PIPING INSPECTOR
1
Email : batamtraining@gmail.com
website : www.batamtraining.com
PIPING INSPECTOR
By : Made Wisnawa Putra
Email : batamtraining@gmail.com
website : www.batamtraining.com
BEFORE FABRICATION
Material receiving inspection
Issuing material process and material
traceability
Transportation material from W/H to Shop,
inspection during material handling, lifting
etc.
Material protection/preservation inspection
prior to deliver to fabrication shop.
Email : batamtraining@gmail.com
website : www.batamtraining.com
Email : batamtraining@gmail.com
website : www.batamtraining.com
Email : batamtraining@gmail.com
website : www.batamtraining.com
Note :
Email : batamtraining@gmail.com
website : www.batamtraining.com
Email : batamtraining@gmail.com
website : www.batamtraining.com
Email : batamtraining@gmail.com
website : www.batamtraining.com
Email : batamtraining@gmail.com
website : www.batamtraining.com
Email : batamtraining@gmail.com
website : www.batamtraining.com
10
MATERIAL
PRESERVATION
Email : batamtraining@gmail.com
website : www.batamtraining.com
11
Email : batamtraining@gmail.com
website : www.batamtraining.com
12
Email : batamtraining@gmail.com
website : www.batamtraining.com
13
Email : batamtraining@gmail.com
website : www.batamtraining.com
14
DURING FABRICATION
Match material with spool/ISO drawing ( size,
rating, THK, material spec etc )
Correct WPS and certified Welder
Spool Dimensional Control ( DC ) check before
spool release from shop is mandatory to
ensure no OOT or re work at erection stage.
Email : batamtraining@gmail.com
website : www.batamtraining.com
15
FABRICATION SEQUENCE
Marking and cutting
Select the pipe as per isometric drawing
Visual checking and check the ovality
Lay the pipe on the proper bed, jack or fixture
Fix the reference point
Select proper tool for more accuracy
Mark on the pipe to the required dimension
Punch mark on the pipe
Cut the pipe trace to the punch mark
Fit and Weld
Email : batamtraining@gmail.com
website : www.batamtraining.com
16
Email : batamtraining@gmail.com
website : www.batamtraining.com
17
MEASURING METHODS
Email : batamtraining@gmail.com
website : www.batamtraining.com
18
Email : batamtraining@gmail.com
website : www.batamtraining.com
19
Email : batamtraining@gmail.com
website : www.batamtraining.com
20
Email : batamtraining@gmail.com
website : www.batamtraining.com
21
Email : batamtraining@gmail.com
website : www.batamtraining.com
22
Email : batamtraining@gmail.com
website : www.batamtraining.com
23
Email : batamtraining@gmail.com
website : www.batamtraining.com
24
Email : batamtraining@gmail.com
website : www.batamtraining.com
25
Email : batamtraining@gmail.com
website : www.batamtraining.com
26
website : www.batamtraining.com
27
website : www.batamtraining.com
28
Inspection -Flange-PipE-flange
Email : batamtraining@gmail.com
website : www.batamtraining.com
29
PipE-elbow-pipE
Pipe-Elbow-Pipe Alignment Measurment
Email : batamtraining@gmail.com
website : www.batamtraining.com
30
Inspection -PipE-elbow-pipE
C = ( A2 + B2)
Email : batamtraining@gmail.com
website : www.batamtraining.com
31
Email : batamtraining@gmail.com
website : www.batamtraining.com
32
Inspection-Pipe to flange
Pipe Centre Line in (00) positions
Email : batamtraining@gmail.com
website : www.batamtraining.com
33
Inspection-Pipe to flange
Email : batamtraining@gmail.com
website : www.batamtraining.com
34
Email : batamtraining@gmail.com
website : www.batamtraining.com
35
Perform
measurements at
two locations on
both ends of the
pipe connections
Email : batamtraining@gmail.com
website : www.batamtraining.com
36
Email : batamtraining@gmail.com
website : www.batamtraining.com
37
PFI-ES-3
Email : batamtraining@gmail.com
website : www.batamtraining.com
38
Email : batamtraining@gmail.com
website : www.batamtraining.com
39
AFTER FABRICATION
Ensure Pipe End Cover/Preservation during
transportation from shop to lay down area or
Module/ platform installation area.
Check latest rev drawing prior to install the spool
to avoid re work post installation.
Internal cleaning inspection ( Boroscope camera
maybe can use )
Line Walk to check actual installation comparing
with latest Rev drawing/design/3 D model.
Email : batamtraining@gmail.com
website : www.batamtraining.com
40
Email : batamtraining@gmail.com
website : www.batamtraining.com
41
Purging connection
for hookup spool
was not considered
during design phase
result in:
New fittings
needs to be
ordered (Tee,
Threadolet,
Cap, Plug,
Flange, Blind
Flange)
Rework on
fabricated spool
Hold up testing
progress
Email : batamtraining@gmail.com
website : www.batamtraining.com
42
website : www.batamtraining.com
43
Email : batamtraining@gmail.com
website : www.batamtraining.com
44
Modification on spray nozzle routing due to spray pattern was obstructed by pipe, cable
tray and pipes
PDMS model
Actual Condition
Email : batamtraining@gmail.com
website : www.batamtraining.com
45
Actual Condition
Email : batamtraining@gmail.com
website : www.batamtraining.com
46
Actual Condition
Email : batamtraining@gmail.com
website : www.batamtraining.com
47
Email : batamtraining@gmail.com
website : www.batamtraining.com
48
Email : batamtraining@gmail.com
website : www.batamtraining.com
49
website : www.batamtraining.com
50
Email : batamtraining@gmail.com
website : www.batamtraining.com
51
Email : batamtraining@gmail.com
website : www.batamtraining.com
52
Email : batamtraining@gmail.com
website : www.batamtraining.com
53
Email : batamtraining@gmail.com
website : www.batamtraining.com
54
Email : batamtraining@gmail.com
website : www.batamtraining.com
55
Boroscope
BOROSCOPE Camera :
To check internal pipe cleanliness before or after
spools installation completed.
With this equipment we can found any debris or
not required thing inside the pipe.
Email : batamtraining@gmail.com
website : www.batamtraining.com
56
Email : batamtraining@gmail.com
website : www.batamtraining.com
57
Boroscope
Found welding wire during boroscope cleanliness inspection,
spool KA210381
Email : batamtraining@gmail.com
website : www.batamtraining.com
58
Boroscope
Found foreign material during boroscope
cleanliness inspection, M2A Mezanine Deck,
Manifold Line. (foreign material stuck
between flanges)
Email : batamtraining@gmail.com
website : www.batamtraining.com
59
Boroscope
Found baslting sand during boroscope
cleanliness inspection, Location M2B
Mezzanine Deck, Open Drain Carbon Steel
Email : batamtraining@gmail.com
website : www.batamtraining.com
60
Boroscope
Found welding wire during Boroscope
Inspection, and water trap inside because in
the centre of End Cap got hole, so water can
go inside.
Email : batamtraining@gmail.com
website : www.batamtraining.com
61
DESIGN ERROR
Bolt removal space
in some place was
not adequate prior
to remove the
valves we need
to cut
Email : batamtraining@gmail.com
website : www.batamtraining.com
62
DESIGN ERROR
Email : batamtraining@gmail.com
website : www.batamtraining.com
63
Email : batamtraining@gmail.com
website : www.batamtraining.com
64
Flange management
Email : batamtraining@gmail.com
website : www.batamtraining.com
65
Flange management
Email : batamtraining@gmail.com
website : www.batamtraining.com
66
Email : batamtraining@gmail.com
website : www.batamtraining.com
67
Email : batamtraining@gmail.com
website : www.batamtraining.com
68
Project Specification/ITP
From NB Project :
Email : batamtraining@gmail.com
website : www.batamtraining.com
69
Project Specification/ITP
From NB Project :
Email : batamtraining@gmail.com
website : www.batamtraining.com
70
Project Specification/ITP
From NB Project :
Email : batamtraining@gmail.com
website : www.batamtraining.com
71
Project Specification/ITP
From NB Project :
Email : batamtraining@gmail.com
website : www.batamtraining.com
72
Project Specification.
From GG Project :
Email : batamtraining@gmail.com
website : www.batamtraining.com
73
Project Specification
From GG Project :
Email : batamtraining@gmail.com
website : www.batamtraining.com
74
Project Specification
From GG Project :
Email : batamtraining@gmail.com
website : www.batamtraining.com
75
Email : batamtraining@gmail.com
website : www.batamtraining.com
76
Email : batamtraining@gmail.com
website : www.batamtraining.com
77
Email : batamtraining@gmail.com
website : www.batamtraining.com
78