Professional Documents
Culture Documents
High-rise reinforced-concrete core wall buildings are a very popular choice in areas of high seismic activity.
Conventionally, a single plastic hinge is allowed at the base of the wall to control responses in these buildings. Recent
studies, however, show that these core walls will be subjected to large inelastic seismic demands in a seismic event.
It is not economical and sometimes difficult to design these walls for large shear and moment demands. To reduce
these demands, a multiple plastic hinges concept is proposed in this study. Locations of the multiple plastic hinges
are identified using elastic modal decomposition analysis. A 40-storey case study building is investigated in detail to
check the effectiveness of the proposed approach. The seismic demands are found using non-linear response history
analysis at maximum considered earthquake level. A comparison of the multiple plastic hinges approach with the
single plastic hinge approach shows that seismic shear demand reduces 17% at the base of the wall, whereas moment
demand reduces 33 and 60% at the base and mid-height of the wall, respectively.
Notation
Ag
fc
FD
h
Lw
R
Rmodified
SD
y
p
y
1.
Introduction
basis earthquake (DBE) and the maximum considered earthquake (MCE) levels, it is not economical to design these walls
in the elastic range. Under such severe shaking, a flexural
single plastic hinge (SPH) is normally allowed to form at the
base of the core wall to reduce the seismic demands. However,
the plastic rotation in the hinge zone must be within an acceptable limit and the wall above the hinge zone is expected to
remain elastic (Eurocode 8 (CEN, 2004); CSA Standard
A233-04 (CSA, 2005); NZS 3101; Panagiotou et al., 2007;
Paulay and Priestley, 1992).
Recent studies on 60-storey and 40-storey RC core wall buildings with SPH at the base in high-seismic areas show that the
base shear demand at MCE level is as high as 1520% of the
total building weight. Furthermore, bending moment demands
at upper levels are greater than at the base level (Klemencic,
2008; Klemencic et al., 2007; Zekioglu et al., 2007). To
address these large shear and moment demands, the design
may not be economically justified for the rare event of a MCE
level. Furthermore, the problem of placing the reinforcement
may arise due to reinforcement congestion. Therefore, these
demands need to be reduced by different possible measures.
Several approaches have been proposed to reduce these
demands. One approach is to allow the wall to yield at any
location along its height. This approach is referred as the
ductile wall (DW) approach and was proposed by Rad and
Adebar (2008). This approach is not economical owing to
stringent ductile detailing requirements all along the wall
height. Furthermore, these buildings may not be economically
Downloaded by [ UNIVERSITY OF MORATUWA] on [14/11/16]. Copyright ICE Publishing, all rights reserved.
2.
2.1
Description of the case study building
The building is taken from previous research studies (Klemencic,
2008; Klemencic et al., 2007; Munir and Warnitchai, 2010;
72 m
72 m
87 m
3 @ 72 m
87 m
X
Plan of the building
Downloaded by [ UNIVERSITY OF MORATUWA] on [14/11/16]. Copyright ICE Publishing, all rights reserved.
689
SH-PR-360 30
HM-H-090 40
LP-HSP-000 15
CM-EUR-090 40
Hon-MGH-EW 40
Chichi-Taipei-090 60
Imp-Ch-012 40
30
25
20
15
Spectral acceleration: g
35
2.2
Target spectra
DBE spectrum (UBC-97, Zone 4, SD)
MCE spectrum (DBE spectrum 15)
10
05
0
0
5
(a)
20
10
15
10
05
0
9
10
Natural period: s
(b)
45
45
40
40
35
30
30
25
25
20
Mode 1
15
Mode 2
Level no.
Level no.
35
05
15
10
10
0
10
20
05
Modal value
1.0
1.0
0
0
05
5
Modal value
05
690
Downloaded by [ UNIVERSITY OF MORATUWA] on [14/11/16]. Copyright ICE Publishing, all rights reserved.
Mode 3
Mode 4
1.0
3.
Mode 1
Time period: s
1
3902
2
0746
3
0303
4
0172
Total mass participation
Frequency
Modal mass
participation: %
026
134
330
582
66
20
7
3
96
40
40
35
35
Combined
30
30
Mode 1
Mode 2
25
Mode 3
Mode 4
20
Level no.
Level no.
25
15
20
15
10
10
0
5
5
0
3
Moment: kN m 106
(a)
50
100
Shear: kN 103
(b)
Figure 4. DBE elastic modal and total seismic demands: (a) elastic
modal DBE moment demands and elastic moment demand;
(b) elastic modal DBE shear demand and elastic shear demand
Downloaded by [ UNIVERSITY OF MORATUWA] on [14/11/16]. Copyright ICE Publishing, all rights reserved.
691
Core wall
Plastic hinge
all along the
height
Columns
Plastic
hinges
Slabs
Plastic
hinge at the
base
Basements
Mode 2
35
35
35
30
30
30
25
25
15
25
Level no.
20
20
15
20
10
10
Columns
15
10
Mode 3
40
40
Level no.
Level no.
Mode 1
40
Slabs
0.5
Core
wall
Plastic
hinges
1
Building elevation
showing plastic hinges
location
4.
Downloaded by [ UNIVERSITY OF MORATUWA] on [14/11/16]. Copyright ICE Publishing, all rights reserved.
beams is influenced by shear, as an approximation the characteristics of the plastic hinges are determined by beam crosssection properties and the plastic hinge length is assumed to be
05 times the depth of the beams, as it is thought these
assumptions do not influence the main conclusions of this
work. The remaining portion of the coupling beam is modelled
as an elastic beam element. All slabs are modelled by elastic
slab elements, whereas columns are modelled by column
elements of the Perform-3D.
5.
Downloaded by [ UNIVERSITY OF MORATUWA] on [14/11/16]. Copyright ICE Publishing, all rights reserved.
693
Concrete material
Stress
Stress
Steel material
'
fcc
fu
fy
dcEo
Eo
Eo
Eo
y
sh
Strain
c'
ft
Park envelope
Perform-3D
Cyclic
'
cc
cu
Strain
Mander envelope
Perform-3D
Unloading
Reloading
Level no.
40
40
35
35
30
30
25
25
20
20
15
15
Conventional
SPH
Proposed MPH
10
10
DPH
5
DW
5
0
Displacement: m
001
002
694
003
Downloaded by [ UNIVERSITY OF MORATUWA] on [14/11/16]. Copyright ICE Publishing, all rights reserved.
004
y: rad
p: rad
Yield displacement: m
Plastic displacement: m
Plastic hinge length = one storey high = 3 m, elastic displacementa = yield displacement = y = 008 0003/Lw h 2, Lw = length of
wall = 10 m, h = 125 m
1
0001
00063
125
034
078
2
00136
90
122
3
000825
63
051
4
000353
41
014
SRSS (hinge 1 + hinge 2 + hinge 3 + hinge 4)
034
155
Total displacement (elastic + plastic)
189
Displacement from NLRHA
185
Difference: %
216
a
Elastic displacement relationship has been developed on the basis of actual elastic displacement found by pushover analysis in
first mode
Downloaded by [ UNIVERSITY OF MORATUWA] on [14/11/16]. Copyright ICE Publishing, all rights reserved.
695
45
40
40
35
30
Level no.
35
30
25
25
20
20
15
15
10
10
5
0
1
Displacement: m
2 106
Hinge 2
1 106
5 105
0012
0
0006
0000
5 105
1 106
0006
0012
t = 00073,
y = 000094,
8 105
Hinge 4
4 105
6
105
6 105
4 105
2 105
2 105
0
0015 0010 0005 0
2 105
p = 000825
8 105
Rotation: rad
0
0015 00100005 5 0
2 10
4 105
6 105
p = 000353
8 105
Rotation: rad
696
t = 00145,
y = 000094,
p = 00136
2 106
Rotation: rad
Moment: kN m
Moment: kN m
105
1 106
1 106
8 105
6
006
0
0015 001000050000 0005 0010 0015
5 105
1 106
105
002
004
Drift ratio: rad
5 105
p = 00063
2 106
Rotation: rad
Hinge 3
2 106
Moment: kN m
Moment: kN m
Hinge 1
FD
SD
Downloaded by [ UNIVERSITY OF MORATUWA] on [14/11/16]. Copyright ICE Publishing, all rights reserved.
Rotation: rad
0009
Initial yield time = 978 s
Maximum rotation time = 1038 s
0006
Hinge 1
0003
Yield rotation +
0
0003
Yield rotation
0
10
20
30
Time: s
0015
50
0012
Rotation: rad
40
0009
0006
Hinge 2
0003
Yield rotation +
Yield rotation
0003
10
20
30
40
50
Time: s
0009
Rotation: rad
0006
0003
Hinge 3
0
yield rotation +
0003
Yield rotation
0006
10
20
30
40
50
Time: s
Initial yield time = 82 s
Maximum rotation time = 942 s
Rotation: rad
0008
0004
Hinge 4
Yield rotation +
0004
Yield rotation
0008
10
20
30
40
50
Time: s
distributed in a stepwise manner in the MPH and DPH approaches. Furthermore, the racking deformation angle is less
than that for the conventional SPH approach in the lower half
because the plastic rotation of the wall was concentrated only
at the base in the case of the conventional SPH approach,
whereas plastic rotation is distributed at four locations along
the height of the wall in the present case.
The MCE inelastic shear and moment demands are shown in
Figure 11. The shear and moment demands are reduced
significantly all along the height of the wall with 33, 17 and
60% reduction in the base shear demand, moment demand at
foundation level and moment demand at the mid-height,
respectively, as compared with those obtained from the conventional SPH approach.
The comparison of the proposed MPH approach with
the DPH approach shows that inducing plastic hinges at effective locations can smoothen the shape of bending moment
demands and hence its magnitude along the wall height.
Downloaded by [ UNIVERSITY OF MORATUWA] on [14/11/16]. Copyright ICE Publishing, all rights reserved.
697
40
30
Conventional
SPH approach
Proposed MPH
approach
DW approach
25
DPH approach
Level no.
35
20
15
10
5
0
5
1
2
Moment: kN m 106
40
80
Shear: kN 103
120
40
Proposed approach
Demands
35
30
DBE design
demands
25
Level no.
Provided strength at
other locations
20
Provided flexural
strength at plastic
hinge locations
15
10
5
0
5
Moment: kN m 106
(a)
2 3 4 5 6 7
Shear: kN 103
(b)
698
Downloaded by [ UNIVERSITY OF MORATUWA] on [14/11/16]. Copyright ICE Publishing, all rights reserved.
9
(c)
6.
6.1
Structural elements designed for inelastic actions
In the previous sections, the design of the structural elements
intended to develop inelastic mechanism, namely, the elements
at plastic hinge locations, has been presented in detail. The
NLRHA demands and provided flexural and shear strength in
the core wall at intended inelastic locations (plastic hinges in
the wall) as well as other locations are shown in Figure 12. It
is noted from Figure 12 that the MCE NLRHA demands at
plastic hinge locations are about 12 times more than provided
flexure strength capacity. This is mainly because of the overstrength due to strain hardening of the rebar material.
To ensure an effective plastic hinge mechanism, the ductile
detailing and boundary elements should be provided in storey
numbers 01, 02, 12, 13, 21, 22, 28 and 29, which are designated as the plastic hinge regions. The ductile detailing should
be provided in only eight out of 40 storeys, consequently
saving a lot of reinforcement in addition to controlling the
spread of damage.
6.2
Structural elements intended to remain elastic
In the capacity design process, the relative strengths of the
different members are attributed in such a way that only the
inelastic mechanisms chosen by the designer can develop
during strong seismic shaking (Priestly, 2003). In this study,
plastic hinge formation at undesirable locations in the core
wall is avoided by providing flexural strength at these locations
about 11 times greater than the NLRHA MCE demands.
NLRHA demands and provided strength capacities are shown
in Figure 12. The nominal strength of the materials and
strength reduction factors as per ACI 318-08 (ACI, 2008) are
used for calculation of flexural and shear strength capacities
for elastic actions and members. This will further enhance the
capacity of the elements, thus minimising the chance of formation of plastic hinges. This is because the actual flexural
7.
&
&
&
&
&
&
Conclusions
In this study, a MPH concept in high-rise RC core wall
buildings by inducing plastic hinges at effective locations is
proposed. In this approach, locations of plastic hinges are
identified based on the DBE elastic bending moment
demands. NLRHA is then performed to verify the
reduction in the moment and shear demands as compared
to the conventional SPH, DPH and DW approaches.
The plastic hinge mechanism is explained by verifying the
displacement at the top of the wall obtained from NLRHA
with that obtained from plastic hinge rotations.
The verification results show that there is significant
reduction in shear and moment demands. The reduction is
60% in terms of moment demand at the mid-height,
whereas it is 17 and 33% in terms of the base shear and
moment demand at base level, respectively, as compared to
the conventional SPH approach.
Comparison with the DPH approach shows that the
proposed MPH approach can effectively reduce the
moment and shear demands at third-mode-dominant
locations, such as one-third and two-thirds the height of
the wall, by 3040% and 1525%, respectively.
Multiple hinges are nearly impossible from a static
viewpoint for stability of the structure. However, under
dynamic excitation, these are possible and favourable to
reduce the bending moment demands along the wall
height. Furthermore, they will flatten the shape of the
bending moment diagram and make the placement of
longitudinal reinforcement easy.
Limiting the plastic hinges to suitable locations, where
they can control the seismic demands most effectively, can
Downloaded by [ UNIVERSITY OF MORATUWA] on [14/11/16]. Copyright ICE Publishing, all rights reserved.
699
&
REFERENCES
Downloaded by [ UNIVERSITY OF MORATUWA] on [14/11/16]. Copyright ICE Publishing, all rights reserved.
Downloaded by [ UNIVERSITY OF MORATUWA] on [14/11/16]. Copyright ICE Publishing, all rights reserved.
701