132/33/11kV Khasab Grid station

Testing schedule

Equipment
Name

Name of the Testing

Witness
required
from
WPOE/RAEC

Testing,Precommissioning and Commissioning activities


Contact resistance
CB functional check
CB timing test
DS & ES timing test
132kV GIS Alarm & indication check
CT test
SF6 gas quality check
Gas density monitor alarm checks
Local interlock checks

Witness
testing
date

24.03.16
26.03.16
05.04.16
06.04.16
03.04.16
03.04.16
27.03.16
28.03.16
09.04.16

Remarks

Completed
Completed

Completed
Completed