You are on page 1of 51

21

Relay Testing and Commissioning


Introduction Electrical type tests Electromagnetic compatibility tests Product s
afety type tests Environmental type tests Software type tests Dynamic validation
type testing Production testing Commissioning tests Secondary injection test eq
uipment Secondary injection testing 21.1 21.2 21.3 21.4 21.5 21.6 21.7 21.8 21.9
21.10 21.11
Primary injection testing 21.12 Testing of protection scheme logic 21.13 Trippin
g and alarm annunciation tests 21.14 Periodic maintenance tests 21.15 Protection
scheme design for maintenance 21.16 References 21.17


21 Relay Testing and Commissioning
21.1 INTRODUCTION The testing of protection equipment schemes presents a number
of problems. This is because the main function of protection equipment is solely
concerned with operation under system fault conditions, and cannot readily be t
ested under normal system operating conditions. This situation is aggravated by
the increasing complexity of protection schemes and use of relays containing sof
tware. The testing of protection equipment may be divided into four stages: i. t
ype tests ii. routine factory production tests iii. commissioning tests iv. peri
odic maintenance tests
21.1.1 Type Tests Type tests are required to prove that a relay meets the publis
hed specification and complies with all relevant standards. Since the principal
function of a protection relay is to operate correctly under abnormal power cond
itions, it is essential that the performance be assessed under such conditions.
Comprehensive type tests simulating the operational conditions are therefore con
ducted at the manufacturer's works during the development and certification of t
he equipment. The standards that cover most aspects of relay performance are IEC
60255 and ANSI C37.90. However compliance may also involve consideration of the
requirements of IEC 61000, 60068 and 60529, while products intended for use in
the EEC also have to comply with the requirements of Directives 89/336/EEC and 7
3/23/EEC. Since type testing of a digital or numerical relay involves testing of
software as well as hardware, the type testing process is very complicated and
more involved than a static or electromechanical relay.
Network Protection & Automation Guide
371

21.1.2 Routine Factory Production Tests These are conducted to prove that relays
are free from defects during manufacture. Testing will take place at several st
ages during manufacture, to ensure problems are discovered at the earliest possi
ble time and hence minimise remedial work. The extent of testing will be determi
ned by the complexity of the relay and past manufacturing experience.
would take 4 years to write the functional type-test specifications, 30 years to
perform the tests and several years to write the test reports that result. Auto
mated techniques/ equipment are clearly required, and are covered in Section 21.
7.2.
Range 0.08 - 4.00In 0.08 - 32In Forward/Reverse/Non-directional -95 to +95 DT/IDMT
0 - 100s IEC Standard Inverse IEC Very Inverse IEC IDMT Time Delay IEC Extremel
y Inverse UK Long Time Inverse Time Multiplier Setting (TMS) 0.025 - 1.2 IEEE Mo
derately Inverse IEEE Very Inverse IEEE IDMT Time Delay IEEE Extremely Inverse U
S-CO8 Inverse US-CO2 Short Time Inverse Time Dial (TD) 0.5 - 15 IEC Reset Time (
DT only) 0 - 100s IEEE Reset Time IDMT/DT IEEE DT Reset Time 0 - 100s IEEE Moder
ately Inverse IEEE Very Inverse IEEE IDMT Reset Time IEEE Extremely Inverse US-C
O8 Inverse US-CO2 Short Time Inverse Table 21.1: Overcurrent relay element speci
fication Element I>1 I>2 Directionality RCA Characteristic Definite Time Delay S
tep Size 0.01In 0.01In 1 0.01s
21.1.3 Commissioning Tests These tests are designed to prove that a particular p
rotection scheme has been installed correctly prior to setting to work. All aspe
cts of the scheme are thoroughly checked, from installation of the correct equip
ment through wiring checks and operation checks of the individual items of equip
ment, finishing with testing of the complete scheme.
0.025
R e l a y Te s t i n g a n d C o m m i s s i o n i n g
21.1.4 Periodic Maintenance Checks These are required to identify equipment fail
ures and degradation in service, so that corrective action can be taken. Because
a protection scheme only operates under fault conditions, defects may not be re
vealed for a significant period of time, until a fault occurs. Regular testing a
ssists in detecting faults that would otherwise remain undetected until a fault
occurs.
0.1 0.01s 0.01s
21.2 ELECTRICAL TYPE TESTS Various electrical type tests must be performed, as f
ollows:
Test 1 Three phase non-directional pick up and drop off accuracy over complete c
urrent setting range for both stages Three phase directional pick up and drop of
f accuracy over complete RCA setting range in the forward direction, current ang
le sweep Three phase directional pick up and drop off accuracy over complete RCA
setting range in the reverse direction, current angle sweep Three phase directi
onal pick up and drop off accuracy over complete RCA setting range in the forwar
d direction, voltage angle sweep Three phase directional pick up and drop off ac
curacy over complete RCA setting range in the reverse direction, voltage angle s
weep Three phase polarising voltage threshold test Accuracy of DT timer over com
plete setting range Accuracy of IDMT curves over claimed accuracy range Accuracy
of IDMT TMS/TD Effect of changing fault current on IDMT operating times Minimum
Pick-Up of Starts and Trips for IDMT curves Accuracy of reset timers Effect of
any blocking signals, opto inputs, VTS, Autoreclose Voltage polarisation memory
21.2.1 Functional Tests

Test 2

21
The functional tests consist of applying the appropriate inputs to the relay und
er test and measuring the performance to determine if it meets the specification
. They are usually carried out under controlled environmental conditions. The te
sting may be extensive, even where only a simple relay function is being tested.
, as can be realised by considering the simple overcurrent relay element of Tabl
e 21.1. To determine compliance with the specification, the tests listed in Tabl
e 21.2 are required to be carried out. This is a time consuming task, involving
many engineers and technicians. Hence it is expensive. When a modern numerical r
elay with many functions is considered, each of which has to be type-tested, the
functional type-testing involved is a major issue. In the case of a recent rela
y development project, it was calculated that if one person had to do all the wo
rk, it
Test 3
Test 4
Test 5 Test 6 Test 7 Test 8 Test 9 Test 10 Test 11 Test 12 Test 13 Test 14
Table 21.2: Overcurrent relay element functional type tests
372
Network Protection & Automation Guide

21.2.2 Rating Tests Rating type tests are conducted to ensure that components ar
e used within their specified ratings and that there are no fire or electric sho
ck hazards under a normal load or fault condition of the power system. This is i
n addition to checking that the product complies with its technical specificatio
n. The following are amongst the rating type tests conducted on protection relay
s, the specified parameters are normally to IEC 60255-6.
seconds. This is carried out between all circuits and case earth, between all in
dependent circuits and across normally open contacts. The acceptance criterion f
or a product in new condition is a minimum of 100M. After a damp heat test the pa
ss criterion is a minimum of 10M. 21.2.7 Auxiliary Supplies Digital and numerical
protection relays normally require an auxiliary supply to provide power to the
on-board microprocessor circuitry and the interfacing optoisolated input circuit
s and output relays. The auxiliary supply can be either a.c. or d.c., supplied f
rom a number of sources or safe supplies - i.e. batteries, UPS, generators, etc.,
all of which may be subject to voltage dips, short interruptions and voltage va
riations. Relays are designed to ensure that operation is maintained and no dama
ge occurs during a disturbance of the auxiliary supply. Tests are carried out fo
r both a.c. and d.c. auxiliary supplies and include mains variation both above a
nd below the nominal rating, supply interruptions derived by open circuit and sh
ort circuit, supply dips as a percentage of the nominal supply, repetitive start
s. The duration of the interruptions and supply dips range from 2ms to 60s inter
vals. A short supply interruption or dip up to 20ms, possibly longer, should not
cause any malfunction of the relay. Malfunctions include the operation of outpu
t relays and watchdog contacts, the reset of microprocessors, alarm or trip indi
cation, acceptance of corrupted data over the communication link and the corrupt
ion of stored data or settings. For a longer supply interruption, or dip in exce
ss of 20ms, the relay self recovers without the loss of any function, data, sett
ings or corruption of data. No operator intervention is required to restore oper
ation after an interruption or dip in the supply. Many relays have a specificati
on that exceeds this requirement, tolerating dips of up to 50ms without operatio
n being affected. In addition to the above, the relay is subjected to a number o
f repetitive starts or a sequence of supply interruptions. Again the relay is te
sted to ensure that no damage or data corruption has occurred during the repetit
ive tests. Specific tests carried out on d.c. auxiliary supplies include reverse
polarity, a.c. waveform superimposed on the d.c. supply and the effect of a ris
ing and decaying auxiliary voltage. All tests are carried out at various levels
of loading of the relay auxiliary supply.
21.2.3 Thermal ithstand The thermal withstand of VTs, CTs and output contact circ
uits is determined to ensure compliance with the specified continuous and shortterm overload conditions. In addition to functional verification, the pass crite
rion is that there is no detrimental effect on the relay assembly, or circuit co
mponents, when the product is subjected to overload conditions that may be expec
ted in service. Thermal withstand is assessed over a time period of 1s for CTs an
d 10s for VTs.
21.2.4 Relay Burden The burdens of the auxiliary supply, optically isolated inpu
ts, VTs and CTs are measured to check that the product complies with its specifica
tion. The burden of products with a high number of input/output circuits is appl
ication specific i.e. it increases according to the number of optically isolated
input and output contact ports which are energised under normal power system lo
ad conditions. It is usually envisaged that not more than 50% of such ports will
be energised in any application.
21.2.5 Relay Inputs Relay inputs are tested over the specified ranges. Inputs in
clude those for auxiliary voltage, VT, CT, frequency, optically isolated digital
inputs and communication circuits.

21.2.6 Relay Output Contacts Protection relay output contacts are type tested to
ensure that they comply with the product specification. Particular withstand an
d endurance type tests have to be carried out using d.c., since the normal suppl
y is via a station battery.
21.2.7 Insulation Resistance The insulation resistance test is carried out accor
ding to IEC 60255-5, i.e. 500V d.c. 10%, for a minimum of 5
21.3 ELECTROMAGNETIC COMPATIBILITY TESTS There are numerous tests that are carri
ed out to determine the ability of relays to withstand the electrical
Network Protection & Automation Guide
373
R e l a y Te s t i n g a n d C o m m i s s i o n i n g 21

environment in which they are installed. The substation environment is a very se


vere environment in terms of the electrical and electromagnetic interference tha
t can arise. There are many sources of interference within a substation, some or
iginating internally, others being conducted along the overhead lines or cables
into the substation from external disturbances. The most common sources are: a.
switching operations b. system faults c. lightning strikes d. conductor flashove
r e. telecommunication operations e.g. mobile phones A whole suite of tests are
performed to simulate these types of interference, and they fall under the broad
umbrella of what is known as EMC, or Electromagnetic Compatibility tests.
that the relay can withstand an interruption in the auxiliary supply without deenergising, e.g. switching off, and that when this time is exceeded and it does
transiently switch off, that no maloperation occurs. It simulates the effect of
a loose fuse in the battery circuit, or a short circuit in the common d.c. suppl
y, interrupted by a fuse. Another source of d.c. interruption is if there is a p
ower system fault and the battery is supplying both the relay and the circuit br
eaker trip coils. hen the battery energises the coils to initiate the circuit b
reaker trip, the voltage may fall below the required level for operation of the
relay and hence a d.c. interrupt occurs. The test is specified in IEC 60255-11 a
nd comprises a interruptions of 2, 5, 10, 20, 50, 100 and 200ms. For interruptio
ns lasting up to and including 20ms, the relay must not de-energise of maloperat
e, while for longer interruptions it must not maloperate. The relay is powered f
rom a battery supply, and both short circuit and open circuit interruptions are
carried out. Each interruption is applied 10 times, and for auxiliary power supp
lies with a large operating range, the tests are performed at minimum, maximum,
and other voltages across this range, to ensure compliance over the complete ran
ge.
R e l a y Te s t i n g a n d C o m m i s s i o n i n g
Broadly speaking, EMC can be defined as: The ability of equipment to co-exist in
the same electromagnetic environment It is not a new subject and has been tested
for by the military ever since the advent of electronic equipment. EMC can cause
real and serious problems, and does need to be taken into account when designin
g electronic equipment. EMC tests determine the impact on the relay under test o
f high-frequency electrical disturbances of various kinds. Relays manufactured o
r intended for use in the EEC have to comply with EEC Directive 89/336/EEC in th
is respect. To achieve this, in addition to designing for statutory compliance t
o this Directive, the following range of tests are carried out: a. d.c. interrup
t test b. a.c. ripple on d.c. supply test
21.3.2 A.C. Ripple on D.C. Supply This test (IEC 60255-11) determines that the r
elay is able to operate correctly with a superimposed a.c. voltage on the d.c. s
upply. This is caused by the station battery being charged by the battery charge
r, and the relevant waveform is shown in Figure 21.1. It consists of a 12% peakto-peak ripple superimposed on the d.c. supply voltage.
60.00 50.00 40.00
Voltage (V)

21
c. d.c. ramp test d. high frequency disturbance test e. fast transient test f. s
urge immunity test g. power frequency interference test h. electrostatic dischar
ge test i. conducted and radiated emissions tests j. conducted and radiated immu
nity tests k. power frequency magnetic field tests
30.00 20.00 10.00 0.00
1 88 175 262 349 436 523 610 697 784 871 958 1045 1132 1219 1306 1393

Time (ms) Figure 21.1: A.C. ripple superimposed on d.c. supply test
21.3.1 D.C Interrupt Test This is a test to determine the maximum length of time
For auxiliary power supplies with a large operating range, the tests are perform
ed at minimum, maximum, and other voltages across this range, to ensure complian
ce for the complete range. The interference is applied using a full wave rectifi
er network, connected in parallel with the battery supply. The relay must contin
ue to operate without malfunction during the test.
374
Network Protection & Automation Guide

21.3.3 D.C. Ramp Down/Ramp Up This test simulates a failed station battery charg
er, which would result in the auxiliary voltage to the relay slowly ramping down
. The ramp up part simulates the battery being recharged after discharging. The
relay must power up cleanly when the voltage is applied and not maloperate. Ther
e is no international standard for this test, so individual manufacturers can de
cide if they wish to conduct such a test and what the test specification shall b
e.
V
Burst period, 300 ms Burst duration (1/15 ms)
t V 5 ns rise time, 50 ns pulse width
Repetition period Figure 21.3: Fast Transient Test waveform
t
21.3.4 High Frequency Disturbance Test The High Frequency Disturbance Test simul
ates high voltage transients that result from power system faults and plant swit
ching operations. It consists of a 1MHz decaying sinusoidal waveform, as shown i
n Figure 21.2. The interference is applied across each independent circuit (diff
erential mode) and between each independent circuit and earth (common mode) via
an external coupling and switching network. The product is energised in both nor
mal (quiescent) and tripped modes for this test, and must not maloperate when th
e interference is applied for a 2 second duration. The product is energised in b
oth normal (quiescent) and tripped modes for this test. It must not maloperate w
hen the interference is applied in common mode via the integral coupling network
to each circuit in turn, for 60 seconds. Interference is coupled onto communica
tions circuits, if required, using an external capacitive coupling clamp.
21.3.6 Surge Immunity Test The Surge Immunity Test simulates interference caused
by major power system disturbances such as capacitor bank switching and lightni
ng strikes on overhead lines within 5km of the substation. The test waveform has
an open circuit voltage of 4kV for common mode surges and 2kV for differential
mode surges. The test waveshape consists on open circuit of a 1.2/50ms rise/fall
time and a short circuit current of 8/20ms rise/fall time. The generator is cap
able of providing a short circuit test current of up to 2kA, making this test po
tentially destructive. The surges are applied sequentially under software contro
l via dedicated coupling networks in both differential and common modes with the
product energised in its normal (quiescent) state. The product shall not malope
rate during the test, shall still operate within specification after the test se
quence and shall not incur any permanent damage.
0 Time
Figure 21.2: High Frequency Disturbance Test waveform

21.3.5 Fast Transient Test The Fast Transient Test simulates the HV interference
caused by disconnector operations in GIS substations or breakdown of the SF6 in
sulation between conductors and the earthed enclosure. This interference can eit
her be inductively coupled onto relay circuits or can be directly introduced via
the CT or VT inputs. It consists of a series of 15ms duration bursts at 300ms i
ntervals, each burst consisting of a train of 50ns wide pulses with very fast (5
ns typical) rise times (Figure 21.3), with a peak voltage magnitude of 4kV.
21.3.7 Power Frequency Interference This test simulates the type of interference
that is caused when there is a power system fault and very high levels of fault
current flow in the primary conductors or the earth grid. This causes 50 or 60H

z interference to be induced onto control and communications circuits. There is


no international standard for this test, but one used by some Utilities is: a. 5
00V r.m.s., common mode b. 250V r.m.s., differential mode
Network Protection & Automation Guide
375
R e l a y Te s t i n g a n d C o m m i s s i o n i n g 21
Voltage

applied to circuits for which power system inputs are not connected. Tests are c
arried out on each circuit, with the relay in the following modes of operation:
1. current and voltage applied at 90% of setting, (relay not tripped) 2. current
and voltage applied at 110% of setting, (relay tripped) 3. main protection and
communications functions are tested to determine the effect of the interference
The relay shall not maloperate during the test, and shall still perform its main
functions within the claimed tolerance.
1. current and voltage applied at 90% of setting, (relay not tripped) 2. current
and voltage applied at 110% of setting, (relay tripped) 3. main protection and
communications functions are tested to determine the effect of the discharge To
pass, the relay shall not maloperate, and shall still perform its main functions
within the claimed tolerance.
21.3.9 Conducted and Radiated Emissions Tests These tests arise primarily from t
he essential protection requirements of the European Community (EU) directive on
EMC. These require manufacturers to ensure that any equipment to be sold in the
countries comprising the European Union must not interfere with other equipment
. To achieve this it is necessary to measure the emissions from the equipment an
d ensure that they are below the specified limits. Conducted emissions are measu
red only from the equipments power supply ports and are to ensure that when conne
cted to a mains network, the equipment does not inject interference back into th
e network which could adversely affect the other equipment connected to the netw
ork. Radiated emissions measurements are to ensure that the interference radiate
d from the equipment is not at a level that could cause interference to other eq
uipment. This test is normally carried out on an Open Area Test Site (OATS) wher
e there are no reflecting structures or sources of radiation, and therefore the
measurements obtained are a true indication of the emission spectrum of the rela
y. An example of a plot obtained during conducted emissions tests is shown in Fi
gure 21.5. The test arrangements for the conducted and radiated emissions tests
are shown in Figure 21.6. hen performing these two tests, the relay is in a qui
escent condition, that is not tripped, with currents and voltages applied at 90%
of the setting values. This is because for the majority of its life, the relay
will be in the quiescent state and the emission of electromagnetic interference
when the relay is tripped is considered to be of no significance. Tests are cond
ucted in accordance with IEC 60255-25 and EN 50081-2, and are detailed in Table
21.3.
Frequency Range 30 - 230MHz Radiated 230 - 1000MHz Specified Limits 30dB(V/m) at
30m 37dB(V/m) at 30m 79dB(V) quasi-peak 66dB(V) average 73dB(V) quasi-peak 60dB(V) av
erage Test Limits 40dB(V/m) at 10m 47dB(V/m) at 10m 79dB(V) quasi-peak 66dB(V) avera
ge 73dB(V) quasi-peak 60dB(V) average
21.3.8 Electrostatic Discharge Test This test simulates the type of high voltage
interference that occurs when an operator touches the relays front panel after b
eing charged to a high potential. This is exactly the same phenomenon as getting
an electric shock when stepping out of a car or after walking on a synthetic fi
bre carpet. In this case the discharge is only ever applied to the front panel o
f the relay, with the cover both on and off. Two types of discharges are applied
, air discharge and contact discharge. Air discharges are used on surfaces that
are normally insulators, and contact discharges are used on surfaces that are no
rmally conducting. IEC 60255-22-2 is the relevant standard this test, for which
the test parameters are: a. cover on: Class 4, 8kV contact discharge, 15kV air d
ischarge b. cover off: Class 3, 6kV contact discharge, 8kV air discharge In both
cases above, all the lower test levels are also tested. The discharge current w
aveform is shown in Figure 21.4.
100 90 80 70 60 50 40 30 20 10 0 0 10
Current, % of Peak

R e l a y Te s t i n g a n d C o m m i s s i o n i n g 21
Rise Time = 0.7 to 1.0 ns. Current specified for 30 ns and 60 ns
20
30
40 50 Time, ns
60
70
80
90
Figure 21.4: ESD Current

aveform

The test is performed with single discharges repeated on each test point 10 time
s with positive polarity and 10 times with negative polarity at each test level.
The time interval between successive discharges is greater than 1 second. Tests
are carried out at each level, with the relay in the following modes of operati
on:
0.15 - 0.5MHz Conducted 0.5 - 30MHz
Table 21.3: Test criteria for Conducted and Radiated Emissions tests
376
Network Protection & Automation Guide

100 90 80 70 Quasi-peak limits Average limits Typical trace


Emissions Level, dBuV
60 50 40 30 20 10 0 0.1 1 Frequency, MHz 10 100
Figure 21.5: Conducted Emissions Test Plot
Screened room
Ante-chamber
E.U.T. Impedance network
Access panel
Support/analysis equipment
(a) Conducted EMC emissions test arrangement
10m

Antenna E.U.T.
Turntable
Earth Plane
(b) Radiated Emissions test arrangement on an OATS E.U.T. - Equipment under test
Figure 21.6: EMC test arrangements
Network Protection & Automation Guide
377
R e l a y Te s t i n g a n d C o m m i s s i o n i n g 21

21.3.10 Conducted and Radiated Immunity Tests These tests are designed to ensure
that the equipment is immune to levels of interference that it may be subjected
to. The two tests, conducted and radiated, arise from the fact that for a condu
ctor to be an efficient antenna, it must have a length of at least 1/4 of the wa
velength of the electromagnetic wave it is required to conduct. If a relay were
to be subjected to radiated interference at 150kHz, then a conductor length of a
t least = 300 x106/(150 x 103 x 4) = 500 m woud be needed to conduct the interf
erence. Even with a the cabing attached and with the ongest PCB track ength
taken into account, it woud be highy unikey that the reay woud be abe to
conduct radiation of this frequency, and the test therefore, woud have no effe
ct. The interference has to be physicay introduced by conduction, hence the co
nducted immunity test. However, at the radiated immunity ower frequency imit o
f 80MHz, a conductor ength of approximatey 1.0m is required. At this frequency
, radiated immunity tests can be performed with the confidence that the reay wi
 conduct this interference, through a combination of the attached cabing and
the PCB tracks. Athough the test standards state that a 6 faces of the equipm
ent shoud be subjected to the interference, in practice this is not carried out
. Appying interference to the sides and top and bottom of the reay woud have
itte effect as the circuitry inside is effectivey screened by the earthed met
a case. However, the front and rear of the reay are not competey encosed by
meta and are therefore not at a we screened, and can be regarded as an EMC
hoe. Eectromagnetic interference when directed at the front and back of the r
eay can enter freey onto the PCBs inside. When performing these two tests, the
reay is in a quiescent condition, that is not tripped, with currents and votag
es appied at 90% of the setting vaues. This is because for the majority of its
ife, the reay wi be in the quiescent state and the coincidence of an eectr
omagnetic disturbance and a faut is considered to be unikey. However, spot ch
ecks are performed at seected frequencies when the main protection and contro
functions of the reay are exercised, to ensure that it wi operate as expected
, shoud it be required to do so. The frequencies for the spot checks are in gen
era seected to coincide with the radio frequency broadcast bands, and in parti
cuar, the frequencies of mobie communications equipment used by personne work
ing in the substation. This is to ensure that when working in the vicinity of a
reay, the personne shoud be abe to
operate their radios/mobie phones without fear of reay maoperation. IEC 60255
-22-3 specifies the radiated immunity tests to be conducted (ANSI/IEEE C37.90.2
is used for equipment buit to US standards), with signa eves of: 1. IEC: Ca
ss III, 10V/m, 80MHz -1000MHz 2. ANSI/IEEE: 35V/m 25MHz - 1000MHz with no modua
tion, and again with 100% puse moduation IEC 60255-22-6 is used for the conduc
ted immunity test, with a test eve of: Cass III, 10V r.m.s., 150kHz - 80MHz.
21.3.11 Power Frequency Magnetic Fied Tests These tests are designed to ensure
that the equipment is immune to magnetic interference. The three tests, steady s
tate, pused and damped osciatory magnetic fied, arise from the fact that for
different site conditions the eve and waveshape is atered. 23.3.11.1 Steady
state magnetic fied tests These tests simuate the magnetic fied that woud be
experienced by a device ocated within cose proximity of the power system. Tes
ting is carried out by subjecting the reay to a magnetic fied generated by two
induction cois. The reay is rotated such that in each axis it is subjected to
the fu magnetic fied strength. IEC 610004-6 is the reevant standard, using
a signa eve of: Leve 5: 300A/m continuous and 1000A/m short duration The tes
t arrangement is shown in Figure 21.7.
R e  a y Te s t i n g a n d C o m m i s s i o n i n g
Induction coi

21
Induction coi
E.U.T.
Ground pane
E.U.T. - Equipment under test Figure 21.7: Power frequency magnetic fied set-up
378
Network Protection & Automation Guide

To pass the steady-state test, the reay sha not maoperate, and sha sti p
erform its main functions within the caimed toerance. During the appication o
f the short duration test, the main protection function sha be exercised and v
erified that the operating characteristics of the reay are unaffected. 21.3.11.
2 Pused magnetic fied These tests simuate the magnetic fied that woud be ex
perienced by a device ocated within cose proximity of the power system during
a transient faut condition. According to IEC 61000-4-9, the generator for the i
nduction cois sha produce a 6.4/16s waveshape with test eve 5, 100A/m with t
he equipment configured as for the steady state magnetic fied test. The reay s
ha not maoperate, and sha sti perform its main functions within the caim
ed toerance during the test. 21.3.11.3 Damped osciatory magnetic fied These
tests simuate the magnetic fied that woud be experienced by a device ocated
within cose proximity of the power system during a transient faut condition. I
EC 61000-4-10 specifies that the generator for the coi sha produce an oscia
tory waveshape with a frequency of 0.1MHz and 1MHz, to give a signa eve in ac
cordance with Leve 5 of 100A/m, and the equipment sha be configured as in Fig
ure 21.7.
open contacts intended for connection to tripping circuits, in accordance with A
NSI/IEEE C37.90 3. 1.0kV r.m.s., 50/60Hz for 1 minute across the normay open c
ontacts of watchdog or changeover output reays, in accordance with IEC 60255-5
The routine dieectric votage withstand test time may be shorter than for the 1
minute type test time, to aow a reasonabe production throughput, e.g. for a
minimum of 1 second at 110% of the votage specified for 1 minute.
21.4.2 Insuation Withstand for Overvotages The purpose of the High Votage Imp
use Withstand type test is to ensure that circuits and their components wi wi
thstand overvotages on the power system caused by ightning. Three positive and
three negative high votage impuses, 5kV peak, are appied between a circuit
s and the case earth and aso between the terminas of independent circuits (but
not across normay open contacts). As before, different requirements appy in
the case of circuits using D-type connectors. The test generator characteristics
are as specified in IEC 60255-5 and are shown in Figure 21.8. No disruptive dis
charge (i.e. fashover or puncture) is aowed. If it is necessary to repeat eit
her the Dieectric Votage or High Votage Impuse Withstand tests these shoud
be carried out at 75% of the specified eve, in accordance with IEC 60255-5, to
avoid overstressing insuation and components.
21.4 PRODUCT SAFETY TYPE TESTS A number of tests are carried out to demonstrate
that the product is safe when used for its intended appication. The essentia r
equirements are that the reay is safe and wi not cause an eectric shock or f
ire hazard under norma conditions and in the presence of a singe faut. A numb
er of specific tests to prove this may be carried out, as foows.
Votage
21.4.1 Dieectric Votage Withstand Dieectric Votage Withstand testing is carr
ied out as a routine test i.e. on every unit prior to despatch. The purpose of t
his test is to ensure that the product buid is as intended by design. This is d
one by verifying the cearance in air, thus ensuring that the product is safe to
operate under norma use conditions. The foowing tests are conducted uness o
therwise specified in the product documentation: 1. 2.0kV r.m.s., 50/60Hz for 1
minute between a terminas and case earth and aso between independent circuit
s, in accordance with IEC 60255-5. Some communication circuits are excuded from
this test, or have modified test requirements e.g. those using D-type connector
s 2. 1.5kV r.m.s., 50/60Hz for 1 minute across normay

5kV peak Rise time (10 % to 90 %) = 1.2 s Duration (50 %) = 50 s

Time
Figure 21.8: Test generator characteristics for insuation withstand test
21.4.3 Singe Faut Condition Assessment An assessment is made of whether a sing
e faut condition such as an overoad, or an open or short circuit, appied to
the product may cause an eectric shock or fire
Network Protection & Automation Guide
379
R e  a y Te s t i n g a n d C o m m i s s i o n i n g 21

hazard. In the case of doubt, type testing is carried out to ensure that the pro
duct is safe.
21.5.2 Humidity Test The humidity test is performed to ensure that the product w
i withstand and operate correcty when subjected to 93% reative humidity at a
constant temperature of 40C for 56 days. Tests are performed to ensure that the
product functions correcty within specification after 21 and 56 days. After the
test, visua inspections are made for any signs of unacceptabe corrosion and m
oud growth.
21.4.4 Earth Bonding Impedance Cass 1 products that rey on a protective earth
connection for safety are subjected to an earth bonding impedance (EBI) type tes
t. This ensures that the earth path between the protective earth connection and
any accessibe earthed part is sufficienty ow to avoid damage in the event of
a singe faut occurring. The test is conducted using a test votage of 12V maxi
mum and a test current of twice the recommended maximum protective fuse rating.
After 1 minute with the current fowing in the circuit under test, the EBI sha
not exceed 0.1. 21.4.5 CE Marking
21.5.3 Cyclic Temperature/Humidity Test This is a short-term test that stresses
the relay by subjecting it to temperature cycling in conjunction with high humid
ity. The test does not replace the 56 day humidity test, but is used for testing
extension to ranges or minor modifications to prove that the design is unaffect
ed. The applicable standard is IEC 60068-2-30 and test conditions of: +25C 3C and 9
5% relative humidity/+55C 2C and 95% relative humidity are used, over the 24 hour c
ycle shown in Figure 21.9.
Relative humidity %
R e l a y Te s t i n g a n d C o m m i s s i o n i n g
A CE mark on the product, or its packaging, shows that compliance is claimed aga
inst relevant European Community directives e.g. Low Voltage Directive 73/23/EEC
and Electromagnetic Compatibility (EMC) Directive 89/336/EEC.
21.5 ENVIRONMENTAL TYPE TESTS Various tests have to be conducted to prove that a
relay can withstand the effects of the environment in which it is expected to w
ork. They consist of: the following tests: 1. temperature 2. humidity 3. enclosu
re protection 4. mechanical
100 90 80 70
96% 95% 90% 15min End of temperature rise 80% temperature Time 95%
+55C
Ambient Temperature C

21
These tests are described in the following sections.
0.5h 3h 12h0.5h 3h 6h 24h
+28C +22C Time
+25C
21.5.1 Temperature Test Temperature tests are performed to ensure that a product
can withstand extremes in temperatures, both hot and cold, during transit, stor

age and operating conditions. Storage and transit conditions are defined as a te
mperature range of 25C to +70C and operating as 25C to +55C. Dry heat withstand tests
are performed at 70C for 96 hours with the reay de-energised. Cod withstand tes
ts are performed at 40C for 96 hours with the reay deenergised. Operating range t
ests are carried out with the product energised, checking a main functions ope
rate within toerance over the specified working temperature range 25C to +55C.
Figure 21.9: Cycic temperature/humidity test profie
For these tests the reay is paced in a humidity cabinet, and energised with no
rma in-service quantities for the compete duration of the tests. In practica
terms this usuay means energising the reay with currents and votages such th
at it is 10% from the threshod for operation. Throughout the duration of the te
st the reay is monitored to ensure that no unwanted operations occur. Once the
reay is removed from the humidity cabinet, its insuation resistance is measure
d to ensure that it has not deteriorated to beow the caimed eve. The reay i
s then functionay tested again, and finay dismanted to
Network Protection & Automation Guide
380

check for signs of component corrosion and growth. The acceptance criterion is t
hat no unwanted operations sha occur incuding transient operation of indicati
ng devices. After the test the reays insuation resistance shoud not have signi
ficanty reduced, and it shoud perform a of its main protection and communica
tions functions within the caimed toerance. The reay shoud aso suffer no si
gnificant corrosion or growth, and photographs are usuay taken of each PCB and
the case as a record of this.
21.5.4 Encosure Protection Test Encosure protection tests prove that the casin
g system and connectors on the product protect against the ingress of dust, mois
ture, water dropets (striking the case at predefined anges) and other poutan
ts. An acceptabe eve of dust or water may penetrate the case during testing, bu
t must not impair norma product operation, safety or cause tracking across insu
ated parts of connectors.
Figure 21.10: Reay undergoing seismic test
1.2A A 0.8A Puse shape (haf sine)
21.5.5 Mechanica Tests Mechanica tests simuate a number of different mechanic
a conditions that the product may have to endure during its ifetime. These fa
 into two categories a. response to disturbances whie energised b. response to
disturbances during transportation (de-energised state) Tests in the first cate
gory are concerned with the response to vibration, shock and seismic disturbance
. The tests are designed to simuate norma in-service conditions for the produc
t, for exampe earthquakes. These tests are performed in a three axes, with th
e product energised in its norma (quiescent) state. During the test, a output
contacts are continuay monitored for change using contact foower circuits.
Vibration eves of 1gn, over a 10Hz-150Hz frequency sweep are used. Seismic tes
ts use excitation in a singe axis, using a test frequency of 35Hz and peak disp
acements of 7.5mm and 3.5mm in the x and y axes respectivey beow the crossove
r frequency and peak acceerations of 2.0gn and 1.0gn in these axes above the cr
ossover frequency. The second category consists of vibration endurance, shock wi
thstand and bump tests. They are designed to simuate the onger-term affects of
shock and vibration that coud occur during transportation. These tests are per
formed with the product de-energised. After these tests, the product must sti
operate within its specification and show no signs of permanent mechanica damag
e. Equipment undergoing a seismic type test is shown in Figure 21.10, whie the
waveform for the shock/bump test is shown in Figure 21.11
Network Protection & Automation Guide
0.4D 2.5D
D
D 2.5D
2.4D = T1 6D = T2 D - duration of nomina puse A - peak acceeration of nomina
puse T1- minimum time for monitoring of puse when conventiona shock/bump mac
hine is used T2 - as T1 when a vibration generator is used Figure 21.11: Shock/B
ump Impuse waveform
The test eves for shock and bump tests are: Shock response (energised): 3 pus
es, each 10g, 11ms duration Shock withstand (de-energised): 3 puses, 15g, 11ms
duration Bump (de-energised): 1000 puses, 10g, 16ms duration

21.6 SOFTWARE TYPE TESTS Digita and numerica reays contain software to impem
ent the protection and measurement functions of a reay. This software must be t
horoughy tested, to ensure that the reay compies with a specifications and
that disturbances of various kinds do not resut in unexpected resuts. Software

is tested in various stages: a. unit testing b. integration testing c. function


a quaification testing
381
R e  a y Te s t i n g a n d C o m m i s s i o n i n g 21
+0.2A 0 -0.2A

The purpose of unit testing is to determine if an individua function or procedu


re impemented using software, or sma group of cosey reated functions, is f
ree of data, ogic, or standards errors. It is much easier to detect these types
of errors in individua units or sma groups of units than it is in an integra
ted software architecture and/or system. Unit testing is typicay performed aga
inst the software detaied design and by the deveoper of the unit(s). Integrati
on testing typicay focuses on these interfaces and aso issues such as perform
ance, timings and synchronisation that are not appicabe in unit testing. Integ
ration testing aso focuses on stressing the software and reated interfaces. Inte
gration testing is back box in nature, i.e. it does not take into account the str
ucture of individua units. It is typicay performed against the software archi
tectura and detaied design. The specified software requirements woud typica
y aso be used as a source for some of the test cases.
21.6.3 Unit Testing Environment Both Dynamic and Static Unit Testing are perform
ed in the host environment rather than the target environment. Dynamic Unit Test
ing uses a test harness to execute the unit(s) concerned. The test harness is de
signed such that it simuates the interfaces of the unit(s) being tested - both
software-software interfaces and software-hardware interfaces - using what are k
nown as stubs. The test harness provides the test data to those units being test
ed and outputs the test resuts in a form understandabe to a deveoper. There a
re many commerciay avaiabe testing toos to automate test harness production
and the execution of tests.
21.6.4 Software/Software Integration Testing Software/Software Integration Testi
ng is performed in the host environment. It uses a test harness to simuate inpu
ts and outputs, hardware cas and system cas (e.g. the target environment ope
rating system).
R e  a y Te s t i n g a n d C o m m i s s i o n i n g
21.6.5 Software/Hardware Integration Testing 21.6.1 Static Unit Testing Static U
nit Testing (or static anaysis as it is often caed) anayses the unit(s) sour
ce code for compexity, precision tracking, initiaisation checking, vaue track
ing, strong type checking, macro anaysis etc. Whie Static Unit Testing can be
performed manuay, it is a aborious and error prone process and is best perfor
med using a proprietary automated static unit anaysis too. It is important to
ensure that any such too is configured correcty and used consistenty during d
eveopment. Software/Hardware Integration Testing is performed in the target env
ironment, i.e. it uses the actua target hardware, operating system, drivers etc
. It is usuay performed after Software/Software Integration Testing. Testing t
he interfaces to the hardware is an important feature of Software/Hardware Integ
ration Testing. Test cases for Integration Testing are typicay based on those
defined for Vaidation Testing. However the emphasis shoud be on finding errors
and probems. Performing a dry run of the vaidation testing often competes In
tegration Testing.
21.6.2 Dynamic Testing

21.6.6 Vaidation Testing The purpose of Vaidation Testing (aso known as Softw
are Acceptance Testing) is to verify that the software meets its specified funct
iona requirements. Vaidation Testing is performed against the software require
ments specification, using the target environment. In idea circumstances, someo
ne independent of the software deveopment performs the tests. Vaidation Testin
g is back box in nature, i.e. it does not take into account the interna structur
e of the software. For reays, the non-protection functions incuded in the soft
ware are considered to be as important as the protection functions, and hence te
sted in the same manner. Each vaidation test shoud have predefined evauation
criteria, to be used to decide if the test has passed or faied. The evauation

criteria shoud be expicit with no room for interpretation or ambiguity.


Network Protection & Automation Guide
21
Dynamic Testing is concerned with the runtime behaviour of the unit(s) being tes
ted and so therefore, the unit(s) must be executed. Dynamic unit testing can be
sub-divided into back box testing and white box testing. Back box testing verifies t
he impementation of the requirement(s) aocated to the unit(s). It takes no ac
count of the interna structure of the unit(s) being tested. It is ony concerne
d with providing known inputs and determining if the outputs from the unit(s) ar
e correct for those inputs. White box testing is concerned with testing the intern
a structure of the unit(s) and measuring the test coverage, i.e. how much of th
e code within the unit(s) has been executed during the tests. The objective of t
he unit testing may, for exampe, be to achieve 100% statement coverage, in whic
h every ine of the code is executed at east once, or to execute every possibe
path through the unit(s) at east once.
382

21.6.7 Traceabiity of Vaidation Tests Traceabiity of vaidation tests to soft


ware requirements is vita. Each software requirement documented in the software
requirements specification shoud have at east one vaidation test, and it is
important to be abe to prove this.
Power system simuators can be divided into two types: a. those which use anaog
ue modes of a power system b. those which mode the power system mathematicay
using digita simuation techniques
21.6.8 Software Modifications - Regression Testing Regression Testing is not a t
ype test in its own right. It is the overa name given to the testing performed
when an existing software product is changed. The purpose of Regression Testing
is to show that unintended changes to the functionaity (i.e. errors and defects
) have not been introduced. Each change to an existing software product must be
considered in its own right. It is impossibe to specify a standard set of regres
sion tests that can be appied as a catch-a for introduced errors and defects. E
ach change to the software must be anaysed to determine what risk there might b
e of unintentiona changes to the functionaity being introduced. Those areas of
highest risk wi need to be regression tested. The utimate regression test is
to perform the compete Vaidation Testing programme again, updated to take acc
ount of the changes made. Regression Testing is extremey important. If it is no
t performed, there is a high risk of errors being found in the fied. Performing
it wi not reduce to zero the chance of an error or defect remaining in the so
ftware, but it wi reduce it. Determining the Regression Testing that is requir
ed is made much easier if there is traceabiity from propery documented softwar
e requirements through design (again propery documented and up to date), coding
and testing.
21.7.1 Use of Power System Anaogue Modes For many years, reays have been test
ed on anaogue modes of power systems such as artificia transmission ines, or
test pant capabe of suppying significant amounts of current [21.1]. However,
these approaches have significant imitations in the current and votage wavefo
rms that can be generated, and are not suitabe for automated, unattended, testi
ng programmes. Whie sti used on a imited basis for testing eectromechanica
and static reays, a radicay different approach is required for dynamic testi
ng of numerica reays.
21.7.2 Use of Microprocessor Based Simuation Equipment The compexity of numeri
ca reays, reiant on software for impementation of the functions incuded, di
ctates some kind of automated test equipment. The functions of even a simpe num
erica overcurrent reay (incuding a auxiiary functions) can take severa mo
nths of automated, 24 hours/day testing to test competey. If such test equipme
nt was abe to appy reaistic current and votage waveforms that cosey match
those found on power systems during faut conditions, the equipment can be used
either for type testing of individua reay designs or of a compete protection
scheme designed for a specific appication. In recognition of this, a new genera
tion of power system simuators has been deveoped, which is capabe of providin
g a far more accurate simuation of power system conditions than has been possib
e in the past. The simuator enabes reays to be tested under a wide range of
system conditions, representing the equivaent of many years of site experience.
21.7.2.1 Simuation hardware Equipment is now avaiabe to provide high-speed,
highy accurate modeing of a section of a power system. The equipment is based
on distributed microprocessor-based hardware containing software modes of the
various eements of a power system, and is shown in Figure 21.12. The modues ha
ve outputs inked to current and votage sources that have a simiar transient c
apabiity and have suitabe output eves for direct connection to the inputs of
reays i.e. 110V for votage and 1A/5A for current. Inputs are aso provided to
monitor the response of reays under test (contact cosures for tripping, etc.)
and these inputs can be used as part of the mode of the power

21.7 DYNAMIC VALIDATION TYPE TESTING There are two possibe methods of dynamica
y proving the satisfactory performance of protection reays or schemes; the fir
st method is by actuay appying fauts on the power system and the second is t
o carry out comprehensive testing on a power system simuator. The former method
is extremey unikey to be used ead times are engthy and the risk of damage
occurring makes the tests very expensive. It is therefore ony used on a very i
mited basis and the fauts appied are restricted in number and type. Because of
this, a proving period for new protection equipment under service conditions ha
s usuay been required. As fauts may occur on the power system at infrequent i
ntervas, it can take a number of years before any possibe shortcomings are dis
covered, during which time further instaations may have occurred.

Network Protection & Automation Guide


383
R e  a y Te s t i n g a n d C o m m i s s i o n i n g 21

R e  a y Te s t i n g a n d C o m m i s s i o n i n g
Figure 21.12: Digita power system simuator for reay/protection scheme testing
system. The software is aso capabe of modeing the dynamic response of CTs and
VTs accuratey. Where it is desired to check the response of a reay or protecti
on scheme to an actua power system transient, the transient can be simuated us
ing sophisticated power systems anaysis software and the resuts transferred di
gitay to the simuator, or the event recorder recording of the transient can b
e used, in either digita or anaogue form as inputs to the simuator mode. Out
put signa conversion invoves circuits to eiminate the quantisation steps norm
ay found in conventiona D/A conversion. Anaogue modes of the system transdu
cer characteristics can be interposed between the signa processors and the outp
ut ampifiers when required. This equipment shows many advantages over tradition
a test equipment: a. the power system mode is capabe of reproducing high freq
uency transients such as traveing waves b. tests invoving very ong time cons
tants can be carried out c. it is not affected by the harmonic content, noise an
d frequency variations in the a.c. suppy d. it is capabe of representing the v
ariation in the current associated with generator fauts and power swings e. sat
uration effects in CTs and VTs can be modeed f. a set of test routines can be sp
ecified in software and then eft to run unattended (or with ony occasiona mon
itoring) to competion, with a detaied record of
test resuts being avaiabe on competion A bock schematic of the equipment is
shown in Figure 21.13, is based around a computer which cacuates and stores t
he digita data representing the system votages and currents. The computer cont
ros conversion of the digita data into anaogue signas, and it monitors and c
ontros the reays being tested. 21.7.2.2 Simuation software Unike most tradit
iona software used for power systems anaysis, the software used is suitabe fo
r the modeing the fast transients that occur in the first few miiseconds aft
er faut inception. Two very accurate simuation programs are used, one based on
time domain and the other on frequency domain techniques. In both programs, sin
ge and doube circuit transmission ines are represented by fuy distributed p
arameter modes. The ine parameters are cacuated from the physica constructi
on of the ine (symmetrica, asymmetrica, transposed or non-transposed), taking
into account the effect of conductor geometry, conductor interna impedance and
the earth return path. It aso incudes, where appropriate, the frequency depen
dence of the ine parameters in the frequency domain program. The frequency depe
ndent variabe effects are cacuated using Fast Fourier Transforms and the resu
ts are converted to the time domain. Conventiona current transformers and capa
citor votage transformers can be simuated. The faut can be appied at any one
point in the system and can be any combination of phase to phase or phase

21
384
Network Protection & Automation Guide

IA
IB
D/A conversion
Linear interpoation circuits
CT mode
Current ampifier
IC VDU I/O Subsystem VA Computer Equipment under test D/A conversion
Linear interpoation circuits
Keyboard VDU
VB
CVT mode
Votage ampifier
VC Contact status monitor Storage Key : CT - Current transformer CVT - Capacitor
votage transformer VDU - Visua dispay unit Signaing Channe Simuation To
second RTDS
Keyboard
Figure 21.13: Bock diagram of microprocessor-based automated reay test system
to earth, resistive, or non-inear phase to earth arcing fauts. For series comp
ensated ines, fashover across a series capacitor foowing a short circuit fau
t can be simuated. The frequency domain mode is not suitabe for deveoping f
auts and switching sequences, therefore the widey used Eectromagnetic Transie
nt Program (EMTP), working in the time domain, is empoyed in such cases. In add
ition to these two programs, a simuation program based on umped resistance and
inductance parameters is used. This simuation is used to represent systems wit
h ong time constants and sow system changes due, for exampe, to power swings.
21.7.2.3 Simuator appications The simuator is used for checking the accuracy
of caibration and performing type tests on a wide range of protection reays d
uring their deveopment. It has the foowing advantages over existing test meth
ods: a. state of the art power system modeing data can be used to test reay
s b. freedom from frequency variations and noise or harmonic content of the a.c.
suppy c. the reay under test does not burden the power system simuation d. a
 tests are accuratey repeatabe e. wide bandwidth signas can be produced f.
a wide range of frequencies can be reproduced g. seected harmonics may be super
imposed on the
power frequency h. the use of direct couped current ampifiers aows time cons
tants of any ength i. capabe of simuating sow system changes j. reproduces f
aut currents whose peak ampitude varies with time k. transducer modes can be
incuded . automatic testing removes the ikeihood of measurement and setting
errors m. two such equipments can be inked together to simuate a system mode
with two reaying points The simuator is aso used for the production testing o
f reays, in which most of the advantages isted above appy. As the tests and m
easurements are made automaticay, the quaity of testing is aso greaty enhan
ced. Further, in cases of suspected mafunction of a reay in the fied under kn
own faut conditions, the simuator can be used to repicate the power system an
d faut conditions, and conduct a detaied investigation into the performance of

the reay. Finay, compex protection schemes can be modeed, using both the
reays intended for use and software modes of them as appropriate, to check the
suitabiity of the proposed scheme under a wide variety of conditions. To ius
trate this, Figure 21.14(a) shows a section of a particuar power system modee
d. The waveforms of Figure 21.14(b) show the three phase votages and currents a
t the primaries of VT1 and CT1 for the faut condition indicated in Figure 21.14
(a).

Network Protection & Automation Guide


385
R e  a y Te s t i n g a n d C o m m i s s i o n i n g 21
Communications ink to second RTDS
(When required)

N 3G L Infinite bus 4G CB3 CT3 F3 Line 2 8G F4 CT4 CB4


9G LR3 LR4
CB1 oad 1 oad 2 oad 3 VT1
CT1
F1 Line 1
F2
CT2
CB2
11G
VT2
LR1 Reay 1
LR2 Reay 2
R e  a y Te s t i n g a n d C o m m i s s i o n i n g
(a) Exampe power system
Va Vb Vc Ia Ib
Figure 21.14: Exampe of appication study
Ic 0 0.08 0.16 0.24 0.32 0.4 0.48 0.56
(b) Votages and currents at VT1/CT1
21.8 PRODUCTION TESTING Production testing of protection reays is becoming far
more demanding as the accuracy and compexity of the products increase. Eectron
ic power ampifiers are used to suppy accurate votages and currents of high st
abiity to the reay under test. The incusion of a computer in the test system
aows more compex testing to be performed at an economica cost, with the adva
ntage of speed and repeatabiity of tests from one reay to another. Figure 21.1
5 shows a modern computer-controed test bench. The hardware is mounted in a sp
ecia rack. Each unit of the test system is connected to the computer via an int
erface bus. Individua test programs for each type of reay are required, but th
e interface used is standard for a reay types. Contro of input waveforms and
anaogue measurements, the monitoring of output signas and the anaysis of tes
t data are performed by the computer. A printout of the test resuts can aso be
produced if required.

21
Figure 21.15: Modern computer-controed test bench
Because software is extensivey tested at the typetesting stage, there is norma
y no need to check the correct functioning of the software. Checks are imited
to determining that the anaogue and digita I/O is functioning correcty. This
is achieved for inputs by
386

Network Protection & Automation Guide

appying known votage and current inputs to the reay under test and checking t
hat the software has captured the correct vaues. Simiary, digita outputs are
exercised by using test software to actuate each output and checking that the c
orrect output is energised. Provided that appropriate procedures are in pace to
ensure that ony type-tested software is downoaded, there is no need to check
the correct functioning of the software in the reay. The fina step is to down
oad the software appropriate to the reay and store it in the EPROM fitted in th
e reay.
b. genera inspection of the equipment, checking a connections, wires on reay
s terminas, abes on termina boards, etc. c. insuation resistance measuremen
t of a circuits d. perform reay sef-test procedure and externa communicatio
ns checks on digita/numerica reays e. test main current transformers f. test
main votage transformers g. check that protection reay aarm/trip settings hav
e been entered correcty h. tripping and aarm circuit checks to prove correct f
unctioning In addition, the foowing checks may be carried out, depending on th
e factors noted earier. i. secondary injection test on each reay to prove oper
ation at one or more setting vaues
21.9 COMMISSIONING TESTS Instaation of a protection scheme at site creates a n
umber of possibiities for errors in the impementation of the scheme to occur.
Even if the scheme has been thoroughy tested in the factory, wiring to the CTs a
nd VTs on site may be incorrecty carried out, or the CTs/VTs may have been incorre
cty instaed. The impact of such errors may range from simpy being a nuisance
(tripping occurs repeatedy on energisation, requiring investigation to ocate
and correct the error(s)) through to faiure to trip under faut conditions, ea
ding to major equipment damage, disruption to suppies and potentia hazards to
personne. The strategies avaiabe to remove these risks are many, but a invo
ve some kind of testing at site. Commissioning tests at site are therefore inva
riaby performed before protection equipment is set to work. The aims of commiss
ioning tests are: 1. to ensure that the equipment has not been damaged during tr
ansit or instaation 2. to ensure that the instaation work has been carried o
ut correcty 3. to prove the correct functioning of the protection scheme as a w
hoe The tests carried out wi normay vary according to the protection scheme
invoved, the reay technoogy used, and the poicy of the cient. In many case
s, the tests actuay conducted are determined at the time of commissioning by m
utua agreement between the cients representative and the commissioning team. He
nce, it is not possibe to provide a definitive ist of tests that are required
during commissioning. This section therefore describes the tests commony carrie
d out during commissioning. The foowing tests are invariaby carried out, sinc
e the protection scheme wi not function correcty if fauts exist. a. wiring d
iagram check, using circuit diagrams showing a the reference numbers of the in
terconnecting wiring
k. testing of protection scheme ogic This section detais the tests required to
cover items (a)(g) above. Secondary injection test equipment is covered in Secti
on 21.10 and Section 21.11 detais the secondary injection that may be carried o
ut. Section 21.12 covers primary injection testing, and Section 21.13 detais th
e checks required on any ogic invoved in the protection scheme. Finay, Secti
on 21.14 detais the tests required on aarm/tripping circuits tripping/aarm ci
rcuits.
21.9.1 Insuation Tests A the deiberate earth connections on the wiring to be
tested shoud first be removed, for exampe earthing inks on current transform
ers, votage transformers and d.c. suppies. Some insuation testers generate im
puses with peak votages exceeding 5kV. In these instances any eectronic equip
ment shoud be disconnected whie the externa wiring insuation is checked. The
insuation resistance shoud be measured to earth and between eectricay sepa
rate circuits. The readings are recorded and compared with subsequent routine te
sts to check for any deterioration of the insuation. The insuation resistance

measured depends on the amount of wiring invoved, its grade, and the site humid
ity. Generay, if the test is restricted to one cubice, a reading of severa h
undred megohms shoud be obtained. If ong engths of site wiring are invoved,
the reading coud be ony a few megohms.

Network Protection & Automation Guide


387
R e  a y Te s t i n g a n d C o m m i s s i o n i n g 21
j. primary injection tests on each reay to prove stabiity for externa fauts
and to determine the effective current setting for interna fauts (essentia fo
r some types of eectromechanica reays)

21.9.2 Reay Sef-Test Procedure Digita and numerica reays wi have a sef-t
est procedure that is detaied in the appropriate reay manua. These tests shou
d be foowed to determine if the reay is operating correcty. This wi norma
y invove checking of the reay watchdog circuit, exercising a digita input
s and outputs and checking that the reay anaogue inputs are within caibration
by appying a test current or votage. For these tests, the reay outputs are n
ormay disconnected from the remainder of the protection scheme, as it is a tes
t carried out to prove correct reay, rather than scheme, operation. Unit protec
tion schemes invove reays that need to communicate with each other. This eads
to additiona testing requirements. The communications path between the reays
is tested using suitabe equipment to ensure that the path is compete and that
the received signa strength is within specification. Numerica reays may be fi
tted with oopback test faciities that enabe either part of or the entire comm
unications ink to be tested from one end. After competion of these tests, it i
s usua to enter the reay settings required. This can be done manuay via the
reay front pane contros, or using a portabe PC and suitabe software. Whiche
ver method is used, a check by a second person that the correct settings have be
en used is desirabe, and the settings recorded. Programmabe scheme ogic that
is required is aso entered at this stage.
robust moving coi, permanent magnet, centre-zero type. A ow votage battery is
used, via a singe-poe pushbutton switch, to energise the primary winding. On
cosing the push-button, the d.c. ammeter, A, shoud give a positive fick and o
n opening, a negative fick. 21.9.3.2 Magnetisation Curve Severa points shoud
be checked on each current transformer magnetisation curve. This can be done by
energising the secondary winding from the oca mains suppy through a variabe
auto-transformer whie the primary circuit remains open; see Figure 21.17. The c
haracteristic is measured at suitabe intervas of appied votage, unti the ma
gnetising current is seen to rise very rapidy for a sma increase in votage.
This indicates the approximate knee-point or saturation fux eve of the curren
t transformer. The magnetising current shoud then be recorded at simiar votag
e intervas as it is reduced to zero. Care must be taken that the test equipment
is suitaby rated. The short-time current rating must be in excess of the CT se
condary current rating, to aow for the measurement of the saturation current.
This wi be in excess of the CT secondary current rating. As the magnetising cu
rrent wi not be sinusoida, a moving iron or dynamometer type ammeter shoud b
e used. It is often found that current transformers with secondary ratings of 1A
or ess have a knee-point votage higher than the oca mains suppy. In these
cases, a step-up interposing transformer must be used to obtain the necessary vo
tage to check the magnetisation curve.
Test pug isoating current transformers from reay cois
R e  a y Te s t i n g a n d C o m m i s s i o n i n g
21.9.3 Current Transformer Tests The foowing tests are normay carried out pr
ior to energisation of the main circuits. 21.9.3.1 Poarity check
P2 _ P1 S2 S1 +
Variabe transformer 250V 8A
A
B
C
A P1 S 1 To reay cois V 250V a.c. suppy

21
P2 S2 Main circuit breaker open _ A +
Step-up transformer if required
Figure 21.17: Testing current transformer magnetising curve
21.9.4 Votage Transformer Tests
Figure 21.16: Current transformer poarity check
Votage transformers require testing for poarity and phasing. 21.9.4.1 Poarity
check The votage transformer poarity can be checked using the method for CT p
oarity tests. Care must be taken to connect the battery suppy to the primary w
inding, with
Each current transformer shoud be individuay tested to verify that the primar
y and secondary poarity markings are correct; see Figure 21.16. The ammeter con
nected to the secondary of the current transformer shoud be a
388
Network Protection & Automation Guide

the poarity ammeter connected to the secondary winding. If the votage transfor
mer is of the capacitor type, then the poarity of the transformer at the bottom
of the capacitor stack shoud be checked. 21.9.4.2 Ratio check This check can b
e carried out when the main circuit is first made ive. The votage transformer
secondary votage is compared with the secondary votage shown on the namepate.
21.9.4.3 Phasing check The secondary connections for a three-phase votage tran
sformer or a bank of three singe-phase votage transformers must be carefuy c
hecked for phasing. With the main circuit aive, the phase rotation is checked u
sing a phase rotation meter connected across the three phases, as shown in Figur
e 21.18. Provided an existing proven VT is avaiabe on the same primary system,
and that secondary earthing is empoyed, a that is now necessary to prove cor
rect phasing is a votage check between, say, both A phase secondary outputs. Ther
e shoud be nominay itte or no votage if the phasing is correct. However, t
his test does not detect if the phase sequence is correct, but the phases are di
spaced by 120 from their correct position, i.e. phase A occupies the position of
phase C or phase B in Figure 21.18. This can be checked by removing the fuses f
rom phases B and C (say) and measuring the phase-earth votages on the secondary
of the VT. If the phasing is correct, ony phase A shoud be heathy, phases B
and C shoud have ony a sma residua votage.
A B C A
Correct phasing shoud be further substantiated when carrying out on oad tests on
any phase-ange sensitive reays, at the reay terminas. Load current in a kno
wn phase CT secondary shoud be compared with the associated phase to neutra VT
secondary votage. The phase ange between them shoud be measured, and shoud
reate to the power factor of the system oad. If the three-phase votage transf
ormer has a brokendeta tertiary winding, then a check shoud be made of the vo
tage across the two connections from the broken deta VN and VL, as shown in Fig
ure 21.18. With the rated baanced three-phase suppy votage appied to the vo
tage transformer primary windings, the broken-deta votage shoud be beow 5V w
ith the rated burden connected.
21.9.5 Protection Reay Setting Checks At some point during commissioning, the a
arm and trip settings of the reay eements invoved wi require to be entered
and/or checked. Where the compete scheme is engineered and suppied by a sing
e contractor, the settings may aready have been entered prior to despatch from
the factory, and hence this need not be repeated. The method of entering setting
s varies according to the reay technoogy used. For eectromechanica and stati
c reays, manua entry of the settings for each reay eement is required. This
method can aso be used for digita/numerica reays. However, the amount of dat
a to be entered is much greater, and therefore it is usua to use appropriate so
ftware, normay suppied by the manufacturer, for this purpose. The software a
so makes the essentia task of making a record of the data entered much easier.
Once the data has been entered, it shoud be checked for compiance with the rec
ommended settings as cacuated from the protection setting study. Where appropr
iate software is used for data entry, the checks can be considered compete if t
he data is checked prior to downoad of the settings to the reay. Otherwise, a
check may required subsequent to data entry by inspection and recording of the r
eay settings, or it may be considered adequate to do this at the time of data e
ntry. The recorded settings form an essentia part of the commissioning document
ation provided to the cient.
V1 C V2 B

VN V VL V2
21.10 SECONDARY INJECTION TEST EQUIPMENT
V1

A B C
Phase rotation meter
Secondary injection tests are aways done prior to primary injection tests. The
purpose of secondary injection testing is to prove the correct operation of the
protection scheme that is downstream from the inputs to the protection reay(s).
Secondary injection tests are aways done prior to primary injection tests. Thi
s is
Figure 21.18: Votage transformer phasing check
Network Protection & Automation Guide 389
R e  a y Te s t i n g a n d C o m m i s s i o n i n g 21

because the risks during initia testing to the LV side of the equipment under t
est are minimised. The primary (HV) side of the equipment is disconnected, so th
at no damage can occur. These tests and the equipment necessary to perform them
are generay described in the manufacturers manuas for the reays, but brief
detais are given beow for the main types of protection reays.
21.10.1 Test Bocks/Pugs for Secondary Injection Equipment It is common practic
e to provide test bocks or test sockets in the reay circuits so that connectio
ns can readiy be made to the test equipment without disturbing wiring. Test pu
gs of either muti-finger or singe-finger design (for monitoring the current in
one CT secondary circuit) are used to connect test equipment to the reay under
test. The top and bottom contact of each test pug finger is separated by an in
suating strip, so that the reay circuits can be competey isoated from the s
witchgear wiring when the test pug is inserted. To avoid open-circuiting CT sec
ondary terminas, it is therefore essentia that CT shorting jumper inks are fi
tted across a appropriate ive side terminas of the test pug BEFORE it is inse
rted. With the test pug inserted in position, a the test circuitry can now be
connected to the isoated reay side test pug terminas. Some modern test bocks
incorporate the ive-side jumper inks within the bock and these can be set to
the cosed or open position as appropriate, either manuay prior to removing the c
over and inserting the test pug, or automaticay upon remova of the cover. Re
mova of the cover aso exposes the coour-coded face-pate of the bock, cear
y indicating that the protection scheme is not in service, and may aso disconne
ct any d.c. auxiiary suppies used for powering reay tripping outputs. Withdra
wing the test pug immediatey restores the connections to the main current tran
sformers and votage transformers and removes the test connections. Repacement
of the test bock cover then removes the short circuits that had been appied to
the main CT secondary circuits. Where severa reays are used in a protection s
cheme, one or more test bocks may be fitted on the reay pane enabing the who
e scheme to be tested, rather than just one reay at a time. Test bocks usua
y offer faciities for the monitoring and secondary injection testing of any pow
er system protection scheme. The test bock may be used either with a muti-fing
ered test pug to aow isoation and monitoring of a the seected conductor p
aths, or with a singe finger test pug that aows the currents on individua c
onductors to be monitored. A modern test bock and test pugs are iustrated in
Figure 21.19.
Figure 21.19: Modern test bock/pugs
21.10.2 Secondary Injection Test Sets The type of the reay to be tested determi
nes the type of equipment used to provide the secondary injection currents and v
otages. Many eectromechanica reays have a non-inear current coi impedance
when the reay operates and this can cause the test current waveform to be disto
rted if the injection suppy votage is fed directy to the coi. The presence o
f harmonics in the current waveform may affect the torque of eectromechanica r
eays and give unreiabe test resuts, so some injection test sets use an adjus
tabe series reactance to contro the current. This keeps the power dissipation
sma and the equipment ight and compact. Many test sets are portabe and incu
de precision ammeters and votmeters and timing equipment. Test sets may have bo
th votage and current outputs. The former are high-votage, ow current outputs
for use with reay eements that require signa inputs from a VT as we as a C
T. The current outputs are high-current, ow votage to connect to reay CT inpu
ts. It is important, however, to ensure that the test set current outputs are tr
ue current sources, and hence are not affected by the oad impedance of a reay
eement current coi. Use of a test set with a current output that is essentia
y a votage source can give rise to serious probems when testing eectromechani
ca reays. Any significant impedance mismatch between the output of the test se
t and the reay current coi during reay operation wi give rise to a variatio
n in current from that desired and possibe error in the test resuts. The reay
operation time may be greater than expected (never ess than expected) or reay
chatter may occur. It is quite common for such errors to ony be found much ater

, after a faut has caused major damage to equipment through faiure of the prim
ary protection to operate. Faiure investigation then shows that the reason for
the primary protection to operate is an incorrecty set reay, due in turn to us
e of a test set with a current output consisting of a votage-source when the re
ay was ast tested. Figure 21.20 shows typica waveforms resuting from use of
test set current output that is a votage

R e  a y Te s t i n g a n d C o m m i s s i o n i n g 21
390
Network Protection & Automation Guide

V reay/source
Time
Saturation eve of magnetic circuit (current) imited ony by D.C. resistance o
f reay coi
Reay with saturation of CDG magnetic circuit (phase shift from CDG inductive o
ad shown).
a) Reay current coi waveform distorted due to use of votage source
Sinusoida CURRENT when changing impedance of reay is swamped out by high sourc
e impedance
Time
Typica VOLTAGE waveform appearing across reay current cois with sinusoida I
above the reay setting (10 x shown).

b) Undistorted reay current coi current distorted due to use of current source
Figure 21.20: Reay current coi waveforms
source the distorted reay coi current waveform gives rise to an extended opera
tion time compared to the expected vaue. Modern test sets are computer based. T
hey comprise a PC (usuay a standard aptop PC with suitabe software) and a po
wer ampifier that takes the ow-eve outputs from the PC and ampifies them in
to votage and current signas suitabe for appication to the VT and CT inputs
of the reay. The phase ange between votage and current outputs wi be adjust
abe, as aso wi the phase anges between the individua votages or currents
making up a
3-phase output set. Much greater precision in the setting of the magnitudes and
phase anges is possibe, compared to traditiona test sets. Digita signas to
exercise the interna ogic eements of the reays may aso be provided. The aa
rm and trip outputs of the reay are connected to digita inputs on the PC so th
at correct operation of the reay, incuding accuracy of the reay tripping char
acteristic can be monitored and dispayed on-screen, saved for incusion in repo
rts generated ater, or printed for an immediate record to present to the cient
. Optiona features may incude GPS time synchronising equipment and remote-oca
ted ampifiers
Network Protection & Automation Guide
391
R e  a y Te s t i n g a n d C o m m i s s i o n i n g 21

to faciitate testing of unit protection schemes, and digita I/O for exercising
the programmabe scheme ogic of modern reays. The software for modern test se
ts is capabe of testing the functionaity of a wide variety of reays, and cond
ucting a set of tests automaticay. Such sets ease the task of the commissionin
g engineer. The software wi normay offer options for testing, ranging from a
test carried out at a particuar point on the characteristic to compete determ
ination of the tripping characteristic automaticay. This feature can be hepfu
 if there is any reason to doubt that the reay is operating correcty with the
tripping characteristic specified. Figure 21.21 iustrates a modern PC-based t
est set. Traditiona test sets use an arrangement of adjustabe transformers and
reactors to provide contro of current and votage without incurring high power
dissipation. Some reays require adjustment of the phase between the injected v
otages and currents, and so phase shifting transformers may be used. Figure 21.
22 shows the circuit diagram of a traditiona test set suitabe for overcurrent
reay resting, whie Figure 21.23 shows the circuit diagram for a test set for d
irectiona/distance reays. Timers are incuded so that the response time of the
reay can be measured.
R e  a y Te s t i n g a n d C o m m i s s i o n i n g
Figure 21.21: Modern PC-based secondary injection test set
21.11 SECONDARY INJECTION TESTING The purpose of secondary injection testing is
to check that the protection scheme from the reay input terminas onwards is fu
nctioning correcty with the settings specified. This is achieved by appying su
itabe inputs from a test set to the inputs of the reays and checking if the ap
propriate aarm/trip signas occur at the reay/contro room/CB ocations. The e
xtent of
testing wi be argey determined by the cient specification and reay techno
ogy used, and may range from a simpe check of the reay characteristic at a sin
ge point to a compete verification of the tripping characteristics of the sche
me, incuding the response to transient waveforms and harmonics and checking of
reay bias characteristics. This may be important when the protection scheme inc
udes transformers and/or generators.

21
Coarse contro reactor K2 Fine contro variabe transformer Start timer Backing
transformer 10% contro Reay current, I = Ammeter reading (A) K1 x K2 Medium co
ntro reactor Injection transformer Stop timer Reay short-circuiting switch A R
ange adjusting CT
K1 I>
I Reay coi
250V a.c. suppy
Figure 21.22: Circuit diagram of traditiona test set for overcurrent reays
392
Network Protection & Automation Guide

A B C N
Variabe transformer contro
Suppy switch 440V 3p phase 4 wire suppy
Faut A-N X( ) 22.5 20.0 17.5 15.0 12.5 10.0 7.5 5.0 2.5 0.0 -2.5 -5.0 -7.5 -10.
0 -15.0 -10.0 -5.0 0.0 5.0 10.0 15.0 R( )
Choke Reay
adjusting CT
A PA A V PA A
440/110V phase p shifting g transformer
> votage eement Variabe transformer for current contro V Votmeter A Ammeter
PA Phase ange meter
To other votage eements of reay y under test (if required)
Figure 21.23: Circuit diagram for traditiona test set for directiona/distance
reays
Figure 21.24: Distance reay zone checking using search technique and toerance
bands
Zn
*
21.11.1 Schemes using Digita or Numerica Reay Technoogy The poicy for secon
dary injection testing varies widey. In some cases, manufacturers recommend, an
d cients accept, that if a digita or numerica reay passes its seftest, it ca
n be reied upon to operate at the settings used and that testing can therefore
be confined to those parts of the scheme externa to the reay. In such cases, s
econdary injection testing is not required at a. More often, it is required th
at one eement of each reay (usuay the simpest) is exercised, using a second
ary injection test set, to check that reay operation occurs at the conditions e
xpected, based on the setting of the reay eement concerned. Another aternativ
e is for the compete functionaity of each reay to be exercised. This is rare
y required with a digita or numerica reay, probaby ony being carried out in
the event of a suspected reay mafunction. To iustrate the resuts that can
be obtained, Figure 21.24 shows the resuts obtained by a modern test set when d
etermining the reach settings of a distance reay using a search technique. Anot
her exampe is the testing of the Power Swing bocking eement of a distance re
ay. Figure 21.25 iustrates such a test, based on using discrete impedance poin
ts. This kind of test may not be adequate in a cases, and test equipment may h
ave the abiity to generate the waveforms simuating a power swing and appy the
m to the reay (Figure 21.26).
PSB-Zone
R
Figure 21.25: Testing of power swing bocking eement discrete points

Figure 21.26: Simuated power swing waveform


21.11.2 Schemes using Eectromechanica/Static Reay Technoogy Schemes using si

nge function eectromechanica or static reays wi usuay require each reay
to be exercised. Thus a scheme with distance and back-up overcurrent eements w
i require a test on each of these functions, thereby taking up more time than
if a digita or numerica reay is used. Simiary, it may be important
Network Protection & Automation Guide
393
R e  a y Te s t i n g a n d C o m m i s s i o n i n g 21
The testing shoud incude any scheme ogic. If the ogic is impemented using t
he programmabe scheme ogic faciities avaiabe with most digita or numerica
reays, appropriate digita inputs may need to be appied and outputs monitored
(see Section 21.13). It is cear that a modern test set can faciitate such tes
ts, eading to a reduced time required for testing.
X

to check the reay characteristic over a range of input currents to confirm para
meters for an overcurrent reay such as: i. the minimum current that gives opera
tion at each current setting ii. the maximum current at which resetting takes p
ace iii. the operating time at suitabe vaues of current iv. the time/current c
urve at two or three points with the time mutipier setting TMS at 1 v. the res
etting time at zero current with the TMS at 1 Simiar considerations appy to di
stance and unit protection reays of these technoogies.
of VTs/CTs may not then be discovered unti either spurious tripping occurs in ser
vice, or more seriousy, faiure to trip on a faut. This hazard is much reduced
where digita/numerica reays are used, since the current and votage measurem
ent/dispay faciities that exist in such reays enabe checking of reay input
vaues against those from other proven sources. Many connection/wiring errors ca
n be found in this way, and by isoating temporariy the reay trip outputs, unw
anted trips can be avoided. Primary injection testing is, however, the ony way
to prove correct instaation and operation of the whoe of a protection scheme.
As noted in the previous section, primary injection tests are aways carried ou
t after secondary injection tests, to ensure that probems are imited to the VTs
and CTs invoved, pus associated wiring, a other equipment in the protection
scheme having been proven satisfactory from the secondary injection tests.
21.11.3 Test Circuits for Secondary Injection Testing
R e  a y Te s t i n g a n d C o m m i s s i o n i n g
The test circuits used wi depend on the type of reay and test set being used.
Uness the test circuits are simpe and obvious, the reay commissioning manua
wi give detais of the circuits to be used. Commony used test circuits can a
so be found in Chapter 23 of reference [21.1]. When using the circuits in this
reference, suitabe simpifications can easiy be made if digita or numerica r
eays are being tested, to aow for their buit-in measurement capabiities ext
erna ammeters and votmeters may not be required. A resuts shoud be carefu
y noted and fied for record purposes. Departures from the expected resuts mus
t be thoroughy investigated and the cause determined. After rectification of er
rors, a tests whose resuts may have been affected (even those that may have g
iven correct resuts) shoud be repeated to ensure that the protection scheme ha
s been impemented according to specification.
21.12.1 Test Faciities An aternator is the most usefu source of power for pro
viding the heavy current necessary for primary injection. Unfortunatey, it is r
arey avaiabe, since it requires not ony a spare aternator, but aso spare b
usbars capabe of being connected to the aternator and circuit under test. Ther
efore, primary injection is usuay carried out by means of a portabe injection
transformer (Figure 21.27), arranged to operate from the oca mains suppy and
having severa ow votage, heavy current windings. These can be connected in s
eries or parae according to the current required and the resistance of the pr
imary circuit. Outputs of 10V and 1000A can be obtained. Aternativey, modern P
C-controed test sets have power ampifiers capabe of injecting currents up to
about 200A for a singe unit, with higher current ratings being possibe by usi
ng mutipe units in parae.

21
21.12 PRIMARY INJECTION TESTS This type of test invoves the entire circuit; cur
rent transformer primary and secondary windings, reay cois, trip and aarm cir
cuits, and a intervening wiring are checked. There is no need to disturb wirin
g, which obviates the hazard of open-circuiting current transformers, and there
is generay no need for any switching in the current transformer or reay circu

its. The drawback of such tests is that they are time consuming and expensive to
organise. Increasingy, reiance is paced on a wiring and instaation diagr
ams being correct and the instaation being carried out as per drawings, and se
condary injection testing being competed satisfactoriy. Under these circumstan
ces, the primary injection tests may be omitted. However, wiring errors between
VTs/CTs and reays, or incorrect poarity
394
A 250V a.c. suppy
Variabe transformer 40A
Injection transformer 250/10 + 10 + 10 + 10V 10kVA
Figure 21.27: Traditiona primary injection test set
Network Protection & Automation Guide

If the main current transformers are fitted with test windings, these can be use
d for primary injection instead of the primary winding. The current required for
primary injection is then greaty reduced and can usuay be obtained using sec
ondary injection test equipment. Unfortunatey, test windings are not often prov
ided, because of space imitations in the main current transformer housings or t
he cost of the windings.
21.12.2 CT Ratio Check Current is passed through the primary conductors and meas
ured on the test set ammeter, A1 in Figure 21.28. The secondary current is measu
red on the ammeter A2 or reay dispay, and the ratio of the vaue on A1 to that
on A2 shoud cosey approximate to the ratio marked on the current transformer
namepate.
A B C
the residua circuit, or reay dispay, wi give a reading of a few miiampere
s with rated current injected if the current transformers are of correct poarit
y. A reading proportiona to twice the primary current wi be obtained if they
are of wrong poarity. Because of this, a high-range ammeter shoud be used init
iay, for exampe one giving fu-scae defection for twice the rated secondar
y current. If an eectromechanica earth-faut reay with a ow setting is aso
connected in the residua circuit, it is advisabe to temporariy short-circuit
its operating coi during the test, to prevent possibe overheating. The singephase injection shoud be carried out for each pair of phases.
Temporary three-phase short circuit Primary injection test set A B C Reay
250V a.c. suppy
Temporary short circuit
A Figure 21.29: Poarity check on main current transformers
P1 S1
Reay
21.12.4 Primary Injection Testing of Reay Eements As with secondary injection
testing, the tests to be carried out wi be those specified by the cient, and/
or those detaied in the reay commissioning manua. Digita and numerica reay
s usuay require far fewer tests to prove correct operation, and these may be r
estricted to observations of current and votage on the reay dispay under norm
a oad conditions.
P2
S2 Reay or test bock contact fingers
A1
Primary injection test set 250V a.c. suppy Figure 21.28: Current transformer ra
tio check
21.13 TESTING OF PROTECTION SCHEME LOGIC Protection schemes often invove the us
e of ogic to determine the conditions under which designated circuit breakers s
houd be tripped. Simpe exampes of such ogic can be found in Chapters 9-14. T
raditionay, this ogic was impemented by means of discrete reays, separate f
rom the reays used for protection. Such impementations woud occur where eect
romechanica or static reay technoogy is used. However, digita and numerica
reays normay incude programmabe ogic as part of the software within the re
ay, together with associated digita I/O. This faciity (commony referred to a
s Programmabe Scheme Logic, or PSL) offers important advantages to the user, by

saving space and permitting modifications to the protection scheme ogic throug
h software if the protection scheme requirements change with time. Changes to th
e ogic are carried out using

21.12.3 CT Poarity Check If the equipment incudes directiona, differentia or


earth faut reays, the poarity of the main current transformers must be check
ed. It is not necessary to conduct the test if ony overcurrent reays are used.
The circuit for checking the poarity with a singe-phase test set is shown in
Figure 21.29. A short circuit is paced across the phases of the primary circuit
on one side of the current transformers whie singe-phase injection is carried
out on the other side. The ammeter connected in
Network Protection & Automation Guide
395
R e  a y Te s t i n g a n d C o m m i s s i o n i n g 21
Test pug insuation u

software hosted on a PC (or simiar computer) and downoaded to the reay. Use o
f anguages defined in IEC 61131, such as adder ogic or Booean agebra is com
mon for such software, and is readiy understood by Protection Engineers. Furthe
r, there are severa commony encountered protection functions that manufacturer
s may suppy with reays as one or more defaut ogic schemes. Because software is
used, it is essentia to carefuy test the ogic during commissioning to ensur
e correct operation. The ony exception to this may be if the reevant defaut sch
eme is used. Such ogic schemes wi have been proven during reay type testing,
and so there is no need for proving tests during commissioning. However, where
a customer generates the scheme ogic, it is necessary to ensure that the commis
sioning tests conducted are adequate to prove the functionaity of the scheme in
a respects. A specific test procedure shoud be prepared, and this procedure
shoud incude:
Many designs of withdrawabe circuit breaker can be operated whie in the mainte
nance position, so that substation operation can continue unaffected except for
the circuit controed by the circuit breaker invoved. In other cases, isoator
s can be used to avoid the need for busbar de-energisation if the circuit invov
ed is not ready for energisation.
21.15 PERIODIC MAINTENANCE TESTS Periodic testing is necessary to ensure that a
protection scheme continues to provide satisfactory performance for many years a
fter instaation. A equipment is subject to gradua degradation with time, an
d reguar testing is intended to identify the equipment concerned so that remedi
a action can be taken before scheme maoperation occurs. However, due care shou
d be taken in this task, otherwise fauts may be introduced as a direct resut
of the remedia work. The cearance of a faut on the system is correct ony if
the number of circuit breakers opened is the minimum necessary to remove the fau
t. A sma proportion of fauts are incorrecty ceared, the main reasons being
: a. imitations in protection scheme design b. fauty reays c. defects in the
secondary wiring d. incorrect connections e. incorrect settings f. known appica
tion shortcomings accepted as improbabe occurrences g. piot wire fauts due to
previous unreveaed damage to a piot cabe h. various other causes, such as sw
itching errors, testing errors, and reay operation due to mechanica shock The
sef-checking faciities of numerica reays assist in minimising faiures due t
o fauty reays. Defects in secondary wiring and incorrect connections are virtu
ay eiminated if proper commissioning after scheme instaation/ateration is
carried out. The possibiity of incorrect settings is minimised by reguar revie
ws of reay settings. Network faut eves change over time, and hence setting c
acuations may need to be revised. Switching and testing errors are minimised b
y adequate training of personne, use of proven software, and wedesigned syste
matic working procedures. A of these can be said to be within the contro of t
he user. The remaining three causes are not controabe, whie two of these thr
ee are unavoidabe engineering is not science and there wi aways be situation
s that a protection reay cannot reasonaby be expected to cover at an affordab
e cost.
Network Protection & Automation Guide
R e  a y Te s t i n g a n d C o m m i s s i o n i n g
a. checking of the scheme ogic specification and diagrams to ensure that the ob
jectives of the ogic are achieved b. testing of the ogic to ensure that the fu
nctionaity of the scheme is proven c. testing of the ogic, as required, to ens
ure that no output occurs for the reevant input signa combinations The degree
of testing of the ogic wi argey depend on the criticaity of the appicatio
n and compexity of the ogic. The responsibiity for ensuring that a suitabe t
est procedure is produced for ogic schemes other than the defaut one(s) suppied
ies with the specifier of the ogic. Reay manufacturers cannot be expected to
take responsibiity for the correct operation of ogic schemes that they have n
ot designed and suppied.


21
21.14 TRIPPING AND ALARM ANNUNCIATION TESTS If primary and/or secondary injectio
n tests are not carried out, the tripping and aarm circuits wi not have been
checked. Even where such checks have been carried out, CB trip cois and/or Cont
ro Room aarm circuits may have been isoated. In such cases, it is essentia t
hat a of the tripping and aarm circuits are checked. This is done by cosing
the protection reay contacts manuay and checking that: 1. the correct circuit
breakers are tripped 2. the aarm circuits are energised 3. the correct fag in
dications are given 4. there is no maoperation of other apparatus that may be c
onnected to the same master trip reay or circuit breaker
396

21.15.1 Frequency of Inspection and Testing Athough protection equipment shoud


be in sound condition when first put into service, probems can deveop uncheck
ed and unreveaed because of its infrequent operation. With digita and numerica
 reays, the in-buit sef-testing routines can be expected to revea and annun
ciate most fauts, but this does not cover any other components that, together,
comprise the protection scheme. Reguar inspection and testing of a protection s
cheme is therefore required. In practice, the frequency of testing may be imite
d by ack of staff or by the operating conditions on the power system. It is des
irabe to carry out maintenance on protection equipment at times when the associ
ated power apparatus is out of service. This is faciitated by co-operation betw
een the maintenance staff concerned and the network operations contro centre. M
aintenance tests may sometimes have to be made when the protected circuit is on
oad. The particuar equipment to be tested shoud be taken out of commission an
d adequate back-up protection provided for the duration of the tests. Such backup protection may not be fuy discriminative, but shoud be sufficient to cear
any faut on the apparatus whose main protection is temporariy out of service.
Maintenance is assisted by the dispays of measured quantities provided on digi
ta and numerica reays. Incorrect dispay of a quantity is a cear indication
that something is wrong, either in the reay itsef or the input circuits.
21.16 PROTECTION SCHEME DESIGN FOR MAINTENANCE If the foowing principes are a
dhered to as far as possibe, the danger of back-feeds is essened and faut inv
estigation is made easier: i. test bocks shoud be used, to enabe a test pug
to be used, and a defective unit to be repaced quicky without interrupting ser
vice ii. circuits shoud be kept as eectricay separate as possibe, and the u
se of common wires shoud be avoided, except where these are essentia to the co
rrect functioning of the circuits iii. each group of circuits which is eectrica
y separate from other circuits shoud be earthed through an independent earth
ink iv. where a common votage transformer or d.c. suppy is used for feeding s
evera circuits, each circuit shoud be fed through separate inks or fuses. Wit
hdrawa of these shoud competey isoate the circuit concerned v. power suppi
es to protection schemes shoud be segregated from those suppying other equipme
nt and provided with fuy discriminative circuit protection vi. a singe auxii
ary switch shoud not be used for interrupting or cosing more than one circuit
vii. terminations in reay panes require good access, as these may have to be a
tered if extensions are made. Modern panes are provided with specia test faci
ities, so that no connections need be disturbed during routine testing viii. ju
nction boxes shoud be of adequate size and, if outdoors, must be made waterproo
f ix. a wiring shoud be ferrued for identification and phase-cooured x. ee
ctromechanica reays shoud have high operating and restraint torques and high
contact pressures; jewe bearings shoud be shrouded to excude dust and the use
of very thin wire for cois and connections shoud be avoided. Dust-tight cases
with an efficient breather are essentia on these types of eectromechanica e
ement xi. static, digita and numerica reays shoud have test faciities acces
sibe from the front to assist in faut finding. The reay manua shoud ceary
detai the expected resuts at each test point when heathy

21.15.2 Maintenance Tests Primary injection tests are normay ony conducted ou
t during initia commissioning. If scheme maoperation has occurred and the prot
ection reays invoved are suspect, or aterations have been made invoving the
wiring to the reays from the VTs/CTs, the primary injection tests may have to be
repeated. Secondary injection tests may be carried out at suitabe intervas to
check reay performance, and, if possibe, the reay shoud be aowed to trip t
he circuit breakers invoved. The interva between tests wi depend upon the cr
iticaity of the circuit invoved, the avaiabiity of the circuit for testing a
nd the technoogy of the reays used. Secondary injection testing is ony necess
ary on the seected reay setting and the resuts shoud be checked against thos
e obtained during the initia commissioning of the equipment. It is better not t
o interfere with reay contacts at a uness they are obviousy corroded. The p

erformance of the contacts is fuy checked when the reay is actuated. Insuati
on tests shoud aso be carried out on the reay wiring to earth and between cir
cuits, using a 1000V tester. These tests are necessary to detect any deteriorati
on in the insuation resistance.
Network Protection & Automation Guide
21.17 REFERENCES 21.1 Protective Reays Appication Guide, 3rd edition. AREVA Tr
ansmission and Distribution, Protection and Contro, 1987.
397
R e  a y Te s t i n g a n d C o m m i s s i o n i n g 21

You might also like