Professional Documents
Culture Documents
Scholars' Mine
International Conference on Case Histories in
Geotechnical Engineering
Baran Ozsoy
Zirve University, Turkey
This Article - Conference proceedings is brought to you for free and open access by Scholars' Mine. It has been accepted for inclusion in International
Conference on Case Histories in Geotechnical Engineering by an authorized administrator of Scholars' Mine. This work is protected by U. S. Copyright
Law. Unauthorized use including reproduction for redistribution requires the permission of the copyright holder. For more information, please contact
scholarsmine@mst.edu.
ABSTRACT
The New Victoria Hospital in Glasgow, Scotland provides a 30,000m Ambulatory Care and Diagnostic (ACAD) facility. The
ground conditions beneath the site comprise a variable thickness of Made Ground overlying Glaciomarine Deposits and Glacial Till
which in turn rests on the Carboniferous bedrock. However the solid geology is complex and interrupted by a number of faults. The
Carboniferous rocks under the site include a number of coal seams, although it is thought that none of these seams has been worked at
this location. Due to the relatively low strength of the glacial soils, it was necessary to support the building on piles socketed into the
bed rock. However the various coal layers could not be relied upon to provide adequate end bearing capacity and therefore piles were
designed to be supported solely on side resistance from the rock socket. In order to investigate pile load bearing capacity and to
differentiate end bearing from shaft friction capacity, a number of preliminary and working load tests were carried out with one pile
particularly using a soft toe system. The results of load tests revealed an ultimate shaft friction capacity value in the rock socket of
approximately 1.3MPa (189psi).
THE DEVELOPMENT
The site forms part of a former battleground of the Battle of
Langside which was fought on 13 May 1568. Some 300 men
were killed during the battle although it is recorded that the
conflict lasted just 45 minutes. The site appears to have
remained as open fields for the many years thereafter and the
first development on the site occurred in the late 1800s when a
road was established through the site and a school, later
referred to as Queens Park Secondary School, was built on the
south western corner of the site. It was at this time that the
Victoria Infirmary (named after Queen Victoria) was built on
the land opposite. Some houses were later built on the site
north of the school, but by the late 1970s these had been
demolished and by 2005 the one remaining school building
had fallen into disrepair.
By this time the local health authority, the NHS Greater
Glasgow Health Board, had identified the need for a new
Ambulatory Care and Diagnostic (ACAD) Hospital to be built
on the site. The proposed new 100million development
comprised a four storey building and a semi-basement to be
built on the now largely derelict land. The development site
extended to approximately 0.3 hectares in area.
GEOLOGICAL HISTORY
Various phases of ground investigation were carried out at the
site and these were latterly supplemented by a further
investigation focused on the proposed development.
Superficial Geology
The published geological map of the area indicates the
majority of the site to be underlain by Quaternary drift
deposits of the late Devensian stage.
Table 1. Published Superficial Geology of the Area
Formation
Paisley Formation
Wilderness Till
Provenance
Marine
Glacial
11,500 -13,500
13,500-27,500
Solid Geology
The published geological map shows the solid strata in the
area to form the following succession:
Table 2. The Published Solid Geology of the Area
Formation
Description
Significant Seams
Middle Coal
Measures
Sandstones,
siltstones and
mudstones with
numerous coal
seams
Mainly sandstones
with fireclays and
thin mudstones and
coals
Sandstones with
mudstones, thin
limestones and
coals
Sandstones,
siltstones and
mudstones with
numerous coals
and ironstones
Glasgow Main
Coal. Humph
Coal, Glasgow
Splint Coal, Virgin
Coal
No named seams
Passage Group
Upper Limestone
Formation
Limestone Coal
Formation
Stratigraphy
The detailed ground investigation revealed a variable
thickness of superficial deposits overlying rockhead, the depth
to rockhead from surface varying from 6 m to 20.4m. The
majority of the site was found to be underlain by made ground
and this is turn was found to overlie a highly variable
succession of Glaciomarine deposits comprising loose sand
and silt overlying soft and occasionally laminated clays. The
Glaciomarine deposits were often found to rest on the Glacial
Till (stiff boulder clay) but the thickness of the Till was
Design parameters
(1)
quc=24 Is(50)
40
60
80
100
20
80
120
160
200
10
15
20
) 25
L
G
B
(m30
h
t
p
e
D
35
40
45
50
240
55
1
60
2
)
m
(
d
a 4
e
h
k
c
o
R
w 5
lo
e
b
h
t
p 6
e
D
8
Unconf ined Com pressive Test
Point Load Test - Axial
9
Point Load Test - Coal
Design Line
10
Given that the occurrence and depth of coal layers beneath the
site has been shown by the ground investigation to be
unpredictable (largely as a the result of significant local
faulting), there was considered to be a significant risk of a pile
tip bearing on, or just above, a weak coal seam. End bearing
resulting from bearing onto coal is only a small proportion of
(2)
where:
=
=
quc =
The piling work and load testing performance criteria were set
out in accordance with the Institution of Civil Engineers
Specification for Piling and Embedded Retaining Walls
(SPERW) dated 1996.
Whilst the Williams and Pells (1981) method gives the highest
value of the other two methods cited by Tomlinson assume
an value of unity. Therefore the approach by Williams and
Pells (1981) is likely to be more conservative than the two
other methods when considering highly fractured rocks.
The acceptance criteria for the test piles selected for the
project were as follows:
a)
Fracture Frequency/m
Mass factor j
0-25
25-50
50-75
75-90
90-100
15
15-8
8-5
5-1
1
0.2
0.2
0.2-0.5
0.5-0.8
0.8-1.0
(3)
(4)
fs
(MPa)
1.71
Rosenberg and
1.09
0.52
Journeaux
(1976)
Horvath (1978)
1.04
0.50
1.47
Horvath &
0.650.50
0.92
Kenney (1979)
0.78
Williams et al.
1.84
0.37
1.31
(1980)
Rowe &
1.42
0.50
2.01
Armitage (1984)
Carter &
0.63
0.50
0.89
Kulhawy (1988)
Fleming et al.
1.30
0.50
1.84
(1992)*
Zhang &
1.26
0.50
1.78
Einstein (1999)
Prakoso (2002)
0.98
0.50
1.39
Kulhawy et al
1.00
0.50
1.41
(2005)
(*)
Not included in Kulhawy et al. data
(psi)
248
213
133
190
292
129
267
258
202
205
1st Preliminary Test Pile with the Soft Toe Feature (TP1)
2000
4000
6000
8000
10000
0
10
TP1
20
)
m
m
(t 30
n
e 40
m
e
v
o 50
M
60
70
80
Fig.5 Pile Load Compression Test Results for TP1 (Soft Toe)
The test was taken to a maximum load of 9450kN (2125kip-f)
which equates to 225% SWL. It was not possible to maintain
the load beyond this point and in view of the soft toe it was
felt advisable for health and safety reasons to terminate the
test when settlement reached 75mm (3). This settlement
corresponds to 10% of the pile diameter and this is in itself an
arbitrary definition of pile failure.
A back analysis of the load-settlement data was undertaken
using the CEMSOLVE program using the method derived by
Fleming (1992). This analysis suggested that higher ultimate
load might have been achievable albeit at very large
settlements. However this could not be confirmed with the
method of testing adopted.
The predicted elastic shortening obtained from CEMSOLVE
using E=30GN/m2 gave values close to the settlement recovery
at the end of the test of around 10mm. However the actualload settlement response was much softer than that might
have been predicted at the outset using CEMSET. Specifically
the shaft flexibility factor Ms was back calculated by curve
fitting and this yielded a value of around 0.005 a value
associated with soft soils. Ms is in fact the tangent slope at the
original of the hyberbolic function representing shaft friction.
The reasons for this disparity are not clear but it is possible
that rock discontinuities and overall roughness of the socket
will have increased the load bearing capacity of the socket but
Fig.6 The Soft Toe Detail for the First Test Pile (TP1)
2nd Preliminary Test Pile without the Soft Toe Feature (TP2)
The second test pile was constructed without the soft toe
feature in order to make a comparison with TP1. The
designated working load for TP2 was 4200kN (944kipf) and
the target peak test load was 10500kN (2360kipf). The pile
settled 8.2mm (0.32) at the peak test load and a residual
settlement of 3.2mm (0.12) was observed at the end of the
test.
The most significant difference between TP1 and TP2 was the
stiffer pile settlement response observed during the second
preliminary test. It is interpreted that due to the relatively short
rock socket length in both cases, the contribution of pile endbearing capacity to the overall pile capacity was more evident
in the second test and some significant end-bearing capacity
might have mobilized before the pile test mobilized the full
shaft capacity.
Load (kN)
0
2000
4000
6000
8000
10000
12000
0
1
TP2
)
m
(m
t
n
e
m
e
v
o
M
3
4
5
6
7
8
9
10
The Working Load Tests for QA/QC Purposes (TP3 and TP4)
Two other test piles were selected for QA/QC purposes and
maintained load tests were performed on these contract piles
up to 150% of their SWL.. The test pile diameters for TP3 and
TP4 were 750mm and 600mm; respectively. The performance
of these two contract piles were also considered satisfactory as
they satisfied the structural performance criteria set out at the
piling specification.
Load (kN)
0
1000
2000
3000
4000
5000
TP3
TP4
(5)
)
m
m
(t 2
n
e
m
e
v
o 3
M
4
Fig.8. Pile Load Compression Test Results for TP3 and TP4
WL (kN)
PTL (kN)
Settlement
@ WL
(mm)
TP1
4200
9450
7.17
TP2
4200
10500
2.36
TP3
3000
4500
1.77
TP4
2500
3750
1.76
(*)
WL: Working Load / PTL: Peak Test Load
Settlement
@ PTL
(mm)
75.39
8.20
3.30
2.90
Load (kN)
0
50
100
150
200
250
300
350
400
LTP1
LTP2
1
)
m
(m
t 2
n
e
m
e
v
o 3
M
ACKNOWLEDGEMENTS
The authors are grateful to AECOM, Balfour Beatty and Stent
Foundations for providing the necessary data to prepare this
paper.
REFERENCES
Fig.10 Pile Lateral Load Test Results
Pile No
Deflection
@ PTL
(mm)
4.59
1.79
WL (kN)
PTL (kN)
Deflection
@ WL
(mm)
LTP1
275
330
2.88
LTP2
275
330
1.25
(*)
WL: Working Load / PTL: Peak Test Load
CONCLUSIONS
The predicted bond strength in a rock socket is usually
estimated from the unconfined compressive strength. However
the accuracy of such an approach is dependent upon obtaining
a representative value of the rock strength. At the Victoria
ACAD site the relationship proposed by Williams et al. (1980)
and also Williams and Pell (1981) gave the closest
approximation to the value which was later verified by the soft
toe pile testing. The method proposed by Kulhawy et al.
(2005) also gave a good approximation.
Although a number of load tests were performed for this
project, it will be necessary to carry out further research and
more rock socket load tests in Carboniferous rocks in the
Glasgow area before more widely applicable design guidance
can be formulated. It is certainly vital to carry out preliminary
load tests particularly as major uncertainties exist in the
prediction of rock socket behaviour.