Professional Documents
Culture Documents
Introduction
14
Prior to the 1960s, the pioneers of the Chinese transformer industry, Tang Ming-qi and Zhou Mao-pei, believed that a distribution transformer of 630 kVA/10 kV should be tested in the network. Thus, they performed the first short-circuit test of a distribution transformer in China in 1965.
In the 1960s and 1970s, four laboratoriesXian High Voltage
Apparatus Research Institute, Shanghai Switchgear Works,
Shenyang Switchgear Works, and Beijing Electric Power Research
Institutewere set up as high power test laboratories for switchgear.
They could also test distribution transformers.
At the beginning of the 1980s, STI designed a prototype power
transformer SJ-8000 kVA/35 kV with some pressure sensors installed in the tank for research purposes. The transformer was sent
to Xian High Voltage Apparatus Research Institute for testing in
1984; this was the first short-circuit test of a power transformer in
China. A 100% short-circuit current test of each phase was carried
out and the pressures at specific locations measured. The transformer withstood the test and critical design data were derived.
15
110 kV
transformer
(MVA)
1 phase test
3 phase test
150 MVA
3-phase
transformer
100 MVA
3-phase
transformer
31.5 MVA
3 phase
transformer
50 MVA
Single-phase
transformer
220 kV
transformer
(MVA)
80 MVA
Single-phase
transformer
under test, and Xs is the power system reactance including the intermediate transformer [IT]), the transformer under test can absorb
1/4 of the system capability; Table 1 lists the maximum limits of
the transformers that can be tested.
If post-short-circuit is used, the capability of the transformer
under test should be reduced to half the above values in the table.
Figure 3 shows the high power lab outline and photographs.
With the postestablished short-circuit method, the burden imposed by the required power of the testing station is balanced by
the following benefits:
The test is more representative of the real situation
The control of the peak value of test current is accurate
In the preestablished short-circuit procedure, the control of the
test current peak value becomes more difficult if the unit under
test is fed through a short-circuit transformer and the make switch
is placed upstream of this transformer
Assuming a test capability of a transformer under test for a preshort-circuit at Xt = Xs (Xt is the reactance of the transformer
Figure 3. The HST high power test lab. (a) The view of the lab, (b) the intermediate transformers, (c) and (d) 220-kV, 120-MVA
transformer under test.
16
Figure 4. High-voltage test lab. (a) General view, (b) power frequency transformer, (c) impulse generator, (d) generator hall.
Summary
Fifty-three sets 110- to 220-kV transformers from 44 factories
(note that the 30- to 60-kV system in the northeast network is the
same class as 110 kV in other parts of China) passed the shortcircuit test. The rate of first-time-qualified 110-kV transformers
was close to 100%. If transformer manufacturers need to pass the
short-circuit test, they can usually do it by themselves; otherwise,
STI (R&D department) can provide help.
Forty transformers that passed the test were delivered to customers and they are now in operation in the power system all over
China. The remaining 13 transformers are in the process of assembly and delivery. Feedback from clients suggests that all these transformers function well. They have been operating from a few months
to more than five years. The report from the State Electric Com-
17
18
No.
Works name
Model
Date
Test station
Result
SF8-50000/110
1996.8
China National
Transformer Quality
Supervision Testing
Center (CTQC)
Passed
SFZ8-31500/110
1996.7
(CTQC)
Passed
SF3-QY-31500/110
1997.2
(CTQC)
Passed
SFSZ8-31500/110
1997.10
(CTQC)
Passed
SFZ8-31500/110
1997.12
(CTQC)
Passed
SFZ8-31500/110
1998.2
(CTQC)
Passed
SFZ8-40000/110
1998.5
(CTQC)
Passed
SFZ8-31500/110
1998.7
(CTQC)
Passed
ChangzhouTransformer Works
SFZ8-40000/110
1998.8
(CTQC)
Passed
10
SFZ9-31500/110
1998.9
(CTQC)
Passed
11
SFZ7-31500/110
1998.9
(CTQC)
Passed
12
SFZ9-40000/110
1998.10
(CTQC)
Passed
13
SFZ7-26000/132
1998.10
(CTQC)
Passed
14
SFZ8-31500/110
1999.1
(CTQC)
Passed
15
SFSZ8-31500/110
1999.1
(CTQC)
Passed
16
Changzhou TransformerWorks
SSZ10-50000/110
1999.3
(CTQC)
Passed
17
SFZ9-31500/110
1999.4
(CTQC)
Passed
18
SFZ7-31500/132
1999.5
(CTQC)
Passed
19
SFZ9-40000/110
1999.6
(CTQC)
Passed
20
SFZ8-31500/110
1999.6
(CTQC)
Passed
21
SZ9-40000/110
1999.6
(CTQC)
Passed
22
DCZ9-10500/110
1999.8
(CTQC)
Passed
23
SFZ9-40000/110
1999.8
(CTQC)
Passed
24
SFZ9-40000/110
1999.9
(CTQC)
Passed
25
SFZ-QY-25000/110
1999.11
(CTQC)
Passed
26
SFZ9-31500/110
1999.12
(CTQC)
Passed
27
SFZ10-40000/110
1999.12
(CTQC)
Passed
28
SFZ9-M-40000/110
1999.12
(CTQC)
Passed
29
SFSZ9-31500/110
1999.12
(CTQC)
Passed
30
SFZ9-31500/66
1999.12
(CTQC)
Passed
31
SFZ9-40000/110
2000.3
(CTQC)
Passed
32
SFZ8-31500/110
2000.3
(CTQC)
Passed
33
SZ8-40000/110
2000.4
(CTQC)
Passed
34
SZ10-M-50000/110
2000.4
(CTQC)
Passed
35
SFZ9-40000/110
2000.5
(CTQC)
Passed
36
SFZ9-40000/110
2000.6
(CTQC)
Passed
37
SFZ9-50000/110
2000.6
(CTQC)
Passed
38
SFZ9-25000/110
2000.7
(CTQC)
Passed
39
SFZ9-31500/110
2000.7
(CTQC)
Passed
Works name
Model
Date
Test station
Result
40
SFZ9-31500/110
2001.1
(CTQC)
Passed
41
SFZ9-30000/66
2001.1
(CTQC)
Passed
42
SFZ9-40000/110
2001.1
(CTQC)
Passed
43
SFZ-20000/110
2001.4
(CTQC)
Passed
44
SZ-50000/110
2001.5
(CTQC)
Passed
45
SFZ9-31500/110
2001.7
(CTQC)
Passed
46
SFZ9-31500/110
2001.7
(CTQC)
Passed
47
SZ10-M-40000/110
2001.7
(CTQC)
Passed
48
S8-QY-20000/110
2001.9
(CTQC)
Passed
49
SF-PQY-25000/110
2001.11
(CTQC)
Passed
50
SZ10-31500/110
2001.11
(CTQC)
Passed
51
SFQY-31500/110
2002.1
(CTQC)
Passed
52
SFZ10-31500/110
2002.1
(CTQC)
Passed
53
SF9-120000/220
2002.2
(CTQC)
Passed
pany indicates that there is no fault in the system due to the new
products from 40 factories (the same series type produced after
special short-circuit test). This suggests that transformer manufacturing and testing in China has improved and become more reliable
than previously and that HST contributes significantly to the Chinese transformer industry.
Future Development
In the next two to three years, we will fully solve the problem of
110-kV power transformers withstanding short circuits. This means
that all types of transformers (no-load and on-load tap change,
double- or triple-winding transformers) from each factory can pass
the short-circuit test.
We have successfully tested a 220-kV, 120-MVA power transformer. We will pay more attention to 220-kV class power transformers and test a few 220-kV, 120-MVA to 180-MVA power transformers in the near future.
The rate of qualification of distribution transformers has improved (Table 2), indicating further improvements in the manufacture and assembly of the active part of the transformers.
Although HST has reached a high industrial level and tested
many power transformers, the equipment for testing higher voltage
classes is still not up to date. Currently, we are not capable of testing 330- to 500-kV class power transformers. In the future, we will
expand HST by adding one generator with a short-circuit power
capacity of 6500 MVA and two IT with the same specifications,
combining the generator with the network. Thus, the test voltage
can potentially reach the 500-kV level and we will be capable of
testing a variety of transformers and further developing transformer
short-circuit tests in China.
References
[1] Y.-Y. He, H.-W. Je, D.-B. Zhu, and J.-X. Yang, The rapid development of the transformer industry in China, IEEE Electrical Insulation Magazine, vol.14 , No.4, pp.23-27, 1998.
[2] Y.-Y. He, 500kV power transformer and its partial discharge, ICEM,
1998.
[3] Y.-Y. He, Feasibility study of Transformers High Power Test Station, Transformer, 12, 1985.
[4] Y.-L. Jing, H. Yiyan, T.-L. Zhang, J.P. Martin (EDF) Shenyang high
power test station present and future, ICAAA, 1993.
[5] Y.-Y. He, HUSHITAI high power test laboratory, Transformer, 5,6,
1995.
[6] Y.-Y. He, M.-S. Wang, W.-G. Tian, J.-S. Du, Test capability of high
power test lab. For distribution, middle, large transformer in the world,
Transformer, 4, 2000.
[7] Y.-Y. He, Present state and improving measures of power transformer
short-circuit withstanding capability in China and IEC standard, Electrical Equipment, vol. 2, 2001.
19