Activity

Activity

Orig

Early

Early

ID

Description

Dur

Start

Finish

PP10 Site Establishment / Documentation

20-May-07 27-May-07

PP20 Shoring Design Approval by TECOM

10

27-May-07

7-Jun-07

PP30 Demarcation of Site

9-Jun-07

13-Jun-07

PP40 Mobilization and Setting out of Site

14-Jun-07 21-Jun-07

PP50 Contiguous Piles

60

23-Jun-07 25-Aug-07

PP60 Capping Beam

30

28-Jul-07

31-Aug-07

PP70 Installation of Dewatering

20

1-Aug-07

20-Aug-07

PP80 Excavation to Anchor Level

20

25-Aug-07 15-Sep-07

PP90 Installation of Tie Back Anchors

30

28-Aug-07 29-Sep-07

PP100 Excavation to Final Required Level

30

10-Sep-07

PP110 Handling over of Site

10-Oct-07 11-Oct-07

Start Date:23-Jun-2007

2007
May

June

July

August

September

October

Date

Revision

Checked

Approved

9-Oct-07

KOREA BORING LLC


(2B+G+3P+19) On Plot no. BB.B01.063
Location: Business Bay, Dubai
Construction Programme

KOREA BORING LLC


QUALITY RECORDS
TEMPORARY GROUND ANCHOR REPORT
PROJECT NAME: (2B+G+3P+19) On Plot No. BB.B01.063

CLIENT

PROJECT NO. KB300/2007

CONSULTANT ________________________________

Anchor
No.

____________________________________

Bonded Free
Total
Post Grout
Strand
No. of Length Length Length Drilling Casing Grouting W/C Grout Vol. Pressure Stressing Lock Off Elongation Elongation
Size (mm) Strands
(m)
(m)
(m)
Date Dia. (mm)
Date
Ratio
(liters)
(bar)
date
Load (kN) Theo. (mm) Act. (mm)

RECORDED BY ___________________

VERIFIED BY ____________________

SHEET ____________

OF _________

Elongation