Construction of T2 at MCIA
PLUMBING WORKS FOR T2

Package No. PACKAGE NO. 3 - WATER TREATMENT AND PRESSURISATION SYSTEM

Sr.No.

Description

DRINKING WATER TREATMENT AND PRESSURISATION SYSTEM


Supply, installation, testing and commissioning of drinking water treatment and
pressurisation system which consist of compact RO system with filters pumps,
pressure vessel and UV sanitizer. Drinking Water System including all the piping,
concrete base and vibration isolator, fibre glass tank, valves, y-strainer, pressure
gauges and fittings including piping from isolation valve to pumps and to
discharge pipe UV sanitizer supply and return pipe line, including high and low
level alarms, low level booster pump cut off at the tank and vfd/vsd with complete
installation of all electrical works and materials such us wiring, panel boards,
controls and other electrical accessories needed to complete the work, including
the pumps and pipe supports, hangers, valves and other accessories as shown in
the drawing and as needed to complete the work, all materials and equipment
must conform with the drawings and specifications provided. Refer specification of
pumps and drawings: GMCAC/MCIA/D/OAP/P50/0001 and
GMCAC/MCIA/D/OAP/P60/0001

Qty.

lot

lot

lot

MVAC WATER SOFTNER


Supply, installation, testing and commissioning of MVAC water softner which
consist of softener, fiberglass water tank, pressure vessel and pumps, including all
the piping, concrete base and vibration isolator, valves, y-strainer, pressure
gauges and fittings including piping from isolation valve to pumps and to
discharge pipe, including high and low level alarms, low level booster pump cut off
at the tank and vfd/vsd with complete installation of all electrical works and
materials such us wiring, panel boards, controls and other electrical accessories
needed to complete the work, pump and pipe supports, hangers and other
accessories needed to complete the work, all materials and equipment must
conform with the drawings and specifications provided. Refer specification of
pumps and drawings: GMCAC/MCIA/D/OAP/P50/0001 and
GMCAC/MCIA/D/OAP/P60/0001

Unit

PRESSURISATION UNIT WITH MAKE-UP TANK


Supply, Installation, Testing and Commisioning of Compact Pressurisation Unit
(Grundfos System or Similar approved brands) designed to integrate the chilled
waterline system demand, including pumps, piping, valves, y-strainer, pressure
gauges and fittings, break tank, pressure vessel tank c/w pressure switch for
High/Low pressure alarm including electrical works like wiring from panel board,
etc. concrete base complete piping of the system, valves and fittings, piping and
tank supports, hangers and other miscellaneous items needed to complete the
work, all materials and equipment must comform with the drawings and
specification provided. Refer spec and drawing : section 15001 / 15185 drawing
no. GMAC/MCIA/D/OAP/M00/0001, GMAC/MCIA/D/OAP/M50/0001and
GMAC/MCIA/D/OAP/M60/0003/B.

Rate

Amount