Quality Procedure

On Scheduling

Page 1 of 3

Document Code:
InEx_IExc-MPO_QP_01

Issue Date:
Effective Date:
Review Date:

Version No.

1.1

REVISION HISTORY
Page No.
N.A.

Author:
Date:
Version No:
File Name:

Details
Initial Issuance

Operations Head
Reviewed by:
Operations Director
10202016
Date:
Version01Revision00
InEx_IExc-MPO_QP_01_Procedure on Scheduling_Version01 Revision00

DRF No.
2016-001

Approved by:
Date:

Chairman/President

Quality Procedure

Issue Date:
Effective Date:
Review Date:

On Scheduling

Page 2 of 3
1

Document Code:
InEx_IExc-MPO_QP_01

Version No.

1.1

Objective: To provide structured procedure for MPO Production Scheduling

1.0 Scope: This covers the Acquisition of Weekly Unilever Requirements Plan until
Printing of Daily MPO Production Schedule.
2.0 Procedure Details:
2.1 Scheduling
Step
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
11.0
12.0
13.0
14.0
15.0

Procedure
Acquire Weekly Unilever Requirements
Plan (WURP) to Unilever Planner
Create Weekly Inex Production Plan (WIPP)
Coordinate WIPP to Production Supervisor
and IE (for new projects)
Check availability of Semi-Finished Goods
(SFG) and Packaging Materials
Inform MPO planner of the Stocks level
Order stocks from Material Purchaser
Request Stocks for Pull out and Transfer
Request Stocks/samples for Project
orientation with line leaders
Conduct project orientation
Conduct TMS Validation
Allocate Manpower based on weekly/daily
plan
Inform Line leaders of Weekly/daily
Schedule and Manpower Allocation
Inform Line Support/Manpower of the
Weekly/daily Schedule
Open and Access Database in preparation
for Printing of Daily schedule
Print Daily Production Schedule
3.0 Documents/Records Generated:
a)
b)
c)
d)

Weekly Inex Production Plan


Weekly Materials Pull out Plan
Weekly Material Requirements Plan
Daily Production Schedule

5. Policy/ies:

Responsible
Person
MPO Planner

Reference Document
WURP

MPO Planner
MPO Planner

InEx_IExc-MPO_FO_15
InEx_IExc-MPO_FO_15

Inventory controller
Inventory controller
Inventory controller
Inventory controller
Production
Supervisor
Industrial Engineer
Industrial Engineer
Production
Supervisor
Production
Supervisor
Line Leader
Production
Supervisor
Production
Supervisor

InEx_IExc-MPO_FO_19
TMS
TMS Project Orientation
Logs
TMS
InEx_IExc-MPO_FO_04
InEx_IExc-MPO_FO_04
InEx_IExc-MPO_FO_04
InEx_IExc-MPO_FO_04
InEx_IExc-MPO_FO_04

Quality Procedure
On Scheduling

Page 3 of 3
i.
ii.
iii.

Document Code:
InEx_IExc-MPO_QP_01

Issue Date:
Effective Date:
Review Date:

Version No.

Weekly Inex Production Plan and Material Requirements Plan must be


submitted every Friday - One week before the Production Week.
Daily Production Schedule must be generated in Database one day before
the Production
Confidentiality of data must be ensured

1.1