9184
OTHERWISWE KNOWN AS AN ACT PROVIDING FOR THE MODERNIZATION,
STANDARDIZATION AND REGULATIONS OF THE PROCUREMENT ACTIVITIES OF
THE GOVERNMENT AND OTHER PURPOSES
GENERAL COVERAGE
All procurement activities from procurement planning up to contract implementation and
termination, except for the following:
a)
b)
Observers
The observers shall come from organization duly registered with the SEC and should meet the
following criteria:
1.
2.
3.
Knowledge and expertise in procurement or in the subject matter of the contract to be bid.
Absence of direct or indirect interest in the contract to be bid out.
Any other criteria that may be determined by the BAC.
BAC Secretariat will serve as the main support unit of the BAC and shall have the following
functions:
1.
2.
3.
4.
5.
Pre-procurement Conference
Advertisement / Posting
Eligibility Screening
Pre-Bid Conference
Submission and Receipt of Bid
Bid Evaluation
Post-Qualification
Award of Contract
1.
Pre-procurement Conference
Prior to advertisement or the issuance of the Invitation to Apply for Eligibility and to Bid, the
BAC, through it Secretariat, shall call for a pre-procurement conference, to;
A.
B.
C.
D.
E.
Ensure that the procurement is in accordance with the project and annual procurement plans;
Determine the readiness of the procurement at hand;
Review modify and agree on the criteria for eligibility screening;
Review, modify and agree on the criteria for the evaluation of bids/proposals;
Clarify that the specifications and other terms in the bidding documents are minimum
requirements;
F. Reiterate and emphasize the importance of confidentiality during the bid evaluation process,
and applicable sanctions and penalties;
The holding of a pre-procurement conference may not be required for small procurements, i.e.,
procurement of infrastructure projects costing five million pesos (P5, 000,000.00) and below.
2.
Advertisement / Posting
A.
For infrastructure projects, the bidding documents shall be issued within thirty (30) calendar
days from last day of the period of advertising and/or posting of Invitation to Apply for
Eligibility and to Bid, and the opening of bids shall be conducted within the following
periods from the last day of the issuance of the bidding documents.
Estimated Contract Cost (PhP)
Up to twenty five (25) million
Above twenty five (25) million
up to fifty (50)
Above fifty (50) million up to
two hundred (200)
Above two hundred (200) million
Period
15 to 30 calendar days
15 to 45 calendar days
30 to 60 calendar days
60 to 90 calendar days
In case of simple or repetitive or standardized works where time is of the essence, the head
of the procuring entity may reduce the above term of issuance to not less than fifty percent
(50%) of the periods indicated above.
Provided, however, That the periods for conducting eligibility check, pre-bid conference and
the issuance of the bidding documents shall be followed.
3. Eligibility Screening
A.
Eligibility Criteria
1.
2.
3.
In the case of a small A and B contractors without similar experience on the contact to be
bid, they may be allowed to bid if the cost of such contract is not more than 50% of their
registration particular for such category. The allowable range of contract cost per PCAB
registration of contractor shall be:
Category
Small A
Small B
Medium A
Registration Particular
Allowable Range of Contract Cost
(in Million Pesos)
Up to 0.5
Up to 10
Up to 50
Medium B
Large A
Large B
Up to 100
Up to 150
Less than or above 150
4.
f.
g.
h.
i.
i.1. Availability of the prospective bidders key personnel, such as project managers,
project engineers, materials engineers and foremen, that may be used for
constructing contracts; and
i.2. Availability of equipment that he owns, has under lease, and/ or has under
purchase agreements, that may be used for constructing contracts, provided that
the ownership of equipment is not a requisite for eligibility.
j. The prospective bidders audited financial statement, stamped received by the
BIR or its duly accredited and authorized, institution, for the immediately preceding
calendar year, showing, among other, the prospective bidders total and current assets
and liabilities.
k. A sworn affidavit of compliance with the Disclosure Provision of RA 9184 in
relation to other provision of R.A. 3019.
l. Tax Clearance Certificate from BIR.
Class B Documents
a.
b.
The prospective bidder or its duly authorized shall certify under oath that each of the documents
submitted in satisfaction of the eligibility requirements is an authentic and original copy, or a
true and faithful reproduction or copy of the original, complete, and that all statement and
information provided therein are true and correct.
4.
Pre-Bid Conference
For contracts to be bid with an a approved budget of P 1,000,000.00 or more, the BAC shall
convene at least one (1) pre-bid conference to clarify and/ or explain any requirements, terms,
conditions and specifications stipulated in the bidding documents.
For contracts to be bid costing less than P1, 000,000.00, pre- bid conference may be conducted
at the discretion of the BAC. Subject to the approval of the BAC, a pre bid conference may
also conducted upon written request of any prospective bidder.
The pre-bid conference shall be held at least twelve (12) calendar days before the deadline for
the submission and receipt of bids. However, attendance of the bidders shall not be mandatory.
The pre-bid conference shall discuss, among other things, the technical and financial
components of the contract to be bid. The minutes of the pre-bid conference shall be recorded
and made available to all participants not later than three (3) calendar days after the pre-bid
conference.
Request for clarification(s) must be in writing and submitted to the BAC at least ten (10)
calendar days before the deadline set for the submission and receipt for bids. The BAC shall
response to the said request by issuing a Supplement/ Bid Bulletin, at last seven (7) calendar
days before the deadline for the submission and receipt of bids.
Any Supplemental/ Bid Bulletin issued by the BAC shall also be posted on the website of
procuring entity concerned, if available, and on the G-EPS.
5.
In two (2) separate sealed bid envelopes, the first containing the technical
component of the bid.
Bids submitted after the deadline shall not be accepted by the BAC.
The first envelope (Technical Proposal) shall contain the following technical information/
documents, at the least:
1.
2.
3.
4.
5.
6.
7.
1.
Bid Opening
The BAC shall open the bids at the time, date and place specified in the Invitation to Apply for
Eligibility and to Bid and the bidding documents. The bidders or their duly authorized
representative may attend the opening of bids. All members of the BAC or their duly authorized
representatives who are present during bid opening shall initial every page of the original copies
of all bids received and opened. The minutes of the bid opening shall be made available to the
public upon written request and payment of a specified fee.
6.
Bid Evaluation
The purpose of bid evaluation is to determine the Lowest Calculated Bid. This bid shall be
subject to post-qualification to determine its responsiveness to the eligibility and bid
requirements. If after post-qualification the Lowest Calculated Bid is determine to be postqualified it shall be considered to the bidder.
Bid Evaluation shall be determined in two steps :
The detailed evaluation of the financial component of the bids, to established
the correct calculated prices of bids; and
The ranking of the total bid prices as so calculated from the lowest to the
highest. The bid with the lowest price shall be identified as the Lowest Calculated Bid
Post-Qualification
The post-qualification shall verify, validated and ascertain all statements made and documents
submitted by the bidder with Lowest Calculated Bid, using non-discretionary criteria. These
criteria shall consider, but shall not be limited to, the following:
a.
1.
2.
3.
4.
Performance Security
Form of Security
Minimum Amount in % of the
Total Contract Price
Cash, certified
check, cashiers check,
Five percent (5%)
Managers check, bank
draft or irrevocable letter
of credit.
Bank Guarantee
Ten percent (10% )
Surety bond,
Thirty percent (30%)
callable on demand
Foreign
One hundred percent (100%)
government guarantee
Warranty
Defects/Liability Period
Warranty Period
1 Year
Project
Completion
2 to 15 Years
Final
Acceptance
After final acceptance of the project by the Government, the contractor shall be held responsible
for structural defects and/ or failure of the complete projects within the following warranty
periods from final acceptance, except those occasioned by force majeure and those caused by
other parties:
Other Structures: Two (2) years. Bailey and wooden bridges, shallow
wells, spring development, and other similar structures.
In cases where structural defects and/ or failure arise during the warranty period the following
persons/ parties shall be held liable:
Contractor - where structural defects and/ or failure arise due to faults attributable to
improper construction use of inferior quality/ substandard materials, and any violation of the
contract plans and specification, the contractors shall be held liable.
Consultant where structural defects and/ or failures arise due to faulty and/ or
inadequate design and specification as well as construction supervision, then the consultant
who prepared the design or undertook construction supervision for the project shall be held.
Third Parties Third parties shall be held liable in case were structural defects/
failure are caused by work undertaken by them such as leaking pipes, digging/ excavations,
underground cables and electrical wires, underground cables and electrical wires,
underground cables and the applicable warranty to such structure should be levied to third
parties for their construction or restoration works.
Users in case where structural defects/ failures are due to abuse/ misuse by the end
user of the constructed facility and/ or non-compliance by a user with the technical design
limits and/ or intended purpose of the same, then the user concerned shall be held liable.
The term Structural Defects shall mean faults/ flaws/ deficiencies in one or more key
structural elements of the competed elements of the project, which may lead to structural failure
of the completed elements or structure.
The term Structural Failures is defined as an occurrence where one or more key structural
elements in an infrastructure facility fails or collapses, thereby rendering the facility or part
thereof incapable of withstanding the design loads, and / or endangering the safety of the users
or the general public.
Bidding for Provincial Projects
Within five (5) years from the effectively of the Act, a contractor who participates in the bidding
of provincial priority programs and infrastructure projects whose principal office is within the
same province, and who submits the Lowest Calculated Bid made by a contractor with principal
office outside the said province, shall be given forty-eight (48) hours from the receipt of written
advice from the BAC to match in writing the Lowest Calculated Bid. Matching shall be through
appropriate adjustments in his unit bid prices without changing the Scope of Work and work
items prescribed by the procuring entity in the bidding documents.
CONTRACT IMPLEMENTATION
Variation Orders - are change orders or extra work orders which should not exceed 10% of the
original project cost.
Variation Orders beyond 10% shall either be subjected to another contract to be bid if the works are
separable from the original contract or if urgently necessary to complete the original scope of work,
be authorized by the head of the procuring entity but not more than 20% subjected to guidelines by
GPPB, but with appropriate sanction to the designer, consultant or official responsible for the
original design.
Supplemental agreement is no longer allowed.
Liquidated Damages shall be imposed for delays in completion of work but Incentive Bonus shall
not be allowed.