Professional Documents
Culture Documents
Session Fourteen:
Hazardous Areas Auditing The Devils in the Details
Kayne Herriman
Hazardous Areas Specialist, Bluefield AMS
Abstract
To say a piece of equipment is compliant means that every detail has been
checked according to the applicable codes, certification and manufacture
specification. This is sometimes seen as dragging out the process but really we
are ensuring that every detail is correct, compliant and the equipment is safe
for operation. The devils in the detail, and the lack of detail is the risk that
many operations continue to expose themselves to. Kayne will share his
experiences of conducting audits on electrical equipment in hazardous areas,
the problems which were found, the details which were overlooked and the
learnings he has taken away to pass on to others.
Introduction
Any hazardous areas audit, is a systematic and critical examination of the
installation, equipment, its operation and safety systems.
To say a piece of equipment is compliant is to say that:
The installation has been correctly classified
The equipment selection is correct
The equipment has been installed as per the certificate of conformity
and/or manufactures specifications
Accessories and terminations comply, have been done correctly and,
where relevant to a correct torque
Equipment has been electrically tested and deemed safe
The inspector is trained, competent and authorised
Currently there are two states (Queensland & Victoria) in Australia which the
state government requires electrical installations in hazardous areas to be
inspected/audited.
In Queensland the Electrical Safety Regulations 2013, Section 221 requires
that an accredited auditor inspects electrical installations in hazardous areas
prior to connection or reconnection to a source of electricity if:
th
Although not legislated in other states, it is still good practice to have the
installation audited. This is not done to delay completion but to allow another
set of qualified and experienced eyes to ensure the finer details have not been
overlooked. These overlooked details can be common when the personnel
completing the project construction/ installation are also responsible for the
compliance audit process.
Another problem that can arise is when the person(s) in charge of the area do
not understand the risks, or their obligations when it comes to hazardous areas.
In these instances when auditors do get called in to audit the installation they
are usually faced with a barrage of questions and can be seen to be holding up
the process. This is usually because they feel they (the person(s) in charge)
have had competent people design, install and commission their equipment,
unfortunately this is not always the case.
Additionally, the installers and engineers are apprehensive and sometimes
defensive when details are found that should have been picked up well before
the final Audit. But this shouldnt surprise us when the volume of learning for
the hazardous areas course is ~780hrs and it is delivered in five days across
Coal, Dust & Gas, which suggests we are not getting the basics right.
This paper will highlight some of the finer details which have been found in
audits.
Keep It Simple
Auditing is the process involving systematic examination of a system.
Developing this process and following it is critical to ensuring the plant and
equipment is compliant, safe and no details are missed.
To simplify a complex process, the following solution has been developed to
audit hazardous areas and if followed gives the Auditor confidence that all
details have been confirmed.
Understanding
the legislation
Verify the
equipment &
inspect for
compliance
Review the
classification &
design report
Analyse the
equipment lists
and certificates
th
th
classification appears to be incorrect, along with the fact the electric motor is in
a defined hazardous zone and doesnt have the appropriate markings.
th
th
Now if the installer didnt look at the certificate they will never know that for the
certified terminal under IECEx SIR 05.0035U there are specific torque setting
which used and unused terminals SHALL be tightened to.
Additionally, anomalies on the marking and certificate can be found which need
to be addressed and feed back to the relevant certifying body, for example
This level of detail is required otherwise how do you say the piece of equipment
is compliant?
th
th
A simple check of AS / NZS 3017 Table 3.2 which has been stated on the
electrical test sheet show that the values appear to be outside of the
MAXIMUM RESISTANCE for RE/RPH.
th
Poor workmanship plays a large part in why equipment is found to be noncompliant usually due to the installation, glanding and terminations. Not only
does this reflect poorly on the installer but these simple problems do not
comply with AS/NZS 3000.
When equipment is installed in damp or wet areas the concern is water ingress
into the equipment. The installer cannot take it upon themselves to compromise
flamepaths. In AS/NZS 60079.14 Section 10.3 Protection of flameproof joints,
both concerns have options provided which need to be followed.
In some cases there are times when equipment is installed in hard to reach
places. In this example the junction box was located on a beam without any
access. The auditor felt comfortable enough to sign off the equipment without
verifying whats installed and simply compared it to a spare junction box making
the following comments.
th
10
After scaffolding was erected it was found that the factory glands were loose
and the equipotential bond was missing.
Another
example
where
verification was important was
a spray booth which has been
in use for the past eight years.
The owner was under the
impression it was compliant as
all the paper work was
available. But, the auditor
identified a limitation in their
final signoff of booth construction was not complete
The findings after the verification was completed was that the lights do not
comply with the state standards AS/NZS 4114 Part 1 & 2 nor to AS/NZS 60079,
and probably havent since the vendors original design.
th
11
This reference is from the Electrical Safety Regulation 2013 Section 221. You
will notice there are key words which are bolded. People (including Auditors)
seem to think that we can wave a magic wand and the installation is compliant.
Hopefully this paper demonstrates a few examples of a very common issue to
emphasise the importance of why we must INSPECT and CONFIRM the
installation before it is energised.
Conclusion
When it comes to hazardous areas auditing the devil is in the detail and the
lack of detail is the risk. There are no shades of grey with compliance, it is
either compliant or it is not. Although the company / people want to be
compliant after issues are found and presented, there is no way around the
requirements that need to be met. One of the biggest risks we see is when a
company truly believes they are compliant yet they are clearly not after if the
audit findings are presented.
The auditor cannot just wave his wand and magically make the installation
compliant. They didnt design, classify, select, install or commission the
equipment, yet they are the ones seen to be holding up the process. If anything
the owners should be happy that the non-compliant issues were found now, not
when there has been an incident or accident.
More focus needs to be placed on getting back to the basics. Just because the
equipment has a certificate of conformity doesnt mean its compliant after its
been installed. So remember whether the issues are from installation,
equipment or administrative everything needs to be fed back through to the
correct channels so that continuous improvement occurs, and always
remember to follow up.
It is important that the people understand their limitations when working in
hazardous areas, as when non-compliances are found and re-work is required
the project soon becomes very costly. There are some of us who have been
fortunate enough to have been taken under the wing of very experience
industry mentors and as the industry moves forward its our responsibility to pay
it forward to lift the standard, as the standard we walk past is the standard we
accept.
th
12
References
Australian Goverment. (n.d.). Training.gov.au. Retrieved 07 09, 2016, from
https://training.gov.au/Home/Tga
Parliamentary Counsel. (n.d.). Queensland Electrical Safety Act 2002.
Parliamentary Counsel. (n.d.). Queensland Electrical Safety Regulation 2013.
Standards Australia Limited/Standards New Zealand. (2009). AS /NZS
60079.17 - Explosive atmospheres Part 17: Electrical installations
inspection and maintenance. Sydney: SAI Global Limited.
Standards Australia Limited/Standards New Zealand. (2009). AS/NZS
60079.14 - Explosive atmospheres Part 14: Electrical installations
design, selection and erection. Sydney: SAI Global Limited.
Standards Australia/Standards New Zealand. (2003). AS/NZS 4114.1 - Spray
painting booths, designated spray painting areas and paint mixing rooms
Part 1: Design, construction and testing. Sydney: Standards Australia
International Ltd.
Standards Australia/Standards New Zealand. (2003). AS/NZS 4114.2 - Spray
painting booths, designated spray painting areas and paint mixing rooms
Part 2: Installation and maintenance. Sydney: Standards Australia
International Ltd,.
Standards Australia/Standards New Zealand. (2007). AS/NZS 3000 Wiring
Rules. Sydney: SAI Global Limited.
Standards Australia/Standards New Zealand. (2007). AS/NZS 3017 - Electrical
installation - Verfication guidelines. Sydney: Standards Australia.
th
13