Professional Documents
Culture Documents
sample only
Report
Stage
Date
.
project
SAMPLE HOUSE
123 Rose Avenue, North Melbourne
Alterations and additions to existing residence
Title
Address
Works
.
for
Architects
Client
Engineer
.
Cost Planner
printed
reference
.
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
sample only
Unit
Qty
Rate
Total
NOTES
This cost report has been prepared to help establish, review and manage a realistic project scope, budget and cost.
This cost report should be reviewed and revised as the documents, program & design progress, and prior to tendering & construction.
This is a measured approximate-quantities cost plan based on the information provided, and assumptions have been made.
Further design & documentation from the Architect & Structural Engineer is recommended.
Estimated cost
The cost of this project (including GST, but excluding design fees & other client costs) is estimated to be $810,000 to $894,000.
The lower figure above includes for some reduced allowances for Builder's supervision & overheads, and escalation & contingencies.
Summarised as follows:
$265,366
$183,993
Services
$110,119
$73,647
$141,972
$775,097
sub total
Escalation, contingencies, etc.
$37,460
Design fees
Excluded
sub total
$812,557
GST
$81,256
Total
$893,813
.
The scope of works is based on the following documents provided by Kelly Byrne Hart & Kelly Architects (received 20.09.2015 u.n.o.)
Architectural drawings
Architectural drawings
Architectural notes
Structural drawings
.
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
The report is based on the following assumed timetable. Delays in this timeframe may lead to cost increases.
Construction is assumed to commence by December, 2015 and to be completed by August, 2016.
Basis
This report is based on having the Tender and Contract Documentation completed and issued by the Architect.
It is assumed the Building Contract will be administered during construction by the Architect.
This report is based on competitive tendering and assumes fixed lump-sum quotes will be received from 3 to 4 builders.
It is assumed the project will be completed in one stage with the builder having full access of the unoccupied site.
This report is not a Tender Estimate or 'Quote' and should not be used for this purpose.
The content and purpose of this cost plan should be treated accordingly.
Exclusions
Costs for the following are excluded, which are either assumed to be provided separately by the client, or are not required.
Maintenance, refurbishment, repair & other works generally and to unaltered areas & surrounds etc.
Landscaping
Client occupation, completing the work in stages, out-of-hours work and/or an accelerated program
Non-traditional forms of procurement; or for the potential reduced competition by tendering to one builder only
All prices are 'installed' or 'supply & install' and exclude GST, unless noted otherwise.
No fixed price / firm trade quotations have been sought or received in preparing this report.
It is important that Tenderers provide a Trade Cost Summary in their quotes for review prior to acceptance.
The structural design is yet to be finalised, and assumptions have been made.
Further information regarding the ground conditions is required. Ground conditions are assumed to be stable.
It is assumed existing ground levels are generally acceptable and there is no requirement for cut or fill.
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
m2 BA
185.3
$/m2 BA
Total
.
Preliminaries
Preliminaries
00 PR
17.47%
$141,972
.
Floors
01 SU
7.62%
$334.16
$61,918
Staircases
04 SC
1.76%
$77.24
$14,311
Roof
05 RF
5.34%
$233.97
$43,353
Walls
0609WL
9.66%
$423.83
$78,533
0708WD
8.28%
$362.95
$67,251
1214FF
9.20%
$403.45
$74,756
15 FT
11.88%
$521.05
$96,546
16 SE
1.56%
$68.49
$12,691
.
Services
1718SP
5.52%
$242.15
$44,868
2124HC
4.43%
$194.45
$36,030
26 LP
3.60%
$157.71
$29,222
.
Alterations
Alterations & renovations
31 AR
3.23%
$141.51
$26,221
.
Site preparation
32 XP
2.06%
$16,706
3334R
1.70%
$13,792
36 XL
0.47%
$3,780
External services
3745X
1.62%
$13,147
.
Special Provisions
Special Provisions - escalation & contingencies, etc.
46 YY
4.61%
$37,460
.
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
100.00%
$812,557
10.00%
$81,256
$893,813
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
sample only
Unit
Qty
Rate
Total
Structure
$265,366
$183,993
Services
$110,119
Alterations
$26,221
Excluded
Excluded
$131,337
GST
Excluded
$717,037
.
m2
133.3
100.0%
133.3
m2
72.4
60.5%
43.8
m2
27.3
30.0%
8.2
m2
233.0
79.5%
185.3
= $/m2
$3,870
= Nett cost of the Building Works per square metre; excl. site costs, contingencies, escalation, fees, client costs & gst
Note: This is an analysis of the data prepared in the detailed cost plan.
These figures very simply summarise the findings in a $/m2 format so that an overall impression can be made of the cost.
They also offer a consistent format so that this project can be fairly compared to other similar projects.
Office use only - Construction Planning and Economics Pty Ltd data:
185.3
$585,700
$47,425
$141,972
$3,870
$717,037
7.5%
$58,060
Building works
m2
External works
Item
Item
4.8%
$37,460
GST
Item
10.0%
$81,256
Total
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
185.3
$893,813
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
Total
.
2.96%
$24,081
Repairs allowances
1.01%
$8,244
0.57%
$4,671
3.42%
$27,826
Structural steelwork
2.97%
$24,117
10.81%
$87,815
5.89%
$47,887
2.52%
$20,462
Plasterboard Linings
1.85%
$15,025
Windows
5.31%
$43,180
1.87%
$15,177
0.47%
$3,814
1.04%
$8,418
Painting
3.57%
$28,987
Polished finishes
1.52%
$12,388
Joinery Fittings
9.47%
$76,920
4.03%
$32,768
1.49%
$12,146
Sanitary fittings
2.39%
$19,408
4.51%
$36,616
4.16%
$33,830
Electrical
3.77%
$30,632
0.34%
$2,723
1.21%
$9,819
0.76%
$6,172
1.75%
$14,245
15.72%
$127,727
4.30%
$34,900
Excluded
0.32%
$2,560
Excluded
.
100.00%
$812,557
10.00%
$81,256
$893,813
.
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
QUANTITIES
BUILDING AREAS
m2
195.3
Existing areas
m2
62.0
m2
62.0
Proposed Areas
m2
133.3
m2
80.1
m2
53.2
m2
73.6
m2
61.0
m2
8.6
m2
4.0
OTHER AREAS
m2
299.0
m2
15.8
m2
11.5
m2
10.4
Site area
m2
261.3
m2
231.5
m2
80.1
m2
15.8
m2
62.0
m2
10.4
Upper floor area - new structure - timber - stair & voids deducted
m2
51.7
m2
11.5
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
m2
165.1
m2
34.9
m2
57.0
m2
73.2
m2
347.5
m2
55.8
m2
34.9
m2
61.4
m2
44.3
m2
58.9
m2
5.2
m2
71.1
m2
3.9
m2
12.0
m2
157.0
m2
87.5
Masonry
m2
15.2
Glazed screen
m2
Nil
m2
54.3
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
Concrete work
Ground floors:
120mm Concrete slab on ground
including reinforcement, sand, membrane, monolithic finish, joints, insulation, etc.
m2
80.1
$295.87
$23,699
Note
Item
m3
m3
5.40
In above
m3
8.90
In above
m3
23.9
In above
m3
1.5
8.0
In above
Nil
$411.78
$618
.
m3
4.5
$779.79
$3,509
Item
Excluded
Item
Assumed nil
.
Upper floors:
Suspended concrete slab; reinforcement, formwork, mono, joints, insulation, etc.
m2
Nil
.
Timber ground floor framing, stumps, pads, bearers, joists, insulation, etc.
m2
Existing to remain
m2
51.7
$104.72
$5,414
m2
3.0
$46.26
$139
m2
3.0
$31.10
$93
.
m2
m2
m2
27.5
$24.27
Nil
14.2
$82.04
Floor boards:
$1,165
.
m2
m2
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
$667
75.5
$138.47
$10,454
Excluded
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
m2
Battens, packers or barriers to framing or slab for floor boards & the like
m2
m2
m2
Excluded
10.0
$35.28
$353
Nil
75.5
$65.39
$4,937
.
Timber ground floor framing, stumps, pads, bearers, joists, etc. - external decks & steps
m2
15.8
$121.22
$1,915
m2
11.5
$86.99
$1,000
m2
11.5
$90.40
$1,040
m2
11.5
$26.78
$308
m2
11.5
$154.08
$1,772
m2
27.3
$116.46
$3,179
m2
11.5
$28.42
$327
Perimeter plinths
11.7
$28.22
$330
Item
1.0
$189.40
$189
m2
30.8
$25.96
$800
.
Existing floors
Prepare, make good or modify existing timber floor linings & framing for new works
m2
Footings, slabs, pads, floor structure & the like; make good or modifications allow
m2
72.4
$61.08
$4,423
In above
.
m2
10.4
$15.13
$157
m2
10.4
m2
Excluded
Item
Excluded
m2
Modify existing timber floors for shower setdowns or strengthen floor for bath
Item
Assumed nil
Nil
1.0
$283.79
$284
.
m2
91.9
$119.17
$10,952
m2
84.5
$22.66
$1,916
m3
m2
5.7
$50.69
$289
m2
5.7
$31.10
$177
In above
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
m2
96.6
$64.36
$6,218
Metal roof cladding fixed to timber framing (supply only @$60/m2), long span / shallow
m2
Excluded
Membrane roofing
m2
Nil
Folded seam composite roof cladding & plumbing including ply substrate, pc allowance
m2
Excluded
.
Item
229.6
$30.09
$6,910
Assumed nil
Note
Nil
.
No.
2.0
$1,852.31
$3,705
No.
1.0
$1,532.40
$1,532
m2
Item
Item
1.0
$179.84
$180
m2
7.2
$123.40
$888
Plasterboard rooflight shaft, & the like linings including edge treatments, cornices etc.
m2
7.2
$54.31
$391
m2
7.2
$31.54
$227
Nil
Assumed nil
Beams, alterations, making good etc. existing roofing & framing after demolition, allowance
m2
73.2
$16.36
$1,198
m2
73.2
$20.45
$1,497
Note
Minor repairs & alterations to existing roofing & roof plumbing to remain, allowance
Item
Existing to remain
76.9
$27.27
$2,096
.
Structural steel framing, bolts, grout & levelling, primed surface treatment
1.64
$8,699.13
$14,238
0.87
$9,326.34
$8,071
0.08
$13,907.70
$1,113
Note
Item
Welding, cranage, access; inspections; samples, temporary works; shop drawings, etc.
Note
m2
Item
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
Assumed nil
Generally nil
0.08
$1,055.26
$84
In above
Nil
Excluded
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
m2
Nil
.
Item
1.0
$7,744.68
$7,745
Item
3.6
$432.85
$1,558
Item
8.5
$589.20
$5,008
.
Item
7.0
$166.04
$1,162
Item
157.9
$13.76
$2,173
Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.
Item
In above
.
m2
88.6
$128.73
$11,405
m2
15.2
$128.73
$1,957
110mm Skin of veneer, solid or cavity external wall, faced (supply only @$1,350/thou)
m2
157.7
$194.75
$30,713
110mm Glazed skin of veneer, solid or cavity external wall, faced (supply only @$3,840/thou)
m2
m2
7.8
$175.23
$1,367
Masonry work in preparing and filling openings, repairs & the like - allowance
Item
1.0
$1,283.25
$1,283
Note
Excluded
Nil
.
m2
Nil
.
m2
78.1
$28.91
$2,257
m2
78.1
$22.02
$1,719
m2
Timber skirting installed (supply only @$4/m) - to new walls & linings
Nil
46.5
$11.38
$529
.
External timber stud framed wall, 90mm, with insulation & sisalation
m2
m2
m2
105.7
$25.12
$2,655
m2
87.5
$60.81
$5,321
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
90.7
$80.65
$7,315
Nil
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
Item
Nil
.
Timber or other external sheet wall linings, installed (supply only @$60/m2)
m2
40.8
$142.05
$5,796
m2
74.0
$16.43
$1,216
m2
48.2
$31.10
$1,499
m2
15.0
$99.31
$1,490
m2
Nil
m2
Nil
Extra for battens, packers or the like - for cladding fixed vertically & the like
m2
Nil
55.8
$18.00
$1,004
.
m2
261.2
$23.94
$6,252
m2
m2
45.6
$7.30
$333
m2
261.2
$22.02
$5,750
Timber skirting installed (supply only @$4/m) - to new walls & linings
87.1
$11.38
$990
Assumed nil
Note
Assumed nil
.
Alterations & making good to existing walls after demolition & new works etc., allow
Item
Structural steel framing in existing walls, new openings & the like, allowance
1.0
$1,636.20
$1,636
Assumed nil
External walls :
Patching, repairs & making good to external wall surfaces & structure to remain, allow
m2
m2
71.1
$20.43
$1,452
Excluded
m2
54.3
$7.29
$396
Patching, repairs & making good to internal wall surfaces / finishes to remain, allow
m2
172.6
$10.98
$1,896
m2
20.0
$35.48
$710
Paint :
m2
71.1
$28.52
$2,028
m2
20.0
$22.02
$440
m2
152.6
$22.02
$3,359
Timber skirting installed (supply only @$4/m) - to new & existing wall linings
32.1
$11.38
$365
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.
Item
1.00%
In above
.
Ground floor windows, in new walls (supply only @$487/m2), timber, glazed
m2
32.1
$663.30
$21,292
First floor windows, in new walls (supply only @$479/m2), timber, glazed
m2
26.8
$653.30
$17,508
Ground & first floor windows, in new walls (supply only @$1,000/m2), steel, glazed
m2
m2
m2
Note
No.
Nil
m2
In above
m2
In above
Excluded
5.2
$707.66
$3,680
Assumed nil
In above
Handle sets, plates, pulls, etc. & lock to glazed door (supply only @$180/each, combined)
No.
5.0
$326.91
$1,635
Seals, closers, grilles, kickplates, indicators, bolts, signage & the like
Note
m2
64.1
$26.21
$1,680
Architraves, reveals, trims, sills, flashings, pelmets etc., installed, to new windows
m2
64.1
$27.25
$1,747
m2
128.2
$29.54
$3,787
Nil
Allowance for repairs & making good to existing windows / glazed screens to remain
m2
12.0
$58.36
$700
m2
12.0
$17.47
$210
Architraves, reveals, trims, sills, flashings, pelmets etc., installed, to existing windows
m2
m2
Existing to remain
24.0
$25.99
$624
.
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
Note
Nil
.
Note
Excluded / By Client
.
No.
1.0
$232.34
$232
No.
1.0
$359.69
$360
Note
12.6
$70.08
$883
Handle sets, plates, pulls, etc. & lock to external door (supply only @$200/each combined)
No.
2.0
$363.24
$726
No.
2.0
$212.44
$425
Nil
Existing doors :
Existing external doors & frames to remain - allow for minor repairs / alterations only
Item
1.0
$58.63
$59
Item
1.0
$117.26
$117
No.
1.0
$212.44
$212
.
No.
5.0
$144.26
$721
Single hinged internal hollow core door, standard (supply only @$25/each)
No.
1.0
$108.43
$108
Single pivot internal door (supply only @$500/each door & pivot mechanism)
No.
2.0
$873.69
$1,747
Single sliding internal door & track (supply only @$300/each; door & track)
No.
2.0
$550.58
$1,101
Single large sliding internal door & track (supply only @$600/each; door & track)
No.
Nil
54.0
$54.92
$2,966
.
Handle sets, plates, pulls, etc. to internal hinged door (supply only @$125/each)
No.
8.0
$203.06
$1,625
Handle sets, plates, pulls, etc. to internal sliding door (supply only @$80/each)
No.
2.0
$151.62
$303
Seals, closers, grilles, kickplates, indicators, bolts, signage & the like
Note
No.
Nil
10.0
$199.94
$1,999
.
Existing doors :
Existing internal doors & frames to remain - allow for minor repairs / alterations only
Item
Item
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
4.0
$175.89
$704
Nil
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
No.
4.0
$199.94
$800
.
No.
Nil
.
Garage doors, operable walls, roller grilles, partitions & other items
Garage doors
Note
None shown
Allow
Nil
.
Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.
Item
1.00%
In above
.
FINISHES
m2
38.0
$120.24
$4,569
.
Floor tiles installed, incl. joints, sealers, etc. (supply only @$50/m2), wet areas
m2
14.2
$131.86
$1,872
Stone or other floor tiles installed, incl. joints, sealers, etc. (supply only @$75/m2)
m2
6.0
$160.90
$965
m2
14.2
$71.20
$1,011
Note
Nil
.
m2
27.5
$75.52
$2,077
Vinyl, linoleum, rubber or similar flooring installed (supply only @$50/m2), allowance
m2
5.0
$84.18
$421
.
m2
146.6
$32.21
$4,723
Plasterboard bulkhead & the like linings including edge treatments, cornices etc.
m2
5.0
$54.31
$272
m2
Excluded
Extra for special cornices, roses, bulkheads, pelmets, coffers & the like
m2
Assumed nil
m2
Nil
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
m2
151.6
$25.04
$3,797
.
Existing ceilings :
Make good to existing ceiling finishes & cornices to remain due to demolition & new work, allow
Item
38.9
$10.81
$420
m2
38.9
$21.47
$835
.
Ply, timber & other wall, floor & ceiling linings / finishes & sundries
m2
Other plywood, timber, laminate, vinyl & other 'decorative' wall & acoustic linings
m2
m2
Ply, timber, laminate & other 'decorative' ceiling & acoustic linings / finishes (supply only @$50/m2)
m2
15.0
$87.74
$1,316
Nil
15.0
$22.02
$330
Assumed nil
.
m2
59.2
m2
Nil
Concrete plinths, tactile indicators, door mats & surrounds, & the like
Note
Nil
Item
Note
Sundries, trims, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.
Item
3.0
$125.86
$1,188.88
$7,451
$3,567
Assumed
1.00%
$36,343.74
$363
.
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
Joinery fittings
Kitchen:
Allowance for kitchen & pantry joinery complete
Item
1.0
Item
5.4
Item
$32,571.35
$32,571
In above
Nil
.
Bath:
Bathroom & ensuite joinery complete
Extra for stone, glass, concrete or similar benchtops / splashbacks
Item
1.0
Item
2.1
$7,879.16
$7,879
In above
.
Laundry:
Laundry joinery complete
Extra for stone, glass, concrete or similar benchtops / splashbacks
Item
1.0
$5,103.45
Item
$5,103
Nil
.
Other areas:
m2
11.2
$907.28
$10,162
m2
7.3
$850.58
$6,209
Seat, upholstered
1.8
TV joinery unit
1.6
$2,381.61
$3,811
3.4
$1,445.98
$4,916
Item
1.0
$4,000.00
$4,000
Item
1.0
$2,268.20
$2,268
Excluded
Assumed loose
Nil
Item
Item
Assumed nil
Item
Excluded
1.0
Excluded
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
m2
9.0
$301.06
$2,710
No.
3.0
$81.23
$244
No.
2.0
$1,611.18
$3,222
No.
1.0
$575.48
$575
No.
1.0
$143.87
$144
No.
2.0
$431.61
$863
No.
1.0
$143.87
$144
No.
Nil
No.
Assumed nil
.
Allowance for external canopies, including all framing & finishing - rear
Item
1.0
$1,908.90
$1,909
Allowance for external vertical screens, including all framing & finishing
m2
15.0
$463.59
$6,954
Motorised awning
Note
Excluded / By Client
Item
Assumed nil
0.05
$13,907.70
$695
.
m2
195.3
$2.18
$426
Item
No.
1.0
$527.09
$527
No.
1.0
$196.34
$196
No.
1.0
$542.45
$542
Allowance for other fittings, joinery, metalwork, sundries & the like
m2
Item
By Client
Assumed nil
Nil
.
Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.
Item
1.00%
In above
.
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
No.
1.0
$3,307.85
$3,308
No.
1.0
$1,960.71
$1,961
No.
1.0
$1,364.86
$1,365
No.
1.0
$545.26
$545
No.
1.0
$1,775.28
$1,775
No.
No.
1.0
$2,341.13
$2,341
No.
1.0
$1,111.25
$1,111
No.
No.
1.0
$59.99
$60
No.
1.0
$119.99
$120
No.
1.0
$104.99
$105
Nil
Excluded
No.
1.0
$1,333.78
$1,334
.
Wall basin, tapsets / mixer & bottletrap (supply only @$975/each combined, with waste)
No.
2.0
$1,389.68
$2,779
Vanity basin & tapsets / mixer (supply only @$700/each combined, with waste)
No.
2.0
$925.82
$1,852
Laundry trough & tapsets / mixer (supply only @$475/each combined, with waste)
No.
1.0
$668.12
$668
.
No.
3.0
$1,454.85
$4,365
.
Bath tub & tapsets / mixer / spout (supply only @$2,200/each combined, with waste)
No.
1.0
$2,799.81
$2,800
Item
1.0
$215.98
$216
No.
1.0
$679.57
$680
No.
2.0
$694.24
$1,388
Shower trench
2.0
$520.86
$1,042
No.
Insinkerator; boiling / chilled water unit; drinking fountain & the like
Note
2.0
$287.97
$576
Nil
.
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
No.
1.0
$1,925.26
$1,925
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
No.
Nil
.
Sanitary plumbing, reticulation, water, gas, waste & sundries to plumbing, fixtures & equipment:
Plumbing fixtures, hot & cold water, sewer / waste & vents reticulation
Item
22.0
$1,147.43
Item
$25,244
Assumed nil
.
Heating
Item
Item
Nil
1.0
$20,179.80
m2
$20,180
Nil
.
No.
1.0
$5,650.34
$5,650
No.
1.0
$152.17
$152
Item
1.0
$1,090.80
$1,091
Item
Excluded
.
Item
Nil
.
Air Conditioning
Item
Item
2.0
$4,000.00
$8,000
Excluded
.
Item
Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.
Item
Nil
2.50%
$38,257.75
$956
.
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
Item
Item
Item
Item
Item
181.0
1.0
In above
Excluded
47.0
No.
No.
2.0
Item
39.0
$3,731
Excluded
Uplight points
Power points
$20.62
$185.96
$8,740
Nil
In above
$146.28
No.
$5,705
Nil
.
TV antenna alterations
Item
1.0
$199.95
$200
No.
6.0
$183.20
$1,099
Smoke detector
No.
2.0
$144.29
$289
Intercom, allowance
Item
Nil
.
Item
1.0
$1,800.30
$1,800
No.
Nil
No.
Nil
.
Note
Excluded
Control systems, Uninterrupted power supply (UPS), generators and the like
Note
Excluded
Item
Nil
Cabling & wiring for computers, data, Pay TV, stereos, etc., allowance
Item
Excluded
Hub, allowance
Item
Nil
.
Solar Power
Solar power installed, pc allowance
Item
Excluded
.
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
Item
1.0
$6,000.00
$6,000
Downlights, wall lights, feature lights, LEDs, externals, & the like
Item
Uplights
No.
Pendant lights
Item
By Client
External fittings
No.
In above
Note
Nil
Note
By Client
In above
Nil
Ceiling 'sweep' fans and the like, installed (supply only @$400/each)
No.
2.0
$672.80
$1,346
.
Note
Excluded
Communications, data; WAP; audio visual equipment; automation systems; ducted vacuum & the like
Note
Excluded
Note
Excluded
.
Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.
Item
1.00%
$31,245.13
$312
.
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
PREPARATION
Internal demolition & removal works allowance & remove the following:
Item
62.0
$16.81
$1,042
Item
1.0
$1,024.27
$1,024
Item
72.0
$28.44
$2,047
Item
86.7
$30.35
$2,630
Doors, frames, joinery, stairs, sanitary fittings, whitegoods, services & the like
Item
14.0
$84.61
$1,185
Item
43.0
$22.36
$961
.
Item
0.4
$10,508.00
Item
$3,993
In above
.
Item
Interface works: preparing, levelling, straightening, propping, bracing, & supports etc. allow
Item
Assumed nil
1.0
$1,155.88
$1,156
.
Repairs, making good & the like, allowances to the existing building, etc.
Item
1.0
$2,500.00
$2,500
Item
1.0
$2,000.00
$2,000
Structural & other repairs to existing footings, floors, walls, roof, etc
Item
Assumed nil
Repairs & making good to faade, verandah etc. & restoration of period features, cappings, etc.
Item
Excluded
Item
Nil
Item
Excluded
Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.
Item
1.00%
In above
.
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
32 xp Site Preparation
Clearance:
External site preparation & clearance, minor demolition, removals, excavation & other costs
Item
1.0
$1,894.07
$1,894
Demolition:
m2
61.0
$127.79
$7,795
Demolish shed
m2
4.0
$43.21
$173
Item
Assumed nil
Remove driveways, paving, fences, gates, decks, landscaping & the like, allowance
Item
1.0
$2,216.98
$2,217
m2
In below
No.
Excluded
Item
Assumed nil
Adjacent buildings:
Repairs & making good, etc. to adjacent buildings, structures, fittings, surfaces or the like
Item
Excluded
.
Item
Disposal
m3
1.0
10.00
Item
$2,454.30
$2,454
In above
Nil
.
Filling, poor ground conditions, rock, blinding, piles, piers, underpinning, etc.
Poor ground conditions, rock, blinding concrete, filling, soft spots or the like
Note
Excluded
Screw piles, bored piers, underpinning & the like are assumed not required
Note
Excluded
.
Hazardous materials; asbestos, lead paint & the like, contaminated soil removal, etc.
Note
Excluded
.
Retaining walls
Note
Excluded
.
Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.
Item
1.00%
In above
.
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
PAVING, FENCING, OUTBUILDINGS & LANDSCAPING, EXTERNAL SERVICES & Special Provisions
m2
28.0
$113.31
$3,173
Item
m2
m2
10.0
$75.46
$755
m2
18.0
$27.27
$491
Item
1.0
$327.24
$327
m2
4.2
$81.81
$344
Gravel paths
m2
Excluded
Nil
Nil
.
m2
10.9
$128.09
$1,396
m2
23.4
$142.49
$3,334
.
Make good existing paths, kerbs & other surfaces disturbed by works - allowance
Item
Item
1.0
$588.94
$589
Nil
.
Item
Existing to remain
19.0
$52.44
$996
6.0
$104.89
$629
No.
1.0
$740.50
$740
Item
Item
Assumed nil
1.0
$294.47
$294
.
Item
Excluded
.
Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.
Item
In above
.
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
Soft landscaping, planting, mulching, grassing, topsoils, planters, irrigation & watering, etc.
Note
Excluded / By Client
BBQ bench
Item
Nil
Item
Nil
.
Pergola
m2
m3
Item
7.7
$490.86
$3,780
In above
Nil
.
Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.
Item
In above
.
External services
Existing stormwater & sewer drainage systems are assumed adequate to remain
Note
Existing to remain
Existing water & gas supplies, meters etc. are assumed adequate to remain
Note
Existing to remain
.
Item
65.1
$91.16
$5,934
Item
Assumed nil
Item
Excluded
Interceptor pits, grease traps, septic systems, grey & black water systems and the like
Item
Nil
Hosecocks, external
Item
2.0
In above
.
Water tanks :
No.
1.0
$1,238.55
$1,239
Extra for pumps, filters, valves, connections, pipes and the like
Item
1.0
$3,200.74
$3,201
Item
1.0
$320.42
$320
Item
Item
Item
Item
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
Nil
4.0
$44.70
$179
Excluded
5.0%
$5,498.03
$275
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
Item
Assumed nil
Item
Existing to remain
Item
Excluded
Phone connection
Note
Excluded
Allowance for new or relocated existing overhead, underground or other power and the like
Note
Excluded
No allowance is included for new or relocating existing power-poles, street lights and the like
Note
Excluded
Item
1.0
$1,250.00
$1,250
.
It is assumed all existing services are in close proximity and are available & sufficient for use
Note
Assumed
Item
Item
Excluded
Item
Nil
Item
Excluded
Item
Excluded
Item
Assumed nil
Sundries, misc. & temporary works, samples, prototypes, BWIC, access, scaffold, deliveries etc.
Item
1.0
1.00%
$749.56
$750
In above
.
46 yy Special Provisions
Special Provisions
Staging of the works; Out of hours work; Accelerated program & the like
Item
Excluded
Item
Excluded
Item
Excluded
.
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
$633,125
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
BUILDER'S PRELIMINARIES
00 pr Preliminaries
Site establishment:
Set-out of the construction works (Site survey is excluded - assumed already completed)
Item
1.1
$1,690.74
$1,860
Supply power, services, wc, offices, sheds, storage, hoists, minor plant & the like
Item
1.0
$1,418.04
$1,418
Note
In above
Note
Excluded
Item
Note
1.20%
$7,598
Assumed
.
Scaffold, stairs, safety netting & the like, delivery, establishment / set up
m2
70.0
$54.54
$3,818
Weeks
21.3
$400.87
$8,518
Cranes & the like, delivery, establishment / set up, and hire
Item
1.0
$1,908.90
$1,909
.
Equipment & tools; deliveries; deposits; hoardings; security, hoists, plant; access, parking
Weeks
34.0
Note
In above
Power, water, phone & other services; Offices, sheds, storage, amenities & consumables, pump
Note
In above
Note
In above
Minor items & access, hoisting etc., site bins & disposal, cleaner
Item
1.0
$327.24
$6,761.67
$11,126
$6,762
.
Site supervisor
Weeks
Note
Site labourer
Weeks
Attendance & profit, administration, off-site expenses, finance, risk & the like
Item
34.0
$1,077.60
$36,638
In above
34.0
$195.15
$6,635
$55,690
.
Sub-total - Construction
$775,097
.
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
Item
4.50%
$34,900
Item
Excluded
Note
Excluded
.
Item
0.32%
$2,560
Note
Included
Note
Excluded
.
$812,557
.
Design, Documentation & Management Fees allowance, Other Allowances & Separate Contracts
Design, documentation and other fees allowance; soil & other tests
Note
Excluded
Item
Excluded
Item
Excluded
Temporary accommodation & relocation costs, disruption, display, sales costs & the like
Item
Excluded
Item
Excluded
.
$812,557
Item
10.0%
$81,256
.
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM
$893,813
WWW.COSTPLANNER.COM.AU
SAMPLE HOUSE, 123 Rose Avenue, North Melbourne - Alterations and additions to existing residence
Monday, 5 October 2015
Unit
sample only
Qty
Rate
Total
This report
Due to the nature of the documents provided, assumptions have been made in preparing this cost report.
This report is based on engaging a building company capable of maintaining multiple projects.
This report is based on engaging a building company employing on-site supervisors, and also with some off-site costs.
Due to the assumptions and inclusions made, potential project costs will not always match builders or sub-contractors' ball-park estimates.
Discussing costs with builders at this early stage is not normally recommended.
Contingencies
Projects may change - during design and documentation (and, even during construction) - having items and costs added.
To help manage & maintain the budget Contingency allowances are included for some of these unexpected costs.
A Design Contingency is included for minor changes during the development of the design and documents.
Items may change or be added (by necessity or request) and some items are yet to be confirmed, considered or fully investigated.
Though this contingency may not cover every possible circumstance or item on your wish list, it should not be deleted at this stage.
This contingency can be excluded when documentation is complete and all aspects of design and construction have been addressed.
A Contract Contingency may be included for minor changes, variations & unexpected costs during construction.
Generally
The contents of this report are Copyright and may not be copied in any form without express permission.
This document may not be reproduced whole or in part without the express permission of Construction Planning and Economics Pty Ltd.
It is assumed that correct professional confidentiality will be observed in relation to this document.
THIS SAMPLE REPORT HAS BEEN PREPARED FOR GENERAL INFORMATION ONLY, AND ITS CONTENTS
sample residential schematic cost plan report october2015.xlsx cost plan 5/10/2015 4:08 PM