Professional Documents
Culture Documents
analysis
Cost analysis
Price vs costs
Scarcity cost
Marginal cost
Investment analysis
Discounting
External costs
Cost-benefit analysis
Opportunity cost
What is
economic
evaluation?
A SOCIAL SCIENCE
THAT EXAMINES
PEOPLES AIM TO FULFIL
THEIR SELF-INTEREST (?)
In a world of limited
resources and unlimited
wants, economics
evaluates how countries
(macro-economics) and
individuals (microeconomics) choose
what, how and for whom
goods (and services) are
produced.
Scarcity
Resources:
Price
Price
Price vs cost
Definitions
Demand
Supply
Law of demand
As the price of a good
goes up so does the
opportunity cost of
buying the good.
Therefore people will
buy less so they dont
have to go without
something else they
value more
Elasticity of demand
The responsiveness of
demand to a change in
price of a good.
Elasticity=
%change in quantity
%change in price
Availability of substitutes
Time
Shift in demand
Law of supply
Producers supply more at a higher price because selling a
higher quantity at a higher price increases revenue.
Law of supply
Spot Market
Short Term
Long Term
Shift in supply
Ecuador?
19
24
Investment analysis
Cons
Typically higher initial costs
Lack of infrastructure
Pre-feasibility Analysis
Feasibility Analysis
Development and Engineering
Construction and
Commissioning
Projects
often stall
here
O&M costs
Major overhaul costs
Decommissioning cost
Financing costs
Unforeseen costs
Simple payback
Discounted payback
Profitability Index
Savings to investment
ratio
Sensitivity analysis
Probability analysis
Payback period
[years]
CC = capital cost of
the Project [$]
Interest
Interest
Simple Interest
= +
100
Compound Interest
It is calculated by:
= 1 +
100
= 1 +
1+100
Based on an assumed
discount rate, DR (interest
rate)
Determined using:
1+100
Project 1 Project 2
Example
Use the NPV method
to evaluate the
financial merits of the
two proposed projects
shown below. Assume
an annual discount
rate of 8% for each
project.
Capital cost
$ 30000
$ 30000
Year
$ 6000
$6600
$ 6000
$6600
$ 6000
$6300
$ 6000
$6300
$ 6000
$ 6000
$ 6000
$ 6000
$ 6000
$5700
$ 6000
$5700
$ 6000
$5400
10
$ 6000
$5400
$ 60000
$ 60000
Solution
Project 1
Year DF for 8%
Project 2
Net savings
Present value
Net savings
Present value
1,000
$ -30.000,00
$ -30.000,00
$ -30.000,00
$ -30.000,00
0,926
6.000,00
5.555,56
6.600,00
6.111,11
0,857
6.000,00
5.144,03
6.600,00
5.658,44
0,794
6.000,00
4.762,99
6.300,00
5.001,14
0,735
6.000,00
4.410,18
6.300,00
4.630,69
0,681
6.000,00
4.083,50
6.000,00
4.083,50
0,630
6.000,00
3.781,02
6.000,00
3.781,02
0,583
6.000,00
3.500,94
5.700,00
3.325,90
0,540
6.000,00
3.241,61
5.700,00
3.079,53
0,500
6.000,00
3.001,49
5.400,00
2.701,34
10
0,463
6.000,00
2.779,16
5.400,00
2.501,24
NPV = $ 10.260,49
NPV = $ 10.873,91
Limitations of NPV
=0 (1+)
N = analysis period
TLCC
example
Annualised Costs
(1 + )
=
(1 + ) 1
=1(1+)
DR = discount rate
N = analysis period
Example of LCOE
Base case
Alternative
Bulb type
75 watt incandescent
40 Watt fluorescent
Hours of operation
6 cents/kWh
6 cents/kWh
Cost of bulb
$1 once a year
For a study period of 5 years and a discount rate of 12% the UCRF is 0.2774
Calculate the LCOE saved
The LCOE (saved) = ([15 - 4.03]/[164.25-87.6])x0.2774 = 0.04 USD/kWh
The cost per unit required to save energy is cheaper than the cost to purchase the energy
(0.04 USD/kWh < 0.06 USD/kWh), so the alternative should be chosen.
Conversely, if the cost of electricity drops below 4 cents/kWh then it should not be
chosen.
Fuel cost
1 GJ = 277 kWh
Is that all???
50
51
Capital cost
Fuel cost:
1 USc/kWh
Total
2.3 USc/kWh
Is that all?
External costs
52
53
External costs
TAXES
54
55
56
Energy prices