Professional Documents
Culture Documents
Abstract
The hardware used in casing while drilling operations over the
past 5 years has proved to be robust and reliable. Several
directional wells have been drilled successfully with casing
using positive displacement motors (PDMs), but the drilling
efficiency was significantly degraded in most of them. This
paper documents the drilling of the first two wells to utilize a
rotary steerable system (RSS) to improve drilling efficiency
when drilling with casing.
Combining an RSS with casing while drilling operations
seemed to be a natural way to eliminate the major weaknesses
in motor bottomhole assembly (BHA) designs. Rotary
steerable systems had not previously been used with casing
while drilling because both are new technologies focused on
different environments. Casing while drilling developed on
land operations while rotary steerables have been popular for
offshore projects.
ConocoPhillips has drilled more than 94 wells in the Lobo
trend of South Texas since 2001 using the new technique. As
part of a technology demonstration project to accelerate the
technology to offshore applications, two wells were drilled
with an RSS.
The first was an operational test conducted by drilling
vertically with the RSS. The second was a full directional test
o
o
with a build to 29 and then a drop to vertical, including a 100
directional turn.
Introduction
ConocoPhillips embarked on an active field development
program in 1997 aimed at drilling hundreds of wells over the
next few years in the Lobo trend of South Texas. Since that
time, over 900 wells have been drilled through the Wilcox
(Lobo) section ranging in depth from 7,500 to 13,000 ft.
However, in 2001, after drilling about 600 wells, the
drilling efficiency had stagnated. A program was undertaken
SPE/IADC 92195
SPE/IADC 92195
Vertical Plot
0
Horizontal Plot
300
2000
200
3000
Neet North
400
1000
100
4000
0
-300
-200
-100
Feet West
5000
Vibrations
Monitoring
sub
Drill Lock
Assembly
(DLA)
6000
MWD
7-in.
23 lbm
casing
to surf
7000
ConocoPhillips
Well 83
Casing Directional Drilling
Bottom Hole Assembly
with Steerable Motor
Tandem
Casing
Stabilizer
Float sub
casing
shoe
8000
0
1000
2000
Vertical Section, ft
non-mag
drill collar
Measured depth, ft
1000
The first motor assembly was run for only 154 ft before
being pulled to replace the motor with a 5 -in. 7/8 lobe, 3o
stage motor with 1.15 bend. While the first motor actually
could deliver slightly higher torque than the second motor, it
was less effective when drilling with casing. Because casing
is larger in diameter than drillpipe, it tends to elongate much
more than drillpipe when the motor begins to pressure up.
This provides a positive feedback system that makes motors
with steep torque/pressure curves difficult to run while drilling
with casing. 5,6
3000
2000
Under reamer
(6 1/4 to 8 7/8-in.)
Pressure
2500
2000
3000
1500
KOP
4-3/4 motor to 5-1/2 motor
4000
1000
20000
WOB
15000
Start Drop
5000
10000
5000
6000
0
35
7000
34
PU Rotary assembly
Block position, ft
33
8000
Picked up
ROP = 16 ft/hr
32
10
15
20
31
0
SPE/IADC 92195
6200
4,000
Sliding
Intervals
5,500
Steerable Motor
6,500
Rotary Pendulum
7,500
8,000
0
10
15
20
1.7
0ft
/10
6600
6800
7000
7200
7400
MWD P. Collar
7,000
Non-Mag
6,000
Directional Control
5,000
Measured Depth, ft
4,500
Measured Depth, ft
6400
7600
0
10
12
Inclination, deg.
Inclination, deg
Fig. 5The sliding intervals in the build and start of the drop for
Well 83. The steerable motor BHA was replaced with a rotary
pendulum BHA to finish the trajectory.
Fig 7The rotary pendulum BHA used to finish the drop and its
directional performance.
SPE/IADC 92195
SPE/IADC 92195
2.5
Inclination, deg
TD 7 casing
section
RSS
fully
operational
Horizontal Plot
1.5
Displacement, ft
0
1.0
1000
Easting (E/-W), ft
2000
-600
0.5
1000
0.0
1000
2000
3000
4000
5000
6000
7000
Well 79
TVD, ft
200
TD
Well 79
Surf
Loc
-200
Depth , ft
Fig. 8The gyro survey run for the 7-in. section of Well 89. There
is a slight build tendency during the RSS verticality test where the
tool was not effective and after the test ended at 4,821 ft. Full
RSS control was established between 3,710 ft and 4,821 ft and the
inclination is nearly vertical.
2000
800
-200
200
Northing (N/-S), ft
-400
3000
4000
Surf
Loc
-400
-600
-800
Well 91
5000
Well 91
-1000
6000
target
-1200
7000
SPE/IADC 92195
7-in.
23 lbm
casing
to surf
DLA
(Drill Lock
Assembly)
8 jts
7 5/8-in.
casing
Tandem
Casing
(internal)
Stabilizer
Casing
shoe
Tandem
(external)
Stabilizer
Conoco Phillips
Well 91
Casing Directional Drilling
Bottom Hole Assembly
With Rotary Steerable System
MWD system
6-in. Straight
Motor
Total Length
Stick-out Length
112 ft
85
Hanging weight
(in mud)
6200 lbm
Filter sub
Tesco
Under reamer
(6 1/8 to 8 7/8)
4 Rotary
Steerable System
Jet Sub
(1x10 nozzle)
6 1/8 PDC bit
(4x10 nozzles)
Fig. 11The rig crew preparing to run the RSS and PDC bit in a
casing directional drilling BHA.
Below the jet sub was the external tandem stabilizer. This
configuration was designed to reduce vibrations and wear on
the underreamer. The gauge of these two stabilizer sections
was 6 1/8 in. minus 1/16 in. Below these sections was a slim
MWD system. The RSS, a push-the-bit type,9 was installed
below the MWD. The bit was a 4-blade PDC bit with -in.
cutters, the same type used to drill this section in other wells in
these fields. The bit and RSS are shown in Fig. 11.
Drilling operations started in the 7-in. section at 1,278 ft.
The proposed kickoff point was 2,100 ft. The RSS was
programmed for verticality mode as in the previous well. The
MWD telemetry was strong. The attenuation was 40 to 50%
instead of the expected 90%. Surveys indicated the wellbore
was nearly vertical. At kickoff point, the RSS was
programmed for three sets between 135 and 160 magnetic
toolface at 60%; therefore, the well kicked off at a compass
direction of 150 (30 East of South) at 60% of full thrusting
capabilities of the RSS. Magnetic directions or toolface are
typically used until the wellbore is at a greater than 5
SPE/IADC 92195
100
18
157m@60%
110
Inclindation, deg
14
12
120
160m
@80%
135m@60%
10
130
18g
@80%
140
36g@100%
18g@100%
150
Azimuth, deg
16
6
4
Vertical mode
180g@80%
160
azimuth
170
inclination
2
0
2000
2100
2200
2300
2400
2500
2600
2700
2800
2900
180
3000
Measured Depth, ft
Fig. 12The first six RSS tool face instruction sets (sets) in the
kick-off of Well
91. The well kicks-off at 2,100 oft starting at an
o
at about 1.9 /100ft turning to
azimuth of 135 . The build continues
o
an azimuth between 160 and 170 .
0 Up
100%
80%
turn
sets
60%
270 Left
40%
20%
The motor was added back on the third run, restoring the
BHA to the design configuration. Drilling proceeded normally
for 200 ft before the ROP dropped significantly. The BHA
was pulled, and a mistake was discovered. The wrong size
underreamer had been run. The underreamer has a small
stabilizer section on it. This stabilizer was 6 in. when it
should have been 6 1/8 in., the bit size. This too-large
stabilizer piece had worked until harder formations were
encountered. The underreamer was replaced, and drilling
continued normally until 5,420 ft where the casing became
differentially stuck. This event caused 50 hr of lost time.
Directionally, the build and turn had been finished, and the
drop was underway. Drilling then continued to 6,360 ft. The
o
well was now at 4 of inclination. A pressure drop indicated a
washout in the BHA. Surface inspection showed the washout
in the connection between the jet sub and external tandem
stabilizer. The jet sub was dropped from the BHA, and drilling
continued to section TD of 6,950 ft.
Casing Directional Drilling Operation Considerations
Drilling torque can become an issue in drilling-with-casing
operations. The 7-in., 23-lbm/ft casing connection used in this
project has an operational torque limit of 16,000 ft-lbf.
Torque and drag calculations can be used effectively to model
the expected torque for the planned trajectory and expected
tortuosity, just as is done in conventionally drilled directional
wells. Fig. 14 shows the modeled versus actual drilling torques
for Well 91. The rotating friction factor at 33% is higher than
in wells using drillpipe.
12
90 Right
drop
sets
180 Down
10
Rotating
Friction factor = 33%
(blue curve) model
Run 1
0
1000
2000
3000
2
4000
4
5000
5
6000
6
7000
Measured Depth, ft
SPE/IADC 92195
Well Days
0
10
12
Well 79
(red)
60
30
Well 91
(blue)
0
20
40
60
80
100
120
140
Conclusions
1. Directional wells can be drilled with casing using steerable
motors but success is difficult to achieve in holes smaller than
8 in. The smaller sizes of BHA components required to fit
through small holes give less-than-optimal power to steer the
underreamer and bit.
2. RSSs can be effective in 8-in. casing-drilled holes.
Directional control in the pilot hole is sufficient to guide the
larger casing to a directional target.
3000
4000
5000
7000
90
2000
6000
120
14
1000
150
Well 79
Well 91
TD 7 casing section
Acknowledgments
The authors thank ConocoPhillips for taking a leadership
position in developing casing directional drilling. Brett
Borland of ConocoPhillips Upstream Technology Group and
Rob Utter of Schlumberger were instrumental in securing
aspects of this project. Finally, we thank the many people in
the three companies who worked hard on these wells. Their
multiple, individual, and specific expertise made the concept
of this project become reality.
10
References
1. Fontenot, K., Warren, T., and Houtchens, B.: Casing Drilling
Proves Successful in South Texas, World Oil (October 2002)
27-32.
2. Fontenot, K., Highnote, J., Warren, T., and Houtchens, B.: Casing
Drilling Activity Expands in South Texas, paper SPE 79862
presented at the 2003 SPE/IADC Drilling Conference,
Amsterdam, 19-21 February.
3. Fontenot, K., Highnote, J., Strickler, R., Beierbach, E., and
Angman, P.: New Rig Design Enhances Casing Drilling
Operation in Lobo Trend, paper WOCD-0306-04 presented at
the World Oil 2003 Casing Drilling Technical Conference,
Houston, 6-7 March.
4. Warren, T., Tessari, R., and Houtchens, B.: Casing Drilling with
Retrievable Drilling Assemblies, paper OTC 16564 presented
at the 2004 Offshore Technology Conference, Houston, 3-6
May.
5. Warren, T., Houtchens, B., and Madell, G.: Directional Drilling
With Casing, paper SPE 79914 presented at the 2003
SPE/IADC Drilling Conference, Amsterdam, 19-21 February.
6. Warren, T., Tessari, R., and Houtchens, B.: Directional Casing
while Drilling, paper WOCD-0430-01 presented at the World
Oil 2004 Casing Drilling Technical Conference, Houston, 3031 March.
7. Maidla, E. and Haci, M.: Understanding Torque: The Key to
Slide-Drilling Directional Wells, paper IADC/SPE 87162
presented at the 2004 SPE/IADC Drilling Conference, Dallas,
2-4 March.
8. Meader, T., Allen, F., and Riley, G.: To the Limit and Beyond
The Secret of World-Class Extended-Reach Drilling
Performance at Wytch Farm, paper IADC/SPE 59204
presented at the 2000 IADC/SPE Drilling Conference, New
Orleans, 23-25 February.
9. Downton, G. and Carrington, D.: Rotary Steerable Drilling
System for the 6-in Hole, paper SPE/IADC 79922 presented at
the 2003 SPE/IADC Drilling Conference, Amsterdam, 19-21
February.
SPE/IADC 92195