You are on page 1of 31

COST AND BUDGET PLAN

Cost Plan Report 1/Schematic Design stage

sample only

Monday, 5 October 2015

Report
Stage
Date
.

project

SAMPLE HOUSE
123 Rose Avenue, North Melbourne
Alterations and additions to existing residence

Title
Address
Works
.

for

Kelly Byrne Hart & Kelly Architects


Mrs & Mr Client
Edward & Joseph Pty Ltd, Engineers

Architects
Client
Engineer
.

CONSTRUCTION PLANNING AND ECONOMICS PTY LTD


5/10/2015 3:24 PM
[ job no. 1 ]

Prepared by : Geoffrey Moyle FAIQS

Cost Planner
printed
reference
.

PO Box 50, Glenrowan Vic 3675 - p 0407 358 184, e gmoyle@costplanner.com.au

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

sample only

Unit

Qty

Rate

Total

NOTES

This cost report

This cost report has been prepared to help establish, review and manage a realistic project scope, budget and cost.

This cost report should be reviewed and revised as the documents, program & design progress, and prior to tendering & construction.

This is a measured approximate-quantities cost plan based on the information provided, and assumptions have been made.

Further cost and budget planning assistance is recommended.

Further design & documentation from the Architect & Structural Engineer is recommended.

Estimated cost

The cost of this project (including GST, but excluding design fees & other client costs) is estimated to be $810,000 to $894,000.

The lower figure above includes for some reduced allowances for Builder's supervision & overheads, and escalation & contingencies.

The budget for this project has been advised to be $725,000.

Summarised as follows:

Structure - floors, roof, walls, windows & doors

$265,366

Finishes and fittings

$183,993

Services

$110,119

Preparation, siteworks & services

$73,647

Builders preliminaries & site costs

$141,972
$775,097

sub total
Escalation, contingencies, etc.

$37,460

Design fees

Excluded

sub total

$812,557

GST

$81,256

Total

$893,813
.

Documents, Advice & Timing

The scope of works is based on the following documents provided by Kelly Byrne Hart & Kelly Architects (received 20.09.2015 u.n.o.)

Sample House - SK A01-, A02A, A03- & A04B

Architectural drawings

Site plan, Existing plan & elevations

Architectural drawings

Scope of works notes, 4 pages, Issue 1/-

Architectural notes

Sketches ST01 & ST02/A

Structural drawings
.

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 2 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

The report is based on the following assumed timetable. Delays in this timeframe may lead to cost increases.
Construction is assumed to commence by December, 2015 and to be completed by August, 2016.

Basis

This report is based on having the Tender and Contract Documentation completed and issued by the Architect.

It is assumed the Building Contract will be administered during construction by the Architect.

This report is based on competitive tendering and assumes fixed lump-sum quotes will be received from 3 to 4 builders.

It is assumed the project will be completed in one stage with the builder having full access of the unoccupied site.

This report is not a Tender Estimate or 'Quote' and should not be used for this purpose.

The content and purpose of this cost plan should be treated accordingly.

Exclusions

Costs for the following are excluded, which are either assumed to be provided separately by the client, or are not required.

Design & Documentation Fees

Loose furniture & equipment, and small appliances

Maintenance, refurbishment, repair & other works generally and to unaltered areas & surrounds etc.

Work or costs to areas not noted or documented

Improvements and upgrades to existing services

Landscaping

Client occupation, completing the work in stages, out-of-hours work and/or an accelerated program

Adopting a negotiated, Cost-Plus, Construction Management, or Owner-builder form of contract

Non-traditional forms of procurement; or for the potential reduced competition by tendering to one builder only

Please note the following:

All prices are 'installed' or 'supply & install' and exclude GST, unless noted otherwise.

The final / contractual scope of works is yet to be fully documented.

No fixed price / firm trade quotations have been sought or received in preparing this report.

It is important that Tenderers provide a Trade Cost Summary in their quotes for review prior to acceptance.

The structural design is yet to be finalised, and assumptions have been made.

Further information regarding the ground conditions is required. Ground conditions are assumed to be stable.

It is assumed existing ground levels are generally acceptable and there is no requirement for cut or fill.

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 3 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

ELEMENTAL COST SUMMARY

m2 BA

185.3

$/m2 BA

Total
.

Preliminaries
Preliminaries

00 PR

17.47%

$141,972
.

Structure, Finishes & Fittings

Floors

01 SU

7.62%

$334.16

$61,918

Staircases

04 SC

1.76%

$77.24

$14,311

Roof

05 RF

5.34%

$233.97

$43,353

Walls

0609WL

9.66%

$423.83

$78,533

Windows & Doors

0708WD

8.28%

$362.95

$67,251

Wall, floor & ceiling finishes

1214FF

9.20%

$403.45

$74,756

Fitments & joinery

15 FT

11.88%

$521.05

$96,546

Special Equipment & Whitegoods

16 SE

1.56%

$68.49

$12,691
.

Services

Sanitary Fixtures & Plumbing

1718SP

5.52%

$242.15

$44,868

Heating & Cooling

2124HC

4.43%

$194.45

$36,030

Electric light & power

26 LP

3.60%

$157.71

$29,222
.

Alterations
Alterations & renovations

31 AR

3.23%

$141.51

$26,221
.

External Siteworks and Services

Site preparation

32 XP

2.06%

$16,706

Paths, paving, fencing & gates

3334R

1.70%

$13,792

Landscaping and improvements

36 XL

0.47%

$3,780

External services

3745X

1.62%

$13,147
.

Special Provisions
Special Provisions - escalation & contingencies, etc.

46 YY

4.61%

$37,460
.

Total - Nett - Excluding GST


Goods and Services Tax
Total - Including GST

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

100.00%

$812,557

10.00%

$81,256
$893,813

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 4 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

sample only

Unit

Qty

Rate

Total

Nett Square Metre Construction Cost Calculation - Building Works Only

Building works costs from above

Structure

$265,366

Finishes & fittings

$183,993

Services

$110,119

Alterations

$26,221

External works & services

Excluded

Special provisions - contingencies, escalation, fees, etc.

Excluded

Builders preliminaries, by proportion

$131,337

GST

Excluded

Nett Total of Building Works only

$717,037
.

'Effective Building Works Area' calculation

New building areas

m2

133.3

100.0%

133.3

Work in existing areas - weighted

m2

72.4

60.5%

43.8

Decks, terraces etc. - weighted

m2

27.3

30.0%

8.2

m2

233.0

79.5%

185.3

= $/m2

$3,870

Divided by 'Effective Building Works Area'

= Nett cost of the Building Works per square metre; excl. site costs, contingencies, escalation, fees, client costs & gst

Note: This is an analysis of the data prepared in the detailed cost plan.

These figures very simply summarise the findings in a $/m2 format so that an overall impression can be made of the cost.

They also offer a consistent format so that this project can be fairly compared to other similar projects.

Office use only - Construction Planning and Economics Pty Ltd data:

185.3

$585,700

$47,425

$141,972

$3,870

$717,037

7.5%

$58,060

Building works

m2

External works

Item

Contingencies & escalation

Item

4.8%

$37,460

GST

Item

10.0%

$81,256

Total

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

185.3

$893,813

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 5 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

TRADE COST SUMMARY

Total
.

Demolition & Site Clearance

2.96%

$24,081

Repairs allowances

1.01%

$8,244

Groundworks & excavation

0.57%

$4,671

Concrete Work, insitu

3.42%

$27,826

Structural steelwork

2.97%

$24,117

10.81%

$87,815

Masonry - Brickwork & blockwork

5.89%

$47,887

Roofing and roof plumbing

2.52%

$20,462

Plasterboard Linings

1.85%

$15,025

Windows

5.31%

$43,180

Doors, frames & hardware

1.87%

$15,177

Carpet, vinyl & rubber wall and floor linings etc.

0.47%

$3,814

Tiling, render & similar finishes

1.04%

$8,418

Painting

3.57%

$28,987

Polished finishes

1.52%

$12,388

Joinery Fittings

9.47%

$76,920

Metalwork, accessories, miscellaneous, & staircases

4.03%

$32,768

Whitegoods & equipment

1.49%

$12,146

Sanitary fittings

2.39%

$19,408

Plumber & hydraulics

4.51%

$36,616

Heating, cooling & mechanical services

4.16%

$33,830

Electrical

3.77%

$30,632

Builder's work in connection with other trades, services, sundries, etc.

0.34%

$2,723

External paving, paths & roadworks

1.21%

$9,819

Site and external works & services

0.76%

$6,172

Scaffold, cranes & the like

1.75%

$14,245

15.72%

$127,727

4.30%

$34,900

Carpentry & Woodwork

Builder's site costs & preliminaries


Design Contingency
Contract Contingency
Escalation

Excluded
0.32%

Loose furniture & fittings, Client Costs & Design Fees

$2,560
Excluded
.

Total - Nett - Excluding GST


Goods and Services Tax
Total - Including GST

100.00%

$812,557

10.00%

$81,256
$893,813
.

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 6 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

COST PLAN DETAILS & MEASUREMENT

QUANTITIES

BUILDING AREAS

m2

195.3

Existing areas

m2

62.0

Existing ground floor building area, to remain

m2

62.0

Proposed Areas

m2

133.3

New ground floor building area

m2

80.1

New first floor building area

m2

53.2

Existing areas to be demolished

m2

73.6

Existing ground floor building area, demolish - attached rear

m2

61.0

Existing building to be demolished - attached deck

m2

8.6

Existing out-building to be demolished - shed

m2

4.0

OTHER AREAS

m2

299.0

Decks and steps, on ground, timber

m2

15.8

External decks - upper

m2

11.5

Verandah / porch - existing to remain

m2

10.4

Site area

m2

261.3

FLOOR AREAS, Structure

m2

231.5

Ground floor area - new structure - concrete slab

m2

80.1

Ground floor area - new structure - timber deck

m2

15.8

Ground floor area - work to existing structure

m2

62.0

Ground floor area - work to existing structure - deck / porch

m2

10.4

Upper floor area - new structure - timber - stair & voids deducted

m2

51.7

Upper levels - new decks

m2

11.5

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 7 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

ROOF AREAS, Structure

m2

165.1

Roof area - lower

m2

34.9

Roof area - upper

m2

57.0

Roof area - existing to remain (on flat)

m2

73.2

EXTERNAL WALL & WINDOW AREAS, Structure

m2

347.5

Timber framed and clad

m2

55.8

Masonry veneer, faced

m2

34.9

Cavity masonry, faced

m2

61.4

Cavity masonry, boundary

m2

44.3

Windows in new walls

m2

58.9

Windows in existing walls

m2

5.2

Existing walls - to remain

m2

71.1

Infilling walls - masonry, double skin

m2

3.9

Existing windows - to remain

m2

12.0

INTERNAL WALL & PARTITION AREAS, Structure

m2

157.0

Timber framed and lined

m2

87.5

Masonry

m2

15.2

Glazed screen

m2

Nil

Existing walls - to remain

m2

54.3

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 8 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

FLOORS, ROOF & WALLS

01 sb Substructure - 03 uf Upper Floors & Staircases - 05 rf Roof

Concrete work

Ground floors:
120mm Concrete slab on ground
including reinforcement, sand, membrane, monolithic finish, joints, insulation, etc.

m2

80.1

$295.87

$23,699

Note

Filling or bedding, allowance

Item

Extra for coloured additive in concrete

m3

Internal beams and attached thickenings to slabs

m3

5.40

In above

Edge beams and attached thickenings to slabs

m3

8.90

In above

Extra for pumping and access

m3

23.9

In above

m3

1.5

Concrete in small pad / pier including excavation, unformed

8.0

In above
Nil

$411.78

$618
.

Strip & pad footings, isolated beams etc., including excavation

m3

4.5

$779.79

$3,509

Blinding concrete including excavation, allowance below footings

Item

Excluded

Sub floor concrete walls, upturns & the like, allowance

Item

Assumed nil
.

Upper floors:
Suspended concrete slab; reinforcement, formwork, mono, joints, insulation, etc.

m2

Nil
.

Timber floor framing

Timber ground floor framing, stumps, pads, bearers, joists, insulation, etc.

m2

Existing to remain

Timber upper floor framing, beams, joists, insulation, etc.

m2

51.7

$104.72

$5,414

Soffit lining to exposed floor framing, (supply only @$18/m2)

m2

3.0

$46.26

$139

Paint to timber or fc plinths, soffits, trims and the like

m2

3.0

$31.10

$93
.

Timber floor linings

Particleboard flooring (supply only @$10/m2)

m2

Plywood flooring (supply only @$20/m2)

m2

CFC flooring (supply only @$45/m2)

m2

27.5

$24.27

Nil
14.2

$82.04

Floor boards:

$1,165
.

Timber floor boards installed (supply only @$60/m2)

m2

Recycled timber floor boards installed (supply only @$100/m2 allow)

m2

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

$667

75.5

$138.47

$10,454
Excluded

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 9 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

Extra for secret nailing

m2

Battens, packers or barriers to framing or slab for floor boards & the like

m2

Particleboard substrate to floor boards

m2

Polished finish to new timber floor boards, including sanding

m2

Excluded
10.0

$35.28

$353
Nil

75.5

$65.39

$4,937
.

Timber deck framing and linings

Timber ground floor framing, stumps, pads, bearers, joists, etc. - external decks & steps

m2

15.8

$121.22

$1,915

Timber upper floor framing, beams, joists, etc. - decks

m2

11.5

$86.99

$1,000

Timber or other substrate to last to receive finish / tanking

m2

11.5

$90.40

$1,040

Insulation to new roof deck areas (supply only @$13/m2)

m2

11.5

$26.78

$308

Tanking to terraces, decks and the like

m2

11.5

$154.08

$1,772

Timber decking installed (supply only @$50/m2)

m2

27.3

$116.46

$3,179

Battens, packers or barriers to framing or slab for decking / tiling

m2

11.5

$28.42

$327

Perimeter plinths

11.7

$28.22

$330

Extra for steps & the like

Item

1.0

$189.40

$189

Seal decks, plinths etc.

m2

30.8

$25.96

$800
.

Existing floors

Prepare, make good or modify existing timber floor linings & framing for new works

m2

Footings, slabs, pads, floor structure & the like; make good or modifications allow

m2

72.4

$61.08

$4,423
In above
.

Allowance for repairs to existing timber floor boards to remain - porch

m2

10.4

$15.13

$157

Polished finish to existing timber floor boards to remain

m2

10.4

Insulation to existing timber floor framing

m2

Excluded

Re-block existing flooring, allowance

Item

Excluded

Floor topping & levelling screeds allowances

m2

Modify existing timber floors for shower setdowns or strengthen floor for bath

Item

Assumed nil

Nil
1.0

$283.79

$284
.

Timber Roof framing

Timber roof and ceiling framing, fascias - generally

m2

91.9

$119.17

$10,952

Insulation to new roof areas (supply only @$11/m2)

m2

84.5

$22.66

$1,916

Other beams, posts and the like

m3

Eaves & other soffit linings (supply only @$15/m2)

m2

5.7

$50.69

$289

Paint to timber or fc eaves, trims and the like

m2

5.7

$31.10

$177

In above

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 10 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

Roof cladding, plumbing, rainwater goods & skylights etc.

Metal roof cladding fixed to timber framing (supply only @$30/m2)

m2

96.6

$64.36

$6,218

Metal roof cladding fixed to timber framing (supply only @$60/m2), long span / shallow

m2

Excluded

Membrane roofing

m2

Nil

Folded seam composite roof cladding & plumbing including ply substrate, pc allowance

m2

Excluded
.

Roof plumbing : gutters, downpipes, valleys, flashing, barges, etc.


Box gutter
Safety mesh, ridge ventilators and roof access hatches are assumed not required

Item

229.6

$30.09

$6,910
Assumed nil

Note

Nil
.

Rooflights, installed (supply only @$1,300/each)

No.

2.0

$1,852.31

$3,705

Rooflights, installed (supply only @$1,000/each), in existing

No.

1.0

$1,532.40

$1,532

Glass roofing & frames, installed (supply only @$800/m2), allow

m2

Electronically controlled blinds to last, including power point

Item

Form opening for new skylights

Item

1.0

$179.84

$180

Timber roof and ceiling framing - rooflights

m2

7.2

$123.40

$888

Plasterboard rooflight shaft, & the like linings including edge treatments, cornices etc.

m2

7.2

$54.31

$391

Paint to new plaster rooflight linings

m2

7.2

$31.54

$227

Nil
Assumed nil

Existing roof framing & roofing - allowances

Beams, alterations, making good etc. existing roofing & framing after demolition, allowance

m2

73.2

$16.36

$1,198

Insulation to existing roof areas (supply only @$8/m2)

m2

73.2

$20.45

$1,497

Existing roof linings, plumbing, sarking etc. are to remain

Note

Minor repairs & alterations to existing roofing & roof plumbing to remain, allowance

Item

Existing to remain
76.9

$27.27

$2,096
.

Structural steel framing, bolts, grout & levelling, primed surface treatment

Structural steel framing, allowance - in existing floors & roof

Structural steel framing in upper floors, allowance

1.64

$8,699.13

$14,238

Structural steel framing in roofs, allowance

0.87

$9,326.34

$8,071

Structural steel framing - other, architectural, allowance - galvanised

0.08

$13,907.70

$1,113

Galvanised finish to steel

Note

Paint finish to exposed steel

Item

Welding, cranage, access; inspections; samples, temporary works; shop drawings, etc.

Note

Purlins and bracing to roof

m2

Fire rating to structural steelwork - extra over allowance

Item

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

Assumed nil

Generally nil
0.08

$1,055.26

$84
In above
Nil
Excluded

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 11 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

Roof plant platform complete for new plant

m2

Nil
.

Staircases, balustrades and handrails

New internal staircase complete with balustrades / handrails

Item

1.0

$7,744.68

$7,745

Internal balustrades / handrails, installed (supply only @$300/m, manufactured)

Item

3.6

$432.85

$1,558

External balustrades / handrails, installed (supply only @$400/m, manufactured)

Item

8.5

$589.20

$5,008
.

Sundries, minor items, bwic, etc.

Subfloor masonry or other walls allowance

Item

7.0

$166.04

$1,162

Termite treatment, barriers, etc. - new & existing areas

Item

157.9

$13.76

$2,173

Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.

Item

In above
.

06 ew External Walls & 09 nw Internal Walls & Screens

Masonry walls, including joints, ties, scaffold, sills, cleaning, etc.

110mm Skin of veneer, solid or cavity external wall, commons

m2

88.6

$128.73

$11,405

110mm Skin of internal wall, commons

m2

15.2

$128.73

$1,957

110mm Skin of veneer, solid or cavity external wall, faced (supply only @$1,350/thou)

m2

157.7

$194.75

$30,713

110mm Glazed skin of veneer, solid or cavity external wall, faced (supply only @$3,840/thou)

m2

110mm Infill skin of wall, commons

m2

7.8

$175.23

$1,367

Masonry work in preparing and filling openings, repairs & the like - allowance

Item

1.0

$1,283.25

$1,283

Credit for re-use of salvaged bricks

Note

Excluded

Nil
.

Hollow or solid block skin of wall

m2

Nil
.

Plasterboard lining to solid walls

m2

78.1

$28.91

$2,257

Paint to new plaster wall linings

m2

78.1

$22.02

$1,719

Paint to masonry walls

m2

Timber skirting installed (supply only @$4/m) - to new walls & linings

Nil
46.5

$11.38

$529
.

Wall framing, linings and insulation

External timber stud framed wall, 90mm, with insulation & sisalation

m2

25mm Foilboard insulation to external stud framed wall

m2

Insulation to external cavity masonry walls (supply only @$10/m2)

m2

105.7

$25.12

$2,655

Internal timber stud framed wall, 90mm, insulated

m2

87.5

$60.81

$5,321

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

90.7

$80.65

$7,315
Nil

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 12 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

Timber infill framing to internal walls

Item

Nil
.

Timber or other external sheet wall linings, installed (supply only @$60/m2)

m2

40.8

$142.05

$5,796

FC external wall linings, installed (supply only @$30/m2)

m2

50x50mm Timber battens to external walls, installed (supply only @$9/m)

74.0

$16.43

$1,216

Paint or stain to timber or fc wall linings, & battens

m2

48.2

$31.10

$1,499

External metal wall cladding, installed (supply only @$40/m2)

m2

15.0

$99.31

$1,490

Zincalume composite external wall cladding, installed - pc allowance

m2

Nil

Extra for backing board

m2

Nil

Extra for battens, packers or the like - for cladding fixed vertically & the like

m2

Nil

55.8

$18.00

$1,004
.

10mm Plasterboard lining to stud walls

m2

261.2

$23.94

$6,252

Fire rated plasterboard to stud walls

m2

Villaboard wall linings for tiles, installed - extra over allowance

m2

45.6

$7.30

$333

Paint to new plaster wall linings

m2

261.2

$22.02

$5,750

Timber skirting installed (supply only @$4/m) - to new walls & linings

87.1

$11.38

$990

Assumed nil

Render, hard plaster and the like


Render, hardplaster and the like to walls

Note

Assumed nil
.

Repairs, linings, patching and making good to walls & finishes

Alterations & making good to existing walls after demolition & new works etc., allow

Item

Structural steel framing in existing walls, new openings & the like, allowance

1.0

$1,636.20

$1,636
Assumed nil

External walls :

Patching, repairs & making good to external wall surfaces & structure to remain, allow

m2

Insulation & sarking to existing external walls (supply only @$8/m2)

m2

71.1

$20.43

$1,452
Excluded

Internal walls & linings :

Repairs & making good to internal wall structures to remain, allow

m2

54.3

$7.29

$396

Patching, repairs & making good to internal wall surfaces / finishes to remain, allow

m2

172.6

$10.98

$1,896

Plasterboard lining to existing walls in altered areas - allowance

m2

20.0

$35.48

$710

Paint :

Paint to existing external wall surfaces etc. to remain

m2

71.1

$28.52

$2,028

Paint to new plaster wall linings

m2

20.0

$22.02

$440

Paint internally to existing wall linings & other surfaces to remain

m2

152.6

$22.02

$3,359

Timber skirting installed (supply only @$4/m) - to new & existing wall linings

32.1

$11.38

$365

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 13 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

Sundries, bwic, etc.

Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.

Item

1.00%

In above
.

WINDOWS & DOORS

07 ww Windows, 08 ed External Doors & 11 nd Internal Doors

Windows, screens and glazed doors

Ground floor windows, in new walls (supply only @$487/m2), timber, glazed

m2

32.1

$663.30

$21,292

First floor windows, in new walls (supply only @$479/m2), timber, glazed

m2

26.8

$653.30

$17,508

Ground & first floor windows, in new walls (supply only @$1,000/m2), steel, glazed

m2

New windows, in existing walls (supply only @$500/m2), glazed

m2

Internal glazed screens, in new walls (supply only @$300/m2)

m2

Sliders for last

Note

Pivot mechanisms (supply only @$400/each)

No.

Nil

Extra over for some minor solar, obscure or other glazing

m2

In above

Allowance for flyscreens, installed

m2

In above

Excluded
5.2

$707.66

$3,680
Assumed nil
In above

Hardware, architraves, reveals, trims, sills, paint, etc. :

Handle sets, plates, pulls, etc. & lock to glazed door (supply only @$180/each, combined)

No.

5.0

$326.91

$1,635

Seals, closers, grilles, kickplates, indicators, bolts, signage & the like

Note

Miscellaneous & minor hardware to windows (supply only @$15/m2)

m2

64.1

$26.21

$1,680

Architraves, reveals, trims, sills, flashings, pelmets etc., installed, to new windows

m2

64.1

$27.25

$1,747

Paint to windows and other trims, externally / internally

m2

128.2

$29.54

$3,787

Nil

Existing windows & glazed doors :

Allowance for repairs & making good to existing windows / glazed screens to remain

m2

12.0

$58.36

$700

Miscellaneous & minor hardware to existing windows (supply only @$10/m2)

m2

12.0

$17.47

$210

Architraves, reveals, trims, sills, flashings, pelmets etc., installed, to existing windows

m2

Paint to existing timber windows and other trims, externally / internally

m2

Existing to remain
24.0

$25.99

$624
.

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 14 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

Automatic & other mechanisms :


Automatic mechanisms & the like

Note

Nil
.

Curtains and blinds, allowances


Curtains and blinds, blackout blinds, external blinds, and curtain tracks

Note

Excluded / By Client
.

External doors, frames & hardware

Single hinged external door, standard (supply only @$100/each)

No.

1.0

$232.34

$232

Single hinged external entry door, standard (supply only @$200/each)

No.

1.0

$359.69

$360

Single hinged external security door

Note

External timber door frame with sill & trims

12.6

$70.08

$883

Handle sets, plates, pulls, etc. & lock to external door (supply only @$200/each combined)

No.

2.0

$363.24

$726

Paint to timber doors & frames, externally

No.

2.0

$212.44

$425

Nil

Existing doors :

Existing external doors & frames to remain - allow for minor repairs / alterations only

Item

1.0

$58.63

$59

Sundry hardware installed, allowance

Item

1.0

$117.26

$117

Paint to existing timber doors & frames, externally

No.

1.0

$212.44

$212
.

Internal doors, frames & hardware

Single hinged internal door, standard (supply only @$50/each)

No.

5.0

$144.26

$721

Single hinged internal hollow core door, standard (supply only @$25/each)

No.

1.0

$108.43

$108

Single pivot internal door (supply only @$500/each door & pivot mechanism)

No.

2.0

$873.69

$1,747

Single sliding internal door & track (supply only @$300/each; door & track)

No.

2.0

$550.58

$1,101

Single large sliding internal door & track (supply only @$600/each; door & track)

No.

Internal timber door frame with trims

Nil
54.0

$54.92

$2,966
.

Handle sets, plates, pulls, etc. to internal hinged door (supply only @$125/each)

No.

8.0

$203.06

$1,625

Handle sets, plates, pulls, etc. to internal sliding door (supply only @$80/each)

No.

2.0

$151.62

$303

Seals, closers, grilles, kickplates, indicators, bolts, signage & the like

Note

Paint to timber doors & frames, internally

No.

Nil
10.0

$199.94

$1,999
.

Existing doors :

Existing internal doors & frames to remain - allow for minor repairs / alterations only

Item

Sundry hardware installed, allowance

Item

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

4.0

$175.89

$704
Nil

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 15 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

Paint to existing timber doors & frames, internally

No.

4.0

$199.94

$800
.

Fire rated doors sets, complete :

Fire rated doors sets, complete

No.

Nil
.

Garage doors, operable walls, roller grilles, partitions & other items

Garage doors

Note

None shown

Operable walls, roller grilles and the like

Allow

Nil
.

Sundries, bwic, etc.

Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.

Item

1.00%

In above
.

FINISHES

12 wf - 14 cf Wall, Floor & Ceiling Finishes

Wall & floor tiling


Wall tiles installed, incl. joints, sealers, etc. (supply only @$40/m2), wet areas

m2

38.0

$120.24

$4,569
.

Floor tiles installed, incl. joints, sealers, etc. (supply only @$50/m2), wet areas

m2

14.2

$131.86

$1,872

Stone or other floor tiles installed, incl. joints, sealers, etc. (supply only @$75/m2)

m2

6.0

$160.90

$965

Bedding for floor tiles, allow

m2

14.2

$71.20

$1,011

Allowance for spare tiles

Note

Nil
.

Carpet, vinyl, linoleum, rubber & the like

Carpet & underlay installed (supply only @$50/m2)

m2

27.5

$75.52

$2,077

Vinyl, linoleum, rubber or similar flooring installed (supply only @$50/m2), allowance

m2

5.0

$84.18

$421
.

Plasterboard ceiling linings

Plasterboard ceiling linings including edge treatments, cornices etc.

m2

146.6

$32.21

$4,723

Plasterboard bulkhead & the like linings including edge treatments, cornices etc.

m2

5.0

$54.31

$272

Extra over allowance for suspended flush plasterboard ceiling - assumed

m2

Excluded

Extra for special cornices, roses, bulkheads, pelmets, coffers & the like

m2

Assumed nil

Fire rated plasterboard ceiling linings

m2

Nil

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 16 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

Paint to new plaster ceiling linings

m2

151.6

$25.04

$3,797
.

Existing ceilings :

Make good to existing ceiling finishes & cornices to remain due to demolition & new work, allow

Item

38.9

$10.81

$420

Paint to existing ceilings

m2

38.9

$21.47

$835
.

Ply, timber & other wall, floor & ceiling linings / finishes & sundries

Timber wall linings, select, (supply only @$40/m2)

m2

Other plywood, timber, laminate, vinyl & other 'decorative' wall & acoustic linings

m2

Paint / stain to timber wall linings

m2

Ply, timber, laminate & other 'decorative' ceiling & acoustic linings / finishes (supply only @$50/m2)

m2

15.0

$87.74

$1,316
Nil

15.0

$22.02

$330
Assumed nil
.

Grind or polished finishes to concrete floors, pc allowance

m2

59.2

Screed for last

m2

Nil

Concrete plinths, tactile indicators, door mats & surrounds, & the like

Note

Nil

Tanking and waterproofing to wet areas, allow

Item

Existing skirtings are assumed to remain

Note

Sundries, trims, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.

Item

3.0

$125.86

$1,188.88

$7,451

$3,567
Assumed

1.00%

$36,343.74

$363
.

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 17 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

JOINERY, FITTINGS AND EQUIPMENT

15 ft Fitments & Joinery

Joinery fittings

Kitchen:
Allowance for kitchen & pantry joinery complete

Item

1.0

Extra for stone, glass, concrete or similar benchtops / splashbacks

Item

5.4

Extra for glass, stone, steel or similar splashbacks

Item

$32,571.35

$32,571
In above
Nil
.

Bath:
Bathroom & ensuite joinery complete
Extra for stone, glass, concrete or similar benchtops / splashbacks

Item

1.0

Item

2.1

$7,879.16

$7,879
In above
.

Laundry:
Laundry joinery complete
Extra for stone, glass, concrete or similar benchtops / splashbacks

Item

1.0

$5,103.45

Item

$5,103
Nil
.

Other areas:

Cupboards / robes complete including doors & fitout

m2

11.2

$907.28

$10,162

Walk-in robe fitout allowance

m2

7.3

$850.58

$6,209

Seat, upholstered

1.8

TV joinery unit

Wall unit to dining room, allow

1.6

$2,381.61

$3,811

Wall unit to family room, allow

3.4

$1,445.98

$4,916

Study joinery, allowance, as advised

Item

1.0

$4,000.00

$4,000

Fireplace joinery, allowance

Item

1.0

$2,268.20

$2,268

Excluded
Assumed loose

Garage joinery, allowance

Nil

BBQ bench, allowance

Item

Other fixed joinery allowance

Item

Assumed nil

Modify & make good existing robes to remain, allowance

Item

Excluded

1.0

Excluded

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 18 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

Bathroom / amenities accessories

Mirrors, installed (supply only @$200/m2)

m2

9.0

$301.06

$2,710

Toilet roll holder, installed (supply only @$50/each)

No.

3.0

$81.23

$244

Shower screens, installed (supply only @$1,200/each)

No.

2.0

$1,611.18

$3,222

Kitchen accessories, installed (supply only @$400/each)

No.

1.0

$575.48

$575

Laundry accessories, rails, etc. installed (supply only @$100/each)

No.

1.0

$143.87

$144

Bathroom / ensuite accessories, rails, etc. installed (supply only @$300/each)

No.

2.0

$431.61

$863

Powder room accessories, rails, etc. installed (supply only @$100/each)

No.

1.0

$143.87

$144

Grab rails and the like, installed (supply only @$500/each)

No.

Nil

Heated towel rails installed (supply only @$1,000/each)

No.

Assumed nil
.

Screens, awnings and the like

Allowance for external canopies, including all framing & finishing - rear

Item

1.0

$1,908.90

$1,909

Allowance for external vertical screens, including all framing & finishing

m2

15.0

$463.59

$6,954

Motorised awning

Note

Excluded / By Client

Allowance for other shutters, screens, canopies, louvres or awnings etc.

Item

Assumed nil

Structural steel framing - other, architectural, allowance - galvanised - in screens

0.05

$13,907.70

$695
.

Miscellaneous and other metalwork & sundry items

Miscellaneous & sundry metalwork installed

m2

195.3

$2.18

$426

Extinguishers, fire blankets

Item

Clothesline, installed (supply only @$300/each)

No.

1.0

$527.09

$527

Letterbox, installed (supply only @$100/each)

No.

1.0

$196.34

$196

TV bracket, installed (supply only @$350/each)

No.

1.0

$542.45

$542

Allowance for other fittings, joinery, metalwork, sundries & the like

m2

Pinboards, whiteboards, pegboards and the like, allowance

Item

By Client

Assumed nil
Nil
.

Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.

Item

1.00%

In above
.

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 19 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

16 se Special Equipment & 17 sf Sanitary Fittings; 18 pd - 20 gs Sanitary Plumbing

Whitegoods & Equipment, installed

Oven (supply only @$2,500/each)

No.

1.0

$3,307.85

$3,308

Cooktop (supply only @$1,500/each)

No.

1.0

$1,960.71

$1,961

Rangehood (supply only @$1,100/each)

No.

1.0

$1,364.86

$1,365

Flue & roof cowl for rangehood

No.

1.0

$545.26

$545

Dishwasher (supply only @$1,400/each)

No.

1.0

$1,775.28

$1,775

Coffee machine (supply only @$1,000/each)

No.

Refrigerator & freezer (supply only @$2,000/each)

No.

1.0

$2,341.13

$2,341

Wine fridge (supply only @$900/each)

No.

1.0

$1,111.25

$1,111

Barbecue (supply only @$1,000/each)

No.

Microwave, supplied by the client - builder to install

No.

1.0

$59.99

$60

Washing machine, supplied by the client - builder to install

No.

1.0

$119.99

$120

Clothes dryer, supplied by the client - builder to install

No.

1.0

$104.99

$105

Nil

Excluded

Sanitary fittings, tapsets, hot water services etc. - allowances, installed


Kitchen sink, drainer & tapsets / mixer (supply only @$1,050/each combined, with waste)

No.

1.0

$1,333.78

$1,334
.

Wall basin, tapsets / mixer & bottletrap (supply only @$975/each combined, with waste)

No.

2.0

$1,389.68

$2,779

Vanity basin & tapsets / mixer (supply only @$700/each combined, with waste)

No.

2.0

$925.82

$1,852

Laundry trough & tapsets / mixer (supply only @$475/each combined, with waste)

No.

1.0

$668.12

$668
.

WC suite (pan, seat & cistern), (supply only @$1,100/each)

No.

3.0

$1,454.85

$4,365
.

Bath tub & tapsets / mixer / spout (supply only @$2,200/each combined, with waste)

No.

1.0

$2,799.81

$2,800

Item

1.0

$215.98

$216

Shower base (supply only @$400/each, with waste)

No.

1.0

$679.57

$680

Shower tapsets, mixer, rose, waste (supply only @$500/each)

No.

2.0

$694.24

$1,388

Shower trench

2.0

$520.86

$1,042

Framing, labour & sundries in bath surround

Washing machine & dishwasher stops (supply only @$220/each)

No.

Insinkerator; boiling / chilled water unit; drinking fountain & the like

Note

2.0

$287.97

$576
Nil
.

Hot water service (supply only @$1,400/each)

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

No.

1.0

$1,925.26

$1,925

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 20 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

Solar hot water service (supply only @$8,000/each)

No.

Nil
.

Sanitary plumbing, reticulation, water, gas, waste & sundries to plumbing, fixtures & equipment:
Plumbing fixtures, hot & cold water, sewer / waste & vents reticulation

Item

Allowance for pumping system, filters, etc.

22.0

$1,147.43

Item

$25,244
Assumed nil
.

HEATING, COOLING & ELECTRICS

21 sh Space Heating - 24 ac Air Conditioning

Heating

Allowance for ducted heating

Item

Hydronic heating, panels & boiler

Item

Screed for heating, assumed

Nil
1.0

$20,179.80

m2

$20,180
Nil
.

Insert-type fireplace & flue, installed (supply only @$4,500/each)

No.

1.0

$5,650.34

$5,650

Power point for last

No.

1.0

$152.17

$152

Allowance for surrounds, hearths and the like

Item

1.0

$1,090.80

$1,091

Repair & reinstate existing open fireplaces, chimneys, surrounds etc.

Item

Excluded
.

External gas, electric, or other, heaters

Item

Nil
.

Air Conditioning

Air conditioning, split system

Item

Air conditioning, fully ducted and concealed systems

Item

2.0

$4,000.00

$8,000
Excluded
.

Sundries, bwic, platforms, enclosures & the like

Plant platforms, enclosures and the like, allowance

Item

Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.

Item

Nil
2.50%

$38,257.75

$956
.

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 21 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

26 lp - 27 cm Electric Light and Power, Communications

Electric light and power


Mains / sub-mains, switchboards, meter board & the like, allowance

Item

New switchboard, allowance

Item

Modify / relocate existing switchboard, allowance

Item

Modify / relocate existing meterboard, allowance

Item

Light points - ceiling / wall & external, including switches

Item

181.0

1.0

In above
Excluded

47.0

No.

Pendant light points

No.

2.0

Item

39.0

Extra over for floor box

$3,731
Excluded

Uplight points

Power points

$20.62

$185.96

$8,740
Nil
In above

$146.28

No.

$5,705
Nil
.

TV antenna alterations

Item

1.0

$199.95

$200

Phone, data, TV, intercom, other - point

No.

6.0

$183.20

$1,099

Smoke detector

No.

2.0

$144.29

$289

Intercom, allowance

Item

Nil
.

Exhaust fans, wiring, flues & the like

Item

1.0

$1,800.30

$1,800

3in1 'XL Tastics' and the like (supply only @$150/each)

No.

Nil

Mirror demister (supply only @$125/each)

No.

Nil
.

Phone line connection, telephone handsets

Note

Excluded

Control systems, Uninterrupted power supply (UPS), generators and the like

Note

Excluded

Pre-wiring allowance for other items, security & the like

Item

Nil

Cabling & wiring for computers, data, Pay TV, stereos, etc., allowance

Item

Excluded

Hub, allowance

Item

Nil
.

Solar Power
Solar power installed, pc allowance

Item

Excluded
.

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 22 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

Light fitting, fans and the like - supply only

Selected light fittings, allowance

Item

1.0

$6,000.00

$6,000

Downlights, wall lights, feature lights, LEDs, externals, & the like

Item

Uplights

No.

Pendant lights

Item

By Client

External fittings

No.

In above

Specialist display, art or other selected light fittings

Note

Nil

Floor and other lamps

Note

By Client

In above
Nil

Ceiling 'sweep' fans and the like, installed (supply only @$400/each)

No.

2.0

$672.80

$1,346
.

Communications, data, security & the like

Security & intercom systems (excludes monitoring)

Note

Excluded

Communications, data; WAP; audio visual equipment; automation systems; ducted vacuum & the like

Note

Excluded

Video phones, satellite dish, Pay TV, CCTV, NBN

Note

Excluded
.

Sundries, bwic, etc.

Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.

Item

1.00%

$31,245.13

$312
.

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 23 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

PREPARATION

31 ar Alterations and Renovations

Internal demolition and preparation to existing structure

Internal demolition & removal works allowance & remove the following:

General and miscellaneous internal demolition & preparation

Item

62.0

$16.81

$1,042

Floors, framing, linings & the like

Item

1.0

$1,024.27

$1,024

Walls, framing, linings & windows

Item

72.0

$28.44

$2,047

Roof framing, linings & plumbing

Item

86.7

$30.35

$2,630

Doors, frames, joinery, stairs, sanitary fittings, whitegoods, services & the like

Item

14.0

$84.61

$1,185

Wall, floor & ceiling finishes & linings

Item

43.0

$22.36

$961
.

Form openings & the like, and other items:

Form, & modify opening in walls

Item

Masonry work - preparation, openings, infilling, patching, making good, etc.

0.4

$10,508.00

Item

$3,993
In above
.

Sawcutting slabs including establishment and disposal, allowance

Item

Interface works: preparing, levelling, straightening, propping, bracing, & supports etc. allow

Item

Assumed nil
1.0

$1,155.88

$1,156
.

Repairs, making good & the like, allowances to the existing building, etc.

General & miscellaneous repairs & the like, allowance

Item

1.0

$2,500.00

$2,500

Damp, dpc's, termites, mould or other similar problems

Item

1.0

$2,000.00

$2,000

Structural & other repairs to existing footings, floors, walls, roof, etc

Item

Assumed nil

Repairs & making good to faade, verandah etc. & restoration of period features, cappings, etc.

Item

Excluded

Work to other existing buildings

Item

Nil

Paint & minor repairs to existing surfaces generally, allowance

Item

Excluded

Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.

Item

1.00%

In above
.

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 24 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

32 xp Site Preparation

Demolition, removal & site clearance

Clearance:

External site preparation & clearance, minor demolition, removals, excavation & other costs

Item

1.0

$1,894.07

$1,894

Demolition:

Demolish attached rear of house

m2

61.0

$127.79

$7,795

Demolish shed

m2

4.0

$43.21

$173

Demolish other items

Item

Assumed nil

Remove the following:

Remove driveways, paving, fences, gates, decks, landscaping & the like, allowance

Item

1.0

$2,216.98

$2,217

Landscaping & the like

m2

In below

Tree removal, large

No.

Excluded

Other items, sundries & minor works

Item

Assumed nil

Adjacent buildings:

Repairs & making good, etc. to adjacent buildings, structures, fittings, surfaces or the like

Item

Excluded
.

Site levelling, excavation, etc.

Site levelling, excavation; removal of topsoil, vegetation, etc.

Item

Disposal

m3

Bulk, or over-site, excavation including removing spoil

1.0
10.00

Item

$2,454.30

$2,454
In above
Nil
.

Filling, poor ground conditions, rock, blinding, piles, piers, underpinning, etc.

Poor ground conditions, rock, blinding concrete, filling, soft spots or the like

Note

Excluded

Screw piles, bored piers, underpinning & the like are assumed not required

Note

Excluded
.

Hazardous materials removal

Hazardous materials; asbestos, lead paint & the like, contaminated soil removal, etc.

Note

Excluded
.

Retaining walls

Retaining walls are assumed not required - none are shown

Note

Excluded
.

Sundries, bwic, etc.

Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.

Item

1.00%

In above
.

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 25 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

PAVING, FENCING, OUTBUILDINGS & LANDSCAPING, EXTERNAL SERVICES & Special Provisions

33 xr - 35 xb Roads, Footpaths, Paved Areas, Fencing, Gates & Outbuildings

Paving, parking and the like

External pavers installed (supply only pc@$30/m2)

m2

28.0

$113.31

$3,173

Allowance for courtyard paving, sub-base, fittings & the like

Item

Concrete slabs (structural) to last

m2

Concrete base / bedding to last

m2

10.0

$75.46

$755

Rock or other bedding to last

m2

18.0

$27.27

$491

Extra for plinths, steps, ramps & the like to last

Item

1.0

$327.24

$327

Concrete path, broomed finish

m2

4.2

$81.81

$344

Gravel paths

m2

Excluded
Nil

Nil
.

Crossover to local council requirements

m2

10.9

$128.09

$1,396

Reinforced concrete slab - driveway

m2

23.4

$142.49

$3,334
.

Existing paving, kerbs & other surfaces :

Make good existing paths, kerbs & other surfaces disturbed by works - allowance

Item

Work to existing roads, footpaths or paved areas external to the site

Item

1.0

$588.94

$589
Nil
.

Fencing and gates

Fencing and gates, allowance

Item

Existing to remain

Timber paling fence

19.0

$52.44

$996

Fence - other, allowance

6.0

$104.89

$629

Single hinged gate, allow (supply only @$400/ea)

No.

1.0

$740.50

$740

Allowance for other new and modified fences and gates

Item

Modify / make good existing fences disturbed by the works

Item

Assumed nil
1.0

$294.47

$294
.

Outbuildings, sheds, etc.

Sheds, carports & other outbuildings

Item

Excluded
.

Sundries, bwic, etc.

Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.

Item

In above
.

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 26 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

36 xl Landscaping and Improvements

Landscaping, planting, furniture and the like

Soft landscaping, planting, mulching, grassing, topsoils, planters, irrigation & watering, etc.

Note

Excluded / By Client

BBQ bench

Item

Nil

External furniture, seats, bike racks/storage, allowance

Item

Nil
.

Pergola

Timber pergola complete, allowance

m2

Concrete pads to pergola

m3

Other infills, battens or wire installed, say

Item

7.7

$490.86

$3,780
In above
Nil
.

Sundries, bwic, etc.

Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.

Item

In above
.

37 xk - 45 xx External Services & Supplies

External services

Existing stormwater & sewer drainage systems are assumed adequate to remain

Note

Existing to remain

Existing water & gas supplies, meters etc. are assumed adequate to remain

Note

Existing to remain
.

Inground services allowance - stormwater, sewer, water & gas

Item

65.1

$91.16

$5,934

Extra over for some larger pipes in ground

Item

Assumed nil

Pits & grated drains, pumps

Item

Excluded

Interceptor pits, grease traps, septic systems, grey & black water systems and the like

Item

Nil

Hosecocks, external

Item

2.0

In above
.

Water tanks :

Water tank, 5,000 litres (supply only @$850/each)

No.

1.0

$1,238.55

$1,239

Extra for pumps, filters, valves, connections, pipes and the like

Item

1.0

$3,200.74

$3,201

Power for pump

Item

1.0

$320.42

$320

Extra for stands, allow

Item

Bedding, paving below tanks

Item

Water tanks, in ground, allowance

Item

Sundries, builders work in connection with tanks

Item

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

Nil
4.0

$44.70

$179
Excluded

5.0%

$5,498.03

$275

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 27 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

External Electric Light and Power

Modifications to existing external power supply and meters - allowance

Item

Assumed nil

External power supply and meters - allowance

Item

Existing to remain

Modifications to existing telephone supply - allowance

Item

Excluded

Phone connection

Note

Excluded

Allowance for new or relocated existing overhead, underground or other power and the like

Note

Excluded

No allowance is included for new or relocating existing power-poles, street lights and the like

Note

Excluded

External lighting, bollards, etc. - allowance including reticulation

Item

1.0

$1,250.00

$1,250
.

External alterations and renovations, special services, etc.

It is assumed all existing services are in close proximity and are available & sufficient for use

Note

Assumed

Demolition, modifications and alterations to existing services

Item

Improvements and upgrades to existing inground services

Item

Excluded

Allowance for external special services

Item

Nil

Extra for rock in trenches and other obstructions

Item

Excluded

Crossing roads or under-road boring to access existing services

Item

Excluded

Services enclosures, & the like

Item

Assumed nil

Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.

Item

1.0

1.00%

$749.56

$750

In above
.

46 yy Special Provisions

Special Provisions

Staging of the works; Out of hours work; Accelerated program & the like

Item

Excluded

Client occupation of works areas

Item

Excluded

Site allowance, induction, site efficiencies, etc. are excluded

Item

Excluded
.

Sub-total - Nett cost

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

$633,125

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 28 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

BUILDER'S PRELIMINARIES

00 pr Preliminaries

Builders site costs & preliminaries

Site establishment:

Set-out of the construction works (Site survey is excluded - assumed already completed)

Item

1.1

$1,690.74

$1,860

Supply power, services, wc, offices, sheds, storage, hoists, minor plant & the like

Item

1.0

$1,418.04

$1,418

Security, fences, protection, tarps, supports, hoardings, screens, etc.

Note

In above

Signboard; Bank guarantee; Site Survey

Note

Excluded

Insurances, permits, fees, inspections, tests, notices & the like

Item

It is assumed that good trafficable access to the site is available

Note

1.20%

$7,598
Assumed
.

Scaffold, cranes & other access:

Scaffold, stairs, safety netting & the like, delivery, establishment / set up

m2

70.0

$54.54

$3,818

Scaffold, hire, incl. planks & safety netting

Weeks

21.3

$400.87

$8,518

Cranes & the like, delivery, establishment / set up, and hire

Item

1.0

$1,908.90

$1,909
.

On going costs, allowance:

Equipment & tools; deliveries; deposits; hoardings; security, hoists, plant; access, parking

Weeks

34.0

Safety; protection, first aid; contracts, documents; dis-establishment

Note

In above

Power, water, phone & other services; Offices, sheds, storage, amenities & consumables, pump

Note

In above

Sundries, access, minor items, b.w.i.c., scale, relocations, etc.

Note

In above

Minor items & access, hoisting etc., site bins & disposal, cleaner

Item

1.0

$327.24

$6,761.67

$11,126

$6,762
.

Site supervision & labour, builders attendance & overheads etc.:

Site supervisor

Weeks

Construction Manager, OH&S Officer, shop steward, other

Note

Site labourer

Weeks

Attendance & profit, administration, off-site expenses, finance, risk & the like

Item

34.0

$1,077.60

$36,638
In above

34.0

$195.15

$6,635
$55,690
.

Sub-total - Construction

$775,097
.

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 29 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

CONTINGENCIES AND ESCALATION

Contingencies and escalation allowances

Contingency & escalation allowances

Design contingency allowance

Item

4.50%

$34,900

Contract contingency allowance

Item

Excluded

Project contingency allowance

Note

Excluded
.

Escalation to commencement, nett allowance, by December 2015

Item

0.32%

$2,560

Escalation during construction

Note

Included

Additional cost escalation is excluded if project is delayed

Note

Excluded
.

Sub-total - Construction cost including escalation

$812,557
.

ITEMS BY THE CLIENT & DESIGN FEES

Items By The Client

Design, Documentation & Management Fees allowance, Other Allowances & Separate Contracts

Design, documentation and other fees allowance; soil & other tests

Note

Excluded

Loose furniture & fittings, small appliances & the like

Item

Excluded

Items by the client, separate contracts & minor miscellaneous costs

Item

Excluded

Temporary accommodation & relocation costs, disruption, display, sales costs & the like

Item

Excluded

Authority & headworks charges

Item

Excluded
.

Total, nett, Excluding GST


Goods & Services Tax

$812,557
Item

10.0%

$81,256
.

Total, gross, Including GST

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

$893,813

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 30 OF 31

Cost and Budget Plan

WWW.COSTPLANNER.COM.AU

Cost Plan Report 1/-, Schematic Design stage

SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015

Unit

sample only
Qty

Rate

Total

Explanations & further information

This report

Due to the nature of the documents provided, assumptions have been made in preparing this cost report.

This report is based on engaging a building company capable of maintaining multiple projects.

This report is based on engaging a building company employing on-site supervisors, and also with some off-site costs.

Due to the assumptions and inclusions made, potential project costs will not always match builders or sub-contractors' ball-park estimates.

Discussing costs with builders at this early stage is not normally recommended.

Contingencies

Projects may change - during design and documentation (and, even during construction) - having items and costs added.

To help manage & maintain the budget Contingency allowances are included for some of these unexpected costs.

A Design Contingency is included for minor changes during the development of the design and documents.

Items may change or be added (by necessity or request) and some items are yet to be confirmed, considered or fully investigated.

Though this contingency may not cover every possible circumstance or item on your wish list, it should not be deleted at this stage.

This contingency can be excluded when documentation is complete and all aspects of design and construction have been addressed.

A Contract Contingency may be included for minor changes, variations & unexpected costs during construction.

Generally

The contents of this report are Copyright and may not be copied in any form without express permission.

This document may not be reproduced whole or in part without the express permission of Construction Planning and Economics Pty Ltd.

It is assumed that correct professional confidentiality will be observed in relation to this document.

CONSTRUCTION PLANNING AND ECONOMICS PTY LTD

PO Box 50, Glenrowan, Vic 3675


.

THIS SAMPLE REPORT HAS BEEN PREPARED FOR GENERAL INFORMATION ONLY, AND ITS CONTENTS

ARE NOT SPECIFIC TO ANY PROJECT OR CIRCUMSTANCE.

sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM

(C) CONSTRUCTION PLANNING AND ECONOMICS PTY LTD | PAGE 31 OF 31

You might also like