You are on page 1of 46

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

The Kingdom of Thailand


Ministry of Transport

MASS RAPID TRANSIT AUTHORITY OF THAILAND

MRT BLUE LINE EXTENSION PROJECT


CONTRACT 1: UNDERGROUND CIVIL WORKS
(HUA LAMPHONG SANAM CHAI SECTION)

METHOD STATEMENT
FOR
PRIMARY AND SECONDARY GROUTING
Document No. ITD/BE1/MS/T007, Rev. C
JULY 2013

PREPARED BY:

ITALIAN-THAI DEVELOPMENT PUBLIC COMPANY LIMITED


Italian-Thai Development PCL.
35

1 July 2013

Page 0 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

Document Title: Method Statement for Primary and Secondary Grouting


Document No: ITD/BE1/MS/T007
Document Amendment Record
Revision

Date

Amendment Record

15 February 2012

11 April 2012

1 July 2013

First submission for approval


Amend as per CSCBLs Letter Ref. CSCBL/C1/ITD/MST/0678,
Dated 14th March 2012
Improving some point of this method statement for making it
correct, practical and perfect: in item 4.1.2.3 page 6, 7 and item
4.2 page 9 and in checklist page 13, 15
Controlled Distribution List

Copy
No

Distribution
List

Type of
Issue

MRTA

PMC

CSC

Recipient

Copy
No

Distribution
List

Type of
Issue

Recipient

Type of Issue
A For Internal Review& Comment
B For ERs Approval

C For Acknowledgement or Information or Reference.


D For Use or Implementation or Construction

Type of Document
Where this page is over-stamped with the words C this means:
1. Distribution is centralized-in this case from the Quality Assurance Manager.
2. Each copy is issued to a particular person or organization. If no longer required it should be returned.
3. It is not to be photocopied either in whole or in part. Additional copies are available on request.
4. Copy holders will be automatically issued with any amendments. Responsibility for incorporating such
amendments rests with the copy holder.

Italian-Thai Development PCL.


35

1 July 2013

Page 1 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C
Prepared by: __________________________
(Nopporn Rattanchayabun)
Section Manager (TBM Tunnel)

Reviewed by: _____________________________


(Prakin Arunotong)
Engineering and Project Control Manager

Date : ______________________

Reviewed by: _____________________________


(Thavesak Rungpiriyadech)
Tunnelling Works Manager

Date : ______________________

Approved by: _____________________________


(Pairach Supavivat)
Project Director

Date : ______________________

Date : ______________________

Table of Contents

1.

Scope........................................................................................................3

2.

Definitions and Abbreviations.....................................................................................3

3.

Specifications and Reference


Documents..................................................................4

4.

Working Procedures...................................................................4

5.

Inspection and Test Plan .........................................................12

6.

Quality Control Checklist for Primary and Secondary


Grouting.............................13

7.

Attachment A Grouting Material for shield Tunneling Work: Proposal for Mix Design
and Testing Method....................................................................................17

8.

Attachment B The Laboratory Test Program for Primary and Secondary Grouting
Works..27

9.

Attachment C ASTM C939-02 Standard Test Method for Preplaced-Aggregate


Concrete (Flow Cone Method)29

10.

Attachment D ASTM D4830-84 (Reapproved 2001) Standard Test Method for


Density of Bentonitic Slurries..33

Italian-Thai Development PCL.


35

1 July 2013

Page 2 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

1.

Scope
This method statement provides information for Primary Grouting and Secondary
Grouting in the MRT Blue Line Extension Project, Contract 1: Hua LamphongSanam Chai Section. The cavity between the segment outer surface and soil shall
be filled with grout material as soon as possible after TBM excavation. Therefore,
the cavity between segments extrados and surrounding ground will be grouted
immediately after TBM excavation suddenly after TBM move through segment hole 2
positions at shoulder left & right. This grouting shall be performed in two steps
namely primary grouting (concurrent with excavation) and later secondary grouting.
As the outline Construction Specifications Volume 6, Clause 9.8.3(C), Proprietary
grouts may be used, subject to the Employers Representatives consent. Therefore,
the thixotopical-gel type which consist of liquid A and liquid B was proposed for
Primary Grout.
The thixotopical-gel grouting was famous using in worldwide. The best benefit of
thixotopical-gel grouting is quick setting time. Comparison between thixotopical-gel
grout and single fluid grout with high water cement ratio, the thixotopical-gel grout
was more quicker setting time and best for protect road surface and building area.
Therefore ITD proposed the thixotopical-gel grouting for the MRT Blue Line
Extension Project.
The secondary grouting shall consist of cement liquid part A from the primary
grouting material which is prepared on ground surface batching plant and then
transported to tunnel.

2.

Definitions and Abbreviations


Inspection and Testing Plan (ITP) is a document made by ITD or manufacturer or
subcontractor to describe the minimum requirements of the quality control
activities, inspection and test items during fabrication, installation and/or
construction phase, reference documents, required acceptance criteria, certifying
or verifying documents, and inspection parties involved, its all for assure that the
work or product will be built in accordance with the project specification. Relevant
inspection levels contained in ITP is defined as follows:

Italian-Thai Development PCL.


35

1 July 2013

Page 3 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

(Hold Point)

Signify an important inspection point. This is used for special tests or inspections
which shall be witnessed, signed and dated by the authorized inspector and/or the
Employer and/or the Employers Representative.
W

(Witness Point)

Signify an important inspection point to be witnessed by the authorized inspector.


W/O

(Witness Point-Optional)

Signify an inspection point to be witnessed or optional point not to be witnessed by


the authorized inspector and/or Employer and/or the Employers Representative.

(Surveillance Point)

Signify an inspection point which may be carried out on a random basis.


Notification of these points are normally not specified (ITD will review the
frequency of inspection results).
X

(Sub-contractor Inspection)

ITPs for sub-contract works shall contain the nominated inspection points and
inspectors.
D

(Documentation Required)

Signify that a test report, material certificate or the like shall be supplied, or that
the particular inspection activity must be verified by a document signed and dated.
It may be in the form of a QA traveler document attached to, or moving through the
process with the products.
R

(Review Point)

Review and verify of quality system documentation and final quality records. This
may vary from a spot review to a full quality audit and may include verification by
ITD that a final report or manufacturers data report has been compiled and is a
complete and accurate record. ITPs shall be reviewed by ITD and at the same time
marked up to indicate ITDs surveillance inspection activities. As previously stated,
all ITPs shall be reviewed and approved by responsible Manager(s) prior to the
commencement of manufacture or construction.
3. Specifications and Reference Documents
Related specification contained in OCS Volume 6 Section 9.8.1 - 9.8.12.
4.

Working Procedures

Italian-Thai Development PCL.


35

1 July 2013

Page 4 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

4.1

Primary Grouting Method


4.1.1

General
This Section provides the information for performing the primary
grouting with the Thixotopical - gel type grout material
The major activities in primary grouting are:
a) Grout Material Quality Control.
b) Grouting, the grout pressure is measured, monitored and
recorded by the tunnel driving monitoring system on the TBM
working platform number 2 and record with print out by ENZAN
software.
c) Tunnel Segment Movement Monitoring, we have two surrey teams
both on ground and in the tunnel to monitoring ground
displacement and segment deformation by check TBM clearance
to segment for diameter result.
The details for each activity are described in following sections.

4.1.2

Grout Material Mixing and Quality Control


In order to ensure that the proposed quality of the thixotropical-gel
type grout material is achieved the quality testing procedure shall be
applied.
Although the testing methods for quality control are described in the
Grouting Material for Shield Tunneling Work: Proposal of Mix Design
and Testing Method, the details method shall be referred to as
follows:
4.1.2.1

Grout Mix
The proposed grout mix is shown in Table 1.

Table 1: Grout Mix for Primary Grout


Solution

Material

Design Quantity
(per 1 m3 mixed grout)

Liquid A

Cement

240 kg

Bentonite

30 kg

Water

830 kg

Stabiliser

2.4 kg

Special Sodium Silicate

80 litre

Liquid B

Italian-Thai Development PCL.


35

1 July 2013

Page 5 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

This final mix design is subject to laboratory test before actual carried out.
4.1.2.2 Instrument and Equipment to be used
The following instruments and equipment shall be used for
the primary grouting mixing and quality control:

4.1.2.3

Unconfined compression apparatus.

ii

Graduated cylinder (1 litter).

iii

Beaker (3 litter).

iv

Stop Watch.

Specimen Mould (5 cm cube).

vi

50 cm cubic case for water measuring.

vii

Grout Mixing Plant and Associated Equipment.

viii

Weight Meter.

Calibration on weight scales of grout mixing plant and check


density of stabilizer and sodium silicate
In order to ensure that the accuracy of weight material
components, mixing ratio, injection flow rate and injection
pressure, the following calibration activities will be
performed every 4 months.
a)

b)
Italian-Thai Development PCL.
35

Calibration on weight scales of grout mixing plant


i.

Remove any object from the top of mixer and make


no load on the mixer.

ii

Confirm that 0 kg (No load) on the mixer.

iii

Put each weight (20kg) on the mixer and add each


weight until 1300 kg (weight 20 kg = 65
block):record the weight displays each step.

iv

Then, lift each weight down from the mixer and


record the weight display each step until weight
display is 0 kg.

Repeat process item (I. to IV.) again.


Total weight shall be measured to an accuracy of
(+ -) 1%.

Check specific gravity of stabilizer.


1 July 2013

Page 6 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

c)

d)

Pour stabilizer 500 cc. in the beaker.

ii

Use specific gravity meter to measure and record


the specific gravity of stabilizer 3 times, then
average the value.
The specific gravity of stabilizer shall be
measured in the range 1.095 to 1.115 g/cm 3.

Check specific gravity of sodium silicate.


i

Pour sodium silicate 500 cc. in the beaker.

ii

Use specific gravity meter to measure and record


the specific gravity of sodium silicate 3 times, then
average the value.
The specific gravity of sodium silicate shall be
measured in the range 1.394 to 1.422 g/cm3.

Check stabilizer pump feed test.


i
line.
ii

e)

Operate the pump and set the flow for the feed
After flow volume stable, take a sample for one
minute.
Conduct the test for three time, compare the
volume which the deviation of volume shall be in
the range (+ -) 3%.

Grout liquid flow rate.


To ensure an accurate mixing rate at the injection point,
each flow rate of liquid A and B shall be checked the
flow rate at the injection point.

f)

Italian-Thai Development PCL.


35

Prepare a container to pour grout liquid near an


injection point.

ii

Start pumping liquid A into a container. Calculate


the flow rate of liquid A upon the time for pumping
and the actual volume of the liquid A shall be in the
range (+-) 3%.

iii

Repeat the same procedure above for liquid B.

iv

Confirm that the flow rate ratio shall be 11.5 (Liquid


A): 1 (Liquid B).

Grout Pressure.

1 July 2013

Page 7 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

To ensure an accurate of grout pressure gauge, the


pressure gauge should be calibrated and has the
calibration certificate by an external and independent
party.
4.1.2.4

Testing Frequency
The frequency of the quality test of the grout material is
shown in Table 3. A summary report shall be submitted
upon the test result of the first 30 rings.

Table 3 The Frequency of the Quality Test of the Grout Material


Period

Frequency

First 30 rings

Every ring

After 30 rings in Initial Drive and in whole Main Drive

Every 5 rings at Batching Plant (on ground)

4.1.2.5

Quality Testing Items


The following tests shall be performed in accordance with
the testing frequency as specified in Table 3. Table 4
shows the testing items and the acceptance criteria for
each test.

Table 4: Testing Item and the Acceptance Criteria for Each Test
Item

Specification

Test Method

Test Standard

Specific Gravity

1.20 + 0.02 g/cm 3

Mud Balance

ASTM D 4380-84
(Reapproved
2001)

Liquid A

Bleeding

0-5% (1 hour after


Liquid A mixing)

Bleeding Test

ASTM C940-98A

Liquid A

Consistency

< 11 seconds

Flow Test

ASTM C939-02

Gel Time

4-12 seconds

Mix Test

N/A

1 Hour

0.03 N/mm 2

ASTM C109M-02

Frequency

Every Shift

Remark

Liquid A
Liquid A+B

Every Ring for

Compressive

Italian-Thai Development PCL.


35

1 July 2013

Page 8 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

Strength

24 Hours

0.4 N/mm 2

first 30 rings

7 Days

0.8 N/mm 2

Every 5 rings

28 Days

1.5 N/mm 2

During
maindrive

4.1.2.6

Mixed
Grout

Deterioration test
In order to ensure that the pot life of liquid A, a
deterioration test shall be performed. All testing as shown
in Table 4 shall be performed both immediately and also
24 hours after mixing Liquid A.
If the test results are within the specified tolerance as per
Table 4, then Liquid A shall be judged to have had no
deterioration.

4.1.3

Grouting
The injection of the grout material shall be performed as the method
statement for tunnel excavation specifies.
The grout pressure and the volume shall be monitored and recorded
by the tunnel driving monitoring system.
The filling rate against the theoretical cavity volume shall be
calculated and recorded by the tunnel driving monitoring system.

4.2

Secondary Grouting Method


4.2.1

Introduction
Secondary grouting will be completed in correlation with deformation
measurement within 10 day after ring completion and not move than
30 meters behind the TBM face. Secondary grouting shall be at a
pressure not greater than 4 bars, consistent with completely filling all
voids.
The mix design are tabulated as below:

Italian-Thai Development PCL.


35

Materials

Proportion

Cement

500 kg

Water

850 litre

Bentonite

50 kg

1 July 2013

Page 9 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

4.2.2 Testing Frequency


The frequencies of the quality test of the grout material are random
checking by 1 sample per time of grouting in tunnel.
4.2.3 Quality Testing Items
The following tests shall be performed in accordance with the testing
frequency. Table of specified requirements shows the testing items
and the acceptance criteria for each test.
Table 5: Specified Requirements of Secondary Grouting Material.
Item

Specification

Test Method

Test Standard

Specific Gravity

1.35 + 0.02 g/cm 3

Mud Balance

ASTM D 4380-84
(Reapproved
2001)

Bleeding

0-5% (1 hour after


Liquid A mixing)

Bleeding Test

ASTM C940-98A

Consistency

N/A

Flow Test

ASTM C939-02

Compressive
Strength Test

1.5 N/mm 2
at 49 days

4.2.4

ASTM C109M-02

Frequency

Remark
Liquid A

Every internal
5 No rings

Liquid A

Random check

Liquid A

Liquid A

Deterioration test
In order to ensure that the pot life of liquid A, deterioration test shall be
performed. All testing as shown in Table 5 of specified requirement
shall be performed both immediately and also 24 hours after mixing
Liquid A.
If the test results are within the specified tolerance as per the above
Table 5, then Liquid A shall be judged to have had no deterioration.

4.2.5

Work Sequence for secondary grout


The injection of the grout material shall be performed after primary
grouting completed. During each shift secondary grouting shall be
performed at the back up on the working stage of TBM. The
secondary grouting shall use the mobile pump order to control the
pressure to 3.5 kg/cm2. The position of grouting shall be located at
existing drill holes at every interval of 5 No rings with wet hole. Any

Italian-Thai Development PCL.


35

1 July 2013

Page 10 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

grout holes showing evidence of water leakage shall also be


secondary grouted, as will those nearest to any wet joints. However,
the most important issue to concern is the surface displacement which
should be considered together between the surface monitoring
instrument result and the tunnel driving monitoring system. If one
both systems can detect the settlement or heave, engineer have to
stop secondary grouting at that point and re-consider grout pressure
before processing the secondary grout.
The procedure for injection of the secondary grout shall be as follows:
a

Open grout hole plug.


Each segment grout hole plug shall be carefully removed in order
to prevent any inflow of ground water or soil through the hole.

Drill hole through the non-return valve in segment grout hole


(never key segment). The 28 mm electric drill (400 mm. length)
shall be inserted into the position of the abandoned non-return
valve.

Installation of injection pipe at grout hole.


The injection pipe shall be installed as soon as possible after
removing grout hole plug.

4.2.6

Connect grout hose to injection pipe.

Carry out the grouting until the pressure achieved 3.0-3.5 kg/cm 2.
(Automatic shut down of pump pressure of 3.0-3.5 kg/cm 2).

Grouting volume shall be measured by measurement liquid


volume using in mixing tank.

Change injection point once the grout pressure has achieved 3.03.5 kg/cm2 and leave the grout injection pipe in the hole until the
grout has set. The grout hole plug shall be replaced and fully
tightened once the grout pipe has been removed.

The compressive strength test specification is required grout


strength 1.5 N/mm2. @ 49 days.

Use new injection pipe for installation into the next grouting
position.

Change grouting hose to next position and continue.

Facilities to be prepared
a

Grouting pump with pressure limiter.

Electric Hand Drill whole size 28 mm. x 400 mm. length

Italian-Thai Development PCL.


35

1 July 2013

Page 11 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

4.2.7

Tank of agitator installed in TBM back up unit.

Injection pipe with ball valve 2 inch dia. same threading with the
grout hole in segment.

Grout hose, size 1 inch.

Quality Control
Following items as the quality control checklist shall be checked and
monitored during the works.

Italian-Thai Development PCL.


35

1 July 2013

Page 12 of

MRT Blue Line Extension Project


Works

Contract 1: Underground Civil


Hua Lamphong Sanam Chai

Section

Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007,

Rev. C

INSPECTION AND TEST PLAN

PROJECT : MRT Blue Line Extension


Contract : Underground Civil Work
(Hua Lamphong Sanam Chai Section)
Location/Area : Tunnel at Hua Lamphong to Sanam Chai Station

Quality System : ISO 9001


Document Type : Controlled

For : Method Statement Primary and Secondary Grouting

Inspection Responsibilities
No.

Main Activity

Relevant
Specification

Acceptance Criteria

Document

ITD

Frequency of Inspection/Test

Verification/Acceptance
sign off by

Form Checklist

Subcontractor

Vendor

Site
Engineer

QC

Every Day

N/A

W/O

Every Day

N/A

W/O

Every Day

N/A

Every Day

N/A

ER

No.

Rev.

W/O

MS/T007/1

Site Engineer

W/O

MS/T007/2

Site Engineer

W/O

W/O

MS/T007/3

Site Engineer

W/O

W/O

MS/T007/3

Site Engineer

Primary Grouting

Primary Grout Material Test

OCS Volume 6
Section 9.8

Primary Grouting Shift


Report

OCS Volume 6
Section 9.8

Secondary Grouting

Secondary Grout Material


Test

OCS Volume 6
Section 9.8

Secondary Grouting Shift


Report

OCS Volume 6
Section 9.8

Italian-Thai Development PCL.

ASTM D 4380-84
(Reapproved 2001),
ASTM C940-98A
ASTM C939-02
ASTM C109-02
ASTM D 4380-84
(Reapproved 2001),
ASTM C940-98A
ASTM C939-02
ASTM C109-02
ASTM D 4380-84
(Reapproved 2001),
ASTM C940-98A
ASTM C939-02
ASTM C109-02
ASTM D 4380-84
(Reapproved 2001),
ASTM C940-98A
ASTM C939-02
ASTM C109-02

1 July 2013

Page 12 of 35

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai Section

Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev. C

Mandatory Hold Point Until Approved

Surveillance Point Random ITP/Each Quantity

Witness Point

Subcontract Inspection

Witness Point-Optional

Document or Record Required

W/O

Italian-Thai Development PCL.

1 July 2013

Page 13 of 35

R
N/A

Review Point
Not Applicable

MRT Blue Line Extension Project


Works

Contract 1: Underground Civil


Hua Lamphong Sanam Chai

Section

Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.

Primary Grout Material Test


(Form No. MS/T007/1, Rev. C)
Time:

No

Test ltem

Specification

Specific Gravity

Set ting

Consistency

Gel time

Tunnel : WB / EB
Test Result

Ring No________

Judgment

Test Standard

Remark

Yes / No

ASTM D 4380-84
(Reapproved 2001),

Liquid A

Yes / No

ASTM C 940-98A

Liquid A

Yes / No

ASTM C939 62

Liquid A

Yes / No

N/A

Liquid (A+B)

1.20
0.02g/cm 3
0-5% (After
1 hour)
< 11
seconds
4 ~ 12
seconds

1 hour

1.
2.
3.
Avg.

0.03 N/mm 2

Yes / No

0.4 N/mm 2

Yes / No

0.8 N/mm 2

Yes / No

1.5 N/mm. 2

Yes / No

See note

1.
24 hour

Compressive Strength Test

Mixing Date:

2.
3.
Avg.

ASTM C109-62

See note

7 days

1.
2.
3.
Avg.

28 days

1.
2.
3.
Avg.

Completed by Site Engineer

Agreed by QC

Name :___________________
(
Date : _____________________

ER

Name :___________________
)

Engineer

See note

)
Engineer

Witnessed Point-Optional by :
__________
(
)

Date : _____________________
Date : ___________________________

Italian-Thai Development PCL.


35

July 2013

Page 13 of

MRT Blue Line Extension Project


Works

Contract 1: Underground Civil


Hua Lamphong Sanam Chai

Section
Rev. C

Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007,

Note: 1 Div. = (Div. x 2.3942 + 0.9710) x 9.81 N; Calibrated Date May 23, 2013.

Italian-Thai Development PCL.


14 of 35

1 July 2013

Page

MRT Blue Line Extension Project


Works

Contract 1: Underground Civil


Hua Lamphong Sanam Chai

Section

Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.

C
Completed by Site Engineer

Agreed by QC

Name :__________________________________

ER

Name :_______________________________

Witnessed Point-Optional by : __________________

)
Engineer

)
Engineer

Date : __________________________________

Date : _______________________________

Date : _____________________________________

Primary Grouting Shift Report

Location: West Bound / East Bound

Previous Ring Excavation

Date: .

Grouting Time

Ring
No.
Ring No.

Time Finished

Italian-Thai Development PCL.


35

Start

Finished

Day Shift / Night Shift

Inspector:

Position of
Injection hole

Grouting Pressure
(2-3.5 kgf/cm 2)
1

1 July 2013

Visual Observation
hole Position
6

Taking Sample

Remark

Page 14 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai Section

Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev. C

(Form No. MS/T007/2, Rev. C)

Italian-Thai Development PCL.

1 July 2013

Page 15 of 35

MRT Blue Line Extension Project


Works

Contract 1: Underground Civil


Hua Lamphong Sanam Chai

Section

Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.

Secondary Grout Material Test


(Form No. MS/T007/3, Rev. C)
Mixing Date:

Time:

Tunnel : WB / EB

No

Test ltem

Specification

Specific Gravity

Set ting

Consistency

Test Result

Ring No________

Judgment

Test Standard

Remark

Yes / No

ASTM D 4380-84
(Reapproved 2001),

Liquid A

Yes / No

ASTM C 940-98 A

Liquid A

Yes / No

ASTM C939 02

Liquid A

1.35
0.02g/cm 3
0-5% (After
1 hour)
< 15
seconds

1 hour

1.
2.
3.
Avg.

Yes / No

Yes / No

2.
3.
Avg.

35 days

1.
2.

ASTM C 109-02

3.
Avg.

Yes / No

Yes / No

1.5 N/mm. 2

Yes / No

1.
42 days

Compressive Strength Test

24 hour

1.

2.
3.
Avg.

49 days

1.
2.
3.
Avg.

Completed by Site Engineer

Italian-Thai Development PCL.


35

Agreed by QC

1 July 2013

See note

ER

Page 16 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
A

Name :___________________
(

Name :___________________
)

Engineer
Date : _____________________

)
Engineer

Witnessed Point-Optional by :
__________
(
)

Date : _____________________
Date : ___________________________

Note: 1 Div. = (Div. x 2.3942 + 0.9710) x 9.81 N Calibrated Date May 23, 2013.

Italian-Thai Development PCL.


35

1 July 2013

Page 17 of

MRT Blue Line Extension Project


Works

Contract 1: Underground Civil


Hua Lamphong Sanam Chai

Section

Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.

Secondary Grouting Shift Report


Location: West Bound / East Bound

Date: .

Day Shift / Night Shift

Inspector:

(Form No. MS/T007/4, Rev. C)

No.

Ring No.

Grout Hole No.

Max Pressure

Grout Volume

Start Time

Finish Time

Remarks

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16

Italian-Thai Development PCL.

1 July 2013

Page 16 of 35

MRT Blue Line Extension Project


Works

Contract 1: Underground Civil


Hua Lamphong Sanam Chai

Section
C

Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.

Completed by Site Engineer


Name :__________________________________

Agreed by QC
Name :_______________________________

Witnessed Point-Optional b

)
Engineer

Date : __________________________________

)
Engineer

Date : _______________________________

Date : _________________

Attachment A
Grouting Material for shield Tunneling Work: Proposal
for Mix Design and Testing Method

Italian-Thai Development PCL.


35

1 July 2013

Page 17 of

MRT Blue Line Extension Project


Works

Contract 1: Underground Civil


Hua Lamphong Sanam Chai

Section

Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.

1.

Introduction
This document was prepared to present the design approach and the testing
method of the grouting material that will be used for shield tunneling Hua lamphong
- Sanam Chai Section In order to secure the maximum effect of filling in the void
between the excavated profile and the permanent linings to the underground
works, thyrotrophic -gel grouting material is proposed. A thyrotrophic-gel grouting
material provides enough strength against the ground pressure and the recovery of
fluidity of the grouting material within one hour after grouting this ensuring a
continuous and impermeable void filling. The required properties of thyrotrophic
-gel grouting material are:

1.1

Non shrinkage after grouting void.

1.2

High resistance to underground water before setting.

1.3

High controllability of grout flow.

1.4

Suitability for along distance pumping.

1.5

No separation of solid material from solution during storing and


pumping.

Specification
Following are the specifications of properties of the thyrotrophic-gel grouting
material for Tunnel Works to secure the maximum effects.
2.1

Gel (Setting) Time of Liquid A and Liquid B


Gel Time is specified between 4 and 12 seconds
Grouting material will be exposed to ground water during grouting while it
has fluidity. If the gel time is too long, the grouting material will be diluted
and lose the expected properties. Conversely, if the gel time is too short,
the void will not be fully filled because the grouting material can not be
flown from the grouting point to the whole void. The resulting insufficient
grouting cause round settlement and poor water tightness.
From the above points, the most appropriate gel time is specified between 4
and 12 seconds.

2.2

Bleeding Rate of Liquid A


The bleeding rate shall be less than 5% at 1 hour after mixing
Grouting material with high bleeding rate does not have long usable life
because much bleeding cause separation of grouting material and blockage
of Liquid A in the pipeline from the grouting plant to tunneling face.

Italian-Thai Development PCL.


35

1 July 2013

Page 18 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

12.3

Consistency (Flow Rate) of Liquid A in P-Type Funnel Test


Consistency of Liquid A shall not be greater than 11 seconds If Liquid A has
high consistency, it may cause a blockage. The maximum value of the
consistency of Liquid A in P-Type funnel is specified as 11 second.

2.4

Compressive Strength
The designed compressive strength is shown as below:
Table-1 Required compressive Strength

2.5

Curing Time

Compressive Strength

Mixing after 1 hour

0.03 N/mm 2

Mixing after 1 day

0.4 N/mm 2

Mixing after 7 days

0.8 N/mm 2

Mixing after 28 days

1.5 N/mm 2

Usable Life of Liquid A


Usable life of Liquid A shall be minimum 24 hours for long distance pumping
from the mixing plant on ground to tunneling face.

3.

Proposed Mix Design


The mix proportion of the thyrotrophic-gel grouting material for Tunnel Westbound
and Eastbound is proposed as below.
Table Mix Design
Solution

Material

Quantity (per 1 m 3 mixed grout)

Liquid A

Cement

240 kg

Bentonite

30 kg

Water

830 liter

Stabiliser

2.4 kg

Special Sodium Silicate

80 liter

Liquid B

This final mix design is subject to laboratory test before actual carried out.

Italian-Thai Development PCL.


35

1 July 2013

Page 19 of

MRT Blue Line Extension Project


Works

Contract 1: Underground Civil


Hua Lamphong Sanam Chai

Section

Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.

4.

Testing Method
Trial mixing and the grouting mix tests for the grouting material to be used for
Tunnel Works are carried out as follows.
4.1

Liquid A mixing procedure


We were separated liquid of cavity grouting to 2 parts, one part is Liquid A
component, betonies, stabilizer and water, another part is Liquid B. It is
accelerator. The density of Liquid A will be measured by volume of weight,
actual measured density and theoretical density should be compared.
4.1.1

4.1.2

4.2

Equipment
4.1.1.1

Electric Balance.

4.1.1.2

Hand Mixer.

4.1.1.3

Bucket of 20 litre.

Procedure
4.1.2.1

Put water in bucket 20 litre amount according to design


mixed.

4.1.2.2

Put betonies in bucket mix by hand mixing, start stop


watch.

4.1.2.3

At time 1.30 minutes put cement in bucket.

4.1.2.4

At time 2.30 minutes put cement in bucket .

4.1.2.5

Mix grout until 3 minutes stop mixing and used Liquid A in


other testing.

Measurement of Liquid A bleeding


Due to keep good pump ability of grout, bleeding of grout material is
unavoidable. Bleeding seams a kind of segregation of mixed grout material.
4.2.1 Equipment
4.2.1.1

Mess cylinder 500 ml.

4.2.1.2

Hand Mixer.

4.2.1.3

Bucket of 20 liter.

4.2.1.4

Stop watch.

Italian-Thai Development PCL.


35

1 July 2013

Page 20 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

4.2.2

Procedure
4.2.2.1

Mixed liquid A in bucket.

4.2.2.2
4.2.2.3

Put Liquid A in mess cylinder 500 ml.


Measure the bled water quantity at one hour later.

4.2.2.4

Bleeding procedure formula is Bleeding percentage = (Bled


water volume (m1.)/500 ml.) *100
Remark

4.3

Limit of Bleeding is defined as 5% and for laboratory


test 2%.

In air entraining type grout the bleeding is less than


ordinary grout.

Measurement of Consistency
4.3.1 Equipment

4.3.2

4.4

4.3.1.1

Bucket of 20 litre.

4.3.1.2

Hand Mixer.

4.3.1.3

Pre pact flow cone.

4.3.1.4

Stop watch.

Procedure
4.3.2.1

Mixed Liquid A in bucket of 20 litre

4.3.2.2

Fill Liquid A in bucket.

4.3.2.3

Discharge grout, stop watch until the grout was empty


record time by sec.

Measurement of gel time


Gel time check is related to the performance of accelerator. It is defined by a
time (see) since start mix liquid A and Liquid B until it become harden (no flow
ability). Gel time is measured by Two cup met hid.
4.4.1 Equipment
4.4.1.1

Beaker of 2000 cc made of plastic w/side hand 2 pieces.

4.4.1.2

Stop watch.

4.4.2 Procedure
Italian-Thai Development PCL.
35

1 July 2013

Page 21 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

4.5

4.4.2.1

Prepare Liquid A (850 cc-950 cc) and Liquid B (50 cc-150


cc) in the beaker.

4.4.2.2

Liquid A pour to Liquid B, start watch and Liquid B pour to


Liquid A repeat this until no flow ability is observed and
measure this time.

4.4.2.3

Record gel time.

Measurement of Compressive Strength


Test cube (5 cm.* 5 cm.) are normally used for this test, 3 test cube are
tested and water curing method is used.
4.5.1 Equipment

4.5.2

4.5.1.1

Beaker of 200 cc. made of plastic w/side hand 2 pieces.

4.5.1.2

Test piece mould for mortar.

4.5.1.3

Compressive strength machine (small capacity 20 kg. More


or less).

4.5.1.4

Electronic balance.

Procedure
4.5.2.1

Prepare Liquid A and Liquid B same quantity as gel time


check.

4.5.2.2

Liquid A pour to Liquid B and Liquid B to Liquid A repeat 2


time and pour Liquid A+B in test piece mould for mortar
before it hardens.

4.5.2.3

Check compressive strength at time 1 hr, 1 day, 7 days, 28


days.

Italian-Thai Development PCL.


35

1 July 2013

Page 22 of

MRT Blue Line Extension Project


Works

Contract 1: Underground Civil


Hua Lamphong Sanam Chai

Section
C

Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.

Italian-Thai Development PCL.


35

1 July 2013

Page 23 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

Measurement of Bleeding

Measurement of Consistency

Italian-Thai Development PCL.


35

1 July 2013

Page 24 of

MRT Blue Line Extension Project


Works

Contract 1: Underground Civil


Hua Lamphong Sanam Chai

Section
C

Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.

Measurement of Specific Gravity

Italian-Thai Development PCL.


35

1 July 2013

Page 25 of

MRT Blue Line Extension Project


Works

Contract 1: Underground Civil


Hua Lamphong Sanam Chai

Section
C

Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.

Measurement of Gel Time

Italian-Thai Development PCL.


35

1 July 2013

Page 26 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

Attachment B
The Laboratory Test Program for Primary and Secondary
Grouting Works

Italian-Thai Development PCL.


35

1 July 2013

Page 27 of

MRT Blue Line Extension Project


Works

Contract 1: Underground Civil


Hua Lamphong Sanam Chai

Section

Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.

Item

Specification

Test Method

Date

Specific Gravity

1.200.02 g/cm 3

Mud Balance

12 June 2012

Bleeding

0.5% (1 hour
after Liquid
A mixing)

Bleeding Test

12 June 2012

Consistency

< 11 seconds

Flow Test

12 June 2012

Gel Time

4.12 seconds

Mix Test

12 June 2012

Compressive

12 June 2012

Compressive

Strength

1 Hour

0.03 N/mm 2

24 Hours

0.4 N/mm 2

7 Days

0.8 N/mm 2

28 Days

1.5 N/mm 2

Strength Test

Place
At the institute
which be inform
and submit at
least 1 month
before test date.
At the institute
which be inform
and submit at
least 1 month
before test date.

At the institute
which be inform
and submit at
least 1 month
before test date.

The Laboratory test Program for Primary and Secondary Grouting Works.

Italian-Thai Development PCL.


35

1 July 2013

Page 28 of

Remark

Liquid A

Liquid A
Liquid A
Liquid A+B

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

Attachment C
ASTM C939-02 Standard Test Method for PreplacedAggregate Concrete (Flow Cone Method)

Italian-Thai Development PCL.


35

1 July 2013

Page 29 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

Italian-Thai Development PCL.


35

1 July 2013

Page 30 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

Italian-Thai Development PCL.


35

1 July 2013

Page 31 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

Italian-Thai Development PCL.


35

1 July 2013

Page 32 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

Italian-Thai Development PCL.


35

1 July 2013

Page 33 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

Italian-Thai Development PCL.


35

1 July 2013

Page 34 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

Italian-Thai Development PCL.


35

1 July 2013

Page 35 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

Attachment D
ASTM D4830-84 (Reapproved 2001) Standard Test
Method for Density of Bentonitic Slurries

Italian-Thai Development PCL.


35

1 July 2013

Page 36 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

Italian-Thai Development PCL.


35

1 July 2013

Page 37 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

Italian-Thai Development PCL.


35

1 July 2013

Page 38 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

Italian-Thai Development PCL.


35

1 July 2013

Page 39 of

MRT Blue Line Extension Project

Contract 1: Underground Civil Works


Hua Lamphong Sanam Chai

Section
Method Statement for Primary and Secondary Grouting Doc No. ITD/BE1/MS/T007, Rev.
C

Italian-Thai Development PCL.


35

1 July 2013

Page 40 of

You might also like