Professional Documents
Culture Documents
Question : 07
The following data have been collected for a British health care IT project for
Two-week reporting periods 2 through 12. Compute the SV, CV, SPI, and CPI
for each period. Plot the EV and the AC on the summary graph provided. Plot
The SPI, CPI, and PCIB on the index graph provided. (You may use your own
Graphs. What is your assessment of the project at the end of period 12?
SOLUTION :
By the end of period 2:
Since task 1 is half completed, EV(1) = 50% of PV(1)Total = 0.5 * 8 = 4.
CV(1) comes to be = EV(1) AC(1) = 4 4 = 0.
SV(1) is = EV(1) PV(1)Period(2) = 4 4 = 0.
By the end of period 4:
Since task 1 is done , EV(1) comes to be = PV(1)Total = 8.
CV(1) = EV(1) AC(1) = 8 10 = -2.
SV(1) = EV(1) PV(1)Period(4) = 8 8 = 0.
By the end of period 6:
Since task 1 is Fully done, EV(1) = PV(1)Total = 8.
CV(1) = EV(1) AC(1) = 8 10 = -2.
SV(1) = EV(1) PV(1)Period(6) = 8 8 = 0.
Since task 2 is 1/4 complete, EV(2) = 25% of PV(2)Total = 0.25 * 40 = 10.
CV(2) comes to be = EV(2) AC(2) = 10 15 = -5.
SV(2) = EV(2) PV(2)Period(6) = 10 10 = 0.
AS task 3 is now 33% complete, EV(3) = 33% of PV(3)Total = 0.33 * 30 = 9.9.
CV(3) = EV(3) AC(3) = 9.9 12 = -2.1.
SV(3) = EV(3) PV(3)Period(6) = 9.9 10 = -0.1.