Professional Documents
Culture Documents
Meagan Brown
Erwin Hechter
Alberto Rodriguez
iCAG
Page 1 of 22
Table of Contents
1. Project Approach............................................................................................................3
2. Scope Statement.............................................................................................................3
3. Work Package Development...........................................................................................4
Work Breakdown Structure.....................................................................................5
Work Package Description......................................................................................6
4. Cost Estimate by Work Package.....................................................................................8
5. Project Schedule.............................................................................................................9
6. Cost Estimate................................................................................................................11
Assumptions.........................................................................................................11
7. Project Risk Assessment...............................................................................................12
Key Risks.............................................................................................................12
Risk Response Actions..........................................................................................12
8. Earned Value Plan.......................................................................................................13
Planned Value.......................................................................................................13
Performance Measurement Baseline.....................................................................14
9. Organizational Chart.....................................................................................................14
10. Proposed Draft Contract.............................................................................................15
Appendix A
Detailed Project Schedule
Appendix B
Labor Cost Detail
Appendix C
Organizational Chart
iCAG
Page 2 of 22
Project Approach
Alamo Research Institute (ARI) has requested proposals to perform an Innovative Capabilities Audit on
its five (5) divisions in order to continue to provide the quality multidisciplinary, problem solving services
in engineering and the physical sciences.
Innovative Capability Audit Group (iCAG) has reviewed the proposed Statement of Work and developed
the requested scope items into distinctive Work Packages. Those Work Packages are further broken into
Activities and then the required tasks were identified. iCAG extensive experience performing Innovative
Capabilities Audits and those tasks requested in the RFQ allows us to identify any cost or schedule
efficiencies.
Each Activity was then analyzed by the personnel required and type of interaction with ARI to determine
which tasks must be performed in series with other Activities and which may be performed in parallel.
Based on this analysis, iCAG was able to determine that a phases approach to the complete all of the
Work Packages would provide the best result.
Experts in providing these types of services have reviewed the scope of work and estimated the labor
requirements for each task. Using all of this information and data, iCAG was able to build the schedule
presented. The Project will take approximately 70 working days, which is about three and a half months.
The Project Costs were calculated using the methods as defined in the RFQ. The total cost for the project
will be approximately $310,000. The two highest cost activities 1.2 and 2.2 include the tasks that are
expected to be on the critical path to meeting the project completion goals. Outside consultants will be
contracted to assist the assigned staff to complete these tasks within the required time period using the
most economical means possible. Cost savings may be realized by using the in-house personnel for these
Activities, but addition time may be required in the schedule.
iCAG has also performed a high level risk assessment to identify any obvious risks to the project. Six
risks were identified and analyzed for the probability of their occurrence, the potential severity of the
consequences, and the project elements that will be impacted. Each risk was analyzed and mitigation
plans detailed.
Finally, the iCAG as included a proposed draft contract. iCAG is extremely confident in our capabilities
to The contract is based on a Cost Plus Incentive Fee model. Each work package will be compensated at
a lump sum amount plus a consulting fee of 10%. In the event the actual cost of the work package
exceeds this amount, iCAG will share in 50% of this overage cost.
Scope Statement
The Innovative Capabilities Audit will encompass all five (5) of ARIs divisions and will focus on these
four (4) main areas: (1) Strategic Management Capacity; (2) Resource Availability and Allocation; (3)
Capacity to Understand Technological Environment; and (4) Capacity to Perform Competition Analyses.
Each category, or work package, will have several activities and associated tasks in order to provide ARI
with a holistic and complete assessment of their capabilities and capacity to adequately and efficiently
perform their work.
The first work package will focus on the Strategic Management Capacity. ARI has requested an
assessment of their capabilities in the efforts to support innovative activities. This will include evaluating
iCAG
Page 3 of 22
the capacity of the current management activities and strategies, assessing cooperative efforts within the
management structure; and evaluate and coach venture managers in the execution of their duties.
The second work package will focus on the assessment of currently available resources and their
allocation to support innovation activities. iCAGs assessment will address corporate funding levels, as
well as the personnel in the research and development (R&D), engineering and market research fields.
This work package will also include an analysis performed on ARIs competencies in the areas of
technology that are relevant to the San Antonio business units. Also, iCAG will assess the distribution of
R&D resources allocated to the various disciplines.
The third work package will assess ARIs capacity to understand the technological environment in which
it operates. iCAG will assess ARIs capacity for technological forecasting and realizing the related
impacts, as well as their capacity to assess technologies and developing roadmaps.
The fourth and final work package will assess ARIs capacity in performing Competition Analyses. This
will include assessing ARIs capacity to identify, analyze and predict key competitor strategies and
relationships between allied industries and to anticipate external forces that may either facilitate or hinder
the firms ability to pursue innovative strategies.
iCAG understands the goals for this project are extremely important to the strategic planning of ARIs
operations. iCAG will work closely with ARI to fully define and develop these goals, so as to accurately
measure the success of the project.
iCAG
Page 4 of 22
iCAG
Page 5 of 22
iCAG
Page 6 of 22
2.0 Phase II
2.1. Capacity to Understand Technological Environment Test
2.1.1.Evaluate firms capacity for technological forecasting
2.1.1.1.
Determine what tools ARI currently uses
2.1.1.2.
Determine tool's current standards
2.1.1.3.
Review previous tech purchases
2.1.1.4.
Determine what other related fields were evaluated when making a decision
2.1.2.Assess firms capacity to forecast impacts between related technological areas
2.1.2.1.
Determine how the company determined relation between tech areas
2.1.2.2.
Identify tools were used to determine related tech areas
2.1.2.3.
Identify published literature during the life of the technology
2.1.2.4.
Cross reference the literature for linkages in the technologies
2.1.3.Assess firms capacity to assess technologies & identify technological opportunities across business units
2.1.3.1.
Verify consistency between business units
2.1.3.2.
Identify BU communications & efficiency when determining technological opportunities
Determine BU information sharing & tool usage efficiency
2.1.4.Assess firms Capacity to develop technology roadmaps
2.1.4.1.
Review previous roadmaps to determine whether company reached goals
2.1.4.2.
Identify and determine efficiency of the usage of SOP
2.1.4.3.
Provide recommendations to improvements to process
2.2. Capacity to perform competition analysis test
2.2.1.Assess the firms capacity to perform timely& meaningful analyses of the competitive environment in
which current & future business operations are conducted
2.2.1.1.
Define competitive environment, analysis parameters, and time frame for analysis completion
2.2.1.2.
Determine if the appropriate personnel exists within the firm to complete this task
2.2.1.3.
Assess the validity of the firms method of analyses compared to standard practices
2.2.2.Evaluate the efficacy of current intelligence gathering systems as well as accuracy & completeness of data
available to support the assessment of competitor capabilities
2.2.2.1.
Determine how information is gathered and where it is gathered from
2.2.2.2.
Determine how the firm defines current information
2.2.2.3.
Determine if the appropriate personnel exists within the firm to monitor the data and information
2.2.3.Assess the firms capacity to identify, analyze and predict key competitor strategies
2.2.3.1.
Determine if the firm has strategic analysts available to complete this task
2.2.3.2.
Define the parameters used to identify and predict strategies
2.2.4.Assess firms capacity to develop scenarios concerning relationship evolutions between allied industries
2.2.4.1.
Identify relationships considered in developing scenarios
2.2.4.2.
Assess existing SOP
2.2.4.3.
Identify if proper personnel/facilities are available to complete/evaluate/monitor the task
2.2.5.Determine firms capacity to identify external forces that facilitate and/or hinder the ability to pursue
innovative strategies
2.2.5.1.
Identify external forces considered (personnel, market, industry practices, etc)
2.2.5.2.
Assess the process used to quantify the impact from external forces
2.2.5.3.
Assess the firm's process for updating the impacts
2.2.5.4.
Assess the firm's ability to identify and implement linkages between forces
2.3. Final Submittal
2.3.1.Data Collation & Document Reproduction
2.3.2.QA/QC Review
2.3.3.Phase II Submittal Delivery
iCAG
Page 7 of 22
The Cost Estimate totals by Work Package are presented in Table 1 above. Further analysis on the cost estimate of the project is detailed in the Cost
Estimate section.
iCAG
Page 8 of 22
Project Schedule
Using the considerable knowledge and experience of the Project Team, iCAG will be able to complete the project
in approximately 70 working days. The Project Schedule was developed using the assumptions that ARI will
award the contract and issue the Notice to Proceed on January 1, 2014. iCAG is proposing to divide the work
packages into two separate phases. This phased approach will allow ARI to receive results on portions of the
work earlier. Also, iCAG will be able to take advantage of efficiencies of the allocation of personnel and
utilization of resources to the project.
Table 2 below details the Work Packages, the durations of each, and the proposed early start and end dates. The
scheduled start and end dates of each task and activity are detailed in Appendix A at the end of this proposal.
Phase 1 will be completed in approximately 30 days and the Final Phase 1 Report will be submitted to ARI on
February 12, 2014. During Phase 1, Work Packages 1.1, 1.2 and 1.3 will be executed. Fortunately only one task
in this phase has been identified as being on the critical path and will control the schedule: Task 1.2.5 . All other
tasks (not including the Final Submittal Development tasks) are allowed some measure of float and are somewhat
flexible on their start dates.
Phase 2 will begin immediately following the submittal of the Phase 1 Report and will last approximately 40 days.
Phase 2 will be comprised of Work Packages 2.1, 2.2 and 2.3. The Final Phase 2 Report will be submitted to ARI
on April 9, 2012. Using the proposed schedule, there will be two tasks on the critical path: Tasks 2.2.2 and 2.2.5.
Throughout both phases of the project, all efforts will be undertaken to shorten the critical path without any
impact to the quality of the work. Any efficiency that may be discovered that results in additional float in the
schedule will be reviewed with ARI. iCAG is committed to providing a high quality audit of ARIs Innovative
Capabilities.
1.0
1.1
1.2*
1.3
2.0
2.1
Phase II
Capacity to Understand Technological Environment
Test
2.2* Capacity to perform competition analysis test
2.3
Final Submittal
Note: * denotes Activities which contain the critical path tasks.
iCAG
Duration
(Days)
0
30
16
19
11
Start Date
End Date
1/1/2014
1/2/2014
1/2/2014
1/2/2014
1/29/2014
1/1/2014
2/12/2014
1/23/2014
1/28/2014
2/12/2014
40
2/13/2014
4/9/2014
18
2/13/2014
3/10/2014
29
11
2/13/2014
3/26/2014
3/25/2014
4/9/2014
Page 9 of 22
iCAG
Page 10 of 22
Cost Estimate
iCAG has developed a detailed cost estimate for the requested scope of work outlined in the RFQ. The following
assumptions were used in developing the estimate.
-
Direct Labor Costs were calculated based on the estimated hours of work to be done for every activity and task
by each given direct labor category found in Appendix A of the RFP;
Direct Overhead and General & Administrative Costs were calculated based on the given accepted rates in
Appendix A of the RFP;
Total Profit was computed, per request, based on the accepted rate given in Appendix A of the RFP;
Direct Non-Labor categories were determined based on previous capabilities audits performed by iCAG;
Materials and Costs includes purchased parts and freight, as it is assumed any purchased commodities will be
paper/electronic documents or software; variability in materials costs is based on work package hours and
computer/telephone costs;
Computer/Telephone Costs are calculated as follows, with the applied percentages listed in the table below: XX
% of work package hours x 15, where 15 is a scalar multiple of time and a half and the XX % is the percentage of
work package hours that will be dedicated (not exclusively) to computer/telephone time;
Travel Costs are monthly and based on the assumption that all travel will be localized San Antonio and
surrounding areas and are calculated as follows: (total work package hours/2.5) x $3.50 + any estimated
consultant travel, where 2.5 is equal to the number of hours that the company cars can be driven non-stop before
needing to refuel with tank of gas remaining, and $3.50 is the price of premium gas at the time of the submission
of the response to the RFP; and
Consultant Costs are based on the standard $150 initial fee plus a subsequent $80/hr; we assume that consultants
will be required for 120 hrs; consultant recruitment is done in order to provide a neutral 3 rd party analysis in
addition to iCAGs analysis for the purposes of inter-rater reliability.
Table 3:
Computer/Telephone Time Applied Percentages
WP 1.1
WP 1.2
WP 1.3
WP 2.1
WP 2.2
WP 2.3
75%
80%
100%
85%
90%
100%
iCAG
Page 11 of 22
Severity of Consequence
Elements Impacted
21%
MEDIUM
Inaccurate Assumptions
Failure to Adequately Define
Audit Topics
Project Charge Request by ARI
10%
HIGH
Scope
6%
HIGH
Scope
80%
LOW
2%
HIGH
Cost
1%
LOW
Cost
Risk
iCAG
Page 12 of 22
iCAG
Page 13 of 22
Figure 3: Performance measurement baseline. The total cost over each work package; and the
cumulative planned value (PV) after each work package.
Organizational Chart
iCAG has developed a proven and successful team of professionals with a combined 45 years of experience in the
research and development industry. iCAG team is organized in a combination of projectized groups and functional
groups. The Audit Group staff was selected to work on specified Work Packages to take advantage of their specific
capabilities and to provide continuity throughout the activities. The Financial Operations and Industry Research
Divisions will assign several staff members to assist the Audit Group with tasks that require their expertise.
Albert Rodriguez, Chief Executive Officer
Alberts duties as CEO will be to continually focus on the future, continual focus on new products, services
and clients. Albert will act as the single communication key between the project stakeholders and the
project staff. Albert will give the final sign off on budget and scope completeness.
Brooke Asemota, Chief Financial Officer
Brooke will work with the Audit Group to assign and manage the Financial Operations Personnel and their
assignments to provide financial consulting support in the execution of the Work. During the Project,
Brookes prime focus will be to manage, monitor, and approve budget expenditures for the project.
iCAG
Page 14 of 22
iCAG
Page 15 of 22
AppendixA
Detailed Project Schedule
1.0
1.1
1.1.1
1.1.2
1.1.3
1.1.4
1.1.5
1.2
1.2.1
1.2.2
1.2.3
1.2.4
1.2.5
1.3
2.0
2.1
iCAG
Duration
(Days)
1
30
16
Start Date
End Date
1/1/2014
1/2/2014
1/2/2014
1/1/2014
2/12/2014
1/23/2014
1/2/2014
1/6/2014
1/7/2014
1/9/2014
1/10/2014
1/13/2014
1/10/2014
1/16/2014
1/17/2014
1/23/2014
19
1/2/2014
1/28/2014
1/2/2014
1/10/2014
1/2/2014
1/14/2014
10
1/13/2014
1/24/2014
1/2/2014
1/13/2014
19
1/2/2014
1/28/2014
11
1/29/2014
2/12/2014
40
2/13/2014
4/9/2014
18
2/13/2014
3/10/2014
Page 16 of 22
iCAG
Duration
(Days)
Start Date
End Date
2/13/2014
2/19/2014
2/13/2014
2/24/2014
10
2/25/2014
3/10/2014
12
2/20/2014
3/7/2014
29
2/13/2014
3/25/2014
2/13/2014
2/24/2014
15
2/13/2014
3/5/2014
12
3/6/2014
3/21/2014
12
3/6/2014
3/21/2014
14
3/6/2014
3/25/2014
11
3/26/2014
4/9/2014
Page 17 of 22
AppendixB
Labor Cost Detail
1.0
1.1
1.1.1
1.1.1.1
1.1.1.2
1.1.2
1.1.2.1
1.1.3
1.1.3.1
1.1.4
1.1.4.1
1.1.5
1.1.5.1
1.2
1.2.1
1.2.1.1
1.2.1.2
1.2.1.3
1.2.1.4
1.2.2
1.2.2.1
1.2.2.2
1.2.2.3
1.2.2.4
1.2.3
1.2.3.1
1.2.3.2
1.2.3.3
1.2.4
1.2.4.1
1.2.4.2
1.2.4.3
1.2.5
1.2.5.1
1.2.5.2
1.2.5.3
1.3
1.3.1
1.3.2
Totals
2.0
2.1
2.1.1
2.1.1.1
2.1.1.2
2.1.1.3
2.1.1.4
2.1.2
2.1.2.1
2.1.2.2
2.1.2.3
2.1.2.4
2.1.3
2.1.3.1
2.1.3.2
2.1.3.3
Exec.
Senior
Prof.
Specialist
Associate
Prof.
Specialist
Apprentice
Prof.
Specialist
Senior
Technician
Junior
Technician
Clerical
$240/
hr
$120/hr
$90/hr
$60/hr
$80/hr
$45/hr
$20/hr
1
6
7
2
1
8
4
3
2
2
1
12
12
10
15
1
3
3
1
4
10
8
3
3
8
6
4
1
4
2
2
5
1
1
2
10
3
2
5
12
4
4
4
1
2
5
3
5
12
6
12
10
8
12
3
3
4
7
2
4
3
2
3
5
5
3
15
12
8
15
10
8
2
6
2
4
1
3
3
2
5
6
6
10
15
20
12
15
20
5
8
2
5
8
4
3
4
4
8
10
96
10
8
229
10
8
204
1
64
57
10
8
63
5
5
5
5
10
12
10
10
10
10
12
12
8
6
6
6
4
4
4
4
3
3
3
3
5
1
2
5
8
3
8
10
12
2
4
12
6
2
1
8
1
3
10
5
2
20
8
5
20
12
5
12
8
2
12
4
1
6
3
1
iCAG
Total Cost
Total Hours
$54,995
$11,160
$ 2,000
$ 1,320
$
680
$ 1,940
$ 1,940
$ 1,185
$ 1,185
$ 2,965
$ 2,965
$ 3,070
$ 3,070
$36,855
$ 4,995
$
660
$ 1,860
$ 1,845
$
630
$ 5,285
$ 2,835
$
630
$
620
$ 1,200
$ 7,605
$ 2,895
$ 1,750
$ 2,960
$ 7,875
$ 3,070
$ 3,000
$ 1,805
$11,095
$ 2,905
$ 4,050
$ 4,140
$ 6,980
$ 2,980
$ 4,000
$54,995
$84,885
$36,995
$11,860
$ 2,980
$ 3,000
$ 2,940
$ 2,940
$ 7,830
$ 2,850
$
670
$ 1,300
$ 3,010
$ 9,955
$ 5,820
$ 2,920
$ 1,215
720
144
24
16
8
24
24
16
16
40
40
40
40
496
64
8
24
24
8
72
40
8
8
16
104
40
24
40
104
40
40
24
152
40
56
56
80
40
40
720
1,122
496
160
40
40
40
40
104
40
8
16
40
136
80
40
16
Page 18 of 22
2.1.4
2.1.4.1
2.1.4.2
2.1.4.3
2.2
2.2.1
2.2.1.1
2.2.1.2
2.2.1.3
2.2.2
2.2.2.1
2.2.2.2
2.2.2.3
2.2.3
2.2.3.1
2.2.3.2
2.2.4
2.2.4.1
2.2.4.2
2.2.4.3
2.2.5
2.2.5.1
2.2.5.2
2.2.5.3
2.2.5.4
2.3
2.3.1
2.3.2
Totals
1
6
7
5
5
2
12
10
5
10
8
8
10
10
5
5
3
8
6
5
12
12
8
8
10
6
4
4
3
3
2
5
3
7
6
16
20
12
3
20
3
2
5
5
7
20
18
12
15
2
5
7
5
6
15
6
12
20
2
12
9
1
3
5
2
5
5
2
2
8
6
2
5
10
8
6
6
12
12
5
2
6
1
3
3
1
8
10
148
10
8
292
10
8
316
185
77
3
3
1
3
5
10
8
97
$ 7,350
$ 3,140
$ 3,020
$ 1,190
$40,910
$ 7,630
$ 2,920
$ 2,900
$ 1,810
$ 9,110
$ 2,830
$ 2,020
$ 4,260
$ 7,310
$ 3,180
$ 4,130
$ 8,500
$ 1,230
$ 3,060
$ 4,210
$ 8,360
$ 1,220
$ 3,030
$ 2,910
$ 1,200
$ 6,980
$ 2,980
$ 4,000
$84,885
96
40
40
16
546
104
40
40
24
120
40
24
56
96
40
56
114
16
42
56
112
16
40
40
16
80
40
40
1,122
AppendixC
iCAG
Page 19 of 22
iCAG
Page 20 of 22