You are on page 1of 6

Pipe Rack Sizing and Loading Data

1 of 6

http://www.svlele.com/piping/pipe_rack.htm

HOME

lelepiping@gmail.com

Piping
Drawings
Piping
Pipe Rack Sizing and Loading Data
Isometrics
P&I Diagrams
Configuration: This is the selection of "fit-for-purpose." Each main run, minor 2D Piping
run and branch run must be looked at to determine its configuration. Will it be 3D Piping
an overhead rack or a sleeper way? Will each be single deck (layer) or multiple Models
deck? Will the support be a single column ("T") support or multi-column
support? How many columns? A second part of the configuration issue effects LISP Training
pipe racks in the process units themselves. This is the question of whether or not Piping Training
the pipe rack will support equipment such as Air Coolers (Fin Fans). Another
part of configuration is the issue of intersections. Poor planning on this issue can Design Info
cause problems later with the piping.
Tubular
Height: How high should each run of rack be? Should they be elevated or low Exchanger
sleepers. The sleepers are concrete with an imbedded steel plate on the top. For Agitator / Mixer
sleepers, they need to be off the ground to allow for maintenance and drainage
also to prevent corrosion. For elevated multi-level racks what should the Design &
separation be? For elevated racks you must plan the height and the separation of Drawings
the whole system together. A key element in the determination of separation is Tubular
Exchanger
the line sizes to be carried on the racks.
Width: This requires a detailed study of the total piping systems for the whole Agitator / Mixer
plant based on pipe rack routing. In the past, a study (called a "Transposition") Zero Hold up
was done to, as best you could, account for each line on each pipe rack. From Filter
this study, a berth sequence was established and the line spacing set. A Process Vessel
percentage was added as an error factor and then the clients "future" reserve Jib Crane
was added. This then constituted the minimum rack width. The final width
would be set after all racks were "sized" and then some might be rounded up in About Me
width for consistency, based on the materials of construction/fabrication My Resume
Contact Me
method.
Spacing: This issue can be addressed after the transposition has been
completed. The transposition identifies all the rack piping from the largest to the Cross Country
smallest From this the average line size for each leg of the rack system can be Piping
established. With the pipe size information (largest, smallest and average pipe
size) the number and spacing of the pipe support bents can be set. A cost
tradeoff is evaluated and made between more pipe supports spaced closer
together or fewer pipe supports and some sort of intermediate support system.
Pipe Rack and Structural form basic framework to hold equipments and Piping.
Pipe Rack work is done in 3 ways.
Concrete : In this case reinforced cement concrete structure is erected. The
reinforcement is provided by tensile strength of steel bars and compression
strength is provided by Cement. The columns and beams are provided with
insert plates, to weld steel members to it. It is time consuming as all work has to
be done on site and the concrete takes long time to cure.
Steel : This is based on steel structural members like Beams, Channels and
Angles. Most of the fitting and aligning work is done in shop and shipped to site.
It is then bolted on site. Design and Erection work is very fast. However,
periodic maintenance and painting is required, if environment is corrosive.

6/6/2559 21:57

Pipe Rack Sizing and Loading Data

2 of 6

http://www.svlele.com/piping/pipe_rack.htm

Steel covered by Concrete : The steel structure bears all the load while cement
cover protects it from corrosion. The steel structure does not melt in case of fire.
Most of the structure is made of vertical columns and horizontal beams, connected to
columns. The equipment and piping rests on beams. Sufficient gap is provided
between beams to lift the equipments and for passage of pipes. Columns are generally
5 meters away and height of beams is 4 meters above the floor level. Cross bracings
are provided to have stability to the structure. This is where anchor points are located,
especially in pipe racks. Most of the pipe supports are created from steel structural
members.
Modular Pipe rack: Sometimes clients look for modular pipe rack / modular structure
for their plants. Module is a series of standard units that function together. Structural
Frames completely fitted with pipes, Cable trays and miscellaneous equipment. If the
project site is at remote location, then it will be very difficult to get good local
contractor. Parallel construction activities are possible (foundation and module
fabrication) and gain in time schedule Controlled construction environment is possible
Controlled quality controlled.
In some countries, labor cost at site is more than labor cost at fabrication / module
assembly shop. So, if you fabricate and fit all the pipes, cable trays etc. at shop, then
you can save the project cost.
Data collection for pipe rack design: Pipe rack is the main artery of any plant. This
carries the pipes and cable trays (raceways) from one equipment to another equipment
within a process unit (called ISBL pipe rack) or carries the pipe and cable trays from
one unit to another unit (called OSBL pipe rack).
Data Collection for different types of pipe rack:
1. Conventional / Continuous Pipe rack: Continuous Pipe racks (conventional
pipe rack) system: This is essentially a system where multiple 2-dimensional
(2D) frame assemblies (commonly called bents), comprised of two or more
columns with transverse beams, are tied together in the longitudinal direction
utilizing beam struts (for support of transverse pipe and raceway elements and
for longitudinal stability of the system) and vertical bracing to form a 3D space
frame arrangement. Pipe racks supporting equipment such as air-cooled heat
exchangers must utilize the continuous system approach.
Data collection for pipe rack design: Due to the fast track nature associated
with most of the projects, often the final piping, raceway, and equipment
information is not available at initiation of the pipe rack design. Therefore, as a
Civil/Structural Engineer, you should coordinate with the Piping group,
Electrical, Control Systems, and Mechanical groups to obtain as much
preliminary information as possible. When received, all design information
should be documented for future reference and verification. In the initial design,
the Engineer should use judgment when applying or allowing for loads that are
not known, justifying them in the design basis
Plot plans and equipment location plans.
3D model showing piping layout, cable tray layout, Pipe rack bent spacing
and elevation of support levels in the transverse direction , Elevation of
longitudinal beam struts and locations of vertical bracing. and location of
pipe bridge, if any.
Piping orthographic drawings.
Vendor prints of equipment located on the rack, e.g., air coolers and
exchangers. The vendor prints should include the equipment layout,
mounting locations and details, access and maintenance requirements, and
the magnitude and direction of loads being transmitted to the pipe rack.
Electrical and control systems drawings showing the routing and location
of electrical and instrumentation raceways and/or supports.
6/6/2559 21:57

Pipe Rack Sizing and Loading Data

3 of 6

http://www.svlele.com/piping/pipe_rack.htm

Underground drawings that show the locations of buried pipes, concrete


structures and foundations, duct banks, etc. in the area of the pipe rack.
Pipe rack construction material (Steel, Cast-in-situ concrete, Pre-cast
concrete) shall be as per project design criteria.
Design loads consideration:
Piping Gravity load (D): In the absence of defined piping loads and
locations, an assumed minimum uniform pipe load of 2.0 kPa should be
used for preliminary design of pipe racks. This corresponds to an
equivalent load of 6 in (150 mm) lines full of water covered with 2 in (50
mm) thick insulation, and spaced on 12 in (300 mm) centers. This
assumption should be verified based on coordination with the Piping
Group, and concentrated loads should also be applied for any anticipated
large pipes. When the actual loads and locations become known, as the
project develops, the structural design should be checked against these
assumed initial load parameters and revised as required. A concentrated
load should then be added for pipes that are 12 in (300 mm) and larger in
diameter. The concentrated load P should be:
P =(W - s x p x d), s = Spacing of pipe rack bent, p = pipe weight
considered (kPa), d = pipe diameter W = pipe concentrated load.
Where consideration of uplift or system stability due to wind or seismic
occurrences is required, use 60% of the design gravity loads as an "all
pipes empty" load condition.
Loading due to hydrostatic testing of lines should be considered in the
design if applicable. Coordinate the testing plan(s) with Construction,
Startup, and/or the Piping Group as necessary, in order to fully understand
how such loads will be applied to the pipe rack structure. Under most
normal conditions, multiple lines will not be simultaneously tested. The
hydro-test loads do not normally need to be considered concurrently with
the other non-permanent loads, such as live load, wind, earthquake, and
thermal. Typical practice is to permit an overstress of 15% for the
hydro-test condition. Because of these considerations, the hydro-test
condition will not normally govern except for very large diameter pipes.
Electrical Tray and Conduits (D): Electrical and control systems
drawings and/or the project 3D model should be reviewed to determine
the approximate weight and location of electrical trays, conduits, and
instrumentation commodities. Unless the weight of the loaded raceways
can be defined, an assumed minimum uniform load of 1.0 kPa should be
used for single tier raceways.
Self weight of Pipe rack (D): The weight of all structural members,
including fireproofing, should be considered in the design of the pipe rack.
Weight of Equipment on pipe rack (D): Equipment weights, including
erection, empty, operating, and test (if the equipment is to be hydro-tested
on the pipe rack), should be obtained from the vendor drawings. The
equipment weight should include the dead weight of all associated
platforms, ladders, and walkways, as applicable. Special Loads: Special
consideration should be given to unusual loads, such as large valves,
expansion loops, and unusual piping or electrical configurations.
Live Load (L): Live load (L) on access platforms and walkways and on
equipment platforms should be considered, as applicable.
Snow Load (S): Snow load to be considered on cable tray and on large
dia pipes. This load shall be calculated per project approved design code
and project design criteria. Generally, you need to consider 100% snow
load on top tier and 50% on other tier of pipe racks.
Wind Load (W): Transverse wind load on structural members, piping,

6/6/2559 21:57

Pipe Rack Sizing and Loading Data

4 of 6

http://www.svlele.com/piping/pipe_rack.htm

electrical trays, equipment, platforms, and ladders should be determined


in accordance with project approved design code. Longitudinal wind
should typically be applied to structural framing, cable tray vertical drop
(if any), large dia pipes vertical drop (if any) and equipment only. The
effects of longitudinal wind on piping and trays running parallel to the
wind direction should be neglected.
Earthquake Loads (E): Earthquake loads in the vertical, transverse, and
longitudinal directions should be determined in accordance with the
project design criteria. Vertical, transverse, and longitudinal seismic forces
generated by the pipes, raceways, supported equipment, and the pipe rack
structure should be considered and should be based on their operating
weights. Pipes must be evaluated for seismic loads under both full and
empty conditions and then combined with the corresponding gravity
loads.
Friction Loading (Tf): Friction forces caused by hot lines sliding across
the pipe support during startup and shutdown are assumed to be partially
resisted through friction by nearby cold lines. Therefore, in order to
provide for a nominal unbalance of friction forces acting on a pipe
support, a resultant longitudinal friction force equal to 7.5% of the total
pipe weight or 30% of any one or more lines known to act simultaneously
in the same direction, whichever is larger, is assumed for pipe rack design.
Friction between piping and supporting steel should not be relied upon to
resist wind or seismic loads.
Anchor and Guide Loads (Ta): Pipe racks should be checked for anchor
and guide loads as determined by the Pipe Stress Group. It may be
necessary to use horizontal bracing if large anchor forces are
encountered. For conventional pipe rack systems, it is normally preferred
to either have the anchors staggered along the pipe rack so that each
support has only one or two anchors, or to anchor most pipes on one
braced support. For initial design, when anchor and guide loads are not
known, use a longitudinal anchor force of 5.0 kN acting at mid span of
each bent transverse beam (refer project design criteria). Guide loads are
usually small and may be ignored until they are defined by the Pipe Stress
Engineer. For non-continuous pipe rack systems, piping may be
transversely guided or anchored at both cantilever frames and anchor
bays. Longitudinal anchors may be located only at anchor bays.
Framing of Continuous/Conventional Pipe rack:
Frames: Main pipe racks are usually designed as moment-resisting frames
in the transverse direction. In the longitudinal direction, there should be at
least one continuous level of beam struts on each side. For pipe racks with
more than one tier, the beam struts should be located at a level that is
usually equal to one-half tier spacing above or below the bottom tier.
Vertical bracing in the longitudinal direction should be provided to carry
the longitudinal forces, transmitted through the beam struts, to the base
plate / foundation level.
Transverse Beam: Transverse beams must be capable of resisting all
forces, moments, and shears produced by the load combinations.
Transverse beams are generally a moment-resisting frame, modeled and
analyzed as part of the frame system. The analysis model must reflect the
appropriate beam end conditions. In the design of beams, consideration
should be given to
Large pipes that are to be hydro-tested.
Anchor and friction load with large magnitude
Central Spine: For steel pipe racks with spans of more than 6 m, a center

6/6/2559 21:57

Pipe Rack Sizing and Loading Data

5 of 6

http://www.svlele.com/piping/pipe_rack.htm

spine consisting of a system of horizontal braces and struts located at mid


span of each level of piping should be considered . This additional light
horizontal framing greatly increases the capacity of the transverse pipe
support beams to resist friction and anchor forces, and also serves to
reduce the unbraced length of the beam compression flange in flexure and
to reduce the unbraced length of the beam about the weak-axis in axial
compression. This concept reduces the required beam sizes and provides a
mechanism for eliminating or minimizing design, fabrication, or field
modifications that could otherwise be required due to late receipt of
unanticipated large pipe anchor forces.
Longitudinal Beam Strut: For typical continuous pipe rack systems, the
longitudinal beam struts should be designed as axially loaded members
that are provided for longitudinal loads and stability. Additionally, the
longitudinal beam struts that support piping or raceway should be
designed for 50% of the gravity loading assumed for the transverse pipe
or raceway support beams, unless unusual loading is encountered. This
50% gravity loading will account for the usual piping and raceway
take-offs. Normally, the gravity loading carried by the beam struts should
not be added to the design loads for the columns or footings since pipes or
raceway contributing to the load on the beam struts would be relieving an
equivalent load on the transverse beams.
For any continuous pipe rack system where the anticipated piping and
raceway take-offs are minimal or none, the 50% loading criteria does not
apply. In such cases, the beam struts should be designed primarily as
axially loaded members. Do not provide beam struts if they are not
needed for piping or raceway support, or for system stability. Conversely,
the 3D model should be checked to verify that beam struts subjected to
unusually large loads (such as at expansion loops) have been given special
consideration. All longitudinal beam struts, including connections, should
be designed to resist the axial loads produced by the longitudinal forces.
When designing the longitudinal beam struts for flexural loads, the full
length of the beam should be considered as the unbraced length for the
compression flange.
Vertical Bracing: When moment-resisting frame design is not used in the
longitudinal direction, vertical bracing should be used to transmit the
longitudinal forces from the beam struts to the foundations. Knee-bracing
or K-bracing is most often used for this purpose. Unless precluded by
equipment arrangement or interferences, bracing should be placed
equidistant between two expansion joints. Design calculations and
drawings must reflect a break in the beam strut continuity between
adjacent braced sections through the use of slotted connections or by
eliminating the beam struts in the bays designated as free bays. The
maximum length of a braced section should be limited to 48m to 50m. If
the braced bay is not located equidistant from the free bays, the maximum
distance from the braced bay to a free bay should be limited such that the
maximum total longitudinal growth or shrinkage of the unrestrained
segment does not exceed 40 mm.
Column: The columns must be capable of resisting all loads, moments,
and shears produced by the load combinations. A moment-resisting frame
analysis should normally be used to determine the axial load, moment,
and shear at points along the columns. The frame analysis model should
be based on the following:
Consider column base as hinge.
Use 4 bolt connections for safety purpose.

6/6/2559 21:57

Pipe Rack Sizing and Loading Data

6 of 6

http://www.svlele.com/piping/pipe_rack.htm

For design of steel columns subjected to flexural loads, the distance


between the base and the first transverse beam or the knee brace
intersection should be considered as the compression flange unbraced
length.

to get all the information as a eBook

6/6/2559 21:57

You might also like