1894.21
2083.63

Cost for 600 cum = (a+b+c+d+e)

22919.95

Rate per sqm = (a+b+c+d+e)/600


3.20

305

38.20
say

38.00

Stripping and Storing Top Soil


Stripping, storing of top soil by road side at 15 m internal and
re-application on embankment slopes, cut slopes and other
areas in localities where the available embankment material
is not conducive to plant growth.
Unit = cum
Taking output = 10 cum
a)

Labour
Mate

day

0.200

232.16

46.43

L-12

Mazdoor

day

5.000

221.61

1108.05

L-13

95

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description
b)

Unit

Quantity

Rate Rs

Remarks/
Input ref.

Machinery
Dozer 80 HP @ 100 cum per hour

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

hour

0.100

3135.24

313.52

P&M-014

146.80
161.48

Cost for 10 cum = (a+b+c+d)

1776.29

Rate per cum = (a+b+c+d)/10

177.63
say

3.21

Cost Rs

178.00

Stripping, Storing and Re-laying Top Soil from Borrow


Areas in Agriculture Fields.
Stripping of top soil from borrow areas located in agriculture
fields, storing at a suitable place, spreading and re-laying
after taking the borrow earth to maintain fertility of the
agricultural field, finishing it to the required levels and
satisfaction of the farmer.
Unit = cum
Taking output = 300 cum
a)

b)

Labour
Mate

day

0.080

232.16

18.57

L-12

Mazdoor

day

2.000

221.61

443.22

L-13

hour

6.000

3135.24

18811.44

Machinery
Dozer, 80 HP

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2120.06

Cost for 300 cum = (a+b+c+d)

23320.61

Rate per cum = (a+b+c+d)/300


3.22

307

P&M-014

1927.32

77.74
say

78.00

Turfing with Sods


Furnishing and laying of the live sods of perennial turf
forming grass on embankment slope, verges or other
locations shown on the drawing or as directed by the
engineer including preparation of ground, fetching of sods
and watering.
Unit = sqm
Taking output = 100 sqm
a)

b)

c)

Labour
Mate

day

0.120

232.16

27.86

L-12

Mazdoor for preparation of ground and fetching of sods

day

3.000

221.61

664.83

L-13

Water tanker including watering for 3 months

hour

2.000

111.24

222.48

P&M-060

Tractor-trolley

hour

1.000

171.02

171.02

P&M-053

cum

0.180

528.65

95.16

M-167

KL

12.000

167.07

2004.82

M-189

Machinery

Material
Farm yard manure @ 0.18 cum per 100 sqm at site of
work
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

318.62

e)

Contractor's profit @ 0.1 on (a+b+c+d)

350.48

Cost for 100 sqm = a+b+c+d+e

3855.26

Rate per 100 sqm = (a+b+c+d+e)/100

38.55
say

3.23

308

Seeding and Mulching


Preparation of seed bed on previously laid top soil,
furnishing and placing of seeds, fertilizer, mulching material,
applying bituminous emulsion at the rate of 0.23 litres per
sqm and laying and fixing jute netting, including watering for
3 months all as per clause 308.
Unit = sqm
Taking output = 240 sqm

96

39.00

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description
a)

b)

Unit

Rate Rs

day

0.400

232.16

92.86

L-12

Mazdoor

day

10.000

221.61

2216.10

L-13

hour

14.000

111.24

1557.36

P&M-060

hour

2.400

171.02

410.44

P&M-053

kg

3.600

21.93

78.94

M-162

Machinery

Material
Sludge/Farm yard manure @ 0.18 cum per 100 sqm

cum

0.430

528.65

227.32

M-167

Bitumen Emulsion

litre

55.200

37.569

2073.81

M-077

Jute netting, open weave, 2.5 cm square opening

sqm

264.000

28.71

7580.72

M-121

KL

84.000

167.07

14033.73

M-189

Cost of water for 3 months


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2827.13
3109.84

Cost for 240 sqm = a+b+c+d+e

34208.26

Rate per sqm = (a+b+c+d+e)/240

142.53
say

309

Remarks/
Input ref.

Mate

Seeds

3.24

Cost Rs

Labour

Water tanker 6 KL capacity including watering for 3


months
Tractor-trolley
c)

Quantity

143.00

Surface Drains in Soil


Construction of unlined surface drains of average cross
sectional area 0.40 sqm in soil to specified lines, grades,
levels and dimensions to the requirement of clause 301 and
309. Excavated material to be used in embankment within a
lead of 50 metres (average lead 25 metres)
Unit = metre
Taking output = 10 metres
A

Mechanical means
a)

Labour
Mate

day

0.010

232.16

2.32

L-12

Mazdoor for dressing of bed and side of drain

day

0.250

221.61

55.40

L-13

hour

0.330

1516.32

500.39

P&M-026

b)

Machinery

c)

Hydraulic Excavator 0.3 cum bucket capacity @ 30


metres per hour
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

55.81
61.39

Cost for 10 metres = a+b+c+d

675.31

Rate per metre = (a+b+c+d)/10

67.53
say

3.24

Manual Means
a)

Labour
Mate

day

0.080

232.16

18.57

L-12

Mazdoor

day

2.000

221.61

443.22

L-13

b)

Overhead charges @ 0.1 on (a)

46.18

c)

Contractor's profit @ 0.1 on (a+b)

50.80

Cost for 10 metres = a+b+c

558.77

Rate per metre = (a+b+c)/10

55.88
say

Note

3.25

309

68.00

Where lining of drain is provided, quantity shall be worked


out based on approved design and drawing and priced on
rate of cement concrete of approved grade or stone/brick
masonry as the case may be.
Surface Drains in Ordinary Rock
Construction of unlined surface drain of average cross
sectional area 0.4 sqm in ordinary rock to specified lines,
grades, levels and dimensions as per approved design and
to the requirement of clause 301 to 309. Excavated material
to be used in embankment at site.
97

56.00

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Unit = metre
Taking output = 10 metres
A

Mechanical Means
a)

Labour
Mate

day

0.020

232.16

4.64

L-12

Mazdoor for dressing of bed and side of drain

day

0.500

221.61

110.81

L-13

hour

0.670

1516.32

1015.93

P&M-026

b)

Machinery

c)

Hydraulic Excavator 0.3 cum bucket capacity @ 15


metres per hour
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

113.14
124.45

Cost for 10 metres = a+b+c+d

1368.97

Rate per metre = (a+b+c+d)/10

136.90
say

3.25

Manual Means
a)

Labour
Mate

day

0.120

232.16

27.86

L-12

Mazdoor

day

3.000

221.61

664.83

L-13

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

69.27
76.20

Cost for 10 metres = a+b+c

838.15

Rate per metre = (a+b+c)/10

83.82
say

3.26

3.27

137.00

309

Surface Drains in Hard Rock

309

Rate per metre may be worked out based on quantity of hard


rock as per design.
For rate of hard rock cutting, refer relevant item in this
chapter
Sub-Surface Drains with Perforated Pipe

84.00

Construction of subsurface drain with perforated pipe of 100


mm internal diameter of metal/ asbestos cement/ cement
concrete/PVC, closely jointed, perforations ranging from 3
mm to 6 mm depending upon size of material surrounding
the pipe, with 150 mm bedding below the pipe and 300 mm
cushion above the pipe, cross section of excavation 450 x
550 mm. Excavated material to be utilised in roadway at site.
Unit = metre
Taking output = 10 metres
a)

c)

Labour
Mate

day

0.040

232.16

9.29

L-12

Mazdoor for excavation and back filling

day

2.000

221.61

443.22

L-13

metre

10.000

107.89

1078.86

M-135

cum

2.400

678.64

1628.74

M-012

Material
Perforated pipe of cement concrete, internal dia 100
mm
Crushed stone as per table 300-3

d)

Overhead charges @ 0.1 on (a+b+c)

316.01

e)

Contractor's profit @ 0.1 on (a+b+c+d)

347.61

Cost for 10 metres = a+b+c+d+e

3823.73

Rate per metre = (a+b+c+d+e)/10

382.37
say

Note
3.28

309

Type of pipe may be modified depending upon provision in


design.
Aggregate Sub-Surface Drains
Construction of aggregate sub surface drain 300 mm x 450
mm with aggregates conforming to table 300-4, excavated
material to be utilised in roadway.
Unit = metre
98

382.00

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output = 10 metres


a)

b)

Labour
Mate

day

0.020

232.16

4.64

L-12

Mazdoor for excavation and back filling with


aggregates
Material

day

1.500

221.61

332.42

L-13

Crushed stone as per table 300-3

cum

1.350

678.64

916.16

M-012

c)

Overhead charges @ 0.1 on (a+b)

125.32

d)

Contractor's profit @ 0.1 on (a+b+c)

137.85

Cost for 10 metres = a+b+c+d

1516.40

Rate per metre = (a+b+c+d)/10

3.29

309

151.64
say

152.00

Underground Drain at Edge of Pavement


Construction of an underground drain 1 m x 1 m (inside
dimensions) lined with RCC-20 cm thick and covered with
RCC slab10 cm in thickness on urban roads.
Unit = Running metre
Taking output = one metre
a) Earthwork in soil

cum

1.500

44.00

66.00

b) RCC work M-20

cum

0.495

4451.00

2203.25
2269.25

Rate per metre = (a+b)


say

Rates for these items may be taken from chapters on earth


work and substructures respectively.

3.30

310

Item No.
3.13
Item 12.8
(C) RCC

2269.00

Preparation and Surface Treatment of Formation.


Preparation and surface treatment of formation by removing
mud and slurry, watering to the extent needed to maintain
the desired moisture content, trimming to the required line,
grade, profile and rolling with 8-10 tonne smooth wheeled
roller, complete as per clause 310.
Unit = sqm
Taking output = 3500sqm
a)

b)

c)

Labour
Mate

day

0.280

232.16

65.00

L-12

Mazdoor

day

6.000

221.61

1329.66

L-13

Mazdoor skilled

day

1.000

306.03

306.03

L-15

Smooth 3 wheeled steel roller 8-10 tonnes

hour

3.000

625.00

1875.00

P&M-044

Water tanker 6 KL, one trip per hour

hour

3.000

111.24

333.72

P&M-060

KL

18.000

167.07

3007.23

M-189

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

691.66
760.83

Cost for 3500 sqm = a+b+c+d+e

8369.14

Rate per sqm = (a+b+c+d+e)/3500

2.39
say

3.31

313

Construction of Rock fill Embankment


Construction of rock fill embankment with broken hard rock
fragments of size not exceeding 300 mm laid in layers not
exceeding 500 mm thick including filling of surface voids
with stone spalls, blinding top layer with granular material,
rolled with vibratory road roller, all complete as per clause
313.
Unit = cum
99

2.00

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output = 100 cum


a)

b)

c)

Labour
Mate

day

0.040

232.16

9.29

L-12

Mazdoor

day

1.500

221.61

332.42

L-13

Dozer 80 HP for spreading @ 200 cum per hour

hour

0.500

3135.24

1567.62

P&M-014

Vibratory road roller 8-10 tonnes @ 100 cum per hour

hour

1.000

1642.00

1642.00

P&M-059

Water tanker 6 KL, one trip per hour

hour

2.000

111.24

222.48

P&M-060

KL

12.000

167.07

2004.82

M-189

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

577.86
635.65

Cost for 100 cum = a+b+c+d+e

6992.13

Rate per cum = (a+b+c+d+e)/100

69.92
say

Note

3.32

301

70.00

It is assumed that rock is available locally at site from


roadway cutting. In case, portion of the rock requires
breaking to acceptable size of 300 mm, breaking charges
will have to be added.
EARTH WORK ON HILL ROAD
Excavation in Hill Area in Soil by Mechanical Means
Excavation in soil in hilly area by mechanical means
including cutting and trimming of side slopes and disposing
of excavated earth with all lifts and lead upto 1000 metres.
Unit = cum
Taking output = 260 cum
a)

b)

Labour
Mate

day

0.240

232.16

55.72

L-12

Mazdoor for trimming slopes and helping in excavation


etc.
Machinery

day

6.000

221.61

1329.66

L-13

Dozer 80 HP (D-80 A 12)@ 43.28 cum per hour

hour

6.000

3135.24

18811.44

P&M-014

Front end loader

hour

6.000

1116.00

6696.00

P&M-017

Tipper 5.5cum capacity, 4 trips per hour.

hour

12.000

830.00

9960.00

P&M-048

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3685.28
4053.81

Cost for 260 cum = a+b+c+d

44591.91

Rate per cum = (a+b+c+d)/260

171.51
say

Note

3.33

301

172.00

In case the land on the valley side is barren and there is no


objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth shall be disposed off on the valley side.
Excavation in Hilly Area in Ordinary Rock by Mechanical
Means not Requiring Blasting.
Excavation in hilly area in ordinary rock not requiring blasting
by mechanical means including cutting and trimming of
slopes and disposal of cut material with all lift and lead upto
1000 metres.
Unit = cum
Taking output = 170 cum
a)

Labour
Mate

day

0.320

232.16

74.29

L-12

Mazdoor

day

8.000

221.61

1772.88

L-13

100

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description
b)

Unit

Quantity

Rate Rs

Machinery
hour

6.000

3135.24

18811.44

P&M-014

Front end loader

hour

7.000

1116.00

7812.00

P&M-017

Tipper 5.5cum capacity, 4 trips per hour.

hour

7.000

830.00

5810.00

P&M-048

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3428.06
3770.87
41479.54

Rate per cum = (a+b+c+d)/170

3.34

301

Remarks/
Input ref.

Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour

Cost for 170 cum = a+b+c+d

Note

Cost Rs

244.00
say

244.00

In case the land on the valley side is barren and there is no


objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth can be disposed off on the valley side.
Excavation in Hilly Areas in Hard Rock Requiring
Blasting
Excavation in hilly areas in hard rock requiring blasting, by
mechanical means including trimming of slopes and disposal
of cut material with all lifts and lead upto 1000 metres.
Unit = cum
Taking output = 170 cum
a)

b)

c)

Labour
Mate

day

0.490

232.16

113.76

L-12

Mazdoor

day

10.000

221.61

2216.10

L-13

Driller

day

2.000

232.16

464.32

L-06

Blaster

day

0.250

306.03

76.51

L-03

Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour

hour

6.000

3135.24

18811.44

P&M-014

Air compressor 250 cfm with two jack hammer @ 20


cum per hour
Front end loader

hour

5.000

293.76

1468.80

P&M-001

hour

7.000

1116.00

7812.00

P&M-017

Tipper 5.5cum capacity, 4 trips per hour.

hour

7.000

830.00

5810.00

P&M-048

kg

35.000

112.77

3946.99

M-104

each

140.000

14.27

Machinery

Materials
Gelatine 80 per cent

d)

Electric Detonators @ 1 Detonator for 2 Gelatine sticks


of 125 gms each
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

4271.72
4698.89

Cost for 170 cum = a+b+c+d+e

51687.78

Rate per cum = (a+b+c+d+e)/170

304.05
say

Note

3.35

1997.26 M-094 /100

In case the land on the valley side is barren and there is no


objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth can be disposed off on the valley side.
In case of hill roads, the altitude effect comes into play. The
output of men and machines decreases progressively after
2100 m elevation leading to increase in cost . High altitude
effect has been explained in the basic approach.
Work in Urban Roads
The cost of earth work in urban roads inhabited area will be
comparatively higher due to following reasons:

101

304.00

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

a) There is mixed traffic on urban roads like slow moving


hand and animal driven carts, rickshaws, cycles, two/ three
wheeler apart from the usual vehicular traffic resulting into
traffic jams. This causes loss of working time which may be
in the range of 10 -15 per cent

3.36

b)
There is considerable disruption of traffic adversely
affecting the efficiency of the working parties including
machines due to congestion caused by pedestrian traffic,
local road side venders, parking of vehicles by the road side,
encroachments by the shopkeepers and local shops who
make use of the berms of the road in front of these shops
and unauthorised conversion of road berms into mini local
market The output of manpower and machines is
substantially reduced due to factors mentioned above.
c)
Cost of living in urban areas is comparatively more
resulting into higher wages.
d)
At times, work is executed during night time due to
heavy traffic during day time. This involves extra expenditure
by way of making arrangement for lighting and special
transport for working parties due to odd hour
In the light of above, the authorities engaged in preparing
the cost estimates may exercise their judgment and cater for
the additional cost to the extent of 2 to 3 per cent, keeping in
view the severity of factors mentioned above. Supporting
details for the extra cost based on the actual conditions in
specific cases will have to give in justification.
Embankment Construction with Flyash/Pond ash
available from coal or lignite burning Thermal Plants as
waste material.

Suggesti
ve

Construction of embankment with Flyash conforming to table


1 of IRC: SP: 58 - 2001 obtained from coal or lignite burning
thermal power stations as waste material, spread and
compacted in layer of 200mm thickness each at OMC, all as
specified in IRC: SP: 58-2001 and as per approved plans.
Unit = cum
Taking output = 360 cum
a)

b)

Labour
Mate

day

0.160

232.16

37.15

L-12

Mazdoor

day

4.000

221.61

886.44

L-13

hour

6.000

1516.32

9097.92

P&M-026

tonne.km

432 x L

2.68

Add 10 per cent of cost of carriagefor loading and


unloading
Dozer 80 HP for spreading @ 200 cum/hour

hour

1.800

3135.24

5643.43

P&M-014

Motor Grader for grading @ 100 cum/hour

hour

3.600

2488.00

8956.80

P&M-032

Water tanker6 KL capacity

hour

12.000

111.24

1334.88

P&M-060

Vibratory Roller 8-10 tonne @ 100 cum/hour

hour

3.600

1642.00

5911.20

P&M-059

Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60
cum/hour
Tipper 10Tcapacity flyash 360 x 1.2 = 432 tonnes

c)

Overhead charges @ 0.1 on (a+b)

3314.06

d)

Contractor's profit @ 0.1 on (a+b+c)

3645.47

Cost for 360 cum = a+b+c+d

40100.12

Rate per cum = (a+b+c+d)/360

111.39
say

Note

1157.07 Lead =1 km
& P&M-047
115.71

1.As flyash is available free of cost as waste material from


Thermal Plants, cost of material has not been added.

102

111.00

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

2.The earth cover on sides and intermediate layers of earth


sandwiching the flyash have not been included in this
analysis. The same are required to be provided as per
approved design and priced separately as embankment
construction.

103

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

RCD/SOR

Analysis of Rate
CHAPTER - 4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Sr No

Ref. to
MoRTH
Spec.

4.1

401

Description

Rate Rs

0.400
2.000
8.000

232.16
306.03
221.61

92.86
612.06
1772.88

L-12
L-15
L-13

6.000
6.000
4.500

2550.00
2136.00
111.24

15300.00
12816.00
500.58

P&M-094
P&M-018
P&M-060

6.000
450 x L

1116.00
2.68

hour
hour

6.000
6.000

2488.00
1642.00

14928.00
9852.00

P&M-032
P&M-059

cum
cum
cum
KL

144.000
57.000
86.400
27.000

816.34
696.99
449.20
167.07

117552.96
39728.43
38810.88
4510.84

M-013
M-017
M-020
M-189

cum
cum
cum
KL

100.800
72.000
115.200
27.000

873.73
696.99
449.20
167.07

88071.98
50183.28
51747.84
4510.84

M-015
M-017
M-020
M-189

cum
cum
cum
KL

100.800
36.000
151.200
27.000

773.79
541.04
449.20
167.07

77998.03
19477.44
67919.04
4510.84

M-016
M-018
M-020
M-189

say

26449.93
29094.92
320044.16
1422.42
1422.00

say

25841.01
28425.12
312676.27
1389.67
1390.00

say

23380.15
25718.17
282899.87
1257.33
1257.00

Granular Sub-Base with Close Graded Material (Table:400-1)


Plant Mix Method
Construction of granular sub-base by providing close graded
Material, mixing in a mechanical mix plant at OMC, carriage of
mixed Material to work site, spreading in uniform layers with
motor grader on prepared surface and compacting with
vibratory power roller to achieve the desired density, complete
as per clause 401
Unit = cum
Taking output = 225 cum (450 tonne)
a) Labour
Mate
day
Mazdoor skilled
day
Mazdoor
day
b) Machinery
Wet mix plant @ 75 tonne capacity per hour
hour
Electric generator 125 KVA
hour
Water tanker 6 KL capacity 5 km lead with one tripper
hour
hour
Front end loader 1 cum bucket capacity
hour
Tipper 10 tonne
tonne.km
Add 10 per cent of cost of carriage to cover loading and
unloading
Motor Grader 110 HP
Vibratory roller 8-10 t
c) Material
Close graded Granular sub-base Material as per table 400-1

4.1A

4.1A

4.1A

(i)

(ii)

(iii)

Cost Rs

Remarks/
Input ref.

Quantity

Unit

For Grading-I Material


53 mm to 9.5 mm @ 50 per cent
9.5 mm to 2.36 mm @ 20 per cent
2.36 mm below @ 30 per cent
Cost of water
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent
9.5 mm to 2.36 mm @ 25 per cent
2.36 mm below @ 40 per cent
Cost of water
OR
For Grading-III Material
9.5 mm to 4.75 mm @ 35 per cent
4.75 mm to 2.36 mm @ 12.5 per cent
2.36 mm below @ 52.5 per cent
Cost of water
Rate per cum for grading-I Material
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 225 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/225

Rate per cum for grading-II Material


d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 225 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/225
Rate per cum for grading-III Material
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 225 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/225

103

6696.00
P&M-017
1205.28 Lead =1 km &
P&M-047
120.53

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description
Note

4.1

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Any one of the grading for material may be adopted as per


design
By Mix in Place Method
Construction of granular sub-base by providing close graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the
desired density, complete as per clause 401
Unit = cum
Taking output = 300 cum
a)

b)

c)

Labour
Mate

day

0.480

232.16

111.44

L-12

Mazdoor skilled

day

2.000

306.03

612.06

L-15

Mazdoor unskilled

day

10.000

221.61

2216.10

L-13

Motor Grader 110 HP @ 50 cum

hour

6.000

2488.00

14928.00

P&M-032

Vibratory roller 8 -10 tonne

hour

6.000

1642.00

9852.00

P&M-059

Tractor - Rotavator

hour

12.000

227.88

2734.56

P&M-054

Water tanker 6 KL capacity

hour

3.000

111.24

333.72

P&M-060

53 mm to 9.5 mm @ 50 per cent

cum

192.000

816.34

156737.28

M-013

9.5 mm to 2.36 mm @ 20 per cent

cum

76.000

696.99

52971.24

M-017

2.36 mm below @ 30 per cent

cum

115.200

449.20

51747.84

M-020

KL

18.000

167.07

3007.23

M-189

26.5 mm to 9.5 mm @ 35 per cent

cum

134.400

873.73

117429.31

M-015

9.5 mm to 2.36 mm @ 25 per cent

cum

96.000

696.99

66911.04

M-017

2.36 mm below @ 40 per cent

cum

153.600

449.20

68997.12

M-020

KL

18.000

167.07

3007.23

M-189

9.5 mm to 4.75 mm @ 35 per cent

cum

134.400

773.79

103997.38

M-016

4.75 mm to 2.36 mm @ 12.5 per cent

cum

48.000

541.04

25969.92

M-018

2.36 mm below @ 52.5 per cent

cum

201.600

449.20

90558.72

M-020

KL

18.000

167.07

3007.23

M-189

Machinery

Material

Close graded Granular sub-base Material as per table 400-1


For Grading-I Material

Cost of water
OR
For Grading-II Material

Cost of water
OR
For Grading-III Material

Cost of water
4.1B

(i)

Rate per cum for grading-I Material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

29525.15
32477.66

Cost for 300 cum = a+b+c+d+e

357254.27

Rate per cum = (a+b+c+d+e)/300

1190.85
say

4.1B

(ii)

Rate per cum for grading-II Material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

28713.26
31584.58

Cost for 300 cum = a+b+c+d+e

347430.42

Rate per cum = (a+b+c+d+e)/300

1158.10
say

4.1B

(iii)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

25432.11
27975.32
307728.56

Rate per cum = (a+b+c+d+e)/300

1025.76
say

4.2

401

1158.00

Rate per cum for grading-III Material


d)

Cost for 300 cum = a+b+c+d+e

Note

1191.00

Any one of the grading for material may be adopted as per


design
Granular Sub-Base with Coarse Graded Material (Table:400- 2)

104

1026.00

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Construction of granular sub-base by providing coarse graded


material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the
desired density, complete as per clause 401.
Unit = cum
Taking output = 300 cum
a)

b)

c)

Labour
Mate

day

0.400

232.16

92.86

L-12

Mazdoor skilled

day

2.000

306.03

612.06

L-15

Mazdoor

day

8.000

221.61

1772.88

L-13

Mortar Grader 110 HP @ 50 cum per hour

hour

6.000

2488.00

14928.00

P&M-032

Vibratory roller 8 -10 tonne

hour

6.000

1642.00

9852.00

P&M-059

Water tanker 6 KL capacity

hour

3.000

111.24

333.72

P&M-060

53 mm to 26.5 mm @ 35 per cent

cum

134.400

730.36

98160.38

M-029

26.5 mm to 4.75 mm @ 45 per cent

cum

172.800

781.01

134958.53

M-026

2.36 mm below @ 20 per cent (Coarse Sand)

cum

76.800

288.57

22162.18

M-022

KL

18.000

167.07

3007.23

M-189

26.5 mm to 4.75 mm @ 75 per cent

cum

288.000

781.01

224930.88

M-026

2.36 mm below @ 25 per cent

cum

96.000

288.57

27702.72

M-022

KL

18.000

167.07

3007.23

M-189

9.5 mm to 4.75 mm @ 66 per cent

cum

255.000

814.39

207669.45

M-025

2.36 mm below @ 34 per cent

cum

129.000

288.57

37225.53

M-022

KL

18.000

167.07

3007.23

M-189

Machinery

Material

For coarse graded Granular sub-base Materials per table 4002


For grading-I Material

Cost of water
OR
For Grading-II Material

Cost of water
OR
For Grading-III Material

Cost of water
4.2

(i)

Rate per cum for grading-I Material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

28587.98
31446.78

Cost for 300 cum = a+b+c+d+e

345914.61

Rate per cum = (a+b+c+d+e)/300

1153.05
say

4.2

(ii)

Rate per cum for grading-II Material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

28323.24
31155.56

Cost for 300 cum = a+b+c+d+e

342711.15

Rate per cum = (a+b+c+d+e)/300

1142.37
say

4.2

(iii)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

27549.37
30304.31
333347.42

Rate per cum = (a+b+c+d+e)/300

1111.16
say

4.3

402

Any one of the grading for material may be adopted as per


design
Lime Stabilisation for Improving Sub-grade
Laying and spreading available soil in the sub-grade on a
prepared surface, pulverising, mixing the spread soil in place
with rotavator with 3 per cent slaked lime having minimum
content of 70 per cent of CaO, grading with motor grader and
compacting with the road roller at OMC to the desired density
to form a layer of improved sub grade
Unit = cum
Taking output = 300 cum (525 tonne)

1142.00

Rate per cum for grading-III Material


d)

Cost for 300 cum = a+b+c+d+e

Note

1153.00

By Mechanical Means

105

1111.00

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description
a)

b)

c)

Unit

Quantity

Rate Rs

Mate

day

0.360

232.16

83.58

L-12

Skilled mazdoor for alignment and geometrics

day

1.000

306.03

306.03

L-15

Mazdoor for spraying lime

day

8.000

221.61

1772.88

L-13

Tractor with ripper and rotavator attachments @ 60 cum


per hour for ripping and 25 cum per hour for mixing

hour

12.000

285.12

3421.44

P&M-055

Motor Grader 110 HP @ 50 cum per hour

hour

6.000

2488.00

14928.00

P&M-032

Vibratory roller 8 - 10 tonne capacity

hour 6.00x0.65*

1642.00

6403.80

P&M-059

Water tanker 6 KL capacity

hour

12.000

111.24

1334.88

P&M-060

tonne

15.750

4427.31

69730.10

M-188

KL

72.000

167.07

12028.91

M-189

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

11000.96
12101.06

Cost for 300 cum= a+b+c+d+e

133111.64

Rate per cum =( a+b+c+d+e)/300

4.3

Remarks/
Input ref.

Labour

Lime at site

Note

Cost Rs

443.71
say

444.00

* Though vibratory roller is required only for 3 hours as per


norms, but the same has to be available at site for 6 hours as
other machines for spreading and mixing will take 6 hours. The
usage rates of roller have been multiplied with a factor of 0.65.
By Manual Means
Unit = cum
Taking output = 150 cum (263 tonnes)
a)

b)

c)

Labour
Mate

day

1.440

232.16

334.31

L-12

Mazdoor skilled

day

1.000

306.03

306.03

L-15

Mazdoor

day

35.000

221.61

7756.35

L-13

Vibratory roller 8 - 10 tonne @ 60 cum per hour

hour

2.500

1642.00

4105.00

P&M-059

Water tanker 6 KL capacity

hour

6.000

111.24

667.44

P&M-060

tonne

8.000

4427.31

35418.46

M-188

KL

36.000

167.07

6014.46

M-189

Machinery

Material
Lime at site
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

5460.20
6006.23

Cost for 150 cum= a+b+c+d+e

66068.48

Rate per cum =( a+b+c+d+e)/150


4.4

402

440.46
say

440.00

Lime Treated Soil for Sub- Base


Providing, laying and spreading soil on a prepared sub grade,
pulverising, mixing the spread soil in place with rotavator with
3 per cent slaked lime with minimum content of 70 per cent
of CaO, grading with motor grader and compacting with the
road roller at OMC to achieve at least 98 per cent of the max
dry density to form a layer of sub base.
Unit = cum
Taking output = 300 cum (525 tonnes)
a)

b)

Labour
Mate

day

0.480

232.16

111.44

L-12

Mazdoor skilled

day

2.000

306.03

612.06

L-15

Mazdoor

day

10.000

221.61

2216.10

L-13

9097.92

P&M-026

Machinery
Excavator 0.90 cum bucket capacity

hour

6.000

1516.32

tonne.km

525 x L

2.68

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Motor Grader 110 HP @ 50 cum per hour

hour

6.000

2488.00

14928.00

P&M-032

Vibratory roller 8 - 10 tonne

hour

6.000

1642.00

9852.00

P&M-059

Tractor with Rotavator and blade @ 25 cum per hour

hour

12.000

227.88

2734.56

P&M-054

Tipper for carriage of soil

106

1406.16 Lead =1 km &


P&M-047
140.62

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description
Water tanker 6 KL capacity
c)

Quantity

Rate Rs

12.000

111.24

tonne

15.750

KL

72.000

Unit
hour

Cost of water

1334.88

P&M-060

4427.31

69730.10

M-188

167.07

12028.91

d)

Overhead charges @ 0.1 on (a+b+c)

M-189

e)

Contractor's profit @ 0.1 on (a+b+c+d)

12419.27
13661.20

Cost for 300 cum = a+b+c+d+e

150273.22

Rate per cum= (a+b+c+d+e)/300


403

Remarks/
Input ref.

Material
Lime at site

4.5

Cost Rs

500.91
say

501.00

Cement Treated Soil Sub Base/ Base


Providing, laying and spreading soil on a prepared sub grade,
pulverising, adding the designed quantity of cement to the
spread soil, mixing in place with rotavator, grading with the
motor grader and compacting with the road roller at OMC to
achieve the desired unconfined compressive strength and to
form a layer of sub-base/base.
Unit = cum
Taking output = 300 cum (525 tonnes)
For 4 per cent quantity of cement by weight of soil
a)

b)

Labour
Mate

day

0.480

232.16

111.44

L-12

Mazdoor skilled

day

2.000

306.03

612.06

L-15

Mazdoor

day

10.000

221.61

2216.10

L-13

9097.92

P&M-026

Machinery
Excavator 0.90 cum bucket capacity

hour

6.000

1516.32

tonne.km

525 x L

2.68

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Motor Grader 110 HP @ 50 cum per hour

hour

6.000

2488.00

14928.00

P&M-032

Vibratory roller 8 - 10 tonne

hour

6.000

1642.00

9852.00

P&M-059

Tractor with Rotavator and blade @ 25 cum per hour

hour

12.000

227.88

2734.56

P&M-054

Water tanker 6 KL capacity

hour

12.000

111.24

1334.88

P&M-060

tonne

21.000

5210.53

109421.05

M-081

KL

72.000

167.07

12028.91

M-189

Tipper for carriage of soil

c)

Material
Cement at site (@ 4 per cent of 525 tonne)
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

16388.37
18027.21

Cost for 300 cum = a+b+c+d+e

198299.27

Rate per cum= (a+b+c+d+e)/300


4.6

403

1406.16 Lead =1 km &


P&M-047
140.62

661.00
say

661.00

Cement Treated Crushed Rock or combination as per


clause 403.2 and table 400.4in Sub base/ Base
Providing, laying and spreading Material on a prepared sub
grade, adding the designed quantity of cement to the spread
Material, mixing in place with rotavator, grading with the motor
grader and compacting with the road roller at OMC to achieve
the desired unconfined compressive strength and to form a
layer of sub-base/base.
Unit = cum
Taking output = 300 cum (600 tonnes)
Quantity of cement assumed as 4 per cent of quantity of
crushed rock by weight.
a) Labour

b)

c)

Mate

day

0.480

232.16

111.44

L-12

Mazdoor skilled

day

2.000

306.03

612.06

L-15

Mazdoor

day

10.000

221.61

2216.10

L-13

Motor Grader 110 HP @ 50 cum per hour

hour

6.000

2488.00

14928.00

P&M-032

Vibratory roller 8 - 10 tonne

hour

6.000

1642.00

9852.00

P&M-059

Tractor with Rotavator and blade @ 25 cum per hour

hour

12.000

227.88

2734.56

P&M-054

Water tanker 6 KL capacity

hour

10.000

111.24

1112.40

P&M-060

tonne

24.000

5210.53

125052.63

Machinery

Material
Cement at site @ 4 per cent by weight of crushed
aggregate (600 tonne)
107

M-081

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Grading of material for sub-base course


37.5 mm to 9.5 mm @ 55 per cent

cum

211.200

889.63

187889.86

M-014

9.5 mm to 4.75 mm @ 20 per cent

cum

76.800

814.39

62545.15

M-025

4.75 mm to 75 micron @ 25 per cent

cum

96.000

518.01

49728.96

M-019

KL

60.000

167.07

10024.09

M-189

37.5 mm to 9.5 mm @ 32.5 per cent

cum

124.800

781.01

97470.05

M-028

9.5 mm to 4.75 mm @ 5 per cent

cum

19.200

814.39

15636.29

M-025

4.75 mm to 75 micron @ 62.5 per cent

cum

240.000

311.50

74760.00

M-023

KL

60.000

167.07

10024.09

M-189

Cost of water
or
Grading of material for Base course

Cost of water
4.6

(i)

For Sub-Base course


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

46680.72
51348.80

Cost for 300 cum = a+b+c+d+e

564836.77

Rate per cum = (a+b+c+d+e)/300

1882.79
say

4.6

(ii)

For Base course


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

35450.96
38996.06

Cost for 300 cum = a+b+c+d+e

428956.64

Rate per cum = (a+b+c+d+e)/300

1429.86
say

Note
4.7

404.3.1

1883.00

1430.00

Quantities of aggregates provided under 'c' above are


uncompacted quantities.
Making 50 mm x 50 mm Furrows
Making 50 mm x 50 mm furrows, 25mm/ 50mm deep, 450 C to
the center line of the road and at one metre interval in the
existing thin bituminous wearing coarse including sweeping
and disposal of excavated material within 1000 metres lead
Unit = sqm
Taking output = 30 m x 7 m = 210 sqm

(i)

25mm deep furrow cutting


a)

Labour
Mate

day

0.080

232.16

18.57

L-12

Mazdoor

day

2.000

221.61

443.22

L-13

hour

0.200

171.02

34.20

P&M-053

b)

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Tractor-trolley

49.60
54.56

Cost for 210 sqm= a+b+c+d

600.16

Rate per sqm =(a+b+c+d)/210

2.86
say

(ii)

50mm deep furrow cutting


a)

Labour
Mate

day

0.160

232.16

37.15

L-12

Mazdoor

day

4.000

221.61

886.44

L-13

hour

0.400

171.02

68.41

P&M-053

b)

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Tractor-trolley

99.20
109.12

Cost for 210 sqm= a+b+c+d

1200.31

Rate per sqm =(a+b+c+d)/210

5.72
say

4.8

404.3.2

2.90

Inverted Choke
Construction of inverted choke by providing, laying, spreading
and compacting screening B type/ coarse sand of specified
grade in uniform layer on a prepared surface with motor grader
and compacting with power roller etc
Unit = cum
Taking output = 600 cum
a)

Labour

108

5.70

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

b)

c)

Unit

Quantity

Rate Rs

day

0.920

232.16

213.59

L-12

Mazdoor skilled

day

2.000

306.03

612.06

L-15

Mazdoor

day

21.000

221.61

4653.81

L-13

Motor Grader 110 HP

hour

6.000

2488.00

14928.00

P&M-032

Vibratory roller 8-10 tonnes @ 60 cum per hour

hour

6.000

1642.00

9852.00

P&M-059

Water tanker 6 KL capacity

hour

18.000

111.24

2002.32

P&M-060

cum

720.000

219.18

157809.60

M-004

KL

108.000

167.07

18043.37

M-189

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

20811.47
22892.62

Cost for 600 cum = a+b+c+d+e

251818.84

Rate per cum = ( a+b+c+d+e)/600


404

Remarks/
Input ref.

Mate

Screening type 'B' or coarse sand

4.9

Cost Rs

419.70
say

420.00

Water Bound Macadam

Providing, laying, spreading and compacting stone aggregates


of specific sizes to water bound macadam specification
including spreading in uniform thickness, hand packing, rolling
with 3 wheeled steel/ vibratory roller 8-10 tonnes in stages to
proper grade and camber, applying and brooming requisite
type of screening/ binding Materials to fill up the interstices of
coarse aggregate, watering and compacting to the required
density.
By Manual Means
Unit = cum
Taking output = 360 cum
a)

b)

Labour
Mate

day

10.080

232.16

2340.17

L-12

Mazdoor skilled

day

2.000

306.03

612.06

L-15

Mazdoor

day

250.000

221.61

55402.50

L-13

hour

6.000

1642.00

9852.00

P&M-059

Smooth 3 wheeled steel roller @ 30cum/hour

hour

12.000

Water tanker 6 KL capacity

hour

24.000

111.24

2669.76

P&M-060

cum

435.600

524.74

228576.74

M-039

cum

97.200

690.16

67083.55

M-042

cum

108.000

129.74

14011.92

M-007

cum

28.800

129.74

3736.51

M-007

KL

144.000

167.07

24057.82

M-189

Machinery
Vibratory roller 8 - 10 tonne @ 60cum per hour
or

4.9A

(i)

c) Material ( Refer table 400 - 7, 8 & 9 )


Grading-I
Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10 sqm for
compacted thickness of 100 mm
Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per 10 sqm
OR
Crushable type such as Moorum or Gravel for grading-I
@ 0.30 cum per 10 sqm
Binding material
Binding Material @ 0.08cum per 10 sqm for grading I
material
Cost of water

4.9A (i)

(a)

Using Screening Crushable type such as Moorum or Gravel


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

33752.30
37127.53

Cost for 360 cum = a+b+c+d+e

408402.81

Rate per cum = (a+b+c+d+e)/360

1134.45
say

1134.00

OR
4.9A (i)

(b)

Using Screening Type-A (13.2mm agg.) with binding material


d)

Overhead charges @ 0.1 on (a+b+c)

39433.11

e)

Contractor's profit @ 0.1 on (a+b+c+d)

43376.42

109

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Quantity

Unit

Rate Rs

Cost for 360 cum = a+b+c+d+e

1325.39
say

(ii)

Remarks/
Input ref.

477140.66

Rate per cum = (a+b+c+d+e)/360


4.9A

Cost Rs

1325.00

Grading-II
Aggregate
Grading-II 63 mm to 45 mm /Grading-III 53 mm to 22.4
mm@ 0.91 cum per 10 sqm for compacted thickness of
75 mm

cum

435.600

595.10

259225.56 M-038 / M-036

cum

57.600

690.16

39753.22

M-042

Crushable type such as Moorum or Gravel for grading II


&III @ 0.22 cum per 10 sqm
OR

cum

105.590

129.74

13699.25

M-007

Type B11.2 mm for grading-III @ 0.20 cum per 10 sqm

cum

96.010

563.97

54146.76

M-041

cum

28.800

129.74

3736.51

M-007

KL

144.000

167.07

24057.82

M-189

Stone Screening
Type A 13.2 mm for grading-II @ 0.12 cum per 10 sqm
OR

Binding material
Binding Material @ 0.06cum per 10 sqm for grading II
material
Cost of water
4.9A (ii)

(a)

Using Screening Crushable type such as Moorum or Gravel


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

36785.91
40464.50

Cost for 360 cum = a+b+c+d+e

445109.54

Rate per cum = (a+b+c+d+e)/360

1236.42
say

1236.00

OR
4.9A (ii)

(b)

Using Screening Type-A (13.2mm agg.) with binding material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

39764.96
43741.46

Cost for 360 cum = a+b+c+d+e

481156.02

Rate per cum = (a+b+c+d+e)/360

1336.54
say

4.9A (ii)

(c)

Using Screening Type-B (11.2mm agg.) with binding material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

41204.31
45324.75

Cost for 360 cum = a+b+c+d+e

498572.21

Rate per cum = (a+b+c+d+e)/360


4.9A

(iii)

1337.00

1384.92
say

1385.00

Grading-III
Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm
for compacted thickness of 75 mm

cum

435.600

615.30

268024.68

M-036

cum

86.400

563.97

48727.01

M-041

cum

105.590

129.74

13699.25

M-007

cum

28.800

129.74

3736.51

M-007

KL

144.000

167.07

24057.82

M-189

Stone Screening
Type B 11.2 mm for grading-III @ 0.18 cum per 10 sqm
OR
Crushable type such as Moorum or Gravel for grading II
&III @ 0.22 cum per 10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for grading II
material
Cost of water
4.9A (iii)

(a)

Using Screening Crushable type such as Moorum or Gravel


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

37665.82
41432.41

Cost for 360 cum = a+b+c+d+e

455756.47

Rate per cum = (a+b+c+d+e)/360

1265.99
say

OR

110

1266.00

RCD/SOR

Analysis of Rate
Sr No
4.9A (iii)

Ref. to
MoRTH
Spec.

Description
(b)

Quantity

Unit

Rate Rs

Cost Rs

Remarks/
Input ref.

Using Screening Type-B (11.2mm agg.)


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

41542.25
45696.48

Cost for 360 cum = a+b+c+d+e

502661.25

Rate per cum = (a+b+c+d+e)/360

1396.28
say

1396.00

( Anyone of the aggregate grading, screening and binding


material may be used as per design)
4.9

By Mechanical Means:
Unit = cum
Taking output = 360 cum
a)

b)

Labour
Mate

day

0.680

232.16

157.87

L-12

Mazdoor skilled

day

2.000

306.03

612.06

L-15

Mazdoor

day

15.000

221.61

3324.15

L-13

Motor grader 110 HP @ 50cum/hr. for spreading

hour

7.200

2488.00

17913.60

P&M-032

Vibratory roller 8-10 tonnes @ 60cum/hr.

hour

6.000

1642.00

9852.00

P&M-059

Smooth 3 wheeled steel roller @ 30cum/hr.

hour

12.000

Water tanker 6 KL capacity

hour

24.000

111.24

2669.76

P&M-060

cum

435.600

524.74

228576.74

M-039

cum

97.200

690.16

67083.55

M-042

cum

108.000

129.74

14011.92

M-007

cum

28.800

129.74

3736.51

M-007

KL

144.000

167.07

24057.82

M-189

Machinery

or

4.9B

(i)

c) Material ( Refer table 400 - 7, 8 & 9 )


Grading-I
Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10 sqm for
compacted thickness of 100 mm
Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per 10 sqm
OR
Crushable type such as Moorum or Gravel for grading-I
@ 0.30 cum per 10 sqm
Binding material
Binding Material @ 0.08cum per 10 sqm for grading I
material
Cost of water

111

RCD/SOR

Analysis of Rate
Sr No
4.9B (i)

Ref. to
MoRTH
Spec.

Description
(a)

Quantity

Unit

Rate Rs

Cost Rs

Remarks/
Input ref.

Using Screening Crushable type such as Moorum or Gravel


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

30117.59
33129.35

Cost for 360 cum = a+b+c+d+e

364422.87

Rate per cum = (a+b+c+d+e)/360

1012.29
say

1012.00

OR
4.9B (i)

(b)

Using Screening Type-A (13.2mm agg.) with binding material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

35798.41
39378.25

Cost for 360 cum = a+b+c+d+e

433160.73

Rate per cum = (a+b+c+d+e)/360

1203.22
say

4.9B

(ii)

1203.00

Grading-II
Aggregate
Grading-II 63 mm to 45 mm /Grading-III 53 mm to 22.4
mm@ 0.91 cum per 10 sqm for compacted thickness of
75 mm

cum

435.600

595.10

259225.56 M-038 / M-036

cum

57.600

690.16

39753.22

M-042

Crushable type such as Moorum or Gravel for grading II


&III @ 0.22 cum per 10 sqm
OR

cum

105.590

129.74

13699.25

M-007

Type B 11.2 mm for grading-III @ 0.20 cum per 10 sqm

cum

96.010

563.97

54146.76

M-041

cum

28.800

129.74

3736.51

M-007

KL

144.000

167.07

24057.82

M-189

Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum per 10 sqm
OR

Binding material
Binding Material @ 0.06cum per 10 sqm for grading II
material
Cost of water
4.9B (ii)

(a)

Using Screening Crushable type such as Moorum or Gravel


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

33151.21
36466.33

Cost for 360 cum = a+b+c+d+e

401129.60

Rate per cum = (a+b+c+d+e)/360

1114.25
say

1114.00

OR
4.9B (ii)

(b)

Using Screening Type-A (13.2mm agg.) with binding material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

36130.26
39743.28

Cost for 360 cum = a+b+c+d+e

437176.09

Rate per cum = (a+b+c+d+e)/360

1214.38
say

4.9B (ii)

(c)

Using Screening Type-B (11.2mm agg.) with binding material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

37569.61
41326.57

Cost for 360 cum = a+b+c+d+e

454592.27

Rate per cum = (a+b+c+d+e)/360


4.9B

(iii)

1214.00

1262.76
say

1263.00

Grading-III
Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm
for compacted thickness of 75 mm

cum

435.600

615.30

268024.68

M-036

cum

86.400

563.97

48727.01

M-041

cum

105.590

129.74

13699.25

M-007

Stone Screening
Type B 11.2 mm for grading-III @ 0.18 cum per 10 sqm
OR
Crushable type such as Moorum or Gravel for grading II
&III @ 0.22 cum per 10 sqm

112

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Cost Rs

Remarks/
Input ref.

Quantity

Rate Rs

cum

28.800

129.74

3736.51

M-007

KL

144.000

167.07

24057.82

M-189

Unit

Binding material
Binding Material @ 0.06cum per 10 sqm for grading II
material
Cost of water
4.9B (iii)

(a)

Using Screening Crushable type such as Moorum or Gravel


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

34031.12
37434.23

Cost for 360 cum = a+b+c+d+e

411776.54

Rate per cum = (a+b+c+d+e)/360

1143.82
say

1144.00

OR
4.9B (iii)

(b)

Using Screening Type-B (11.2mm agg.) with binding material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

37907.55
41698.30

Cost for 360 cum = a+b+c+d+e

458681.31

Rate per cum = (a+b+c+d+e)/360


Note
4.10

405

1274.11
say

1274.00

As three wheeled smooth rollers are also very commonly used,


the same has been provided as an alternative.
Crushed Cement Concrete Sub-base / Base
Breaking and crushing of material obtained by breaking
damaged cement concrete slabs to size range not exceeding
75 mm as specified in table 400.7 transporting the aggregates
obtained from breaking of cement concrete slabs at a lead of L
km., laying and compacting the same as sub base/ base
course, constructed as WBM to clause 404 except the use of
screening or binding Material.
Unit = cum
Taking output =360 cum
a)

b)

Labour
Mate

day

4.160

232.16

965.79

L-12

Mazdoor skilled

day

2.000

306.03

612.06

L-15

Mazdoor for crushing broken cement concrete


pavement/slabs into aggregate
Machinery

day

102.000

221.61

22604.22

L-13

Motor Grader,110 HP @ 50 cum/hr.

hour

6.000

2488.00

14928.00

P&M-032

Vibratory roller 8 - 10 tonne@ 60 cum per hour

hour

6.000

1642.00

9852.00

P&M-059

Smooth 3 wheeled steel roller @ 30cum/hr.

hour

12.000

Front end loader 1 cum bucket capacity

hour

6.000

1116.00

6696.00

P&M-017

tonne.km

720 x L

2.68

hour

12.000

111.24

1334.88

P&M-060

KL

72.000

167.07

12028.91

M-189

or

Tipper 10 tonne capacity

c)

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Water tanker 6 KL capacity with 5 km lead @ 1 trip per
hour
Material

1928.45 Lead =1 km &


P&M-047
192.84

Material available from dismantled concrete slab after crushing


/ breaking and only carriage is required to be provided
Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

7114.32
7825.75

Cost for 360 cum = a+b+c+d+e

86083.21

Rate per cum = (a+b+c+d+e)/360

239.12
say

With Vibratory Roller


With Smooth 3 wheeled Steel Roller

Note

1. It is assumed that dismantling of concrete slab/pavement


has been considered separately. Hence same is not added in
this analysis. Only labour for crushing the dismantled slab into
aggregate has been added. Carriage from stock pile to work
site has been provided with a lead of L km.

113

239.00

239.00
231.00

RCD/SOR

Analysis of Rate
Sr No

4.11

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

2. In case of breaking of slabs is done locally without


involvement of transportation, the provision of tipper, front end
loader and loading/unloading charges may be deleted.
3. As three wheeled smooth steel rollers are commonly in use,
the same has been provided as an alternative.
Penetration Coat Over Top Layer of Crushed Cement
Concrete Base

405.2

Spraying of bitumen over cleaned dry surface of crushed


cement concrete base at the rate of 25 kg per 10 sqm by a
bitumen pressure distributor, spreading of key aggregates at
the rate of 0.13 cum per 10 sqm by a mechanical gritter and
rolling the surface as per clause 506.3.8
Unit = sqm
Taking output = 7500 sqm
a)

b)

c)

Labour
Mate

day

0.560

232.16

130.01

L-12

Mazdoor skilled

day

2.000

306.03

612.06

L-15

Mazdoor

day

12.000

221.61

2659.32

L-13

Mechanical broom hydraulic @ 1250 sqm per hour

hour

6.000

462.00

2772.00

P&M-031

Hydraulic self propelled chips spreader

hour

6.000

2423.52

14541.12

P&M-025

Front end loader 1 cum bucket capacity

hour

6.000

1116.00

6696.00

P&M-017

Tipper 10 tonne capacity

hour

6.000

830.00

4980.00

P&M-048

Vibratory roller 8 -10 tonnes @ 30 cum per hour

hour 6.00x0.65*

1642.00

6403.80

P&M-059

Bitumen pressure distributor @ 1750 sqm per hour

hour

4.280

986.04

4220.25

P&M-004

cum

97.500

723.14

70506.15

M-051

tonne

0.250

32859.22

8214.81

M-074

Machinery

Material
Crushed stone aggregate 11.2 mm size
Bitumen (60-70 grade)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

12173.55
13390.91

Cost for 7500 sqm = a+b+c+d+e

147299.97

Rate per sqm = (a+b+c+d+e)/7500


Note

4.12

406

19.64
say

19.60

Though vibratory roller is required only for 3 hours as per


norms, the same is required to be available at site for 6 hours
to match with other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65.
Wet Mix Macadam
Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including
premixing the Material with water at OMC in mechanical mix
plant carriage of mixed Material by tipper to site, laying in
uniform layers with paver in sub- base / base course on well
prepared surface and compacting with vibratory roller to
achieve the desired density.
Unit = cum
Taking output = 225 cum (495 tonnes)
a)

b)

Labour
Mate

day

0.480

232.16

111.44

L-12

Mazdoor skilled

day

2.000

306.03

612.06

L-15

Mazdoor

day

10.000

221.61

2216.10

L-13

Wet mix plant of 75 tonne hourly capacity

hour

6.600

2550.00

16830.00

P&M-094

Electric generator 125 KVA

hour

6.000

2136.00

12816.00

P&M-018

Front end loader 1 cum capacity

hour

6.000

1116.00

6696.00

P&M-017

Paver finisher

hour

6.000

1167.00

7002.00

P&M-035

Vibratory roller 8 - 10 tonne

hour

6x0.65

1642.00

6403.80

P&M-059

Smooth 3 wheeled steel roller @ 8-10 tonnes.

hour

12.000

Water tanker 6 KL capacity

hour

3.000

111.24

333.72

P&M-060

tonne.km

495 x L

2.68

Machinery

or

Tipper

c)

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Material ( Table 400-11)

114

1325.81 Lead =1 km &


P&M-047
132.58

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Quantity

Unit

Rate Rs

cum

89.100

793.41

70692.83

M-034

22.4 mm to 2.36 mm @ 40 per cent

cum

118.800

867.97

103114.84

M-031

2.36 mm to 75 micron@ 30 per cent

cum

89.100

288.57

25711.59

M-022

KL

18.000

167.07

3007.23

M-189

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

25700.60
28270.66

Cost for 225 cum = a+b+c+d+e

310977.24

Rate per cum = (a+b+c+d+e)/225

1382.12
say

4.13

407

Remarks/
Input ref.

45 mm to 22.4 mm@ 30 per cent

Cost of water

Note

Cost Rs

1382.00

1. Though vibratory roller is required only for 3 hours as per


norms, the same is required to be available at site for 6 hours
to match with other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65
2. As three wheeled smooth steel rollers are commonly in use,
the same has been provided as an alternative which can be
used if the thickness of individual layer does not exceed 100
mm.
Construction of Median and Island with Soil Taken from
Roadway Cutting
Construction of Median and Island above road level with
approved material deposited at site from roadway cutting and
excavation for drain and foundation of other structures, spread,
graded and compacted as per clause 407
Unit = cum
Taking output =21 cum
a)

b)

c)

Labour
Mate

day

0.240

232.16

55.72

L-12

Mazdoor

day

6.000

221.61

1329.66

L-13

Water tanker 6 KL with 5 km lead and 1 trip per hour

hour

1.000

111.24

111.24

P&M-060

Plate compactor @ 3.5 cum per hour

hour

6.000

142.99

857.95

P&M-086

KL

6.000

167.07

1002.41

M-189

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

335.70
369.27

Cost for 21 cum = a+b+c+d+e

4061.95

Rate per cum = (a+b+c+d+e)/21

193.43
say

Note

4.14

407

193.00

This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case granular
fill is required to be paved, quantities of paving are required to
be calculated as per approved design and paid separately.
Construction of Median and Island with Soil Taken from
Borrow Areas
Construction of median and Island above road level with
approved material brought from borrow pits, spread, sloped
and compacted as per clause 407
Unit = cum
Taking output = 21 cum
a)

b)

Labour
Mate

day

0.160

232.16

37.15

L-12

Mazdoor

day

4.000

221.61

886.44

L-13

Water tanker with 5 km lead

hour

1.000

111.24

111.24

P&M-060

Plate Compactor @ 3.5 cum per hour

hour

6.000

142.99

857.95

P&M-086

Hydraulic Excavator1.0 cum bucket capacity @60 cum


per hour
Tipper 10 tonne capacity

hour

0.500

1516.32

758.16

P&M-026

tonne.km

52.5 x L

2.68

KL

6.000

167.07

Machinery

Add 10 per cent of cost of transportation to cover cost


of loading and unloading
c) Material
Cost of water

115

140.62 Lead =1 km &


P&M-047
14.06

1002.41

M-189

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Quantity

Unit

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Rate Rs

418.88
4607.71

Rate per cum = (a+b+c+d+e)/ 21

219.41
say

4.15

Remarks/
Input ref.

380.80

Cost for 21 cum = a+b+c+d+e

Note

Cost Rs

219.00

This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case surface
finish is of hard type, the same may be provided separately as
per approved design.
Construction of Shoulders
A. Earthen Shoulders
The rate as applicable for sub-grade construction may be
adopted.
B. Hard Shoulders
Rate as applicable for sub-base and or base may be adopted
as per approved design.
C. Paved shoulders

4.16

409

The rate may be adopted as applicable for different layers of


pavement depending upon approved design of paved
shoulders.
Footpaths and Separators
Construction of footpath/separator by providing a 150 mm
compacted granular sub base as per clause 401 and 25 mm
thick cement concrete grade M15, over laid with pre-cast
concrete tiles in cement mortar 1:3 including provision of all
drainage arrangements but excluding kerb channel..
Unit = sqm
Taking output = 300 sqm
a)

b)

c)

Labour
Mate

day

1.360

232.16

315.74

L-12

Mason

day

4.000

353.52

1414.08

L-11

Mazdoor

day

30.000

221.61

6648.30

L-13

Vibratory road roller 8 -10 tonnes @60 cum per hour

hour

0.750

1642.00

1231.50

P&M-059

Water tanker 6 KL capacity @ 1 trip per hour

hour

2.000

111.24

222.48

P&M-060

Concrete mixer 0.4/0.28 cum per hour

hour

6.000

211.68

1270.08

P&M-009

53 mm to 26.5 mm @ 35 per cent

cum

20.790

730.36

15184.18

M-029

26.5 mm to 4.75 mm @ 45 per cent

cum

26.730

781.01

20876.40

M-026

2.36 mm below @ 20 per cent

cum

11.880

288.57

3428.21

M-022

Aggregate 12 mm crushed @ 0.9 cum of concrete

cum

6.750

827.86

5588.06

M-052

Sand @ 0.45 cum/cum of concrete

cum

3.380

219.18

740.83

M-005

tonne

1.880

5210.53

9795.79

M-081

Machinery

Material

i) For Granular sub base material

ii) For cement concrete grade M157.5 cum

Cement
iii) For cement plaster 1:3
Sand
Cement

cum

3.840

219.18

841.65

M-005

tonne

1.830

5210.53

9535.26

M-081

each

3300.000

23.18

76496.36

M-184

iv) Pre-cast cement concrete tiles


Tiles size 300 x 300 mm and 25 mm thick
v) RCC pipes
Pipes 200 mm dia,2.5 m long for drainage
vi) Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

metre

22.500

124.65

2804.52

M-137

KL

12.000

167.07

2004.82

M-189

15839.83
17423.81

Cost for 300 sqm = a+b+c+d+e

191661.90

Rate per sqm = (a+b+c+d+e)/300

638.87
say

4.17

410

Crusher Run Macadam Base

116

639.00

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Providing crushed stone aggregate, depositing on a prepared


surface by hauling vehicles, spreading and mixing with a motor
grader, watering and compacting with a vibratory roller to
clause 410 to form a layer of sub-base/Base
Unit = cum
Taking output = 360 cum
A

By Mix in Place Method


a)

b)

c)

Labour
Mate

day

0.480

232.16

111.44

L-12

Mazdoor skilled

day

2.000

306.03

612.06

L-15

Mazdoor

day

10.000

221.61

2216.10

L-13

Tractor attached with rotavator @ 25 cum per hour

hour

12.000

227.88

2734.56

P&M-054

Motor grader 110 HP

hour

6.000

2488.00

14928.00

P&M-032

Vibratory roller 8 -10 tonnes @ 60 cum per hour

hour

6.000

1642.00

9852.00

P&M-059

Water tanker 6 KL capacity

hour

6.000

111.24

667.44

P&M-060

63 mm to 45 mm @ 33 per cent

cum

157.460

595.10

93704.45

M-038

22.5 mm to 5.6 mm@ 32 per cent

cum

151.060

838.98

126736.32

M-032

Below 5.6 mm @ 35 per cent

cum

166.680

265.64

44276.88

M-030

KL

36.000

167.07

6014.46

M-189

Machinery

Material

Aggregate at site
i) For 53 mm maximum size

Cost of water
Or
ii) For 45 mm maximum size
45 mm to 22.5 mm@ 5 per cent

cum

24.120

793.41

19137.05

M-034

22.4 mm to 5.6 mm@ 50 per cent

cum

237.600

838.98

199341.65

M-032

Below 5.6 mm@ 45 per cent

cum

213.480

265.64

56708.83

M-030

KL

36.000

167.07

6014.46

M-189

Cost of water
4.17A

(i)

For 53 mm maximum size


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

30185.37
33203.91

Cost for 360.0cum = a+b+c+d+e

365242.97

Rate per cum = (a+b+c+d+e)/360

1014.56

or
4.17A

(ii)

say

For 45 mm maximum size


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

31232.36
34355.59

Cost for 360.0cum = a+b+c+d+e

377911.53

Rate per cum = (a+b+c+d+e)/360

1049.75
say

Note
4.17

1015.00

1050.00

Any one of the aggregate grading may be adopted


By Mixing Plant :
Unit = cum
Taking output = 225 cum (450 tonnes)
a)

b)

Labour
Mate

day

0.280

232.16

65.00

L-12

Mazdoor skilled

day

1.000

306.03

306.03

L-15

Mazdoor

day

6.000

221.61

1329.66

L-13

Wet mix plant @ 75 tonne per hour

hour

6.000

1128.60

6771.60

P&M-093

Electric generator 125 KVA

hour

6.000

2136.00

12816.00

P&M-018

Front end loader 1 cum bucket capacity

hour

6.000

1116.00

6696.00

P&M-017

Motor grader 110 HP

hour

6.000

2488.00

14928.00

P&M-032

Vibratory roller 8 - 10 tonne

hour

6.000

1642.00

9852.00

P&M-059

Water tanker 6 KL capacity

hour

3.000

111.24

333.72

P&M-060

tonne.km

450 x L

2.68

Machinery

Tipper 10 tonne capacity

c)

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Material

Aggregate at site

117

1205.28 Lead =1 km &


P&M-047
120.53

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

i) For 53 mm maximum size


63 mm to 45 mm @ 33 per cent

cum

98.400

595.10

58557.84

M-038

22.5 mm to 5.6 mm@ 32 per cent

cum

94.410

838.98

79208.10

M-032

Below 5.6 mm @ 35 per cent

cum

104.180

265.64

27674.38

M-030

Or
ii) For 45 mm maximum size
45 mm to 22.5 mm@ 5 per cent

cum

15.060

793.41

11948.75

M-034

22.4 mm to 5.6 mm@ 50 per cent

cum

148.500

838.98

124588.53

M-032

Below 5.6 mm@ 45 per cent

cum

133.430

265.64

35444.35

M-030

KL

18.000

167.07

3007.23

M-189

Cost of water
4.17 B

(i)

For 53 mm maximum size


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

21986.41
24185.06

Cost for 225 cum = a+b+c+d+e

266035.61

Rate per cum = (a+b+c+d+e)/225

1182.38
say

4.17 B

(ii)

For 45 mm maximum size


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

22941.27
25235.39

Cost for 225 cum = a+b+c+d+e

277589.34

Rate per cum = (a+b+c+d+e)/225

1233.73
say

4.18

Suggesti
ve

1182.00

1234.00

Lime, Flyash Stabilised Soil Sub-Base


Construction of Sub-base using lime - Flyash admixture with
granular soil, free from organic matter/ deleterious material or
clayey silts and low plasticity clays having PI between 5 and
20 and liquid limit less than 25 and commercial dry lime,
slaked at site or pre-slaked with CaO content not less than 50
per cent, Flyash to conform to gradation as per clause 4.3 of
IRC: 88-1984, lime + Flyash content ranging between 10 to 30
per cent, the minimum un-confined compressive strength and
CBR value after 28 days curing and 4 days soaking to be
7.5kg/sq, cm and 25 per cent respectively, all as specified in
IRC: 88-1984.
Unit = cum
Taking output = 480 cum (720 tonnes, density 1.50 t/cum)
Assumptions made
Total mass taken for analysis = 720 t
Lime + Flyash admixture @ 20 per cent = 0.2 x 720=144 t
Soil = 720 -144 = 576 t
576 /1.6 = 360 cum
Lime + Flyash = 144 t
Ratio Lime 4 : Flyash 16
Lime = 29 kg.
Flyash = 115 kg.
a)

b)

Labour
Mate

day

0.240

232.16

55.72

L-12

Mazdoor

day

6.000

221.61

1329.66

L-13

Mazdoor (Skilled)

day

1.000

306.03

306.03

L-15

9097.92

P&M-026

Machinery
Hydraulic Excavator 0.90 cum bucket capacity @
60cum/hr. for 360 cum soil
Tipper 10T capacity for carriage of soil 576 tonnes

hour

6.000

1516.32

tonne.km

578 x L

2.68

1548.12 Lead =1 km &


P&M-047

Tipper 10T capacity for carriage of 115 tonnes Flyash

tonne.km

115 x L

2.68

308.02 Lead =1 km &


P&M-047

Tipper 10T capacity for carriage of 29 tonnes of lime


from store to work site
Add 10 per cent of cost of carriage to cover cost of
loading and unloading
Tractor with disc harrows for pulverisation

hour

3.000

830.00

hour

6.000

171.02

1026.11

P&M-053

Motor Grader 110 HP @ 50 cum per hour for mixing inplace and grading
Vibratory roller 8 - 10 tonne

hour

9.600

2488.00

23884.80

P&M-032

hour

6.000

1642.00

9852.00

P&M-059

118

2490.00

P&M-048

249.00

RCD/SOR

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description
Water tanker 6 KL capacity
c)

Rate Rs

12.000

111.24

1334.88

tonne

29.000

4427.31

128391.93

M-188

cum

360.000

25.10

9036.00

M-092

hour

P&M-060

Material
Slaked Lime
Compensation for earth taken from private source

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

18891.02
20780.12

Cost for 480 cum = a+b+c+d+e

228581.31

Rate per cum= (a+b+c+d+e)/480

476.21
say

Note

Cost Rs

Remarks/
Input ref.

Quantity

Unit

1.Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be clearly stated in the cost estimate.
2.Cost of Flyash has not been considered as same will be
available free of cost. Only carriage of Flyash has been
provided.
3.Lime + Flyash has been taken as 20 per cent of total mass
and ratio of lime and Flyash as 1:4 for estimating purposes.
Total quantities will be as per approved design.

119

476.00

Sr No
5.15

Ref. to
MoRTH
Spec.
516

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Slurry Seal
Providing and laying slurry seal consisting of a mixture of fine
aggregates, portland cement filler, bituminous emulsion and
water on a road surface including cleaning of surface, mixing
of slurry seal in a suitable mobile plant, laying and compacting
to provide even riding surface.
Case (i) 5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum
weight of mix = 176 tonnes
a) Labour

b)

c)

Mate

day

0.240

232.16

55.72

L-12

Mazdoor

day

6.000

221.61

1329.66

L-13

Mechanical broom

hour

6.000

462.00

2772.00

P&M-031

Air compressor 250 cfm

hour

6.000

293.76

1762.56

P&M-001

Mobile slurry seal equipment

hour

6.000

926.64

5559.84

P&M-033

Front end loader 1 cum bucket capacity

hour

6.000

1116.00

6696.00

P&M-017

Tipper 5.5 cum capacity for carriage of aggregate from


stockpile on road side to slurry equipment, bitumen
emulsion and filler.
Pneumatic tyred roller with individual wheel load not
exceeding 1.5 tonnes
Water tanker6 KL capacity

hour

6.000

830.00

4980.00

P&M-048

hour

6.000

1143.72

6862.32

P&M-037

hour

2.000

111.24

222.48

P&M-060

19.360 37569.11

727337.97

M-077

Machinery

Material
Residual Binder @ 11 per cent of mix 80 x 2.2 x 0.11
Fine aggregate 4.75 mm and below 87 per cent of total
mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking density1.5,
= 153.12/1.5 = 102.08 cum
Filler @ 2 per cent of total mix = 80 x 2.2 x 0.02
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

tonne
cum

102.080

265.64

27116.53

M-030

tonne

3.520

4427.31

15584.12

M-188

KL

12.000

167.07

2004.82

M-189

80228.40
88251.24

Cost for 16000 sqm = a+b+c+d+e

970763.67

Rate per sqm = (a+b+c+d+e)/16000

60.67
say

5.15

61.00

Case (ii) 3 mm thickness


Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour

b)

c)

Mate

day

0.200

232.16

46.43

L-12

Mazdoor

day

5.000

221.61

1108.05

L-13

Mechanical broom

hour

6.000

462.00

2772.00

P&M-031

Air compressor 250 cfm

hour

6.000

293.76

1762.56

P&M-001

Mobile slurry seal equipment

hour

6.000

926.64

5559.84

P&M-033

Front end loader 1 cum bucket capacity

hour

6.000

1116.00

6696.00

P&M-017

Tipper 5.5 cum capacity for carriage of aggregate from


stockpile on road side to slurry equipment, bitumen
emulsion and filler
Water tanker6 KL capacity

hour

6.000

830.00

4980.00

P&M-048

hour

2.000

111.24

222.48

P&M-060

17.160 37569.11

644685.93

M-077

Machinery

Material
Residual Binder @ 13 per cent of mix = 60 x 2.2 x 0.13

tonne

Fine aggregate 3 mm and below 85 per cent of total


mix, 60x 2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,

cum

Filler @ 2 per cent of total mix = 60x 2.2 x 0.02


Cost of water

119

74.800

288.57

21585.04

M-022

tonne

2.640

4427.31

11688.09

M-188

KL

12.000

167.07

2004.82

M-189

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Quantity

Rate Rs

Remarks/
Input ref.

70311.12
77342.24

Cost for 20000 sqm = a+b+c+d+e

850764.60

Rate per sqm = (a+b+c+d+e)/20000

42.54
say

5.15

Cost Rs

43.00

Case (iii) 1.5 mm thickness


Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour

b)

c)

Mate

day

0.200

232.16

46.43

L-12

Mazdoor

day

5.000

221.61

1108.05

L-13

Mechanical broom

hour

6.000

462.00

2772.00

P&M-031

Air compressor 250 cfm

hour

6.000

293.76

1762.56

P&M-001

Mobile slurry seal equipment

hour

6.000

926.64

5559.84

P&M-033

Front end loader 1 cum bucket capacity

hour

6.000

1116.00

6696.00

P&M-017

Tipper 5.5 cum capacity for carriage of aggregate from


stockpile on road side to slurry equipment, bitumen
emulsion and filler.
Water tanker6 KL capacity

hour

6.000

830.00

4980.00

P&M-048

hour

2.000

111.24

222.48

P&M-060

12.670 37569.11

476000.62

M-077

12495.08

M-022

Machinery

Material
Residual Binder @ 16 per cent of mix, 36 x 2.2 x 0.16

tonne

Fine aggregate 2.36 mm and below,82 per cent of total


mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density 1.5

cum

Filler @ 2 per cent of total mix = 36x 2.2 x 0.02


Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

43.300

288.57

tonne

1.580

4427.31

6995.15

M-188

KL

12.000

167.07

2004.82

M-189

52064.30
57270.73

Cost for 24000 sqm = a+b+c+d+e

629978.07

Rate per sqm = (a+b+c+d+e)/24000

26.25
say

Note
5.16

517

26.00

1.Tack coat, if required to be provided, before laying slurry


seal may be measured and paid separately
Recycling of Bituminous Pavement with Central
Recycling Plant
Recycling pavement by cold milling of existing bituminous
layers, planning the surface after cold milling, reclaiming
excavated material to the extent of 30 per cent of the
required quantity, hauling and stockpiling the reclaimed
material near the central recycling plant after carrying out
necessary checks and evaluation, adding fresh material
including rejuvenators as required, mixing in a hot mix plant,
transporting and laying at site and compacting to the required
grade, level and thickness, all as specified in clause 517.
Unit = cum
Taking output = 120 cum (276 tonnes)
a) Labour

b)

Mate

day

0.480

232.16

111.44

L-12

Mazdoor

day

10.000

221.61

2216.10

L-13

Mazdoor skilled

day

2.000

306.03

612.06

L-15

Cold milling machine @ 20 cum per hour

hour

6.000

855.36

5132.16

P&M-069

Mechanical broom @ 1250 sqm per hour

hour

1.280

462.00

591.36

P&M-031

Air compressor 250 cfm

hour

1.280

293.76

376.01

P&M-001

Bitumen pressure distributor @ 1750 sqm per hour

hour

0.910

986.04

897.30

P&M-004

Hot mix plant 100-120 TPH producing an average of 75


tonnes per hour

hour

3.000 40201.00

120603.00

P&M-021

Machinery

120

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Electric generator set 250 KVA

hour

3.000

2973.00

8919.00

P&M-081

Front end loader 1.00 cum bucket capacity

hour

3.000

1116.00

3348.00

P&M-017

Tipper 5.5 cum capacity

hour

18.000

830.00

14940.00

P&M-048

Smooth wheeled roller 8-10 tonnes

hour 3.00x0.65*

625.00

1218.75

P&M-044

Vibratory roller 8 tonnes

hour 3.00x0.65*

1642.00

3201.90

P&M-059

Smooth wheeled tandem roller 6-8 tonnes

hour 3.00x0.65*

1051.92

2051.24

P&M-045

tonne

1.9872 32859.22

65297.84

M-074

tonne

7.728 32859.22

253936.05

M-074

Material

i) Bitumen
A bitumen content is 4.5 per cent bitumen weight of mix. For
reclaimed material, fresh bitumen will be required to the
extent of 60 per cent of normal requirement.
In a mix of 276 tonnes, 82.8 tonne is reclaimed and balance
193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne @ 60
per cent = 82.8 x 0.60 x0.04 = 1.99
Bitumen required for fresh mix of 193.2 tonnes = 193.2 x
0.04 = 7.73
ii) Aggregates
Percentage of mix requiring fresh aggregates - 70 per cent
Weight of fresh mix = 276 x 0.70 = 193.2 tonne
Weight of fresh aggregate in the mix = 193.2 x 0.96 = 185.47
tonne
Taking average density of 1.5 tonnes/cum, total volume
of aggregate = 123.65 cum.
Size wise requirement of fresh aggregates
37.5 - 25 mm @ 23 per cent

cum

28.440

823.08

23408.40

M-049

25 - 10 mm @ 15 per cent

cum

18.550

989.57

18356.52

M-046

10- 5 mm @ 20 per cent

cum

24.730

770.47

19053.72

M-040

Below 5 mm @40 per cent

cum

49.460

265.64

13138.55

M-030

tonne

5.520

5210.53

28762.11

M-081

Filler (cement) @ 2 per cent = 5.52tonnes of 276 tonne


d)

Overhead charges @ 0.1 on (a+b+c)

58617.15

e)

Contractor's profit @ 0.1 on (a+b+c+d)

64478.87

Cost for 120 cum of DBM = a+b+c+d+e

709267.53

Rate per cum = (a+b+c+d+e)/120

5910.56
say

Note

Although the total rolling time is only 4 hours as per norms, all
the three rollers have to be available at site for 3 hours each
to match with the output of re-cycling plant. To cater for their
idling time, these have been multiplied with a factor of 0.65.

121

5911.00

RCD/SOR

CHAPTER- 6

CEMENT CONCRETE PAVEMENTS


Ref. to
Sr No
MoRTH
Spec.
6.1
601

Description

Unit

Rate Rs

1.120
6.000
22.000

232.16
306.03
221.61

6.000
6.000
6.000
6.000
8.000
8.000
990 x L

1116.00
2052.00
1600.00
2980.00
1642.00
111.24
2.68

cum

405.000

883.00

357615.00

M-052 and
M-054

cum

203.000

219.18

44493.54

M-004

tonne
KL

67.500
48.000

5210.53
167.07

351710.53
8019.27
83224.07
91546.47
1007011.20
2237.80
say
2238.00

M-081
M-189

day
day
day

2.000
15.000
35.000

232.16
306.03
221.61

Dry Lean Cement Concrete Sub- base


Construction of dry lean cement concrete Sub- base over a
prepared sub-grade with coarse and fine aggregate
conforming to IS: 383, the size of coarse aggregate not
exceeding 25 mm, aggregate cement ratio not to exceed
15:1, aggregate gradation after blending to be as per table
600-1, cement content not to be less than 150 kg/ cum,
optimum moisture content to be determined during trial
length construction, concrete strength not to be less than 10
Mpa at 7 days, mixed in a batching plant, transported to site,
laid with a paver with electronic sensor, compacting with 8-10
tonnes vibratory roller, finishing and curing.
Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate
day
Mazdoor skilled
day
Mazdoor
day
b) Machinery
Front end loader 1 cum bucket capacity
hour
Cement concrete batch mix plant @ 75 cum per hour
hour
Electric generator 100 KVA
hour
Paver with electronic sensor
hour
Vibratory roller 8-10 t capacity
hour
Water tanker6 KL capacity
hour
Tipper
tonne.km
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
c) Material
Crushed stone coarse aggregate of 25 mm and 12.5
mm nominal sizes graded as per table 600-1 @ 0.90
cum/cum of concrete conforming to clause 602.2.4.
Coarse Sand as per IS: 383 @ 0.45 cum/cum of
concrete
Cement @ 150 kg/cum of concrete
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 450 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/450
Note

6.2

602

Cost Rs

Remarks/
Input ref.

Quantity

260.02
1836.18
4875.42

L-12
L-15
L-13

6696.00 P&M-017
12312.00 P&M-068
9600.00 P&M-080
17880.00 P&M-034
13136.00 P&M-059
889.92 P&M-060
2651.62 Lead =1 km
& P&M-047
265.16

Quantity provided for aggregate is for estimating purpose.


Exact quantity shall be as per mix design.
Cement Concrete Pavement
Construction of un-reinforced, dowel jointed, plain cement
concrete pavement over a prepared sub base with 43 grade
cement @ 400 kg per cum, coarse and fine aggregate
conforming to IS 383, maximum size of coarse aggregate not
exceeding 25 mm, mixed in a batching and mixing plant as
per approved mix design, transported to site, laid with a fixed
form or slip form paver, spread, compacted and finished in a
continuous operation including provision of contraction,
expansion, construction and longitudinal joints, joint filler,
separation membrane, sealant primer, joint sealant,
debonding strip, dowel bar, tie rod, admixtures as approved,
curing compound, finishing to lines and grades as per
drawing
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate
Mazdoor skilled
Mazdoor
b) Machinery
122

464.32
4590.45
7756.35

L-12
L-15
L-13

RCD/SOR
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Road Sweeper @ 1250 sqm per hour


Front end loader 1 cum bucket capacity
Cement concrete batch mix plant @ 175 cum per hour
(effective output)
Electric generator 250 KVA
Slip form paver with electronic sensor
Water tanker6 KL capacity
Transit truck agitator 5 cum capacity.
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
Concrete joint cutting machine .
Texturing machine .
c) Material
Crushed stone coarse aggregates of 25mm and
12.5mm nominal size @ 0.90 cum/cum of concrete
conforming to clause 602.2.4. .
Sand as per IS: 383 and conforming to clause 602.2.4
@ 0.45 cum/cum of concrete
Cement 43 grade @ 400 kg/cum of concrete
32 mm mild steel dowel bars of grade S 240
16 mm deformed steel tie bars of grade S 415
Separation Membrane of impermeable plastic sheeting
125 micron thick
Pre moulded Joint filler, 25 mm thick for expansion
joint.
Joint sealant
Sealant primer
Plastic sheath,1.25 mm thick for dowel bars
Curing compound
Super plastisizer admixture IS marked as per 91031999 @ 0.5 per cent by weight of cement
Cost of water

Rate Rs

hour
hour
hour

2.800
18.000
6.000

462.00
1116.00
4787.64

1293.60
20088.00
28725.84

hour
hour
hour
tonne.km

6.000
6.000
36.000
2415xL

2973.00
2637.36
111.24
4.32

17838.00 P&M-081
15824.16 P&M-006
4004.64 P&M-060
10432.80 Lead =1 km
& P&M-050

hour
hour

12.000
12.000

214.92
71.50

2579.04
857.95

P&M-083
P&M-088

cum

945.000

883.00

834435.00

M-052 and
M-054

cum

473.000

219.18

103672.14

M-004

tonne 414.000
tonne
9.450
tonne
1.170
sqm 3675.000

5210.53
34467.93
36191.33
11.00

2157157.89
325721.94
42343.86
40418.14

M-081
M-126
M-082
M-164

16.330

708.07

11562.79

M-141

kg 875.000
kg 116.670
sqm
46.670
liter 1850.000
kg 2070.000

17.81
9.01
10.96
91.13
112.77

15580.69
1050.96
511.68
168585.65
233436.07

M-120
M-097
M-138
M-090
M-180

36086.74

M-189

sqm

KL

216.000

167.07

Add 1 per cent of material for cost of miscellaneous


materials like tarpauline, Hessian cloth, metal cap, cotton /
compressible sponge and cradle for dowel bars, work bridges
for men to approach concrete surface without walking over it,
cutting blades and bites, minor equipments like scabbling
machine, threads, ropes, guide wires and any other
unforeseen items.
d) Overhead charges @ 0.1 on (a+b+c)

412576.76

e)

453834.44

39705.64

Contractor's profit @ 0.1 on (a+b+c+d)

4992178.81

Rate per cum = (a+b+c+d+e)/1050

6.3

603

P&M-031
P&M-017
P&M-067

1043.28

Cost for 1050cum = a+b+c+d+e

Note

Cost Rs

Remarks/
Input ref.

Quantity

4754.46
say

4754.00

1.200

232.16

278.59

L-12

The quantities for cement, coarse aggregate and fine


aggregates are for estimating only .The exact quantities will
be as per mix design.
Rolled Cement Concrete Base
Construction of rolled cement concrete base course with
coarse and fine aggregate conforming to IS:383, the size of
coarse aggregate not exceeding 25 mm with minimum,
aggregate cement ratio15:1 and minimum cement content of
200 kg/cum, aggregate gradation to be as per table 600-4
after blending, mixing in batching plant at optimum moisture
content, transporting to site, laying with a paver with
electronic sensor, compacting with 8-10 tonnes smooth
wheeled vibratory roller to achieve, the designed flexural
strength, finishing and curing.
Unit = cum
Taking output = 450 cum (990 tonne)
a)

Labour
Mate

day

Mazdoor skilled

day

7.000

306.03

2142.21

L-15

Mazdoor

day

23.000

221.61

5097.03

L-13

123

RCD/SOR
Sr No

Ref. to
MoRTH
Spec.

Description
b)

Unit

Quantity

Rate Rs

Machinery
hour

6.000

1116.00

6696.00

P&M-017

Cement concrete batch mix plant @ 75 cum per hour

hour

6.000

2052.00

12312.00

P&M-068

Electric generator 100 KVA

hour

6.000

1600.00

9600.00

P&M-080

Paver with electronic sensor @ 75 cum/hr.

hour

6.000

2980.00

17880.00

P&M-034

Vibratory roller 8-10 t capacity

hour

8.000

1642.00

13136.00

P&M-059

Water tanker with 5 km lead 6 KL capacity

hour

8.000

111.24

889.92

P&M-060

tonne.km

990xL

2.68

Add 10 per cent of cost of carriage to cover cost of loading


and unloading

Cost of water

265.16

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

cum

405.000

883.00

357615.00

M-052 and
M-054

cum

203.000

219.18

44493.54

M-004

tonne

90.000

5210.53

468947.37

M-081

KL

48.000

167.07

8019.27

M-189

95002.37
104502.61

Cost for 450cum = a+b+c+d+e

1149528.69

Rate per cum = (a+b+c+d+e)/450

2554.51
say

6.4

6.5

New

Suggestive

2651.62 Lead =1 km
& P&M-047

Material
Crushed stone coarse aggregates of 25mm and
12.5mm nominal size @ 0.90 cum/cum of concrete
conforming to clause 602.2.3.
Sand as per IS: 383 and conforming to clause 602.2.3
@ 0.45 cum/cum of concrete
Cement @ 200 kg/cum of concrete

Note

Remarks/
Input ref.

Front end loader 1 cum bucket capacity

Tipper

c)

Cost Rs

2555.00

The quantities for cement, coarse aggregate and fine


aggregates are for estimating only .The exact quantities will
be as per mix design.
Transition Section between Rigid and Flexible Pavement
Due to change in the properties of materials and type of
construction, a gradual changeover from rigid pavement to
flexible pavement is desirable to avoid any damage at the
butting joint. After provision of an expansion joint in the
cement concrete slab, the thickness of slab should be
tapered to 10 cm over a length of 3 m towards the flexible
pavement. The deficiency of thickness caused due to
tapering of the slab should be made up by the asphaltic
layers.
The quantities of items should be worked out based on the
approved design and drawings and priced as per rates given
under respective clauses for cement concrete and asphaltic
work.
Construction of Base/Sub-Base of Pavement with Lean
Concrete - Flyash.
Construction of Base/sub-base using cement, sand, fly ash
and coarse aggregates proportioned as per table 4 of IRC:
74/1979 and with water content ratio, slump and compressive
strength as defined in the said table, mix prepared in a
batching and mixing plant and compacted with a vibratory
roller 8-10 tonnes capacity within the time limit laid down vide
clause 7.6.3 of IRC: 74-1979, construction joints properly
formed at the end of day's work, cured for 14 days, all as
specified in IRC: 74-1979 and as per approved plans.
Unit = cum
Taking output = 450 cum (990 tonne)
a)

b)

Labour
Mate

day

1.120

232.16

260.02

L-12

Mazdoor skilled

day

6.000

306.03

1836.18

L-15

Mazdoor

day

22.000

221.61

4875.42

L-13

hour

6.000

1116.00

6696.00

P&M-017

Machinery
Front end loader 1 cum bucket capacity
124

RCD/SOR
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Cement concrete batch mix plant @ 75 cum per hour

hour

6.000

2052.00

12312.00

P&M-068

Electric generator 100 KVA

hour

6.000

1600.00

9600.00

P&M-080

Paver finisher with electronic sensor

hour

6.000

2980.00

17880.00

P&M-034

Vibratory roller 8-10 t capacity

hour

8.000

1642.00

13136.00

P&M-059

Water tanker6 KL capacity


Tipper 10 T Capacity

hour

8.000

111.24

tonne.km

990 x L

2.68

cum

405.000

830.30

336271.50

M-055

cum

110.960

219.18

24320.21

M-004

tonne

67.500

5210.53

351710.53

M-081

cum

91.540

0.00

0.00

M-011

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
c) Material
Crushed stone coarse aggregate of 40 mm nominal
size @ 0.90 cum/cum of concrete conforming to table 2
of IRC: 74-1979.
Coarse Sand as per IS: 383 - 1970
Cement @ 150 kg/cum of concrete
Fly ash conforming to IS: 3812 ( Part II )

889.92 P&M-060
2651.62 Lead =1 km
& P&M-047
265.16

( Total fine aggregates = 450 x 0.45 = 202.50 cum To be


divided in ratio of 2 sand : 1.65 flyash. Refer table 4 of IRC:
74-1979).
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

78270.46
86097.50

Cost for 450cum = a+b+c+d+e

947072.51

Rate per cum = (a+b+c+d+e)/450

2104.61
say

Note

2105.00

1.Depending upon approved designs, crushed stone


aggregates of nominal size 20mm can also be used as per
gradation given in table 2 of IRC: 74-1979.
2.The ratio of specific gravities of fly ash and sand has been
assumed to be 0.827.
3.The quantities of materials given in the analyses are for
estimating purposes. Actual quantities shall be as per job mix
formula.
4.Construction procedure as laid down in clause, of IRC: 741979 shall be followed.

6.6

Suggestive

Cement - Flyash Concrete Pavement.


Construction of un-reinforced, dowel jointed, plain cement
concrete pavement over a prepared sub base with 43 grade
cement, coarse and fine aggregate conforming to IS 383,
maximum size of coarse aggregate not exceeding 25 mm,
replacing cement by fly ash to the extent of 15 per cent and
sand by 10 per cent, mixed in a batching and mixing plant as
per approved mix design, transported to site, laid with a fixed
form or slip form paver, spread, compacted and finished in a
continuous operation including provision of contraction,
expansion, construction and longitudinal joints, joint filler,
separation membrane, sealant primer, joint sealant,
debonding strip, dowel bar, tie rod, admixtures as approved,
curing compound, finishing to lines and grades as per
drawing
Unit = cum
Taking output = 1050 cum (2415 tonne)
a)

b)

Labour
Mate

day

2.000

232.16

464.32

L-12

Mazdoor skilled

day

15.000

306.03

4590.45

L-15

Mazdoor

day

35.000

221.61

7756.35

L-13

Machinery
Road Sweeper @ 1250 sqm per hour

hour

2.800

462.00

1293.60

P&M-031

Front end loader 1 cum bucket capacity

hour

18.000

1116.00

20088.00

P&M-017

Cement concrete batch mix plant @ 175 cum per hour


(effective output)
Electric generator 250 KVA

hour

6.000

4787.64

28725.84

P&M-067

hour

6.000

2973.00

17838.00

P&M-081

125

RCD/SOR
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Rate Rs

hour

6.000

2637.36

15824.16

P&M-006

hour

36.000

111.24

4004.64

P&M-060

tonne.km

2415xL

4.32

10432.80

P&M-050
Lead= 1 km

1043.28
hour

12.000

214.92

2579.04

P&M-083

hour

12.000

71.50

857.95

P&M-088

Crushed stone coarse aggregates of 25mm and


12.5mm nominal size @ 0.90 cum/cum of concrete
conforming to clause 602.2.4.

cum

945.000

883.00

834435.00

M-052 and
M-054

Sand as per IS: 383 and conforming to clause 602.2.4

cum

425.000

219.18

93151.50

M-004

Cement 43 grade

tonne

357.000

5210.53

1860157.89

M-081

Fly ash conforming to IS: 3812-1966 (Part-I)

tonne

109.000

0.00

0.00

M-011

32 mm mild steel dowel bars of grade S 240

tonne

9.450

34467.93

325721.94

M-126

16 mm deformed steel tie bars of grade S 415

tonne

1.170
sqm 3675.000

36191.33

42343.86

M-082

11.00

40418.14

M-164

Texturing machine .
Material

Separation Membrane of impermeable plastic sheeting


125 micron thick
Pre moulded Joint filler, 25 mm thick for expansion
joint.
Joint sealant

sqm

16.330

708.07

11562.79

M-141

kg

875.000

17.81

15580.69

M-120

kg

116.670

9.01

1050.96

M-097

Plastic sheath,1.25 mm thick for dowel bars

sqm

46.670

10.96

511.68

M-138

Curing compound

liter 1850.000
kg 2070.000

91.13

168585.65

M-090

112.77

233436.07

M-180

36086.74

M-189

Sealant primer

Super plastisizer admixture IS marked as per 91031999 @ 0.5 per cent by weight of cement
Cost of water

KL

216.000

167.07

Add 1 per cent of material for cost of miscellaneous


materials like tarpauline, Hessian cloth, metal cap, cotton /
compressible sponge and cradle for dowel bars, work bridges
for men to approach concrete surface without walking over it,
cutting blades and bites, minor equipments like scabbling
machine, threads, ropes, guide wires and any other
unforeseen items.
d) Overhead charges @ 0.1 on (a+b+c)

36630.43

381517.18

Contractor's profit @ 0.1 on (a+b+c+d)

419668.89

Cost for 1050cum = a+b+c+d+e

4616357.84

Rate per cum = (a+b+c+d+e)/1050

4396.53
say

Note

Remarks/
Input ref.

Water tanker6 KL capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Concrete joint cutting machine .

e)

Cost Rs

Slip form paver with electronic sensor


Transit truck agitator 5 cum capacity.

c)

Quantity

1.The quantities for cement, coarse aggregate and fine


aggregates are for estimating only .The exact quantities will
be as per mix design.
2.IRC: 68-1976 may be referred for guidelines on the design
of cement-fly ash concrete for rigid pavement construction.
*Calculation of cement, sand and fly ash.
Cement @ 400 kg/cum = 1050 x 400 = 420 tonnes. 15 per
cent of cement to be replaced by fly ash = 63 tonnes.
Balance cement = 357 tonnes. Quantity of fly ash = 63 x
specific gravity of fly ash /specific gravity of cement = 63 x
2.25/3.15 = 45 tonnes.
Sand @ 0.45 cum / cum of concrete = 1050 x 0.45 = 472.50
x 1.6 = 756 tonnes.10 per cent to be replaced by flyash.
Balance sand = 756 x 0.9 = 680.4 tonnes = 680.4 / 1.6 = 425
cum. Quantity of flyash = (756-680.4) x specific gravity of fly
ash/specific gravity of sand = 76.4 x 2.25 / 2.687 = 63.97
tonnes (say 64 tonnes)
Fly ash Total fly ash = 45 + 64 = 109 tonnes.

126

4397.00

CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Sr No
7.1

Ref. to
MoRTH
Spec.
702

Description

Unit

Cost Rs

Remarks/ Input
ref.

Quantity

Rate Rs

day
day
day

0.040
0.250
0.500

232.16
306.03
221.61

9.29
76.51
110.81

L-12
L-15
L-13

sqm
sqm
sqm

1.000
1.000
2.000

77.51
77.51
60.75

77.51
77.51
121.50
5.53

M-107
M-106
M-108

Sub-Surface Drain with Geotextiles


Construction of sub surface drain 200 mm dia using geotextiles
treated with carbon black with physical properties as given in
clause 702.2.3 formed in to a stable network and a planar
geocomposite structure, joints wrapped with geotextile to prevent
ingress of soil, all as per clause 702 and approved drawings
including excavation and backfilling
Unit = Running metre
Taking output = one metre
a) Labour
Mate
Mazdoor skilled
Mazdoor
b) Material
Geonets, geomembrane and geotextile to make planar
geocomposite stable network for sub surface drain including
wrapping of joints with 160 mm over lapping with geotextile .
Geonets
Geomembrane
Geotextile
Add 2 per cent cost of material for miscellaneous items like
synthetic cord
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per metre = a+b+c+d

7.2

702.4

703

0.040
0.250
0.500

232.16
306.03
221.61

9.29
76.51
110.81

L-12
L-15
L-13

1.000
1.250

65.26
60.75

65.26
75.94
2.82

M-134
M-109

Note Surplus excavated material to be used at site. Hence seprate cost


for disposal not added.
Narrow Filter Sub-Surface Drain
Construction of a narrow filter sub- surface drain consisting of
porous or perforated pipe laid in narrow trench surrounded by a
geotextile filter fabric, with a minimum of 450 mm overlap of fabric
and installed as per clause 702.3 and 309.3.5 including excavation
and backfilling
Unit = Running metre length
Taking output = one metre
a) Labour
Mate
day
Mazdoor skilled
day
Mazdoor
day
b) Material
Perforated geosynthetic pipe 150 mm dia
metre
Geotextile filter fabric
sqm
Add 2 per cent cost of material for miscellaneous item like
synthetic cord
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per metre = a+b+c+d

7.3

say

47.87
52.65
579.17
579.00

say

34.06
37.47
412.15
412.00

232.16
221.61

185.73
4432.20

Note Surplus excavated material to be used at site. Hence Separate cost


for disposal not added.
Laying Paving Fabric Beneath a Pavement Overlay
Providing and laying paving fabric with physical requirements as
per table 704-2 over a tack coat of paving grade Bitumen 80-100
penetration, laid at the rate of 1 kg per sqm over thoroughly
cleaned and repaired surface to provide a water resistant
membrane and crack retarding layer. Paving fabric to be free of
wrinkling and folding and to be laid before cooling of tack coat,
brooming and rolling of surface with pneumatic roller to maximise
paving fabric contact with pavement surface
Unit = sqm
Taking output = 2800 sqm
a) Labour
Mate
Mazdoor

day
day
127

0.800
20.000

L-12
L-13

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Machinery
Road sweeper 1250 sqm per hour
Pneumatic roller 14 tonnes 2000 sqm per hour
Bitumen pressure distributor 1750 sqm per hour
c) Material
Paving Fabric
Paving Bitumen 80-100
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 2800 sqm = a+b+c+d+e
Rate per sqm =(a+b+c+d+e)/2800

Quantity

Rate Rs

Cost Rs

2.240
1.400
1.680

462.00
1143.72
986.04

1034.88
1601.21
1656.55

sqm 2940.000
tonne
2.800

60.75
31938.10

178609.66
89426.68
27694.69
30464.16
335105.76
119.68
120.00

Remarks/ Input
ref.

b)

hour
hour
hour

say
7.4

704

P&M-031
P&M-037
P&M-004
M-133
M-075

Laying Boulder Apron in Crates of Synthetic Geogrids


Providing, preparing and laying of geogrid crated apron 1 m x 5 m,
600 mm thick including excavation and backfilling with baffles at 1
metre interval, made with geogrids having characteristics as per
clause 704.2, joining sides with connectors/ring staples, top
corners to be tie tensioned, placing of suitable cross interval ties in
layers of 300 mm connecting opposite side with lateral braces and
tied with polymer braids to avoid bulging, constructed as per clause
704.3. filled with stone with minimum size of 200 mm and specific
gravity not less than 2.65, packed with stone spalls, keyed to the
foundation recess in case of sloping ground and laid over a layer of
geotextile to prevent migration of fines, all as per clause 704 and
laid as per clause 2503.3 and approved design.

Unit = cum
Taking output = 3.00 cum
a) Labour

b)

Mate

day

0.060

232.16

13.93

L-12

Mazdoor skilled

day

0.500

306.03

153.02

L-15

Mazdoor

day

1.500

221.61

332.42

L-13

sqm

21.000

77.51

1627.72

M-105

Material
Geo grids
Connectors/ Staples

each

50.000

#VALUE!

#VALUE!

M-085

metre

20.000

#VALUE!

#VALUE!

M-140

Stones with minimum size of 200 mm

cum

3.450

397.97

1373.00

M-003

Stones spall for filling voids

cum

0.450

370.06

166.53

M-008

Polymer braids

c)

Overhead charges @ 0.1 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Cost for 3 cum = a+b+c+d

#VALUE!

Rate per cum = (a+b+c+d)/ 3

#VALUE!
say

7.5

3100

Reinforced Earth Structures


Reinforced earth Structures have four main components as under:
a) Excavation for foundation, foundation concrete and cement
concrete grooved seating in the foundation for facing elements
(facia material).
b) Facia material and its placement.
c)
Assembling, joining with facing elements and laying of the
reinforcing elements.
d) Earth fill with granular material which is to be retained by the
wall.
Each component is analysed separately as under:
considering Average height of wall = 8 m.

7.5

3102

(i) Assembling, joining and laying of reinforcing elements.


A

With reinforcing element of steel / Aluminium strips /


polymeric strips.
Unit = Running Metre
Taking Output = 450 m
a)

Labour
128

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/ Input
ref.

Mate

day

0.360

232.16

83.58

L-12

Mazdoor

day

6.000

221.61

1329.66

L-13

Mazdoor skilled

day

3.000

306.03

918.09

L-15

@ Reinforcement strips 60 mm wide 5 mm thick as per clause


3102.
1.Galvanised carbon steel strips
metre

450*1.1

480.32

237758.96

M-154

metre

450*1.1

480.32

237758.96

M-153

metre

450*1.1

237.03

117328.88

M-157

metre

450*1.1

237.03

117328.88

M-156

5.Glass reinforced polymer/fibre reinforced polymer/polymeric metre


strips
@ Any one of the above alternative may be adopted as per
approved design.

450*1.1

480.32

237758.96

M-155

b)

Material

or
2.Copper Strips
or
3.Aluminium Strips
or
4.Stainless steel strips
or

Add 10 per cent of the cost of reinforcing strip towards accessories


like tie-strips, nuts and bolts and loops/lugs for joining reinforcing
elements with the facia pannels, overlaps, heat bonding or
extension.
Type 1.Galvanised carbon steel strips
1
c) Overhead charges @ 0.1 on (a+b)
d)

24009.03

Contractor's profit @ 0.1 on (a+b+c)

24009.03

Cost of 450 m = a+b+c+d

288108.35

Rate per metre =(a+b+c+d)/450

640.24
say

Type 2.Copper Strips


2
c) Overhead charges @ 0.1 on (a+b)
d)

24009.03

Contractor's profit @ 0.1 on (a+b+c)

24009.03

Cost of 450 m = a+b+c+d

288108.35

Rate per metre =(a+b+c+d)/450

640.24
say

Type 3.Aluminium Strips


3
c) Overhead charges @ 0.1 on (a+b)
d)

Contractor's profit @ 0.1 on (a+b+c)

11966.02
143592.25

Rate per metre =(a+b+c+d)/450

319.09
say

Type 4.Stainless steel strips


4
c) Overhead charges @ 0.1 on (a+b)

11966.02
143592.25

Rate per metre =(a+b+c+d)/450

319.09
say

Type 5.Glass reinforced polymer/fibre reinforced polymer/polymeric


strips
5
c) Overhead charges @ 0.1 on (a+b)

24009.03
288108.35

Rate per metre =(a+b+c+d)/450


B

319.00

24009.03

Contractor's profit @ 0.1 on (a+b+c)

Cost of 450 m = a+b+c+d

7.5(i)

319.00

11966.02

Contractor's profit @ 0.1 on (a+b+c)

Cost of 450 m = a+b+c+d

d)

640.00

11966.02

Cost of 450 m = a+b+c+d

d)

640.00

640.24
say

640.00

232.16

83.58

With reinforcing elements of synthetic geogrids


Unit = sqm
Taking output = 300 sqm
a)

Labour
Mate

day
129

0.360

L-12

Ref. to
MoRTH
Spec.

Sr No

Description

b)

Unit

Quantity

Rate Rs

day

6.000

221.61

1329.66

L-13

Mazdoor skilled

day

3.000

306.03

918.09

L-15

sqm

300.000

85.89

25767.05

Material

c)

Add 10 per cent of the cost of reinforcing elements (synthetic


geogrids) for accessories like tie-strips, nuts and bolts and
loops/lugs for joining reinforcing elements with the facia
pannels, overlaps and other protective elements for synthetic
geogrids.
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3374.26

Cost of 300 sqm of Synthetic geogrids = a+b+c+d

37116.85

M-181

2576.71

3067.51

Rate per sqm = (a+b+c+d)/ 300

123.72
say

3104

Remarks/ Input
ref.

Mazdoor

Synthetic Geogrids as per clause 3102.8 and approved


design and specifications.

7.5

Cost Rs

124.00

(ii) Facing elements of RCC


Unit = sqm
Taking output = 75 sqm
a)

b)

Labour
Mate

day

0.180

232.16

41.79

L-12

Mazdoor

day

3.000

221.61

664.83

L-13

Mazdoor skilled

day

1.500

306.03

459.05

L-15

hour

6.000

532.00

3192.00

P&M-013

Pre-cast RCC M-35 facing elements of size as per design and cu.m
18 cm thick for 75 sqm. (Refer Item 12.8 (H))
HYSD steel @ 5 kg / sqm (Refer Item 12.6)
tonnes

13.500

3631.00

49018.50

0.380

55828.00

21214.64

Item 12.8 (H)


Case I
Item 13.6

Machinery
Light crane with lifting capacity upto 3 tonne

c)

Material

Add 2 per cent of cost of facia pannels, for all necessary temporary
form work, scaffolding and provision of loops/lugs for lifting of
pannels and joining the reinforcing elements.
d)

Overhead charges @ 0.1 on (a+b)

e)

Contractor's profit @ 0.1 on (a+b+d)

1404.66

435.77
479.34

Cost for 75 sqm = a+b+c+d+e

76910.58

Rate per sqm = (a+b+c+d+e)/ 75

1025.47
say

Note 1.The specification and construction details to be adopted shall be


as per section 3100 of MoRTH Specification.
2.Drainage arrangement shall be made as per approved design
and drawings.
3.The quantity of filler media shall be calculated as per approved
design and specifications and shall be priced separately.The rate
for same to be adopted from chapter 15.
4.Excavation for foundation including foundation concrete and
groove in the foundation for seating of bottom most facia panel and
capping beam to be calculated as per design and priced
separately. The rates for excavation and foundation concrete shall
be taken from the chapter 12 & 13 in bridge section.

5.The earth fill to be retained is not included in this analysis. The


same is to be worked out and provided separately complete as per
clause 305.
6.For compaction of Earthwork, attention is invited to clause 3105.5
of MoRTH Specification.
7.Length of reinforcing strips will vary with the height of wall and will
be as per approved design and drawings.
8.The type of reinforcing elements to be adopted shall be as per
approved design and specifications.
9.The market rate for supply of reinforcing elements and their
accessories are to be ascertained from reputed firms in the field of
earth reinforcement.

130

1025.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

10.The earth fill material shall be clean, free draining, granular with
high friction and low cohesion, non-corrosive, coarse grained with
not 10 per cent of particles passing 75 micron sieve, free of any
deleterious matter, chlorides, salts, acids, alkalies, mineral oil,
fungus and microbes and shall be of specified PH value.
11.Capping beam is to be priced separately as per approved
design. The rate for cement concrete shall be taken from the
chapter of sub-structure in bridge section.
12.The cost of reinforced earth retaining wall shall include
following:
(I) Excavation for foundation including backfilling.
(ii) Foundation concrete as per approved design.
(iii) Cost of facial pannels and their erection .
(iv) Cost of reinforcing elements including their fixing and joining
with the facial pannels.
(v) Drainage arrangement including filter media as per approved
design and drawings.
13. The compacted earth filling to be retained shall form part of
embankment.

131

Quantity

Rate Rs

Cost Rs

Remarks/ Input
ref.

CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Sr No
8.1

Ref. to
MoRTH
Spec.
408

Description

A.

Unit

Cast in Situ Cement Concrete M20 Kerb


Construction of cement concrete kerb with top and bottom
width 115 and 165 mm respectively, 250 mm high in M 20
grade PCC on M-10 grade foundation 150 mm thick,
foundation having 50 mm projection beyond kerb stone, kerb
stone laid with kerb laying machine, foundation concrete laid
manually, all complete as per clause 408
Unit = Running metre
Taking output = 360 metre
Using Concrete Mixer
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base= 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate
Mason
Mazdoor
b) Machinery
Kerb casting machine @ 60 metres/hour
Concrete mixer 0.48/0.28 cum capacity
Water tanker6 KL capacity
c) Material
Crushed stone aggregate 20 mm nominal size 59 per
cent
Coarse sand 30 per cent
Cement 11 per cent
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 360 meter = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/360
Using Concrete Batching and Mixing Plant
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base = 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate
Mason
Mazdoor
b) Machinery
Kerb casting machine @ 60 metres/hour
Concrete batching and mixing plant @ 15 cum/hr.
Water tanker6 KL capacity
Tipper 5.5 cum capacity
c) Material
Crushed stone aggregate 20 mm nominal size 59 per
cent
Coarse sand 30 per cent
Cement 11 per cent
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 360 meter = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/360

Quantity

Rate Rs

408

Cast in Situ Cement Concrete M 20 Kerb with Channel


Construction of cement concrete kerb with channel with top
and bottom width 115 and 165 mm respectively, 250 mm
high in M 20 grade PCC on M10 grade foundation 150 mm
thick, kerb channel 300 mm wide, 50 mm thick in PCCM20
grade, sloped towards the kerb, kerb stone with channel laid
with kerb laying machine, foundation concrete laid manually,
all complete as per clause 408
132

Remarks/ Input
ref.

day
day
day

0.720
2.000
16.000

232.16
353.52
221.61

167.16
707.04
3545.76

L-12
L-11
L-13

hour
hour
hour

6.000
12.000
5.000

279.72
211.68
111.24

1678.32
2540.16
556.20

P&M-029
P&M-009
P&M-060

cum

21.790

938.92

20459.07

M-053

cum
tonne
KL

10.900
5.700
30.000

219.18
5210.53
167.07

M-005
M-081
M-189

say

2389.06
29700.00
5012.05
6675.48
7343.03
80773.32
224.37
224.00

day
day
day

0.120
1.000
2.000

232.16
353.52
221.61

27.86
353.52
443.22

L-12
L-11
L-13

hour
hour
hour
hour

6.000
1.600
5.000
6.000

279.72
1704.24
111.24
830.00

1678.32
2726.78
556.20
4980.00

P&M-029
P&M-003
P&M-060
P&M-048

cum

21.790

938.92

20459.07

M-053

cum
tonne
KL

10.900
5.700
30.000

219.18
5210.53
167.07

2389.06
29700.00
5012.05
6832.61
7515.87
82674.56
229.65
230.00

M-004
M-081
M-189

say
8.2

Cost
Rs

Sr No

Ref. to
MoRTH
Spec.

Description
A

Unit

Quantity

Rate Rs

Labour
Mate

b)

c)

day

0.720

232.16

167.16

L-12

707.04

L-11

Mason

day

2.000

353.52

Mazdoor

day

16.000

221.61

3545.76

L-13

Machinery
Kerb casting machine @ 50 metres/hour for laying kerb
and channel
Concrete mixer 0.48/0.28

hour

6.000

279.72

1678.32

P&M-029

hour

16.000

211.68

3386.88

P&M-009

Water tanker6 KL capacity

hour

6.000

111.24

667.44

P&M-060

Material
Crushed stone aggregate 20 mm nominal size 60 per
cent
Coarse sand 30 per cent

cum

36.590

938.92

34355.08

M-053

cum

18.300

219.18

4010.99

M-005

Cement 10 per cent

tonne

9.010

5210.53

46946.84

M-081

KL

36.000

167.07

6014.46

M-189

Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

10148.00
11162.80
122790.76

Cost for 300 metre = a+b+c+d+e

409.30

Rate per metre = (a+b+c+d+e)/300


say
B

Remarks/ Input
ref.

Using Concrete Mixer


Unit = Running metre
Taking output = 300 metre length
Cement Concrete
Cement concrete of grade M20= 17.48 cum
Cement concrete of grade M10 for base = 23.18 cum
Total Concrete = 40.66 cum
a)

8.2

Cost
Rs

409.00

Using Concrete Batching and Mixing Plant


Unit = Running metre
Taking output = 300 metre length
Cement Concrete
Cement concrete of grade M20= 17.48 cum
Cement concrete of grade M10 for base = 23.18 cum
Total Concrete = 40.66 cum
a)

b)

c)

Labour
Mate

day

0.120

232.16

27.86

L-12

Mason

day

1.000

353.52

353.52

L-11

Mazdoor

day

2.000

221.61

443.22

L-13

Machinery
Kerb casting machine @ 50 metres/hour for laying kerb
and channel
Concrete batching and mixing plant @ 15 cum/hr.

hour

6.000

279.72

1678.32

P&M-029

hour

2.700

1704.24

4601.45

P&M-003

Water tanker6 KL capacity

hour

6.000

111.24

667.44

P&M-060

Tipper of 5.5 cum capacity

hour

6.000

830.00

4980.00

P&M-048

Material
Crushed stone aggregate 20 mm nominal size 60 per
cent
Coarse sand 30 per cent

cum

36.590

938.92

34355.08

M-053

cum

18.300

219.18

4010.99

M-004

Cement 10 per cent

tonne

9.010

5210.53

46946.84

M-081

KL

36.000

167.07

6014.46

M-189

Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

10407.92
11448.71
125935.81

Cost for 300 meter = a+b+c+d+e

419.79

Rate per metre = (a+b+c+d+e)/300


say
8.3

801

Printing New Letter and Figures of any Shade


Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade

133

420.00

Sr No

Ref. to
MoRTH
Spec.

Description
(i)

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Hindi ( Matras commas and the like not to be measured and


paid for Half letter shall be counted as half )
Details for 100 letters of 16 cm height i.e. 1600 cm
Unit = per cm height per letter
a)

Labour
Mate

b)

day

0.120

232.16

27.86

L-12

707.04

L-18

221.61

L-13

96.85

M-131

Painter

day

2.000

353.52

Mazdoor

day

1.000

221.61

Litre

0.700

138.35

Material
Paint

c)

Overhead charges @ 0.1 on (a+b)

105.34

d)

Contractor's profit @ 0.1 on (a+b+c)

115.87
1274.56

Cost for 1600 cm = a+b+c+d

0.80

Rate per cm height per letter = (a+b+c+ d)/1600


say
8.3

(ii)

0.80

English and Roman


Hyphens and the like not to be measured and paid for
Detail for 100 letters of 16 cm height. i.e.1600 cm
Unit = per cm height per letter
a)

b)

Labour
Mate

day

0.070

232.16

16.25

L-12

Painter Ist class

day

1.250

353.52

441.90

L-18

Mazdoor

day

0.500

221.61

110.81

L-13

Litre

0.500

138.35

69.18

M-131

Material
Paint

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

63.81
70.19
772.14

Cost for 1600 cm = a+b+c+d

0.48

Rate per cm height per letter = (a+b+c +d)/1600


say
8.4

801

0.50

Retro-Reflectorised Traffic Signs


Providing and fixing of retro- reflectorised cautionary,
mandatory and informatory sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 1.5 mm thick supported on a mild steel
angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the
ground by means of properly designed foundation with M15
grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below
ground level as per approved drawing
Unit = Each
Taking output = one traffic sign

a)

i)

Excavation for foundation

cum

0.216

224.00

48.38

item 3.13 (1) A

ii)

Cement concrete M15 grade

cum

0.120

4109.00

493.08

Item 12.8 (A)

iii)

Painting angle iron post two coats

sqm

0.430

48.00

20.64

Item 8.9

day

0.010

232.16

2.32

L-12

day

0.250

221.61

55.40

L-13

kg

19.000

37.995

721.910

Labour (For fixing at site)


Mate
Mazdoor

b)

(i)
( ii )
( iii )

Material

Mild steel angle iron 75 x 75 x 6 mm


Aluminium sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as
applicable
Add 2 per cent of cost of angle iron towards cost of drilling
holes, nuts, bolts etc.
90 cm equilateral triangle
or
60 cm equilateral triangle
or
60 cm circular
134

M-179 /1000

14.44
sqm

0.350

7902.33

2765.81

M-061

sqm

0.156

7902.33

1232.76

M-061

sqm

0.283

7902.33

2236.36

M-061

Sr No

Ref. to
MoRTH
Spec.
( iv )

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Description

Unit

or
80 mm x 60 mm rectangular

sqm

0.480

7902.33

3793.12

M-061

sqm

0.270

7902.33

2133.63

M-061

sqm

0.360

7902.33

2844.84

M-061

sqm

0.672

7902.33

5310.36

M-061

hour

0.010

171.02

1.71

or
(v)
(vi )
( vii )
c)

60 cm x 45 cm rectangular
or
60 cm x 60 cm square
or
90 cm high octagon
Machinery
Tractor-trolley

(i)

90 cm equilateral triangle
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

356.16
391.78
4871.64

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)


say
( ii )

d)

Overhead charges @ 0.1 on (a+b+c)

202.85

e)

Contractor's profit @ 0.1 on (a+b+c+d)

223.14
3016.65

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)


say
( iii )

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

303.21
333.54
4231.00
say

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

458.89
504.78
6114.67
say

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

292.94
322.24
4106.69
say

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

364.06
400.47
4967.26
say

d)

Overhead charges @ 0.1 on (a+b+c)

610.61

e)

Contractor's profit @ 0.1 on (a+b+c+d)

671.68
7950.54
say

1.Any one area of aluminium sheeting given at (i) to (vii) may


be adopted as per site requirement and in accordance with
IRC : 67
2.Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
3. The depth of foundation and quantity of cement concrete in
the foundation are indicative. These may be increased for
areas having higher wind velocities like in coastal areas. This
is applicable to all road signs and directions boards.

8.5

801

4967.00

90 cm high octagon

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

Note

4107.00

60 cm x 60 cm square

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)


( vii )

6115.00

60 cm x 45 cm rectangular

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)


(vi )

4231.00

80 mm x 60 mm rectangular

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)


(v)

3017.00

60 cm circular

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)


( iv )

4872.00

60 cm equilateral triangle

Direction and Place Identification Signs upto 0.9 sqm


Size Board.

135

7951.00

P&M-053

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Providing and erecting direction and place identification retroreflectorised sign as per IRC:67 made of high intensity grade
sheeting vide clause 801.3, fixed over aluminium sheeting, 2
mm thick with area not exceeding 0.9 sqm supported on a
mild steel single angle iron post 75 x 75 x 6 mm firmly fixed
to the ground by means of properly designed foundation with
M15 grade cement concrete 45 x 45 x 60 cm, 60 cm below
ground level as per approved drawing
Unit = sqm
Taking output = 0.9 sqm

a)

i) Excavation for foundation

cum

0.216

224.00

48.38

Item No. 3.13

ii) Cement concrete M15 grade

cum

0.120

4109.00

493.08

Item 12.8 (A)

iii) Painting angle iron post two coats

sqm

0.430

48.00

20.64

Item 8.9

Mate

day

0.010

232.16

2.32

L-12

Mazdoor

day

0.200

221.61

44.32

L-13

kg

19.000

37.995

721.91

M-179 /1000

sqm

0.900

7902.33

7112.09

M-061

Labour (For fixing at site)

b)

Material
Mild steel angle iron 75 mm x 75 mm x 6 mm,2.85
metres long
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting of size 0.9 sqm
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.
c) Machinery
Tractor-trolley

156.68

hour

0.020

171.02

Overhead charges @ 0.1 on (a+b+c)

804.07

e)

Contractor's profit @ 0.1 on (a+b+c+d)

884.48

11434.90
say

8.6

801

P&M-053

10291.41

Cost for 0.9 sqm =I+ii+ii+ a+b+c+d+e


Rate per sqm (for sign having area upto 0.9 sqm) =
(I+ii+iii+a+b+c+d+e)/0.90

Note

3.42

d)

11435.00

I) Lettering and arrow marks on sign board to be provided


separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
Direction and Place Identification Signs with size more
than 0.9 sqm size Board.
Providing and erecting direction and place identification retroreflectorised sign as per IRC :67 made of high intensity grade
sheeting vide clause 801.3, fixed over aluminium sheeting, 2
mm thick with area exceeding 0.9 sqm supported on a mild
steel angle iron post 75 mm x 75 mm x 6 mm, 2 Nos. firmly
fixed to the ground by means of properly designed foundation
with M 15 grade cement concrete45 cm x 45 cm x 60 cm, 60
cm below ground level as per approved drawing
Unit = sqm
Taking output = 1.50 sqm
i)

a)

b)

cum

Excavation for foundation

0.430

224.00

96.32

Item No. 3.13

986.16

Item 12.8 (A)

41.28

Item 8.9

ii)

Cement concrete M15 grade

cum

0.240

4109.00

iii)

Painting angle iron post 2 coats

sqm

0.860

48.00

Mate

day

0.010

232.16

2.32

L-12

Mazdoor

day

0.300

221.61

66.48

L-13

kg

38.000

37.995

1443.82

M-179 /1000

sqm

1.500

7902.33

11853.49

M-061

Labour (For fixing at site)

Material
Mild steel angle iron 75 mm x 75 mm x 6 mm, 2.85
metres long, 2 nos

Aluminium sheeting fixed with encapsulated lens type


reflective sheeting
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.
136

265.95

Sr No

Ref. to
MoRTH
Spec.

Description
c)

Unit

Quantity

Rate Rs

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

hour

0.020

171.02

P&M-053

1499.90
17622.70
11748.46
say

802

3.42
1363.55

Cost for 1.5 sqm =I+ii+ii+ a+b+c+d+e


Rate per sqm ( for sign having area more than 0.9 sqm) =
( i+ii+iii+a+b+c+d+e)/1.50

8.7

Remarks/ Input
ref.

Machinery
Tractor-trolley

Note

Cost
Rs

11748.00

i) Lettering and arrow marks on sign board to be provided


separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
Overhead Signs
Providing and erecting overhead signs with a corrosion
resistant 2mm thick aluminium alloy sheet reflectorised with
high intensity retro-reflective sheeting of encapsulated lense
type with vertical and lateral clearance given in clause 802.2
and 802.3 and installed as per clause 802.7 over a designed
support system of aluminium alloy or galvanised steel trestles
and trusses of sections and type as per structural design
requirements and approved plans

Truss and Vertical Support


Unit = tonne
Taking output = 1 tonne
a)

Labour
Mate

day

0.240

232.16

55.72

L-12

Blacksmith

day

2.000

353.52

707.04

L-02

Mazdoor including for handling & fixing at site.

day

4.000

221.61

886.44

L-13

tonne

1.050

46239.26

48551.23

b)

Material
Aluminium alloy/galvanised steel including 5 per cent
wastage
Add 1 per cent on cost of material for nuts, bolts and drilling
and welding consumables
Add 15 per cent on cost of material for fabrication of trusses
as per approved design
c) Machinery

485.51
7355.51

Crane 3 tonne capacity

hour

3.000

532.00

Truck

hour

0.500

745.00

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

P&M-013

372.50

P&M-057

6601.09
72612.04
say

1596.00
6000.99

Rate per tonne = (a+b+c+d+e)


8.7

M-060

72612.00

Aluminium Alloy Plate for Over Head Sign


Unit = sqm
Taking output = 1 sqm
a)

Labour
Mate

day

0.020

232.16

4.64

L-12

Blacksmith

day

0.100

353.52

35.35

L-02

Mazdoor

day

0.150

221.61

33.24

L-13

sqm

1.000

1580.88

1580.88

b)

Material
Aluminium alloy plate,2 mm thick, fixed with high
intensity grade sheeting vide clause 801.3
Miscellaneous
Add 1 per cent of cost of labour for lifting arrangement, like
ladders, pulleys, ropes etc
c) Overhead charges @ 0.1 on (a+b)
d)

0.73
165.49
182.03

Contractor's profit @ 0.1 on (a+b+c)

2002.37

Rate per sqm = (a+b+c+d)


say

137

2002.00

M-059

Sr No

Ref. to
MoRTH
Spec.

Description

Note

8.8

803

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

1. The cost of excavation and foundation concrete for fixing


of vertical support system to be worked out separately as per
the approved drawing/design and to be included in the
estimate.
2. Lettering and arrow marks on sign board to be provided
separately as per actual requirement. Rates for these items
have been included separately in this chapter.
Painting Two Coats on New Concrete Surfaces
Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces
Unit = sqm
Taking output = 40 sqm
a)

Labour
Mate

day

0.120

232.16

27.86

L-12

Painter

day

2.000

353.52

707.04

L-18

Mazdoor

day

1.000

221.61

221.61

L-13

Litre

6.000

138.35

830.12

M-132

b)

Material

c)

Paint conforming to requirement of clause 803.3.


Add for scaffolding @ 1 per cent of labour cost where
required
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

9.57
179.62
197.58
2173.40

Cost for 40 sqm = a+b+c+d

54.33

Rate per sqm = (a+b+c+d)/40


say
8.9

803

54.00

Painting on Steel Surfaces


Providing and applying two coats of ready mix paint of
approved brand on steel surface after through cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a)

b)

Labour
Mate

day

0.030

232.16

6.96

L-12

Painter

day

0.450

353.52

159.08

L-18

Mazdoor

day

0.250

221.61

55.40

L-13

Litre

1.250

138.35

172.94

M-131

Material
Paint ready mixed approved brand.

1.73

Add @ 1 per cent on cost of material for scaffolding


c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

39.61
43.57
479.31

Cost for 10 sqm = a+b+c+d

47.93

Rate per sqm= (a+b+c+d)/10


say
8.10

803

48.00

Painting on Wood Surfaces


Providing and applying two coats of ready mix paint of
approved brand on wood surface after thorough cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a)

Labour
Mate

b)

day

0.030

232.16

6.96

L-12

176.76

L-18

Painter

day

0.500

353.52

Mazdoor

day

0.200

221.61

44.32

L-13

Litre

1.500

138.35

207.53

M-131

Material
Paint ready mixed of approved brand.
Add @ 1 per cent on cost of material for scaffolding

2.08

c)

Overhead charges @ 0.1 on (a+b)

43.77

d)

Contractor's profit @ 0.1 on (a+b+c)

48.14
138

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

52.96

Rate per sqm = (a+b+c+d)/10


say
803

(i)

Remarks/ Input
ref.

529.56

Cost for 10 sqm = a+b+c+d

8.11

Cost
Rs

53.00

Painting Lines, Dashes, Arrows etc on Roads in Two


Coats on New Work
Painting lines, dashes, arrows etc on roads in two coats on
new work with ready mixed road marking paint conforming to
IS:164 on bituminous surface, including cleaning the surface
of all dirt, dust and other foreign matter, demarcation at site
and traffic control
Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a)

b)

Labour
Mate

day

0.090

232.16

20.89

L-12

Painter

day

0.550

353.52

194.44

L-18

Mazdoor

day

1.550

221.61

343.50

L-13

Litre

1.480

138.35

204.76

M-132

Material
Road marking Paint as per IS :164

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

76.36
83.99
923.94

Cost for 10 sqm = a+b+c+d

92.39

Rate per sqm= (a+b+c+d)/10


say
8.11

(ii)

92.00

Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a)

b)

Labour
Mate

day

0.070

232.16

16.25

L-12

Painter

day

0.350

353.52

123.73

L-18

Mazdoor

day

1.350

221.61

299.17

L-13

Litre

1.480

138.35

204.76

M-132

Material
Road marking paint

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

64.39
70.83
779.14

Cost for 10 sqm = a+b+c+d

77.91

Rate per sqm = (a+b+c+d)/10

8.12

803

(i)

say

78.00

Painting Lines, Dashes, Arrows etc on Roads in Two


Coats on Old Work
Painting lines, dashes, arrows etc on roads in two coats on
old work with ready mixed road marking paint conforming to
IS: 164 on bituminous surface, including cleaning the surface
of all dirt, dust and other foreign matter, demarcation at site
and traffic control
Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a)

b)

Labour
Mate

day

0.060

232.16

13.93

L-12

Painter Ist class

day

0.300

353.52

106.06

L-18

Mazdoor

day

1.250

221.61

277.01

L-13

Litre

0.900

138.35

124.52

M-132

Material
Road marking paint

c)

Overhead charges @ 0.1 on (a+b)

52.15

d)

Contractor's profit @ 0.1 on (a+b+c)

57.37
631.03

Cost for 10 sqm = a+b+c+d

63.10

Rate per sqm = (a+b+c+d)/10


say
139

63.00

Sr No

Ref. to
MoRTH
Spec.

8.12

Description
(ii)

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a)

b)

Labour
Mate

day

0.070

232.16

16.25

L-12

Painter Ist class

day

0.350

353.52

123.73

L-18

Mazdoor

day

1.350

221.61

299.17

L-13

Litre

0.900

138.35

124.52

M-132

Material
Road marking Paint

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

56.37
62.00
682.05

Cost for 10 sqm= a+b+c+d

68.20

Rate per sqm = (a+b+c+d)/10

8.13

803

say

68.00

Road Marking with Hot Applied Thermoplastic


Compound with Reflectorising Glass Beads on
Bituminous Surface
Providing and laying of hot applied thermoplastic compound
2.5 mm thick including reflectorising glass beads @ 250 gms
per sqm area, thickness of 2.5 mm is exclusive of surface
applied glass beads as per IRC:35 .The finished surface to
be level, uniform and free from streaks and holes.
Unit = sqm
Taking output = 640 sqm
a)

b)

c)

Labour
Mate

day

0.500

232.16

116.08

L-12

Mazdoor

day

2.000

221.61

443.22

L-13

Road marking machine @ 80 sqm per hour

hour

8.000

85.86

686.88

P&M-043

Tractor-trolley

hour

8.000

171.02

1368.14

P&M-053

Litre

2000.000

127.55

255097.14

M-118

kg

200.000

70.68

14135.96

M-152

Machinery

Material
Hot applied thermoplastic compound
Reflectorising glass beads

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

27184.74
29903.22
328935.39

Cost for 640 sqm = a+b+c+d+e

140

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

8.14

804

(i)

Remarks/ Input
ref.

513.96

Rate per sqm = a+b+c+d+e)/640

Note

Cost
Rs

say

514.00

1. A sealing primer may be applied in advance on cement


concrete pavement to ensure proper bonding. Any laitance
and/or curing compound to be removed where paint is
required to be applied on concrete surface.
2.Cost of painter is already included in hire charges of road
marking machine.
Kilometre Stone
Reinforced cement concrete M15grade kilometre stone of
standard design as per IRC:8-1980, fixing in position
including painting and printing etc
5th kilometre stone (precast)
Unit = Nos.
Taking output = 6 Nos.
a)

M-15 grade of concrete

b)

Steel reinforcement @ 5 kg per sqm

g)

2.350

4109.00

9656.15

Item 12.8 (A)

kg

22.080

55.828

1232.68

Item 13.6 /1000

224.00

376.32

Item No. 3.13

54.00

531.90

Item 8.8

0.50

900.00

Item 8.3

c)

Excavation in soil for foundation

cum

1.680

d)

Painting two coats on concrete surface

sqm

9.850

e) Lettering on km post (average 30 letters of 10


cm height each)
Transportation and fixing
f)

cum

per cm per
letter

1800.000

Labour
Mate

day

0.260

232.16

60.36

L-12

Mason

day

0.600

353.52

212.11

L-11

Mazdoor including loading/unloading

day

6.000

221.61

1329.66

L-13

hour

6.000

171.02

1026.11

P&M-053

Machinery
Tractor-trolley

h)

Overhead charges @ 0.1 on (f+g)

i)

Contractor's profit @ 0.1 on (f+g+h)

262.82
289.11
15877.22

Cost for 6 Nos. 5th km stone = a+b+c+ d+e +f+g+h +i

2646.20

Rate for each 5th km stone = (a+b+c+d+e+f+g+h+i)/ 6


8.14

(ii)

say

2646.00

3.770

4109.00

15490.93

Item 12.8 (A)

kg

26.320

55.828

1469.39

Item 13.6 /1000

cum

2.770

224.00

620.48

Item No. 3.13

sqm
per cm per
letter

11.410

54.00

616.14

Item 8.8

0.50

840.00

Item 8.3

Ordinary kilometer stone (precast)


Unit = Nos.
Taking output = 14 Nos.
a)

M-15 grade of concrete

b)

Steel reinforcement @ 5 kg per sqm

c)

Excavation in soil for foundation

cum

d) Painting two coats on concrete surface


e) Lettering on km post ( average 12 letters of 10
cm height each)
Transportation and fixing
f)

Labour
Mate

day

0.320

232.16

74.29

L-12

Mason

day

1.000

353.52

353.52

L-11

day

7.000

221.61

1551.27

L-13

hour

6.000

171.02

1026.11

P&M-053

Mazdoor
g)

1680.000

Machinery
Tractor-trolley

h)

Overhead charges @ 0.1 on (f+g)

300.52

i)

Contractor's profit @ 0.1 on (f+g+h)

330.57

Cost for 14 Nos. ordinary km stone = (a+b+ c+d+e+f+g+h+i)

141

22673.22

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Rate for each ordinary km stone = (a+b+ c+d+e+f+g+h+j)


/14
8.14

(iii)

Cost
Rs

Remarks/ Input
ref.

1619.52
say

1620.00

Hectometer stone (precast)


Unit = Nos.
Taking output = 33 Nos.
a)

M-15 grade of concrete

b)

Steel reinforcement @ 5 kg per sqm

c)

Excavation in soil for foundation

cum

1.580

4109.00

6492.22

Item 12.8 (A)

kg

66.000

55.828

3684.65

Item 13.6 /1000

cum

1.390

224.00

311.36

Item No. 3.13

6.270

54.00

338.58

Item 8.8

0.50

165.00

Item 8.3

d) Painting two coats on concrete surface


sqm
e) Lettering on km post (average 1 letter of 10 cm per cm per
height each)
letter
Transportation and fixing
f)

Labour
Mate

g)

330.000

day

0.340

232.16

78.93

L-12

530.28

L-11

Mason

day

1.500

353.52

Mazdoor

day

7.000

221.61

1551.27

L-13

hour

6.000

171.02

1026.11

P&M-053

Machinery
Tractor-trolley

h)

Overhead charges @ 0.1 on (f+g)

318.66

i)

Contractor's profit @ 0.1 on (f+g+h)

350.53
14847.58

Cost for 33 Nos. Hectometer stone = (a+b+c+d+e+f+ g+h+i)


Rate for each Hectometer stone = (a+b +c +d+e+f+
g+h+i) / 33

449.93
say

Note
8.15

805

450.00

The rate for excavation, cement concrete, steel


reinforcement, painting and lettering may be taken from
respective chapters.
Road Delineators
Supplying and installation of delineators (road way indicators,
hazard markers, object markers), 80-100 cm high above
ground level, painted black and white in 15 cm wide strips,
fitted with 80 x 100 mm rectangular or 75 mm dia circular
reflectorised panels at the top, buried or pressed into the
ground and conforming toIRC-79 and the drawings.
Unit = Each
Taking output= 30 Nos.
a)

Labour
Mate

day

0.040

232.16

9.29

L-12

Mazdoor for fixing

day

1.000

221.61

221.61

L-13

each

30.000

451.08

13532.53

b)

Material
Cost of approved type of delineators from ISI certified
firm as per the standard drawing given in IRC - 79
Add 10 per cent cost of material for installation
c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1353.25
1511.67
1662.83
18291.18

Cost for 30 Nos. delineators = (a+b+ c+d)

609.71

Rate per delineators = (a+b+c+d) /30


say

Note

8.16

806

In case of soft ground, a proper foundation may be provided


as per approved design. In case foundation is required to be
provided, the items of excavation and foundation concrete
are required to be measured and paid separately.
Boundary pillar
Reinforced cement concrete M15 grade boundary pillars of
standard design as per IRC:25-1967, fixed in position
including finishing and lettering but excluding painting
Unit = Each

142

610.00

M-091

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Taking output = 57 Nos.


a)

M-15 grade of the boundary stone

b)

Steel reinforcement

c)

Excavation in soil

d)

Lettering, each 10 cm high

cum

1.250

4109.00

5136.25

Item 12.8 (A)

kg

79.800

55.828

4455.07

Item 13.6 /1000

10.720

224.00

2401.28

Item No. 3.13

0.50

1140.00

Item 8.3

cum
per letter
per cm high

2280.000

Transportation and fixing


e)

f)

Labour
Mate

day

0.570

232.16

132.33

L-12

Mazdoor

day

14.250

221.61

3157.94

L-13

hour

6.000

171.02

1026.11

P&M-053

cum

11.970

370.06

4429.62

M-008

Machinery
Tractor-trolley

g)

Material
Stone spall

h)

Overhead charges @ 0.1 on (e+f+g)

874.60

i)

Contractor's profit @ 0.1 on (e+f+g+h)

962.06
23715.26

Cost for 57 Nos. boundary pillar = (a+b +c+d +e+ f+g+h+i )

416.06

Rate for each boundary pillar = (a+b+c+d+e+ f+g+h+i)/57

Note

8.17

807

say

416.00

In case of soft ground, a proper foundation may be provided


as per approved design. In case foundation is required to be
provided, the items of excavation and foundation concrete
are required to be measured and paid separately.
G.I Barbed Wire Fencing 1.2 Metre High
Providing and fixing 1.2 metres high GI barbed wire fencing
with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm placed
every 3 metres center to center founded in M15 grade
cement concrete, 0.6 metre below ground level, every 15th
post, last but one end post and corner post shall be strutted
on both sides and end post on one side only and provided
with 9 horizontal lines and 2 diagonals interwoven with
horizontal wires, fixed with GI staples, turn buckles etc
complete as per clause 807
Unit = per running metre
Taking output = 30 metres
a)

Labour
Mate

day

0.090

232.16

20.89

L-12

Blacksmith

day

0.250

353.52

88.38

L-02

day

2.000

221.61

443.22

L-13

kg

31.420

58.68

1843.61

M-063

kg

80.500

37.995

3058.62

M-179 /1000

Mazdoor
b)

Material
Barbed wire 335 metres length @ 9.38 kg per 100
metres
MS angle iron 40 mm x 40mm x 6 mm, 23 metres in
length @ 3.5 kg per metre
Add for GI staple binding wire, drilling holes etc. @ 2 per
cent of the cost of material
c) Painting
Applying two coats of painting on exposed surface of
angle iron posts ( Rate as per item no. 8.9)
d) Overhead charges @ 0.1 on (a+b)
e)

98.04

sqm

2.110

48.00

555.28
610.80

Contractor's profit @ 0.1 on (a+b+d)

6820.12

Cost for 30 metres fencing = a+b+c+d+e

227.34

Rate per metre = (a+b+c+d+e)/30


say
Note
8.18

807

101.28

Cost of excavation for foundation and foundation concrete to


be added separately in the cost estimate as per approved
design. The rate for these items may be taken from
respective chapters.
G.I Barbed Wire Fencing 1.8 Metre High
143

227.00

Item 8.9

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Providing and fixing 1.8 metres high GI barbed wire fencing


with 2.4 m angle iron posts 50 mm x 50 mm x 6 mm placed
every 3 metres center to center founded in M15 grade
cement concrete, 0.6 metre below ground level, every 15th
post, last but one end post and corner post shall be strutted
on both sides and end post on one side only and provided
with 12 horizontal lines and 2 diagonals interwoven with
horizontal wires, fixed with GI staples, turn buckles etc
complete as per clause 807
Unit = per running metre
Taking output = 30 metres
a)

b)

Labour
Mate

day

0.120

232.16

27.86

L-12

Blacksmith

day

0.400

353.52

141.41

L-02

Mazdoor

day

2.500

221.61

554.03

L-13

kg

40.150

58.68

2355.85

M-063

kg

152.000

37.995

5775.28

M-179 /1000

d)

Material
Barbed wire 428 metres length @ 9.38 kg per 100
metres
MS angle iron 50 mm x 50 mm x 6 mm,33.8 metres in
length @ 4.5 kg per metre
Add for GI staple, binding wire, drilling holes etc. @ 2
per cent of the cost of material
Painting
Applying two coats of painting on exposed surface of
angle iron posts
Overhead charges @ 0.1 on (a+b)

e)

Contractor's profit @ 0.1 on (a+b+d)

c)

162.62

sqm

48.00

3.960

991.87
11100.70
370.02

Rate per metre fencing = (a+b+c +d+e)/30


say

8.19

Suggest
ive

Item 8.9

901.70

Cost for 30 metres fencing = a+b+c+d+e

Note

190.08

370.00

Cost of excavation for foundation and foundation concrete to


be added separately in the cost estimate as per approved
design. The rate for these items may be taken from
respective chapters.
Fencing With Welded Steel Wire Fabric 75 mm x 50 mm
Providing 1.20 metre high fencing with angle iron posts 50
mm x 50 mm x 6 mm at 3 metre center to center with 0.40
metre embedded in M15 grade cement concrete, corner, end
and every 10th post to be strutted, provided with welded steel
wire fabric of 75 mm x 50 mm mesh or 75 mm x 25 mm mesh
and fixed to iron posts by flat iron 50 x 5 mm and bolts etc.
complete in all respects.
Unit = Running metre
Taking output = 30 m
a)

b)

Labour
Mate

day

0.120

232.16

27.86

L-12

Welder

day

1.000

353.52

353.52

L-02

Mazdoor

day

2.000

221.61

443.22

L-13

kg

106.000

37.995

4027.50

M-179 /1000

kg

26.000

37.995

987.88

M-179 /1000

kg

151.000

#VALUE!

M-191

kg

293.000

Material
i) Angle iron for posts 50 x 50 x 6 mm

ii) Runner flat 50 x 5 mm


iii) Welded steel wire fabric 75x50 mm mesh @ 4
kg/sqm,4 x 30 x 1.2 + 5 per cent wastage
OR
Welded steel wire fabric 75 x 25 mm mesh @ 7.75
kg/sqm, 7.75 x 30 x 1.2 + 5 per cent wastage
Add 2.5 per cent of cost of material for drilling holes in
angles, flats, splitting angle at bottom, nuts and bolts and
welded consumables
c) Machinery
Tractor-trolley
d)

#VALUE!

hour

Painting
144

input

0.100

171.02

17.10

P&M-053

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Painting two coats including priming

sqm

Quantity
8.000

Rate Rs
48.00

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+e)

#VALUE!

808

Remarks/ Input
ref.
Item 8.9

#VALUE!
#VALUE!

Rate per metre = (a+b+c+d+e+f)/30

8.20

384.00

e)

Cost for 30 metre = a+b+c+d+e+f

Note

Cost
Rs

say

#VALUE!

224.00

290.30

Item No. 3.13

4109.00

2662.63

Item 12.8 (A)

48.00

226.08

Item 8.9

48.00

103.68

Item 8.9

i) Adopt any one type of welded steel wire fabric 75 x 50 mm


or 75 x 25 mm as per approved design.
ii) The item of excavation and cement concrete in foundation
shall be measured and paid separately
Tubular Steel Railing on Medium Weight Steel Channel (
ISMC series) 100 mm x 50 mm
Providing, fixing and erecting 50 mm dia steel pipe railing in
3 rows duly painted on medium weight steel channels (ISMC
series) 100 mm x 50 mm, 1.2 metres high above ground, 2 m
centre to centre, complete as per approved drawings
Unit = Running metre
Taking output = 10metres
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x
0.6
ii) Foundation concrete M-15 grade PCC 6 x 0.6 x
0.6 x 0.3
iii) Painting of pipe
iv) Painting of channel section 6 nos,1.8 metres
each 0.2 x 1.8 x 6 = 2.16
a) Labour (For fixing at site)
Mate

b)

1.296

cum

0.648

sqm

4.710

sqm

2.160

day

0.010

232.16

2.32

L-12

55.40

L-13
L-02

Mazdoor

day

0.250

221.61

Plumber

day

0.010

353.52

3.54

metre

30.000

172.29

5168.67

M-175

37.995

3775.21

M-179 /1000

Material

Steel pipe 50 mm external dia as per IS:1239


Medium weight steel channel (ISMC series) 100 mm x
50 mm,10.8 metres length @ 9.2 kg per metre
Add for drilling holes @ 2 per cent of cost of channels
c)

cum

kg

99.360

75.50

Machinery
Tractor-trolley

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

hour

0.040

171.02

1360.72
14967.92
1496.79

Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10

808

P&M-053

1237.02

Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e

8.21

6.84

say

1497.00

224.00

290.30

Item No. 3.13

4109.00

2662.63

Item 12.8 (A)

5297.00

1695.04

Item 14.1(A)

226.08

Item 8.9

Tubular Steel Railing on Precast RCC Posts, 1.2 m High


Above Ground Level
Providing, fencing and erecting 50 mm dia painted steel pipe
railing in 3 rows on precast M20 grade RCC vertical posts1.8
metres high (1.2 m above GL) with 3 holes 50 mm dia for
pipe, fixed 2 metres centre to, complete as per approved
drawing
Unit = Running metre
Taking output = 10metres
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x
0.6
ii) Foundation concrete M - 15 grade PCC 6 x 0.6 x
0.6 x 0.3
iii) RCC M - 20 for pre cast posts 6 nos of 1.8
metres each
iv) Painting of pipe
a)

cum

1.296

cum

0.648

cum

0.320

sqm

4.710

48.00

day

0.014

232.16

3.25

L-12

77.56

L-13

3.54

L-02

Labour
Mate
Mazdoor

day

0.350

221.61

Plumber

day

0.010

353.52

145

Sr No

Ref. to
MoRTH
Spec.

Description
b)

Unit

Rate Rs

metre

30.000

172.29

5168.67

hour

0.250

171.02

42.75

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

M-175
P&M-053

529.58
582.54
11281.95

Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e

1128.19

Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10


809

Remarks/ Input
ref.

Machinery
Tractor-trolley

8.22

Cost
Rs

Material
Steel pipe 50 mm dia as per IS:1239

c)

Quantity

say

1128.00

Reinforced Cement Concrete Crash Barrier


Provision of an Reinforced cement concrete crash barrier at
the edges of the road, approaches to bridge structures and
medians, constructed with M-20 grade concrete with HYSD
reinforcement conforming to IRC:21 and dowel bars 25 mm
dia, 450 mm long at expansion joints filled with pre-moulded
asphalt filler board, keyed to the structure on which it is built
and installed as per design given in the enclosure to MOST
circular No. RW/NH - 33022/1/94-DO III dated 24 June 1994
as per dimensions in the approved drawing and at locations
directed by the Engineer, all as specified
Unit = Linear metre
Taking output = 10 m
(i)

a)

M 20 grade concrete
cum

3.000

4109.00

12327.00

Mate

day

0.040

232.16

9.29

L-12

Mazdoor

day

1.000

221.61

221.61

L-13

HYSD steel reinforcement including dowel bars

tonne

0.280

36191.33

10133.57

M-082

Pre-moulded asphalt filler board

sqm

0.320

708.07

226.58

M-144

M 20 grade concrete
b)

c)

Labour

Material

d)

Overhead charges @ 0.1 on (b+c)

e)

Contractor's profit @ 0.1 on (b+c+d)

1059.11
1165.02
25142.17

Cost for 10 metre = a+b+c+d+e

2514.22

Rate per metre = (a+b+c+d+e)/10


say
Note

8.23

810
A

Item 14.1(A)

2514.00

i) Excavation and backfilling are incidental to work and not to


be measured separately.
ii) Rate for RCC M 20 may be taken from chapter on super
structure.
Metal Beam Crash Barrier
Type - A, "W" : Metal Beam Crash Barrier
Providing and erecting a "W" metal beam crash barrier
comprising of 3 mm thick corrugated sheet metal beam rail,
70 cm above road/ground level, fixed on ISMC series
channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to
centre, 1.8 m high, 1.1 m below ground/road level, all steel
parts and fitments to be galvanised by hot dip process, all
fittings to conform to IS:1367 and IS:1364, metal beam rail to
be fixed on the vertical post with a spacer of channel section
150 x 75 x 5 mm, 330 mm long complete as per clause 810
Unit = Running metre
Taking output = 4.5 metre length
a)

Labour
Mate

day

0.060

232.16

13.93

L-12

Blacksmith

day

0.500

353.52

176.76

L-02

day

1.000

221.61

221.61

L-13

hour

0.100

171.02

17.10

P&M-053

Mazdoor
b)

Machinery
Tractor-trolley

c)

Material
146

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Corrugated sheet,3 mm thick, "W" beam section


railing,4.5 m in length
Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @
16.4 kg per metre
Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @
16.4 kg per metre
Nuts and bolts
Add 25 per cent of the cost of material for fabrication, nuts,
bolts and washers etc.)
d) Overhead charges @ 0.1 on (a+b+c)
e)

Quantity

kg

41.210

kg

88.560

kg

16.240

kg

20.000

Rate Rs

1565.78

M-179 /1000

37.995

3364.86

M-179 /1000

37.995

617.04

M-179 /1000

45.42

908.43

M-130

1614.03
849.95
934.95

Contractor's profit @ 0.1 on (a+b+c+d)

10284.45
2285.43

Rate per metre = (a+b+c+d+e)/4.5


say
B

Remarks/ Input
ref.

37.995

Cost for 4.5 metre = a+b+c+d+e

8.23

Cost
Rs

2285.00

Type - B, "THRIE" : Metal Beam Crash Barrier


Providing and erecting a "Thrie" metal beam crash barrier
comprising of 3 mm thick corrugated sheet metal beam rail,
85 cm above road/ground level, fixed on ISMC series
channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to
centre, 2 m high with 1.15 m below ground level, all steel
parts and fitments to be galvanised by hot dip process, all
fittings to conform to IS:1367 and IS:1364, metal beam rail to
be fixed on the vertical post with a space of channel section
150 x 75 x 5 mm, 546 mm long complete as per clause 810
Unit = Running metre
Taking output = 4.5 metre length
a)

b)

Labour
Mate

day

0.060

232.16

13.93

L-12

Blacksmith

day

0.500

353.52

176.76

L-02

Mazdoor

day

1.000

221.61

221.61

L-13

hour

0.100

171.02

17.10

P&M-053

kg

72.940

37.59

2741.84

M-088

kg

98.400

37.995

3738.73

M-179 /1000

kg

26.860

37.995

1020.55

M-179 /1000

kg

30.000

45.42

1362.65

M-130

Machinery
Tractor-trolley

c)

Material
Corrugated sheet,3 mm thick, "Thrie" beam section
railing,4.5 m in length
Channel post 150 x 75 x 5 mm, 2 m long,3 Nos @ 16.4
kg per metre
Spacer 150 x 75 x 5 mm channel 0.546 m long,3 Nos

Nuts and bolts


Add 15 per cent of the cost of material for fabrication, nuts,
bolts and washers etc.)
d) Overhead charges @ 0.1 on (a+b+c)
e)

1329.57
1062.27
1168.50

Contractor's profit @ 0.1 on (a+b+c+d)

12853.52

Cost for 4.5 metre = a+b+c+d+e

2856.34

Rate per metre= (a+b+c+d+e)/4.5


say

Note

8.24

811

Note

8.25

Suggest
ive

In the case of median crash barrier, 'W' metal beam or thrie


beam section should be provided on both sides of the vertical
posts fixed in the median. Extra provision for metal beam
railing and spacer is required to be made when fixed in the
median depending on approved design.
Road Traffic Signals electrically operated
Since it is a ready made item commercially produced and
erected by specialised firm in the electrical and electronic
field, rate may be taken based on market enquiry from firms
specialised in this field and ISI certified for the approved
design and drawing.
Flexible Crash Barrier, Wire Rope Safety Barrier

147

2856.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Providing and erecting a wire rope safety barrier with vertical


posts of medium weight RS Joist (ISMB series) 100 mm x 75
mm (11.50 kg/m), 1.50 m long 0.85 m above ground and 0.65
m below ground level, split at the bottom for better grip,
embedded in M 15 grade cement concrete 450 x 450 x 450
mm, 1.50 m center to center and with 4 horizontal steel wire
rope 40 mm dia and anchored at terminal posts 15 m apart.
Terminal post to be embedded in M 15 grade cement
concrete foundation 2400 x 450 x 900 mm (depth),
strengthened by a strut of RS joist 100 x 75 mm, 2 m long
at 450 C inclination and a tie 100 x 8 mm, 1.50 m long at the
bottom, all embedded in foundation concrete as per approved
design and drawing, rate excluding excavation and cement
concrete.
Unit = Running metre
Taking output = 15 metre
a) Labour

b)

Mate

day

0.120

232.16

27.86

L-12

Mazdoor

day

2.000

221.61

443.22

L-13

Blacksmith

day

1.000

353.52

353.52

L-02

kg

190.000

37.995

7219.10

M-179 /1000

kg

46.000

37.995

1747.78

M-179 /1000

kg

188.400

37.995

7158.30

M-179 /1000

kg

65.000

29.76

1934.34

M-177

Material
i) RS Joist 100 x 75 mm - 16.5 m @ 11.5 kg per metre

ii) Struts - 2 Nos. for terminal posts,2 m long each 2 x 2


x 11.50
iii) Tie 2 Nos. of 8 mm steel plate,1.5 sqm each for
terminal posts @ 62.80 kg/sqm (2 x 1.5)
iv) Steel wire rope 40 mm, including 7.50 per cent
extra for fixing at ends 15 x 4 x 1.075 @ 1 kg per m
Add 5 per cent of cost of material for drilling, gripping, fixing,
fabrication and welding consumables
c) Painting
Applying 2 coats of painting on exposed surface
d)

902.98

sqm

16.500

48.00

hour

0.250

171.02

e)

Overhead charges @ 0.1 on (a+b+d)

f)

Contractor's profit @ 0.1 on (a+b+d+e)

2181.28
1652.41
say

The items of excavations and cement concrete works will be


measured and included separately as per the approved
designs and drawings.
Anti-Glare Devices in Median

Plantation
Plantation of shrubs and plants of approved species in the
median. apart from cutting off glare from vehicle coming from
opposite direction, these plants provide a pleasant
envoirenment and are eco-friendly. The rate for this item is
available in the chapter 11 on horticulture.
Anti-glare screen with 25 mm steel pipe framework fixed
with circular and rectangular vanes
Providing and erecting an anti - glare screen with 25 mm dia
vertical pipes fabricated and framed in the form of panels of
one metre length and 1.75 metre height fixed with circular
vane 250 mm dia at top and rectangular vane 600 x 300 mm
at the middle, made out of steel sheet of 3 mm thickness,
end vertical pipes of the panel made larger for embedding in
foundation concrete, applying 2 coats of paint on all exposed
surfaces, all as per approved design and drawings.
Unit = Running metre
Taking output = one metre
a)

P&M-053

24786.11

Rate per m = (a+b+c+d+e+f)/15

Suggest
ive

42.75
1982.98

Cost for 15 m = a+b+c+d+e+f

8.26

Item 8.9

Machinery
Tractor-trolley

Note

792.00

Labour
148

1652.00

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Quantity

Rate Rs

day

0.004

232.16

0.93

L-12

Mazdoor

day

0.100

221.61

22.16

L-13

metre

16.000

97.11

1553.73

M-174

kg

4.320

37.995

164.14

M-179 /1000

kg

4.800

37.995

182.38

M-179 /1000

Material

Applying 2 coats of painting on exposed surface


d)

Overhead charges @ 0.1 on (a+b)

e)

Contractor's profit @ 0.1 on (a+b+d)

95.01

sqm

1.830

48.00

Item 8.9

222.02
2530.05
say

87.84
201.84

Rate per metre = a+b+c+d+e

8.26

Remarks/ Input
ref.

Mate

i) 25 mm steel pipe
ii) MS sheet for 600 x 300 x 3 mm rectangular vane,
one number @ 24kg/sqm
iii) MS sheet for 250 mm dia circular vane 3 mm thick,4
numbers @ 24 kg/sqm
Add 5 per cent cost of material for fabrication, welding,
bending, nuts, bolts etc
c) Painting

Note

Cost
Rs

2530.00

The items of excavation and cement concrete as per


approved design to be measured and paid separately
Anti-glare screen with rectangular vane of MS sheet
Providing and erecting anti - glare screen with rectangular
vanes of size 750 x 500 mm made from MS sheet, 3 mm
thick and fixed on MS angle 50 x 50 x 6 mm at an angle of
450 C to the direction of flow of traffic, 1.5 m center to
center, top edge of the screen 1.75 m above ground level,
vertical post firmly embedded in M-15 cement concrete
foundation 0.60 m below ground level, applying 2 coats of
paint on exposed faces, all complete as per approved design
and drawings
Unit = Running metre
Taking output = 1.50 metre
a)

Labour
day

0.004

232.16

0.93

L-12

day

0.100

221.61

22.16

L-13

i) Angle iron post,50 x 50 x 6 mm, length 2.35 m

kg

10.580

37.995

401.99

M-179 /1000

ii) MS sheet 3 mm thick @ 24 kg/sqm

kg

9.000

37.995

341.96

M-179 /1000

Mate
Mazdoor
b)

Material

37.20

Add 5 percent of cost of material for fabrication,nuts,bolts etc


c)

Machinery
Tractor-trolley

d)

hour

0.100

171.02

17.10

P&M-053

sqm

0.850

48.00

40.80

Item 8.9

Painting
Applying 2 coats of painting

e)

Overhead charges @ 0.1 on (a+b+c)

f)

Contractor's profit @ 0.1 on (a+b+c+e)

82.13
90.35
1034.62

Cost for 1.5 m = a+b+c+d+e+f

689.74

Rate per metre = (a+b+c+d+e+f)/1.50


say
Note

8.27

Suggest
ive

The items of excavation and cement concrete as per


approved design to be measured and paid separately. Rate
of painting has been analaysed separately in this chapter.
Street Lighting
Providing and erecting street light mounted on a steel circular
hollow pole of standard specifications for street lighting, 9 m
high spaced 40 m apart, 1.8 m overhang on both sides if
fixed in the median and on one side if fixed on the footpath,
fitted with sodium vapour lamp and fixed firmly in concrete
foundation.
Unit = Each
Taking output = one light

149

690.00

Sr No

Ref. to
MoRTH
Spec.

Description
a)

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Labour
Mate

0.030

232.16

6.96

L-12

0.500

221.61

110.81

L-13

day

0.250

353.52

88.38

L-02

each

1.000

each

1.000

day

Mazdoor

day

Electrician
b)

Material
i) Steel circular hollow pole of standard specification for
street lighting to mount light at 9 m height above road
level
ii) Sodium vapour lamp
Add 5 per cent of cost of material for holder, electric cable,
insulation, ladder, scaffolding etc
c) Painting

(i)

For Fixing in Median


Providing two coats of alluminium paint over steel
circular hollow pipe with overhang on both sides
For fixing in Footpath
Providing two coats of alluminium paint over steel
circular hollow pipe with overhang on one side
For Fixing in Median

#VALUE!

679.79

sqm

5.750

8.28

Suggest
ive

679.79

M-168

sqm

4.630

48.00

276.00

Item 8.9

48.00

222.24

Item 8.9

d)

Overhead charges @ 0.1 on (a+b)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+d)

#VALUE!
#VALUE!
say

#VALUE!

say

#VALUE!

For fixing in Footpath


#VALUE!

Rate per light for Fixing in Footpath = a+b+c+d+e

Note

M-171

#VALUE!

Rate per light for fixing in Median= a+b+c+d+e


(ii)

#VALUE!

The items of excavation and cement concrete foundation will


be measured and included separately in the estimate as per
approved design and drawing. The rate for painting has been
analysed in this chapter.
Lighting on Bridges
Providing and fixing lighting on bridges, mounted on steel
hollow circular poles of standard specifications, 5 m high
fixed on parapets with cement concrete, 20 m apart and fitted
with sodium vapour lamp
Unit = Each
Taking output = one light
a)

b)

Labour
Mate

day

0.020

232.16

4.64

L-12

Mazdoor

day

0.400

221.61

88.64

L-13

Electrician

day

0.200

353.52

70.70

L-02

each

1.000

each

1.000

Material
i) Steel circular hollow pole of standard specification for
street lighting to mount light at 5 m above deck level

ii) Sodium vapour lamp 70 watt


Add 1 per cent of cost of material for holder, electric cable,
insulation, ladder, scaffolding etc
c) Painting
Providing two coats of alluminium paint over steel
circular hollow pipe
d) Overhead charges @ 0.1 on (a+b)
e)

#VALUE!
679.79

sqm

2.760

48.00

Suggest
ive

679.79

M-168

132.48
#VALUE!
#VALUE!

Contractor's profit @ 0.1 on (a+b+d)

#VALUE!
say

8.29

M-170

#VALUE!

Rate per light = a+b+c+d+e

Note

#VALUE!

The items of cement concrete to be measured and paid


separately as per approved design. The rate for painting has
already been analysed in this chapter.
Cable Duct Across the Road

150

#VALUE!

Item 8.9

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Providing and laying of a reinforced cement concrete pipe


duct, 300 mm dia, across the road (new construction),
extending from drain to drain in cuts and toe of slope to toe of
slope in fills, constructing head walls at both ends, providing
a minimum fill of granular material over top and sides of RCC
pipe as per IRC:98-1997, bedded on a 0.3 m thick layer of
granular material free of rock pieces, outer to outer distance
of pipe at least half dia of pipe subject to minimum 450 mm in
case of double and triple row ducts, joints to be made leak
proof, invert level of duct to be above higher than ground
level to prevent entry of water and dirt, all as per IRC: 98 1997 and approved drawings.
Case(i) Single row for one utility service
Unit = Running metre
Taking output = 20metres
a) Random Rubble masonry/Brick masonry in
cement mortar 1:6 for head wall both side
b) Labour

d)

Item 12.7 ( B)

Mate

day

0.050

232.16

11.61

L-12

Mazdoor

day

1.000

221.61

221.61

L-13

day

0.250

306.03

76.51

L-15

Reinforced Cement Concrete pipe 300 mm dia


Granular soil with PI less than 6 for bedding and sides
of pipe (0.6 x 0.6 x 20 m)
Collar for joints 300 mm dia

metre

20.000

924.00

18480.00

M-151

166.19

1196.57

M-009

Cement mortar 1:2 for joints

Material

cum

7.200

each

9.000 input

cum

0.020

3915.00

78.30

Item 12.6 (B)

hour

0.500

171.02

85.51

P&M-053

#VALUE!

M-083

Machinery
Tractor-trolley

e)

Overhead charges @ 0.1 on (b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!
#VALUE!

Cost for 20 metre = a+b+c+d+e+f

#VALUE!

Rate per metre = (a+b+c+d+e+f)/20


8.29

7299.48

2.360

Mazdoor skilled
c)

3093.00

cum

say

#VALUE!

3093.00

10423.41

Case(ii) Double row for two utility services


Unit = Running metre
Taking output = 20metres
a) Random Rubble brick/Brick masonry in cement
mortar 1:6 for head wall both sides.
b) Labour

3.370

Mate

day

0.050

232.16

11.61

L-12

Mazdoor

day

2.000

221.61

443.22

L-13

day

0.250

306.03

76.51

L-15

metre

40.000

924.00

36960.00

M-151

166.19

2393.14

M-009

Mazdoor skilled
c)

Material
Reinforced Cement Concrete pipe 300 mm dia
Granular soil with PI less than 6 for bedding and sides
of pipe (0.6 x 0.6 x 40 m)
Collar for joints 300 mm dia
Cement mortar 1:2 for joints

d)

cum

14.400

each

18.000 input

cum

0.040

3915.00

hour

1.000

171.02

#VALUE!

M-083

156.60

Item 12.6 (B)

171.02

P&M-053

Machinery
Tractor-trolley

e)

Overhead charges @ 0.1 on (b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!
#VALUE!

Cost for 20 metre = a+b+c+d+e+f

#VALUE!

Rate per metre = (a+b+c+d+e+f)/20


say
8.29

Item 12.7 ( B)

cum

Case(iii) Triple rRow for three utility services


Unit = Running metre
Taking output = 20metres
151

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

a) Random Rubble brick/Brick masonry in cement


mortar 1:6 for head wall both sides.
Labour
Mate

c)

Rate Rs
3093.00

4.380

day

0.160

232.16

37.15

L-12

664.83

L-13
L-15

3.000

Mazdoor skilled

day

1.000

306.03

306.03

metre

60.000

924.00

55440.00

M-151

166.19

3589.70

M-009

Material

cum

21.600

each

27.000 input

cum

0.060

3915.00

hour

1.500

171.02

#VALUE!

M-083

234.90

Item 12.6 (B)

256.53

P&M-053

Machinery

e)

Overhead charges @ 0.1 on (b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!
#VALUE!

Cost for 20 metre = a+b+c+d+e+f

#VALUE!

Rate per metre = (a+b+c+d+e+f)/20


say

Suggest
ive

Item 12.7 ( B)

cum

day

Tractor-trolley

8.30

13547.34

Remarks/ Input
ref.

Mazdoor

Cement mortar 1:2 for joints

Note

Cost
Rs

221.61

Reinforced Cement Concrete pipe 300 mm dia


Granular soil with PI less than 6 for bedding and sides
of pipe (0.6 x 0.6 x 60 m)
Collar for joints 300 mm dia
d)

Quantity

1.Inspection chamber at both ends is the responsibility of the


agency who is laying the duct. Hence not included.
2.The rates for stone masonry / brick masonry and cement
mortar to be adopted from respective clauses.
Highway Patrolling and Traffic Aid Post
It is proposed to locate one Traffic Aid Post every 50-60 km
of the highway.
The organisation and financial aspect are required to be
finalised in consultation with administrative and traffic
authorities .

152

#VALUE!

Sr No
8.31

8.32

Ref. to
MoRTH
Spec.
Suggest
ive

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Items Related to Underpass/ Subway/ Overhead Bridge/


Overhead Foot Bridge
The items involved for underpass/ subway/ overhead bridge/
overhead foot bridge are earthwork, plain cement concrete,
plastering, painting, information sign etc. The rates for these
items are available in respective chapters which can be
adopted for the quantities derived from the approved designs
and drawings

Suggest
ive

Traffic Control System and Communication System


Providing a traffic control centre and communication system
including telecommunication facilities and related
accessories, CCTV, radar, vehicle detection camera, central
computer system
These are specialised item of telecommunication system and
are the commercial products. The designer is required to
contact the manufacturers to ascertain market prices. In case
of civil works required to be executed for these installations,
pricing may be done as per rates in relevant chapters for
quantities derived as per approved design and drawing.
As regards the locations where such devices are required to
be installed, the traffic control authority should be consulted
to finalise the location

8.33

Suggest
ive

Gantry Mounted Variable Message Sign Board

(i)

Providing and erecting gantry mounted variable message


sign board electronically operated capable of flashing the
desired message over a designed support system of
aluminium alloy or galvanised steel, erected as per approved
design and drawings and with lateral clearance as per clause
802.3
Gantry Support System
Unit = tonne
Taking output=1 tonne
a)

b)

c)

Labour
Mate

day

0.120

232.16

27.86

L-12

Mazdoor

day

2.000

221.61

443.22

L-13

Blacksmith

day

1.000

353.52

353.52

L-02

tonne

1.050

46239.26

48551.23

Material
Alluminium alloy/galvanised steel including 5 per cent
wastage
Add 15 per cent of cost of material for fabrication and
erection.
Add 1 per cent of cost of material for nuts, bolts and
welding
Machinery
Truck 10 tonne

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

7282.68
485.51

hour

1.000

745.00

6367.79
70045.72
say

(ii)

745.00
5788.90

Rate per tonne = a+b+c+d+e


8.33

Message Display
Message display board 6 sqm electronically operated with
complete electronic fitments for flashing the pre-determined
messages.
This is a specilised commercial product and the lumpsum
rate including erection at site is required to be as certained
from the market and including in the rate analysis. The size
of the board will vary depending upon specific location.
The rate for the gantry mounted variable sign would be the
addition of cost of gantry support system as per approved
design determined at (i) above and the cost of message
display board as certained from the market at (ii) above

153

M-060

70046.00

P&M-057

Sr No
8.34

Ref. to
MoRTH
Spec.
Suggest
ive

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Traffic Impact Attenuators at Abutments and Piers


A

With Scrap Tyres


Provision and installation of traffic attenuators at
abutment/pier of flyovers bridges using scrap tyres of size
100 x 20 retrieved from trucks laid in 2 rows and 4 tiers, one
above the other and tied with 20 mm wire rope as per
approved design and drawings.
Unit = sqm
Taking output = 20sqm
a)

b)

Labour
Mate

day

0.080

232.16

18.57

L-12

Mazdoor

day

1.500

221.61

332.42

L-13

Blacksmith

day

0.250

353.52

88.38

L-02

each

80.000

59.20

4736.38

M-161

150.000

29.76

4463.85

M-176

Material
Scrap tyres of size 900 x 20
20 mm steel wire rope

kg

44.64

Add 1 per cent of cost of wire rope for clamps etc.


c)

Machinery
Tractor-trolley

hour

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3.000

171.02

1121.70
616.94

Rate per sqm = (a+b+c+d+e)/20


say
B

P&M-053

12338.73

Cost for 20 sqm = a+b+c+d+e

8.34

513.05
1019.73

617.00

Using Plastic/Steel Barrel, Filled with Sand


Provision and installation of traffic impact attenuator at
abutment/pier of flyovers bridges using plastic/steel barrels
0.60 m dia and 1.0 m in height, filled with sand in three rows
and tied with20 mm steel wire rope as per approved design
and drawings
Unit = sqm
Taking output = 20sqm
a)

Labour
Mate

day

0.130

232.16

30.18

L-12

Mazdoor

day

3.000

221.61

664.83

L-13

day

0.250

353.52

88.38

L-02

each

50.000

Steel barrels

each

50.000

90.84

4542.17

M-172

Sand

cum

8.000

219.18

1753.44

M-004

kg

15.000

29.76

446.39

M-176

Blacksmith
b)

Material
Plastic barrels
or

20 mm steel wire rope

4.46

Add 1 per cent of cost of wire rope for clamps etc.


c)

Machinery
Tractor-trolley

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

hour

2.000

171.02

787.19
865.91
9524.98

Cost for 20 sqm = a+b+c+d+e

476.25

Rate per sqm = (a+b+c+d+e)/20


say
8.34

342.04

With HI - DRO cell Sandwich (Patented)


(In this patented HI - DRO cell system, water gets discharged
from plastic tubes on impact over a pre-determined time, thus
absorbing the energy)

154

476.00

P&M-053

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Providing and installing a patentend HI - DRO cell system as


a traffic impact attenuators, using plastic tubes 50 cm dia, 1.2
m in height, 25 mm opening at the top, placed in three rows,
filled with water and tied with a 20 mm steel wire rope
Unit = sqm
Taking output = 10sqm
a)

b)

Labour
Mate

day

0.100

232.16

23.22

L-12

Mazdoor

day

2.500

221.61

554.03

L-13

Material
each

40.000

#VALUE!

M-139

Cost of water

KL

12.000

167.07

2004.82

M-189

20 mm steel wire rope

kg

100.000

29.76

2975.90

M-176

Plastic tubes 50 cm dia,1.2 m high

#VALUE!

29.76

Add 1 per cent of cost of wire rope for clamps etc.


c)

Machinery
Tractor-trolley

hour

Water tanker6 KL capacity

hour

2.000

171.02

342.04

P&M-053

2.000

111.24

222.48

P&M-060

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
#VALUE!

Cost for 10 sqm = a+b+c+d+e

#VALUE!

Rate per sqm = (a+b+c+d+e)/10


say
8.35

Suggest
ive

#VALUE!

Road Markers/Road Stud with Lense Reflector


Providing and fixing of road stud 100x 100 mm, die-cast in
aluminium, resistant to corrosive effect of salt and grit, fitted
with lense reflectors, installed in concrete or asphaltic surface
by drilling hole 30 mm upto a depth of 60 mm and bedded in
a suitable bituminous grout or epoxy mortar, all as per BS
873 part 4:1973
Unit = Nos
Taking output = 50Nos
a)

Labour
Mate

0.040

232.16

9.29

L-12

day

1.000

221.61

221.61

L-13

each

50.000

167.01

8350.30

M-062

day

Mazdoor
b)

Material
Aluminium studs 100 x 100 mm fitted with lense
reflectors
Add 10 per cent of cost of material for fixing and installation
c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

835.03
941.62
1035.78
11393.63

Cost for 50 studs = a+b+c+d

227.87

Rate per studs = (a+b+c+d)/50


say
8.36

Suggest
ive

228.00

Traffic Cone
Provision of red fluorescent with white reflective sleeve traffic
cone made of low density polyethylene (LDPE)
material
with a square base of 390 x 390 x 35 mm and a height of 770
mm, 4 kg in weight, placed at 1.5 m interval, all as per BS
873
Unit = Running metre
Taking output = 68 Nos.
a)

b)

Labour
Mate

day

0.020

232.16

4.64

L-12

Mazdoor

day

0.500

221.61

110.81

L-13

each

68.000

394.70

26839.51

Material
Traffic cones with 150 mm reflective sleeve

155

M-186

Sr No

Ref. to
MoRTH
Spec.

Description
c)

Unit

Quantity

Rate Rs

hour

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

0.100

171.02

2966.93
32636.19
479.94

Rate per metre = (a+b+c+d+e)/68


say
Roadside Amenities
A

Rest areas
Providing plainly furnished accommodation for rest rooms,
dormitories, restaurants, stalls, shops, petrol pump,
telephone booth, first aid room, traffic aid post, police
assistance booth, including electricity, toilet and sewerage
system
Pricing may be done based on current plinth area rates
approved by PWD/CPWD/MES for a particular zone. Area is
required to be assessed for specific location as per actual
site conditions
Parking areas and bus laybyes for trucks, buses and
light vehicles
Pricing of parking areas may be done for the quantities of
various items based on the approved dimensions and
pavement design for a particular terrain and soil. Rates for
items may be from respective chapters.
Lawn
Providing a lawn planted with grass and its maintenance
Pricing of lawn may be done as per rates given in the chapter
on horticulture for the quantities as per approved dimensions
in the drawings

8.38

Suggest
ive

Rumble Strips
Provision of 15 nos rumble strips covered with premix
bituminous carpet, 15-20 mm high at center, 250 mm wide
placed at 1 m center to center at approved locations to
control speed, marked with white strips of road marking paint.
Unit = sqm
Taking output = 100 sqm (including gaps)
The rate per sqm of premix carpet and road marking may be
adopted from chapter 5 & 8 respectively for the quantities
calculated from approved drawings

8.39

Suggest
ive

Policeman Umbrella
Provision of a 2 m high (floor to roof) umbrella for traffic
policeman at road crossings, where necessary, installed on a
raised platform, built on a central support of a steel pipe 100
mm dia, roof made of 25 mm dia steel pipe to provide
covered area of 3 sqm, roofed with CGI sheets, all steel parts
to be given 2 coats of paint
Unit = each
Taking output = one number
Earthwork
Cement Concrete
brick masonry or

Quantities of these items to be


calculated as per approved design and
cost added as per rates of these items
given in chapter 3 and 13

stone masonry

b)

cum
cum
cum
cum
sqm

2.500

Mate

day

0.090

Mazdoor

day

1.000

Blacksmith

day

1.000

Welder

day

0.250

metre

3.500

Painting
a)

17.10
2697.21

Cost for 68 Nos. = a+b+c+d+e

Suggest
ive

Remarks/ Input
ref.

Machinery
Tractor-trolley

8.37

Cost
Rs

Labour

Material
Steel pipe 100 mm dia
156

480.00

P&M-053

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Steel pipe 25 mm dia


CGI sheets

Quantity

metre

10.000

kg

8.000

hour

0.500

Add 25 per cent of cost of material for fabrication


Add 2 per cent of cost of material for welding consumables,
J-hooks, washers etc.
c) Machinery
Tractor-trolley
d)

Overheads @ per cent on (a+b+c)

e)

Contractors Profit@ per cent on (a+b+c+d)

Rate per policeman umbrella = a+b+c+d+e


8.40

suggesti
ve

High Mast Pole Lighting at Interchanges and Flyovers


Providing and erecting a high mast pole lighting with 30 m
high hot dip galvanised mast designed to withstand forces
exerted with wind speeds of 180 km per hour with 3 seconds
gust, as per IS:875 (Part 3) - 1978, fitted with a base flange,
door at the base of mast with heavy duty internal lock, lantern
carriage, suitable winching arrangement for safe working
load of 750 kg and high powered electrically driven power
tools for raising and lowering of lantern carriage, flexible 8
core electric cable, lightening conductor, earthing terminal,
and fixing 2 nos aviation obstruction lights on top of the mast,
all complete as per approved design and drawings
This is a specialised work and is generally done by firms who
specialise in such jobs. The detailed designs and estimates
are submitted by the firms along with their tender for checks
by the Department. The cost of this work is required to be
worked out based on approved design, drawings and
estimate of the lowest tender. A separate contract for this
work is concluded as the contractors for road and bridge
works generally donot undertake such jobs.

8.41

Toll Plaza
The construction, operation and maintenance of Toll Plaza
can be broken into separate items of work as under based on
the approved design and drawings:a) Provision of toll collection service lane to separate
different categories of vehicles for purpose of toll collection.
This involves considerable increase in carriage way width
b)
Provision of 2.5 m wide separators for different toll
collection service lanes for safety
c) Toll booths with integrated roof cover
d) Barrier gates for individual lanes
e)
Provision of building to provide facility to toll plaza
personnel
f) Toll plaza office equipment and furniture
g) Water supply, electricity, sanitation, septic-tank system
and drainage
h)
Telephone, intercomes, wireless communication
system
i) High mast lighting
j) Pavement marking
k) Overhead signs
l) Fixed message signs (Advance)
m) Variable message signs
n) Traffic cones and pylons
o) First aid post

8.42

p) Traffic aid post and security


The quantities for the above mentioned items may be
calculated from the approved design and drawings and their
rates adopted from respective chapters of the Standard Data
Book
Safety Devices and Signs in Construction Zones
157

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Provision and fixing of traffic signs for limited period at


suitable locations in construction zone comprising of warning
zone, approach transition zone, working zone and terminal
transition zone with a minimum distance of 60 cm from the
edge of the kerb in case of kerbed roads and 2 to 3 m from
the edge of the carriageway in case of un-kerbed roads, the
bottom edge of the lowest sign plate to be not less than 2 m
above the road level, fixed on 60 mm x 60 mm x 6 mm angle
iron post, founded and installed as per approved design and
drawings, removed and disposed of after completion of
construction work, all as per IRC:SP:55-2001
Unit = each
Taking output = one sign post
Following types of signs are required to be fixed in
construction zones for safety of traffic
a) Diversion one km ahead
b)

Traffic sign ahead

c)

Road ahead closed

d)

Men at work

e)

Road narrow

f)

Single file traffic

g)

Right lane diverted

h)

Left lane diverted

i)

Right lane closed

j) Left lane closed


k) Median closed
l) Diversion to other carriageway
m) Traffic signal ahead
n) Two way traffic
o) Un - even road
p) Slippery road
q) Loose chippings
r) Dual carriageway ends
s) Diversion
t) Do not enter
u) Road closed
v) Stop
w) Slow
x) One way
y) Give way
z)
aa)

Overtaking prohibited
Speed limit

bb)

Weight limit

cc)

Height and length limit

dd)

No stopping or standing

ee) Any other warning or regulatory safety sign as per site


requirement and consistent with IRC:SP:55-2001 and IRC:67
The rate for traffic signs are already worked out and given
elsewhere in this chapter. The same may be adopted.
8.43

suggesti
ve

Portable Barricade in Construction Zone


Installation of a steel portable barricade with horizontal rail
300 mm wide, 2.5 m in length fitted on a 'A' frame made with
45 x 45 x 5 mm angle iron section, 1.5 m in height, horizontal
rail painted (2 coats) with yellow and white stripes, 150 mm
in width at an angle of 450 C, 'A' frame painted with 2 coats of
yellow paint, complete as per IRC:SP:55-2001
Unit = each

158

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Taking output = one steel portable barricade


a)

Labour
Mate

b)

day

232.16

4.64

L-12

55.40

L-13

Mazdoor

day

0.250

221.61

Painter

day

0.500

353.52

176.76

L-18

Welder

day

0.250

353.52

88.38

L-02

kg

25.000

37.995

949.88

M-179 /1000

kg

15.000

37.995

569.93

M-179 /1000

litre

0.500

138.35

69.18

M-131

Material
Angle iron 45 x 45 x 5 mm
MS sheet 300 mm wide,2.5 m long and 2.6 mm thick

Paint
Add 2 per cent of cost of steel for welding consumables,
nuts & bolts and drilling holes
c) Overhead charges @ 0.1 on (a+b)
d)

0.020

30.40
194.46
213.90

Contractor's profit @ 0.1 on (a+b+c)

2352.93

Rate per barricade = a+b+c+d

8.44

suggesti
ve

say

2353.00

0.050

232.16

11.61

L-12

66.48

L-13

Permanent Type Barricade in Construction Zone


A

With steel components


Construction of a permanent type barricade made of steel
components, 1.5 m high from road level, fitted with 3
horizontal rails 200 mm wide and 4 m long on 50 x 50 x 5
mm angle iron vertical support, painted with yellow and white
strips, 150 mm in width at an angle of 450 C, complete as per
IRC:SP:55-2001
Unit = each
Taking output = one barricade
a)

Labour
Mate

b)

day

Mazdoor

day

0.300

221.61

Painter

day

0.600

353.52

212.11

L-18

Welder

day

0.300

353.52

106.06

L-02

kg

15.000

37.995

569.93

M-179 /1000

kg

50.000

37.995

1899.76

M-179 /1000

litre

1.000

138.35

138.35

M-131

Material
Angle iron 50 x 50 x 5 mm,2 m long,2 Nos.

MS sheet of 12 SWG,3 Nos of 200 mm width and 4 m


length
Paint
Add 1 per cent of cost of steel for welding consumables,
nuts & bolts and drilling holes
c) Overhead charges @ 0.1 on (a+b)
d)

24.70
302.90
333.19

Contractor's profit @ 0.1 on (a+b+c)

3665.09

Rate per barricade = a+b+c+d


8.44

say

3665.00

With wooden components


Construction of a permanent type barricade made of wooden
components, 1.5 m high from road level, fitted with 3
horizontal planks 200 mm wide and 3.66 m long on 100 x
100mm wooden vertical post, painted with yellow and white
strips, 150 mm in width at an angle of 450 C, complete as per
IRC:SP:55-2001
Unit = each
Taking output = one barricade
a)

b)

Labour
Mate

day

0.050

232.16

11.61

L-12

Mazdoor

day

0.300

221.61

66.48

L-13

Painter

day

0.600

353.52

212.11

L-18

Carpenter

day

0.600

353.52

212.11

L-04

cum

0.180

31666.24

5699.92

M-185

Material
Timber

Add 1 per cent of cost of timber for nuts & bolts, nails, etc.
159

57.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

c)

Overhead charges @ 0.1 on (a+b)

625.92

d)

Contractor's profit @ 0.1 on (a+b+c)

688.52

Remarks/ Input
ref.

7573.68

Rate per barricade = a+b+c+d


8.44

Cost
Rs

say

7574.00

With bricks
Construction of a permanent type barricade made with brick
work in mud mortar, 1.5 m high, 4 m long, 600 mm thick,
plastered with cement mortar 1:6, painted with yellow and
white strips
Unit = each
Taking output = one barricade
a)

b)

Labour
Mate

day

0.240

232.16

55.72

L-12

Mazdoor

day

3.000

221.61

664.83

L-13

Painter

day

1.000

353.52

353.52

L-18

Mason

day

2.000

353.52

707.04

L-11

each

1800.000

4.92

8857.52

M-079

22.000

5.211

114.63

M-081 /1000

Material
Brick
Cement

kg

Sand

cum

0.090

219.18

19.73

M-005

Paint

litre

1.250

138.35

172.94

M-131

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1094.59
1204.05
13244.57

Rate per barricade = a+b+c+d


say
8.45

suggesti
ve

13245.00

Drum Delineator in Construction Zone


Provision of metal drum/empty bitumen drum delineator, 300
mm in diameter, 800 mm high, filled with earth for stability,
painted in circumferential strips of alternate black and white
100 mm wide fitted with reflectors 3 Nos of 7.5 cm dia, all as
per IRC:SP:55-2001
Unit = each
Taking output = one drum delineator
a)

b)

Labour
Mate

day

0.020

232.16

4.64

L-12

Mazdoor

day

0.250

221.61

55.40

L-13

Painter

day

0.250

353.52

88.38

L-18

Steel drum 300 mm dia 1.2 m high/empty bitumen drum

each

1.000

90.84

90.84

M-172

Paint

litre

0.500

138.35

69.18

M-131

Material

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

30.84
33.93
373.22

Rate per drum delineator = a+b+c+d


say
8.46

suggesti
ve

373.00

Flagman
Positioning of a smart flagman with a yellow vest and a
yellow cap and a red flag 600 x 600 mm securely fastened to
a staff 1 m in length for guiding the traffic
Unit = each
Taking output = one flagman
a)

b)

Labour
Mate

day

0.040

232.16

9.29

L-12

Mazdoor

day

1.000

221.61

221.61

L-13

each

1.000

34.46

34.46

M-099

22.52

22.52

M-196

Material
Flag of red color cloth 600 x 600 mm
Wooden staff for fastening of flag 25 mm dia, one m
long
160

each

1.000

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost
Rs

c)

Overhead charges @ 0.1 on (a+b)

28.79

d)

Contractor's profit @ 0.1 on (a+b+c)

31.67
348.33

Rate per flagman = a+b+c+d


say

161

348.00

Remarks/ Input
ref.

CHAPTER-9
PIPE CULVERTS
Sr No
9.1

Ref. to
MoRTH
Spec.
408

Description

PCC 1:3:6 in Foundation


Plain cement concrete 1:3:6 mix with crushed stone
aggregate 40 mm nominal size mechanically mixed, placed
in foundation and compacted by vibration including curing for
14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate
day
Mason
day
Mazdoor
day
b) Material
40mm Aggregate at site
cum
Sand at site
cum
Cement at site
tonne
Cost of water
KL
c) Machinery
Concrete mixer0.4/ 0.28 cum
hour
Generator set 33 KVA
hour
Water tanker6 KL capacity
hour
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Note

9.2

Unit

2900

Quantity Rate Rs

Cost Rs

Remarks/
Input ref.

0.640
1.000
15.000

232.16
353.52
221.61

148.58
353.52
3324.15

L-12
L-11
L-13

13.800
6.900
3.300
18.000

830.30
219.18
5210.53
167.07

11458.14
1512.34
17194.74
3007.23

M-055
M-005
M-081
M-189

6.000
6.000
3.000

211.68
342.36
111.24

P&M-009
P&M-079
P&M-060

say

1270.08
2054.16
333.72
4065.67
4472.23
49194.56
3279.64
3280.00

Vibrator is a part of minor T & P which is already included in


overhead charges of the contractor.
Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Single Row .
Laying Reinforced cement concrete pipe NP4/prestressed
concrete pipe for culverts on first class bedding of granular
material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets .
Unit = metre
Taking output = 12.5 metres ( 5 pipes of 2.5 m length
each )
1000 mm dia
a)

Labour
Mate
Mason
Mazdoor
b) Material
Sand at site
Cement at site
RCC pipe NP-4 /prestressed concrete pipe including
collar at site
Granular material passing 5.6 mm sieve for bedding
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 12.5 metres = a+b+c+d
Rate per metre = (a+b+c+d)/12.5
Note

9.2

day
day
day

0.180
0.500
4.000

232.16
353.52
221.61

41.79
176.76
886.44

L-12
L-11
L-13

cum
tonne
metre

0.070
0.050
12.500

219.18
5210.53
4395.60

15.34
260.53
54945.00

M-005
M-081
M-149

cum

4.500

166.19

M-009

say

747.86
5707.37
6278.11
69059.19
5524.74
5525.00

232.16

65.00

1. In case of cement craddle bedding, quantity of PCC M15


is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
1200 mm dia
a) Labour
Mate
162

day

0.280

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mason
Mazdoor
b) Material
Sand at site
Cement at site
RCC pipe NP-4/prestressed concrete pipe including
collar at site
Granular material passing 5-6 mm sieve for class
bedding
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 12.5 metres = a+b+c+d
Rate per metre= (a+b+c+d)/12.5
Note

9.3

2900

Quantity Rate Rs

day
day

1.000
6.000

353.52
221.61

353.52
1329.66

L-11
L-13

cum
tonne
metre

0.090
0.070
12.500

219.18
5210.53
5319.60

19.73
364.74
66495.00

M-005
M-081
M-150

cum

5.000

166.19

830.95

M-009

say

6945.86
7640.45
84044.90
6723.59
6724.00

Taking output = 12.5 metres ( 10 pipes of 2.5 m length


each in two rows.)
1000 mm dia

b)

Labour
Mate

day

0.360

232.16

83.58

L-12

Mason

day

1.000

353.52

353.52

L-11

Mazdoor

day

8.000

221.61

1772.88

L-13

Material
Sand at site

cum

0.140

219.18

30.69

M-005

Cement at site

tonne

0.100

5210.53

521.05

M-081

RCC pipe NP-4/prestressed concrete pipe including


collar at site
Granular material passing 5.6 mm sieve for bedding

metre

25.000

4395.60

109890.00

M-149

cum

12.500

166.19

2077.38

M-009

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

11472.91
12620.20

Cost for 12.5 metres = a+b+c+d

138822.20

Rate per metre = (a+b+c+d)/12.5

9.3

Remarks/
Input ref.

1. In case of cement craddle bedding, quantity of PCC M15


is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Double Row .
Laying Reinforced cement concrete pipe NP4 / prestressed
concrete pipe for culverts on first class bedding of granular
material in double row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets .
Unit = metre

a)

Note

Cost Rs

11105.78

1. In case of cement craddle bedding, quantity of PCC M15


is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
1200 mm dia
a)

b)

say

11106.00

Labour
Mate

day

0.560

232.16

130.01

L-12

Mason

day

2.000

353.52

707.04

L-11

Mazdoor

day

12.000

221.61

2659.32

L-13

cum

0.180

219.18

39.45

Material
Sand at site
163

M-005

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity Rate Rs

Remarks/
Input ref.

Cement at site

tonne

0.140

5210.53

729.47

M-081

metre

25.000

5319.60

132990.00

M-150

cum

13.750

166.19

2285.11

M-009

c)

RCC pipe NP-4 /prestressed concrete pipe including


collar at site
Granular material passing 5-6 mm sieve for class
bedding
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

13954.04
15349.44

Cost for 12.5 metres = a+b+c+d

168843.89

Rate per metre= (a+b+c+d)/12.5


Note

Cost Rs

13507.51

1. In case of cement craddle bedding, quantity of PCC M15


is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections

164

say

13508.00

CHAPTER- 10
MAINTENANCE OF ROADS
Sr No
10.1

Ref. to
MoRTH
Spec.
3002

Description

Unit

Tipper ( L is average lead in km for borrow earth)


Add 10 per cent of cost of carriage towards loading and
unloading charges.
Plate compactor
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 10 cum = a+b+c+d
Rate per cum = (a+b+c+d)/10
Note

3003

Tipper ( L is average lead in km for borrow earth)


Add 10 per cent of cost of transportation to cover cost of
loading and unloading
Plate compactor @ 25 sqm per hour
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 100 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)100
3003

Cost Rs

Remarks/
Input ref.

day
day

0.080
2.000

232.16
221.61

18.57
443.22

L-12
L-13

197.12

P&M-026

hour

0.130

1516.32

tonne.km

12 x L

2.27

hour

0.500

142.99

27.22 Lead =1 km &


P&M-058
2.72
P&M-086

say

71.50
76.03
83.64
920.02
92.00
92.00

Only 75 per cent of fresh material has been provided as 25


per cent can be retrieved at site from earth that is flown
down the slope in the form of slurry and deposited at the foot
of the rain cuts
Maintenance of Earthen Shoulder (filling with fresh soil)
Making up loss of material/ irregularities on shoulder to the
design level by adding fresh approved soil and compacting it
with appropriate equipment.
Unit = sqm
Taking output = 100 sqm
Assuming average thickness of filling to be 150 mm
Quantity of fresh material = 15 cum
a) Labour
Mate
Mazdoor
b) Machinery
Excavator1.0 cum bucket capacity @ 60 cum per hour

10.3

Rate Rs

Restoration of Rain Cuts


Restoration of rain cuts with soil, moorum, gravel or a
mixture of these, clearing the loose soil, benching for 300
mm width, laying fresh material in layers not exceeding 250
mm and compacting with plate compactor or power rammers
to restore the original alignment, levels and slopes
Unit = cum
Taking output = 10 cum
a) Labour
Mate
Mazdoor
b) Machinery
Excavator1.0 cum bucket capacity @ 60 cum per hour

10.2

Quantity

day
day

0.180
4.500

232.16
221.61

41.79
997.25

L-12
L-13

379.08

P&M-026

hour

0.250

1516.32

tonne.km

24xL

2.27

hour

12.000

142.99

54.43 Lead =1 km &


P&M-058
5.44
P&M-086

say

1715.90
319.39
351.33
3864.61
38.65
39.00

Maintenance of Earth Shoulder (stripping excess soil)


Stripping excess soil from the shoulder surface to achieve
the approved level and compacting with plate compactor
Unit = sqm
Taking output = 100 sqm
Assuming average depth of stripping as 75 mm
Quantity of earth cutting involved = 7.5 cum
a) Labour
Mate
Mazdoor
b) Machinery
Plate compactor @ 25 sqm per hour
c) Overhead charges @ 0.1 on (a+b)
165

day
day

0.100
2.500

232.16
221.61

23.22
554.03

L-12
L-13

hour

4.000

142.99

571.97
114.92

P&M-086

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

d) Contractor's profit @ 0.1 on (a+b+c)


Cost for 100 sqm = a+b+c+d
Rate per sqm on = (a+b+c+d)100
say
Note
10.4

3004.2

b)

c)

126.41
1390.54
13.91
14.00

Day

3.760

232.16

872.92

L-12

Mazdoor

Day

90.000

221.61

19944.90

L-13

Mazdoor skilled

Day

4.000

306.03

1224.12

L-15

Air compressor 250 cfm

hour

6.000

293.76

1762.56

P&M-001

HMP 100-110 TPH Capacity

hour

6.000

30613.00

183678.00

P&M-022

Tipper 10 tonnes capacity

hour

45.000

830.00

37350.00

P&M-048

Smooth wheeled roller 8-10 tonnes

hour

12.000

625.00

7500.00

P&M-044

cum

184.500

827.86

152740.17

M-052

cum

92.250

723.14

66709.67

M-051

tonne

14.970

31938.10

478113.36

M-075

tonne

2.460

37569.11

92420.01

M-077

Machinery

Material
Crushed stone aggregates nominal size 13.2mm @
0.18 cum per 10 sqm
Crushed stone aggregates nominal size 11.2mm @
0.09 cum/10 sqm
Bitumen 80/100 @ 14.6 kg per 10 sqm

d)

Bitumen emulsion for tack coat including vertical sides


of pot hole.
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

104231.57
114654.73

Cost for 10250 sqm = a+b+c+d+e

1261202.00

Rate per sqm = (a+b+c+d+e)/10250

123.04
say

3004.2

Remarks/
Input ref.

The earth stripped from earthen shoulders to be dumped on


the side slopes locally for disposal.
Filling Pot-holes and Patch Repairs with open-Graded
Premix surfacing, 20mm.
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with hot bituminous
material as per clause 511, compacting, trimming and
finishing the surface to form a smooth continuous surface, all
as per clause 3004.2
Unit = Sqm
Taking out put = 10250 sqm (205 cum)(405 tonne)
a) Labour
Mate

10.5

Cost Rs

123.00

Filling Pot-holes and Patch Repairs with Bituminous


concrete, 40mm.
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with hot bituminous
material as per clause 504, compacting, trimming and
finishing the surface to form a smooth continuous surface, all
as per clause 3004.2
Unit = Sqm
Taking out put = 4900 sqm (196 cum)(450 Tonnes)
a)

b)

c)

Labour
Mate

Day

2.920

232.16

677.91

L-12

Mazdoor

Day

70.000

221.61

15512.70

L-13

Mazdoor skilled

Day

3.000

306.03

918.09

L-15

Air compressor 250 cfm

hour

6.000

293.76

1762.56

P&M-001

HMP 100-110 TPH Capacity

hour

6.000

30613.00

183678.00

P&M-022

Tipper 10 tonnes capacity

hour

45.000

830.00

37350.00

P&M-048

Smooth wheeled roller 8-10 tonnes

hour

12.000

625.00

7500.00

P&M-044

I) Bitumen

tonne

22.500

31938.10

718607.25

M-075

ii) Bitumen emulsion for tack coat .

tonne

1.180

37569.11

44331.55

M-077

Machinery

Material

166

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

117088.55

M-045

iii) Aggregates
Grading I - 19mm(Nominal size)
20-10mm 35 per cent

cum

99.750

1173.82

10-5 mm 23 per cent

cum

65.550

814.39

53383.26 M-025,M-040

cum

114.000

265.64

30282.96

M-030

tonne

8.620

4427.31

38163.39

M-188

5mm and below 40 per cent


Filler 2 per cent by weight of aggregate
Add 5 per cent for wastage

1908.17

or
Grading-II 13mm (Nominal size)
13.2-10 mm 30 per cent

cum

85.500

988.49

84515.90

M-044

10-5 mm 25 per cent

cum

71.250

814.39

58025.29

M-025

5 mm and Below43 per cent

cum

122.550

265.64

32554.18

M-030

tonne

8.620

4427.31

38163.39

M-188

Filler 2 per cent


Add 5 per cent for wastage

10.5

(i)

1908.17

Any one of the above alternatives of aggregate i.e. 19mm or


13mm nominal size may be adopted as per approved
design.
for grading I Material
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

125116.44
137628.08

Cost for 4900 cum = a+b+c+d+e

1513908.91

Rate per cum = (a+b+c+d+e)/4900

308.96
say

309.00

#REF!
10.5

(ii)

for grading II Material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

122550.50
134805.55

Cost for 4900 cum = a+b+c+d+e

1482861.03

Rate per cum = (a+b+c+d+e)/4900

302.62
say

303.00

#REF!
Note
10.6

3004.3.3

For detailed working of quantities of aggregates, refer item


5.8 of chapter 5
Crack Filling
Filling of crack using slow - curing bitumen emulsion and
applying crusher dust in case crack are wider than 3mm.
Unit = Running Meter
Taking out put = 500m
a)

b)

Labour
Mate

day

0.040

232.16

9.29

L-12

Mazdoor

day

1.000

221.61

221.61

L-13

Kg

33.000

37.57

1239.78

M-077

cum

0.020

259.58

5.19

M-021

Material
Slow-curing bitumen emulsion
Stone crusher dust

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

147.59
162.35

Cost for 500sqm = a+b+c+d

1785.80

Rate per meter = (a+b+c+d+e)/500


10.7

3004.4

3.57
say

3.60

Dusting
Applying crusher dust to areas of road where bleeding
of excess bitumen has occurred.
Unit = Sqm
Taking output = 3500 sqm
a)

Labour
Mate

day

0.080

232.16

18.57

L-12

Mazdoor

day

2.000

221.61

443.22

L-13

167

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

b)

Material

c)

Stone crusher dust finer than 3mm with not more


than 10 per cent passing 0.075 sieve.
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Quantity

cum

6.250

Rate Rs

259.58

229.26
0.72
say

Fog Seal

(ii)
(iii)
(iv)

10.8

10.9

(C)
3004.5

sqm

35.00

Item 5.17

Stress Absorbing Membrane (SAM) crack width less than 6


mm
Stress Absorbing Membrane (SAM) with crack width 6 mm
to 9 mm
Stress Absorbing Membrane (SAM) crack width above 9 mm
and cracked area above 50 per cent

sqm

47.00

sqm

57.00

sqm

75.00

Item 5.21
Case-I
Item 5.21
Case-II
Item 5.21
Case-IV

Bitumen Impregnated Geotextile

sqm

125.00

Item 5.21
Case-IV

Item 5.15
Case-I
Item 5.15
Case-II
Item 5.15
Case-III

Slurry Seal
(i)

5 mm thickness

sqm

61.00

(ii)

3 mm thickness

sqm

43.00

(iii)

1.5 mm thickness

sqm

26.00

71.00 Item 5.9 CaseI


57.00 Item 5.9 CaseII

(D)
3004.6

3005.1

0.70

Crack Prevention courses.


(i)

10.8

M-021

2521.84

Rate per meter = (a+b+c+d)/3500

(A)
3004.3.2
(B)
3004.3.4

1622.38

Remarks/
Input ref.

208.42

Cost for 3500sqm = a+b+c+d

10.8

Cost Rs

Surface Dressing for maintenance works.


(i)

19 mm nominal chipping size

sqm

(ii)

13 mm nominal size chipping

sqm

The above mentioned items have already been included in


chapter 5.
Repair of Joint Grooves with Epoxy Mortar
Repair of spalled joint grooves of contraction joints,
longitudinal joints and expansion joints in concrete
pavements using epoxy mortar or epoxy concrete
Unit = running metre
Taking output = 10 metres
a)

b)

c)

Labour
Mate

day

0.040

232.16

9.29

L-12

Mazdoor

day

0.500

221.61

110.81

L-13

Chiseller

day

0.500

306.03

153.02

L-05

Material
Epoxy primer

kg

2.500

9.01

22.52

M-097

Epoxy compound with accessories for preparing epoxy


mortar
Machinery

kg

10.000

282.81

2828.09

M-095

hour

0.050

293.76

Air compressor 250 cfm for cleaning


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

345.22

Cost for 10 metres = a+b+c+d+e

3797.47

Rate per metre = (a+b+c+d+e)/10

379.75
say

10.10

3005.2

14.69
313.84

Repair of old Joints Sealant


Removal of existing sealant and re sealing of contraction,
longitudinal or expansion joints in concrete pavement with
fresh sealant material
Unit = running metre
168

380.00

P&M-001

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output = 10 metres


a)

b)

c)

Labour
Mate

day

0.040

232.16

9.29

L-12

Mazdoor

day

0.500

221.61

110.81

L-13

Primer

kg

0.250

90.84

22.71

M-146

Sealant

kg

1.000

17.81

17.81

M-120

hour

0.050

293.76

14.69

P&M-001

Material

Machinery
Air compressor 250 cfm for cleaning

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

17.53
19.28

Cost for 10 metres = a+b+c+d+e

212.11

Rate per metre = (a+b+c+d+e)/10

21.21
say

10.11

3000

21.20

Hill Side Drain Clearance


Removal of earth from the choked hill side drain and
disposing it on the valley side manually
Unit = running metre
Taking output = 10 metres
Assuming muck causing choking of drain to be 0.2 cum per
metre, quantity of earth to be removed for 10 metres = 2
cum
a) Labour
Mate

day

0.080

232.16

18.57

L-12

Mazdoor

day

1.000

221.61

221.61

L-13

b)

Overhead charges @ 0.1 on (a+b)

c)

Contractor's profit @ 0.1 on (a+b)

24.02
26.42

Cost for 10 metres = a+b+c

290.62

Rate per metre = (a+b+c)/10


10.12

3000

29.06
say

29.10

Land Slide Clearance in soil


Clearance of land slides in soil and ordinary rock by a bulldozer D 80 A-12, 180 HP and disposal of the same on the
valley side
Unit = cum
Taking output = 100 cum
a)

b)

Labour
Mate

day

0.040

232.16

9.29

L-12

Mazdoor

day

1.000

221.61

221.61

L-13

hour

1.670

3135.24

5235.85

P&M-014

Machinery
Dozer 80 HP @ 60 cum per hour

c)

Overhead charges @ 0.1 on (a+b)

546.67

d)

Contractor's profit @ 0.1 on (a+b+c)

601.34

Cost for 100 cum = a+b+c+d

6614.76

Rate per cum = (a+b+c+d)/100

66.15
say

Note

10.13

3000

Land Slide clearance involves pushing of loose earth slided


on the road surface from hill face on the valley side. Since
no cutting of original ground is involved, the output of dozer
has been taken as 60 cum per hour for soil, ordinary rock
and blasted hard rock. However, if there are objection to
disposing of earth on valley side, additional resources for its
disposal shall be considered as per site conditions.
Landslide Clearance in Hard Rock Requiring Blasting
Clearing of land slide in hard rock requiring blasting for 50
per cent of the boulders and disposal of the same on the
valley side.
Unit = cum
Taking output = 100 cum
169

66.00

Sr No

Ref. to
MoRTH
Spec.

Description
a)

b)

c)

Unit

Quantity

Rate Rs

Mate

day

0.090

232.16

20.89

L-12

Mazdoor

day

1.500

221.61

332.42

L-13

Driller

day

0.750

232.16

174.12

L-06

Blaster

day

0.070

306.03

21.42

L-03

Dozer D 80 A-12,180 HP @ 60 cum per hour

hour

1.670

3135.24

5235.85

P&M-014

Air compressor 250 cfm with two jack hammer

hour

2.500

293.76

734.40

P&M-001

kg

17.500

112.77

1973.49

M-104

each

70.000

14.27

998.63

M-094 /100

Machinery

Materials

c)

Electric Detonators @ 1 Detonator for 2 Gelatine sticks


of 125 gms each
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

949.12
1044.03

Cost for 100 cum = a+b+c+d+e

11484.38

Rate per cum = (a+b+c+d+e)/100

114.84
say

10.14

3000

Remarks/
Input ref.

Labour

Gelatine 80 per cent @ 35 kg per 100 cum

Note

Cost Rs

115.00

Credit for the rock if found acceptable as construction


material shall be afforded
Snow Clearance on Roads with Dozer
Snow clearance from road surface by a bull- dozer 165 Hp
and disposing it on the valley side
Unit = cum
Taking output = 5000 cum
a)

b)

Labour
Mate

day

0.080

232.16

18.57

L-12

Mazdoor

day

2.000

221.61

443.22

L-13

hour

5.880

3135.24

18435.21

Machinery
Dozer D 80 A-12,180 HP @ 850 cum per hour

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2078.67

Cost for 5000 cum = a+b+c+d

22865.37

Rate per cum = (a+b+c+d)/5000

4.57
say

Note

10.15

3000

P&M-014

1889.70

4.60

i) Labour provided will not be cutting the snow. They will be


guiding the dozer operator on the alignment of the road as
entire surface gets covered with snow and the edges of the
road are not visible and for changing the blade angle. Also
they will keep a watch on the hill side for any eventuality of
avalanches, slide etc
Snow Clearance on Roads with Snow Blowers
Snow clearance from road surface by a snow blower and
disposing on the valley side.
Unit = cum
Taking output = 3600 cum
a)

b)

Labour
Mate

day

0.080

232.16

18.57

L-12

Mazdoor

day

2.000

221.61

443.22

L-13

#VALUE!

P&M-087

Machinery
Snow blower equipment 140 HP @ 600 cum per hour

hour

6.000 Value

c)

Overhead charges @ 0.1 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Cost for 3600 cum (a+b+c+d)

#VALUE!

Rate per cum = (a+b+c+d)/3600

#VALUE!
say

170

#VALUE!

CHAPTER-11

HORTICULTURE
Sr No
11.1

Ref. to
MoRTH
Spec.
307

Description

Quantity

Rate Rs

Cost Rs

day
day

0.040
1.000

232.16
221.61

L-12
L-13

say

9.29
221.61
23.09
25.40
279.38
18.63
18.60

Spreading of Sludge Farm Yard Manure or/and good


Earth
Spreading of sludge farm yard manure or/ and good earth in
required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Unit = cum
Taking output = 15 cum
a) Labour
Mate
Mazdoor
b) Overhead charges @ 0.1 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Cost for 15 cum= a+b+c
Rate per cum = (a+b+c)/15

11.2

Remarks/
Input ref.

Unit

307

Grassing with ' Doobs' Grass

(i)

Grassing with 'Doobs' grass including watering and


maintenance of the lawn for 30 days or more till the grass
forms a thick lawn free from weeds and fit for moving
including supplying good earth if needed
Unit = sqm
Taking output = 100 sqm
In rows 15 cm apart in either direction
a)

Labour
Mate
Mazdoor for grassing
Mazdoor for maintenance for 30 days
b) Machinery
Water tanker6 KL capacity
c) Material
Doob grass
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e
Rate per sqm= (a+b+c+d+e)/100
11.2

(ii)

In rows 7.5 cm apart in either direction


a) Labour
Mate
Mazdoor for grassing.
for maintenance for 30 days
b) Machinery
Water tanker6 KL capacity
c) Material
Doob grass
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100

day
day
day

0.170
0.750
1.000

232.16
221.61
221.61

39.47
166.21
221.61

L-12
L-13
L-13

hour

0.500

111.24

55.62

P&M-060

kg

100.000

3.04

M-112

say

304.00
78.69
86.56
952.15
9.52
9.50

day
day
day

0.220
1.250
1.000

232.16
221.61
221.61

51.08
277.01
221.61

L-12
L-13
L-13

hour

0.750

111.24

83.43

P&M-060

kg

200.000

3.04

608.00
124.11
136.52
1501.76
15.02
15.00

M-112

say
Note

11.3

307

In the case of horticulture one mate has been provided for


every 10 mazdoors as maintenance of grass and plants
require more care.
Making Lawns including Ploughing and Dragging with
'Swagha' Breaking of Clod
Making lawns including ploughing and breaking of clod,
removal of rubbish, dressing and supplying doobs grass
roots and planting at 15 cm apart, including supplying and
spreading of farm yard manure at rate of 0.18 cum per 100
sqm
Unit = sqm
Taking output = 100 sqm

171

Sr No

Ref. to
MoRTH
Spec.

Description
Labour
Mate
Mazdoor for preparation of ground
Mali for fetching doobs grass roots and grassing at 15
cm apart
b) Machinery
Water tanker6 KL capacity
Tractor with filler
c) Material
Supply of farm yard manure at site of work
Fine grass
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

day
day
day

0.150
0.500
1.000

232.16
221.61
232.11

34.82
110.81
232.11

L-12
L-13
L-09

hour
hour

0.500
0.010

111.24
171.02

55.62
1.71

P&M-060
P&M-053

cum
kg

0.180
100.000

528.65
3.04

95.16
304.00
83.42
91.76
1009.41

M-167
M-113

say

10.10

a)

Rate per sqm = (a+b+c+d+e)/100


11.4

307

10.09

Maintenance of Lawns or Turfing of Slopes


Maintenance of lawns or Turfing of slopes (rough grassing)
for a period of one year including watering etc
Unit = sqm
Taking output = 100 sqm
a)

Labour
Mali

b)

Water tanker6 KL capacity


c)

day

10.000

232.11

2321.10

L-09

hour

15.000

111.24

1668.60

P&M-060

KL

90.000

167.07

15036.14

M-189

Machinery
Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1902.58
2092.84

Cost for 100 sqm = a+b+c+d+e

23021.27

Rate per sqm = (a+b+c+d+e)/100

230.21
say

11.5

307

230.00

Turfing Lawns with Fine Grassing including Ploughing,


Dressing
Turfing lawns with fine grassing including ploughing,
dressing including breaking of clods, removal of rubbish,
dressing and supplying doobs grass roots at 10 cm apart,
including supplying and spreading of farm yard manure at
rate of 0.6 cum per 100 sqm
Unit = sqm
Taking output = 100 sqm
a)

b)

c)

Labour
Mate

day

0.250

232.16

58.04

L-12

Mazdoor for preparation of ground

day

1.000

221.61

221.61

L-13

Mali for fetching doobs grass roots hedges and


grassing at 10 cm apart
Machinery

day

1.500

232.11

348.17

L-09

Water tanker6 KL capacity

hour

0.500

111.24

55.62

P&M-060

Tractor with tiller

hour

0.010

171.02

1.71

P&M-053

cum

0.600

528.65

317.19

M-167

kg

100.000

3.04

304.00

M-113

Material
Supply of farm yard manure at site of work @ 0.6 cum
per 100 sqm
Fine grass

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

130.63
143.70

Cost for 100 sqm = a+b+c+d+e

1580.67

Rate per sqm = (a+b+c+d+e)/100

15.81

172

Sr No

Ref. to
MoRTH
Spec.

11.6

307

Description

Unit

Quantity

Rate Rs

Cost Rs

say

15.80

Remarks/
Input ref.

Maintenance of Lawns with Fine Grassing for the First


Year
Maintenance of lawns with fine grassing for the first year
including watering etc
Unit = sqm
Taking output = 100 sqm
a)

Labour
Mali

b)

Water tanker6 KL capacity


c)

day

10.000

232.11

2321.10

L-09

hour

20.000

111.24

2224.80

P&M-060

KL

60.000

167.07

10024.09

M-189

Machinery
Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

1457.00

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1602.70

Cost for 100 sqm = a+b+c+d+e

17629.69

Rate per sqm = (a+b+c+d+e)/100

176.30
say

11.7

307

176.00

Planting and Maintaining of Permanent Hedges


(a)

Planting permanent hedges including digging of


trenches
Planting permanent hedges including digging of trenches, 60
cm wide and 45 cm deep, refilling the excavated earth mixed
with farmyard manure, supplied at the rate of 4.65 cum per
100 metres and supplying and planting hedge plants at 30
cm apart
Unit = Running metre
Taking output = 100metre
a)

b)
c)

Labour
Mate

day

1.400

232.16

325.02

L-12

Mazdoor for digging of trench 60 cm wide and 45 cm


deep
Mazdoor for refilling the excavated earth mixed with
cow dung, preparation of ground and digging of plant,
from the nursery carriage to site and planting in
position
Machinery

day

10.000

221.61

2216.10

L-13

day

4.000

221.61

886.44

L-13

Water tanker6 KL capacity

hour

0.500

111.24

55.62

P&M-060

Cost of hedge plants 2 rows at 30 cm apart

each

2x340

22.80

15504.00

M-116

Supply of farm yard manure at site of work

cum

4.670

528.65

2468.80

M-167

Pesticide

kg

0.250

56.39

14.10

M-136

Cost of water

KL

3.000

167.07

501.20

M-189

Material

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2197.13
2416.84

Cost for 100 metres = a+b+c+d+e

26585.25

Rate per metre = a+b+c+d+e)/100

265.85
say

(b)

266.00

Maintenance of hedge for one year


Unit = Running metre
Taking output = 100 m
a)

b)

Labour
Mate

day

3.000

232.16

696.48

L-12

Mazdoor

day

30.000

221.61

6648.30

L-13

hour

5.000

111.24

556.20

P&M-060

cum

2.000

528.65

1057.30

M-167

Machinery
Water tanker6 KL capacity

c)

Material
Manure sludge/Farm yard manure

173

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

kg

0.500

56.39

28.19

M-136

Cost of water

KL

30.000

167.07

5012.05

M-189

each

68.000

22.80

1550.40

M-116

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1554.89
1710.38

Cost for 100 metres = a+b+c+d+e

18814.19

Rate per metre = a+b+c+d+e)/100

188.14
say

307
(a)

Remarks/
Input ref.

Pesticide
Cost of hedge plants @ 10 per cent casualty

11.8

Cost Rs

188.00

Planting and Maintaining of Flowering Plants and


Shrubs
Planting flowering plants and shrubs in central verge
Unit = Running metres 200 plants and 800 shrubs in two
rows in one km length of road where width of verge is
3m and above.
Taking output = 1000 metres
a)

b)

Labour
Mate

day

1.200

232.16

278.59

L-12

Mazdoor

day

12.000

221.61

2659.32

L-13

hour

6.000

111.24

667.44

P&M-060

Plants

each

200.000

23.94

4787.19

M-100

Shrubs

each

800.000

11.40

9120.00

M-166

Manure sludge/Farm yard manure

Machinery
Water tanker6 KL capacity

c)

Material

cum

63.640

528.65

33643.29

M-167

Pesticide

kg

0.500

56.39

28.19

M-136

Cost of water

KL

36.000

167.07

6014.46

M-189

d)

Overhead charges @ 0.1 on (a+b+c)

5719.85

e)

Contractor's profit @ 0.1 on (a+b+c+d)

6291.83

Rate per Km = (a+b+c+d+e)

69210.15
say

11.8

(b)

69210.00

Maintenance of flowering plants and shrubs in central


verge for one year
Unit = km
Taking output = one km
a)

b)

Labour
Mate

day

36.000

232.16

8357.76

L-12

Mazdoor

day

365.000

221.61

80887.65

L-13

hour

90.000

111.24

10011.60

P&M-060

Machinery
Water tanker6 KL capacity

c)

Material
Manure Sludge / farm yard manure at site

cum

10.000

528.65

5286.50

M-167

Cost of water

KL

180.000

167.07

30072.28

M-189

Plants

each

20.000

23.94

478.72

M-100

Shrubs

each

80.000

11.40

912.00

M-166

kg

1.500

56.39

84.58

M-136

Replacement of casualties @ 10 per cent

Pesticides
d)

Overhead charges @ 0.1 on (a+b+c)

13609.11

e)

Contractor's profit @ 0.1 on (a+b+c+d)

14970.02

Rate per Km for one year = (a+b+c+d+e)

164670.22
say

11.9

307

Planting of Trees and their Maintenance for one Year


Planting of trees by the road side (Avenue trees) in 0.60 m
dia holes, 1 m deep dug in the ground, mixing the soil with
decayed farm yard/sludge manure, planting the saplings,
backfilling the trench, watering, fixing the tree guard and
maintaining the plants for one year
Unit = Each
174

164670.00

Sr No

Ref. to
MoRTH
Spec.

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Mate

day

1.700

232.16

394.67

L-12

Mazdoor for planting

day

2.000

221.61

443.22

L-13

Mazdoor for maintenance for one year

day

15.000

221.61

3324.15

L-13

hour

2.000

111.24

222.48

P&M-060

Sapling 2 m high 25 mm dia

each

10.000

17.54

175.42

M-160

Farm yard manure

cum

0.940

528.65

496.93

M-167

Pesticide

kg

0.500

56.39

28.19

M-136

Cost of water

KL

12.000

167.07

2004.82

M-189

Description
Taking output = 10 trees
a)

b)

Labour

Machinery
Water tanker6 KL capacity

c)

Material

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

708.99
779.89

Cost for 10 trees = a+b+c+d+e

8578.76

Rate per trees = (a+b+c+d+e)/10

857.88
say

11.10

308

858.00

Renovation Lawns including, Weeding, Forking the


Ground, Top Dressing with Forked Soil
Renovation lawns including, weeding, forking the ground,
top dressing with forked soil, watering and maintenance the
lawns, for 30 days or more, till the grass forms a thick lawn,
free from weeds, and fit for moving and disposal of rubbish
as directed, including supplying good earth, if needed but
excluding the cost of well decayed farm yard manure
Unit = sqm
Taking output = 100 sqm
a)

b)

Labour
Mate

day

0.120

232.16

27.86

L-12

Mazdoor

day

3.000

221.61

664.83

L-13

hour

0.500

111.24

55.62

P&M-060

KL

3.000

167.07

501.20

M-189

Machinery
Water tanker6 KL capacity

c)

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

124.95
137.45

Cost for 100 sqm = a+b+c+d+e

1511.91

Rate per sqm = (a+b+c+d+e) / 100


11.11

308.2

15.12
say

15.10

528.65

528.65

Supply at Site Well Decayed Farm Yard Manure


Supply at site of work well decayed farm yard manure, from
any available source, approved by the engineer in charge
including screening and stacking
Unit = cum
Taking output = one cum
a)

Material
a) Cost of well decayed farm yard manure duly
screened, loading, carriage, unloading and
stacking at site

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

cum

1.000

52.87
58.15

Rate per cum = (a+b+c)

639.67
640.00

11.12

308.20

Supply at Site of Work/ Store-Deoiled Neem Cake


Supply at site of work/ store-deoiled neem cake duly packed
in used gunny bags
Unit = quintal

175

M-167

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

quintal

1.000

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output = one quintal


a) Cost, carriage, loading, unloading and stacking in
store/site
b) Overheads@ per cent on (a)
c)

Contractors profit@ per cent on (a+b)

Rate per quintal = a+b+c


11.13

308.2

VALUE

Supplying Sludge
Supplying sludge duly stacked at site/ store
Unit = cum
Taking output = one cum
a) Cost of sludge including carriage, loading,
unloading and stacking at site
b) Overheads@ per cent on (a)
c)

cum

1.000

Contractors profit@ per cent on (a+b)

Rate per cum = a+b+c


11.14

New

VALUE

Half Brick Circular Tree Guard, in 2nd Class Brick,


internal diametre 1.25 metres, and height 1.2 metres,
above ground and 0.20 metre below ground
Half brick circular tree guard, in 2nd class brick, internal
diametre 1.25 metres, and height 1.2 metres, above ground
and 0.20 metre below ground, bottom two courses laid dry,
and top three courses in cement mortar 1:6 (1 cement 6
sand) and the intermediate courses being in dry honey comb
masonry, as per design complete
Unit = Each
Taking output = one tree guard
a)

b)

Labour
Mate

day

0.050

232.16

11.61

L-12

Mason

day

0.250

353.52

88.38

L-11

Mazdoor

day

0.250

221.61

55.40

L-13

Brick 2nd class including carriage

each

230.000

4.92

1131.79

M-079

Cement mortar 1:6

cum

0.025

2002.00

50.05

Item 12.6
(D)

Material

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

133.72
147.10

Rate per tree Guard = a+b+c+d

1618.05
say

1618.00
#REF!

Edging with 2nd class bricks, laid dry lengthwise, including


excavation, refilling, consolidation, with a hand packing and
spreading nearly surplus earth within a lead of 50 metres
Unit = Metre
Taking output= 10 metres
a)

b)

Labour
Mate

day

0.002

232.16

0.46

L-12

Mason

day

0.050

353.52

17.68

L-11

Mazdoor

day

0.050

221.61

11.08

L-13

each

50.000

4.92

246.04

M-079

Material
Brick 2nd class including carriage

c)

Overhead charges @ 0.1 on (a+b)

27.53

d)

Contractor's profit @ 0.1 on (a+b+c)

30.28

Cost for 10 metre = a+b+c+d

333.07

Rate per metre = (a+b+c+d)/10

33.31
say

11.16

New

Making Tree Guard 53 cm dia and 1.3 m High as per


Design from Empty Bitumen Drums

176

33.30

Sr No

Ref. to
MoRTH
Spec.

Description

Cost Rs

Remarks/
Input ref.

232.16

4.64

L-12

353.52

53.03

L-02

0.070

221.61

15.51

L-13

each

1.000

90.84

90.84

M-172

kg

0.650

38.00

24.70

each

22.000

5.64

124.05

M-179
/1000
M-158

Unit

Quantity

Rate Rs

Mate

day

0.020

Blacksmith

day

0.150

Mazdoor

day

Making tree guard 53 cm dia and 1.3 m high as per design


from empty bitumen drum, slit suitably to permit sun and air,
(supplied by the department at stock issue rate) including
providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with
rivets, complete in all respect
Unit = Each
Taking output = one tree guard
a)

b)

Labour

Material
Empty bitumen drum
MS sheet 50 x 0.5 mm
Rivets 6 mm dia and 10 mm in length

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

31.28
34.40

Rate for each tree guard = a+b+c+d

378.45
say

11.17

New

378.00

Making Tree Guard 53 cm dia and 2 Metre High as per


Design from Empty Bitumen Drums
Making tree guard 53 cm dia and 2 metres high as per
design from empty bitumen drums, slit suitably to permit sun
and air, ( supplied by the department at stock issue rate)
including providing and fixing four legs 40 cm long of 30 x 3
mm MS riveted to tree guard and providing and fixing 2 nos
MS sheet rings 50 x 0.5 mm with rivets complete in all
respects
Unit = Each
Taking output = one tree guard
a)

Labour
Mate
Blacksmith

day

Mazdoor
b)

0.040

232.16

9.29

L-12

0.200

353.52

70.70

L-02

0.200

221.61

44.32

L-13

Material
Empty bitumen drum

each

1.500

90.84

136.27

M-172

MS sheet50 x 0.5 mm

kg

0.650

38.00

24.70

each

50.000

5.64

281.93

M-179
/1000
M-158

kg

1.300

38.00

49.39

Rivets 6 mm dia and 10 mm in length


MSplate30 x 3 mm
c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

61.66
67.83

Rate for each tree guard = a+b+c+d


11.18

New

M-179
/1000

746.08
say

746.00

Wrought Iron and Mild Steel Welded Work


Wrought iron and mild steel welded work (using angles,
square bars, tees and channel grills, grating frames, gates
and tree guards of any size and design etc. including cost of
screens and welding rods or bolts and nuts complete fixed in
position but without the cost of excavation and concrete for
fixing which will be paid separately
Unit = quintal
Taking output = one quintal
a)

b)

Labour
Mate

day

0.450

232.16

104.47

L-12

Blacksmith/ welder for cutting to design and shape and


jointing
Mazdoor for fixing and helper for Blacksmith/welder

day

2.000

353.52

707.04

L-02

day

2.500

221.61

554.03

L-13

Material
177

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Angle, tees, channels etc

quintal

Deduct the cost of scrap

quintal

Cost Rs

1.050

3799.52

3989.50

M-179 /10

0.050

-1266.51

(63.33)

M-179/10/3

Add 5 per cent of cost of material for welding rods and other
welding accessories
c) Overhead charges @ 0.1 on (a+b)
d)

196.31
548.80

Contractor's profit @ 0.1 on (a+b+c)

603.68

Rate per quintal = a+b+c+d


11.19

New

Remarks/
Input ref.

Rate Rs

6640.50
say

6641.00

Tree Guard with MS Iron


Providing and fixing MS iron tree guard 60 cm dia and 2
metre high above ground level formed of 4 Nos (25 x 6 mm)
and 8 Nos (25 x 3 mm) vertical MS riveted to 3 Nos (25 x 6
mm) iron rings in two halves, bolted together with 8 mm dia
and 30 mm long bolts including painting two coats with paint
of approved brand over a coat of priming, complete in all
respects.
Unit = Each
Taking output = one tree guard
a)

b)

c)

Labour
Mate

day

0.050

232.16

11.61

L-12

Blacksmith

day

0.250

353.52

88.38

L-02

Mazdoor

day

0.250

221.61

55.40

L-13

MS iron 25 x 6 mm

kg

19.200

37.995

729.51

MS iron 25 x 3 mm

kg

9.600

37.995

364.75

M-179
/1000
M-179
/1000

hour

0.040

171.02

6.84

P&M-053

sqm

1.770

48.00

84.96

Item 8.9

Material

Add 5 per cent of cost of material for riveting, bolting


and welding accessories
Machinery
Tractor-trolley

d)

Painting
Painting two coats including priming

e)

Overhead charges @ 0.1 on (a+b+c)

f)

Contractor's profit @ 0.1 on (a+b+c+e)

125.65
138.21

Rate per tree guard =a+b+c+d+e+f

11.20

1605.32

Note

1 The items of excavation and concreting to be measured


and paid separately as per design .
2 . Rate of painting may be adopted from the chapter as
Traffic signs.

New

Tree Guard with MS Angle Iron and Steel Wire

say

1605.00

Providing and fixing tree guard 0.60 metre square, 2.00


metre high fabricated with MS angle iron 30 x 30 x 3 mm,
MS iron 25 x 3 mm and steel wire3 mm dia welded and
fabricated as per design in two halves bolted together
Unit = Each
Taking output = one tree guard
a)

b)

Labour
Mate

day

0.050

232.16

11.61

L-12

Blacksmith

day

0.250

353.52

88.38

L-02

Welder

day

0.250

353.52

88.38

L-02

Mazdoor

day

0.250

221.61

55.40

L-13

MS angle 30 x 30 x 3 mm

kg

13.500

38.00

512.94

MS iron 25 x 3 mm

kg

18.000

38.00

683.91

Steel wire 3 mm dia

kg

6.000

30.28

181.69

M-179
/1000
M-179
/1000
M-192

Material

178

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Unit

Rate Rs

Add 5 per cent of cost of material for riveting, bolting


and welding accessories
Machinery
Tractor-trolley

d)

Quantity

68.93

hour

0.040

171.02

sqm

1.500

48.00

6.84

P&M-053

72.00

Item 8.9

e)

Overhead charges @ 0.1 on (a+b+c)

169.81

f)

Contractor's profit @ 0.1 on (a+b+c+e)

186.79

Rate per tree guard = a+b+c+d+e+f


New

Remarks/
Input ref.

Painting
Painting two coats including priming

11.21

Cost Rs

2126.67
say

2127.00

Compensatory Afforestation
Planting trees as compensatory afforestation at the rate of
290 trees per hectare at a spacing of 6 m by grubbing and
leveling the ground upto a depth of 150 mm, digging holes
0.9 m dia, 1 m deep, mixing farm yard/sludge manure with
soil, planting of sapling 2 m high with 25 cm dia stem,
backfilling the hole and watering
Unit = Hectare
Taking output = one hectare
a)

Labour

i) Planting
Mate

day

2.500

232.16

580.40

L-12

Mazdoor

day

25.000

221.61

5540.25

L-13

ii) For Maintenance for one year

b)

c)

Mate

day

5.000

232.16

1160.80

L-12

Mazdoor

day

50.000

221.61

11080.50

L-13

Dozer 80 HP @ 1000 sqm/hour

hour

10.000

2028.78

20287.80

P&M-015

Water tanker6 KL capacity (for planting)

hour

3.000

111.24

333.72

P&M-060

Water tanker6 KL capacity (for maintenance)

hour

25.000

111.24

2781.00

P&M-060

Sapling 1 to 1.5 m high 2 cm dia stem

each

290.000

14.03

4069.78

M-160 x 0.8

Add 10 per cent of sapling

each

29.000

14.03

406.98

M-160 x 0.8

Decayed farm yard/sludge manure (planting)

cum

60.900

528.65

32194.79

M-167

Decayed farm yard/sludge manure (maintenance)

cum

4.000

528.65

2114.60

M-167

Pesticides for planting

kg

0.500

56.39

28.19

M-136

Pesticides for maintenance

kg

1.500

56.39

84.58

M-136

Cost of water

KL

18.000

167.07

3007.23

M-189

Machinery

Material

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

8367.06
9203.77

Rate per hectare = a+b+c+d+e

101241.44
say

Note

Cost of fencing to be provided as per size of plot and


approved design, measured and paid separately

179

101241.00

CHAPTER-12

FOUNDATIONS
Sr No
12.1

Ref. to
MoRTH
Spec.
304

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Excavation for Structures


Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom and
backfilling with approved material.
Ordinary soil
Unit = cum
Taking output = 10 cum

A
(i)

Manual Means
Depth upto 3 m
a) Labour
Mate
Mazdoor
b) Overhead charges @ 0.25 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10

day

0.14

232.16

32.50

L-12

day

3.50

221.61

775.64

L-13

202.03
101.02
1111.19
111.12

say

Note

12.1 (I) A

(ii)

1. Cost of dewatering may be added where required upto, 10


percent of labour cost assessment for dewatering shall be
made as per site conditions.
2.The excavated earth can be used partially for backfilling of
foundation pit and partly for road work except for marshy soil.
Hence cost of disposal has not been added except for marshy
soil. This remark is common to all cases of item 12.1
excluding marshy soil.
3.The cost of shoring and shuttering, where needed, may be
added @ 1 per cent on cost of excavation for open
foundation.
Depth 3 m to 6 m
a) Labour
Mate/Supervisor
Mazdoor
b) Overhead charges @ 0.25 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10

day

0.18

232.16

41.79

L-12

day

4.50

221.61

997.25

L-13

259.76
129.88
1428.67
142.87

say

Note

12.1 (I) A

(iii)

Cost of dewatering may be added where required upto 15 per


cent of labour cost. Assessment for dewatering shall be done
as per actual ground conditions.
Depth above 6 m
a) Labour
Mate/Supervisor
Mazdoor
b) Overhead charges @ 0.25 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10

12.1 (I)

B
(i)

1. Cost of dewatering may be added where required upto 20


per cent of labour cost. Assessment for dewatering shall be
made as per site conditions..
Mechanical Means
Depth upto 3 m
Unit = cum
Taking output = 240 cum
a) Labour
Mate
Mazdoor
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity
c) Overhead charges @ 0.25 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
180

143.00

day

0.24

232.16

55.72

L-12

day

6.00

221.61

1329.66

L-13

346.34
173.17
1904.90
190.49

say

Note

111.00

190.00

day

0.32

232.16

74.29

L-12

day

8.00

221.61

1772.88

L-13

hour

6.00

1516.32

9097.92

P&M-026

2736.27
1368.14

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

62.71

say

12.1 (I) B

(ii)

Depth 3 m to 6 m

Hydraulic excavator 1.0 cum bucket capacity


c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

day

0.32

232.16

74.29

L-12

day

8.00

221.61

1772.88

L-13

hour

6.00

1516.32

9097.92

P&M-026

2736.27
1368.14
15049.50

Cost for 210 cum = a+b+c+d

71.66

Rate per cum = (a+b+c+d)/210


say

12.1 (I) B

(iii)

63.00

Cost of dewatering upto 5 per cent of (a+b) may be added,


where required. Assessment for dewatering shall be made as
per site conditions..
Unit = cum
Taking output = 210 cum
a) Labour
Mate
Mazdoor
b) Machinery

Note

Remarks/
Input ref.

15049.50

Cost for 240 cum = a+b+c+d


Rate per cum = (a+b+c+d)/240
Note

Cost Rs

72.00

Cost of dewatering upto 7.5 per cent of (a+b) may be


added, where required. Assessment for dewatering shall be
made as per site conditions..

Depth above 6m
Unit = cum
Taking output = 180 cum
a)

b)

Labour
Mate

day

0.40

232.16

92.86

L-12

Mazdoor

day

10.00

221.61

2216.10

L-13

hour

6.00

1516.32

9097.92

P&M-026

Machinery
Hydraulic excavator 1.0 cum bucket capacity

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2851.72
1425.86
15684.47

Cost for 180 cum = a+b+c+d

87.14

Rate per cum = (a+b+c+d)/180


say

Note

12.1

1. Cost of dewatering upto 10 per cent of (a+b) may be


added, where required. Assessment for dewatering shall be
made as per site conditions.
2.Labour provided for excavation by mechanical means
includes that required for trimming of bottom and side slopes.

II

Ordinary Rock (not requiring blasting)

Manual Means

(i)

87.00

Depth upto 3 m
Unit = cum
Taking output = 10 cum
a)

Labour
Mate

day

0.20

232.16

46.43

L-12

Mazdoor

day

5.00

221.61

1108.05

L-13

b)

Overhead charges @ 0.25 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

288.62
144.31
1587.41

Cost for 10 cum = a+b+c

158.74

Rate per cum = (a+b+c)/10


say

Note

12.1(II)

Cost of dewatering upto 10 per cent of labour cost may be


added, where required. Assessment for dewatering shall be
made as per site conditions.
Mechanical Means
Unit = cum
Taking output = 180 cum
a)

Labour
181

159.00

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Quantity

Rate Rs

day

0.24

232.16

55.72

L-12

Mazdoor

day

6.00

221.61

1329.66

L-13

hour

6.00

1516.32

9097.92

P&M-026

Machinery

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2620.82
1310.41
14414.54

Cost for 180 cum = a+b+c+d

80.08

Rate per cum = (a+b+c+d)/180

12.1

III
A

Remarks/
Input ref.

Mate

Hydraulic excavator 1.0 cum bucket capacity

Note

Cost Rs

say

80.00

1.Cost of dewatering upto 10 per cent of (a+b), may be


added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond 3 m is not dug and
hence not included.
Hard Rock ( requiring blasting )
Manual Means
Unit = cum
Taking output = 10 cum
a)

b)

Labour
Mate

day

0.35

232.16

81.26

L-12

Driller

day

0.50

232.16

116.08

L-06

Blaster

day

0.25

306.03

76.51

L-03

Mazdoor

day

8.00

221.61

1772.88

L-13

hour

1.00

293.76

293.76

P&M-001

Machinery
Air Compressor 250 cfm with 2 jack hammer for drilling.

c)

Material
Blasting Material

kg

3.50

112.77

394.70

M-104

Detonator electric

each

14.00

14.27

199.73

M-094/100

d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

733.73
366.86
4035.50

Cost for 10 cum = a+b+c+d+e

403.55

Rate per cum = (a+b+c+d+e)/10


say

Note

12.1

IV

404.00

Cost of dewatering @ 10 percent of (a+b) may be added,


where required. Assessment for dewatering shall be made as
per site conditions.
Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 10 cum

Mechanical Means
a)

Labour
Mate

day

0.20

232.16

46.43

L-12

Mazdoor

day

5.00

221.61

1108.05

L-13

hour

6.00

293.76

1762.56

P&M-001

b)

Machinery

c)

Air Compressor 250 cfm with 2 leads of pneumatic


breaker
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

729.26
364.63
4010.93

Cost for 10 cum = a+b+c+d

401.09

Rate per cum = (a+b+c+d)/10


say

Note

12.1

1. Cost of dewatering upto10 per cent of (a+b), may be


added, where required. Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and hence
not included.

Marshy Soil
Unit = cum

182

401.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output = 10 cum


Depth upto 3 m
A

Manual means
a)

b)

Labour
Mate/Supervisor

day

0.40

232.16

92.86

L-12

Mazdoor

day

10.00

221.61

2216.10

L-13

hour

2.67

171.02

456.62

P&M-053

Machinery
Tractor-trolley for removal.

c)

Overhead charges @ 0.25 on (a+b)

691.40

d)

Contractor's profit @ 0.1 on (a+b+c)

345.70
3802.68

Cost for 10 cum = a+b+c+d

380.27

Rate per cum = ( a+b+c+d)/ 10


say

Note

380.00

1. Cost of dewatering @ 30 per cent of (a), may be added,


where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 15 per cent of (a), where required may
be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item12.1-IA (ii) to (iii) for ordinary soil

12.1 (V)

Mechanical Means
a)

b)

Labour
Mate

day

0.08

232.16

18.57

L-12

Mazdoor for dressing sides, bottom and backfilling

day

2.00

221.61

443.22

L-13

hour

0.17

1516.32

257.77

P&M-026

hour

0.45

830.00

373.50

P&M-048

Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 cum
per hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

273.27
136.63
1502.97

Cost for 10 cum = a+b+c+d

150.30

Rate per cum = (a+b+c+d)/10


say

Note

VI

150.00

1. Cost of dewatering @ 20 percent of (a+b) may be added,


where required
2. Shoring & strutting @ 10 percent of (a+b), where required
may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item 12.1-IB (ii) to (iii) for ordinary soil
Back Filling in Marshy Foundation Pits
Unit : Cum
Taking Output : 6 cum
a)

b)

Labour
Mate

day

0.12

232.16

27.86

L-12

Mazdoor for dressing sides, bottom and backfilling

day

3.00

221.61

664.83

L-13

hour

2.00

171.02

342.04

P&M-053

Machinery
Tractor-trolley for transportation

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

258.68
129.34
1422.75

Cost for 6 cum = a+b+c+d

237.12

Rate per cum = (a+b+c+d)/6


say

12.2

304

237.00

Filling Annular Space Around Footing in Rock


Unit = cum
Taking out put = 1 cum
Lean cement concrete 1:3:6 nominal mix. Rate may be taken
as per item 12.4.
183

VALUE

Sr No
12.3

Ref. to
MoRTH
Spec.
304

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Sand Filling in Foundation Trenches as per Drawing &


Technical Specification
Unit = cum
Taking output = 1 cum
a)

b)

Labour
Mate

day

0.01

232.16

2.32

L-12

Mazdoor

day

0.30

221.61

66.48

L-13

cum

1.20

120.42

144.50

M-006

Material
Sand (assuming 20 per cent voids)

c)

Overhead charges @ 0.25 on (a+b)

53.33

d)

Contractor's profit @ 0.1 on (a+b+c)

26.66
293.30

Rate per cum = a+b+c+d


12.4

2100

say

293.00

232.16

148.58

L-12

PCC 1:3:6 in Foundation


Plain cement concrete 1:3:6 nominal mix in foundation with
crushed stone aggregate 40 mm nominal size mechanically
mixed, placed in foundation and compacted by vibration
including curing for 14 days.
Unit = cum
Taking output = 15 cum
a)

b)

Labour
day

Mason

day

1.00

353.52

353.52

L-11

Mazdoor

day

15.00

221.61

3324.15

L-13

40 mm Aggregate

cum

13.50

830.30

11209.05

M-055

coarse Sand

cum

6.75

219.18

1479.47

M-005

tonne

3.45

5210.53

17976.32

M-081

KL

18.00

167.07

3007.23

M-189

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Water tanker 6 KL capacity

hour

2.00

111.24

222.48

P&M-060

Material

cement
Cost of water
c)

0.64

Mate

Machinery

d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

10261.26
5130.63
56436.92

Cost for 15 cum = a+b+c+d+e

3762.46

Rate per cum = (a+b+c+d+e)/15


Note
12.5

1300

say

3762.00

Vibrator is a part of minor T & P which is already included in


overhead charges of the contractor.
Brick Masonry Work in Cement Mortar 1:3 in Foundation
complete excluding Pointing and Plastering, as per
Drawing and Technical Specifications.
Unit = cum
Taking output = 5 cum
a)

b)

Material
Bricks Ist class

each

2500.00

4.92

12302.11

M-079

Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis)

cum

1.20

3096.00

3715.20

Item 12.6
(A)

Mate

day

0.48

232.16

111.44

L-12

Mason

day

4.00

353.52

1414.08

L-11

Mazdoor

day

8.00

221.61

1772.88

L-13

Labour

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

4828.93
2414.46
26559.10

Cost for 5 cum = a+b+c+d

5311.82

Rate per cum (a+b+c+d)/5


say

184

5312.00

Sr No

12.6

Ref. to
MoRTH
Spec.

Subanalysis

Description

Unit

Quantity

Rate Rs

Cost Rs

(i)

Rate for Brick Work in C. M. 1:2 in foundation

5582.00

(ii)

Rate for Brick Work in C. M. 1:3 in foundation

5312.00

(iii)

Rate for Brick Work in C. M. 1:4 in foundation

5128.00

(iv)

Rate for Brick Work in C. M. 1:6 in foundation

4951.00

(A)

Cement Mortar 1:3 (1 cement : 3 sand)

Remarks/
Input ref.

Unit = 1 cum
Taking output = 1 cum
a)

Materials
tonne

0.51

5210.53

2657.37

M-081

cum

1.05

219.18

230.14

M-005

Mate

day

0.04

232.16

9.29

L-12

Mazdoor

day

0.90

221.61

199.45

L-13

say

3096.00

Cement
Sand
b)

Labour

Total Material and Labour = (a+b)


Subanalysis
(Addl.)

(B)

Cement Mortar1:2 (1cement :2 sand)

Unit = 1 cum
Taking output = 1 cum
a)

Materials
tonne

0.672

5210.53

3501.47

M-081

cum

0.933

219.18

204.57

M-005

Mate

day

0.04

232.16

9.29

L-12

Mazdoor

day

0.90

221.61

199.45

L-13

say

3915.00

Cement
Sand
b)

Labour

Total Material and Labour = (a+b)


Subanalysis
(Addl.)

(C)

Cement Mortar1:4 (1cement :4 sand)

Unit = 1 cum
Taking output = 1 cum
a)

Materials
tonne

0.40

5210.53

2084.21

M-081

cum

1.12

219.18

245.48

M-005

Mate

day

0.04

232.16

9.29

L-12

Mazdoor

day

0.90

221.61

199.45

L-13

say

2538.00

Cement
Sand
b)

Labour

Total Material and Labour = (a+b)


Subanalysis
(Addl.)

(D)

Cement Mortar1:6 (1cement :6 sand)

Unit = 1 cum
Taking output = 1 cum
a)

Materials
tonne

0.288

5210.53

1500.63

M-081

cum

1.337

219.18

293.07

M-005

Mate

day

0.04

232.16

9.29

L-12

Mazdoor

day

0.90

221.61

199.45

L-13

say

2002.00

360.24

1981.32

Cement
Sand
b)

Labour

Total Material and Labour = (a+b)


12.7

1400

Stone Masonry Work in Cement Mortar 1:3 in Foundation


complete as per Drawing and Technical Specifications.
Unit = cum
Taking output = 5 cum

1405.4

(A)

Square Rubble Coursed Rubble Masonry (first sort)


a)

Material
cum

Stone

185

5.50

M-169

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

each

35.00

6.06

211.97

M-182

cum

1.50

3096.00

4644.00

Item 12.6
(A)

Mate

day

0.66

232.16

153.23

L-12

Mason

day

7.50

353.52

2651.40

L-11

Mazdoor

day

9.00

221.61

1994.49

L-13

Through and bond stone


(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis)
b)

Labour

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2909.10
1454.55
16000.06

Cost for 5 cum = a+b+c+d

3200.01

Rate per cum (a+b+c+d)/5


1405.3

(B)

say

3200.00

Random Rubble Masonry


( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a)

Material
Stone

cum

5.50

359.72

1978.45

M-148

Through and bond stone

each

35.00

6.06

211.97

M-182

cum

1.55

3096.00

4798.80

Item 12.6
(A)

Mate

day

0.62

232.16

143.94

L-12

Mason

day

6.00

353.52

2121.12

L-11

Mazdoor

day

9.00

221.61

1994.49

L-13

(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)


Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis)
b)

Labour

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2812.19
1406.10
15467.06

Cost for 5 cum = a+b+c+d

3093.41

Rate per cum (a+b+c+d)/5


Note

12.8

1500,
1700 &
2100

say

3093.00

The labour already considered in cement mortar has been


taken into account while proposing labour for masonry works.
Plain/Reinforced Cement Concrete in Open Foundation
complete as per Drawing and Technical Specifications.

PCC Grade M15


Unit = cum
Taking output = 15 cum
a)

Material
tonne

4.13

5210.53

21519.47

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

40 mm Aggregate

cum

8.10

830.30

6725.43

M-055

20 mm Aggregate

cum

4.05

938.92

3802.63

M-053

10 mm Aggregate

cum

1.35

723.14

976.24

M-051

Mate

day

0.86

232.16

199.66

L-12

Mason

day

1.50

353.52

530.28

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 63 KVA

hour

6.00

361.80

2170.80

P&M-019

Cement

b)

c)

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost of
material, labour and machinery

186

2874.00
1724.25

Sr No

Ref. to
MoRTH
Spec.

Description
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Unit

Quantity

Rate Rs

5603.81
61641.94
4109.46

Rate per cum = (a+b+c+d+e+f)/15

12.8

Remarks/
Input ref.

11207.63

Cost for 15 cum = a+b+c+d+e+f

Note

Cost Rs

say

4109.00

Needle Vibrator is an item of minor T & P which is already


included in overhead charges. Hence not added in rate
analysis of cement concrete works.
PCC Grade M20
Unit : cum
Taking output = 15 cum
a)

Material
tonne

5.16

5210.53

26886.32

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

40 mm Aggregate

cum

5.40

830.30

4483.62

M-055

20 mm Aggregate

cum

5.40

938.92

5070.17

M-053

10 mm Aggregate

cum

2.70

723.14

1952.48

M-051

Mate

day

0.86

232.16

199.66

L-12

Mason

day

1.50

353.52

530.28

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

Machinery

3224.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost of
material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)
f)

1934.34
12573.19
6286.60

Contractor's profit @ 0.1 on (a+b+c+d+e)

69152.55

Cost for 15 cum = a+b+c+d+e+f

4610.17

Rate per cum = (a+b+c+d+e+f)/15


12.8

C
Case I

say

4610.00

RCC Grade M20


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

5.21

5210.53

27146.84

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

20 mm Aggregate

cum

8.10

938.92

7605.25

M-053

10 mm Aggregate

cum

5.40

723.14

3904.96

M-051

Mate

day

0.86

232.16

199.66

L-12

Mason

day

1.50

353.52

530.28

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

Machinery

d)

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Formwork @ 4 per cent on (a+b+c)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3242.00
1944.92
12641.95
6320.98
69530.74

Cost for 15 cum = a+b+c+d+e+f

4635.38

Rate per cum = ( a+b+c+d+e+f )/15


say

12.8 C

Case II With Batching Plant, Transit Mixer and Concrete Pump

187

4635.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Unit : cum
Taking Output = 120 cum
a) Material
tonne

41.66

5210.53

217070.53

M-081

Coarse Sand

cum

54.00

219.18

11835.72

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

10 mm Aggregate

cum

43.20

723.14

31239.65

M-051

day

0.84

232.16

195.01

L-12

Mason

day

3.00

353.52

1060.56

L-11

Mazdoor

day

18.00

221.61

3988.98

L-13

Cement

b)

Labour
Mate

c)

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2598.00

15588.00

P&M-002

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader 1 cum capacity

hour

6.00

1116.00

6696.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

234.36

Lead beyond 1 km, L-lead in km

hour

Concrete Pump

3114.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost of
material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)
f)

14945.47
97145.59
48572.79

Contractor's profit @ 0.1 on (a+b+c+d+e)

534300.73

Cost for 120 cum = a+b+c+d+e+f

4452.51

Rate per cum = ( a+b+c+d+e+f )/120


12.8

D
Case I

P&M-050
Lead= 1 km
1406.16
P&M-007

say

4453.00

PCC Grade M25


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

5.99

5210.53

31211.05

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

40 mm Aggregate

cum

5.40

830.30

4483.62

M-055

20 mm Aggregate

cum

5.40

938.92

5070.17

M-053

10 mm Aggregate

cum

2.70

723.14

1952.48

M-051

Mate

day

0.86

232.16

199.66

L-12

Mason

day

1.50

353.52

530.28

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

Machinery

3513.00

d)

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Formwork @ 3.75 per cent of (a+b+c)

e)

Overhead charges @ 0.25 on (a+b+c+d)

13664.69

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

6832.35

1975.62

75155.82

Cost for 15 cum = a+b+c+d+e+f

5010.39

Rate per cum = ( a+b+c+d+e+f )/15


12.8 D

say

5010.00

5210.53

249844.74

Case II With Batching Plant, Transit Mixer and Concrete Pump


Unit : cum
Taking Output = 120 cum
a)

Material
tonne

Cement
188

47.95

M-081

Sr No

Ref. to
MoRTH
Spec.

Description

b)

c)

Unit

Rate Rs

cum

54.00

219.18

11835.72

M-004

cum

43.20

830.30

35868.96

M-055

20 mm Aggregate

cum

43.20

938.92

40561.34

M-053

10 mm Aggregate

cum

21.60

723.14

15619.82

M-051

Mate

day

0.84

232.16

195.01

L-12

Mason

day

3.00

353.52

1060.56

L-11

Mazdoor

day

18.00

221.61

3988.98

L-13

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2598.00

15588.00

P&M-002

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader 1 cum capacity

hour

6.00

1116.00

6696.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

P&M-050
Lead= 1 km

234.36

1406.16

P&M-007

hour

Concrete Pump

3387.00
15239.23
105404.70
52702.35

Contractor's profit @ 0.1 on (a+b+c+d+e)

579725.83

cost of 120 cum = a+b+c+d+e+f

4831.05

Rate per cum = (a+b+c+d+e+f)/120


E
Case I

Remarks/
Input ref.

40 mm Aggregate

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.75 per cent of cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)

12.8

Cost Rs

Coarse sand

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead


in Kilometer

f)

Quantity

say

4831.00

RCC Grade M25


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

6.05

5210.53

31523.68

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

20 mm Aggregate

cum

8.10

938.92

7605.25

M-053

10 mm Aggregate

cum

5.40

723.14

3904.96

M-051

Mate

day

0.86

232.16

199.66

L-12

Mason

day

1.50

353.52

530.28

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

Machinery

3534.00

d)

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Formwork @ 3.75 per cent of a+b+c.

e)

Overhead charges @ 0.25 on (a+b+c+d)

13746.81

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

6873.40

1987.49

75607.43

cost of 15 cum = a+b+c+d+e+f

5040.50

Rate per cum (a+b+c+d+e+f )/15


12.8 E

say

5040.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


Unit: cum
Taking Output = 120 cum
a)

Material
tonne

48.38

5210.53

252085.26

M-081

Coarse sand

cum

54.00

219.18

11835.72

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

10 mm Aggregate

cum

43.20

723.14

31239.65

M-051

Cement

189

Sr No

Ref. to
MoRTH
Spec.

Description
b)

c)

Unit

Rate Rs

day

0.84

232.16

195.01

L-12

Mason

day

3.00

353.52

1060.56

L-11

Mazdoor

day

18.00

221.61

3988.98

L-13

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2598.00

15588.00

P&M-002

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader 1 cum capacity 1 cum

hour

6.00

1116.00

6696.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

P&M-050
Lead= 1 km

6.00

234.36

1406.16

P&M-007

hour

Concrete Pump

3406.00
15324.44
105994.01
52997.01

Contractor's profit @ 0.1 on (a+b+c+d+e)

582967.06

cost of 120 cum = a+b+c+d+e+f

4858.06

Rate per cum (a+b+c+d+e+f )/120


F
Case I

Remarks/
Input ref.

Labour

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d)
Formwork @ 3.75 per cent on cost of concrete i.e.
cost of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)

12.8

Cost Rs

Mate

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead


in Kilometer

f)

Quantity

say

4858.00

PCC Grade M30


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

6.08

5210.53

31680.00

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

40 mm Aggregate

cum

5.40

830.30

4483.62

M-055

20 mm Aggregate

cum

5.40

938.92

5070.17

M-053

10 mm Aggregate

cum

2.70

723.14

1952.48

M-051

Mate

day

0.86

232.16

199.66

L-12

Mason

day

1.50

353.52

530.28

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

Machinery

3544.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)
f)

1860.32
13753.11
6876.55

Contractor's profit @ 0.1 on (a+b+c+d+e)

75642.09

cost of 15 cum = a+b+c+d+e+f

5042.81

Rate per cum (a+b+c+d+e+f )/15


12.8 F

say

5043.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit : cum
Taking Output = 120 cum
a)

Material
tonne

48.60

5210.53

253231.58

M-081

Coarse sand

cum

54.00

219.18

11835.72

M-004

40 mm Aggregate

cum

43.20

830.30

35868.96

M-055

20 mm Aggregate

cum

43.20

938.92

40561.34

M-053

10 mm Aggregate

cum

21.60

723.14

15619.82

M-051

day

0.84

232.16

195.01

Cement

b)

Labour
Mate
190

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Unit

Rate Rs

day

3.00

353.52

1060.56

L-11

day

18.00

221.61

3988.98

L-13

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2598.00

15588.00

P&M-002

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader 1 cum capacity

hour

6.00

1116.00

6696.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

P&M-050
Lead= 1 km

hour

6.00

234.36

1406.16

P&M-007

3415.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)

14341.82
106027.05
53013.53

Contractor's profit @ 0.1 on (a+b+c+d+e)

583148.80

cost of 120 cum = a+b+c+d+e+f

4859.57

Rate per cum (a+b+c+d+e+f )/120


G
Case I

Remarks/
Input ref.

Mazdoor

Concrete Pump

12.8

Cost Rs

Mason

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead


in Kilometer

f)

Quantity

say

4860.00

RCC Grade M30


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

6.10

5210.53

31784.21

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

20 mm Aggregate

cum

8.10

938.92

7605.25

M-053

10 mm Aggregate

cum

5.40

723.14

3904.96

M-051

Mate

day

0.86

232.16

199.66

L-12

Mason

day

1.50

353.52

530.28

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

Machinery

3551.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.5 per cent on cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)
f)

1864.11
13781.09
6890.55

Contractor's profit @ 0.1 on (a+b+c+d+e)

75796.01

cost of 15 cum = a+b+c+d+e+f

5053.07

Rate per cum = (a+b+c+d+e+f)/15


12.8 G

say

5053.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

Material
tonne

48.80

5210.53

254273.68

M-081

Coarse sand

cum

54.00

219.18

11835.72

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

10 mm Aggregate

cum

43.20

723.14

31239.65

M-051

Mate

day

0.84

232.16

195.01

L-12

Mason

day

3.00

353.52

1060.56

L-11

Mazdoor

day

18.00

221.61

3988.98

L-13

2598.00

15588.00

P&M-002

Cement

b)

c)

Labour

Machinery
hour

Batching Plant @ 20 cum/hour


191

6.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

1600.00

9600.00

P&M-080

hour

6.00

1116.00

6696.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

P&M-050
Lead= 1 km

6.00

234.36

1406.16

P&M-007

hour

3424.00
14379.40
106304.86
53152.43

Contractor's profit @ 0.1 on (a+b+c+d+e)

584676.72

cost of 120 cum = a+b+c+d+e+f

4872.31

Rate per cum (a+b+c+d+e+f )/120


H
Case I

Remarks/
Input ref.

hour

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.5 per cent of cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)

12.8

Cost Rs

Loader 1 cum capacity

Concrete Pump

6.00

Rate Rs

Generator 100 KVA

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead


in Kilometer

f)

Quantity

say

4872.00

RCC Grade M35


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

6.33

5210.53

32982.63

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

20 mm Aggregate

cum

8.10

938.92

7605.25

M-053

10 mm Aggregate

cum

5.40

723.14

3904.96

M-051

Mate

day

0.86

232.16

199.66

L-12

Mason

day

1.50

353.52

530.28

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

Machinery

d)

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Formwork @ 3 per cent on a+b+c

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3631.00
1633.76
14023.11
7011.56
77127.11

cost of 15 cum = a+b+c+d+e+f

5141.81

Rate per cum = (a+b+c+d+e+f)/15


12.8 H

say

5142.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit ; cum
Taking Output = 120 cum
a)

Material
tonne

50.64

5210.53

263861.05

M-081

Coarse sand

cum

54.00

219.18

11835.72

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

10 mm Aggregate

cum

43.20

723.14

31239.65

M-051

Mate

day

0.84

232.16

195.01

L-12

Mason

day

3.00

353.52

1060.56

L-11

Mazdoor

day

18.00

221.61

3988.98

L-13

Cement

b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2598.00

15588.00

P&M-002

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader1 cum capacity

hour

6.00

1116.00

6696.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

854.55

12818.25

P&M-049

192

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead


in Kilometer

tonne.km

hour

Concrete Pump

Rate Rs

Remarks/
Input ref.

300L

4.32

1296.00

P&M-050
Lead= 1 km

6.00

234.36

1406.16

P&M-007

12612.82
108260.06
54130.03

Contractor's profit @ 0.1 on (a+b+c+d+e)

595430.31

cost of 120 cum = a+b+c+d+e+f

4961.92

Rate per cum = (a+b+c+d+e+f)/120


say

Note:

Cost Rs

3504.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3 per cent on cost of concrete i.e. cost of
material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)
f)

Quantity

4962.00

Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.

WELL FOUNDATION
12.9

1200

Providing and Constructing Temporary Island 16 m


diameter for Construction of Well Foundation for 8m dia.
Well.
Assuming depth of water 1.0 m and height of island to be
1.25 m including Royality for earth @ Rs. 3768.00 for each
Island.
Unit = 1 No
Taking output = 1 No.
a)

b)

c)

Material
Earth (compacted)

cum

251.20

25.1

6305.12

M-092

Sand bags

each

750.00

1.73

1298.57

M-159

Labour
Mate

day

0.40

232.16

92.86

L-12

Mazdoor for filling sand bags, stitching and placing

day

15.00

221.61

3324.15

L-13

hour

20.00

784.62

15692.40

P&M-012

Machinery
Crane with grab 1 cum capacity

392.31

Consumables @ 2.5 per cent of (c) above


d)

Overhead charges @ 0.25 on (a+b+c)

6776.35

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3388.18
37269.95

Rate per No. (a+b+c+d+e)


say

Note
12.9

37270.00

It is assumed that earth will be available within the working


space of crane with grab bucket.
Assuming depth of water 4.0 m and height of island 4.5 m
including Royality for earth @ Rs. 13565.00 for each
Island.
Unit = 1No
Taking output = 1 No
a)

b)

c)

Material
Earth (compacted)

cum

904.32

25.10

22698.43

M-092

Sand bags

each

6000.00

1.73

10388.57

M-159

Wooden ballies 8" Dia and 9 m long

each

95.00

49.23

4676.82

M-194

Wooden ballies 2" Dia for bracing

metre

190.00

17.81

3383.23

M-193

Labour
Mate

day

5.60

232.16

1300.10

L-12

Mazdoor for piling 8" dia ballies for piling 8" dia ballies

day

18.00

221.61

3988.98

L-13

Mazdoor for bracing with 2" dia ballies

day

12.00

221.61

2659.32

L-13

Mazdoor for filling sand bags, stitching and placing

day

110.00

221.61

24377.10

L-13

hour

50.00

784.62

39231.00

P&M-012

Machinery
Crane with grab 1 cum capacity

2817.59

Consumables and other arrangements for piling ballies @ 2.5


per cent of (a+b+c).
d) Overhead charges @ 0.25 on (a+b+c)

28880.29

e)

14440.14

Contractor's profit @ 0.1 on (a+b+c+d)


193

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

12.9

Remarks/
Input ref.

158841.58

Rate per No. (a+b+c+d+e)


Note

Cost Rs

say

158842.00

For other well diameters rate can be worked out on the basis
of cross-sectional area of well. The diameter of the island
shall be in the conformity with clause 1203.2 of MoRTH
specifications.
Providing and constructing one span service road to
reach island location from one pier location to another
pier location including Royality for earth @ Rs. 225.00 per
m for service Road.
Assuming span length 30 m, width of service road 10m and
depth of water 1m
Unit = 1 meter
Taking output = 30 metre
a)

b)

c)

Material
Earth

cum

450.00

25.10

11295.00

M-092

Sand bags

each

300.00

1.73

519.43

M-159

Mate

day

0.24

232.16

55.72

L-12

Mazdoor for filling sand bags, stitching and placing

day

6.00

221.61

1329.66

L-13

Front end Loader 1 cum capacity

hour

27.00

1116.00

30132.00

P&M-017

Tipper 5.5 cum capacity

hour

28.00

830.00

23240.00

P&M-048

Labour

Machinery

d)

Overhead charges @ 0.25 on (a+b+c)

16642.95

e)

Contractor's profit @ 0.1 on (a+b+c+d)

8321.48
91536.23

Cost for 30 m (a+b+c+d+e)

3051.21

Rate per m (a+b+c+d+e)/30


12.10

1200 &
1900

say

3051.00

Providing and Laying Cutting Edge of Mild Steel weighing


40 kg per metre for Well Foundation complete as per
Drawing and Technical Specification.
Unit = 1 MT
Taking output = 1 MT
a)

Material
tonne

1.05

37995.24

39895.00

M-179

Kg

20.00

45.42

908.43

M-130

day

1.32

232.16

306.45

L-12

Fitter

day

5.50

306.03

1683.17

L-08

Blacksmith

day

5.50

353.52

1944.36

L-02

Welder

day

5.50

353.52

1944.36

L-02

Mazdoor

day

16.50

221.61

3656.57

L-13

Structural steel in plates, angles, etc including 5 per


cent wastage
Nuts & bolts
b)

Labour

(for cutting, bending, making holes, joining, welding and


erecting in position)
Mate

4080.34

Electrodes, cutting gas and other consumables @ 10 per cent


of cost of (a) above
c) Overhead charges @ 0.25 on (a+b)
d)

13604.67
6802.33

Contractor's profit @ 0.1 on (a+b+c)

74825.68

Rate per MT (a+b+c+d)


say

12.11

1200,
1500 &
1700

Plain/Reinforced Cement Concrete, in Well Foundation


complete as per Drawing and Technical Specification.
Unit = 1 cum
Taking output = 1 cum
A

Well curb

(i)

RCC M20 Grade


Same as for 12.8 (C) except for formwork which shall be@ 20
per cent of the cost of concrete instead of 4 per cent.

194

74826.00

Sr No

Ref. to
MoRTH
Spec.

Description
Case I

Unit

Quantity

Rate Rs

3242.00 Item 12.8


(C)

d)

formwork @ 20 per cent of the cost of concrete

648.40

e)

Overhead charges @ 0.25 on (a+b+c+d)

972.60

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

486.30
5349.30

Rate perm (a+b+c+d+e+f)


say

3113.00 Item 12.8


(C)

formwork @ 20 per cent of the cost of concrete

622.60

e)

Overhead charges @ 0.25 on (a+b+c+d)

933.90

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

d)

466.95
5136.45

Rate perm (a+b+c+d+e+f)


say

(ii)

Case I

RCC M25 Grade

3534.00 Item 12.8


(E)

d)

formwork @ 20 per cent of the cost of concrete

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

706.80
1060.20
530.10
5831.10

Rate perm (a+b+c+d+e+f)


say

3406.00 Item 12.8


(E)

d)

formwork @ 20 per cent of the cost of concrete

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

681.20

510.90
5619.90

say

(iii)

Case I

DIR used
item

1021.80

Rate perm (a+b+c+d+e+f)

5620.00

RCC M35 Grade


Same as for 12.8 (H) except for formwork which shall be@ 20
per cent of the cost of concrete instead of 3.0 per cent.
Using Concrete Mixer
3631.00 Item 12.8
(H) Case I

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 20 per cent of the cost of concrete

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

726.20
1089.30
544.65
5991.15

Rate perm (a+b+c+d+e+f)


say

12.11 A
(iii)

5831.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

12.11 A

5136.00

Same as for 12.8 (E) except for formwork which shall be@ 20
per cent of the cost of concrete instead of 3.75 per cent.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

12.11 A
(ii)

5349.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

12.11 A

Remarks/
Input ref.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

12.11 A
(i)

Cost Rs

5991.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


3694.00 Item 12.8
(H)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 20 per cent of the cost of concrete

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

738.80
1108.20
554.10
6095.10

Rate perm (a+b+c+d+e+f)


say

Note.

If curb concrete is carried out within steel liner, cost of


formwork shall be excluded.

195

6095.00

DIR used
item

Sr No
12.11

Ref. to
MoRTH
Spec.

Description
B

Well steining

(I)

PCC M15 Grade

Case I

Unit

Quantity

Rate Rs

2874.00 Item 12.8


(A)

d)

formwork @ 10 per cent of the cost of concrete

287.40

e)

Overhead charges @ 0.25 on (a+b+c+d)

790.35

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

395.18
4346.93

Rate perm (a+b+c+d+e+f)


say

(ii)

Case I

PCC M20 Grade

3224.00 Item 12.8


(B) PCC

d)

formwork @ 10 per cent of the cost of concrete

322.40

e)

Overhead charges @ 0.25 on (a+b+c+d)

886.60

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

443.30
4876.30

Rate perm (a+b+c+d+e+f)


say

(iii)

4347.00

Same as for 12.8 (B) except for formwork which shall be @


10 per cent of the cost of concrete instead of 4 per cent.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

12.11 B

Remarks/
Input ref.

Same as for 12.8 (A) except for formwork which shall be @


10 per cent of the cost of concrete instead of 4 per cent.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

12.11 B

Cost Rs

4876.00

RCC M20 Grade


Same as for 12.8 (C) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Case I

Using Concrete Mixer


3242.00 Item 12.8
(C)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


formwork @ 10 per cent of the cost of concrete

324.20

e)

Overhead charges @ 0.25 on (a+b+c+d)

891.55

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

d)

445.78
4903.53

Rate perm (a+b+c+d+e+f)


say

12.11 B
(iii)

Case II With Batching Plant, Transit Mixer and Concrete Pump


3113.00 Item 12.8
(C)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 10 per cent of the cost of concrete

311.30

e)

Overhead charges @ 0.25 on (a+b+c+d)

856.08

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

428.04
4708.41

Rate perm (a+b+c+d+e+f)


say

12.11 B

(iv)

Case I

4708.00

PCC M25 Grade


Same as for 12.8 (D) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.
Using Concrete Mixer
3513.00 Item 12.8
(D)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 10 per cent of the cost of concrete

351.30

e)

Overhead charges @ 0.25 on (a+b+c+d)

966.08

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

483.04
5313.41

Rate perm (a+b+c+d+e+f)


say

12.11 B
(iv)

4904.00

5313.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

3386.00 Item 12.8


(D)

d)

formwork @ 10 per cent of the cost of concrete

338.60

e)

Overhead charges @ 0.25 on (a+b+c+d)

931.15

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

465.58

196

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

say

(v)

Case I

Same as for 12.8 (E) except for formwork which shall be @


10 per cent of the cost of concrete instead of 3.5 per cent.
Using Concrete Mixer
3534.00 Item 12.8
(E)

d)

formwork @ 10 per cent of the cost of concrete

353.40

e)

Overhead charges @ 0.25 on (a+b+c+d)

971.85

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

485.93
5345.18

Rate perm (a+b+c+d+e+f)


say

3406.00 Item 12.8


(E)

formwork @ 10 per cent of the cost of concrete

340.60

e)

Overhead charges @ 0.25 on (a+b+c+d)

936.65

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

d)

468.33

say

(vi)

Case I

PCC M30 Grade

3544.00 Item 12.8


(F)

d)

formwork @ 10 per cent of the cost of concrete

354.40

e)

Overhead charges @ 0.25 on (a+b+c+d)

974.60

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

487.30
5360.30

Rate perm (a+b+c+d+e+f)


say

5360.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


3414.00 Item 12.8
(F)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


formwork @ 10 per cent of the cost of concrete

341.40

e)

Overhead charges @ 0.25 on (a+b+c+d)

938.85

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

d)

469.43
5163.68

Rate perm (a+b+c+d+e+f)


say

(vii)

Case I

5164.00

RCC M30 Grade


Same as for 12.8 (G) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.
Using Concrete Mixer
3551.00 Item 12.8
(G)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 10 per cent of the cost of concrete

355.10

e)

Overhead charges @ 0.25 on (a+b+c+d)

976.53

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

488.26
5370.89

Rate perm (a+b+c+d+e+f)


say

12.11 B
(vii)

5152.00

Same as for 12.8 (F) except for formwork which shall be @


10 per cent of the cost of concrete instead of 3.5 per cent.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

'12.11 B

DIR used
item

5151.58

Rate perm (a+b+c+d+e+f)

12.11 B
(vi)

5345.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

'12.11 B

5121.00

RCC M25 Grade

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

12.11 B
(v)

Remarks/
Input ref.

5121.33

Rate perm (a+b+c+d+e+f)


'12.11 B

Cost Rs

5371.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

3424.00 Item 12.8


(G)

d)

formwork @ 10 per cent of the cost of concrete

342.40

e)

Overhead charges @ 0.25 on (a+b+c+d)

941.60

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

470.80
5178.80

Rate perm (a+b+c+d+e+f)


197

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

say

'12.11 B

(viii)

Case I

5179.00

Same as for 12.8 (H) except for formwork which shall be @


10 per cent of the cost of concrete instead of 3 per cent.
Using Concrete Mixer
3631.00 Item 12.8
(H) Case I

d)

formwork @ 10 per cent of the cost of concrete

363.10

e)

Overhead charges @ 0.25 on (a+b+c+d)

998.53

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

499.26
5491.89

Rate perm (a+b+c+d+e+f)


say

5492.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


3694.00 Item 12.8
(H)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

369.40

formwork @ 10 per cent of the cost of concrete

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

(ix)

DIR used
item

1015.85
507.93
5587.18

Rate perm (a+b+c+d+e+f)


'12.11 B

Remarks/
Input ref.

RCC M35 Grade

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

12.11 B
(viii)

Cost Rs

say

5587.00

RCC M40 Grade


Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a)

Material
tonne

51.60

5210.53

268863.16

M-081

Coarse Sand

cum

54.00

219.18

11835.72

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

10 mm Aggregate

cum

43.20

723.14

31239.65

M-051

kg

206.00

112.77

23230.84

M-180

Mate

day

0.84

232.16

195.01

L-12

Mason

day

3.00

353.52

1060.56

L-11

Mazdoor

day

18.00

221.61

3988.98

L-13

Cement

Admixture
b)

c)

Labour

Machinery
Batching Plant

hour

2598.00

15588.00

P&M-002

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader 1 cum capacity

hour

6.00

1116.00

6696.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

854.55

12818.25

P&M-049

4.32

1296.00

234.36

1406.16

Lead= 1 ,
P&M-050
P&M-007

Transit Mixer 4 cum capacity for lead beyond 1 km.

hour

Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
d) Formwork @ 10 per cent on cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)
f)

tonne.km

6.00

300xL
6.00

3739.00
44866.03
123381.59
61690.80

Contractor's profit @ 0.1 on (a+b+c+d+e)

678598.77

cost of 120 cum = a+b+c+d+e+f

5654.99

Rate per cum = (a+b+c+d+e+f)/120


say

12.11 C

Bottom Plug
Concrete to be placed using tremie pipe

(i)
Case I

Note: 10% extra cement to be added where under water


concreting is involved
PCC Grade M20
Using Concrete Mixer
Unit = cum

198

5655.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output = 15 cum


a)

Material
tonne

5.55

5210.53

28918.42

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

40 mm Aggregate

cum

5.40

830.30

4483.62

M-055

20 mm Aggregate

cum

5.40

938.92

5070.17

M-053

10 mm Aggregate

cum

2.70

723.14

1952.48

M-051

Kg

18.60

112.77

2097.54

M-180

Mate

day

0.90

232.16

208.94

L-12

Mason

day

1.50

353.52

530.28

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Light Crane 3 tonnes capacity for handling tremie pipe

hour

6.00

532.00

3192.00

P&M-013

Cement

Admixture
b)

c)

Labour

Machinery

3713.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2458.66

14537.00
7268.50
79953.52

cost of 15 cum = a+b+c+d+e

5330.23

Rate per cum = (a+b+c+d+e)/15


12.11 C
(i)

say

5330.00

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Unit ; cum
Taking Output = 120 cum
a)

Material
tonne

44.40

5210.53

231347.37

M-081

Coarse sand

cum

54.00

219.18

11835.72

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

10 mm Aggregate

cum

43.20

723.14

31239.65

M-051

Kg

148.80

112.77

16780.33

M-180

Mate

day

0.88

232.16

204.30

L-12

Mason

day

3.00

353.52

1060.56

L-11

Mazdoor

day

18.00

221.61

3988.98

L-13

Cement

Admixture
b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2598.00

15588.00

P&M-002

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader 1 cum capacity

hour

6.00

1116.00

6696.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

P&M-050
Lead= 1 km

6.00

234.36

1406.16

P&M-007

Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer

hour

Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c)
e)

3373.00
17864.95

105642.07
52821.04

Contractor's profit @ 0.1 on (a+b+c+d)

581031.39

cost of 120 cum = a+b+c+d+e

4841.93

Rate per cum = (a+b+c+d+e)/120


say

'12.11 C

(ii)

PCC Grade M25


199

4842.00

Sr No

Ref. to
MoRTH
Spec.

Description
Case I

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Using Concrete Mixer


Unit = cum
Taking output = 15 cum
a)

Material
tonne

5.99

5210.53

31211.05

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

40 mm Aggregate

cum

5.40

830.30

4483.62

M-055

20 mm Aggregate

cum

5.40

938.92

5070.17

M-053

10 mm Aggregate

cum

2.70

723.14

1952.48

M-051

Kg

21.60

112.77

2435.85

M-180

Mate

day

0.90

232.16

208.94

L-12

Mason

day

1.50

353.52

530.28

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

hour

6.00

532.00

3192.00

P&M-013

Cement

Admixture
b)

c)

Labour

Machinery

Light Crane of 3 tonnes capacity for handling tremie


pipe
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.

3889.00
2590.20

d)

Overhead charges @ 0.25 on (a+b+c)

15227.63

e)

Contractor's profit @ 0.1 on (a+b+c+d)

7613.81
83751.94

cost of 15 cum = a+b+c+d+e

5583.46

Rate per cum = (a+b+c+d+e)/15


12.11 C
(ii)

say

5583.00

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Unit = cum
Taking output = 120 cum
a)

Material
tonne

47.88

5210.53

249480.00

M-081

Coarse sand

cum

54.00

219.18

11835.72

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

10 mm Aggregate

cum

43.20

723.14

31239.65

M-051

Kg

172.80

112.77

19486.84

M-180

Mate

day

0.88

232.16

204.30

L-12

Mason

day

3.00

353.52

1060.56

L-11

Mazdoor

day

18.00

221.61

3988.98

L-13

Cement

Admixture
b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2598.00

15588.00

P&M-002

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader 1 cum capacity

hour

6.00

1116.00

6696.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

P&M-050
Lead= 1 km

hour

6.00

234.36

1406.16

P&M-007

Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer


Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c)
e)

3547.00
18906.90

111112.34
55556.17

Contractor's profit @ 0.1 on (a+b+c+d)

611117.89

cost of 120 cum = a+b+c+d+e

200

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

(iii)
Case I

Remarks/
Input ref.

5092.65

Rate per cum = (a+b+c+d+e)/120


'12.11 C

Cost Rs

say

5093.00

PCC Grade M30


Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a)

Material
tonne

6.08

5210.53

31680.00

M-081

cum

6.75

219.18

1479.47

M-005

40 mm Aggregate

cum

5.40

830.30

4483.62

M-055

20 mm Aggregate

cum

5.40

938.92

5070.17

M-053

10 mm Aggregate

cum

2.70

723.14

1952.48

M-051

Kg

21.60

112.77

2435.85

M-180

Mate

day

0.90

232.16

208.94

L-12

Mason

day

1.50

353.52

530.28

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

hour

6.00

532.00

3192.00

P&M-013

Cement
Coarse sand

Admixture
b)

c)

Labour

Machinery

Light Crane of 3 tonnes capacity for handling tremie


pipe
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3920.00
2613.65

15350.73
7675.36
84428.99

cost of 15 cum = a+b+c+d+e

5628.60

Rate per cum = (a+b+c+d+e)/15


12.11 C
(iii)

say

5629.00

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Unit = cum
Taking output = 120 cum
a)

Material
tonne

48.64

5210.53

253440.00

M-081

Coarse sand

cum

54.00

219.18

11835.72

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

10 mm Aggregate

cum

43.20

723.14

31239.65

M-051

Kg

172.80

112.77

19486.84

M-180

Mate

day

0.88

232.16

204.30

L-12

Mason

day

3.00

353.52

1060.56

L-11

Mazdoor

day

18.00

221.61

3988.98

L-13

Cement

Admixture
b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2598.00

15588.00

P&M-002

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader 1 cum capacity

hour

6.00

1116.00

6696.00

P&M-017

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

P&M-050
Lead= 1 km

6.00

234.36

1406.16

P&M-007

Transit Mixer 4 cum capacity for lead upto 1 km.


Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer

hour

Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
201

3580.00
19104.90

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Unit

Quantity

Rate Rs

56075.92
616835.14
5140.29

Rate per cum = (a+b+c+d+e)/120


(iv)
Case I

Remarks/
Input ref.

112151.84

cost of 120 cum = a+b+c+d+e

'12.11 C

Cost Rs

say

5140.00

PCC Grade M35


Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a)

Material
tonne

6.29

5210.53

32774.21

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

40 mm Aggregate

cum

5.40

830.30

4483.62

M-055

20 mm Aggregate

cum

5.40

938.92

5070.17

M-053

10 mm Aggregate

cum

2.70

723.14

1952.48

M-051

Kg

21.60

112.77

2435.85

M-180

Mate

day

0.90

232.16

208.94

L-12

Mason

day

1.50

353.52

530.28

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

hour

6.00

532.00

3192.00

P&M-013

Cement

Admixture
b)

c)

Labour

Machinery

Light Crane of 3 tonnes capacity for handling tremie


pipe
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c)
e)

3993.00
2668.36

15637.96
7818.98

Contractor's profit @ 0.1 on (a+b+c+d)

86008.75

cost of 15 cum = a+b+c+d+e

5733.92

Rate per cum = (a+b+c+d+e)/15


12.11 C
(iv)

say

5734.00

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Unit = cum
Taking output = 120 cum
a)

Material
tonne

50.28

5210.53

261985.26

M-081

Coarse sand

cum

54.00

219.18

11835.72

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

10 mm Aggregate

cum

43.20

723.14

31239.65

M-051

Kg

172.80

112.77

19486.84

M-180

Mate

day

0.88

232.16

204.30

L-12

Mason

day

3.00

353.52

1060.56

L-11

Mazdoor

day

18.00

221.61

3988.98

L-13

Cement

Admixture
b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2598.00

15588.00

P&M-002

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader 1 cum capacity

hour

6.00

1116.00

6696.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

P&M-050
Lead= 1 km

hour

6.00

234.36

1406.16

P&M-007

Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer


Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
202

3651.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

19532.17

Add 5 per cent of cost of material and labour towards cost of


forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c)
e)

114394.98
57197.49

Contractor's profit @ 0.1 on (a+b+c+d)

629172.36

cost of 120 cum = a+b+c+d+e

5243.10

Rate per cum = (a+b+c+d+e)/120


say

12.11

D
(i)

Case I

Grade M20 PCC


Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
3713.00

d)

Overhead charges @ 0.25 on (a+b+c)

928.25

e)

Contractor's profit @ 0.1 on (a+b+c+d)

464.13
5105.38

Rate per cum = (a+b+c+d+e)


say

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

843.25
421.63
4637.88

say

(ii)

Case I

Grade M25 PCC

3889.00

d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

972.25
486.13
5347.38

Rate per cum = (a+b+c+d+e)


say

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

886.75
443.38
4877.13

say

(iii)

Case I

4877.00

Grade M30 PCC


Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Using Concrete Mixer
3920.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

980.00
490.00
5390.00

Rate per cum = (a+b+c+d+e)


say

12.11 D
(iii)

5347.00

3547.00

Rate per cum = (a+b+c+d+e)


'12.11 D

4638.00

Same as in bottom plug concrete, excluding cost of forming


sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

12.11 D
(ii)

5105.00

3373.00

Rate per cum = (a+b+c+d+e)


'12.11 D

5243.00

Intermediate plug

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

12.11 D
(i)

Cost Rs

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

5390.00

3580.00

d)

Overhead charges @ 0.25 on (a+b+c)

895.00

e)

Contractor's profit @ 0.1 on (a+b+c+d)

447.50

203

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

say

Top plug

(i)

Grade M15 PCC

Remarks/
Input ref.

4922.50

Rate per cum = (a+b+c+d+e)


12.11

Cost Rs

4923.00

Same as Item 12.8(a) excluding formwork


Case I

Using Concrete Mixer


2874.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

718.50
359.25
3951.75

Rate per cum = (a+b+c+d+e)


say

3952.00

Same as Item 12.8(b) excluding formwork


Case I

Using Concrete Mixer


3224.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

806.00
403.00
4433.00

Rate per cum = (a+b+c+d+e)


say

Same as Item 12.8 (d)


Case I

excluding formwork

Using Concrete Mixer


3513.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

878.25
439.13
4830.38

Rate per cum = (a+b+c+d+e)


say

12.11 E
(iii)

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)
d)

Overhead charges @ 0.25 on (a+b+c)

846.50

e)

Contractor's profit @ 0.1 on (a+b+c+d)

423.25
4655.75

say

(iv)

4830.00

3386.00

Rate per cum = (a+b+c+d+e)


'12.11 E

4433.00

4656.00

Grade M30 PCC


Same as Item 12.8(f) excluding formwork

Case I

Using Concrete Mixer


3544.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

886.00
443.00
4873.00

Rate per cum = (a+b+c+d+e)


say

12.11 E
(iv)

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3414.00
853.50
426.75
4694.25

Rate per cum = (a+b+c+d+e)


12.11

Well cap

(i)

RCC Grade M20

Case I

4873.00

say

4694.00

5210.53

26677.89

Using Concrete Mixer


Unit = cum
Taking output = 15 cum
a)

Material
tonne

Cement
204

5.12

M-081

Sr No

Ref. to
MoRTH
Spec.

Description

b)

c)

Unit

Quantity

Rate Rs

Remarks/
Input ref.

Coarse sand

cum

6.75

219.18

1479.47

M-005

20 mm Aggregate

cum

8.10

938.92

7605.25

M-053

10 mm Aggregate

cum

5.40

723.14

3904.96

M-051

Mate

day

0.86

232.16

199.66

L-12

Mason

day

1.50

353.52

530.28

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

hour

6.00

211.68

1270.08

P&M-009

hour

6.00

342.36

2054.16

P&M-079

Labour

Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA

1926.16

Form Work @ 4 per cent of a+b+c


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

12520.03
6260.01
68860.14

cost of 15 cum = a+b+c+d+e

4590.68

Rate per cum = (a+b+c+d+e)/15


12.11 F (i)

Cost Rs

say

4591.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

Material
tonne

40.92

5210.53

213214.74

M-081

Coarse sand

cum

54.00

219.18

11835.72

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

10 mm Aggregate

cum

43.20

723.14

31239.65

M-051

Mate

day

0.84

232.16

195.01

L-12

Mason

day

3.00

353.52

1060.56

L-11

Mazdoor

day

18.00

221.61

3988.98

L-13

Cement

b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2598.00

15588.00

P&M-002

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader (capacity 1 cum)

hour

6.00

1116.00

6696.00

P&M-017

P&M-049

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

15.00

854.55

12818.25

tonne.km

300L

4.32

1296.00

hour

6.00

234.36

Formwork @ 4 per cent of (a+b+c)

14791.24

d)

Overhead charges @ 0.25 on (a+b+c)

96143.08

e)

Contractor's profit @ 0.1 on (a+b+c+d)

48071.54
528786.95

cost of 120 cum = a+b+c+d+e

4406.56

Rate per cum = (a+b+c+d+e)/120


12.11 F

(ii)
Case I

P&M-050
Lead= 1 km
1406.16
P&M-007

say

4407.00

RCC Grade M25


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

6.05

5210.53

31523.68

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

20 mm Aggregate

cum

8.10

938.92

7605.25

M-053

10 mm Aggregate

cum

5.40

723.14

3904.96

M-051

Mate

day

0.86

232.16

199.66

L-12

Mason

day

1.50

353.52

530.28

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

Cement

b)

c)

Labour

Machinery
205

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Remarks/
Input ref.

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

1987.49

Form Work @ 3.75 per cent of a+b+c


d)

Overhead charges @ 0.25 on (a+b+c)

13746.81

e)

Contractor's profit @ 0.1 on (a+b+c+d)

6873.40
75607.43

cost of 15 cum = a+b+c+d+e

5040.50

Rate per cum = (a+b+c+d+e)/15


12.11 F
(ii)

Cost Rs

say

5040.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

Material
tonne

48.40

5210.53

252189.47

M-081

Coarse sand

cum

54.00

219.18

11835.72

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

10 mm Aggregate

cum

43.20

723.14

31239.65

M-051

Mate

day

0.84

232.16

195.01

L-12

Mason

day

3.00

353.52

1060.56

L-11

Mazdoor

day

18.00

221.61

3988.98

L-13

Cement

b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2598.00

15588.00

P&M-002

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader (capacity 1 cum)

hour

6.00

1116.00

6696.00

P&M-017

P&M-049

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

15.00

854.55

12818.25

tonne.km

300L

4.32

1296.00

hour

6.00

234.36

Formwork @ 3.75 per cent of ( a+b+c)

15328.34

d)

Overhead charges @ 0.25 on (a+b+c)

106021.04

e)

Contractor's profit @ 0.1 on (a+b+c+d)

53010.52
583115.73

cost of 120 cum = a+b+c+d+e

4859.30

Rate per cum = (a+b+c+d+e)/120


12.11 F

(iii)
Case I

P&M-050
Lead= 1 km
1406.16
P&M-007

say

4859.00

RCC Grade M30


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

6.10

5210.53

31784.21

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

20 mm Aggregate

cum

8.10

938.92

7605.25

M-053

10 mm Aggregate

cum

5.40

723.14

3904.96

M-051

Mate

day

0.86

232.16

199.66

L-12

Mason

day

1.50

353.52

530.28

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

Machinery

1864.11

Formwork @ 3.5 per cent of (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

13781.09
6890.55
75796.01

cost of 15 cum = a+b+c+d+e

5053.07

Rate per cum = (a+b+c+d+e)/15


say

206

5053.00

Sr No
12.11 F
(iii)

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

Material
tonne

48.79

5210.53

254221.58

M-081

Coarse sand

cum

54.00

219.18

11835.72

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

10 mm Aggregate

cum

43.20

723.14

31239.65

M-051

Mate

day

0.84

232.16

195.01

L-12

Mason

day

3.00

353.52

1060.56

L-11

Mazdoor

day

18.00

221.61

3988.98

L-13

6.00

2598.00

15588.00

P&M-002

6.00

Cement

b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

Generator 100 KVA

hour

1600.00

9600.00

P&M-080

Loader (capacity 1 cum)

hour

6.00

1116.00

6696.00

P&M-017

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

P&M-050
Lead= 1 km

hour

6.00

234.36

1406.16

P&M-007

14377.58

Formwork @ 3.5 per cent of (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

106291.38
53145.69
584602.57

cost of 120 cum = a+b+c+d+e

4871.69

Rate per cum = (a+b+c+d+e)/120


12.11 F

(iv)
Case I

say

4872.00

RCC Grade M35


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

6.33

5210.53

32982.63

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

20 mm Aggregate

cum

8.10

938.92

7605.25

M-053

10 mm Aggregate

cum

5.40

723.14

3904.96

M-051

Mate

day

0.86

232.16

199.66

L-12

Mason

day

1.50

353.52

530.28

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

Machinery

1633.76

Formwork @ 3 per cent of (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

14023.11
7011.56
77127.11

cost of 15 cum = a+b+c+d+e

5141.81

Rate per cum = (a+b+c+d+e)/15


12.11 F
(iv)

say

5142.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

Material
tonne

50.64

5210.53

263861.05

M-081

Coarse sand

cum

54.00

219.18

11835.72

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

Cement

207

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

c)

Rate Rs

Cost Rs
31239.65

Remarks/
Input ref.

cum

43.20

723.14

Mate

day

0.84

232.16

195.01

L-12

Mason

day

3.00

353.52

1060.56

L-11

Mazdoor

day

18.00

221.61

3988.98

L-13

10 mm Aggregate
b)

Quantity

M-051

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2598.00

15588.00

P&M-002

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader (capacity 1 cum)

hour

6.00

1116.00

6696.00

P&M-017

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

P&M-050
Lead= 1 km

hour

6.00

234.36

1406.16

P&M-007

12612.82

Formwork @ 3 per cent of (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

108260.06
54130.03
595430.31

cost of 120 cum = a+b+c+d+e

4961.92

Rate per cum = (a+b+c+d+e)/120


Note

'12.11 F

(v)

say

4962.00

Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a)

Material
tonne

52.20

5210.53

271989.47

M-081

Coarse Sand

cum

54.00

219.18

11835.72

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

10 mm Aggregate

cum

43.20

723.14

31239.65

M-051

kg

206.00

112.77

23230.84

M-180

Mate

day

0.84

232.16

195.01

L-12

Mason

day

3.00

353.52

1060.56

L-11

Mazdoor

day

18.00

221.61

3988.98

L-13

2598.00

15588.00

P&M-002

Cement

Admixture
b)

c)

Labour

Machinery
6.00

Batching Plant

hour

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader 1 cum capacity

hour

6.00

1116.00

6696.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300.L

4.32

1296.00

P&M-050
Lead= 1 km

hour

6.00

1406.16

P&M-007

Transit Mixer 4 cum capacity for lead beyond 1 km.


Concrete Pump

d)

Formwork @ 3 per cent on cost of concrete i.e. cost of


material, labour and machinery
Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

234.36

13553.60
116335.06
58167.53
639842.85

cost of 120 cum = a+b+c+d+e

5332.02

Rate per cum = (a+b+c+d+e)/120


say

12.12

Section
1200

Sinking of 6 m external diameter well (other than


pneumatic method of sinking) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
208

5332.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 6 m.
A
(i)

Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking = 0.50 m per hour.
a)

Labour
Mate

day

0.12

232.16

27.86

L-12

Sinker ( skilled )

day

1.00

306.03

306.03

L-15

day

2.00

232.16

464.32

L-14

hour

2.00

1176.12

2352.24

P&M-075

Sinking helper ( semi-skilled )


b)

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

235.22
846.42
423.21
4655.30

Rate per metre = (a+b+c+d)


say

12.12 A

(ii)

4655.00

Beyond 3m upto 10m depth


Rate of sinking = 0.33 m per hour.
a)

b)

Labour
Mate

day

0.15

232.16

34.82

L-12

Sinker

day

1.25

306.03

382.54

L-15

Sinking helper ( semi-skilled )

day

2.50

232.16

580.40

L-14

hour

3.00

1176.12

3528.36

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

352.84
1219.74
609.87
6708.57

Rate per metre = (a+b+c+d)


say

12.12 A

(iii)
a

12.12 A

(iv)
a
b

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

7044.00

12th m

5%

7396.00

13th m

5%

7766.00

14th m

5%

8154.00

15th m

5%

8562.00

16th m

5%

8990.00

17th m

5%

9440.00

18th m

5%

9912.00

19th m

5%

10408.00

20th m

5%

10928.00

Total Cost from 10m upto 20m

88600.00

Avg Rate per metre

8860.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.

(a)

(b) Including
20% for
Kentledge
14098.00

21st m

7.5%

11748.00

22nd m

7.5%

12629.00

15155.00

23rd m

7.5%

13576.00

16291.00

24th m

7.5%

14594.00

17513.00

25th m

7.5%

15689.00

18827.00

26th m

7.5%

16866.00

20239.00

209

6709.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
7.5%

18131.00

21757.00

28th m

7.5%

19491.00

23389.00

29th m

7.5%

20953.00

25144.00

30th m

7.5%

22524.00

27029.00

166201.00

199442.00

16620.00

19944.00

Avg Rate per metre


(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.

31st m

10%

24776.00

29731.00

32nd

10%

27254.00

32705.00

33rd m

10%

29979.00

35975.00

34th m

10%

32977.00

39572.00

35th m

10%

36275.00

43530.00

36th m

10%

39903.00

47884.00

37th m

10%

43893.00

52672.00

38th m

10%

48282.00

57938.00

39th m

10%

53110.00

63732.00

40th m

10%

Avg Rate per metre


B

Cost Rs

Remarks/
Input ref.

(a) (b)Including 20%


for Kentledge

Total Cost from 30m upto 40m


12.12

Rate Rs

27th m

Total Cost from 20m upto 30m


12.12 A

Quantity

58421.00

70105.00

394870.00

473844.00

39487.00

47384.00

Clayey Soil ( 6m dia. Well )


Unit = Running Meter.
Taking output = 1 meter

(i)

Depth below bed level upto 3.0 M


Rate of sinking = 0.33 m per hour.
a)

b)

Labour
Mate

day

0.15

232.16

34.82

L-12

Sinker ( skilled )

day

1.50

306.03

459.05

L-15

Sinking helper ( semi-skilled )

day

2.25

232.16

522.36

L-14

hour

3.00

1176.12

3528.36

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

352.84
1224.36
612.18
6733.96

Rate per metre = (a+b+c+d)


say

12.12 B

(ii)

6734.00

Beyond 3m upto 10m depth


Rate of sinking = 0.17 m per hour.
a)

b)

Labour
Mate

day

0.30

232.16

69.65

L-12

Sinker

day

3.00

306.03

918.09

L-15

Sinking helper ( semi-skilled )

day

4.50

232.16

1044.72

L-14

hour

6.00

1176.12

7056.72

P&M-075

hour

2.00

513.00

1026.00

P&M-063

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

808.27
2730.86
1365.43
15019.74

Rate per metre = (a+b+c+d)


say

12.12 B

(iii)
a

Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
210

15020.00

Sr No

Ref. to
MoRTH
Spec.

Description
b

Unit

(a)

Add for dewatering @ 5 per cent of cost, if required.

5%

15771.00

5%

16560.00

17388.00

13th m

5%

17388.00

18257.00

14th m

5%

18257.00

19170.00

15th m

5%

19170.00

20129.00

16th m

5%

20129.00

21135.00

17th m

5%

21135.00

22192.00

18th m

5%

22192.00

23302.00

19th m

5%

23302.00

24467.00

5%

24467.00

25690.00

Avg Rate per metre


a
b
c

(a) (c)Including 25%


for Kentledge

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).
7.5%

26302.00

32878.00

22nd m

7.5%

28275.00

35344.00

37111.00

23rd m

7.5%

30396.00

37995.00

39895.00

24th m

7.5%

32676.00

40845.00

42887.00

25th m

7.5%

35127.00

43909.00

46104.00

26th m

7.5%

37762.00

47203.00

49563.00

27th m

7.5%

40594.00

50743.00

53280.00

28th m

7.5%

43639.00

54549.00

57276.00

29th m

7.5%

46912.00

58640.00

61572.00

30th m

7.5%

50430.00

63038.00

66190.00

372113.00

465144.00

488400.00

37211.00

46514.00

48840.00

(b) Including
20% for
Kentledge

(b)Including
5% for
dewatering, if
required
69896.00

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

31st m

10%

55473.00

66568.00

32nd

10%

61020.00

73224.00

76885.00

33rd m

10%

67122.00

80546.00

84573.00

34th m

10%

73834.00

88601.00

93031.00

35th m

10%

81217.00

97460.00

102333.00

36th m

10%

89339.00

107207.00

112567.00

37th m

10%

98273.00

117928.00

123824.00

38th m

10%

108100.00

129720.00

136206.00

39th m

10%

118910.00

142692.00

149827.00

40th m

10%

130801.00

156961.00

164809.00

Avg Rate per metre


C

(a)

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

Total Cost from 30m upto 40m


12.12

(b) Including
5% for
dewatering, if
required
34522.00

21st m

(v)

208290.00

20829.00

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering of the cost, if required

Avg Rate per metre

198371.00

19837.00

Beyond 20m upto 30 m

Total Cost from 20m upto 30m


12.12 B

Cost Rs

(b)Including for
dewatering @
5% of cost, if
required
16560.00

12th m

Total Cost from 10m upto 20m


(iv)

Rate Rs

11th m

20th m

12.12 B

Quantity

Soft Rock (6m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in Soft rock strata up to 3m
Rate of sinking = 0.25 m per hour.
211

884089.00

1060907.00

1113951.00

88409.00

106091.00

111395.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description
a)

b)

Unit

Quantity

Rate Rs

Mate

day

0.92

232.16

213.59

L-12

Sinker ( skilled )

day

3.00

306.03

918.09

L-15

Sinking helper ( semi-skilled )

day

20.00

232.16

4643.20

L-14

Diver

day

0.50

232.16

116.08

L-07

hour

4.00

1176.12

4704.48

P&M-075

hour

3.50

513.00

1795.50

P&M-063

Machinery

Consumables in sinking @ 10 per cent of (b)

650.00

Add for dewatering @ of 5 per cent of (a+b), if required

652.05

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3423.25
1711.62
18827.85

Rate per metre = (a+b+c+d)


D

Remarks/
Input ref.

Labour

Hire & running charges of crane with grab bucket of 0.75


cum capacity and accessories.
Air compressor with pneumatic breakers

12.12

Cost Rs

say

18828.00

Hard Rock (6m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking = 0.17 m per hour.
a)

b)

c)

Material
Gelatine 80 per cent

Kg

4.00

112.77

451.08

M-104

Electric Detonators

each

18.00

14.27

256.79

M-094/100

Mate

day

1.56

232.16

362.17

L-12

Driller

day

2.00

232.16

464.32

L-06

Blaster

day

0.25

306.03

76.51

L-03

Mazdoor

day

12.00

221.61

2659.32

L-13

Mazdoor (Skilled)

day

4.00

306.03

1224.12

L-15

hour

6.00

1176.12

7056.72

P&M-075

hour

2.00

513.00

1026.00

P&M-063

Labour

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.

643.46
808.27

Consumables in sinking @ 10 per cent of cost of (b).


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3757.19
1878.60
20664.55

Rate per metre = (a+b+c+d+e)


say

12.13

Section
1200

20665.00

Sinking of 7 m external diameter well ( other than


pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 7 m.
A
(i)

Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking = 0.30 m per hour.
a)

b)

Labour
Mate

day

0.15

232.16

34.82

L-12

Sinker ( skilled )

day

1.25

306.03

382.54

L-15

Sinking helper ( semi-skilled )

day

2.50

232.16

580.40

L-14

hour

3.25

1176.12

3822.39

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
212

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1300.60
650.30
7153.29

Rate per metre = (a+b+c+d)


say

12.13 A

(ii)

Remarks/
Input ref.

382.24

Consumables in sinking @10 per cent of (b)


c)

Cost Rs

7153.00

Beyond 3m upto 10m depth


Rate of sinking = 0.22 m per hour.
a)

Labour
day

0.18

232.16

41.79

L-12

Sinker

day

1.50

306.03

459.05

L-15

Sinking helper ( semi-skilled )

day

3.00

232.16

696.48

L-14

hour

4.50

1176.12

5292.54

P&M-075

Mate

b)

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

529.25
1754.78
877.39
9651.27

Rate per metre = (a+b+c+d)


say

12.13 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

10134.00

12th m

5%

10641.00

13th m

5%

11173.00

14th m

5%

11732.00

15th m

5%

12319.00

16th m

5%

12935.00

17th m

5%

13582.00

18th m

5%

14261.00

19th m

5%

14974.00

20th m

5%

12747.00

Avg Rate per metre


12.13 A

(iv)
a
b

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).

(a) (b)Including 20%


for Kentledge

21st m

7.5%

16902.00

20282.00

22nd m

7.5%

18170.00

21804.00

23rd m

7.5%

19533.00

23440.00

24th m

7.5%

20998.00

25198.00

25th m

7.5%

22573.00

27088.00

26th m

7.5%

24266.00

29119.00

27th m

7.5%

26086.00

31303.00

28th m

7.5%

28042.00

33650.00

29th m

7.5%

30145.00

36174.00

30th m

7.5%

32406.00

38887.00

Total Cost from 20m upto 30m


Avg Rate per metre
12.13 A

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.

15723.00
127474.00

Total Cost from 10m upto 20m

239121.00

286945.00

23912.00

28695.00

(a) (b)Including 20%


for Kentledge

31st m

10%

35647.00

42776.00

32nd

10%

39212.00

47054.00

213

9651.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
10%

43133.00

51760.00

34th m

10%

47446.00

56935.00

35th m

10%

52191.00

62629.00

36th m

10%

57410.00

68892.00

37th m

10%

63151.00

75781.00

38th m

10%

69466.00

83359.00

39th m

10%

76413.00

91696.00

40th m

10%

84054.00

100865.00

Avg Rate per metre


B

Rate Rs

33rd m

Total Cost from 30m upto 40m


12.13

Quantity

568123.00

681747.00

56812.00

68175.00

Cost Rs

Remarks/
Input ref.

Clayey Soil ( 7m dia. Well )


Unit = Running Meter.
Taking output = 1 cum

(I)

Depth below bed level upto 3.0 M


Rate of sinking = 0.22 m per hour.
a)

b)

Labour
Mate

day

0.18

232.16

41.79

L-12

Sinker ( skilled )

day

1.50

306.03

459.05

L-15

Sinking helper ( semi-skilled )

day

3.00

232.16

696.48

L-14

hour

4.50

1176.12

5292.54

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

529.25

d)

Overhead charges @ 0.25 on (a+b)

1754.78

e)

Contractor's profit @ 0.1 on (a+b+c)

877.39
9651.27

Rate per metre = (a+b+c+d)


say

12.13 B

(ii)

9651.00

Beyond 3m upto 10m depth


Rate of sinking = 0.17 m per hour.
a)

b)

Labour
Mate

day

0.26

232.16

60.36

L-12

Sinker

day

2.00

306.03

612.06

L-15

Sinking helper ( semi-skilled )

day

4.00

232.16

928.64

L-14

hour

6.00

1176.12

7056.72

P&M-075

hour

3.25

513.00

1667.25

P&M-063

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

872.40

c)

Overhead charges @ 0.25 on (a+b)

2799.36

d)

Contractor's profit @ 0.1 on (a+b+c)

1399.68
15396.46

Rate per metre = (a+b+c+d)


say

12.13 B

(iii)
a
b

Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

11th m

5%

(a) (b) Including for


dewatering @
5% of cost, if
required
16166.00
16974.00

12th m

5%

16974.00

17823.00

13th m

5%

17823.00

18714.00

14th m

5%

18714.00

19650.00

15th m

5%

19650.00

20633.00

16th m

5%

20633.00

21665.00

17th m

5%

21665.00

22748.00

18th m

5%

22748.00

23885.00

19th m

5%

23885.00

25079.00

214

15396.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
5%

20th m
Total Cost from 10m upto 20m
Avg Rate per metre
12.13 B

(iv)
a
b
c

21350.00

( c) Including
25% for
Kentledge

Remarks/
Input ref.

(b) Including
5% for
dewatering, if
required
35385.00

26960.00

33700.00

32nd

7.5%

28982.00

36228.00

38039.00

33rd m

7.5%

31156.00

38945.00

40892.00

34th m

7.5%

33493.00

41866.00

43959.00

35th m

7.5%

36005.00

45006.00

47256.00

36th m

7.5%

38705.00

48381.00

50800.00

37th m

7.5%

41608.00

52010.00

54611.00

38th m

7.5%

44729.00

55911.00

58707.00

39th m

7.5%

48084.00

60105.00

63110.00

40th m

7.5%

51690.00

64613.00

67844.00

381412.00

476765.00

500603.00

38141.00

47677.00

50060.00

( c) Including
20% for
Kentledge

(b) Including
5% for
dewatering, if
required
71643.00

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
(a)

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).
31st m

10%

56859.00

68231.00

32nd

10%

62545.00

75054.00

78807.00

33rd m

10%

68800.00

82560.00

86688.00

34th m

10%

75680.00

90816.00

95357.00

35th m

10%

83248.00

99898.00

104893.00

36th m

10%

91573.00

109888.00

115382.00

37th m

10%

100730.00

120876.00

126920.00

38th m

10%

110803.00

132964.00

139612.00

39th m

10%

121883.00

146260.00

153573.00

40th m

10%

134071.00

160885.00

168929.00

906192.00

1087432.00

1141804.00

90619.00

108743.00

114180.00

Total Cost from 30m upto 40m


Avg Rate per metre
C

20334.00

7.5%

Avg Rate per metre

12.13

26333.00
213504.00

(a)

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

(v)

25079.00
203337.00

Cost Rs

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Total Cost from 30m upto 40m

Rate Rs

Beyond 20m upto 30 m

31st m

12.13 B

Quantity

Soft Rock ( 7m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking = 0.22 m per hour.
a)

b)

Labour
Mate

day

0.58

232.16

134.65

L-12

Sinker ( skilled )

day

4.00

306.03

1224.12

L-15

Sinking helper ( semi-skilled )

day

10.00

232.16

2321.60

L-14

Diver

day

0.75

232.16

174.12

L-07

hour

4.50

1176.12

5292.54

P&M-075

hour

3.75

513.00

1923.75

P&M-063

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Air compressor with pneumatic breakers

c)

Consumables in sinking @ 10 per cent of (b)

721.63

Add for dewatering @ of 5 per cent of (a+b), if required

553.54
3086.49

Overhead charges @ 0.25 on (a+b)


215

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Unit

Quantity

Rate Rs

Remarks/
Input ref.

1543.24

Contractor's profit @ 0.1 on (a+b+c)

16975.68

Rate per metre = (a+b+c+d)


12.13

Cost Rs

say

16976.00

Hard Rock ( 7m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in Hard rock strata up to 3 m
Rate of sinking = 0.17 m per hour.
a)

b)

c)

Material
Gelatine 80 per cent

Kg

7.00

112.77

789.40

M-104

Electric Detonators

each

30.00

14.27

427.98

M-094/100

Mate

day

1.60

232.16

371.46

L-12

Driller

day

2.00

232.16

464.32

L-06

Blaster

day

0.25

306.03

76.51

L-03

Mazdoor

day

18.00

221.61

3988.98

L-13

Mazdoor (Skilled)

day

4.00

306.03

1224.12

L-15

Diver

day

0.50

232.16

116.08

L-07

hour

6.00

1176.12

7056.72

P&M-075

hour

2.00

513.00

1026.00

P&M-063

Labour

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.

716.21
879.89

Consumables in sinking @ 10 per cent of cost of (b).


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

4284.42
2142.21
23564.29

Rate per metre = (a+b+c+d+e)


say

12.14

Section
1200

23564.00

Sinking of 8 m external diameter well ( other than


pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 8 m.
A
(i)

Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a)

Labour
day

0.18

232.16

41.79

L-12

Sinker ( skilled )

day

1.50

306.03

459.05

L-15

Sinking helper ( semi-skilled )

day

3.00

232.16

696.48

L-14

hour

4.00

1176.12

4704.48

P&M-075

Mate

b)

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

470.45
1593.06
796.53
8761.83

Rate per metre = (a+b+c+d)


say

12.14 A

(ii)

8762.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.20 m/hour
a)

Labour
Mate

day

0.25

232.16

58.04

L-12

Sinker

day

1.75

306.03

535.55

L-15

Sinking helper ( semi-skilled )

day

3.50

232.16

812.56

L-14

216

Sr No

Ref. to
MoRTH
Spec.

Description
b)

Unit

Quantity

Rate Rs

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

hour

5.00

1176.12

588.06

984.35
10827.87

say

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

11369.00

12th m

5%

11937.00

13th m

5%

12534.00

14th m

5%

13161.00

15th m

5%

13819.00

16th m

5%

14510.00

17th m

5%

15236.00

18th m

5%

15998.00

19th m

5%

16798.00

20th m

5%

17638.00
143000.00

Total Cost from 10m upto 20m

14300.00

Avg Rate per metre


12.14 A

(iv)
a
b

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.

(a)

7.5%

18961.00

22nd m

7.5%

20383.00

24460.00

23rd m

7.5%

21912.00

26294.00

24th m

7.5%

23555.00

28266.00

25th m

7.5%

25322.00

30386.00

26th m

7.5%

27221.00

32665.00

27th m

7.5%

29263.00

35116.00

28th m

7.5%

31458.00

37750.00

29th m

7.5%

33817.00

40580.00

30th m

7.5%

Avg Rate per metre


(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.

43624.00
321894.00

26825.00

32189.00

(a)

(b) Including
20% for
Kentledge
47986.00

10%

39988.00

32nd

10%

43987.00

52784.00

33rd m

10%

48386.00

58063.00

34th m

10%

53225.00

63870.00

35th m

10%

58548.00

70258.00

36th m

10%

64403.00

77284.00

37th m

10%

70843.00

85012.00

38th m

10%

77927.00

93512.00

39th m

10%

85720.00

102864.00

40th m

10%

94292.00

113150.00

Avg Rate per metre


B

36353.00
268245.00

31st m

Total Cost from 30m upto 40m


12.14

(b) Including
20% for
Kentledge
22753.00

21st m

Total Cost from 20m upto 30m


12.14 A

5880.60

1968.70

Rate per metre = (a+b+c+d)


(iii)

Remarks/
Input ref.

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

12.14 A

Cost Rs

Clayey Soil ( 8m dia. Well )

217

637319.00

764783.00

63732.00

76478.00

10828.00

P&M-075

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Unit = Running Meter.


Taking output = 1 meter
(i)

Depth from bed level upto 3.0 M


Rate of sinking @ 0.18 m/hour
a)

b)

Labour
Mate

day

0.22

232.16

51.08

L-12

Sinker ( skilled )

day

2.00

306.03

612.06

L-15

Sinking helper ( semi-skilled )

hour

3.50

232.16

812.56

L-14

5.50

1176.12

6468.66

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

646.87
2147.81
1073.90
11812.93

Rate per metre = (a+b+c+d)


12.14 B

(ii)

say

11813.00

74.29

L-12

Beyond 3m upto 10m depth


Rate of sinking @ 0.17 m/hour
a)

b)

Labour
Mate

day

0.32

232.16

Sinker

day

2.50

306.03

765.08

L-15

Sinking helper ( semi-skilled )

day

4.50

232.16

1044.72

L-14

hour

6.00

1176.12

7056.72

P&M-075

hour

3.50

513.00

1795.50

P&M-063

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

885.22
2905.38
1452.69
15979.60

Rate per metre = (a+b+c+d)


say

12.14 B

(iii)
a
b

Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

11th m

5%

(a) (b) Including for


dewatering @
5% of cost, if
required
16779.00
17618.00

12th m

5%

17618.00

18499.00

13th m

5%

18499.00

19424.00

14th m

5%

19424.00

20395.00

15th m

5%

20395.00

21415.00

16th m

5%

21415.00

22486.00

17th m

5%

22486.00

23610.00

18th m

5%

23610.00

24791.00

19th m

5%

24791.00

26031.00

20th m

5%

26031.00

27333.00

211048.00

221602.00

21105.00

22160.00

Total Cost from 10m upto 20m


Avg Rate per metre
12.14 B

(iv)
a
b
c

15980.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
(a) (c)Including 25%
for Kentledge

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).
7.5%

31st m

218

27983.00

34979.00

(b) Including
5% for
dewatering, if
required
36728.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
7.5%

30082.00

37603.00

39483.00

7.5%

32338.00

40423.00

42444.00

34th m

7.5%

34763.00

43454.00

45627.00

35th m

7.5%

37370.00

46713.00

49049.00

36th m

7.5%

40173.00

50216.00

52727.00

37th m

7.5%

43186.00

53983.00

56682.00

38th m

7.5%

46425.00

58031.00

60933.00

39th m

7.5%

49907.00

62384.00

65503.00

40th m

7.5%

53650.00

67063.00

70416.00

395877.00

494849.00

519592.00

39588.00

49485.00

51959.00

(c ) Including
20% for
Kentledge

(b) Including
5% for
dewatering, if
required
74359.00

Avg Rate per metre


Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

(a)

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).
31st m

10%

59015.00

70818.00

32nd

10%

64917.00

77900.00

81795.00

33rd m

10%

71409.00

85691.00

89976.00

34th m

10%

78550.00

94260.00

98973.00

35th m

10%

86405.00

103686.00

108870.00

36th m

10%

95046.00

114055.00

119758.00

37th m

10%

104551.00

125461.00

131734.00

38th m

10%

115006.00

138007.00

144907.00

39th m

10%

126507.00

151808.00

159398.00

40th m

10%

139158.00

166990.00

175340.00

940564.00

1128676.00

1185110.00

94056.00

112868.00

118511.00

Total Cost from 30m upto 40m


Avg Rate per metre
12.14

Cost Rs

33rd m

(v)

Rate Rs

32nd

Total Cost from 30m upto 40m


12.14 B

Quantity

Remarks/
Input ref.

Soft Rock ( 8m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.20 m/hour
a)

Labour
Mate

day

0.68

232.16

157.87

L-12

Sinker ( skilled )

day

4.00

306.03

1224.12

L-15

Sinking helper ( semi-skilled )

day

12.00

232.16

2785.92

L-14

day

1.00

232.16

232.16

L-07

hour

5.00

1176.12

5880.60

P&M-075

hour

3.75

513.00

1923.75

P&M-063

Diver
b)

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)

780.44

Add for dewatering @ of 5 per cent of (a+b), if required

649.24

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3408.52
1704.26
18746.88

Rate per metre = (a+b+c+d)


12.14

say

18747.00

112.77

902.17

Hard Rock ( 8m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.17 m/hour
a)

Material
Kg

Gelatine 80 per cent

219

8.00

M-104

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

c)

Rate Rs

32.00

14.27

456.52

M-094/100

Mate

day

1.09

232.16

253.05

L-12

Driller

day

2.00

232.16

464.32

L-06

Blaster

day

0.25

306.03

76.51

L-03

Mazdoor

day

20.00

221.61

4432.20

L-13

Mazdoor (Skilled)

day

4.00

306.03

1224.12

L-15

hour

6.00

1176.12

7056.72

P&M-075

hour

2.00

513.00

1026.00

P&M-063

Machinery

726.65
645.02

Consumables in sinking @ 10 per cent of cost of (b).


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

4315.82
2157.91
23737.00

Rate per metre = (a+b+c+d+e)


say

Section
1200

Remarks/
Input ref.

Labour

Hire & running charges of crane with grab bucket of 0.75


cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.

12.15

Cost Rs

each

Electric Detonators
b)

Quantity

23737.00

Sinking of 9 m external diameter well ( other than


pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 9 m.
A
(i)

Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a)

b)

Labour
Mate

day

0.19

232.16

44.11

L-12

Sinker ( skilled )

day

1.50

306.03

459.05

L-15

Sinking helper ( semi-skilled )

day

3.25

232.16

754.52

L-14

hour

4.00

1176.12

4704.48

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

470.45
1608.15
804.08
8844.83

Rate per metre = (a+b+c+d)


say

12.15 A

(ii)

8845.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.18 m/hour
a)

b)

Labour
Mate

day

0.27

232.16

62.68

L-12

Sinker

day

1.75

306.03

535.55

L-15

Sinking helper ( semi-skilled )

day

4.00

232.16

928.64

L-14

hour

5.50

1176.12

6468.66

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

646.87
2160.60
1080.30
11883.30

Rate per metre = (a+b+c+d)


say

12.15 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m
220

5%

12477.00

11883.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

12th m

5%

13101.00

13th m

5%

13756.00

14th m

5%

14444.00

15th m

5%

15166.00

16th m

5%

15924.00

17th m

5%

16720.00

18th m

5%

17556.00

19th m

5%

18434.00

20th m

5%

a
b

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
7.5%

20807.70

22nd m

7.5%

22368.00

26842.00

23rd m

7.5%

24046.00

28855.00

24th m

7.5%

25849.00

31019.00

25th m

7.5%

27788.00

33346.00

26th m

7.5%

29872.00

35846.00

27th m

7.5%

32112.00

38534.00

28th m

7.5%

34520.00

41424.00

29th m

7.5%

37109.00

44531.00

30th m

7.5%

39892.00

47870.00

294363.70

353236.00

29436.00

35324.00

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.

(a)

(b) Including
20% for
Kentledge
52657.00

31st m

10%

43881.20

32nd

10%

48269.00

57923.00

33rd m

10%

53096.00

63715.00

34th m

10%

58406.00

70087.00

35th m

10%

64247.00

77096.00

36th m

10%

70672.00

84806.00

37th m

10%

77739.00

93287.00

38th m

10%

85513.00

102616.00

39th m

10%

94064.00

112877.00

40th m

10%

103470.00

124164.00

699357.20

839228.00

69936.00

83923.00

Avg Rate per metre


B

(b) Including
20% for
Kentledge
24969.00

21st m

Total Cost from 30m upto 40m


12.15

19356.00

(a)

Avg Rate per metre

Remarks/
Input ref.

Beyond 20m upto 30 m

Total Cost from 20m upto 30m


12.15 A

Cost Rs

15693.00

Avg Rate per metre


(iv)

Rate Rs

156934.00

Total Cost from 10m upto 20m


12.15 A

Quantity

Clayey Soil ( 9m dia. Well )


Unit = Running Meter.
Taking output = 1 cum

(i)

Depth below bed level upto 3.0 M


Rate of sinking 0.17 m / hour
a)

b)

Labour
Mate

day

0.24

232.16

55.72

L-12

Sinker ( skilled )

day

2.25

306.03

688.57

L-15

Sinking helper ( semi-skilled )

day

3.75

232.16

870.60

L-14

hour

5.75

1176.12

6762.69

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.

221

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2263.46
1131.73
12449.04

Rate per metre = (a+b+c+d)


say

12.15 B

(ii)

Remarks/
Input ref.

676.27

Consumables in sinking @ 10 per cent of (b)


c)

Cost Rs

12449.00

Beyond 3m upto 10m depth


Rate of sinking 0.15 m / hour
a)

Labour
day

0.34

232.16

78.93

L-12

Sinker

day

2.50

306.03

765.08

L-15

Sinking helper ( semi-skilled )

day

5.00

232.16

1160.80

L-14

hour

6.50

1176.12

7644.78

P&M-075

hour

3.75

513.00

1923.75

P&M-063

Mate

b)

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

956.85
3132.55
1566.27
17229.01

Rate per metre = (a+b+c+d)


say

12.15 B

(iii)
a
b

Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

11th m

5%

(a) (b) Including for


dewatering @
5% of cost, if
required
18090.00
18995.00

12th m

5%

18995.00

19945.00

13th m

5%

19945.00

20942.00

14th m

5%

20942.00

21989.00

15th m

5%

21989.00

23088.00

16th m

5%

23088.00

24242.00

17th m

5%

24242.00

25454.00

18th m

5%

25454.00

26727.00

19th m

5%

26727.00

28063.00

20th m

5%

Total Cost from 10m upto 20m


Avg Rate per metre
12.15 B

(iv)
a
b
c

17229.00

28063.00

29466.00

227535.00

238911.00

22754.00

23891.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
(a)

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

( c) Including
25% for
Kentledge

(b) Including
5% for
dewatering, if
required
39596.00

31st m

7.5%

30168.00

37710.00

32nd

7.5%

32431.00

40539.00

42566.00

33rd m

7.5%

34863.00

43579.00

45758.00

34th m

7.5%

37478.00

46848.00

49190.00

35th m

7.5%

40289.00

50361.00

52879.00

36th m

7.5%

43311.00

54139.00

56846.00

37th m

7.5%

46559.00

58199.00

61109.00

38th m

7.5%

50051.00

62564.00

65692.00

39th m

7.5%

53805.00

67256.00

70619.00

40th m

7.5%

57840.00

72300.00

75915.00

426795.00

533495.00

560170.00

42680.00

53350.00

56017.00

Total Cost from 30m upto 40m


Avg Rate per metre
222

Sr No
12.15 B

Ref. to
MoRTH
Spec.

Description

Unit

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

b
c

(a)

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

( c) Including
20% for
Kentledge

Cost Rs

Remarks/
Input ref.

(b) Including
5% for
dewatering, if
required
80166.00

10%

63624.00

76349.00

32nd

10%

69986.00

83983.00

33rd m

10%

76985.00

92382.00

97001.00

34th m

10%

84684.00

101621.00

106702.00

35th m

10%

93152.00

111782.00

117371.00

36th m

10%

102467.00

122960.00

129108.00

37th m

10%

112714.00

135257.00

142020.00

38th m

10%

123985.00

148782.00

156221.00

39th m

10%

136384.00

163661.00

171844.00

40th m

10%

150022.00

180026.00

189027.00

1014003.00

1216803.00

1277642.00

101400.00

121680.00

127764.00

Avg Rate per metre


C

Rate Rs

31st m

Total Cost from 30m upto 40m


12.15

Quantity

88182.00

Soft Rock ( 9m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata up to 3m
Rate of sinking 0.15 m / hour
a)

b)

Labour
Mate

day

0.76

232.16

176.44

L-12

Sinker ( skilled )

day

4.00

306.03

1224.12

L-15

Sinking helper ( semi-skilled )

day

14.00

232.16

3250.24

L-14

Diver

day

1.20

232.16

278.59

L-07

hour

6.50

1176.12

7644.78

P&M-075

hour

4.00

513.00

2052.00

P&M-063

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Air compressor with pneumatic breakers

969.68

Consumables in sinking @ 10 per cent of (b)


Add for dewatering @ of 5 per cent of (a+b), if required

1559.59

c)

Overhead charges @ 0.25 on (a+b)

4288.86

d)

Contractor's profit @ 0.1 on (a+b+c)

2144.43
23588.73

Rate per metre = (a+b+c+d)


12.15

say

23589.00

Hard Rock ( 9m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.15 m / hour
a)

b)

c)

Material
Gelatine 80 per cent

Kg

10.00

112.77

1127.71

M-104

Electric Detonators

each

40.00

14.27

570.65

M-094/100

Mate

day

1.17

232.16

271.63

L-12

Driller

day

2.00

232.16

464.32

L-06

Blaster

day

0.25

306.03

76.51

L-03

Mazdoor

day

22.00

221.61

4875.42

L-13

Mazdoor (Skilled)

day

4.00

306.03

1224.12

L-15

Diver

day

1.00

232.16

232.16

L-07

hour

7.00

1176.12

8232.84

P&M-075

Labour

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.

223

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Hire & running charges of compressor with pneumatic


breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.

hour

Quantity
2.50

Rate Rs
513.00

P&M-063

714.42

d)

Overhead charges @ 0.25 on (a+b+c)

4976.31

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2488.16
27369.71

Rate per metre = (a+b+c+d+e)


say

1200

1282.50

Remarks/
Input ref.

832.97

Consumables in sinking @ 10 per cent of cost of (b).

12.16

Cost Rs

27370.00

Sinking of 10 m external diameter well ( other than


pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter
Taking output = 1 m
Diameter of well - 10 m.
A

Sandy Soil

(i)

Depth below bed level upto 3.0 M


Rate of sinking 0.20 m / hour
a)

b)

Labour
Mate

day

0.20

232.16

46.43

L-12

Sinker ( skilled )

day

1.50

306.03

459.05

L-15

Sinking helper ( semi-skilled )

day

3.50

232.16

812.56

L-14

hour

5.00

1176.12

5880.60

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

588.06
1946.67
973.34
10706.71

Rate per metre = (a+b+c+d)


say

12.16 A

(ii)

10707.00

Beyond 3m upto 10m depth


Rate of sinking 0.17 m / hour
a)

b)

Labour
Mate

day

0.31

232.16

71.97

L-12

Sinker

day

2.00

306.03

612.06

L-15

Sinking helper ( semi-skilled )

day

4.25

232.16

986.68

L-14

hour

5.75

1176.12

6762.69

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

676.27
2277.42
1138.71
12525.79

Rate per metre = (a+b+c+d)


say

12.16 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

13152.00

12th m

5%

13810.00

13th m

5%

14501.00

14th m

5%

15226.00

15th m

5%

15987.00

16th m

5%

16786.00

17th m

5%

17625.00

18th m

5%

18506.00

19th m

5%

19431.00

20th m

5%

20403.00

224

12526.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

a
b

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.

(a)

7.5%

21933.00

22nd m

7.5%

23578.00

28294.00

23rd m

7.5%

25346.00

30415.00

24th m

7.5%

27247.00

32696.00

25th m

7.5%

29291.00

35149.00

26th m

7.5%

31488.00

37786.00

27th m

7.5%

33850.00

40620.00

28th m

7.5%

36389.00

43667.00

29th m

7.5%

39118.00

46942.00

30th m

7.5%

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.

50462.00
372351.00

31029.00

37235.00

(b) Including
20% for
Kentledge
55508.00

31st m

10%

46257.00

32nd

10%

50883.00

61060.00

33rd m

10%

55971.00

67165.00

34th m

10%

61568.00

73882.00

35th m

10%

67725.00

81270.00

36th m

10%

74498.00

89398.00

37th m

10%

81948.00

98338.00

38th m

10%

90143.00

108172.00

39th m

10%

99157.00

118988.00

40th m

10%

109073.00

130888.00

Avg Rate per metre


B

42052.00
310292.00

(a)

Total Cost from 30m upto 40m


12.16

(b) Including
20% for
Kentledge
26320.00

21st m

Avg Rate per metre

Remarks/
Input ref.

Beyond 20m upto 30 m

Total Cost from 20m upto 30m


12.16 A

Cost Rs

16543.00

Avg Rate per metre


(iv)

Rate Rs

165427.00

Total Cost from 10m upto 20m


12.16 A

Quantity

737223.00

884669.00

73722.00

88467.00

Clayey Soil (10m dia. Well )


Unit = Running Meter
Taking output = 1 cum

(i)

Depth below bed level upto 3.0 M


Rate of sinking 0.18m/hour.
a)

b)

Labour
Mate

day

0.25

232.16

58.04

L-12

Sinker ( skilled )

day

2.50

306.03

765.08

L-15

Sinking helper ( semi-skilled )

day

5.50

232.16

1276.88

L-14

hour

6.00

1176.12

7056.72

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

705.67

c)

Overhead charges @ 0.25 on (a+b)

2465.60

d)

Contractor's profit @ 0.1 on (a+b+c)

1232.80
13560.78

Rate per metre = (a+b+c+d)


say

12.16 B

(ii)

13561.00

Beyond 3m upto 10m depth


Rate of sinking 0.15m/hour.
a)

Labour
Mate

day

0.40

232.16

92.86

L-12

Sinker

day

3.00

306.03

918.09

L-15

225

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Sinking helper ( semi-skilled )


b)

Quantity

Rate Rs

day

5.50

232.16

1276.88

L-14

hour

6.00

1176.12

7056.72

P&M-075

hour

4.00

513.00

2052.00

P&M-063

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

910.87
3076.86
1538.43
16922.71

Rate per metre = (a+b+c+d)


say

(iii)
a
b

11th m

5%

(a) (b) Including for


dewatering @
5% of cost, if
required
17769.00
18657.00

12th m

5%

18657.00

19590.00

13th m

5%

19590.00

20570.00

14th m

5%

20570.00

21599.00

15th m

5%

21599.00

22679.00

16th m

5%

22679.00

23813.00

17th m

5%

23813.00

25004.00

18th m

5%

25004.00

26254.00

19th m

5%

26254.00

27567.00

20th m

5%

27567.00

28945.00

223502.00

234678.00

22350.00

23468.00

Avg Rate per metre


(iv)
a
b
c

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
(a)

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).
7.5%

29635.00

37044.00

7.5%

31858.00

39823.00

41814.00

33rd m

7.5%

34247.00

42809.00

44949.00

34th m

7.5%

36816.00

46020.00

48321.00

35th m

7.5%

39577.00

49471.00

51945.00

36th m

7.5%

42545.00

53181.00

55840.00

37th m

7.5%

45736.00

57170.00

60029.00

38th m

7.5%

49166.00

61458.00

64531.00

39th m

7.5%

52853.00

66066.00

69369.00

7.5%

56817.00

71021.00

74572.00

Avg Rate per metre


(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

(b) Including
5% for
dewatering, if
required
38896.00

32nd

Total Cost from 30m upto 40m

( c) Including
25% for
Kentledge

31st m

40th m

12.16 B

16923.00

Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

Total Cost from 10m upto 20m


12.16 B

Remarks/
Input ref.

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay
Consumables in sinking @ 10 per cent of (b)

12.16 B

Cost Rs

419250.00

524063.00

550266.00

41925.00

52406.00

55027.00

( c) Including
20% for
Kentledge

(b) Including
5% for
dewatering, if
required
78749.00

(a)

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).
31st m

10%

62499.00

74999.00

32nd

10%

68749.00

82499.00

33rd m

10%

75624.00

90749.00

95286.45

34th m

10%

83186.00

99823.00

104814.15

226

86624.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Cost Rs

10%

91505.00

109806.00

115296.30

36th m

10%

100656.00

120787.00

126826.35

37th m

10%

110722.00

132866.00

139509.30

38th m

10%

121794.00

146153.00

153460.65

39th m

10%

133973.00

160768.00

168806.40

40th m

10%

147370.00

176844.00

185686.20

996078.00

1195294.00

1255058.80

99608.00

119529.00

125506.00

Avg Rate per metre


C

Rate Rs

35th m

Total Cost from 30m upto 40m


12.16

Quantity

Remarks/
Input ref.

Soft Rock (10m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking 0.14m/hour.
a)

b)

Labour
Mate

day

0.86

232.16

199.66

L-12

Sinker ( skilled )

day

4.00

306.03

1224.12

L-15

Sinking helper ( semi-skilled )

day

16.00

232.16

3714.56

L-14

Diver

day

1.40

232.16

325.02

L-07

hour

7.00

1176.12

8232.84

P&M-075

hour

4.25

513.00

2180.25

P&M-063

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Air compressor with pneumatic breakers

1041.31

Consumables in sinking @ 10 per cent of (b)

572.72

Add for dewatering @ 5 per cent of cost, if required


c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

4372.62
2186.31
24049.41

Rate per metre = (a+b+c+d)


12.16

say

24049.00

Hard Rock (10m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.12 m/ hour.
a)

b)

c)

Material
Gelatine 80 per cent

Kg

11.00

112.77

1240.48

M-104

Electric Detonators

each.

44.00

14.27

627.71

M-094/100

Mate

day

1.27

232.16

294.84

L-12

Driller

day

2.00

232.16

464.32

L-06

Blaster

day

0.25

306.03

76.51

L-03

Mazdoor

day

24.00

221.61

5318.64

L-13

Mazdoor (Skilled)

day

4.00

306.03

1224.12

L-15

hour

8.50

1176.12

9997.02

P&M-075

hour

3.00

513.00

1539.00

P&M-063

Labour

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required.

576.80

Consumables in sinking @ 10 per cent of cost of (b+c).

1949.13

d)

Overhead charges @ 0.25 on (a+b+c)

5827.14

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2913.57
32049.28

Rate per metre = (a+b+c+d+e)


say

227

32049.00

Sr No
12.17

Ref. to
MoRTH
Spec.
1200

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Sinking of 11 m external diameter well ( other than


pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter
Taking output = 0.50 m
Diameter of well - 11 m.
A

Sandy Soil

(i)

Depth from bed level upto 3.0 M


Rate of sinking @ 0.15 m/hour
a)

b)

Labour
Mate

day

0.21

232.16

48.75

L-12

Sinker ( skilled )

day

1.50

306.03

459.05

L-15

Sinking helper (semi-skilled)

day

3.30

232.16

766.13

L-14

hour

6.00

1176.12

7056.72

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

705.67
2259.08
1129.54
12424.94

Cost for 0.5m = a+b+c+d

24849.88

Rate per metre = (a+b+c+d)/0.50


say

12.17 A

(ii)

24850.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.13 m/hour
a)

b)

Labour
Mate

day

0.32

232.16

74.29

L-12

Sinker

day

2.00

306.03

612.06

L-15

Sinking helper (semi-skilled)

day

4.50

232.16

1044.72

L-14

hour

4.00

1176.12

4704.48

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b+c)

d)

Contractor's profit @ 0.1 on (a+b+c+d)

470.45
1726.50
863.25
9495.75

Cost for 0.5m = a+b+c+d

18991.50

Rate per metre = (a+b+c+d)/0.50


say

12.17 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

19941.00

12th m

5%

20938.00

13th m

5%

21985.00

14th m

5%

23084.00

15th m

5%

24238.00

16th m

5%

25450.00

17th m

5%

26723.00

18th m

5%

28059.00

19th m

5%

29462.00

20th m

5%

Total Cost from 10m upto 20m

25082.00

Avg Rate per metre


12.17 A

(iv)
a

30935.00
250815.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

228

18991.00

Sr No

Ref. to
MoRTH
Spec.

Description
b

Unit

21st m

7.5%

33255.00

39906.00

22nd m

7.5%

35749.00

42899.00

23rd m

7.5%

38430.00

46116.00

24th m

7.5%

41312.00

49574.00

25th m

7.5%

44410.00

53292.00

26th m

7.5%

47741.00

57289.00

27th m

7.5%

51322.00

61586.00

28th m

7.5%

55171.00

66205.00

29th m

7.5%

59309.00

71171.00

30th m

7.5%

63757.00

76508.00

470456.00

564546.00

47046.00

56455.00

Avg Rate per metre


(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.

(a)

10%

70133.00

32nd

10%

77146.00

92575.00

33rd m

10%

84861.00

101833.00

34th m

10%

93347.00

112016.00

35th m

10%

102682.00

123218.00

36th m

10%

112950.00

135540.00

37th m

10%

124245.00

149094.00

38th m

10%

136670.00

164004.00

39th m

10%

150337.00

180404.00

10%

165371.00

198445.00

Total Cost from 30m upto 40m


Avg Rate per metre
B

Cost Rs

Remarks/
Input ref.

(b) Including
20% for
Kentledge
84160.00

31st m

40th m

12.17

Rate Rs

(a) (b)Including 20%


for Kentledge

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour.

Total Cost from 20m upto 30m


12.17 A

Quantity

1117742.00

1341289.00

111774.00

134129.00

Clayey Soil (11 m dia. Well )


Unit = Running Meter
Taking output = 0.50 meter

(i)

Depth from bed level upto 3.0 M


Rate of sinking @ 0.10 m/hour
a)

b)

Labour
Mate

day

0.26

232.16

60.36

L-12

Sinker ( skilled )

day

2.50

306.03

765.08

L-15

Sinking helper (semi-skilled)

day

4.00

232.16

928.64

L-14

hour

5.00

1176.12

5880.60

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

588.06
2055.68
1027.84
11306.26

Cost for 0.5m = a+b+c+d

22612.53

Rate per metre = (a+b+c+d)/0.50


12.17 B

(ii)

say

22613.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.08 m/hour
a)

b)

Labour
Mate

day

0.43

232.16

99.83

L-12

Sinker

day

3.50

306.03

1071.11

L-15

Sinking helper (semi-skilled)

day

5.75

232.16

1334.92

L-14

hour

6.00

1176.12

7056.72

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
229

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Air compressor with pneumatic chisel attachment for


cutting hard clay
Consumables in sinking @ 10 per cent of (b)

hour

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Quantity
4.25

Rate Rs
513.00

923.70

1583.32
17416.47
34832.93

Rate per metre = (a+b+c+d)/0.50


say

(iii)
a
b

Add 5 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

(a)

5%

36575.00

12th m

5%

38404.00

40324.00

13th m

5%

40324.00

42340.00

14th m

5%

42340.00

44457.00

15th m

5%

44457.00

46680.00

16th m

5%

46680.00

49014.00

17th m

5%

49014.00

51465.00

18th m

5%

51465.00

54038.00

19th m

5%

54038.00

56740.00

5%

56740.00

59577.00

Avg Rate per metre


a
b
c

(a) (c)Including 25%


for Kentledge

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

(b)Including
5% for
dewatering, if
required
80057.00

21st m

7.5%

60996.00

76245.00

22nd

7.5%

65571.00

81964.00

86062.00

23rd m

7.5%

70489.00

88111.00

92517.00

24th m

7.5%

75776.00

94720.00

99456.00

25th m

7.5%

81459.00

101824.00

106915.00

26th m

7.5%

87568.00

109460.00

114933.00

27th m

7.5%

94136.00

117670.00

123554.00

28th m

7.5%

101196.00

126495.00

132820.00

29th m

7.5%

108786.00

135983.00

142782.00

30th m

7.5%

116945.00

146181.00

153490.00

862922.00

1078653.00

1132586.00

86292.00

107865.00

113259.00

(c ) Including
20% for
Kentledge

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

483039.00

48304.00

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

Avg Rate per metre

460037.00

46004.00

Beyond 20m upto 30 m

Total Cost from 20m upto 30m


12.17 B

(b)Including for
dewatering @
5% of cost, if
required
38404.00

11th m

Total Cost from 10m upto 20m


(iv)

34833.00

Beyond 10 m upto 20 m

20th m

12.17 B

2180.25

3166.63

Cost for 0.5m = a+b+c+d

12.17 B

Cost Rs

(a)

31st m

10%

128640.00

154368.00

(b)Including
5% for
dewatering, if
required
162086.00

32nd

10%

141504.00

169805.00

178295.00

33rd m

10%

155654.00

186785.00

196124.00

34th m

10%

171219.00

205463.00

215736.00

35th m

10%

188341.00

226009.00

237309.00

36th m

10%

207175.00

248610.00

261041.00

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

230

Remarks/
Input ref.
P&M-063

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Cost Rs

10%

227893.00

273472.00

287146.00

38th m

10%

250682.00

300818.00

315859.00

39th m

10%

275750.00

330900.00

347445.00

40th m

10%

303325.00

363990.00

382190.00

2050183

2460220

2583231

205018.00

246022.00

258323.00

Avg Rate per metre


C

Rate Rs

37th m

Total Cost from 30m upto 40m


12.17

Quantity

Remarks/
Input ref.

Soft Rock (11m dia well )


Unit = Running Meter.
Taking output = 0.50 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.06 m/hour
a)

b)

Labour
Mate

day

0.95

232.16

220.55

L-12

Sinker ( skilled )

day

4.25

306.03

1300.63

L-15

Sinking helper (semi-skilled)

day

18.00

232.16

4178.88

L-14

Diver

day

1.50

232.16

348.24

L-07

hour

8.00

1176.12

9408.96

P&M-075

hour

4.50

513.00

2308.50

P&M-063

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Air compressor with pneumatic breakers

1171.75

Consumables in sinking @ 10 per cent of (b)

c)

Add for dewatering @ 5 per cent of cost of (b), if


required
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

644.46
4895.49
2447.75
26925.20

Cost for 0.5m = a+b+c+d

53850.41

Rate per metre = (a+b+c+d)/0.50


12.17

say

53850.00

Hard Rock (11m dia well )


Unit = Running Meter.
Taking output = 0.50 m
Depth in hard rock upto 3 m
Rate of sinking @ 0.05 m/hour
a)

Material
Kg

12.00

112.77

1353.25

M-104

each.

48.00

14.27

684.78

M-094/100

Mate

day

1.35

232.16

313.42

L-12

Driller

day

2.00

232.16

464.32

L-06

Blaster

day

0.25

306.03

76.51

L-03

Mazdoor

day

26.00

221.61

5761.86

L-13

Mazdoor (Skilled)

day

4.00

306.03

1224.12

L-15

hour

10.00

1176.12

11761.20

P&M-075

hour

3.50

513.00

1795.50

P&M-063

Gelatine 80 per cent


Electric Detonators
b)

c)

Labour

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required.

677.84

Consumables in sinking @ 10 per cent of cost of (b+c).

2139.69

d)

Overhead charges @ 0.25 on (a+b+c)

6563.12

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3281.56
36097.16

Cost for 0.5m = a+b+c+d

72194.32

Rate per metre = (a+b+c+d)/0.50


say

231

72194.00

Sr No
12.18

Ref. to
MoRTH
Spec.
1200

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Sinking of 12 m external diameter well ( other than


pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter
Taking output = 0.25 m
Diameter of well - 12 m.
A

Sandy Soil

(i)

I) Depth below bed level upto 3.0 M


Rate of sinking @ 0.05 m/hour
a)

b)

Labour
Mate

day

0.22

232.16

51.08

L-12

Sinker ( skilled )

day

1.75

306.03

535.55

L-15

Sinking helper (semi-skilled)

day

4.00

232.16

928.64

L-14

hour

6.00

1176.12

7056.72

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

705.67
2319.41
1159.71
12756.78

Cost for 0.25m = a+b+c+d

51027.13

Rate per metre = (a+b+c+d)/0.25


say

12.18 A

(ii)

51027.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.038 m/hour
a)

b)

Labour
Mate

day

0.37

232.16

85.90

L-12

Sinker

day

2.50

306.03

765.08

L-15

Sinking helper (semi-skilled)

day

4.75

232.16

1102.76

L-14

hour

6.50

1176.12

7644.78

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

764.48

c)

Overhead charges @ 0.25 on (a+b)

2590.75

d)

Contractor's profit @ 0.1 on (a+b+c)

1295.37
14249.11

Cost for 0.25m = a+b+c+d

56996.46

Rate per metre = (a+b+c+d)/0.25


say

12.18 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

59846.00

12th m

5%

62838.00

13th m

5%

65980.00

14th m

5%

69279.00

15th m

5%

72743.00

16th m

5%

76380.00

17th m

5%

80199.00

18th m

5%

84209.00

19th m

5%

88419.00

20th m

5%

75273.00

Avg Rate per metre


12.18 A

(iv)
a

92840.00
752733.00

Total Cost from 10m upto 20m


Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

232

56996.00

Sr No

Ref. to
MoRTH
Spec.

Description
b

Unit

21st m

7.5%

99803.00

119764.00

22nd m

7.5%

107288.00

128746.00

23rd m

7.5%

115335.00

138402.00

24th m

7.5%

123985.00

148782.00

25th m

7.5%

133284.00

159941.00

26th m

7.5%

143280.00

171936.00

27th m

7.5%

154026.00

184831.00

28th m

7.5%

165578.00

198694.00

29th m

7.5%

177996.00

213595.00

7.5%

191346.00

229615.00

Total Cost from 20m upto 30m


Avg Rate per metre
(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports,


loading arrangement, and Labour etc.

1411921.00

1694306.00

141192.00

169431.00

31st m

10%

210481.00

252577.00

32nd

10%

231529.00

277835.00

33rd m

10%

254682.00

305618.00

34th m

10%

280150.00

336180.00

35th m

10%

308165.00

369798.00

36th m

10%

338982.00

406778.00

37th m

10%

372880.00

447456.00

38th m

10%

410168.00

492202.00

39th m

10%

451185.00

541422.00

40th m

10%

496304.00

595565.00

Avg Rate per metre


B

Cost Rs

Remarks/
Input ref.

(a) (b)Including 20%


for Kentledge

Total Cost from 30m upto 40m


12.18

Rate Rs

(a) (b)Including 20%


for Kentledge

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour.

30th m

12.18 A

Quantity

3354526

4025431

335453.00

402543.00

Clayey Soil (12 m dia. Well )


Unit = Running Meter.
Taking output = 0.25 meter.

(i)

Depth below bed level upto 3.0 M


Rate of sinking @ 0.04 m/hour
a)

b)

Labour
Mate

day

0.30

232.16

69.65

L-12

Sinker ( skilled )

day

3.00

306.03

918.09

L-15

Sinking helper (semi-skilled)

day

4.50

232.16

1044.72

L-14

hour

6.25

1176.12

7350.75

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

735.08
2529.57
1264.79
13912.64

Cost for 0.25m = a+b+c+d

55650.56

Rate per metre = (a+b+c+d)/0.25


say

12.18 B

(ii)

55651.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.03 m/hour
a)

b)

Labour
Mate

day

0.48

232.16

111.44

L-12

Sinker

day

3.75

306.03

1147.61

L-15

Sinking helper (semi-skilled)

day

6.00

232.16

1392.96

L-14

Machinery

233

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Hire & running charges of crane with grab bucket of 0.75


cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

Quantity

Rate Rs

8.33

1176.12

9797.08

P&M-075

hour

4.50

513.00

2308.50

P&M-063

1210.56

c)

Overhead charges @ 0.25 on (a+b)

3992.04

d)

Contractor's profit @ 0.1 on (a+b+c)

1996.02
21956.20
87824.81

Rate per metre = (a+b+c+d)/0.25


say

(iii)
a
b

Add 5 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

(a)

a
b
c

5%

12th m

5%

96827.00

101668.00

13th m

5%

101668.00

106751.00

14th m

5%

106751.00

112089.00

15th m

5%

112089.00

117693.00

16th m

5%

117693.00

123578.00

17th m

5%

123578.00

129757.00

18th m

5%

129757.00

136245.00

19th m

5%

136245.00

143057.00

20th m

5%

143057.00

150210.00

1159881.00

1217875.00

115988.00

121788.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
(a) (c)Including 25%
for Kentledge

21st m

7.5%

153786.00

192233.00

(b)Including
5% for
dewatering, if
required
201845.00

22nd

7.5%

165320.00

206650.00

216983.00

23rd m

7.5%

177719.00

222149.00

233256.00

24th m

7.5%

191048.00

238810.00

250751.00

25th m

7.5%

205377.00

256721.00

269557.00

26th m

7.5%

220780.00

275975.00

289774.00

27th m

7.5%

237339.00

296674.00

311508.00

28th m

7.5%

255139.00

318924.00

334870.00

29th m

7.5%

274274.00

342843.00

359985.00

30th m

7.5%

294845.00

368556.00

386984.00

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

Total Cost from 20m upto 30m


Avg Rate per metre
12.18 B

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

b
c

92216.00

(b)Including for
dewatering @
5% of cost, if
required
96827.00

11th m

Avg Rate per metre


(iv)

87825.00

Beyond 10 m upto 20 m

Total Cost from 10m upto 20m


12.18 B

2175627

2719535

2855513

217563.00

271954.00

285551.00

(c ) Including
20% for
Kentledge

(a)

31st m

10%

324330.00

389196.00

(b)Including
5% for
dewatering, if
required
408656.00

32nd

10%

356763.00

428116.00

449522.00

33rd m

10%

392439.00

470927.00

494473.00

34th m

10%

431683.00

518020.00

543921.00

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

234

Remarks/
Input ref.

hour

Cost for 0.25m = a+b+c+d

12.18 B

Cost Rs

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Cost Rs

10%

474851.00

569821.00

598312.00

36th m

10%

522336.00

626803.00

658143.00

37th m

10%

574570.00

689484.00

723958.00

38th m

10%

632027.00

758432.00

796354.00

39th m

10%

695230.00

834276.00

875990.00

40th m

10%

764753.00

917704.00

963589.00

5168982

6202779

6512918

516898.00

620278.00

651292.00

Avg Rate per metre


C

Rate Rs

35th m

Total Cost from 30m upto 40m


12.18

Quantity

Remarks/
Input ref.

Soft Rock (12m dia well )


Unit = Running Meter
Taking output = 0.25 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.025 m/hour
a)

b)

Labour
Mate

day

1.06

232.16

246.09

L-12

Sinker ( skilled )

day

4.50

306.03

1377.14

L-15

Sinking helper (semi-skilled)

day

20.00

232.16

4643.20

L-14

Diver

day

1.75

232.16

406.28

L-07

hour

10.00

1176.12

11761.20

P&M-075

hour

4.75

513.00

2436.75

P&M-063

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

1419.80
780.89

Add for dewatering @ 5 per cent, if required


c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

5767.83
2883.92
31723.09

Cost for 0.25m = a+b+c+d

126892.35

Rate per metre = (a+b+c+d)/0.25


12.18

say

126892.00

Hard Rock (12m dia well )


Unit = Running Meter
Taking output = 0.25 m

(i)

Depth in hard rock strata upto 3 m


Rate of sinking @ 0.020 m/hour
a)

Material
Kg

14.00

112.77

1578.79

M-104

each.

56.00

14.27

798.90

M-094/100

Mate

day

1.44

232.16

334.31

L-12

Driller

day

2.00

232.16

464.32

L-06

Blaster

day

0.25

306.03

76.51

L-03

Mazdoor

day

28.00

221.61

6205.08

L-13

Mazdoor (Skilled)

day

4.50

306.03

1377.14

L-15

hour

12.50

1176.12

14701.50

P&M-075

hour

4.00

513.00

2052.00

P&M-063

Gelatine80 per cent


Electric detonator
b)

c)

Labour

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent, if required.

837.68

Consumables in sinking @ 10 per cent of (c).

1759.12

d)

Overhead charges @ 0.25 on (a+b+c)

7546.34

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3773.17
41504.85

Cost for 0.25m = a+b+c+d+e

166019.39

Rate per metre = (a+b+c+d+e)/0.25


say

235

166019.00

Sr No
12.19

Ref. to
MoRTH
Spec.
1200

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Sinking of Twin D Type well (other than pneumatic


method of sinking) through all types of strata namely
sandy soil, clayey soil and rock as shown against each
case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter
Taking output = 1 m
Dimensions of well.
Overall length = 12 m
Overall width = 6 m
A
(i)

Sandy Soil
Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a)

b)

Labour
Mate

day

0.20

232.16

46.43

L-12

Sinker ( skilled )

day

1.25

306.03

382.54

L-15

Sinking helper (semi-skilled)

day

3.75

232.16

870.60

L-14

hour

5.50

1176.12

6468.66

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

646.87
2103.77
1051.89
11570.76

Rate per metre = (a+b+c+d)


say

12.19 A

(ii)

11571.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.17 m/hour
a)

b)

Labour
Mate

day

0.30

232.16

69.65

L-12

Sinker

day

1.50

306.03

459.05

L-15

Sinking helper (semi-skilled)

day

4.00

232.16

928.64

L-14

hour

5.88

1176.12

6915.59

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

691.56
2266.12
1133.06
12463.66

Rate per metre = (a+b+c+d)


say

12.19 A

(iii)
a

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

13087.00

12th m

5%

13741.00

13th m

5%

14428.00

14th m

5%

15149.00

15th m

5%

15906.00

16th m

5%

16701.00

17th m

5%

17536.00

18th m

5%

18413.00

19th m

5%

19334.00

20th m

5%

Total Cost from 10m upto 20m

16460.00

Avg Rate per metre


12.19 A

(iv)
a

20301.00
164596.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

236

12464.00

Sr No

Ref. to
MoRTH
Spec.

Description
b

Unit

21st m

7.5%

21824.00

26189.00

22nd m

7.5%

23461.00

28153.00

23rd m

7.5%

25221.00

30265.00

24th m

7.5%

27113.00

32536.00

25th m

7.5%

29146.00

34975.00

26th m

7.5%

31332.00

37598.00

27th m

7.5%

33682.00

40418.00

28th m

7.5%

36208.00

43450.00

29th m

7.5%

38924.00

46709.00

30th m

7.5%

41843.00

50212.00

308754.00

370505.00

30875.00

37051.00

Avg Rate per metre


(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.

31st m

10%

46027.00

55232.00

32nd

10%

50630.00

60756.00

33rd m

10%

55693.00

66832.00

34th m

10%

61262.00

73514.00

35th m

10%

67388.00

80866.00

36th m

10%

74127.00

88952.00

37th m

10%

81540.00

97848.00

38th m

10%

89694.00

107633.00

39th m

10%

98663.00

118396.00

40th m

10%

108529.00

130235.00

Avg Rate per metre


B

Cost Rs

Remarks/
Input ref.

(a) (b)Including 20%


for Kentledge

Total Cost from 30m upto 40m


12.19

Rate Rs

(a) (b)Including 20%


for Kentledge

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour.

Total Cost from 20m upto 30m


12.19 A

Quantity

733553.00

880264.00

73355.00

88026.00

Clayey Soil (Twin D Type Well )


Unit = Running Meter
Taking output = 1 meter

(i)

Depth below bed level upto 3.0 M


Rate of sinking @ 0.16 m/hour
a)

b)

Labour
Mate

day

0.26

232.16

60.36

L-12

Sinker ( skilled )

day

2.50

306.03

765.08

L-15

Sinking helper (semi-skilled)

day

4.00

232.16

928.64

L-14

hour

6.25

1176.12

7350.75

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

735.08
2459.98
1229.99
13529.86

Rate per metre = (a+b+c+d)


12.19 B

(ii)

say

13530.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.15 m/hour
a)

b)

Labour
Mate

day

0.45

232.16

104.47

L-12

Sinker

day

3.25

306.03

994.60

L-15

Sinking helper (semi-skilled)

day

6.00

232.16

1392.96

L-14

hour

6.67

1176.12

7844.72

P&M-075

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.

237

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Air compressor with pneumatic chisel attachment for


cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

hour

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Quantity
4.50

Rate Rs
513.00

3415.14
1707.57
18783.29

say

(iii)
a
b

Add 5 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

(a)

a
b
c

5%

19722.00

12th m

5%

20708.00

21743.00

13th m

5%

21743.00

22830.00

14th m

5%

22830.00

23972.00

15th m

5%

23972.00

25171.00

16th m

5%

25171.00

26430.00

17th m

5%

26430.00

27752.00

18th m

5%

27752.00

29140.00

19th m

5%

29140.00

30597.00

20th m

5%

30597.00

32127.00

248065.00

260470.00

24807.00

26047.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
(a) (c)Including 25%
for Kentledge

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).
7.5%

32892.00

41115.00

22nd

7.5%

35359.00

44199.00

46409.00

23rd m

7.5%

38011.00

47514.00

49890.00

24th m

7.5%

40862.00

51078.00

53632.00

25th m

7.5%

43927.00

54909.00

57654.00

26th m

7.5%

47222.00

59028.00

61979.00

27th m

7.5%

50764.00

63455.00

66628.00

28th m

7.5%

54571.00

68214.00

71625.00

29th m

7.5%

58664.00

73330.00

76997.00

30th m

7.5%

63064.00

78830.00

82772.00

Avg Rate per metre


(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

b
c

(b)Including
5% for
dewatering, if
required
43171.00

21st m

Total Cost from 20m upto 30m


12.19 B

(b)Including for
dewatering @
5% of cost, if
required
20708.00

11th m

Avg Rate per metre


(iv)

18783.00

Beyond 10 m upto 20 m

Total Cost from 10m upto 20m


12.19 B

2308.50
1015.32

Rate per metre = (a+b+c+d)


12.19 B

Cost Rs

465336.00

581672.00

610757.00

46534.00

58167.00

61076.00

(c ) Including
20% for
Kentledge

(b)Including
5% for
dewatering, if
required
87406.00

(a)

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).
31st m

10%

69370.00

32nd

10%

76307.00

91568.00

96146.00

33rd m

10%

83938.00

100726.00

105762.00

34th m

10%

92332.00

110798.00

116338.00

35th m

10%

101565.00

121878.00

127972.00

36th m

10%

111722.00

134066.00

140769.00

37th m

10%

122894.00

147473.00

154847.00

238

83244.00

Remarks/
Input ref.
P&M-063

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Cost Rs

10%

135183.00

162220.00

170331.00

39th m

10%

148701.00

178441.00

187363.00

40th m

10%

163571.00

196285.00

206099.00

1105583.00

1326699.00

1393033.00

110558.00

132670.00

139303.00

Avg Rate per metre


C

Rate Rs

38th m

Total Cost from 30m upto 40m


12.19

Quantity

Remarks/
Input ref.

Soft Rock (Twin D Type Well )


Unit = Running Meter
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.12 m/hour
a)

b)

Labour
Mate

day

0.86

232.16

199.66

L-12

Sinker ( skilled )

day

4.50

306.03

1377.14

L-15

Sinking helper (semi-skilled)

day

15.00

232.16

3482.40

L-14

Diver

day

1.50

232.16

348.24

L-07

hour

8.33

1176.12

9797.08

P&M-075

hour

6.00

513.00

3078.00

P&M-063

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Air compressor with pneumatic breakers

1287.51

Consumables in sinking @ 10 per cent of (b)

708.13

Add for dewatering @ 5 per cent, if required


c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

5069.54
2534.77
27882.46

Rate per metre = (a+b+c+d)

12.19

say

27882.00

Hard Rock (Twin D Type Well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.10 m/hour
a)

b)

c)

Material
Geletine80 per cent

Kg

10.00

112.77

1127.71

M-104

Electric detonators

each.

40.00

14.27

570.65

M-094/100

Mate

day

1.34

232.16

311.09

L-12

Driller

day

2.00

232.16

464.32

L-06

Blaster

day

0.25

306.03

76.51

L-03

Mazdoor

day

25.00

221.61

5540.25

L-13

Mazdoor (Skilled)

day

4.25

306.03

1300.63

L-15

hour

10.00

1176.12

11761.20

P&M-075

hour

3.00

513.00

1539.00

P&M-063

Labour

Machinery
Hire & running charges of crane with grab bucket of 0.75
cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost of (b+c), if required.

1049.65

Consumables in sinking @ 10 per cent of (b).

1434.98

d)

Overhead charges @ 0.25 on (a+b+c)

6294.00

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3147.00
34616.99

Rate per metre = (a+b+c+d+e)


say

239

34617.00

Sr No
12.20

Ref. to
MoRTH
Spec.
1200

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Pneumatic sinking of wells with equipment of approved


design, drawing and specifications worked by competent
and trained personnel and comprising of compression
and decompression chambers, reducers, two air locks
separately for men and plant & materials, arrangement for
supply of fresh air to working chambers, check valves,
exhaust valves, shafts made from steel plates of riveted
construction not less than 6 mm thick to withstand an air
pressure of 0.50 MPa, controlled blasting of hard rock
where required, staircases and 1 m wide landing
plateforms with railing, arrangement for compression and
decompression, electric lighting of 50 V maximum,
proper rooms for rest and medical examinations and
compliance with safety precautions as per IS:4138, all as
per clause1207.6 of MoRTH Specifications.
Unit - 1 cum
Taking output = 5 cum
a)

Material
M35 grade RCC corbel provided for supporting of
equipment (Dimensions as per ground conditions). Rate
may be adopted vide Item 12.8 (H)
HYSD bar reinforcement in corbel

Cum

8.00

3504.00

28032.00

Item 12.8
(H)

tonne

0.48

36191.33

17371.84

M-082

Blasting material
Kg

1.50

112.77

169.16

M-104

each

6.00

14.27

85.60

M-094/100

Medical Officer

day

0.50

353.52

176.76

L-16

Para medical personnel

day

1.00

0.00

0.00

L-19

Mate

day

1.86

232.16

431.82

L-12

Driller

day

1.00

232.16

232.16

L-06

Blaster

day

0.50

306.03

153.02

L-03

Mazdoor (for cutting, blasting, cleaning, removal of


Material etc.)
Mazdoor (Skilled) (for fixation and removal of adopter for
air lock, carrying out mechanical and electrical
operations and repairs and other skilled jobs.)
Diver

day

30.00

221.61

6648.30

L-13

day

10.00

306.03

3060.30

L-15

day

4.00

232.16

928.64

L-07

hour

6.00

#VALUE!

P&M-082

Gelatine 80 per cent


Electric detonators
b)

c)

Labour

Machinery
(i) Induction, deinduction and erection of plant and
equipment including all components and
accessories for pneumatic method of well sinking.

100000.00

L.S

Induction and deinduction

150000.00

L.S

Erection at site and commissioning

Note

Value

6.00

3834.00

23004.00

P&M-038

hour

2x6

293.76

3525.12

P&M-001

Hire and running charges of crane of 15 tonne capacity

hour

6.00

770.04

4620.24

P&M-072

Motorised barge of 20 tonne capacity

hour

6.00

142.56

855.36

P&M-066

Boat to carry atleast 20 persons

hour

6.00

142.56

855.36

P&M-066

Electric generating set 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Tipper 10 tonne capacity

hour

6.00

830.00

4980.00

P&M-048

Usage of plant and equipment for pneumatic method of


well sinking
Air compressor 250 cfm, 2 nos.

hour

#VALUE!

d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 5 cum = a+b+c+d+e (see notes below)

#VALUE!

Rate per cum = (a+b+c+d+e)/5

#VALUE!

1.The cost of induction, deinduction and erection of


equipment shall be divided by the total quantity of pneumatic
sinking for all the wells of a particular bridge to arrive at the
per cum rate on account of this item.

240

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

2.Cost of pneumatic sinking per cum of individual wells will be


added to the cost indicated at (1) above to arrive at the final
rate of pneumatic sinking per cum.
3.The cost of induction and deinduction will depend upon the
distance involved for shifting of equipment which may be
assessed in individual cases as per actual ground conditions
at the time of making of cost estimates.
4.In case pneumatic sinking is involved on a dry bed, the
provision of barge and boat may be omitted.
5.The necessity and dimensions of the corbel will be as per
actual ground conditions.
6.Small equipments like welding sets, pumps, vibrators,
pneumatic tools, portable lamps, fire extinguishers, hose
pipes etc., have not been included as the same are covered
as items of minor T&P under overhead charges.
7.Depth of sinking shall be restricted to 30 m.
12.21

1207

Sand Filling in Wells complete as per Drawing and


Technical Specifications.
Unit = 1 cum
Taking output = 1 cum
a)

Material
cum

1.20

120.42

Mate

day

0.01

232.16

2.32

L-12

Mazdoor

day

0.30

221.61

66.48

L-13

Sand (assuming 20 per cent voids )


b)

1200 &
1900

M-006

Labour

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

53.33
26.66
293.30

Rate per cum (a+b+c+d)


12.22

144.50

say

293.00

39895.00

Providing Steel Liner 10 mm thick for Curbs and 6 mm


thick for Steining of Wells including Fabricating and
Setting out as per Detailed Drawing.
Unit = 1 MT
Taking output = 1 MT
a)

Material
tonne

1.05

37995.24

Mate

day

1.24

232.16

287.88

L-12

Fitter

day

6.00

306.03

1836.18

L-08

Blacksmith

day

5.00

306.03

1530.15

L-01

Welder

day

5.00

353.52

1767.60

L-02

Mazdoor

day

10.00

221.61

2216.10

L-13

i) Structural steel including 5 per cent wastage


b)

c)

Electrodes, cutting gas and other consumables @ 5 per


cent on cost a (a) above.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1994.75
12381.91
6190.96
68100.53

Rate for per MT (a+b+c+d)


12.23

1100 &
1700

M-179

Labour

say

68101.00

5243.00

34708.66

Bored cast-in-situ M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-750 mm
Unit = meter
Taking output = 15 m
a)

Materials
cum

PCC Grade M35


Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.

241

6.62

Item 12.11
(C) iv

Sr No

Ref. to
MoRTH
Spec.

Description
b)

c)

Unit

Quantity

Rate Rs

Machinery( for boring and construction )


hour

6.00

5023.08

30138.48

P&M-036

hour

0.50

532.00

266.00

P&M-013

hour

6.00

Loader I cum bucket capacity.

hour

0.30

Rate included in
piling rig
1116.00

334.80

P&M-017

Tipper 5.5 cum capacity for disposal of muck from pile


bore hole
Bentonite

hour

0.30

830.00

249.00

P&M-048

kg

300.00

2.24

673.49

M-071

Mate/Supervisor

day

0.14

232.16

32.50

L-12

Mazdoor

day

3.50

221.61

775.64

L-13

Labour

d)

Overhead charges @ 0.25 on (b+c)

e)

Contractor's profit @ 0.1 on (b+c+d)

8117.48
4058.74
79354.79
5290.32

Rate per metre (a+b+c+d+e)/15

1100,160
0 & 1700

Remarks/
Input ref.

Hire and running charges of hydraulic piling rig with


power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering
reinforcement cage
Hire and running charges of Bentonite pump

Cost for 15 m = a+b+c+d+d+e

12.24

Cost Rs

say

5290.00

Bored cast-in-situ M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-1000 mm
Unit = meter
Taking output = 10 m
a)

Materials
cum

7.85

5243.00

41157.55

Item 12.11
(C) iv

Hire and running charges of hydraulic piling rig with


power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering
reinforcement cage
Hire and running charges of Bentonite pump

hour

6.00

5023.08

30138.48

P&M-036

hour

0.50

532.00

266.00

P&M-013

hour

6.00

Loader I cum bucket capacity.

hour

0.40

Rate included in
piling rig
1116.00

446.40

P&M-017

Tipper 5.5 cum capacity for disposal of muck from pile


bore hole
Bentonite

hour

0.40

830.00

332.00

P&M-048

kg

350.00

2.24

785.74

M-071

Mate/Supervisor

day

0.16

232.16

37.15

L-12

Mazdoor

day

4.00

221.61

886.44

L-13

PCC Grade M35


Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)

c)

Machinery( for boring and construction )

Labour

d)

Overhead charges @ 0.25 on (b+c)

e)

Contractor's profit @ 0.1 on (b+c+d)

8223.05
4111.53
86384.34

Cost for 10 m = a+b+c+d+d+e

8638.43

Rate per metre (a+b+c+d+e)/10


12.25

1100 &
1700

say

8638.00

5243.00

53321.31

Bored cast-in-situ M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
a)

Materials
cum

PCC Grade M35

242

10.17

Item 12.11
(C) iv

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)

c)

Machinery( for boring and construction )


Hire and running charges of hydraulic piling rig with
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering
reinforcement cage
Hire and running charges of Bentonite pump

hour

6.00

5023.08

30138.48

P&M-036

hour

0.50

532.00

266.00

P&M-013

hour

6.00

Loader I cum bucket capacity.

hour

0.50

Rate included in
piling rig
1116.00

558.00

P&M-017

Tipper 5.5 cum capacity for disposal of muck from pile


bore hole
Bentonite

hour

0.50

830.00

415.00

P&M-048

864.32

M-071

kg

385.00

2.24

Mate/Supervisor

day

0.18

232.16

41.79

L-12

Mazdoor

day

4.50

221.61

997.25

L-13

Labour

d)

Overhead charges @ 0.25 on (b+c)

e)

Contractor's profit @ 0.1 on (b+c+d)

8320.21
4160.10
99082.45

Cost for 9 m = a+b+c+d+d+e

11009.16

Rate per metre (a+b+c+d+e)/9


12.26

1100 &
1700

say

11009.00

5243.00

92591.38

Item 12.11
(C) iv

Driven cast-in-place vertical M35 grade R.C.C. Pile


excluding Reinforcement complete as per Drawing and &
Technical Specification
Pile diameter - 750 mm
Unit = Running meter
Taking output = 40 metre
a)

Materials
cum

17.66

i) C.I. shoes for the pile

Kg

160.00

56.39

9021.68

M-080

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m

Kg

70.00

66.31

4641.36

M-124

50.00

51.16

2558.23

M-173

c)

iii) Steel helmet and cushion block on top of casing head


during driving
Machinery

Kg

hour

6.00

5023.08

30138.48

P&M-085

hour

0.50

599.40

299.70

P&M-070

d)

Hire and running charges of piling rig Including double


acting pile driving hammer complete with power unit and
accessories..
Hiring and running charges for light crane 5 tonnes
lifting capacity for lowering reinforcement and handling
steel casing.
Labour
Mate/Supervisor

day

0.12

232.16

27.86

L-12

Mazdoor

day

3.00

221.61

664.83

L-13

PCC Grade M35


Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
b) Materials Pile shoes

e)

Overhead charges @ 0.25 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

11838.04
5919.02
157700.59

Cost for 40 m = a+b+c+d+e

3942.51

Rate per metre (a+b+c+d+e)/40


say

Note

1.The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven castin-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
243

3943.00

Sr No
12.27

Ref. to
MoRTH
Spec.
1100 &
1700

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Driven cast-in-place vertical M35 grade R.C.C. Pile


excluding Reinforcement complete as per Drawing and &
Technical Specification
Pile diameter - 1000 mm
Unit = Running meter
Taking output = 30 metre
a)

Materials
cum

23.55

i) C.I. shoes for the pile

Kg

160.00

56.39

9021.68

M-080

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m

Kg

70.00

66.31

4641.36

M-124

Kg

50.00

51.16

2558.23

M-173

c)

iii) Steel helmet and cushion block on top of casing head


during driving
Machinery

hour

6.00

5023.08

30138.48

P&M-085

hour

0.50

599.40

299.70

P&M-070

hour

0.50

532.00

266.00

P&M-013

d)

Hire and running charges of piling rig Including double


acting pile driving hammer complete with power unit and
accessories.
Hiring and running charges for light crane 5 tonnes
lifting capacity for lowering reinforcement and handling
steel casing.
Hire and running charges for light crane for lowering
reinforcement cage.
Labour
Mate/Supervisor

day

0.16

232.16

37.15

L-12

Mazdoor

day

4.00

221.61

886.44

L-13

PCC Grade M35

5243.00

123472.65

Item 12.11
(C) iv

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes

e)

Overhead charges @ 0.25 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

11962.26
5981.13
189265.09

Cost for 30 m = a+b+c+d+e

6308.84

Rate per metre (a+b+c+d+e)/30


Note

12.28

1100 &
1700

say

6309.00

5243.00

118544.23

1.The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven castin-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
Driven cast-in-place vertical M35 grade R.C.C. Pile
excluding Reinforcement complete as per Drawing and &
Technical Specification
Pile diameter - 1200 mm
Unit = Running meter
Taking output = 20 metre
a)

Materials
cum

22.61

i) C.I. shoes for the pile

Kg

160.00

56.39

9021.68

M-080

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m

Kg

70.00

66.31

4641.36

M-124

iii) Steel helmet on top of casing head during driving

Kg

50.00

51.16

2558.23

M-173

hour

6.00

5023.08

30138.48

P&M-085

hour

0.50

599.40

299.70

P&M-070

PCC Grade M35

Item 12.11
(C) iv

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes

c)

Machinery
Hire and running charges of piling rig Including double
acting pile driving hammer complete with power unit and
accessories.
Hiring and running charges for light crane 5 tonnes
lifting capacity for lowering reinforcement and handling
steel casing.
244

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Unit

Quantity

Rate Rs

Labour
day

0.18

232.16

41.79

L-12

Mazdoor

day

4.50

221.61

997.25

L-13

e)

Overhead charges @ 0.25 on (b+c+d)

11924.62

f)

Contractor's profit @ 0.1 on (b+c+d+e)

5962.31
184129.66
9206.48

Rate per metre (a+b+c+d+e)/20

12.29

1100 &
1700

Remarks/
Input ref.

Mate/Supervisor

Cost for 20 m = a+b+c+d+e

Note

Cost Rs

say

9206.00

1.The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven castin-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification
Pile Diameter = 500 mm
Unit = Running Meter
Taking output = 60 m
a)

Materials
cum

11.78

4962.00

58452.36

Item 12.11
(F) iv

a) C.I Shoes

Kg

240.00

56.39

13532.53

M-080

b) M.S. shoes

Kg

105.00

42.08

4418.43

M-125

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery

Kg

30.00

51.16

1534.94

M-173

Crane20 t capacity

hour

6.00

785.16

4710.96

P&M-073

Vibrating Pile driving hammer complete with power unit


and accessories.
Labour

hour

6.00

#VALUE!

P&M-092

Mate/Supervisor

day

0.12

232.16

27.86

L-12

Mazdoor

day

3.00

221.61

664.83

L-13

RCC Grade M35


Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes

c)

d)

Value

e)

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Overhead charges @ 0.25 on (b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

#VALUE!

#VALUE!

Cost for 60 m = a+b+c+d+e+f

#VALUE!

Rate per metre (a+b+c+d+e+f)/60


Note

12.30

1100 &
1700

say

#VALUE!

4962.00

109560.96

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification
Pile Diameter = 750 mm
Unit = Running Meter
Taking output = 50 m
a)

Materials
cum

RCC Grade M35


Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
245

22.08

Item 12.11
(F) iv

Sr No

Ref. to
MoRTH
Spec.

Description

c)

d)

Unit

Quantity

Rate Rs

Kg

160.00

56.39

9021.68

M-080

b) M.S. shoes

Kg

70.00

42.08

2945.62

M-125

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery

Kg

40.00

51.16

2046.59

M-173

Crane 40 T capacity

hour

6.00

1166.40

6998.40

P&M-074

Vibrating Pile driving hammer complete with power unit


and accessories.
Labour

hour

6.00

#VALUE!

P&M-092

Mate/Supervisor

day

0.16

232.16

37.15

L-12

Mazdoor

day

4.00

221.61

886.44

L-13

Value

e)

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Overhead charges @ 0.25 on (b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

#VALUE!

#VALUE!
#VALUE!

Rate per metre (a+b+c+d+e+f)/50

12.31

1100 &
1700

Remarks/
Input ref.

a) C.I. shoes

Cost for 50 m = a+b+c+d+e+f

Note

Cost Rs

say

#VALUE!

4962.00

155806.80

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification
Pile Diameter = 1000 mm
Unit = Running Meter
Taking output = 40 m
a)

Materials
cum

31.40

a) C.I. shoes for the pile

Kg

160.00

56.39

9021.68

M-080

b) M.S. shoes @ 35 Kg per pile of 15 m

Kg

70.00

42.08

2945.62

M-125

Kg

50.00

51.16

2558.23

M-173

c)

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery
Crane 50 t capacity.

hour

6.00

1176.12

7056.72

P&M-011

hour

6.00

#VALUE!

P&M-092

d)

Vibrating Pile driving hammer complete with power unit


and accessories.
Labour
Mate/Supervisor

day

0.20

232.16

46.43

L-12

Mazdoor

day

5.00

221.61

1108.05

L-13

RCC Grade M35

Item 12.11
(F) iv

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes

Value

#VALUE!

e)

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Overhead charges @ 0.25 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

#VALUE!

#VALUE!

Cost for 40 m = a+b+c+d+e+f

#VALUE!

Rate per metre (a+b+c+d+e+f)/40


say

Note

12.32

1100&17
00

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification
Size of pile - 300 mm x 300 mm
Unit = Running Meter
Taking output = 60 m

246

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description
a)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Materials

RCC Grade M-35


Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes

c)

1100
&1700

4962.00

26794.80

Item 12.11
(F) iv

kg

240.00

56.39

13532.53

M-080

b) M. S shoes

kg

105.00

42.08

4418.43

M-125

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery

Kg

30.00

51.16

1534.94

M-173

hour

6.00

627.48

3764.88

P&M-071

hour

6.00

#VALUE!

P&M-092

Mate/Supervisor

day

0.12

232.16

Mazdoor

day

3.00

221.61

Vibrating Pile driving hammer complete with power unit


and accessories.
d ) Labour

12.33

5.40

a) C I shoes

Crane 10 tonne capacity

Note

cum

Value

27.86

L-12

664.83

L-13

#VALUE!

e)

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Overhead charges @ 0.25 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

#VALUE!

Cost for 60 m = a+b+c+d+e+f

#VALUE!

Rate per metre (a+b+c+d+e+f)/60

#VALUE!

say

#VALUE!

4962.00

62025.00

Item 12.11
(F) iv

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification
Size of pile - 500 mm x 500 mm
Unit = Running Meter
Taking output = 50 m
a)

Materials

RCC Grade M-35


cum

12.50

kg

160.00

56.39

9021.68

M-080

b) M. S shoes

kg

70.00

42.08

2945.62

M-125

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery

Kg

30.00

51.16

1534.94

M-173

hour

6.00

785.16

4710.96

P&M-073

hour

6.00

#VALUE!

P&M-092

Mate/Supervisor

day

0.16

232.16

37.15

L-12

Mazdoor

day

4.00

221.61

886.44

L-13

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C I shoes

c)

Crane 20 tonne capacity


Vibrating Pile driving hammer complete with power unit
and accessories.
d ) Labour

Value

#VALUE!

e)

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Overhead charges @ 0.25 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

#VALUE!

#VALUE!

Cost for 50 m = a+b+c+d+e+f

#VALUE!

Rate per metre (a+b+c+d+e+f)/50


say

Note

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.

247

#VALUE!

Sr No
12.34

Ref. to
MoRTH
Spec.
1100
&1700

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Driven precast vertical M35 grade R.C.C. Piles excluding


Reinforcement complete as per Drawing and & Technical
Specification
Size of pile - 750 mm x 750 mm
Unit = Running Meter
Taking output = 40 m
a)

Materials

RCC Grade M-35


cum

22.50

a) C I shoes

kg

160.00

56.39

9021.68

M-080

b) M. S shoes

kg

70.00

42.08

2945.62

M-125

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery

Kg

30.00

51.16

1534.94

M-173

hour

6.00

785.16

4710.96

P&M-073

hour

6.00

#VALUE!

P&M-092

Mate/Supervisor

day

0.18

232.16

41.79

L-12

Mazdoor

day

4.50

221.61

997.25

L-13

Rate for concrete may be adopted same as for bottom


plug vide item no. 13.11( F ) (IV)
b ) Material

4962.00

111645.00

Item 12.11
(F) iv

Pile shoes

c)

Crane 20 tonne capacity


Vibrating Pile driving hammer complete with power unit
and accessories.
d ) Labour

Value

#VALUE!

e)

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Overhead charges @ 0.25 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

#VALUE!

#VALUE!

Cost for 40 m = a+b+c+d+e+f

#VALUE!

Rate per metre (a+b+c+d+e+f)/40


Note

12.35

1100,
1900

say

#VALUE!

6.04

37995.24

229491.24

627.48

3764.88

P&M-071

#VALUE!

P&M-092

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven Vertical Steel Piles complete as per Drawing and &
Technical Specification
Section of the pile - H Section steel column 400 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 70 m
a)

Materials

b)

Structural steel including 5 per cent wastage @ 82.20


kg/m
Machinery

c)

tonnes

Crane 10 T capacity

hour

6.00

Vibrating Pile driving hammer complete with power unit


and other accessories.
Labour

hour

6.00

Mate/Supervisor

day

0.12

232.16

27.86

L-12

Mazdoor

day

3.00

221.61

664.83

L-13

Value

#VALUE!

d)

Add 0.5 per cent of (a+b+c) for providing steel


helmet on top of pile head during driving, stacking of
piles at site, providing anti-corrosion treatment and other
imponderables during installation.
Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

#VALUE!

#VALUE!

Cost for 70 m = a+b+c+d+e

#VALUE!

Rate per metre (a+b+c+d+e)/70


say

12.36

1100
&1900

M-179

Driven Vertical Steel Piles complete as per Drawing and &


Technical Specification

248

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Section of the pile - H Section steel column 450 x 250 mm


(ISHB Series)
Unit = Running Meter
Taking output = 60 m
a)

Materials

b)

Structural steel including 5 per cent wastage @92.50


kg/m
Machinery

c)

12.37

1100

tonnes

5.83

37995.24

221512.24

627.48

3764.88

P&M-071

#VALUE!

P&M-092

Crane 10 T capacity

hour

6.00

Vibrating Pile driving hammer complete with power unit


and accessories.
Labour

hour

6.00

Mate/Supervisor

day

0.14

232.16

Mazdoor

day

3.50

221.61

Value

M-179

32.50

L-12

775.64

L-13

Add 0.5 per cent of (a+b+c) for providing steel


helmet and cushion block on top of pile head during
driving, stacking of piles at site, providing anti-corrosive
treatment and other imponderables during installation.

#VALUE!

d)

Overhead charges @ 0.25 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 60 m = a+b+c+d+e

#VALUE!

Rate per metre (a+b+c+d+e)/60

#VALUE!

say

#VALUE!

300.00

Pile Load Test on single Vertical Pile in accordance with


IS:2911(Part-IV)
Unit = 1 MT
Taking output = 1 MT

Note

12.38

1100,
1500
&1700

a) Initial and routine load test

tonne

1.00

300.00

b) Lateral load test

tonne

1.00

5000.00

5000.00
5300.00

Although, this item is incidental to work and is not required to


be included in BOQ of contract, the same is required to be
added in the estimate to assess cost of work.
Cement Concrete for Reinforced Concrete in Pile Cap
complete as per Drawing and Technical Specification

RCC Grade M20


Unit = cum
Taking output = 15 cum

(i)

Using Concrete Mixer


a)

Material
tonne

5.12

5210.53

26677.89

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

20 mm Aggregate

cum

8.10

938.92

7605.25

M-053

10 mm Aggregate

cum

5.40

723.14

3904.96

M-051

Mate

day

0.90

232.16

208.94

L-12

Mason

day

1.50

306.03

459.05

L-10

Mazdoor for concreting

day

20.00

221.61

4432.20

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

221.61

221.61

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator (capacity 33 KVA)

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

d)

Formwork @ 4 per cent on cost of concrete i.e. cost of


a) Material, b) Labour and c) Machinery
Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1932.54
12561.54
6280.77
69088.46

Cost for 15 cum = a+b+c+d+e

4605.90

Rate per metre (a+b+c+d+e)/15

249

Sr No

12.38A

Ref. to
MoRTH
Spec.

Description

(ii)

Unit

Quantity

Rate Rs

Cost Rs

say

4606.00

Remarks/
Input ref.

Using Batching Plant, Transit Mixer and Concrete Pump


a)

Material
tonne

5.12

5210.53

26677.89

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-004

20 mm Aggregate

cum

8.10

938.92

7605.25

M-053

10 mm Aggregate

cum

5.40

723.14

3904.96

M-051

Mate

day

0.16

232.16

37.15

L-12

Mason

day

0.38

306.03

116.29

L-10

Mazdoor for concreting

day

2.50

221.61

554.03

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

221.61

221.61

L-13

Batching Plant @ 20 cum/hour

hour

0.75

2598.00

1948.50

P&M-002

Generator 100 KVA

hour

0.75

1600.00

1200.00

P&M-080

Loader (capacity 1 cum)

hour

1116.00

837.00

P&M-017

1709.10

P&M-049

Cement

b)

c)

Labour

0.75

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

d)

Formwork @ 4 per cent on cost of concrete i.e. cost of


a) Material, b) Labour and c) Machinery
Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

hour

2.00

854.55

tonne.km

37.5L

4.32

hour

0.75

234.36

P&M-007

12123.54
6061.77
66679.48
4445.30

Rate per metre (a+b+c+d+e)/15

12.38

175.77
1865.16

Cost for 15 cum = a+b+c+d+e

Note

162.00 Lead =1 km
& P&M-050

say

4445.00

The value of a, b and c may be taken as applicable i.e. either


using concrete mixer or batching plant.
RCC Grade M25
Unit = cum
Taking output = 15 cum

(i)

Using Concrete Mixer


a)

Material
tonne

5.99

5210.53

31211.05

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

20 mm Aggregate

cum

8.10

938.92

7605.25

M-053

10 mm Aggregate

cum

5.40

723.14

3904.96

M-051

Mate

day

0.90

232.16

208.94

L-12

Mason

day

1.50

306.03

459.05

L-10

Mazdoor for concreting

day

20.00

221.61

4432.20

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

221.61

221.61

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator (capacity 33 KVA)

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

d)

Formwork @ 4 per cent on cost of concrete i.e. cost of


a) Material, b) Labour and c) Machinery
Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2113.87
13740.16
6870.08
75570.87

Cost for 15 cum = a+b+c+d+e

5038.06

Rate per metre (a+b+c+d+e)/15


say

12.38B

(ii)

Using Batching Plant, Transit Mixer and Concrete Pump


a)

Material
250

5038.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

c)

Rate Rs

Cost Rs

Remarks/
Input ref.

tonne

5.99

5210.53

31211.05

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-004

20 mm Aggregate

cum

8.10

938.92

7605.25

M-053

10 mm Aggregate

cum

5.40

723.14

3904.96

M-051

Mate

day

0.16

232.16

37.15

L-12

Mason

day

0.38

306.03

116.29

L-10

Mazdoor for concreting

day

2.50

221.61

554.03

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

221.61

221.61

L-13

Batching Plant @ 20 cum/hour

hour

0.75

2598.00

1948.50

P&M-002

Generator 125 KVA

hour

0.75

2136.00

1602.00

P&M-018

Loader (capacity 1 cum)

hour

1116.00

837.00

P&M-017

1709.10

P&M-049

Cement

b)

Quantity

Labour

0.75

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

d)

Formwork @ 4 per cent on cost of concrete i.e. cost of


a) Material, b) Labour and c) Machinery
Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

hour

2.00

854.55

tonne.km

37.5L

4.32

hour

0.75

234.36

2062.57
13406.68
6703.34
73736.76

Cost for 15 cum = a+b+c+d+e

4915.78

Rate per metre (a+b+c+d+e)/15


Note
12.38

162.00 Lead =1 km
& P&M-050
175.77
P&M-007

say

4916.00

The value of a, b and c may be taken as applicable i.e. either


using concrete mixer or batching plant.
RCC Grade M30
Unit = cum
Taking output = 15 cum

(i)

Using Concrete Mixer


a)

Material
tonne

6.10

5210.53

31784.21

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

20 mm Aggregate

cum

8.10

938.92

7605.25

M-053

10 mm Aggregate

cum

5.40

723.14

3904.96

M-051

Mate

day

0.90

232.16

208.94

L-12

Mason

day

1.50

306.03

459.05

L-10

Mazdoor for concreting

day

20.00

221.61

4432.20

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

221.61

221.61

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator (capacity 33 KVA)

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

d)

Formwork @ 4 per cent on cost of concrete i.e. cost of


a) Material, b) Labour and c) Machinery
Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2136.80
13889.18
6944.59
76390.49

Cost for 15 cum = a+b+c+d+e

5092.70

Rate per metre (a+b+c+d+e)/15


'12.38C

(ii)

say

5093.00

Using Batching Plant, Transit Mixer and Concrete Pump


a)

Material
tonne

6.10

5210.53

31784.21

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-004

20 mm Aggregate

cum

8.10

938.92

7605.25

M-053

Cement

251

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

c)

Rate Rs

Cost Rs
3904.96

Remarks/
Input ref.

cum

5.40

723.14

Mate

day

0.16

232.16

37.15

L-12

Mason

day

0.38

306.03

116.29

L-10

Mazdoor for concreting

day

2.50

221.61

554.03

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

221.61

221.61

L-13

Batching Plant @ 20 cum/hour

hour

0.75

2598.00

1948.50

P&M-002

Generator 100 KVA

hour

0.75

1600.00

1200.00

P&M-080

Loader (capacity 1 cum)

hour

1116.00

837.00

P&M-017

1709.10

P&M-049

10 mm Aggregate
b)

Quantity

M-051

Labour

0.75

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

d)

Formwork @ 4 per cent on cost of concrete i.e. cost of


a) Material, b) Labour and c) Machinery
Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

hour

2.00

854.55

tonne.km

37.5L

4.32

hour

0.75

234.36

2069.41
13451.18
6725.59
73981.52

Cost for 15 cum = a+b+c+d+e

4932.10

Rate per metre (a+b+c+d+e)/15


Note
12.38

162.00 Lead =1 km
& P&M-050
175.77
P&M-007

say

4932.00

The value of a, b and c may be taken as applicable i.e. either


using concrete mixer or batching plant.
RCC Grade M35
Unit = cum
Taking output = 15 cum

(i)

Using Concrete Mixer


a)

Material
tonne

6.33

5210.53

32982.63

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

20 mm Aggregate

cum

8.10

938.92

7605.25

M-053

10 mm Aggregate

cum

5.40

723.14

3904.96

M-051

Mate

day

0.90

232.16

208.94

L-12

Mason

day

1.50

306.03

459.05

L-10

Mazdoor

day

20.00

221.61

4432.20

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

221.61

221.61

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator (capacity 33 KVA)

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

d)

Formwork @ 4 per cent on cost of concrete i.e. cost of


a) Material, b) Labour and c) Machinery
Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2184.73
14200.77
7100.38
78104.23

Cost for 15 cum = a+b+c+d+e

5206.95

Rate per metre (a+b+c+d+e)/15


'12.38D

(ii)

say

5207.00

Using Batching Plant, Transit Mixer and Concrete Pump


a)

Material
tonne

6.33

5210.53

32982.63

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-004

20 mm Aggregate

cum

8.10

938.92

7605.25

M-053

10 mm Aggregate

cum

5.40

723.14

3904.96

M-051

day

0.16

232.16

37.15

Cement

b)

Labour
Mate

252

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Mason

day

0.38

306.03

116.29

L-10

Mazdoor for concreting

day

2.50

221.61

554.03

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

221.61

221.61

L-13

Batching Plant @ 20 cum/hour

hour

0.75

2598.00

1948.50

P&M-002

Generator 125 KVA

hour

0.75

2136.00

1602.00

P&M-018

Loader (capacity 1 cum)

hour

1116.00

837.00

P&M-017

1709.10

P&M-049

0.75

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

d)

Formwork @ 4 per cent on cost of concrete i.e. cost of


a) Material, b) Labour and c) Machinery
Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

hour

2.00

854.55

tonne.km

37.5L

4.32

hour

0.75

234.36

2133.43
13867.29
6933.65
76270.12

Cost for 15 cum = a+b+c+d+e

5084.67

Rate per metre (a+b+c+d+e)/15


12.39

1100&17
00

162.00 Lead =1 km
& P&M-050
175.77
P&M-007

say

5085.00

Levelling Course for Pile cap


Providing and laying of PCC M15 levelling course 100mm
thick below the pile cap.
Unit = cum
Taking output = 15 cum
a)

Material
tonne

4.13

5210.53

21519.47

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

40 mm aggregate

cum

8.10

830.30

6725.43

M-055

20 mm Aggregate

cum

4.05

938.92

3802.63

M-053

cum

1.35

723.14

976.24

M-051

Mate

day

0.86

232.16

199.66

L-12

Mason

day

1.50

306.03

459.05

L-10

Mazdoor

day

20.00

221.61

4432.20

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Cement

10 mm Aggregate
b)

c)

Labour

Machinery

d)

Overhead charges @ 0.25 on (a+b+c)

10729.59

e)

Contractor's profit @ 0.1 on (a+b+c+d)

5364.80
59012.77

Cost for 15 cum = a+b+c+d+e

3934.18

Rate per metre (a+b+c+d+e)/15


12.40

1600

say

3934.00

Supplying, Fitting and Placing un-coated HYSD bar


Reinforcement in Foundation complete as per Drawing
and Technical Specifications.
Unit = 1 MT
Taking output = 1 MT
a)

Material
tonne

1.05

36191.33

38000.90

M-082

Kg

6.00

62.52

375.14

M-072

day

0.40

232.16

92.86

L-12

Blacksmith

day

2.00

353.52

707.04

L-02

Mazdoor

day

6.00

221.61

1329.66

L-13

HYSD bars including5 per cent overlaps and wastage


Binding wire
b)
Labour for cutting, bending, shifting to site, tying
and placing in position
Mate

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

10126.40
5063.20

253

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

1600

Remarks/
Input ref.

55695.20

Rate per MT (a+b+c+d)


12.41

Cost Rs

say

55695.00

Supplying, fitting and placing un-coated Mild steel


reinforcement complete in foundation as per drawing and
technical specification
Unit = 1 MT
Taking output = 1 MT
a)

Material
tonne

1.05

34467.93

36191.33

M-126

Kg

6.00

62.52

375.14

M-072

day

0.43

232.16

99.83

L-12

Blacksmith

day

2.25

353.52

795.42

L-02

Mazdoor

day

6.50

221.61

1440.47

L-13

MS bars including 5 per cent overlaps and wastage


Binding wire
b) Labour for straightening, cutting, bending, shifting
to site, tying and placing in position
Mate

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

9725.55
4862.77
53490.50

Rate for per MT (a+b+c+d)


say

254

53491.00

RCD/SOR

CHAPTER-13

SUB-STRUCTURE
Ref. to
Sr No MoRTH
Spec.
13.1 1300 &
2200

Description

Unit

Brick masonry work in 1:3 in sub-structure complete


excluding pointing and plastering, as per drawing and
Technical Specifications
Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class
Cement mortar 1:3 (Rate as in Item 12.6 A subanalysis)
b) Labour
Mate
Mason
Mazdoor
Add for scaffolding @ 5 per cent of cost of material
and labour
c) Overhead charges @ 0.25 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per cum (a+b+c+d)

each
cum

day
day
day

Quantity

Rate Rs

500.00
0.24

4.92
3096.00

0.06
0.80
0.80

232.16
353.52
221.61

say
13.2

1300 &
2200

Pointing with cement mortar (1:3 ) on brick work in


substructure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6 )
Labour
Mate
Mason
Mazdoor
c) Overhead charges @ 0.25 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per 10 sqm (a+b+c+d)

cum

0.03

3096.00

day
day
day

0.04
0.50
0.50

232.16
353.52
221.61

Cost Rs

Remarks/
Input ref.

M-079
2460.42
743.04 Item 12.6 (A)

13.93
282.82
177.29
183.87

L-12
L-11
L-13

965.34
482.67
5309.38
5309.00

92.88 Item 12.6 (A)

b)

say
13.3

Note
1300 &
2200

Scaffolding is already included in item 13.1


Plastering with cement mortar (1:3 ) on brick work in
sub-structure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6)
b) Labour
Mate
Mason
Mazdoor
c) Overhead charges @ 0.25 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per 10 sqm (a+b+c+d)

Note

13.4

1400 &
2200
A

1.Scaffolding is already included in item no. 13.1


2.The number of masons and Mazdoors already catered in
the cement mortar have been taken into account while
providing these categories in brick masonry, pointing and
plastering.
Stone masonry work in cement mortar 1:3 for
substructure complete as per drawing and Technical
Specifications
Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 1 cum
a) Material
Stone
Through and bond stone
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6)
b) Labour
Mate
Mason
Mazdoor
Add for scaffolding @ 5 per cent of cost of a)
Material and b) Labour
c) Overhead charges @ 0.25 on (a+b)
d)

cum

0.144

3096.00

day
day
day

0.04
0.50
0.50

232.16
353.52
221.61

9.29
176.76
110.81
97.43
48.72
535.88
536.00

445.82 Item 12.6 (A)

say

9.29
176.76
110.81
185.67
92.83
1021.18
1021.00

359.72
42.39

cum
No

1.00
7.00

359.72
6.06

cum

0.33

3096.00

day
day
day

0.10
1.20
1.20

232.16
353.52
221.61

23.22
424.22
265.93
106.86

280.50

Rate per cum (a+b+c+d)


say

253

L-12
L-11
L-13

M-148
M-182

1021.68 Item 12.6 (A)

561.01

Contractor's profit @ 0.1 on (a+b+c)

L-12
L-11
L-13

3085.53
3086.00

L-12
L-11
L-13

RCD/SOR
Ref. to
Sr No MoRTH
Spec.
13.4

Description
B

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Coursed rubble masonry (first sort )


Unit = cum
Taking output = 1 cum
a) Material
Stone

cum

1.10

359.72

395.69

M-148

Through and bond stone

each

7.00

6.06

42.39

M-182

cum

0.30

3096.00

Mate

day

0.12

232.16

27.86

L-12

Mason

day

1.50

353.52

530.28

L-11

Mazdoor

day

1.50

221.61

332.42

L-13

(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)


b)

Cement mortar 1:3 (Rate as in Item 12.6)


Labour

c)

Add for scaffolding @ 5 per cent of cost of material


and labour
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

112.87
592.58
296.29

Rate per cum (a+b+c+d)


13.4

928.80 Item 12.6 (A)

say

3259.18
3259.00

Ashlar masonry ( first sort )


Plain ashlar
Unit = cum
Taking output = 1 cum
a) Material
Stone

cum

1.11

360.24

399.87

M-169

Through and bond stone

each

7.00

6.06

42.39

M-182

cum

0.33

3096.00

Mate

day

0.20

232.16

46.43

L-12

Mason

day

2.50

353.52

883.80

L-11

Mazdoor

day

2.50

221.61

554.03

L-13

(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)


b)

Cement mortar 1:3 (Rate as in Item 12.6)


Labour for masonry work

c)

Add for scaffolding @ 5 per cent of cost of a)


Material and b) Labour
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

147.41
773.90
386.95

Rate per cum (a+b+c+d)


say
Note

13.5

1021.68 Item 12.6 (A)

4256.46
4256.00

The labour already considered in the cement mortar have


been taken into account while providing these categories in
the stone masonry works.
Plain/Reinforced cement concrete in sub-structure
complete as per drawing and Technical Specifications

1500,
1700 &
2200

Unit = cum
Taking output = 1 cum
A

PCC Grade M15

(p) Height upto 5m


Same as Item 12.8 (A) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (A)
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

2874.00 Item 12.8 (A)

10.00

287.40
790.35
395.18

Rate per cum (a+b+c+d+e+f)


say
13.5

4346.93
4347.00

PCC Grade M20

(p) Height upto 5m


Same as Item 12.8 (B) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (B)
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3224.00 Item 12.8 (B)


PCC
10.00

322.40
886.60
443.30

Rate per cum (a+b+c+d+e+f)


say

254

4876.30
4876.00

RCD/SOR
Ref. to
Sr No MoRTH
Spec.
13.5

Description
C

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

PCC Grade M25

(p) Height upto 5m


Same as Item 12.8 (D) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.75 per cent of cost of material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3513.00 Item 12.8 (D)

10.00

351.30
966.08
483.04

Rate per cum (a+b+c+d+e+f)


say
13.5 C
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3386.00 Item 12.8 (D)

10.00

338.60
931.15
465.58

Rate per cum (a+b+c+d+e+f)


say
13.5 C

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3513.00 Item 12.8 (D)

12.00

421.56

2.00

70.26
1001.21
500.60

Rate per cum (a+b+c+d+e+f)


say
Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case II
d) formwork

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

12.00

406.32

2.00

67.72
965.01
482.51
say

(r)

5506.63
5507.00

3386.00 Item 12.8 (D)

Rate per cum (a+b+c+d+e+f)


13.5 C

5121.33
5121.00

(q) Height 5m to 10m


Same as Item 12.8 (D) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.75 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case I
d) formwork

13.5 C
(q)

5313.41
5313.00

5307.56
5308.00

Height above 10m

Same as Item 12.8 (D) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form
work shall be 15 per cent instead of 3.75 per cent of cost
of material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case I
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3513.00 Item 12.8 (D)

15.00

526.95

4.00

140.52
1045.12
522.56

Rate per cum (a+b+c+d+e+f)


say

255

5748.15
5748.00

RCD/SOR
Ref. to
Sr No MoRTH
Description
Spec.
13.5 C
Case With Batching Plant, Transit Mixer and Concrete Pump
(r)
II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case II
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Unit

Quantity

Rate Rs

3386.00 Item 12.8 (D)

15.00

507.90

4.00

135.44
1007.34
503.67

Rate per cum (a+b+c+d+e+f)


say
13.5

Cost Rs

Remarks/
Input ref.

5540.34
5540.00

PCC Grade M30

(p) Height upto 5m


Same as Item 12.8 (F) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.50 per cent of cost of material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3544.00 Item 12.8 (F)

10.00

354.40
974.60
487.30

Rate per cum (a+b+c+d+e+f)


say
13.5 D
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3414.00 Item 12.8 (F)

10.00

341.40
938.85
469.43

Rate per cum (a+b+c+d+e+f)


say
13.5 D

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3544.00 Item 12.8 (F)

12.00

425.28

2.00

70.88
1010.04
505.02

Rate per cum (a+b+c+d+e+f)


say
Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case II
d) formwork

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

12.00

409.68

2.00

68.28
972.99
486.50
say

(r)

5555.22
5555.00

3414.00 Item 12.8 (F)

Rate per cum (a+b+c+d+e+f)


13.5 D

5163.68
5164.00

(q) Height 5m to 10m


Same as Item 12.8 (F) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.50 per cent of
cost of material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case I
d) formwork

13.5 D
(q)

5360.30
5360.00

Height above 10m


Same as Item 12.8 (F) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form
work shall be 15 per cent instead of 3.50 per cent of cost
of material, labour and machinery

256

5351.45
5351.00

RCD/SOR
Ref. to
Sr No MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case I
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3544.00 Item 12.8 (F)

15.00

531.60

4.00

141.76
1054.34
527.17

Rate per cum (a+b+c+d+e+f)


say
13.5 D
(r)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case II
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

15.00

512.10

4.00

136.56
1015.67
507.83
say

5798.87
5799.00

3414.00 Item 12.8 (F)

Rate per cum (a+b+c+d+e+f)


13.5

Cost Rs

Remarks/
Input ref.

5586.16
5586.00

RCC Grade M20

(p) Height upto 5m


Same as Item 12.8 (C) upto 5 m height, except for
formwork which shall be 10 per cent instead of 4 per cent
of cost of material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3242.00 Item 12.8 (C)

10.00

324.20
891.55
445.78

Rate per cum (a+b+c+d+e+f)


say
13.5 E
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3113.00 Item 12.8 (C)

10.00

311.30
856.08
428.04

Rate per cum (a+b+c+d+e+f)


say
13.5 E

4708.41
4708.00

(q) Height 5m to 10m


For height, upto 10m, add 2 per cent of cost as above
excluding formwork. For cost of formwork add 12 per cent
of cost of material, labour and machinery instead of 4 per
cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case I
d) formwork

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3242.00 Item 12.8 (C)

12.00

389.04

2.00

64.84
923.97
461.99

Rate per cum (a+b+c+d+e+f)


say
13.5 E
(q)

4903.53
4904.00

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 12 per cent of cost of material, labour and
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift

257

5081.84
5082.00

3113.00 Item 12.8 (C)

12.00

373.56

2.00

62.26

RCD/SOR
Ref. to
Sr No MoRTH
Spec.

Description
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Unit

Quantity

Rate Rs

887.21
443.60

Rate per cum (a+b+c+d+e+f)


say
13.5 E

(r)

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3242.00 Item 12.8 (C)

15.00

486.30

4.00

129.68
964.50
482.25

Rate per cum (a+b+c+d+e+f)


say
Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case II
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

15.00

466.95

4.00

124.52
926.12
463.06
say

5304.72
5305.00

3113.00 Item 12.8 (C)

Rate per cum (a+b+c+d+e+f)


13.5

4879.63
4880.00

Height above 10m

Same as Item 12.8 (C) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form
work shall be 15 per cent instead of 4 per cent of cost of
material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case I
d) formwork

13.5 E
(r)

Cost Rs

Remarks/
Input ref.

5093.65
5094.00

RCC Grade M25

(p) Height upto 5m


Same as Item 12.8 (E) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.75 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3534.00 Item 12.8 (E)

10.00

353.40
971.85
485.93

Rate per cum (a+b+c+d+e+f)


say
13.5 F
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3406.00 Item 12.8 (E)


DIR used item

10.00

340.60
936.65
468.33

Rate per cum (a+b+c+d+e+f)


say
13.5 F

5345.18
5345.00

5151.58
5152.00

(q) Height 5m to 10m


For height, upto 10m, add 1.8 per cent of cost as above
excluding formwork. For cost of formwork add 11.8 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case I
d) formwork
Add 11.8 per cent of cost of material, labour and
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift

258

3534.00 Item 12.8 (E)

11.80

417.01

1.80

63.61

RCD/SOR
Ref. to
Sr No MoRTH
Spec.

Description
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Unit

Quantity

Rate Rs

1003.66
501.83

Rate per cum (a+b+c+d+e+f)


say
13.5 F
(q)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case II
d) formwork

e)

Add 11.8 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

DIR used item

11.80

401.91

1.80

61.31
967.30
483.65
say

(r)

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3534.00 Item 12.8 (E)

15.00

530.10

4.00

141.36
1051.37
525.68

Rate per cum (a+b+c+d+e+f)


say
Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case II
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

DIR used item

15.00

510.90

4.00

136.24
1013.29
506.64
say

5782.51
5783.00

3406.00 Item 12.8 (E)

Rate per cum (a+b+c+d+e+f)


13.5

5320.17
5320.00

Height above 10m

For height, above 10m, add 4 per cent of cost as above


excluding formwork. For cost of formwork add 15 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case I
d) formwork

13.5 F
(r)

5520.11
5520.00

3406.00 Item 12.8 (E)

Rate per cum (a+b+c+d+e+f)


13.5 F

Cost Rs

Remarks/
Input ref.

5573.07
5573.00

RCC Grade M30

(p) Height upto 5m


Same as Item 12.8 (G) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.5 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3551.00 Item 12.8 (G)

10.00

355.10
976.53
488.26

Rate per cum (a+b+c+d+e+f)


say
13.5 G
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5370.89
5371.00

3424.00 Item 12.8 (G)

10.00

342.40
941.60
470.80

Rate per cum (a+b+c+d+e+f)


say

259

5178.80
5179.00

RCD/SOR
Ref. to
Sr No MoRTH
Spec.
13.5 G

Description

Unit

Quantity

Rate Rs

(q) Height 5m to 10m


For height, upto 10m, add 1.6 per cent of cost as above
excluding formwork. For cost of formwork add 11.5 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case I
d) formwork

e)

Add 11.5 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3551.00 Item 12.8 (G)

11.50

408.37

1.60

56.82
1004.05
502.02

Rate per cum (a+b+c+d+e+f)


say
13.5 G
(q)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case II
d) formwork

e)

Add 11.5 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

11.50

393.76

1.60

54.78
968.14
484.07
say

(r)

e)

Add 14 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3551.00 Item 12.8 (G)

14.00

497.14

3.50

124.29
1043.11
521.55

Rate per cum (a+b+c+d+e+f)


say
Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case II
d) formwork

e)

Add 14 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

14.00

479.36

3.50

119.84
1005.80
502.90
say

5737.08
5737.00

3424.00 Item 12.8 (G)

Rate per cum (a+b+c+d+e+f)


13.5

5324.75
5325.00

Height above 10m

For height, above 10m, add 3.5 per cent of cost as above
excluding formwork. For cost of formwork add 14 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case I
d) formwork

13.5 G
(r)

5522.25
5522.00

3424.00 Item 12.8 (G)

Rate per cum (a+b+c+d+e+f)


13.5 G

Cost Rs

Remarks/
Input ref.

5531.90
5532.00

RCC Grade M35

(p) Height upto 5m


Same as Item 12.8 (H) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3631.00 Item 12.8 (H)


Case I
10.00

363.10
998.53
499.26

Rate per cum (a+b+c+d+e+f)


say
13.5 H
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 10 per cent of cost of material, labour and
machinery (a+b+c) for Formwork
260

5491.89
5492.00

3694.00 Item 12.8 (H)


DIR used item

10.00

369.40

RCD/SOR
Ref. to
Sr No MoRTH
Spec.

Description
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Unit

Quantity

Rate Rs

1015.85
507.93

Rate per cum (a+b+c+d+e+f)


say
13.5 H

(q) Height 5m to 10m

e)

Add 11 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3631.00 Item 12.8 (H)


Case I
11.00

399.41

1.40

50.83
1020.31
510.16

Rate per cum (a+b+c+d+e+f)


say
Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case II
d) formwork

e)

Add 11 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

11.00

406.34

1.40

51.72
1038.01
519.01
say

(r)

Height above 10m

5709.08
5709.00
5530.00

For height, above 10m, add 3 per cent of cost as above


excluding formwork. For cost of formwork add 13 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case I
d) formwork

e)

Add 13 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3631.00 Item 12.8 (H)


Case I
13.00

472.03

3.00

108.93
1052.99
526.50

Rate per cum (a+b+c+d+e+f)


say
13.5 H
(r)

5611.71
5612.00

3694.00 Item 12.8 (H)

Rate per cum (a+b+c+d+e+f)


13.5 H

5587.18
5587.00
5412.00

For height, upto 10m, add 1.4 per cent of cost as above
excluding formwork. For cost of formwork add 11 per cent
of cost of material, labour and machinery .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case I
d) formwork

13.5 H
(q)

Cost Rs

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case II
d) formwork

e)

Add 13 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5791.45
5791.00

3694.00 Item 12.8 (H)

13.00

480.22

3.00

110.82
1071.26
535.63

Rate per cum (a+b+c+d+e+f)


say

5891.93
5892.00
5707.00

Note

13.6

Section
1600 &
2200

Remarks/
Input ref.

The basic components of this analysis are the same as


those of items 13.8 (A to H). The only changes are as under:
a) Ramps/Stairs: Extra expenditure on structures which
are more than 5 m high @ 2 per cent of cost for height upto
10 m and 4 per cent for heights above 10 m will be involved
for approaching the work spot by providing higher ramp/stair
case for use by the working parties.
b) The above mentioned percentages have been suitably
modified for different categories as cost for various
categories varies, whereas effort for access for same height
will be similar. As the cost of richer concrete is comparatively
more, the percentage to be added has been reduced to
maintain the same cost for extra efforts.
Supplying, fitting and placing HYSD bar reinforcement
in sub-structure complete as per drawing and Technical
Specifications

261

RCD/SOR
Ref. to
Sr No MoRTH
Spec.

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Description

Unit

HYSD bars including 5 per cent overlaps and


wastage
Binding wire
b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate

tonne

1.05

36191.33

38000.90

M-082

kg

6.00

62.52

375.14

M-072

day

0.34

232.16

78.93

L-12

day

2.00

353.52

707.04

L-02

day

6.50

221.61

1440.47

L-13

Output: MT
Taking output = 1 MT
a) Material

Blacksmith
c)

Mazdoor
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

10150.62
5075.31

Rate for per MT (a+b+c+d)


13.7

1600 &
2200

say

55828.41
55828.00

Supplying, fitting and placing Mild steel reinforcement


complete in sub-structure as per drawing and Technical
Specification
Unit = MT
Taking output = 1 MT
a) Material
MS bars including 5 per cent overlaps and wastage
Binding wire
b) Labour for straightening, cutting, bending, shifting
to site, tying and placing in position
Mate
Blacksmith
c)

Mazdoor
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

tonne

1.05

34467.93

36191.33

M-126

kg

6.00

62.52

375.14

M-072

day

0.28

232.16

65.00

L-12

day

1.50

353.52

530.28

L-02

day

5.50

221.61

1218.86

L-13

9595.15
4797.58

Rate for per MT (a+b+c+d)


13.8

2706 &
2200

say

52773.34
52773.00

31.50

50.28

1583.73

Providing weep holes in Brick masonry/Plain/


Reinforced concrete abutment, wing wall/ return wall
with 100 mm dia AC pipe, extending through the full
width of the structure with slope of 1V :20H towards
drawing foce. Complete as per drawing and Technical
Specifications
Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per cent
)
Average length of weep hole is taken as one metre for the
purpose of estimating.
MS clamp

metre

each.

30.00

24.33

729.88

M-123

collar for AC pipe (average) taking 10% of above pipe


rate
Cement mortar 1:3 (Rate as in Item 12.6)
Labour

each.

10.00

5.03

50.28

M-056/10

cum

0.05

3096.00

Mate

day

0.03

232.16

6.96

L-12

Mason

day

0.50

353.52

176.76

L-11

day

0.25

221.61

55.40

L-13

b)

c)

Mazdoor
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

344.73
3792.00
say

13.9

154.80 Item 12.6 (A)

689.45

Cost for 30 m = a+b+c+d


Rate per No. (a+b+c+d)/30
Note

M-056

126.40
126.00

1. In case of stone masonry, the size of the weep hole shall


be 150 mm x 80 mm or circular with 150 mm diameter.
2. For structure in stone masonry, the weep holes shall be
deemed to be included in the item of stone masonry work
and shall not be paid separately.
Back filling behind abutment, wing wall and return wall
complete as per drawing and Technical Specification

710.1.4.
of
IRC:78
& 2200

Unit = cum
Taking output = 10 cum
A

Granular material
a)

Labour
Mate

day

0.28

232.16

65.00

L-12

day

7.00

221.61

1551.27

L-13

b)

Mazdoor
Material
Granular material
Machinery

cum

12.00

166.19

1994.28

M-009

c)

Plate compactor/power rammer

hour

2.50

142.99

357.48

P&M-086

Water Tanker

hour

0.05

111.24

5.56

P&M-060

262

RCD/SOR
Ref. to
Sr No MoRTH
Spec.

Description
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Unit

Quantity

Rate Rs

993.40
496.70

Cost for 10 cum of granular backfill = a+b+c+d+e


Rate per cum = (a+b+c+d+e)/10

5463.70
say

13.9

Labour
Mate

day

0.28

232.16

65.00

L-12

day

7.00

221.61

1551.27

L-13

b)

Mazdoor for filling, watering, ramming etc.


Material
Sand
Machinery

cum

12.00

120.42

1445.04

M-006

c)

Plate compactor/power rammer

hour

2.50

142.99

357.48

P&M-086

hour

0.06

111.24

6.67

P&M-060

d)

Water Tanker
Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

428.18

Cost for 10 cum of sandy backfill = a+b+c+d+e


Rate per cum = (a+b+c+d+e)/10

4710.02

856.37

say
710.1.4.
of
IRC:78
and
2200

546.37
546.00

Sandy material
a)

13.10

Cost Rs

Remarks/
Input ref.

471.00
471.00

Providing and laying of Filter media with granular


materials/stone crushed aggregates satisfying the
requirements laid down in clause 2504.2.2. of MoRTH
specifications to a thickness of not less than 600 mm
with smaller size towards the soil and bigger size
towards the wall and provided over the entire surface
behind abutment, wing wall and return wall to the full
height compacted to a firm condition complete as per
drawing and Technical Specification.
Unit = cum
Taking output = 10 cum.
a) Labour
Mate

day

0.32

232.16

74.29

L-12

Mazdoor for filling, watering, ramming etc.

day

7.00

221.61

1551.27

L-13

day

1.00

306.03

306.03

L-15

b)

Mazdoor (Skilled)
Material

cum

12.00

678.64

8143.68

M-012

c)

Filter media of stone aggregate conforming to clause


2504.2.2. of MoRTH specifications.
Machinery
Water Tanker of 6 KL capacity
Overhead charges @ 0.25 on (a+b+c)

hour

0.06

111.24

d)
e)

Contractor's profit @ 0.1 on (a+b+c+d)

13862.68
say

2000,
1000 &
2200

P&M-060

1260.24

cost for 10 cum of Fiter Media = a+b+c+d+e


Rate per cum = (a+b+c+d+e)/10
13.11

6.67
2520.49

1386.27
1386.00

Supplying, fitting and fixing in position true to line and


level cast steel rocker bearing conforming to IRC: 83(Pt.1) section IX and clause 2003 of MoRTH specifications
complete including all accessories as per drawing and
Technical Specifications.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis
a) Labour
Mate

day

0.06

232.16

13.93

L-12

Mazdoor (Skilled)

day

0.50

306.03

153.02

L-15

day

1.00

221.61

221.61

L-13

b)

Mazdoor
Material

each.

1.00

55883.28

55883.28

c)

Cast steel rocker bearing assembly of 250 tonne


design load capacity duly painted complete with all its
components as per drawing and specifications
Add 1 per cent of cost of bearing assembly for
foundation anchorage bolts, lifting arrangements,
grease and other consumables.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

558.83

14207.67
7103.83

cost for 250 tonnes capacity bearing = a+b+c+d


Rate per tonne capacity = (a+b+c+d)/250

78142.16
say

263

312.57
313.00

M-065

RCD/SOR
Ref. to
Sr No MoRTH
Spec.
13.12 2000 ,
1000 &
2200

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Supplying, fitting and fixing in position true to line and


level forged steel roller bearing conforming to IRC:
83(Pt.-1) section IX and clause 2003 of MoRTH
specifications complete including all accessories as per
drawing and Technical Specifications.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis
a) Labour
Mate

day

0.06

232.16

13.93

L-12

Mazdoor

day

1.00

221.61

221.61

L-13

day

0.50

306.03

153.02

L-15

b)

Mazdoor (Skilled)
Material

each.

1.00

37256.21

37256.21

c)

Forged steel roller bearing of 250 tonne design load


capacity duly painted complete with all its
components as per drawing and specifications
Add 1 per cent of cost of bearing assembly for
foundation anchorage bolts, lifting arrangements,
grease and other consumables.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

372.56

9504.33
4752.17

cost for 250 tonnes capacity bearing = a+b+c+d


Rate per tonne capacity = (a+b+c+d)/250

52273.83
say

13.13

2000 &
2200

M-067

209.10
209.00

Supplying, fitting and fixing in position true to line and


level sliding plate bearing with PTFE surface sliding on
stainless steel complete including all accessories as
per drawing and Technical Specifications and BS: 5400,
and clause 2004 of
section 9.1 & 9.2 (for PTFE)
MoRTH Specifications.
Unit: one tonne capacity
Considering a 80 tonne capacity bearing for this analysis
a) Labour

b)

Mate

day

0.06

232.16

13.93

L-12

Mazdoor

day

1.00

221.61

221.61

L-13

Mazdoor (Skilled)
Material

day

0.50

306.03

153.02

L-15

each.

1.00

#VALUE!

#VALUE!

M-069

PTFE sliding plate bearing assembly of 80 tonnes


design load capacity duly painted complete with all its
components as per drawing and Technical
Specifications
Add 1 per cent for foundation anchorage bolts and
consumables.

264

#VALUE!

RCD/SOR
Ref. to
Sr No MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

c)

Overhead charges @ 0.25 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

cost for 80 tonnes capacity bearing = a+b+c+d


Rate per tonne capacity = (a+b+c+d)/80

#VALUE!
say

13.14

2000 &
2200

Cost Rs

Remarks/
Input ref.

#VALUE!
#VALUE!

Supplying, fitting and fixing in position true to line and


level elastomeric bearing conforming to IRC: 83 (Part-II)
section IX and clause 2005 of MoRTH specifications
complete including all accessories as per drawing and
Technical Specifications.
Unit: one cubic centimetre
Considering an elastomeric bearing of size 500 x 400 x 96
mm for this analysis.
Overall volume - 19200 cu.cm
Volume of 6 nos. 488 x 388 x 4 mm size reinforcing steel
plates = 4545 cu.cm.
Hence volume of elastometer = 14655 cu.cm.
a) Labour
Mate

day

0.06

232.16

13.93

L-12

Mazdoor

day

1.00

221.61

221.61

L-13

day

0.50

306.03

153.02

L-15

b)

Mazdoor (Skilled)
Material

19200.00

0.50

9623.13

M-066

c)

Elastomeric bearing assembly consisting of 7 layers


of elastomer bonded to 6 nos. internal reinforcing
steel laminates by the process of vulcanisation,
complete with all components as per drawing and
Technical Specifications.
Add 1 per cent of cost of bearing assembly for
foundation anchorage bolts and consumables.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

cucm

96.23
2526.98
1263.49

cost for 19200cc of elastomeric bearing = a+b+c+d


Rate per cc of elastomeric bearing = (a+b+c+d)/19200

13898.38
0.72
say

13.15

2000 &
2200

0.72

Supplying, fitting and fixing in position true to line and


level sliding plate bearing with stainless steel plate
sliding on stainless steel plate with mild steel matrix
complete including all accessories as per drawing and
Technical Specifications.
Unit: one tonne capacity
Considering the sliding bearing of 80 tonnes design capacity
for this analysis.
a) Labour
Mate

day

0.04

232.16

9.29

L-12

Mazdoor

day

0.75

221.61

166.21

L-13

day

0.35

306.03

107.11

L-15

b)

Mazdoor (Skilled)
Material

each.

1.00

22579.27

22579.27

c)

Supply of sliding plate bearing of 80 tonne design


capacity complete as per drawings and Technical
Specifications.
Add 1 per cent of cost of bearing assembly for
foundation anchorage bolts and consumables.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2885.96

cost for 80 tonnes of capacity bearing = a+b+c+d


Rate per tonne Capacity =(a+b+c+d) / 80

31745.54

225.79
5771.92

say

265

396.82
397.00

M-070

RCD/SOR
Ref. to
Sr No MoRTH
Spec.
13.16 2000 &
2200

Description

Unit

Quantity

Supplying, fitting and fixing in position true to line and level


POT-PTFE bearing consisting of a metal piston supported
by a disc or unreinforced elastomer confined within a metal
cylinder, sealing rings, dust seals, PTFE surface sliding
against stainless steel mating surface, complete assembly to
be of cast steel/fabricated structural steel, metal and
elastomer elements to be as per IRC: 83 part-I & II
respectively and other parts conforming to BS: 5400, section
9.1 & 9.2 and clause 2006 of MoRTH Specifications
complete as per drawing and approved Technical
Specifications.
Unit: one tonne capacity

Rate Rs

Cost Rs

Remarks/
Input ref.

387.20

Considering a Pot bearing assembly of 250 tonne capacity


for this analysis.
a) Labour
Mate

day

0.08

232.16

18.57

L-12

Mazdoor

day

1.50

221.61

332.42

L-13

day

0.50

306.03

153.02

L-15

b)

Mazdoor (Skilled)
Material

each.

1.00

31752.36

31752.36

c)

Pot type bearing assembly consisting of a metal


piston supported by a disc, PTFE pads providing
sliding surfaces against stainless steel mating
together with cast steel assemblies/fabricated
structural steel assemblies duly painted with all
components as per clause 2006 and complete as per
drawings and Technical Specifications.
Add 1 per cent of cost of bearing assembly for
foundation anchorage bolts and consumables.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

317.52
8143.47
4071.74

cost for 250 tonnes capacity bearing = a+b+c+d


Rate per tonne capacity = (a+b+c+d)/250

44789.09
say

266

179.16
179.00

M-068

CHAPTER-14

SUPER-STRUCTURE
Sr No
14.1

Ref. to
MoRTH
Spec.
1500
&1600
1700

Description

Cost Rs

Remarks/
Input ref.

Unit

Quantity

Rate Rs

Cement

tonne

5.12

5210.53

26677.89

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

20 mm Aggregate

cum

8.10

938.92

7605.25

M-053

10 mm Aggregate

cum

5.40

723.14

3904.96

M-051

Mate

day

0.86

232.16

199.66

L-12

Mason

day

1.50

353.52

530.28

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Furnishing and Placing Reinforced/ Prestressed cement


concrete in super-structure as per drawing and Technical
Specification
RCC Grade M20

Case I Using Concrete Mixer


Unit = 1 cum
Taking output = 15 cum
a)

b)

c)

Material

Labour

Machinery

Basic Cost of Labour, Material & Machinery (a+b+c) for


15 cum
For formwork and staging add the following:
14.1A Case
I

(i)

For solid slab super-structure, 20-30 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 20 per cent of (a+b+c)

48154.00

for 15

48154.00
20.00

9630.80

e)

Overhead charges @ 0.25 on (a+b+c+d)

14446.20

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

7223.10

Cost for 15 cum = a+b+c+d+e+f

79454.10

Rate per cum = (a+b+c+d+e+f)/15

5296.94
say

14.1A Case
I (i)

(q)

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

48154.00
25.00

12038.50
15048.13
7524.06

Cost for 15 cum = a+b+c+d+e+f

82764.69

Rate per cum = (a+b+c+d+e+f)/15

5517.65
say

14.1A
Case I (i)

(r)

5518.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 30 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

48154.00
30.00

14446.20
15650.05
7825.03

Cost for 15 cum = a+b+c+d+e+f

86075.28

Rate per cum = (a+b+c+d+e+f)/15

5738.35
say

14.1A Case
I

5297.00

5738.00

(ii) For T-beam & slab, 25-35 per cent of (a+b+c)


(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 25 per cent of (a+b+c)
268

for 15

48154.00
25.00

12038.50

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Quantity

Rate Rs

7524.06
82764.69

Rate per cum = (a+b+c+d+e+f)/15

5517.65
say

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

48154.00
30.00

14446.20
15650.05
7825.03

Cost for 15 cum = a+b+c+d+e+f

86075.28

Rate per cum = (a+b+c+d+e+f)/15

5738.35
say

(r)

5738.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 35 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

48154.00
35.00

16853.90
16251.98
8125.99

Cost for 15 cum = a+b+c+d+e+f

89385.86

Rate per cum = (a+b+c+d+e+f)/15


14.1A

5518.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1A
Case I (ii)

Remarks/
Input ref.

15048.13

Cost for 15 cum = a+b+c+d+e+f

14.1A Case
I (ii)

Cost Rs

5959.06
say

5959.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

b)

c)

Material
Cement

tonne

40.92

5210.53

213214.74

M-081

Coarse sand

cum

54.00

219.18

11835.72

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

10 mm Aggregate

cum

43.20

723.14

31239.65

M-051

Mate

day

0.84

232.16

195.01

L-12

Mason

day

3.00

353.52

1060.56

L-11

Mazdoor

day

18.00

221.61

3988.98

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2598.00

15588.00

P&M-002

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader

hour

6.00

1116.00

6696.00

P&M-017

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

6.00

234.36

Labour

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

Basic Cost of Labour, Material & Machinery (a+b+c) for


120 cum
For formwork and staging add the following:
14.1A Case
II

(i)
(p)

1296.00 Lead =1 km
& P&M-050
1406.16 P&M-007

369782.00

For solid slab super-structure, 20-30 per cent of (a+b+c)


Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 20 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

369782.00
20.00

73956.40
110934.60
55467.30

Cost for 120 cum = a+b+c+d+e+f

610140.30

Rate per cum = (a+b+c+d+e+f)/120

5084.50
say
269

5085.00

Sr No
14.1A
Case II (i)

Ref. to
MoRTH
Spec.

Description
(q)

Unit

Quantity

Rate Rs

369782.00
25.00

92445.50

e)

Overhead charges @ 0.25 on (a+b+c+d)

115556.88

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

57778.44

Cost for 120 cum = a+b+c+d+e+f

635562.81

Rate per cum = (a+b+c+d+e+f)/120

5296.36
say

(r)

369782.00
30.00

110934.60

e)

Overhead charges @ 0.25 on (a+b+c+d)

120179.15

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

60089.58

Cost for 120 cum = a+b+c+d+e+f

660985.33

Rate per cum = (a+b+c+d+e+f)/120

5508.21
say

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

369782.00
25.00

92445.50
115556.88
57778.44

Cost for 120 cum = a+b+c+d+e+f

635562.81

Rate per cum = (a+b+c+d+e+f)/120

5296.36
say

(q)

369782.00
30.00

110934.60

e)

Overhead charges @ 0.25 on (a+b+c+d)

120179.15

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

60089.58

Cost for 120 cum = a+b+c+d+e+f

660985.33

Rate per cum = (a+b+c+d+e+f)/120

5508.21
say

(r)

369782.00
35.00

129423.70

e)

Overhead charges @ 0.25 on (a+b+c+d)

124801.43

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

62400.71

Cost for 120 cum = a+b+c+d+e+f

686407.84

Rate per cum = (a+b+c+d+e+f)/120


B

5508.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 35 per cent of (a+b+c)

14.1

5296.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1A Case
II (ii)

5508.00

(ii) For T-beam & slab, 25-35 per cent of (a+b+c)


(p)

14.1A Case
II (ii)

5296.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1A Case
II

Remarks/
Input ref.

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 25 per cent of (a+b+c)

14.1A
Case II (i)

Cost Rs

5720.07
say

5720.00

RCC Grade M25

Case I Using Concrete Mixer


Unit = 1 cum
Taking output = 15 cum
a)

b)

Material
Cement

tonne

5.99

5210.53

31211.05

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

20 mm Aggregate

cum

8.10

938.92

7605.25

M-053

10 mm Aggregate

cum

5.40

723.14

3904.96

M-051

Labour
270

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Quantity

Rate Rs

Mate

day

0.86

232.16

199.66

L-12

Mason

day

1.50

353.52

530.28

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Machinery

Basic Cost of Labour, Material & Machinery (a+b+c) for


15 cum
For formwork and staging add the following:
14.1B Case
I

(i)
(p)

52688.00

For solid slab super-structure, 20-30 per cent of (a+b+c)


Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 20 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

52688.00
20.00

10537.60
15806.40
7903.20

Cost for 15 cum = a+b+c+d+e+f

86935.20

Rate per cum = (a+b+c+d+e+f)/15

5795.68
say

14.1B
Case I (i)

(q)

for 15

52688.00
25.00

13172.00

e)

Overhead charges @ 0.25 on (a+b+c+d)

16465.00

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

8232.50

Cost for 15 cum = a+b+c+d+e+f

90557.50

Rate per cum = (a+b+c+d+e+f)/15

6037.17
say

(r)

for 15

52688.00
30.00

15806.40

e)

Overhead charges @ 0.25 on (a+b+c+d)

17123.60

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

8561.80

Cost for 15 cum = a+b+c+d+e+f

94179.80

Rate per cum = (a+b+c+d+e+f)/15

6278.65
say

(ii)

For T-beam & slab, 25-35 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 25 per cent of (a+b+c)

for 15
25.00

13172.00

e)

Overhead charges @ 0.25 on (a+b+c+d)

16465.00

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

8232.50
90557.50

Rate per cum = (a+b+c+d+e+f)/15

6037.17
say

(q)

6279.00

52688.00

Cost for 15 cum = a+b+c+d+e+f

14.1B Case
I (ii)

6037.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1B Case
I

5796.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 25 per cent of (a+b+c)

14.1B
Case I (i)

Cost Rs

Remarks/
Input ref.

Unit

6037.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 30 per cent of (a+b+c)

for 15

52688.00
30.00

15806.40

e)

Overhead charges @ 0.25 on (a+b+c+d)

17123.60

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

8561.80

Cost for 15 cum = a+b+c+d+e+f

94179.80

Rate per cum = (a+b+c+d+e+f)/15

6278.65
say
271

6279.00

Sr No
14.1B Case
I (ii)

Ref. to
MoRTH
Spec.

Description
(r)

Unit

Quantity

Rate Rs

Remarks/
Input ref.

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 35 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

52688.00
35.00

18440.80
17782.20
8891.10

Cost for 15 cum = a+b+c+d+e+f

97802.10

Rate per cum = (a+b+c+d+e+f)/15


14.1B

Cost Rs

6520.14
say

6520.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

b)

c)

Material
Cement

tonne

47.95

5210.53

249844.74

M-081

Coarse sand

cum

54.20

219.18

11879.56

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

10 mm Aggregate

cum

43.20

723.14

31239.65

M-051

Mate

day

0.84

232.16

195.01

L-12

Mason

day

3.00

353.52

1060.56

L-11

Mazdoor

day

18.00

221.61

3988.98

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2598.00

15588.00

P&M-002

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader

hour

6.00

1116.00

6696.00

P&M-017

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

6.00

234.36

Labour

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

Basic Cost of Labour, Material & Machinery (a+b+c) for


120 cum
For formwork and staging add the following:
14.1B Case
II

(i)
(p)

406455.00

For solid slab super-structure, 20-30 per cent of (a+b+c)


Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 20 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

406455.00
20.00

81291.00
121936.50
60968.25

Cost for 120 cum = a+b+c+d+e+f

670650.75

Rate per cum = (a+b+c+d+e+f)/120

5588.76
say

14.1B Case
II (i)

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

406455.00
25.00

101613.75
127017.19
63508.59

Cost for 120 cum = a+b+c+d+e+f

698594.53

Rate per cum = (a+b+c+d+e+f)/120

5821.62
say

(r)

5589.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 25 per cent of (a+b+c)

14.1B Case
II (i)

1296.00 Lead =1 km
& P&M-050
1406.16 P&M-007

5822.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum
d)

Formwork and staging 30 per cent of (a+b+c)


272

406455.00
30.00

121936.50

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Quantity

Rate Rs

66048.94
726538.31

Rate per cum = (a+b+c+d+e+f)/120

6054.49
say

(ii)
(p)

Height upto 5m

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

406455.00
25.00

101613.75
127017.19
63508.59

Cost for 120 cum = a+b+c+d+e+f

698594.53

Rate per cum = (a+b+c+d+e+f)/120

5821.62
say

(q)

406455.00
30.00

121936.50

e)

Overhead charges @ 0.25 on (a+b+c+d)

132097.88

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

66048.94

Cost for 120 cum = a+b+c+d+e+f

726538.31

Rate per cum = (a+b+c+d+e+f)/120

6054.49
say

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

406455.00
35.00

142259.25
137178.56
68589.28

Cost for 120 cum = a+b+c+d+e+f

754482.09

Rate per cum = (a+b+c+d+e+f)/120


C

6054.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 35 per cent of (a+b+c)

14.1

5822.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1B
Case II (ii)

6054.00

For T-beam & slab, 25-35 per cent of (a+b+c)

Basic Cost of Labour, Material & Machinery (a+b+c) for 120


cum
d) Formwork and staging 25 per cent of (a+b+c)

14.1B
Case II (ii)

Remarks/
Input ref.

132097.88

Cost for 120 cum = a+b+c+d+e+f

14.1B Case
II

Cost Rs

6287.35
say

6287.00

RCC Grade M 30

Case I Using Concrete Mixer


Unit = 1 cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.10

5210.53

31784.21

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

20 mm Aggregate

cum

8.10

938.92

7605.25

M-053

10 mm Aggregate

cum

5.40

723.14

3904.96

M-051

Mate

day

0.90

232.16

208.94

L-12

Mason

day

1.50

353.52

530.28

L-11

Mazdoor

day

21.00

221.61

4653.81

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Labour

Machinery

Basic Cost of Labour, Material & Machinery (a+b+c) for


15 cum
For formwork and staging add the following:
14.1C Case
I

(i)

For solid slab super-structure, 20-30 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
273

for 15

53492.00

53492.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

d)

Formwork and staging 20 per cent of (a+b+c)

e)

Overhead charges @ 0.25 on (a+b+c+d)

16047.60

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

8023.80

20.00

10698.40

Cost for 15 cum = a+b+c+d+e+f

88261.80

Rate per cum = (a+b+c+d+e+f)/15

5884.12
say

14.1C
Case I (i)

(q)

for 15

53492.00
25.00

13373.00

e)

Overhead charges @ 0.25 on (a+b+c+d)

16716.25

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

8358.13

Cost for 15 cum = a+b+c+d+e+f

91939.38

Rate per cum = (a+b+c+d+e+f)/15

6129.29
say

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

53492.00
30.00

16047.60
17384.90
8692.45

Cost for 15 cum = a+b+c+d+e+f

95616.95

Rate per cum = (a+b+c+d+e+f)/15

6374.46
say

(ii)

For T-beam & slab, 25-35 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 25 per cent of (a+b+c)

for 15
25.00

13373.00

e)

Overhead charges @ 0.25 on (a+b+c+d)

16716.25

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

8358.13
91939.38

Rate per cum = (a+b+c+d+e+f)/15

6129.29
say

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

53492.00
30.00

16047.60
17384.90
8692.45

Cost for 15 cum = a+b+c+d+e+f

95616.95

Rate per cum = (a+b+c+d+e+f)/15

6374.46
say

(r)

6374.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 35 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

53492.00
35.00

18722.20
18053.55
9026.78

Cost for 15 cum = a+b+c+d+e+f

99294.53

Rate per cum = (a+b+c+d+e+f)/15

6619.64
say

14.1C

6129.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1C Case
I (ii)

6374.00

53492.00

Cost for 15 cum = a+b+c+d+e+f

14.1C Case
I (ii)

6129.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1C Case
I

5884.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 25 per cent of (a+b+c)

14.1C
Case I (i)

Cost Rs

Case II Using Batching Plant, Transit Mixer and Concrete Pump.


Unit = cum
Taking output = 120 cum
274

6620.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Cement

tonne

48.79

5210.53

254221.58

M-081

Coarse sand

cum

54.60

219.18

11967.23

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

10 mm Aggregate

cum

43.20

723.14

31239.65

M-051

Mate

day

0.88

232.16

204.30

L-12

Mason

day

3.00

353.52

1060.56

L-11

Mazdoor

day

19.00

221.61

4210.59

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2598.00

15588.00

P&M-002

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader

hour

6.00

1116.00

6696.00

P&M-017

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

6.00

234.36

Description
a)

b)

c)

Material

Labour

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

Basic Cost of Labour, Material & Machinery (a+b+c) for


120 cum
For formwork and staging add the following:
14.1C Case
II

(i)
(p)

411151.00

For solid slab super-structure, 20-30 per cent of (a+b+c)


Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 20 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

411151.00
20.00

82230.20
123345.30
61672.65

Cost for 120 cum = a+b+c+d+e+f

678399.15

Rate per cum = (a+b+c+d+e+f)/120

5653.33
say

14.1C Case
II (i)

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

411151.00
25.00

102787.75
128484.69
64242.34

Cost for 120 cum = a+b+c+d+e+f

706665.78

Rate per cum = (a+b+c+d+e+f)/120

5888.88
say

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

411151.00
30.00

123345.30
133624.08
66812.04

Cost for 120 cum = a+b+c+d+e+f

734932.41

Rate per cum = (a+b+c+d+e+f)/120

6124.44
say

(ii)
(p)

5889.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1C Case
II

5653.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 25 per cent of (a+b+c)

14.1C Case
II (i)

1296.00 Lead =1 km
& P&M-050
1406.16 P&M-007

6124.00

For T-beam & slab, 25-35 per cent of (a+b+c)


Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Cost for 120 cum = a+b+c+d+e+f

411151.00
25.00

102787.75
128484.69
64242.34
706665.78

275

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Rate per cum = (a+b+c+d+e+f)/120


(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

411151.00
30.00

123345.30
133624.08
66812.04

Cost for 120 cum = a+b+c+d+e+f

734932.41

Rate per cum = (a+b+c+d+e+f)/120

6124.44
say

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

411151.00
35.00

143902.85
138763.46
69381.73

Cost for 120 cum = a+b+c+d+e+f

763199.04

Rate per cum = (a+b+c+d+e+f)/120


D

6124.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 35 per cent of (a+b+c)

14.1

5889.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1C Case
II (ii)

Remarks/
Input ref.

5888.88
say

14.1C Case
II (ii)

Cost Rs

6359.99
say

6360.00

RCC/PSC Grade M35

Case I Using Concrete Mixer.


Unit = 1 cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.33

5210.53

32982.63

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

20 mm Aggregate

cum

8.10

938.92

7605.25

M-053

10 mm Aggregate

cum

5.40

723.14

3904.96

M-051

Mate

day

0.90

232.16

208.94

L-12

Mason

day

1.50

353.52

530.28

L-11

Mazdoor

day

21.00

221.61

4653.81

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Labour

Machinery

Basic Cost of Labour, Material & Machinery (a+b+c) for


15 cum
For formwork and staging add the following:
14.1D Case
I

(i)

For solid slab super-structure, 18-28 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 18 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

54690.00

for 15

54690.00
18.00

9844.20
16133.55
8066.78

Cost for 15 cum = a+b+c+d+e+f

88734.53

Rate per cum = (a+b+c+d+e+f)/15

5915.64
say

14.1D
Case I (i)

(q)

5916.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 23 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Cost for 15 cum = a+b+c+d+e+f

for 15

54690.00
23.00

12578.70
16817.18
8408.59
92494.46

276

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Rate per cum = (a+b+c+d+e+f)/15

6166.30
say

14.1D
Case I (i)

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

54690.00
28.00

15313.20
17500.80
8750.40

Cost for 15 cum = a+b+c+d+e+f

96254.40

Rate per cum = (a+b+c+d+e+f)/15

6416.96
say

(ii)
(p)

Height upto 5m

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

54690.00
23.00

12578.70
16817.18
8408.59

Cost for 15 cum = a+b+c+d+e+f

92494.46

Rate per cum = (a+b+c+d+e+f)/15

6166.30
say

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

54690.00
28.00

15313.20
17500.80
8750.40

Cost for 15 cum = a+b+c+d+e+f

96254.40

Rate per cum = (a+b+c+d+e+f)/15

6416.96
say

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

54690.00
33.00

18047.70
18184.43
9092.21

Cost for 15 cum = a+b+c+d+e+f

100014.34

Rate per cum = (a+b+c+d+e+f)/15

6667.62
say

(iii)
(p)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

54690.00
38.00

20782.20
18868.05
9434.03

Cost for 15 cum = a+b+c+d+e+f

103774.28

Rate per cum = (a+b+c+d+e+f)/15

6918.29
say

(q)

6668.00

For box girder and balanced cantilever, 38-58 per cent of


cost of concrete.
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 38 per cent of (a+b+c)

14.1D
Case I (iii)

6417.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 33 per cent of (a+b+c)

14.1D Case
I

6166.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 28 per cent of (a+b+c)

14.1D Case
I (ii)

6417.00

For T-beam & slab, 23-33 per cent of (a+b+c)

Basic Cost of Labour, Material & Machinery (a+b+c)


cum
d) Formwork and staging 23 per cent of (a+b+c)

14.1D Case
I (ii)

6166.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 28 per cent of (a+b+c)

14.1D Case
I

Cost Rs

6918.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 48 per cent of (a+b+c)

for 15

54690.00
48.00

26251.20

e)

Overhead charges @ 0.25 on (a+b+c+d)

20235.30

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

10117.65

277

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost for 15 cum = a+b+c+d+e+f

7419.61
say

(r)

Remarks/
Input ref.

111294.15

Rate per cum = (a+b+c+d+e+f)/15


14.1D
Case I (iii)

Cost Rs

7420.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 58 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

54690.00
58.00

31720.20
21602.55
10801.28

Cost for 15 cum = a+b+c+d+e+f

118814.03

Rate per cum = (a+b+c+d+e+f)/15

7920.94
say

7921.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

b)

c)

Material
Cement

tonne

50.64

5210.53

263861.05

M-081

Coarse sand

cum

54.00

219.18

11835.72

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

10 mm Aggregate

cum

43.20

723.14

31239.65

M-051

Mate

day

0.88

232.16

204.30

L-12

Mason

day

3.00

353.52

1060.56

L-11

Mazdoor

day

19.00

221.61

4210.59

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2598.00

15588.00

P&M-002

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader

hour

6.00

1116.00

6696.00

P&M-017

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

6.00

234.36

Labour

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

Basic Cost of Labour, Material & Machinery (a+b+c) for


120 cum
For formwork and staging add the following:
14.1D Case
II

(i)
(p)

420659.00

For solid slab super-structure, 18-28 per cent of (a+b+c)


Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 18 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

420659.00
18.00

75718.62
124094.41
62047.20

Cost for 120 cum = a+b+c+d+e+f

682519.23

Rate per cum = (a+b+c+d+e+f)/120

5687.66
say

14.1D Case
II (i)

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

420659.00
23.00

96751.57
129352.64
64676.32

Cost for 120 cum = a+b+c+d+e+f

711439.53

Rate per cum = (a+b+c+d+e+f)/120

5928.66
say

(r)

5688.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 23 per cent of (a+b+c)

14.1D Case
II (i)

1296.00 Lead =1 km
& P&M-050
1406.16 P&M-007

Height above 10m


278

5929.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Basic Cost of Labour, Material & Machinery (a+b+c) for 120


cum
d) Formwork and staging 28 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Quantity

Rate Rs

420659.00
28.00

117784.52
134610.88
67305.44

Cost for 120 cum = a+b+c+d+e+f

740359.84

Rate per cum = (a+b+c+d+e+f)/120

6169.67
say

14.1D Case
II

(ii)

For T-beam & slab, 23-33 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 23 per cent of (a+b+c)

23.00

96751.57

e)

Overhead charges @ 0.25 on (a+b+c+d)

129352.64

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

64676.32
711439.53

Rate per cum = (a+b+c+d+e+f)/120

5928.66
say

(q)

420659.00
28.00

117784.52

e)

Overhead charges @ 0.25 on (a+b+c+d)

134610.88

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

67305.44

Cost for 120 cum = a+b+c+d+e+f

740359.84

Rate per cum = (a+b+c+d+e+f)/120

6169.67
say

(r)

420659.00
33.00

138817.47

e)

Overhead charges @ 0.25 on (a+b+c+d)

139869.12

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

69934.56

Cost for 120 cum = a+b+c+d+e+f

769280.15

Rate per cum = (a+b+c+d+e+f)/120

6410.67
say

(iii)
(p)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

420659.00
38.00

159850.42
145127.36
72563.68

Cost for 120 cum = a+b+c+d+e+f

798200.45

Rate per cum = (a+b+c+d+e+f)/120

6651.67
say

(q)

6411.00

For box girder and balanced cantilever, 38-58 per cent of


cost of concrete.
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 38 per cent of (a+b+c)

14.1D Case
II (iii)

6170.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 33 per cent of (a+b+c)

14.1D Case
II

5929.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 28 per cent of (a+b+c)

14.1D
Case II (ii)

6170.00

420659.00

Cost for 120 cum = a+b+c+d+e+f

14.1D
Case II (ii)

Cost Rs

6652.00

Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c) for 120


cum
d) Formwork and staging 48 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

420659.00
48.00

201916.32
155643.83
77821.92

Cost for 120 cum = a+b+c+d+e+f

856041.07

Rate per cum = (a+b+c+d+e+f)/120

7133.68
say

279

7134.00

Remarks/
Input ref.

Sr No
14.1D Case
II (iii)

Ref. to
MoRTH
Spec.

Description
(r)

Unit

Quantity

Rate Rs

420659.00
58.00

243982.22

e)

Overhead charges @ 0.25 on (a+b+c+d)

166160.31

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

83080.15

Cost for 120 cum = a+b+c+d+e+f

913881.68

Rate per cum = (a+b+c+d+e+f)/120


E

Remarks/
Input ref.

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c) for 120


cum
d) Formwork and staging 58 per cent of (a+b+c)

14.1

Cost Rs

7615.68
say

7616.00

PSC Grade M-40

Case 1 Using concrete mixer.


Unit = 1 cum
Taking output = 15 cum
a)

Material
Cement

tonne

6.45

5210.53

33607.89

M-081

Coarse sand

cum

6.75

219.18

1479.47

M-005

20 mm Aggregate

cum

8.10

938.92

7605.25

M-053

10 mm Aggregate

cum

5.40

723.14

3904.96

M-051

kg

25.80

112.77

2909.49

M-180

Mate

day

0.96

232.16

222.87

L-12

Mason

day

2.00

353.52

707.04

L-11

Mazdoor

day

22.00

221.61

4875.42

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Admixture @ 0.4 per cent of cement


b)

c)

Labour

Machinery

Basic Cost of Labour, Material & Machinery (a+b+c) for


15 cum
For formwork and staging add the following:
14.1E Case
I

(i)

For solid slab super-structure, 20-30 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 20 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

58637.00

for 15

58637.00
20.00

11727.40
17591.10
8795.55

Cost for 15 cum = a+b+c+d+e+f

96751.05

Rate per cum = (a+b+c+d+e+f)/15

6450.07
say

14.1E
Case I (i)

(q)

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

58637.00
25.00

14659.25
18324.06
9162.03

Cost for 15 cum = a+b+c+d+e+f

100782.34

Rate per cum = (a+b+c+d+e+f)/15

6718.82
say

14.1E
Case I (i)

(r)

6450.00

6719.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 30 per cent of (a+b+c)

for 15

58637.00
30.00

17591.10

e)

Overhead charges @ 0.25 on (a+b+c+d)

19057.03

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

9528.51

Cost for 15 cum = a+b+c+d+e+f

104813.64

Rate per cum = (a+b+c+d+e+f)/15

6987.58
280

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs
say

14.1E Case
I

(ii)
(p)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

58637.00
25.00

14659.25
18324.06
9162.03
100782.34

Rate per cum = (a+b+c+d+e+f)/15

6718.82
say

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

58637.00
30.00

17591.10
19057.03
9528.51

Cost for 15 cum = a+b+c+d+e+f

104813.64

Rate per cum = (a+b+c+d+e+f)/15

6987.58
say

(r)

6988.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 35 per cent of (a+b+c)

for 15

58637.00
35.00

20522.95

e)

Overhead charges @ 0.25 on (a+b+c+d)

19789.99

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

9894.99

Cost for 15 cum = a+b+c+d+e+f

108844.93

Rate per cum = (a+b+c+d+e+f)/15


14.1E

6719.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1E Case
I (ii)

6988.00

Height upto 5m

Cost for 15 cum = a+b+c+d+e+f

(q)

Remarks/
Input ref.

For T-beam & slab, 25-35 per cent of (a+b+c)

Basic Cost of Labour, Material & Machinery (a+b+c)


cum
d) Formwork and staging 25 per cent of (a+b+c)

14.1E Case
I (ii)

Cost Rs

7256.33
say

7256.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

Material
Cement

tonne

51.60

5210.53

268863.16

M-081

Coarse sand

cum

54.00

219.18

11835.72

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

10 mm Aggregate

cum

43.20

723.14

31239.65

M-051

kg

206.40

112.77

23275.94

M-180

Mate

day

0.94

232.16

218.23

L-12

Mason

day

3.50

353.52

1237.32

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2598.00

15588.00

P&M-002

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader

hour

6.00

1116.00

6696.00

P&M-017

12818.25

P&M-049

Admixture @ 0.4 per cent of cement


b)

c)

Labour

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
For formwork and staging add the following:
14.1E Case
II

(i)
(p)

For solid/voided slab super-structure, 18-28 per cent of


(a+b+c)
Height upto 5m
281

hour

15.00

854.55

tonne.km

300L

4.32

hour

6.00

234.36

449349.00

1296.00 Lead =1 km
& P&M-050
1406.16 P&M-007

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum
d)

Formwork and staging 18 per cent of (a+b+c)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

449349.00
18.00

80882.82
132557.96
66278.98

Cost for 15 cum = a+b+c+d+e+f

729068.75

Rate per cum = (a+b+c+d+e+f)/120

6075.57
say

14.1E Case
II (i)

(q)

449349.00
23.00

103350.27

e)

Overhead charges @ 0.25 on (a+b+c+d)

138174.82

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

69087.41

Cost for 120 cum = a+b+c+d+e+f

759961.50

Rate per cum = (a+b+c+d+e+f)/120

6333.01
say

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

449349.00
28.00

125817.72
143791.68
71895.84

Cost for 120 cum = a+b+c+d+e+f

790854.24

Rate per cum = (a+b+c+d+e+f)/120

6590.45
say

(ii)
(p)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

449349.00
23.00

103350.27
138174.82
69087.41

Cost for 120 cum = a+b+c+d+e+f

759961.50

Rate per cum = (a+b+c+d+e+f)/120

6333.01
say

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

449349.00
28.00

125817.72
143791.68
71895.84

Cost for 120 cum = a+b+c+d+e+f

790854.24

Rate per cum = (a+b+c+d+e+f)/120

6590.45
say

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

449349.00
33.00

148285.17
149408.54
74704.27

Cost for 120 cum = a+b+c+d+e+f

821746.98

Rate per cum = (a+b+c+d+e+f)/120

6847.89
say

(iii)

6590.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 33 per cent of (a+b+c)

14.1E Case
II

6333.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 28 per cent of (a+b+c)

14.1E
Case II (ii)

6590.00

For T-beam & slab inclduing launching of precast girders by


launching truss upto 40 m, 23-33 per cent of cost of
concrete
(a+b+c)
Height upto
5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 23 per cent of (a+b+c)

14.1E Case
II (ii)

6333.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 28 per cent of (a+b+c)

14.1E Case
II

6076.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 23 per cent of (a+b+c)

14.1E Case
II (i)

Cost Rs

For cast-in-situ box girder, segment construction and


balanced cantilever, 38-58 per cent of cost of concrete.
282

6848.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description
(p)

Unit

Quantity

Rate Rs

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

449349.00
38.00

170752.62
155025.41
77512.70

Cost for 120 cum = a+b+c+d+e+f

852639.73

Rate per cum = (a+b+c+d+e+f)/120

7105.33
say

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

449349.00
48.00

215687.52
166259.13
83129.57

Cost for 120 cum = a+b+c+d+e+f

914425.22

Rate per cum = (a+b+c+d+e+f)/120

7620.21
say

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

449349.00
58.00

260622.42
177492.86
88746.43

Cost for 120 cum = a+b+c+d+e+f

976210.70

Rate per cum = (a+b+c+d+e+f)/120


F

7620.00

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c) for 120


cum
d) Formwork and staging 58 per cent of (a+b+c)

14.1F

7105.00

Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c) for 120


cum
d) Formwork and staging 48 per cent of (a+b+c)

14.1E Case
II (iii)

Remarks/
Input ref.

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 38 per cent of (a+b+c)

14.1E Case
II (iii)

Cost Rs

8135.09
say

8135.00

PSC Grade M-45


Unit = 1 cum
Taking output = 120 cum
a)

Material
Cement

tonne

55.80

5210.53

290747.37

M-081

Coarse sand

cum

54.00

219.18

11835.72

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

10 mm Aggregate

cum

43.20

723.14

31239.65

M-051

kg

223.20

112.77

25170.50

M-180

Mate

day

0.94

232.16

218.23

L-12

Mason

day

3.50

353.52

1237.32

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2598.00

15588.00

P&M-002

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader

hour

6.00

1116.00

6696.00

P&M-017

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

6.00

234.36

Admixture @ 0.4 per cent of cement


b)

c)

Labour

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

Basic Cost of Labour, Material & Machinery (a+b+c) for


120 cum
For formwork and staging add the following:
14.1F

(i)
(p)

1296.00 Lead =1 km
& P&M-050
1406.16 P&M-007

473128.00

For solid slab/voided slab super-structure, 16-26 per cent


of cost of concrete (a+b+c)
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
283

for 120

473128.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

d)

Formwork and staging 16 per cent of (a+b+c)

e)

Overhead charges @ 0.25 on (a+b+c+d)

137207.12

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

68603.56

16.00

75700.48

Cost for 120 cum = a+b+c+d+e+f

754639.16

Rate per cum = (a+b+c+d+e+f)/120

6288.66
say

14.1F (i)

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

473128.00
21.00

99356.88
143121.22
71560.61

Cost for 120 cum = a+b+c+d+e+f

787166.71

Rate per cum = (a+b+c+d+e+f)/120

6559.72
say

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

473128.00
26.00

123013.28
149035.32
74517.66

Cost for 120 cum = a+b+c+d+e+f

819694.26

Rate per cum = (a+b+c+d+e+f)/120

6830.79
say

(ii)

(p)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

473128.00
21.00

99356.88
143121.22
71560.61

Cost for 120 cum = a+b+c+d+e+f

787166.71

Rate per cum = (a+b+c+d+e+f)/120

6559.72
say

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

473128.00
26.00

123013.28
149035.32
74517.66

Cost for 120 cum = a+b+c+d+e+f

819694.26

Rate per cum = (a+b+c+d+e+f)/120

6830.79
say

(r)

6831.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 31 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

473128.00
31.00

146669.68
154949.42
77474.71

Cost for 120 cum = a+b+c+d+e+f

852221.81

Rate per cum = (a+b+c+d+e+f)/120

7101.85
say

14.1F

6560.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 26 per cent of (a+b+c)

14.1F (ii)

6831.00

For T-beam & slab including launching of precast girders by


launching truss upto 40 m span, 21-31 per cent of cost of
concrete.
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 21 per cent of (a+b+c)

14.1F (ii)

6560.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 26 per cent of (a+b+c)

14.1F

6289.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 21 per cent of (a+b+c)

14.1F (i)

Cost Rs

(iii)

For cast-in-situ box girder, segmental construction and


balanced cantilever, 36-56 per cent of cost of concrete.

(p)

Height upto 5m

284

7102.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Basic Cost of Labour, Material & Machinery (a+b+c) for 120


cum
d) Formwork and staging 36 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Quantity

Rate Rs

36.00

170326.08
160863.52
80431.76
884749.36

Rate per cum = (a+b+c+d+e+f)/120

7372.91
say

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

473128.00
46.00

217638.88
172691.72
86345.86

Cost for 120 cum = a+b+c+d+e+f

949804.46

Rate per cum = (a+b+c+d+e+f)/120

7915.04
say

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

473128.00
56.00

264951.68
184519.92
92259.96

Cost for 120 cum = a+b+c+d+e+f

1014859.56

Rate per cum = (a+b+c+d+e+f)/120


G

7915.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 56 per cent of (a+b+c)

14.1

7373.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 46 per cent of (a+b+c)

14.1F (iii)

Remarks/
Input ref.

473128.00

Cost for 120 cum = a+b+c+d+e+f

14.1F (iii)

Cost Rs

8457.16
say

8457.00

PSC Grade M-50


Unit = 1 cum
Taking output = 120 cum
a)

Material
Cement

tonne

58.80

5210.53

306378.95

M-081

Coarse sand

cum

54.00

219.18

11835.72

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

10 mm Aggregate

cum

43.20

723.14

31239.65

M-051

kg

235.20

112.77

26523.75

M-180

Mate

day

0.94

232.16

218.23

L-12

Mason

day

3.50

353.52

1237.32

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2598.00

15588.00

P&M-002

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader

hour

6.00

1116.00

6696.00

P&M-017

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

6.00

234.36

Admixture @ 0.4 per cent of cement


b)

c)

Labour

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

Basic Cost of Labour, Material & Machinery (a+b+c) for


120 cum
For formwork and staging add the following:
14.1G

(i)

For cast-in-situ box girder, segmental construction and


balanced cantilever, 35-55 per cent of cost of concrete

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 35 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)


285

1296.00 Lead =1 km
& P&M-050
1406.16 P&M-007

490113.00

490113.00
35.00

171539.55
165413.14

Sr No

Ref. to
MoRTH
Spec.

Description
f)

Unit

Quantity

Rate Rs

Contractor's profit @ 0.1 on (a+b+c+d+e)

909772.26

Rate per cum = (a+b+c+d+e+f)/120

7581.44
say

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

490113.00
45.00

220550.85
177665.96
88832.98

Cost for 120 cum = a+b+c+d+e+f

977162.79

Rate per cum = (a+b+c+d+e+f)/120

8143.02
say

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

490113.00
55.00

269562.15
189918.79
94959.39

Cost for 120 cum = a+b+c+d+e+f

1044553.33

Rate per cum = (a+b+c+d+e+f)/120


H

8143.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 55 per cent of (a+b+c)

14.1

7581.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 45 per cent of (a+b+c)

14.1G (i)

Remarks/
Input ref.

82706.57

Cost for 120 cum = a+b+c+d+e+f

14.1G (i)

Cost Rs

8704.61
say

8705.00

PSC Grade M- 55
Unit = 1 cum
Taking output = 120 cum
a)

Material
Cement

tonne

63.50

5210.53

330868.42

M-081

Coarse sand

cum

54.00

219.18

11835.72

M-004

20 mm Aggregate

cum

64.80

938.92

60842.02

M-053

10 mm Aggregate

cum

43.20

723.14

31239.65

M-051

kg

254.00

112.77

28643.85

M-180

Mate

day

0.94

232.16

218.23

L-12

Mason

day

3.50

353.52

1237.32

L-11

Mazdoor

day

20.00

221.61

4432.20

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2598.00

15588.00

P&M-002

Generator 100 KVA

hour

6.00

1600.00

9600.00

P&M-080

Loader

hour

6.00

1116.00

6696.00

P&M-017

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

6.00

234.36

Admixture @ 0.4 per cent of cement


b)

c)

Labour

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

Basic Cost of Labour, Material & Machinery (a+b+c) for


120 cum
For formwork and staging add the following:
14.1H

(i)

(p)

1296.00 Lead =1 km
& P&M-050
1406.16 P&M-007

516722.00

For cast-in-situ box girder, segmental construction and


balanced cantilever, 35-55 per cent of cost of concrete
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 35 per cent of (a+b+c)

516722.00
35.00

180852.70

e)

Overhead charges @ 0.25 on (a+b+c+d)

174393.68

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

87196.84

Cost for 120 cum = a+b+c+d+e+f

959165.21

Rate per cum = (a+b+c+d+e+f)/120

7993.04
say
286

7993.00

Sr No

Ref. to
MoRTH
Spec.

14.1H (i)

Description
(q)

Unit

Quantity

Rate Rs

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

516722.00
45.00

232524.90
187311.73
93655.86

Cost for 120 cum = a+b+c+d+e+f

1030214.49

Rate per cum = (a+b+c+d+e+f)/120

8585.12
say

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

516722.00
55.00

284197.10
200229.78
100114.89

Cost for 120 cum = a+b+c+d+e+f

1101263.76

Rate per cum = (a+b+c+d+e+f)/120

1600

8585.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 55 per cent of (a+b+c)

14.2

Remarks/
Input ref.

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
cum
d) Formwork and staging 45 per cent of (a+b+c)

14.1H (i)

Cost Rs

9177.20
say

9177.00

1.05 36191.33

38000.90

M-082

500.19

M-072

Note 1.Where ever concrete is carried out using batching plant, transit
mixer, concrete pump, admixers conforming IS: 9103 @ 0.4 per
cent of weight of cement may be added for achieving desired
slump of concrete.
2. Cement provided for various components of the super
structure is for estimating purpose only. Actual quantity of
cement will be as per approved mix design. Similarly, the
provision for coarse and fine aggregates is for estimating
purpose and the exact quantity shall be as per the mix design.
3. The items like needle and surface vibrators are part of minor T
& P which is already covered under the overhead charges. As
such these items have not been added separately in the rate
analysis.
Supplying, fitting and placing HYSD bar reinforcement in
super-structure complete as per drawing and technical
specifications
Unit = 1 MT
Taking output = 1 MT
a)

Material
HYSD bars including 5 per cent for laps and wastage
Binding wire

b)
Labour for cutting, bending, tying and placing in
position
Mate
Blacksmith
Mazdoor

tonne
Kg

8.00

62.52

day

0.44

232.16

102.15

L-12

day

3.00

353.52

1060.56

L-02

8.00

221.61

1772.88

L-13

day
Basic Cost of Labour & Material (a+b)

41437.00

c)

Overhead charges @ 0.25 on (a+b)

10359.17

d)

Contractor's profit @ 0.1 on (a+b+c)

5179.58

Rate per MT = a+b+c+d


14.3

1800

56975.43
say

56975.00

tonne

0.385 62418.78

24031.23

M-119

metre

42.00

2595.56

M-165

High tensile steel wires/strands including all accessories for


stressing, stressing operations and grouting complete as
per drawing and Technical Specifications
Unit = 1 MT
Taking output = 0.377 MT
Details of cost for 12T13 strand 40 m long cable (weight = 0.377
MT)
a) Material
H.T. Strand @ 9.42 kg/m including 2 per cent for wastage
and extra length for jacking
Sheathing duct ID 66 mm along with 5 per cent extra
length 40 x 1.05 = 42 m.

287

61.80

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Tube anchorage set complete with bearing plate,


permanent wedges etc
Cement for grouting including 3 per cent wastage @ 3.00
kg/m = 3 x 1.03 x 40 = 123.60 kg (say, = 125 kg)
Add 0.50 per cent cost of material for Spacers, Insulation
tape and miscellaneous items
Labour

Cost Rs

Remarks/
Input ref.

Unit

Quantity

Rate Rs

each

2.00

34.35

68.71

M-187

tonne

0.125

5210.53

651.32

M-081

136.73

i) For making and fixing cables, anchorages


Mate

day

0.16

232.16

37.15

L-12

Blacksmith

day

1.00

353.52

353.52

L-02

Mazdoor

day

3.00

221.61

664.83

L-13

Mate/Supervisor

day

0.05

232.16

11.61

L-12

Prestressing operator / Fitter

day

0.25

306.03

76.51

L-08

Mazdoor

day

1.00

221.61

221.61

L-13

Mate/Supervisor

day

0.05

232.16

11.61

L-12

Mason

day

0.25

353.52

88.38

L-11

Mazdoor

day

1.00

221.61

221.61

L-13

Stressing jack with pump

hour

2.50

116.10

290.25

P&M-040

Grouting pump with agitator

hour

1.00

112.77

112.77

M-111

Generator 33 KVA.

hour

3.50

342.36

1198.26

P&M-079

ii) For prestressing

iii) For grouting

c)

Machinery

d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

7692.91
3846.46

Cost for 0.377 MT (a+b+c+d+e)

42311.01

Rate per MT = (a+b+c+d+e)/0.377

112230.80
say

14.4

2702

112231.00

Note Cost of HT steel has been taken for delivery at site. Hence
carriage has not been considered.
Providing and laying Cement concrete wearing coat M-30
grade including reinforcement complete as per drawing and
Technical Specifications
Unit = 1 cum
Taking output = 1 cum
a)

Material

b)

Cement concrete M30 Grade Refer relevant item of


concrete in Item 14.1 excluding formwork
HYSD bar reinforcement Rate as per item No
14.2(Excluding OH & CP)
Labour
Mazdoor for cleaning deck slab concrete surface.

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

cum
tonne

3426.00

3426.00 Item 14.1(C)

0.075 41437.00

3107.78 Item 14.2 A

1.00

DIR used item

day

0.15

221.61

820.88

Rate per cum (a+b+c+d)

9029.65
say

14.5

515 &
2702

33.24
1641.75

Mastic Asphalt
Providing and laying 12 mm thick mastic asphalt wearing
course on top of deck slab excluding prime coat with paving
grade bitumen meeting the requirements given in table 50029, prepared by using mastic cooker and laid to required
level and slope after cleaning the surface, including
providing antiskid surface with bitumen precoated fine
grained hard stone chipping of 9.5 mm nominal size at the
rate of 0.005cum per 10 sqm and at an approximate spacing
of 10 cm center to center in both directions, pressed into
surface when the temperature of surfaces not less than 100
deg. C, protruding 1 mm to 4 mm over mastic surface, all
complete as per clause 515.
Unit = sqm

288

9030.00

L-13

Sr No

Ref. to
MoRTH
Spec.

Description

Cost Rs

Remarks/
Input ref.

Unit

Quantity

Rate Rs

Mate

day

0.49

232.16

113.76

L-12

Mazdoor

day

11.00

221.61

2437.71

L-13

Mazdoor (Skilled)

day

1.25

306.03

382.54

L-15

Taking output = 72.46 sqm (2 tonnes)(0.869 cum) assuming


a density of 2.3 tonnes/cum.
a) Labour

b)

Machinery

289

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Cost Rs

Remarks/
Input ref.

Unit

Quantity

Rate Rs

Mechanical broom @ 1250 sqm per hour

hour

0.06

462.00

27.72

P&M-031

Air compressor 250 cfm

hour

0.06

293.76

17.63

P&M-001

Mastic cooker 1 tonne capacity

hour

6.00

54.81

328.86

P&M-030

Bitumen boiler 1500 litres capacity

hour

6.00

182.52

1095.12

P&M-005

Tractor for towing and positioning of mastic cooker and


bitumen boiler
Material

hour

1.00

171.02

171.02

P&M-053

0.204 32859.22

6703.28

M-074

Base mastic (without coarse aggregates) = 60 per cent


Coarse aggregate(3.35mm to 9.5 mm size) = 40 per cent .
Proportion of material required for mastic asphalt with coarse
aggregates (based on mix design done by CRRI for a specific
case)
i) Bitumen 80/100 or 60/70 @ 10.2 per cent by weight of
mix. 2 x 10.2/100 = 0.204
ii) Crusher stone dust @ 31.9 per cent by weight of mix = 2
x 31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium carbonate content not
less than 80 per cent by weight @ 17.92 per cent by
weight of mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 9.5 mm to 3.35 mm size @ 40 per
cent by weight of mix = 2 x 40/100 = 0.8 MT = 0.8/1.456 =
0.55
v) Pre-coated stone chips of 9.5 mm nominal size for skid
resistance = 72.46x0.005/10 = 0.036
vi) Bitumen for coating of chips @ 2 per cent by weight =
0.036 x 1.456 x 2/100 = 0.001048MT = 1.05kg
d) Overhead charges @ 0.25 on (a+b+c)
e)

tonne
cum

0.39

259.58

101.24

M-021

tonne

0.36

4427.31

1593.83

M-188

cum

0.55

723.14

397.73

M-051

cum

0.036

#VALUE!

#VALUE!

M-142

kg

1.05

32.86

34.50 M-074/1000
#VALUE!

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 72.46 sqm = a+b+c+d+e

#VALUE!

Rate per sqm = (a+b+c+d+e)/72.46

#VALUE!
say

#VALUE!

Note 1.The rates for 6 mm or any other thickness may be worked out
on pro-rata basis.
2. Where tack coat is required to be provided before laying
mastic asphalt, the same is required to be measured and paid
separately.
3.The quantities of binder, filler and aggregates are for
estimating purpose. Exact quantities shall be as per mix design.
4.This rate analysis is based on design made by CRRI for a
specific case and is meant for estimating purposes only. Actual
design is required to be done for each case.
5.The quantity of bitumen works out 17 per cent of the mastic
asphalt blocks without aggregates and falls within the standards
laid down by MoRTH Specifications.
14.6

2703,
1500,
1600 &
1700

Construction of precast RCC railing of M30 Grade, aggregate


size not exceeding 12 mm, true to line and grade, tolerance
of vertical RCC post not to exceed 1 in 500, centre to centre
spacing between vertical post not to exceed 2000 mm,
leaving adequate space between vertical post for expansion,
complete as per approved drawings and technical
specifications.
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m
a)

Material
i) M30 Grade Reinforced Cement Concrete
No. of vertical posts = (12 + 2)2 = 28 Nos., External area of
vertical post 0.25x0.275 = 0.069sqm, Concrete in Vertical
posts = 0.069 x 28 = 1.932 cum, Hand rail in 3 tiers = 3 x
24 = 72 m, External area = 0.170 x 0.175 = 0.03 sqm,
Concrete in hand rails = 0.03 x 72 = 2.16 cum, Total
Concrete = 1.932 + 2.16 = 4.092 cum. (Refer MoRTH SD /
202).

290

cum

4.092

3426.00

14019.19 Item 14.1(C)


DIR used
item

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Add 5 per cent of above cost for form work for casting in
casting yard.
ii) HYSD bar reinforcement Rate as per item No
14.2(Excluding OH & CP)
Refer MoRTH SD / 202.

b)

Add 5 per cent of (a) for handling and fixing of precast


panels in position
Overhead charges @ 0.25 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

Quantity

Rate Rs

tonne

0.865 41437.00

35843.01 Item 14.2 A


DIR used item

2528.16
13272.83
6636.41
73000.56

Rate per metre (a+b+c)/48

1520.84
say

2703,
1500,
1600 &
1700

Remarks/
Input ref.

700.96

Rate for 48 m (a+b+c)

14.7

Cost Rs

1521.00

Note 1.Quantities of material have been adopted from standard plans


of MoRTH vide drawing no. SD/202.
2.48 m length is the total linear length adding both sides of 24 m
span.
Construction of RCC railing of M30 Grade in-situ with 20 mm
nominal size aggregate, true to line and grade, tolerance of
vertical RCC post not to exceed 1 in 500, centre to centre
spacing between vertical post not to exceed 2000 mm,
leaving adequate space between vertical post for expansion,
complete as per approved drawings and technical
specifications.
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m.
a)

Material
i) M30 Grade Reinforced Cement Concrete

cum

4.092

3426.00

14019.19 Item 14.1(C)

tonne

0.865 41437.00

35843.01 Item 14.2 A

No. of vertical posts = (12 + 2)2 = 28 Nos., External area of


vertical post 0.25x0.275 = 0.069sqm, Concrete in vehicle
posts = 0.069 x 28 = 1.932 cum, Hand rail in 3 tiers = 3 x
24 = 72 m, External area = 0.170 x 0.175 = 0.03 sqm,
Concrete in hand rails = 0.03 x 72 = 2.16 cum, Total
Concrete = 1.932 + 2.16 = 4.092 cum. (Refer MoRTH SD /
202).
Add 12 per cent of above cost for form work.
ii) HYSD bar reinforcement Rate as per item No
14.2(Excluding OH & CP)
refer MoRTH SD / 202.
b)

Overhead charges @ 0.25 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

1682.30

12886.13
6443.06

Rate for 48 m (a+b+c)

70873.69

Rate per metre (a+b+c)/48

14.8

2703.2 &
1900

1476.54
say

1477.00

Note 1. Quantities of material have been adopted from standard plans


of MoRTH vide drawing no. SD/202.
2. 48 m length is the total linear length adding both sides of 24 m
span.
Providing, fitting and fixing mild steel railing complete as
per drawing and Technical Specification
Unit = 1 RM
Taking output = 2 x 50 m span = 100 m
a)

Material:
1) ISMC 100 = 2.806 x 1.05 = 2.946 MT

tonne

2.946 37995.24

111933.97

M-179

2) MS Flat = 0.964 x 1.05 = 1.012 MT

tonne

1.012 37995.24

38451.18

M-179

3) MS bars = 0.17 x 1.05 = 0.180 MT

tonne

0.18 37995.24

6839.14

M-179

4) MS bolts, nuts and washers

tonne

0.15 45421.67

Add @ 5 per cent of cost of material for painting one shop


coat with red oxide primer and three coats of synthetic
enamel paint and consumables to safeguard against
weathering and corrosion.
Add for cost of concrete for fixing vertical posts in the
performed recess @ 1 per cent of cost of material.
Add for electricity charges, welding and drilling equipment,
electrodes and other consumables @ 1 per cent of cost of
material.
291

6813.25 M-130*1000
8201.88

1640.38
1640.38

Sr No

Ref. to
MoRTH
Spec.

Description
b)

Unit

Quantity

Rate Rs

Labour
day

2.80

232.16

650.05

L-12

Mazdoor (Skilled)

day

30.00

306.03

9180.90

L-15

Mazdoor

day

40.00

221.61

8864.40

L-13

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

48553.88
24276.94
267046.34

Rate per metre (a+b+c+d)/100

2670.46
say

2705

Remarks/
Input ref.

Mate

Cost for 100 m steel railing = a+b+c+d

14.9

Cost Rs

2670.00

Drainage Spouts complete as per drawing and Technical


specification
Unit = 1 No.
Taking output = 1 No.
a)

b)

Material
Corrosion resistant Structural steel including 5 per cent
wastage
GI pipe 100mm dia

Kg

4.00

38.00

151.98 M-087/1000

metre

6.00

50.28

301.66

M-056

GI bolt 10 mm Dia

each

6.00

11.07

66.41

M-110

Galvanised MS flat clamp

each

2.00

11.07

22.14

M-101

Mate

day

0.02

232.16

4.64

L-12

Skilled (Blacksmith, welder etc.)

day

0.02

353.52

7.07

L-02

Mazdoor

day

0.02

221.61

4.43

L-13

Mate

day

0.01

232.16

2.32

L-12

Mason

day

0.01

353.52

3.54

L-11

Mazdoor

day

0.20

221.61

44.32

L-13

Labour

For fabrication

For fixing in position

c)

Add @ 5 per cent of cost of material and labour for


electrodes, cutting gas, sealant, anti-corrosive bituminous
paint, mild steel grating etc.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

30.43

159.74
79.87

Rate per metre (a+b+c+d)

878.54
say

879.00

Note 1. In case of viaducts in urban areas, the drainage spouts should


be connected with suitably located pipelines to discharge the
surface run-off to drains provided at ground level.

14.10

2700

2. In case of bridges, sufficient length of G.I Pipe shall be


provided to ensure that there is no splashing of water from the
drainage spout on the structure.
PCC M15 Grade leveling course below approach slab
complete as per drawing and Technical specification
Unit = 1 cum
Taking output = 1 cum
Material
Concrete, Rate as per item No. 12.8 (A) excluding
formworks
Rate per cum

14.11

1500,160
0,1700 &
2704

cum

1.00

3952.00
say

3952.00 Item 12.8 (A)


3952.00

Reinforced cement concrete approach slab including


reinforcement and formwork complete as per drawing and
Technical specification
Unit = 1 cum
Taking output = 1 cum
a)

Material
Cement concreteM30 Grade Refer relevant item of
concrete in item 12.8(G)by using batching plant, excluding
formwork i.e. per cum basic cost (a+b+c) (Excluding OH &
CP)

292

cum

1.00

3424.00

3424.00 Item 12.8 (G)

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

b)

( Refer relevant item of concrete in item No. 13.8 (G)


except that form work may be added at the rate of 2 per
cent of cost against 3.5 per cent provided in the
foundation concrete.
HYSD bar reinforcement Rate as per item No
14.2(Excluding OH & CP)
Overhead charges @ 0.25 on (a)

c)

Contractor's profit @ 0.1 on(a+b)

Quantity

Rate Rs

tonne

0.05 41437.00

2071.85 Item 14.2 A


1391.08
695.54
7650.95

say

1600

Remarks/
Input ref.

68.48

Rate per cum (a+b+c)

14.12

Cost Rs

7651.00

Note The grade of reinforced cement concrete may be adopted as


M30 for severe conditions and M25 for moderate conditions.
Providing anti-corrosive treatment to HYSD reinforcement
with Fusion Bonded Epoxy Coating (FBEC)
Unit = 1 MT
Taking output = 1 MT
To be taken as per the prevailing market rates.

14.13

1800 &
2300

VALUE

Note Contractors generally do not have expertise for this item . The
job is therefore, got done from specialised firms who have the
expertise in the field of construction chemicals. The prevailing
rate in the market is required to be ascertained from the market
and added in the cost estimate. Detailed guidelines in this regard
have been issued by MoRTH vide their circular no. RW/NH34041/44/91-S&R dated 21.3.2000.
Precast - pretensioned Girders
Providing, precasting, transportation and placing in position
precast pretensioned concrete girders as per drawing and
technical specifications
Unit = 1 cum
Taking output = 1 cum
Grade of concrete - M40
a)

b)

Material
Cement

tonne

0.47

5210.53

2448.95

M-081

Coarse sand

cum

0.45

219.18

98.63

M-004

20 mm Aggregate

cum

0.54

938.92

507.02

M-053

10 mm Aggregate

cum

0.36

723.14

260.33

M-051

Admixture @ 0.4 per cent of cement

Kg

1.88

112.77

212.01

M-180

HYSD steel .

tonne

0.10 36191.33

3619.13

M-082

HT strand with 5 per cent as wastage and extra length for


anchoring
LDO for steam curing

tonne

0.06 62418.78

3745.13

M-119

#VALUE!

M-122

Litre

37.00

#VALUE!

Add consumables such as binding wire, foam, packing


tape, shuttering oil, HDPE pipe for unbonding of strand, bolt
& nuts etc @ 1 per cent of material cost
Labour

(i) Cutting, bending, making reinforcement cage, placing in


position, binding etc. complete
Taking quantity of steel 100 Kg/cum of concrete including
laps and wastage
Mate

#VALUE!

day

0.06

232.16

13.93

L-12

Mazdoor (Skilled)

day

0.35

306.03

107.11

L-15

Mazdoor

day

1.40

221.61

310.25

L-13

Mate

day

0.02

232.16

4.64

L-12

Mazdoor (Skilled)

day

0.14

306.03

42.84

L-15

Mazdoor

day

0.50

221.61

110.81

L-13

(ii) Cable cutting and threading in position including binding


by insulation tape with HDPE pipes etc., prestessing and
cutting of extra length of HT strand after de-stressing.
Taking quantity of HT strand 60 Kg/cum

(iii) Erection and dismantling of shuttering


Taking shuttering area 10 sqm/cum of concrete
293

Sr No

Ref. to
MoRTH
Spec.

Description

Quantity

Rate Rs

Mate

day

0.12

232.16

27.86

L-12

Mazdoor (Skilled)

day

1.00

306.03

306.03

L-15

Mazdoor

day

2.00

221.61

443.22

L-13

(iv) Concreting by Batching plant and stationary concrete


pump
Mate

Cost Rs

Remarks/
Input ref.

Unit

day

0.03

232.16

6.96

L-12

Mazdoor (Skilled)

day

0.05

306.03

15.30

L-15

Mazdoor

day

0.60

221.61

132.97

L-13

Mate

day

0.01

232.16

2.32

L-12

Mazdoor

day

0.35

221.61

77.56

L-13

day

0.01

232.16

2.32

L-12

day

0.25

221.61

55.40

L-13

Mate

day

0.01

232.16

2.32

L-12

Mazdoor (Skilled)

day

0.06

306.03

18.36

L-15

Mazdoor

day

0.24

221.61

53.19

L-13

Generator 100 KVA

hour

0.05

1600.00

80.00

P&M-080

Batching Plant @ 20 cum/hour

hour

0.05

2598.00

129.90

P&M-002

Transit Mixer 4 cum capacity

hour

0.10

854.55

85.46

P&M-049

Concrete Pump stationary

hour

0.05

234.36

11.72

P&M-007

Crane 35 tonne capacity

hour

0.10

784.62

78.46

P&M-012

Trailor 30 tonne capacity

hour

0.10

1864.08

186.41

P&M-089

Loader

hour

0.05

1116.00

55.80

P&M-017

117.69

P&M-012

(v) Steam curing and manual curing

(vi) Handling of precast girder, stacking in stockyard and


again loading in trailor
Mate
Mazdoor
(vii) Placement of girders in position over pier caps
including placement of sand jacks, channel, levelling etc.

c)

Machinery

i) At casting yard

ii) For transportation and placement at site


Crane 35 tonne capacity
Trailer 30 tonne capacity for transporting to site.

hour

0.15

784.62

tonne.km

2.5xL

2.27

hour

0.15

1864.08

5.67 Lead =1 km
& P&M-090

(L - Lead in Kilometer)
Trailor 30 tonne capacity during placement.

#VALUE!

d)
e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

1700 &
1800

P&M-089

#VALUE!

Rate per cum = (a+b+c+d+e)


14.14

279.61

Cost of formwork, steam curing arrangement, pretensioning


arrangement etc @ 5 per cent of cost material, labour and
machinery
Overhead charges @ 0.25 on (a+b+c)

#VALUE!
say

#VALUE!

Providing and fixing Helical pipes in voided concrete slabs


Unit = 1 RM
Taking output = 1 RM
a)

Material
Helical pipes 600mm diameter

metre

1.00

#VALUE!

#VALUE!

M-117

Tie rods 20mm diameter

each

1.00

47.51

47.51

M-183

Consumables for sealing joints etc.@ 5 per cent of cost of


material
b) Labour

#VALUE!

Mate

day

0.01

232.16

2.32

L-12

Fitter

day

0.05

306.03

15.30

L-08

Mazdoor

day

0.20

221.61

44.32

L-13

c)

Overhead charges @ 0.25 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Rate per cum (a+b+c+d)

#VALUE!
say
294

#VALUE!

Sr No
14.15

14.16

Ref. to
MoRTH
Spec.
800

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Crash Barriers
The rate analysis for rigid crash barrier in reinforced cement
concrete, semi-rigid crash barrier with metal beam and flexible
crash barrier with wire ropes have been made and included in
chapter-8 on Traffic and Transportation.
Painting on concrete surface

800

Per m

VALUE

Providing and applying 2 coats of water based cement paint


to unplastered concrete surface after cleaning the surface of
dirt, dust, oil, grease, efflorescence and applying paint @ of
1 litre for 2 sqm.
Unit = sqm
Taking output = 10 sqm
a)

Labour
Mate

day

0.01

232.16

2.32

L-12

Painter

day

0.25

353.52

88.38

L-18

Mazdoor (Skilled)

day

0.25

306.03

76.51

L-15

Litres

5.00

75.18

375.90

M-190

b)

Material

c)

Water based paint of approved quality for cement concrete


surface
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

135.78
67.89

Cost for 10 sqm (a+b+c+d)

746.78

Rate per sqm (a+b+c+d)/10

74.68
say

14.17

2604

75.00

Burried Joint
Providing and laying a burried expansion joint, expansion
gap being 20 mm, covered with 12 mm thick, 200 mm wide
galvanised weldable structural steel plate as per IS: 2062,
placed symmetrical to centre line of the joint, resting freely
over the top surface of the deck concrete, welding of 8 mm
dia. 100 mm long galvanised nails spaced 300 mm c/c along
the centre line of the plate, all as specified in clause 2604.
Unit = Running meter
Taking output = 12 m
a)

Labour
Mate

day

0.02

232.16

4.64

L-12

Mazdoor

day

0.40

221.61

88.64

L-13

Mazdoor (Skilled)

day

0.20

306.03

61.21

L-15

kg

237.50

46.24

b)

Material

c)

Galvanised M.S plate 200 mm wide,12 mm thick @ 94.20


kg/sqm including 5 per cent wastage
Add 1 per cent of cost of steel plate cutting, welding
consumables and galvanised nails.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

10981.82 M-060/1000
109.82
2811.53
1405.77

Cost for 12 m = (a+b+c+d)

15463.44

Rate per m = (a+b+c+d)/12

1288.62
say

1289.00

Note Guidelines laid down vide the MoRTH circular No. RW/NH34059/1/96-S&R dated 30.11.2000 and subsequent corrigendum
dated 25.01.2001 may be reffered for expansion joints.
14.18

2605

Filler joint
(i)

Providing & fixing 2 mm thick corrugated copper plate in


expansion joint complete as per drawing & Technical
Specification.
Unit = Running meter
Taking output = 12 m
a)

Labour

Cutting, bending, carrying & fixing etc.


Mate

day

0.04

232.16

9.29

L-12

Mazdoor

day

0.50

221.61

110.81

L-13

295

Sr No

Ref. to
MoRTH
Spec.

Description
Mazdoor (Skilled)
b)

Unit

Quantity

Rate Rs

Cost Rs

day

0.50

306.03

153.02

kg

55.00

481.39

26476.19

Remarks/
Input ref.
L-15

Material
Copper plate - 12m long x 250 mm wide

M-086

Area = 12 x 0.25 = 3 sqm


Weight = 3 x 0.002 x 8900 = 53.4 kg
Wastage @ 2.5 per cent = 1.33 kg/54.73 kg say = 55 kg.
c)

Overhead charges @ 0.25 on (a+b)

6687.32

d)

Contractor's profit @ 0.1 on (a+b+c)

3343.66

Cost for 12 m = (a+b+c+d)

36780.28

Rate per m = (a+b+c+d)/12

3065.02
say

14.18

(ii)

3065.00

Providing & fixing 20 mm thick compressible fibre board in


expansion joint complete as per drawing & Technical
Specification.
Unit = Running meter
Taking output = 12 m
a)

Labour

For carrying, placing & fixing.

b)

Mate

day

0.01

232.16

1.86

L-12

Mazdoor

day

0.10

221.61

22.16

L-13

Mazdoor (Skilled)

day

0.10

306.03

30.60

L-15

sqm

3.00

603.53

1810.60

Material

20 mm thick compressible fibre board 12 m long x 25 cm


deep.
Area = 12 x 0.25 = 3 sqm
c)

Overhead charges @ 0.25 on (a+b)

466.31

d)

Contractor's profit @ 0.1 on (a+b+c)

233.15

Cost for 12 m = (a+b+c+d)

2564.68

Rate per m = (a+b+c+d)/12


14.18

(iii)

M-084

213.72
say

214.00

Providing and fixing in position 20 mm thick premoulded


joint filler in expansion joint for fixed ends of simply
supported spans not exceeding 10 m to cater for a
horizontal movement upto 20 mm, covered with sealant
complete as per drawing and technical specifications.
Unit = Running meter
Taking output = 12 m
a)

Labour
Mate

day

0.01

232.16

2.32

L-12

Mazdoor

day

0.20

221.61

44.32

L-13

Mazdoor (Skilled)

day

0.10

306.03

30.60

L-15

sqm

3.60

708.07

2549.05

b)

Material

c)

Premoulded joint filler 12 m long,20 mm thick and 300 mm


deep.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

656.57
328.29

Cost for 12 m = (a+b+c+d)

3611.16

Rate per m = (a+b+c+d)/12

300.93
say

14.18

(iv)

Providing and filling joint sealing compound as per


drawings and technical specifications with coarse sand and
6 per cent bitumen by weight
Unit = Running meter
Taking output = 12 m
12m long x 100 mm wide x 10mm deep recess

296

301.00

M-141

Sr No

Ref. to
MoRTH
Spec.

Description
a)

b)

Cost Rs

Remarks/
Input ref.

Unit

Quantity

Rate Rs

Mate

day

0.02

232.16

4.64

L-12

Mazdoor

day

0.50

221.61

110.81

L-13

Mazdoor (Skilled)

day

0.10

306.03

30.60

L-15

cum

0.012

219.18

2.63

M-005

cum

0.001 32859.22

32.86

M-074

Labour

Material
Sand

Volume 12 x 0.1 x 0.01 = 0.012 cum


Weight 0.012 x 1400 = 16.8kg
Bitumen
16.8 x 0.06 = 1 kg
c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

45.39
22.69

Cost for 12 m = (a+b+c+d)

249.62

Rate per m = (a+b+c+d)/12

20.80
say

20.80

Note For arriving at the final rate of filler joints per m


length and per cm depth of joint filling compound,
the rates at Sl. No. i), ii), iii) & iv) shall be added
14.19

2600

Asphaltic Plug joint


Providing and laying of asphaltic plug joint to provide for
horizontal movement of 25 mm and vertical movement of 2
mm, depth of joint varying from 75 mm to 100 mm, width
varying from 500 mm to 750 mm (in traffic direction),
covered with a closure plate of 200mm x 6mm of weldable
structural steel conforming to IS: 2062, asphaltic plug to
consist of polymer modified bitumen binder, carefully
selected single size aggregate of 12.5 mm nominal size and
a heat resistant foam caulking/backer rod, all as per
approved drawings and specifications.
Unit = Running meter
Taking output = 12 m
a)

b)

Labour
Mate

day

0.052

232.16

12.07

L-12

Mazdoor

day

1.00

221.61

221.61

L-13

Mazdoor (Skilled)

day

0.30

306.03

91.81

L-15

620.90

M-052

Material
Crushed stone aggregate 12.5 mm nominal size

c)

cum

0.75

827.86

Polymer modified bitumen

kg

77.50

33.81

2620.43 M-078/ 1000

Galvanised structural steel plate 200 mm wide,6 mm thick,


12 m long (2.4 sqm) @ 47.10 kg/sqm including 5 per cent
wastage
Add 1 per cent for welding and foam caulking/backer rod
and other incidentals.
Machinery

kg

113.00

38.63

4365.70

79.33

Mastic cooker 1 tonne capacity

hour

1.00

54.81

54.81

P&M-030

Smooth 3-wheeled steel roller 8-10 capacity

hour

0.50

625.00

312.50

P&M-044

d)

Overhead charges @ 0.25 on (a+b+c)

2094.79

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1047.39

Cost for 12 m asphalt plug joint = (a+b+c+d+e)

11521.34

Rate per m = (a+b+c+d+e)/12

960.11
say

14.20

2606

M-103

Note The nominal size of aggregates shall be 12.5 mm for depth of


joint upto 75 mm and 20 mm for joints of depth more than 75
mm.
Elastomeric Slab Steel Expansion Joint

297

960.00

Sr No

Ref. to
MoRTH
Spec.

Description

Cost Rs

Remarks/
Input ref.

Unit

Quantity

Rate Rs

Mate

day

0.06

232.16

13.93

L-12

Mazdoor

day

1.00

221.61

221.61

L-13

Mazdoor (Skilled)

day

0.50

306.03

153.02

L-15

12.00 19422.70

233072.41

Providing and laying of an elastomeric slab steel expansion


joint, catering to right or skew (less than 20 deg., moderately
curved with maximum horizontal movement upto 50 mm,
complete as per approved drawings and standard
specifications to be installed by the manufacturer/supplier
or their authorised representative ensuring compliance to
the manufacturer's instructions for installation and clause
2606 of MoRTH specifications for road & bridge works.
Unit = Running meter
Taking output = 12 m
a)

Labour

b)

Material

c)

Supply of elastomeric slab seal expansion joint assembly


manufactured by using chloroprene, elastomer for
elastomeric slab unit conforming to clause 915.1 of IRC: 83
(part II), complete as per approved drawings and standard
specification conforming to clause 2606 of MoRT&H
Specification
Add 5 per cent of cost of material for anchorage
reinforcement, welding and other incidentals.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

metre

11653.62
61278.65
30639.32

Cost for 12 m = (a+b+c+d)

337032.56

Rate per m = (a+b+c+d)/12

28086.05
say

14.21

2600

M-093

28086.00

Compression Seal Joint


Providing and laying of compression seal joint consisting of
steel armoured nosing at two edges of the joint gap suitably
anchored to the deck concrete and a preformed chloroprene
elastomer or closed cell foam joint sealer compressed and
fixed into the joint gap with special adhesive binder to cater
for a horizontal movement upto 40 mm and vertical
movement of 3 mm.
Unit = Running meter
Taking output = 12 m
a)

b)

Labour
Mate

day

0.036

232.16

8.36

L-12

Mazdoor

day

0.60

221.61

132.97

L-13

Mazdoor (Skilled)

day

0.30

306.03

91.81

L-15

kg

446.00

38.63

17231.00

Material
1. Galvanised angle sections 100mm x 100mm of 12mm
thickness weldable structural steel as per IS: 2062, 2 nos.
of 12 m length each @ 17.7 kg/m and 5 per cent wastage.

c)

Add 5 per cent of cost of above for structural steel for


anchorage, welding and other incidentals.
Preformed continuous chloroprene elastomer or closed cell
foam sealing element with high tear strength, vulcanised in
a single operation for the full length of a joint to ensure
water tightness.
Add 1 per cent of cost of sealing element for lubricant-cumadhesive and other consumables.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

873.21
metre

12.00

#VALUE!

#VALUE!

#VALUE!
#VALUE!
#VALUE!

Cost for 12 m = (a+b+c+d)

#VALUE!

Rate per m = (a+b+c+d)/12

#VALUE!
say

Note 1. The installation shall be done by the manufacturer or his


authorised representative to the satisfaction of the Engineer.

298

M-103

#VALUE!

M-143

Sr No

14.22

Ref. to
MoRTH
Spec.

2607

Description

Cost Rs

Remarks/
Input ref.

Unit

Quantity

Rate Rs

Mate

day

0.05

232.16

11.61

L-12

Mazdoor

day

1.00

221.61

221.61

L-13

Mazdoor (Skilled)

day

0.25

306.03

76.51

L-15

metre

12.00

6043.69

72524.32

2. The concreting for joining the expansion joint assembly with


the deck has not been included in this analysis as the same is
catered in the quantities of RCC deck.
3. The anchoring bars of the expansion joint assembly shall be
welded to the main reinforcement of the deck.
Strip Seal Expansion Joint
Providing and laying of a strip seal expansion joint catering
to maximum horizontal movement upto 70 mm, complete as
per approved drawings and standard specifications to be
installed by the manufacturer/supplier or their authorised
representative ensuring compliance to the manufacturer's
instructions for installation.
Unit = Running meter
Taking output = 12 m
a)

Labour

b)

Material

c)

Supply of complete assembly of strip seal expansion joint


comprising of edge beams, anchorage, strip seal element
and complete accessories as per approved specifications
and drawings.
Add 5 per cent of cost of material for anchorage
reinforcement, welding and other incidentals.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3641.70
19118.94
9559.47

Cost for 12 m = (a+b+c+d)

105154.15

Rate per m = (a+b+c+d)/12

8762.85
say

14.23

2600

M-178

8763.00

Note 1. The installation shall be done by the manufacturer or his


authorised representative to the satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly with
the deck has not been included in this analysis as the same is
catered in the quantities of RCC deck.
Modular Strip / Box Seal Joint
Providing and laying of a modular strip Box seal expansion
joint including anchorage catering to a horizontal movement
beyond 70 mm and upto 140mm, complete as per approved
drawings and standard specifications to be installed by the
manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions for
installation.
Unit = Running meter
Taking output = 12 m
a)

Labour
Mate

day

0.056

232.16

13.00

L-12

Mazdoor

day

1.00

221.61

221.61

L-13

Mazdoor (Skilled)

day

0.40

306.03

122.41

L-15

12.00 21404.46

256853.52

b)

Material

c)

Supply of a modular strip/box seal joint assembly


comprising of edge beams, central beam,2 modules
chloroprene seal, anchorage elements, support and control
system, all steel sections protected against corrosion and
installed by the manufacturer or his authorised
representative.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

metre

64302.63
32151.32

Cost for 12 m Modular strip/box seal joint = (a+b+c+d)

353664.49

Rate per m = (a+b+c+d)/12

29472.04
say

Note 1. The installation shall be done by the manufacturer or his


authorised representative to the satisfaction of the Engineer.
299

29472.00

M-127

Sr No

14.24

Ref. to
MoRTH
Spec.

2600

Description

Cost Rs

Remarks/
Input ref.

Unit

Quantity

Rate Rs

Mate

day

0.07

232.16

16.25

L-12

Mazdoor

day

1.25

221.61

277.01

L-13

Mazdoor (Skilled)

day

0.50

306.03

153.02

L-15

metre

12.00

#VALUE!

#VALUE!

M-128

2. The concreting for joining the expansion joint assembly with


the deck has not been included in this analysis as the same is
catered in the quantities of RCC deck.
3. The anchoring bars of the expansion joint assembly shall be
welded to the main reinforcement of the deck.
Modular Strip / Box Seal Joint
Providing and laying of a modular strip box seal expansion
joint catering to a horizontal movement beyond 140mm and
upto 210mm, complete as per approved drawings and
standard specifications to be installed by the
manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions for
installation.
Unit = Running meter
Taking output = 12 m
a)

Labour

b)

Material

c)

Supply of a modular box/box seal joint assembly containing


3 modules/cells and comprising of edge beams, two central
beams, chloroprene seal, anchorage elements, support and
control system, all steel sections protected against
corrosion and installed by the manufacturer or his
authorised representative.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!
#VALUE!

Cost for 12 m Modular strip/box seal joint = (a+b+c+d)

#VALUE!

Rate per m = (a+b+c+d)/12

#VALUE!
say

Note 1. The installation shall be done by the manufacturer or his


authorised representative to the satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly with
the deck has not been included in this analysis as the same is
catered in the quantities of RCC deck.
3. The anchoring bars of the expansion joint assembly shall be
welded to the main reinforcement of the deck.

300

#VALUE!

CHAPTER - 15

RIVER TRAINING AND PROTECTION WORKS


Sr No
15.1

Ref. to
MoRTH
Spec.
2503

Description

*
Note
15.2

2503

Unit

Providing and laying boulders apron on river bed for


protection against scour with stone boulders weighing not
less than 40 kg each complete as per drawing and Technical
specification.
Boulder Laid Dry Without Wire Crates.
Unit = cum
Taking output = 1 cum
a) Material
Stone
Stone Spalls
b) Labour
Mate
Mason
Mazdoor *
c) Overhead charges @ 0.25 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per cum = (a+b+c+d)
Including excavation for trimming for preparation of bed.
Nominal excavation required for preparation of bed has been taken
into account while making provision for labour.
Boulder Apron Laid in Wire Crates
Providing and laying of boulder apron laid in wire crates made with
4mm dia GI wire conforming to IS: 280 & IS:4826 in 100mm x
100mm mesh (weaved diagonally) including 10 per cent extra for
laps and joints laid with stone boulders weighing not less than 40
kg each.
Unit = cum
Taking output = 3 mx1.5mx1.25m = 5.63 cum
a) Material
4mm GI wire crates woven in mesh size of 100 mm x 100 mm.
Stone
Stone Spalls
b) Labour
Mate
Mazdoor (Skilled)
Mazdoor
c) Overhead charges @ 0.25 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 5.63 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5.63

Quantity Rate Rs

15.3

2503

Including excavation for trimming for preparation of bed.


Readymade woven wire crate rolls have been considered in the
rate analysis. In case readymade rolls are not available, GI wire
4mm dia. @ 32 kg per 10 sqm may be provided. In that case 2 per
cent of the cost of GI wire may be added for weaving the wire
crates.
Cement Concrete Blocks (size 0.5 x 0.5 x 0.5 m)
Providing and laying of apron with cement concrete blocks of size
0.5x0.5x0.5 m cast in-situ and made with nominal mix of M-15
grade cement concrete with a minimum cement content of 250
kg/cum as per IRC: 21-2000.
Unit = cum
Taking out put = 1 cum
Concrete Grade M15 Rate as per item No. 12.8 (A) including OH &
CP
Add 2 per cent of cost to account for excavation for preparation of
bed, nominal surface reinforcement and filling of granular material
in recesses between blocks.
Rate per cum

1.00
0.20

397.97
370.06

397.97
74.01

day
day
day

0.04
0.35
0.75

232.16
353.52
221.61

L-12
L-11
L-13

say

9.29
123.73
166.21
192.80
96.40
1060.41
1060.00

2504

Providing and laying Pitching on slopes laid over prepared


filter media including boulder apron laid dry in front of toe of
embankment complete as per drawing and Technical
specifications
300

M-003
M-008

sqm
cum
cum

22.00
5.63
1.13

73.09
397.97
370.06

1608.03
2240.57
418.17

M-102
M-003
M-008

day
day
day

0.18
1.50
*3.00

232.16
306.03
221.61

41.79
459.05
664.8
1358.1
679.05
7469.60
1326.75
1327.00

L-12
L-15
L-13

cum

1.00

4109.00

4109.00 Item 12.8 (A)


82.18

say
15.4

Remarks/
Input ref.

cum
cum

say
*
Note

Cost Rs

4191.18
4191.00

Sr No

Ref. to
MoRTH
Spec.

Description
A

Unit

Stone/Boulder
Unit = cum
Taking output = 1 cum
a) Material
Stone weighing not less than 40kg
Stone spalls of minimum 25 mm size
b) Labour
Mate
Mason
Mazdoor
c) Overhead charges @ 0.25 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per cum = (a+b+c+d)

Quantity Rate Rs

cum
cum

1.00
0.20

397.97
370.06

397.97
74.01

day
day
day

0.04
0.35
0.75

232.16
353.52
221.61

9.29
123.73
166.21
192.80
96.40
1060.41
1060.00

say
15.4

Cost Rs

Remarks/
Input ref.

M-003
M-008
L-12
L-11
L-13

Cement Concrete Blocks of size 0.3x0.3 x0.3 m cast in cement


concrete of Grade M15
Unit = cum
Taking output = 1 cum
Concrete Grade M15 Rate as per item No. 12.8 (A)

cum

1.00

4109.00

Add 2 per cent of cost to account for nominal surface


reinforcement and filling of granular material in recesses between
blocks.
Rate per cum
15.5

2504

4109.00 Item 12.8 (A)


82.18

4191.18
say

4191.00

Providing and laying Filter material underneath pitching in


slopes complete as per drawing and Technical specification
Unit = cum
Taking output = 1 cum
a)

Material
cum

1.20

678.64

814.37

M-012

Mate

day

0.05

232.16

11.61

L-12

Mazdoor (Skilled)

day

0.25

306.03

76.51

L-15

Mazdoor *

day

1.00

221.61

221.61

L-13

Graded stone aggregate of required size


b)

Labour

281.02

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

140.51
1545.63

Rate per cum = (a+b+c+d)


say

1546.00

Includes Mazdoor required for trimming of slope to proper profile


and preparation of bed.
15.6

700 &
2504

Geotextile Filter
Laying of a geotextile filter between pitching and embankment
slopes on which pitching is laid to prevent escape of the
embankment material through the voids of the stone
pitching/cement concrete blocks as well as to allow free movement
of water without creating any uplift head on the pitching.
Unit = sqm
Taking output = 10 sqm.
a)

Labour

Mate

day

0.02

232.16

4.64

L-12

Mazdoor

day

0.30

221.61

66.48

L-13

Mazdoor (Skilled)

day

0.10

306.03

30.60

L-15

sqm

11.00

85.89

944.79

M-181

b) Material
Permeable synthetic geotextile including 5 per cent for overlap
and wastage
c) Overhead charges @ 0.25 on (a+b)
d)

Contractor's profit @ 0.1 on (a+b+c)

261.63
130.82
1438.97

Cost for 10 sqm = a+b+c+d

143.90

Rate per sqm = (a+b+c+d)/10


301

Sr No

Ref. to
MoRTH
Spec.

15.7

2504.4

Description

Unit

Quantity Rate Rs

Cost Rs

say

144.00

Remarks/
Input ref.

Toe protection
A toe wall for toe protection can either be in dry rubble masonry in
case of dry rubble pitching or pitching with stones in wire crates or
it can be in PCC M15 nominal mix if cement concert block have
been used for pitching . Rates for toe wall can be adopted from
respective clauses depending upon approved design. The rate for
excavation for foundation, dry rubble masonry and PCC M15 have
been analysed and given in respective chapters.

15.8

2505

Providing and laying Flooring complete as per drawing and


Technical specifications laid over cement concert bedding.
A

Rubble stone laid in cement mortar 1:3


Unit = cum
Taking output = 1 cum
a) Cement mortor 1:3 (Rate as in Item 12.6 sub-analysis)
excluding OH & CP
b)
Add for cement concrete bedding (M15 Nominal mix)
vide Item 12.8 (A) excluding OH & CP . Quantity shall be
adopted as per design ( Assume Rubble stone Flooring
thickness 300mm and cement concrete bedding thickness
100mm)
Add 1 per cent of cost to account for excavation for preparation of
bed.
c) Material

cum

0.33

3096.00

1021.68 Item 12.6 (A)

cum

0.33

2874.00

948.42 Item 12.8 (A)

19.70

cum

1.00

397.97

397.97

M-003

cum

0.20

370.06

74.01

M-008

Mate

day

0.08

232.16

18.57

L-12

Mason

day

0.50

353.52

176.76

L-11

Mazdoor (for laying stones, filling of quarry spalls)

day

1.50

221.61

332.42

L-13

Stone
Stone Spalls
d)

Labour

e)

Overhead charges @ 0.25 on (a+c+d)

f)

Contractor's profit @ 0.1 on (a+c+d+e)

505.35
252.68
3747.56

Rate per cum = (a+b+c+d+e+f)


say
15.8

15.9

2506

Includes cement mortar for laying and filling of joints.

Cement Concrete blocks Grade M15


Concrete Grade M15 block. (Rate as per item No. 12.8 (A)
including OH & CP.
Add for cement concrete bedding (M15 Nominal mix) vide Item
12.8 (A) including OH & CP. Quantity shall be adopted as per
design ( Assume Cement Concrete blocks thickness 300mm and
cement concrete bedding thickness 100mm)
Add 1 per cent of cost to account for excavation for preparation of
bed.
Rate per cum

3748.00

cum

1.00

4109.00

4109.00 Item 12.8 (A)

cum

0.33

4109.00

1355.97 Item 12.8 (A)

54.65
5519.62
say

5520.00

Dry Rubble Flooring


Construction of dry rubble flooring at cross drainage works for
relatively less important works.
Unit = cum
Taking output = 1 cum
a)

Material

Stone

cum

1.00

397.97

397.97

M-003

Stone Spalls

cum

0.20

370.06

74.01

M-008

Mate

day

0.10

232.16

23.22

L-12

Mason

day

0.50

353.52

176.76

L-11

mazdoor

day

1.50

221.61

332.42

L-13

b)

Labour

Add 1 per cent of (b) for trimming and preparation of base.

302

5.32

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity Rate Rs

c)

Overhead charges @ 0.25 on (a+b)

252.42

d)

Contractor's profit @ 0.1 on (a+b+c)

126.21
say

2507.2
A

Rate same as per item No. 12.7 (A)

cum

1.00

Note

15.11

2507.2

3200.00

3200.00 Item 12.7 (A )

including OH & CP
say

Rate per cum


B

1388.00

Curtain wall complete as per drawing and Technical


specification
Stone masonry in cement mortar (1:3)
Coursed rubble masonry (1st sort)

15.10

Remarks/
Input ref.

1388.33

Rate per cum = (a+b+c+d)


15.10

Cost Rs

Cement concrete Grade M15


Concrete Grade M15 Rate as per item No. 12.8 (A) including OH &
CP
Rate per cum
Other items like excavation for foundation, filling behind wall, filter
media, weep holes etc. shall be added separately as per approved
design.
Flexible Apron :Construction of flexible apron 1 m thick
comprising of loose stone boulders weighing not less than 40
kg beyond curtain wall.
Unit = cum

cum

1.00

4109.00

3200.00

4109.00 Item 12.8 (A)

say

4109.00

Taking Output = 1 cum


a)

Material

Stone

cum

1.00

397.97

397.97

M-003

Stone Spalls

cum

0.20

370.06

74.01

M-008

Mate

day

0.05

232.16

11.61

L-12

Mason

day

0.25

353.52

88.38

L-11

Mazdoor
Add 1 per cent of cost of (a+b) for trimming and preparation of
bed.
c) Overhead charges @ 0.25 on (a+b)

day

1.00

221.61

221.61

L-13

b)

d)

Labour

7.94
200.38
100.19

Contractor's profit @ 0.1 on (a+b+c)

1102.08

Rate per cum = (a+b+c+d)


say
15.12

2503.3

1102.00

Gabian Structure for Retaining Earth


Providing and construction of a gabian structure for retaining earth
with segments of wire crates of size 7 m x 3 m x 0.6 m each
divided into 1.5 m compartments by cross netting, made from 4
mm galvanised steel wire @ 32 kg per 10 sqm having minimum
tensile strength of 300 Mpa conforming to IS:280 and galvanizing
coating conforming to IS:4826, woven into mesh with double twist,
mesh size not exceeding 100 x 100 mm, filled with boulders with
least dimension of 200 mm, all loose ends to be tied with 4 mm
galvanised steel wire
Unit = cum
Taking output = 7 x 3 x 0.6 = 12.60 cum
a)

Labour

Mate

day

0.28

232.16

65.00

L-12

Mazdoor

day

5.00

221.61

1108.05

L-13

Mazdoor (Skilled)

day

2.00

306.03

612.06

L-15

sqm

61.00

73.09

4458.63

M-102

cum

12.60

397.97

5014.42

M-003

cum

2.52

370.06

932.55

M-008

b) Material
Galvanised steel wire crates of mesh size 100 mm x 100 mm
woven with 4mm dia. GI wire in rolls of required size.
Stone boulders with least dimension of 200 mm
Stone spalls of minimum size 25 mm
c)

Overhead charges @ 0.25 on (a+b)

3047.68

d)

Contractor's profit @ 0.1 on (a+b+c)

1523.84
16762.24

Cost for 12.60 cum (a+b+c+d)


303

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity Rate Rs

Cost Rs

say

1330.00

1330.34

Rate per cum (a+b+c+d)/12.60


Note

15.13

2503.3

Remarks/
Input ref.

Readymade woven wire crate rolls have been considered in the


rate analysis. In case readymade rolls are not available, GI wire
4mm dia. @ 32 kg per 10 sqm may be provided. In that case 2 per
cent of the cost of GI wire may be added for weaving the wire
crates.
Gabian Structure for Erosion Control, River Training Works
and Protection works
Providing and constructing gabian structures for erosion control,
river training works and protection works with wire crates of size 2
m x 1 m x 0.3 m each divided into 1m compartments by cross
netting, made from 4 mm galvanised steel wire @ 32 kg per 10
sqm having minimum tensile strength of 300 Mpa conforming to
IS:280 and galvanizing coating conforming to IS:4826, woven into
mesh with double twist, mesh size not exceeding 100 mm x 100
mm, filled with boulders with least dimension of 200 mm, all loose
ends to be securely tied with 4 mm galvanised steel wire.
Unit = cum
Taking output = 2 x 1 x 0.3 x 10 Nos. = 6.00 cum
a)

Labour

Mate

day

0.14

232.16

32.50

L-12

Mazdoor

day

2.50

221.61

554.03

L-13

Mazdoor (Skilled)

day

1.00

306.03

306.03

L-15

sqm

65.00

73.09

4751.00

M-102

cum

6.00

397.97

2387.82

M-003

cum

1.20

370.06

444.07

M-008

b) Material
Galvanised steel wire crates of mesh size 100 mm x 100 mm
woven with 4mm dia. GI wire in rolls of required size to cover 6.00
cum.
Stone boulders with least dimension of 200 mm
Stone spalls of minimum size 25 mm

2118.86

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1059.43
11653.75

Cost for 6.00 cum (a+b+c+d)

1942.29

Rate per cum (a+b+c+d)/6.00


say
Note

Readymade woven wire crate rolls have been considered in the


rate analysis. In case readymade rolls are not available, GI wire
4mm dia. @ 32 kg per 10 sqm may be provided. In that case 2 per
cent of the cost of GI wire may be added for weaving the wire
crates.

304

1942.00

CHAPTER-16

REPAIR AND REHABILITATION


Sr No
16.1

Ref. to
MoRTH
Spec.
2809

Description

Unit

2809

Rate Rs

day
day

0.06
1.00

232.16
221.61

13.93
221.61

L-12
L-13

hour

1.00

293.76

293.76

P&M-001

hour

0.50

171.02

P&M-053

say

85.51
184.44
79.93
879.18
87.92
88.00

day
day

0.03
0.75

232.16
221.61

6.96
166.21

L-12
L-13

hour
hour

0.75
0.40

293.76
171.02

220.32
68.41
138.57
60.05
660.52
66.05
66.00

P&M-001
P&M-053

say
2807

Guniting concrete surface with cement mortar applied with compressor after
cleaning surface and spraying with epoxy complete as per Technical
Specification
Unit = Sq m
Taking output = 1 sqm
Assuming thickness 25 mm
a) Material
Cement
Graded sand
Wire mesh 50mm x 50mm size of 3mm wire
Epoxy
Accelerator compound for guniting @ 4 per cent of weight of cement

kg
cum
kg
kg
kg

16.00
0.04
2.00
0.67
0.64

5.211
219.18
30.28
282.81
112.77

Add 2 per cent of cost of material for miscellaneous consumables like


nozzles, wire brush, cotton waste etc.
b)

c)

Labour
Mate
Mason
Mazdoor
Machinery
Compressor with guniting equipment along with accessories

2800

83.37 M-081/1000
M-005
8.77
M-192
60.56
M-095
189.48
M-180
72.17
8.29

day
day
day

0.01
0.04
0.14

232.16
353.52
221.61

2.32
14.14
31.03

hour

0.10

Value

#VALUE!

d)

Overhead charges @ 0.3 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Rate per sqm = (a+b+c+d+e)


16.4

Remarks/
Input ref.

Removal of existing asphaltic wearing coat comprising of 50 mm thick asphaltic


concert laid over 12 mm thick mastic asphalt including disposal with all lift and
lead upto 1000 m.
Unit = Sq m
Taking output = 10 sqm
a) Labour
Mate
Mazdoor
b) Machinery
Air Compressor 250 cfm with pneumatic breaker.
Tractor-trolley.
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 10 sqm = (a+d+c+d)
Rate per sqm = (a+b+c+d)/10

16.3

Cost Rs

Removal of existing cement concrete wearing coat including its disposal


complete as per Technical Specification without causing any detrimental effect
to any part of the bridge structure and removal of dismantled material with all
lifts and lead upto 1000 m
Unit = Sq m ( Thickness 75 mm)
Taking output = 10 sqm
a) Labour
Mate
Mazdoor
b) Machinery
Air Compressor 250 cfm with pneumatic breaker/jack hammer along with
accessories.
Tractor-trolley.
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 10 sqm = (a+d+c+d)
Rate per sqm = (a+b+c+d)/10

16.2

Quantity

L-12
L-11
L-13
P&M-076

#VALUE!

Providing and inserting nipples with approved fixing compound after drilling
holes for grouting as per Technical Specifications including subsequent
cutting/removal and sealing of the hole as necessary of nipples after
completion of grouting with Cement/Epoxy
Unit = Number
Taking output = 1 No.
a) Material
Nipples
Cement, fixing compound and consumables @ 15 per cent of cost of nipple

305

each

1.00

say

#VALUE!

5.64

5.64
0.85

M-129

b)

Labour
Mate

day

0.01

232.16

2.32

L-12

Mazdoor (Skilled) labour for drilling

day

0.08

306.03

24.48

L-15

Mazdoor (Skilled) labour for fixing nipple and sealing inlets

day

0.08

306.03

24.48

L-15

Mazdoor for cutting and removing of nipples

day

0.04

221.61

8.86

L-13

c)

Add 10 per cent of labour cost for drilling holes etc


Overhead charges @ 0.3 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

6.02
21.80
9.44

Rate per No. = (a+b+c+d)


say
16.5

2806

Sealing of cracks/porous concrete by injection


nipples/Grouting complete as per Technical Specification.
A

process

through

Cement Grout
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage
Admixtures (anti shrinkage compound) @ 20 per cent of cost of cement
b) Labour
Mate
Mazdoor (Skilled)
Mazdoor
c) Machinery
Grout pump with agitator and accessories
d) Overhead charges @ 0.3 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Rate per kg = (a+b+c+d+e)

kg

1.10

5.21

day
day
day

0.08
0.10
0.10

232.16
306.03
221.61

18.57
30.60
22.16

hour

0.10

112.77

11.28
26.85
11.63
127.97
128.00

say
B

Cement Mortar (1:1) Grouting


Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage
Sand including 10 per cent wastage
Admixtures (anti shrinkage compound)

103.89
104.00

L-12
L-15
L-13
M-111

kg
kg

0.55
0.55

5.21
0.15

day
day
day

0.08
0.10
0.10

232.16
306.03
221.61

18.57
30.60
22.16

hour

0.10

112.77

M-111

say

11.28
25.84
11.20
123.17
123.00

@ 20 per cent of cost of cement

Labour
Mate
Mazdoor (Skilled)
Mazdoor
c) Machinery
Grout pump with agitator and accessories
d) Overhead charges @ 0.3 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Rate per kg = (a+b+c+d+e)

5.73 M-081/1000
1.15

2.87 M-081/1000
0.08 M-005/1500
0.57

b)

16.6

2800

L-12
L-15
L-13

Patching of damaged concrete surface with polymer concrete and curing


compounds, initiator and promoter, available in present formulations, to be
applied as per instructions of manufacturer and as approved by the Engineer.

Unit = sqm
Taking output = 10 sqm for an average thickness of 25mm.
a)

b)

Labour
Mate
Mazdoor (Skilled)
Mazdoor
Material
Pre-packed polymer concrete based on epoxy system complete with curing
compound, intiator and promoter including 5 per cent wastage.

Machinery
Grout pump with agitator and accessories
d) Overhead charges @ 0.3 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 10 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10

day
day
day

0.06
0.75
0.75

232.16
306.03
221.61

13.93
229.52
166.21

L-12
L-15
L-13

kg

315.00

#VALUE!

#VALUE!

M-145

2.00

112.77

225.54
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

M-111

c)

hour

say
Note

This item is a proprietory item available in market as pre-packed polymer concrete


and is required to be applied as per instructions of the manufacturer.

306

16.7

2803

Sealing of crack / porous concrete with Epoxy Grout by injection through


nipples complete as per clause 2803.1.
Unit = kg
Taking output = 1 kg
a) Material
Epoxy including 10 per cent wastage
b) Labour
Mate
Mazdoor (Skilled)
Mazdoor
c) Machinery
Epoxy Injection gun
d) Overhead charges @ 0.3 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Rate per kg = (a+b+c+d+e)

kg

1.10

282.81

311.09

M-095

day
day
day

0.08
0.10
0.10

232.16
306.03
221.61

18.57
30.60
22.16

L-12
L-15
L-13

hour

0.10

Value

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

P&M-078

say
16.8

2804

Applying epoxy mortar over leached, honey combed and spalled concrete
surface and exposed steel reinforcement complete as per Technical
Specification
Unit = sqm
Taking output = 10 sqm
Assume average 10mm thickness of epoxy mortar
a) Material
Epoxy resin-hardener mix for prime coat
Epoxy mortar
Epoxy resin -hardener mix for seal coat.
Add 3 per cent cost of material for other consumables like acetone etc and to
cover wastage.
b) Labour
Mate
Mazdoor (Skilled)
Mazdoor
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10

16.9

2807

kg
kg
kg

2.50
2.20
2.00

481.82
169.69
481.82

1204.56
373.31
963.65
76.25

M-098
M-096
M-098

day
day
day

0.04
0.50
0.50

232.16
306.03
221.61

L-12
L-15
L-13

say

9.29
153.02
110.81
867.26
375.81
4133.93
413.39
413.00

Removal of defective concrete, cleaning the surface thoroughly, applying the


shotcrete mixture mechanically with compressed air under pressure,
comprising of cement, sand, coarse aggregates, water and quick setting
compound in the proportion as per clause 2807.1., sand and coarse aggregates
conforming to IS: 383 and table 1 of IS: 9012 respectively, water cement ratio
ranging from 0.35 to 0.50, density of gunite not less than 2000 kg/cum, strength
not less than 25 Mpa and workmanship conforming to clause 2807.6.
unit: sqm
Taking output = 10 sqm, 40 mm average thickness.
a) Labour
Mate
Mazdoor
Mazdoor (Skilled)
b) Machinery
Air compressor 250 cfm
Shotcreteing equipment
water tanker 6 KL capacity
c) Material
Cement
Sand
Coarse aggregate of size 4.75mm
Quick setting compound
Water
d) Overhead charges @ 0.3 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 10 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10

day
day
day

0.04
0.50
0.50

232.16
221.61
306.03

9.29
110.81
153.02

L-12
L-13
L-15

hour
hour
hour

1.00
1.00
0.02

293.76
Value
111.24

293.76
#VALUE!
2.22

P&M-001
P&M-076
P&M-060

kg
cum
cum
kg
KL

120.00
0.15
0.15
2.50
0.10

5.211
219.18
311.50
99.20
167.07

say
16.10

2800

625.26 M-081/1000
M-005
32.88
M-024
46.73
M-147
247.99
M-189
16.71
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Applying pre-packed cement based polymer mortar of strength 45 Mpa at 28


days for replacement of spalled concrete
Unit = sqm
Taking output = 10 sqm
Assumed thickness - 10 mm
a) Material
Acrylic polymer bonding coat
pre-packed cement based polymer mortar of strength 45 Mpa at 28 days
Add 3 per cent of (a ) above for wastage.

Litre
kg

1.40
12.00

129.48
#VALUE!

181.27
#VALUE!
#VALUE!

307

M-057
M-145

b)

Labour

308

Mate
Mazdoor (Skilled)
Mazdoor
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
16.11

2805

day
day
day

Eproxy bonding of new concrete to old concrete


Unit = sqm
Taking output = 10 sqm
a) Material
Epoxy resin with pot life not less than 60-90 minutes and satisfying testing as
per clause 2803.9

kg

0.04
0.50
0.50

8.00

L-12
L-15
L-13

say

9.29
153.02
110.81
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

481.82

3854.58

M-098

232.16
306.03
221.61

Add 3 per cent of (a ) above for wastage.

115.64

b)

Labour
Mate
Mazdoor (Skilled)
Mazdoor
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
16.12

2810

day
day
day

L-12
L-15
L-13

say

9.29
153.02
110.81
1273.00
551.63
6067.96
606.80
607.00

1.05

62418.78

65539.72

M-119

17074.37

M-114

0.04
0.50
0.50

232.16
306.03
221.61

Providing external prestressing with high tensile steel wires/strands including


drilling for passage of prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per drawing and Technical
Specification
Span assumed: 25 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 1 MT
Assume 12.7mm dia. Strand in 12T13 system. Weight-9.42 kg/m of cable.
a)

Material
HTS strand including 5 per cent wastage and extra length for jacking
HDPE pipes 75mm dia including 5 per cent wastage

metre

112.00

152.45

Cement for grouting


Tube anchorage set complete with bearing plate, permanent wedges etc

kg
each

400.00
8.00

5.211
34.35

Epoxy
MS plates for deviator (where deviator blocks are not provided)

b)

tonne

kg

6.00

282.81

1696.85

M-095

tonne

2.10

37995.24

79790.00

M-179

Add 20 per cent cost of material for other materials like lead sheet, sleeves,
deviator fixtures etc.
Labour

i) For making holes in the structure .


Mate
Mazdoor Semi-skilled)
Mazdoor
ii) For making and fixing anchorages for cables and placement of cables .
Mate
Blacksmith
Mazdoor
iii) For prestressing
Mate/Supervisor
Fitter
Mazdoor
iv) For grouting
Mate/Supervisor
Mason
Mazdoor
c) Machinery
Stressing jack with pump
Grouting pump with agitator
d) Overhead charges @ 0.3 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Rate per MT = (a+b+c+d+e)

309

2084.21 M-081/1000
M-187
274.83

33292.00

day
day
day

0.24
3.00
3.00

232.16
232.16
221.61

55.72
696.48
664.83

L-12
L-14
L-13

day
day
day

0.44
3.00
8.00

232.16
353.52
221.61

102.15
1060.56
1772.88

L-12
L-02
L-13

day
day
day

0.13
0.70
2.65

232.16
306.03
221.61

30.18
214.22
587.27

L-12
L-08
L-13

day
day
day

0.13
0.70
2.65

232.16
353.52
221.61

30.18
247.46
587.27

L-12
L-11
L-13

hour
hour

4.00
1.35

116.10
112.77

464.40
152.24
61925.34
26834.32
295177.48

say

295177.00

P&M-040
M-111

16.13

2810

Providing external prestressing with high tensile steel wires/strands including


drilling for passage of prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per drawing and Technical
Specification
Span assumed: 50 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 3.10 MT
Assume 12.7mm dia. Strand in 19T13 system. Weight-14.73 kg/m of cable.
a)

Material
HTS strand including 5 per cent wastage and extra length for jacking

tonne

3.10

62418.78

193498.21

M-119

HDPE pipes 90mm dia including 5 per cent wastage

metre

Cement for grouting


Tube anchorage set complete with bearing plate, permanent wedges etc

tonne
each

224.00

152.45

34148.74

M-115

1.01
8.00

5210.53
34.35

5262.63
274.83

M-081
M-187

Epoxy
MS plates for deviator (where deviator blocks are not provided)

kg
tonne

10.00
7.00

282.81
37995.24

2828.09
265966.67

M-095
M-179

Add 20 per cent cost of material for other materials like lead sheet, sleeves,
deviator fixtures etc.
b) Labour
i) For making holes in the structure .
Mate
Mazdoor Semi-skilled)
Mazdoor
ii) For making and fixing anchorages for cables and placement of cables .
Mate
Blacksmith
Mazdoor
iii) For prestressing
Mate/Supervisor
Fitter
Mazdoor
iv) For grouting
Mate/Supervisor
Mason
Mazdoor
c) Machinery
Stressing jack with pump
Grouting pump with agitator
d) Overhead charges @ 0.3 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 3.10 MT = a+b+c+d+e
Rate per MT = (a+b+c+d+e)/3.10
16.14

2810

100395.83

day
day
day

0.08
8.00
8.00

232.16
232.16
221.61

18.57
1857.28
1772.88

L-12
L-14
L-13

day
day
day

1.28
7.00
25.00

232.16
353.52
221.61

297.16
2474.64
5540.25

L-12
L-02
L-13

day
day
day

0.20
1.00
4.00

232.16
306.03
221.61

46.43
306.03
886.44

L-12
L-08
L-13

day
day
day

0.26
1.50
5.00

232.16
353.52
221.61

60.36
530.28
1108.05

L-12
L-11
L-13

hour
hour

7.00
3.00

116.10
112.77

P&M-040
M-111

say

812.70
338.31
185527.32
80395.17
884346.89
285273.19
285273.00

Providing external prestressing with high tensile steel wires/strands including


drilling for passage of prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per drawing and Technical
Specification
Span assumed: 100 m
No. of cables: 6 no.
No. of anchorages : 12 no.
Unit = MT
Taking output = 9.28 MT
Assume 12.7mm dia. Strand in 19T13 system. Weight-14.73 kg/m of cable.
a)

Material
HTS strand including 5 per cent wastage and extra length for jacking

tonne

9.28

62418.78

579246.24

M-119

HDPE pipes 90 mm dia including 5 per cent wastage


Cement for grouting

metre
tonne

672.00
3.04

152.45
5210.53

102446.23
15840.00

M-115
M-081

Tube anchorage set complete with bearing plate, permanent wedges etc

each

12.00

34.35

412.24

M-187

kg

14.00

282.81

3959.33

M-095

tonne

20.00

37995.24

759904.76

M-179

Epoxy
MS plates for deviator (where deviator blocks are not provided)
Add 20 per cent cost of material for other materials like lead sheet, sleeves,
deviator fixtures etc.
b) Labour
i) For making holes in the structure .
Mate

310

292361.76

day

1.72

232.16

399.32

L-12

16.15

2808

Mazdoor Semi-skilled)
Mazdoor
ii) For making and fixing anchorages for cables and placement of cables .

day
day

18.00
25.00

232.16
221.61

4178.88
5540.25

L-14
L-13

Mate
Blacksmith
Mazdoor
iii) For prestressing
Mate/Supervisor
Fitter
Mazdoor
iv) For grouting
Mate/Supervisor
Mason
Mazdoor
c) Machinery
Stressing jack with pump
Grouting pump with agitator
d) Overhead charges @ 0.3 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 9.28 MT = a+b+c+d+e
Rate per MT = (a+b+c+d+e)/9.28

day
day
day

4.00
20.00
80.00

232.16
353.52
221.61

928.64
7070.40
17728.80

L-12
L-02
L-13

day
day
day

0.30
1.50
6.00

232.16
306.03
221.61

69.65
459.05
1329.66

L-12
L-08
L-13

day
day
day

1.00
5.00
20.00

232.16
353.52
221.61

232.16
1767.60
4432.20

L-12
L-11
L-13

hour
hour

10.00
10.00

116.10
112.77

P&M-040
M-111

say

1161.00
1127.71
540178.76
234077.46
2574852.11
277462.51
277463.00

P&M-084
L-12
L-15
L-13
M-195

Replacement of Bearings complete as per Technical Specification


Unit = No
Taking output = 3 No.
Lifting of superstructure span by jacking up from below i.e. by placing the jacks on
pier/abutment caps for span length of 30m.
a)

Lifting of span
i) Hire charges for jack of 40 tonne lifting capacity.
Mate
Mazdoor (Skilled)
Mazdoor
v) Wooden packing
b) Replacement of bearing
Cost of bearing.
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost of repair of 3 bearings = a+b+c+d
Rate of repair per bearing = (a+b+c+d)/3

16.16

Note

The work entails replacement of all the bearings on one side of the span.

2808

Rectification of Bearings as per Technical Specifications

each
day
day
day
cum

3.00
0.64
4.00
12.00
0.15

758.16
232.16
306.03
221.61
#VALUE!

2274.48
148.58
1224.12
2659.32
#VALUE!

each

3.00

55883.28

say

167649.83
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

M-065

Unit = 1 No
Taking output = 3 No.
a) Lifting of superstructure span by jacking up from below i.e. by placing the
jacks on pier/abutment caps for span length of 30m.
i) Hire charges for jack of 40 tonne lifting capacity.
ii) Mate
iii) Mazdoor (Skilled)
iv) Mazdoor
v) Wooden packing
b) Cost of parts to be replaced for 3 bearings.
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost of repair of 3 bearings = a+b+c+d
Rate of repair per bearing = (a+b+c+d)/3

each

3.00

758.16

2274.48

P&M-084

day
day
day
cum
each

0.64
4.00
12.00
0.15
3.00

232.16
306.03
221.61
#VALUE!
#VALUE!

148.58
1224.12
2659.32
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

L-12
L-15
L-13
M-195
M-064

say
Note
16.17

The rectification of 3 bearings included in this analysis are on the same side of the
span.
Replacement of Expansion Joints complete as per drawings
Unit -1 RM
Taking output = 12 RM
a) Material
Epoxy for bonding new concrete to old concrete @ 0.8 kg/sqm
M-30 grade cement concrete excluding OH & CP (Rate as per items 14.1 C (i)
b)

Labour

311

kg
cum

9.60
3.60

282.81
4112.00

M-095
2714.97
14803.20 Item 14.1(C)

Removal of old expansion joint including breaking of concrete, cutting of lugs and
shifting of broken material etc.
Mate
Mazdoor
Mazdoor (Skilled)
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for replacement of 12 RM = a+b+c+d
Rate per RM = (a+b+c+d)/12
Note

16.18

day
day
day

Replacement of Damaged Concrete Railing.


Unit = RM
Taking output = 10 RM
a) Labour
Labour for dismantling old railing and disposal of dismantled material.

Note
16.19

day
day

0.20
5.00

232.16
221.61

46.43
1108.05

L-12
L-13

hour

1.00

171.02

P&M-053

say

171.02
397.65
172.32
1895.47
189.55
190.00

The rate for the provision of new railing may be adopted from the chapter on
superstructure.
Replacement of Crash Barrier.
Unit = RM
Taking output = 10 M
a) Labour
Labour for dismantling old railing and disposal of dismantled material.
Mate
Mazdoor
b) Machinery
Tractor-trolley for disposal of dismantled material
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 10 m = a+b+c+d
Rate per metre = (a+b+c+d)/10

Note

day
day

0.40
10.00

232.16
221.61

92.86
2216.10

L-12
L-13

hour

1.00

171.02

P&M-053

say

171.02
743.99
322.40
3546.37
354.64
355.00

The rate for the construction of new crash barrier may be adopted from chapter 8 on
Traffic and Transportation.
Replacement of Damaged Mild Steel Railing
Unit = RM
Taking output = 10 M
a) Labour
Labour for dismantling old railing and disposal of dismantled material.
Mate
Mazdoor
b) Machinery
Tractor-trolley for disposal of dismantled material
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 10 m = a+b+c+d
Rate per metre = (a+b+c+d)/10

16.21

L-12
L-13
L-15

say

60.36
1329.66
153.02
5718.36
2477.96
27257.52
2271.46
2271.00

232.16
221.61
306.03

The rate for the installation of new expansion joints may be taken from the chapter on
superstructure. Broken concrete will have to be replaced which has been included in
this analysis.

Mate
Mazdoor
b) Machinery
Tractor-trolley for disposal of dismantled material
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 10 m = a+b+c+d
Rate per metre = (a+b+c+d)/10

16.20

0.26
6.00
0.50

day
day

0.16
4.00

232.16
221.61

37.15
886.44

L-12
L-13

hour

1.00

171.02

P&M-053

say

171.02
328.38
142.30
1565.28
156.53
157.00

232.16
221.61

9.29
221.61

L-12
L-13

Repair of Crash Barrier


Repair of concrete crash barrier with cement concert of M-30 grade by cutting and
trimming the damaged portion to a regular shape, cleaning the area to be repaired
thoroughly, applying cement concert after erection of proper form work.
Unit = Running meter.
Taking output = 10 M.
It is assumed that damage is to the extent of 10 per cent of the volume of concrete
.This will require 0.30 cum of concrete.
a)

Manpower*
Mate
Mazdoor

day
day

312

0.04
1.00

* For dismantling and trimming the surface to a regular shape and removal of damaged
material.
b) Material
M-30 grade cement concrete excluding OH & CP (Rate as per items 14.1 C (i)

cum

0.30

4112.00

1233.60 Item 14.1(C)


DIR used item

This may be priced based on the rate given the chapter of superstructure.
c)

Overhead charges @ 0.3 on (a)

d)

Contractor's profit @ 0.1 on (a+c)

439.35
190.38

Cost for 10 m = a+b+c+d

2094.23

Rate per m = (a+b+c+d)/10

209.42
say

16.22

209.00

Repair of RCC Railing


Carrying out repair of RCC M30 railing to bring it to the original shape.
Unit = Running meter.
Taking output = 10 M.
It is assumed that damage is to the extent of 10 per cent .
a)

b)

Material
M-30 grade cement concrete excluding OH & CP (Rate as per items 14.1 C (i)

cum

0.10

4112.00

411.20 Item 14.1(C)

HYSD bar reinforcement Rate as per item No 14.2(Excluding OH & CP)

tonne

0.013

41437.00

538.68 Item 14.2 A


DIR used item

Labour*
Mate

day

0.016

232.16

3.71

L-12

mazdoor

day

0.20

221.61

44.32

L-13

say

299.38
129.73
1427.02
142.70
143.00

* For dismantling and trimming the surface to a regular shape and removal of damaged
material.
c) Overhead charges @ 0.3 on (b)
d) Contractor's profit @ 0.1 on (b+c)
Cost for 10 m = a+b+c+d
Rate per m = (a+b+c+d)/10

16.23

Repair of Steel Railing


Repair of steel railing to bring it to the original shape
It is assumed that the damage to the steel railing is to the extent of 10 per cent .
Unit = Running meter.
Taking output = 10 M.
a) Material
Mild steel ISMC series
Flat iron
MS Bolt and nuts
Add 5 per cent of cost of material for painting.
b) Labour
Mate
Mazdoor (Skilled)
Mazdoor
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost of repair for10m = a+b+c+d
Cost of meter = (a+b+c+d)/10

kg
kg
kg

29.00
10.00
1.00

38.00
38.00
45.42

day
day
day

0.016
0.20
0.20

232.16
306.03
221.61

say

313

1101.86 M-179/1000
379.95 M-179/1000
M-130
45.42
76.36
3.71
61.21
44.32
513.85
222.67
2449.36
244.94
245.00

L-12
L-15
L-13

Sub - Analysis_B

Sr No
3.1

Ref. to
MoRTH
Spec.
301

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Excavation in Soil by Manual Means .

SUB ANA
-B (1)

Excavation for roadway in soil using manual means


including loading in truck for carrying of cut earth to
embankment site with all lifts and lead upto1000
metres.Including royality @ Rs. 24.00 per cum but
excluding the cost of watering , rolling & compaction
Note In case there is a situation where the crosssection is of cut and fill and cut earth is required
to be used in embankment in the immediate
vicinity, the item of carriage in the truck shall be
omitted.
Unit = cum
Taking output = 120 cum
a)

Labour
Mate

c)

Mazdoor
Machinery
Truck 5.5 cum capacity
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

b)

day

1.800

232.16

417.89

L-12

day

45.000

221.61

9972.45

L-13

hour

10.000

0.00

0.00
1039.03

P&M-057

1142.94

Cost of 120 cum = a+b+c+d

12572.31

Rate per cum = (a+b+c+d)/120


Royality @ Rs. 24.00 per Cum
Rate per cum
3.1

301

SUB ANA
-B (2)

104.77
24.00

Excavation for roadway in soil using manual means


including loading in truck for carrying of cut earth to
embankment site with all lifts and lead upto1000
metres.
Unit = cum
Taking output = 120 cum
a) Labour
Mate
Mazdoor
b) Machinery
Truck 5.5 cum capacity
Smooth wheel roller @ 70 cum per hour
Water Tanker @ 6.0 KL capicity
c) Materials
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)

301

SUB ANA
-B

day
day

1.800
45.000

232.16
221.61

417.89
9972.45

L-12
L-13

hour
hour
hour

10.000
1.500
0.800

745.00
625.00
111.24

7450.00
937.50
88.99

P&M-057
P&M-044
P&M-060

KL

4.800

167.07

801.93
1966.88
2163.56

M-189

say

23799.20
198.33
24.00
222.00

232.16

650.05

Excavation in Ordinary Rock by Manual Means


Excavation in ordinary rock using manual means
including loading in a truck and carrying of excavated
material to embankment site with in all lifts and leads
upto 1000 metres (including royality @ Rs. 24.00 per
cum but excluding watering, rolling & compaction)
Unit = cum
Taking output = 120 cum
a) Labour
Mate

RCD/SOR_2nd Edition

129.00

Excavation in Soil by Manual Means .

Cost of 120 cum = a+b+c+d+e


Rate per cum = (a+b+c+d+e)/120
Royality @ Rs. 24.00 per Cum
Rate per cum
3.2

say

day

2.800

L-12

Sub - Analysis_B
Mazdoor
b) Machinery
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 120 cum = a+b+c+d
Rate per cum = (a+b+c+d)/120
Royality @ Rs. 24.00 per Cum
Rate per cum

3.2

301

70.000

221.61

15512.70

say

1616.27
1777.90
19556.93
162.97
24.00
186.97
187.00

L-13

Note In case there is a situation where the cross-section is


of cut and fill and cut earth is required to be used in
embankment in the immediate vicinity, the item of
carriage in the truck shall be omitted.
Excavation in Ordinary Rock by Manual Means

SUB ANA
-B

3.6

day

Excavation in ordinary rock using manual means


including loading in a truck and carrying of excavated
material to embankment site with in all lifts and leads
upto 1000 metres (including royality @ Rs. 30.00 per
cum, watering, rolling & compaction - from immediate
vicinity)
Unit = cum
Taking output = 120 cum
a) Labour
Mate
Mazdoor
b) Machinery
Truck 5.5 cum capacity
Smooth wheel roller @ 70 cum per hour
Water Tanker @ 6.0 KL capicity
c) Materials
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 120 cum = a+b+c+d
Rate per cum = (a+b+c+d)/120
Royality @ Rs. 24.00 per Cum
Rate per cum
301

SUB ANA
-B

RCD/SOR_2nd Edition

day
day

2.800
70.000

232.16
221.61

650.05
15512.70

L-12
L-13

hour
hour
hour

10.000
1.500
0.800

745.00
625.00
111.24

7450.00
937.50
88.99

P&M-057
P&M-044
P&M-060

KL

4.800

167.07

M-189

say

801.93
2544.12
2798.53
30783.81
256.53
24.00
280.53
281.00

Excavation in Soil using Hydraulic Excavator CK


90 and Tippers with Disposal upto 1000 metres.
Excavation for roadwork in soil with hydraulic
excavator of 0.9 cum bucket capacity including
cutting and loading in tippers, trimming bottom and
side slopes, in accordance with requirements of
lines, grades and cross sections, and transporting to
the embankment location within all lifts and lead upto
1000m (including royality @ Rs. 24.00 per cum,
watering, rolling & compaction)
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor
b) Machinery
Hydraulic excavator 0.9 cum bucket capacity @
60 cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.
Smooth wheel roller @ 70 cum per hour
Water Tanker @ 6.0 KL capicity
c) Materials
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 360 cum = a+b+c+d
Rate per cum = (a+b+c+d)/360
Royality @ Rs. 24.00 per Cum

day
day

0.080
2.000

232.16
221.61

18.57
443.22

L-12
L-13

hour

6.000

1516.32

9097.92

P&M-026

hour
hour
hour

16.000
4.500
2.400

830.00
625.00
111.24

13280.00
2812.50
266.98

P&M-048
P&M-044
P&M-060

KL

14.400

167.07

2405.78
2832.50
3115.75
34273.22
95.20
24.00

M-189

Sub - Analysis_B
Rate per cum
3.7

301

SUB ANA
-B

3.10
SUB ANA
-B

119.20
119.00

Excavation in Ordinary Rock using Hydraulic


Excavator CK-90 and Tippers with Disposal upto
1000 metres.
Excavation for roadway in ordinary rock with
hydraulic excavator of 0.9 cum bucket capacity
including cutting and loading in tippers, transporting
to embankment site within all lifts and lead upto 1000
m, trimming bottom and side slopes in accordance
with requirements of lines, grades and cross sections
(including royality @ Rs. 24.00 per cum , watering,
rolling & compaction)
Unit = cum
Taking output = 240 cum
a) Labour
Mate
Mazdoor
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity
@ 36 cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.
Smooth wheel roller @ 70 cum per hour
Water Tanker @ 6.0 KL capicity
c) Materials
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 240 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/240
Royality @ Rs. 24.00 per Cum
Rate per cum

301

say

day
day

0.080
2.000

232.16
221.61

18.57
443.22

L-12
L-13

hour

6.000

1516.32

9097.92

P&M-026

hour
hour
hour

11.000
3.000
1.600

830.00
625.00
111.24

9130.00
1875.00
177.98

P&M-048
P&M-044
P&M-060

KL

9.600

167.07

M-189

say

1603.85
2234.66
2458.12
27039.33
112.66
24.00
136.66
137.00

Excavation in Marshy Soil


Excavation for roadway in marshy soil with hydraulic
excavator 0.9 cum bucket capacity including cutting
and loading in tippers and disposal with in all lifts and
lead upto 1000 metres, trimming of bottom and side
slopes in accordance with requirements of lines,
grades and cross sections (including royality @ Rs.
24.00 per cum , watering, rolling & compaction)
Unit = cum
Taking output = 300 cum
a) Labour
Mate
Mazdoor
b) Machinery
Hydraulic excavator 0.90 cum bucket capacity
@ 50 cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.
Smooth wheel roller @ 70 cum per hour
Water Tanker @ 6.0 KL capicity
c) Materials
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)

day
day

0.080
2.000

232.16
221.61

18.57
443.22

L-12
L-13

hour

6.000

1516.32

9097.92

P&M-026

hour
hour
hour

13.640
3.750
2.000

830.00
625.00
111.24

11321.20
2343.75
222.48

P&M-048
P&M-044
P&M-060

KL

12.000

167.07

2004.82
2545.20
2799.72

M-189

Cost for 300 cum = a+b+c+d+e


Rate per cum = (a+b+c+d+e)/300
Royality @ Rs. 24.00 per Cum
Rate per cum
say
3.16

305

RCD/SOR_2nd Edition

Construction of Embankment
obtained from Borrowpits

with Material

30796.87
102.66
24.00
126.66
127.00

Sub - Analysis_B
SUB ANA
-B

Construction of embankment with approved material


obtained from borrow pits with all lifts and leads,
transporting to site, spreading, grading to required
slope and compacting to meet requirement of table
300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate
Mazdoor
b) Machinery
Hydraulic Excavator1 cum bucket capacity @
60 cum per hour
Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover
cost of loading and unloading
Dozer 80 HP for spreading @ 200 cum per
hour
Motor grader for grading @ 100 cum per hour
Water tanker6 KL capacity
Smooth wheel roller 8-10 tonnes @ 70 cum per
hour
c) Material
Cost of water
Compensation & Royality for earth taken from
private land
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 100 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/100

3.17

305

SUB ANA
-B

Compensation for earth will vary from place to place


and will have to be assessed realistically as per
particular ground situation. In case earth is available
from Govt. land, compensation for earth will not be
required. The position is required to be clearly stated
in the cost estimate.
Construction of Embankment with Material
Deposited from Roadway Cutting
Construction of embankment with approved
materials deposited at site from roadway cutting and
excavation from drain and foundation of other
structures graded and compacted to meet
requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate
Mazdoor
b) Machinery
Dozer 80 HP for spreading @ 200 cum per
hour
Motor grader for grading @ 100 cum per hour
Water tanker6 KL capacity
Smooth wheel roller 8-10 tonnes @ 56 cum per
hour
c) Material
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Rate for 100 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/100

day
day

0.040
1.000

232.16
221.61

9.29
221.61

L-12
L-13

hour

1.670

1516.32

2532.25

P&M-026

tonne.km

160 x L

2.68

428.54
42.85

P&M-047

hour

0.500

3135.24

1567.62

P&M-014

hour

1.000

2488.00

2488.00

P&M-032

hour
hour

4.000
1.430

111.24
625.00

444.96
893.75

P&M-060
P&M-044

KL
cum

24.000
100.000

167.07
25.10

4009.64
2510.00

M-189
M-092

say

1514.85
1666.34
18329.71
183.30
183.00

day
day

0.020
0.500

232.16
221.61

4.64
110.81

L-12
L-13

hour

0.500

3135.24

1567.62

P&M-014

hour

1.000

2488.00

2488.00

P&M-032

hour
hour

4.000
1.430

111.24
625.00

444.96
893.75

P&M-060
P&M-044

KL

24.000

167.07

4009.64
951.94
1047.14
11518.49
115.18

say

RCD/SOR_2nd Edition

115.00

M-189
M-189
M-092

Sub - Analysis_B

3.18

In case the earth cutting is done by dozer and


pushed for filling in the embankment, the input of
dozer in the cost of embankment shall be deleted as
the same is already provided in the cost of
excavation. However, if the earth is dumped by
tippers from roadway cutting, the input of dozer for
spreading is required to be provided.
Construction of Subgrade and Earthen Shoulders

305

SUB ANA
-B

Construction of sub-grade and earthen shoulders


with approved material obtained from borrow pits
with all lifts & leads, transporting to site, spreading,
grading to required slope and compacted to meet
requirement of table No. 300-2
Unit = cum
Taking output = 100 cum
a) Labour
Mate
Mazdoor
b) Machinery
Hydraulic excavator1 cum bucket capacity @
60 cum per hour
Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover
cost of loading and unloading
Dozer 80 HP for spreading @ 200 cum per
hour
Motor grader for grading @ 50 cum per hour
Water tanker with 6 km lead
Smooth wheel roller 8-10 tonnes @ 56 cum per
hour
c) Material
Cost of water
Compensation & Royality for earth taken from private
land
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)

day
day

0.040
1.000

232.16
221.61

9.29
221.61

L-12
L-13

hour

1.670

1516.32

2532.25

P&M-026

tonne.km

175xL

2.68

468.72
46.87

P&M-047

hour

0.500

3135.24

1567.62

P&M-014

hour

2.000

2488.00

4976.00

P&M-032

hour
hour

4.000
1.790

111.24
625.00

444.96
1118.75

P&M-060
P&M-044

KL
cum

24.000
100.000

167.07
25.10

4009.64
2510.00

M-189
M-092

1790.57
1969.63

Cost for 100 cum = a+b+c+d+e


Rate per cum = (a+b+c+d+e)/100
3.19

SUB ANA
-B

305.3.4

Compacting Original Ground


Compacting original ground supporting subgrade
Case-I Loosening of the ground upto a level of 500 mm
below the sub-grade level, watered, graded and
compacted in layers to meet requirement of table
300-2 for sub-grade construction.
Unit = cum
Taking output = 600 cum
a) Labour
Mate
Mazdoor
b) Machinery
Tractor with ripper attachment
Motor grader for grading
Water tanker 6 KL capacity
Smooth wheel roller 8-10 tonnes @ 56 cum per
hour
c) Material
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 600 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/600

3.19

RCD/SOR_2nd Edition

Compacting original ground supporting


embankment

say

21665.91
216.66
217.00

day
day

0.120
3.000

232.16
221.61

27.86
664.83

L-12
L-13

hour
hour
hour
hour

9.000
6.000
4.000
10.710

285.12
2488.00
111.24
625.00

2566.08
14928.00
444.96
6693.75

P&M-055
P&M-032
P&M-060
P&M-044

KL

24.000

167.07

4009.64
2933.51
3226.86
35495.49
59.16

M-189

say

59.00

Sub - Analysis_B
SUB ANA
-B

Case-II Loosening, leveling and Compacting original ground


supporting embankment to facilitate placement of
first layer of embankment, scarified to a depth of 150
mm, mixed with water at OMC and then compacted
by rolling so as to achieve minimum dry density as
given in Table 300-2 for embankment construction.
Unit = cum
Taking output = 600 cum
a)

b)

c)

Labour
Mate

day

0.080

232.16

18.57

L-12

Mazdoor

day

2.000

221.61

443.22

L-13

Machinery
Tractor with ripper attachment

hour

6.000

285.12

1710.72

P&M-055

Smooth wheel roller 8-10 tonnes @ 56 cum per


hour
Water tanker6 KL capacity

hour

10.710

625.00

6693.75

P&M-044

hour

4.000

111.24

444.96

P&M-060

KL

24.000

167.07

4009.64

M-189

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

1332.09

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1465.29

Cost for 600 cum = (a+b+c+d+e)

16118.24

Rate per sqm = (a+b+c+d+e)/600

26.86
say

5.11

512

Sub Analysis
for Type
'B"

27.00

Close Graded Premix Surfacing/Mixed Seal


Surfacing
Mechanical means using HMP of appropriate
capacity not less than 75 tonnes/hour.
Case I Providing, laying and rolling of close-graded premix
surfacing material of 20 mm thickness composed of
11.2 mm to 0.09 mm (Type-a) or 13.2 mm to 0.09
mm (Type-b) aggregates using penetration grade
bitumen to the required line, grade and level to serve
as wearing course on a previously prepared base,
including mixing in a suitable plant, laying and rolling
with a Smooth wheeled roller 8-10 tonne capacity,
and finishing to required level and grade.
Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Labour

b)

Mate

day

0.840

232.16

195.01

L-12

Mazdoor working with HMP, road sweeper,


paver and roller
Skilled mazdoor for checking line & levels

day

16.000

221.61

3545.76

L-13

day

5.000

306.03

1530.15

L-15

i) HMP of appropicate capacity - 75 t per hour

hour

6.000

30613.00

183678.00

P&M-022

ii) Electric Generator Set 250 KVA

hour

6.000

2973.00

17838.00

P&M-081

iii) Front end loader 1 cum bucket capacity

hour

6.000

1116.00

6696.00

P&M-017

tonne.km

450 x L

2.68

hour

6.000

2980.00

17880.00

P&M-034

hour

6.000

625.00

3750.00

P&M-044

tonne

19.480

32859.22

640097.61

M-074

cum

276.750

690.16

191001.78

M-042

Machinery

iv) Tipper 10 tonne capacity


Add 10 per cent of cost of carriage to cover cost of
loading and unloading
v) Paver finisher hydrostatic with sensor
attachment
iv) Smooth wheeled8-10 tonnes weight
c)

1205.28 Lead =1 km &


P&M-047
120.53

Material

Type - B
Bitumen @ 19 kg per 10 sqm

d)
RCD/SOR_2nd Edition

Stone crushed aggregates 13.2 mm to 0.09 mm


@ 0.27 cum per 10 sqm
Overhead charges @ 0.1 on (a+b+c)

106753.81

Sub - Analysis_B
e)

Contractor's profit @ 0.1 on (a+b+c+d)

117429.19

Cost for 10250 sqm = a+b+c+d+e

1291721.12

Rate per sqm = (a+b+c+d+e)/10250

126.02
For Type 'B'

say

126.00

With Smooth wheel Roller


4.9

404

Water Bound Macadam

SUB ANA
-B

Providing, laying, spreading and compacting stone


aggregates of specific sizes to water bound
macadam specification including spreading in
uniform thickness, hand packing, rolling with 3
wheeled steel/ vibratory roller 8-10 tonnes in stages
to proper grade and camber, applying and brooming
requisite type of screening/ binding Materials to fill up
the interstices of coarse aggregate, watering and
compacting to the required density.
By Manual Means
A

Unit = cum
Taking output = 360 cum
a)

b)

Labour
Mate

day

10.080

232.16

2340.17

L-12

Mazdoor skilled

day

2.000

306.03

612.06

L-15

Mazdoor

day

250.000

221.61

55402.50

L-13

Smooth 3 wheeled steel roller @ 30cum/hour

hour

12.000

625.00

7500.00

P&M-044

Water tanker 6 KL capacity

hour

24.000

111.24

2669.76

P&M-060

cum

435.600

524.74

228576.74

Type A 13.2 mm for grading-I @ 0.27 cum per


10 sqm
OR

cum

97.200

690.16

67083.55 M-042

Crushable type such as Moorum or Gravel for


grading-I @ 0.30 cum per 10 sqm

cum

108.000

129.74

14011.92

M-007

cum

28.800

129.74

3736.51

M-007

KL

144.000

167.07

24057.82

M-189

Machinery

c) Material ( Refer table 400 - 7, 8 & 9 )


Grading-I

4.9A
(i)

Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10
sqm for compacted thickness of 100 mm

M-039

Stone Screening

Binding material
Binding Material @ 0.08cum per 10 sqm for
grading I material
Cost of water
4.9A (i)

Using Scrining Crushable type such as Moorum or Gravel


(a)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

33517.10
36868.81

Cost for 360 cum = a+b+c+d+e

405556.89

Rate per cum = (a+b+c+d+e)/360

1126.55
say

1127.00

OR
4.9A (i)

Using Scrining Type-A (13.2mm agg.)


(b)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

39197.91
43117.70

Cost for 360 cum = a+b+c+d+e

474294.74

Rate per cum = (a+b+c+d+e)/360

1317.49
say

4.9A

Grading-II
(ii)

RCD/SOR_2nd Edition

Aggregate

1317.00

Sub - Analysis_B
Grading-II 63 mm to 45 mm /Grading-III 53 mm
to 22.4 mm@ 0.91 cum per 10 sqm for
compacted thickness of 75 mm

cum

435.600

595.10

Type A 13.2 mm for grading-II@ 0.12 cum per


10 sqm
OR

cum

57.600

690.16

39753.22 M-042

Crushable type such as Moorum or Gravel for


grading II &III @ 0.22 cum per 10 sqm
OR

cum

105.590

129.74

13699.25

cum

86.400

563.97

48727.01 M-041

cum

28.800

129.74

3736.51

M-007

KL

144.000

167.07

24057.82

M-189

259225.56

M-038

Stone Screening

Type B11.2 mm for grading-III @ 0.18 cum per


10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for
grading II material
Cost of water
4.9A (ii)

M-007

Using Scrining Crushable type such as Moorum or Gravel


(a)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

36550.71
40205.78

Cost for 360 cum = a+b+c+d+e

442263.62

Rate per cum = (a+b+c+d+e)/360

1228.51
say

1229.00

OR
4.9A (ii)

Using Scrining Type-A (13.2mm agg.)


(b)

d)

Overhead charges @ 0.1 on (a+b+c)

39529.76

e)

Contractor's profit @ 0.1 on (a+b+c+d)

43482.74

Cost for 360 cum = a+b+c+d+e

478310.10

Rate per cum = (a+b+c+d+e)/360

1328.64
say

4.9A (ii)

1329.00

Using Scrining Type-B (11.2mm agg.)


(c)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

40427.14
44469.85

Cost for 360 cum = a+b+c+d+e

489168.39

Rate per cum = (a+b+c+d+e)/360


4.9A

1358.80
say

1359.00

268024.68

Grading-III
(iii)

Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per
10 sqm for compacted thickness of 75 mm

cum

435.600

615.30

M-036

Type B 11.2 mm for grading-III @ 0.18 cum per


10 sqm
OR

cum

86.400

563.97

48727.01 M-041

Crushable type such as Moorum or Gravel for


grading II &III @ 0.22 cum per 10 sqm

cum

105.590

129.74

13699.25

M-007

cum

28.800

129.74

3736.51

M-007

KL

144.000

167.07

24057.82

M-189

Stone Screening

Binding material
Binding Material @ 0.06cum per 10 sqm for
grading II material
Cost of water
4.9A (iii)

Using Scrining Crushable type such as Moorum or Gravel


(a)

d)

Overhead charges @ 0.1 on (a+b+c)

37430.62

e)

Contractor's profit @ 0.1 on (a+b+c+d)

41173.69

Cost for 360 cum = a+b+c+d+e

452910.55

Rate per cum = (a+b+c+d+e)/360

1258.08
say

RCD/SOR_2nd Edition

1258.00

Sub - Analysis_B
OR
4.9A (iii)

Using Scrining Type-B (11.2mm agg.)


(b)

d)

Overhead charges @ 0.1 on (a+b+c)

41307.05

e)

Contractor's profit @ 0.1 on (a+b+c+d)

45437.76

Cost for 360 cum = a+b+c+d+e

499815.33

Rate per cum = (a+b+c+d+e)/360

1388.38
say

1388.00

( Anyone of the aggregate grading, screening and


binding material may be used as per design)
4.9
SUB ANA
-B

By Mechanical Means:
B

Unit = cum
Taking output = 360 cum
a)

b)

Labour
Mate

day

0.680

232.16

157.87

L-12

Mazdoor skilled

day

2.000

306.03

612.06

L-15

Mazdoor

day

15.000

221.61

3324.15

L-13

Motor grader 110 HP @ 50cum/hr. for


spreading
Smooth 3 wheeled steel roller @ 30cum/hr.

hour

7.200

2488.00

17913.60

P&M-032

hour

12.000

625.00

7500.00

P&M-044

Water tanker 6 KL capacity

hour

24.000

111.24

2669.76

P&M-060

cum

435.600

524.74

228576.74

cum

97.200

690.16

67083.55 M-042

cum

108.000

129.74

14011.92

M-007

cum

28.800

129.74

3736.51

M-007

KL

144.000

167.07

24057.82

M-189

Machinery

c) Material ( Refer table 400 - 7, 8 & 9 )


Grading - I

4.9B
(i)

Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10
sqm for compacted thickness of 100 mm

M-039

Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per
10 sqm
OR
Crushable type such as Moorum or Gravel for
grading-I @ 0.30 cum per 10 sqm
Binding material
Binding Material @ 0.08cum per 10 sqm for
grading I material
Cost of water
4.9B (i)

Using Scrining Crushable type such as Moorum or Gravel


(a)

d)

Overhead charges @ 0.1 on (a+b+c)

29882.39

e)

Contractor's profit @ 0.1 on (a+b+c+d)

32870.63

Cost for 360 cum = a+b+c+d+e

361576.95

Rate per cum = (a+b+c+d+e)/360

1004.38
say

1004.00

OR
4.9B (i)

Using Scrining Type-A (13.2mm agg.)


(b)

d)

Overhead charges @ 0.1 on (a+b+c)

35563.21

e)

Contractor's profit @ 0.1 on (a+b+c+d)

39119.53

Cost for 360 cum = a+b+c+d+e

430314.81

Rate per cum = (a+b+c+d+e)/360


4.9B

1195.32
say

1195.00

595.10

259225.56

Grading - II
(ii)

Aggregate
Grading-II 63 mm to 45 mm /Grading-III 53 mm
to 22.4 mm@ 0.91 cum per 10 sqm for
compacted thickness of 75 mm

RCD/SOR_2nd Edition

cum

435.600

M-038

Sub - Analysis_B

Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum per
10 sqm
OR

cum

57.600

690.16

39753.22 M-042

Crushable type such as Moorum or Gravel for


grading II &III @ 0.22 cum per 10 sqm
OR

cum

105.590

129.74

13699.25

cum

86.400

563.97

48727.01 M-041

cum

28.800

129.74

3736.51

M-007

KL

144.000

167.07

24057.82

M-189

Type B11.2 mm for grading-III @ 0.18 cum per


10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for
grading II material
Cost of water
4.9B (ii)

M-007

Using Scrining Crushable type such as Moorum or Gravel


(a)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

32916.01
36207.61

Cost for 360 cum = a+b+c+d+e

398283.68

Rate per cum = (a+b+c+d+e)/360

1106.34
say

1106.00

OR
4.9B (ii)

Using Scrining Type-A (13.2mm agg.)


(b)

d)

Overhead charges @ 0.1 on (a+b+c)

35895.06

e)

Contractor's profit @ 0.1 on (a+b+c+d)

39484.56

Cost for 360 cum = a+b+c+d+e

434330.17

Rate per cum = (a+b+c+d+e)/360

1206.47
say

4.9B (ii)

1206.00

Using Scrining Type-B (11.2mm agg.)


(c)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

36792.43
40471.68

Cost for 360 cum = a+b+c+d+e

445188.45

Rate per cum = (a+b+c+d+e)/360


4.9B

1236.63
say

1237.00

268024.68

Grading - III
(iii)

Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per
10 sqm for compacted thickness of 75 mm

cum

435.600

615.30

M-036

Type B11.2 mm for grading-III @ 0.18 cum per


10 sqm
OR

cum

86.400

563.97

48727.01 M-041

Crushable type such as Moorum or Gravel for


grading II &III @ 0.22 cum per 10 sqm

cum

105.590

129.74

13699.25

M-007

cum

28.800

129.74

3736.51

M-007

KL

144.000

167.07

24057.82

M-189

Stone Screening

Binding material
Binding Material @ 0.06cum per 10 sqm for
grading II material
Cost of water
4.9B (iii)

Using Scrining Crushable type such as Moorum or Gravel


(a)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

33795.92
37175.51

Cost for 360 cum = a+b+c+d+e

408930.62

Rate per cum = (a+b+c+d+e)/360

1135.92
say

OR
4.9B (iii)

RCD/SOR_2nd Edition

Using Scrining Type-B (11.2mm agg.)

1136.00

Sub - Analysis_B
(b)

d)

Overhead charges @ 0.1 on (a+b+c)

37672.35

e)

Contractor's profit @ 0.1 on (a+b+c+d)

41439.58

Cost for 360 cum = a+b+c+d+e

455835.39

Rate per cum = (a+b+c+d+e)/360


4.10

405

1266.21
say

1266.00

965.79
612.06
22604.22

Crushed Cement Concrete Sub-base / Base

SUB ANA
-B

Breaking and crushing of material obtained by


breaking damaged cement concrete slabs to size
range not exceeding 75 mm as specified in table
400.7 transporting the aggregates obtained from
breaking of cement concrete slabs at a lead of L km.,
laying and compacting the same as sub base/ base
course, constructed as WBM to clause 404 except
the use of screening or binding Material.
Unit = cum
Taking output =360 cum
a) Labour
Mate
Mazdoor skilled
Mazdoor for crushing broken cement concrete
pavement/slabs into aggregate
b) Machinery
Motor Grader,110 HP @ 50 cum/hr.
Smooth 3 wheeled steel roller @ 30cum/hr.
Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover
cost of loading and unloading
Water tanker 6 KL capacity with 5 km lead @ 1
trip per hour
c) Material
Material available from dismantled concrete slab
after crushing / breaking and only carriage is
required to be provided
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)

day
day
day

4.160
2.000
102.000

232.16
306.03
221.61

hour
hour
hour
tonne.km

6.000
12.000
6.000
720 x L

2488.00
625.00
1116.00
2.68

hour

12.000

111.24

1334.88

P&M-060

KL

72.000

167.07

12028.91
6879.12
7567.03

M-189

Cost for 360 cum = a+b+c+d+e


Rate per cum = (a+b+c+d+e)/360

L-12
L-15
L-13

P&M-032
14928.00
P&M-044
7500.00
P&M-017
6696.00
1928.45 Lead =1 km &
P&M-047
192.84

83237.29
231.21

With Smooth 3 wheeled Steel Roller

say

231.00

232.16

111.44

1. It is assumed that dismantling of concrete


slab/pavement has been considered separately.
Hence same is not added in this analysis. Only
labour for crushing the dismantled slab into
aggregate has been added. Carriage from stock pile
to work site has been provided with a lead of L km.

4.12
SUB ANA
-B

406

Note 2. In case of breaking of slabs is done locally without


involvement of transportation, the provision of tipper,
front end loader and loading/unloading charges may
be deleted.
Wet Mix Macadam
Providing, laying, spreading and compacting graded
stone aggregate to wet mix macadam specification
including premixing the Material with water at OMC
in mechanical mix plant carriage of mixed Material by
tipper to site, laying in uniform layers with paver in
sub- base / base course on well prepared surface
and compacting with vibratory roller to achieve the
desired density.
Unit = cum
Taking output = 225 cum (495 tonnes)
a) Labour
Mate

RCD/SOR_2nd Edition

day

0.480

L-12

Sub - Analysis_B
Mazdoor skilled
Mazdoor
b) Machinery
Wet mix plant of 75 tonne hourly capacity
Electric generator 125 KVA
Front end loader 1 cum capacity
Paver finisher
Smooth 3 wheeled steel roller @ 8-10 tonnes.
Water tanker 6 KL capacity
Tipper

c)

d)
e)

day
day

2.000
10.000

306.03
221.61

hour
hour
hour
hour
hour
hour
tonne.km

6.600
6.000
6.000
6.000
12.000
3.000
495 x L

2550.00
2136.00
1116.00
1167.00
625.00
111.24
2.68

cum
cum
cum
KL

89.100
118.800
89.100
18.000

793.41
867.97
288.57
167.07

Add 10 per cent of cost of carriage to cover


cost of loading and unloading
Material ( Table 400-11)
45 mm to 22.4 mm@ 30 per cent
22.4 mm to 2.36 mm @ 40 per cent
2.36 mm to 75 micron@ 30 per cent
Cost of water
Overhead charges @ 0.1 on (a+b+c)
Contractor's profit @ 0.1 on (a+b+c+d)

Cost for 225 cum = a+b+c+d+e


Rate per cum = (a+b+c+d+e)/225

612.06
2216.10

L-15
L-13

P&M-094
16830.00
P&M-018
12816.00
P&M-017
6696.00
P&M-035
7002.00
P&M-044
7500.00
P&M-060
333.72
1325.81 Lead =1 km &
P&M-047
132.58

70692.83
103114.84
25711.59
3007.23
25810.22
28391.24

say

312303.65
1388.02
1388.00

M-034
M-031
M-022
M-189

1. Though vibratory roller is required only for 3 hours


as per norms, the same is required to be available at
site for 6 hours to match with other machines. The
usage rates of vibratory roller may be multiplied with
a factor of 0.65.
Note 2. As three wheeled smooth steel rollers are
commonly in use, the same has been provided as an
alternative which can be used if the thickness of
individual layer does not exceed 100 mm.
12.5

1300

SUB ANA
-B

Brick Masonry Work in Cement Mortar 1:2 in


Foundation complete excluding Pointing and
Plastering, as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum
a) Material
Bricks Ist class
Cement mortar 1:2 (Rate as in Item 12.6 B subanalysis)
b) Labour
Mate
Mason
Mazdoor
c) Overhead charges @ 0.25 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 5 cum = a+b+c+d
Rate per cum (a+b+c+d)/5

12.5

1300

SUB ANA
-B

2500.00
1.20

4.92
3915.00

12302.11
4698.00

M-079
Item 12.6 (B)

day
day
day

0.48
4.00
8.00

232.16
353.52
221.61

L-12
L-11
L-13

say

111.44
1414.08
1772.88
5074.63
2537.31
27910.45
5582.09
5582.00

Brick Masonry Work in Cement Mortar 1:4 in


Foundation complete excluding Pointing and
Plastering, as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum
a) Material
Bricks Ist class
Cement mortar 1:4 (Rate as in Item 12.6 C subanalysis)
b) Labour
Mate
Mason

RCD/SOR_2nd Edition

each
cum

each
cum

2500.00
1.20

4.92
2538.00

12302.11
3045.60

M-079
Item 12.6 (C)

day
day

0.48
4.00

232.16
353.52

111.44
1414.08

L-12
L-11

Sub - Analysis_B
Mazdoor
c) Overhead charges @ 0.25 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 5 cum = a+b+c+d
Rate per cum (a+b+c+d)/5

12.5

1300

SUB ANA
-B

day

8.00

L-13

say

1772.88
4661.53
2330.76
25638.40
5127.68
5128.00

221.61

Brick Masonry Work in Cement Mortar 1:6 in


Foundation complete excluding Pointing and
Plastering, as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum
a) Material
Bricks Ist class
Cement mortar 1:6 (Rate as in Item 12.6 D subanalysis)
b) Labour
Mate
Mason
Mazdoor
c) Overhead charges @ 0.25 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 5 cum = a+b+c+d
Rate per cum (a+b+c+d)/5

each
cum

2500.00
1.20

4.92
2002.00

12302.11
2402.40

M-079
Item 12.6 (D)

day
day
day

0.48
4.00
8.00

232.16
353.52
221.61

111.44
1414.08
1772.88
4500.73
2250.36
24754.00
4950.80
4951.00

L-12
L-11
L-13

say

RCD/SOR_2nd Edition

CHAPTER-1
CARRIAGE OF MATERIALS
Sr No

Ref. to
MoRTH
Spec.

Description

1.1

Loading and Unloading of Stone


Boulder/ Stone aggregates/Sand/
Kanker/Moorum

Unit

Quantity

Remarks/
Input ref.

Rate Rs

Cost Rs

830.00

273.90

P&M-048

368.28

P&M-017

cum

Placing tipper at loading point, loading with


front end loader, dumping, turning for
return trip, excluding time for haulage and
return trip
Unit = cum
Taking output = 5.5 cum
Time required for
i)

1 Min

Positioning of tipper at loading point

13 Min

ii)
Loading by front end loader 1 cum
bucket capacity @ 25 cum per hour
iii)
Maneuvering, reversing, dumping and
turning for return
iv)
Waiting time, unforeseen
contingencies etc
Total
a)

b)
c)

2 Min
4 Min
20 Min

Machinery
Tipper 5.5 tonnes capacity

hour

0.330

Front end-loader 1 cum bucket capacity @


25 cum/hour
Overhead charges @ 0.1 on (a)

hour

0.330

1116.00

64.22
70.64

Contractor's profit @ 0.1 on (a+b)

777.04

Cost for 5.5 cum = a+b+c

141.28

Rate per cum = (a+b+c)/ 5.5


Note
1.2

say

Unloading will be by tipping.

141.00

Loading and Unloading of Boulders by


Manual Means
Unit = cum
Taking output = 5.5 cum
a)

b)

Labour
Mate

day

0.110

232.16

25.54

L-12

Mazdoor for loading and unloading

day

0.750

221.61

166.21

L-13

hour

0.750

830.00

622.50

P&M-048

Machinery
Tipper 5.5 tonne capacity

c)

Overhead charges @ 0.1 on (a+b)

81.42

d)

Contractor's profit @ 0.1 on (a+b+c)

89.57
985.24

Cost for5.5 cum = a+b+c+d

179.13

Rate per cum = (a+b+c+d)/5.5


Note
1.3

say

Unloading will be by tipping.

179.00

Loading and Unloading of Cement or


Steel by Manual Means and Stacking.
Unit = tonne
Taking output = 10 tonnes
a)

b)

Labour
Mate

day

0.080

232.16

18.57

L-12

Mazdoor for loading and unloading

day

2.000

221.61

443.22

L-13

hour

2.000

745.00

1490.00

P&M-057

Machinery
Truck 10 tonne capacity

c)

Overhead charges @ 0.1 on (a+b)

195.18

d)

Contractor's profit @ 0.1 on (a+b+c)

214.70
2361.67

Cost for10 tonnes = a+b+c+d

236.17

Rate per tonnes = (a+b+c+d)/10

say
1.4

Cost of Haulage Excluding Loading and


Unloading
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.

Unit = t.km
Taking output 10 tonnes load and lead 10
km = 100 t.km

236.00

(i)

Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty :35 km / hour.
a)

Machinery.
Tipper 10 tonne capacity
Time taken for onward haulage with load

hour

0.400

830.00

332.00

P&M-048

Time taken for empty return trip.

hour

0.290

830.00

240.70

P&M-048

b)

Overhead charges @ 0.1 on (a)

57.27

c)

Contractor's profit @ 0.1 on (a+b)

63.00
692.97

cost for 100 t km = a+b+c

6.93

Rate per t.km = (a+b+c)/100


1.4

(ii)

say

6.90

Unsurfaced Graveled Road


Speed with load: 20 km / hour
Speed for empty return trip :30 km / hour
a)

Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage with load

hour

0.500

830.00

415.00

P&M-048

Time taken for empty return trip

hour

0.330

830.00

273.90

P&M-048

b)

Overhead charges @ 0.1 on (a)

68.89

c)

Contractor's profit @ 0.1 on (a+b)

75.78
833.57

Cost for 100 t .km = a+b+c

8.34

Rate per t.Km = (a+b+c)/100


1.4

(iii)

say

8.30

Katcha Track and Track in River


Bed/Nallah Bed and Choe Bed
Speed with load :10 km / hour
Speed while returning empty:15 km / hour
a)

Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage

hour

1.000

830.00

830.00

P&M-048

Time taken for empty return trip

hour

0.670

830.00

556.10

P&M-048

b)

Overhead charges @ 0.1 on (a)

138.61

c)

Contractor's profit @ 0.1 on (a+b)

152.47
1677.18

Cost for 100 t .km = a+b+c

16.77

Rate per t.Km = (a+b+c)/100

say

16.80

You might also like