You are on page 1of 149

KERALA STATE ELECTRICITY BOARD

LIMITED

KSEB DATA BOOK


for
CIVIL WORKS

PREFACE

The existing PWD Data Book is followed by KSE Board for preparation of
estimate of civil works. But it is observed that the majority of civil works in
KSE Board are carried out in hilly and remote area. The nature of works is also
risky, difficult and different than the works as per PWD Data Book. Hence,
KSE Board vide B.O.(FM)No.1787/2011 (MG/General/2003) dated 19.07.2011
constituted a team to prepare KSE Board Data Book for preparation of estimate
for civil works. The team held several sittings and after elaborate discussions,
enquiries and verifications prepared this Data Book.
The emphasis of this Data Book is mainly for preparation of estimate of
hydro electric projects. In line with the present construction scenario, majority
of the data includes incorporation of usage of machineries. Design mixes were
adopted for data of concrete items based on the details obtained from Research
wing, KSE Board, Idamalayar. In general, the data for different items were
arrived based on field observations, prevailing market rates and other technical
considerations.
Separate chapters have been provided for items coming under the same
category as given in the Index. The data have been also prepared in excel linked
format for easy usage of this Data Book. For arriving rates for items using
machineries, separate annexure is provided under Use rate of equipments. The
use rate of equipments is prepared based on CWC guide lines.
Whenever data for new item of works is found necessary, the same will
have to be prepared based on actual observations and got approved by the Chief
Engineer before inclusion under the respective chapter of this book. The method

of preparation of estimate using this data book is explained separately under


Method of preparation of estimate
The Chairman expresses deep gratitude to the team members for their
sincere efforts and whole-hearted support in preparing this Data Book. The team
is indebted to persons who have given their valuable suggestions and
supplemented with details. The Chairman acknowledges

sincere thanks to

Chief Engineer(CC) South and Chief Engineer(CC) North for their valuable
guidance and active support.
Suggestions are invited to make this book more precise and
comprehensive.

23 05 - 2014
Chairman, Data Team
Dy.Chief Engineer,
O/o the Chief Engineer (CC) North,
Kozhikode

INDEX
Chapter

Name

Page Nos.

Clearing site and Felling trees.

II

Dismantling and Demolition

III

Excavation and Allied works.

IV

Drilling and Grouting.

16

Reinforcement and Form work..

20

VI

Concreting.

23

VII

Masonry works.

36

VIII

Plastering and Pointing..

43

IX

White washing and Painting

49

Doors, Windows and Ventilators..

59

XI

Water supply and Sanitory works..

64

XII

Flooring.

72

XIII

Roofing.

78

XIV

Road works..

81

XV

Tunnel and Surge..

90

XVI

Penstock..

100

XVII

Gates and Trashrack.

105

XVIII

Miscellaneous works.

107

XIX

Investigation works

116

Annexure - A Use Rate of Equipments.


Annexure - B Additional Use Rate of Equipments.
Annexure - C Machinery details.

KSEB DATA BOOK


INSTRUCTIONS FOR PREPARATION OF DATA BOOK
1. The data is prepared in excel linked format and the data for
estimate may be prepared using the soft copy made available with
this Data Book.
2. In the data under Use rate of equipments, the cost of equipments,
charges, capacity and cost of fuel as per prevailing SOR/approved
data may be filled under appropriate columns.
3. In the data, HA and OH may be considered as per the nature of
terrain and nature of work.
4. Item No.2 of chapter III Excavation and Allied works, may be
taken only for excavation works in which conveyance of excavated
materials by using tipper is considered.
5. In the data, generally for all works, all lifts are considered to be
inclusive, other than stated separately.
6. Considering the availability and economy of form work materials,
steel formwork is only considered in the data. While preparing the
estimate, the same may only be considered.
7. If data of any item is not available in this Data Book, the existing
PWD Data Book may be referred.

CHAPTER I
CLEARING SITE AND FELLING TREES
Sl.
No.
1.

Quantity

Description of items

100 m2

Clearing light jungle and removal of rubbish


upto a distance of 150m outside the
periphery of the area cleared.

0.4 hr
%
%

Grass cutter (up to 2.5 HP) - (UR)


OH
CP

Rate

Unit

1 hr

/100m2

100 m2

Clearing thick and thorny jungle and small


trees of girth up to 30cm including removal
of rubbish up to a distance of 150m outside
the periphery of the area cleared.

0.6 hr
0.1 No
%
%
%

Grass cutter (up to 2.5 HP) - (UR)


Man
HA
OH
CP

1 hr
1 Each

/100m2

Total
3.

1 No

1 hr
0.50 No
5%
%
%
%

4.

1 No

1.5 hr
1 No
5%
%
%
%

Remarks
Note: UR-Hourly use rate
.
HA & OH may be
allowed subject to the
nature of works

Total
2.

Amount

Felling trees of girth beyond 30cm and upto


120cm including cutting trunks and
branches, removing the roots completely and
stacking serviceable materials .

Chain saw wood cutter (up to 4 HP)- (UR)


Helper
Sundries, ropes, etc. of above two items
HA
OH
CP
Total

1 hr
1 Each

/Each

Felling trees of girth beyond 120 cm and


upto 240cm including cutting trunks and
branches, removing the roots completely and
stacking serviceable materials .

Chain saw wood cutter (above 4 HP)- (UR)


Helper
Sundries, ropes, etc. of above two items
HA
OH
CP
Total

1 hr
1 Each

/Each

5.

1 No

3.5 hr
2 No
5%
%
%
%

6.

1 No

0.17 hr
0.08 No
5%
%
%
%

7.

1 No

1 hr
0.25 No
5%
%
%
%

Felling trees of girth beyond 240cm


including cutting trunks and branches,
removing the roots completely and stacking
serviceable materials .
Chain saw wood cutter (above 4 HP)- (UR)
Helpers
Sundries, ropes, etc. of above two items
HA
OH
CP
Total

1 hr
1 Each

/Each

Felling arecanut trees including cutting


trunks and removing the roots completely
and stacking serviceable materials .

Chain saw wood cutter (up to 4 HP)- (UR)


Helper
Sundries, ropes, etc. of above two items
HA
OH
CP
Total

1 hr
1 Each

/Each

Felling coconut and palm trees including


cutting trunks and removing the roots
completely and
stacking
serviceable
materials .
Chain saw wood cutter (up to 4 HP)- (UR)
Helper
Sundries, ropes, etc. of above two items
HA
OH
CP
Total

1 hr
1 Each

/Each

CHAPTER II
DISMANTLING AND DEMOLITION
Sl.
No.
1

Quantity
1 m3

0.70 No
%
%
%

Description of items

Rate

Unit

1 m3

1.60 No
%
%
%

Note: UR-Hourly use


rate .
HA & OH may
be allowed subject to the
nature of works

Man
HA
OH
CP

1 Each

/m3

Dismantling, clearing away and carefully


stacking materials useful for reuse for any
thickness of walls of brick, laterite or rubble
in cement mortar /Lime/Surkhi mortar
including disposal of debris within a distance
of 150 m.
Man
HA
OH
CP

1 Each

/m3

Total
3

1 m3

Cutting/chipping and removing portions of


existing RCC works carefully without
damaging the remaining structure and
removing the debris within a distance of 150
m.

12 hr
1 No
5%
%
%
%

Concrete cutter up to 2.5 HP - (UR)


Man
Scaffolding,platform, etc. of above two items
HA
OH
CP
Total

1 m2

0.025 No
0.025 No
%
%
%

Remarks

Dismantling, clearing away and carefully


stacking materials useful for reuse for any
thickness of walls of brick, laterite or rubble
in mud /dry, including disposal of debris
within a distance of 150 m.

Total
2

Amount

1 Each
1 Each

/m3

Lifting and removing tiles set in mortar in


floors, including clearing and stacking
materials and removing the debris within a
distance of 150 m.
Mason
Man
HA
OH
CP

1 Each
1 Each

Total

/m2

1 m2

0.05 No
%
%
%

Dismantling and removing Mangalore tiles


over roofs including ridges, hips, vallery
sheets, wind ties and bordering but excluding
roof timber and stacking materials within a
distance of 150 m.
Man
HA
OH
CP

1 Each

/m2

Total
6

1 m2

0.10 No
%
%
%

1 m3

1.40 No
1.40 No
%
%
%

Dismantling and removing pan or pot tiles


over roofs and stacking materials within a
distance of 150 m.
Man
HA
OH
CP
Total

1 Each

/m2

Dismantling and removing wrought and


framed timbers in roofs and floors and
stacking materials within a distance of 150 m

Carpenter
Man
HA
OH
CP

1 Each
1 Each

/m3

Total
8

1 Each

0.20 No
0.18 No
0.30 No
%
%
%

Dismantling and removing doors with or


without ventilators including removal of
shutters, hinges, holdfasts and all other
fittings and stacking materials within a
distance of 150 m.
Mason
Carpenter
Man
HA
OH
CP

1 Each
1 Each
1 Each

Total
9

1 No

0.15 No
0.10 No
0.20 No
%

/Each

Dismantling and removing windows with or


without ventilators including removal of
shutters, hinges, holdfasts and all other
fittings and stacking materials within a
distance of 150 m
Mason
Carpenter
Man
HA

1 Each
1 Each
1 Each

%
%

OH
CP
Total

10

1 No

0.10 No
0.05 No
0.10 No
%
%
%

/Each

Dismantling and removing ventilators


including removal of shutters, hinges,
holdfasts and all other fittings and stacking
materials within a distance of 150 m
Mason
Carpenter
Man
HA
OH
CP

1 Each
1 Each
1 Each

Total
11

1 m2

0.035 No
0.035 No
%
%
%

/Each

Dismantling, removing and lowering planked


sheeting, boarded floor, ceiling, etc. and
stacking materials within a distance of 150
m.
Carpenter
Man
HA
OH
CP

1 Each
1 Each

/m2

Total
12

1 m2

0.10 No
0.10 No
%
%
%

Taking down shutters of doors, with or


without ventilators including removal of
hinges and all other fittings and stacking
within a distance of 150 m.
Carpenter
Man
HA
OH
CP

1 Each
1 Each

/m2

Total
13

1 m2

0.10 No
0.05 No
%
%
%

Taking down shutters of windows with or


without ventilators including removal of
hinges and all other fittings and stacking
within a distance of 150 m.
Carpenter
Man
HA
OH
CP

1 Each
1 Each

/m2

Total
14

1 m2

0.05 No

Taking down shutters of ventilators


including removal of hinges and all other
fittings and stacking within a distance of 150
m.
Carpenter

1 Each
5

0.02 No
%
%
%

Man
HA
OH
CP

1 Each

/m2

Total
15

1 m2

0.035 No
0.035 No
%
%
%

Dismantling and removing AC sheet over


roof including loosening the purlins,ridge
pieces, nuts, bolts and all other fittings and
stacking materials within a distance of 150m
Fitter
Man
HA
OH
CP

1 Each
1 Each

/m2

Total
16

1 m2

0.02 No
0.02 No
%
%
%

17

1 Kg

0.004 No
0.004 No
0.003 No
%
%
%

Dismantling and removing roofing sheet


other than AC sheets over roof including
loosening the purlins,ridge pieces, nuts, bolts
and all other fittings and stacking materials
within a distance of 150m
Fitter
Man
HA
OH
CP
Total

1 Each
1 Each

/m2

Dismantling and removing steel truss, purlins


etc. and all other fittings and stacking
materials within a distance of 150m
Blacksmith
Heavy load mazdoor
Man
HA
OH
CP

1 Each
1 Each
1 Each

Total
18

1 Kg

0.005 No
0.003 No
%
%
%

/Kg

Dismantling and removing steel gate, grills


etc. and all other fittings and stacking
materials within a distance of 150m
Heavy load mazdoor
Man
HA
OH
CP

1 Each
1 Each

Total

/Kg

19

1 m2

0.06 No
0.07 No
0.10 No
%
%
%

20

1 m3

0.50 No
%
%
%

21

1 m3

3.00 hr.
0.75 No
%
%
%

22

1 m3

4.00 hr.
1.00 No
5%
%
%
%

Dismantling
and
removing
rolling
shutter,collapsible gate and all other fittings
and stacking materials within a distance of
150m
Fitter
Mason
Man
HA
OH
CP
Total
Demolishing mud or sundried brick walls of
any thickness including disposal of debris
within a distance of 150 m.
Man
HA
OH
CP
Total
Demolishing plain cement concrete and
clearing away the debris within a distance of
150 m.
Concrete cutter up to 2.5 HP - (UR)
Man
HA
OH
CP
Total

1 Each
1 Each
1 Each

/m2

1 Each

/m3

1 hr
1 Each

/m3

Demolishing
R.C.C.
work
including
separately removing and stacking available
reinforcement and clearing away the debris
within a distance of 150 m.
Concrete cutter up to 2.5 HP - (UR)
Man

1 hr
1 Each

Scaffolding,platform, etc. of above two items


HA
OH
CP
/m3

Total

23

1 m2

0.05 No
%
%
%

Demolishing and removing old cement


plaster and disposal of the debris within a
distance of 150 m.
Man
HA
OH
CP

1 Each

Total

/m2

CHAPTER III
EXCAVATION AND ALLIED WORKS
Sl.
No.
1

Quantity
1 m3

0.04 hr
%
%
2

1 m3

0.025 hr
0.100 hr
%
%

Description of items

Rate

Unit

1 m3

20 %

Note: UR-Hourly use rate


.
HA & OH may be
allowed subject to the
nature of works

Excavator (0.93 m3) for excavating ,


loading, etc. (UR)

1 hr

OH
CP
/m3

Total
Common excavation in all classes of soil
including boulders up to 500 dm3 in size and
disposing the unserviceable materials within
up to 1 km lead and all lifts
Excavator (0.93 m3) for excavating ,
loading, etc. (UR)

Add 0.04 hour for every


additional km lead for
tipper use rate

1 hr

Tipper (7 T) for conveyance (UR)


OH
CP

1 hr

/m3

Common excavation in all classes of soil


including boulders up to 500 dm3 in size and
disposing the unserviceable materials ( in or
under water or liquid mud)
Rate of item 1 or 2 above
Add 20% of the above
/m3

Total
4

1 m3

0.32
2.50
3.13
0.037
0.018
0.04

Kg
No.
m
No.
No.
hr.
%
%
%

Remarks

Common excavation in all classes of soil


including boulders up to 500 dm3 in size and
disposing the unserviceable materials within
50 m lead and all lifts

Total
3

Amount

Excavation in rock and boulders above 500


dm3 in size in wet/ dry condition at all
elevations using modern explosives with jack
hammer etc. drilling, conveying and
disposing the unserviceable materials with in
50 m lead and all lift and cost of compressed
air, jack hammer, water line, etc.
Special gelatine 80%
Electric detonator
Drilling with jack hammer
Blaster for charging
Helper
Excavator (0.93 cum) for excavating ,
loading, etc. (UR)
HA
OH
CP

25
1
1
1
1

Kg
Each
m
Each
Each

1 hr.

Total

/m3

1 m3

0.32 Kg

Special gelatine 80%

2.50 No.

Electric detonator

1 Each

3.13 m

Drilling with jack hammer

1m

0.037 No.

Blaster for charging

1 Each

0.018 No.

Helper

1 Each

0.025 hr.

Excavator (0.93 cum) for excavating ,


loading, etc. (UR)
Tipper (7 T) for conveyance (UR)

1 hr.
1 hr

0.10 hr
%
%
%
6

Add 0.04 hour for every


additional km lead for
tipper use rate

Excavation in rock and boulders above 500


dm3 in size in wet/ dry condition at all
elevations using modern explosives with jack
hammer etc. drilling, conveying and
disposing the unserviceable materials up to 1
km lead and all lift and cost of compressed
air, jack hammer, water line, etc.

1 m3

0.19
3.00
3.75
0.037
0.018
0.04

Kg
No.
m
No.
No.
hr.

0.05 No.
8.30 No.
%
%
%

25 Kg

HA
OH
CP
/m3

Total
Excavation in rock and boulders above 500
dm3 in size by controlled and protected
blasting in wet/ dry condition at all
elevations using modern explosives with jack
hammer etc. drilling, conveying and
disposing the unserviceable materials within
50 m lead and all lift and cost of compressed
air, jack hammer, water line, etc.

Special gelatine 80%


Electric detonator
Drilling with jack hammer
Blaster for charging
Helper
Excavator (0.93 cum) for excavating ,
loading, etc. (UR)

25
1
1
1
1

Kg
Each
m
Each
Each

1 hr.

Man for filling, tying, placing and replacing


gunny bags
Gunny bags( used 2 times)
HA
OH
CP
Total

1 Each
10 No.

/m3

1 m3

0.19
3.00
3.75
0.037
0.018
0.025

Kg
No.
m
No.
No.
hr.

0.10 hr
0.05 No.
8.30 No.
%
%
%

1 m3

34.00
25.00
0.50
0.50
5

Kg
m
No
No
%

0.04 hr.
%
%
%

Add 0.04 hour for every


additional km lead for
tipper use rate

Excavation in rock and boulders above 500


dm3 in size by controlled and protected
blasting in wet/ dry condition at all
elevations using modern explosives with jack
hammer etc. drilling, conveying and
disposing the unserviceable materials up to 1
km and all lift and cost of compressed air,
jack hammer, water line, etc.
Special gelatine 80%
Electric detonator
Drilling with jack hammer
Blaster for charging
Helper
Excavator (0.93 cum) for excavating ,
loading, etc. (UR)
Tipper (7 T) for conveyance (UR)
Man for filling, tying, placing and replacing
gunny bags
Gunny bags( used 2 times)
HA
OH
CP
Total

25
1
1
1
1

Kg
Each
m
Each
Each

1 hr.
1 hr
1 Each
10 No.

/m3

Excavation in rock and boulders above 500


dm3 in size by non explosive agent/splitter or
any other method with out resorting to the
use of conventional explosive materials with
jack hammer etc. drilling, conveying and
disposing the unserviceable materials within
50m leads and all lifts, cost of compressed
air, jack hammer, water, etc.
Cost of non explosive
Drilling with jack hammer
Hammermen
Men for picking etc.
Usage of wedge, crow bar, dewatering etc.
@ 5% total of above
Excavator (0.93 cum) for excavating ,
loading, etc. (UR)
H.A
OH
CP
Total

10

1
1
1
1

Kg
m
Each
Each

1 hr.

/m3

1 m3

34.00
25.00
0.50
0.50
5

Kg
m
No
No
%

0.025 hr.
0.10 hr
%
%
%

Add 0.04 hour for every


additional km lead for
tipper use rate

Excavation in rock and boulders above 500


dm3 in size by non explosive agent/splitter or
any other method with out resorting to the
use of conventional explosive materials with
jack hammer etc. drilling, conveying and
disposing the unserviceable materials up to 1
km lead and all lifts, cost of compressed air,
jack hammer, water, etc.
Cost of non explosive
Drilling with jack hammer
Hammermen
Men for picking etc.
Usage of wedge, crow bar,dewatering etc. @
5% total of above
Excavator (0.93 cum) for excavating ,
loading, etc. (UR)
Tipper (7 T) for conveyance (UR)
H.A
OH

1
1
1
1

Kg
m
Each
Each

1 hr.
1 hr

CP
/m3

Total
10

1 hp/hr

10.00 hp/hr
20.00 m
5%

%
%

Bailing out of water with pump including


conveyance to the site and erection, cost of
fuel, lubricating oil and other stores
including accessories, labour charges etc.
Rate for 10 hp/hr
Pump charges (UR)
Accessories (UR)
Conveyance and erection charges, temporary
bund, etc. @ 5% of above two items

10 hp/hr
60 m

OH
CP
Total for 10 hp/hr
Hence for 1 hp/hr

11

1 m2

/hp/hr

Providing steel shoring using


plates,
angles etc. of suitable size and thickness and
to maintain the shoring so as not to affect the
work till the works are completed including
cost of all labours, materials , erection and
dismantiling charges etc

35.00 Kg

steel angles

1 Qtl

60.00 Kg
20.00 %

steel plates
Fabrication charges, cost of ties, nails, ropes
etc @ 20% above items
Foreman
Khalasi
Man
H.A
OH
CP

1 Qtl

0.10 No
0.30 No
0.30 No
%
%
%

Total

11

Angles and plates - 20


times usage

1 Each
1 Each
1 Each

/m2

12

1 m3

5.40
0.50
0.50
5

m
No.
No.
%

0.04 hr.
%
%
%

Chiselling, Wedging, barring, picking, etc.


on hard rock / concrete wherever necessary
and disposing the unserviceable materials
within 50 m leads including all charges
Drilling with jack hammer
Hammerman
Men for picking etc.
Usage of wedge, crow bar, etc. @ 5% total
of above
Excavator (0.93 cum) for excavating ,
loading, etc. (UR)
HA
OH
CP

1m
1 Each
1 Each

1 hr.

/m3

Total
13

1 m3

5.40
0.50
0.50
5

m
No.
No.
%

0.025 hr.
0.10 hr
%
%
%

Add 0.04 hour for every


additional km lead for
tipper use rate

Chiselling, Wedging, barring, picking, etc.


on hard rock / concrete wherever necessary
and disposing the unserviceable materials up
to 1 km lead including all charges.
Drilling with jack hammer
Hammerman
Man for picking etc.
Usage of wedge, crow bar, etc. @ 5% total
of above
Excavator (0.93 cum) for excavating ,
loading, etc. (UR)
Tipper (7 T) for conveyance (UR)
HA
OH

1m
1 Each
1 Each

1 hr.
1 hr

CP
/m3

Total
14

1 m3
0.175 No
%
%
%

Stacking rubble for measurment including


all labour charges.
Man
HA
OH
CP
Total

12

1 Each

/m3

15

1 m2

0.10
2.00
130.00
5

No.
min
litres
%
%
%
%

16

1 Bag

1.00 Bag
0.01 No.
%
%
%

Foundation preparation for placing concrete


including chisel dressing wherever required
at all elevations and cleaning the surface with
compressed air and water etc.and disposing
the unserviceble materials including all lead,
lift conveyance and labour charges etc.

Man for cleaning


Cost of compressed air at 100 cfm
Water charges
Air and water connection @ 5% of ii and iii
above
HA
OH
CP
Total

1 Each
1 hr
1000 litres

/m2

Providing earth filled bag wherever


necessary including cost and conveyance of
all materials, labour charges, etc.
Empty bag
Man
HA
OH
CP

/Bag

Total
17

1 m3

0.04 hr.
%
%
18

1m

0.03 hr.
0.10 hr
%
%

Back filling with departmental earth within


50m lead and all lift, labour charges, etc.
Excavator for loading, spreading and
levelling etc. (UR)
OH
CP

1 hr.

/m3

Total
Back filling with departmental earth within
up to 1 km lead and all lift, labour charges,
etc.
Excavator for loading,spreading and
levelling etc. (UR)
Tipper (7 T) for conveyance (UR)
OH
CP

Add 0.04 hour for every


additional km lead for
tipper use rate

1 hr.
1 hr

/m3

Total
19

1 m3

Back filling with contractors earth including


all leads and lifts, labour charges, etc.

1.00 m3
0.03 hr.

Earth for filling


Excavator for spreading and levelling etc.
(UR)
OH
CP
Total

%
%

Note: If earth is not


avilable free of cost, cost
may be included

1 Each
1 Each

13

1 m3
1 hr.

/m3

20

1 m3

0.04 hr.
%
%

Back filling with departmental earth within


50 m lead and lift and compacting in layers
including , labour charges etc.
Excavator for loading, spreading, levelling
and compacting etc. (UR)
OH
CP

1 hr.

/m3

Total
21

1 m3

0.03 hr.
0.10 hr
%
%

22

1 m3

Back filling with contractors earth and


compacting in layers including all lead and
lift , labour charges etc.

1.00 m3
0.03 hr.

Earth for filling


Excavator for spreading and levelling etc.
(UR)
OH
CP
Total

%
%

23

Back filling with departmental earth up to 1


km lead and lift and compacting in layers
including , labour charges etc.
Excavator for loading, spreading, levelling
and compacting etc. (UR)
Tipper (7 T) for conveyance (UR)
OH
CP
Total

1 m2

0.16 No.
%
%
%

Turfing the slopes with sods including


trimming, dressing and watering as required
until the turf properly takes root and in any
case for a period not less than 1 month
including cost of all materials, labour charges
etc.
Man
HA
OH
CP
Total

14

Add 0.04 hour for every


additional km lead for
tipper use rate

1 hr.
1 hr

/m3

3
1m

1 hr.

/m3

1 Each

/m2

Open well excavation


24(a)

1m

2.60 No.
10 %
%
%
%

24(b)

1 m3

20 %

Note: in or under water


or liquid add 20 % extra.
For rock, 2 times of
corresponding rate of soil

Open well excavation in all classes of soil


for all diameters, and disposing the
unserviceable materials within 150m
including all lead and lift.
For first depth upto 1.50m
Man for digging, shaping, lifting, conveying,
etc.
Cost of tools, lifting arrangements, etc. @
10% of above
H.A on
OH on
CP on
Total

1 Each

/m3

For every subsequent depth of 1.50m or part


there of.
3
1m

Rate vide item above 23(a)


Add 20% extra
Total

15

/m3

CHAPTER IV
DRILLING AND GROUTING
Sl.
No
1

Quantity

Description of items

1m

Drilling holes for providing anchor /dowel


bars varying in depth and diameter in rock or
concrete and cleaning the holes, grouting
with cement grout (CM 1:2) after fixing
dowel bars including cost of all materials,
labour etc. complete as per specification and
drawings.

1.67
0.002
1.00
5

Kg
m3
m
%
%
%

1 Set

km
km
3.00 No
4.00 No

%
%
%

Rate

Cement
M sand / river sand
Drilling with jack hammer
Conveyance of materials, cleaning, fixing,
grouting charges, etc. @ 5% of above
OH
CP
Total

Unit

1 No.

1.00 No.
1.00
2.00
4.00
20.00
0.05

No.
No
No
No
No.
%
%
%

Remarks
Note: 1. UR-Hourly use
rate. HA & OH may be
allowed subject to the
nature of works.
2. Cost of cement may be
included in the item or
excluded and measured
as a separate item.

1 MT
1 m3
1m

/m
Transporting back need
not be considered if the
machine is not conveyed
back.

Transporting drilling machine, pumpset and


other accessories including loading and
unloading charges, and transporting back
after competion of works as per the direction
of departmental officers.( Approximate wt 5
MT)
Lorry conveyance in plain
Lorry conveyance in hilly
Khalasis for loading and unloading
Man for loading and unloading
Total
Transporting back @ 100% of above
HA
OH
CP

1
1
1
1

MT
MT
Each
Each

/Set

Total
3

Amount

Conveying the drilling machine, pumpset and


accessories to drilling location, erecting,
dismantling and shifting to nearest location/
road access including all leads, lifts, labour
and machine charges etc.
First class mechanic

1 Each

Fitter
Khalasis
Man
Gunny bags( used 2 times)
Man for filling, tying, placing and replacing
gunny
HA bags
OH
CP
Total
16

1
1
1
10
1

Each
Each
Each
Nos.
Each

/Each

1m

1.00 m
0.10 hr.
5%
%
%

1m

1.00 m
2.00 hr
%
%

Drilling in soil consisting of earth and


boulders using diamond drill, and re-drilling
wherever required, including labour charges,
machinery, air, water, etc.
Drilling with diamond drill in soil (UR)
10 hp pump (UR)
Provision for casing pipe, clamp, etc. @ 5%
of above items
OH
CP
Total

1m
1 hr.

/m

Drilling in rock / concrete using diamond


drill(without cores), and re-drilling wherever
required,
including
labour
charges,
machinery, air, water, etc.
Drilling with diamond drill in rock(UR)
10 hp pump (UR)
OH
CP

1m
1 hr.

/m

Total
6

1m

Drilling in rock / concrete using diamond


drill (with core), and re-drilling wherever
required, taking cores, serially numbering
with paint, placing the same in core boxes
and transporting including labour charges,
machinery, air, water, etc. (excluding cost of
core box)

1.00 m
2.00 hrs.
10 %

Drilling with diamond drill in rock(UR)


10 hp pump (UR)
Provision for core barrel, collecting cores,
numbering, placing in core box, transporting
etc. @ 10% of above items
OH
CP
Total

%
%

1m

1.00 m
0.50 hr.
%
%

Drilling in rock / concrete using percussion


drill, and re-drilling wherever required,
including labour charges, machinery, air,
water, etc.
Drilling with percussion drill
10 hp pump (UR)
OH
CP
Total

17

1m
1 hr.

/m

1m
1 hr.

/m

1 Set

Hook-up to grout holes for washing seams,


cavities, etc. in foundation and testing holes
in such a way that in a group of four holes
are selected for washing foundation, one hole
is capped for water, two for air and other left
open to permit the outflow of washed
materials using compressed air required at
the rate of 200 cfm and water at 500 litres/
minute including cost and conveyance of all
materials, labour charges, shifting, etc
complete as per standard specifications and
as directed by the departmental officers.

0.75 hr.

Air compressor 250 cfm(UR)

5000 litres

Charges for water

0.25 hr.
0.50 No.
1.00 No.
%
%
%

Grout pump (10 HP) (UR)


Foreman
Man
HA
OH
CP

100 cfm
1000 litres
1 hr.
1 Each
1 Each

Total
9

50 Kg

50.00
0.25
375.00
0.002
10

Kg
hr.
litres
m3
%
%
%

/Set

Pressure grouting with cement with/without


packers at required consistency including all
labour charges, machinery, equipment, air,
water, etc. as per specifications and as
directed by the departmental officers, but
excluding cost of cement.
Cement
Grout pump (10 HP)
Cost of water
Cost of M sand / R sand
Shifting and mixing charges, sealing seams,
etc. @ 10% of above items
OH
CP
Total

18

1
1
1000
1

MT
hr.
litres
m3

/50Kg

10

1 Kg

Supplying M.S core boxes with 150x60x10


cm with 7 inside compartments and hinged
top cover with locking arrangements and 2
Nos. handle on sides, using 2mm thick M.S
plate and 30x5mmM.S flats including
cutting, shaping, welding, applying a coat of
iron primer after scrapping and cleaning,
painting with 2 coats of synthetic enamel
paint, painting bore hole details and name
scheme on both sides of lid for identification,
etc. complete as per direction of
departmental officers.

0.263 Kg

MS flats ( assume 25% of weight of box)

0.788 Kg

MS plates ( assume 75% of weight of box)

1 Qtl.
1 Qtl.
1.00 No

Welding rods, 8g

0.05
0.05
0.02
5

Blacksmith
Fitter
Welder
Hire charges,painting charges, sundries,
conveyance, etc. @ 5% above
H.A
OH
CP
Total

No
No
No
%
%
%
%

11

100 No.

1 Kg

Providing rock bolts of specified diameter


and length, cutting and threading steel rods
after drilling at specified locations at all
elevations including cost of all materials,
cement, scaffolding, labour, curing etc,

9.73 Kg
3.14 Kg
20 %

20mm dia. MS rod 3.1m long


MS plate 200X200x10mm
Cutting, threading , fabrication , cost of nut
etc @ 20% of above items
Drilling hole with jack hammer
Cement
Fitter
Man
Scaffolding, sundries, etc. @ 5% of above
items
H.A
OH
CP
Total
Hence for 1Kg

3.00
3.00
0.20
0.50
5

m
Kg
No.
No.
%
%
%
%

19

1 Each
1 Each
1 Each

/Kg

1 Qtl
1 Qtl

1
1
1
1

m
MT
Each
Each

/Kg

12

1 Kg

1 Kg
0.015 No.
%
%
%

Providing anchor bars of varying depth using


Tor steel, bend, jumped, etc. including cost
and conveyance of steel, labour charges, etc.
complete as per the specifications and
drawing as directed by the departmental
officers.
Tor steel
Black smith
H.A
OH
CP

1 Qtl
1 Each

Total

20

/Kg

CHAPTER V
REINFORCEMENT AND FORMWORK
Sl.
No
1

Quantity
1 Kg

Description of items

Rate

Unit

Amount

Remarks

Reinforcement for RCC works bent, tied and


placed in position using Tor steel including
cost and conveyance of all materials and all
labour charges etc. complete.
Data for 1 Qtl

1.00
0.45
1.00
1.48

Qtl
Kg
No.
No.
%
%
%

TMT steel
Iron wire for tying (16G)
Black smith
Man
H.A
OH
CP

1
1
1
1

Qtl
Kg
Each
Each

Total
Hence for 1 Kg
2

1 No

/Kg

Welding "V" cut ends for Reinforcement


bars (36 mm dia) including cost and
conveyance of all materials, labour charges
etc. complete but excluding cost of steel.
100 No

36 mm dia - 6.50 nos.


32 mm dia - 5.00 nos.
25 mm dia - 3.50 nos.
22 mm dia - 3.00 nos.
20 mm dia - 2.25 nos.
16 mm dia - 1.50 nos.
12 mm dia
1.00 nos.
Gauge of welding rod
8g/10g/12g
may
be
decided according to the
reinforcement bar dia.

6.50 No

Welding Rod

0.48 hrs

Welding set

1 hr

36 mm dia
32 mm dia
25 mm dia
22 mm dia
20 mm dia
16 mm dia
12 mm dia -

0.125 No

Blacksmith

1 Each

36
32
25
22
20
16
12

21

mm dia
mm dia
mm dia
mm dia
mm dia
mm dia
mm dia

- 0.48 hrs.
- 0.40 hrs.
- 0.36 hrs.
- 0.32 hrs.
- 0.28 hrs
- 0.24 hrs.
0.24 hrs.

- 0.125 nos.
- 0.100 nos.
- 0.100 nos.
- 0.080 nos.
- 0.070 nos.
- 0.060 nos.
- 0.050 nos.

0.25 No

Special Mazdoor

1 Each

36
32
25
22
20
16
12

0.25 No

Man

1 Each

36
nos.
0.20
mm
22
nos.
dia
16
nos.
dia

Welder

1 Each

36 mm dia
32 mm dia
25 mm dia
22 mm dia
20 mm dia
16 mm dia
12 mm dia

0.125 No

%
%
%

1 m2

a
26.98 Kg
18.01 Kg
19.50 Kg

/Each

Formwork for concrete works including cost


and conveyance of all materials, labour
charges etc. complete.
For slabs
Structural steel (average cost of MS channel
and MS joists)
MS plate
MS rounds, pipes etc ( average cost of MS
round and MS plates)

22

life 25 times

1 Qtl
1 Qtl

life 15 times
life 25 times

1 Qtl

- 0.25 nos.
- 0.20 nos.
- 0.20 nos.
- 0.16 nos.
- 0.14 nos.
- 0.12 nos.
- 0.10 nos.

mm dia
- 0.25
32 mm dia nos.
25
dia
- 0.20 nos.
mm dia
- 0.16
20 mm
0.14 nos.
mm dia
- 0.12
12 mm
- 0.10 nos.

HA
OH
CP
Total

mm dia
mm dia
mm dia
mm dia
mm dia
mm dia
mm dia

- 0.125 nos.
- 0.100 nos.
- 0.100 nos.
- 0.080 nos.
- 0.070 nos.
- 0.060 nos.
- 0.050 nos.

20.00 %
0.01 No.
0.10 No.
0.10 No.
%
%
%
b
10 %

c
20 %

Fabrication charges, wooden planks, cleats,


sundries etc@ 20% of above
Foreman
Khalasi
Man
HA
OH
CP
Total
For lintels, sunshades and beams
Rate for slabs
Add extra 10 %
Total

Note: Form work for


roof slab of more than 4
m height in a single
stretch, add 20% extra
for 2m additional height,
of rate of formwork.

1 Each
1 Each
1 Each

Note: For additional lift


of form work for building
works,for first floor 10 %
of labour over Ground
floor ,for 2 nd floor 20 %
of labour over ground
floor, for 3rd floor 30 %
of labour over ground
floor and so on.For other
than building works, lift
taken as every 3m and %
of labour same as that of
building works.

For columns
Rate for slabs
Add extra 20 %
Total

23

/m2

CHAPTER VI
CONCRETING
All measurements shall be taken to the nearest centimetre, except that thickness of slabs, partition, etc., and sectional dimensions in
case of posts, columns, beams and the like shall be taken to the nearest half centimetre.
No deductions shall be made for (1) ends of dissimilar materials (eg. Joist beams, posts, girders, rafters, purlins, trusses, corbels,
steps, etc.) upto 500 cm 2 in section. (2) opening upto 0.10 m 2 .Note:- In calculating area of opening upto 0.10 m 2 , the size of opening
includes the thickness of any seperate lintels or sills.No extra labour for forming such openings or voids shall be measured.
In volume occupied by water pipes, conduits, etc., not exceeding 25 cm 2 each in cross sectional area shall not be deducted.
Reinforcement shall be measured separately and paid for.
In T- beam construction, the floor or roof shall be taken as running continuosly through, and the beams as that portion above or
below the floor or roof.
Columns shall be measured from the floor surface to the underside of beams or slabs as the case may be. Where columns are
connected to beams by haunchings, the columns shall be measured upto the springing of the haunchings and the latter included with the
beams. Where the width of the beam is less than the width of the column, the extra width at the junction shall be included with the beam.

Sl.
No
1

Quantity
1 m3

Rate

Unit

1m

40 mm coarse aggregate

3
1m

20 mm coarse aggregate

12 mm coarse aggregate
Water including for curing
Batching and mixing plant (UR) forbatching
and mixing
Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead)

0.42 m

0.52 m
0.30 m

0.21 m
150.00 litre
0.08 hr.
0.08 hr.
No
No
hr.
No.
%
%
%

1 m3

210 Kg

Note: 2. Add 0.05 hour


for every additional km
lead for Transit mixer
use rate -Transit mixer -

2m 3 volume

1m

Man for placing


Mason for placing
Vibrator (UR)
Man for curing
H.A
OH

3
1m
1000 litre
1 hr.

Note 3. For additional


lift of concrete, for
building works,for first
floor 15 % of labour over
Ground floor ,for 2 nd
floor 30 % of labour over
ground floor, for 3rd
floor 45 % of labour over
ground floor and so
on.For
other
than
building
works, lift
taken as every 3m and %
of labour same as that of
building works.

1 hr.
1
1
1
1

Each
Each
hr.
Each

CP
/m3
Note 4. Cost of cement
may be included in the
item or excluded and
measured as separate
items.

Cement concrete M10 with 40mm graded


aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials and labour charges, etc.
complete but excluding cost of cement.

0.45 m

Cement
M sand / R sand

3
1m

3
0.47 m

40 mm coarse aggregate

3
1m

3
0.28 m

20 mm coarse aggregate

3
1m

Remarks

1 MT

Total
2

Amount

Note:1 UR - Hourly use


rate.
HA & OH may
be allowed subject to the
nature of works

Cement concrete M7.5 with 40mm graded


aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials, labour and conveyance
charges, etc. complete but excluding cost of
cement.
Cement
M sand / R sand

180.00 Kg

1.95
0.20
0.20
0.25

Description of items

1 MT

24

3
0.19 m
165 lit.
0.08 hr.

0.08 hr.
1.95
0.20
0.20
0.25

No
No
hr.
No.
%
%
%

1 m3

200.00 Kg

3
1m
1000 litre

1 hr.
1
1
1
1
1

hr.
Each
Each
hr.
Each

Cement concrete M15 with 75mm graded


aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials and labour charges, etc.
complete but excluding cost of cement.
Cement
M sand / R sand

1 MT

3
0.35 m

75 mm coarse aggregate

3
1m

3
0.35 m

40 mm coarse aggregate

3
1m

3
0.28 m

20 mm coarse aggregate

3
1m

0.08 hr.
0.05 hr.
1.95
0.20
0.20
0.25

No
No
hr.
No.
%
%
%

1 m3

230.00 Kg

3
1m

12 mm coarse aggregate
Water including for curing
Batching and mixing plant (UR) forbatching
and mixing
Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead)
Man for placing
Mason for placing
Vibrator (UR)
Man for curing
HA
OH
CP
Total

3
1m
1000 litre

1 hr.
1
1
1
1
1

hr.
Each
Each
hr.
Each

/m3

Cement concrete M15 with 40mm graded


aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials and labour charges, etc.
complete but excluding cost of cement.
Cement
M sand / R sand

1 MT

0.48 m

40 mm coarse aggregate

3
1m

3
0.33 m

20 mm coarse aggregate

3
1m

0.43 m

3
0.21 m
170.00 litre

0.08 hr.

Note 5. If the placing of


concrete is done by
pump, instead of 1.95 No.
man for placing, add 0.04
hr. Concrete pump and
accessories for placing
concrete (UR) and 0.02
No. man for placing.

/m3

3
0.39 m

3
0.20 m
165.00 litre

12 mm coarse aggregate
Water including for curing
Batching and mixing plant (UR) for batching
and mixing
Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead)
Man for placing
Mason for placing
Vibrator (UR)
Man for curing
H.A
OH
CP
Total

3
1m

12 mm coarse aggregate
Water including for curing
Batching and mixing plant (UR) forbatching
and mixing
25

3
1m
1000 litre

1 hr.

0.08 hr.
1.95
0.20
0.20
0.25

No
No
hr.
No.
%
%
%

1 m3

305.00 Kg
3

0.48 m

0.57 m

0.26
215.00
0.08
0.08

m3
litre
hr.
hr.

1.95
0.20
0.20
0.25

No
No
hr.
No.
%
%
%

1 m3

245.00 Kg

Transit mixer (UR) for conveyance to site of


placement ( up to 1 Km lead)
Man for placing
Mason for placing
Vibrator (UR)
Man for curing
H.A
OH
CP
Total
Cement concrete M15 with 20mm graded
aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials, labour and conveyance
charges, etc. complete but excluding cost of
cement.
Cement
M sand / R sand

1
1
1
1
1

hr.
Each
Each
hr.
Each

/m3

1 MT
3
1m
3
1m

20 mm coarse aggregate
12 mm coarse aggregate
Water including for curing
Batching and mixing plant (UR) forbatching
Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead)
Man for placing
Mason for placing
Vibrator (UR)
Man for curing
HA
OH
CP
Total

3
1m
1000 litre
1 hr.

1
1
1
1
1

hr.
Each
Each
hr.
Each

/m3

Cement concrete M20 with 75mm graded


aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials and labour charges, etc.
complete but excluding cost of cement.
1 MT

0.38 m

Cement
M sand / R sand

3
0.37 m

75 mm coarse aggregate

3
1m

3
0.32 m

40 mm coarse aggregate

3
1m

3
0.30 m

20 mm coarse aggregate

3
1m

3
0.19 m
165.00 lit.

0.08 hr.
0.05 hr.
1.95
0.20
0.20
0.25

No
No
hr.
No.
%
%

3
1m

12 mm coarse aggregate
Water including for curing
Batching and mixing plant (UR) forbatching
and mixing
Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead)
Man for placing
Mason for placing
Vibrator (UR)
Man for curing
HA
OH
26

3
1m
1000 litre

1 hr.
1
1
1
1
1

hr.
Each
Each
hr.
Each

CP
/m3

Total
7

1 m3

290.00 Kg

Cement
M sand / R sand

1 MT

0.44 m

40 mm coarse aggregate

3
1m

3
0.28 m

20 mm coarse aggregate

3
1m

0.44 m

3
0.21 m
195.00 lit.

0.08 hr.
0.08 hr.
1.95
0.20
0.20
0.25

Cement concrete M20 with 40mm graded


aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials and labour charges, etc.
complete but excluding cost of cement.

No
No
hr.
No.
%
%
%

1 m3

380.00 Kg
3

0.41 m

0.49 m

3
0.37 m
240.00 litre

0.08 hr.
0.08 hr.
1.95
0.20
0.20
0.25

No.
No.
hr.
No.
%
%
%

3
1m

12 mm coarse aggregate
Water including for curing
Batching and mixing plant (UR) forbatching
and mixing
Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead)
Man for placing
Mason for placing
Vibrator (UR)
Man for curing
H.A
OH
CP
Total
Cement concrete M20 with 20mm graded
aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials, labour and conveyance
charges, etc. complete but excluding cost of
cement.
Cement
M sand / R sand

3
1m
1000 litre

1 hr.
1
1
1
1
1

hr.
Each
Each
hr.
Each

/m3

1 MT
3
1m
3
1m

20 mm coarse aggregate
12 mm coarse aggregate
Water including for curing
Batching and mixing plant (UR) forbatching
and mixing
Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead)
Man for placing
Mason for placing
Vibrator (UR)
Man for curing
HA
OH
CP
Total

27

3
1m
1000 litre

1 hr.
1
1
1
1
1

hr.
Each
Each
hr.
Each

/m3

10

11

1 m3

395.00
0.44
0.47
0.30
245.00
0.08
0.08

Kg
m3
m3
m3
litre
hr.
hr.

1.95
0.20
0.20
0.25

No
No
hr.
No.
%
%
%

1 m3

390.00
0.37
0.50
0.28
0.15
215.00
0.08
0.08

Kg
m3
m3
m3
m3
litre
hr.
hr.

1.95
0.20
0.20
0.25

No
No
hr.
No.
%
%
%

1 m3

430.00 Kg
0.38 m3
0.52
0.34
240.00
0.08

m3
m3
litre
hr.

Cement concrete M20 with 12mm graded


aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials, labour and conveyance
charges, etc. complete but excluding cost of
cement.
Cement
M sand / R sand
12 mm coarse aggregate
6 mm coarse aggregate
Water including for curing
Batching and mixing plant (UR) forbatching
Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead)
Man for placing
Mason for placing
Vibrator (UR)
Man for curing
H.A
OH
CP
Total

1
1
1
1
1000
1
1
1
1
1
1

MT
m3
m3
m3
litre
hr.
hr.
Each
Each
hr.
Each

/m3

Cement concrete M25 with 40mm graded


aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials and labour charges, etc.
complete but excluding cost of cement.
Cement
M sand / R sand
40 mm coarse aggregate
20 mm coarse aggregate
12 mm coarse aggregate
Water including for curing
Batching and mixing plant (UR) forbatching
Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead)
Man for placing
Mason for placing
Vibrator (UR)
Man for curing
H.A
OH
CP
Total
Cement concrete M25 with 20mm graded
aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials, labour and conveyance
charges, etc. complete but excluding cost of
cement.
Cement
M sand / R sand
20 mm coarse aggregate
12 mm coarse aggregate
Water including for curing
Batching and mixing plant (UR) forbatching

28

1
1
1
1
1
1000
1
1
1
1
1
1

MT
m3
m3
m3
m3
litre
hr.
hr.
Each
Each
hr.
Each

/m3

1 MT
1 m3
1
1
1000
1

m3
m3
litre
hr.

0.08 hr.
1.95
0.20
0.20
0.25

12

No
No
hr.
No.
%
%
%

1 m3

405.00 Kg

1
1
1
1
1

hr.
Each
Each
hr.
Each

/m3

Cement concrete M30 with 40mm graded


aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials and labour charges, etc.
complete but excluding cost of cement.
Cement
M sand / R sand

1 MT

3
0.38 m
3
0.53 m

40 mm coarse aggregate

3
1m

3
0.26 m

20 mm coarse aggregate

3
1m

3
0.14 m
220.00 litre

0.08 hr.
0.08 hr.
1.95
0.20
0.20
0.25

13

Transit mixer (UR) for conveyance to site of


placement ( up to 1 Km lead)
Man for placing
Mason for placing
Vibrator (UR)
Man for curing
H.A
OH
CP
Total

No
No
hr.
No.
%
%
%

1 m3

3
1m

12 mm coarse aggregate
Water including for curing
Batching and mixing plant (UR) forbatching
and mixing
Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead)
Man for placing
Mason for placing
Vibrator (UR)
Man for curing
HA
OH
CP
Total

3
0.45 m

Cement concrete M30 with 20mm graded


aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials, labour and conveyance
charges, etc. complete but excluding cost of
cement.
Cement
M sand / R sand

3
0.54 m

20 mm coarse aggregate

435.00 Kg

3
0.36 m
220.00 litre

0.08 hr.
0.08 hr.
1.95
0.20
0.20
0.25

No
No
hr.
No.
%
%

3
1m
1000 litre

1 hr.
1
1
1
1
1

hr.
Each
Each
hr.
Each

/m3

1 MT
3
1m
3
1m

12 mm coarse aggregate
Water including for curing
Batching and mixing plant (UR) forbatching
and mixing
Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead)
Man for placing
Mason for placing
Vibrator (UR)
Man for curing
HA
OH
29

3
1m
1000 litre

1 hr.
1
1
1
1
1

hr.
Each
Each
hr.
Each

CP
/m3

Total
14

15

1 m3

420.00
0.36
0.51
0.27
0.14
225.00
0.08
0.08

Kg
m3
m3
m3
m3
litre
hr.
hr.

1.95
0.20
0.20
0.25

No
No
hr.
No.
%
%
%

1 m3

445.00
0.47
0.54
0.31
215.00

Kg
m3
m3
m3
litre

0.08 hr.
0.08 hr.
1.95
0.20
0.20
0.25

16

No
No
hr.
No.
%
%
%

1 m3

450.00 Kg
3
0.32 m
3
0.92 m

Cement concrete M35 with 40mm graded


aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials and labour charges, etc.
complete but excluding cost of cement.
Cement
M sand / R sand
40 mm coarse aggregate
20 mm coarse aggregate
12 mm coarse aggregate
Water including for curing
Batching and mixing plant (UR) forbatching
Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead)
Man for placing
Mason for placing
Vibrator (UR)
Man for curing
HA
OH
CP
Total
Cement concrete M35 with 20mm graded
aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials, labour and conveyance
charges, etc. complete but excluding cost of
cement.
Cement
M sand / R sand
20 mm coarse aggregate
12 mm coarse aggregate
Water including for curing
Batching and mixing plant (UR) forbatching
and mixing
Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead)
Man for placing
Mason for placing
Vibrator (UR)
Man for curing
HA
OH
CP
Total
Cement concrete M40 with 12mm graded
aggregates laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials, labour and conveyance
charges, etc. complete but excluding cost of
cement.
Cement
M sand / R sand
12 mm coarse aggregate
30

1
1
1
1
1
1000
1
1
1
1
1
1

MT
m3
m3
m3
m3
litre
hr.
hr.
Each
Each
hr.
Each

/m3

1
1
1
1
1000

MT
m3
m3
m3
litre

1 hr.
1
1
1
1
1

hr.
Each
Each
hr.
Each

/m3

1 MT
3
1m
3
1m

205.00 litre
0.08 hr.
0.08 hr.
1.95
0.20
0.20
0.25

17

No
No
hr.
No.
%
%
%

1 m3

280.00 Kg
3

0.60 m

3
0.40 m
175.00 litre

0.08 hr.
0.08 hr.
1.95
0.20
0.20
0.25

18

No
No
hr.
No.
%
%
%

1 m3

1 m3
10 %

Water including for curing


Batching and mixing plant (UR) forbatching
and mixing
Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead)
Man for placing
Mason for placing
Vibrator (UR)
Man for curing
HA
OH
CP
Total

1000 litre
1 hr.
1
1
1
1
1

hr.
Each
Each
hr.
Each

/m3

No-sand cement concrete 1:8 with 40mm


graded aggregates laying to lines and levels
at all elevations, consolidating, curing,
including cost of all materials and labour
charges, etc. complete but excluding cost of
cement.
Cement

1 MT

40 mm coarse aggregate

3
1m

20 mm coarse aggregate
Water including for curing
Batching and mixing plant (UR) forbatching
and mixing
Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead)
Man for placing
Mason for placing
Vibrator (UR)
Man for curing
HA
OH
CP
Total

3
1m
1000 litre

1 hr.
1
1
1
1
1

hr.
Each
Each
hr.
Each

/m3

Second stage concrete (with specified mixes)


at all elevations without disturbing the lines
and levels of embedded parts, proper
consolidating, curing, including cost of all
materials, labour and conveyance charges,
etc. complete but excluding cost of cement.
Cement concrete charges
Provision for less efficiency @ 10% of above
/m3

Total
19

1 m3

380.00 Kg

Cement concrete M20 with 20mm graded


aggregates for pre-cast slab laying the same
to lines and levels at all elevations,
consolidating, curing, including cost of all
materials, labour and conveyance charges,
formwork etc. complete but excluding cost of
cement.
Cement

1 MT
31

3
0.41 m

M sand / R sand

3
1m

3
0.49 m

20 mm coarse aggregate

3
1m

3
0.37 m
240.00 litre
0.08 hr.

0.08 hr.
1.95
0.20
0.20
0.25

No
No
hr.
No.

10 %
%
%
%

20

1 m3

3
0.60 m
3
0.40 m
0.60 No.
%
%
%

12 mm coarse aggregate
Water including for curing
Batching and mixing plant (UR) forbatching
and mixing
Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead)
Man for placing
Mason for placing
Vibrator (UR)
Man for curing

3
1m
1000 litre

1 hr.
1
1
1
1
1

hr.
Each
Each
hr.
Each

Provision for formwork, conveying and


laying the slabs, etc. @ 10% of total above
HA
OH
CP
Total

/m3

Plum cement concrete M10 with 40mm


graded aggregates (60%), over plumming of
broken rubbles of size 10 -23 cm (40%),
laying to lines and levels at all elevations,
consolidating, curing, including cost of all
materials and labour charges, etc. complete
but excluding cost of cement.
1 m3
1 m3

Cement concrete M10 MSA 40


Rubble
Man for conversion, laying, etc.
HA
OH
CP

1 Each

Total

32

/m3

21

1 m3

432.00
0.45
0.90
260.00
0.20
1.00
3.50

Kg
m3
m3
litre
No
No
No
%
%
%

Cement concrete 1:1.5:3 using 20mm


nominal size aggregate, laying to lines and
levels at all elevations, consolidating, curing,
including cost of all materials and labour
charges, etc. complete but excluding cost of
cement.
Cement
M sand / R sand
20 mm coarse aggregate
Water including for curing
Mason
Man
Man/Women including watering
HA
OH
CP

1
1
1
1000
1
1
1

MT
m3
m3
litre
Each
Each
Each

/m3

Total
22

1 m3

330.00
0.45
0.90
198.00
0.20
1.00
3.50

23

Kg
m3
m3
litre
No
No
No
%
%
%

1 m3

228.00
0.48
0.95
137.00
0.10
1.00
1.40

Kg
m3
m3
litre
No
No
No
%
%
%

Cement concrete 1:2:4 using 20mm nominal


size aggregate, laying to lines and levels at
all
elevations,
consolidating, curing,
including cost of all materials and labour
charges, etc. complete but excluding cost of
cement.
Cement
M sand / R sand
20 mm coarse aggregate
Water including for curing
Mason
Man
Man/Women including watering
HA
OH
CP
Total

1
1
1
1000
1
1
1

MT
m3
m3
litre
Each
Each
Each

/m3

Cement concrete 1:3:6 using 40mm nominal


size aggregate, laying to lines and levels at
all
elevations,
consolidating, curing,
including cost of all materials and labour
charges, etc. complete but excluding cost of
cement.
Cement
M sand / R sand
40 mm coarse aggregate
Water including for curing
Mason
Man
Man/Women including watering
HA
OH
CP

1
1
1
1000
1
1
1

Total

33

MT
m3
m3
litre
Each
Each
Each

/m3

24

1 m3

171.00
0.48
0.95
103.00
0.10
1.00
1.40

Kg
m3
m3
litre
No
No
No
%
%
%

Cement concrete 1:4:8 using 40mm nominal


size aggregate, laying to lines and levels at
all
elevations,
consolidating, curing,
including cost of all materials and labour
charges, etc. complete but excluding cost of
cement.
Cement
M sand / R sand
40 mm coarse aggregate
Water including for curing
Mason
Man
Man/Women including watering
HA
OH
CP

1
1
1
1000
1
1
1

MT
m3
m3
litre
Each
Each
Each

/m3

Total
25

1 m2

588.00 Kg
0.125 m3
0.125 m3
0.75 m3
225.00 litre
*%
0.08 hr.
0.08 hr.
2.00 hrs.
0.25 No.
10 %

%
%
%

26

1 m2

* Note for item nos.


25&26. the percentage of
wastage allowance for
rebound may be taken
accordingly as, (i) for
floor/slabs 5-15%
(ii) for sloping and
vertical walls - 15-30%
(iii) for overhead work 25-50%.

Shotcreting with 9mm graded aggregates


thickness of 50mm in one layer, laying to
lines and levels at all elevations,
consolidating, curing, including cost of all
materials and labour charges, etc. complete
but excluding cost of cement.
Data for 1m3
Cement
9mm aggregate

1 MT

6mm aggregate

3
1m

3
1m

M sand / R sand
Water including for curing
Wastage allowance for rebound @ __% of
above
Batching and mixing plant (UR) forbatching
and mixing
Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead)
Shotcreting charges (UR)
Man for curing
Provision for surface cleaning, scaffolding,
admixtures, sundries, etc. @ 10% of total
above
HA
OH
CP
Total
Hence rate per m2 for 50 mm thickness
divided by 20
Hence rate per m2 for 100 mm thickness
divided by10
Guniting to average thickness of 50mm in
one layer, laying to lines and levels at all
elevations, consolidating, curing, including
cost of all materials and labour charges, etc.
complete but excluding cost of cement.

34

3
1m
1000 litre

1 hr.
1 hr.
1 hr.
1 Each

/20

/10

/m2
/m2

588.00 Kg
1.00 m3
225.00 litre
*%
0.08 hr.
0.08 hr.
2.00 hrs.
0.25 No.
10 %

%
%
%

27

1 m2

1.00 m2
0.04 No.
0.01 No.
20 %
%
%
%

28

Data for 1m3


Cement
M sand / R sand

1 MT

Water including for curing


Wastage allowance for rebound @ ___% of
above
Batching and mixing plant (UR) forbatching
and mixing
Transit mixer (UR) for conveyance to site of
placement ( up to 1 Km lead)
Guniting charges (UR)
Man for curing
Provision for surface cleaning, scaffolding,
admixtures, sundries, etc. @ 10% of total
above
HA
OH
CP
Total
2
Hence rate per m for 50 mm thickness

3
1m
1000 litre

1 hr.
1 hr.
1 hr.
1 Each

/20

Supplying, furnishing and installing chain


link / welded mesh for shotcreting/guniting
wherever required at all elevations including
cost of all materials and labour charges, etc.
complete.
Cost of chain link/welded mesh
Black smith
Man
Cost of pin, scaffolding, drilling, cutting,
placing, etc. @ 20% above
HA
OH
CP
Total

1 MT

Supply and usage of cement at site including


cost of cement, conveyance charge, storage
arrangements, charges for stacking and restacking if nescessery, etc. complete.

1 MT
5%

Cost of cement at site


Charges for stacking/ re-stacking, storage
arrangements, etc. @5 % of above item

2
1m
1 Each
1 Each

/m2

1 MT

Total
29

/m2

1 litre

Supply and usage of admixture at site


including cost of admixture, conveyance
charge, storage arrangements if nescessery
etc. complete.

1 litre
5%

Cost of admixture at site(MR)


For conveyance and mixiang charges etc.
Total
35

/MT

1 litre
/litre

CHAPTER VII
MASONRY WORKS
Sl.
No
1

Quantity
3

1m

1.00
0.30
86.00
0.70
1.05

m3
m3
Kg
No.
No.
%
%
%

Description of items

Unit

Rate

1 m3

1.00
0.30
72.00
0.70
1.05

m3
m3
Kg
No.
No.
%
%
%

Blasted rubble
River sand / M sand
Cement
Rubble mason
Man
HA
OH
CP

Note: Cost of cement may


be included in the item or
excluded and measured
as a separate item.

1
1
1
1
1

m3
m3
MT
Each
Each

/m3

Random rubble masonry in CM 1:6 for


foundation and basement including cost of
all materials, conveyance, labour charges,
etc. complete as per specifications.
Blasted rubble
River sand / M sand
Cement
Rubble mason
Man
HA
OH
CP

1
1
1
1
1

m3
m3
MT
Each
Each

/m3

Total
3

1 m3

1.05 m3
0.80 No.
0.70 No.
%
%
%

Dry rubble masonry for foundation and


basement including cost of all materials,
conveyance, labour charges, etc. complete as
per specifications.
Blasted rubble
Rubble mason
Man
HA
OH
CP

1
1
1

Total
4

1 m3

Remarks

A. STONE MASONRY
Random rubble masonry in CM 1:5 for
foundation and basement including cost of
all materials, conveyance, labour charges,
etc. complete as per specifications.

Total
2

Amount

For superstructure above foundation and


basement of Random rubble masonry/ Dry
rubble masonry
Add to corresponding items of work in
foundation and basement

36

m3
Each
Each

/m3

15 %

%
%
%

Labour required for foundation and basement


( includes hire charges of scaffolding
materials etc.)
HA
OH
CP
/m3

Total
5

1 m3

1.05 m3
0.35 No.
1.40 No.
%
%
%

Rubble pitching/ Rough stone dry packing to


lines and levels including cost of all
materials, conveyance, labour charges, etc.
complete as per specifications.
Blasted rubble
Rubble mason
Man
HA
OH
CP

1
1
1

m3
Each
Each

/m3

Total
6

1 m3

1.05 m3
0.70 No.
%
%
%

Quarry rubbish backing for revetment


including cost of all materials, labour charges
etc. complete as per specifications.
Blasted rubble
Man
HA
OH
CP

1
1

m3
Each

/m3

Total

1m

60.00 No.
0.16
46.00
1.50
0.85

m3
Kg
No.
No.
%
%
%

B. LATERITE MASONRY
Laterite masonry in CM 1:5 for foundation
and basement including cost of all materials,
conveyance, labour charges, etc. complete as
per specifications.
Laterite
stones
(44x24x14cm)

roughly

Quantity of Laterite stone


of size 35x20x20 cm 65 Nos 35x20x14 cm 90 Nos.

dressed
100

River sand / M sand


Cement
Laterite/ Brick mason
Man
HA
OH
CP

1
1
1
1

Total

37

No.
m3
MT
Each
Each

/m3

1 m3

60.00 No.
0.16
38.00
1.50
0.85

m3
Kg
No.
No.
%
%
%

1 m3

15 %

%
%
%
10

1 m3

15 %

%
%
%
11

1 m3

63.00 No.
0.16
46.00
2.00
0.94
2.0

m
Kg
No.
No.
%
%
%
%

Laterite masonry in CM 1:6 for foundation


and basement including cost of all materials,
conveyance, labour charges, etc. complete as
per specifications.
Laterite
stones
(44x24x14cm)
River sand / M sand

roughly

dressed

100
1
1
1
1

Cement
Laterite/ Brick mason
Man/Woman
HA
OH
CP

No.
m3
MT
Each
Each

Total

/m3

For superstructure in ground floor upto 5m


height
Add to the corresponding items of work in
foundation and basement
Labour required for foundation and basement
( includes hire charges of scaffolding
materials)
HA
OH
CP
Total

/m3

For superstructure in first floor upto 5m


height or in each successive floors upto 5m
height in each floor
Add to the corresponding items of work in
superstructure ground floor or previous
floors
Labour required for foundation and basement
( includes hire charges of scaffolding
materials)
HA
OH
CP
Total

/m3

Laterite masonry in CM 1:5 for flat, semi


circular segmental arch work including cost
of all materials, conveyance, labour charges,
etc. complete as per specifications.
Laterite
stones
(44x24x14cm)
River sand

roughly

dressed

River sand / M sand


Laterite/ Brick mason
Man
Scafolding,centering etc complete ( 2 % of
labour)
HA
OH
CP
Total
38

100
1
1
1
1

No.
m3
MT
Each
Each

/m3

12

1 m3

63.00 Nos.
0.16
46.00
2.00
1.44
2.0

m
Kg
No.
No.
%
%
%
%

13

1 m3

500.00 No.
3
0.20 m
58.00 Kg
0.70 No.
1.05 No.
%
%
%

Laterite masonry in CM 1:5 for well lining,


cornices, copings etc. including cost of all
materials, conveyance, labour charges, etc.
complete as per specifications.
Laterite
stones
(44x24x14cm)
River sand / M sand

roughly

dressed

Cement
Laterite/ Brick mason
Man
Scafolding,centering etc complete ( 2 % of
labour)
HA
OH
CP
Total
C. BRICK WORK
Brick work in cement mortar 1:5 with wire
cut bricks for foundation and basement
including cost of all materials, conveyance,
labour charges, etc. complete as per
specifications.
Wire cut bricks (19cmx9cmx9cm)
River sand / M sand
Cement
Brick mason
Man
HA
OH
CP

100
1
1
1
1

No.
m3
MT
Each
Each

/m3

1000
1
1
1
1

No.
m3
MT
Each
Each

/m3

Total
14

1 m3

500.00 No.
3
0.24 m
69.00 Kg
0.70 No.
1.05 No.
%
%
%

Brick work in cement mortar 1:5 with


country burnt bricks for foundation and
basement including cost of all materials,
conveyance, labour charges, etc. complete as
per specifications.
Country burnt bricks(19cmx9cmx9cm)
River sand / M sand

1000
1
1
1
1

Cement
Brick mason
Man/Woman
HA
OH
CP
Total

15

1 m3

Brick work in cement mortar 1:6 with wire


cut bricks for foundation and basement
including cost of all materials, conveyance,
labour charges, etc. complete as per
specifications.
39

No.
m3
MT
Each
Each

/m3

500.00 No.
3
0.20 m
49.00 Kg
0.70 No.
1.05 No.
%
%
%

Wire cut bricks (19cmx9cmx9cm)


River sand / M sand

1000
1
1
1
1

Cement
Brick mason
Man/Woman
HA
OH
CP

No.
m3
MT
Each
Each

/m3

Total
16

1 m3

500.00 No.
0.24
58.00
0.70
1.05

17

m
Kg
No.
No.
%
%
%

1 m3

15 %

%
%
%

18

1 m3

15 %

%
%
%

Brick work in cement mortar 1:6 with


country burnt bricks for foundation and
basement including cost of all materials,
conveyance, labour charges, etc. complete as
per specifications.
Country burnt bricks(19cmx9cmx9cm)

1000 No.

River sand / M sand

1
1
1
1

Cement
Brick mason
Man/Woman
HA
OH
CP

m3
MT
Each
Each

Total

/m3

For superstructure in ground floor upto 5m


height
Add to the corresponding items of work in
foundation and basement
Labour required for foundation and basement
( includes hire charges of scaffolding
materials)
HA
OH
CP
Total

/m3

For superstructure in first floor upto 5m


height or in each successive floors upto 5m
height in each floor
Add to the corresponding items of work in
superstructure ground floor or previous
floors
Labour required for foundation and basement
( includes hire charges of scaffolding
materials)
HA
OH
CP
Total

/m3

40

19

1 m3

525.00 No.
3
0.20 m
58.00 Kg
1.12 No.
1.66 No.
2%
%
%
%

20

1m

55.00 No.
0.15
43.00
1.50
0.85

m
Kg
No.
No.
%
%
%

Brick work in cement mortar 1:5 with wire


cut bricks for flat, semicircular or segmental,
arch works, etc. including cost of all
materials, conveyance, labour charges, etc.
complete as per specifications.
Wire cut bricks (19cmx9cmx9cm)
River sand / M sand
Cement
Brick mason
Man
Scafolding,centering etc complete ( 2 % of
labour)
HA
OH
CP
Total

1000
1
1
1
1

No.
m3
MT
Each
Each

/m3

D. CEMENT BLOCK MASONRY


Cement solid/hollow block work in cement
mortar 1:5 for foundation and basement
including cost of all materials, conveyance,
labour charges, etc. complete as per
specifications.
100 No.
1 m3
1 MT
1 Each
1 Each

Cement blocks (40cmx20cmx20cm)


River sand / M sand
Cement
Laterite/ Brick mason
Man/Woman
HA
OH
CP

/m3

Total
21

1 m3

55.00 No.
3
0.15 m
36.00 Kg
1.50 No.
0.85 No.
%
%
%

Cement solid/hollow block work in cement


mortar 1:6 for foundation and basement
including cost of all materials, conveyance,
labour charges, etc. complete as per
specifications.
Cement blocks (40cmx20cmx20cm)
River sand / M sand

100
1
1
1
1

Cement
Laterite/ Brick mason
Man/Woman
HA
OH
CP
Total

22

1 m3

For superstructure in ground floor upto 5m


height
Add to the corresponding items of work in
foundation and basement

41

No.
m3
MT
Each
Each

/m3

15 %

%
%
%

23

1 m3

15 %

%
%
%

Labour required for foundation and basement


( includes hire charges of scaffolding
materials)
HA
OH
CP
Total

/m3

For superstructure in first floor upto 5m


height or in each successive floors upto 5m
height in each floor
Add to the corresponding items of work in
superstructure ground floor or previous
floors
Labour required for foundation and basement
( includes hire charges of scaffolding
materials)
HA
OH
CP
Total

42

/m3

CHAPTER VIII
PLASTERING AND POINTING
Sl.
No

Quantity

1 m2

0.01
4.30
0.09
0.165

m3
Kg
No.
No.
%
%
%

Description of items

Unit

Rate

1 m2

0.014
6.60
0.09
0.165

m3
Kg
No.
No.
%
%
%

River sand/Msand
Cement
Mason
Man/Woman
HA
OH
CP

Note: Cost of cement may


be included in the item or
excluded and measured
as a separate item.

1
1
1
1

m3
MT
Each
Each

/m2

Plastering with CM 1:3, 12 mm thick


including cost of all materials, conveyance,
labour charges, etc. complete.
River sand/Msand

1
1
1
1

Cement
Mason
Man/Woman
HA
OH
CP

m3
MT
Each
Each

/m2

Total
3

1 m2

0.015
7.20
0.09
0.165

m3
Kg
No.
No.
%
%
%

Plastering with CM 1:3, 15 mm thick


including cost of all materials, conveyance,
labour charges, etc. complete.
River sand/Msand

1
1
1
1

Cement
Mason
Man/Woman
HA
OH
CP

m3
MT
Each
Each

/m2

Total
4

1 m2

0.015
5.40
0.09
0.17

m3
Kg
No.
No.
%
%
%

Remarks

A. PLASTERING
Plastering with CM 1:3, 9mm thick including
cost of all materials, conveyance, labour
charges, etc. complete.

Total
2

Amount

Plastering with CM 1:4, 12 mm thick


including cost of all materials, conveyance,
labour charges, etc. complete.
River sand/Msand

1
1
1
1

Cement
Mason
Man/Woman
HA
OH
CP
Total

43

m3
MT
Each
Each

/m2

1 m2

0.017
5.90
0.09
0.17

m3
Kg
No.
No.
%
%
%

Plastering with CM 1:4, 15 mm thick


including cost of all materials, conveyance,
labour charges, etc. complete.
River sand/M sand
Cement
Mason
Man/Woman
HA
OH
CP

1
1
1
1

m3
MT
Each
Each

/m2

Total
6

1 m2

0.015
4.30
0.09
0.17

m3
Kg
No.
No.
%
%
%

Plastering with CM 1:5, 12 mm thick


including cost of all materials, conveyance,
labour charges, etc. complete.
River sand/M sand
Cement
Mason
Man/Woman
HA
OH
CP

1
1
1
1

m3
MT
Each
Each

/m2

Total
7

1 m2

0.017
4.80
0.09
0.17

m3
Kg
No.
No.
%
%
%

Plastering with CM 1:5, 15 mm thick


including cost of all materials, conveyance,
labour charges, etc. complete.
River sand/Msand
Cement
Mason
Man/Woman
HA
OH
CP

1
1
1
1

m3
MT
Each
Each

/m2

Total
8

1 m2

0.015
3.60
0.09
0.17

m3
Kg
No.
No.
%
%
%

Plastering with CM 1:6,12 mm thick


including cost of all materials, conveyance,
labour charges, etc. complete.
River sand/Msand
Cement
Mason
Man/Woman
HA
OH
CP

1
1
1
1

m3
MT
Each
Each

/m2

Total
9

1 m2

0.017
4.00
0.09
0.17

m3
Kg
No.
No.
%
%
%

Plastering with CM 1:6, 15 mm thick


including cost of all materials, conveyance,
labour charges, etc. complete.
River sand/Msand
Cement
Mason
Man/Woman
HA
OH
CP
Total
44

1
1
1
1

m3
MT
Each
Each

/m2

10

1 m2
2.20 Kg
0.05 No.
%
%
%

Add to cement plastering items for plastering


with neat cement flushing coat
Cement
Mason
HA
OH
CP

1 MT
1 Each

/m2

Total
11

1 m2
2.20 Kg
%
%
%

Add to cement plastering items for use of


coloured cement flushing coat
Add the excess value of coloured cement

1 MT

HA
OH
CP
/m2

Total
12

1 m2
0.02 No.
%
%
%

Add to cement plastering items for thread


lining to plastered surface
Mason
HA
OH
CP

1 Each

/m2

Total
13

1 m2

For plastering works in first floor upto 5m


height or in each successive floors upto 5m
height in each floor
Add to the corresponding plastering items of
work in ground floor or previous floors

15 %

%
%
%

Labour required for plastering works (


includes hire charges of scaffolding
materials)
HA
OH
CP
/m2

Total
14

1 m2

0.001
0.60
0.05
0.011

m3
Kg
No.
No.
%
%
%

Providing boarder 75mm wide and 15mm


thick in CM 1:3 including cost of all
materials, conveyance, labour charges, etc.
complete.
River sand/Msand
Cement
Mason
Man/Woman
HA
OH
CP
Total

45

1
1
1
1

m3
MT
Each
Each

/m2

15

1 m2

0.05 No.
0.019 No.
%
%
%

Clearing and removal of old plaster from


walls including racking out joints clearing
the surface for replaster including disposal of
debris within 150m.
Mason
Man/Woman
HA
OH
CP

1 Each
1 Each

/m2

Total
16

1 m2

0.003
1.325
0.08
0.11

m3
Kg
No.
No.
%
%
%

B. POINTING
Pointing brick work with CM 1:3 including
cost of all materials, conveyance, labour
charges, etc. complete.
River sand/M sand

1
1
1
1

Cement
Mason
Man/Woman
HA
OH
CP

m3
MT
Each
Each

/m2

Total
17

1 m2

0.003
1.00
0.08
0.11

m3
Kg
No.
No.
%
%
%

Pointing brick work with CM 1:4 including


cost of all materials, conveyance, labour
charges, etc. complete.
River sand/M sand

1
1
1
1

Cement
Mason
Man/Woman
HA
OH
CP

m3
MT
Each
Each

/m2

Total
18

1 m2

0.003
1.858
0.08
0.11

m3
Kg
No.
No.
%
%
%

Pointing Random rubble masonry with CM


1:2 including cost of all materials,
conveyance, labour charges, etc. complete.
River sand/M sand

1
1
1
1

Cement
Mason
Man/Woman
HA
OH
CP

m3
MT
Each
Each

/m2

Total
19

1 m2

3
0.003 m
1.325 Kg

Pointing Random rubble masonry with CM


1:3 including cost of all materials,
conveyance, labour charges, etc. complete.
3
1 m
1 MT

River sand/M sand


Cement

46

0.08 No.
0.11 No.
%
%
%

Mason
Man/Woman
HA
OH
CP

1 Each
1 Each

/m2

Total
20

1 m2

0.003
1.00
0.08
0.11

m3
Kg
No.
No.
%
%
%

Pointing Random rubble masonry with CM


1:4 including cost of all materials,
conveyance, labour charges, etc. complete.
River sand/M sand

1
1
1
1

Cement
Mason
Man/Woman
HA
OH
CP

m3
MT
Each
Each

/m2

Total
21

1 m2

0.001
0.662
0.04
0.019

m3
Kg
No.
No.
%
%
%

Pointing Laterite masonry with CM 1:3


including cost of all materials, conveyance,
labour charges, etc. complete.
River sand/M sand

1
1
1
1

Cement
Mason
Man/Woman
HA
OH
CP

m3
MT
Each
Each

/m2

Total
22

1 m2

0.002
0.5
0.04
0.019

m3
Kg
No.
No.
%
%
%

Pointing Laterite masonry with CM 1:4


including cost of all materials, conveyance,
labour charges, etc. complete as per
specification.
River sand/M sand
Cement
Mason
Man/Woman
HA
OH
CP

1
1
1
1

m3
MT
Each
Each

/m2

Total
23

1 m2

0.001
0.53
0.08
0.11

m3
Kg
No.
No.
%
%
%

Pointing Cement block masonry with CM 1:3


including cost of all materials, conveyance,
labour charges, etc. complete.
River sand/M sand

1
1
1
1

Cement
Mason
Man/Woman
HA
OH
CP
Total
47

m3
MT
Each
Each

/m2

24

1 m2

0.001
0.4
0.08
0.11

m3
Kg
No.
No.
%
%
%

Pointing Cement block masonry with CM 1:4


including cost of all materials, conveyance,
labour charges, etc. complete.
River sand/M sand

1
1
1
1

Cement
Mason
Man/Woman
HA
OH
CP
Total

48

m3
MT
Each
Each

/m2

CHAPTER IX
WHITE WASHING AND PAINTING
Sl.
No.

Quantity

Description of item

Rate

Unit

Amount

Remarks

A. CEMENT WORKS
1

1 m

0.148
0.012
0.009
2

Kg
No.
No.
%
%
%
%

Note: Cost of cement may


be included in the item or
excluded and measured
as a separate item.

White cement washing one coat for new


surface including cost and conveyance of all
materials, labour charges, etc. complete.
White cement
Special mazdoor
Man
Sundries, of total above
HA
OH
CP

1 Kg
1 Each
1 Each

Total
2

1 m

0.248
0.02
0.015
2

Kg
No.
No.
%
%
%
%

/m

White cement washing two coats for new


surface including cost and conveyance of all
materials, labour charges, etc. complete.
White cement
Special mazdoor
Man
Sundries, of total above
HA
OH
CP

1 Kg
1 Each
1 Each

Total
3

1 m

0.148
0.012
0.009
2

Kg
No.
No.
%
%
%
%

1 m

0.248
0.02
0.015
2

Kg
No.
No.
%
%
%
%

Cement washing one coat for new surface


including cost and conveyance of all
materials, labour charges, etc. complete.
Cement
Special mazdoor
Man
Sundries, of total above
HA
OH
CP
Total

/m

1 MT
1 Each
1 Each

/m

Cement washing two coats for new surface


including cost and conveyance of all
materials, labour charges, etc. complete.
Cement
Special mazdoor
Man
Sundries, of total above
HA
OH
CP

1 MT
1 Each
1 Each

Total
49

/m

1 m

0.1
0.008
0.006
2

Kg
No.
No.
%
%
%
%

Cement washing one coat for old surface


including cost and conveyance of all
materials, labour charges, etc. complete.
Cement
Special mazdoor
Man
Sundries, of total above
HA
OH
CP

1 MT
1 Each
1 Each

Total
6

1 m

0.20
0.016
0.012
2

Kg
No.
No.
%
%
%
%

/m

Cement washing two coats for old surface


including cost and conveyance of all
materials, labour charges, etc. complete.
Cement
Special mazdoor
Man
Sundries, of total above
HA
OH
CP

1 MT
1 Each
1 Each

Total
7

1 m

0.10 litre
0.04 No.
2%
%
%
%

/m

Painting with one coat of primer of approved


quality on new / old surface after cleaning,
including cost and conveyance of all
materials, labour charges, etc. complete.
Wall Primer
Painter
Sundries, of total above
HA
OH
CP

1 litre
1 Each

Total
8

1 m

0.19
0.03
0.04
2

Kg
No.
No.
%
%
%
%

/m

Finishing new surface with cement water


proof paint of approved quality and color,
one coat including cost and conveyance of all
materials, labour charges, etc. complete.
Cement water proof paint
Painter
Man
Sundries, of total above
HA
OH
CP

1 Kg
1 Each
1 Each

Total

50

/m

1 m

0.32
0.05
0.07
2

Kg
No.
No.
%
%
%
%

Finishing new surface with cement water


proof paint of approved quality and color,
two coats including cost and conveyance of
all materials, labour charges, etc. complete.
Cement water proof paint
Painter
Man
Sundries, of total above
HA
OH
CP

1 Kg
1 Each
1 Each

Total
10

1 m

0.14
0.025
0.025
2

Kg
No.
No.
%
%
%
%

/m

Finishing old surface with cement water


proof paint of approved quality and color,
one coat including cost and conveyance of all
materials, labour charges, etc. complete.
Cement water proof paint
Painter
Man
Sundries, of total above
HA
OH
CP

1 Kg
1 Each
1 Each

Total
11

1 m

0.28
0.05
0.05
2

Kg
No.
No.
%
%
%
%

/m

Finishing old surface with cement water


proof paint of approved quality and color,
two coats including cost and conveyance of
all materials, labour charges, etc. complete.
Cement water proof paint
Painter
Man
Sundries, of total above
HA
OH
CP

1 Kg
1 Each
1 Each

Total
12

1 m

0.10 Kg
0.03 No.
2%
%
%
%

/m

Finishing new surface with distemper of


approved quality and color, one coat
including smoothening with sand paper, cost
and conveyance of all materials, labour
charges, etc. complete.
Distemper
Painter
Sundries, of total above
HA
OH
CP

1 Kg
1 Each

Total
51

/m

13

1 m

0.15 Kg
0.05 No.
2%
%
%
%

Finishing new surface with distemper of


approved quality and color, two coats
including smoothening with sand paper, cost
and conveyance of all materials, labour
charges, etc. complete.
Distemper
Painter
Sundries, of total above
HA
OH
CP

1 Kg
1 Each

Total
14

1 m

0.06 Kg
0.025 No.
2%
%
%
%

/m

Finishing old surface with distemper of


approved quality and color, one coat
including smoothening with sand paper, cost
and conveyance of all materials, labour
charges, etc. complete.
Distemper
Painter
Sundries, of total above
HA
OH
CP

1 Kg
1 Each

Total
15

1 m

0.11 Kg
0.045 No.
2%
%
%
%

/m

Finishing old surface with distemper of


approved quality and color, two coats
including smoothening with sand paper, cost
and conveyance of all materials, labour
charges, etc. complete.
Distemper
Painter
Sundries, of total above
HA
OH
CP

1 Kg
1 Each

Total
16

1 m

0.115
0.10
0.155
2

litre
litre
No.
%
%
%
%

/m

Painting new surface with emulsion paint of


approved quality and color, one coat over a
coat of primer, after smoothening with sand
paper and cleaning the surface, including
cost and conveyance of all materials, labour
charges, etc. complete.
Emulsion paint
Wall Primer
Painter
Sundries, of total above
HA
OH
CP

1 litre
1 litre
1 Each

Total
52

/m

17

1 m

0.155
0.10
0.195
2

litre
litre
No.
%
%
%
%

Painting new surface with emulsion paint of


approved quality and color, two coats over a
coat of primer, after smoothening with sand
paper and cleaning the surface, including
cost and conveyance of all materials, labour
charges, etc. complete.
Emulsion paint
Wall Primer
Painter
Sundries, of total above
HA
OH
CP

1 litre
1 litre
1 Each

Total
18

1 m

0.04 litre
0.04 No.
2%
%
%
%

/m

Painting old surface with emulsion paint of


approved quality and colour, one coat, after
smoothening with sand paper and cleaning
the surface, including cost and conveyance of
all materials, labour charges, etc. complete.

Emulsion paint
Painter
Sundries, of total above
HA
OH
CP

1 litre
1 Each

Total
19

1 m

0.08 litre
0.08 No.
2%
%
%
%

/m

Painting old surface with emulsion paint of


approved quality and color, two coats, after
smoothening with sand paper and cleaning
the surface, including cost and conveyance of
all materials, labour charges, etc. complete.
Emulsion paint
Painter
Sundries, of total above
HA
OH
CP

1 litre
1 Each

Total
20

1 m

0.10
0.08
0.20
0.155
0.08
2

litre
litre
Kg
No.
No.
%

/m

Painting new surface with emulsion paint of


approved quality and color, one coat over
over a coat of primer, after smoothening with
sand paper and finishing with wall putty,
including cost and conveyance of all
materials, labour charges, etc. complete.
Emulsion paint
Wall Primer
Wall putty
Painter
Man
Sundries, of total above

1
1
1
1
1

53

litre
litre
Kg
Each
Each

%
%
%

HA
OH
CP
Total

21

1 m

0.14
0.08
0.20
0.195
0.08
2

litre
litre
Kg
No.
No.
%
%
%
%

/m

Painting new surface with emulsion paint of


approved quality and color, two coats over a
coat of primer, after smoothening with sand
paper and finishing with wall putty, including
cost and conveyance of all materials, labour
charges, etc. complete.
Emulsion paint
Wall Primer
Wall putty
Painter
Man
Sundries, of total above
HA
OH
CP

1
1
1
1
1

litre
litre
Kg
Each
Each

Total
22

1 m

0.08
0.08
0.08
0.08
2

litre
litre
No.
No.
%
%
%
%

/m

Painting old surface with emulsion paint of


approved quality and color, two coats over a
coat of primer, after smoothening with sand
paper and the cleaning surface, including
cost and conveyance of all materials, labour
charges, etc. complete.
Emulsion paint
Wall Primer
Painter
Man
Sundries, of total above
HA
OH
CP

1
1
1
1

litre
litre
Each
Each

Total
23

1 m

0.08
0.08
0.20
0.12
0.08
2

litre
litre
Kg
No.
No.
%
%
%
%

/m

Painting old surface with emulsion paint of


approved quality and color, two coats over a
coat of primer, after smoothening with sand
paper and finishing with wall putty, including
cost and conveyance of all materials, labour
charges, etc. complete.
Emulsion paint
Wall Primer
Wall putty
Painter
Man
Sundries, of total above
HA
OH
CP

1
1
1
1
1

Total

54

litre
litre
Kg
Each
Each

/m

24

1 m

0.14 litre
0.05 No.
2%
%
%
%

Painting new surface with black/ brown


japan paint of approved quality, one coat
after rubbing with sand paper and cleaning
the surface including cost and conveyance of
all materials, labour charges, etc. complete.
Black/ brown japan paint
Painter
Sundries, of total above
HA
OH
CP

1 litre
1 Each

Total
25

1 m

0.23 litre
0.08 No.
2%
%
%
%

/m

Painting new surface with black/ brown


japan paint of approved quality, two coats
after rubbing with sand paper and cleaning
the surface including cost and conveyance of
all materials, labour charges, etc. complete.
Black/ brown japan paint
Painter
Sundries, of total above
HA
OH
CP

1 litre
1 Each

Total
26

1 m

0.09 litre
0.04 No.
2%
%
%
%

/m

Painting old surface with black/ brown japan


paint of approved quality, one coat after
rubbing with sand paper and cleaning the
surface including cost and conveyance of all
materials, labour charges, etc. complete.

Black/ brown japan paint


Painter
Sundries, of total above
HA
OH
CP

1 litre
1 Each

Total
27

1 m

0.18 litre
0.07 No.
2%
%
%
%

/m

Painting old surface with black/ brown japan


paint of approved quality, two coats after
rubbing with sand paper and cleaning the
surface including cost and conveyance of all
materials, labour charges, etc. complete.
Black/ brown japan paint
Painter
Sundries, of total above
HA
OH
CP

1 litre
1 Each

Total
B. WOOD WORKS
55

/m

28

1 m

0.115
0.14
0.18
2

29

litre
litre
No.
%
%
%
%

1 m

0.095 litre
0.095 No.
2%
%
%
%

Note: Measurement area


may be taken as
1.
Wooden panelled or
framed - add 12.5% of
area fpr each side
2.Fully glazed - Deduct
50% of area for each
side.

Painting new wood surface with enamel paint


of approved quality and colour, two coats
over two coats of wood primer, after
smoothening with sand paper and cleaning
the surface, including cost and conveyance of
all materials, labour charges, etc. complete.

Enamel paint
Wood Primer
Painter
Sundries, of total above
HA
OH
CP

1 litre
1 litre
1 Each

Total
Painting old wood surface with enamel paint
of approved quality and colour, two coats,
after smoothening with sand paper and
cleaning the surface, including cost and
conveyance of all materials, labour charges,
etc. complete.
Enamel paint
Painter
Sundries, of total above
HA
OH
CP

/m

1 litre
1 Each

Total
30

1 m

0.05 litre
0.05 No.
2%
%
%
%

Painting old wood surface with enamel paint


of approved quality and colour, one coat,
after rubbing with sand paper and cleaning
the surface including cost and conveyance of
all materials, labour charges, etc. complete.

Enamel paint
Painter
Sundries, of total above
HA
OH
CP

1 litre
1 Each

Total

31

1 m

/m

C. STEEL WORKS
Painting new iron surface with priming coat
of approved quality one coat, after rubbing
with emery paper and cleaning the surface
including cost and conveyance of all
materials, labour charges, etc. complete.

56

/m

Note: Measurement area


may be taken as guard bars, balustrades,
gates, gratings, grills,
cages, railings, braces,
rails, stays, etc. - Deduct
50% area for each side.

0.075 litre
0.04 No.
2%
%
%
%

Iron primer
Painter
Sundries, of total above
HA
OH
CP

1 litre
1 Each

Total
32

1 m

0.105 litre
0.025 No.
2%
%
%
%

/m

Painting new iron surface with aluminium


paint of approved quality one coat including
cost and conveyance of all materials, labour
charges, etc. complete.
Aluminium paint
Painter
Sundries, of total above
HA
OH
CP

1 litre
1 Each

Total
33

1 m

0.08 litre
0.025 No.
2%
%
%
%

/m

Painting old iron surface with aluminium


paint of approved quality, one coat, after
smoothening with sand paper and cleaning
the surface, including cost and conveyance of
all materials, labour charges, etc. complete.

Aluminium paint
Painter
Sundries, of total above
HA
OH
CP

1 litre
1 Each

Total
34

1 m

0.115
0.075
0.14
2

litre
litre.
No.
%
%
%
%

/m

Painting new iron surface with enamel/


epoxy/ similar paint of approved quality and
color two coats over a coat of iron primer,
after smoothening with sand paper and
cleaning the surface, including cost and
conveyance of all materials, labour charges,
etc. complete.
Enamel/ epoxy/ similar paint
Iron Primer
Painter
Sundries, of total above
HA
OH
CP

1 litre
1 litre.
1 Each

Total

57

/m

35

1 m

Painting old iron surface with enamel/ epoxy/


similar paints of approved quality and color
two coats, after smoothening with sand paper
and cleaning the surface, including cost and
conveyance of all materials, labour charges,
etc. complete.

0.095 litre

Enamel/ epoxy/ similar paint

1 litre

0.095 No.
2%
%
%
%

Painter
Sundries, of total above
HA
OH
CP

1 Each

Total
36

1 m

0.05 litre
0.05 No.
2%
%
%
%

/m

Painting old iron surface with enamel/ epoxy/


similar paints of approved quality and color
one coat, after smoothening with sand paper
and cleaning the surface, including cost and
conveyance of all materials, labour charges,
etc. complete.
Enamel/ epoxy/ similar paint
Painter
Sundries, of total above
HA
OH
CP

1 litre
1 Each

Total

58

/m

CHAPTER X
DOORS, WINDOWS & VENTILATORS
Sl.
No.
1

Quantity

Description of item

1 m2

Providing and fixing wood pannelled door in


single leaf with frames of 100 x 70 mm (
with out sill) and shutters of frame 100 x 35
mm panel (four horizondals) with plank of
16mm thick including cost of all materias
and labour charges,etc.complete
but
excluding cost of fittings

0.060 m3
0.60 No
3.27 No
0.36 No
0.015 m3
%
%
%

1 m3

(If size of frame and


shutter varies, qty of
wood will vary)

Sawyers
Carpenter
Man
Deduct
Cost of outerslabs at 25% of cost of wood
log value.
HA
OH
CP
Total

1 Each
1 Each
1 Each

(10 nos per cum)

1
1
1
1

Wood log
Sawyers
Carpenter
Man

1
1
1
1

1m

0.077
0.77
4.16
0.46

m3
No
No
No
2

0.36 m

(If size of frame and


shutter varies, qty of
wood will vary)

m3
Each
Each
Each

(54 nos per cum)


(6 nos per cum)

/m2
(If size of frame and
shutter varies, qty of
wood will vary)

m3
Each
Each
Each

1 m

59

(10 nos per cum)

3
1 m

Glass panels

(6 nos per cum)

/m2

Wood log
Sawyers
Carpenter
Man
Deduct
Cost of outerslabs at 25% of cost wood log
value
HA
OH
CP
Total
Providing and fixing glazed windows with
wooden frames of 100 x 70 mm and shutters
of wooden frame 70 x 35 mm panel with
glass panels including cost of all materials
and labour charges,etc.complete
but
excluding cost of fittings , grills etc.

(54 nos per cum)

3
1 m

m3
No
No
No

%
%
%

Remarks

Wood log

Providing and fixing wood pannelled


windows with frames of 100 x 70 mm and
shutters of frame 70 x 35 mm pannel with
plank of 16mm thick including cost of all
materials andl labour charges,etc.complete
but excluding cost of fittings , grills etc.

0.021 m3

Amount

Note:
1. For I st floor, add 10
% of extra labour of
Ground floor
2. For II nd floor, add 20
% of extra labour of
Ground floor and so on

1 m2

0.085
0.85
4.59
0.51

Unit

Rate

(10 nos per cum)


(54 nos per cum)
(6 nos per cum)

0.019 m3
%
%
%
4

1 m2

0.093
0.93
5.02
0.56

m3
No
No
No
2

0.70 m

0.023 m3
%
%
%
5

Wood log
Sawyers
Carpenter
Man
Deduct
Cost of outerslabs at 25% of cost wood log
value
HA
OH
CP
Total

1 m2

3
18.1 dm
0.46 No
0.055 No

4.5 dm3
%
%
%
7

Glass panels
Deduct
Cost of outerslabs at 25% of cost wood log
value
HA
OH
CP
Total

dm3
No
No
No

%
%
%

1 Kg

/m2
(If size of frame and
shutter varies, qty of
wood will vary)

m3
Each
Each
Each

Wood log
Sawyers
Carpenter
Man

Providing
wood
pieces
for
doors,windows,ventilators,and other items of
suitable size and shape etc.

0.399 dm3

1 m3

Providing and fixing glazed ventilator with


wooden frames of 100 x 70 mm and
louvered glass panes including cost of all
materials and labour charges,etc. complete
but excluding cost of fittings , etc.

1 dm3

1.512
0.015
0.022
0.012

Deduct
Cost of outerslabs at 25% of cost wood log
value
HA
OH
CP
Total

(10 nos per cum)


(54 nos per cum)
(6 nos per cum)

m3

/m2

m3
Each
Each
Each

m3

/dm3
(if thickness vary qty will
vary)

Providing wooden planks of 12mm thick of


suitable
size
and
shape
after
planing,grooving etc.
Wood log
Sawyers
Man
Deduct
Cost of outerslabs at 25% of cost wood log
value
HA
OH
CP
Total
Providing MS flats to windows and
ventilators
including
cutting,making
holes,etc. complete.
60

m3
Each
Each

m3

/m2

1.05 Kg
0.05 No
0.008 No
%
%
%
8

1 Kg

1.05 Kg
0.02 No
0.02 No
%
%
%
9

1 Kg

1.05 Kg
20 %
%
%

Flat iron
Black smith
Man
HA
OH
CP

Qtl
Each
Each

Total
Providing MS rods to windows and
ventuilators including cutting, etc. complete.

/Kg

Qtl

M S rod
Black smith
Man
HA
OH
CP

Each
Each

Total
Fabricating, fixing steel windows including
frames and shutters, fixing arrangements and
fittings such as hinges, stoppers, closers etc.
but excluding glass panels.
Cost of angles, flat, MS rods, etc (average
cost of angles, rods, flats)
Fabrication charges, sundries etc ( 20 % of
above)

/Kg

Qtl

OH
CP
Total

10

1 m2

Supplying ang fixing glass panels for steel


windows icluding cost of all materials and
labour charges etc. complete.

2
1.00 m
20 %

Glass
For biniding materials, beadings, etc. ( 20 %
of above)
Fitter
Man
HA
OH

0.15 No
0.15 No
%
%
%

/Kg

m2

Each
Each

CP
/m2

Total
11

1 m2

3.50
0.86
0.12
0.12
5

m
2

m
No
No
%
%
%
%

Supplying and fitting PVC fully panelled


doors including cost of all fittings and
labour charges etc. complete.
Square tubes
Shutter
Fabricator
Man
Cost of fittings ( 5 % of above total)
HA
OH
CP

m
m2
Each
Each

Total

61

/m2

12

1 m2

Fabricating & fixing Anodised Aluminium


partialy glased single shutter door with 63
x 37 x 1.5 mm door frames and shutter
frames of size 45x45x1.5 mm at top ,middle
and
side,
95x45x1.5mm
aluminium
rectangular tube at bottom and providing
plain glass and hylam sheet ( equally
devided) for shutter including aluminium
clips and rubber beeding for fixing glass/
sheet, reinforcing with steel rod at top and
bottom of shutter including all materials and
fixing charges etc. but excluding cost of
fittings.

1.95 Kg
2.05 Kg

Aluminium tube for outer frame


Aluminium tube for sides, top and middle of
shutter
Aluminium tube for bottom of shutter
Hylam sheet(prelaminated sheet-12mm)

Kg

Glass
Rubber beeding with clip
Aluminium fabricator
Fitter
Man
HA
OH
CP

m2
m
Each
Each
Each

0.53 Kg
0.39 m2
0.39
3.38
0.54
0.54
0.54

13

m2
m
No
No
No
%
%
%
2

1m

1.72 Kg
3.01 Kg
0.53 Kg
2
0.74 m
4.44 m
0.55 No
0.55 No
0.55 No
%
%
%

(if size of frame and


shutter varies, quantity of
Aluminium and glass will
vary)

Kg
Kg
m2

/m2

Total
Fabricating & fixing Anodised Aluminium
fully glazed double shutter door with 63 x
37 x 1.5 mm door frames and shutter frames
of size 45x45x1.5 mm at top ,middle and
side, 95x45x1.5mm aluminium rectangular
tube at bottom and providing thick plain
glass for shutter, including aluminium clips
and rubber beeding for fixing glass
reinforcing with steel rod at top and bottom
of shutter including all materials and fixing
charges etc. but excluding cost of fittings.
Aluminium tube for outer frame
Aluminium tube for sides, top and middle of
shutter
Aluminium tube for bottom of shutter
Glass
Rubber beeding with clip
Aluminium fabricator
Fitter
Man
HA
OH
CP
Total

62

(if size of frame and


shutter varies, quantity of
Aluminium and glass will
vary)

Kg
Kg
m
m2
m
Each
Each
Each

/m2

14

1 m2

3.40 Kg
2.57 Kg
2
0.71 m
4.84 m
0.58 No
0.58 No
%
%
%

(if size of frame and


shutter varies, quantity of
Aluminium and glass will
vary)

Fabricating & fixing Anodised Aluminium


fully glazed window with aluminium tube
frames of 63 x 37 x 1.5 mm in size and
37x24x1.5 mm frame with glass as shutters
including all materials and fixing charges etc.
but excluding cost of fittings.
Aluminium tube for outer frame
Aluminium shutter frame

Kg
Kg
m2
m
Each
Each

Glass
Rubber beeding with clip
Aluminium fabricator
Man
HA
OH
CP
Total

15

1 m2

4.45 Kg
3.00 Kg
2
0.88 m
6.71 m
1.11 No
0.56 No
%
%
%

Fabricating & fixing Anodised Aluminium


fully glazed ventilator with Aluminium
sections 50 x 25 x 1.5 mm in size with 4mm
thick plain glass as shutters including cost of
all fittings such as aluminium stay , hooks,
hinges etc. complete.
Aluminium tube for outer frame
Aluminium shutter frame

Kg
Kg
m2
m
Each
Each

Glass
Rubber beeding with clip
Aluminium fabricator
Man
HA
OH
CP
Total

63

/m2

CHAPTER XI
WATER SUPPLY AND SANITARY WORKS
Sl.
No.

Quantity

Description of items

Unit

Rate

Amount

Remarks

A. WATER SUPPLY WORKS


1

1m

30.00
15
0.67
0.67
2

m
%
No.
No.
%
%
%
%

1m

Internal work
Supplying, laying and jointing 20mm
nominal dia. PVC pipes ( Kgf/cm) and
specials such as tees, bends, elbows,
checknuts etc. including cutting and making
good the walls, etc. complete.
Details of cost for 30m.
PVC pipes 20mm dia. ( Kgf/cm)
Add for specials
Fitter
Man mazdoor
Solvent cement and other sundries (2 % of
HA
OH
CP
Total
Hence for 1m

1m
1 Each
1 Each

/30

/m

Supplying, laying and jointing 25mm


nominal dia. PVC pipes ( Kgf/cm) and
specials such as tees, bends, elbows,
checknuts etc. including cutting and making
good the walls, etc. complete.
Details of cost for 30m.

30.00 m
15 %

1m

Add for specials

1.00 No.

Fitter

1 Each

0.67 No.
2%

Man mazdoor
Solvent cement and other sundries (2 % of
cost of PVC pipe)
HA
OH
CP
Total
Hence for 1m

1 Each

%
%
%

PVC pipes 25mm dia. (10Kgf/cm)

1m

/30

/m

Supplying, laying and jointing 32mm


nominal dia. PVC pipes ( Kgf/cm) and
specials such as tees, bends, elbows,
checknuts etc. including cutting and making
good the walls, etc. complete.
Details of cost for 30m.

30.00 m
15 %

PVC pipes 32mm dia. ( Kgf/cm)

1m

Add for specials

1.00 No.

Fitter

1 Each

1.00 No.
2%

Man mazdoor
Solvent cement and other sundries (2 % of
cost of PVC pipe)

1 Each

64

%
%
%

HA
OH
CP
Total
Hence for 1m

1m

30.00
15
1.00
1.33
2

m
%
No.
No.
%
%
%
%

1m

30.00
15
1.33
1.33
2

m
%
No.
No.
%
%
%
%

1m

30.00
15
1.33
1.33
2

m
%
No.
No.
%
%
%

/30

/m

Supplying, laying and jointing 40mm


nominal dia. PVC pipes (Kgf/cm) and
specials such as tees, bends, elbows,
checknuts etc. with clamps including cutting
and making good the walls, painting the paint
two coats, etc. complete.
Details of cost for 30m.
PVC pipes 40mm dia. ( Kgf/cm)
Add for specials
Fitter
Man mazdoor
Solvent cement and other sundries (2 % of
cost of PVC pipe)
HA
OH
CP
Total
Hence for 1m

1m
1 Each
1 Each

/30

/m

Supplying, laying and jointing 50mm


nominal dia. PVC pipes ( Kgf/cm) and
specials such as tees, bends, elbows,
checknuts etc. including cutting and making
good the walls, etc. complete.
Details of cost for 30m.
PVC pipes 50mm dia. ( Kgf/cm)
Add for specials
Fitter
Man mazdoor
Solvent cement and other sundries (2 % of
cost of PVC pipe)
HA
OH
CP
Total
Hence for 1m

1m
1 Each
1 Each

/30

/m

Supplying, laying and jointing 63mm


nominal dia. PVC pipes ( Kgf/cm) and
specials such as tees, bends, elbows,
checknuts etc. including cutting and making
good the walls, etc. complete.
Details of cost for 30m.
PVC pipes 63mm dia. ( Kgf/cm)
Add for specials
Fitter
Man mazdoor
Solvent cement and other sundries (2 % of
cost of PVC pipe)
HA
OH
65

1m
1 Each
1 Each

CP
Total
Hence for 1m

1m

30.00
15
1.333
1.333
2

m
%
No.
No.
%
%
%
%

1m

30.00
15
1.333
1.333
2

m
%
No.
No.
%
%
%
%

1m

30.00
15
1.333
1.333
2

m
%
No.
No.
%
%
%
%

Supplying, laying and jointing 75mm


nominal dia. PVC pipes ( Kgf/cm)
including cutting and making good the walls,
etc. complete.
Details of cost for 30m.
PVC pipes 75mm dia. ( Kgf/cm)
Add for specials
Fitter
Man mazdoor
Solvent cement and other sundries (2 % of
cost of PVC pipe)
HA
OH
CP
Total
Hence for 1m

/30

/m

1m
1 Each
1 Each

/30

/m

Supplying, laying and jointing 90mm


nominal dia. PVC pipes ( Kgf/cm)
including cutting and making good the walls,
etc. complete.
Details of cost for 30m.
PVC pipes 90mm dia. ( Kgf/cm)
Add for specials
Fitter
Man mazdoor
Solvent cement and other sundries (2 % of
cost of PVC pipe)
HA
OH
CP
Total
Hence for 1m

1m
1 Each
1 Each

/30

/m

Supplying, laying and jointing 110mm


nominal dia. PVC pipes ( Kgf/cm)
including cutting and making good the walls,
etc. complete.
Details of cost for 30m.
PVC pipes 110mm dia. ( Kgf/cm)
Add for specials
Fitter
Man mazdoor
Solvent cement and other sundries (2 % of
cost of PVC pipe)
HA
OH
CP
Total
Hence for 1m
External work

66

1m
1 Each
1 Each

/30

/m

10

1m

30.00
5
0.17
0.17
1.50
2

m
%
No.
No.
No.
%
%
%
%

11

1m

30.00
5
0.25
0.25
1.50
2

m
%
No.
No.
No.
%
%
%
%

12

1m

30.00
5
0.33
0.33
1.50
2

m
%
No.
No.
No.
%
%
%
%

Supplying, laying and jointing 20mm


nominal dia. PVC pipes ( Kgf/cm) and
specials such as tees, bends, elbows,
checknuts, etc. including refilling the
trenches, etc. complete.
Details of cost for 30m.
PVC pipes 20mm dia.(10Kgf/cm)
Add for specials
Fitter
Man mazdoor
Man mazdoors for trenching and refilling
Solvent cement and other sundries (2 % of
cost of PVC pipe)
HA
OH
CP
Total
Hence for 1m

1m
1 Each
1 Each
1 Each

/30

/m

Supplying, laying and jointing 25mm


nominal dia. PVC pipes ( Kgf/cm) and
specials such as tees, bends, elbows,
checknuts, etc. including refilling the
trenches, etc. complete.
Details of cost for 30m.
PVC pipes 25mm dia.( Kgf/cm)
Add for specials
Fitter
Man mazdoor
Man mazdoors for trenching and refilling
Solvent cement and other sundries (2 % of
cost of PVC pipe)
HA
OH
CP
Total
Hence for 1m

1m
1 Each
1 Each
1 Each

/30

/m

Supplying, laying and jointing 32mm


nominal dia. PVC pipes ( Kgf/cm) and
specials such as tees, bends, elbows,
checknuts, etc. including refilling the
trenches, etc. complete .
Details of cost for 30m.
PVC pipes 32mm dia.(10Kgf/cm)
Add for specials
Fitter
Man mazdoor
Man mazdoors for trenching and refilling
Solvent cement and other sundries (2 % of
cost of PVC pipe)
HA
OH
CP
Total
Hence for 1m

67

1m
1 Each
1 Each
1 Each

/30

/m

13

1m

30.00
5
0.33
0.33
1.50
2

m
%
No.
No.
No.
%
%
%
%

14

1m

Supplying, laying and jointing 40mm


nominal dia. PVC pipes ( Kgf/cm) and
specials such as tees, bends, elbows,
checknuts, etc. including refilling the
trenches, etc. complete.
Details of cost for 30m.
PVC pipes 40mm dia.( Kgf/cm)
Add for specials
Fitter
Man mazdoor
Man mazdoor for trenching and refilling
Solvent cement and other sundries (2 % of
cost of PVC pipe)
HA
OH
CP
Total
Hence for 1m

1m
1 Each
1 Each
1 Each

/m

/30

Supplying, laying and jointing 50mm


nominal dia. PVC pipes ( Kgf/cm) and
specials such as tees, bends, elbows,
checknuts, etc. including refilling the
trenches, etc. complete.
Details of cost for 30m.

30.00
5
0.33
0.33
1.50
2

m
%
No.
No.
No.
%

PVC pipes 50mm dia.( gf/cm)


Add for specials
Fitters
Man mazdoor
Man mazdoor for trenching and refilling
Solvent cement and other sundries (2 % of
cost of PVC pipe)

%
%
%

HA
OH
CP
Total
Hence for 1m

15

1m

30.00
5
0.33
0.33
1.50
2

m
%
No.
No.
No.
%
%
%
%

1m
1 Each
1 Each
1 Each

/30

Supplying, laying and jointing 63mm


nominal dia. PVC pipes ( Kgf/cm) and
specials such as tees, bends, elbows,
checknuts, etc. including refilling the
trenches, etc. complete.
Details of cost for 30m.
PVC pipes 63mm dia.( Kgf/cm)
Add for specials
Fitter
Man mazdoor
Man mazdoor for trenching and refilling
Solvent cement and other sundries (2 % of
cost of PVC pipe)

/m

1 Each
1 Each
1 Each

HA
OH
CP
Total
Hence for 1m
68

/30

/m

16

30.00
5
0.33
0.33
1.50
2

m
%
No.
No.
No.
%
%
%
%

Supplying, laying and jointing 75mm


nominal dia. PVC pipes ( Kgf/cm) and
specials such as tees, bends, elbows,
checknuts, etc. including refilling the
trenches, etc. complete.
Details of cost for 30m.
PVC pipes 75mm dia.(Kgf/cm)
Add for specials
Fitter
Man mazdoor
Man mazdoor for trenching and refilling
Solvent cement and other sundries (2 % of
cost of PVC pipe)
HA
OH
CP
Total
Hence for 1m

1 Each
1 Each
1 Each

/30

/m

Supplying, laying and jointing 90mm


nominal dia. PVC pipes ( Kgf/cm) and
specials such as tees, bends, elbows,
checknuts, etc. including refilling the
trenches, etc. complete.

17

30.00
5
0.33
0.33
1.50
2

m
%
No.
No.
No.
%

Details of cost for 30m.


PVC pipes 90mm dia.(Kgf/cm)
Add for specials
Fitter
Man mazdoor
Man mazdoor for trenching and refilling
Solvent cement and other sundries (2 % of
cost of PVC pipe)

%
%
%

HA
OH
CP
Total
Hence for 1m

18

30.00
5
0.330
0.330
1.50
2

m
%
No.
No.
No.
%
%
%
%

Supplying, laying and jointing 110mm


nominal dia. PVC pipes ( Kgf/cm) and
specials such as tees, bends, elbows,
checknuts, etc. including refilling the
trenches, etc. complete.
Details of cost for 30m.
PVC pipes 110mm dia.( Kgf/cm)
Add for specials
Fitter
Man mazdoor
Man mazdoor for trenching and refilling
Solvent cement and other sundries (2 % of
cost of PVC pipe)
HA
OH
CP
Total
Hence for 1m

69

1 Each
1 Each
1 Each

/m

/30

1 Each
1 Each
1 Each

/30

/m

Supplying, laying and jointing 160mm


nominal dia. PVC pipes ( Kgf/cm) and
specials such as tees, bends, elbows,
checknuts, etc. including refilling the
trenches, etc. complete.

19

30.00
5
0.330
0.330
1.50

m
%
No.
No.
No.

2%
%
%
%

Details of cost for 30m.


PVC pipes 160mm dia
Add for specials
Fitter
Man mazdoor
Man mazdoor for trenching and refilling

1 Each
1 Each
1 Each

Solvent cement and other sundries (2 % of


cost of PVC pipe)
HA
OH
CP
Total
Hence for 1m

/m

/30

B. SANITARY WORKS
1 Each Supplying and fixing European type
20
earthenware WC pan with trap and
Duroplastic seat with lid , 15 litres PVC low
level flush tank with all fittings, including
cutting and making good the walls and
floors, cost and conveyance of all materials,
labour charges, etc. complete.
1.00
1.00
1.00
4.00
0.50
0.50
1.00
1

21

No
No
No.
Kg
No
No
No
%
%
%
%

1 Each

1.00
1.00
1.00
1.00
1.00
1.00
1.00
2.00
0.50

No.
No.
No.
No.
No.
No.
pair
Kg
No

Earternware European type WC pan


Duroplastic seat cover
PVC low level flush tank 15 litre capacity
Cement
Plumber
Mason
Man mazdoor
Sundries etc ( 1 % of above )
HA
OH
CP
Total

1
1
1
1
1
1
1

Each
Each
Each
MT
Each
Each
Each

/Each

Supplying and fixing .xmm or


nearest size eartern ware wash hand basin
with fitting like CP angle cock,
couplings,nylone connections,bolts, etc.
including cutting and making good to the
wall etc. complete.
Wash hand basin
15 mm C.P. brass pillar tap
15 mm C.P. angle cock
15 mm C.P. waste coupling.(MR)
15 mm nylone connection
32mm PVC waste pipe heavy
Brackets
Cement
Plumber

1
1
1
1
1
1
1
1
1
70

Each
Each
Each
Each
Each
Each
pair
MT
Each

0.50 No
1.00 No
2%
%
%
%

Mason
Man mazdoor

1 Each
1 Each

Sundries etc ( 2 % of above material)


HA
OH
CP
Total

22

1 Each

1.00 No
1.00 No
5%
0.60 No
0.60 No
%
%
%

23

1 No

1 No
10 %
%
%
%

/Each

Supplying and fixing Orissa pan water closet


with trap 'S' or 'P' including embedding the
closet and trap concrete and forming
squatting platform of suitable size plastered
over with cement mortar 1:3, cutting and
making good to the floors including cost and
conveyance of all materials, labour charges,
etc. complete.
Orissa pan water closet
Trap
Provision for making platform, Sundries etc (
5 % of above material)
Mason
Man mazdoor
HA
OH
CP
Total
Supplying and fitting sanitary fittings like
trap, cowl, mirror,soap dish, towel rail etc
including cost of all materials and labour
charges etc. complete
Cost of trap/cowl etc
fitting charges, sundries such as solvent,
plugs, etc. 10 % of above
HA
OH
CP
Total

71

1 Each
1 Each

1 Each
1 Each

/Each

/Each

CHAPTER XII
FLOORING
Sl.
No.
1

Quantity
1 m

Description of item

Unit

Rate

Note: Cost of cement may


be included in the item or
excluded and measured
as a separate item.

Cement

1 MT

0.036
0.0713
0.01
0.18

M sand / River sand

1
1
1
1

40 mm coarse aggregate
Mason
Man
HA
OH
CP
Plastering with C.M.1:3, 12mm thick

m
m
Each
Each

1 m
Total

1 m

Flooring with C.C.1:4:8, 75mm thick using


40mm nominal size aggregate and plastered
over with 12mm thick C.M.1:3 one coat and
floated hard and trowelled smooth with neat
cement flushing coat including cost of all
materials and labour charges etc. complete.

1.00 m

Cost of 1m2 C.C.1:4:8 75mm thick with


12mm thick plasterin in C.M 1:3

1.00 m

Cost of cement flushing coat

/m

1 m
1 m

Total
3

1 m

Flooring with C.C.1:4:8, 75mm thick using


40mm nominal size aggregate and plastered
over with 12mm thick C.M.1:4 one coat and
floated hard and trowelled smooth with neat
cement flushing coat and thread lining
including cost of all materials, labour
charges, etc. complete.

1.00 m

Cost of 1m2 C.C.1:4:8 75mm thick with


12mm thick plasterin in C.M 1:3 including
flushing coat.

1.00 m

Thread lining
Total

1 m

Remarks

Flooring with C.C.1:4:8, 75mm thick using


40mm nominal size aggregate and plastered
over with 12mm thick C.M.1:3 one coat
floated hard and trowelled smooth, including
cost of all materials and labour charges etc.
complete.

12.825 Kg
m
m
No
No
%
%
%
1.00 m

Amount

Floor plastering with C.M. 1:3, 12mm thick


one coat and floated hard and trowelled
smooth with neat cement flushing coat mixed
with red / black oxide, including cost of all
materials, labour charges, etc. complete.
72

/m

1 m
1 m
/m

1.00 m
1.00 m
0.10 Kg
%
%

Plastering with C.M.1:3, 12mm thick


Cost of cement flushing coat
Cost of red / black oxide powder
OH
CP

1 m
1 m
1 Kg

Total
5.a

1 m

1.05
1.00
0.48
0.15
0.09
1

m
m
Kg
No
No
%
%
%
%

5.b

1 m

1.05
1.00
0.30
0.18
1

m
m
No
No
%
%
%
%

6.a

Supplying and paving Ceramic / Vitrified


tiles of approved quality, size and colour on
floors over C.M 1:6, 15mm thick and
flushing coat, pointing with coloured cement,
including cost of all materials and labour
charges etc. complete.
Ceramic / Vitrified tiles
Plastering in C.M 1:6, 15mm thick
Cement
Tile paver
Man
Coloured cement, sundries, etc., 1 % of total
above
HA
OH
CP
Total
Supplying and Dadoing walls with Ceramic /
Vitrified tiles of approved quality, size and
colour over a cement flusing coat and
pointing with coloured cement, including
cost of all materials, labour charges etc.
complete.
Ceramic / Vitrified tiles
Cement Flushing coat
Tile paver
Man
Coloured cement, sundries, etc., 1 % of total
above
HA
OH
CP
Total

1 m

Supplying and paving Marble slabs of


approved quality and colour on floors
overC.M.1:6, 15 mm thick and flushig coat,
pointing with coloured cement, polishing
with machine 3 coats to smooth finish and
wax polishing including cost of all materials,
labour charges, etc. complete.

1.05 m
1.00 m
0.20 Kg

Marble slabs
Plastering in C.M 1:6, 15mm thick
Cement for flushing coat
Labour for laying
Tile paver
Man
Coloured cement, sundries, etc., 1 % of total
above
Labour for polishing

0.20 No.
0.1000 No.
1%

/m

73

1
1
1
1
1

m
m
MT
Each
Each

/m

1
1
1
1

m
m
Each
Each

/m

1 m
1 m
1 MT
1 Each
1 Each

0.40 No.

Spl. Mazdoor for polishing

1 Each

0.20 No.
5.00 %

Man
Polishing machine, stones, etc.( 5 % of total
above)
Mansion polish
HA
OH
CP
Total
Supplying and Dadoing walls with Marble
slabs of approved quality and colour over
cement flushing coat and polishing with
machine 3 coats to smooth finish, pointing
with coloured cement and wax polishing,
including cost of all materials, labour charges
etc. complete.

1 Each

Marble slabs
Cement flusging coat
Labour for laying
Tile paver
Man
Coloured cement, sundries, etc., 1 % of total
above
Labour for polishing
Spl. Mazdoor for polishing
Man
Polishing machine, stones, etc.( 5 % of total
above)
Mansion polish

1 m
1 m

0.01 Kg
%
%
%
6.b

1 m

1.05 m
1.00 m
0.30 No.
0.2000 No.
1%

0.40 No.
0.20 No.
5.00 %
0.01 Kg
%
%
%

1 Kg

/m

1 Each
1 Each

1 Each
1 Each

1 Kg

HA
OH
CP
Total

7.a

1 m

Supplying, paving and polishing Marble


tiles of approved quality and colour on floors
over C.M.1:6, 15mm thick and flushing coat
and polishing with machine 3 coats to
smooth finish,pointing with coloured cement
and wax polishing, including cost of all
materials and labour charges etc. cement.

1.05 m
1.00 m
0.20 Kg

Marble tiles
Plastering in C.M 1:6, 15mm thick
Cement for flushing coat
Labour for laying
Tile paver
Man
Coloured cement, sundries, etc., 1 % of total
above
Labour for polishing
Spl. Mazdoor for polishing
Man
Polishing machine, stones, etc.( 5 % of total
above)
Mansion polish

0.10 No.
0.05 No.
1%

0.40 No.
0.20 No.
5.00 %
0.01 Kg

74

/m

1 m
1 m
1 MT
1 Each
1 Each

1 Each
1 Each

1 Kg

%
%
%
7.b

1 m

1.05 m
1.00 m
0.15 No.
0.088 No.
1%

0.60 No.
0.20 No.
0.01 Kg
%
%
%

8.a

1 m

1.05 m
1.00 m
0.20 Kg
0.20 No.
0.10 No.
1%
%
%
%

HA
OH
CP
Total
Supplying and Dadoing walls with Marble
tiles of approved quality and colour over
cement flushing coat and polishing with
machine 3 coats to smooth finish, pointing
with coloured cement and wax polishing,
including cost of all materials, labour charges
etc. complete.
Marble tiles
Cement flusging coat
Labour for laying
Tile paver
Man
Coloured cement, sundries, etc., 1 % of total
above
Labour for polishing
Spl. Mazdoor for polishing
Man
Mansion polish
HA
OH
CP
Total
Supplying and paving Granite slabs of
approved quality and colour on floors
overC.M.1:6, 15 mm thick and flushig coat,
pointing with coloured cement, including
cost of all materials, labour charges, etc.
complete.
Granite slabs
Plastering in C.M 1:6, 15mm thick
Cement for flushing coat
Labour for laying
Tile paver
Man
Coloured cement, sundries, etc., 1 % of total
above
HA
OH
CP
Total

75

/m

1 m
1 m
1 Each
1 Each

1 Each
1 Each
1 Kg

/m

1 m
1 m
1 MT
1 Each
1 Each

/m

8.b

1 m

Supplying and Dadoing walls with Granite


slabs of approved quality and colour over
cement flushing coat , pointing with
coloured cement ,including cost of all
materials, labour charges etc. complete.

1.05 m
1.00 m

Granite slabs
Cement flusging coat
Labour for laying
Tile paver
Man
Coloured cement, sundries, etc., 1 % of total
above
HA
OH
CP
Total

0.30 No.
0.20 No.
1%
%
%
%

9.a

/m

Supplying, paving and polishing Granite


tiles of approved quality and colour on floors
over C.M.1:6, 15mm thick and flushing coat
,pointing with coloured cement , including
cost of all materials and labour charges etc.
cement.

1.05 m
1.00 m
0.20 Kg

Granite tiles
Plastering in C.M 1:6, 15mm thick
Cement
Labour for laying
Tile paver
Man
Coloured cement, sundries, etc., 1 % of total
above
HA
OH
CP
Total
Supplying and Dadoing walls with Granite
tiles of approved quality and colour over
cement flushing coat , pointing with
coloured cement ,including cost of all
materials, labour charges etc. complete.

1 m
1 m
1 MT

1 m
1 m

Granite tiles
Cement flusging coat
Labour for laying
Tile paver
Man
Coloured cement, sundries, etc., 1 % of total
above
HA

%
%

OH
CP

%
%
%
1 m

1.05 m
1.00 m
0.20 No.
0.10 No.
1%

Total
10

1 Each
1 Each

1 m

0.10 No.
0.05 No.
1%

9.b

1 m
1 m

1 m

Supplying and Fixing PVC / Vinyl sheet


flooring of approved make including cost of
all materials, labour charges, etc. complete.
76

1 Each
1 Each

/m

1 Each
1 Each

/m

1.05
0.03
0.03
5.00

m
No.
No.
%
%
%
%

PVC / Vinyl flooring sheet


Special Mazdoor
Man
Adhesives, sundries, etc., of total above
HA
OH
CP

1 m
1 Each
1 Each

Total

77

/m

CHAPTER XIII
ROOFING
Sl.
Quantity
No.
1

Description of item

Rate

1 Kg

Fabricating supplying and installing steel


roof truss, purlins etc using MS angles, plates
etc. including cost of all materials, labour
charges ,painting with two coats of synthetic
enamel paint over a coat of iron primer etc
complete

1.05 Kg

Cost of MS angles, plates , etc ( Average


cost)
Iron primer
Synthetic enamel paint
Welding Rod

0.002 litre
0.005 litre
1 No
0.02 No
0.013 No
0.003 No
0.01 No
0.003 No
10 %

%
%
%

Unit

1
1
2
100

1 Kg

1.05
0.002
0.005
1.00
0.014
0.009
0.002
0.01
0.003
10

Remarks

Qtl
litre
litre
No

3
1m
1 Each
1 Each

Blacksmith
Heavy load Mazdoor
Fitter
Welder

1 Each

Painter

1 Each

Erection charge, hire for welding plant,


grinding stone, current charge etc ( 1 % of
cost of steel materials)
HA
OH
CP
Total

Amount

/Kg

Fabricating supplying and installing steel


roof truss, purlins etc using pipes / hollow
section pipes etc. including cost of all
materials, labour charges ,painting with two
coats of synthetic enamel paint over a coat of
iron primer etc complete

Kg
litre
litre
No
No
No
No
No
No
%

Cost of pipe
Iron primer
Synthetic enamel paint
Welding Rod
Blacksmith
Heavy load Mazdoor
Fitter
Welder
Painter
Erection charge, hire for welding plant,
grinding stone, current charge etc ( 1 % of
cost of steel materials)

%
%
%

HA
OH
CP
Total

78

1
1
2
100
1
1
1
1
1

Qtl
litre
litre
No
Each
Each
Each
Each
Each

/Kg

1 m2

8.60 kg

Roofing with GI corrugated sheet for roofs,


shades including all fittngs like nuts and
bolts, clambs, J -bolts, including cost all
materials, labour charges, etc. complete.
GI corrugated sheet

1 MT
Wt. considered for 0.8mm
thick sheet. Wt. may be
varied according to the
thickness
of
sheet
considered.

2.20 No
10 %
0.135 No
0.135 No
%
%
%
4

1 m2

1.15 m2
1.4 No
10 %
0.16 No
0.16 No
%
%
%

GI hooks with bolt and nuts


Sundries, scaffolding etc ( 10 % of cost of
sheet)
Fitter
Man
HA
OH
CP
Total

1 Each

1 Each
1 Each
`

/m2

Roofing with AC corrugated sheet for roofs,


shades including all fittings like nuts and
bolts, clambs ,J -bolts, including cost all
materials, labour charges etc. complete
AC Corrugated sheet

1 m2

GI hooks with bolt and nuts


Sundries, scaffolding etc ( 10 % of cost of
sheet)
Fitter

1 Each

Man
HA
OH
CP

1 Each
1 Each
`

/m2

Total
5

1m

1.03 Pair
0.05 No
0.05 No
%
%
%
6

Providing AC Ridge with all fittings


including cost of all materials, labour charges
etc. complete.
AC Ridge
Carpenter
Man
HA
OH
CP
Total

1 m2

Roofing with MP Ist class tiles for roofs,


shades etc including cost of all materials,
labour charges etc. complete.

16 No
10 %

MP Tiles
Sundries, scaffolding etc ( 10 % of cost of
sheet)
Mason
Man
HA
OH
CP
Total

0.035 No
0.035 No
%
%
%

79

1 pair
1 Each
1 Each

/m

1000 No

1 Each
1 Each
`

/m2

1m

2.7 No
0.020
0.72
0.08
0.05

m
kg
No
No
%
%
%

Providing MP Hip and Ridge tiles, pointing


with Cement Mortar 1:6 including cost of all
materials, labour charges, etc complete.
MP Hip and Ridge tiles
Sand
Cement
Mason
Man
HA
OH
CP

1000
1
1
1
1

No
m3
MT
Each
Each
`

Total

80

/m

CHAPTER XIV
ROAD WORKS
Sl.
No.
1

Quantity
1 m2
0.05 No.
%
%
%

1 m2
0.025 No.
%
%
%

1 m

1 m
0.18 No.
%
%
%

1 m

1 m
0.18 No.
%
%
%

1 m

0.70 m
0.30 m
0.18 No.
%
%
%

Description of item

Rate

Unit

Amount

Remarks

Sectioning upto 150mm and forming the


surface of new roads
Man
HA
OH
CP
Total

/m2

Sectioning upto 150mm and forming the


surface of old roads
Man
HA
OH
CP
Total

/m2

Collection and supply of 60mm IRC size


hard granite broken stone including stacking
on road side in standard profiles for
measurements, etc. complete.
60mm broken stone
Man for stacking
HA
OH
CP
Total
Collection and supply of 36mm IRC size
hard granite broken stone including stacking
on road side in standard profiles for
measurements, etc. complete.
36mm broken stone
Man for stacking
HA
OH
CP
Total

1 m

/m

1 m

/m

Collection and supply of 60mm & 36mm


(7:3) IRC size hard granite broken stone
including stacking on road side in standard
profiles for measurements, etc. complete.
60mm broken stone
36mm broken stone
Man for stacking
HA
OH
CP

1 m
1 m

Total

81

/m

1 m

1 m
0.18 No.
%
%
%

Collection and supply of 12mm IRC size


hard granite broken stone including stacking
on road side in standard profiles for
measurements, etc. complete.
12mm broken stone
Man for stacking
HA
OH
CP

1 m

Total
7

1 m

1 m
0.18 No.
%
%
%

/m

Collection and supply of 6mm IRC size hard


granite broken stone including stacking on
road side in standard profiles for
measurements, etc. complete.
6mm broken stone
Man for stacking
HA
OH
CP

1 m

Total
8

1 m

1 m
0.12 No.
%
%
%

/m

Collection and supply of good quality red


earth including stacking on road side in
standard profiles for measurements, etc.
complete.
Red earth
Man for stacking
HA
OH
CP

1 m

Total
9

1 m

1 m
0.10 No.
%
%
%

/m

Collection and supply of quarry dust


including stacking on road side in standard
profiles for measurements, etc. complete.
Quarry dust
Man for stacking
HA
OH
CP

1 m

Total

82

/m

10

1 m

0.117 No.
0.067 No.
0.022 litre
2%
0.0012 day
%
%
%

Metalling the roadway, 100mm spread


thickness compacted to 75mm using
departmental broken stones (grade in the
ratio of 7:3 of 60mm and 36mm sizes) 1m
per 10m and departmental blinding
materials 0.20m per 10m, bed rolling,
spreading broken stones to template, rolling
dry to compaction from sides to centre until
the movement of broken stones cease,
watering profusely and rolling until the fines
cream up and fill the voids of the stones, then
spreading the gravelly earth and sweeping
into the joints, watering and rerolling until
the gravelly earth has worked into all the
crevises and only a thin coat of slurry
remains, then take off the roller and allow to
set to harden for 24 hours and any deformity
is rectified, including fencing, lighting,
watching and maintaining the surface free of
ruts for 15 days after completion including
hire charges of power roller, all labour
charges, etc. complete for W.B.M.Sub base
course.

(Daily out-turn of roller 840m)


Man for spreading broken stones and
blinding materials
Woman for spreading broken stones and
blinding materials and watering
Diesel for roller
Sundries(such as fencing, lighting, watching,
etc.)2 % of total of above
Hire charges for power roller
HA
OH
CP
Total

83

1 Each
1 Each
1 litre

1 day

/m2

11

1 m

0.117 No.
0.067 No.
0.022 litre
2%
0.0012 day
%
%
%

Metalling the roadway, 100mm spread


thickness compacted to 75mm using 36mm
departmental broken stones, 1m per 10m
and departmental blinding materials 0.15m
per 10m, bed rolling, spreading broken
stones to template, rolling dry to compaction
from sides to centre until the movement of
broken stones cease, watering profusely and
rolling until the fines creame up and fill the
voids of the stones, then spreading the
gravelly earth and sweeping into the joints,
watering and rerolling untiluntil the fines
cream up and fill the voids of the stones, the
gravelly earth has worked into all the
crevises and only a thin coat of slurry
remains, then take off the roller and allow to
set to harden for 24 hours and any deformity
is rectified, including fencing, lighting,
watching and maintaining the surface free of
ruts for 15 days after completion including
hire charges of power roller, all labour
charges, etc. complete for W.B.M. base
course.

(Daily out-turn of roller 840m)


Man for spreading broken stones and
blinding materials
Woman for spreading broken stones and
blinding materials and watering
Diesel for roller
Sundries(such as fencing, lighting, watching,
etc.)2 % of total of above
Hire charges for power roller
HA
OH
CP
Total

84

1 Each
1 Each
1 litre

1 day

/m2

12

1 m

0.035 No.
0.035 No.
0.026 No.
0.022 litre
2%
0.0012 day
%
%
%

13

1 m

Remetalling the roadway with departmental


broken stones and blinding materials (new
broken stones supplied at 0.50m for 10m
and blinding materials at 0.12m for 10m)
including picking the old metalled surface
for a minimum depth of 50mm, sectioning,
spreading the new broken stones to template,
rolling dry to compaction from sides to
centre until the movement of broken stones
cease, watering profusely and rolling until
fines creame up and fill the voids of the the
stones, then spreading the gravelly earth and
sweeping into the joints, watering and
rerolling until the gravelly earth has worked
into all the crevises and only a thin coat of
slurry remains, then take off the roller and
allow to set to harden for 24 hours and any
deformity is rectified, including fencing,
lighting, watching and maintaining the
surface free of ruts for 15 days after
completion including hire charges of power
roller, all labour charges, etc. complete for
W.B.M. base course.

(Daily out-turn of roller 840m)


Man for spreading metal and blinding
material
Woman for spreading broken stones and
blinding materials and watering
Man
Diesel for roller
Sundries(such as fencing, lighting, watching,
etc.)2 % of total of above
Hire charges for power roller
HA
OH
CP
Total

Providing bitumen levelling course with


60mm departmental broken stone by
spreading the broken stone to lines and levels
and rolling until the compacted course
aggregate has a firm surface and applying hot
bitumen
with pressure
sprayer
@
16.33Kg/m of aggregates including cost of
bitumen, all conveyance, heating, mixing,
spreading in appropriate locations to proper
levels, compacting with power roller and all
other sundry expenses.

85

1 Each
1 Each
1 Each
1 litre

1 day

/m2

0.50
0.25
0.65
0.20
2
0.011
0.011
0.033
16.33

No.
No.
litre
litre
%
day
day
day
Kg
%
%
%

Daily out-turn of roller 45m


Special mazdoor
Woman
Kerosene
Diesel
Sundries, of total of above
Hire for power roller
Hire for boiler and sprayer
Hire for wheel barrows
Cost of bitumen 80/100
HA
OH
CP

1
1
1
1

Each
Each
litre
litre

1
1
1
1

day
day
day
MT

Total
14

1 m

1.00
0.50
0.80
0.40
2
0.022
0.022
0.066
20.00

No.
No.
litre
litre
%
day
day
day
Kg
%
%
%

/m

Providing bitumen levelling course with


36mm departmental broken stone by
spreading the broken stone to lines and levels
and rolling until the compacted course
aggregate has a firm surface and applying hot
bitumen with pressure sprayer @ 20Kg/m of
metal including cost of bitumen, all
conveyance, heating, mixing, spreading in
appropriate locations to proper levels,
compacting with power roller and all other
sundry expenses.
Daily out-turn of roller 45m
Special mazdoor
Woman
Kerosine
Diesel
Sundries, of total of above
Hire for power roller
Hire for boiler and sprayer
Hire for wheel barrows
Cost of bitumen 80/100
HA
OH
CP

1
1
1
1

Each
Each
litre
litre

1
1
1
1

day
day
day
MT

Total
15

1 m

3.75
1.50
4.00
2.00
0.82
1.50

No.
No.
litre
litre
litre
litre

/m

Providing bitumen pre-mix levelling course


with 12mm departmental broken stone by
spreading the pre-mix (formed of 1m3 loose
broken stone mixed with 48Kg of bitumen)
to lines and levels, rolling to dense surface,
including cost of bitumen, all conveyance,
heating, mixing, compacting with power
roller, other sundry expenses, etc. complete.
Daily out-turn of roller 22.20m
Special mazdoor
Woman
Kerosene for heating aggregates
Kerosene for heating bitumen
Diesel for roller
Diesel for H.M.plant

1
1
1
1
1
1
86

Each
Each
litre
litre
litre
litre

2
0.045
0.045
0.045
0.135
48.00

%
day
day
day
day
Kg
%
%
%

Sundries, of total of above


Hire for power roller
Hire for boiler and sprayer
Hire for H.M.plant
Hire for wheel barrows
Cost of bitumen 80/100
HA
OH
CP

1
1
1
1
1

day
day
day
day
MT

Total
16

1 m

0.075
0.030
0.108
0.116
0.022
0.040
2

No.
No.
litre
litre
litre
litre
%

0.0012
0.0012
0.0012
0.0036
2.9100

day
day
day
day
Kg
%
%
%

/m

Providing 20mm pre-mixed chipping carpet


over W.B.M. surface with departmental
broken stone after cleaning the base and
applying a priming coat of 7.50Kg of
bitumen per 10m and spreading the hot premix (formed of 0.27m of departmental
12mm broken stone and 12.96Kg of bitumen
per 10m) rolling to dense surface, then
spreading the seal coat (comprising of a hot
premix of 0.09m of 6mm departmental
broken stone and 8.64Kg of bitumen per
10m again rolling including the cost of
bitumen, oil and fuel, hire of bass brooms,
camber board, roller and other machineries,
watching, lighting and other charges, etc.
complete. (Total usage of bitumen is
29.10Kg per 10m)
Daily out-turn of roller 840m
Special mazdoor
Woman
Kerosene for heating aggregates
Kerosene for heating bitumen
Diesel for roller
Diesel for H.M.plant
Sundries(such as fencing, lighting, watching,
etc.)2 % of total of above
Hire for power roller
Hire for boiler and sprayer
Hire for H.M.plant
Hire for wheel barrows
Cost of bitumen 80/100
HA
OH
CP
Total

87

1
1
1
1
1
1

Each
Each
litre
litre
litre
litre

1
1
1
1
1

day
day
day
day
MT

/m2

17

18

1 m

0.075
0.030
0.108
0.116
0.022
0.040
2

No.
No.
litre
litre
litre
litre
%

0.0012
0.0012
0.0012
0.0036
2.66

day
day
day
day
Kg
%
%
%

1 m

0.075
0.016
0.340
2
0.001
0.864

19

No.
litre
Kg
%
day
Kg
%
%
%

1 m2

Providing 20mm pre-mixed chipping carpet


over existing black topped surface with
departmental broken stone after cleaning the
base and applying a priming coat of 5.00Kg
of bitumen per 10m and spreading the hot
pre-mix (formed of 0.27m of departmental
12mm metal and 12.96Kg of bitumen per
10m) rolling to dense surface, then
spreading the seal coat (comprising of a hot
premix of 0.09m of 6mm departmental
metal and 8.64Kg of bitumenper 10m) again
rolling including the cost of bitumen, oil and
fuel, hire of bass brooms, camber board,
roller and other machineries, watching,
lighting and other charges, etc. complete.
(Total usage of bitumen is 26.60Kg per
10m)
Daily out-turn of roller 840m
Special mazdoor
Woman
Kerosene for heating aggregates
Kerosene for heating bitumen
Diesel for roller
Diesel for H.M.plant
Sundries(such as fencing, lighting, watching,
etc.)2 % of total of above
Hire for power roller
Hire for boiler and sprayer
Hire for H.M.plant
Hire for wheel barrows
Cost of bitumen 80/100
HA
OH
CP
Total

Providing heavy seal coat using 6mm


departmental broken stone @ 0.09m/10m
with hot bitumen @ 8.64Kg/10m including
hire charges for power roller, spreading, etc
complete.
Special mazdoor
Diesel for roller
Cost of fire wood
Sundries, of total of above
Hire for power roller
Cost of bitumen 80/100
HA
OH
CP
Total
Trimming, dressing and sectioning the road
berms including labour charges, etc.
complete as per the direction of departmental
officers.
88

1
1
1
1
1
1

Each
Each
litre
litre
litre
litre

1
1
1
1
1

day
day
day
day
MT

/m2

1 Each
1 litre
1 MT
1 day
1 MT

/m2

0.02 No.
%
%
%

Man
HA

1 Each

OH
CP
/m2

Total
20

1 No

30 Kg

Note: Cost of cement may


be included in the item or
excluded and measured
as a separate item.

Supplying and fixing guard stones 20x20x90


cms size of pre-cast reinforced cement
concrete M15 using 20mm graded
aggregates,
fixed in base concrete
45x45x45cms size of M10 using 40mm
graded aggregates, laying to lines and levels
at all elevations, consolidating, curing and
painting with two coats of emulsion paint in
alternate bands of black and white colour
over a coat of priming coat including cost of
all materials and labour charges etc.
complete.
Cement
M sand / R sand

1 MT

3
0.05 m
3
0.08 m

40 mm coarse aggregate

3
1m

m3
No
No
No
m2

20 mm coarse aggregate
Mason
Man
Woman
Form work

1
1
1
1

Painting

2
1m

0.03
0.02
0.12
0.24
0.44

0.52 m2
5%
%
%
%

3
1m

m3
Each
Each
Each
2
1m

Provision for excavation, cost of water,


conveyance of post, etc. @ 5% of above
HA
OH
CP
Total

89

/Each

CHAPTER XV
TUNNEL AND SURGE
A. TUNNEL WORKS
Sl.
No.
1

Quantity
1 m3

Description of items

Rate

Excavated quantity per cycle


Average depth of holes to be drilled
Number of holes including dummy (if not
specified, take 5.77 Nos per sq:m)
Total depth of drilling
Average output of Jack hammer per hour
Number of hours required

Kg
0 Nos
10 %
10 %

Remarks

Tipper use rate per m 3 .


4 . Cost of cement may be
included in the item or
excluded and measured
as a separate item.

Cross sectional Area


Average pull (if not specified, take as 1.2m)

5%

Amount

Note:
1 .This data may be used
for up to 4 m (Excavated
diameter) .
2.
Above
4m dia
(excavated
diameter),
less 10% of rate of
driving Tunnel.
3 . A lead of 1 km is
considered.
Add
0.06hour, for
every
additional km lead, of

Driving the tunnel in rock as per approved


cross sections to lines and levels including
all the required operations like drilling,
blasting using modern explosives, mucking,
scaling, etc. and removing and depositng the
excavated materials(muck) at designated
places including all leads and lifts, cost of
all materials, machinery, fuel, labour,
lighting,
ventilation,
water
supply,
compressed air, dewatering, etc. complete as
per specifications and as directed by the
departmental officers.

Excavated diameter of Tunnel

Unit

1.Material charges
Drill bit

0.00

m2

1.20

1.50

m3
m
No.

7.50

m
m
hrs

1 Each

life 150 m

Extra for sharpening @ 5% of above


Gelatine (0.45 kg per hole)
Delay detonators ( 85% number of holes)
Other petty consumables, wires, etc. @ 10%
of above two items
Provision for pipe lines for air and water,
electric lines, fixtures, scaffoldings, wire
ropes, safety items, conveyance charges, etc.
@ 10% of above items

25 Kg
1 No.

Total
Total Material charges per m3
2.Labour charges for 10 m3 ( D - Shape )
0.77 No.
0.77 No.

Foreman
Supervisor

0.77 No.

Fitter

Note: For other shapes,


add 10% of extra labour

1 Each
1 Each
1 Each
90

0.77
0.77
0.77
3.08
40

No.
No.
No.
No.
%
%

Blaster
Electrician
Special mazdoor
Helper for cleaning holes, scaling, etc.
Difficult work allowance
Hill allowance

1
1
1
1

Each
Each
Each
Each

Total
Total Material charges per m3
Note: For other shapes,
add
10
%
extra
machinery charges

3.Machinery charges per m3 ( D - Shape )


hr
0.32 hr
0.64 hr
0.91 hr

Jack Hammer
Loader - 0. 5 cum
Tipper
Ventilation blower

1
1
1
1

hr
hr
hr
hr

Total
Total Material charges per m3
4.Shop charges per m3
5%

Machine shop, Structural shop, Steel metal


shop, Air and water pipe shop, Carpentary
shop etc. @ 10% of machinery charges
Total shop charges per m3

0.125 No.
40 %
%

5%

5%

3%

5.Maintenance charges per m3


Man for maintenance of electrical line, water
line, air line, etc.

1 Each

Difficult work allowance of labour


Hill allowance
Total Maintenance charges per m3
Total 1 to 5 (A)
6.Electric and Water charges
Electric, Water and Dewatering charges @
5% of (A)
7.Spare Charges
Jack hammer, ventilation blower, water line,
air line, cables, bulbs, pumps etc. @ 5% of
(A)
8.Uninterrupted Power Supply Charges
Maintenance of diesel generator, acessories,
etc. @ 3% of (A)
9.Insurance Charges

2%

3%
%
%

Machines, equipments, labour, etc @ 2% of


(A)
10.Maintenance of haul roads
Haul roads @ 3% of (A)
OH
CP
Total
Rate per 1m3 of driving tunnel

91

/m3

1 m3

Driving the tunnel as per approved cross


sections to lines and levels in weak rock
strata including all the required operations
like drilling, blasting using modern
explosives, mucking, scaling, etc. and
removing and depositng the excavated
materials(muck) at designated places
including all leads and lifts, cost of all
materials, machinery, fuel, labour, lighting,
ventilation, water supply, compressed air,
dewatering,
etc.
complete
as
per
specifications and as directed by the
departmental officers.
Rate per 1m3 of driving tunnel
Add 20% of the above

20 %

/m3

Total
1 m3

Mucking loose and jointed rock fallen due to


weak nature of rock in tunnel and depositing
the muck at designated areas including all
leads and lifts, machinery, fuel, labour,
lighting, ventilation, dewatering, etc.
complete as per the direction of departmental
officers.

0.05 No.
0.20 No.
0.10 hr.

Foreman
Man for scaling, etc.
Loader ( 0.5 m3) for loading
Dumper for conveyance (UR)
Shop, maintenance, electric, water, spare
charges, etc. @ 5% of above items
HA
OH
CP
Total

0.20 hr.
5%
%
%
%

m3

1 Each
1 Each
1 hr.
1 hr.

/m3
Invert may be considered
as: 1 . For D-shape level upto which circular
portion starts. 2 . For
circular shape - bottom
half

Cement concrete (M20MSA40) for lining of


tunnel invert portion including cost of all
materials, form work, labour, conveying,
laying, vibrating , curing etc, complete
1.Materials and Labour charges

0.35 No.
0.1 No.
40 %
%
0.3 hr

m3

Cost of CCM20 MSA40

Extra man due to inefficiency in conveying


concrete
Extra mason due to inefficiency in placing
concrete
Difficult work allowance
HA on
Ventilation blower
Total

1 Each

Total material and labour charges per m3


(A)

92

1 Each

1 Hr

Concrete mix may be


suitably taken

2.Extra lead
Extra lead (up to 1 km) @ 5% of (A)
3.Form work
Formwork, scaffolding etc @ 10% of (A)
4.Electric and Water charges
Electric, Water and Dewatering charges @
5% of (A)
5.Spare Charges, maintanance etc
water line, air line, cables, bulbs, pumps etc.
@ 3% of (A)
6.Uninterrupted Power Supply Charges
Maintenance of diesel generator, acessories,
etc. @3% of (A)
OH
CP
Total
3
Rate per 1m of lining

5%
10 %
5%

3%

3%
%
%

m3

1m

0.35 No.
40 %
%
4.50 m2
50 %
0.30 hr

5%
5%

5%
5%

3%

3%
%
%

Note: Add 5% for every


additional km.

/m3

Cement concrete (M20MSA40) for lining of


tunnel overt portion including cost of all
materials, form work, labour, conveying,
laying, vibrating , curing etc, complete.
1.Materials and Labour charges
Cost of CCM20 MSA40
Extra man due to inefficiency in conveying
concrete
Difficult work allowance
HA on
Steel Form work
Add Extra for designed shape (50 % of
above Item)
Ventilation blower

Concrete mix may be


suitably taken

3
1m
1 Each

1 m2

Note: Form work for


tunnel lining of more
than
4m
finished
diameter, add 20% extra
of the normal rate

1 hr

Total
Total material and labour charges per m3
(A)
2.Extra lead
Extra lead (up to 1 km) @ 5% of (A)
3.Extra for form work, scaffolding etc
Moving rail platform formwork, scaffolding
etc @ 5% of (A)
4.Extra for placing
Extra fror placing etc @ 5% of (A)
5.Electric and Water charges
Electric, Water and Dewatering charges @
5% of (A)
6.Spare Charges, maintanance etc
water line, air line, cables, bulbs, pumps etc.
@ 3% of (A)
7.Uninterrupted Power Supply Charges
Maintenance of diesel generator, acessories,
etc. @ 3% of (A)
OH
CP
Total
Rate per 1m3 of lining
93

Note: Add 5% for every


additional km.

/m3

1m

B. SURGESHAFT
Driving of pilot shaft in rock of approved
cross section to lines and levels including all
the required operations using modern
explosives and machine drilling, lighting,
ventilation, water supply, dewatering,
compressed air etc and depositing the
excavated material(muck) in the dumpyard
or at designated places including all leads
and lifts, cost of all materials, machinery,
fuel and labour etc complete.
Diameter of Pilot shaft
Driven Area
Average pull
Excavated quantity per cycle
Average depth of holes to be drilled
Number of holes (pattern - 0.40 sq:m)
Total depth of drilling
Average output of Jack hammer per hour
Number of hr required

m
5%
Kg
No
10 %
10 %

Note:A lead of 1 km is
considered.
Add
0.06hour, for
every
additional km lead, of
dumper/tipper use rate
per m 3

m
m2
m
m3
m
No
m
m
hr

0.90
1.50

7.50

1.Material charges
Drill bit
Extra for sharpening @ 5% of above
Gelatine (0.45 kg per hole)
Delay detonators
Other petty consumables, wires, etc. @ 10 %
of above two items
Provision for pipe lines for air and water,
electric lines, fixtures, scaffoldings, wire
ropes,safety items, conveyance charges, etc.
@ 10 % of above items

1 Each
25 Kg
1 No.

Total
Total Material charges per m3

0.88
0.88
0.88
0.88
0.88
1.00
4.00
40

No.
No.
No.
No.
No.
No.
No.
%
%

2.Labour charges for 10 m3


Foreman
Supervisor
Fitter
Blaster
Electrician
Special mazdoor
Helper for cleaning holes, scaling, etc.
Difficult work allowance
Hill allowance

1
1
1
1
1
1
1

Each
Each
Each
Each
Each
Each
Each

Total
Total Labour charges per m3

hr
0.32
0.64
0.50
0.91

hr
hr
hr
hr

3.Machinery charges per m3


Jack Hammer
Loader - 0. 5 m3
Tipper
Crane
Ventilation blower

1 hr
1 hr
1 hr
1 hr
1 hr

Total
Total Machinery charges per m3
94

life 150 m

5%

4.Shop charges per m3


Machine shop, Structural shop, Steel metal
shop, Air and water pipe shop, Carpentary
shop etc. @ 5% of machinery charges
Total shop charges per m3

0.125 No
40 %
%

5%

5%

3%

2%

3%
%
%

1 m3

5.Maintenance charges per m3


Man for maintenance of electrical line, water
line, air line, etc.

1 Each

Difficult work allowance of labour


Hill allowance
Total Maintenance charges per m3
Total 1 to 5 (A)
6.Electric and Water charges
Electric, Water and Dewatering charges @
5% of (A)
7.Spare Charges
Jack hammer, ventilation blower, water line,
air line, cables, bulbs, pumps etc. @ 5% of
(A)
8.Uninterrupted Power Supply Charges
Maintenance of diesel generator, acessories,
etc. @ 3% of (A)
9.Insurance Charges
Machines, equipments, labour, etc @ 2% of
(A)
10.Maintenance of haul roads
Haul roads @ 3% of (A)
OH
CP
Total
3
Rate per 1m of pilot driving

/m3
Note:A lead of 1 km is
considered.
Add
0.06hour, for
every
additional km lead, of
dumper/tipper use rate

Driving the surge shaft in rock to full section


as per approved cross section to lines and
levels including all the required operations
using modern explosives and machine
drilling, lighting, ventilation, water supply,
dewatering, compressed air etc and
depositing the excavated material(muck) in
the dumpyard or at designated places
including all leads and lifts, cost of all
materials, machinery, fuel and labour etc
complete.

per m 3

Excavated Diameter of surge

m
m2
m

Driven Area
Diameter of pilot shaft
Area of slashing
Average pull

1.20

Excavated quantity
Average depth of holes to be drilled
Number of holes (pattern - 0.40 m2)
Total depth of drilling
Average output of Jack hammer per hour
Number of hours required

1.50

7.50

95

m
m3
m
No
m
m
hr

m
5%
Kg
Nos.
10 %
10 %

1.Material charges
Drill bit
Extra for sharpening @ 5% of above
Gelatine (0.45 kg per hole)
Delay detonators
Other petty consumables, wires, etc. @10%
of above two items

1 Each
25 Kg
1 No.

Provision for pipe lines for air and water,


electric lines, fixtures, scaffoldings, wire
ropes, safety items, conveyance charges, etc.
10% of above items
Total
Total Material charges per m3

0.20
0.20
0.20
0.20
0.20
0.50
2.00
40

No.
No.
No.
No.
No.
No.
No.
%
%

2.Labour charges for 10 m3


Foreman
Supervisor
Fitter
Blaster
Electrician
Special mazdoor
Helper for cleaning holes, scaling, etc.
Difficult work allowance
Hill allowance

1
1
1
1
1
1
1

Each
Each
Each
Each
Each
Each
Each

1
1
1
1
1

hr
hr
hr
hr
hr

Total
Total Labour charges per m3

0.32
0.64
0.50
0.45

hr
hr
hr
hr
hr

5%

3.Machinery charges per m3


Jack Hammer
Loader - 0. 5 cum
Tipper
Crane
Ventilation blower
Total
Total Machinery charges per m3
4.Shop charges per m3
Machine shop, Structural shop, Steel metal
shop, Air and water pipe shop, Carpentary
shop etc. @ 5% of machinery charges
Total shop charges per m3

0.125 No
40 %
%

5%

5.Maintenance charges per m3


Men for maintenance of electrical line,
water line, air line, etc.
Difficult work allowance of labour

1 Each

Hill allowance
Total Maintenance charges per m3
Total 1 to 5 (A)
6.Electric and Water charges
Electric, Water and Dewatering charges @
5% of (A)

96

5%

3%

2%

3%
%
%

1 m3

1 m3
0.35 No.
0.1 No.
40 %
2
3.50 m
40 %
0.5 hr
2%
%
%
%

7.Spare Charges
Jack hammer, ventilation blower, water line,
air line, cables, bulbs, pumps etc. @ 5% of
(A)
8.Uninterrupted Power Supply Charges
Maintenance of diesel generator, acessories,
etc. @ 3% of (A)
9.Insurance Charges
Machines, equipments, labour, etc @ 2% of
(A)
10.Maintenance of haul roads
Haul roads @ 3% of (A)
OH
CP
Total
3
Rate per 1m of slashing to full section of
shaft
Cement concrete (M25MSA20) for lining of
surge shaft including cost of all materials,
form work, labour, conveying, laying,
vibrating, curing etc, complete
Cost of CC M25 MSA20
Extra man due to inefficiency in conveying
concrete
Extra mason due to inefficiency in placing
concrete
Difficult work allowance for labour
Steel Form work
Extra for circular formwork
Crane
Provision for electric and water charges,
platform etc. @ 2% of cost of concrete
HA
OH
CP
Total
3
Rate per 1m of lining

1 m3

Cement concrete (M20MSA20) for the floor


of surge shaft including cost of all materials,
labour, conveying, laying, vibrating , curing
etc, complete

1 m3

Cost of CC M20 MSA20

0.18 No.
40 %
0.5 hr
2%
%
%
%

/m3
Where ever rock is not
available or at upsurge
area, add 15% extra

Concrete mix may be


suitably taken

3
1m
1 Each

1 Each

1 m2
1 hr

/m3

Concrete mix may be


suitably taken

3
1m

Extra man due to inefficiency in conveying


and placing of concrete
Difficult work allowance
Crane
Provision for electric and water charges,
platform etc. @ 2% of cost of concrete
HA
OH
CP
Total
Rate per 1m3
97

1 Each
1 hr

/m3

10

1 m3

C. PRESSURE SHAFT
Driving the tunnel for laying horizontal
pressure pipe in rock as per approved cross
sections to lines and levels including all the
required operations like drilling, blasting
using modern explosives, mucking, scaling,
etc. and removing and depositng the
excavated materials(muck) at designated
places including all leads and lifts, cost of
all materials, machinery, fuel, labour,
lighting,
ventilation,
water
supply,
compressed air, dewatering, etc. complete as
per specifications and as directed by the
departmental officers.
Rate per 1m3 of driving tunnel
Add 25% of above
Rate per 1m3 of driving tunnel for
pressure pipe

11

1 m3

Note:
1 .This data may be used
for up to 2.50 m
(Excavated diameter).
2 . Above 2.50m dia
(excavated
diameter),
less 15% of rate of
driving the Tunnel for
pressure pipe.
3 . A lead of 1 km is
considered.
Add
0.06hour, for
every
additional km lead, of
Tipper use rate per m

3
.

/m3
Note:
1 .This data may be used
for up to 2.50 m
(Excavated diameter).
2 . Above 2.50m dia
(excavated
diameter),
less 15% of rate of
driving the Tunnel for
pressure pipe.
3 . A lead of 1 km is
considered.
Add
0.06hour, for
every
additional km lead, of

Driving the tunnel for laying inclined


pressure pipe in rock as per approved cross
sections to lines and levels including all the
required operations like drilling, blasting
using modern explosives, mucking, scaling,
etc. and removing and depositng the
excavated materials(muck) at designated
places including all leads and lifts, cost of
all materials, machinery, fuel, labour,
lighting,
ventilation,
water
supply,
compressed air, dewatering, etc. complete as
per specifications and as directed by the
departmental officers.
Rate per 1m3 of driving tunnel
Add 90% of above
Rate per 1m3 of driving tunnel for
pressure pipe

Tipper use rate per m 3 .

/m3

98

CHAPTER XVI
PENSTOCK
Sl. Quantity
1 m2
1

0.025 No.

Technician

0.025 No.
3 min

Man
Hire charges of 3T crane

%
%
%

1 MT

Unit

Description of item
Rate
Ultrasonic inspection of steel plate (ASTM A
285 Grade C or its equivalent IS) at place of
delivery/ fabrication, prior to fabrication of
plates including all expenses for testing
arrangements, labour charges etc. complete
as per specifications, approved drawings and
as directed by departmental officers.

1.40
0.40
0.40
0.75
0.10
0.14
0.70
5

m3
Kg
No.
No.
No.
No.
No.
%

Remarks

1 Each
1 Each
1 hr.

Hire charges of ultrasonic machine @ 70%


of above
HA
OH
CP
Total

/ m2

Design, Supply and Fabrication of penstock


pipes at erection site using steel plates
conforming to ASTM A 285 Grade C/or its
equivalent IS specifications, including cost
of steel, electrodes, welding flux and
accessories, carrying out stress relieving and
all tests other than those for which separate
items are included, shot/sand blasting and
protective coating for inside two coats of
Zinc rich primer and two coats of coal tar
epoxy paint, for outside one coat of zinc rich
primer followed by cement wash having a
composition of cement, water and pottassium
dichromate in 20:8:1 ratio first coat at
workshop, insurance charges, all labour
charges, transportation charges etc. complete
as per specifications, approved drawings and
as directed by the departmental officers.

A. Cost of Steel
1.01 MT

Amount

Cost of steel plates


B. Design Charges
Design charges @ 1% of cost of steel
C. Fabrication Charges
a.Cutting and Edge preparation
Oxygen
LPG
Fitter
Gas Cutter/Blacksmith
Supervisor/Skill Asst.(ITI)
Khalasi
Man
Gas cutting nozzle, hose, glouse, punch etc.
@ 5% of total (a) above
99

1 MT

1
1
1
1
1
1
1

m3
Kg
Each
Each
Each
Each
Each

2.00 hrs.
2.50 hrs.
205 Nos
6.80 hrs.
1%
2.00 hrs.
8 Nos
1.00 hr.
10 %

b.Conveying,lifting,placing etc.
Mobile crane (UR)
c.Bending and rolling of sheet
Bending machine (UR)
d.Welding of Rolled sheet
Welding rods (8G)
Welding set (UR)
Cotton etc. @ 1% of above total (d)
e. Grinding of cutting plate
Grinding machine (UR)
Grinding stone
D. Shot/Sand blasting
Shot blasting machine (UR)
Aggregates for shot blasting @ 10% of
above

E. Painting
3.10 litres. Zinc rich primer
1.70 litres. Coal tar epoxy paint
1%
Potassium dichromate @ 1% of total cost of
above
3.70 kg
Cement
4.70 No.
Painter
%
HA
%
OH
%
CP
Total
3

1 MT

1.03 MT

1 hr.
1 hr.
100 No.
1 hr.

1 hr.
1 Each
1 hr.

1 litres.
1 litres.

1 MT
1 Each

/MT

Design, Supply and Fabrication of flanges,


bends, expanders, reducers, Y piece etc by
using steel plates conforming to ASTM A
285 Grade C/or its equivalent IS
specifications,
including cost of steel,
electrodes, welding flux and accessories,
carrying out stress relieving and all tests
other than those for which separate items are
included, sand blasting and protective
coating for inside two coats of Zinc rich
primer and two coats of coal tar epoxy paint,
for outside one coat of zinc rich primer
followed by cement wash having a
composition of cement, water and pottassium
dichromate in 20:8:1 ratio first coat at
workshop, insurance charges, all labour
charges, transportation charges etc. complete
as per specifications, approved drawings and
as directed by the departmental officers.

A. Cost of Steel
Cost of steel plates

1 MT

B. Design Charges
Design charges @ 1% of cost of steel

100

C. Fabrication Charges
Fabrication charges @ 120% of Fabrication
charges of penstock pipe vide item (2)
D. Shot/Sand blasting
Sandblasting machine (UR)
Aggregates for shot blasting @ 10% of
above
E. Painting
3.10 litres. Zinc rich primer
1.70 litres. Coal tar epoxy paint
1.00 %
Potassium dichromate @ 1% of total cost of
above
3.70 Kg
Cement
4.70 No
Painter
%
HA
%
OH
%
CP
Total
1.00 hr.

4a.

1m

Radiographic inspection of shop weld carried


out at fabrication site/ factory as per
specifications including all expences for
testing arrangements and labour charges etc.
complete as directed by the departmental
officers.

2 hrs

Hire charges of Radiographic testing


machine including licence charges
Cost of film (MR)
Provision for ladder, crane etc. @ 3% of
above
OH
CP
Total

0.025 m2
3%
%
%

4b.

1m

Radiographic inspection of field weld as per


specification including all expences for
testing arrangements and labour charges etc.
complete as directed by the departmental
officers.

2 hr

Hire charges of Radiographic testing


machine including licence charges
Cost of film (MR)
Provision for ladder, crane etc. @ 10% of
above
OH
CP
Total
Say Rs.

0.025 m2
10 %
%
%

101

1 hr.

1 litres.
1 litres.

1 MT
1 Each

/MT

hr

UR (1m tesing -2hrs.)

1 m2

/m

m
2
1 m

/m

UR (1m tesing -2hrs.)

1 MT

0.25
0.25
0.05
0.01
0.05

hr.
hr.
No.
No.
No.

6.00 hrs.
1.00 No.
0.33
0.33
1.00
2.00

No.
No.
No.
No.

385 No.
12.8 hr

7.00 hr
15.00 No.

3.00 kg

0.70 No.
%
%
%

Erection and installation of pipes, flanges,


bends, Y-piece, expanders, reducers etc.
including conveyance to the haulage position
over the substructure anchors, placing in
position, assembling, welding, followed by
second coat of cement wash having a
composition of cement, water and pottassium
dichromate in 20:8:1 ratio, etc. complete as
per specifications and approved drawings
including all labour charges, transportation
charges, equipments, final protective coating,
insurance charges etc. complete as directed
by the departmental officers.

a.Conveyance charges
Mobile crane (UR)
Tipper (UR)
Khalasis
Supervisor(ITI)
Helper
Packing and testing materials @ 10% of
above
b.Lifting, positioning and aligning

1
1
1
1
1

Mobile crane (UR)


Winch and trolly (75% of Mobile crane)
Fitter

hr.
hr.
Each
Each
Each

1 hr.

Supervisor/Skill Asst.(ITI)
Rigger
Khalasi
Helper
Jacky, wooden blocks, steel sections, etc. @
10% of above
c.Welding (circumferencial )
Welding rods (8G)
Welding set (UR)
Cotton etc. @ 1% of above
d.Grinding
Grinding machine (UR)
Grinding stone (MR)
Gloves, Cotton etc. @ 1% of above
e.Painting
Cement
Potassium dichromate @ 10% of cost of
cement
Painter
HA
OH
CP
Total

102

1
1
1
1
1

Each
Each
Each
Each
Each

100 No.
1 hr

1 hr
1 No.

1 MT

1 Each

/MT

1 MT

1.05 MT

0.98
0.28
0.28
0.53
0.07
0.10

m3
Kg
No.
No.
No.
No.

Design, Supply, Fabrication and Erection of


rocker supports to the penstock using various
size steel sections etc., straightening, cutting
fabricating and hoisting including applying
one coat of iron primer and painting with
coaltar epoxy paint 2 coats, etc. complete. as
per drawing and as directed by the
departmental officers.

A. Cost of Steel
Cost of steel sections
B. Design Charges
Design charges @ 1% of cost of steel
C. Fabrication and Erection Charges
a.Cutting
Oxygen
LPG (MR)
Fitter
Gas Cutter/Blacksmith
Supervisor/Skill Asst.(ITI)
Khalasi

1 MT

0.49 No.

Man
Gas cutting nozzle, hose, glouse, punch etc.
b.Conveying, lifting, placing etc.
1.40 hr
Hire charges of Mobile crane (UR)
c.Welding
144 Nos
Welding rods (8G)
4.80 hrs.
Welding set
Cotton etc. @ 1% of above
d. Grinding
1.40 hr
Grinding machine (UR)
6 No
Grinding stone (MR)
D. Painting
0.70 litres. Iron primer
1.20 litres. Coal tar epoxy paint
1.50 Nos
Painter
%
HA
%
OH
%
CP
Total

103

1
1
1
1
1
1
1

0.00

m3
Kg
Each
Each
Each
Each
Each

1 hr.
100 No
1 hr.

1 hr.
1 Each
1 litres.
1 litres.
1 Each

/MT

CHAPTER XVII
GATES AND TRASH RACK
Sl.
No.

Quantity

1 MT

1.01 MT
1%

2.80 m3
0.80 Kg
5.00 No
15.00 No
5.00 No
10.00 No
3.70 No

hr
4.00 hr.
75 No.
7.00 hr.

1.50 hr.
3 No
1.20 litre.
1.80 litre.
2.00 No.
4.00
1.00
0.35
0.10
0.35

2.67
0.33
0.33
1.00
2.00

hr.
hr.
No.
No.
No.

hr.
No.
No.
No.
No.

Description of items

Unit

Rate

Design, Supply, Fabrication and Erection of


Gate using various size steel sections etc.,
straightening, cutting, fabricating and
hoisting including applying one coat of iron
primer and painting with epoxyl paint 2
coats, etc. complete as per drawings and as
directed by the departmental officers.

A. Cost of Steel
Cost of steel

1 MT

B. Design Charges
Design charges @ 1% of cost of steel
C. Fabrication Charges
a.Cutting
Oxygen
LPG (MR)
Fitter
Turner I
Welder
Blacksmith
Man
Gas cutting nozzle, hose, glouse, punch etc.
@ 5% of total above (a)
b.Conveying,lifting,placing etc.
Mobile crane (UR)
c.Welding
Welding rods (8G)
Welding set (UR)
Cotton etc. @ 1% of above
d. Grinding
Grinding machine (UR)
Grinding stone
e. Painting
Iron primer
Coal tar epoxy paint
Painter
D.Erection charges
a.Conveyance charges
Mobile crane (UR)
Tipper
Khalasis
Supervisor(ITI)
Helper
Packing and testing materials @ 10% of total
above (a)
b.Lifting, aligning and positioning
Mobile crane (UR)
Fitter
Supervisor/Skill Asst.(ITI)
Khalasi
Man
Jacky, wooden blocks, steel sections, etc. @
10% of total above (b)
HA

104

1
1
1
1
1
1
1

m3
Kg
Each
Each
Each
Each
Each

1 hr.
100 No.
1 hr.

1 hr.
1 Each
1 litre.
1 litre.
1 Each

1
1
1
1
1

hr.
hr.
Each
Each
Each

1
1
1
1
1

hr.
Each
Each
Each
Each

Amount

Remarks

%
%

OH
CP
/MT

Total
2

1.00 MT

Design, Supply, Fabrication and Erection of


Trashrack using various size steel sections
etc., straightening, cutting, fabricating and
hoisting including applying one coat of iron
primer and painting with epoxy paint 2 coats,
etc. complete as per drawings and as directed
by the departmental officers.

A. Cost of Steel
1.05 MT
1%

1000
36.00
12.00
6.00
4

No
No
No
No
%

1.20 litre.
1.80 litre.
2.00 No.

4.00
1.00
0.35
0.10
0.35

hr.
hr.
No.
No.
No.

2.67
0.33
0.33
1.00
2.00

hr.
No.
No.
No.
No.

%
%
%

Cost of steel sections


B. Design Charges
Design charges @ 1% of cost of steel

1 MT

C. Fabrication Charges
a. Cutting,Welding, etc.
Welding rods
Blacksmith
Heavy load mazdoor / Khalasi
Welder
Current charges , grinding stone,and sundries
4% of (a)
b. Painting
Iron primer
Coal tar Apoxy paint
Painter
D.Erection charges
a.Conveyance charges
Mobile crane
Tipper
Khalasis
Supervisor(ITI)
Helper
Packing and testing materials @ 10% of total
above (a)
b.Lifting,aligning and positioning
Mobile crane
Fitter
Supervisor/Skill Asst.(ITI)
Khalasi
Man
Jacky, wooden blocks, steel sections, etc. @
10% of total above (b)

100
1
1
1

No
Each
Each
Each

1 litre.
1 litre.
1 Each

1
1
1
1
1

hr.
hr.
Each
Each
Each

1
1
1
1
1

hr.
Each
Each
Each
Each

HA
OH
CP
Total

105

/MT

CHAPTER XVIII
MISCELLANEOUS WORKS
Sl.
No.
1

Quantity
1 Kg

1
0.03
0.035
5

Kg
No.
No.
%
%
%
%

1 Kg

1
0.03
0.035
5

Description of items

Rate

Unit

Amount

Remarks

Furnishing and placing Copper sealing strips


in joints and at other locations as per
drawings and specifications including cost
of GI strips, conveyance, labour, etc.
complete.
Copper sealing strips
Fitter
Man
Provision for tools, conveyance etc. @ 5 %
of above
HA
OH
CP
Total

1 Kg
1 Each
1 Each

/Kg

Furnishing and placing GI strips in joints and


at other locations as per drawings and
specifications including cost of GI strips,
labour, etc. complete.

Kg
No.
No.
%

GI strips
Fitter
Man
Provision for tools, conveyance etc. @ 5 %
of above

%
%
%

HA
OH
CP

1 Qtl
1 Each
1 Each

Total
3

1 m2

1 m2
0.1 No.
5%
%
%
%

/Kg

Providing and filling the expansion joints


with bitumen pad (25 mm) as per drawings
and specifications and as directed by
departmental officers including cost of all
materials, labour, etc. complete.
1 m2
1 Each

Cost of bitumen pad


Fitter
Provision for tools, conveyance etc. @ 5 %
of above
HA
OH
CP
Total

/m2
`

106

1 No

Providing and fixing elastomeric bearing pad


...mm or nearest size over the bed
block as per drawings and specifications and
as directed by departmental officers
including cost of all materials, labour etc.
complete.

1 No
5%

Cost of bearing pad (MR)


Provision for tools, conveyance etc. @ 5 %
of above
HA
OH
CP
Total

%
%
%

1m

Furnishing and placing PVC water stops


conforming to IS specifications in joints and
at other locations as per drawings and
specifications
and
as
directed
by
departmental officers including cost of all
materials, labour, etc. complete.

1m
5%

Cost of PVC water stops (MR)


Provision for tools, conveyance etc. @ 5 %
of above
Carpenter for fixing
Man for assisting
HA
OH
CP
Total

0.05 No.
0.05 No.
%
%
%
6

1 m2

Supplying and laying Tar paper/ HDPE


sheet as per drawings and specifications and
as directed by departmental officers
including cost of all materials, labour, etc.
complete.

1 m2
5%

Cost of HDPE Sheet (MR)


Provision for conveyance, laying etc. @ 5%
of above
HA
OH
CP
Total

%
%
%

1 m3

0.80 m3
0.20 m3
1 No.
%
%
%

1 Each

/Each

1 m

1 Each
1 Each

/m

1 m2

/m2

Providing course gravel cushion with 20 to


40mm graded aggregates laying to lines and
levels as per drawings and specifications and
as directed by departmental officers
including cost of all materials, labour
charges, etc. complete
1 m3
1 m3
1 Each

40mm coarse aggregates


20mm coarse aggregates
Man for laying to lines and levels
HA
OH
CP
Total
107

/m3

1 m3

0.40
0.30
0.30
1

Providing course gravel cushion with 5 to


20mm graded aggregates laying to lines and
levels as per drawings and specifications and
as directed by departmental officers
including cost of all materials, labour
charges, etc. complete

m3
m3
m3
No.

20mm coarse aggregate


12mm coarse aggregate
6mm coarse aggregate
Man for laying to lines and levels

%
%
%

HA
OH
CP

1
1
1
1

m3
m3
m3
Each

/m3

Total
9

1 m

1 m
0.75 No.
%
%
%

Providing aggregate cushion using fine


aggregate/coarse sand , laying to lines and
levels as per drawings and specifications and
as directed by departmental officers
including cost of all materials, labour
charges, etc. complete
Fine aggregate/ Course sand
Man for laying to lines and level
HA
OH
CP

1 m
1 Each

/m3

Total
10

1 m

Supplying and spreading 40 mm broken


stone for required thickness, laying to lines
and levels as per drawings and specifications
and as directed by departmental officers
including cost of all materials, labour
charges, etc. complete

1 m
1 No.
%
%
%

Cost of 40 mm broken stone


Man for laying to lines and level
HA
OH
CP

1 m
1 Each

/m3

Total
11

1 m

Supplying and spreading 20 mm broken


stone for required thickness, laying to lines
and levels as per drawings and specifications
and as directed by departmental officers
including cost of all materials, labour
charges, etc. complete

1 m
1 No.
%
%
%

20mm aggregate at site


Man for laying to lines and level
HA
OH
CP

1 m3
1 Each

Total

108

/m3

12

1 m

1 m
0.75 No.
%
%
%

Supplying and spreading sand for required


thickness, laying to lines and levels as per
drawings and specifications and as directed
by departmental officers including cost of all
materials, labour charges, etc. complete
Sand
Man for laying to lines and level
HA
OH
CP

1 m
1 Each

/m3

Total
13

1 Kg

1
0.03
0.03
0.01

Kg
No
No
No

10 %
%
%
%

14

Supplying and fixing MS pipe of required


diameter and thickness, laying to lines and
levels as per drawings and specifications and
as directed by departmental officers
including cost of all materials, labour
charges, etc. complete
Cost of steel pipe
Fitter
Man
Welder

1
1
1
1

Supplying and fixing best quality sluice


valve of approved diameter and make for
connecting with the pipe including cost of
valve, flanges, packings, transportation
charges, installation and painting charges,
etc. complete.

1 No.

Cost of Valve (MR)

%
%
%

Each

Provision for welding set, rods etc. @ 10 %


of cost of above all
HA
OH
CP
Total

1 No.

10 %

Qtl
Each
Each

/Kg

1 Each

Cost of flanges, packings, transportation


charges, installation and painting charges, etc
@ 10 % of above
HA
OH
CP
Total

15

1m

1.05
0.02
0.02
0.02

m
No.
No
No

/Each

Supplying and fixing hand rails / ladder with


GI pipes of mm including cost of all
materials, labour, fabrication charges,
applying one coat primer coat , etc.
Cost of GI Pipe
Fitter
Man
Welder

1 m
1 Each
1 Each
1 Each

109

10 %
%
%
%

16

1 Kg

1.05
0.02
0.02
0.02
10

Kg
No.
No
No
%
%
%
%

17

1 Kg

1.05
0.01
0.01
0.02
10

Kg
No.
No.
No.
%
%
%
%

18

Provision for specials, welding, and cost of


priming coat etc @ 10% of above
HA
OH
CP
Total
Supplying and fixing MS Grills / gates
including cost of all materials, labour,
fabrication charges, applying one coat
primer, etc. complete.
Cost of Ms Square/round , etc
Fitter
Man
Welder
Provision for welding, and cost of priming
coat etc @ 10% of above
HA
OH
CP
Total

MS angles, flat, plates, channel, etc.


Blacksmith
Welder
Man
Provision for welding, and cost of priming
coat etc @ 10% of above
HA
OH
CP
Total
Supplying and laying PVC perforated pipe
including cost of all materials, labour, etc.
complete.

1m

PVC pipe

0%
0%

1 Qtl
1 Each
1 Each
1 Each

/Kg

Fabricating, supplying and installing


miscellaneous metal works for various works
or any other steel item specified in drawing
such as hatch cover, frames, gratings,
chequered plates, rails, embedded parts,
angle post of chain link fencing, etc. at all
elevations including cost of all materials,
fabrication, welding and fixing charges,
applying one coat primer, etc. complete.

1m

10 %

/m

1 Qtl
1 Each
1 Each
1 Each

/Kg

1 m

Provision for making perforations, solvent


cement, labour charges and other sundries @
10% of above.
OH
CP
Total

110

/m

19

1m

Supplying and laying PVC pipe (other than


for water supply / sanitary works) including
cost of all materials, conveyance, labour, etc.

1m
5%

Cost of PVC pipe


Solvent cement, labour charges etc @5% of
above.

%
%

1 m

OH
CP
Total

20

1 No

Supplying and fixing PVC specials (other


than for water supply / sanitary works) such
as Tee ,Elbow, Bend, Coupling etc including
cost of all materials, conveyance, labour, etc.

1 No
5%

Cost of PVC special


Solvent cement, labour charges etc @5% of
above.
OH
CP
Total

%
%

21

1m

Supplying and fixing PVC rain water gutter


of suitable size including necessary fittings
such as clamps, screws, end stopper etc.
including cost of all materials, labour
charges, scaffolding etc.

1m

150 mm dia PVC rain water gutter

/m

1 Each

/Each

1 m

10 %

Provision for drill, bends, end stoppers,


clamps, screws, scaffolding and other
sundries @ 10% of above.

0.1 No.

Plumber

1 Each

0.1 No.

Man

1 Each

%
%
%

HA
OH
CP
Total

22

1m

Supplying and fixing PVC down water pipe


of suitable dia including necessary fittings
such as, bends, elbows, reducers, clamps,
screws etc., fixing the pipe to the wall ,
cutting
masonry/concrete
wherever
necessary, scaffolding etc. complete.

1m
10 %

Cost of PVC pipe


Provision for elbow, bends, clamps, screws,
scaffolding and other sundries etc @ 10% of
above.
Plumber
Man

0.07 No.
0.07 No.
%
%
%

/m

1 m

1 Each
1 Each

HA
OH
CP
Total
111

/m

23

1 m2

3
0.18
0.1
0.3

Kg
Kg
No
No

5%

%
%
%

24

1 m2

Note: Item may be


suitably
modified
acording
to
the
availability of materials
in the market.

Chemical treatment to the wall and slab


wherever necessary with water proofing
slurry applied with brush in 3 coats
consisting of polymer modified pulversied
material based powder and acrylic based
polymer bonding agent working on the
principles of water proofing by crystalline
penetration or equivalent treatment as per
specifications for the purpose including
surface cleaning to remove the deposits of oil
and grease, cost of materials, labour charges,
curing, scaffolding, etc. complete.

Dichtament Ds or equivalent (MR)


Nafufill or equivalent (MR)
Man
Painter

1
1
1
1

Kg
Kg
Each
Each

Provision for conveyance of materials,


scaffolding and other sundries @ 5% of
above.
HA
OH
CP
Total

/m2

Supplying and fixing mechanically operated


rolling shutters of approved make, made of
80 x 1.25 mm laths interlocked together
through their entire length and jointed
together at the end by the end locks mounted
on specially designed pipe shaft with
brackets, side guides and arrangements for
inside and outside locking with push and pull
operation and painted with two coats of
synthetic enamel paint over a coats of iron
primer including cost of all materials, labour
charges etc.complete

1 m2
0.3 No.

Cost of rolling shutter


Fitter

1 m2
1 Each

0.3 No.
0.3 No.

Man
Mason

1 Each
1 Each

Painting with two coats of synthetic enamel


paint over two coats of iron primer

1 m2

2.28 m2

%
%
%

HA
OH
CP
Total

112

/m2

25

1 m2

Supplying and fixing electrically operated


(with reversible switch and accessories)
rolling shutters of approved make, made of
80 x 1.25 mm laths interlocked together
through their entire length and jointed
together at the end by the end locks mounted
on specially designed pipe shaft with
brackets, side guides and arrangements for
inside and outside locking with push and pull
operation and painted with two coats of
synthetic enamel paint over a coats of iron
primer including cost of all materials, labour
charges etc.complete

1 m2

Cost of rolling shutter

1 m2

0.3 No.

Fitter

1 Each

0.3 No.

Man

1 Each

0.3 No.

Mason

1 Each

Painting with two coats of synthetic enamel


paint over two coats of iron primer

1 m2

Electric motor and accessories (MR)

20 m2

Mechanic Gr.I
Electrician

1 Each
1 Each

2.28 m2

1 No.
0.025 No.
0.025 No.
5%

%
%
%

for conveyance, lead wire, fixing foundation


bolt, etc. @ 10% of above three items
HA
OH
CP
/m2

Total
26

1m

Supplying and fixing rolling shutter cover


of approved make and painted with two coat
of synthetic enamel paint over a coats of
iron primer including cost and conveyance of
all materials, labour charges etc.complete.

1m

Rolling shutter cover

1 m2

0.15 No.

Fitter

1 Each

0.15 No.

Man

1 Each

0.15 No.

Mason

1 Each

Painting with two coats of synthetic enamel


paint over a coat of iron primer

1 m2

1.5 m2
%
%
%

Shutter
size
of
4.00x5.00m is assumed.

HA
OH
CP
Total

113

/m

27

1 litre

Supplying and placing in position PVC


water storage tank of approved make
including all fittings, etc. complete.

1 litre
5%

cost 1 lit water tank


Fitting charges and sundries etc. @5% above

0%
0%

OH
CP
Total

114

1 litre

/litre

CHAPTER XIX
INVESTIGATION WORKS
Sl.
No.
1

Quantity

Description of items

Rate

1 Km

Assisting
departmental
Officers
for
conducting Reconnaissance survey through
easy terrain including clearing light jungle,
cutting earth for making steps wherever
necessary etc, complete.

2 No.
10 %

Man Mazdoor
Sundries such as rope, knife, axe, spade, etc.

%
%

Unit

1 Each

HA
CP

1 Km

Assisting
departmental
Officers
for
conducting Reconnaissance survey through
steep and difficult terrain including clearing
light jungle, cutting earth for making steps
wherever necessary, etc. complete.

3 No.
10 %

Man Mazdoor
Sundries such as rope, knife, axe, spade, etc.

%
%

/Km
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle

1 Each

HA
CP
Total

1 Km

Assisting departmental Officers for survey


works for fixing the preliminary alignment of
roads etc. including clearing light jungle,
cutting earth for making steps wherever
necessary, etc. complete.

4 No.
5%

Man Mazdoor
Sundries such as rope, knife, axe, spade, etc.

%
%

/Km
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle

1 Each

HA
CP
Total

1 Km

Assisting
departmental
Officers
for
conducting compass survey for fixing the
bearings of the alignment for preparing
survey drawings, including clearing light
jungle, cutting earth for making steps
wherever necessary, etc. complete.

4 No.
5%

Man Mazdoor
Sundries such as rope, knife, axe, spade, etc.

%
%

Remarks
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle

Total
2

Amount

/Km
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle

1 Each

HA
CP
Total

115

/Km

1 Ha

Assisting
departmental
Officers
for
conducting contour survey using Theodolite/
Total Station for preparing survey drawings,
through easy terrain including clearing light
jungle, cutting earth for making steps
wherever necessary, etc. complete.

4 No.
5%

Man Mazdoor
Sundries such as rope, knife, axe, spade, etc.

%
%

An additional provision
of one Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle

1 Each

HA
CP
Total

1 Ha

6 No.

Assisting
departmental
Officers
for
conducting contour survey using Theodolite/
Total Station
for preparing
survey
drawings, through steep and difficult terrain
including clearing light jungle, cutting earth
for making steps wherever necessary, etc.
complete.
Man Mazdoor

5%

Sundries such as rope, knife, axe, spade, etc.

%
%

/Ha
An additional provision
of 1.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle

1 Each

HA
CP
Total

1 Ha

Assisting
departmental
Officers
for
conducting detailed site survey for colony
roads, buildings, etc. using Theodolite/
Total Station including clearing jungle
wherever necessary, etc. complete.

1.5 No.
5%

Man Mazdoor
Sundries such as rope, knife, axe, spade, etc.

%
%

/Ha

1 Each

HA
CP
Total

1 Set

Writing Bench mark details like B.M. value,


B.M No. and the letter KSEB on concrete,
rock and other surfaces after cleaning etc.,
with synthetic enamel paint two coats as
directed by departmental officers.

0.1 No.
10 %

Painter
Sundries such as cost of paint, brush, cotton,
etc.
HA
CP
Total

%
%

116

/Ha

1 Each

/Set

1 Set

0.75 No.
5%
%
%

10

1 No.

0.17 m3
0.09 m3
42 Kg
0.02 No.
0.18 No.
0.25 No.
15 %

%
%

Establishing permanent Bench mark on solid


rock by engraving B.M. value, B.M No. and
the letter KSEB after chipping and leveling
the surface for an area 30 cms x 30 cms etc.
complete.
Stone Cutter
Sundries such as chisel, hammer etc.
HA
CP
Total

1 Each

/Set

Establishing cement concrete block of size


45cm x 45cm x 90cm with CC 1:3:6 using
40mm aggregates and having one number
16mm dia M.S rod, 20 cm long at centre and
the block 45 cm above ground level and the
rod projecting 3 mm above top level of the
block including excavation, marking Bench
Mark details, cost of materials, labour
charges etc. complete as directed by the
departmental officers.
40mm broken stone
Sand
Cement
Mason
Man Mazdoor
Woman
Provision for digging pit, formwork, cost of
M.S rod, collecting water, marking B.M
details, etc. @ 15% above total

1
1
1
1
1
1

m3
m3
MT
Each
Each
Each

HA
CP
Total

11

1 Km

1.5 No.
0.5 No
5%
%
%

/Each
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle

Assisting
departmental
Officers
for
connecting fly levels using levelling
instrument/ Total Station from Bench marks
for establishing permanent or temporary
Bench marks, including daily closing and
other checking of levels through easy terrain
including clearing light jungle, cutting earth
for making steps wherever necessary, etc.
complete.
Special Mazdoor
Man Mazdoor
Sundries such as rope, knife, axe, spade, etc.

1 Each
1 Each

HA
CP
Total

117

/Km

12

1 Km

Assisting
departmental
Officers
for
connecting fly levels using levelling
instrument/ Total Station from Bench marks
for establishing permanent or temporary
Bench marks, including daily closing and
other checking of levels found necessary,
through steep and difficult terrain including
clearing light jungle, cutting earth for making
steps wherever necessary, etc. complete.

3 No.
1 No
5%

Special Mazdoor
Man Mazdoor
Sundries such as rope, knife, axe, spade, etc.

%
%

An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle

1 Each
1 Each

HA
CP
Total

13

1 Km

2.25 No.
0.75 No
5%
%
%

/Km
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle

Assisting
departmental
Officers
for
connecting double fly levels using levelling
instrument/ Total Station from Bench marks
for establishing permanent or temporary
Bench marks, including daily closing and
other checking of levels through easy terrain
including clearing light jungle, cutting earth
for making steps wherever necessary, etc.
complete.
Special Mazdoor
Man Mazdoor

1 Each
1 Each

Sundries such as rope, knife, axe, spade, etc.


HA
CP
Total

14

1 Km

3.75 No.
1.25 No
5%
%
%

/Km
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle

Assisting
departmental
Officers
for
connecting double fly levels using levelling
instrument/ Total Station from Bench marks
for establishing permanent or temporary
Bench marks, including daily closing and
other checking of levels found necessary,
through steep and difficult terrain including
clearing light jungle, cutting earth for making
steps wherever necessary, etc. complete.
Special Mazdoor
Man Mazdoor
Sundries such as rope, knife, axe, spade, etc.

1 Each
1 Each

HA
CP
Total

118

/Km

15

1 Ha

2.25 No.
0.75 No
5%
%
%

An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle

Assisting
departmental
Officers
for
conducting
traverse
survey
using
Theodolite/ Total Station for locating project
control points, plot locations, measurements
of land, preparation of site plan etc, through
easy terrain including clearing light jungle,
cutting earth for making steps wherever
necessary, etc. complete.
Special Mazdoor
Man Mazdoor

1 Each
1 Each

Sundries such as rope, knife, axe, spade, etc.


HA
CP
Total

16

1 Ha

Assisting
departmental
Officers
for
conducting
traverse
survey
using
Theodolite/ Total Station for plot locations,
measurements of land, preparation of site
plan etc, through steep and difficult terrain
including clearing light jungle, cutting earth
for making steps wherever necessary, etc.
complete.

3 No.
1 No

Special Mazdoor
Man Mazdoor

5%

Sundries such as rope, knife, axe, spade, etc.

%
%

/Ha
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle

1 Each
1 Each

HA
CP
Total

17

1 No.

Establishing precast survey blocks /


boundary stones / center line blocks etc., of
size 15x15x60cms or nearest size including
excavation upto 45 cms, marking details with
paint, cost of block/stone,conveyance and
labour charges etc. complete as directed by
the departmental officers.

1 No.
0.2 No.

Block/stone
Man Mazdoor

10 %

Provision for conveyance, marking details,


etc.
HA
CP

15 %
10 %

1 Km

MR

1 Each
1 Each

Total
18

/Ha

Assisting departmental Officers for taking


profile along the tunnel/penstock alignment
using levelling instrument/ Total Station
through easy terrain including clearing light
jungle, cutting earth for making steps
wherever necessary, etc. complete.
119

/Each
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle

4.5 No.
1.5 No.
5%
%
%

Special Mazdoor
Man Mazdoor

1 Each
1 Each

Sundries such as rope, knife, axe, spade, etc.


HA
CP
Total

19

1 Km

7.5 No.
2.5 No.
5%
%
%

/Km
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle

Assisting departmental Officers for taking


profile along the tunnel/penstock alignment
using levelling instrument/ Total Station
through steep and difficult terrain including
clearing light jungle, cutting earth for making
steps wherever necessary, etc. complete.
Special Mazdoor
Man Mazdoor

1 Each
1 Each

Sundries such as rope, knife, axe, spade, etc.


HA
CP
Total

20

1 Km

An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle

Assisting departmental Officers for taking


longitudinal section (L.S) along road, land
etc., using levelling instrument/ Total
Station at suitable intervals and covering all
requisite points through easy terrain
including clearing light jungle, cutting earth
for making steps wherever necessary, etc.
complete.

2.25 No.

Special Mazdoor

0.75 No
5%

Man Mazdoor
Sundries such as rope, knife, axe, spade, etc.

%
%

/Km

1 Each
1 Each

HA
CP
Total

21

1 Km

Assisting departmental Officers for taking


longitudinal section (L.S) along road, land
etc. using levelling instrument/ Total Station
at suitable intervals and covering all requisite
points through steep and difficult terrain
including clearing light jungle,cutting earth
for making steps wherever necessary, etc.
complete.

3 No.
1 No
5%

Special Mazdoor
Man Mazdoor
Sundries such as rope, knife, axe, spade, etc.

%
%

/Km
An additional provision
of 0.5 Ordinary Mazdoor
to be provided in areas of
thick and thorny jungle

1 Each
1 Each

HA
CP
Total
120

/Km

22

1 Km

Assisting departmental Officers for taking


longitudinal section (L.S) of river and other
streams using levelling instrument/ Total
Station at suitable intervals and covering all
requisite points through easy terrain
including cutting earth for making steps
wherever necessary, etc. complete.

3 No.
1 No

Special Mazdoor
Man Mazdoor

5%

Sundries such as rope, spade, etc.

%
%

1 Each
1 Each

HA
CP
Total

23

1 Km

Assisting departmental Officers for taking


longitudinal section (L.S) of river and other
streams using levelling instrument/ Total
Station at suitable intervals and covering all
requisite points through steep and difficult
terrain including cutting earth for making
steps wherever necessary, etc. complete.

5 No.
2 No.

Special Mazdoor
Man Mazdoor

5%

Sundries such as rope, spade, etc.

%
%

/Km

1 Each
1 Each

HA
CP
Total

24

1 No

0.11 No.
0.04 No.
5%
%
%

Assisting departmental Officers for taking


cross section (C.S) along road, land etc., of
width up to 50 m. using levelling
instrument/ Total Station at suitable intervals
and covering all requisite points through
easy terrain including clearing light jungle,
cutting earth for making steps wherever
necessary, etc. complete.
Special Mazdoor
Man Mazdoor

1 Each
1 Each

Sundries such as rope, knife, axe, spade, etc.


HA
CP
Total

25

1 No

/Km

Assisting departmental Officers for taking


cross section (C.S) along road, land etc., of
width up to 50 m. using levelling
instrument/ Total Station at suitable intervals
and covering all requisite points through
steep and difficult terrain including clearing
light jungle, cutting earth for making steps
wherever necessary, etc. complete.
121

/Each

0.19 No
0.06 No.
5%
%
%

Special Mazdoor
Man Mazdoor

1 Each
1 Each

Sundries such as rope, knife, axe, spade, etc.


HA
CP
Total

26

1 No

0.15 No
0.05 No.
5%
%
%

/Each
For every additional
100m width, add 0.20
Ordinary Mazdoor.

Assisting departmental Officers for taking


cross section (C.S) along road, land etc., of
width up to 100 m. using levelling
instrument/ Total Station at suitable intervals
and covering all requisite points through
easy terrain including clearing light jungle,
cutting earth for making steps wherever
necessary, etc. complete.
Special Mazdoor
Man Mazdoor
Sundries such as rope, knife, axe, spade, etc.
HA
CP

1 Each
1 Each

Total
27

1 No

0.23 No
0.07 No.
5%
%
%

/Each
For every additional
100m width, add 0.30
Ordinary Mazdoor.

Assisting departmental Officers for taking


cross section (C.S) along road, land etc., of
width up to 100 m. using levelling
instrument/ Total Station at suitable intervals
and covering all requisite points through
steep and difficult terrain including clearing
light jungle, cutting earth for making steps
wherever necessary, etc. complete.
Special Mazdoor
Man Mazdoor
Sundries such as rope, knife, axe, spade, etc.

1 Each
1 Each

HA
CP
Total

28

1 No

0.19 No
0.06 No.
5%
%
%

/Each

Assisting departmental Officers for taking


cross section (C.S) of river and other streams
of width up to 50 m. covering portions of
adjacent bank using levelling instrument/
Total Station at suitable intervals and
covering all requisite points through easy
terrain including clearing light jungle, cutting
earth for making steps wherever necessary,
etc. complete.
Special Mazdoor
Man Mazdoor

1 Each
1 Each

Sundries such as rope, spade, etc.


HA
CP
Total
122

/Each

29

1 No

0.26 No
0.09 No.
5%
%
%

Assisting departmental Officers for taking


cross section (C.S) of river and other streams
of width up to 50 m. covering portions of
adjacent bank using levelling instrument/
Total Station at suitable intervals and
covering all requisite points through steep
and difficult terrain including clearing light
jungle, cutting earth for making steps
wherever necessary, etc. complete.
Special Mazdoor
Man Mazdoor
Sundries such as rope, spade, etc.
HA
CP

1 Each
1 Each

Total
30

1 No

0.23 No
0.07 No.
5%
%
%

/Each
For every additional
100m width, add 0.30
Ordinary Mazdoor.

Assisting departmental Officers for taking


cross section (C.S) of river and other streams
of width up to 100 m. covering portions of
adjacent bank using levelling instrument/
Total Station at suitable intervals and
covering all requisite points through easy
terrain including clearing light jungle, cutting
earth for making steps wherever necessary,
etc. complete.
Special Mazdoor
Man Mazdoor

1 Each
1 Each

Sundries such as rope, spade, etc.


HA
CP
Total

31

1 No

0.38 No
0.12 No.
5%
%
%

/Each
For every additional
100m width, add 0.40
Ordinary Mazdoor.

Assisting departmental Officers for taking


cross section (C.S) of river and other streams
of width up to 100 m. covering portions of
adjacent bank using levelling instrument/
Total Station at suitable intervals and
covering all requisite points through steep
and difficult terrain including clearing light
jungle, cutting earth for making steps
wherever necessary, etc. complete.
Special Mazdoor
Man Mazdoor

1 Each
1 Each

Sundries such as rope, spade, etc.


HA
CP
Total

123

/Each

32

1 Station Assisting
departmental
Officers
for
reconnaissance
and
preliminary
establishment of triangulation station using
Theodolite/ Total Station including clearing
jungle, etc. complete.
2 No.
1 No
5%
%
%

Special Mazdoor
Man Mazdoor
Sundries such as rope, knife, axe, spade, etc.

1 Each
1 Each

HA
CP
Total

33

/Each

1 Station Assisting
departmental
Officers
for
triangulation survey using Theodolite/ Total
Station for all readings from a station
including clearing jungle, etc. complete.
3.5 No.
2 No.
5%
%
%

Special Mazdoor
Man Mazdoor

1 Each
1 Each

Sundries such as rope, knife, axe, spade, etc.


HA
CP
Total

34

/Each
For remote station deep
inside the forest, an
additional provision of
0.20 Special mazdoor to
be provided.

1 Station/ Taking rainfall readings/ river gauge


day
readings
and
other
meteorological
observations in wet months at specified time
and recording the same in prescribed format
at one station including watching of the
station etc, complete.
0.35 No.
%
%

Man Mazdoor
HA
CP

1 Each

Total
35

/Each
For remote station deep
inside the forest, an
additional provision of
0.20 Special mazdoor to
be provided.

1 Station/ Taking rainfall readings/ river gauge


day
readings
and
other
meteorological
observations in dry months at specified time
and recording the same in prescribed format
at one station including watching of the
station etc, complete.
0.2 No.
%
%

Man Mazdoor
HA

1 Each

CP
Total

124

/Each

ANNEXURE A - USE RATE OF EQUIPMENTSS


Note:
(i)
Hill
allowance may be
provided as per
nature of terrain. (ii)
Indirect Charges for
labour @ 55% for
semi
skilled
/
unskilled
workers
and @ 80% of
skilled workers may
be provided for large
projects in remote
areas.

Batching & Mixing plant (27 cum)


70 HP
Cost of Equipment(Rs.),E
55,00,000.00
Schedule life in Years,Y
18.00
Schedule life in Hours,H
30000.00
Life time repair provision(% of cost of Equipment),R
75.00
Estimated annual operational hours,O
1500.00
1
Ownership Cost:
(i)
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
183.33
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
165.00
Average hourly depreciation (Rs.),D3= (D1+D2)/2
174.17
2
Operational Cost:
(i)
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
137.50
( ii ) O&M crew charges
Category
Nos
Wages/ shift Days/month Amount (in Rs.)
Operator
2
563
25
28150.00
Helper (Man mazdoor)
6
377
25
56550.00
Mechanic -1
0.50
505
25
6312.50
Foreman (Diploma holder)
0.50
673
25
8412.50
Watchman
1.00
377
25
9425.00
108850.00
Total Monthly Wages
Total Direct crew charges/year
1306200.00
Increase for hilly area (if necessary)
15
195930.00
Total Crew Charges/year (Rs),Cc1
1502130.00
Hourly Crew Charges (Rs),Cc2 =Cc1/O
1001.42
( iii ) POL and Energy Charges
For Electricity
Power of Electric Motor (KW),P
BHP =
70
P =(746*BHP/1000)
52.22
Hourly Energy Consumption(KWH),Ec= P*.4*1
41.78
Rate of Electricity (Rs./KWH),e
4.00
Cost of Electricity (Rs.),Ce=Ec*e
167.10
Lubricant charges,Lc=(Ce*v%
50.13
Lubricants-u%of fuel & v% of electricity charges)
(Generally u = 25% & v = 30%)
Hourly POL and Energy Charges(Rs.), Pe=Ce+Lc
217.24
d For compressed air
Cost of compressed air, Cair
0.00
Hourly POL and Energy Charges(Rs.), Pe=Cair
0.00
( iv ) Miscellaneous charges ,Mc =C*z%
13.75
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc
1544.07

Chain saw wood cutter (light)


2.7 HP
Cost of Equipment(Rs.),E
28,000.00
Schedule life in Years,Y
2.00
Schedule life in Hours,H
2400.00
Life time repair provision(% of cost of Equipment),R
125.00
Estimated annual operational hours,O
1500.00
1
Ownership Cost:
(i)
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
8.40
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
10.50
Average hourly depreciation (Rs.),D3= (D1+D2)/2
9.45
2
Operational Cost:
(i)
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
14.58
( ii ) O&M crew charges
Category
Nos
Wages/ shift Days/month Amount (in Rs.)
Operator - III
1
377
25
9425.00
Helper (Man mazdoor)
1
377
25
9425.00
Total Monthly Wages
18850.00
Total Direct crew charges/year
226200.00
Increase for hilly area (if necessary)
15
33930.00
Total Crew Charges/year (Rs),Cc1
260130.00
Hourly Crew Charges (Rs),Cc2 =Cc1/O
173.42
( iii ) POL and Energy Charges
a For Petrol
F.H.P of Engine
2.70
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1
0.30
Rate of Petrol (Rs./lit),d
70.00
Cost of Petrol (Rs.), Cd= Fc*d
20.79
Lubricant charges,Lc=(Cd*u%))
5.20
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc
25.99
( iv ) Miscellaneous charges ,Mc =C*z%
1.46
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc
224.90

Chain saw wood cutter (heavy)


4.9 HP
Cost of Equipment(Rs.),E
46,000.00
Schedule life in Years,Y
2.00
Schedule life in Hours,H
2400.00
Life time repair provision(% of cost of Equipment),R
125.00
Estimated annual operational hours,O
1500.00
Ownership Cost:
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
13.80
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
17.25
Average hourly depreciation (Rs.),D3= (D1+D2)/2
15.53
Operational Cost:
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
23.96
O&M crew charges
Category
Nos
Wages/ shift Days/month Amount (in Rs.)
Operator - III
1
377
25
9425.00
Helper (Man mazdoor)
1
377
25
9425.00
Total Monthly Wages
18850.00
Total Direct crew charges/year
226200.00
Increase for hilly area (if necessary)
15
33930.00
Total Crew Charges/year (Rs),Cc1
260130.00
Hourly Crew Charges (Rs),Cc2 =Cc1/O
173.42

1
(i)

2
(i)

( ii )

( iii )

POL and Energy Charges


a For Petrol
F.H.P of Engine
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1
Rate of Petrol (Rs./lit),d
Cost of Petrol (Rs.), Cd= Fc*d
Lubricant charges,Lc=(Cd*u%))
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc
( iv ) Miscellaneous charges ,Mc =C*z%
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc

4.90
0.54
70.00
37.73
9.43

47.16
2.40
262.46

Concrete cutter
1.5 HP
Cost of Equipment(Rs.),E
47,000.00
Schedule life in Years,Y
2.00
Schedule life in Hours,H
2400.00
Life time repair provision(% of cost of Equipment),R
125.00
Estimated annual operational hours,O
1500.00
1
Ownership Cost:
(i)
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
14.10
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
17.63
Average hourly depreciation (Rs.),D3= (D1+D2)/2
15.86
2
Operational Cost:
(i)
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
24.48
( ii ) O&M crew charges
Category
Nos
Wages/ shift Days/month Amount (in Rs.)
Operator - III
1
377
25
9425.00
Helper (Man mazdoor)
1
377
25
9425.00
Total Monthly Wages
18850.00
Total Direct crew charges/year
226200.00
Increase for hilly area (if necessary)
15
33930.00
Total Crew Charges/year (Rs),Cc1
260130.00
Hourly Crew Charges (Rs),Cc2 =Cc1/O
173.42
( iii ) POL and Energy Charges
a For Electricity
Power of Electric motor(KW),P
BHP =
5
P=(746*BHP/1000)
3.73
Hourly Energy Consumption(KWH),Ec=P*0.8*1
2.98
Rate of Electricity (Rs/KWh),e
4.00
Cost of Electricity(Rs.),Ce=Ec*e
11.94
Lubricant charges,Lc=Ce*v%
3.58
(generally v=30%)
Hourly POL and Energy Charges(Rs.), Pe=Ce+Lc
15.52
( iv ) Miscellaneous charges ,Mc =C*z%
2.45
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc
231.73
Concrete placer
Cost of Equipment(Rs.),E
Schedule life in Years,Y
Schedule life in Hours,H
Life time repair provision(% of cost of Equipment),R
Estimated annual operational hours,O

8,00,000.00
5.00
8000.00
100.00
1500.00

1
(i)

2
(i)

( ii )

( iii )

( iv )

Ownership Cost:
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
96.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
90.00
Average hourly depreciation (Rs.),D3= (D1+D2)/2
93.00
Operational Cost:
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
100.00
O&M crew charges
Category
Nos
Wages/ shift Days/month Amount (in Rs.)
Operator - III
1
377
25
9425.00
Helper (Man mazdoor)
1
377
25
9425.00
0.167
377
25
1573.98
Watchman
0.167
505
25
2108.38
Mechanic -1
0.125
673
25
2103.13
Foreman (Diploma holder)
Total Monthly Wages
24635.48
Total Direct crew charges/year
295625.70
Increase for hilly area (if necessary)
15
44343.86
Total Crew Charges/year (Rs),Cc1
339969.56
Hourly Crew Charges (Rs),Cc2 =Cc1/O
226.65
POL and Energy Charges
For compressed air
Cost of compressed air ( 100 cfm), Cair
437.51
Hourly POL and Energy Charges(Rs.), Pe=Cair
437.51
Miscellaneous charges ,Mc =C*z%
10.00
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc
867.16

Diesel Air Compressor (200 cfm)


50 HP
Cost of Equipment(Rs.),E
8,70,000.00
Schedule life in Years,Y
8.00
Schedule life in Hours,H
10000.00
Life time repair provision(% of cost of Equipment),R
100.00
Estimated annual operational hours,O
1500.00
1
Ownership Cost:
(i)
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
65.25
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
78.30
Average hourly depreciation (Rs.),D3= (D1+D2)/2
71.78
2
Operational Cost:
(i)
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
87.00
( ii ) O&M crew charges
Category
Nos
Wages/ shift Days/month Amount (in Rs.)
Operator
1
377
25
9425.00
Helper (Man mazdoor)
1
377
25
9425.00
Mechanic -1
0.25
505
25
3156.25
Foreman (Diploma holder)
0.125
673
25
2103.13
Watchman
0.25
377
25
2356.25
Total Monthly Wages
26465.63
Total Direct crew charges/year
317587.50
Increase for hilly area (if necessary)
15
47638.13
Total Crew Charges/year (Rs),Cc1
365225.63
Hourly Crew Charges (Rs),Cc2 =Cc1/O
243.48
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine
50.00
Hourly fuel consumption in litres,Fc=0.22*FHP*1*0.75
8.25
Rate of Diesel(Rs./lit),d
45.00
Cost of Diesel (Rs.), Cd= Fc*d
371.25
4

( iv )

Lubricant charges,Lc=(Cd*u%))
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc
Miscellaneous charges ,Mc =C*z%
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc
Hourly Use Rate ofor 100 cfm

92.81

464.06
8.70
875.02
437.51

Diamond Drill
10 HP
Cost of Equipment(Rs.),E
4,20,000.00
Schedule life in Years,Y
10.00
Schedule life in Hours,H
10,000.00
Life time repair provision(% of cost of Equipment),R
80.00
Estimated annual operational hours,O
1,500.00
1
Ownership Cost:
(i)
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
25.20
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
37.80
Average hourly depreciation (Rs.),D3= (D1+D2)/2
31.50
2
Operational Cost:
(i)
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
33.60
( ii ) O&M crew charges
Category
Nos
Wages/ shift Days/month Amount(in Rs.)
Operator - III
2
377
25
18850.00
Helper (Man mazdoor)
1
377
25
9425.00
Mechanic -1
0.25
505
25
3156.25
Foreman (Diploma holder)
0.125
673
25
2103.13
Watchman
0.25
377
25
2356.25
35890.63
Total Monthly Wages
Total Direct crew charges/year
430687.50
Increase for hilly area (if necessary)
15
64603.13
Total Crew Charges/year (Rs),Cc1
495290.63
Hourly Crew Charges (Rs),Cc2 =Cc1/O
330.19
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine
10.00
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1
1.10
Rate of Diesel(Rs./lit),d
45.00
Cost of Diesel (Rs.), Cd= Fc*d
49.50
Lubricant charges,Lc=(Cd*u%))
12.38
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc
61.88
( iv ) Miscellaneous charges ,Mc =C*z%
3.36
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc
460.53
Electric Pump

1
(i)

10 HP

Cost of Equipment(Rs.),E
Schedule life in Years,Y
Schedule life in Hours,H
Life time repair provision(% of cost of Equipment),R
Estimated annual operational hours,O
Ownership Cost:
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
Average hourly depreciation (Rs.),D3= (D1+D2)/2
5

93,000.00
12.00
20,000.00
70.00
1,500.00

4.65
4.19
4.42

Operational Cost:
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
3.26
( ii ) O&M crew charges
Category
Nos
Wages/ shift Days/month Amount(in Rs.)
Operator - III
1
377
25
9425.00
Mechanic -1I
0.25
471
25
2943.75
Electrician
0.125
443
25
1384.38
Total Monthly Wages
13753.13
Total Direct crew charges/year
165037.50
Increase for hilly area (if necessary)
15
24755.63
Total Crew Charges/year (Rs),Cc1
189793.13
Hourly Crew Charges (Rs),Cc2 =Cc1/O
126.53
( iii ) POL and Energy Charges
a For Electricity
Power of Electric motor(KW),P
BHP =
10
P=(746*BHP/1000)
7.46
Hourly Energy Consumption(KWH),Ec=P*0.8*1
5.97
Rate of Electricity (Rs/KWh),e
4.00
Cost of Electricity(Rs.),Ce=Ec*e
23.87
Lubricant charges,Lc=Ce*v%
7.16
(generally v=30%)
Hourly POL and Energy Charges(Rs.), Pe=Ce+Lc
31.03
( iv ) Miscellaneous charges ,Mc =C*z%
0.33
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc
165.56
(i)

Electric Pump
5 HP
Cost of Equipment(Rs.),E
25,000.00
Schedule life in Years,Y
12.00
Schedule life in Hours,H
20,000.00
Life time repair provision(% of cost of Equipment),R
70.00
Estimated annual operational hours,O
1,500.00
1
Ownership Cost:
(i)
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
1.25
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
1.13
Average hourly depreciation (Rs.),D3= (D1+D2)/2
1.19
2
Operational Cost:
(i)
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
0.88
( ii ) O&M crew charges
Nos
Wages/ shift Days/month Amount(in Rs.)
Category
Operator - III
1
377
25
9425.00
Mechanic -1I
0.25
471
25
2943.75
Electrician
0.125
443
25
1384.38
Total Monthly Wages
13753.13
Total Direct crew charges/year
165037.50
Increase for hilly area (if necessary)
15
24755.63
Total Crew Charges/year (Rs),Cc1
189793.13
Hourly Crew Charges (Rs),Cc2 =Cc1/O
126.53
( iii ) POL and Energy Charges
a For Electricity
Power of Electric motor(KW),P
BHP =
5
P=(746*BHP/1000)
3.73
Hourly Energy Consumption(KWH),Ec=P*0.8*1
2.98
Rate of Electricity (Rs/KWh),e
4.00
Cost of Electricity(Rs.),Ce=Ec*e
11.94
Lubricant charges,Lc=Ce*v%
3.58
(generally v=30%)
Hourly POL and Energy Charges(Rs.), Pe=Ce+Lc
15.52
6

( iv )

10

Miscellaneous charges ,Mc =C*z%


(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc

0.09
144.20

Grinding Machine
2.7 HP
Cost of Equipment(Rs.),E
25,000.00
15.00
Schedule life in Years,Y
18,000.00
Schedule life in Hours,H
120.00
Life time repair provision(% of cost of Equipment),R
1,500.00
Estimated annual operational hours,O
1
Ownership Cost:
(i)
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
1.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
1.25
Average hourly depreciation (Rs.),D3= (D1+D2)/2
1.13
2
Operational Cost:
(i)
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
1.67
( ii ) O&M crew charges
Category
Nos
Wages/ shift Days/month Amount(in Rs.)
Fitter
0.5
456
25
5700.00
Mechanic -1I
0.5
471
25
5887.50
Grinder
1
456
25
11400.00
Helper
0.5
377
25
4712.50
Total Monthly Wages
27700.00
Total Direct crew charges/year
332400.00
Increase for hilly area (if necessary)
15
49860.00
Total Crew Charges/year (Rs),Cc1
382260.00
Hourly Crew Charges (Rs),Cc2 =Cc1/O
254.84
( iii ) POL and Energy Charges
a For Electricity
Power of Electric motor(KW),P
BHP =
2.7
P=(746*BHP/1000)
2.01
Hourly Energy Consumption(KWH),Ec=P*0.8*1
1.61
Rate of Electricity (Rs/KWh),e
4.00
Cost of Electricity(Rs.),Ce=Ec*e
6.45
Lubricant charges,Lc=Ce*v%
1.93
(generally v=30%)
Hourly POL and Energy Charges(Rs.), Pe=Ce+Lc
8.38
( iv ) Miscellaneous charges ,Mc =C*z%
0.17
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc
266.18
Grout Pump

11

1
(i)

2
(i)

10 HP

Cost of Equipment(Rs.),E
Schedule life in Years,Y
Schedule life in Hours,H
Life time repair provision(% of cost of Equipment),R
Estimated annual operational hours,O
Ownership Cost:
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
Average hourly depreciation (Rs.),D3= (D1+D2)/2
Operational Cost:
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H

2,00,000.00
10.00
2,400.00
100.00
1,500.00

12.00
75.00
43.50

83.33

( ii )

O&M crew charges


Category
Operator III
Helper
Mechanic -1I
Foreman (Diploma holder)
Watchman

Wages/ shift Days/month Amount (in Rs.)


1
377
25
9425.00
1
377
25
9425.00
0.167
471
25
1966.43
0.125
673
25
2103.13
0.167
377
25
1573.98
Total Monthly Wages
24493.53
Total Direct crew charges/year
293922.30
Increase for hilly area (if necessary)
15
44088.35
Total Crew Charges/year (Rs),Cc1
338010.65
Hourly Crew Charges (Rs),Cc2 =Cc1/O
225.34
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine
10.00
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1
1.10
Rate of Diesel(Rs./lit),d
45.00
Cost of Diesel (Rs.), Cd= Fc*d
49.50
Lubricant charges,Lc=(Cd*u%))
12.38
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc
61.88
( iv ) Miscellaneous charges ,Mc =C*z%
8.33
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc
422.38

12

Nos

Hydraulic Excavator (0.93 cum)


128 HP
Cost of Equipment(Rs.),E
47,00,000.00
Schedule life in Years,Y
10.00
Schedule life in Hours,H
12,000.00
Life time repair provision(% of cost of Equipment),R
100.00
Estimated annual operational hours,O
1,500.00
Ownership Cost:
1
(i)
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
282.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
352.50
Average hourly depreciation (Rs.),D3= (D1+D2)/2
317.25
2
Operational Cost:
(i)
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
391.67
( ii ) O&M crew charges
Category
Nos
Wages/ shift Days/month Amount (in Rs.)
Operator I
1
563
25
14075.00
1
377
25
9425.00
Helper
0.25
505
25
3156.25
Mechanic -1
Foreman (Diploma holder)
0.25
673
25
4206.25
Watchman
0.25
377
25
2356.25
Total Monthly Wages
33218.75
Total Direct crew charges/year
398625.00
Increase for hilly area (if necessary)
15
59793.75
Total Crew Charges/year (Rs),Cc1
458418.75
Hourly Crew Charges (Rs),Cc2 =Cc1/O
305.61
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine
128.00
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1
14.08
Rate of Diesel(Rs./lit),d
45.00
Cost of Diesel (Rs.), Cd= Fc*d
633.60
Lubricant charges,Lc=(Cd*u%))
158.40
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc
792.00
8

( iv )

Miscellaneous charges ,Mc =C*z%


(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc

Jack hammer

13

1
(i)

2
(i)

( ii )

( iii )

( iv )

14

1
(i)

2
(i)

( ii )

39.17
1845.70

12

kg
Cost of Equipment(Rs.),E
58,000.00
Schedule life in Years,Y
10.00
Schedule life in Hours,H
8000.00
Life time repair provision(% of cost of Equipment),R
80.00
Estimated annual operational hours,O
1500.00
Ownership Cost:
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
3.48
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
6.53
Average hourly depreciation (Rs.),D3= (D1+D2)/2
5.00
Operational Cost:
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
5.80
O&M crew charges
Category
Nos
Wages/ shift Days/month Amount (in Rs.)
Operator - III
1
377
25
9425.00
Helper (Man mazdoor)
0.5
377
25
4712.50
Supervisor
0.2
505
25
2525.00
Mechanic -II
0.125
471
25
1471.88
Watchman
0.125
377
25
1178.13
Total Monthly Wages
19312.50
Total Direct crew charges/year
231750.00
Increase for hilly area (if necessary)
15
34762.50
Total Crew Charges/year (Rs),Cc1
266512.50
Hourly Crew Charges (Rs),Cc2 =Cc1/O
177.68
POL and Energy Charges
For compressed air
Cost of compressed air ( 100 cfm), Cair
437.51
Hourly POL and Energy Charges(Rs.), Pe=Cair
437.51
Miscellaneous charges ,Mc =C*z%
0.58
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc
626.57

Mobile Crane 10 T
100 HP
12,00,000.00
Cost of Equipment(Rs.),E
Schedule life in Years,Y
10.00
Schedule life in Hours,H
12,000.00
Life time repair provision(% of cost of Equipment),R
150.00
1,500.00
Estimated annual operational hours,O
Ownership Cost:
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
72.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
90.00
Average hourly depreciation (Rs.),D3= (D1+D2)/2
81.00
Operational Cost:
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
150.00
O&M crew charges
Category
Nos
Wages/ shift Days/month Amount (in Rs.)
Operator II
1
396
25
9900.00
2
377
25
18850.00
Helper
Mechanic -II
0.25
471
25
2943.75
Electrician
0.25
443
25
2768.75
Foreman
0.5
673
25
8412.50
Watchman
1
377
25
9425.00
Total Monthly Wages
52300.00
9

Total Direct crew charges/year


Increase for hilly area (if necessary)
15
Total Crew Charges/year (Rs),Cc1
Hourly Crew Charges (Rs),Cc2 =Cc1/O
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1
Rate of Diesel(Rs./lit),d
Cost of Diesel (Rs.), Cd= Fc*d
Lubricant charges,Lc=(Cd*u%))
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc
( iv ) Miscellaneous charges ,Mc =C*z%
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc

15

627600.00
94140.00
721740.00
481.16

100.00
11.00
45.00
495.00
123.75

618.75
15.00
1345.91

Percussion Drill
10 HP
Cost of Equipment(Rs.),E
5,00,000.00
Schedule life in Years,Y
10.00
Schedule life in Hours,H
9,000.00
Life time repair provision(% of cost of Equipment),R
80.00
1,500.00
Estimated annual operational hours,O
1
Ownership Cost:
(i)
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
30.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
50.00
Average hourly depreciation (Rs.),D3= (D1+D2)/2
40.00
2
Operational Cost:
(i)
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
44.44
( ii ) O&M crew charges
Nos
Wages/ shift Days/month Amount (in Rs.)
Category
1
396
25
9900.00
Operator II
1
377
25
9425.00
Helper
0.25
471
25
2943.75
Mechanic -II
Foreman (Diploma holder)
0.125
673
25
2103.13
0.25
377
25
2356.25
Watchman
26728.13
Total Monthly Wages
Total Direct crew charges/year
320737.50
Increase for hilly area (if necessary)
15
48110.63
Total Crew Charges/year (Rs),Cc1
368848.13
Hourly Crew Charges (Rs),Cc2 =Cc1/O
245.90
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine
10.00
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1
1.10
Rate of Diesel(Rs./lit),d
45.00
Cost of Diesel (Rs.), Cd= Fc*d
49.50
Lubricant charges,Lc=(Cd*u%))
12.38
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc
61.88
( iv ) Miscellaneous charges ,Mc =C*z%
4.44
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc
396.66

10

16

Tipper 5 T
32 HP
Cost of Equipment(Rs.),E
10,00,000.00
Schedule life in Years,Y
8.00
Schedule life in Hours,H
10,000.00
Life time repair provision(% of cost of Equipment),R
175.00
Estimated annual operational hours,O
1,500.00
1
Ownership Cost:
(i)
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
75.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
90.00
Average hourly depreciation (Rs.),D3= (D1+D2)/2
82.50
2
Operational Cost:
(i)
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
175.00
( ii ) O&M crew charges
Category
Nos
Wages/ shift Days/month Amount (in Rs.)
Driver
1
436
25
10900.00
Helper
1
377
25
9425.00
Mechanic -I
0.125
505
25
1578.13
Watchman
0.167
377
25
1573.98
Total Monthly Wages
23477.10
Total Direct crew charges/year
281725.20
Increase for hilly area (if necessary)
15
42258.78
Total Crew Charges/year (Rs),Cc1
323983.98
Hourly Crew Charges (Rs),Cc2 =Cc1/O
215.99
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine
32.00
Hourly fuel consumption in litres,Fc=0.22*FHP*0.3*1
2.11
Rate of Diesel(Rs./lit),d
45.00
Cost of Diesel (Rs.), Cd= Fc*d
95.04
Lubricant charges,Lc=(Cd*u%))
23.76
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc
118.80
( iv ) Miscellaneous charges ,Mc =C*z%
17.50
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc
609.79

17

Transit Mixer (4 cum)


100 HP
Cost of Equipment(Rs.),E
20,00,000.00
Schedule life in Years,Y
10.00
Schedule life in Hours,H
10,000.00
Life time repair provision(% of cost of Equipment),R
120.00
Estimated annual operational hours,O
1,500.00
Ownership Cost:
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
120.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
180.00
Average hourly depreciation (Rs.),D3= (D1+D2)/2
150.00
Operational Cost:
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
240.00
O&M crew charges
Category
Nos
Wages/ shift Days/month Amount (in Rs.)
Operator II
1
396
25
9900.00
Helper
1
377
25
9425.00
Mechanic -II
0.25
471
25
2943.75
Foreman (Diploma holder)
0.125
673
25
2103.13
Watchman
0.25
377
25
2356.25
Total Monthly Wages
26728.13

1
(i)

2
(i)

( ii )

11

Total Direct crew charges/year


Increase for hilly area (if necessary)
15
Total Crew Charges/year (Rs),Cc1
Hourly Crew Charges (Rs),Cc2 =Cc1/O
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1
Rate of Diesel(Rs./lit),d
Cost of Diesel (Rs.), Cd= Fc*d
Lubricant charges,Lc=(Cd*u%))
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc
( iv ) Miscellaneous charges ,Mc =C*z%
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc

18

320737.50
48110.63
368848.13
245.90

100.00
11.00
45.00
495.00
123.75

618.75
24.00
1278.65

Sheet Bending Machine


50 HP
Cost of Equipment(Rs.),E
15,00,000.00
Schedule life in Years,Y
12.00
Schedule life in Hours,H
20,000.00
Life time repair provision(% of cost of Equipment),R
175.00
Estimated annual operational hours,O
1,500.00
1
Ownership Cost:
(i)
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
75.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
67.50
Average hourly depreciation (Rs.),D3= (D1+D2)/2
71.25
2
Operational Cost:
(i)
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
131.25
( ii ) O&M crew charges
Nos
Wages/ shift Days/month Amount (in Rs.)
Category
1
396
25
9900.00
Operator II
Helper
1.5
377
25
14137.50
Mechanic -II
1.5
471
25
17662.50
Khalasi
0.5
396
25
4950.00
2
456
25
22800.00
Fabricator
Foreman (Diploma holder)
0.5
673
25
8412.50
Supervisor
1
505
25
12625.00
Total Monthly Wages
90487.50
Total Direct crew charges/year
1085850.00
Increase for hilly area (if necessary)
15
162877.50
Total Crew Charges/year (Rs),Cc1
1248727.50
Hourly Crew Charges (Rs),Cc2 =Cc1/O
832.49
( iii ) POL and Energy Charges
a For Electricity
Power of Electric motor(KW),P
BHP =
50
P=(746*BHP/1000)
37.30
Hourly Energy Consumption(KWH),Ec=P*0.8*1
29.84
Rate of Electricity (Rs/KWh),e
4.00
Cost of Electricity(Rs.),Ce=Ec*e
119.36
Lubricant charges,Lc=Ce*v%
35.81
(generally v=30%)
Hourly POL and Energy Charges(Rs.), Pe=Ce+Lc
155.17
( iv ) Miscellaneous charges ,Mc =C*z%
13.13
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc
1203.28

12

6 cum/hr

Shortcrete/Guniting machine

19

1
(i)

2
(i)

( ii )

( iii )

( iv )

Cost of Equipment(Rs.),E
3,00,000.00
Schedule life in Years,Y
5.00
Schedule life in Hours,H
6000.00
Life time repair provision(% of cost of Equipment),R
100.00
Estimated annual operational hours,O
1500.00
Ownership Cost:
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
36.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
45.00
Average hourly depreciation (Rs.),D3= (D1+D2)/2
40.50
Operational Cost:
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
50.00
O&M crew charges
Nos
Wages/ shift Days/month Amount (in Rs.)
Category
Operator - II
1
396
25
9900.00
Helper (Man mazdoor)
1
377
25
9425.00
0.5
471
25
5887.50
Mechanic -II
0.125
673
25
2103.13
Foreman (Diploma holder)
Watchman
0.25
377
25
2356.25
29671.88
Total Monthly Wages
Total Direct crew charges/year
356062.50
Increase for hilly area (if necessary)
15
53409.38
Total Crew Charges/year (Rs),Cc1
409471.88
Hourly Crew Charges (Rs),Cc2 =Cc1/O
272.98
POL and Energy Charges
For compressed air
Cost of compressed air ( 100 cfm), Cair
437.51
Hourly POL and Energy Charges(Rs.), Pe=Cair
437.51
Miscellaneous charges ,Mc =C*z%
5.00
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc
805.99

Weed cutter

20

1
(i)

2
(i)

( ii )

1.8 HP

Cost of Equipment(Rs.),E
20,000.00
Schedule life in Years,Y
2.00
Schedule life in Hours,H
2,400.00
Life time repair provision(% of cost of Equipment),R
125.00
Estimated annual operational hours,O
1,500.00
Ownership Cost:
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
6.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
7.50
Average hourly depreciation (Rs.),D3= (D1+D2)/2
6.75
Operational Cost:
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
10.42
O&M crew charges
Category
Nos
Wages/ shift Days/month Amount(in Rs.)
Operator III
1
377
25
9425.00
Helper
0.5
377
25
4712.50
Total Monthly Wages
14137.50
Total Direct crew charges/year
169650.00
Increase for hilly area (if necessary)
15
25447.50
Total Crew Charges/year (Rs),Cc1
195097.50
Hourly Crew Charges (Rs),Cc2 =Cc1/O
130.07

13

( iii )

POL and Energy Charges


a For Diesel
F.H.P of Engine
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1
Rate of Diesel(Rs./lit),d
Cost of Diesel (Rs.), Cd= Fc*d
Lubricant charges,Lc=(Cd*u%))
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc
( iv ) Miscellaneous charges ,Mc =C*z%
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc

21

22

1.80
0.20
45.00
8.91
2.23

11.14
1.04
159.41

Welding Set
2.7 HP
Cost of Equipment(Rs.),E
53,000.00
Schedule life in Years,Y
5.00
Schedule life in Hours,H
10,000.00
Life time repair provision(% of cost of Equipment),R
50.00
Estimated annual operational hours,O
1,500.00
1
Ownership Cost:
(i)
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
6.36
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
4.77
Average hourly depreciation (Rs.),D3= (D1+D2)/2
5.57
2
Operational Cost:
(i)
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
2.65
( ii ) O&M crew charges
Category
Nos
Wages/ shift Days/month Amount (in Rs.)
Helper
1
377
25
9425.00
Mechanic -II
0.5
471
25
5887.50
Fitter
1
456
25
11400.00
Welder
1
471
25
11775.00
Electrician
0.25
443
25
2768.75
Total Monthly Wages
41256.25
Total Direct crew charges/year
495075.00
Increase for hilly area (if necessary)
15
74261.25
Total Crew Charges/year (Rs),Cc1
569336.25
Hourly Crew Charges (Rs),Cc2 =Cc1/O
379.56
( iii ) POL and Energy Charges
a For Electricity
Power of Electric motor(KW),P
BHP =
2.7
P=(746*BHP/1000)
2.01
Hourly Energy Consumption(KWH),Ec=P*0.8*1
1.61
Rate of Electricity (Rs/KWh),e
4.00
Cost of Electricity(Rs.),Ce=Ec*e
6.45
Lubricant charges,Lc=Ce*v%
1.93
(generally v=30%)
Hourly POL and Energy Charges(Rs.), Pe=Ce+Lc
8.38
( iv ) Miscellaneous charges ,Mc =C*z%
0.27
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc
396.42
Vibrator ( Diesel)

2 HP

Cost of Equipment(Rs.),E
Schedule life in Years,Y
Schedule life in Hours,H
Life time repair provision(% of cost of Equipment),R
Estimated annual operational hours,O

14

19,500.00
3.00
6,000.00
70.00
1,500.00

Ownership Cost:
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
3.90
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
2.93
Average hourly depreciation (Rs.),D3= (D1+D2)/2
3.41
2
Operational Cost:
(i)
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
2.28
( ii ) O&M crew charges
Category
Nos
Wages/ shift Days/month Amount (in Rs.)
Operator III
1
377
25
9425.00
Helper
0.5
377
25
4712.50
Total Monthly Wages
14137.50
Total Direct crew charges/year
169650.00
Increase for hilly area (if necessary)
15
25447.50
Total Crew Charges/year (Rs),Cc1
195097.50
Hourly Crew Charges (Rs),Cc2 =Cc1/O
130.07
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine
2.00
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1
0.22
Rate of Diesel(Rs./lit),d
45.00
Cost of Diesel (Rs.), Cd= Fc*d
9.90
Lubricant charges,Lc=(Cd*u%))
2.48
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc
12.38
( iv ) Miscellaneous charges ,Mc =C*z%
0.23
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc
148.36
(i)

23

1
(i)

2
(i)

( ii )

Loader 0.5 cum


75 HP
Cost of Equipment(Rs.),E
7,80,000.00
Schedule life in Years,Y
10.00
Schedule life in Hours,H
15,000.00
Life time repair provision(% of cost of Equipment),R
200.00
Estimated annual operational hours,O
1,500.00
Ownership Cost:
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
46.80
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
46.80
Average hourly depreciation (Rs.),D3= (D1+D2)/2
46.80
Operational Cost:
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
104.00
O&M crew charges
Category
Nos
Wages/ shift Days/month Amount (in Rs.)
Helper
1
377
25
9425.00
Mechanic I
0.25
505
25
3156.25
0.125
673
25
2103.13
Foreman (Diploma holder)
Operator II
1
396
25
9900.00
Watchmen
0.167
377
25
1573.98
Total Monthly Wages
13577.10
Total Direct crew charges/year
162925.20
Increase for hilly area (if necessary)
15
24438.78
Total Crew Charges/year (Rs),Cc1
187363.98
Hourly Crew Charges (Rs),Cc2 =Cc1/O
124.91

15

( iii )

POL and Energy Charges


a For Diesel
F.H.P of Engine
Hourly fuel consumption in litres,Fc=0.22*FHP*0.58*1
Rate of Diesel(Rs./lit),d
Cost of Diesel (Rs.), Cd= Fc*d
Lubricant charges,Lc=(Cd*u%))
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc
( iv ) Miscellaneous charges ,Mc =C*z%
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc

24

25

75.00
9.57
45.00
430.65
107.66

538.31
10.40
824.42

Ventilation Blower
50 HP
Cost of Equipment(Rs.),E
3,00,000.00
Schedule life in Years,Y
12.00
Schedule life in Hours,H
20,000.00
Life time repair provision(% of cost of Equipment),R
80.00
Estimated annual operational hours,O
1,500.00
1
Ownership Cost:
(i)
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
15.00
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
13.50
Average hourly depreciation (Rs.),D3= (D1+D2)/2
14.25
2
Operational Cost:
(i)
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
12.00
( ii ) O&M crew charges
Nos
Wages/ shift Days/month Amount (in Rs.)
Category
Operator II
0.25
396
25
2475.00
0.25
471
25
2943.75
Mechanic II
0.5
377
25
4712.50
Helper
4712.50
Total Monthly Wages
Total Direct crew charges/year
56550.00
Increase for hilly area (if necessary)
15
8482.50
Total Crew Charges/year (Rs),Cc1
65032.50
Hourly Crew Charges (Rs),Cc2 =Cc1/O
43.36
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine
50.00
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1
5.50
Rate of Diesel(Rs./lit),d
45.00
Cost of Diesel (Rs.), Cd= Fc*d
247.50
Lubricant charges,Lc=(Cd*u%))
61.88
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc
309.38
( iv ) Miscellaneous charges ,Mc =C*z%
1.20
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc
380.18
Accessories for pumping
Cost of Equipment(Rs.),E
Schedule life in Years,Y
Schedule life in Hours,H
Life time repair provision(% of cost of Equipment),R
Estimated annual operational hours,O

16

17,167.50
6.00
12,000.00
70.00
1,500.00

1
(i)

2
(i)

( ii )

( iii )

26

1
(i)

2
(i)

( ii )

( iv )

Ownership Cost:
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
1.72
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
1.29
Average hourly depreciation (Rs.),D3= (D1+D2)/2
1.50
Operational Cost:
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
1.00
O&M crew charges
Nos
Wages/ shift Days/month Amount (in Rs.)
Category
0.5
377
25
4712.50
Helper
0.25
471
25
2943.75
Plumber
7656.25
Total Monthly Wages
Total Direct crew charges/year
91875.00
Increase for hilly area (if necessary)
15
13781.25
Total Crew Charges/year (Rs),Cc1
105656.25
Hourly Crew Charges (Rs),Cc2 =Cc1/O
70.44
Miscellaneous charges ,Mc =C*z%
0.10
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc
73.04

Radiografic testing machine


0 HP
Cost of Equipment(Rs.),E
3,15,000.00
Schedule life in Years,Y
10.00
Schedule life in Hours,H
10,000.00
Life time repair provision(% of cost of Equipment),R
80.00
Estimated annual operational hours,O
1,500.00
Ownership Cost:
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
18.90
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
28.35
Average hourly depreciation (Rs.),D3= (D1+D2)/2
23.63
Operational Cost:
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
25.20
O&M crew charges
Category
Nos
Wages/ shift Days/month Amount (in Rs.)
Foreman (Diploma holder)
673
25
8412.50
0.5
Helper (Man mazdoor)
377
25
9425.00
1
Total Monthly Wages
17837.50
Total Direct crew charges/year
214050.00
Increase for hilly area (if necessary)
15
32107.50
Total Crew Charges/year (Rs),Cc1
246157.50
Hourly Crew Charges (Rs),Cc2 =Cc1/O
164.11
Miscellaneous charges ,Mc =C*z%
2.52
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc
215.45
Concrete Pump

27

1
(i)

38 cum/ hr.

Cost of Equipment(Rs.),E
Schedule life in Years,Y
Schedule life in Hours,H
Life time repair provision(% of cost of Equipment),R
Estimated annual operational hours,O
Ownership Cost:
Depreciation:
Hourly depreciation w.r.t. Life in years,D1=0.9*E/(Y*O)
Hourly depreciation w.r.t. Life in hours,D2=0.9*E/H
Average hourly depreciation (Rs.),D3= (D1+D2)/2

17

42,00,000.00
5.00
8,000.00
100.00
2,500.00

302.40
472.50
387.45

Operational Cost:
Repair Charges:
Hourly Repair Charges:
Average over life time(Rs.),C= E*(R/100)/H
525.00
( ii ) O&M crew charges
Category
Nos
Wages/ shift Days/month Amount (in Rs.)
Foreman
0.125
673
25
2103.13
Operator Gr II
1
396
25
9900.00
0.17
471
25
2001.75
Mechanic Gr. II
1
377
25
9425.00
Helper
0.17
377
25
1602.25
Watchman
Total Monthly Wages
11027.25
Total Direct crew charges/year
132327.00
Increase for hilly area
15
19849.05
(if necessary)
Total Crew Charges/year (Rs),Cc1
152176.05
Hourly Crew Charges (Rs),Cc2 =Cc1/O
503.23
( iii ) POL and Energy Charges
a For Diesel
F.H.P of Engine
75.00
Hourly fuel consumption in litres,Fc=0.22*FHP*0.5*1
9.57
Rate of Diesel(Rs./lit),d
45.00
Cost of Diesel (Rs.), Cd= Fc*d
430.65
Lubricant charges,Lc=(Cd*u%))
107.66
Lubricants-u%of fuel )
( u = 25% )
Hourly POL and Energy Charges(Rs.), Pe=Cd+Lc
538.31
( iv ) Miscellaneous charges ,Mc =C*z%
52.50
(z% of repair charges,generally z=10%)
Hourly Use Rate of the Equipment = D3+C+Cc2+Pe+Mc
2006.49
(i)

18

ANNEXURE B - ADDITIONAL USE RATE OF EQUIPMENTS


Sl.
Quantity Description of items
No.
1
1m
Drilling charges using jack hammer
0.13 hr
0.01 No
5%
2

1m
0.10
5
0.1
5

1m
2.00
5
0.10
5

hr
%
No
%

1m
0.50
5
0.03
5

hr
%
No
%

hr
%
No
%

Rate

Unit

Amount

Remarks

Jack hammer (UR)


Drill bit
Extra for sharpening @ 5% of above
Total
Drilling charges using Diamond drill
for earth and boulders

1 hr
1 Each

Diamond drill (UR)


Shifting charges @ 5 % of above
Drill bit
Extra for sharpening @ 5% of above
Total
Drilling charges using Diamond drill
for rock
Diamond drill (UR)
Shifting charges @ 5 % of above
Drill bit
Extra for sharpening @ 5% of above
Total

1 hr

out turn 10m/hr

1 Each

Life 10 m

out turn 7.5 m/hr


Life 150 m

/m

/m

1 hr

out turn 0.5 m/hr

1 Each

Life 10 m

/m

Drilling charges using percussion drill


Percussion drill (UR)
Shifting charges @ 5 % of above
Drill bit
Extra for sharpening @ 5% of above
Total

1 hr

out turn 2 m/hr

1 Each

Life 30 m

/m

1 hp/hrCost of accessories for pumping


Accessories for 60m
60.00
5.00
1.00
1.00
1.00
5.00
5

m
No
No
No
No
No
%

75 mm dia. Pipe (12 Kg/ cm2)


Bend
Foot valve
Non-Return valve
Ball valve
Pipe Nipple
Spares @ 5% of accessories

1
1
1
1
1
1
Total

m
Each
Each
Each
Each
Each
/hp/hr

70

kw

5500000

18

30000

75

1500

Chain saw wood cutter (light)

2.7

HP

28000

2400

125

1500

6
1

Chain saw wood cutter (heavy)

4.9

HP

46000

2400

125

1500

Concrete cutter

1.5

HP

47000

2400

125

1500

Concrete placer

45

800000

8000

100

1500

0.167 0.125

Diamond Drill

10

HP

420000

10

10000

80

1500

0.25

0.125

0.25

Diesel Air Compressor (200 cfm)

50

HP

870000

10000

100

1500

0.25

0.125

0.25

0.167

Electric Pump

10

HP

93000

12

20000

70

1500

0.25

0.125

Electric Pump

HP

25000

12

20000

70

1500

0.25

0.125

10

Grinding Machine

2.7

HP

25000

15

18000

120

1500

11

Grout Pump

10

HP

200000

10

2400

100

1500

12

Hydraulic Excavator (0.93 cum)

128

HP

4700000

10

12000

100

1500

13

Jack hammer

12

Kg

58000

10

8000

80

1500

1
1

0.5

0.5

0.167

1
1

0.5

Loader 0.5 cum

75

HP

780000

10

15000

200

1500

100

HP

1200000

10

12000

150

1500

0.25

16

Percussion Drill

10

HP

500000

10

9000

80

1500

0.25

17

Tipper 5 T

32

HP

1000000

10000

175

1500

18

Transit Mixer (4 cum)

100

HP

2000000

10

10000

120

1500

0.25

19

Sheet Bending Machine

50

HP

1500000

12

20000

175

1500

1.5

1.5

0.25 0.125
0.5

0.5

20

Shortcrete/Guniting machine

cum/hr

300000

6000

100

1500

0.5

Ventilation Blower

50

HP

300000

12

20000

80

1500

0.25

0.5

0.25

Weed cutter

1.8

HP

20000

2400

125

1500

2.7

HP

53000

10000

50

1500

24

Vibrator ( Diesel)

HP

19500

6000

70

1500

25

Accessories for pumping

10

HP

17167.5

12000

70

1500

0.5

26

Radiografic testing machine

315000

10

10000

80

1500

27

Concrete Pump

4200000

8000

100

2500

0.5

0.5

0.167
0.33

0.25

1
0.25

0.125

21

Welding Set

0.125

0.125

22

0.25
0.2

23

0.167

0.25

0.125

Mobile Crane 10 T

cum/hr

0.125
0.25

14

Cost of Labour

15

38

0.5

0.5

1
0.125

0.5

0.5

0.25
1

0.125

0.167

0.25

0.25
0.25
0.5
0.17

0.125

0.17

Hourly Use rate

Watchmen

Driver

Plumber

0.5

Electrician

0.5

Supervisor (ITI)

Fabricator

Welder

Grinder

Khalasi

Fitter

Rigger (Mechanic II)

Helper

Operator -III

Operator - II

Foreman (Diploma)

Batching & Mixing plant (27 cum)

Mechanic - I

Operator-I

Estimated annual operational


hours (O)

Life time repair provision (R)

Machinery

Schedule life in Hour (H)

Cost of Equipment (E)

Capacity

Sl.No

Schedule life in Year (Y)

ANNEXURE C - MACHINERY DETAILS

You might also like