REV.0
DATE:04/09/2016
METHODSTATEMENTFORINSTALLATION
OFABOVEGROUNDDRAINAGEPIPES
ANDFITTINGS
Page1of8
PROJECT
:RESTAURANTFITOUTWORKSATCURVEHOTEL
CLIENT
CONSULTANT
:MR.IBRAHIMALMISNAD
:MZPWLL.
MAINCONTRACTOR :INTERSPACE(AsubsidiaryofGulfContractingCompany)
METHODSTATEMENTFORINSTALLATIONOFABOVEGROUND
DRAINAGEPIPESANDFITTINGS
REV0
REVNO
INITIALISSUE
JMBARBASTRO
MRMARAIS
MRELIERAHAL
ALMISNAD
04/09/2016
SUBJECT OF THE
AMENDMENT
PREPAREDBY
ELECQATAR
REVIEWEDBY
INTERSPACE
APPROVED
BYMZP
APPROVEDBY
CLIENT
DATE
DOCNO:AM/ISP/I16021/MSDR001
REV.0
DATE:04/09/2016
METHODSTATEMENTFORINSTALLATION
OFABOVEGROUNDDRAINAGEPIPES
ANDFITTINGS
Page2of8
TableofContents
1. Purpose ...................................................................................................................................... 3
2. Scope of Works ......................................................................................................................... 3
3. Responsible Persons/Site Organization for Health and Safety Control ................................ 3
4. Health and Safety risks and Controls ...................................................................................... 3
4.1.
4.2.
5.1
11.2.
Delivery Briefing:................................................................................................................... 7
11.3.
12. Attachments............................................................................................................................... 7
13. Risk Assessment ....................................................................................................................... 8
DOCNO:AM/ISP/I16021/MSDR001
REV.0
DATE:04/09/2016
METHODSTATEMENTFORINSTALLATION
OFABOVEGROUNDDRAINAGEPIPES
ANDFITTINGS
Page3of8
1. Purpose
ThepurposeofthisMethodStatementistooutlinetheworktobeundertakenbyElecQatar
fortheinstallationofabovegrounddrainagepipesandfittingsforCurveRestaurant.
This activity should be performed strictly in compliance with the Safety Regulations in
conjunctionwithISPSafetypoliciesandprojectsapplicablestandards.
2. ScopeofWorks
The scope of works covered by this Method Statement will involve material delivery,
coordinationwithconsultant,siteinstallationandEngineersinspection.
This Method Statement confirms that the installation of above ground drainage pipes and
fittingsbyElecQatarwillbeexecutedinlinewiththeinformationprovidedbytheapproved
drawings,specifications,approvedmaterialssubmittalsandscheduleofworks.
3. ResponsiblePersons/SiteOrganizationforHealthandSafetyControl
AiosaProsperBaroElecQatarWll
JuvilBarbastroElecQatarWll
GhangadharanVenkathesanElecQatarWll
SaturdaythroughThursdayworkinghourswillbebetween06:00amto05:00pm.
4. HealthandSafetyrisksandControls
4.1. RiskandControlAssessment
PleaserefertotheattachedcomprehensiveRiskAssessment.
All operatives should be subject to ISP Safety induction before entering the project site. A
safetyinductionlistshallbeatsiteatalltimesavailableinworkingsite.
4.2. PersonalProtectiveEquipment
PPE will be required as per ISP requirements, and shall include, but not be limited to the
followingitems:
HighVisibilityVest
SafetyGlasses/Goggles
DOCNO:AM/ISP/I16021/MSDR001
REV.0
DATE:04/09/2016
METHODSTATEMENTFORINSTALLATION
OFABOVEGROUNDDRAINAGEPIPES
ANDFITTINGS
Page4of8
Safetygloves
EarMuffs
Hardhats
Coveralls
Safetyboots
FaceMasks
5. WorkPlaceAccess/Egress
5.1
SiteInductionandEnteringtheProjectSite
Allemployees/operativesarerequiredtoundergoaSafetyInductionwiththeISPSafety.A
designated gate(s) shall be used when entering the area of operation; operatives should
ensurethatworkersareinductedbeforeworkingonthesite.
6. WorkPlaceLighting
SiteworksSiteworksshallbemainlyunderdaylight.Backgroundlightingshallbeprovidedby
thecontractoringeneralaccessandegressareasaswellasinallworkareas.
Specific task lighting ensuring the provision of standards of lighting required for safe
undertakingofworksisalsoprovidedbycontractor.
7. PlantandEquipment
All personnel carrying out their specific job will be responsible for the tools and
equipmentthattheyuse;
1.Stepladders
2. Toolbox
3. Tapemeasure
4. Drill
5. Cuttinginstrument
6. Hammer
7. Hacksaw
8. Scaffolding
9. SpiritLevel
10. Pipejoiner
11. Handtools(ScrewDrivers,MonkeyPliers,CuttingPliers..)
12. TestingTools
Each supervisor shall be responsible in monitoring all tools brought within the
constructionsite.Notools shallbeleftunattendedwithintheworkareas.
DOCNO:AM/ISP/I16021/MSDR001
REV.0
DATE:04/09/2016
METHODSTATEMENTFORINSTALLATION
OFABOVEGROUNDDRAINAGEPIPES
ANDFITTINGS
Page5of8
8. WorkMethodology
This installation methodology is applicable to all above ground drainage pipes and fittings
works.Priortocommencementofwork,coordinationwillbedonewithotherservices.
8.1. InstallationofPipes
a. Marktherouteofabovegrounddrainagepipingonsoffitofslab.Drilltherequired
holesizeanddepthaccordingtothesizeoftheanchorbolts.
b. Determinethelengthofsupportandfixittotheanchorboltsandensureallfixing
threadedrods,angles,andclampsarestraightandsecure.Cutexcesslengthof
threadedrod,paintwithsilverpaintandtiewarningtapetopreventanyinjury.
c. Installthedrainagepipesontothesupports.Ensureproperslopeandgradienti.e.
1in40to1in110aremaintainedforallhorizontalrunsofdrainagepipes.
d. Installallpipesandfittingsasperthefollowingprocedures:
i.
Ensurethatthepipesarecutsquarebeforetheyarejoinedandthatthe
insideofthepipesarefreefromanydebris.
ii.
Clean both surfaces to be joined by dry clean cloth to remove all dirt.
Applysolventcementaspermanufacturer'srecommendation.Insertpipe
intocoupling,withslighttwistingactionanduptofullsocketdepth.
iii.
Removeexcesssolventbyapieceofcloth.
e. Pipesandfittingsthatarepushfittypesaretobeconnectedasfollows:
i.
Lubricatethepipes(cutinsquareandchamfered)aswellasfittingswith
rubberlubricantandpushfittofullsocketdepth.
ii.
Withdrawpipe5mmonwastesystemand1Ommonsoilsystemtoallow
forexpansion.
iii.
Soil fittings with spigot ends should be inserted into sockets to depth
marks engraved on spigots. This procedure automatically allows for
expansion.
f. GradientIslopeshallbemaintainedasshownintheapprovedshopdrawingsand
aspermanufacturer'srecommendation.Forhorizontalventpipesrun,makesure
thatithasanupwardslope.
g. Pipesshallbeinstalledinsuchawaythatitshallbeatthecenterofthesleevesby
installingspacerorinsertbetweenpipeandsleeves.Detailsofthesleeves(type
ofmaterial,clearancebetweenpipeandsleeve,packingmaterials,etc.)shallbe
indicatedintheapprovedshopdrawings.
h. RaiseWIRforeverycompletedsectionofworkpriortoproceedtothenextcourse
ofactivity.
DOCNO:AM/ISP/I16021/MSDR001
REV.0
DATE:04/09/2016
METHODSTATEMENTFORINSTALLATION
OFABOVEGROUNDDRAINAGEPIPES
ANDFITTINGS
Page6of8
8.2. GravityTestingofDrainagePiping
a. Hydro test of piping will be carried out after completing the installation of
horizontalandriserpipesasperfollowingprocedure.
i.
TestDrainageandventpipingoncompletionofroughinginforleakage.
ii.
Installdrainoutletatthelowestpointofthedrainagepiping.
iii.
Closeopeninginpipingsystemandfillwithwatertopointofoverflow.
iv.
For15minutes,observesthelevelofwater,levelmustnotdrop.
v.
Inspectjointsifanyleakage.Ifanyleaksaredetected,repairthelaking
portionpriortoproceedingfurther.
vi.
Afterrectificationofanyleaks.Repeatthetestingprocedures.
vii.
Thestarttimeofgravitytesttoberecordedandthelevelshouldbeheld
foraminimumof2hours.
viii.
Alltesttoberecorded.
9. HazardousMaterialsandSubstances
RefertoattachedRiskAssessment
10. WasteManagement
a. After installation is complete, contractors will ensure work area is free of any
rubbish/debristhathadaccumulatedthoughtheinstallationprocess.
b. Contractors will ensure that floor is free of any dust that will interfere with the
paintingprocess.
c. Afterinstallationisapproved,contractorswillkeepallplantmaterialandtoolsaway
fromwallandceilingtoprotectfromanypossibleandtomaintainfreeaccessinthe
eventofanemergency.
11. SpecialControlMeasures
AlloperativesshallstrictlyadherewiththeISPSafetyregulations.
11.1.
MethodStatementandRiskAssessmentBriefing:
Allpersonneldirectlyinvolvedwiththeoperationwillbebriefedonthecontent
of the method statement and risk assessment. In particular, the access
arrangementstosite,emergencyarrangementsandkeyrisksassociatedwith
theoperationwillbelookedat.
DOCNO:AM/ISP/I16021/MSDR001
11.2.
REV.0
DATE:04/09/2016
METHODSTATEMENTFORINSTALLATION
OFABOVEGROUNDDRAINAGEPIPES
ANDFITTINGS
Page7of8
DeliveryBriefing:
Beforearrivalofnewdeliverytositeallpersonneldirectlyinvolvedwiththe
operationswillbe briefed aboutthecontentofthedelivery andthe related
installationplan.
DeliveryPaperworkandInstallationDrawingsarepartofthedeliveryandwill
be reviewed and discussed before the start of any new activities. The Store
Keeperisinchargeinmakingsurethatproperrecordsarekeptandmaterials
arestoredpermanufacturersrecommendation.
11.3.
DailysafetyTalkInstructionsToolboxtalk:
Everydayalloperativeswillgettogetherforanupdateonsafetyrequirements,
tool conditions and further planned actions as well as feedback on previous
completedtasks.
AllSitepersonnelwillbegivenatoolboxtalktoexplainallthesafetymeasures
put in place, and to explain the importance of not interfering with any fire
detection devices and firefighting equipment. They will be warned that
interference with any firefighting devices may result in police arrest and
potentiallyseverepenalties.
12. Attachments
ThenameslistedbelowconfirmthereceiptofthisMethodStatementandhavehadthe contents
explainedtothem/understanditandareawareofthesiteES&Hrequirement.
S#
Name
Company
Date
Signature
DOCNO:AM/ISP/I16021/MSDR001
13. RiskAssessment
REV.0
DATE:04/09/2016
METHODSTATEMENTFORINSTALLATION
OFABOVEGROUNDDRAINAGEPIPES
ANDFITTINGS
Page8of8
No
AM-ISP-I16021-RA-DR-001
Activities
Rev
Initial Risk
Rating
Hazards
Overloading of supports
Material
not
as
specification/approved
material submittal
RR
per
5
Installation of Pipes,
fittings and supports
Control Measures
Residual Risk
Risk
Accepted?
RR
Yes
No
Yes
--
Residual Risk
after controls
Rev
Working at height
RA-006
Yes
Yes
--
Monitoring
through daily
inspection,
Toolbox talks.
___________________________________________________________________________________________________________________________________________
Management Risk Assessment
Page 1 of 2
AM-ISP-I16021-RA-DR-001
Rev Date
03-09-2016
No
Owner
Rev
Elec-Qatar Wll
Likelihood
No
Identify Hazards
No
Likelihood x Severity
No
1
2
3
4
Severity
Negligible Hazard will not result in serious injury or illness,
remote possibility of damage beyond minor first aid case
Marginal Hazard can cause illness, injury or equipment
damage, but the results would not be expected to be serious
Critical Hazard can result in serious illness, severe injury,
property and equipment damage
Catastrophic Imminent danger exists, hazard capable of
causing death or illness on a wide scale
Name
Designation
Signatures
Prepared By
A. Baro
HSE (Elec-Qatar)
Methodology
Detail Controls
Calculate Residual Risk Rating with Final Risk
Rating
Severity
Doc Ref No
10
15
20
25
20-25
High Risk
12
16
20
10-16
Medium Risk
12
15
1-9
10
Low Risk
Likelihood
Reviewed By
Approved By
HSE (ISP)
HSE (ISP)
Date
___________________________________________________________________________________________________________________________________________
Management Risk Assessment
Page 2 of 2