Professional Documents
Culture Documents
Rev 4
COS 03/31/2010
SATIP No.
APPROVED DATE
SATIP-G-005-01
PROJECT TITLE:
ITEM
NO.
1.0
MECHANICAL-Rotating Equipment
CONTRACTOR/SUBCONTRACTOR
PROJECT PHASE
& ACTIVITY CODE
DOCUMENT REVIEW
31-Aug-11
DISCIPLINE:
TASK / ACTIVITY
QUALITY
PROCEDURE
QUALITY
RECORD
INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR
REMARKS
SAUDI
ARAMCO
Centrifugal Pump Installation is a Special Process per Schedule Q. An installation procedure shall include elements from checklists below, at a minimum.
Review of Material & Equipt Storage,
Handling and Preservation Procedure-
SAIC-G-2001
SAIC-G-2001
RH
RH
2.1
SAIC-G-2002
SAIC-G-2002
2.2
SAIC-G-2003
SAIC-G-2003
2.3
See Remarks
See Remarks
See Remarks
See Remarks
See SATIP-Q-001-02
SAIC-M-2006
SAIC-M-2006
SAIC-G-2021
SAIC-G-2021
Use SATR-G-2005
Use SATR-G-2004
1.1
2.0
3.0
MATERIAL RECEIVING
INSTALLATION
3.1
3.2
3.3
3.4
SAIC-G-2022
SAIC-G-2022
3.5
See Remarks
See Remarks
3.6
SAIC-G-2004
SAIC-G-2004
3.7
See Remarks
See Remarks
Refer to SATIP-J-600-01
3.8
Welding
See Remarks
See Remarks
See SATIP-W-011-01
SAIC-G-2005
SAIC-G-2005
SAIC-L-2014
SAIC-L-2014
3.9
3.10
3.11
See Remarks
See Remarks
3.12
See Remarks
See Remarks
Refer to SATIP-P-515-01
3.13
See Remarks
See Remarks
Refer to SATIP-J-902-03
SAIC-G-2022
SAIC-G-2022
4.0
4.1
PRE-COMMISSIONING
Page 1 of 2
Use SATR-G-2004
Rev 4
COS 03/31/2010
SATIP No.
APPROVED DATE
SATIP-G-005-01
PROJECT TITLE:
ITEM
NO.
4.2
1.0
31-Aug-11
DISCIPLINE:
MECHANICAL-Rotating Equipment
CONTRACTOR/SUBCONTRACTOR
PROJECT PHASE
& ACTIVITY CODE
DOCUMENT REVIEW
4.3
4.3
TASK / ACTIVITY
QUALITY
PROCEDURE
INSPECTION RESPONSIBILITY
ASSIGNMENTS
QUALITY
RECORD
CNTRCTR
REMARKS
SAUDI
ARAMCO
Instrumentation and Electrical PreRefer to the respective SATIPs for Electrical &
Remarks
See Remarks
Centrifugal Pump
is a SpecialSee
Process
per Schedule
Q. An installation procedure shall include elements
from checklists
below, at a minimum.
Commissioning
priorInstallation
MCC
Instrumentation
noted above.
Final Inspection/walkthrough (by
SAIC-G-2007 SAIC-G-2007
H
W
Use SATR-A-2011
Contractor)
Final Inspection for mechanical
Form SA-6133 Form SA-6133
H
completion acceptance
GENERAL NOTES
1
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels
of Saudi Aramco participation based upon the Contractors performance.
Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness:
QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative
is not present.
Hold:
If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
LEGEND
H
Witness Inspection/Test
Surveillance
R
RH
I
Page 2 of 2
Review of Documents
Review and Approval of Documents
100% Contractor Inspection