BILL OF QUANTITIES

Bill of Quantity

: PERENCANAAN TEKNIS JALAN PANTAI UTARA JAWA

Package Number

: AP - 03

Package Name

: PERENCANAAN TEKNIS JALAN BEKASI - CIKAMPEK

Province

: JAWA BARAT

Pay

Description

Unit

Item

Estimate

Unit

Total

Quantity

Price

Bid Price

(Rupiah)
a

(Rupiah)
f = (d x e)

DIVISION 1 GENERAL
1.2

Mobilization and Demobilization

Lump sum

1.00

312,330,000.00

Total Bid Price for Division 1 (carry to summary of Bill of Quantities)

312,330,000.00

312,330,000.00

DIVISION 2 DRAINAGE
2.1

Excavation for Drainage Ditches and Waterways

Cu.m

21,505.00

2.2

Mortared Stone Work

Cu.m

262,593.00

2.3 (1)

Reinforced Concrete Pipe Culvert Inside .Diameter < 45 Cm

Ln.m

183,689.00

2.3 (2)

Reinforced Concrete Pipe Culvert Inside, Diameter 45 - 75 Cm

Ln.m

261,146.00

2.3 (3)

Reinforced Concrete Pipe Culvert Inside, Diameter 75 - 95 Cm

Ln.m

717,891.00

2.3 (4)

Reinforced Concrete Pipe Culvert Inside, Diameter 95 - 150 Cm

Ln.m

717,891.00

2.3 (5)

Unreinforced Concrete Pipe Culvert Inside,Diameter 20 - 30 Cm

Ln.m

59,500.00

2.3 (6)

Corrugated Steel Culvert

Tonne

1,267,760.92

2.4 (1)

Porous Drainage or Filter Material

Cu.m

121,761.00

2.4 (2)

Plastic Filter Fabric

Sq.m

13,049.30

2.4 (3)

Perforated Pipe for Subsurface Drainage Works

Ln.m

25,832.99

Total Bid Price for Division 2 (carry to summary of Bill of Quantities)

DIVISION 3 EARTHWORK
3.1 (1)

Common Excavation

Cu.m

19,964.00

3.1 (2)

Rock Excavation

Cu.m

81,674.00

3.1 (3)

Structure Excavation 0 -2 depth

Cu.m

61,183.00

3.1 (4)

Common Excavation 2 - 4 depth

Cu.m

66,987.00

3.1 (5)

Common Exacvation 4 - 6 depth

Cu.m

70,000.00

3.1 (6)

Cofferdam,Shoring,Bracing and Related works

3.1 (7)

Excavation on Existing Asphalt Pavement Material with Cold Milling

Lump sum
Cu.m

Macine
3.1 (8)

Excavation on Existing Asphalt Pavement Material without Cold

Cu.m

Milling Machine
3.1 (9)

Extra for Haulage of Excavated Materials in Excess of 5 Km

3.2 (1)

Common Embankment

Cu.m

38,989.00

3.2 (2)

Selected Embankment

Cu.m

76,624.00

3.2 (3)

Selected Embankment for Swampy Areas(measure by truck volume)

Cu.m

51,567.58

Grade Preparation

Sq.m

2,249.00

3.3

Total Bid Price for Division 3 (carry to summary of Bill of Quantities)

File : 340062358.xls

Cu.m/Km

BILL OF QUANTITIES
Bill of Quantity

: PERENCANAAN TEKNIS JALAN PANTAI UTARA JAWA

Package Number

: AP - 03

Package Name

: PERENCANAAN TEKNIS JALAN BEKASI - CIKAMPEK

Province

: JAWA BARAT

Pay

Description

Unit

Item

Estimate

Unit

Total

Quantity

Price

Bid Price

(Rupiah)
a

(Rupiah)
f = (d x e)

DIVISION 4 PAVEMENT WIDENING AND SHOULDERS


4.2 (1)

Aggregate Class A

Cu.m

164,128.00

4.2 (2)

Aggregate Class B

Cu.m

132,640.00

4.2 (3)

Cement for Soil Cement Base

Tonne

752,401.00

4.2 (4)

Soil Cement Base

Cu.m

34,184.47

4.2 (5)

Single Surface Dressing Aggregate

Sq.m

6,076.63

4.2 (6)

Bituminous Material for Surface Dressing

Litre

4,281.37

4.2 (7)

Prime Coat

Litre

3,561.77

Total Bid Price for Division 4 (carry to summary of Bill of Quantities)

DIVISION 5 GRANULAR PAVEMENT


5.1 (1)

Aggregate Class A

Cu.m

165,918.00

5.1 (2)

Aggregate Class B

Cu.m

153,249.00

5.2 (1)

Aggregate Class C

Cu.m

131,203.00

5.4 (1)

Cement for Soil Cement Base

Tonne

752,400.69

5.4 (2)

Soil Cement Base

Cu.m

39,610.00

Total Bid Price for Division 5 (carry to summary of Bill of Quantities)

DIVISION 6 ASPHALT PAVEMENT


6.1 (1)

Prime Coat

Litre

3,448.00

6.1 (2)

Tack Coat

Litre

4,059.00

6.2 (1)

Single Surface Dressing Aggregate (SST)

Sq.m

737.09

6.2 (2)

Double Surface Dressing Aggregate (DBST)

Sq.m

1,428.84

6.2 (3)

Bituminous Binder Material for Surface Dressing

Litre

4,232.44

6.3 (1)

Sand Sheet Class A (SS-A)

Sq.m

19,386.51

6.3 (2)

Sand Sheet Class B (SS-B)

Sq.m

15,048.48

6.3 (3)

Hot Rolled Sheet - WC (HRS - WC)

Sq.m

25,970.97

6.3 (4)

Hot Rolled Sheet - BC (HRS - BC)

Cu.m

6.3 (5)

Asphaltic Concrete Wearing Course (AC - WC)

Sq.m

34,407.00

6.3 (6)

Asphaltic Concrete Binder Course (AC-BC)

Cu.m

795,711.00

6.3 (7)

Asphaltic Concrete Base Course (AC-BASE)

Cu.m

845,195.29

6.4 (1)

Lasbutag

Sq.m

4,587.55

6.4 (2)

Latasbusir Class A

Sq.m

1,842.93

6.4 (3)

Latasbusir Class B

Sq.m

2,501.04

6.4 (4)

Asbuton Bitumen

Tonne

6.4 (5)

Modifier Bitumen

Tonne

6.4 (6)

Anti-Stripping Agent

Litre

6.5 (1)

Cold Mix Asphalt for Resurfacing

Cu.m

855,349.71

Penetration Macadam Levelling

Cu.m

564,780.04

6.6

Total Bid Price for Division 6 (carry to summary of Bill of Quantities)

File : 340062358.xls

BILL OF QUANTITIES
Bill of Quantity

: PERENCANAAN TEKNIS JALAN PANTAI UTARA JAWA

Package Number

: AP - 03

Package Name

: PERENCANAAN TEKNIS JALAN BEKASI - CIKAMPEK

Province

: JAWA BARAT

Pay

Description

Unit

Item

Estimate

Unit

Total

Quantity

Price

Bid Price

(Rupiah)
a

(Rupiah)
f = (d x e)

DIVISION 7 STRUCTURES
7.1 (1)

Structural Concrete Class K500

Cu.m

728,429.00

7.1 (2)

Structural Concrete Class K400

Cu.m

608,849.00

7.1 (3)

Structural Concrete Class K350

Cu.m

735,811.00

7.1 (4)

Structural Concrete Class K300

Cu.m

556,918.00

7.1 (5)

Structural Concrete Class K250

Cu.m

558,263.00

7.1 (6)

Unreinforced Concrete Class K175

Cu.m

433,419.00

7.1 (7)

Cyclopean Concrete Class K175

Cu.m

401,684.00

7.1 (8)

Concrete Class K125

Cu.m

427,244.00

7.2 (1)

Precast Unit Type I Girder span 16 M

Each

7.2 (2)

Precast Unit Type I Girder span 20 M

Each

7.2 (3)

Precast Unit Type I Girder span 22 M

Each

7.2 (4)

Precast Unit Type I Girder span 25 M

Each

7.2 (5)

Precast Unit Type I Girder span 28 M

Each

7.2 (6)

Precast Unit Type I Girder span 30 M

Each

7.2 (7)

Precast Unit Type I Girder span 31 M

Each

7.2 (8)

Precast Unit Type I Girder span 35 M

Each

7.2 (9)

Strand for Cast In-Situ Post tensioned Concrete Work

7.2 (10)

Precast Hollow Slab span 21 M

7.2 (11)

Diaphragm Concrete Class K350 including Post tensioning work

M3

7.3 (1)

Reinforcing Steel Plain U-24

Kg

7.3 (2)

Reinforcing Steel Plain U-32

Kg

7.3 (3)

Reinforcing Steel Plain U-32

Kg

8,343.00

7.3 (4)

Reinforcing Steel Plain U-39

Kg

7,093.00

7.3 (5)

Reinforcing Steel Plain U-48

Kg

7.3 (6)

Welded Wire Mesh

Kg

7.4 (1)

Structural Steel,Yield Point of 2500 kg/cm2,furnished and Installation

Kg

7.4 (2)

Structural Steel,Yield Point of 2800 kg/cm2,furnished and Installation

Kg

7.4 (3)

Structural Steel,Yield Point of 3500 kg/cm2,furnished and Installation

Kg

7.5 (1)

Erection of Steel Bridge Structures

Kg

7.5 (2)

Transportation of Steel Bridge Materials

7.6 (1)

Grouping of Mini Timber Piles(cerucuk) furnished and driven

Ln.m

7.6 (2)

Untreated Timber Sheet Pile

Sq.m

7.6 (3)

Treated Timber Sheet Pile

Sq.m

7.6 (4)

Structural Steel Sheet Pile

Sq.m

7.6 (5)

Precast Concrete Sheet Pile

Sq.m

7.6 (6)

Untreated Timber Pile, furnished

Cu.m

7.6 (7)

Treated Timber Pile,furnished

Cu.m

7.6 (8)

Steel Pipe Pile

7.6 (9)

Precast Reinforced Concrete Pile Id 40 cm, furnished

Ln.m

192,618.51

7.6 (10)

Precast Prestressed Concrete Pile,furnished

Cu.m

92,651.24

Timber Pile Driven

Ln.m

7.6(13)a

Steel Pipe Pile ,40 cm diameter driven

Ln.m

7.6(13)

Steel Pipe Pile ,50 cm diameter driven

Ln.m

7.6(14)

Steel Pipe Pile ,60 cm diameter driven

Ln.m

7.6(15)

Precast Concrete Pile, 30 cm x 30 cm square or 40 cm diameter

Ln.m

7.6(11)

Kg
Each
7,759.00

Kg

Kg

1,394.78

29,116.10

64,568.69

driven
7.6 (16)

Precast Concrete Pile, 40 cm x 40 cm square or 40 cm diameter

Ln.m

Driven

DIVISI 7 berlanjut ke halaman berikut.

File : 340062358.xls

BILL OF QUANTITIES
Bill of Quantity

: PERENCANAAN TEKNIS JALAN PANTAI UTARA JAWA

Package Number

: AP - 03

Package Name

: PERENCANAAN TEKNIS JALAN BEKASI - CIKAMPEK

Province

: JAWA BARAT

Pay

Description

Unit

Item

Estimate

Unit

Total

Quantity

Price

Bid Price

(Rupiah)
a
7.6 (17)

b
Precast Concrete Pile, 50 cm x 50 cm square or 50 cm diameter

(Rupiah)
f = (d x e)

Ln.m

driven
7.6 (18)

Cast in Place Concrete Pile,60 cm diameter

Ln.m

7.6 (19)

Cast in Place Concrete Pile,80 cm diameter

Ln.m

7.6 (20)

Cast in Place Concrete Pile,100 cm diameter

Ln.m

7.6 (21)

Cast in Place Concrete Pile,120 cm diameter

Ln.m

7.6 (22)

Cast in Place Concrete Pile

Ln.m

7.6 (23)

Additional Price to Prices Nos 7.6(11) ~ 7.6(17) when the Pile is

Ln.m

Executed in the Water Stream


7.6 (24)

Additional Price to Prices Nos 7.6(18) ~ 7.6(22) when the Pile is

Ln.m

Executed in the Water Stream


7.6 (25)

Load Test for diameter pile of to 600 mm

Each

7.6 (26)

Load Test for diameter pile of more than 600 mm

Each

7.7 (1)

Caisson 250 cm diameter,furnished

Ln.m

7.7 (2)

Caisson 300 cm diameter,furnished

Ln.m

7.7 (3)

Caisson 350 cm diameter,furnished

Ln.m

7.7 (4)

Caisson 400 cm diameter,furnished

Ln.m

7.7 (5)

Caisson 250 cm diameter,sunk

Ln.m

7.7 (6)

Caisson 300 cm diameter,sunk

Ln.m

7.7 (7)

Caisson 350 cm diameter,sunk

Ln.m

7.7 (8)

Caisson 400 cm diameter,sunk

Ln.m

Stone Masonry

Cu.m

7.10 (1)

Grouted Rip Rap

Cu.m

94,883.00

7.10 (2)

Non-Grouted Rip Rap

Cu.m

94,883.00

7.10 (3)

Gabions

Cu.m

155,311.75

7.11 (1)

Expansion Joint Torma Type

Ln.m

7.11 (2)

Expansion Joint Seal Rubber Type 1(Gap 21-41 mm)

Ln.m

7.11 (3)

Expansion Joint Seal Rubber Type 2(Gap 32-62 mm)

Ln.m

7.11 (4)

Expansion Joint Seal Rubber Type 3(Gap 42-82 mm)

Ln.m

7.11 (5)

Joint Filler for Construction Joint

Ln.m

7.11 (6)

Expansion Joint Steel Angle Type

Ln.m

7.12 (1)

Metal Bearing

Each

7.12 (2)

Elastomeric Bearing Type 1 ( 300 x 350 x 36)

Each

7.12 (3)

Elastomeric Bearing Type 2 ( 350 x 400 x 39)

Each

7.12 (4)

Elastomeric Bearing Type 3 (400 x 450 x 45)

Each

7.12 (5)

Strip Bearing

Ln.m

7.9

7.13

Steel Bridge Ralling

Ln.m

7.14

Bridge Name Plate

Each

7.15 (1)

Demolition of Stone Masonry

Cu.m

7.15 (2)

Demolition of Concrete

Cu.m

7.15 (3)

Demolition of Prestressed Concrete

Cu.m

7.15. (4)

Demolition of Building

Cu.m

7.15 (5)

Demolition of Steel Truss

Sq.m

7.15 (6)

Demolition of Steel Stringer

Ln.m

7.15 (7)

Demolition of Timber Deck

Ln.m

7.15 (8)

Demolition of Timber Bridge

Ln.m

7.15 (9)

Haulage in excess of 5 Km

Ln.m

Total Bid Price for Division 7 (carry to summary of Bill of Quantities)

File : 340062358.xls

7,365,313.30

310,155.00

BILL OF QUANTITIES
Bill of Quantity

: PERENCANAAN TEKNIS JALAN PANTAI UTARA JAWA

Package Number

: AP - 03

Package Name

: PERENCANAAN TEKNIS JALAN BEKASI - CIKAMPEK

Province

: JAWA BARAT

Pay

Description

Unit

Item

Estimate

Unit

Total

Quantity

Price

Bid Price

(Rupiah)
a

(Rupiah)
f = (d x e)

DIVISION 8 REINSTATEMENT AND MINOR WORK


8.1 (1)

Aggregate Class A (for minor work)

Cu.m

8.1 (2)

Aggregate Class B (for minor work)

Cu.m

8.1 (3)

Aggregate for Unsealed Roads (for minor work)

Cu.m

8.1 (4)

Waterbound Macadam (for minor work)

Cu.m

8.1 (5)

Hot Asphaltic Mixture (for minor work)

Cu.m

8.1 (6)

Lasbutag or Latasbusir (for minor work)

Cu.m

8.1 (7)

Penetration Macadam (for minor work)

Cu.m

8.1 (8)

Cold Asphaltic Mixture (for Minor work)

Cu.m

8.1 (9)

Residual Bitumen (for minor work)

Litre

8.2 (1)

Excavation for Shoulder and Other Minor Work

Cu.m

8.2 (2)

Selected Tree Removal Diameter 15 - 30 cm

Each

8.2 (3)

Selected Tree Removal Diameter 30 - 50 cm

Each

8.2 (4)

Selected Tree Removal Diameter 50 - 75 cm

Each

8.2 (5)

Selected Tree Removal Diameter > 75 cm

Each

8.3 (1)

Stabilization by Vegetation

Sq.m

8.3 (2)

Shrubs

Sq.m

8.3 (3)

Trees

Each

8.4 (1)

Pavement Marking (Thermoplastic Type)

Sq.m

8.4 (2)

Pavement Marking ( Non Thermoplastic Type)

Sq.m

80,975.00

8.4 (3)

Road Sign with Reflector of Engineering Grade

Each

362,402.00

8.4 (4)

Road Sign with Reflector of High Intensity Grade

Each

394,302.00

8.4 (5)

Guide Post

Each

52,273.60

8.4 (6)

Kilometre Post

Each

187,945.00

8.4 (7)

Guard Rail

Ln.m

388,274.00

8.4 (8)

Roads Studs

Each

8.4 (9)

Cat Eyes

Each

8.4 (10)

Precast Portland Cement Concrete Curb

Ln.m

8.4 (11)

Re-Used Existing Precast Portland Cement Concrete Curb

Ln.m

8.4 (12)

Block Paving on Sidewalks or Medians

Sq.m

8.5 (1)

Reinstatement of Concrete Bridge Decks

Sq.m

8.5 (2)

Reinstatement of Timber Bridge Decks

Sq.m

8.5 (3)

Reinstatement of Structural Steel Surface Coatings

Sq.m

Total Bid Price for Division 8 (carry to summary of Bill of Quantities)

File : 340062358.xls

164,047.54

BILL OF QUANTITIES
Bill of Quantity

: PERENCANAAN TEKNIS JALAN PANTAI UTARA JAWA

Package Number

: AP - 03

Package Name

: PERENCANAAN TEKNIS JALAN BEKASI - CIKAMPEK

Province

: JAWA BARAT

Pay

Description

Unit

Item

Estimate

Unit

Total

Quantity

Price

Bid Price

(Rupiah)
a

(Rupiah)
f = (d x e)

DIVISION 9 DAYWORK
9.1.(1)

Foreman

Hour

9.1.(2)

Labour

Hour

9.1.(3)

Skilled Labour

Hour

9.1.(4)

Dump Truck 3 - 4 M3

Hour

9.1.(5)

Flat Bed Truck 3-4 M3

Hour

9.1.(6)

Water Tank 3000 - 4500 Litre

Hour

9.1.(7)

Bulldozer 100 - 150 HP

Hour

9.1.(8)

Motor Grader min 100 HP

Hour

9.1.(9)

Wheel Loader 1.0 - 1.6 M3

Hour

9.1.(10)

Crawler Loader 75 - 100 HP

Hour

9.1.(11)

Excavator 80 - 140 HP

Hour

9.1.(12)

Crane on Wheel 10 - 15 Tonne

Hour

9.1.(13)

Tandem Roller 6 - 9 Ton

Hour

9.1.(14)

Vibrator Roller 5 - 8 Tonne

Hour

9.1.(15)

Hand Vibrator 1.5 - 3.0 HP

Hour

9.1.(16)

Peneumatic Tire Roller 8 - 10 Ton

Hour

9.1.(17)

Compresor 4000 - 6500 Ltr/mnt

Hour

9.1.(18)

Concrete Mixer 0.3 - 0.6 M3

Hour

9.1.(19)

Water Pump 70 - 100 MM

Hour

9.1.(20)

Jack Hammer

Hour

Total Bid Price for Division 9 (carry to summary of Bill of Quantities)

DIVISION 10 ROUTINE MAINTENANCE WORK


10.1 (1)

Routine Maintenance of Pavement

Lump sum

10.1 (2)

Routine Maintenance of Shoulder

Lump sum

10.1 (3)

Routine Maintenance of Ditches,Drains,Cutting and Embankment

Lump sum

10.1 (4)

Routine Maintenance of Road Furniture

Lump sum

10.1 (5)

Routine Maintenance of Bridge

Lump sum

Total Bid Price for Division 10 (carry to summary of Bill of Quantities)

File : 340062358.xls

BILL OF QUANTITIES
Bill of Quantity

: PERENCANAAN TEKNIS JALAN PANTAI UTARA JAWA

Package Number

: AP - 02

Package Name

: PERENCANAAN TEKNIS JALAN BEKASI - CIKAMPEK

Province

: JAWA BARAT

Pay

Description

Unit

Item

Estimate

Unit

Total

Quantity

Price

Bid Price

(Rupiah)
a

(Rupiah)
f = (d x e)

DIVISION 1 GENERAL
1.2

Mobilization and Demobilization

Lump sum

1.00

312,330,000.00

Total Bid Price for Division 1 (carry to summary of Bill of Quantities)

312,330,000.00

312,330,000.00

DIVISION 2 DRAINAGE
2.1

Excavation for Drainage Ditches and Waterways

Cu.m

21,505.00

2.2

Mortared Stone Work

Cu.m

262,593.00

2.3 (1)

Reinforced Concrete Pipe Culvert Inside .Diameter < 45 Cm

Ln.m

183,689.00

2.3 (2)

Reinforced Concrete Pipe Culvert Inside, Diameter 45 - 75 Cm

Ln.m

261,146.00

2.3 (3)

Reinforced Concrete Pipe Culvert Inside, Diameter 75 - 95 Cm

Ln.m

717,891.00

2.3 (4)

Reinforced Concrete Pipe Culvert Inside, Diameter 95 - 150 Cm

Ln.m

717,891.00

2.3 (5)

Unreinforced Concrete Pipe Culvert Inside,Diameter 20 - 30 Cm

Ln.m

59,500.00

2.3 (6)

Corrugated Steel Culvert

Tonne

1,267,760.92

2.4 (1)

Porous Drainage or Filter Material

Cu.m

121,761.00

2.4 (2)

Plastic Filter Fabric

Sq.m

13,049.30

2.4 (3)

Perforated Pipe for Subsurface Drainage Works

Ln.m

25,832.99

Total Bid Price for Division 2 (carry to summary of Bill of Quantities)

DIVISION 3 EARTHWORK
3.1 (1)

Common Excavation

Cu.m

3.1 (2)

Rock Excavation

Cu.m

1,964.95

19,964.00
81,674.00

39,228,261.80
-

3.1 (3)

Structure Excavation 0 -2 depth

Cu.m

61,183.00

3.1 (4)

Common Excavation 2 - 4 depth

Cu.m

66,987.00

3.1 (5)

Common Exacvation 4 - 6 depth

Cu.m

70,000.00

3.1 (6)

Cofferdam,Shoring,Bracing and Related works

3.1 (7)

Excavation on Existing Asphalt Pavement Material with Cold Milling

Lump sum
Cu.m

Macine
3.1 (8)

Excavation on Existing Asphalt Pavement Material without Cold

Cu.m

Milling Machine
3.1 (9)

Extra for Haulage of Excavated Materials in Excess of 5 Km

3.2 (1)

Common Embankment

Cu.m

3.2 (2)

Selected Embankment

Cu.m

76,624.00

3.2 (3)

Selected Embankment for Swampy Areas(measure by truck volume)

Cu.m

51,567.58

Grade Preparation

Sq.m

2,249.00

3.3

Total Bid Price for Division 3 (carry to summary of Bill of Quantities)

File : 340062358.xls

Cu.m/Km
193,622.23

38,989.00

7,549,137,125.47

7,588,365,387.27

BILL OF QUANTITIES
Bill of Quantity

: PERENCANAAN TEKNIS JALAN PANTAI UTARA JAWA

Package Number

: AP - 02

Package Name

: PERENCANAAN TEKNIS JALAN BEKASI - CIKAMPEK

Province

: JAWA BARAT

Pay

Description

Unit

Item

Estimate

Unit

Total

Quantity

Price

Bid Price

(Rupiah)
a

(Rupiah)
f = (d x e)

DIVISION 4 PAVEMENT WIDENING AND SHOULDERS


4.2 (1)

Aggregate Class A

Cu.m

164,128.00

4.2 (2)

Aggregate Class B

Cu.m

132,640.00

4.2 (3)

Cement for Soil Cement Base

Tonne

752,401.00

4.2 (4)

Soil Cement Base

Cu.m

34,184.47

4.2 (5)

Single Surface Dressing Aggregate

Sq.m

6,076.63

4.2 (6)

Bituminous Material for Surface Dressing

Litre

4,281.37

4.2 (7)

Prime Coat

Litre

3,561.77

Total Bid Price for Division 4 (carry to summary of Bill of Quantities)

DIVISION 5 GRANULAR PAVEMENT


5.1 (1)

Aggregate Class A

Cu.m

165,918.00

5.1 (2)

Aggregate Class B

Cu.m

153,249.00

5.2 (1)

Aggregate Class C

Cu.m

131,203.00

5.4 (1)

Cement for Soil Cement Base

Tonne

752,400.69

5.4 (2)

Soil Cement Base

Cu.m

39,610.00

Total Bid Price for Division 5 (carry to summary of Bill of Quantities)

DIVISION 6 ASPHALT PAVEMENT


6.1 (1)

Prime Coat

Litre

3,448.00

6.1 (2)

Tack Coat

Litre

4,059.00

6.2 (1)

Single Surface Dressing Aggregate (SST)

Sq.m

737.09

6.2 (2)

Double Surface Dressing Aggregate (DBST)

Sq.m

1,428.84

6.2 (3)

Bituminous Binder Material for Surface Dressing

Litre

4,232.44

6.3 (1)

Sand Sheet Class A (SS-A)

Sq.m

19,386.51

6.3 (2)

Sand Sheet Class B (SS-B)

Sq.m

15,048.48

6.3 (3)

Hot Rolled Sheet - WC (HRS - WC)

Sq.m

25,970.97

6.3 (4)

Hot Rolled Sheet - BC (HRS - BC)

Cu.m

6.3 (5)

Asphaltic Concrete Wearing Course (AC - WC)

Sq.m

6.3 (6)

Asphaltic Concrete Binder Course (AC-BC)

Cu.m

795,711.00

6.3 (7)

Asphaltic Concrete Base Course (AC-BASE)

Cu.m

845,195.29

6.4 (1)

Lasbutag

Sq.m

4,587.55

6.4 (2)

Latasbusir Class A

Sq.m

1,842.93

6.4 (3)

Latasbusir Class B

Sq.m

2,501.04

6.4 (4)

Asbuton Bitumen

Tonne

6.4 (5)

Modifier Bitumen

Tonne

6.4 (6)

Anti-Stripping Agent

Litre

6.5 (1)

Cold Mix Asphalt for Resurfacing

Cu.m

855,349.71

Penetration Macadam Levelling

Cu.m

564,780.04

6.6

Total Bid Price for Division 6 (carry to summary of Bill of Quantities)

File : 340062358.xls

160,529.50

34,407.00

5,523,338,575.31

5,523,338,575.31

BILL OF QUANTITIES
Bill of Quantity

: PERENCANAAN TEKNIS JALAN PANTAI UTARA JAWA

Package Number

: AP - 02

Package Name

: PERENCANAAN TEKNIS JALAN BEKASI - CIKAMPEK

Province

: JAWA BARAT

Pay

Description

Unit

Item

Estimate

Unit

Total

Quantity

Price

Bid Price

(Rupiah)
a

(Rupiah)
f = (d x e)

DIVISION 7 STRUCTURES
7.1 (1)

Structural Concrete Class K500

Cu.m

728,429.00

7.1 (2)

Structural Concrete Class K400

Cu.m

608,849.00

7.1 (3)

Structural Concrete Class K350

Cu.m

735,811.00

7.1 (4)

Structural Concrete Class K300

Cu.m

556,918.00

7.1 (5)

Structural Concrete Class K250

Cu.m

558,263.00

7.1 (6)

Unreinforced Concrete Class K175

Cu.m

433,419.00

7.1 (7)

Cyclopean Concrete Class K175

Cu.m

401,684.00

7.1 (8)

Concrete Class K125

Cu.m

427,244.00

7.2 (1)

Precast Unit Type I Girder span 16 M

Each

7.2 (2)

Precast Unit Type I Girder span 20 M

Each

7.2 (3)

Precast Unit Type I Girder span 22 M

Each

7.2 (4)

Precast Unit Type I Girder span 25 M

Each

7.2 (5)

Precast Unit Type I Girder span 28 M

Each

7.2 (6)

Precast Unit Type I Girder span 30 M

Each

7.2 (7)

Precast Unit Type I Girder span 31 M

Each

7.2 (8)

Precast Unit Type I Girder span 35 M

Each

7.2 (9)

Strand for Cast In-Situ Post tensioned Concrete Work

7.2 (10)

Precast Hollow Slab span 21 M

7.2 (11)

Diaphragm Concrete Class K350 including Post tensioning work

M3

7.3 (1)

Reinforcing Steel Plain U-24

Kg

7,759.00

7.3 (2)

Reinforcing Steel Plain U-32

Kg

7.3 (3)

Reinforcing Steel Plain U-32

Kg

8,343.00

7.3 (4)

Reinforcing Steel Plain U-39

Kg

7,093.00

7.3 (5)

Reinforcing Steel Plain U-48

Kg

7.3 (6)

Welded Wire Mesh

Kg

7.4 (1)

Structural Steel,Yield Point of 2500 kg/cm2,furnished and Installation

Kg

7.4 (2)

Structural Steel,Yield Point of 2800 kg/cm2,furnished and Installation

Kg

7.4 (3)

Structural Steel,Yield Point of 3500 kg/cm2,furnished and Installation

Kg

7.5 (1)

Erection of Steel Bridge Structures

Kg

7.5 (2)

Transportation of Steel Bridge Materials

7.6 (1)

Grouping of Mini Timber Piles(cerucuk) furnished and driven

Ln.m

7.6 (2)

Untreated Timber Sheet Pile

Sq.m

7.6 (3)

Treated Timber Sheet Pile

Sq.m

7.6 (4)

Structural Steel Sheet Pile

Sq.m

7.6 (5)

Precast Concrete Sheet Pile

Sq.m

7.6 (6)

Untreated Timber Pile, furnished

Cu.m

7.6 (7)

Treated Timber Pile,furnished

Cu.m

7.6 (8)

Steel Pipe Pile

1,394.78

7.6 (9)

Precast Reinforced Concrete Pile Id 40 cm, furnished

Ln.m

192,618.51

7.6 (10)

Precast Prestressed Concrete Pile,furnished

Cu.m

92,651.24

Timber Pile Driven

Ln.m

7.6(13)a

Steel Pipe Pile ,40 cm diameter driven

Ln.m

29,116.10

7.6(13)

Steel Pipe Pile ,50 cm diameter driven

Ln.m

7.6(14)

Steel Pipe Pile ,60 cm diameter driven

Ln.m

7.6(15)

Precast Concrete Pile, 30 cm x 30 cm square or 40 cm diameter

Ln.m

64,568.69

7.6(11)

Kg
Each

Kg

Kg

driven
7.6 (16)

Precast Concrete Pile, 40 cm x 40 cm square or 40 cm diameter

Ln.m

Driven

DIVISI 7 berlanjut ke halaman berikut.

File : 340062358.xls

BILL OF QUANTITIES
Bill of Quantity

: PERENCANAAN TEKNIS JALAN PANTAI UTARA JAWA

Package Number

: AP - 02

Package Name

: PERENCANAAN TEKNIS JALAN BEKASI - CIKAMPEK

Province

: JAWA BARAT

Pay

Description

Unit

Item

Estimate

Unit

Total

Quantity

Price

Bid Price

(Rupiah)
a
7.6 (17)

b
Precast Concrete Pile, 50 cm x 50 cm square or 50 cm diameter

(Rupiah)
f = (d x e)

Ln.m

driven
7.6 (18)

Cast in Place Concrete Pile,60 cm diameter

Ln.m

7.6 (19)

Cast in Place Concrete Pile,80 cm diameter

Ln.m

7.6 (20)

Cast in Place Concrete Pile,100 cm diameter

Ln.m

7.6 (21)

Cast in Place Concrete Pile,120 cm diameter

Ln.m

7.6 (22)

Cast in Place Concrete Pile

Ln.m

7.6 (23)

Additional Price to Prices Nos 7.6(11) ~ 7.6(17) when the Pile is

Ln.m

Executed in the Water Stream


7.6 (24)

Additional Price to Prices Nos 7.6(18) ~ 7.6(22) when the Pile is

Ln.m

Executed in the Water Stream


7.6 (25)

Load Test for diameter pile of to 600 mm

Each

7.6 (26)

Load Test for diameter pile of more than 600 mm

Each

7,365,313.30

7.7 (1)

Caisson 250 cm diameter,furnished

Ln.m

7.7 (2)

Caisson 300 cm diameter,furnished

Ln.m

7.7 (3)

Caisson 350 cm diameter,furnished

Ln.m

7.7 (4)

Caisson 400 cm diameter,furnished

Ln.m

7.7 (5)

Caisson 250 cm diameter,sunk

Ln.m

7.7 (6)

Caisson 300 cm diameter,sunk

Ln.m

7.7 (7)

Caisson 350 cm diameter,sunk

Ln.m

7.7 (8)

Caisson 400 cm diameter,sunk

Ln.m

Stone Masonry

Cu.m

7.10 (1)

310,155.00

Grouted Rip Rap

Cu.m

94,883.00

7.10 (2)

Non-Grouted Rip Rap

Cu.m

94,883.00

7.10 (3)

Gabions

Cu.m

155,311.75

7.11 (1)

Expansion Joint Torma Type

Ln.m

7.11 (2)

Expansion Joint Seal Rubber Type 1(Gap 21-41 mm)

Ln.m

7.11 (3)

Expansion Joint Seal Rubber Type 2(Gap 32-62 mm)

Ln.m

7.11 (4)

Expansion Joint Seal Rubber Type 3(Gap 42-82 mm)

Ln.m

7.11 (5)

Joint Filler for Construction Joint

Ln.m

7.11 (6)

Expansion Joint Steel Angle Type

Ln.m

7.12 (1)

Metal Bearing

Each

7.12 (2)

Elastomeric Bearing Type 1 ( 300 x 350 x 36)

Each

7.12 (3)

Elastomeric Bearing Type 2 ( 350 x 400 x 39)

Each

7.12 (4)

Elastomeric Bearing Type 3 (400 x 450 x 45)

Each

7.12 (5)

Strip Bearing

Ln.m

7.9

7.13

Steel Bridge Ralling

Ln.m

7.14

Bridge Name Plate

Each

7.15 (1)

Demolition of Stone Masonry

Cu.m

7.15 (2)

Demolition of Concrete

Cu.m

7.15 (3)

Demolition of Prestressed Concrete

Cu.m

7.15. (4)

Demolition of Building

Cu.m

7.15 (5)

Demolition of Steel Truss

Sq.m

7.15 (6)

Demolition of Steel Stringer

Ln.m

7.15 (7)

Demolition of Timber Deck

Ln.m

7.15 (8)

Demolition of Timber Bridge

Ln.m

7.15 (9)

Haulage in excess of 5 Km

Ln.m

Total Bid Price for Division 7 (carry to summary of Bill of Quantities)

File : 340062358.xls

BILL OF QUANTITIES
Bill of Quantity

: PERENCANAAN TEKNIS JALAN PANTAI UTARA JAWA

Package Number

: AP - 02

Package Name

: PERENCANAAN TEKNIS JALAN BEKASI - CIKAMPEK

Province

: JAWA BARAT

Pay

Description

Unit

Item

Estimate

Unit

Total

Quantity

Price

Bid Price

(Rupiah)
a

(Rupiah)
f = (d x e)

DIVISION 8 REINSTATEMENT AND MINOR WORK


8.1 (1)

Aggregate Class A (for minor work)

Cu.m

8.1 (2)

Aggregate Class B (for minor work)

Cu.m

8.1 (3)

Aggregate for Unsealed Roads (for minor work)

Cu.m

8.1 (4)

Waterbound Macadam (for minor work)

Cu.m

8.1 (5)

Hot Asphaltic Mixture (for minor work)

Cu.m

8.1 (6)

Lasbutag or Latasbusir (for minor work)

Cu.m

8.1 (7)

Penetration Macadam (for minor work)

Cu.m

8.1 (8)

Cold Asphaltic Mixture (for Minor work)

Cu.m

8.1 (9)

Residual Bitumen (for minor work)

Litre

8.2 (1)

Excavation for Shoulder and Other Minor Work

Cu.m

8.2 (2)

Selected Tree Removal Diameter 15 - 30 cm

Each

8.2 (3)

Selected Tree Removal Diameter 30 - 50 cm

Each

8.2 (4)

Selected Tree Removal Diameter 50 - 75 cm

Each

8.2 (5)

Selected Tree Removal Diameter > 75 cm

Each

8.3 (1)

Stabilization by Vegetation

Sq.m

8.3 (2)

Shrubs

Sq.m

8.3 (3)

Trees

Each

8.4 (1)

Pavement Marking (Thermoplastic Type)

Sq.m

164,047.54

8.4 (2)

Pavement Marking ( Non Thermoplastic Type)

Sq.m

80,975.00

8.4 (3)

Road Sign with Reflector of Engineering Grade

Each

362,402.00

8.4 (4)

Road Sign with Reflector of High Intensity Grade

Each

394,302.00

8.4 (5)

Guide Post

Each

52,273.60

8.4 (6)

Kilometre Post

Each

187,945.00

8.4 (7)

Guard Rail

Ln.m

388,274.00

8.4 (8)

Roads Studs

Each

8.4 (9)

Cat Eyes

Each

8.4 (10)

Precast Portland Cement Concrete Curb

Ln.m

8.4 (11)

Re-Used Existing Precast Portland Cement Concrete Curb

Ln.m

8.4 (12)

Block Paving on Sidewalks or Medians

Sq.m

8.5 (1)

Reinstatement of Concrete Bridge Decks

Sq.m

8.5 (2)

Reinstatement of Timber Bridge Decks

Sq.m

8.5 (3)

Reinstatement of Structural Steel Surface Coatings

Sq.m

Total Bid Price for Division 8 (carry to summary of Bill of Quantities)

File : 340062358.xls

BILL OF QUANTITIES
Bill of Quantity

: PERENCANAAN TEKNIS JALAN PANTAI UTARA JAWA

Package Number

: AP - 02

Package Name

: PERENCANAAN TEKNIS JALAN BEKASI - CIKAMPEK

Province

: JAWA BARAT

Pay

Description

Unit

Item

Estimate

Unit

Total

Quantity

Price

Bid Price

(Rupiah)
a

(Rupiah)
f = (d x e)

DIVISION 9 DAYWORK
9.1.(1)

Foreman

Hour

9.1.(2)

Labour

Hour

9.1.(3)

Skilled Labour

Hour

9.1.(4)

Dump Truck 3 - 4 M3

Hour

9.1.(5)

Flat Bed Truck 3-4 M3

Hour

9.1.(6)

Water Tank 3000 - 4500 Litre

Hour

9.1.(7)

Bulldozer 100 - 150 HP

Hour

9.1.(8)

Motor Grader min 100 HP

Hour

9.1.(9)

Wheel Loader 1.0 - 1.6 M3

Hour

9.1.(10)

Crawler Loader 75 - 100 HP

Hour

9.1.(11)

Excavator 80 - 140 HP

Hour

9.1.(12)

Crane on Wheel 10 - 15 Tonne

Hour

9.1.(13)

Tandem Roller 6 - 9 Ton

Hour

9.1.(14)

Vibrator Roller 5 - 8 Tonne

Hour

9.1.(15)

Hand Vibrator 1.5 - 3.0 HP

Hour

9.1.(16)

Peneumatic Tire Roller 8 - 10 Ton

Hour

9.1.(17)

Compresor 4000 - 6500 Ltr/mnt

Hour

9.1.(18)

Concrete Mixer 0.3 - 0.6 M3

Hour

9.1.(19)

Water Pump 70 - 100 MM

Hour

9.1.(20)

Jack Hammer

Hour

Total Bid Price for Division 9 (carry to summary of Bill of Quantities)

DIVISION 10 ROUTINE MAINTENANCE WORK


10.1 (1)

Routine Maintenance of Pavement

Lump sum

10.1 (2)

Routine Maintenance of Shoulder

Lump sum

10.1 (3)

Routine Maintenance of Ditches,Drains,Cutting and Embankment

Lump sum

10.1 (4)

Routine Maintenance of Road Furniture

Lump sum

10.1 (5)

Routine Maintenance of Bridge

Lump sum

Total Bid Price for Division 10 (carry to summary of Bill of Quantities)

File : 340062358.xls

PERHITUNGAN VOLUME PEKERJAAN


PROYEK PERENCANAAN JALAN PANTAI UTARA JAWA
PAKET AP-01

A. Panjang Jalan Yang di Overlay


Jembatan = 10 m
Panjang Jalan
* Perkerasan (7x2 m)
AC - WC (4 cm)
AC - BC (6 cm)
Tack Coat
Prime Coat
AC Base (15 cm)

=
=
=
=
=
=

3,589.469 M

3,579.469 M

14.00
14.00
0.84
9.80

M
M
M2
M2

50,252.57
3,015.15
35,078.80
38,403.75
5,760.56

M2
M3
Liter
Liter
M3

( untuk pelebaran )

B. Perkerasan Untuk Bahu Jalan


Agregat A
AC Binder

=
=

1,927.50 M3
771.00 M3

C. Saluran Samping
- Type 3A
Panjang

Prime Coat =

2,248.75 LITER

1,361.00 M

Beton
Besi
Galian
LC

=
=
=
=

1,197.68
71,860.80
2,994.20
81.66

M3
Kg
M3
M3

- Type 3C

Panjang

4,100.00 M

Batu Kali =
Beton =
Besi
=
Galian =

2,870.00
369.00
22,140.00
10,086.00

M3
M3
Kg
M3

- Median Culvert

Panjang

1,040.00 M

Beton
Besi
Galian
LC

748.80
44,928.00
1,248.00
62.40

M3
Kg
M3
M3

TOTAL
Batu Kali
Beton
Besi
LC
Galian

=
=
=
=
=

2,870.00
2,315.48
138,928.80
144.06
14,328.20

M3
M3
Kg
M3
M3

D. Marka Jalan
- Marka Tepi
=
- Marka Tengah =
Total
=

1,718.15 M2
322.15 M2
2,040.30 M2

E. Kansteen
Kansteen

7,158.94 M

=
=
=
=

BILL OF QUANTITIES
Bill of Quantity

: PERENCANAAN TEKNIS JALAN PANTAI UTARA JAWA

Package Number

: AP - 01

Package Name

: PERENCANAAN TEKNIS JALAN BEKASI - KARAWANG

Province

: JAWA BARAT

Pay

Description

Unit

Item

Estimate

Unit

Total

Quantity

Price

Bid Price

(Rupiah)
a

(Rupiah)
f = (d x e)

DIVISION 1 GENERAL
1.2

Mobilization and Demobilization

Lump sum

1.00

312,330,000.00

Total Bid Price for Division 1 (carry to summary of Bill of Quantities)

312,330,000.00

312,330,000.00

DIVISION 2 DRAINAGE
2.1

Excavation for Drainage Ditches and Waterways

Cu.m

14,328.20

21,505.00

308,127,941.00

2.2

Mortared Stone Work

Cu.m

2,870.00

262,593.00

753,641,910.00

2.3 (1)

Reinforced Concrete Pipe Culvert Inside .Diameter < 45 Cm

Ln.m

183,689.00

2.3 (2)

Reinforced Concrete Pipe Culvert Inside, Diameter 45 - 75 Cm

Ln.m

261,146.00

2.3 (3)

Reinforced Concrete Pipe Culvert Inside, Diameter 75 - 95 Cm

Ln.m

411,509.00

2.3 (4)

Reinforced Concrete Pipe Culvert Inside, Diameter 95 - 150 Cm

Ln.m

717,891.00

2.3 (5)

Unreinforced Concrete Pipe Culvert Inside,Diameter 20 - 30 Cm

Ln.m

59,500.00

2.3 (6)

Corrugated Steel Culvert

Tonne

1,267,760.92

2.4 (1)

Porous Drainage or Filter Material

Cu.m

121,761.00

2.4 (2)

Plastic Filter Fabric

Sq.m

13,049.30

2.4 (3)

Perforated Pipe for Subsurface Drainage Works

Ln.m

25,832.99

Total Bid Price for Division 2 (carry to summary of Bill of Quantities)

1,061,769,851.00

DIVISION 3 EARTHWORK
3.1 (1)

Common Excavation

Cu.m

3.1 (2)

Rock Excavation

Cu.m

3.1 (3)

Structure Excavation 0 -2 depth

Cu.m

3.1 (4)

Common Excavation 2 - 4 depth

Cu.m

3.1 (5)

Common Exacvation 4 - 6 depth

Cu.m

3.1 (6)

Cofferdam,Shoring,Bracing and Related works

3.1 (7)

Excavation on Existing Asphalt Pavement Material with Cold Milling

14,967.46

19,964.00

298,810,371.44

81,674.00
61,183.00
18.09

66,987.00

1,211,553.68

70,000.00

Lump sum
Cu.m

Macine
3.1 (8)

Excavation on Existing Asphalt Pavement Material without Cold

Cu.m

Milling Machine
3.1 (9)

Extra for Haulage of Excavated Materials in Excess of 5 Km

3.2 (1)

Common Embankment

Cu.m

3.2 (2)

Selected Embankment

Cu.m

3.2 (3)

Selected Embankment for Swampy Areas(measure by truck volume)

Cu.m

Grade Preparation

Sq.m

3.3

Total Bid Price for Division 3 (carry to summary of Bill of Quantities)

File : 340062358.xls

Cu.m/Km
2,694.20

38,989.00

105,044,163.80

76,624.00
51,567.58
30,338.75

2,249.00

68,231,848.75

473,297,937.67

BILL OF QUANTITIES
Bill of Quantity

: PERENCANAAN TEKNIS JALAN PANTAI UTARA JAWA

Package Number

: AP - 01

Package Name

: PERENCANAAN TEKNIS JALAN BEKASI - KARAWANG

Province

: JAWA BARAT

Pay

Description

Unit

Item

Estimate

Unit

Total

Quantity

Price

Bid Price

(Rupiah)
a

(Rupiah)

f = (d x e)

DIVISION 4 PAVEMENT WIDENING AND SHOULDERS


4.2 (1)

Aggregate Class A

Cu.m

7,680.75

164,128.00

1,260,626,136.00

4.2 (2)

Aggregate Class B

Cu.m

9,166.13

132,640.00

1,215,795,483.20

4.2 (3)

Cement for Soil Cement Base

Tonne

752,401.00

4.2 (4)

Soil Cement Base

Cu.m

34,184.47

4.2 (5)

Single Surface Dressing Aggregate

Sq.m

6,076.63

4.2 (6)

Bituminous Material for Surface Dressing

Litre

4.2 (7)

Prime Coat

Litre

4,281.37
2,248.75

3,561.77

Total Bid Price for Division 4 (carry to summary of Bill of Quantities)

8,009,526.32

2,484,431,145.52

DIVISION 5 GRANULAR PAVEMENT


5.1 (1)

Aggregate Class A

Cu.m

165,918.00

5.1 (2)

Aggregate Class B

Cu.m

153,249.00

5.2 (1)

Aggregate Class C

Cu.m

131,203.00

5.4 (1)

Cement for Soil Cement Base

Tonne

752,400.69

5.4 (2)

Soil Cement Base

Cu.m

39,610.00

Total Bid Price for Division 5 (carry to summary of Bill of Quantities)

DIVISION 6 ASPHALT PAVEMENT


6.1 (1)

Prime Coat

Litre

38,403.75

3,448.00

132,416,130.00

6.1 (2)

Tack Coat

Litre

35,078.80

4,059.00

142,384,833.78

6.2 (1)

Single Surface Dressing Aggregate (SST)

Sq.m

737.09

6.2 (2)

Double Surface Dressing Aggregate (DBST)

Sq.m

1,428.84

6.2 (3)

Bituminous Binder Material for Surface Dressing

Litre

4,232.44

6.3 (1)

Sand Sheet Class A (SS-A)

Sq.m

19,386.51

6.3 (2)

Sand Sheet Class B (SS-B)

Sq.m

15,048.48

6.3 (3)

Hot Rolled Sheet - WC (HRS - WC)

Sq.m

25,970.97

6.3 (4)

Asphalt Treated Base (ATB)

Cu.m

862,644.00

6.3 (5)

Asphaltic Concrete Wearing Course (AC - WC) t =46 cm

Sq.m

50,252.57

34,407.00

1,729,040,038.36

6.3 (6)

Asphaltic Concrete Binder Course (AC-BC) t = 6 cm

Cu.m

3,786.15

795,711.00

3,012,684,353.67

6.3 (7)

Asphaltic Concrete Base Course (AC-BASE)

Cu.m

5,760.56

845,195.29

4,868,800,292.49

6.4 (1)

Lasbutag

Sq.m

4,587.55

6.4 (2)

Latasbusir Class A

Sq.m

1,842.93

6.4 (3)

Latasbusir Class B

Sq.m

2,501.04

6.4 (4)

Asbuton Bitumen

Tonne

6.4 (5)

Modifier Bitumen

Tonne

6.4 (6)

Anti-Stripping Agent

Litre

6.5 (1)

Cold Mix Asphalt for Resurfacing

Cu.m

855,349.71

Penetration Macadam Levelling

Cu.m

564,780.04

6.6

Total Bid Price for Division 6 (carry to summary of Bill of Quantities)

File : 340062358.xls

9,885,325,648.29

BILL OF QUANTITIES
Bill of Quantity

: PERENCANAAN TEKNIS JALAN PANTAI UTARA JAWA

Package Number

: AP - 01

Package Name

: PERENCANAAN TEKNIS JALAN BEKASI - KARAWANG

Province

: JAWA BARAT

Pay

Description

Unit

Item

Estimate

Unit

Total

Quantity

Price

Bid Price

(Rupiah)
a

(Rupiah)

f = (d x e)

DIVISION 7 STRUCTURES
7.1 (1)

Structural Concrete Class K500

Cu.m

7.1 (2)

Structural Concrete Class K400

Cu.m

7.1 (3)

Structural Concrete Class K350

Cu.m

7.1 (4)

Structural Concrete Class K300

Cu.m

7.1 (5)

Structural Concrete Class K250

Cu.m

7.1 (6)

Unreinforced Concrete Class K175

Cu.m

7.1 (7)

Cyclopean Concrete Class K175

Cu.m

12.56

401,684.00

5,045,151.04

7.1 (8)

Concrete Class K125

Cu.m

146.79

427,244.00

62,715,146.76

7.2 (1)

Precast Unit Type I Girder span 13 M

Each

6.00

18,750,000.00

112,500,000.00

7.2 (2)

Precast Unit Type I Girder span 20 M

Each

7.2 (3)

Precast Unit Type I Girder span 22 M

Each

7.2 (4)

Precast Unit Type I Girder span 25 M

Each

7.2 (5)

Precast Unit Type I Girder span 28 M

Each

7.2 (6)

Precast Unit Type I Girder span 30 M

Each

7.2 (7)

Precast Unit Type I Girder span 31 M

Each

7.2 (8)

Precast Unit Type I Girder span 35 M

Each

7.2 (9)

Strand for Cast In-Situ Post tensioned Concrete Work

7.2 (10)

Precast Hollow Slab span 21 M

7.2 (11)

Diaphragm Concrete Class K350 including Post tensioning work

M3

7.3 (1)

Reinforcing Steel Plain U-24

Kg

7.3 (2)

Reinforcing Steel Plain U-32

Kg

7.3 (3)

Reinforcing Steel Plain U-32

Kg

7.3 (4)

Reinforcing Steel Plain U-39

Kg

7.3 (5)

Reinforcing Steel Plain U-48

Kg

7.3 (6)

Welded Wire Mesh

Kg

7.4 (1)

Structural Steel,Yield Point of 2500 kg/cm2,furnished and Installation

Kg

7.4 (2)

Structural Steel,Yield Point of 2800 kg/cm2,furnished and Installation

Kg

7.4 (3)

Structural Steel,Yield Point of 3500 kg/cm2,furnished and Installation

Kg

7.5 (1)

Erection of Steel Bridge Structures

Kg

7.5 (2)

Transportation of Steel Bridge Materials

7.6 (1)

Grouping of Mini Timber Piles(cerucuk) furnished and driven

Ln.m

7.6 (2)

Untreated Timber Sheet Pile

Sq.m

7.6 (3)

Treated Timber Sheet Pile

Sq.m

7.6 (4)

Structural Steel Sheet Pile

Sq.m

7.6 (5)

Precast Concrete Sheet Pile

Sq.m

7.6 (6)

Untreated Timber Pile, furnished

Cu.m

7.6 (7)

Treated Timber Pile,furnished

Cu.m

7.6 (8)

Steel Pipe Pile

7.6 (9)

Precast Reinforced Concrete Pile Id 40 cm, furnished

Ln.m

192,618.51

7.6 (10)

Precast Prestressed Concrete Pile,furnished

Cu.m

92,651.24

Timber Pile Driven

Ln.m

7.6(13)a

Steel Pipe Pile ,40 cm diameter driven

Ln.m

7.6(13)

Steel Pipe Pile ,50 cm diameter driven

Ln.m

7.6(14)

Steel Pipe Pile ,60 cm diameter driven

Ln.m

7.6(15)

Precast Concrete Pile, 30 cm x 30 cm square or 40 cm diameter

Ln.m

7.6(11)

728,429.00
608,849.00
136.35

735,811.00

100,327,829.85

556,918.00
2,315.48

558,263.00

1,292,646,811.24

433,419.00

Kg
Each
7,759.00
155,796.95

8,343.00

1,299,813,953.85

7,093.00

Kg

Kg

1,394.78

29,116.10

64,568.69

driven
7.6 (16)

Precast Concrete Pile, 40 cm x 40 cm square or 40 cm diameter

Ln.m

Driven

DIVISI 7 berlanjut ke halaman berikut.

File : 340062358.xls

BILL OF QUANTITIES
Bill of Quantity

: PERENCANAAN TEKNIS JALAN PANTAI UTARA JAWA

Package Number

: AP - 01

Package Name

: PERENCANAAN TEKNIS JALAN BEKASI - KARAWANG

Province

: JAWA BARAT

Pay

Description

Unit

Item

Estimate

Unit

Total

Quantity

Price

Bid Price

(Rupiah)
a
7.6 (17)

b
Precast Concrete Pile, 50 cm x 50 cm square or 50 cm diameter

(Rupiah)
f = (d x e)

Ln.m

driven
7.6 (18)a

Precast Concrete Pile, 50 cm diameter furnished

Ln.m

173,800.00

7.6 (18)b

Precast Concrete Pile, 50 cm diameter driven

Ln.m

27,886.33

7.6 (19)

Cast in Place Concrete Pile,80 cm diameter

Ln.m

7.6 (20)

Cast in Place Concrete Pile,100 cm diameter

Ln.m

7.6 (21)

Cast in Place Concrete Pile,120 cm diameter

Ln.m

7.6 (22)

Cast in Place Concrete Pile

Ln.m

7.6 (23)

Additional Price to Prices Nos 7.6(11) ~ 7.6(17) when the Pile is

Ln.m

Executed in the Water Stream


7.6 (24)

Additional Price to Prices Nos 7.6(18) ~ 7.6(22) when the Pile is

Ln.m

Executed in the Water Stream


7.6 (25)

Load Test for diameter pile of to 600 mm

Each

7.6 (26)

Load Test for diameter pile of more than 600 mm

Each

7.7 (1)

Caisson 250 cm diameter,furnished

Ln.m

7.7 (2)

Caisson 300 cm diameter,furnished

Ln.m

7.7 (3)

Caisson 350 cm diameter,furnished

Ln.m

7.7 (4)

Caisson 400 cm diameter,furnished

Ln.m

7.7 (5)

Caisson 250 cm diameter,sunk

Ln.m

7.7 (6)

Caisson 300 cm diameter,sunk

Ln.m

7.7 (7)

Caisson 350 cm diameter,sunk

Ln.m

7.7 (8)

Caisson 400 cm diameter,sunk

Ln.m

Stone Masonry

Cu.m

7.10 (1)

Grouted Rip Rap

Cu.m

94,883.00

7.10 (2)

Non-Grouted Rip Rap

Cu.m

94,883.00

7.10 (3)

Gabions

Cu.m

155,311.75

7.11 (1)

Expansion Joint Torma Type

Ln.m

7.11 (2)

Expansion Joint Seal Rubber Type 1(Gap 21-41 mm)

Ln.m

7.11 (3)

Expansion Joint Seal Rubber Type 2(Gap 32-62 mm)

Ln.m

7.11 (4)

Expansion Joint Seal Rubber Type 3(Gap 42-82 mm)

Ln.m

7.11 (5)

Joint Filler for Construction Joint

Ln.m

7.11 (6)

Expansion Joint Steel Angle Type

Ln.m

7.12 (1)

Metal Bearing

Each

7.12 (2)

Elastomeric Bearing Pad in Place (300x300x60 mm)

Each

7.12 (3)

Elastomeric Bearing Type 2 ( 350 x 400 x 39)

Each

7.12 (4)

Elastomeric Bearing Type 3 (400 x 450 x 45)

Each

7.12 (5)

Strip Bearing

Ln.m

7.9

7.13

Steel Bridge Ralling

Ln.m

7.14

Bridge Name Plate

Each

7.15 (1)

Demolition of Stone Masonry

Cu.m

7.15 (2)

Demolition of Concrete

Cu.m

7.15 (3)

Demolition of Prestressed Concrete

Cu.m

7.15. (4)

Demolition of Building

Cu.m

7.15 (5)

Demolition of Steel Truss

Sq.m

7.15 (6)

Demolition of Steel Stringer

Ln.m

7.15 (7)

Demolition of Timber Deck

Ln.m

7.15 (8)

Demolition of Timber Bridge

Ln.m

7.15 (9)

Haulage in excess of 5 Km

Ln.m

Total Bid Price for Division 7 (carry to summary of Bill of Quantities)

File : 340062358.xls

7,365,313.30

310,155.00

44.00

2,480,000.00

109,120,000.00

12.00

346,995.00

4,163,940.00

2,986,332,832.74

BILL OF QUANTITIES
Bill of Quantity

: PERENCANAAN TEKNIS JALAN PANTAI UTARA JAWA

Package Number

: AP - 01

Package Name

: PERENCANAAN TEKNIS JALAN BEKASI - KARAWANG

Province

: JAWA BARAT

Pay

Description

Unit

Item

Estimate

Unit

Total

Quantity

Price

Bid Price

(Rupiah)
a

(Rupiah)
f = (d x e)

DIVISION 8 REINSTATEMENT AND MINOR WORK


8.1 (1)

Aggregate Class A (for minor work)

Cu.m

8.1 (2)

Aggregate Class B (for minor work)

Cu.m

8.1 (3)

Aggregate for Unsealed Roads (for minor work)

Cu.m

8.1 (4)

Waterbound Macadam (for minor work)

Cu.m

8.1 (5)

Hot Asphaltic Mixture (for minor work)

Cu.m

8.1 (6)

Lasbutag or Latasbusir (for minor work)

Cu.m

8.1 (7)

Penetration Macadam (for minor work)

Cu.m

8.1 (8)

Cold Asphaltic Mixture (for Minor work)

Cu.m

8.1 (9)

Residual Bitumen (for minor work)

Litre

8.2 (1)

Excavation for Shoulder and Other Minor Work

Cu.m

8.2 (2)

Selected Tree Removal Diameter 15 - 30 cm

Each

8.2 (3)

Selected Tree Removal Diameter 30 - 50 cm

Each

8.2 (4)

Selected Tree Removal Diameter 50 - 75 cm

Each

8.2 (5)

Selected Tree Removal Diameter > 75 cm

Each

8.3 (1)

Stabilization by Vegetation

Sq.m

8.3 (2)

Shrubs

Sq.m

8.3 (3)

Trees

Each

8.4 (1)

Pavement Marking (Thermoplastic Type)

Sq.m

8.4 (2)

Pavement Marking ( Non Thermoplastic Type)

Sq.m

2,040.30

80,975.00

165,213,076.30

8.4 (3)

Road Sign with Reflector of Engineering Grade

Each

26.00

362,402.00

9,422,452.00

8.4 (4)

Road Sign with Reflector of High Intensity Grade

Each

8.4 (5)

Guide Post

Each

52,273.60

8.4 (6)

Kilometre Post

Each

187,945.00

8.4 (7)

Guard Rail

Ln.m

388,274.00

8.4 (8)

Roads Studs

Each

8.4 (9)

Cat Eyes

Each

8.4 (10)

Precast Portland Cement Concrete Curb

Ln.m

8.4 (11)

Re-Used Existing Precast Portland Cement Concrete Curb

Ln.m

8.4 (12)

Block Paving on Sidewalks or Medians

Sq.m

8.5 (1)

Reinstatement of Concrete Bridge Decks

Sq.m

8.5 (2)

Reinstatement of Timber Bridge Decks

Sq.m

8.5 (3)

Reinstatement of Structural Steel Surface Coatings

Sq.m

Total Bid Price for Division 8 (carry to summary of Bill of Quantities)

File : 340062358.xls

164,047.54

394,302.00

7,158.94

74,532.00

533,569,967.02

708,205,495.31

BILL OF QUANTITIES
Bill of Quantity

: PERENCANAAN TEKNIS JALAN PANTAI UTARA JAWA

Package Number

: AP - 01

Package Name

: PERENCANAAN TEKNIS JALAN BEKASI - KARAWANG

Province

: JAWA BARAT

Pay

Description

Unit

Item

Estimate

Unit

Total

Quantity

Price

Bid Price

(Rupiah)
a

(Rupiah)
f = (d x e)

DIVISION 9 DAYWORK
9.1.(1)

Foreman

Hour

9.1.(2)

Labour

Hour

9.1.(3)

Skilled Labour

Hour

9.1.(4)

Dump Truck 3 - 4 M3

Hour

9.1.(5)

Flat Bed Truck 3-4 M3

Hour

9.1.(6)

Water Tank 3000 - 4500 Litre

Hour

9.1.(7)

Bulldozer 100 - 150 HP

Hour

9.1.(8)

Motor Grader min 100 HP

Hour

9.1.(9)

Wheel Loader 1.0 - 1.6 M3

Hour

9.1.(10)

Crawler Loader 75 - 100 HP

Hour

9.1.(11)

Excavator 80 - 140 HP

Hour

9.1.(12)

Crane on Wheel 10 - 15 Tonne

Hour

9.1.(13)

Tandem Roller 6 - 9 Ton

Hour

9.1.(14)

Vibrator Roller 5 - 8 Tonne

Hour

9.1.(15)

Hand Vibrator 1.5 - 3.0 HP

Hour

9.1.(16)

Peneumatic Tire Roller 8 - 10 Ton

Hour

9.1.(17)

Compresor 4000 - 6500 Ltr/mnt

Hour

9.1.(18)

Concrete Mixer 0.3 - 0.6 M3

Hour

9.1.(19)

Water Pump 70 - 100 MM

Hour

9.1.(20)

Jack Hammer

Hour

Total Bid Price for Division 9 (carry to summary of Bill of Quantities)

DIVISION 10 ROUTINE MAINTENANCE WORK


10.1 (1)

Routine Maintenance of Pavement

Lump sum

10.1 (2)

Routine Maintenance of Shoulder

Lump sum

10.1 (3)

Routine Maintenance of Ditches,Drains,Cutting and Embankment

Lump sum

10.1 (4)

Routine Maintenance of Road Furniture

Lump sum

10.1 (5)

Routine Maintenance of Bridge

Lump sum

Total Bid Price for Division 10 (carry to summary of Bill of Quantities)

File : 340062358.xls

SUMMARY
Bill of Quantity
Package Number
Package Name
Province
Contract

: PERENCANAAN TEKNIS JALAN PANTAI UTARA JAWA


: AP - 01
: PERENCANAAN TEKNIS JALAN BEKASI - KARAWANG
: JAWA BARAT
:

Division
No

Total
Bid Price
(Rupiah)

Description

General

#NAME?

Drainage

#NAME?

Earthworks

#NAME?

Pavement Widening Shoulders

#NAME?

Granular Pavement

#NAME?

Asphalt Pavement

#NAME?

Structures

#NAME?

Reinstatement and Minor Works

#NAME?

Daywork

#NAME?

10

Routine Maintenance Works

#NAME?

(A)

Sum of Division 1 to 10

#NAME?

(B)

Value Added Tax ( VAT ) = 10% x (A)

#NAME?

(C)

TOTAL BID PRICE = (A) + (B)

#NAME?

Written

BID PRICE COMPONENT CARRIED TO BID

(i) Local Currency Component of Total Bid Price


(% x (A)} + (B)

Written

..

..

..

(ii) Foreign Currency Component of Total Bid Price


(..% x (A)} / Exchange Rate

Written

..

..

Exchange Rate,as specified in the Instructions to Bidders,


used to convert the foreign currency component to Rupiah;

1..(FC) = Rp.

Perencanaan Jalan Pantura Jawa Barat

Jakarta, .2004

(.)
Signature and Seal

Summary of BOQ