Professional Documents
Culture Documents
SHIPBUILDING DIVISION
INDEX
S. No.
Description
SURFACE PREPARATION
Page Nos.
3 - 11
Abrasive Blasting
Vacuum Blasting
Power Tooling
Dust removal
10
10
11
10
12
10
PAINTING
11 - 16
Spraying Method
11
Manual Method
12
Stripe Coats
12
Feathering
13
Paint Application
13
Maintenance Painting
15
SAFETY
16 - 18
Material Safety
16
Equipment Safety
17
Personal Safety
17
18
Fire Hazards
18
Paint Shop
Page 1
of 29
S. No.
SHIPBUILDING DIVISION
Description
Page Nos.
QUALITY ASSURANCE
19 - 19
20 - 20
21 26
Man
21
Machine
23
Material
24
25
Services
25
SUPPLIER INFORMATION
27 - 27
APPENDIX
28 - 29
Appendix A
28
Appendix B
29
Paint Shop
Page 2
of 29
SHIPBUILDING DIVISION
SCOPE OF REQUIREMENT
1. Following are the minimum requirements, but not limited to, for Blasting and
Painting of the ships being built at MDL.
2. The intention of this Scope of Work is that all labour, material, equipment,
and other items necessary for the proper execution and completion of the
Work are included in the scope of contractor, except for any items expressly
identified as MDL Supply.
3. All work and services required for the administration of the Project shall be in
the scope of the Contractor.
4. Scope of Requirement is not intended to enumerate each and every item of
Work required. Words which have well-known technical or trade meanings
are used in the Contract in accordance with such recognized meanings.
Surface Preparation
1. Abrasive Blasting(Chilled Iron/Steel grit/Copper Slag)
i.
ii. The abrasives must be of good quality, should be hard and dry, free of
foreign matters and non-contaminated. There should be no soft sand, soft
particles and the like.
Paint Shop
Page 3
of 29
SHIPBUILDING DIVISION
Paint Shop
Page 4
of 29
SHIPBUILDING DIVISION
2. Vacuum Blasting
i. Vacuum blasting is less dusty and less likely to contaminate adjacent areas
than open nozzle abrasive blasting. Hence where ever machineries and
equipments have already been installed prior to painting, Vacuum Blasting
may be necessarily required to be done. Similarly weather decks where
openings to lower & upper decks, drain holes, vents etc. are present may
be required to be vaccum blasted to Sa2 standard.
ii. Abrasive quality should be hard and non-contaminated. There should be
no soft sand.
iii. Abrasive size distribution must be 0.2-1.1 mm for general work unless
specified otherwise.
3. Power Tooling
i.
Power tool cleaning to bare metal shall include removal of all rust, loose
mill scale, and paint to bare metal by chipping, scraping, sanding or wire
brushing. A minimum of a onemil profile is required.
ii. Chipping hammers, deck crawlers, needle guns, and wire brushes must be
used to remove tight corrosion, mill scale, and old paint from large
metallic areas.
iii. Wire brushes (cup or radial) are to be used to remove loose mill scale, old
paint, weld flux, slag, and dirt deposits.
iv. Grinders and sanders are to be used to smooth excessively rough surfaces.
v. Pneumatic power tools are to be used preferably (Grinders, Disc Sander
and Wire Brush)
vi. Electrical power tools, if must be used, should work at 110 V only.
vii. Compressed air must be free from oil and water.
viii. Wire brush must not polish the surface, hence worn out ones must not be
used.
ix. Care shall be exercised with power impact and grinding tools so they do
not cut too deeply into the surface, resulting in burrs that are difficult to
cover and protect satisfactorily.
Blasting and Painting
Paint Shop
Page 5
of 29
SHIPBUILDING DIVISION
4. Dust Removal
i.
ii. Dust may spoil the machines and equipments in its surroundings, hence
covering of machines must be ensured by the contractor to prevent
damages by dust during cleaning, blasting and painting.
iii. Removal of dust must be undertaken by
(a) Industrial Vacuum cleaners fitted with brushes.
(b) Clean bristle brush.
(c) Blowing with dry, clean compressed air.
iv. To establish whether dust has been sufficiently removed, transparent
adhesive tape must be used in which very small amount of dust should
remain.
v. No separate rate for removal of dust shall be given. Dust removal is to be
undertaken as a standard practice in each of the above dust generating
surface preparation methods and especially before painting.
5. Removal of Oil and Grease
i.
Oil and grease must be removed from the surface with Labolene solution,
method of preparation of which is given in Appendix A.
ii. Use only solvent cleaning on small areas and never on painted surface.
(a) Prior to solvent cleaning, remove any heavy deposits of oil, grease,
etc., with a scraper.
(b) Remove remaining oil, grease, etc., by wiping/scrubbing the surface
with rags or brushes wetted with solvent.
(c) It is important that the final wash/rinse be made with clean
rags/brushes and solvent so that a film of oil/grease, etc., wont be left
on the surface when the solvent evaporates.
iii. Rags must be changed regularly so that only clean rags are used.
iv. If water forms droplets, there is still oil/grease on the surface and hence
repeat the cleaning procedure.
v. The water must run-off in puddles.
Blasting and Painting
Paint Shop
Page 6
of 29
SHIPBUILDING DIVISION
340-680 bar/5,000-10,000psi.
Paint Shop
Page 7
of 29
SHIPBUILDING DIVISION
All sharp edges, weld splatter, etc. on the steel structure is to be rounded
off prior to abrasive blasting as a preparation for the application of Heavyduty paint coatings.
ii. All surfaces where abrasive blasting and heavy-duty paint is not required
are first to be thoroughly cleaned of all dirt, oil, grease and other foreign
matters by thoroughly washing with labolene solution, scrubbing with
short bristle brushes followed by rinsing with clean fresh water and then
dried.
iii. The steel surfaces are to be abrasive blast cleaned to Sa2 of Swedish
standards using chilled iron/steel grits conforming to DS Cat NO.
5350-000139 and 5350-000140 to produce a blast cleaned surface profile
of 50 to 75 microns.
iv. After the abrasive blasting has been carried out to the required standard,
the surfaces are to be thoroughly cleaned of all dust arising and spent
Blasting and Painting
Paint Shop
Page 8
of 29
SHIPBUILDING DIVISION
abrasive using suitable industrial type vacuum cleaner fitted with brush
attachment to ensure that the arising are removed before applying the
specified paint system.
v. Once cleaned, the surfaces are not to be allowed to oxidise or become
contaminated in any way prior to the application of the specified paint
system.
9. Internal Underwater Areas and Tanks
Machinery Bilges, Void Spaces, and Ballast Tanks
Internal tanks for Fresh Water, AVGAS/AVCAT, Diesel Oil, Water
Compensated Diesel Oil, FFO, Hydraulic oil, Acid store, Battery Charging
Room (except Battery Pits), Oil Drains and Oil Sullage.
i.
The surface preparation for application of the paint scheme on the steel
substrate except Machinery Bilges shall be Sa2 conforming to Swedish
Standards. However, the surface preparation standard shall be St3 for
Machinery Bilges.
ii. For Sa2 standards, the steel surfaces are to be vacuum/abrasive blasted
using chilled iron/steel grits (DS Cat No. 5350-000139 or 5350-000140) to
produce a blast cleaned surface profile of 50 to 75 microns. For St3
standards, the steel substrates are to be prepared using power tools/wire
brushing.
iii. After the abrasive blasting has been carried out to the requisite standard,
the surfaces are to be thoroughly cleaned of all dust arising due to spent
abrasive by means of suitable compressed air.
iv. For Tanks-steel work, All sharp edges to be broken or rounded off. Holes in
welding seams, undercuts, etc. may necessiate extra stripe coating or
filling. All loose and dense weld splatters to be removed.
10. External Underwater Areas(Steel Substrate)
i.
Paint Shop
Page 9
of 29
SHIPBUILDING DIVISION
Paint Shop
Page 10
of 29
SHIPBUILDING DIVISION
Paint Shop
Page 11
of 29
SHIPBUILDING DIVISION
viii. The finished coating must be applied homogeneously and as close to the
specifications as possible. Care must be taken to avoid exaggerated film
thickness.
ix. Great care must be taken to cover edges, openings, rear sides of stiffeners
etc. even though these areas must also be stripe coated.
x. Wet film thickness shall be regularly checked and recorded during paint
application.
xi. Both during and following the application of paint, all operatives entering
the confines of coated tanks/compartments/passage/decks must wear
soft-soled shoes or overshoes.
2. Manual Method
i.
ii. A good quality brush must be used for stripe coating on welding seams, on
all edges before application of full coats with airless spray.
iii. Rollers should only be used for applying a cosmetic coat on an already well
protected surface.
iv. If Rollers must be used for application of primer or intermediate coats,
apply evenly without 'stretching' the paint.
v. Several (2-4) coats may be necessary to substitute one coat applied by
spray.
vi. Special attention must be paid to areas difficult to reach and coat. These
include all edges, welding seams, corrugated areas, behind bulb angles,
behind hand rails, mouse holes, underside of coamings, etc. etc. Stripe
coating and extra coats on such spots are a must.
3. Stripe Coats
i.
Stripe Coats are to be applied by brush or roller depending upon items and
or area concerned.
Paint Shop
Page 12
of 29
SHIPBUILDING DIVISION
ii. The stripe coat must be applied as a coherent film showing good film
formation and no visible defects such as pores or un-wetted areas.
iii. The coating should be applied as a regular film without excessive
brush/roller marks in order to avoid cratering by entrapped air.
iv. Typical areas where stripe coats must be applied include :
(a) Behind bars
(b) Plate edges
(c) Cut outs i.e. Scallops, manholes etc.
(d) Welds
(e) Areas of difficult access
(f) ladders and hand rails
(g) small fitments of difficult configuration
(h) areas
(i) etc. etc.
4. Feathering(Tapering)
i.
ii. Overlap zones of paint must be feathered (tapered) with great care.
iii. Consecutive layers of paint coatings must be given larger and larger
overlaps.
iv. Overlap area shall be considered for calculating the cost of feathering.
5. Paint Application
i.
Paint Shop
Page 13
of 29
SHIPBUILDING DIVISION
Paint Shop
Page 14
of 29
SHIPBUILDING DIVISION
Paint Shop
Page 15
of 29
SHIPBUILDING DIVISION
The contractor shall ensure that paint handed over to it for usage is safely
stored in a suitable container.
Paint Shop
Page 16
of 29
SHIPBUILDING DIVISION
ii. All couplings must be of a close fit, especially on high pressure equipment.
iii. Replace damaged hoses.
iv. During airless spraying the paint is under an immense hydraulic pressure.
Release of the pressure through the spray gun or any leaks of the
equipment is dangerous, and a stream of paint may easily penetrate
human skin, in which case immediate medical aid is required.
3. Personal Safety
The safety of personnel is of prime importance.
i.
The contractor shall ensure that its personnel have minimum contact of
paint with skin.
ii. Sensible working clothes must be provided which can cover as much as
possible.
iii. Hand Gloves, Safety Shoes and eye protection must always be worn during
work.
iv. Usage of a suitable barrier cream on exposed skin must be considered.
v. Air fed hood/mask or respirator in confined spaces must be used.
vi. Safe access and adequate lighting must be ensured.
vii. Tidying up, as work proceeds, must be followed - good housekeeping
contributes to safety.
viii. Yard safety regulations must be respected and followed.
Blasting and Painting
Paint Shop
Page 17
of 29
SHIPBUILDING DIVISION
Never allow Naked flames - matches - cigarettes -in the same area where
paint is being applied or stored.
ii. Always thoroughly ventilate any area where paint is spilled. Clean up
immediately and dispose of the cleaning material in a closed metal
container.
iii. And if a fire should occur, do not attempt to put it out with water - use
powder or carbon dioxide (CO2) type of fire extinguishers.
Paint Shop
Page 18
of 29
SHIPBUILDING DIVISION
Quality Assurance
i.
ii. Blasting record shall contain the machine details with which the area was
blasted and will include compressor air pressure, nozzle air pressure,
nozzle size, grit type, grit size, quantity of grit used(fresh & recycled), etc.
iii. Records of Film Thickness Measurements(Wet and Dry), Cross cut
Adhesion Testing, Porosity Detection, and climatic condition
testing(surface temperature, Relative Humidity and Dew Point) must be
monitored to ensure timely corrective actions.
iv. Rework on account of defective surface preparation and faulty application
will attract a penalty on the contractor by redoing the job; No cost shall be
paid for this additional rework and moreover the cost of paint so
consumed shall be recovered from the contractor at actuals.
v. In case of excess DFT applied (80/20 rule method), the cost of excess paint
consumed shall be recovered from the contractor.
vi. The Blasting, Surface preparation, Painting, Number of coats and other
parameters affecting painting will be checked by MDL/Naval agency or any
other inspecting authority as per Paint Specification/paint manufactures
approved procedures.
vii. The Contractor will have to offer the completed work to the inspection
authority for inspection & certification as advised by MDL.
viii. Areas will be jointly measured and certified by MDL/Naval authorities.
ix. The Contractor has to follow the schedule given strictly in order to
maintain the overall progress of the Ship. LD shall be applicable in case of
delays non-attributable to any convincing reasons.
Paint Shop
Page 19
of 29
SHIPBUILDING DIVISION
Paint Shop
Page 20
of 29
SHIPBUILDING DIVISION
Paint Shop
Page 21
of 29
SHIPBUILDING DIVISION
Paint Shop
Page 22
of 29
SHIPBUILDING DIVISION
2. Machine
All tools and tackles, machines and equipments, gadgets and instruments,
etc., incidental to, in the execution of above work, shall be provided by the
contractor. Minimum requirements are listed below but the list may not be
complete.
i.
Paint Shop
Page 23
of 29
SHIPBUILDING DIVISION
Paint Shop
Page 24
of 29
SHIPBUILDING DIVISION
ii. Removal of spent/excess and reusable grits within 7 days from the date of
work done.
iii. Transportation of paint drums from store to point of use.
iv. Removal of empty paint drums and cartons from work site to disposal area
on daily basis.
v. Empty paint tins of Component B of size 6l and below are to be returned
to Paint Shop without damaging them and the quantity of such tins shall
be mentioned and tallied in the Material Reconciliation Report. Such tins
are intended for reuse by MDL. Loss of tins shall attract penalty equivalent
to the cost of procurement of fresh empty tins by MDL on the contractor.
Paint Shop
Page 25
of 29
SHIPBUILDING DIVISION
vi. Scaffolds if provided and used of MDL, must be dismantled and put in
place as instructed by the dealing executive.
vii. Neither MDL nor the Naval agencies nor the OEM nor any other Inspection
Agencies shall be responsible to supervise or direct the Work or the
activities of Contractors employees.
viii. However, the Contractor shall participate with MDL and, if MDL elects, the
OEM/Naval agencies or any other Inspection authority, in performing full
job walk-throughs whenever required by MDL. The purpose of such walkthroughs is to check that the Work performed are in accordance with the
Specifications and other Contract Documents and that the Work on the
Project is progressing in accordance with the Schedule.
ix. The Contractor shall assist MDL personnel and Inspection/OEM autorities,
if any, when they perform inspections. The Contractor shall furnish a
detailed report to MDL of observed discrepancies, deficiencies and
omissions in the Work performed by the contractor and the actions being
taken to correct such discrepancies, deficiencies and omissions in the
Work. Unless MDL directs the Contractor to correct such discrepancies,
deficiencies or omissions within 24 hours, the Contractor shall correct nonconforming or defective work within seven (7) days of any report issued
(including reports issued by the MDL or the Naval/OEM/Inspection
authorities) unless such non-conforming or defective work cannot be
corrected within such time, in which case Contractor shall commence
corrective action and furnish MDL its written plan for correcting such nonconforming or defective work within such seven (7) day period and shall
report its progress with respect thereto whenever requested by MDL.
Paint Shop
Page 26
of 29
SHIPBUILDING DIVISION
Supplier Information
The contractor shall submit the following additional information for evaluating
the technical competence of the firms :
i.
Paint Shop
Page 27
of 29
SHIPBUILDING DIVISION
Appendix A
Method of Preparation of Labolene
(MDL Supply)
1. Labolene is a liquid detergent and is a proprietary product of Glaxo India Ltd.
2. The solution is to be prepared by mixing 6 ml of the detergent in one litre of
fresh water.
3. The solution is applied on the surface with brush or cotton rags or sponge and
allowed to react with the contamination for about 10 minutes.
4. Subsequently, this is to be washed down twice with fresh water and the
surface should be dried with clean sponge or cloth.
Note:
1. Do not wash dirty paint work with alkali or soap solution, as it is harmful for
the paint film.
2. Residual alkali/soap on painted surfaces results in poor inter coat adhesion
when a fresh coat is applied.
3. This leads to flaking of the fresh paint film and promotes discolouring of paint.
Paint Shop
Page 28
of 29
SHIPBUILDING DIVISION
Appendix B
Test for Presence of Mill Scale
Paint Shop
Page 29
of 29